Government of South Australia GC21 (Edition 1 as amended) General Conditions of Subcontract for Design (to the extent specified) and Construction Page ii of v Department of Planning, Transport and Infrastructure 2009 This work is copyright. Apart from any use as permitted under the Copyright Act 1968 (Cwlth), no part may be reproduced by any process without written permission. ACKNOWLEDGMENT The South Australian Government Department of Planning, Transport and Infrastructure acknowledges authority from the New South Wales Department of Finance and Services to use the New South Wales Government GC21 (Edition 1) General Conditions of Contract as the basis for this document. Page iii of v TABLE OF CONTENTS SUBCONTRACT FRAMEWORK ...................................................................................... 1 Roles and relationships .............................................................................................. 1 1. General responsibilities .............................................................................. 1 2. Authorised persons .................................................................................... 1 3. Co-operation .............................................................................................. 2 4. Duty not to hinder performance .................................................................. 2 5. Early warning ............................................................................................. 2 6. Evaluation and monitoring .......................................................................... 2 The Subcontract .......................................................................................................... 3 7. The Subcontract ......................................................................................... 3 8. Assignment ................................................................................................ 3 9. Governing law of the Subcontract............................................................... 3 10. Scope of the Subcontract Works, Temporary Work and work methods ...... 3 Statutory Requirements and guidelines .................................................................... 5 11. Statutory Requirements.............................................................................. 5 12. Goods and Services Tax ............................................................................ 6 12A. South Australian policy matters .................................................................. 7 12C. Australian Government Agreement ............................................................ 8 13. Compliance with codes .............................................................................. 9 14. Collusive arrangements.............................................................................. 9 15. Work health and safety management ....................................................... 10 16. Industrial relations management .............................................................. 10 17. Quality management ................................................................................ 10 18. Environmental management..................................................................... 11 19. NOT USED .............................................................................................. 13 20. NOT USED .............................................................................................. 14 21. NOT USED .............................................................................................. 14 22. NOT USED .............................................................................................. 14 23. Media releases and enquiries................................................................... 14 24. Registration and licences ......................................................................... 14 Management duties ................................................................................................... 14 25. Time management ................................................................................... 14 26. Working days and hours of work .............................................................. 16 27. Intellectual property .................................................................................. 16 28. Licences and approvals............................................................................ 17 29. Care of people, property and the environment ......................................... 17 30. Notices and instructions in writing ............................................................ 18 Sub-subcontractors, Suppliers and Consultants.................................................... 18 31. Sub-subcontractor relationships ............................................................... 18 Page iv of v 32. Engaging Sub-subcontractors .................................................................. 20 33. Sub-subcontractors' warranties ................................................................ 20 34. Consultant and Supplier relationships ...................................................... 20 CARRYING OUT THE SUBCONTRACT WORKS .......................................................... 20 Starting ...................................................................................................................... 20 35. Start-up workshop .................................................................................... 21 36. Insurance ................................................................................................. 21 37. Security .................................................................................................... 23 38. Site access............................................................................................... 25 39. Engagement of Valuer.............................................................................. 26 The Site ...................................................................................................................... 26 40. Site information ........................................................................................ 26 41. Site Conditions ......................................................................................... 27 Design ........................................................................................................................ 30 42. Ambiguities .............................................................................................. 30 43. Subcontractor's Documents ..................................................................... 31 44. Adopting Contractor's Documents ............................................................ 32 45. Submitting Subcontractor's Documents .................................................... 33 46. Innovation ................................................................................................ 33 Construction .............................................................................................................. 34 47. Setting out the Works ............................................................................... 34 48. Construction ............................................................................................. 35 49. Testing ..................................................................................................... 35 50. Defects ..................................................................................................... 36 51. Acceptance with Defects not made good.................................................. 37 Changes to work ....................................................................................................... 37 52. Variations ................................................................................................. 37 53. Changes in Statutory Requirements ......................................................... 40 Changes to time ........................................................................................................ 40 54. Extensions of time .................................................................................... 40 55. Delay costs .............................................................................................. 41 56. Acceleration ............................................................................................. 43 57. Contractor's suspension ........................................................................... 43 58. Subcontractor's suspension ..................................................................... 44 Payment ..................................................................................................................... 44 59. 60. 61. 62. 63. 64. 65. 66. The Subcontract Price .............................................................................. 44 Entitlements ............................................................................................. 45 Prepayment .............................................................................................. 46 Payment Claims ....................................................................................... 47 Payments ................................................................................................. 50 Completion Amount .................................................................................. 51 Final payment .......................................................................................... 51 Interest on late payments ......................................................................... 52 Page v of v 67. Set-off ...................................................................................................... 53 Completion ................................................................................................................ 53 68. Early use .................................................................................................. 53 69. Completion ............................................................................................... 54 70. Close-out workshop ................................................................................. 54 71. After Completion ...................................................................................... 54 CLAIM AND ISSUE RESOLUTION ................................................................................. 54 Claim resolution ........................................................................................................ 55 72. Subcontractor's Claims ............................................................................ 55 Issue resolution......................................................................................................... 56 73. Notification of Issue .................................................................................. 56 74. Resolution by senior executives ............................................................... 57 75. Expert Determination................................................................................ 57 76. Parties to perform the Subcontract ........................................................... 59 TERMINATION ................................................................................................................ 59 77. Termination for Subcontractor's Default or Insolvency .............................. 59 78. Termination for Contractor's convenience ................................................ 60 79. Termination for Contractor's default ......................................................... 61 80. Termination of Contract ............................................................................ 61 81. Termination notices .................................................................................. 62 MEANINGS ..................................................................................................................... 62 82. Interpretation ............................................................................................ 62 83. Definitions ................................................................................................ 62 Meanings of words and phrases .............................................................................. 62 SUBCONTRACT INFORMATION ..................................................................................... 2 Page 1 of 69 SUBCONTRACT FRAMEWORK This section deals with the purpose and structure of the Subcontract. It allocates responsibilities and sets up the procedures for making the Subcontract work. Underlying it are the basic principles of this Subcontract: co-operative contracting, enhanced communication, clear definition of roles, responsibility for outcomes, and focus on enabling best practice. Roles and relationships Although the parties have different responsibilities, co-operation is a key element of the Subcontract. 1. General responsibilities 1.1 1.2 1.3 2. The Subcontractor must: 1.1.1 construct the Subcontract Works including any required Design to Completion in accordance with the Subcontract; 1.1.2 perform the Subcontractor's Design obligations as specified in Subcontract Information item 37A; and 1.1.3 perform and observe all its other obligations under the Subcontract. The Contractor must: 1.2.1 pay the Subcontractor the Subcontract Price for its performance, in accordance with and subject to the Subcontract. The basis of payment may be lump sum, Schedule of Rates or a combination of these as referred to in clause 59 and specified in Subcontract Information item 43; and 1.2.2 perform and observe all its other obligations under the Subcontract. The Contractor may give instructions to the Subcontractor concerning the Subcontract Works and anything connected with the Subcontract Works, and the Subcontractor must comply at its own cost unless an entitlement to payment is specified under clause 60.1. Authorised persons 2.1 The Subcontractor must ensure that at all times there is a person appointed to act with its full authority in all matters relating to the Subcontract as the Subcontractor's Authorised Person and must keep the Contractor informed in writing of the name of that person, and of any change. If the Contractor reasonably objects to the person appointed from time to time, the Subcontractor must replace that person. 2.2 The Contractor must ensure that there is a person appointed to act on behalf of the Contractor in relation to the Subcontract as the Contractor's Authorised Person. The Contractor must keep the Subcontractor informed in writing of the name of that person and of any change. The person does not act as independent certifier, assessor or valuer. The person acts only as agent of the Contractor. Page 2 of 69 2.3 3. Co-operation 3.1 4. 6. The parties must do all they reasonably can to co-operate in all matters relating to the Subcontract, but their rights and responsibilities under the Subcontract (or otherwise) remain unchanged unless the parties agree in writing to change them. Duty not to hinder performance 4.1 5. The Contractor will advise the Subcontractor in writing if the Contractor's Authorised Person delegates any of its powers to others. Each party must do all it reasonably can to avoid hindering the performance of the other under the Subcontract. Early warning 5.1 Each party must do all it reasonably can to promptly inform the other of anything of which it becomes aware which is likely to affect the time for Completion, cost or quality of the Subcontract Works, and the parties must then investigate how to avoid or minimise any adverse effect on the Subcontract Works and Scheduled Progress. 5.2 Clause 5.1 does not change the rights and responsibilities of either party under the Subcontract, unless they agree in writing to change them. 5.3 Neither party may disclose in any Issue resolution proceedings (including Expert Determination and litigation) anything discussed or provided under clause 5.1. Evaluation and monitoring As the project proceeds, regular meetings (usually monthly) allow the parties to evaluate performance and identify priorities for improvement. These meetings allow others concerned with the Works to participate, where appropriate. 6.1 If required by the Contractor, the Subcontractor must meet regularly with those concerned with the Contract, at the times specified by the Contractor, to evaluate and monitor performance of the Subcontract and project using the Performance Evaluation and Performance Evaluation Record forms in Attachments 2 and 3. The forms in Attachments 2 and 3 may be amended by agreement between the parties. These forms list appropriate topics for performance assessment and allow progress to be monitored as the project proceeds. The parties may amend the forms to suit the specific attributes of the Subcontract and project. The forms provide a structure for evaluation and for discussion, and focus on achievable improvements in project communication and management. 6.2 Participation in meetings does not give the participants any additional rights or responsibilities. 6.3 Attachments 1, 2 and 3 are not part of the Subcontract. Nothing concerning or in connection with them changes either party's rights and responsibilities, or can be relied on or used by one party against another in any proceedings. 6.4 Each party and any others who participate in the evaluation and monitoring meetings must meet their own costs for attendance at the meetings, and the parties to the Contract will share equally the other costs. Page 3 of 69 THE SUBCONTRACT 7. The Subcontract The Subcontract is formed by the signing of the Subcontract Agreement by the parties, or by the Contractor sending a letter awarding the Subcontract to the Subcontractor (Letter of Award). 7.1 The Subcontract is made up solely of the Subcontract Documents, which supersede all understandings, representations and communications between the parties related to the subject matter of the Subcontract made before the Date of Subcontract. The Subcontract Documents are: 7.1.1 these General Conditions of Subcontract; 7.1.2 the Subcontract Information; 7.1.3 annexed Schedules; 7.1.4 Contractor's Documents (at the Date of Subcontract); and 7.1.5 any documents listed in Subcontract Information item 17 as Reference Subcontract Documents. The Letter of Award (or the Subcontract Agreement, if used instead) is a Reference Subcontract Document. 8. 7.2 The Subcontract Documents must be read as a whole, and anything in one such document must be read as included in all other such documents, unless the context requires otherwise. 7.3 The terms of the Subcontract cannot be amended or waived unless both parties agree in writing. 7.4 The Contractor must give the Subcontractor the number of copies of the Contractor's Documents in Subcontract Information item 18 Assignment 8.1 9. Governing law of the Subcontract 9.1 10. The Subcontractor must not assign a right or benefit under the Subcontract without first obtaining the Contractor's consent in writing. The Subcontract is governed by the laws of South Australia, and the parties submit to the non-exclusive jurisdiction of the courts of South Australia. Scope of the Subcontract Works, Temporary Work and work methods The Subcontract Works 10.1 The scope of the Subcontract Works is described in brief in Subcontract Information item 3 and more specifically in the Contractor's Documents and other Subcontract Documents (as applicable), and includes: 10.1.1 all the work specifically referred to in or otherwise contemplated by the Subcontract; Page 4 of 69 10.2 10.3 10.1.2 all items not specifically referred to or described in the Subcontract which nonetheless are required to complete the Subcontract Works and achieve the effective and efficient use and operation of the Subcontract Works; 10.1.3 all items referred to in one or more of the Subcontract Documents or otherwise necessary for the Subcontract Works to be fit for the purposes required by the Subcontract but omitted from other Subcontract Documents. Those omitted items are included in the scope of the Subcontract Works, unless the context requires otherwise; and 10.1.4 all items of work reasonably inferred from the Subcontract Documents as necessary to properly execute and complete the Subcontract Works. The Subcontractor acknowledges that: 10.2.1 it is both experienced and expert in work of the type and scale of the Subcontract Works; and 10.2.2 it has made full allowance in the Subcontract Price for the matters referred to in clause 10.1. The Subcontractor acknowledges that Variations instructed by the Contractor will cause the scope of the Subcontract Works to change. Temporary Work 10.4 The Subcontractor must carry out and be responsible for all Temporary Work, and carry out, perform, provide and do everything necessary including all ancillary or other work for or in connection with the Design (to the extent applicable) and construction of the Subcontract Works, subject to the following: 10.4.1 The Contractor may instruct the Subcontractor at any time to use a particular method or type of Temporary Work and the Subcontractor must comply with the Contractor's instruction. 10.4.2 Subject to clause 10.4.3, if the Contractor's instruction directly causes the Subcontractor to incur necessarily and unavoidably any extra costs when compared with the costs the Subcontractor would have incurred had the Contractor not given the instruction, the Subcontractor may be entitled to those extra costs and an extension of time under clause 54 (if applicable). 10.4.3 If the need for the instruction in clause 10.4.1 arises from the Subcontractor's own act or omission, then the Subcontractor is not entitled to those extra costs or extensions of time. Work methods 10.5 The Subcontractor is free to use any work method, subject to the following: 10.5.1 The Subcontractor is solely responsible for all work methods, whether specified in the Subcontract or not. 10.5.2 The Subcontractor warrants that it has undertaken all necessary investigation and inquiry to satisfy itself that all work methods Page 5 of 69 specified in the Subcontract or which the Subcontractor otherwise proposes to use are appropriate for the purposes of the Subcontract. 10.5.3 If a particular work method is specified in the Subcontract, the Subcontractor must use it. 10.5.4 If a particular work method is specified in the Subcontract but it is not possible to use that method, the Subcontractor must use another method without entitlement to extra cost or an extension of time. 10.5.5 If a particular work method for which the Subcontractor is responsible is impractical and the Subcontractor, with or without the instruction of the Contractor, uses another work method by necessity to complete the Subcontract Works, the Subcontractor is not entitled to an extension of time or extra cost. 10.5.6 The Contractor may instruct the Subcontractor at any time to use a particular work method. 10.5.7 Subject to clauses 10.5.4 and 10.5.5, if the Contractor's instruction directly causes the Subcontractor to incur necessarily and unavoidably any extra costs when compared with the costs the Subcontractor would have incurred had the Contractor not given the instruction, the Subcontractor is entitled to those extra costs (if it demonstrates to the reasonable satisfaction of the Contractor that it has incurred such extra costs) and may be entitled to an extension of time under clause 54 (if applicable). Statutory Requirements and guidelines 11. Statutory Requirements 11.1 The Subcontractor is responsible for: 11.1.1 compliance with all Statutory Requirements, subject to clause 53, except if (because of the nature of the requirement) only the Contractor or others can comply; and 11.1.2 the giving of all notices necessary to comply with Statutory Requirements and the payment of all necessary fees, charges and other imposts, other than those notices and imposts to be given or paid by the Contractor under the Subcontract or the Principal (or given or paid by the Contractor or the Principal prior to the Date of Subcontract). Clause 53 deals with changes in Statutory Requirements 11.2 Upon request by the Contractor and as a condition of achieving Completion, the Subcontractor must give to the Contractor all original documents issued by authorities or providers of services, including those evidencing approvals, authorisations and consents in connection with the Subcontract Works and the Site. Page 6 of 69 12. Goods and Services Tax The Subcontract Price and any associated amount is Goods and Services Tax inclusive. 12.1 In this clause 12 the expressions "adjustment note", "consideration", "Goods and Services Tax", "GST", "input tax credit", "supply", "tax invoice", "recipient", "Recipient Created Tax Invoice" ("RCTI") and "taxable supply" have the meanings given in the A New Tax System (Goods and Services Tax) Act 1999 (Cwlth) and the expression "net dollar margin" has the meaning given in the guidelines issued by the Australian Competition and Consumer Commission. Calculation of GST 12.2 Unless otherwise expressly stated in the Subcontract, all prices, rates or other sums payable or for which payment is to be made under or in accordance with the Subcontract, include an amount for GST. 12.3 No additional amount on account of GST is payable by a party who receives a taxable supply under or in connection with the Subcontract. All amounts payable reflect the GST-inclusive market value of the taxable supply. 12.4 Any contract entered into by a party to the Subcontract with a third party which involves supplies being made, the cost of which will affect the cost of any supplies made under or in connection with the Subcontract, must include a clause including equivalent terms to clauses 12.2, 12.3 and 12.4. GST invoices 12.5 The Contractor will issue a tax invoice for each taxable supply it makes to the Subcontractor without request. 12.6 Each party must immediately notify the other party if it ceases to be registered for GST. 12.7 Each party acknowledges and warrants that at the time of entering into the Subcontract, it is registered for the GST. Reimbursable expenses 12.8 If the Subcontract requires a party to pay for, reimburse or contribute to any expense, loss or outgoing ("reimbursable expense") suffered or incurred by the other party, the amount required to be paid, reimbursed or contributed by the first party must be the sum of: 12.8.1 the amount of the reimbursable expense net of input tax credits (if any) to which the other party (or its representative member) is entitled in respect of the reimbursable expense; and 12.8.2 to the extent that the other party's recovery from the first party is consideration for a taxable supply to the first party, any GST payable in respect of that supply. Contractor supplies 12.9 If the Contractor makes any supply to the Subcontractor as a consequence of any matter arising under or in connection with this Subcontract, the Subcontractor must pay to the Contractor on demand an amount equal to any GST payable in relation to that supply. Pay As You Go 12.10 If the Subcontractor does not quote its ABN in its tender (to be provided in Subcontract Information item 8) or on its Payment Claims or invoices, or the Page 7 of 69 Subcontractor does not otherwise advise the Contractor of its ABN relating to the service, the Contractor will withhold tax from payments in accordance with the A New Tax System (Pay As You Go) Act 1999 (Cwlth). Fines and penalties 12.11 Nothing in this clause requires the Contractor to pay any amount on account of a fine, penalty, interest or other amount for which the Subcontractor is liable as a consequence of failure by the Subcontractor to comply with legislation which governs GST. 12A. South Australian policy matters 12A.1 Nothing in the Subcontract derogates from the powers of the AuditorGeneral under the Public Finance and Audit Act 1987 (SA). 12A.2 The Subcontractor must, if it is a relevant employer within the meaning of the Equal Opportunity for Women in the Workplace Act 1999 (Cth) comply with its obligations under that Act, and use its best endeavours to ensure that any subcontractor who is a relevant employer complies with its obligations under that Act. 12A.3 The Subcontractor must not accept the services of any person who, either directly or through an independent contractor or third party, within the last three years, has received a separation package from the South Australian Government under its various schemes where the service may breach the conditions under which the separation package was paid to the former public sector employee. 12B. Compliance with Building Code 2013 12B.1 For the purpose of this clause 12B, the following definitions shall apply: ‘the Building Code’ means the Building Code 2013. The Building Code can be downloaded from http://www.fwbc.gov.au/building-code/; ‘the Supporting Guidelines’ means the Supporting Guidelines for the Building Code 2013; ‘the Organisation’ means the State of South Australia to which the Commonwealth has directed the Program Expenditure; ‘the Program Expenditure’ mean the funding provided by the Commonwealth for the Project; ‘the Project Parties’ means all contractors, subcontractors, consultants, and employees who perform on Site work in relation to the Project; ‘the Project’ means the works to be executed through the Program Expenditure. 12B.2 The Contractor must comply with the Building Code. 12B.3 Compliance with the Building Code shall not relieve the Contractor from responsibility to perform the Contract, or from liability for any defect in the works arising from compliance with the Building Code. 12B.4 Where a change in the Contract is proposed and that change would affect compliance with the Building Code, the Contractor must submit a report to the Commonwealth specifying the extent to which the Contractor’s compliance with the Building Code will be affected. 12B.5 The Contractor must maintain adequate records of the compliance with the Page 8 of 69 Building Code by: 12B.5.1 the Contractor; 12B.5.2 its subcontractors; 12B.5.3 consultants; and 12B.5.4 its Related Entities (refer Section 8 of the Building Code). 12B.6 If the Contractor does not comply with the requirements of the Building Code in the performance of this Contract such that a sanction is applied by the Minister for Employment and Workplace Relations, the Code Monitoring Group or the Commonwealth, without prejudice to any rights that would otherwise accrue, those parties shall be entitled to record that noncompliance and take it, or require it to be taken, into account in the evaluation of any future tenders that may be lodged by the Contractor or a related entity in respect of work funded by the Commonwealth or its agencies. 12B.7 The Contractor must not appoint a subcontractor or consultant in relation to the Project where: 12B.8 12B.7.1 the appointment would breach a sanction imposed by the Minister for Employment and Workplace Relations; or 12B.7.2 the subcontractor or consultant has had an adverse Court or Tribunal decision (not including decisions under appeal) for a breach of workplace relations law, work health and safety law, or workers’ compensation law and the tenderer has not fully complied, or is not fully complying, with the order. The Contractor agrees to require that it and its subcontractors or consultants and its related entities provide the Commonwealth or any person authorised by the Commonwealth, including a person occupying a position in the Fair Work Building Industry Inspectorate, with access to: 12B.8.1 inspect any work, material, machinery, appliance, article or facility; 12B.8.2 inspect and copy any record relevant to the Project the subject of this Contract; and 12B.8.3 interview any person as is necessary to demonstrate its compliance with the Building Code. 12B.9 The Contractor agrees that the Contractor and its related entities will agree to a request from the Commonwealth or any person authorised by the Commonwealth, including a person occupying a position in the Fair Work Building Industry Inspectorate, to produce a specified document within a specified period, in person, by fax or by post. 12B.10 The Contractor must ensure that all subcontracts impose obligations on subcontractors equivalent to the obligations under this clause 12B. 12C. Australian Government Agreement 12C.1 For the purpose of this clause 12C, the following definitions shall apply: ‘Agreement’ means the agreement between the Commonwealth of Australia and State of South Australia that will be entered for the provision of funds for the Project; Page 9 of 69 ‘OHS Accreditation Scheme’ means the Australian Government Building and Construction OHS accreditation scheme established by the Fair Work (Building Industry) Act 2012; ‘Project’ means the project to construct the project name. 12C.2 The Subcontractor acknowledges that the State will enter into an Agreement. 12C.3 The Subcontractor agrees to cooperate in all respects during the life of the Subcontract to enable the State to perform its obligations under the Agreement and without limitation, the Subcontractor will: 12C.3.1 preserve the confidentiality of the Commonwealth Funding Agreement; 12C.3.2 not do anything or permit anything to be done (whether by act or omission) which may cause or contribute towards a breach of the Agreement by the State or otherwise prejudice the Agreement; 12C.3.3 provide any information requested by the Commonwealth pursuant to the Agreement. 12C.4 In the event that the Commonwealth either: 12C.4.1 terminates the Agreement; or 12C.4.2 otherwise withdraws funding for the Project, then the Contractor has the right to terminate this Subcontract with no liability to the Contractor, except that the Contractor will pay the Subcontractor for services rendered prior to such termination. 12D. NOT USED 13. Compliance with codes The South Australian Government has established codes of practice, which address principles and standards of behaviour in the construction industry. 13.1 14. Subject to the express provisions of the Subcontract, the parties must comply with the relevant provisions of the codes of practice listed in Subcontract Information item 14. Collusive arrangements 14.1 The Subcontractor warrants and represents to the Contractor and agrees with the Contractor that it is a fundamental condition of the Subcontract that: 14.1.1 14.1.2 the Subcontractor has no knowledge of the tender price of any other tenderer for the Subcontract; except as disclosed in its tender, and by agreement in writing with the Contractor, it has not entered into any contract, arrangement or understanding to pay or allow any money directly or indirectly to a trade or industry association or to or on behalf of Page 10 of 69 any other tenderer in relation to its tender or this Subcontract, nor paid or allowed any money on that account, nor will it pay or allow any money on that account; and 14.1.3 15. if the Subcontractor pays to a trade association, industry association or another tenderer or pays to anyone on behalf of a trade association, industry association or another tenderer any money in breach of clause 14.1.2, the Subcontractor must immediately give the Contractor written notice of such an event and such money is deemed to be held on trust for and becomes immediately payable to the Contractor. The Subcontractor must use its best endeavours to recover the money and pay it to the Contractor. If it fails to do so within the time specified in a notice by the Contractor to the Subcontractor or otherwise (in the absence of a notice) within a reasonable time, the Contractor will be entitled to withhold, deduct or set off from any payment due to the Subcontractor on any account an equivalent sum or make a demand against the Undertakings provided under clause 37. Work health and safety management The Subcontractor must be committed to creating a safe working environment and to continuous improvement in work health and safety. 16. 15.1 The Subcontractor is responsible for and must comply with the requirements of the Subcontract for work health and safety, subject to the express provisions of the Work Health and Safety Act 2012 (SA) and the Work Health and Safety Regulations 2012 (SA). 15.2 Where applicable, as indicated in Subcontract Information item 16, at least 14 days before starting Design (if applicable) and construction, the Subcontractor must document, submit and implement a work health and safety management plan which complies with the Work Health and Safety Regulations 2012 (SA). 15.3 The Subcontractor must systematically manage its work health and safety management processes in accordance with any systems, plans, standards and codes specified in the Subcontract. 15.4 The Subcontractor must demonstrate to the Contractor, whenever requested, that it has met and is meeting at all times its obligations under clauses 15.1 to 15.3. Industrial relations management The Subcontractor must manage industrial relations at the enterprise level, and to integrate industrial relations management activities into subcontract planning and management, subject to the Contractor's overall control of industrial relations management on the Site. The Subcontractor must manage all aspects of industrial relations in connection with its Sub-subcontractors, Suppliers and Consultants, and keep the Contractor informed of industrial relations issues which affect or are likely to affect the carrying out of the Subcontract Works. 17. Quality management The Subcontractor must and it must also ensure that its Sub-subcontractors, Suppliers and Consultants systematically plan and manage their work to achieve specified quality Page 11 of 69 outcomes, reduce the occurrence and costs of error and waste and to achieve continuous improvement in the quality of the product or service provided. 17.1 The Subcontractor must systematically manage its processes in accordance with any quality management systems, plans, standards and codes specified in the Subcontract. 17.2 The Subcontractor must: 17.3 18. 17.2.1 submit documentation required by the Subcontract by the time or times specified in the Subcontract; 17.2.2 review and update the Subcontractor's quality management procedures and documentation so they remain adequate at all times to manage and ensure the quality of the Subcontract Works complies with the requirements of the Subcontract; 17.2.3 control non-conforming services and/or products and undertake corrective and preventative action as and when necessary; 17.2.4 establish, maintain and keep records of all activities related to the management of quality; and 17.2.5 provide sufficient access to the workplace, and to information, records and other relgevant documentation, resources (including personnel), and all other things necessary to allow the Contractor to carry out reviews, surveillance and audit of the Subcontractor's procedures and conformance with the contractual quality management requirements. The Subcontractor must demonstrate to the Contractor, whenever requested, that it has met and is meeting at all times its obligations under clauses 17.1 to 17.2. Environmental management The Contractor requires the Subcontractor to implement a systematic approach to the management of environmental impacts of the Subcontract. 18A 18.1 Environmental management requirements specified in the Subcontract may be in addition to, but are not in substitution for, any environmental management obligations of the Subcontractor under the laws of South Australia or the Commonwealth. 18.2 The Subcontractor must systematically manage its environmental management processes in accordance with any systems, plans, standards and codes specified in the Subcontract. 18.3 The Subcontractor must demonstrate to the Contractor, whenever requested, that it has met and is meeting at all times its obligations under clauses 18.1 and 18.2. Workforce Participation and Skills Development The Contractor requires the Subcontractor to implement a systematic approach to meeting objectives for increased employment of Apprentices and Trainees, Cadets, Aboriginal people and Local People with Barriers to Employment. 18A.1 This clause 18A applies if it is stated to apply in Subcontract Information item 16A. Page 12 of 69 18A.2 The Subcontractor acknowledges that: 18A.2.1 an objective of the Contract is to increase the employment and training of Apprentices and Trainees, Cadets, Aboriginal people and Local Persons with Barriers to Employment (the “Target Group”) and to Upskill people engaged directly in connection with the performance of the Contract; and 18A.2.2 the Contractor has obligations to the Principal in relation to the objective set out in Clause 18A.2.1, and is relying on the Subcontractor to satisfy some or all of the obligations. 18A.3 The Contractor must provide to the Subcontractor a copy of its Workforce Participation and Skills Development Plan or Workforce Participation and Skills Development Strategy (as the case may be) and any amendments to the plan or strategy which it has submitted to the Principal under the terms of the Contract within 10 days of its submission to the Principal. 18A.4 The Subcontractor must support, implement and comply with the Contractor’s Workforce Participation and Skills Development Plan or Workforce Participation and Skills Development Strategy (as the case may be), as amended to the extent it indicates that obligations will be undertaken by the Subcontractor. 18A.5 The Subcontractor must: 18A.5.1 keep records of compliance with this clause including (without limitation) records of the following information: A. the number of hours of work performed by each person on the Site; B. the total labour hours for all workers; and C. details of the Upskilling provided to people engaged directly in connection with the performance of the Subcontract, including the hours undertaken, the name and date of the course and the name of the training organisation; 18A.5.2 provide the Contractor with such other information and assistance as the Contractor may require to: A. satisfy its reporting obligations under the Contract in connection with the obligations referred to in Clause 18A.2.2; and B. in connection with the Principal carrying out an audit of the Contractor’s compliance with the Contract. 18A.6 The Subcontractor must not contravene the Privacy Act 1988 (Cth). This may require the Subcontractor to obtain a person’s consent prior to disclosing that person’s personal information in connection with this clause. 18A.7 For the purpose of this clause: “Aboriginal person” means a person who identifies as being Aboriginal and/or is considered by members of his or her community as being Aboriginal. This definition includes Torres Strait Islander people; Page 13 of 69 “Apprentice/Trainee” means a person (who may be either an apprentice or a trainee) undertaking training in a trade or declared vocation under a training contract as provided for in the Training and Skills Development Act 2008 (SA) whether on a full-time or part-time basis; “Cadet” means a person undertaking tertiary or post-graduate study linked to paid employment with the Contractor (or its subcontractor), provided that both the person’s employment and study are linked to the building and civil construction industry (for example, employment and training in civil engineering, structural engineering, mechanic engineering, architecture, surveying or construction management); “Local Person With Barriers to Employment” means any person residing in South Australia who is unemployed at the time of commencing employment with the Contractor (or its subcontractor). A Local Person with Barriers to Employment includes a person who is: 1. registered with Centrelink or a Job Services Australia provider; 2. registered with the Disability Employment Network; 3. a skilled migrant job seeker holding a General Skilled Migrant visa; 4. a participant in a South Australia Works program (being the initiative of the South Australian Government which links people with skills and jobs through a range of learning, training and work programs). A person maintains his or her status as a Local Person with Barriers to Employment for 12 months from the commencement of employment with the Contractor or subcontractor (as the case may be); “Target Group” has the meaning given to it in clause 18A.2.1; “Upskilling” means training where: 1. 2. the training is: on the list of courses eligible for CITB funding support; provided by an organisation approved by the CITB (a list of eligible courses and approved providers is available from the CITB or by visiting www.dfeest.sa.gov.au/15percent); and is relevant to the employment and skills required for the performance of the Contract; or the training is otherwise approved by CITB as eligible to be included in the Upskilling Component. Notwithstanding this definition, Upskilling does not include any off-Site training undertaken by Cadets; “Workforce and Skills Development Plan” means the plan so called and which, if required by the Contract, has been submitted by the Contractor to the Principal in accordance with the terms of the Contract; and “Workforce and Skills Development Strategy” means the strategy so called and which, if required by the Contract, has been submitted by the Contractor to the Principal in accordance with the terms of the Contract. 18B NOT USED 19. NOT USED Page 14 of 69 20. NOT USED 21. NOT USED 22. NOT USED 23. Media releases and enquiries 23.1 24. The Subcontractor must obtain the Contractor's prior written consent to: 23.1.1 any press release or advertisement it wishes to make or place concerning the Subcontract, the Principal, the Contractor or the Subcontract Works; or 23.1.2 the release for publication in any media of any information, publication, document or article concerning the Subcontract, the Principal, the Contractor or the Subcontract Works. 23.2 The Subcontractor must refer any media enquiries concerning the Subcontract, the Principal, the Contractor or the Subcontract Works to the Contractor, for the Contractor's prior written consent to any response, which consent may be given or withheld, in the Contractor's absolute discretion. 23.3 The Subcontractor must ensure that all Consultants, Sub-subcontractors and Suppliers engaged by the Subcontractor for the performance of the Subcontract, comply with the requirements of this clause 23 and obtain the Contractor's prior written consent (through the Subcontractor) before responding to enquiries or publishing anything of the type referred to in clause 23. Registration and licences 24.1 All vehicles and plant used in performing work in connection with the Subcontract must be properly registered by the Subcontractor, if required by law to be registered. 24.2 The Subcontractor must ensure that all drivers who operate vehicles or plant in performing work in connection with the Subcontract are properly and appropriately licensed as required by law to operate those vehicles or plant. 24.3 Whenever requested by the Contractor, the Subcontractor must provide promptly, documentary evidence of compliance with clauses 24.1 and 24.2. Management duties 25. Time management The Subcontractor must actively manage progress, anticipating and responding to events to stay on schedule. 25.1 The Subcontractor must commence Design (if applicable) and construction of the Subcontract Works on Site in accordance with the Subcontract Program (or the contractual program as referred to in clause 25.6, as applicable). 25.2 The Subcontractor must carry out Design (to the extent applicable) and Page 15 of 69 construction of the Subcontract Works in accordance with Scheduled Progress. 25.3 Whenever requested, the Subcontractor must demonstrate to the Contractor that it is achieving Scheduled Progress. 25.4 If the Subcontractor is not achieving Scheduled Progress, the Contractor may instruct the Subcontractor to take all reasonable steps to achieve Scheduled Progress, at the Subcontractor's cost. 25.5 The parties acknowledge that an instruction under clause 25.4 is not an Acceleration Notice. 25.6 The Subcontractor must submit to the Contractor a program which complies with clause 25.9 within 14 days of the Date of Subcontract. Until the Subcontractor provides this program complying with clause 25.9, the program submitted by the Subcontractor with its tender shall be the contractual program, if the Contractor so advises the Subcontractor in writing. 25.7 The Contractor need not respond to the Subcontractor concerning the program submitted. If the Contractor raises no objection and the program submitted by the Subcontractor under this clause 25 complies with clause 25.9, it becomes the Subcontract Program. If the program does not comply with clause 25.9, the Subcontractor must promptly and in any event within 14 days of being notified by the Contractor of the non-compliance, submit to the Contractor a further program complying with the requirements for the Subcontract Program in clause 25.9. 25.8 The Subcontractor must update and resubmit the Subcontract Program when directed by the Contractor acting reasonably, taking into account actual progress, any changed circumstances and the effects of delays and approved extensions of time. 25.9 The Subcontract Program must comply with the following requirements: 25.9.1 show the dates of, or, in the case of future activities and events, the dates for commencement and completion of Design and construction activities, other significant events, Subcontract Milestones and the Subcontract Works and also include Contractual Completion Dates; 25.9.2 reflect Scheduled Progress and be consistent with all constraints on access, performance and co-ordination; 25.9.3 show the logical relationship between activities and events shown in the program, identify time leads and lags, resource and other constraints and the sequence of activities which constitute the critical path or critical paths; 25.9.4 show the dates when the Subcontractor will require information, documents, materials or instructions from the Contractor and the dates when the Subcontractor will provide information or documents to the Contractor. These dates are to be consistent with dates which the Contractor could reasonably have anticipated at the Date of Subcontract that this information, documents, materials and instructions would be required and provided; and 25.9.5 be in such form and include such detail as the Contractor Page 16 of 69 reasonably requires and be accurate, comprehensive and complete in all respects. When requested by the Contractor, the Subcontractor must provide the Subcontract Program in electronic form to the Contractor. All of the requirements of clauses 25.9.1 to 25.9.5 must be accessible and clearly shown in the electronic form of the Subcontract Program. The software used by the Subcontractor must be acceptable to the Contractor. 25.10 The Subcontractor will not be entitled to make a Subcontractor's Claim for an extension of time under clause 54.3 or otherwise, until the Subcontractor has submitted to the Contractor a Subcontract Program in conformance with clause 25.9, notwithstanding the references to the contractual program in clauses 25.1 & 25.6. The Subcontract Program submitted in respect of a Subcontractor's Claim for an extension of time must be the Subcontract Program current (as adjusted under clause 25.8) at the time of the event or events giving rise to the Subcontractor's Claim. 25.11 All extension of time Subcontractor's Claims must show how the Subcontractor has been or will be delayed in reaching Completion, by specific reference to an activity or activities on the then current (as adjusted under clause 25.8) critical path or paths of the Subcontract Program. 25.12 Provision of the Subcontract Program does not relieve the Subcontractor of any of its obligations under the Subcontract. 26. Working days and hours of work 26.1 27. The Subcontractor must observe Statutory Requirements which regulate working days and hours of work and any requirements of the Contractor which regulate working days and hours of work, as specified in Contract Information Item 39. Intellectual property 27.1 The Subcontractor assigns or otherwise transfers Intellectual Property Rights in all Data created specifically for the Subcontract, upon its creation, to the Principal. The Subcontractor, at its own cost, will do all things necessary, including execution of all necessary documentation, to vest ownership of all such Intellectual Property Rights in the Principal. 27.2 The Subcontractor must include provisions in all Sub-subcontracts and agreements with Consultants to ensure that Intellectual Property Rights in all Data created specifically for the Subcontract is assigned or otherwise transferred to the Principal upon its creation. The Subcontractor, Subsubcontractors and Consultants are granted licences to use the Data for the purposes of the Subcontract. 27.3 For Data provided by or for the Subcontractor, but not created specifically for the Subcontract, the Subcontractor must obtain irrevocable royalty-free licences to allow the Principal to use, operate, maintain, modify and decommission the Subcontract Works. 27.4 Licences referred to in clause 27.3 must apply from the Date of Subcontract or (if the Data has not then been created or is not then available) from the date the Data is created or becomes available (as applicable) in perpetuity. 27.5 The Subcontractor is responsible for the timely payment of all royalties and Page 17 of 69 fees for Intellectual Property Rights in connection with the Subcontract and the Subcontract Works. The Subcontractor indemnifies the Contractor and the Principal against any claims (including Subcontractor's Claims), actions, and loss or damage arising out of any failure to make these payments or any infringement or alleged infringement of Intellectual Property Rights in relation to the Data provided by or for the Subcontractor and used under the Subcontract or required to use, operate, maintain, modify or decommission the Subcontract Works. 28. 27.6 The Subcontractor must ensure that Data created specifically for the Subcontract by or for the Subcontractor is only used by the Subcontractor and Sub-subcontractors, Suppliers and Consultants for the purposes of the Subcontract. 27.7 The Subcontractor must maintain all Data secret and confidential and disclose it only to those persons to whom disclosure is reasonably necessary for the purposes of the Subcontract. This provision does not relate to Data which is generally available to the public or which is required to be disclosed by law. This provision survives termination or expiry of the Subcontract or of the Subcontractor's employment under the Subcontract. Licences and approvals 28.1 29. The Subcontractor must obtain at its own cost all licences, authorisations, approvals and consents necessary to carry out the Subcontract Works in accordance with the Subcontract. Care of people, property and the environment 29.1 The Subcontractor is liable for and indemnifies the Contractor against loss or damage to: 29.1.1 the Subcontract Works, from the date the Subcontractor begins carrying out the Subcontract Works; and 29.1.2 the Site and anything brought onto the Site for the purposes of the Subcontract, from the date the Subcontractor is given access to the Site (or the relevant part of the Site), arising out of carrying out work for or in connection with the Subcontract, until and including the Actual Completion Date of the whole of the Subcontract Works. 29.2 After the Actual Completion Date of the whole of the Subcontract Works, the Subcontractor remains liable for and indemnifies the Contractor against loss or damage arising out of performing Variations, making good Defects, and removing Materials from the Site. 29.3 The Subcontractor is liable for and indemnifies the Contractor against all claims, actions, and loss or damage and all other liability arising out of carrying out the Subcontract Works: 29.4 29.3.1 to or in connection with any property (other than property covered under clause 29A); and 29.3.2 arising out of personal injury or death. The Subcontractor's liability for and responsibility to indemnify the Page 18 of 69 Contractor under clauses 29.1, 29.2 and 29.3 is reduced to the extent that an Excepted Risk contributes to an injury or death or loss or damage to property. 29.5 29.6 30. The Subcontractor is responsible for all of the following: 29.5.1 preventing personal injury or death, or loss or damage to the Site, the Subcontract Works and the Temporary Work; 29.5.2 preventing loss or damage to adjoining and other properties and the environment arising out of carrying out the Subcontract Works; 29.5.3 the locating and care of existing services; 29.5.4 repairing or making good loss or damage to the Subcontract Works, the environment and the Site arising out of carrying out the Subcontract Works; and 29.5.5 bearing the cost of repairing, or making good, loss or damage to adjoining and other properties and the environment arising out of carrying out the Subcontract Works. if urgent action is required to avoid death, injury, loss or damage, and the Subcontractor does not take the necessary action immediately when the Contractor requests it, the Contractor may take the action (without relieving the Subcontractor of its obligations), at the Subcontractor's cost with the Contractor's costs being recoverable as a deduction from the Subcontract Price. Notices and instructions in writing 30.1 Notices must be sent to the relevant persons at the relevant postal or other addresses specified in Subcontract Information items 4 to 11. 30.2 All notices must be in writing, and all instructions by the Contractor must be in writing or confirmed in writing as soon as practicable, where given orally when urgent action is required. Sub-subcontractors, Suppliers and Consultants Contractual relationships between the Subcontractor, Sub-subcontractors, Suppliers and Consultants must be on a similar basis to those between the Contractor and Subcontractor. Clause 34 specifies which clauses also apply to Consultants and Suppliers. 31. Sub-subcontractor relationships 31.1 The Subcontractor is solely responsible for all Sub-subcontractors and for their acts and omissions, and for the termination of any Sub-subcontract and replacement of any Sub-subcontractor. 31.2 The Subcontractor indemnifies the Contractor against all claims (including Claims), actions, and loss or damage and all other liability arising out of any acts or omissions of Sub-subcontractors. 31.3 The Contractor must provide to the Subcontractor, before the Subcontractor begins work, a copy of the following clauses and Subcontract Information items in the Contract: Page 19 of 69 31.3.1 clause 62; 31.3.2 clause 66; 31.3.3 clauses 72 to 76; and 31.3.4 Contract Information items 20 to 22 and 50. 31.4 The Subcontractor must make Payment Claims in accordance with clauses 62 and 65, and the Contractor must pay the Subcontractor in accordance with clauses 63 and 65. 31.5 The Contractor must comply with clauses 37.7 to 37.8. Requirements for all Sub-subcontracts 31.6 31.7 The Subcontractor must include in each Sub-subcontract (including agreements with Suppliers) written provisions which bind the Subsubcontractor to all of the following: 31.6.1 those of the Subcontractor's obligations under this Subcontract which are to be performed by the Sub-subcontractor; 31.6.2 the provisions of the Subcontract applying to termination for convenience (clause 78); and 31.6.3 instructions of the Contractor issued to the Subcontractor which necessarily apply to the Sub-subcontractor. Each Sub-subcontract must require the Subcontractor to pay the Subsubcontractor within 15 Business Days of the Sub-subcontractor claiming payment in accordance with the Sub-subcontract. Further Sub-subcontract requirements Clause 31.8 applies only to Sub-subcontracts worth more than the amount in Subcontract Information item 21. It applies in addition to clauses 31.6 and 31.7. 31.8 The Subcontractor must include written provisions acceptable to the Contractor, to the effect of those in this clause 31.8, in each Subsubcontract of value more than the amount in Subcontract Information item 21 (which must be the same as the amount in Contract Information item 21 of the Contract); and the Subcontractor must ensure that each subcontract entered into by a Sub-subcontractor of more than that value includes written provisions to the same effect. 31.8.1 Any Sub-subcontract which: (a) requires the Sub-subcontractor to provide a cash security to the Subcontractor; or (b) allows the Subcontractor to deduct retention money from any payment made by it to the Sub-subcontractor, must allow the Sub-subcontractor to provide an undertaking in a form equivalent to the relevant Undertaking in Schedule 2 in place of a cash security or retention money. 31.8.2 The Subcontractor may only withhold amounts from Progress Payments that may properly be withheld by the Subcontractor Page 20 of 69 under the relevant Sub-subcontract or agreement with a Supplier. 32. 34. Each Sub-subcontract must include provisions equivalent to clauses 37.6 to 37.8 and 66 of the Subcontract, and must prescribe a rate of interest the same as the rate prescribed under clause 66. 31.8.4 Each Sub-subcontract must include provisions equivalent to clauses 73 to 76 of the Subcontract, except that they are not to apply if the only remedy sought by the Sub-subcontractor is an order that the Subcontractor pay to it an amount which is not disputed to be payable under the Sub-subcontract. 31.8.5 Each Sub-subcontract must require the Subcontractor to provide to the Sub-Subcontractor, before the Sub-subcontractor starts work, a copy of clauses 31.8, 66, 73 to 76 of the Subcontract, and notify the Sub-subcontractor of the rate of interest for late payments. Engaging Sub-subcontractors 32.1 33. 31.8.3 The Subcontractor must not without prior written approval of the Contractor subcontract the whole or any part of the Subcontract Works. Sub-subcontractors' warranties 33.1 For each trade or area of work listed in Subcontract Information item 25, the Subcontractor must provide to the Contractor, before the Subcontractor completes its work, a warranty to the Principal in the form of Schedule 1 (Subcontractor's Warranty) to remedy any Defects and to remedy or replace Design, Materials or workmanship which does not comply with the Subcontract. 33.2 Clause 33.1 does not affect any of the Subcontractor's other obligations under the Subcontract. Consultant and Supplier relationships 34.1 Clauses 31.1 and 31.2 apply to Consultants in the same way they apply to Sub-subcontractors, unless the context requires otherwise. 34.2 Clauses 31.1, 31.2, 31.3 (excluding clause 31.3.1), 31.4 and 33 apply to Suppliers in the same way they apply to Sub-subcontractors, unless the context requires otherwise. CARRYING OUT THE SUBCONTRACT WORKS This section deals with design and construction activities. It contains most of the provisions in the Subcontract conditions that apply to the physical carrying out of the Subcontract Works, and also covers procedures for payment. Starting Page 21 of 69 35. Start-up workshop Under the Contract, the Principal convenes the start-up workshop at the beginning of the Contract. The start-up workshop is held to encourage the parties and others concerned with the Contract to work co-operatively. See Attachment 1. 36. 35.1 If requested by the Contractor, the Subcontractor must attend a start-up workshop convened by the Principal. 35.2 Each party and any others who participate in the workshop must meet their own costs for attendance at the start-up workshop, and the parties to the Contract will share equally the other costs. Insurance Contractor's obligations 36.1 36.2 The Subcontractor acknowledges that, under the Contract, the Contractor must take out (and pay all premiums for) the following insurance policies (except to the extent that the Contractor has notified the Subcontractor within 14 days of the Date of Subcontract that the Principal has effected any of Works, public liability and marine liability policies of insurance which include cover for the Contractor, Consultants, Subcontractors and Suppliers), which (apart from that under clause 36.1.3) must cover the Subcontractor as an insured: 36.1.1 a Works policy of insurance to cover loss or damage to the Works (including the Subcontract Works) and the Temporary Work (excluding the Subcontractor's plant) and including Materials stored off-Site or in transit, as specified in Subcontract Information item 26; 36.1.2 a public liability policy of insurance to cover loss or damage to property or injury or death to persons arising out of or in connection with carrying out the Subcontract Works, as specified in Subcontract Information item 27; 36.1.3 (if required in Subcontract Information item 28) a professional indemnity policy of insurance to cover liability for breach of professional duty (whether in contract or otherwise) arising out of any negligence, whether in relation to errors in design, documentation, supervision or other professional duties of the Contractor (whether in contract or otherwise), as specified in Subcontract Information item 28, and extended to include cover for any breach of all such professional duties carried out on behalf of the Subcontractor by Sub-subcontractors, Suppliers or Consultants; and 36.1.4 if any work for or in connection with the Subcontract includes the use of waterborne craft of 8 or more metres in length, a marine liability policy of insurance to cover the use of such craft, as specified in Subcontract Information item 30. The Contractor must provide copies of the policies of insurance taken out by the Contractor under clause 36.1, or by the Principal (as applicable) if requested by the Subcontractor. The Subcontractor may itself take out and maintain any additional insurances which it considers necessary. Subcontractor's obligations Page 22 of 69 36.3 36.4 Before starting work under the Subcontract, the Subcontractor must: 36.3.1 insure for the minimum amount specified in Subcontract Information item 31, and pay all premiums for all Workers' Compensation and related liability in accordance with the requirements of the Workers Rehabilitation and Compensation Act 1986 (SA); or 36.3.2 (if Workers' Compensation cover cannot legally be obtained) insure under a personal accident policy of insurance to cover personal accidents and related liability, as specified in Subcontract Information item 32; 36.3.3 if required in Subcontract Information Item 32A, obtain and maintain an asbestos liability policy to cover asbestos removal and decontamination and associated risks; and 36.3.4 insure for any other risks as required under the Subcontract. The Subcontractor must ensure that every Sub-subcontractor and Consultant is insured at all times: 36.4.1 for Workers' Compensation and related liability in accordance with the requirements of the Workers Compensation Act 1987 (NSW); or 36.4.2 (if Workers Compensation cover cannot legally be obtained) under a personal accident policy of insurance to cover personal accidents and related liability, as specified in Subcontract Information item 32. Approval 36.5 The Subcontractor must obtain the written approval of the Contractor for all insurers and for the terms and conditions of the policies it is required to maintain under the Subcontract. Policy requirements 36.6 The Subcontractor must ensure that each policy required to be effected and maintained under the Subcontract, under Sub-subcontracts or agreements with Consultants is in effect for the relevant period specified in the contract. 36.7 If the Subcontract requires the Subcontractor to take out additional insurance, all such policies must: 36.7.1 require the insurer to notify the Contractor (other than in relation to Workers Compensation and personal accident) at the same time as the insurer receives or gives any notice concerning the policy, and at least 7 days before any proposed cancellation of a policy; and 36.7.2 provide that a notice of claim given to the insurer by the Principal, the Contractor, the Subcontractor, or a Sub-subcontractor, Supplier or Consultant will be accepted by the insurer as a notice of claim given by all of the insured. Proof of Cover 36.8 Before the Subcontractor starts any work for or in connection with the Page 23 of 69 Subcontract and whenever requested in writing by the Contractor, the Subcontractor must supply proof that all insurance policies required under the Subcontract and under Sub-subcontracts are current. 36.9 The Contractor need not make any payment under the Subcontract to the Subcontractor unless the Subcontractor has complied with and continues to comply with clause 36.8. 36.10 If the Subcontractor fails to comply with clauses 36.3, 36.4, 36.5 and 36.8, where possible, the Contractor may effect and maintain that insurance and pay the necessary premiums. The Contractor may recover from the Subcontractor the cost of the premiums and the Contractor's reasonable costs of effecting and maintaining the insurance, as a deduction from the Subcontract Price. Excesses 36.11 The Subcontractor must bear all excesses under the policies of insurance taken out by the Contractor under clause 36.1 which relate to the Subcontract Works. Claims 36.12 The Subcontractor must, as soon as practicable, inform the Contractor in writing of the occurrence of an event that may give rise to a claim under a policy of insurance effected as required by the Subcontract and must ensure that the Contractor is kept fully informed of subsequent action and developments concerning the claim. The Subcontractor must take such steps as are necessary or appropriate to ensure that a Sub-subcontractor, Supplier or Consultant (as applicable) will, in respect to an event or claim of a like nature arising out of or relating to the operations or responsibilities of the Sub-subcontractor, Supplier or Consultant (as applicable), take in relation to the Contractor similar action to that which the Subcontractor is required to take under this clause 36.12. 36.13 If there is a claim for significant damage or destruction under the Works policy of insurance (as determined by the Principal, acting reasonably): 36.13.1 all settlement amounts must be paid by the insurer directly to the Principal; 36.13.2 the Contractor may decide to have the Subcontract Works reinstated, or may decide not to proceed with the Subcontract Works, as instructed by the Principal under the Contract, without creating any default by the Contractor under the Subcontract; and 36.13.3 the Subcontractor must reinstate the Subcontract Works if instructed to by the Contractor and except as otherwise provided in the Subcontract may only make a Subcontractor's Claim for payment for reinstatement of the Subcontract Works up to the relevant amount of any insurance settlement. No limitation 36.14 The requirements for insurance to be effected and maintained do not affect or limit the Subcontractor's liabilities or other obligations under the Subcontract. 37. Security Page 24 of 69 The Subcontractor is required to provide security to the Contractor in the form of cash security, retention money or Undertakings to pay on demand, provided by financial institutions on the Subcontractor's behalf. Provision of Security 37.1 Within 14 days after the Date of Subcontract the Subcontractor must give the Contractor the Completion Undertaking and the Post-Completion Undertaking for the amounts calculated as specified in Contract Information items 33 and 34, or equivalent cash security. The Undertakings must be in the form specified in Schedule 2 (Undertaking). Otherwise, the Contractor is entitled to deduct equivalent amounts in retention money at the time of making Progress Payments. 37.2 All Undertakings must be provided by a bank, building society, credit union or insurance company acceptable to the Contractor. Return of Security 37.3 Unless the Contractor has made or intends to then make a demand against any Undertaking, the Contractor must return Undertakings to the Subcontractor as follows: 37.3.1 the Completion Undertaking within 14 days after the Actual Completion Date of the whole of the Subcontract Works; and 37.3.2 the Post-Completion Undertaking at the end of the period in Contract Information item 35 (or 12 months if no period is specified there) after the Actual Completion Date of the whole of the Subcontract Works provided all Defects then known have been remedied and otherwise when all Defects then known are remedied. 37.4 When Completion of a Subcontract Milestone is achieved, the Contractor may (in its absolute discretion) agree to a proportionate reduction in the level of security held, based on the proportion of the Subcontract Works in the Subcontract Milestone. 37.5 The Subcontractor must not prevent the Contractor making any demand against the Undertakings (or the equivalent cash security or retention money), or prevent the provider of an Undertaking complying with the Undertaking or any demand by the Contractor. Cash Security 37.6 If the Contractor receives or retains security in cash or converts security to cash, that security is held in trust by the Contractor from the time it receives, retains or converts it. 37.7 If the Contractor receives payment under the Contract for, or on account of, work done or Materials supplied by the Subcontractor, and does not pay the Subcontractor the whole amount to which the Subcontractor is entitled under the Subcontract, the difference is held in trust for payment for the work done or Materials supplied. 37.8 The Contractor must deposit all money it receives in trust under clauses 36.6 and 37.7 into a trust account in a bank selected by the Contractor no later than the next Business Day, and: 37.8.1 the money must be held in trust for whichever party is entitled to receive it until it is paid in favour of that party (subject to clause Page 25 of 69 37.5 and 67); 38. 37.8.2 the Contractor must maintain proper records to account for this money and make them available to the Subcontractor on request; and 37.8.3 any interest earned by the trust account is owned by the party which becomes entitled to the money held in trust. Site access 38.1 Subject to compliance by the Subcontractor with the provisions of clauses 38.2 and 38.3, within the time period stated in Contract Information item 13, or, if no time period is stated, then within 14 days of the Date of Subcontract, the Contractor must give the Subcontractor access to the Site, or enough of it to allow for start of Design (if applicable) and construction of the Subcontract Works or such part of the Subcontract Works for which commencement has been authorised. If the Contractor does not give the Subcontractor access to the Site or enough of it to allow for start of Design (if applicable) and construction of the Subcontract Works, or such part of the Subcontract Works for which commencement has been authorised, by the time specified in clause 38.1, the Subcontractor may be entitled to an extension of time under clause 54 as its sole remedy and, notwithstanding clause 55, will not be entitled to any costs, losses, expenses or damages under clause 55, or otherwise. 38.2 The Subcontractor must meet all its obligations under the Subcontract to provide Undertakings (or the equivalent cash security) and effect insurance before it is entitled to start any work for or in connection with the Subcontract. Refer to clauses 36 (Insurance) and 37 (Security). 38.3 Before Design (if applicable) or construction work commences the Subcontractor must comply to the extent specified in the Subcontract with requirements for industrial relations, environmental, safety (including under all work health and safety legislation) and quality management, other Statutory Requirements and any other requirements specified in the Subcontract to be complied with by the Subcontractor before Design (if applicable) and construction work commences. The Subcontractor is not entitled to access to the Site or any part of the Site until the Subcontractor demonstrates to the Contractor that it complies with those requirements. 38.4 Where required for the purposes of the Contract and the Subcontract, at all reasonable times the Subcontractor acknowledges that the Principal (including its authorised employees and agents) and the Contractor will require access to the Site and to the premises of the Subcontractor and must arrange for such access to the premises of Sub-subcontractors, Suppliers and Consultants. This may include for the purpose of surveillance, audit, inspection, Testing, certification, recording of information in any form or for any other reasonable purpose required by the Principal and the Contractor in connection with the Contract and the Subcontract. Access for Principal’s contractors 38.5 If required by the Principal (by written notice to the Contractor), the Contractor must permit persons engaged by the Principal (“Principal’s Page 26 of 69 contractors”) to have access to the Site, to deliver and store materials on the Site and to carry out work on the Site, and must take all reasonable measures to cooperate with them and coordinate the Subcontractor’s work with their work. 39. Engagement of Valuer 39.1 At the discretion of the Principal and the Contractor, a Valuer may be engaged under the Contract to determine the value and time associated with Variations and other matters referred to the Valuer under the Contract. 39.2 To the extent specified in the Subcontract, the Subcontractor is bound by any determination of the Valuer. The Site 40. Site information 40.1 The parties acknowledge that: 40.1.1 at the Date of Subcontract, the Contractor has provided in good faith the geotechnical or other information concerning the Site as specified in Subcontract Information items 36A and 36B; 40.1.2 the information specified in Subcontract Information items 36A and 36B does not form part of the Subcontract; 40.1.3 the Contractor does not guarantee the completeness of the information specified in Contract Information item 36A; 40.1.4 the Contractor does not guarantee the accuracy, quality or completeness of the information specified in Contract Information item 36B; 40.1.5 the Contractor accepts no duty of care in connection with information listed in Subcontract Information item 36B (or with having provided it); 40.1.6 the Subcontractor warrants that it: 40.1.7 (a) has made its own inquiries (including the checking of information provided by the Contractor) concerning the Site; (b) did not in any way rely on the completeness of the information provided by the Contractor specified in Subcontract Information Item 36A other than as a guide for ascertaining what Further Site Information the Subcontractor considers it needs to obtain under clause 40.3; and (c) did not in any way rely on the information (which information could contain errors, omissions and other inaccuracies) provided by the Contractor, as specified in Subcontract Information item 36B; and the Subcontractor also warrants that it has made its own Page 27 of 69 interpretations, deductions and conclusions from the information provided by the Contractor and did not in any way rely on interpretations, deductions and conclusions made by or for the Contractor. Other information concerning the Site may be included in the Contract. 40.2 41. The Subcontractor warrants that it has: 40.2.1 examined the Site and surrounds and satisfied itself through its own investigation as to the condition and characteristics which may be encountered on, in or under the Site (including sub-surface conditions) and as to the further geotechnical or other information for the Site that may be required to be obtained by the Subcontractor; and 40.2.2 made its own assessment of the risks, contingencies and other circumstances which might affect the Subcontract Works and has allowed fully for these in the Subcontract Price (subject to clause 41). 40.2.3 If the Contractor considers that further geo-technical or other information for the Site is required, it may obtain Further Site Information and must give the Contractor details of Further Site Information as it is obtained. 40.2.4 Further Site Information does not include any information in the Subcontract Documents or information which by the Subcontract the Subcontractor is required to otherwise obtain. 40.2.5 Except if the Subcontract provides otherwise, the Subcontractor must bear the cost of obtaining Further Site Information. Site Conditions Early warning should serve to reduce the severity of possible cost and time implications when adverse Site Conditions are encountered. For this purpose, the Subcontractor is encouraged to obtain Further Site Information in advance of construction. 41.1 The Subcontractor agrees that it has no other entitlement arising out of or in connection with Site Conditions other than as referred to in this clause 41. 41.2 If the Contractor encounters, in the execution of the Subcontract Works (including when obtaining Further Site Information), Site Conditions which are materially adverse in comparison to the Site Conditions which the Subcontractor should have reasonably foreseen at the Date of Subcontract, having regard to the warranty in clause 40.2, the Subcontractor must notify the Contractor in writing forthwith and in any event within 7 days of encountering these Site Conditions (and prior to making any related Subcontractor 's Claim), giving full details of: 41.2.1 the Site Conditions encountered; 41.2.2 the manner in which they are said to be materially adverse (having regard to the warranty in clause 40.2), together with information supporting this contention; 41.2.3 the effect on the Subcontract Works; Page 28 of 69 41.2.4 subject to clause 41.8, the estimated additional cost (if any) of dealing with the Site Conditions encountered and the additional work and resources involved; 41.2.5 the delay (if any) to progress of the Subcontract Works; and 41.2.6 any other relevant matters. The Contractor may request the Subcontractor to provide any further information relating to the circumstances of the Site Conditions encountered. 41.3 The Subcontractor is solely responsible for dealing with the Site Conditions encountered in a manner so as to minimise any extra costs and in a manner to which the Contractor has no objection. 41.4 Subject to clause 41.8: 41.4.1 the Subcontractor will be entitled as an adjustment to the Subcontract Price to its direct, reasonable additional costs (including costs of delay or disruption), necessarily and unavoidably incurred by the Subcontractor in dealing with materially adverse Site Conditions, from the date of provision to the Contractor of the written notice required by clause 41.2, having taken all reasonable steps to minimise the costs in dealing with materially adverse Site Conditions; and 41.4.2 the Subcontractor may also be entitled to an extension of time for Completion under clause 54 for delays caused by the materially adverse Site Conditions occurring from the date of provision to the Contractor of the written notice required by clause 41.2. 41.5 If a Variation is instructed or agreed as a result of Site Conditions shown by Further Site Information given to the Contractor no later than 21 days before construction on the relevant part of the Site would have started, but for the Variation, it must be dealt with (including the matters of value and extension of time for Completion) under the Variation procedures in clause 52. 41.6 If a Variation is instructed or agreed as a result of Site Conditions, but the Subcontractor does not give to the Contractor the Further Site Information within the time provided in clause 41.5; 41.6.1 the Variation must be valued under clause 52 but the value of the Variation must exclude the costs of any aborted work arising out of the Variation; and 41.6.2 no payment will be made to the Subcontractor for costs of delay or any aborted work under any other provision of the Contract or otherwise. 41.7 Clause 41.6 applies regardless of any provisions to the contrary in the Subcontract. 41.8 Notwithstanding anything in clause 41, when specified in Contract Information item 41 that the Subcontractor is to bear the full risk of encountering and dealing with materially adverse Site Conditions: 41.8.1 the Subcontractor is not entitled to the costs of dealing with Page 29 of 69 materially adverse Site Conditions; and 41.8.2 41.9 notwithstanding clause 54, if the Subcontractor is or will be delayed in reaching Completion as a result of dealing with materially adverse Site Conditions, the Subcontractor will not be entitled to an extension of time for Completion. If a Variation is instructed or agreed as a result of Site Conditions, the parties' rights and obligations are not affected by clause 41.8. 41B. Collaboration in design, planning and cost control 41B.1 The Subcontractor must contribute to deliberations of the Principal’s Project Team on all matters concerning planning, plant, structural methods, constructability, servicing systems, programming, and progressive cost control. In this role it is required that the Subcontractor provides input before design and documentation solutions are finalised. 41B.2 The Subcontractor must assist the Contractor and the Principal’s Project Team to evaluate and initiate alternative construction methods and actively assist with the documentation of the selected scheme so the Principal’s Project Team may collectively achieve an economic solution that satisfies the aesthetic and functional design requirements of the brief. 41B.3 The Subcontractor must contribute constructability advice aimed at achieving efficient functionality and site operation during all stages of construction. 41B.4 The Subcontractor must develop, in conjunction with the Contractor, a plan for the pro-active investigation and management of potential site and building conditions with the objective of minimising the impact on budget and program through comprehensive documentation of the requirements. 41B.5 The Subcontractor must contribute to the process of contract documentation with the objective of achieving comprehensive and complete documents. 41B.6 Not used 41B.7 Not used 41B.8 The Subcontractor must attend meetings with the Contractor and the Principal’s Project Team on matters of design, construction, budget and program as required. 41B.9 Not used 41B.10 The Subcontractor must do everything in its power to: 41B.10.1 not used; 41B.10.2 assist the Principal to minimise Variations; and 41B.10.3 minimise the cost of Variations. 41B.11 The Subcontractor must: 41B.11.1 not used; 41B.11.2 provide advice on design and construction problems as they arise; Page 30 of 69 41B.11.3 provide costing advice to the Contractor and the Principal’s Professional Service Contractors during the preparation of progressive estimates of cost; 41B.11.4 assist in the costing of acceptable alternatives to enable budgets to be achieved and participate in value management exercises and savings strategies as required; 41B.11.5 propose innovations; 41B.11.6 not used; and 41B.11.7 work collaboratively with the Contractor, Principal and the Principal’s Professional Service Contractors to minimise delays and to resolve design and construction problems arising from any cause. Design The Subcontractor may have some design, design coordination and design management responsibility. The extent of Design by the Subcontractor may be as little as shop detailing, as much as the full Design of the Subcontract Works, or it may be some requirement in between, and Clause 43 applies in all these cases. In addition, the Subcontractor may be required to check, adopt and be responsible for design carried out before the Date of Subcontract by the Contractor or by the Principal. In that case, it is specified in Contract Information item 38, and clause 44 applies. 42. Ambiguities Clause 42 applies to all Subcontract Documents, including Contractor's Documents. 42.1 The Subcontractor, in addition to any responsibility to check Contractor's Documents under clause 44 (if applicable), must check the Subcontract Documents and notify the Contractor of any ambiguities, inconsistencies or discrepancies at least 21 days before the Subcontractor proposes to use them for Design (if applicable) or construction (including procurement, manufacture or fabrication of any part of the Subcontract Works) or for other Subcontract purposes. 42.2 The Contractor must resolve any ambiguities, inconsistencies or discrepancies in the Subcontract Documents which are notified by the Subcontractor to the Contractor for resolution. 42.3 Subject to clause 42.4, if the resolution in clause 42.2 results in the Subcontractor incurring increased or reduced costs than the Subcontractor should reasonably have anticipated at the time of tender, the Subcontract Price must be adjusted by the difference in costs agreed or valued under the procedures in clause 52 (and where applicable, dealt with under clauses 72 to 75). In the assessment of what the Subcontractor should reasonably have anticipated (as referred to above) regard must be had to the provisions of the Subcontract, in particular clause 10, and to whether the ambiguity, inconsistency or discrepancy was (or should have been) reasonably apparent to the Subcontractor at the time of tender. 42.4 If the Subcontractor fails to take the steps required in clause 42.1, and a Variation is instructed by the Contractor due to any ambiguity, inconsistency Page 31 of 69 or discrepancy: 43. 42.4.1 the Subcontractor will not be entitled to costs for delay or the cost of any aborted work (including Design) resulting from the Variation; except that 42.4.2 if clause 44 is not applicable, the Subcontractor will be entitled to the reasonable and unavoidable cost of any aborted work (including Design) if the ambiguity, inconsistency or discrepancy is included in the Contractor's Documents forming part of the Subcontract Documents. Subcontractor's Documents 43.1 The Subcontractor must produce Subcontractor's Documents which meet the requirements of all of the following: 43.1.1 the Subcontract; 43.1.2 Contractor's instructions; 43.1.3 Statutory Requirements; 43.1.4 the Building Code of Australia (if required in Contract Information item 37B), and relevant Australian Standards; and 43.1.5 if no other standard is specified in the Subcontract, then good industry standards applicable to the Subcontract Works. 43.2 The Subcontractor acknowledges that the Subcontractor must not change the Contractor's design in the Contractor's Documents without the Contractor's prior written approval. Whenever requested by the Contractor, the Subcontractor must promptly confirm in writing that Subcontractor's Documents are consistent with and comply with the Contractor's Documents and other relevant Subcontract Documents. If the Contractor's design is required to be changed (with the Contractor's prior written approval), the Variation must be dealt with under the procedures in clause 52. 43.3 The Subcontractor warrants that Subcontractor's Documents and any related Design, materials, documents and methods of working will not infringe any Intellectual Property Rights. The Subcontractor indemnifies the Principal and the Contractor against any costs, losses, expenses or damages arising out of the Subcontractor infringing any Intellectual Property Rights. 43.4 The Subcontractor must produce Subcontractor's Documents which will ensure that the Subcontract Works and every part of them are fit for the purposes required by the Subcontract. This responsibility is reduced to the extent that the Subcontractor's Documents are not fit because of design work by the Contractor for which the Contractor retains responsibility. The Contractor retains responsibility for design work by the Contractor except as provided by clause 44, if it applies. 43.5 The requirements of clause 43.4 are not reduced or affected by any Variations. Page 32 of 69 44. Adopting Contractor's Documents This clause only applies when this is indicated in Subcontract Information item 38. It does not replace any other provisions of the Subcontract, but adds further responsibilities when required. If clause 44 applies, the Subcontractor must accept full responsibility for design carried out by the Contractor (or the Principal) before the Date of Subcontract, in addition to Design to be carried out by the Subcontractor. 44.1 If Contract Information item 38 specifies that the Subcontractor must accept full responsibility for design carried out by the Contractor (or the Principal), then before submitting Subcontractor's Documents to the Contractor in accordance with clause 45 the Subcontractor (at its own cost) must: 44.1.1 check, and notify the Contractor of details (together with appropriate supporting documents) of any Fault in the Contractor's Documents; 44.1.2 amend the documents to correct Faults so that, on Completion, the Subcontract Works and every part will be fit for the purposes required by the Subcontract; and 44.1.3 accept and adopt the Contractor's Documents as if the Subcontractor prepared them so that they (amended by the Subcontractor as necessary) become Subcontractor's Documents when submitted under clause 45. See clause 43 for requirements applying to Subcontractor's Documents. 44.2 Subject to any provisions of the Subcontract which provide for change to the Contractor's Documents and clause 42, the Contractor must instruct a Variation if the Subcontractor notifies the Contractor of a Fault in the Contractor's Documents and the Contractor requires a change to the Subcontract Works as a result. 44.3 If Contractor's Documents adopted by the Subcontractor contain a Fault not notified to the Contractor by the Subcontractor in accordance with clause 44.1.1: 44.3.1 the Subcontractor will be responsible for, and not entitled to payment for delays or the cost any of aborted work arising out of the Fault; and 44.3.2 the value of any Variation the Contractor instructs as a result of the Fault must not include the cost of such delays or aborted work. 44.3.3 The Subcontractor acknowledges that the Contractor's design is incomplete and may contain Faults or conflict with Statutory Requirements or the Building Code of Australia (if applicable, as referred to in Contract Information item 37B) or other codes or standards which the Subcontractor is required to comply with under the Subcontract. 44.3.4 The Contractor makes no representation concerning Contractor's design and the Subcontractor is not entitled to rely on the completeness or accuracy of the Contractor's design. 44.3.5 The Contractor relies on the Subcontractor to identify and remedy Faults in the Contractor's Documents. Page 33 of 69 45. 46. Submitting Subcontractor's Documents 45.1 The Subcontractor must submit Subcontractor's Documents (as developed progressively and in stages, but so that each part is complete and in sufficient detail to explain what is proposed) to the Contractor at least 21 days before the date the Subcontractor proposes to use them for construction (including procurement, manufacture or fabrication) of any part of the Subcontract Works. The Subcontractor must provide the number of copies of the Subcontractor's Documents specified in Subcontract Information item 19 when submitting Subcontractor's Documents. 45.2 To the extent specified in the Subcontract, the Subcontractor must undertake design review and consider the Design with those persons specified in the Subcontract Documents, or those persons identified by the Contractor, including those involved in using or occupying any part of the Subcontract Works as end users. The Subcontractor must carry out such design review and consideration with the Contractor and those other persons and develop the Design and Subcontractor's Documents using the outcomes of this review and consideration. The Subcontractor must then submit to the Contractor for its consideration any necessary amendments to the Contractor's Documents proposed by the Subcontractor, including those arising out of the design review and consideration, prior to the Subcontractor submitting Subcontractor's Documents, as referred to in clause 45.1. 45.3 The Contractor need not respond to the Subcontractor about the Subcontractor's Documents submitted. 45.4 If the Contractor objects to the Subcontractor's Documents, the Subcontractor must take the objections into account and discuss them with the Contractor. The Subcontractor must correct any Fault in the Subcontractor's Documents. 45.5 Notwithstanding the design review and consideration by others under clause 45, the Subcontractor remains fully responsible for all Subcontractor's Documents. 45.6 Nothing the Contractor does or omits to do in connection with this clause 45 makes the Contractor liable for Subcontractor's Documents, or prevents the Contractor from relying on or enforcing a right, under the Subcontract or otherwise. Innovation This clause provides an incentive to the Subcontractor to improve its service to the Contractor by innovation. If the Contractor accepts the Subcontractor's proposal, the Subcontractor benefits by retaining immediate savings in its costs; the Principal or Contractor benefit from the added value to the Works, reduced operating or maintenance costs, or similar savings. Alternatively, if stated in Subcontract Information Item 42, the parties agree to share the savings in costs derived from an innovation. 46.1 The Subcontractor may submit in writing to the Contractor, at its own cost, a detailed proposal for changes to the Subcontract Works, including Design or Materials, which is likely to offer significant benefits (including long-term or repeated benefits) to the Principal or the Contractor. 46.2 If the Contractor requires it, and if the Subcontractor wants to proceed with the proposal, the Subcontractor must provide (at no cost to the Contractor and the Principal) a report on the details, implications and benefits of the proposal. The report must be prepared by a Consultant acceptable to the Page 34 of 69 Contractor and the Principal. 46.3 The proposal must not include anything which might adversely affect the quality of Design or construction or operation or maintenance of the Subcontract Works. Proposed changes must be consistent with the purpose and intent of the Subcontract and the Subcontract Works. 46.4 The Contractor must consider the Subcontractor's proposal, but is not bound to accept any proposal or proposed changes. No Subcontractor's Claim will arise out of the Contractor's consideration of or failure to accept any proposal or proposed changes. 46.5 Subject to clause 46.7 and 46.8, if the Contractor accepts any changes proposed by the Subcontractor, any actual direct saving in the cost to the Subcontractor of the Subcontract Works resulting from the changes will be for the benefit of the Subcontractor. 46.6 The Contractor may accept the proposed changes subject to conditions. 46.7 The Subcontractor is fully responsible to the Contractor for the compliance of the Subcontract Works and for the changes and their consequences. 46.8 Notwithstanding the provisions of clause 46.5, if indicated in Subcontract Information item 42, the savings in the cost to the Subcontractor of the Subcontract Works with the changes proposed by the Subcontractor and accepted by the Contractor under clause 46 must be shared by the Subcontractor and the Contractor in the proportions of the savings stated in Subcontract Information item 42. The calculated savings must include the assessed reduction in the costs of the Subcontract Works to the Subcontractor and Sub-subcontractors and Suppliers, less any costs incurred by the Contractor in assessing or implementing the changes, including but not limited to related design work. Construction 47. Setting out the Works 47.1 The Subcontractor must set out and construct the Subcontract Works at the locations and levels specified in or required by the Subcontract. 47.2 The Subcontractor may request in writing from the Contractor any necessary additional information to be provided by the Contractor relating to setting out the Subcontract Works not included in the Subcontract Documents. The Subcontractor must make the request at least 14 days prior to the date the Subcontractor proposes to use the information for set out for construction of the part of the Subcontract Works to which the information applies. As soon as practicable, the Contractor must provide any additional information which it has or can reasonably obtain. 47.3 While carrying out the Subcontract Works, if the Subcontractor discovers or is made aware of any error in the location, level, dimension or alignment of the Subcontract Works: 47.3.1 the Subcontractor must notify the Contractor; 47.3.2 the Contractor need not respond to the Subcontractor about any error; Page 35 of 69 47.4 48. 47.3.3 the Contractor may instruct the Subcontractor regarding necessary rectification work and the subcontractor must comply; 47.3.4 the Subcontractor must rectify any error to ensure that the Subcontract Works comply with the Subcontract; and 47.3.5 if an error occurs because of the Contractor's design for which the Contractor retains responsibility and causes the Subcontractor to incur necessarily and unavoidably any extra costs, the Subcontractor may be entitled to those extra costs and an extension of time under clause 54. The Subcontractor must give the Contractor a copy of a survey showing the Subcontract Works as constructed on the Site, including the relationship of the Subcontract Works to any relevant property boundaries, easements, (including any right of way) and improvements on the Site. If requested in writing by the Subcontractor, the Contractor may agree (but is not obliged to do so) by notice in writing that certain matters can be excluded from the survey. The survey must be performed by a registered surveyor or other surveyor to whom the Contractor has no objection. Construction 48.1 48.2 The Subcontractor must supply all Materials and construct the Subcontract Works in accordance with all of the following: 48.1.1 the Subcontract; 48.1.2 the Subcontractor's Documents; 48.1.3 the Contractor's instructions concerning the Subcontract Works; 48.1.4 Statutory Requirements; 48.1.5 the Building Code of Australia (if applicable, as referred to in Subcontract Information item 37B), and relevant Australian Standards; and 48.1.6 if no other standard is specified in the Subcontract, then good industry standards applicable to the Subcontract Works. The Subcontractor must comply with this clause 48 and ensure that the Subcontract Works and every part of them are fit for the purposes required by the Subcontract. This responsibility is reduced to the extent that the Subcontract Works are not fit because of design work by the Contractor for which the Contractor retains responsibility. The Contractor retains responsibility for design wok by the Contractor except as provided by clause 44, if it applies. 48.3 49. The provisions of clause 48.2 are not reduced or affected by any Variations. Testing 49.1 The Subcontractor must: 49.1.1 Test (at its own cost) all parts of the Subcontract Works specified in the Subcontract to be Tested; Page 36 of 69 50. 49.1.2 The Contractor may instruct the Subcontractor at any time to Test any part of the Subcontract Works. The Contractor must pay for the Tests (as an addition to the Subcontract Price) if the results of the Tests show full compliance with the Subcontract. Otherwise, the Subcontractor must pay. 49.1.3 The Subcontractor must repeat the Tests (at its own cost) of all parts of the Subcontract Works where Defects have been found, until the results of these Tests, as reported in writing to the Contractor, confirm that all Defects have been made good and that the Subcontract Works comply with the Subcontract. Defects The Contractor considers the Subcontractor to be an expert in Design and construction of the Subcontract Works and holds the Subcontractor responsible for its work. The Contractor requires Completion to be defect-free. These Defects provisions are to ensure that the Subcontract Works are constructed to the standards required by the Contractor. The Contractor can also rely on its common law rights. Also refer to clause 71 which deals with Defects after Completion. 50.1 The Subcontractor must identify and promptly make good all Defects so that the Subcontract Works comply with the Subcontract. This requirement does not affect any other remedy or right of the Contractor. 50.2 At any time before Completion, the Contractor may instruct the Subcontractor to make good Defects within the time specified in a Defect Notice issued by the Contractor. A similar provision applies after Completion under clause 71.1. 50.3 50.4 50.5 If the Subcontractor fails to make good the Defects in the time specified in the Defect Notice, the Contractor may have the Defects made good by others and then: 50.3.1 the cost will be a debt due to the Contractor and may be deducted from the Subcontract Price, unless a Variation applies under clause 50.5; and 50.3.2 the Subcontractor will be responsible for the work involved in making good the Defects as if the Subcontractor had performed the work. Nothing in this clause 50: 50.4.1 reduces the Subcontractor's warranties and other liabilities and obligations under the Subcontract; or 50.4.2 affects the Contractor's common law right of damages. If at any time before Completion the Subcontractor becomes aware of any defect which results from design or other work or actions for which it is not responsible, it must: 50.5.1 promptly notify the Contractor; and 50.5.2 make good the defect as a Variation under clause 52 if instructed to by the Contractor. Page 37 of 69 51. Acceptance with Defects not made good 51.1 The Contractor, in its absolute discretion (and at any time, whether before or after Completion), may accept that specific Defects defined by the Contractor need not be made good. 51.2 Before the Contractor does so: 51.2.1 the Contractor may propose deductions from the Subcontract Price, and any terms it requires; 51.2.2 if the Subcontractor agrees with the deductions and the terms, the Subcontract Price will be adjusted accordingly; and 51.2.3 if the Subcontractor agrees with the terms but not with the proposed deductions: (a) the Subcontractor is bound by any determination of the Valuer under the Contract in respect of the deductions (provided their value if separately identifiable in the Valuer's certificate) adjusted to take account of the Contractor's Margin; or (b) if there is no Valuer under the Contract or if there is no separately identifiable value determined by the Valuer under the Contract, the Contractor must determine a reasonable price for the deductions under clause 52.5. 51.3 If the parties do not agree in writing on the Contractor's terms, the Subcontractor must make good the Defects defined by the Contractor. 51.4 The Subcontractor remains liable for Defects whether known or not known at the time the Contractor accepts that defined Defects need not be made good under this clause 51. Changes to work 52. Variations Variation instructions 52.1 The Contractor may instruct Variations in writing at any time before Completion (and after Completion in accordance with clause 71.1), and the Subcontractor must comply with these instructions. 52.2 Unless the Contractor considers that urgent or special circumstances exist and instructs the Subcontractor to proceed, the Subcontractor must not begin to carry out a Variation until: 52.2.1 the parties have agreed on its value (including delay costs under clause 55.1) and time implications; or 52.2.2 a party to the Contract has made a request to the Valuer, if a Valuer is engaged; or 52.2.3 where no Valuer is engaged under the Contract, the Contractor makes a determination under clause 52.5 and instructs the Subcontractor to proceed, in each case in accordance with clause Page 38 of 69 52.4. Variation Pricing 52.3 When requested to by the Contractor, the Subcontractor must advise the Contractor of its price (including amounts for any delay costs claimed in accordance with clause 55.1) for a proposed Variation and its effect (if any) on the time for Completion, or on any other matter specified, within the time specified in the request. In advising the Contractor of its effect on the time for Completion, the Subcontractor thereby acknowledges its responsibility to take all reasonable steps: 52.3.1 to carry out the work concurrently with other work whenever possible; and 52.3.2 to otherwise minimise the effects of the Variation on the Contractual Completion Date, including for any Subcontract Milestone. Valuer’s determination 52.4 If the parties agree that a Variation applies, they must endeavour to agree in writing on its value and effect on the time for Completion (if any). Failing agreement on value or time, then: 52.4.1 52.4.2 the Subcontractor is bound by any determination of the Valuer under the Contract in respect of that Variation, if: (a) its value is separately identifiable in the Valuer's certificate; and (b) before the determination, the Subcontractor was given an opportunity to provide information or make known its views to the Valuer, either directly or as part of a submission by a party to the Contract; but if there is no such determination by the Valuer under the Contract, then the Contractor must determine reasonably the value or the adjustment to the time for Completion or both (whichever is not agreed), in accordance with clause 52.5. Contractor's determination 52.5 The Contractor must make any determination under clause 52.4.2 as follows: 52.5.1 If a Variation involves additional or increased work, its value is the sum of the following: (a) the additional reasonable material and plant costs of the Subcontractor; (b) the additional reasonable costs of Sub-subcontract work involved in carrying out the Variation; (c) the additional percentage in Subcontract Information item 48A on the total costs of clauses 52.5.1(a) and 52.5.1(b), which allows for the Subcontractor's Margin; and Page 39 of 69 (d) 52.5.2 52.6 the additional labour costs of the Subcontractor at the hourly rate in Subcontract Information item 48B. If a Variation involves decreased or omitted work, its value is that of the work included in the Subcontract Price: (a) as specified in the Subcontract, or otherwise as determined by the Contractor based on the rates and sums in the Subcontract or otherwise applying at the Date of Subcontract; and (b) including a reasonable Subcontractor's Margin and a reasonable allowance for any time-dependent costs not included in the Subcontractor's Margin which will not be incurred as a result of the decreased or omitted work. 52.5.3 The Contractor must not include any Subcontractor's Margin in the costs in clauses 52.5.1(a) and 52.5.1(b). 52.5.4 The Contractor must not include any amount in the valuation of Subcontract work under clause 52.5.1(b), for extra costs, losses or expenses attributable to any default or negligence of the Subcontractor. 52.5.5 The Contractor must not include any amount in the valuation of a Variation for costs of delay or disruption caused by the Variation. 52.5.6 If the Variation involves an omission or decrease in work, the Contractor must determine a reasonable reduction to the time for Completion. The Subcontract Price must be adjusted to account for the value of the Variation. Disputed Variations 52.7 If the parties do not agree that a Variation applies, all issues relating to the claimed Variation must be dealt with under the Issue resolution procedure in clauses 72 to 75. 52.8 The Subcontractor acknowledges that the development of Design (if applicable) by the Subcontractor does not constitute a Variation. 52.9 Regardless of any other provision of the Subcontract, if the Subcontractor considers that a Variation applies but the Contractor has not instructed a Variation, the Subcontractor must make its Subcontractor's Claim within 5 days from the start of the event giving rise to the Variation, or from the time when the event should have become known to the Subcontractor with reasonable diligence on its part (as applicable). Refer also to clause 72.3. 52.10 Variations instructed by the Contractor must be generally consistent with or of a similar nature to the work included in the Subcontract Works at the Date of Subcontract. Variations under the Contract 52.11 If a Variation (as defined in the Contract) is instructed under the Contract which results in a substantial change (including any omission or decrease of Page 40 of 69 work) in the Subcontract Works, the Subcontractor must comply with the Contractor's instructions to vary the Subcontract Works. This does not cause any default on the part of the Contractor or any entitlement of the Subcontractor to compensation (other than in the case of a Variation requiring the Subcontractor to carry out increased or extra work or changed work). 53. Changes in Statutory Requirements 53.1 If Statutory Requirements change after the Date of Subcontract and a change to the Subcontract Works may be required as a result, the Subcontractor must promptly notify the Contractor. The Contractor must instruct a Variation under clause 52 if the Contractor requires a change to the Subcontract Works as a result. Changes to time The Subcontractor is responsible for managing progress to meet Contractual Completion Dates for Subcontract Milestones of any) and for the Subcontract Works. These dates or times for Completion are initially given in the Subcontract Information, but may be adjusted under clauses 41 (Site Conditions), 52 (Variations), 54 (Extensions of time), and 56 (Acceleration). 54. Extensions of time Under the conditions set out in clause 54 the Contractor will extend the time for Completion if there is nothing the Subcontractor can reasonably do to avert circumstances beyond its control to avoid delay. Refer also to clauses 25 Time management and 69 Completion. 54.1 If the Subcontractor is or will be delayed in reaching Completion, the Subcontractor will be entitled to an extension of time for Completion for the number of days assessed by the Contractor, if the Subcontractor satisfies the Contractor that all the following conditions apply: 54.1.1 The cause of the delay was beyond the control of the Subcontractor (including an act, default or omission of the Contractor, but not including a Variation instructed or agreed by the Contractor or otherwise determined). Extensions of time for Variations are dealt with under clause 52 or under clauses 72 to 75. 54.1.2 The Subcontractor has taken all reasonable steps to avoid and minimise the delay and its effects. 54.1.3 The Subcontractor has given to the Contractor each of the notices required under clauses 54.2 and 54.3. 54.1.4 The delay occurred to an activity or activities on a critical path of the then current Contract Program, as provided for in clause 25, and the Subcontractor has submitted this Contract Program with the notice required under clause 54.3. 54.2 The Subcontractor must give the Contractor notice of the delay, its cause, relevant facts, and its expected impact, as soon as practicable (and in any event within 3 days) after the delay commenced. 54.3 Within 7 days of commencement of the delay, the Subcontractor must give Page 41 of 69 the Contractor notice of the extension of time claimed, together with the information required under clause 25.11 and other information sufficient for the Contractor to assess the Subcontractor's Claim. If the delay continues for more than 7 days, the Subcontractor must give a further notice every 14 days thereafter, until after the delay ends, if the Subcontractor wishes to make a Subcontractor's Claim for a further extension of time, together with further information of the kind required by this clause 54.3, 55. 54.4 An extension of time is only given for delays occurring on days on which the Subcontractor usually carries out work for the Subcontract. 54.5 When concurrent events cause a delay in reaching Completion and one or more of the events is within the control of the Subcontractor, then to the extent that the events are concurrent, the Subcontractor will not be entitled to an extension of time for Completion notwithstanding that another cause of the delay is such that the Subcontractor would have had an entitlement to an extension of time. 54.6 The Contractor may in its absolute discretion for the benefit of the Contractor extend the time for Completion at any time and for any reason, whether or not the Subcontractor has made a Subcontractor's Claim for an extension of time. The Subcontractor is not entitled to an extension of time for Completion under this clause 54.6 unless the Contractor exercises its discretion to extend the time for Completion. 54.7 This clause 54 is subject to the provisions of any other clause in the Subcontract which entitles the Subcontractor to an extension of time for Completion. Delay costs Delays caused by the Contractor Clauses 55.1 and 55.2 prescribe the Subcontractor's rights when the Contractor causes a delay to the Subcontractor in reaching Completion. Where prescribed in the Subcontract, the Subcontractor may be entitled to payment of delay costs which are caused by a specified delaying event. Otherwise, the Subcontractor is not entitled to extra payment for delay, disruption or interference of any nature whatsoever caused by the Contractor (including for a breach of the Subcontract by the Contractor). 55.1 Subject to clause 55.1A, the Subcontractor is entitled to delay costs at the rate or rates in Contract Information item 51A, for the number of days by which the time for Completion is extended because of a delay caused only by: 55.1.1 a Variation, other than one for which, under clauses 41.6, 42.4 and 44.3, there is no payment for delays; or Clause 41.6 deals with Site Conditions, 42.4 with ambiguities in the Contract Documents, and 44.3 with Faults in Contractor's Documents. 55.1.2 a breach of the Subcontract by the Contractor which causes delay, disruption or interference to the Subcontractor carrying out the Subcontract Works. 55.1A Any payment under clause 55.1 is subject to the following exceptions: 55.1A.1 where the Subcontract provides for Subcontract Milestones each with a separate Contractual Completion Date, an amount shall only be payable under clause 55.1 where the Subcontractor has been granted an extension of time in respect of the Contractual Page 42 of 69 Completion Date which is latest in time (and not otherwise); 55.1A.2 where an event causes concurrent delays to more than one Subcontract Milestone, then to the extent the delays are concurrent, the delay rate shall only be applied once; 55.1A.3 delay costs shall only be calculated for days on which the Subcontractor usually carries out work for the Contract; and 55.1A.4 nothing in clause 55.1 shall oblige the Contractor to pay extra costs for delay or disruption which have already been included in the value of a Variation or any other payment under the Subcontract. 55.2 The rate or rates of delay costs will be reduced where the Principal (or anyone authorised by the Principal) is using or occupying any part of the Works prior to Completion, under clause 68. This reduction in the delay costs will be determined by the Contractor acting reasonably. The reduced rate or rates of delay costs will be the same proportion of the full rate or rates as is the value (as agreed by the parties or failing agreement, as determined reasonably by the Contractor) of the remaining work to achieve Completion to the Subcontract Price. 55.3 The Subcontractor's only remedies for delay, disruption or interference of any nature whatsoever caused by the Contractor (including for a breach of the Subcontract by the Contractor, as referred to in clause 55.1.2) whether under the Subcontract, at law or otherwise, are an extension of time for Completion under clauses 41, 52 or 54, and delay costs under clause 55.1 and 55.2. Delay to Completion If indicated in Subcontract Information Item 51, the Subcontract provides for liquidated damages to be payable by the Subcontractor to the Contractor, if the Subcontractor fails to achieve Completion by the Contractual Completion Date. 55.4 If the Subcontractor fails to achieve Completion by the Contractual Completion Date as required by clause 69, the Subcontractor will be liable to pay the Contractor liquidated damages as a debt due and owing at the rate stated in Subcontract Information item 51B for every day after the Contractual Completion Date to and including the Actual Completion Date. If, however, the Subcontract is terminated under clauses 78 or 79, before the Subcontractor reaches Completion, any applicable liquidated damages for failure to achieve Completion by the Contractual Completion Date will run to the date of termination of the Subcontract. 55.5 The Contractor, in its absolute discretion, may demand payment of the liquidated damages amount from the Subcontractor or may deduct, withhold or set-off the liquidated damages amount from any amount otherwise payable to, or security provided by the Subcontractor. A failure by the Contractor at any time to demand payment or to deduct, withhold or set-off the liquidated damages will not amount to a waiver of or otherwise affect the Contractor's rights and entitlements. 55.6 If the Contractual Completion Date is extended after the Subcontractor has paid or the Contractor has deducted liquidated damages, the excess amount of liquidated damages paid by the Subcontractor or deducted by the Contractor will be payable by the Contractor to the Subcontractor, subject to any right of set-off which the Contractor may have. 55.7 The amount of liquidated damages will be reduced where the Principal or Page 43 of 69 the Contractor (or anyone authorised by the Principal or the Contractor) is using or occupying any part of the Subcontract Works prior to Completion, under clause 68. This reduction in the amount of liquidated damages otherwise payable under the Subcontract will be determined by the Contractor acting reasonably. The reduced amount will be an amount which is in the same proportion to the full amount of liquidated damages otherwise payable as is the value (as agreed by the parties or failing agreement, as determined reasonably by the Contractor) of that part of the Subcontract Works used or occupied is to the Subcontract Price. 56. 57. 55.8 The Subcontractor acknowledges that the rate for liquidated damages set out in Subcontract Information item 51B represents a genuine pre-estimate of the amount of loss or damage, as calculated at the Date of Subcontract, which the Contractor is likely to suffer if the Subcontractor fails to reach Completion by the Contractual Completion Date. The Subcontractor warrants that it will not challenge the rate for liquidated damages as being in the nature of a penalty. 55.9 The provisions of clauses 55.4 to 55.8 apply to a failure by the Subcontractor to achieve Completion by the Contractual Completion Date, in respect of the Subcontract Works and also in respect of any Subcontract Milestones. Acceleration 56.1 The Contractor may instruct the Subcontractor to accelerate progress of the carrying out of the Subcontract Works. The instruction must be in the form of an Acceleration Notice, and the Subcontractor must comply unless, before taking any steps to accelerate, it demonstrates to the satisfaction of the Contractor that the acceleration as instructed cannot be reasonably achieved. 56.2 The Subcontractor is not entitled to payment under this clause 56 if no Acceleration Notice is issued. 56.3 Whenever possible, the parties must agree on the steps to be taken and basis for payment for acceleration before the Subcontractor takes those steps, or failing agreement, the Contractor must determine a reasonable value. 56.4 The Contractor must pay the Subcontractor for acceleration (as an addition to the Subcontract Price) if it achieves the acceleration instructed by the Contractor, but the value must take into account any relevant extensions of time which may be granted under clauses 41, 52 or 54 for delay during the period of acceleration. Contractor's suspension 57.1 The Contractor may instruct the Subcontractor to suspend progress of the Subcontract Works and Temporary Work, and the Subcontractor must comply. 57.2 The Subcontractor must resume carrying out the Subcontract Works and Temporary Work when instructed to by the Contractor. 57.3 If the need for the suspension arises from the Contractor's own act or omission, then the Subcontractor will be entitled to: 57.3.1 any extension of time granted under clauses 52 or 54; and Page 44 of 69 57.3.2 57.4 58. (as an addition to the Subcontract Price) its reasonable, direct Site and off-Site costs of the suspension, unavoidably incurred, having taken all reasonable steps to minimise the costs. The Subcontractor has no other remedies in connection with the suspension. Subcontractor's suspension 58.1 The Subcontractor may suspend work for or in connection with the Subcontract if the Contractor: 58.1.1 has both; (a) become liable to pay the Subcontractor the full amount of a Payment Claim made in accordance with clause 62 (excluding payments already made), or the Scheduled Amount; and (b) failed to pay it within the time prescribed by clause 63. 58.2 Before it suspends work under this clause 58, the Subcontractor must give the Contractor at least 2 Business Days notice of its intention to do so. The Subcontractor may suspend work on expiry of the 2 Business Days if it has still not been paid. 58.3 The Subcontractor must resume all work within 3 Business Days of having been paid the amount referred to in clause 58.1. 58.4 If the Subcontractor elects to suspend work under this clause 58, then it may be entitled to an extension of time under clause 54, but despite clause 55, the Subcontractor will not be entitled to delay costs or damages under clause 55. Payment 59. The Subcontract Price 59.1 The Subcontract Price, and the rates and/or lump sums it includes, are not adjusted for rise or fall in the cost of labour or Materials provided by the Subcontractor, or for new, changed or increased taxes, duties or other imposts, unless expressly stated in the Subcontract. If specified in Subcontract Information item 40 that rise and fall adjustments are to be made, the provisions of Schedule 8 (Cost Adjustment Formula) apply. Schedules of Rates 59.2 At the Date of Subcontract, quantities in a Schedule of Rates are estimated only, and the Contractor does not guarantee either the estimated quantities or the descriptions of the items. 59.3 If a Schedule of Rates is included in the Subcontract, the Subcontract Price is the sum of the products of the quantities and the relevant rate for each item in the Schedule of Rates, plus all lump sums of any). Before an item is completed, the estimated quantity is used in the calculation of the Subcontract Price. After an item is completed, the actual quantity measured in accordance with the Contract will be used in the calculation of the Page 45 of 69 Subcontract Price. 59.4 The Subcontractor is entitled to payment of the Subcontract Price calculated for actual quantities measured in accordance with the Subcontract. Provisional Sums and Provisional Quantities Provisional Sums and Provisional Quantities (if any) are shown in a Reference Subcontract Document listed at Contract Information item 17. 60. 59.5 The Subcontractor must carry out work which is the subject of a Provisional Sum as instructed by the Contractor, on the terms the Contractor specifies in the instruction. 59.6 If the Contractor instructs the Subcontractor to carry out work which will be the subject of a Provisional Sum the Subcontract Price will be adjusted as follows: 59.6.1 The amount of the Provisional Sum specified in the Subcontract must be deducted from the Subcontract Price. 59.6.2 The cost of work performed by a Sub-subcontractor or a Supplier under a Sub-subcontract or by a Consultant (excluding any amount payable due to default or negligence of the Subcontractor) must be added to the Subcontract Price, together with the amount calculated by applying the Provisional Sum margin percentage stated in Subcontract Information item 47 to the cost of work. 59.6.3 The cost of any work performed directly by the Subcontractor, and the cost of Materials supplied directly by the Subcontractor (including in each case a reasonable allowance for overhead and profit), must be added to the Subcontract Price without a Provisional Sum margin. 59.7 If the Contractor does not instruct the Subcontractor to carry out work which is the subject of a Provisional Sum the amount allowed in the Subcontract Price for that work must be deducted from the Subcontract Price. 59.8 If the Contractor instructs the Subcontractor to carry out work which is the subject of a Provisional Quantity and that instruction requires the Subcontractor to carry out a greater or lesser quantity of work than the Provisional Quantity, including that no work the subject of the Provisional Quantity will be carried out, the Subcontract Price must be adjusted by the amount calculated by multiplying the contract rate applicable to the Provisional Quantity work by the difference between the Provisional Quantity and the quantity of work carried out. Entitlements 60.1 Except as otherwise expressly stated under the Subcontract, the Subcontract Price is only to be increased if required under any of the following clauses: 60.1.1 clause 10.4 (Temporary Work); 60.1.2 clause 10.5 (Work methods); 60.1.3 clause 41 (Site Conditions); 60.1.4 clause 42 (Ambiguities); Page 46 of 69 60.1.5 clause 49 (Testing); 60.1.6 clause 52.5 (Variations); 60.1.7 clause 55.1.1 (Delay costs); 60.1.8 clause 56.4 (Acceleration); 60.1.9 clause 57.3 (Contractor's suspension); 60.1.10 clause 59.3 (Subcontract Price - Schedules of Rates); 60.1.11 clause 59.6 (Subcontract Price - Provisional Sums); 60.1.12 clause 59.8 (Subcontract Price - Provisional Quantities); and 60.1.13 clause 66 (Interest on late payments). 60.2 60.3 61. The Subcontract Price may be decreased if required by the Subcontract. Clauses that allow decreases in the Subcontract Price include: 60.2.1 clause 29.6 (Care of people and property); 60.2.2 clause 36.10 (Insurance — Proof of Cover) 60.2.3 clause 42 (Ambiguities); 60.2.4 clause 50.3 (Defects); 60.2.5 clause 51.2 (Acceptance with Defects not made good); 60.2.6 clause 52.5 (Variations); 60.2.7 clause 59.3 (Subcontract Price - Schedules of Rates); 60.2.8 clause 59.6, 59.7 & 59.8 (Subcontract Price - Provisional Sums and Provisional Quantities); and 60.2.9 clause 71.1 (After Completion). The Subcontractor is not entitled to any other payments related to the subject matter of the Subcontract, under the Subcontract or otherwise, except: 60.3.1 under clauses 64, 78 and 79; 60.3.2 for breach of the Subcontract; or 60.3.3 where this exclusion is not permitted by law. Prepayment Prepayment is an advance payment against the Subcontract Price which provides early cash flow to the Subcontractor, Sub-subcontractors, Suppliers and Consultants. They can keep the Prepayment, until it is deducted from amounts otherwise payable towards the end of the series of Progress Payments or Milestone Payments, unless the Subcontractor requests earlier return of Undertakings provided to the Principal in respect of the Page 47 of 69 Prepayment. Prepayment may be utilised by the Subcontractor, Sub-subcontractors, Suppliers and Consultants for any purpose related to the Subcontract. 61.1 62. The Subcontractor may claim Prepayment, as advance payment against the Subcontract Price (separate from Payment Claims) at any time before achieving Completion if all the following apply: 61.1.1 the total amount claimed for Prepayment is no more than the amount in Subcontract Information item 44; 61.1.2 if required by the Contractor, and in consideration of the Principal accepting the Undertaking and providing the Prepayment, the Subcontractor has provided an Undertaking (additional to Undertakings required under clause 37) to the Principal for the amount of the Prepayment allocated to the Subcontractor; and 61.1.3 the Contractor has assigned those Prepayment amounts directly to the Subcontractor, in writing, and has notified the Principal of the assignment; and 61.1.4 the Subcontractor has acknowledged in writing to the Principal that it understands the Principal may make a demand against the Undertakings in the circumstances provided or in this clause 61. 61.2 The Subcontractor is entitled to receive payment of the amount claimed within 14 days after all the conditions in clauses 61.1 have been met. 61.3 The Contractor must cause the Undertaking provided for Prepayment to be returned, after deducting the value of the Prepayment made (as adjusted by any earlier such deductions) from payments otherwise payable to the Subcontractor, as follows: 61.3.1 on achieving Completion of the whole of the Subcontract Works; 61.3.2 as requested in writing by the Subcontractor; or 61.3.3 when the total of the Prepayment made (as adjusted by such deductions) and Payment Claims to date equals or exceeds the Subcontract Price. Payment Claims The Subcontract allows for payment by regular (usually monthly) Progress Payments, or on the Completion of Subcontract Milestones. The two can be used together. 62.1 Unless otherwise specified in the Subcontract, the Subcontractor must make Payment Claims for the Claimed Amount based on the Valued Completed and as specified in clause 62. Subject to clause 62.2, Payment Claims must be made monthly on the date in each month specified in Subcontract Information item 49A, starting no earlier than the 14th day after the Date of Subcontract and ending with the Final Payment Claim referred to in clause 65. Payment Claims made monthly are to include amounts for work carried out to the end of the previous month. 62.2 If Subcontract Information item 49B specifies payment by Milestone Payment, then the Subcontractor may only make a Payment Claim for the value of a Subcontract Milestone on its Completion. If Subcontract Information item 49B specifies payment by Milestone Payment and monthly Page 48 of 69 Progress Payment, then the Subcontractor must make a Payment Claim in accordance with this clause 62.2 for Milestone Payments and clause 62.1 otherwise. 62.3 The Subcontractor must submit Payment Claims in the form of Schedule 3 (Payment Claim Worksheet), or in such other form to which the Contractor agrees. 62.4 A 62.5 62.6 62.7 Payment Claim must: 62.4.1 identify the work and Materials to which the Payment Claim relates; 62.4.2 indicate the amount of the Progress Payment that the Subcontractor claims to be due for the work done to which the payment relates, in accordance with clause 62.1, after allowing for the retention of the Completion Amount under clause 64 and for payments already made, as the Value Completed Payment Claims must show all Subcontractor's Claims: 62.5.1 for amounts the Contractor has agreed to or is required to pay in connection with a Subcontractor's Claim under clause 72 or another provision of the Subcontract; and 62.5.2 for interest (if any) due to the Subcontractor under clause 66. Payment Claims must be accompanied by: 62.6.1 all relevant calculations; 62.6.2 a completed and true statutory declaration executed on the date of the Payment Claim, in the form of Schedule 7 (Statutory Declaration) relating to payment of employees, Subcontractors, Suppliers and Consultants, workers compensation insurance premiums, payroll tax payments and to all Subcontract monies held in trust by the Contractor; 62.6.3 Conformance Records showing conformance with particular requirements of the Subcontract, as provided in the Subcontract, and the certificates in the form of Schedule 4 (Certificate of Compliance), signed by the Subcontractor and also by any Consultants involved in the work, verifying that all work that has been done including Design and construction with Materials that have been supplied are in accordance with the Subcontract; and 62.6.4 any other information specified in the Subcontract. Payment Claims, the Claimed Amount and the Value Completed must not include amounts for: 62.7.1 subject to the provisions of clause 62.8, work or Materials not yet incorporated into the Subcontract Works; or 62.7.2 Subcontractor's Claims (including Subcontractor's Claims for Variations not agreed to by the Contractor, nor determined by the Valuer, nor determined under clause 52.4.2 or otherwise) not agreed to by the Contractor or Subcontractor's Claims not yet Page 49 of 69 determined, as referred to in clauses 72 to 75. 62.8 62.9 Subject to all of the following conditions, the Subcontractor may include an amount in a Payment Claim for Materials intended for incorporation in the Subcontract Works but not yet incorporated, if: 62.8.1 prior to the Subcontractor giving the Payment Claim, the Contractor agrees in writing to pay the Subcontractor for Materials not yet incorporated into the Subcontract Works; 62.8.2 the Subcontractor provides a detailed schedule of the specified Materials and evidence that the Materials are marked in the name of the Principal and are insured for their full value, no later than 14 days before submitting the Payment Claim; 62.8.3 prior to submitting the Payment Claim the Subcontractor provides an Undertaking to the Principal equal to the amount to be included in the Payment Claim for the specified Materials not yet incorporated into the Subcontract Works; 62.8.4 the only unfixed Materials included in the valuation are those that have become or, on payment for Materials still unfixed, will become the property of the Contractor free of any Encumbrance; 62.8.5 the Subcontractor provides to the Contractor evidence of the Subcontractor's ownership; and 62.8.6 for any such Materials imported or to be imported into Australia the Subcontractor has given the Contractor a clean on board bill of lading for the Materials, drawn or endorsed to the order of the Principal, appropriate insurance certificates and a Customs invoice for the Materials. The Subcontractor warrants for itself and for and on behalf of Subsubcontractors and Suppliers that no Encumbrance exists over any Materials incorporated into the Subcontract Works by the Subcontractor. If the Subcontract or the Subcontractor's employment under the Subcontract is terminated by the Contractor, the Subcontractor must ensure that the Contractor, in respect of any unfixed Materials for which payment has been made or which have been appropriated to the Subcontract, may enter upon any premises where the Materials are stored and take possession of these Materials. 62.10 For work carried out and allowed in each Payment Claim, the following applies in calculating the Claimed Amount and the Value Completed: 62.10.1 For work covered by a lump sum: (a) The Subcontractor may claim a lump sum by instalments with each Payment Claim calculated as follows. The total of the lump sum instalments must never exceed the total of the lump sum. (b) For each activity or element of the Works listed in Schedule 3 (Payment Claim Worksheet) under "activity" (column 1), record the percentage completed under "activity completed %" (column 4). The value of work claimed for that activity is Page 50 of 69 the percentage of the "value of activity" or lump sum (column 3) and is recorded under "Value Completed $" (column 5). The subtotal of "Value Completed $" amounts for all activities is recorded in column 5. 62.10.2 For work covered by a Schedule of Rates: (a) For each item carried out listed in Schedule 3 (Payment Claim Worksheet) under "activity" (column 1), calculate the product of the "quantity completed" (column 4) actually carried out (measured in accordance with the Subcontract) and its rate (column 3) in the Schedule of Rates as the "Value Completed $" and record it in column 5. (b) The subtotal of "Value Completed $" of work for all Schedule of Rates items is recorded in the Payment Claim Worksheet under "Value Completed $" (column 5). 62.10.3 The Value Completed at the time of the Payment Claim is the sum of the values of work completed (and subtotal "Value Completed $" amounts) calculated under clauses 62.10.1 and 62.10.2. 63. Payments 63.1 When given a Payment Claim by the Subcontractor, the Contractor must within 15 Business Days: 63.1.1 if it agrees with the Payment Claim, adopt it as its assessment; or 63.1.2 if it disagrees with the Payment Claim, prepare its own assessment, in consultation with the Subcontractor if appropriate, and give to the Subcontractor a Subcontract Payment Schedule. 63.2 The Contractor's assessment in the Subcontract Payment Schedule must: 63.2.1 identify the Payment Claim to which it relates: 63.2.2 indicate the amount of the payment (if any) that the Contractor proposes to make as the Scheduled Amount; and 63.2.3 if the Scheduled Amount is less than the Claimed Amount (excluding payments already made) indicate why it is less and Of it is less because the Contractor is withholding payment for any reason), the Contractor's reasons for withholding payment. 63.3 If the Scheduled Amount which the Contractor proposes to pay is less than the Claimed Amount (excluding payments already made), the Subcontractor may give notice of an Issue under clause 73. 63.4 Reasons why the Scheduled Amount may be less than the Claimed Amount (excluding payments already made) or for withholding payment include: 63.4.1 disagreement with the Claimed Amount; 63.4.2 progressive retention of the Completion Amount under clause 64; Page 51 of 69 63.5 64. 63.4.3 the costs and estimated costs associated with remedying Defects; 63.4.4 amounts the Contractor is otherwise entitled to withhold, set-off or otherwise deduct; 63.4.5 Prepayment deductions in accordance with clause 61; and/or 63.4.6 exclusion of amounts the Contractor has not agreed, or is not required, to pay in connection with a Subcontractor's Claim under clause 72 or another provision of the Subcontract. The Contractor must pay to the Subcontractor as a Progress Payment the Scheduled Amount by the later of: 63.5.1 the number of Business Days specified in Subcontract Information item 49C (or if no period is specified than 15 Business Days) after expiry of the 15 Business Day period in clause 63.1; and 63.5.2 the period specified in the Subcontract, after the Subcontractor takes any other actions and complies with any other obligations required which are stated in the Subcontract to be pre-conditions to payment before any payment is payable. 63.6 Unless the parties agree on another method, all payments to the Subcontractor must be made by electronic funds transfer to the Subcontractor's account specified in the relevant Payment Claim Worksheet provided by the Subcontractor. 63.7 Payment by the Contractor is not evidence that the Contractor accepts the value, quantity or quality of work or that the Subcontractor has complied with the Subcontract or that the Subcontractor has any particular entitlement, and is payment on account only. Payments made by the Contractor do not affect or prejudice any of the Contractor's rights, powers, remedies or defences and are subject to review pursuant to the provisions of clauses 73 to 75 or otherwise as permitted by the Subcontract (including by litigation). Completion Amount The Completion Amount provides an incentive; the earlier the Subcontractor achieves defect-free Completion of the whole of the Subcontract Works, the earlier the payment occurs. 65. 64.1 The Completion Amount, if one is specified in Contract Information item 45, becomes an entitlement of the Subcontractor on Completion of the whole of the Subcontract Works. The Subcontractor may then claim it in the next Subcontract Payment Claim, subject to the Contractor's right to set-off under clause 67. 64.2 The Contractor will retain the Completion Amount from Subcontract Payment Claims when the Value Completed exceeds fifty percent (50%) of the Subcontract Price. 64.3 The Contractor will own any interest earned on the monies retained for the Completion Amount. Final payment This clause contains provisions which apply to the Subcontractor's Final Payment Claim Page 52 of 69 and the Contractor's Final Subcontract Payment Schedule in addition to those in clauses 62 and 63. 65.1 The Subcontractor must submit a Final Payment Claim within 12 weeks after achieving Completion of the whole of the Subcontract Works. The Final Payment Claim must include any Subcontractor's Claim not previously claimed in a Payment Claim, and which is then permitted under clauses 62 and 63 of the Subcontract, being a Subcontractor's Claim agreed to by the Contractor or if not agreed, having been determined in accordance with the Subcontract. 65.2 Within 15 Business Days of receiving the Final Payment Claim (or, if the Subcontractor has not submitted a Final Payment Claim, within 13 weeks after the Subcontractor has achieved Completion of the whole of the Subcontract Works), the Contractor must give the Subcontractor a Final Subcontract Payment Schedule stating the amount payable by one party to the other and where the Subcontractor has submitted a Final Payment Claim, complying with the relevant provisions of clause 63. 65.3 Any payments by the Subcontractor to the Contractor in accordance with the Final Subcontract Payment Schedule must be made within a further 28 days after it is issued. Refer to clause 63 for provisions covering payments by the Contractor to the Subcontractor. 65.4 Any other Subcontractor's Claim not previously brought which the Subcontractor is then entitled under the Subcontract to bring must be made (separate from the Final Payment Claim) within 12 weeks after achieving Completion of the whole of the Subcontract Works. Otherwise it is barred. If the Contractor agrees to a Subcontractor's Claim involving money under this clause 65.4, the Contractor will make payment within 28 days of such agreement or of it being determined in accordance with the Contract. 65.5 The issue of the Final Subcontract Payment Schedule is conclusive evidence that all necessary increases to the Subcontract Price or to any other entitlement of the Subcontractor have been made, except for those required by: 65.6 66. 65.5.1 arithmetical error; or 65.5.2 valuation of Variations under clause 52 relating to a Subcontractor's Claim made in accordance with clause 65.4; and 65.5.3 resolution under clauses 72 to 75 (as applicable) of: (a) any Subcontractor's Claim (other than Variations valued under clause 52) made in accordance with clause 65.4; or (b) any other Issue raised which may properly be raised in accordance with the Subcontract during a period of 28 days following the issue of the Final Subcontract Payment Schedule. The Subcontractor's liability under the Subcontract or otherwise is not affected by the issue of the Final Subcontract Payment Schedule. The Subcontractor's liability continues until any limitation period under statute expires. Interest on late payments Page 53 of 69 66.1 67. A party which fails to make a payment by the time or by the last day of the period prescribed by the Subcontract must pay interest to the other party, at the rate in Subcontract Information item 50, for the period the payment is late. Set-off 67.1 If the Contractor claims a sum under or arising out of the Subcontract, either in circumstances when Subcontractor's Insolvency applies, or in relation to a matter for which the Principal has claimed a sum under the Contract, then it may: 67.1.1 withhold, deduct or set-off the claimed sum against any sum to which the Subcontractor is otherwise entitled under or arising out of the Subcontract; and 67.1.2 make a demand against the Undertakings, cash security or retention money provided under clause 37 for any amount of the claimed sum in excess of the sum to which the Subcontractor is then entitled. Completion 68. Early use 68.1 Before the Subcontractor achieves Completion, the Principal (and anyone authorised by the Principal) may use or occupy (but is not obligated to) any part of the Subcontract Works which is sufficiently complete, or the whole of the Subcontract Works and then: 68.1.1 the Subcontractor's responsibilities are not affected, except if they are reduced under clause 29.4 or if the Principal or the Contractor (or anyone authorised by the Principal or the Contractor to use or occupy any part of the Subcontract Works) causes the Subcontractor's work to be hindered; and 68.1.2 the Principal or the Contractor (as applicable) becomes responsible for any additional insurance required. 68.2 If the Principal or the Contractor requires to use or occupy any part or the whole of the Subcontract Works before the Subcontractor achieves Completion, as provided in clause 68.1, the Contractor must give not less than 21 days notice in writing to the Subcontractor that the Principal will be using or occupying a part or parts, or the whole of the Subcontract Works and must specify those parts, or that the whole of the Subcontract Works is, to be so used or occupied. 68.3 The Subcontractor must do everything necessary to provide to the Contractor promptly, but in any event no later than 14 days after receipt of the notice in clause 68.2, all documents and other things relevant to the parts to be used or occupied as are listed in the second paragraph of the definition of Completion, and to otherwise provide full assistance and cooperation to the Principal or the Contractor (as applicable) (and anyone authorised by the Principal or the Contractor (as applicable)) in the use and occupation of the Subcontract Works. Page 54 of 69 69. Completion The Subcontract requires defect-free Completion. There is no concept of 'practical completion" applying to the Subcontract. Completion applies to any Subcontract Milestones as well as to the whole of the Subcontract Works. 70. 69.1 The Subcontractor must achieve Completion by the Contractual Completion Date. 69.2 When the parties agree that Completion has been achieved, each party acting reasonably, the Contractor must give the Subcontractor a notice stating the Actual Completion Date. Close-out workshop The close-out workshop is an opportunity to review the management of the Subcontract. It is also used to collect and provide feedback to the parties to enable them to improve the overall communication and management process for any possible future contracts. The purpose of the workshop is to provide a realistic assessment of the performance by the workshop participants. 71. 70.1 If required by the Contractor, the Subcontractor must attend a close-out workshop convened by the Principal within 21 days after achieving Completion of the whole of the Works. The structure and processes that apply to evaluation and monitoring meetings under clause 6 apply to the close-out workshop. 70.2 Each party and any others who participate in the workshop must meet their own costs for attendance at the close-out workshop, and the parties to the Contract will share equally the other costs. After Completion 71.1 At any time after Completion: 71.1.1 the Contractor may instruct the Subcontractor to make good Defects within the time specified in a Defect Notice 71.1.2 if the Subcontractor fails to make good the Defects in the time specified in the Defect Notice, the provisions of clauses 50.3 and 50.4 will apply; and 71.1.3 the Contractor may instruct a Variation in connection with any Defect instead of requiring the Defect to be made good under clause 71.1.1. 71.2 This clause 71 does not reduce the Subcontractor's liability, whether arising under the Contract or otherwise. The Subcontractor's liability continues until any limitation period under statute expires. 71.3 This clause 71 does not affect the Contractor's rights under clause 51. CLAIM AND ISSUE RESOLUTION This section provides a step-by-step procedure for handling Subcontractor's Claims and Issues. Generally, the aim of the Subcontract is for the parties to resolve matters through discussions as soon as possible and within the times specified. Further steps are only needed if the parties have been unable to resolve matters between themselves. Page 55 of 69 Claim resolution 72. Subcontractor's Claims 72.1 Any Subcontractor's Claim not made, assessed and determined under another provision of the Subcontract must be made, assessed and determined under this clause 72 (unless determination of the Subcontractor's Claim is regulated by a separate procedure under any applicable legislation). These clauses deal with Subcontractor's Claims made, assessed and determined under another provision of the Subcontract: 41 Site Conditions 42 Ambiguities (In pad) 44 Adopting Contractor's Documents 49 Testing 51 Acceptance with Defects not made good 53 Changes in Statutory Requirements 52 Variations (in part) 54 Extensions of time 55 Delay costs 61 Prepayment 62 Payment Claims 64 Completion Amount 65 Final payment (in part). 72.2 Where the Subcontractor is entitled to make a Subcontractor's Claim under a provision of the Subcontract including under clause 65.4, which does not specify a time for making the Subcontractor's Claim or otherwise in relation to the Subcontract or the Subcontract Works, then the Subcontractor's Claim must be made within 21 days from: 72.2.1 the start of the event giving rise to it; or 72.2.2 the time the event should have become known to the Subcontractor, with reasonable diligence on its part. 72.3 If the Subcontractor fails to make a Subcontractor's Claim within the specified time, the Subcontractor is not entitled to interest on any amount involved in the Subcontractor's Claim for the period before the Subcontractor made the Subcontractor's Claim. However, any Subcontractor's Claim not made within the times specified in clause 65 is barred. 72.4 Each Subcontractor's Claim must include information sufficient for the Contractor to assess the Subcontractor's Claim, without the need for further information. This includes the factual and legal basis, detailed quantification and responses by the Subcontractor to the questions set out in paragraphs 1.1 and 1.2 of the Schedule 6 (Expert Determination Procedure). 72.5 The Contractor must assess a Subcontractor's Claim, and reach agreement Page 56 of 69 about it with the Subcontractor or reject it, within 21 days after receiving the Subcontractor's Claim with all information required by clause 72.4. 72.6 If the Contractor agrees to a Subcontractor's Claim involving money, the Subcontractor may claim the agreed amount only by including it in a Payment Claim under clause 62.9 or 65.1 (excluding a Subcontractor's Claim made under clause 65.4, for which the Contractor will make payment within 28 days of such agreement or of it being determined in accordance with the Subcontract). 72.7 If a Subcontractor's Claim is rejected or not agreed it will be an Unresolved Subcontractor's Claim, and then the Subcontractor may notify the Contractor that it disputes the rejection or failure to agree as an Issue, within 7 days after the end of the 21 day period referred to in clause 72.5. 72.8 The provisions of clauses 72.2 to 72.7 (where no alternative provision applies or these provisions are not consistent with the context) apply generally to all Subcontractor's Claims whether made under clause 72 or under another provision of the Subcontract. Issue resolution 73. Notification of Issue 73.1 The Subcontractor may dispute an assessment, determination or instruction of the Contractor, or an Unresolved Subcontractor's Claim, by giving notice to the Contractor (copied to the Contractor's senior executive named in Subcontract Information item 7A) of an Issue within 21 days after the assessment, determination or instruction, or within 7 days as provided in clause 72.7 for an Unresolved Claim. 73.2 Either party may give notice to the other (copied to that party's senior executive) of an Issue (excluding an Issue referred to in clause 73.1, but including a claim by the Contractor) about the meaning or effect of the Subcontract, or about any matter arising under, out of or in any way connected with the Subcontract, within 21 days after becoming aware of the Issue. 73.3 The parties must follow the Issue resolution procedure in clauses 73, 74 and 75 before either commences proceedings or takes similar action. 73.4 Subject to clauses 65 and 72, if the Contractor or the Subcontractor (as applicable) gives notice of an Issue but not within the time provided by clauses 73.1 and 73.2, (in the case of the Subcontractor) or within the time provided by the clause 73.2 (in the case of the Contractor) and it is resolved in favour of the party giving notice of the Issue, that party will not be entitled to interest on any amount involved in the Issue for the period before notice of the Issue was given. 73.5 The Contractor is not liable to pay damages (whether in contract, for negligence or otherwise) for making an incorrect assessment, determination or instruction. However, the Subcontractor will be entitled to the amount determined by an expert or the court, with simple interest as referred to in clause 66, from the date the expert or the court decides that the amount should have been paid. 73.6 The Contractor's assessments, determinations or instructions may, subject Page 57 of 69 to this Contract, be reviewed and revised in any Expert Determination or court proceedings which might follow this Issue resolution procedure. 74. 75. 73.7 This Issue resolution procedure does not prevent a party from seeking an urgent declaration or injunction from a court. 73.8 Notwithstanding any other provision in the Subcontract, if an Issue relates to a Claim or a potential Claim then the Contractor is not obliged to proceed with any procedure in clause 73, 74 or 75 for the resolution of the Issue until the Subcontractor has fully particularised the Claim by providing the information required in respect of a Claim under clause 72.4 (that is, information establishing the factual and legal basis of the Claim, detailed quantification and responses by the Subcontractor to the questions set out in paragraphs 1.1 and 1.2 of Schedule 6). Resolution by senior executives 74.1 If a party gives notice of an Issue under clause 73, the senior executives named in Subcontract Information items 7A and 10 must promptly confer to try to resolve the Issue. 74.2 A party is not entitled to refer an Issue to Expert Determination until 14 days after giving notice of an Issue under clause 73. 74.3 A party may only refer an Issue to Expert Determination by giving notice to the other party (specifying the Issue to be decided and copied to that party's senior executive) within the number of days specified in Subcontract Information item 53 or if no such period is specified, then within 21 days of becoming entitled to under clause 74.2. 74.4 An Issue for which notice has not been given within the time limited by and in the form prescribed by clause 74.3 is barred from Expert Determination or any other action or proceedings (including court proceedings). Expert Determination 75.1 If issues have been referred to Expert Determination under the Contract which involve Issues referred to Expert Determination under the Subcontract, and if the Principal requires or permits it: 75.1.1 the Subcontractor is to be added as a party to the Expert Determination under the Contract; 75.1.2 the Expert Determination under the Subcontract is not to proceed; 75.1.3 the Contractor and Subcontractor must bear equally a proportion of the costs and expenses of the Expert Determination under the Contract commensurate with the extent to which the Expert’s work relates to the issues arising under the Subcontract; and 75.2 If required by the Principal or the Contractor, before the procedure for Expert Determination is commenced, or at any subsequent stage, the Subcontractor and the Contractor must place sufficient funds in a trust account or provide other adequate security for the payment of the fees and out of pocket expenses of the Expert for the determination. 75.3 If an Issue is to be referred to Expert Determination under clause 74, and clause 75.1.2 does not apply, the parties must endeavour to agree on the Expert to be engaged. If they cannot agree within 14 days of the receipt of a Page 58 of 69 notice under clause 74.3, the Expert will be nominated (on the application of either party) by the person named in Subcontract Information item 55. That person must not nominate: 75.4 75.3.1 an employee of the Contractor or the Subcontractor; 75.3.2 a person who has been connected with the Subcontract Works or the Subcontract; or 75.3.3 a person who the Contractor and the Subcontractor have not been able to agree on. When the person to be the Expert has been agreed or nominated, the Contractor, on behalf of both parties, must engage the Expert by letter of engagement (copied to the Subcontractor) setting out: 75.4.1 the Issues referred to the Expert for determination; 75.4.2 the Expert's fees; 75.4.3 the procedure for Expert Determination in Schedule 6 (Expert Determination Procedure); and 75.4.4 any other matters which are relevant to the engagement. 75.5 The Contractor and the Subcontractor must share equally the fees and outof-pocket expenses of the Expert for the determination, and bear their own costs. 75.6 If required by either party, before the procedure for Expert Determination is commenced, or at any subsequent stage, each party must place sufficient funds in a trust account or provide other adequate security for the payment of the fees and out of pocket expenses of the Expert for the determination. 75.7 The procedure for Expert Determination is set out in Schedule 6 (Expert Determination Procedure). 75.8 In answer to any Issue referred to the Expert by a party, the other party may raise any defence, set-off or cross-claim. 75.9 If the Expert determines that one party must pay the other an aggregated amount exceeding the amount in Subcontract Information item 56 (calculating the amount without including interest on it, and after allowing for set-offs), or if the Expert's determination involves a finding which does not involve paying a sum of money, or if the Expert fails (without the agreement of both parties) to follow the procedure set out in Schedule 6 or exhibits bias, then either party may commence litigation in respect of the amount referred to above (which amount exceeds the amount in Subcontract Information Item 56) or the finding which does not involve paying a sum of money, as applicable, at any time before the expiry of 42 days after the Expert has issued a determination, but no later . 75.10 Unless a party has a right to commence litigation under clause 75.8: 75.10.1 the parties must treat each determination of the Expert as final and binding and give effect to it; and 75.10.2 if the Expert determines that one party owes the other money, that party must pay the money within 21 days. Page 59 of 69 75.11 The representative of the Contractor for all of the purposes of this clause 75 is the person specified in Subcontract Information item 54. This person (and his/her address) may differ from the person (and his/her address) for the giving of notices to the Contractor, as specified in clause 30.1. 76. Parties to perform the Subcontract During Subcontractor's Claim and Issue resolution procedures under clauses 72 to 75, the parties must continue to perform their obligations under the Subcontract. TERMINATION 77. Termination for Subcontractor's Default or Insolvency 77.1 The Contractor may terminate the Subcontractor's employment under the Subcontract for Subcontractor's Default or Subcontractor's Insolvency by giving notice, as set out in this clause 77. 77.2 In the case of Subcontractor's Default, the Contractor must first give notice to the Subcontractor that it has 4 days after the notice is given to the Subcontractor to remedy the Subcontractor's Default. 77.3 If the Subcontractor fails to give the Contractor a notice containing clear evidence that it has remedied a Subcontractor's Default, or fails to propose steps reasonably acceptable to the Contractor to remedy the Subcontractor's Default, the Contractor may give the Subcontractor a notice terminating its employment under the Contract. 77.4 Nothing in this clause 77 affects or negates the Contractor's common law rights to terminate or for damages. If a right to terminate exists at common law, a notice to terminate at common law may be given without first giving notice to remedy a default. 77.5 In the case of Subcontractor's Insolvency, the Contractor may give the Subcontractor a notice terminating its employment under the Subcontract. 77.6 If the Contractor terminates the Subcontractor's employment under this clause 77, it may at its sole discretion, employ others to complete the Subcontract Works and all the following will then apply: 77.6.1 The Subcontractor must leave the Site as soon as reasonably practicable and remove all Temporary Work it has brought onto the Site, but must leave any Temporary Work required by the Contractor to have the Subcontract Works completed. 77.6.2 The Subcontractor must assign to the Contractor the Subcontractor's rights and benefits in all its contracts concerning the Subcontract Works, warranties and unconditional undertakings, cash security, bank guarantees, insurance bonds, other security of a similar nature or purpose and retention money held by the Subcontractor, with effect from the date of termination of its employment under the Subcontract. 77.6.3 The Subcontractor must consent to a novation to the Contractor or its nominee of all Sub-subcontracts and its other contracts concerning the Subcontract Works, as required by the Contractor Page 60 of 69 and must procure at the time of entering into each Sub-subcontract and other contracts, the consent in writing of all of its Subsubcontractors, Suppliers and Consultants to the novation. The Contractor may at any time make payments and may deduct, withhold or set-off any amounts to be paid under the novated contracts from amounts otherwise payable to the Subcontractor or from any Undertakings given on the Contractor's behalf. 78. 77.6.4 The Subcontractor must do everything and sign all documents necessary to give effect to this clause 77, and it irrevocably appoints the Contractor as its attorney to do this in its name if it fails to do so. 77.6.5 If, on Completion, the cost to the Contractor of completing the Subcontract Works exceeds the amount that would have been paid to the Subcontractor to complete them, taking into account any Prepayments, then the difference will be a debt due by the Subcontractor to the Contractor. 77.6.6 The Contractor may make provisional assessments of the amounts payable to the Contractor under clause 77.6.5 and may demand them under the Undertakings. Termination for Contractor's convenience 78.1 The Contractor may terminate the Subcontract, by giving notice with effect from the date stated in the notice, for its convenience and without the need to give reasons. 78.2 The Subcontractor must comply with any instructions of the Contractor to wind down and stop work. 78.3 The Subcontractor must leave the Site by the date stated in the termination notice and remove all Temporary Work it has brought onto the Site for constructing the Subcontract Works, except for those items identified in the termination notice as to be retained on the Site. 78.4 After termination under clause 78.1, subject to its rights under the Subcontract, including clause 67, the Contractor must pay the Subcontractor: 78.4.1 the Value Completed for all work carried out (as determined under clauses 62 and 63) to the date the termination notice takes effect, after taking into account previous payments and any Prepayments, and any deductions, retentions or set-offs under clauses 63, 64 or 67; 78.4.2 the cost of Materials reasonably ordered by the Subcontractor for the Subcontract Works which it is legally liable to accept, but only if on payment these unfixed Materials become the property of the Contractor, free of any Encumbrance; 78.4.3 the reasonable, direct costs of removal of Temporary Work and other things from the Site incurred by the Subcontractor, but only if the Subcontractor complies with a strict duty to mitigate costs; 78.4.4 an amount of 2% of the unpaid portion (after taking into account Page 61 of 69 the amount payable under clause 78.4.1) of the Subcontract Price; and 78.4.5 79. 80. costs reasonably incurred by the Subcontractor in the expectation of completing the Subcontract Works and not included in any other payment by the Contractor. 78.5 The Contractor must return the Undertakings, cash security or retention money, subject to its rights under the Subcontract. 78.6 The payments referred to in clause 78.4 are full compensation for termination under this clause 78, and the Subcontractor has no Subcontractor's Claim for damages or other entitlement whether under the Subcontract or otherwise. 78.7 The Subcontractor must, wherever possible, include in all Sub-subcontracts and other contracts an equivalent provision to this clause 78. Termination for Contractor's default 79.1 If the Contractor fails to pay the Subcontractor any amount in accordance with the Subcontract which is not in dispute, or commits any fundamental breach of the Subcontract, then the Subcontractor may give notice requiring the Contractor to remedy the default within 21 days after receiving the notice. 79.2 If the Contractor fails to remedy the default, or fails to propose steps reasonably acceptable to the Subcontractor to do so, the Subcontractor may issue a notice terminating the Subcontract and clauses 78.3 to 78.6 will then apply and the Contractor must pay the Subcontractor the applicable amounts referred to in clause 78.4 as its sole remedy and in full compensation for the Contractor's breach. 79.3 In the case of Contractor's Insolvency, the Subcontractor may terminate the Subcontract by giving notice to the Contractor, and clauses 78.4 to 78.6 apply. 79.4 If the Subcontractor terminates the Subcontract, it must leave the Site as soon as reasonably practicable and remove all Temporary Work it has brought onto the Site for constructing the Subcontract Works. 79.5 The Subcontractor has no other right to terminate the Subcontract, under the common law or otherwise. Termination of Contract 80.1 If the Contract is terminated, then the Subcontract is deemed to have been terminated, with effect on the date of termination of the Contract. 80.2 If the Contractor's employment under the Contract is terminated, then the Subcontractor's employment under the Subcontract is deemed to have been terminated, with effect on the date of termination of the Contractor's employment under the Contract. 80.3 In either case, the Contractor must promptly give the Subcontractor a copy of the relevant notice of termination given under the Contract. 80.4 If this action is taken for reason of Contractor's Default or Contractor's Insolvency under the Contract, then: Page 62 of 69 81. 80.4.1 the Subcontractor must accept a novation of this Subcontract to the Principal, if required by the Principal; and 80.4.2 clauses 78.4 to 78.6 apply. Termination notices Notices under clauses 77, 78 and 79 must be in writing and be delivered by hand, registered post or equivalent, or facsimile. MEANINGS 82. 83. Interpretation 82.1 Words in the singular must be interpreted to include the plural, and vice versa. 82.2 No legal interpretation applies to the disadvantage of any party on the basis that the party provided the Contract Documents, or any part of them. 82.3 Notes are provided to guide the parties and do not form part of the Subcontract. 82.4 Attachments 1, 2 and 3 do not form part of the Subcontract. Definitions Some words and phrases have special meanings in the Contract. In some cases, the defined meaning is different from the meaning that the word or phrase might have in ordinary usage, or it might include conditions that don't normally apply. In order to understand the Contract, you need to take these special meanings into account. All defined words and phrases have initial capitals (except for 'day' and 'end users') and are in italics in this Subcontract unless they are one of the following 12 basic terms, which appear too often for italics to be used: consultant Contract Contractor Date of Subcontract day Principal Site Subcontract Subcontractor Subcontract Works Sub-subcontractor Supplier Wherever the following words and phrases are used in this Subcontract with initial capitals (except for 'day' and 'end users'), they have the special meanings set out below them in this clause 83 unless the context requires otherwise. Meanings of words and phrases Acceleration Notice A written instruction under clause 56.1 by the Contractor to the Subcontractor to accelerate progress of the Subcontract Works, titled "Acceleration Notice ". Page 63 of 69 Actual Completion Date The date on which Completion of the Subcontract Works or of a Subcontract Milestone (as applicable) is achieved by the Subcontractor. Business Day Any day other than a Saturday, Sunday, public holiday in South Australia, or 27, 28, 29, 30 or 31 December. Certificates of Compliance Certificates in the form of Schedule 4, as referred to in clause 63.5.2. Claimed Amount The amount claimed by the Subcontractor in a Payment Claim. Completion The state of the Subcontract Works or a Subcontract Milestone (as applicable) being complete, except for Defects not known. This includes, without limitation: 1. the supply to the Contractor of all Schedule 1 Subcontractor's Warranties, operating and maintenance manuals, licences, access codes, as-built drawings or work-as-executed drawings; 2. certificates, authorisations, approvals and consents from statutory authorities and service providers; 3. those certificates required for the occupation, use and maintenance of the Subcontract Works; and 4. all other documents, Testing, training and other requirements specified in the Subcontract. Completion Amount An amount stated in Subcontract Information item 45 and included in the Subcontract Price, which under clause 64 may be claimed by the Subcontractor after the Actual Completion Date of the whole of the Subcontract Works. Completion Undertaking The Undertaking required under clause 37.1, for the percentage of the Subcontract Price (at the Date of Subcontract) specified in Subcontract Information item 33. Conformance Records Records which show conformance by the Subcontractor with particular requirements of the Subcontract, as provided in the Contract and as referred to in clause 63. Consultant A consultant engaged by the Subcontractor to design parts of the Subcontract Works or to provide other professional services. It includes a consultant whose Subcontract with the Contractor is novated to one with the Subcontractor. Contract The agreement between the Contractor and the Principal, as specified in Subcontract Information item 3B. Contractor The party named as such in Subcontract Information item 4, and including its Page 64 of 69 successors and permitted assigns. Contractor's Authorised Person The person appointed to act for the Contractor in terms of clause 2, as named in Subcontract Information item 5. Contractor's Documents The design and other documents prepared by the Contractor for the Subcontract and provided to the Subcontractor at the Date of Subcontract and included in the Subcontract Documents, and any modified or further such documents later provided by the Contractor to the Subcontractor for the Subcontract. Contractual Completion Date The date (or the last day of the period) specified in Subcontract Information item 13 on, or by which, the Subcontractor must achieve Completion of the Subcontract Works or of a Subcontract Milestone (as applicable), as may be adjusted under clauses 41, 52 and 54. Data Drawings, sketches, specifications, digital records and computer software and all other data and information relating to the Subcontract. Date of Subcontract The date of the Letter of Award or if no Letter of Award is issued by the Contractor to the Subcontractor, the date the Subcontract Agreement is signed by the Contractor after the Subcontractor has signed it. Day A calendar day, including all Business Days and non-Business Days. Defect Includes an error, omission, shrinkage, blemish in appearance or other fault in the Works or which affects the Works, which results from a failure of the Subcontractor to comply with the Subcontract. Defect Notice A notice issued by the Contractor under clause 50.2 or 71.1 instructing that specified Defects be made good within a given period. Design Design of the Subcontract Works to be carried out by the Subcontractor, including the completion of any of the Contractor's design work which is described in the Contractor's Documents, to the extent specified in Subcontract Information item 37; Designed, the Design, and other derivatives of Design have a corresponding meaning. Encumbrance Any mortgage, charge, lien, title retention, trust, power or other encumbrance. End users Persons to be involved in using or occupying any part of the Subcontract Works, as referred to in clauses 6.2 and 45.2. Excepted Risks Any of the following: Page 65 of 69 1. any negligent act or omission of the Contractor, the Contractor's Authorised Person or the employees, consultants or agents of the Contractor; 2. any risk specifically excepted in the Subcontract; 3. war, invasion, act of foreign enemies, hostilities, (whether war be declared or not), act of terrorism, civil war, rebellion, revolution Contractor is maintaining complete records to account for the cash. The records are available to the relevant Subcontractors and the Principal on request., insurrection or military or usurped power, martial law or confiscation by order of any Government or public authority; or 4. ionising radiations or contamination by radioactivity from any nuclear fuel or from any nuclear waste from the combustion of nuclear fuel not caused by the Subcontractor or the Subcontractor's employees or agents. Expert A person engaged to determine Issues under clause 75. Expert Determination The process of determination of an Issue by an Expert, under clause 75 and the procedure in Schedule 6 (Expert Determination Procedure). Fault Ambiguity, inconsistency, discrepancy, omission, error or other fault. Final Payment Claim A Payment Claim given by the Subcontractor to the Contractor under clause 65.1. Final Subcontract Payment Schedule A Payment Schedule given by the Contractor to the Subcontractor under clause 65.2. Further Site Information Site information obtained after the Date of Subcontract by the Subcontractor. Intellectual Property Rights Includes copyright, patent right, registered design, trade mark or name and other protected rights. Issue Any issue, dispute or difference raised by either party under clause 73. Letter of Award A letter from the Contractor to the Subcontractor awarding the Subcontract to the Subcontractor as referred to in clause 7. Materials Includes materials, plant, equipment and other goods. Milestone Payment A payment to the Subcontractor on Completion of a Subcontract Milestone. Payment Claim A Subcontractor's Claim for payment made by the Subcontractor to the Contractor under clauses 62 or 65. Post-Completion Undertaking The Undertaking required under clause 37.1, for the percentage of the Subcontract Page 66 of 69 Price (at the Date of Subcontract) specified in Subcontract Information item 34. Prepayment The amount to be advanced to the Subcontractor in accordance with clause 61 and Subcontract Information item 44. Principal The entity named as such in Subcontract Information item 3C. Progress Payment A payment by the Contractor in response to a Payment Claim, on account of the Subcontract Price. Provisional Sum A sum included in the Subcontract Price and identified as a provisional, monetary, prime cost, contingency or other such sum or allowance for the work specified in the Subcontract against that sum or allowance. Provisional Quantity The quantity of an item of work which is specified in the Subcontract, but the quantity of which or whether that item of work will actually be required is not known definitively at the Date of Subcontract. Reference Subcontract Documents The documents expressly referred to as such in Subcontract Information item 17 and forming part of the Contract. Schedule of Rates Any schedule in the Subcontract stated to be a Schedule of Rates, and which shows rates payable for carrying out items of work described in the schedule. Scheduled Amount The amount of payment (if any) stated in a Payment Schedule, that the Contractor proposes to make in relation to a Payment Claim as referred to in clause 63.2.2. Scheduled Progress The rate of progress to be achieved by the Subcontractor in Designing and constructing the Subcontract Works, such that the Subcontractor is proceeding with due expedition and without undue delay (other than a delay for which the Contractual Completion Date is adjusted under the Subcontract), so that it will (or is likely to) complete the Subcontract Works and all Subcontract Milestones by theit respective Contractual Completion Dates. Site The lands and other places to be made available by the Contractor to the Subcontractor for the purpose of executing the Subcontract Works, and including any existing buildings, services or other improvements, as specified in Subcontract Information item 2. Site Conditions Any physical conditions of the Site (including sub-surface conditions, but excluding weather conditions or physical conditions which are a consequence of weather conditions) encountered in the execution of the Subcontract Works. Statutory Requirements Page 67 of 69 The laws relating to the Subcontract Works, the Site, or the environment or the lawful requirements of any authority or provider of services having jurisdiction over the Subcontract Works, the Site, or anyone or anything connected with the Subcontract Works, the Site or otherwise relating to the Subcontract. Subcontract An agreement constituted by the Subcontract Documents. Subcontract Agreement An agreement in the form annexed to the Subcontract. Subcontract Documents All the documents listed or referred to in clause 7.1. Subcontract Information The document described as such in the Subcontract Documents, which sets out information for the purposes of the Subcontract. Subcontract Milestone A part of the Subcontract Works specified as such in Subcontract Information item 13. Subcontract Payment Schedule A payment schedule containing the Contractor's assessment of a Payment Claim and stating the amount the Contractor proposes to pay as the Scheduled Amount, as referred to in clause 63. Subcontract Price The amount stated as such in Subcontract Information item 43, subject to adjustment in accordance with the Subcontract. Subcontract Program The program described in clause 25. Subcontract Works The works to be Designed and constructed by the Subcontractor, as referred to in clause 10, including all works and items of the type referred to in clause 10.1 and Variations, but excluding Temporary Work; it applies to the Subcontract Works as a whole and also to any part of the Subcontract Works unless stated otherwise or the context requires otherwise. Subcontractor The entity named as that party in Subcontract Information item 8. It includes its successors and permitted assigns Subcontractor’s Authorised Person The person appointed to act for the Subcontractor under clause 2, including as named in Subcontract Information item 9. Subcontractor's Claim A claimed entitlement of the Subcontractor under or arising out of or connected with the Subcontract, in tort, in equity, under any statute, or otherwise. It includes a claimed entitlement to an extension of time or for breach of Subcontract by the Contractor. Subcontractor’s Default Page 68 of 69 A substantial breach of the Subcontract by the Subcontractor, including, without limitation, any of the following: 1. abandoning the carrying out of the Subcontract Works; 2. suspending progress of the carrying out of the Subcontract Works in whole or part without the written agreement of the Contractor, except for suspension under clause 58; 3. significantly failing to achieve Scheduled Progress; 4. failing to comply with an instruction in writing or confirmed in writing by the Contractor; 5. failing to carry out the Subcontract Works with professional skill, care and competence; 6. failing to maintain any registration or licence required by law to carry on activities required under the Subcontract; 7. failing to provide security as required under clause 37 of the Subcontract; or 8. failing to effect and maintain insurance policies as required under the Subcontract. Subcontractor's Documents Both: 1. drawings, specifications, calculations and other documents and information, meeting the requirements of clause 43, which the Subcontractor must produce to Design and construct the Subcontract Works in accordance with the Subcontract; and 2. documents which become Subcontractor's Documents under the Subcontract, including Contractor's Documents checked, accepted and adopted under clause 44. Subcontractor's Insolvency Any of the following applying to the Subcontractor: 1. insolvency; 2. the Subcontractor indicates it does not have the resources to perform the Subcontract; 3. an application for winding up is made which is not stayed within 14 days; 4. a winding-up order is made; 5. a controller, administrator, receiver, receiver and manager, provisional liquidator, or liquidator is appointed; 6. a mortgagee enters into possession of any property of the Subcontractor; 7. notice is given of a meeting of creditors for the purposes of a deed of arrangement; or 10. any actions having a similar effect are taken. Subcontractor's Margin An amount or proportion added for profit and additional overhead costs (including administration, supervision, establishment and attendance costs) incurred solely as a result of a Variation, but not including any overhead costs relating to delay, disruption or interference caused by the Variation. Sub-subcontract Page 69 of 69 An agreement between the Subcontractor and its Sub-subcontractor or a Supplier. Sub-subcontractor An entity engaged by the Subcontractor to carry out part of the Subcontract Works Works or Temporary Work, or both. Supplier An entity engaged by the Subcontractor to supply part of the Subcontract Works or Temporary Work, or both. Temporary Work Temporary structures, amenities, physical services and other work, including Materials, plant and equipment used in or in relation to the carrying out of the Subcontract Works but not forming part of the Subcontract Works. Test Examine, inspect, measure, prove and trial, including opening up of any part covered up, if necessary; Testing and other derivatives of Test have a corresponding meaning. Undertaking An unconditional undertaking to pay on demand, in the relevant form of Schedule 2 (Undertaking), provided as security by the Subcontractor. Unresolved Subcontractor's Claim A Subcontractor's Claim rejected or not agreed under clause 72.7. Value Completed The value of work (including Design, if applicable) carried out by the Subcontractor and incorporated into the Subcontract Works, as referred to in clause 62. Valuer The entity engaged to determine time and cost matters under the Contract. Variation Any change to the Subcontract Works including additions, increases, omissions and reductions to and from the Subcontract Works, but not including such changes or otherwise in respect of the development by the Subcontractor of Design (including without limitation development of shop drawings and other Subcontractor's Documents) in accordance with the requirements of the Subcontract, and not including omissions of the type referred to in clause 10.1.3. Page 1 of 13 SUBCONTRACT AGREEMENT Refer to clause 7 of the Subcontract Definition Subcontract title: Subcontract number: Dated: The Contractor: The Subcontractor: This Subcontract »………………………………………. »………………………………………. »………………………………………. is made between »………………………………………. ABN»…………………………………. and »………………………………………. ABN»…………………………………. Agreement The parties agree: 1. The Subcontractor must: 1.1 construct the Subcontract Works to Completion in accordance with the Subcontract; 1.2 perform the Design obligations specified in the Contract; and 1.3 perform and observe all its other obligations under the Subcontract. 2 The Contractor must: 2.1 pay the Subcontractor the Subcontract Price (on the basis of a lump sum, schedule of rates or a combination of these as specified in the Subcontract) for its performance, in accordance with and subject to the Subcontract; and 2.2 perform and observe all its other obligations under the Subcontract. 3 The Subcontract is defined in the attached Subcontract. 4 The attached Subcontract Information forms part of the Subcontract. 5 Words in this Subcontract Agreement have the meanings given in the Subcontract. Executed as an agreement on the date stated above Executed for and on behalf of the subcontractor by its duly authorised officers: Signature of Director/Secretary »………………………………………. Name of Director/Secretary »………………………………………. Signature of Director »………………………………………. Page 2 of 13 Name of Director »………………………………………. Executed for and on behalf of the Contractor by its duly authorised officers Signature of Director/Secretary »………………………………………. Name of Director/Secretary »………………………………………. Signature of Director »………………………………………. Name of Director »………………………………………. SUBCONTRACT INFORMATION The Subcontract Information is part of the Subcontract. Words and phrases are defined in clause 83. Project, Subcontract & Contract Item 1 Project and Contract Name The Project and Contract name is: The Contract number is: 2 » » Site Mentioned in clause 40 & 83 The Site is: 3 » Description of the Subcontract Works A - The Subcontract Works Mentioned in clauses 10 & 83 Description of the Subcontract Works: » B - The Contract The Contract is: »the agreement dated………. between the Principal and the Contractor. Title: Contract No. C - The Principal The Principal is: Contractor's details » Page 3 of 13 4 Contractor The Contractor is: 5 » ABN » Contractor's Authorised Person Mentioned in clause 2 The Contractor's Authorised Person is: 6 » Notices to the Contractor Mentioned in clause 30 Notices must go to the Contractor's Authorised Person listed above, at the address or number shown here. »………………………………….. »………………………………….. »………………………………….. »………………………………….. Postal address: »………………………………….. (for delivery by registered post registered post) »………………………………….. »………………………………….. »………………………………….. Facsimile number: »………………………………….. e-mail address »………………………………….. Office address: (for delivery by hand) 7 Senior executive A - Contractor's senior executive Mentioned in clauses 73 & 74 The Contractor's senior executive is: »………………………………….. B - Documents copied to the Contractor’s senior executive Mentioned in clauses 73 When documents must be copied to the Contractor's senior executive the address is as follows: »………………………………….. »………………………………….. »………………………………….. »………………………………….. Postal address: »………………………………….. (for delivery by registered post registered post) »………………………………….. »………………………………….. »………………………………….. Facsimile number: »………………………………….. e-mail address »………………………………….. Office address: (for delivery by hand) Subcontractor's details Page 4 of 13 8 Subcontractor The following information in the Subcontract Information Items 8 to 11 is to be provided by the tenderer in the Tender Schedule (Schedule of Subcontract Information). Details must then be inserted by the Contractor at the Subcontract award. The Subcontractor is: 9 »…………………………………. »…………………………………. ABN»……………………………. Subcontractor's Authorised Person Mentioned in clauses 2 The Subcontractor’s Authorised Person is: »…………………………………. 10 Senior executive Mentioned in clauses 74 The Subcontractor’s senior executive is: 11 »…………………………………. Notices to Subcontractor Mentioned in clauses 30 Notices must go to the personnel listed above, at the address or number shown here. »………………………………….. »………………………………….. »………………………………….. »………………………………….. Postal address: »………………………………….. (for delivery by registered post registered post) »………………………………….. »………………………………….. »………………………………….. Facsimile number: »………………………………….. e-mail address »………………………………….. Office address: (for delivery by hand) Dates and times 12 Date of Subcontract Mentioned in clause 83 Date to be inserted by the Contractor at Subcontract Award. This is the date the Contractor signs the Subcontract Agreement after the Subcontractor has signed, or the date of the Contractor's Letter of Award to the Contractor (as applicable). Date of Contract is: » (“The date of the Letter of Award” applies if not filled in). 13 Contractual Completion Date and times Mentioned in clause 83 The time periods for Completion include the 14 days or other time periods referred to in Clause 38. Whole of the Subcontract Works Time period for possession of the Site is: » 14 days from Date of Subcontract Page 5 of 13 Time period for Completion is: » 50 calendar weeks from Date of Subcontract Whole of the Subcontract Works and Subcontract Milestones Insert number of weeks for the milestones (eg '52 weeks). Add time periods for possession of the whole of the site or parts of the site if Milestones are required, describe them and add times to suit each. Ensure the whole of the Subcontract Works is covered by the Subcontract Milestones. Subcontract Milestone 1 Description of Subcontract Milestone: Time period for possession of the Site is: Time period for Completion is: » » » weeks from » » » » weeks from » » » » weeks from » Subcontract Milestone 2 Description of Subcontract Milestone: Time period for possession of the Site is: Time period for Completion is: Subcontract Milestone 3 Description of Subcontract Milestone: Time period for possession of the Site is: Time period for Completion is: When additional Subcontract Milestones are required copy and paste the format above to ensure the whole of the works is covered by the Subcontract Milestones. South Australian Government requirements 14 Codes Mentioned in clause 13 The SA Government codes that apply are: 15 Code of Practice for the South Australian Construction Industry Principal contractor Not Used 16 SA Government construction guidelines requirements A - WHS Management Plan Mentioned in clause 15.3 Is the Subcontractor required to submit a Project WHS Management Plan? (Yes/No) » (“Yes” applies if not filled in). Page 6 of 13 B - Environmental Management Plan Mentioned in clause 18.2 Is the Subcontractor required to submit an Environmental Management Plan? (Yes/No) 16A » (“Yes” applies if not filled in). Workforce Participation and Skills Development Mentioned in clause 18A Does clause 18A apply? (Yes/No) » Reference Subcontract Documents 17 Reference Subcontract Documents Mentioned in clause 7.1.5 The Reference Subcontract Documents are: Subcontract Agreement / Letter of Award ; and» (Letter of Award applies if not filled in); Contractor's Documents 18 Copies of Contractor's Documents Mentioned in clause 7.4 The number of copies of the Contractor’s Documents to be provided to the Subcontractor is » (“5 printed copies” applies if not filled in) Subcontractor's Documents 19 Copies of Subcontractor's Documents Mentioned in clause 45.1 5 The number of copies of the Subcontractor’s Documents to be provided to the Contractor is Sub-subcontract work 20 Use of GC21 Subcontract » (“5 printed copies” applies if not filled in) Page 7 of 13 Not Used 21 Use of equivalent clauses Mentioned in clauses 31.3 & 31.4 Sub-subcontract value requiring use of equivalent clauses is: 22 » (must be the same as the value in the Contract Information item 21 of the Contract) Payment for minor Sub-subcontract Mentioned in clauses 31.3 Maximum period before payment for minor Sub-subcontract: 23 » (must be the same as the value in the Contract Information item 22 of the Contract) Preferred Subcontractors Not used 24 Pre qualified Contractors Not used 25 Subcontractor's warranty Mentioned in clause 33.1 Trades or areas of work requiring a Subcontractor's warranty are: » (“Not required” applies if not filled in) Insurance by the Contractor (or Principal) Mentioned in clause 36.1 & 36 2 26 Works Insurance Minimum cover: Insurer: Policy Number: Period of cover: 27 Public liability Minimum cover: Insurer: Policy number: Period of cover: 28 » » » Until issue of Final Subcontract Payment Schedule. » » » Until issue of Final Subcontract Payment Schedule. Professional indemnity Is a professional indemnity policy to be held » by the Subcontractor? (“Yes” applies if not filled in). Page 8 of 13 Minimum cover: Insurer: Policy number: Period of cover: 29 » » » » Asbestos liability Not used 30 Marine liability Minimum cover: Insurer: Policy number: Period of cover: » » » The whole of the period of use of waterborne craft of 8 or more metres in length on work for or in connection with the Contract. Insurance by the Subcontractor Mentioned in clause 36.3 31 Workers compensation Details to be provided by preferred tenderer and inserted by the Contractor. Minimum cover: Insurer: Policy number: Period of cover: 32A As required by law. » » Until issue of Final Subcontract Payment Schedule. Asbestos liability Details to be provided by preferred tenderer and inserted by the Contractor. Minimum cover: Insurer: Policy number: Period of cover: 32 As required by law » » » Personal accident Details to be provided by preferred tenderer and inserted by the Contractor. Minimum cover: Insurer: Policy number: Period of cover: Security Death and permanent disability $» Temporary disablement $» » » » Page 9 of 13 33 Completion Undertaking Mentioned in clause 37.1 Percentage of the Subcontract Price at the Date of Subcontract is: 34 » Post-Completion Undertaking Mentioned in clause 37.1 Percentage of the Subcontract Price at the Date of Subcontract is: 35 » Return of Post-Completion Undertaking Mentioned in clause 37.2.2 Period for return of Post-Completion Undertaking is: » months (12 months if not filled in). Site information 36 Site information Mentioned in clause 40 Information contained in the documents listed in Items 36A and 36B does not form part of the Contract: A - Documents not guaranteed for completeness Documents not guaranteed for completeness are: » B - Documents not guaranteed for accuracy, quality or completeness Documents not guaranteed for accuracy, quality or completeness are: » Scope of activities 37 Scope of Design activities A - Extent of Design by the Subcontractor Mentioned in clauses 1.1.1 & 43.1 Extent of Design by the Subcontractor is: B - Building Code of Australia » Page 10 of 13 Mentioned in clauses 43.1 & 48 Is the Building Code of Australia to apply to the Design in the Subcontractor's Documents (clause 43.4) and to the Materials used in the construction of the Subcontract Works (clause 48)? (Yes/No) 38 » ("Yes" applies if not filled in). Responsibility for Design Mentioned in clause 44 Is the Subcontractor to assume responsibility for design carried out by the Contractor and does clause 44 apply? (Yes/No) 39 » ("No" applies if not filled in). Working days and hours of work Mentioned in clause 26 Working days and hours of work: » ("Comply with Statutory Requirements" applies if not filled in). 40 Rise or fall adjustments Mentioned in clause 59.1 Are rise or fall adjustments applicable to the Subcontract? (Yes/No) 41 » ("No" applies if not filled in). Site Conditions Mentioned in clause 41.8 Is the Subcontractor to bear the full risk, including cost and time implications, of encountering and dealing with materially adverse Site Conditions? (Yes/No) » ("No" applies if not filled in). Innovation 42 Innovation Mentioned in clause 46.8 Do the parties agree to share the savings in the cost to the Subcontractor of the Subcontract Works resulting from changes accepted by the Contractor and Principal? (Yes/No) » ("No" applies if not filled in). If "No", the Subcontractor keeps the direct saving in the cost to the Subcontractor of the Subcontract Works, as provided in clause 46.5. Percentage of saving to be allocated to the Subcontractor is: » (100% applies if not filled in). Page 11 of 13 Percentage of saving to be allocated to the Contractor is: » (0% applies if not filled in). Payments 43 Subcontract Price at the Date of Subcontract Mentioned in clause 59 The Subcontract Price and basis of payment must be inserted by the Contractor at the Subcontract Award. Subcontract Price at the Date of Subcontract is: »$ Basis of payment: Basis of payment is: » (Lump sum / Schedule of Rates / Schedule of Rates and lump sums) 44 Amount of Prepayment Mentioned in clause 61.1.1 Amount of Prepayment is: 45 »$ Completion Amount Mentioned in clauses 62.4.2 & 64 The Completion Amount is: »$ (must be no more than the value in the Contract Information item 45 of the Contract) 46 Provisional Sums Mentioned in clause 59 Option 1 applies when Provisional Sums are to be used. If Option 1 is used delete Option 2 Provisional Sums items referred to in clause 59: Option 2 Provisional Sums items referred to in clause 59: 47 »A list is provided in clause » Not applicable. Provisional Sum margin Mentioned in clause 59.6.2 The Provisional Sum margin percentage is: » (10% if not filled in). 48 Variations A - Subcontractor's Margin on Variations Mentioned in clauses 52 & 83 The percentage for Subcontractor's Margin on Variations is: » (10% if not filled in). B - Subcontractor's hourly labour rate Mentioned in clause 52.5.4 Page 12 of 13 The tendered Subcontractor's hourly labour rate or rates must be inserted by the Contractor at the Subcontract Award. The Subcontractor's hourly labour rate(s): 49 » Payment date and method A - Date for Payment Claims Date in month for making Payment Claims is: » (3 Business Days before the date for a Payment Claim under the Contract applies if not filled in). B - Type of payment Mentioned in clause 62.2 The method of payment will be by: (Progress Payment / Milestone Payment) » (Monthly Progress Payments apply if not filled in). C - Time for payment Mentioned in clause 63.5 Time that a payment becomes payable Subject to clause 63.5 is: 50 » (10 Business Days applies if not filled in). Interest on late payments Mentioned in clause 66 Rate of interest per annum is: » (must be the same as the value in the Contract Information item 50 of the Contract) Delay costs 51 Delay costs Mentioned in clauses 55.1 to 55.3 A - Delay costs Rate per day is: »$ B - Delay to Completion and liquidated damages Mentioned in clauses 55.4 to 55.9 Clause 55.4 applies to this Subcontract? (Yes/No) » ("No" applies if not filled in). If "No" applies, the Contractor reserves its rights to claim general damages if the Subcontractor fails to achieve Completion by the Contractual Completion Date). *The rates for each are separate and distinct from each other. Engagement of Valuer Page 13 of 13 52 Engagement of Valuer The Valuer is not engaged under the Subcontract. Expert Determination 53 Time to refer Issue to Expert Determination Mentioned in clause 74.3 Maximum number of days for either party to refer an Issue to Expert Determination is: 54 Within 21 days of becoming entitled to refer an Issue to Expert Determination under clause 74.2. Expert Determination representative Mentioned in clause 75 The name of the representative of the Contractor for all of the purposes in clause 75, to whom all documents must be copied under Schedule 6 (Expert Determination Procedure) is: » Insert the office street and postal addresses (including postcodes), Facsimile Number and e-Mail address for the person in Item 54 above. »………………………………….. »………………………………….. »………………………………….. »………………………………….. Postal address: »………………………………….. (for delivery by registered post registered post) »………………………………….. »………………………………….. »………………………………….. Facsimile number: »………………………………….. e-mail address »………………………………….. Office address: (for delivery by hand) 55 Person to nominate Expert Person to nominate Expert is: Telephone Facsimile 56 » » » Threshold amount for litigation Mentioned in clause 75.86 Threshold amount for litigation following a determination is: » Page 1 of 1 SCHEDULES Schedule 1 Subcontractor's Warranty Schedule 2A Undertaking to the principal (on behalf of the Subcontractor or Consultant) Schedule 2B Undertaking to the Contractor (on behalf of Subcontractor, Supplier or Consultant) Schedule 3 Payment Claim Worksheet Schedule 4 Certificate of Compliance Schedule 5 Agreement with Valuer (Not used) Schedule 6 Expert Determination Procedure Schedule 7 Statutory Declaration Schedule 8 Cost Adjustment Formula (Not used) Schedule 9 Principles for Valuing Daywork Variation (Not used) Page 1 of 4 SCHEDULE 1 SUBCONTRACTOR'S WARRANTY Refer to clause 33.1 of the Subcontract. DEFINITIONS »………………………………………. between Subcontractor or Supplier: »………………………………………. »………………………………………. ABN »………………………………… and The Principal: »………………………………………. concerning The Contract: The contract between the Principal and the Contractor Contract title: »………………………………………. Contract number: »………………………………………. Works: The works to be Designed and constructed by the Contractor, as described in the Contract. The Contractor: »………………………………………. ABN»………………………………..… »………………………………………. Subcontract Work or Products: »………………………………………. Warranty Period: » ….. years from the Actual Completion Date of the whole of the Works. Deed dated: Other words and phrases in this Deed have the meanings given in the GC21 Subcontract. In this Deed, the term Subcontractor includes Supplier. The terms Subcontractor, Contractor and Principal include their successors and permitted assigns. TERMS OF DEED 1. Warranty 1.1 The Subcontractor warrants that all work performed and all Materials supplied by the Subcontractor as part of the Subcontract Work or Products will: 1.2 1.1.1 comply in all respects with the requirements of the Contract; 1.1.2 comply with the applicable industry standards, including (without limitation) the Building Code of Australia and any applicable Australian Standards, to the extent that the quality of Materials or standard of workmanship is not specified in the Contract; and 1.1.3 be fit for the purposes for which they are required. The Subcontractor warrants that it will use reasonable skill and care in performing all work associated with the Subcontract Work or Products. Page 2 of 4 2 Replacement or making good 2.1 The Subcontractor promises to replace or make good, to the reasonable satisfaction of the Principal, any of the Subcontract Work or Products which, within the Warranty Period, are found to: 2.1.1 be of a lower standard or quality than referred to in clause 1 of this Deed; or 2.1.2 have deteriorated to such an extent that they are no longer fit for the purposes for which they were required. 2.2 Nothing in this clause 2 affects the Subcontractor's liability until any limitation period under statute expires. 2.3 The liability of the Subcontractor under this clause is reduced to the extent that deterioration is caused by: 2.3.1 mishandling, damage before installation, or incorrect installation, in each case caused by others; 2.3.2 normal wear and tear; 2.3.3 incorrect operational procedures or maintenance, in each case not attributable to the Subcontractor; or 2.3.4 any other cause beyond the control of the Subcontractor. 3 Costs 3.1 The Subcontractor promises to undertake and meet the reasonable cost of any work necessary: 3.1.1 to carry out any part of the Works to enable the requirements of clause 2 of this Deed to be carried out; or 3.1.2 restore or make good the Works after carrying out those requirements, whichever the Principal requires. 4 Indemnity 4.1 The Subcontractor indemnifies the Principal against Claims, actions and loss or damage arising out of breach by the Subcontractor of clauses 1 or 2 of this Deed. 5 Notice of Defects 5.1 The Principal may notify the Subcontractor in writing if it considers there has been any breach of any provision of this Deed. 6 Time to remedy 6.1 The Subcontractor must do everything to remedy the breaches notified to it under clause 5 of this Deed within a reasonable time after the Principal's notice. Page 3 of 4 7 Failure to remedy 7.1 If the Subcontractor fails to carry out and complete the work specified in the Principal's notice under clause 5 of this Deed within a period determined by the Principal to be reasonable in the circumstances, the Principal may give written notice to the Subcontractor that the Principal intends to have that work carried out by others. This notice must allow a reasonable period for the Subcontractor to respond. 7.2 If the Subcontractor fails to complete the work by the date specified in clause 7.1, or another date agreed by the parties, the Principal may have the work carried out by others, and the Subcontractor indemnifies the Principal for the reasonable costs and expenses of doing so. 8 Urgent action by Principal 8.1 The Principal may take any urgent action necessary to protect the Works, other property or people as a result of a breach of clause 1 of this Deed. 8.2 The Subcontractor agrees that the Principal taking such action does not affect any obligation of the Subcontractor under this Deed. 8.3 The Subcontractor indemnifies the Principal for the reasonable costs and expenses paid or payable in taking that action. 9 Assignment 9.1 The Principal may assign the benefit of this Deed to the owner or operating authority of the Works and must give notice of that assignment to the Subcontractor. 10 Operation of Deed This Deed comes into effect when executed by the Subcontractor, and is effective whether or not executed by the Principal. Executed as a deed The common seal of the Subcontractor was affixed in accordance with its Articles of Association in the presence of: Signature of Director/Secretary »………………………………………. Name of Director/Secretary »………………………………………. Signature of Director »………………………………………. Name of Director »………………………………………. or (if the Subcontractor is not a corporation) Signed, sealed and delivered on behalf of the Subcontractor by: Signature of Authorised Person »………………………………………. Name of Authorised Person »………………………………………. Page 4 of 4 and witnessed by: Signature of witness »………………………………………. Name of witness (in full) »………………………………………. Signed, sealed and delivered on behalf of the Principal by: Signature of Authorised Person »………………………………………. Name of Authorised Person »………………………………………. and witnessed by: Signature of witness: »………………………………………. Name: »………………………………………. Place: »………………………………………. Page 1 of 2 SCHEDULE 2 (A) UNDERTAKING TO THE PRINCIPAL Refer to clause 61 of the Subcontract. On behalf of the Subcontractor or Consultant Name of Financial Institution: The Principal: The Contractor: The Subontractor: Security Amount The Contract: Contract Title: Contract Number: »………………………………………. »………………………………………. »………………………………………. ABN»…………………………………. »………………………………………. ABN»…………………………………. $»……………………………………… The contract between the Principal and the Contractor »………………………………………. »………………………………………. Other words and phrases in this Undertaking have the meanings given in the GC21 Subcontract. Undertaking 1. At the request of the Subcontractor or Consultant (as applicable) and the Financial Institution, and in consideration of the Principal accepting this undertaking from the Financial Institution in connection with the Contract and the agreement between the Contractor and the Subcontractor or Consultant (as applicable), the Financial Institution unconditionally undertakes to pay on demand any amount or amounts demanded by the Principal to the maximum aggregate sum of the Security Amount. 2. The Financial Institution unconditionally agrees that, if notified in writing by the Principal (or someone authorised by the Principal) that it requires all or some of the Security Amount, the Financial Institution will pay the Principal at once, without reference to the Subcontractor or Consultant (as applicable) and despite any notice from the Subcontractor or Consultant (as applicable) not to pay. 3. The Principal must not assign this Undertaking without the prior written agreement of the Financial Institution, which must not be unreasonably withheld. 4. This undertaking continues until one of the following occurs: 5 4.1 the Principal notifies the Financial Institution in writing that the Security Amount is no longer required; or 4.2 this undertaking is returned to the Financial Institution; or 4.3 the Financial Institution pays the Principal the whole of the Security Amount, or as much as the Principal may require overall. At any time, without being required to, the Financial Institution may pay the Page 2 of 2 Principal the Security Amount less any amounts previously paid under this undertaking (or a lesser sum specified by the Principal) and the liability of the Financial Institution will then immediately end. Dated »………………………………………. »………………………………………. Execution by the Financial Institution: at Page 1 of 2 SCHEDULE 2 (B) UNDERTAKING TO THE CONTRACTOR Refer to clause 37 of the Subcontract. On behalf of the Subcontractor, Supplier or Consultant Name of Financial Institution: The Contractor: Subcontractor, Supplier or Consultant: Security Amount »………………………………………. »………………………………………. ABN»…………………………………. »………………………………………. ABN »………………………………… $»……………………………………… Other words and phrases in this Undertaking have the meanings given in the GC21 Subcontract. Undertaking 1. At the request of the Subcontractor, Supplier or Consultant (as applicable) and the Financial Institution, and in consideration of the Contractor accepting this undertaking from the Financial Institution in connection with the agreement between the Contractor and the Subcontractor, Supplier or Consultant (as applicable), the Financial Institution unconditionally undertakes to pay on demand any amount or amounts demanded by the Contractor to the maximum aggregate sum of the Security Amount. 2. The Financial Institution unconditionally agrees that, if notified in writing by the Contractor (or someone authorised by the Contractor) that it requires all or some of the Security Amount, the Financial Institution will pay the Contractor at once, without reference to the Subcontractor, Supplier or Consultant (as applicable) and despite any notice from the Subcontractor, Supplier or Consultant (as applicable) not to pay. 3. The Contractor must not assign this Undertaking without the prior written agreement of the Financial Institution, which must not be unreasonably withheld. 4. This undertaking continues until one of the following occurs: 5. 4.1 the Contractor notifies the Financial Institution in writing that the Security Amount is no longer required; or 4.2 this undertaking is returned to the Financial Institution; or 4.3 the Financial Institution pays the Contractor the whole of the Security Amount, or as much as the Contractor may require overall. At any time, without being required to, the Financial Institution may pay the Contractor the Security Amount less any amounts previously paid under this undertaking (or a lesser sum specified by the Contractor) and the liability of the Financial Institution will then immediately end. Dated »………………………………………. at Page 2 of 2 »………………………………………. Execution by the Financial Institution: Page 1 of 2 SCHEDULE 3 PAYMENT CLAIM WORKSHEET Refer to clause 62 of the Subcontract. Details for electronic funds transfer to the Subcontractor's account are included in clause 63.6. The Subcontractor: The Subcontract: Subcontract Title: Subcontract Number: Name of Financial Institution: Account Name: Account Number »………………………………………. ABN»…………………………………. »………………………………………. »………………………………………. »………………………………………. »………………………………………. »………………………………………. »………………………………………. 1 Activity (& Subcontract Milestone) to suit Schedule of prices and/or activities for work covered by a lump sum 2 5 3 4 Subcontract Value of Value Activity Milestone activity (& completed Completed & activity) Subcontract % $ Milestone) number $ Amount brought forward from previous sheet $ $ Amount carried forward to next sheet $ $ 1 Item or activity to suit Schedule of Rates 2 Item activity number 3 4 Price rate or Quantity price for completed item or activity $ 5 Value Completed $ (col 3 x col 4) Amount brought forward from previous sheet $ Amount carried forward to next sheet $ Complete this section on the last sheet only Subtotal for any Schedule of Rates items $ Page 2 of 2 $ $ $ $ Value Completed Less payments already made Less retention for the Completion Amount under clause 64, if applicable Claimed Amount $ $ $ $ Page 1 of 1 SCHEDULE 4 CERTIFICATE OF COMPLIANCE Refer to clause 62.6.3 of the Subcontract. Contract The Contract: Subcontract Title: Subcontract Number: Dated: The contract between the Contractor and the Subcontractor » »………………………………………. »………………………………………. »………………………………………. Certificate The Contractor: The Subcontractor: Consultant: Consultant (2): To: »………………………………………. From: »………………………………………. ABN»…………………………………. »………………………………………. ABN»…………………………………. »………………………………………. ABN»…………………………………. In accordance with clause 62.6.3 of the Subcontract, we certify that all design work done (and all construction work* relating to the Design to the date of this Certificate of Compliance) is in accordance with the Subcontract. Consultant: Signature of Authorised Person Name of Authorised Person Date Date: Consultant (2): Signature of Authorised Person Name of Authorised Person Date: Signed by the Consultant(s): »………………………………………. »………………………………………. »………………………………………. »………………………………………. »………………………………………. »………………………………………. * delete if not applicable In accordance with clause 62.6.3 of the Subcontract, we certify that all work done (including Design and construction work done and Materials supplied) to the date of this Certificate of Compliance is in accordance with the Subcontract. Signature of Authorised Person Name of Authorised Person Date: Signed by the Subcontractor: »………………………………………. »………………………………………. »………………………………………. Page 1 of 1 SCHEDULE 5 AGREEMENT WITH VALUER Refer to clauses 39, 51 and 52 of the Subcontract. Not used Page 1 of 3 SCHEDULE 6 EXPERT DETERMINATION PROCEDURE Refer to clause 75 of the Subcontract 1 Questions to be determined by the Expert 1.1 The Expert must determine for each Issue the following questions (to the extent that they are applicable to the Issue): 1.1.1 1.1.2 1.1.3 Is there an event, act or omission which gives the claimant a right to compensation, or otherwise assists in resolving the Issue if no compensation is claimed: (I) under the Subcontract (2) for damages for breach of the Subcontract, or (3) otherwise in law? If so: (1) what is the event, act or omission? (2) on what date did the event, act or omission occur? (3) what is the legal right which gives rise to the liability to compensation or resolution otherwise of the Issue? (4) is that right extinguished, barred or reduced by any provision of the Subcontract, estoppel, waiver, accord and satisfaction, set-off, cross-claim, or other legal right? In the light of the answers to clauses 1.1.1 and 1.1.2 of this Expert Determination Procedure: (1) what compensation, if any, is due from one party to the other and when did it fall due? (2) applying the rate of interest specified in the Subcontract, what interest, if any, is due when the Expert determines that compensation? (3) if compensation is not claimed, what otherwise is the resolution of the Issue? 1.2 The Expert must determine for each Issue any other questions identified or required by the parties, having regard to the nature of the Issue. 2 Submissions 2.1 The procedure for submissions to the Expert is as follows: 2.1.1 The party to the Subcontract which has referred the Issue to Expert Page 2 of 3 Determination must make a submission in respect of the Issue, within 15 Business Days after the date of the letter of engagement of the Expert referred to in clause 75.2 of the Subcontract. 2.1.2 The other party must respond within 15 Business Days after receiving a copy of that submission or such longer period as the other party may reasonably require, having regard to the nature and complexity of the Issue and the volume of the submission. If the parties do not agree on that longer period, the Expert will promptly determine any extra time permitted, following a submission on the point by a party desiring to make a submission, within the time specified by the Expert. The response to the submission in clause 2.1.1 may include cross-claims. 2.1.3 The party referred to in clause 2.1.1 may reply to the response of the other party, but must do so within 10 Business Days or such longer period as that party may reasonably require (in the same terms as in clause 2.1.2) after receiving the response, and must not raise new matters 2.1.4 The other party may comment on the reply, but must do so within 10 Business Days or such longer period as that party may reasonably require (in the same terms as in clause 2.1.2) after receiving the reply, and must not raise new matters. 2.2 The Expert must ignore any submission, response, reply, or comment not made within the time given in clause 2.1 of this Expert Determination Procedure, unless the Contractor and the Subcontractor agree otherwise. 2.3 The Expert may request further information from either party. The request must be in writing, with a time limit for the response. The Expert must send a copy of the request and the response to the other party, and give the other party a reasonable opportunity to comment on the response. 2.4 All submissions, responses, replies, requests and comments must be in writing. If a party to the Subcontract gives information to the Expert, it must at the same time give a copy to the other party. All documents to be copied to the Contractor under this Expert Determination Procedure must be sent to the relevant person at the relevant postal or other address specified in Subcontract Information item 54. This address may be different to the address for the giving of notices to the Contractor under clause 30.1. 3 Conference 3.1 The Expert may request a conference with both parties to the Subcontract. The request must be in writing, setting out the matters to be discussed. 3.2 The parties agree that such a conference is not to be a hearing which would give anything under this Expert Determination Procedure the character of an arbitration. 4 Role of Expert 4.1 The Expert: 4.1.1 acts as an Expert and not as an arbitrator; 4.1.2 must make its determination on the basis of the submissions of the parties, including documents and witness statements, and the Expert's own Page 3 of 3 expertise; and 4.1.3 4.2 must issue a certificate in a form the Expert considers appropriate, stating the Expert's determination and giving reasons, within 16 weeks, or as otherwise agreed by the parties, after the date of the letter of engagement of the Expert referred to in clause 75.2 of the Subcontract. If a certificate issued by the Expert contains a clerical mistake, an error arising from an accidental slip or omission, a material miscalculation of figures, a mistake in the description of any person, matter or thing, or a defect of form, then the Expert must correct the certificate. Page 1 of 3 SCHEDULE 7 STATUTORY DECLARATION Refer to clause 62.6.2 of the Subcontract Oaths Act 1936 (SA) Definitions The Contractor is: The Subcontractor is: The Subcontract: Subcontract Title: Subcontract Number: Dated: »………………………………………. »………………………………………. ABN»…………………………………. The contract between the Contractor and the Subcontractor »………………………………………. »………………………………………. »……………….(Date of Subcontract). Declaration Full Name: Address: I, »………………………………………. of »………………………………………. do hereby solemnly declare the following and I make this solemn declaration conscientiously believing the same to be true, and by virtue of the provisions of the Oaths Act 1936 (SA): 1. I am the representative of the Subcontractor in the Office Bearer capacity of: Insert position title of the Declarant » …………………………………………………………………………………….. 2. I am in a position to make this statutory declaration about the facts attested to. 3. I make this declaration in relation to work done under the Subcontract up to the date of this statutory declaration. Delete the words in italics that are not applicable 4. The Subcontractor has/has not entered into Sub-subcontracts, Supplier or Consultant agreements for the performance of the work under the Subcontract. Remuneration of Subcontractor's employees engaged to carry out work under the Subcontract 5. All remuneration payable to the Subcontractor's relevant employees for work under the Subcontract has been paid and the Subcontractor has made provision for all other benefits accrued in respect of the employees. "Relevant employees" are Page 2 of 3 those engaged in carrying out the Subcontract work. "Remuneration" means remuneration or other amounts payable to relevant employees by legislation, or under an industrial instrument, in connection with work done by the employees, in connection with work done by the employees . Workers Compensation insurance of the Subcontractor's employees 7. All workers compensation insurance premiums payable by the Subcontractor in respect of the work done in connection with the Subcontract have been paid. This statutory declaration is accompanied by a copy of any relevant certificate of currency in respect of that insurance. Workers Compensation insurance for workers of Sub-subcontractors Delete the words in italics that are not applicable 8. The Subcontractor has been given written statements that all workers compensation insurance premiums payable by each subcontractor in respect of the work done in connection with the Subcontract to the date of this statutory declaration have been paid, accompanied by a copy of any relevant certificate of currency in respect of that insurance. Payments to Sub-subcontractors 16. The Subcontractor has paid every Sub-subcontractor, Supplier and Consultant to the Subcontractor all amounts payable to each of them by the Subcontractor as at the date of this statutory declaration with respect to engagement of each of them for the performance of work or the supply of materials for or in connection with the Subcontract. 17. The provisions of clauses 31 in the Subcontract have been complied with by the Subcontractor. 18. The Subcontractor has been informed by each Sub-subcontractor and Consultant to the Subcontractor (except for Sub-subcontracts not exceeding $25,000 at their commencement) by statutory declaration in equivalent terms to this declaration (made no earlier than the date 14 days before the date of this declaration): 19. 18.1 that their Sub-subcontracts with their subcontractors, suppliers and consultants comply with the requirements of clause 31 of the Subcontract, and 18.2 that all of their employees, subcontractors, consultants and suppliers, as at the date of the making of such a declaration: (1) have been paid all remuneration and benefits due and payable to them by; or (2) had accrued to their account all benefits to which they are entitled from the Sub-subcontractor or Consultant of the Subcontractor or from any other subcontractor or consultant (except for subcontracts not exceeding $25,000 at their commencement) in respect of any work for or in connection with the Subcontract. I am not aware of anything to the contrary of any statutory declaration referred to Page 3 of 3 in paragraph 18 of this declaration and on the basis of the statutory declarations provided, I believe the matters set out in paragraph 18 to be true. 20. And I make this solemn declaration, as to the matters aforesaid, according to the law in this behalf made, and subject to the punishment by law provided for any wilfully false statement in any such declaration. Subcontract Cash Security 21. All Subcontract security held in the form of cash and all cash retentions from Subcontractor payments are held in trust by the Contractor. The cash security and retentions are held in trust for whichever party is entitled to them, until payment is made to that party. 22. The Contractor is maintaining complete records to account for the cash. The records are available to the relevant Subcontractors and the Principal on request. Signature of Declarant: Place: Date: Signature of legally authorised person* before whom the declaration is made: Name and title of person* before whom the declaration is made: »………………………………………. declared at: »………………………………………. on »…………………………………… before me: »………………………………………. »………………………………………. Notes 1. 2. In this declaration: (a) the words 'principal contractor" "relevant employee" and "relevant employees" have the meanings applicable under the relevant Act; (b) the word "subcontractor" in paragraphs 6 and 10 has the meaning applicable under the relevant Act; and (c) otherwise the words "Contractor', "Subcontractor", "Sub-subcontractor", "Supplier"; "Consultant", "subcontractor", "supplier" and "Consultant" have the meanings given in or applicable under the Subcontract * The declaration must be made before one of the following persons: (a) (b) where the Declaration is sworn within the State of South Australia: (i) a justice of the peace of the State of South Australia; (ii) a solicitor of the Supreme Court of South Australia with a current practising certificate; (iii) a notary public; or (iv) another prescribed person legally authorised to administer an oath under the Oaths Act 1936 (SA). where the Declaration is sworn in a place outside the State of South Australia: (i) a notary public; or (ii) any person having authority to administer an oath in that place. Page 1 of 1 SCHEDULE 8 COSTS ADJUSTMENT FORMULA Not used Page 1 of 1 SCHEDULE 9 PRINCIPLES FOR VALUING DAYWORK VARIATION Not used Page 1 of 1 ATTACHMENTS Attachment 1 Start-up Workshop Attachment 2 Performance Evaluation Attachment 3 Performance Evaluation Record Page 1 of 1 ATTACHMENT 1 THE START-UP WORKSHOP Refer to clause 35 of the Subcontract. The start-up workshop is held to encourage the parties and others concerned with the Contract and the Works to work co-operatively to achieve a successful project. this Attachment 1 is intended as a simple guide for the participants. The workshop takes place within 28 days of the Date of Contract. The workshop should take half a day, although large or complex projects may require longer. Participants The workshop includes representatives of the Principal and Contractor together with others concerned with the Works. This might include representatives of authorities, eventual users of the Works, the local community, Consultants, Subcontractors and Suppliers. The sample agenda, which is a guideline for a Start-up workshop, includes: - welcome by the facilitator; - introduction of participants; - workshop purpose, agenda review, workshop guidelines; - project overview; - co-operative contracting - overview; - monitoring and evaluation; - co-operative contracting applied to the Contract; - develop communications framework and directory; - identify key concerns and solutions; - opportunities for Innovation; - prioritization and review; - closing comments and feedback; and - close of workshop. Page 1 of 2 ATTACHMENT 2 PERFORMANCE EVALUATION Refer to clause 6 of the Subcontract. (This form is provided for guidance only) Contract Title: Contract Number: Date: Topic Communication Time Cost Quality Safety Claims and Issue Resolution Rating system » » » Contract Clause Objectives 3 co-operation between parties 4 duty not to hinder performance 5 early warning 6 evaluation and monitoring 25 time management 54 extensions of time 69 Completion by Contractual Completion Dates 52 Variations 61 Prepayment 63, 65 Payments, final payment 17 quality standards 42 - 45 Design requirements 43, 44, 48 fitness for purpose 46 innovation 50 Faults, Defects rectification 69 defect-free Completion 71 after Completion 15 Work health and safety management Sched 5 Valuer 72 Claim resolution 73, 74 Issue resolution 75, Expert Determinations energy & water conservation, waste management, resource conservation, pollution reduction, protection of environment, health Sched 6 Environment 18 29 1 excellent 2 above expectation 3 meeting expectation 4 below expectation 5 unsatisfactory Your rating (this period) Group rating (this period) Page 2 of 2 Topic Contract Clause Objectives Your rating (this period) Group rating (this period) work environment Contract Relations 13 - 20 compliance with SA Government Code of Practice for the South Australian Construction Industry industrial relations management Subcontractor, Supplier and Consultant performance 16 31 - 34 The participants should decide on an action plan during the meeting, after discussing project and contract objectives, comments, observations and suggestions for improvement. Page 1 of 2 ATTACHMENT 3 PERFORMANCE EVALUATION RECORD The participants ratings for each topic are recorded here so that the overall performance can be assessed. Contract Title: Contract Number: Date: Rating system » » » 1 Meeting Number Number Month Year Communication 1 2 3 4 5 Time 1 2 3 4 5 Cost 1 2 3 4 5 Quality 1 2 3 4 5 Safety 1 2 3 4 5 1 2 3 4 5 1 2 3 4 5 Claim and Issue Resolution Environment Contract Relations 1 2 3 4 2 3 4 5 6 7 1 excellent 2 above expectation 3 meeting expectation 4 below expectation 5 unsatisfactory 8 9 10 11 12 Page 2 of 2 5