DRAFT ERCOT Dynamic Voltage Recovery Criteria v2

advertisement
DRAFT
ERCOT Dynamic Voltage Recovery Criteria
For,
NERC Category A Contingencies
NERC Category B Contingencies
NERC Category C Contingencies
NERC Category D Contingencies that a transmission planning entity has
determined should meet NERC Category C requirements. (See note 1)
1. Do not allow a voltage collapse
2. For systems with undervoltage load shedding (UVLS) schemes, allow no
UVLS load to be shed.
3. Generator terminal voltages must recover to 90% of nominal voltage within
10 seconds after the terminal voltage falls below 90% of nominal voltage.
For,
NERC Category D Contingencies that a transmission planning entity has
determined to be of credible concern. (See note 1)
1. For systems without an UVLS scheme, do not allow a voltage collapse
2. For systems with UVLS schemes, allow no more than 1250 MW of UVLS
load to be shed
or 300 MW (DOE reportable load shed)
or % of system load
or MW size of largest unit in the affected system
or % of load on UVLS
other
3. Generator terminal voltages must recover to 90% of nominal voltage within
10 seconds after the terminal voltage falls below 90% of nominal voltage.
1
Category D contingencies considered under this standard should be those that have been
demonstrated to have a relatively high probability of occurrence relative to other category
D contingencies. This determination should be supported by statistically significant
outage history data for the subject transmission system.
This document contains proprietary information and shall not be reproduced in whole or in part without prior
written permission of ERCOT
1
DRAFT
Steady-state Reactive Adequacy
Design for sufficient steady-state resources is the industry accepted first step in
providing adequate reactive support. Steady-state adequacy can be evaluated using either
PV analysis or QV analysis. Voltage collapse is caused by reactive demand exceeding
reactive supply. There are essentially two mechanisms that result in the steady-state
reactive demand not being met:
1. The reactive demand exceeds the reactive capability of the reactive sources.
2. The network impedance limits the amount of reactive that can be delivered to the
load to a value less than the demand.
Voltage collapse is initially a local phenomenon. Voltage collapse can occur at one
bus or a limited number of buses and can cascade to large areas if not arrested. It is
possible and desirable to identify these groups of buses that act as a coherent bus group
during voltage collapse. Similarly, the sources that can fully deliver reactive power to a
coherent bus group will not be very distant (roughly less than 50 miles) from the coherent
bus group. To properly analyze the first voltage collapse mechanism mentioned above, it
is necessary to identify the dynamic reactive sources that can deliver reactive power to
each coherent bus group.
The second mechanism describes the situation commonly observed where reactive
reserves of nearby sources become exhausted and reactive reserves on remaining sources
must be delivered across the impedance of the supply system. Reactive reserves on the
remaining sources cannot be fully delivered before collapse occurs. As the reactive
demand increases, the voltage drop across the supply impedance increases and eventually
reaches the collapse point in the area of high demand.
Both of these mechanisms come into play in most power grids. They are addressed in
slightly different ways by the following steady-state criteria.
ERCOT Steady-state PV Criteria
This method directly addresses the combined collapse mechanism which has been
cited as the typical voltage collapse scenario for most power systems.
From ERCOT Operating Guides Section 5.1.4:
Voltage stability margin shall be sufficient to maintain post-transient voltage stability
within a defined importing (Load) area under the following study conditions:
 Peak Load conditions, with import to the area increased by five percent (5%) of the
forecasted area Load, and NERC Category A or B operating conditions (see NERC
Table I in ERCOT Planning Criteria); and
 Peak Load conditions, with import to the area increased by two and one half percent
(2.5%) of the forecasted area Load, and NERC Category C operating conditions
This document contains proprietary information and shall not be reproduced in whole or in part without prior
written permission of ERCOT
2
DRAFT
ERCOT Steady-state QV guidelines
For a given coherent bus group the reactive margin calculated using QV should be at
least equal to the greater of:


The reactive capability of the largest plant or dynamic reactive source contained in
the coherent bus group. The reactive capability of the largest plant is defined as the
sum of the Qmax of all on line dynamic reactive sources (generators, STATCOM’s,
etc.) at a station connected to the transmission system at the same voltage; or
The increased reactive demand following any Category A, B, or C contingency.
Category D contingencies or other contingencies having a probability of occurrence
comparable to a Category C contingency, may be treated as a Category C contingency
for voltage stability/reactive margin purposes
How are coherent bus groups determined? One method is to perform modal analysis
on the transmission system. Another method is to first note all on-line dynamic reactive
sources that are not at their Qmax. Then, for all load buses of interest, perform QV
analysis. For each bus, note the dynamic reactive sources that have reached their Qmax at
the QV knee point. Coherent buses are all the buses that had the same dynamic reactive
sources reach their Qmax at the knee point. (Put another way, the knee point represents
the largest stable reactive load for that bus. The dynamic reactive sources that have
reached their Qmax when the QV analysis reached the knee point are the dynamic
reactive sources that can supply reactive power to that bus load. Buses that are supplied
reactively by the same dynamic reactive sources will experience voltage collapse together
because their reactive supply (the same dynamic reactive sources) cannot supply any
more reactive power.)
The second bullet of the ERCOT Steady-state QV guidelines can be calculated by
summing the pre-contingency Qmax and Qgen of the dynamic reactive sources supplying
reactive power to the coherent bus group. The difference between the Qmax sum and
Qgen sum is the pre-contingency reactive capability. Apply the contingency and solve the
load flow case. If the case does not solve, the pre-contingency reactive capability is
inadequate. If it does solve, sum the dynamic reactive source Qmax and Qgen and take
the difference. This is the post-contingency reactive capability. The difference between
the pre-contingency and post-contingency capability is the needed reactive margin for
this contingency.
Dynamic Reactive Adequacy
The following discusses methods for determining critical contingencies, reactive
margins of dynamic resources, and/or the need for additional dynamic reactive sources.
Adherence to the ERCOT Dynamic Voltage Recovery Criteria can be evaluated by the
following three methods:
This document contains proprietary information and shall not be reproduced in whole or in part without prior
written permission of ERCOT
3
DRAFT
Method 1
For a given coherent bus group the reactive margin calculated using QV should be
at least equal to:

Six times the steady-state motor reactive requirement for buses whose voltage
drops below 70% or 80% or 60% of nominal during a fault. The reactive
capability of generators supplying reactive power to the coherent bus group
shall be X (X to be determined) times the generator’s Qmax value.
Unless more specific information is available, consider 75% of the load flow
reactive load to be motor load in summer cases, and 20% motor load in all other
seasons. Industrial loads should be considered 75% motor load regardless of
season.
Note: it is recognized that the above involves numerous simplifying assumptions
about the distribution network and load. The above is considered a reasonable
compromise between network detail and computational efficiency.
The following discussion gives some of the rational for the guidelines.
Dynamic simulations can be very time consuming, when and a large number of
contingencies must be evaluated. The above guidelines are intended to be applied to load
flow cases. (Determining buses that drop below 70% or 80% or 60% will require
dynamic simulation.) Once the critical contingencies are determined, it is recommended
that detailed dynamic simulations be performed to verify the margin determined above is
adequate.
For any contingency, it is possible to calculate the steady-state reactive needs of
coherent bus groups. Dynamic reactive margin means maintaining sufficient precontingency dynamic reactive resources so that should a contingency occur, sufficient
reactive power can be delivered to the load (coherent bus group) to meet the short term
dynamic reactive demand and allow transition back to acceptable steady-state conditions.
The six times motor reactive in bullet three approximates motor inrush reactive
demand and the x% voltage recognizes that motor inrush will not occur at higher
voltages. The multiplier increasing the generator reactive capability recognizes the fact
that generator exciters have a short time overload capability to help meet the motor inrush
demand.
How are coherent bus groups determined? One method is to perform modal
analysis on the transmission system. Another method is to first note all on-line dynamic
reactive sources that are not at their Qmax. Then, for all load buses of interest, perform
Q-V analysis. For each bus, note the dynamic reactive sources that have reached their
Qmax at the Q-V knee point. Coherent buses are all the buses that had the same dynamic
reactive sources reach their Qmax at the knee point. (Put another way, the knee point
This document contains proprietary information and shall not be reproduced in whole or in part without prior
written permission of ERCOT
4
DRAFT
represents the largest stable reactive load for that bus. The dynamic reactive sources that
have reached their Qmax when the Q-V analysis reached the knee point are the dynamic
reactive sources that can supply reactive power to that bus load. Buses that are supplied
reactively by the same dynamic reactive sources will experience voltage collapse together
because their reactive supply (the same dynamic reactive sources) cannot supply any
more reactive power.
Method 2
Some industry experts maintain that most results of long-term simulation for
voltage and reactive studies can be accomplished manually using a series of quasidynamic studies. This class of analysis can be performed with a standard power flow
program.
The first step in the analysis is to model generators as controlling low side
terminal voltage. Regular power flow studies typically model generators as controlling
the transmission voltage when in reality the automatic voltage regulators almost always
use the generator terminal voltage as the setpoint. Regulation of the transmission voltage
is typically achieved by occasional manual adjustment of the terminal voltage setpoint by
the generator operator. Quasi-dynamic studies assume that no manual adjustment takes
place during the short-term post-contingency period (0 to 3 minutes). This can be
modeled in the power flow by adding explicit elements that represents the generator main
power transformer if they are not already included. The base case is solved with the
generators regulating the transmission voltage to the desired level and the generator
terminal voltages are recorded. The generator data is then modified to have the generators
regulate their terminal voltage to the level that was present in the base solution. This now
becomes the new base case for contingency analysis.
The second step is to lock taps to model short time response of system. The
automatic tap changers will not have time to fully respond in the short term post
contingency state. For conservative results in quasi-dynamic studies the taps should be
locked at their base case positions in the power flow contingency solution. Contingency
analysis and PV analysis are then performed with these modeling assumptions.
This method is used to differentiate the need and amount of dynamic reactive
resources from static reactive sources. However, it is still recommended that detailed
dynamic simulation be performed to verify the results.
Method 3
If the transmission planner has developed the dynamic models needed for a
dynamic voltage analysis, then they can screen the transmission system using dynamic
simulation to determine the critical contingencies resulting in slow transient voltage
recovery. Generally this screening can be applied to a set of contingencies that is known
to be of interest due to steady-state results or actual experience, rather than be applied to
an exhaustive list of contingencies. Appendix 1 contains a report compiled by the
This document contains proprietary information and shall not be reproduced in whole or in part without prior
written permission of ERCOT
5
DRAFT
ERCOT Dynamics Working Group in 2003 which gives some basic parameters to test the
system. Note that the document discusses ERCOT Transient Voltage Security Criteria.
Just to avoid confusion, the TVS (Transient Voltage Stability) criterion was adopted and
the TVD (Transient Voltage Dip) criterion was not adopted for ERCOT. A number of
consultants screen for critical contingencies using the same basic method. Essentially,
the transmission planner applies a fault at a bus for some length of time and trips either
one or two elements and then after several cycles or seconds of simulation determines if a
bus or a number of buses are below a particular voltage. A full dynamic voltage analysis
would then be performed on the critical contingencies identified by the screening process.
Additional Discussion
Applying the guidelines discussed in Method 1 or 2 would require a minimal
amount of dynamic simulation. Meeting the reactive margins as discussed would meet
the dynamic reactive adequacy requirement, but as it was stated, detailed dynamic
simulations are recommended to verify the dynamic reactive margins are adequate.
Likewise, if these methods indicate that no reactive margin exists or is in fact in deficit
for a critical contingency, dynamic simulation is required for determining the amount and
type of dynamic reactive resources required to ensure the transmission system meets the
ERCOT Dynamic Voltage Recovery criteria.
When performing full dynamic simulations, it is recommended that the
transmission planner include a dynamic load model that takes into account the effect of
small motor (such as residential air conditioners) and large motor characteristics on
voltage recovery.
This document contains proprietary information and shall not be reproduced in whole or in part without prior
written permission of ERCOT
6
Appendix 1
This document contains proprietary information and shall not be reproduced in whole or in part without prior
written permission of ERCOT
7
ERCOT TRANSIENT VOLTAGE SECURITY
CRITERIA DEVELOPMENT (PART I)
PREPARED FOR ERCOT RELIABILITY OPERATIONS SUBCOMMITTEE
BY ERCOT DYNAMICS WORKING GROUP
September 9, 2003
This document contains proprietary information and shall not be reproduced in whole or in part without prior
written permission of ERCOT
8
Table of Contents:
Acknowledgments
Transient Voltage Security Subgroup
Disclaimer
1. Executive Summary and Recommendations
2. Scope of Work and Voltage Stability Problem
2.1 Scope of Work
2.2 Introduction
2.3 Transient Voltage Security
3. Development of Transient Voltage Dip Acceptability Criteria
3.1 Absolute Voltage Magnitude vs. Percent of the Initial Value
3.2 ERCOT TVD Criteria
4. Development of Transient Voltage Stability Criteria
4.1 Factors Involved in TVS and Load Modeling requirements
4.2 Analytical Techniques and Dynamic Simulation
4.3 Margin to Voltage Instability
4.4 ERCOT TVS criteria
5. Conclusions and Further Investigations
6. Bibliography
Appendix A. ERCOT Transient Voltage Security Criteria
Appendix B. A Sample System Transient Voltage Stability Analysis
This document contains proprietary information and shall not be reproduced in whole or in part without prior
written permission of ERCOT
9
Acknowledgments
The ERCOT DWG members thank Mike Connolly of Center Point Energy, and Biju Mathew,
and James Armke of Austin Energy for their support, reviews and suggestions.
This document contains proprietary information and shall not be reproduced in whole or in part without prior
written permission of ERCOT
10
Transient Voltage Security Subgroup:
From 2003 ERCOT Dynamics Working Group
Tom Bao
Vance Beauregard
Roy Boyer
Jose Conto
Reza Ebrahimian*
John Moore
Yan Ou
Juan Santos
Wesley Woitt
Lower Colorado River Authority
American Electric Power
Oncor
ERCOT System Planning
Austin Energy
South Texas Electric Cooperative
ERCOT Operations
ERCOT System Planning
Center Point Energy
* 2003 Chair of DWG
This document contains proprietary information and shall not be reproduced in whole or in part without prior
written permission of ERCOT
11
Disclaimer
The Electric Reliability Council of Texas (ERCOT) Dynamics Working Group prepared this
document. Conclusions reached in this report are a “snapshot in time” that can change with the
addition (or elimination) of plans for new generation, transmission facilities, equipment, or loads.
ERCOT AND ITS CONTRIBUTING MEMBER COMPANIES DISCLAIM ANY
WARRANTY, EXPRESS OR IMPLIED, INCLUDING ANY WARRANTY OF
MERCHANTABILITY OR FITNESS FOR ANY PARTICULAR PURPOSE WHATSOEVER
WITH RESPECT TO THE INFORMATION BEING PROVIDED IN THIS REPORT.
The use of this information in any manner constitutes an agreement to hold harmless and
indemnify ERCOT, its Member Companies, employees and/or representatives from all claims of
any damages. In no event shall ERCOT, its Member Companies, employees and/or
representatives be liable for actual, indirect, special or consequential damages in connection with
the use of this data. Users are advised to verify the accuracy of this information with the original
source of the data.
ERCOT is the corporation that administers the state's power grid. ERCOT serves approximately
85 percent of the state's electric load and oversees the operation of approximately 70,000
megawatts of generation and over 37,000 miles of transmission lines. Its members include retail
consumers, investor and municipally owned electric utilities, rural electric co-ops, river
authorities, independent generators, power marketers, and retail electric providers.
ERCOT is one of ten regional reliability councils in North America operating under the reliability
and safety standards set by the North American Electric Reliability Council (NERC). As a NERC
member, ERCOT's primary responsibility is to facilitate reliable power grid operations in the
ERCOT region by working with the area's electric utility industry organizations. The Public
Utility Council of Texas (PUCT) has primary jurisdictional authority over ERCOT to ensure the
adequacy and reliability of electricity across the state's main interconnected power grid. An
independent Board of Directors comprised of electric utility Market Participants governs ERCOT.
This document contains proprietary information and shall not be reproduced in whole or in part without prior
written permission of ERCOT
12
1. Executive Summary and Recommendations:
The ERCOT Dynamic Working Group (DWG) was directed by the ERCOT Reliability and Operations
subcommittee (ROS) on March 12, 2003 to develop the ERCOT Transient Voltage Security criteria. The
directive was given in the following form:
1. Make a recommendation on an interim operating criteria regarding transient voltage dip to be
used in determining operating limits and making other operational decisions. Consider effects on
loads. Review industry standards as they apply.
2. At this time, do not attempt to determine the costs of compliance.
3. Include in the scope of the investigation what transient voltage performance and operating
criteria, if any, should be adopted for new generating units connecting to the ERCOT
transmission system.
In response, the DWG has developed the following criteria to address ERCOT’S transient voltage
security requirements. These criteria have two parts, part one addresses transient voltage stability and part
two addresses transient voltage dip acceptability. The main focuses of these two subsets are as follows:
1. Transient Voltage Stability criteria, relate to maintaining transient voltage stability at a bus.
2. Transient Voltage Dip Acceptability criteria are based on load sensitivity and are intended to
reduce uncontrolled loss of load.
These criteria described in Appendix A of this report, are intended as interim and should not be
incorporated into the ERCOT operating guides at this time. Since there is a high degree of uncertainty
regarding load models for transient voltage security assessment, DWG does not recommend these criteria
to become mandatory until sufficient experience is gained with their application within ERCOT, and after
they have been proven to be appropriate. However, the DWG encourages and recommends that the
member TDSPs apply these criteria and share their experience regarding their effectiveness for their
future refinements.
This report describes the development of the above ERCOT transient voltage security criteria, and the
procedures for conducting dynamic simulation for transient voltage security using PTI’s PSS/E dynamics
software.
General voltage stability assessment should generally follow this order:
 Steady-state voltage security analysis
 Generator rotor angle stability analysis
 Transient voltage stability analysis
 Transient voltage dip acceptability analysis.
Within the past few months ERCOT has adopted a voltage/reactive series of standards that includes a
steady-state voltage stability criteria. This document has been approved by the ERCOT Technical
Advisory Committee (TAC) and will merge into the ERCOT Operating Guides and Protocols.
This document contains proprietary information and shall not be reproduced in whole or in part without prior written
permission of ERCOT
1
The proposed transient voltage stability and transient voltage dip acceptability criteria given in this report
should be considered for revision within a few years based on experience gained from their application to
ERCOT power system, and further investigation of the ERCOT dynamic load model.
In our investigations we did not find any robust and uniformly applicable criteria to address transient
voltage security. Although the industry has made great strides in understanding the related phenomena
there is still a great deal of work to be done in the areas of load modeling and development of a robust and
uniform approach for assessing transient voltage security. This report intends to describe the present level
of knowledge and techniques used in transient voltage analysis using time-domain transient stability
utilizing PTI’s PSS/E software. It is possible that other robust and uniform methodologies may emerge
that may be more suitable for transient voltage security assessment. However, utilizing the methodology
described in this report will shed light on and provide a better understanding of the problem. As
mentioned the load model is a major uncertainty factor. At this time EPRI has initiated another research
project to improve load model and has solicited ERCOT participation and support. The study team
believes strongly that it is in the interest of ERCOT to support and participate actively in this project.
Because of the load model uncertainties and sensitivity of the load to transient voltage security at each
bus, and lack of experience with the application of these criteria, the proposed criteria given in this report
should be considered as preliminary guides to be used when there are not any better information or guides
available. Each TDSP should exercise judgment in assessing their transient voltage security depending on
the nature of the loads and consequences of possible transient voltage security problems at each bus to
make proper decisions regarding reactive support requirements at that bus.
The open planning process that ERCOT has recently implemented will be a valuable venue in assessing
the effectiveness of these criteria over the next few yeas, if the member TDSPs also consider these criteria
when conducting transient voltage security analysis.
The issue of potential cost for reactive compensation and its balance with the level of desired security has
not been analyzed in this project. Of course with any good engineering solution, the economic feasibility
should be considered. When these criteria are revisited, it may be appropriate to perform an economic
feasibility analysis of their application.
This is the first part of the ERCOT transient voltage security criteria report. A second part will be
amended to this report within a few months briefly describing the effect of generation performance and
operating philosophy on transient voltage security, as described in the third directive given by the ROS to
the DWG.
Remedial measures for reactive support for transient voltage stability are not described in this report.
Summary of the DWG Recommendations:
1. TDSPs should apply these criteria when appropriate and share their experience regarding their
effectiveness. The ERCOT planning open process provides an excellent venue for this activity.
2. These criteria should not be made mandatory until the load model is further investigated and
sufficient experience is gained in their application to ERCOT.
3. ERCOT should participate in the present EPRI project on dynamic load modeling. Additional
load modeling and data collection should be performed to fill any gaps not covered by the EPRI
effort.
This document contains proprietary information and shall not be reproduced in whole or in part without prior written
permission of ERCOT
2
4. Additional investigations will be needed to evaluate cost effectiveness of these guides.
5. After a reasonable period, when enough experience is gained in applying these criteria, they
should be revisited, and possibly revised. At that time also the issue of including these criteria in
the ERCOT Operating Guides should be considered.
This document contains proprietary information and shall not be reproduced in whole or in part without prior written
permission of ERCOT
3
2. Scope of Work and Voltage Stability Problem
2.1 Scope of Work
The ERCOT DWG was given the following directives by the ERCOT ROS on March 12, 2003 for the
development of the ERCOT transient voltage security criteria:
1. Make a recommendation on an interim operating criteria regarding transient voltage dip to be
used in determining operating limits and making other operational decisions. Consider effects on
loads. Review industry standards as they apply.
2. At this time, do not attempt to determine the costs of compliance.
3. Include in the scope of the investigation what transient voltage performance and operating
criteria, if any, should be adopted for new generating units connecting to the ERCOT
transmission system.
In the interim and in response to item 1, the DWG developed criteria using the Western Electric
Coordinating Council (WECC) Transient Voltage Dip (TVD) criteria as a reference (See Appendix A).
This report describes the ERCOT transient voltage security criteria, which also includes transient voltage
stability criteria. The work on the third task will begin after completion of the development of part I of the
ERCOT transient voltage security criteria. The time required for the completion of the third task is
estimated to be three months.
The objective for the development of these criteria is to protect the ERCOT transmission system from a
potential transient voltage instability or voltage collapse. In addition, relevant industry standards and the
effect of the criteria on the load are also investigated.
The DWG conducted a literature search to survey the present level of knowledge and standards available
on the transient voltage security and relevant criteria. Furthermore, the DWG conducted a survey to gauge
the present practices and established criteria by other NERC regional councils. However, no useful
response was received from the survey. This may be an indication that such criteria presently do not exist.
At this stage, the effect of the economics of the criteria is not investigated. Furthermore, since ERCOT
members that would conduct transient voltage stability analysis use PSS/E to conduct their dynamic
stability studies, this work is focused on providing guidance such that relevant analysis can be conducted
and understood using PSS/E dynamics module. Therefore, this report does not cover any emerging
methodologies such as use of Bifurcation theory, and eigenvalue techniques.
2.2 Introduction
Voltage collapse is often a complex process involving several elements including system component
behavior and system operation. The following provides some brief background information. More
detailed information can be obtained from the listed references or from a large body of literature available
elsewhere [1].
Voltage collapse is typically associated with the reactive power demands of loads not being met because
of limitations on the production and transmission of reactive power. Limitations on the production of
reactive power include generator and SVC reactive power limits and the reduced reactive power
This document contains proprietary information and shall not be reproduced in whole or in part without prior written
permission of ERCOT
4
production by capacitors at low voltages. The primary limitations on the transmission of power are the
high reactive power loss on heavily loaded lines, as well as possible line outages that reduce transmission
capacity. Reactive power demands of loads increase with load increases (examples include additional
motor load and increased air conditioning use with increasing temperature), changes in voltage, motor
stalling, or changes in load composition.
A power system without adequate dynamic reactive support can become unstable when subjected to large
disturbances. During such disturbances the transmission system voltage can fall below a critical threshold,
resulting in induction motors dropping out (control devices disconnecting the motors) or motor stalling.
Transient voltage instability or voltage collapse can occur when stalled motors remain connected to the
system, or motors previously disconnected are automatically reconnected causing a large, mostly reactive,
starting current. Furthermore, motors at power plants can drop out or stall upon low voltage, thus leading
to tripping of generators as well. Such a disturbance is classified as a transient voltage stability
phenomenon, with a time frame in the order of seconds. The IEEE/CIGRE task force on power system
stability terms, definitions and classifications refers to this as “short-term voltage stability”. Factors such
as increased use of low inertia compressor motors, air conditioning, heat pumps, and refrigeration,
increased use of voltage-insensitive power electronic loads, and increased use of capacitor banks for
reactive compensation, and more intensive use of transmission systems, are increasing the likelihood of
transient voltage instability [2].
There are several power system changes known to contribute to voltage collapse.





Increase in loading
Generators, synchronous condensers, or SVC reaching reactive power limits
Action of tap-changing transformers
Load recovery dynamics
Line tripping or generator outages
Most of these changes have a significant effect on reactive power production, consumption and
transmission. Switching of shunt capacitors, blocking of tap-changing transformers, re-dispatch of
generation, rescheduling of generator and pilot bus voltages, secondary voltage regulation, load shedding,
and temporary reactive power overload of generators are some of the control actions used as
countermeasures against voltage collapse.
It appears that there are two distinct time frames to consider for voltage stability, transient (0 to 10
seconds or so) and longer term voltage stability (10 seconds to 2 or more hours)[3]. With proper
modeling and data, traditional transient stability programs can be used for the transient time frame. For
the longer time frame, three possibilities exist, traditional load flow based tools, extended term time
domain simulation, or Quasi-Dynamic simulation programs. Because of the significant amount of CPU
and engineering time involved, it seems reasonable to suggest using power flow based tools to calculate
voltage stability margins for the base case and all contingency cases, and use extended term time domain
simulation only to bench mark the power flow results, and to determine the chronology of voltage
instability following a few selected critical contingencies.
While the literature indicates several tools available for voltage stability analysis [2], [4], the tools
currently available for most DWG members are load flow and traditional transient stability programs.
The use of these tools does not guarantee voltage collapse will not occur, or that decisions made as a
This document contains proprietary information and shall not be reproduced in whole or in part without prior written
permission of ERCOT
5
result of studies using these tools will be optimum and the most economical. Judgment must be used,
both in making the studies and interpreting the results.
Performing a voltage stability study usually involves the following activities:





Determine the margin for all design contingencies with all elements in service and some elements
out of service in accordance with the ERCOT planning standards.
In general, voltage stability margins are defined as the difference between the value of a Key
System Parameter at the current operating condition and at the voltage stability critical point.
Key System Parameters used include P-V based parameters, such as area load or power transfer
across an interface; and Q-V based parameters, such as reactive reserve or reactive injection at a
bus or group of buses.
In addition to the criterion for voltage stability margin, TDSPs must establish bus voltage limits.
They may need to establish other criteria such as reactive reserve criteria.
The criteria appropriate for a given system can only be determined after extensive analysis of the
system in order to establish the Key System Parameter and the sensitivities of the system stability
to changes in the Key System Parameter values.
2.3 Transient Voltage Security
There are several factors that may describe transient voltage security at a bus [5], [6], [7]. These include
transient angle stability, transient voltage stability, and transient voltage dip acceptability. Transient angle
stability relates to synchronous generators maintaining synchronism. Loss of synchronism and tripping of
generators can cause transient voltage swings. This issue is well understood and relevant studies are
conducted by TDSPs addressing this issue. There is also an oscillatory phenomenon, which is associated
with power systems that fit the structure of a single equivalent generator supplying an equivalent
composite load, which may be traceable to interaction of induction motor loads with automatic voltage
regulators [8].
Transient voltage stability is related mostly to the stability of dynamic loads such as induction motors.
The small low inertia induction motors that are used in the residential air conditioners are perhaps major
contributors to such phenomenon, during the summer peaks in ERCOT. A typical scenario would be a
fault resulting in a significant, momentary drop in voltage. Motors can react to the voltage drop in several
ways depending on such factors as the type of motor, the type of load, and the motor controls. Residential
window air conditioning units typically have very simple controls. Thus, if the voltage drops and reduces
the electrical torque below the mechanical load torque, the motor may stall, and eventually be
disconnected by the motor thermal overload. Residential split system air conditioners usually have
contactors to control the compressor motor. On low voltage, the contactor will usually disconnect the
motor before it stalls. However, once the fault is cleared and voltage is restored, the contactor may close
restarting the motor. The starting motor will have a highly reactive inrush current, typically 4 to 6 times
full load. Air conditioners with mechanical thermostats are most likely to restart immediately upon
restoration of voltage. Air conditioners with electronic thermostats often have a time delay that will
postpone restarting the compressor motor after voltage is restored for, typically, 5 minutes.
Transient voltage dip acceptability is related to the load sensitivity and is not particularly related to a
system-wide stability problem.
This document contains proprietary information and shall not be reproduced in whole or in part without prior written
permission of ERCOT
6
Our investigations have shown that system-wide voltage stability criteria involving a voltage dip
magnitude and duration to be used for all of the ERCOT transmission buses may not exist. The criterion
for each bus may be different. The transient voltage trajectory at each bus depends on the effect of the
performance of the generators supplying reactive power to the bus (particularly their excitation systems
performance), other sources of reactive power, and the thevenin impedance of the system at that bus, and
its load characteristics. Thus each bus would have different requirements to maintain voltage stability. If
the criteria for transient voltage stability and transient voltage dip acceptability for a bus are determined,
the values describing them maybe different. In other words transient voltage dip acceptability at a bus
does not guarantee that the bus is “transient voltage-stable” and vise versa. To help clarify this issue, in
Appendix B we present a brief description of how to conduct transient voltage stability studies using
PSS/E dynamics program, including an example of the above scenarios.
3. Development of the ERCOT Transient Voltage Dip (TVD)
Acceptability Criteria:
As was described in the previous section, transient voltage dip acceptability is different from transient
voltage stability. TVD is based on load sensitivity. Several organizations such as CBEMA (now ITI),
ANSI, and IBM have proposed such standards to be applied anywhere in a power system to protect the
voltage-sensitive loads. Members of some regional reliability councils such as WECC use TVD criteria as
part of their planning criteria for protection of their loads.
As a starting point, the DWG investigated the development of the WECC criteria. Reference [9] describes
the development of the WECC criteria [10]. The present WECC criteria were developed in the early
1990’s. Some of the WECC members previously had used a minimum swing voltage magnitude of 0.8
p.u. of nominal voltage for assessing their transmission system transient stability. This criterion included
margins to avoid the tripping of the auxiliary nuclear plant induction motors that are protected with undervoltage relays.
The present WECC criteria are established to avoid uncontrolled loss of load for the NERC category B
and C disturbances. The values selected are based upon the response of electronic equipment to voltage
dips. It was believed that these loads are the most sensitive to voltage swings. The values were selected
based on evaluation of the load sensitivity curves to voltage dip and durations published by IBM. The
ANSI/IEEE 446.1987, CBEMA, and SDG&E (San Diego Gas and Electric) curves were also evaluated.
During a one-year trial WECC conducted load sensitivity studies for evaluation of the appropriateness of
the voltage dip criteria and concluded that the criteria was appropriate.
3.1 Absolute Voltage Magnitude vs. Percent of the Initial Value:
The ERCOT TVD criteria are stated in terms of an initial bus voltage. This initial voltage can be defined
in at least two ways, absolute voltage magnitude or percent of initial value. If the absolute voltage
magnitude is used as a criterion where the load is represented at high voltage and the initial voltage is
above 1.00 p.u. (often the case for the 345 kV systems), the voltage on the low voltage buses where the
load is actually connected will be less than 1.00 p.u. Hence, it is more appropriate to use percent voltage
of the initial values than using the absolute voltage magnitude. Both the WECC and the ERCOT TVD
criteria use a percent value relative to the per-disturbance voltage magnitude.
This document contains proprietary information and shall not be reproduced in whole or in part without prior written
permission of ERCOT
7
3.2 The ERCOT TVD Criteria
The ERCOT TVD criteria are presented in the Appendix A and were developed using the WECC criteria
as a reference, some of the differences are described below.
1. The ERCOT criteria are described in six sections for six different conditions to avoid ambiguities.
2. The ERCOT criteria clarify that the percent voltages are relative to the pre-disturbance values and
not the absolute voltage magnitudes.
3. The WECC criteria refer to the effects of the voltage dip on other systems. The DWG felt that
such criteria is difficult to apply since “other” systems has to be defined, and may not apply to
ERCOT, since ERCOT is a single control area. Hence, the ERCOT TVD criteria do not refer to
“other” systems.
4. The WECC criteria do not specifically mention whether the fault duration is included in the
voltage dip duration criteria. The ERCOT TVD criteria clearly specify that the fault duration is
not included in the voltage dip duration criteria.
4. Development of the ERCOT Transient Voltage Stability Criteria
We described in section 2 that transient voltage stability (TVS) is a fast dynamics phenomenon occurring
in the order of seconds. In this section we will describe the mechanisms involved in transient voltage
stability and describe modeling requirements for accurate simulations using PSS/E.
4.1 Factors Involved in TVS and Load Modeling Requirements
The main factors affecting transient voltage stability of a bus are the induction motor load magnitudes and
their characteristics, the thevenin impedance of the system at that bus, and the reactive sources for the
bus. For proper dynamic simulation using PSS/E, the load should be decomposed into similar load types,
such as small motor, large motor, discharge lighting, resistive load, constant power, transformer
saturation, and “remaining load” using PSS/E CLODXX and CIM5XX and /or CIMWXX. To use
CIM5XX or CIMWXX effectively, knowledge of the motor load speed-torque characteristic is required.
Furthermore, the distribution power transformers, feeders, and capacitors should also be included as
appropriate [11].
4.2 Analytical Techniques and Dynamic Simulation
When using PSS/E for short-term voltage stability simulations, appropriate portion of the ERCOT load
should be modeled as described in section 4.1 and [11]. To observe that the system is transient voltage
stable the equivalent motor load terminal voltage (load voltage) and the motor slip should be plotted. If
the slip is increasing after the voltage has passed its maximum then the load is unstable. On the other hand
if the slip is not increasing after the voltage has passed it minimum then the load is stable.
This document contains proprietary information and shall not be reproduced in whole or in part without prior written
permission of ERCOT
8
4.3 Margin to Voltage Instability
Margin to voltage instability is a function of the degree of uncertainty in the models, data, and actual
operating conditions and the sensitivity of the stability limits to these uncertainties. Each TDSP should
consider the above and other factors such as cost of adding compensation to improve voltage stability in
conjunction with the effects of voltage instability on the customers being served when establishing a
margin to voltage instability.
4.4 ERCOT TVS criteria
Proposing a transient voltage stability criterion based on solid data and analysis is problematic in
ERCOT. Our survey suggested few if any regional reliability councils have such a criterion. There are no
known standards that apply. An effective criterion may differ from one bus to another bus within ERCOT.
The analysis tools used by most TDSPs will not guarantee voltage stability is maintained. One of the
most critical components for any simulation, the load composition and dynamic characteristics, is
generally unknown. Each TDSP should use judgment when evaluating voltage stability. With the above
in mind, the following may be used as transient voltage stability criteria when no other guidance is
available:
Considering realistic power transfers between zones,
a. Allow a 5% margin load increase to a zone for category B contingencies and
b. Allow a 2.5% margin load increase to a zone for category C contingencies.
Again as was mentioned earlier, the application of these criteria are not mandatory, and they are proposed
here as guidelines. Individual TDSPs should adjust these values based on local knowledge and conditions.
Furthermore, because of the uncertainties involved in transient voltage stability analysis, particularly of
the nature of the load, the approach and the criteria presented in this report should be revisited in a few
years, after enough experience is gained in applying the above criteria.
5. Conclusions and Further Investigations
This report describes the development of ERCOT transient voltage security criteria. It describes and
demonstrates use of PTI PSS/E in conducting such analysis. The criteria were developed considering the
presently available analytical tools to majority of the ERCOT member TDSPs. The emerging
technologies such as use of eigenvalue methods, energy function, Bifurcation theory, and artificial
intelligence methodologies were not considered. These criteria and procedures are intended as guides and
should be applied after steady-state voltage security and generator rotor angle stability assessment are
completed. Furthermore, transient voltage stability should be assessed before transient voltage dip
acceptability is evaluated. We do not recommend that these criteria be included in the ERCOT Operating
Guides at this time. They are not mandatory, and deviations from these criteria are appropriate based on
engineering judgment and the nature of the loads being served. The engineer conducting such analysis
This document contains proprietary information and shall not be reproduced in whole or in part without prior written
permission of ERCOT
9
should gain a good understanding of induction motor dynamics modeling and aggregate representation in
power systems [12], [13], [14], [15], [16], [17]. This is important not only for the computational
procedures, but also in selecting the proper models for the buses under study and in evaluating the
simulation results.
The criteria given here need to be tested for their effectiveness and feasibility within ERCOT. Each TDSP
is encouraged to perform the necessary evaluations, apply the criteria, and evaluate the effectiveness of
the process and criteria. The recently adopted ERCOT open transmission planning process also is a
valuable venue to test these criteria and evaluate their usefulness. After a few years of experience, these
should be re-evaluated and revised if necessary.
Both TVD and TVS are short time-frame phenomena with maximum duration of approximately 30
seconds. Another aspect of dynamic voltage stability includes extended-term dynamics such as the effects
of excitation limiters, ULTCs, AGCs, etc. Historically, most major voltage collapse incidents developed
over a period of minutes to hours, and the above extended-term dynamic elements were significant
contributors to voltage collapse. Thus, TVD and TVS will not capture these extended term equipment
action, or voltage collapse evolving over an extended period of time. At this time none of the ERCOT
DWG members conduct extended-term dynamic simulations. PTI offers such a tool as an extension to
PSS/E intended for extended-term dynamic simulation. However, few, if any ERCOT members have this
tool. ERCOT DWG should consider this tool or other extended-term dynamic simulation software for
evaluation for further investigation of ERCOT voltage security assessment.
The results of TVD and TVS simulations are highly dependent upon the load model. Currently, there is
no adequate, up-to-date load model or data for ERCOT loads. As mentioned previously, it is unlikely any
one load model or set of load data will be appropriate for every load bus in ERCOT. It is anticipated that
participation in the EPRI load modeling effort will result in some load models and data appropriate to
ERCOT. At present, the best that can be done in most cases is to use generic load models and data, and
thus obtain somewhat generic simulation results. Such results are certainly useful but may lead to overly
conservative or over confident decisions about the ability of the ERCOT system to avoid voltage
instability. The DWG recommends that ERCOT participate in the EPRI load modeling effort. The DWG
also recommends that additional load modeling and data collection be performed to fill any gaps not
covered by the EPRI effort. Establishing criteria is certainly important, but can never fully fulfill its
intended purpose without adequate simulation tools, models, and data.
The second part of this project includes investigation of the effect of generators transient voltage
performance and operating criteria for transient voltage stability.
This document contains proprietary information and shall not be reproduced in whole or in part without prior written
permission of ERCOT
10
6. Biblograhpy
[1] IEEE Committee Report, “Voltage Stability Assessment: Concepts, Practices and Tools”, by
IEEE/PES Power System Stability Subcommittee Special Publication, Aug 2002.
[2] John Diaz de Leon II, and Carson Taylor “Understanding and Solving Short-term Voltage Stability
Problems” Proceedings of the IEEE/PES 2002 Summer Meeting.
[3] Carson Taylor, “Introduction, Definitions, Time Frames/Scenarios, and Incidents”, NERC Survey of
the voltage collapse phenomenon, pp 51-65, Aug. 1991.
[4] Les M. Hajogos, Behnam Danai, “Laboratory Measurements and Models of Modern Loads and Their
Effects on Voltage Stability Studies”, IEEE Transactions on Power Systems, Vol. 13, No. 2, pp 584-592,
May 1998
[5] Y. Xue, T. Xu, B. Liu, and Y. Li ,“Quantitative Assessments for Transient Voltage Security”, IEEE
Transactions on Power Systems, Vol. 15, No. 3, pp. 1077-1083, Aug. 2000.
[6] Y. Xue, T. Xu, B. Lui, Y. Li, “The Formulation and Quantification of Transient Voltage-Dip Security.
In ICEE’98, Korea, Jul. 1998.
[7] Y. Xue, T. Xu, Z. Han, and Y. Li, “A Criterion and Margin for Transient Voltage Stability
Considering Induction Motors”, in IPEC’97, Singapore, May 1997.
[8] F.P. de Mello, “Voltage Oscillatory Instability Caused by Induction Motor Loads”, IEEE Transactions
on Power Systems, Vol. 11, No. 3, Aug. 1996, pp 1279-1285.
[9] J. Kondragunta, and WSCC Reliability Subcommittee, “WECC Supporting Document for Reliability
Criteria for Transmission Planning”, August 1994
[10] NERC/WECC Planning Standards, Revision August 9, 2002
[11] IEEE Committee Report, “Standard Load Models for Power Flow and Dynamic Performance
Simulation”, IEEE Task Force on Load Representation for Dynamic Performance, IEEE Transactions on
Power Systems, Vol. 10, No. 3, pp 1302-1313, August 1995
[12] P. Kundur, Power System Stability and Control, McGraw-Hill, 1994.
[13] C. W. Taylor, Power System Voltage Stability, McGraw-Hill, 1994.
[14] F. Nozari, M. D. Kankam, and W. Price, “Aggregation of Induction Motors for Transient Stability
Load Modeling”, IEEE Transactions on Power Systems, Vol PWRS-2, No. 4, Nov. 1987. pp 1096-1103.
[15] D.C. Franklin, A. Morelato, “Improving Dynamic Aggregation of Induction Motor Models”, IEEE
Transactions on Power Systems, Vol. 9, No. 4, Nov. 1994. pp 1934-1941.
This document contains proprietary information and shall not be reproduced in whole or in part without prior written
permission of ERCOT
11
[16] L. Pereira, D. Kosterev, P. Mackin, D. Davies, J. Undrill, W. Zhu, “An Interim Dynamic Induction
Motor Model for Stability Studies in the WSCC”, IEEE Transaction on Power Systems, Vol. 17, No. 4,
Nov. 2002, pp 1108-1115.
[17] T.Y.J Lem and R.T.H. Alden, “Comparison of Experimental and Aggregated Induction Motor
Responses”, IEEE Transactions on Power Systems, Vol 9, No. 4, Nov. 1994. pp 1895-1900.
[18] J. Shaffer, “Air Conditioner Response to Transmission Faults”, IEEE Transactions on Power
Systems, Vol. 12, No. 2, May 1997, pp 614-621.
[19] B.R. Williams, W. S. Schumus, D. C. Dawson,”Transmission Voltage Recovery Delayed by Stalled
Air Conditioner Compressors”, IEEE Transactions on Power Systems,Vol 7, No.3, Aug 1992, pp 11731179
[20] M. Z. El-Sadek, and F.N. Abdelbarr, “Effects of Induction Motor Load in Provoking Transient
Voltage Instabilities in Power Systems”, Electric Power Systems Research, 17(1989), pp 119-127.
[21] M. Z. El-Sadek, “Voltage Instabilities Subsequent to Short-Circuit Recoveries”, Electric Power
Systems Research, 21(1991) 9-16.
This document contains proprietary information and shall not be reproduced in whole or in part without prior written
permission of ERCOT
12
Appendix A. ERCOT Transient Voltage Security Criteria
The ERCOT transient voltage security criteria are given in the form of two sets of criteria. After analysis
has shown that there are no rotor angle stability problems, the ERCOT transient voltage stability criteria
can be utilized, and then the criteria for ERCOT transient voltage dip acceptability should be applied.
These criteria are provided as interim guidance for applying the applicable sections of the Protocols and
Operating Guides. This guidance does not relieve any entity from their responsibility of complying with
the Protocols and Operating Guides. Deviations from this interim guideline are appropriate when local
conditions or engineering judgment suggest an alternative approach fulfills the requirements of the
Protocols and Operating Guides.
This guideline does not imply that transient voltage simulations for every bus or contingency should be
performed. There may be other, more efficient calculation methods available or emerging for general
assessment of system voltage security. Caution should be taken when using the standard “ZIP” model.
Although this load model is used by ERCOT members, in many cases the ZIP model may result in overly
optimistic results. When motors are a significant part of the load, it is suggested that proper dynamic load
models, such as the PTI PSS/E CLODXX and CIM5XX and/ or CIMWXX models be used. Typical
parameters for induction motors are available in references [11], and [13].
ERCOT Transient Voltage Stability (TVS) Criteria
According to the IEEE voltage stability working group, voltage stability and voltage collapse are defined
as follows: voltage stability is the ability of a system to maintain voltage so that when load admittances
are increased, load power will increase, so that both power and voltage are controllable, voltage collapse
is the process by which voltage instability leads to loss of voltage in significant part of the system.
Transient voltage stability is related mostly to stability of dynamic loads such as induction motors.
Transient voltage instability at a bus may lead to voltage collapse at that bus or even a large portion of the
system.
Proposing a transient voltage stability criterion based on solid data and analysis is problematic in
ERCOT. Our survey suggested few if any regional reliability councils have such a criterion. There are no
known standards that apply. An effective criterion may differ from one bus to another bus within ERCOT.
The analysis tools used by most TDSPs will not guarantee voltage stability is maintained. One of the
most critical components for any simulation, the load composition and dynamic characteristics, is
generally unknown. Each TDSP should use judgment when evaluating voltage stability. With the above
in mind, the following may be used as transient voltage stability criteria when no other guidance is
available:
Considering realistic power transfers between zones,
a. Allow a 5% margin load increase to a zone for category B contingencies and
b. Allow a 2.5% margin load increase to a zone for category C contingencies.
Again as was mentioned earlier, the application of these criteria are not mandatory, and they are proposed
here as guidelines. Individual TDSPs should adjust these values based on local knowledge and conditions.
This document contains proprietary information and shall not be reproduced in whole or in part without prior written
permission of ERCOT
13
Furthermore, because of the uncertainties involved in transient voltage stability analysis, particularly of
the nature of the load, the approach and the criteria presented in this report should be revisited in a few
years.
ERCOT Transient Voltage Dip Acceptability (TVD) Criteria
Transient voltage dip acceptability is related to the load sensitivity and is not particularly related to
system-wide stability problem. The following is proposed by the ERCOT DWG as an interim transient
voltage dip acceptability criteria.
Category
Contingency*
A
Not applicable
Category
Contingency*
B
1.
2.
3.
Category
Contingency*
Except from the time of fault inception to the time the fault is
cleared, the post contingency voltage at a bus should not
drop below 80% of pre–disturbance voltage for longer than
20 cycles.
Except from the time of fault inception to the time the fault is
cleared, the post contingency voltage at a load bus should not
drop below 75% of pre–disturbance voltage.
Except from the time of fault inception to the time the fault is
cleared, the post contingency voltage at a non-load bus
should not drop below 70% of pre–disturbance voltage.
C
Except from the time of fault inception to the time the fault is
cleared, the post contingency voltage at a bus should not
drop below 80% of pre–disturbance voltage for longer than
40 cycles.
Except from the time of fault inception to the time the fault is
2.
cleared, the post contingency voltage at a load bus should not
drop below 70% of pre–disturbance voltage.
Except from the time of fault inception to the time the fault is
3.
cleared, the post contingency voltage at a non-load bus
should not drop below 70% of pre–disturbance voltage.
* Contingencies and faults as defined by NERC planning criteria table and ERCOT Protocols and
Operating Guides.
1.
Note: For the purpose of dynamics simulation the fault duration should be determined based upon
the equipment capabilities which include relay operation time, time delay, and breaker operation
time.
This document contains proprietary information and shall not be reproduced in whole or in part without prior written
permission of ERCOT
14
Appendix B. Sample System Transient Voltage Stability Analysis
In this section we will present an example using conventional time-domain dynamic stability to conduct
transient voltage stability analysis. Transient voltage dip acceptability analysis is conducted in the same
fashion; however, it is more trivial.
Fig.1 shows a sample system one-line diagram used in this illustration. Fig 2, and Fig 3 show the load
flow and dynamics data associated with this system in PSS/E Version 28 format. The induction motor
model is taken from the reference [18]. Induction motor model parameters for several load types are given
in [11] and [13], gathered through research conducted by EPRI.
Note that Fig. 1 includes the models of the distribution power transformer, line, and the capacitor banks.
These are required to conduct an accurate transient voltage stability analysis [11], [13], [18], [19].
Fig 1. Study System One-line Diagram
This document contains proprietary information and shall not be reproduced in whole or in part without prior written
permission of ERCOT
15
0,
100.00
/ PSS/E-28.1
TUE, SEP 02 2003 15:31
9 BUS POWER FLOW TEST CASE
BASE
1,'REMOTGEN', 20.0000,3,
0.000,
0.000,
1,
1,1.00000,
0.0000,
1
2,'REMOTGEN', 138.0000,1,
0.000,
0.000,
1,
1,1.02824, -4.9475,
1
3,'LOCALGEN', 20.0000,2,
0.000,
0.000,
1,
1,1.02577, -1.7904,
1
4,'LOCALGEN', 138.0000,1,
0.000,
0.000,
1,
1,1.02000, -6.6012,
1
5,'138TRANS', 138.0000,1,
0.000,
0.000,
1,
1,1.01246, -7.5153,
1
6,'DISTLINE', 13.8000,1,
0.000,
0.000,
1,
1,1.01966, -10.1919,
1
7,' LOAD1 ', 138.0000,1,
0.000,
0.000,
1,
1,1.01013, -7.9893,
1
8,' LOAD2 ', 138.0000,1,
0.000,
0.000,
1,
1,1.00912, -8.1124,
1
9,'DISTLOAD', 13.8000,1,
0.000,
0.000,
1,
1,0.99050, -13.7715,
1
0 / END OF BUS DATA, BEGIN LOAD DATA
7,'1 ',1,
1,
1,
0.000,
0.000,
0.000,
0.000,
100.000,
-25.000,
1
8,'1 ',1,
1,
1,
0.000,
0.000,
0.000,
0.000,
100.000,
-25.000,
1
9,'1 ',1,
1,
1,
0.000,
0.000,
0.000,
0.000,
50.000,
-20.000,
1
9,'M ',1,
1,
1,
50.000,
20.000,
0.000,
0.000,
0.000,
0.000,
1
0 / END OF LOAD DATA, BEGIN GENERATOR DATA
1,'1 ',
155.576,
49.519,
100.000,
-50.000,1.00000,
0,
300.000,
0.00000,
0.20000,
0.00000,
0.00000,1.00000,1, 100.0,
300.000,
50.000,
1,1.0000
3,'1 ',
150.000,
62.532,
75.000,
-50.000,1.02000,
4,
250.000,
0.00000,
0.20000,
0.00000,
0.00000,1.00000,1, 100.0,
200.000,
50.000,
1,1.0000
0 / END OF GENERATOR DATA, BEGIN BRANCH DATA
2,
7,'1 ',
0.00800,
0.07425,
0.03600, 400.00, 500.00, 500.00, 0.00000, 0.00000, 0.00000, 0.00000,1, 25.00,
1,1.0000
2,
8,'1 ',
0.00800,
0.07425,
0.03600, 400.00, 500.00, 500.00, 0.00000, 0.000 00, 0.00000, 0.00000,1, 25.00,
1,1.0000
4,
5,'1 ',
0.00160,
0.01485,
0.00720, 400.00, 500.00, 500.00, 0.00000, 0.00000, 0.00000, 0.00000,1,
5.00,
1,1.0000
4,
-7,'1 ',
0.00800,
0.07425,
0.03600, 400.00, 500.00, 500.00, 0.00000, 0.00000, 0.00000, 0.00000,1, 25.00,
1,1.0000
5,
-8,'1 ',
0.00800,
0.07425,
0.03600, 400.00, 500.00, 500.00, 0.00000, 0.00000, 0.00000, 0.00000,1, 25.00,
1,1.0000
6,
9,'1 ',
0.01050,
0.06630,
0.00001, 108.00, 108.00, 108.00, 0.00000, 0.00000, 0.00000, 0.00000,1,
1.00,
1,1.0000
7,
-8,'1 ',
0.00320,
0.02720,
0.01580, 400.00, 500.00, 500.00, 0.00000, 0.00000, 0.00000, 0.00000,1, 10.00,
1,1.0000
0 / END OF BRANCH DATA, BEGIN TRANSFORMER DATA
1,
2,
0,'G1',1,1,1,
0.00000,
0.00000,1,'
',1,
1,1.0000
0.00000,
0.06000, 100.00
0.95000,
0.000,
0.000, 250.00, 250.00, 250.00, 0,
0, 1.10000, 0.90000, 1.10000, 0.90000, 33, 0, 0.00000, 0.00000
1.00000,
0.000
3,
4,
0,'G1',1,1,1,
0.00000,
0.00000,1,'
',1,
1,1.0000
0.00000,
0.06000, 100.00
0.97500,
0.000,
0.000, 250.00, 250.00, 250.00, 0,
0, 1.10000, 0.90000, 1.10000, 0.90000, 33, 0, 0.00000, 0.00000
1.00000,
0.000
5,
6,
0,'D1',1,1,1,
0.00000,
0.00000,1,'
',1,
1,1.0000
0.00200,
0.05000, 100.00
0.97500,
0.000,
0.000, 250.00, 250.00, 250.00, 0,
0, 1.10000, 0.90000, 1.10000, 0.90000, 33, 0, 0.00000, 0.00000
1.00000,
0.000
0 / END OF TRANSFORMER DATA, BEGIN AREA DATA
0 / END OF AREA DATA, BEGIN TWO-TERMINAL DC DATA
0 / END OF TWO-TERMINAL DC DATA, BEGIN SWITCHED SHUNT DATA
9,0,1.50000,0.50000,
0,
15.00, 1, 15.00
0 / END OF SWITCHED SHUNT DATA, BEGIN IMPEDANCE CORRECTION DATA
0 / END OF IMPEDANCE CORRECTION DATA, BEGIN MULTI-TERMINAL DC DATA
0 / END OF MULTI-TERMINAL DC DATA, BEGIN MULTI-SECTION LINE DATA
0 / END OF MULTI-SECTION LINE DATA, BEGIN ZONE DATA
0 / END OF ZONE DATA, BEGIN INTER-AREA TRANSFER DATA
0 / END OF INTER-AREA TRANSFER DATA, BEGIN OWNER DATA
0 / END OF OWNER DATA, BEGIN FACTS DEVICE DATA
0 / END OF FACTS DEVICE DATA
Fig 2. Study System Load Flow Data in PTI PSS/E RAWD Format
This document contains proprietary information and shall not be reproduced in whole or in part without prior written
permission of ERCOT
16
1,'GENROU',1,6.0,0.025,0.75,0.05,5.0,0,2.1,2.0,0.22,0.5,0.2,0.18,0.1,0.4,/REMOTGEN
1,'EXAC1',1,0,0,0,400,0.02,5,-4.5,0.166,0.03,1,0.2204,0.3986,1,3,0.044,4,0.25,/REMOTGEN
3,'GENROU',1,6.0,0.025,0.75,0.05,5.0,0,2.1,2.0,0.22,0.5,0.2,0.18,0.1,0.4,/LOCALGEN
3,'EXAC1',1,0,0,0,400,0.02,5,-4.5,0.166,0.03,1,0.2204,0.3986,1,3,0.044,4,0.25,/LOCALGEN
9,'CIM5BL',M,2,0.025,0.08,5,0.028,0.04,0.07,0.03,1,0.06,1.2,0.6,0,1.2,0.3,0,0,0,1,0,/
Fig 3. Study System Dynamics Data in PTI PSS/E DYDA Format
Figs 4, 5, 6, and 7 show the results of a simulation for duration of 2 and 5 seconds. Figs 4, and 6 show the
voltage at bus 9 and the slip of aggregate induction motor model. The fault duration was 4 cycles, and the
fault admittance was 1000 MVA. Plots in Fig 4 and 5 are for the same simulation as plots in figs 6 and 7,
but plotted with a different time length. Note that the voltage at bus 9 recovers in less than one seconds,
and the motor slip increases during the fault. However, after the fault clears the motor slip reduces and
stabilizes to a constant value. Since the slip has reduced to a small constant value and voltage has
recovered, the induction motor is stable; hence, bus 9 maintains transient voltage stability.
Figs 4,5, 6,and 7 show the voltages at bus 5, 6, 7, and 9, and the motor’s Telec, Tload, Slip, P, and Q. We
can see that the Telec is larger than Tload after the fault clears. Since the Telect is larger than Tload, the
motor remains stable [5]. Note that the reactive power is increasing during the fault and reduces and
becomes constant after the fault has cleared. Similarly the real power consumption P during the fault
increases, and returns to a constant value after the fault has cleared.
In summary, since Telec is larger than Tload throughout the disturbance and slip returns to a small
constant value, we can conclude that this bus maintains voltage stability when subjected to the described
disturbance.
Now, let us consider applying a 7-cycle fault with fault admittance of 1000 MVA. Figs 8, 9, 10, 11 show
the results of this simulation for duration of 2 and 5 seconds. Figs 8, and 10 show the voltage at bus 9 and
the slip of the motor. Since the slip is monotonically increasing while the motor terminal voltage has
passed it is maximum, the motor is unstable. Figs 8, 9, 10, and 11 show that indeed the motor stalls, if it
remains connected. Note that this example is intended to demonstrate instability. However, it is possible
that the motor contactor may disconnect the motor from the system, which would yield different results.
Figs 8, 9, 10, and 11show the voltage at buses 5, 6, and 9, Telec, Tload, slip, P, and Q. Note that during
the fault the motor Q increases, that is the motor begins to absorb a large amount of reactive power. Telec
is less than Tload, which indicates that the motor is unstable. Hence there are two indications of the motor
instability 1) the slip is increasing while the terminal voltage has passed its maximum, and 2) Telec is less
than Tload even after the fault has cleared [5], [20], [21].
In summary, since Telec is less than Tload and the slip increases monotonically after the voltage has
passed its maximum, we can conclude that this bus does not maintains voltage stability when subjected to
the described disturbance.
This document contains proprietary information and shall not be reproduced in whole or in part without prior written
permission of ERCOT
17
Fig 4. Stable scenario.
This document contains proprietary information and shall not be reproduced in whole or in part without prior
written permission of ERCOT
18
Fig 5. Stable scenario.
This document contains proprietary information and shall not be reproduced in whole or in part without prior
written permission of ERCOT
19
Fig 6. Stable scenario.
This document contains proprietary information and shall not be reproduced in whole or in part without prior
written permission of ERCOT
20
Fig 7. Stable scenario.
This document contains proprietary information and shall not be reproduced in whole or in part without prior
written permission of ERCOT
21
Fig 8. Unstable scenario.
This document contains proprietary information and shall not be reproduced in whole or in part without prior
written permission of ERCOT
22
Fig 9. Unstable scenario.
This document contains proprietary information and shall not be reproduced in whole or in part without prior
written permission of ERCOT
23
Fig 10. Unstable scenario.
This document contains proprietary information and shall not be reproduced in whole or in part without prior
written permission of ERCOT
24
Fig 11. Unstable scenario.
This document contains proprietary information and shall not be reproduced in whole or in part without prior
written permission of ERCOT
25
Download