EXHIBIT A SCOPE OF WORK CONTRACT No. Yavapai County Flood Control District West Chino Valley Floodplain Delineation Re-Study GENERAL This floodplain delineation re-study will determine mapping changes for the existing Zone AE (with floodway) along the Chino Valley Stream and Tributaries south of Road 5 North in Yavapai County. Approximately eleven linear miles of floodplain will be re-delineated. The existing floodplains are within Yavapai County and are included as exhibits to this scope of work. This Yavapai County Flood Control District (DISTRICT) project consists of utilizing the 100-year hydrologic analysis for the 24-hour rainfall event completed in 2002 to prepare the re-delineation of the 100-year floodplains based on improved topographic mapping (also completed in 2002) and the revised hydrology and changed conditions within the watershed. The floodplain will be based on results of using the U.S. Army Corps of Engineer's HEC RAS computer model. The CONSULTANT will utilize the existing topographic data and hydrology, with minor updates, to redelineate the floodplains. All work will meet Arizona Department of Water Resources (ADWR) and Federal Emergency Management Agency (FEMA) requirements for floodplain delineations. Prior to the finalization of this contract, FEMA and the DISTRICT must review and accept the results of this study, and all items called for in this Scope of Work must be delivered to the DISTRICT. The CONSULTANT will submit the study to FEMA for review and approval. All work must be completed within 638 days from the Notice to Proceed (NTP). The Consultant will complete the project within 273 days for submittal to FEMA for their review and approval. This includes 30 days for DISTRICT reviews. An additional 365 days are allotted for FEMA review and approval. West Chino Valley FDS Page 1 of 9 Scope of Work 8-8-07 TASK 1 – PROJECT MANAGEMENT 1.1 Within fourteen (14) days of the NTP, the CONSULTANT will submit a project schedule to the DISTRICT’s Project Manager showing meetings and completion dates for each task identified in the Scope of Work (SOW). The CONSULTANT will update this project schedule when appropriate. 1.2 The CONSULTANT will participate in regular progress meetings with the DISTRICT's Project Manager. The CONSULTANT is responsible for the minutes for all meetings. 1.3 The CONSULTANT will submit monthly progress reports at the time of the submittal of the monthly invoices. The progress reports may be submitted electronically. 1.4 The DISTRICT will be responsible for placing the legal advertisement at the beginning of the study. The advertisement will be run twice, one week apart, in a widely circulated newspaper. Also, if a local newspaper serves the area being studied, the DISTRICT will also place an advertisement, to run twice, in the local newspaper. After the newspapers run the ad, the DISTRICT will supply the CONSULTANT with the original affidavit of publication from each newspaper for each day that the ad ran. 1.5 The CONSULTANT will notify property owners located within close proximity of study watercourses by regular mail and obtain any necessary Rights of Entry for the study area, using a list of property owners furnished by the DISTRICT. The CONSULTANT will furnish the DISTRICT with a sample of the Notification/ Right of Entry letter. 1.6 When the results of the study are known, the CONSULTANT will notify property owners located within close proximity of study watercourses by regular mail, if applicable, regarding the floodplain boundary delineations. The CONSULTANT will furnish the DISTRICT with a sample of the notification letter and a list of expected mail recipients. TASK 2 - DATA COLLECTION 2.1 The CONSULTANT will collect and review pertinent data provided by the DISTRICT, FEMA, ADWR and other sources. Data to be collected will include previous flood hazard reports and hydrology for the study area, existing topographic mapping, readily available historical flooding information, as-built plans for existing structures, relevant storm drain infrastructure information, and drainage design reports for the adjacent roadways, FEMA Flood Hazard Boundary Maps, FEMA Letters of Map Amendment/Revision, and other pertinent information. 2.2 The CONSULTANT will contact officials from the COUNTY transportation departments to obtain information on current and planned public works projects, channel modifications, storm-drainage systems, significant development in the watershed, and corporate limits. 2.3 A data collection summary report will be submitted to the DISTRICT for information purposes. A preliminary draft report will be submitted to the DISTRICT within (45) days of the NTP. The final report will be included in Appendix A of the Technical Data Notebook. TASK 3 - TOPOGRAPHIC MAPPING West Chino Valley FDS Page 2 of 9 Scope of Work 8-8-07 3.1 As required for the floodplain delineation, the CONSULTANT shall use the existing Digital Terrain Model and topographic mapping. The elevation contour interval for the topographic mapping is 2 feet and the horizontal scale is 1 inch = 100 feet. TASK 4 – SUPPLEMENTAL FIELD SURVEY 4.1 Mapping and surveying ground control for floodplain delineation shall meet current FEMA minimum criteria as defined in FEMA’s Guidelines and Specifications for Flood Hazard Mapping Partners, April 2003. a. Horizontal control will be on the Arizona Coordinate System Central Zone 1983 North American Datum (NAD), and the vertical control will be on the North American Vertical Datum of 1988 (NAVD 88). Documentation of how it was derived shall be included in the Technical Data Notebook. b. Additional road profile and cross-section data as specified by the DISTRICT will be collected by GPS RTK methods and will meet the technical requirements of the project. c. The CONSULTANT shall incorporate existing control points from surrounding studies into the ground control for the existing study if applicable. d. Any permanent markers will be set flush to the ground. 4.2 The CONSULTANT shall verify the accuracy of the mapping by the procedures called for in FEMA’s Guidelines and Specifications for Flood Hazard Mapping Partners, April 2003, or other methods approved by FEMA. This shall include the verification of cross sections used in the floodplain delineation. 4.3 Field surveys of significant hydraulic structures not previously obtained, and significant stormwater storage basins will be obtained by the CONSULTANT when as-built plans are not available. This information will be compiled into an 11"x 17" (maximum size) drawing for inclusion in the final report. 4.4 The CONSULTANT shall prepare a Survey Report for this study. This will be included as a part of the TDN. Copies of the survey field books and office calculations must be included in the Technical Data Notebooks. TASK 5 - HYDROLOGY 5.1 The CONSULTANT shall revise the existing hydrologic model to include the rainfall predicted by the NOAA Atlas 14. The results of this updated hydrologic model will be used for the floodplain delineation. All calculations and assumptions used in developing sub-basin and routing parameters shall be documented and made a part of the TDN. 5.2 The CONSULTANT will conduct a field reconnaissance of the study area to ensure the hydrologic model is still representative of the conditions of the watershed. 5.3 The Hydrologic Report 5.3.1 The findings of the hydrologic study will be presented in Section 3 of the Technical Data Notebook and will be prepared in accordance with ADWR State Standards Attachment 1-90 (SSA 1-90). The report will be organized as specified by the DISTRICT, following SSA 190 format. West Chino Valley FDS Page 3 of 9 Scope of Work 8-8-07 5.3.2 Tables and Figures for the appendices: a. Topographic base map(s) showing the sub-basins, routing reaches, Tc flow paths or lag flow paths, major man-made structures, and references (i.e., street names, Township, Range, Section, etc.) at a scale of 1 inch = 1000 feet (or an appropriate scale), on 24 in. by 36 in. sheets. b. Soils map(s) at the same scale as the base map (with References). c. Land use map(s) at the same scale as above (with References). d. Schematic map for the HEC-1 showing the topography, sub-basins (area, Tc), the flow paths, the routing reaches (length, slope, friction, width, velocities, transmission losses, etc.), order of combining the hydrographs, channel, pipe or culvert dimensions (where appropriate). The final version of the HEC-1 schematic shall include peak discharges for the 100yr-24hr storm event at major concentration points. e. Pertinent data on all the structures in the watershed (such as spillway elevation, rating curves, etc.). f. One set of study maps (i.e., sub-basin boundary maps, flow path maps, soils maps, land use maps) to be folded and delivered in a binder. 5.12.3 All calculations, assumptions used in developing sub-basin and routing parameters shall be documented and made a part of the appendix for the hydrologic report. TASK 6 - FLOODPLAIN DELINEATION 6.1 Floodplain delineations will be conducted using methodology as outlined by FEMA. The CONSULTANT will prepare the study using the guidelines established in FEMA’s Guidelines and Specifications for Flood Hazard Mapping Partners, April 2003. The CONSULTANT shall provide the DISTRICT review submittals at each of the following steps: a. b. c. 6.2 Draft field reconnaissance section of the TDN and estimation of Manning's "n" values. Proposed location and alignment of the cross sections. Approximate floodplain delineation. The delineation work shall meet requirements for floodplain delineations as prescribed by FEMA and the Arizona Department of Water Resources. The mapping scale shall be 200’ per inch or as approved by the District. The hydraulic modeling and delineation work maps shall be in the North American Vertical Datum of 1988 (NAVD 88). The delineations shall be based upon the final results of the hydrologic study. 6.3 Field Reconnaissance 6.3.1 The CONSULTANT shall conduct a field reconnaissance of the study area. This will include observation of channel and floodplain conditions for estimating Manning's "n" values; photographic documentation of floodplain characteristics; determination of channel bank characteristics; observation of possible overflow areas; observation of levees or other structures in the floodplain. 6.3.2 Manning’s "n" values are to be determined using the methodology in the USGS report, Estimated Manning's Roughness Coefficients for Stream Channels and Flood Plains in Maricopa County, Arizona, April 1991. Manning’s Roughness Coefficients will be West Chino Valley FDS Page 4 of 9 Scope of Work 8-8-07 presented for typical reach types observed in the project area, rather than specific reaches of specific named watercourses. 6.3.3 6.4 Cross Sections 6.4.1 6.5 Representative “n” values for each typical reach type will be selected. The reconnaissance report will present the determination of channel and over bank "n" values using captioned color photographs or color photocopies for each identified reach type in the project area, and the extents of the typical reach types shall be displayed on an aerial photo exhibit. The report will also discuss floodplain conditions affecting the delineation, describe structures and obstructions, and provide color photos or photocopies of major hydraulic structures. Photo locations for channels, structures, and "n" value determinations will be displayed on reduced scale mapping and included in the Final Report The CONSULTANT shall develop cross sections for the study watercourses. Cross section placement locations shall be selected with respect to existing structures such as roads, railways, drainage features and confluences. Cross section spacing shall be approximately 500 feet and done in such a way as to minimize computational head losses and where natural grade breaks occur as defined by thalwag profile plots. Cross section stationing will be from left to right looking downstream. Identification of cross sections will be in river miles, increasing upstream from the confluence with major drainages. The stationing will begin at the downstream end with the stationing of the existing mapping. The cross sections may need to be re-oriented or altered after running the HEC-RAS model to ensure that they are perpendicular to flow per FEMA criteria. Cross sections developed by the HEC-RAS interpolation feature are not to be used. Floodplain Delineation/HEC-RAS Modeling 6.5.1 The floodplain delineation shall be based on the updated final discharges from the revised 2002 hydrologic study as directed by the DISTRICT. 6.5.2 The CONSULTANT will develop a HEC-RAS model and delineate approximately 11 miles of Zone AE (or appropriate zone designation) floodplain with floodway based upon the final results of the existing hydrologic study as directed by the DISTRICT. Floodways are to be determined using method 4 or 5 with equal conveyance encroachment to start with, but only encroachment method 1 will be used in the final analysis. The floodway encroachment should produce a rise in the water surface elevation that is as near the one-foot maximum as possible. 6.5.3 The hydraulic effects of bridges and culverts should be incorporated into assessing the floodplain around such structures. The Zone AE limits must be determined according to FEMA criteria and clearly labeled on the final drawings. Minor conveyance structures such as small culverts (i.e., less than 30” in diameter) or structures considered likely to become clogged during the 100-year peak discharge shall not be included in the hydraulic analyses. Floodplain may be required to be assessed for elevated structures using the “with and without” scenarios. In these cases the existing conditions model will serve as the “with” structure model. For the “without” structure model the topography will be modified to removed the elevated structures. West Chino Valley FDS Page 5 of 9 Scope of Work 8-8-07 6.5.4 The CONSULTANT and the DISTRICT shall conduct a field trip to review the results of the Floodplain Delineations. 6.5.5 The main project description box of the HEC-RAS models should include the following: a. Project Name and FCD Contract Number b. Consultant(s) and Modeler's Name(s) c. File Name and latest run date/final date if completed d. Vertical Datum of the model, base map date, and base map contractor information e. Source of the peak discharges used in the hydraulic analysis In addition, minor descriptions should be added to the model for hydraulic sections located above and below drainage structures, at section lines, at major transportation crossings, and at confluences. Model descriptions should be added for culverts and lateral structures, and at any other feature considered more important to the modeling. 6.5.6 The CONSULTANT shall review the output of the HEC-RAS computer model to ensure the flow depths and velocities are reasonable and realistic with those expected in this watershed. The use of separate modeling software such as FlowMaster may be used for this review. 6.6 The CONSULTANT shall provide work maps on base maps from the 2002 West Chino ADMS Study. The work map drawings will be 24" X 36" in size. The work map scale shall be 1”=200’. Flood Zones must be determined according to FEMA criteria and clearly labeled on the work maps. A cover sheet will be part of the work-study drawings and shall include the project title, source and date of topographic mapping, and a location map showing geographic range covered by each specific mapping sheet. Each drawing will include the watercourse names and floodplain boundaries, floodway boundaries, a north arrow, scale, section corners, current streets and highway names, Horizontal and Vertical Datum references (State Plane Coordinate System, NAD 83, and NAVD 88), any DISTRICT monument labels located within individual sheet boundaries, major drainage features, corporate boundaries, hydraulic cross section lines, channel station ceterline, index map, base flood elevations (BFE), ,peak discharges at concentration points, and Section, Township, Range for each watercourse delineated. 6.7 Technical Data Notebook 6.7.1 The findings of the floodplain delineation study will be presented in Section 5 of the Technical Data Notebook and will be prepared in accordance with ADWR State Standards Attachment 1-97 (SSA 1-97). The report will be organized as specified by the DISTRICT standards, following SSA 1-97 format. 6.7.2 The Hydraulic analysis/HEC-RAS output of the Technical Data Notebook, in addition to summary tables and full output report, should include fully labeled cross section plots. Section plots should be grouped per study reach, and reach groups should be separated and then indexed within the main report to expedite data recovery. 6.8 The CONSULTANT shall fill out all the forms required by FEMA for the submittal of a Floodplain Delineation Study. TASK 7 – FLOODPRONE STRUCTURES West Chino Valley FDS Page 6 of 9 Scope of Work 8-8-07 7.1 Following the re-delineation of floodplains, the CONSULTANT shall provide the DISTRICT with a list of buildings that remain within the floodplain. TASK 8 – PUBLIC INVOLVEMENT 8.1 The CONSULTANT shall prepare for and attend a public meeting when results of the new delineations are known and prior to the submittal to FEMA. The public meeting will present the proposed delineations. The CONSULTANT shall provide graphics and exhibits for the public meeting. The DISTRICT will provide addresses for mailings and the CONSULTANT shall send notifications to property owners and secure the meeting location. Copies of all advertisements/notices, and any public comments shall be included in the TDN. The meeting notice may be sent with the results letter sent to property owners within a close proximity of the study watercourses. The CONSULTANT shall be prepared to take public comments and organize and include them in the TDN. TASK 9 – DELIVERABLES The CONSULTANT shall prepare for and provide the following deliverable items for this project: 9.1 Pre-FEMA Submittal: The CONSULTANT will deliver the following items to the DISTRICT for review and approval: 9.1.1. Three (3) sets of blackline topographic base maps with floodplain delineations. 9.1.2. Three (3) copies of the draft Technical Data Notebook, including completed FEMA forms, annotated Flood Insurance Rate Maps, HEC-1 and HEC-RAS (if used) model results (on diskettes). 9.2 FEMA Submittal: Following the DISTRICT’S review and the incorporation of comments into the study documents, the CONSULTANT will submit the study to FEMA. A copy of the items submitted shall be provided to the DISTRICT. All of the following products are deliverables for the FEMA submittal: 9.2.1 One (1) complete set of blackline paper topographic base maps with the floodplain delineations shown. All drawings will be signed and sealed by persons of appropriate professional registration(s). Each registrant will provide a specific statement as to what service they performed. 9.2.2 One (1) complete copy of the Technical Data Notebook, including completed FEMA forms, annotated Flood Insurance Rate Maps showing the proposed delineation, HEC-1, and HECRAS input/output files on diskettes. The notebook will be organized as specified by the DISTRICT, following SSA 1-90 format. 9.3 Final Submittal: The following products are the deliverables for the final submittal to the DISTRICT after FEMA approval is issued: 9.3.1 One (1) complete set of Mylars and three (3) complete sets of sealed blackline paper topographic maps with the floodplain/floodway delineations shown. All drawings will be West Chino Valley FDS Page 7 of 9 Scope of Work 8-8-07 signed and sealed by persons of appropriate professional registration(s). Each registrant will provide a specific statement as to what service they performed. 9.3.2 All remaining hydrologic and floodplain delineation data in conformance with the contract specifications. 9.3.3 Three (3) complete copies of the Technical Data Notebook including HEC-1 input/output files on diskettes. The Technical Data Notebook shall include any correspondence and/or meeting minutes with the reviewing agencies and shall reflect any revisions required by those reviewing agencies. Revisions may include, but are not limited to, addressing FEMA's comments, modifications to the delineation maps, the HEC-1 model and/or the Final Report. 9.3.4 Three (3) electronic copies of the TDN report on CD's as pdf files. West Chino Valley FDS Page 8 of 9 Scope of Work 8-8-07 Exhibit A (Fee Schedule) Yavapai County Flood Control District FLOODPLAIN DELINEATION STUDY CONSULTANT/SUBCONSULTANT ESTIMATED LABOR HOURS AND DIRECT LABOR COSTS August 14, 2007 LABOR-HOUR ESTIMATE Estimated Fee Tasks Task 1 Project Management $ 13,243 Task 2 Data Collection $ 12,403 Task 3 Topographic Mapping $ - Task 4 Field Survey $ 10,617 Task 5 Hydrology $ 18,787 Task 6 Floodplain Delineation $ 93,373 Task 7 Floodprone Structures $ 2,968 Task 8 Public Involvement $ 6,518 Task 9 Deliverables/FEMA Submittals $ 24,786 $ 4,220 Total Lump Sum Project Cost $ 186,915 Direct Expenses West Chino Valley FDS Page 9 of 9 Scope of Work 8-8-07