P-192.319-Installation-of-Pipe-in-a-Ditch

advertisement
Gas Operations and
Maintenance Manual
Description
Regulatory
Applicability
P-192.319
Installation of Pipe in a Ditch
This procedure provides guidance for excavation and backfilling to prevent
damage to the pipeline.
Regulated Transmission Pipelines
Regulated Gathering Pipelines (Type A)
Regulated Gathering Pipelines (Type B)1
Regulated Distribution Pipelines
Frequency
As needed
Reference
49 CFR 192.319
Installation of Pipe in a Ditch
49 CFR 192.325
Underground Clearance
49 CFR 192.327
Cover
LA Title 43 Part XIII 1719
Installation of Pipe in a Ditch
LA Title 43 Part XIII 1725
Underground Clearance
LA Title 43 Part XIII 1727
Cover
OSHA 1926.651(c)(2) Specific Excavation Requirements
Forms / Record
Retention
WTG-1100 Exposed Pipeline Inspection / 5 Years
Related
Specifications
None
OQ Covered
Task
1341
Provide
Or
Assure
Adequate
Pipeline
During Operator Initiated Excavation Activities
Support
(In order to perform the tasks listed above, personnel must be qualified in accordance
with West Texas Gas’s Operator Qualification program or directly supervised by a
qualified individual.)
1
If the line is new, replaced, relocated or changed.
Page 1 of 7
Revised: December 2013
Gas Operations and
Maintenance Manual
P-192.319
Installation of Pipe in a Ditch
Procedure Steps
Excavation
1. In the event of an excavation, refer to your state specific Damage Prevention Plan located at
www.westtexasgas.com for WTG approved procedures regarding excavation and damage
prevention.
2. Lowering Main and Lateral Lines
a) When lowering a main or lateral line without cutting the pipe, the pressure in the line shall
be decreased to the minimum pressure required to maintain continuity of service.
b) Wherever possible on lateral lines, the pressure shall be decreased to five (5) pounds
during the lowering process.
c) Lowering or relocating any portion of a piping system under operating pressure will not be
done due to the secondary stresses imposed.
3. New Excavation and Ditch
a) The excavation or ditch requires considerable attention and in some cases it may be
necessary to grade and pad the bottom of the ditch in order that the pipe may have
continuous bearing on the S bottom of the ditch.
b) In rock, cinders or salty soil, the ditch should be at least 6 inches below the bottom of the
pipe and the space filled with clean earth, free of rock, welding rod and other debris, to the
same distance above the top of the pipe.
c) Care should be exercised in all backfilling to prevent damage to the pipe and coating.
4. Test atmosphere for oxygen and other flammable gasses.
a) Prior to beginning work in the trench and on a periodic basis while work is being performed,
test for an oxygen deficient atmosphere containing less than 19.5% oxygen and unsafe
accumulations of vapor (concentration of flammable gas in excess of 20% of the lower
flammable limit (LFL) of the gas) or gas. Use SCBA as appropriate.
5. Install excavation shoring structures.
a) Shore, lay back to a stable slope, or provide some other equivalent means of protection
where personnel may be exposed to moving ground or cave-ins when the trench is more
than 5 feet deep. This protection will also be provided in trenches less than 5 feet deep if
soil conditions so dictate. Refer to the diagram on the next page as a guide in sloping
banks.
b) Minimize water accumulation in trenches as necessary. This may be done with diversion
ditches, dikes, or other suitable means.
c) Use Devices such as stop logs or chocks to prevent mobile equipment from accidentally
entering the excavation. When possible, the grade in such areas will slope away from the
excavation.
Page 2 of 7
Revised: December 2013
P-192.319
Gas Operations and
Maintenance Manual
Installation of Pipe in a Ditch
d) Provide an exit such as a sloped cut-out, ladder or steps in trenches that are 4 feet deep or
more. These should be located so that no more than 25 feet of lateral travel is required.
Provide rescue harnesses and lines as appropriate.
6. Provide proper safety equipment.
a) Where hazardous atmospheric conditions exist or may reasonably be expected to develop,
emergency rescue equipment, (i.e. breathing apparatus, safety harness and lifeline, basket
stretcher, etc.), must be readily available and attended when in use.
b) Employees entering bell-bottom pier holes, or other similar deep and confined footing
excavations, must wear a harness with a lifeline securely attached to it. The lifeline must
be separate from any other line used to handle material and must be individually attended
at all times.
7. Compact soil for proper pipe support regarding size of support, spacing, etc.
a) Ensure excavated or other materials are at least 2 feet from the edge of the trench.
Surface encumbrances (trees, boulders, etc.) that may create a hazard to employees
involved in excavation work need to be removed or secured.
Approximate Angle of Repose For Sloping of Sides of Excavations
Page 3 of 7
Well rounded loose sand 2:1 (28 degrees 34
minutes)
Compacted sharp sand 1 ½ : 1 (33 degrees
41 minutes)
Recommended slope for average soils 1:1
(45 degrees)
Compacted anular gravels ½:1 (XX degrees
XX minutes)
Original ground line
Solid rock, shale, or cemented sand and
gravels (90 degrees)
NOTE: Clays, silts, loams, or non-homogenous soils require shoring and bracing. The presence
of ground water requires special treatment.
Revised: December 2013
Gas Operations and
Maintenance Manual
P-192.319
Installation of Pipe in a Ditch
Backfilling
1. Inspect ditch and backfill soil
a) Ensure materials capable of damaging coating are not present.
b) All timber, sticks, stones, hard clods of earth, projecting rocks and other hard objects,
which might damage the pipe or pipe coating shall be removed from the bottom of the
trench.
c) Before lowering in, the trench depth shall be checked to ensure that the specified cover
can be maintained, taking account of any padding that may be required.
d) Uses shovel or other tool to spot check backfill material.
e) Observes backfilling operation to make certain no damaging material is mixed with the
backfill material.
2. Identify foreign objects that could cause damage to the pipeline system
a) Identify foreign objects by telling, showing at the job site or selecting from a list.
b) Take appropriate action to remove foreign material or objects.
c) The person being evaluated may remove the foreign objects/material or he may direct that
it be removed.
3. Determine when backfill material is unsuitable for backfill around pipeline.
a) Replace if de-rocking is not feasible.
b) Replace if too many roots, too much brush or other foreign material to remove cost
effectively.
4. Rock Trenches (if applicable)
a) The bottom of the trench shall be padded with sand or other approved padding material. A
layer of at least 6 inches of soft padding shall be placed in the bottom of the trench so as to
cover all projections in the trench bottom.
b) Protective shields shall be placed along the trench walls to prevent damage to the coating
during lowering-in if necessary. The shields shall be removed only after the pipe is in place
and subject to no further movement.
5. Initial Backfill
a) Ensure that any/all damage to the protective coating and wrapping has been repaired
before allowing the pipeline to be backfilled.
b) Ensure the pipe is adequately supported along its entire length to avoid undue stresses
and not bearing upon any stones, rock or other material which may damage the coating.
c) The best backfill material shall be used as soft surround for the installed pipe. Carefully
place this material around the pipe and thoroughly compact until the level is 8 inches above
the crown of the pipe across the full width of the trench.
6. Final Backfill
Page 4 of 7
Revised: December 2013
Gas Operations and
Maintenance Manual
P-192.319
Installation of Pipe in a Ditch
a) The remaining excavated material of suitable quality, together with any imported material,
shall be returned to the trench. The backfill material shall be heaped up along the trench
line to leave a crown of 8-12 inches above adjacent ground level unless otherwise
specified in the job plan.
b) Remove surplus excavated subsoil, if any, from site or spread over the right-of-way on
exposed subsoil. Do not spread surplus subsoil on topsoil.
7. Provide erosion protection if necessary
a) On steep slopes or any other sections of the pipeline subject to erosion where there is
danger of the backfill being washed out of the trench, place sandbags in position prior to
backfilling.
b) Provide diversionary furrows if necessary to direct the flow of water into natural drainage
courses and away from the pipeline trench.
8. Support against Settlement
a) Where the pipeline emerges above ground, take special care to ensure that the buried
section of the pipeline is adequately supported against settlement.
9. Backfilling of Made Roads, Footpaths and Paved Areas
a) Backfill across highway and road cuts shall be made with selected, moist backfill material
which is placed in layers, thoroughly compacted by mechanical tamping.
b) Verify that compaction has been achieved by testing crossing to permit or agreement.
10. Backfill in Irrigation and Draining Areas
a) After backfilling the pipe trench across irrigated fields, make furrows across the backfill
crown and pipeline right-of-way to maintain or reinstate the flow of irrigation or drainage
water into its normal flow pattern.
b) Where the sides of drainage or irrigation ditches are cut by the pipe trench, the ground
shall be backfilled and suitably compacted so as to provide a good bond between the
undisturbed sides of the drainage or irrigation ditch and the new backfill material.
11. Ensure each buried Transmission Line is provided with adequate cover per 49 CFR 192.327
Location
Normal
soil
Consolidated
rock
Class 1 locations
30
18
Class 2, 3, and 4 locations
36
24
Drainage ditches of public roads and railroad crossings
36
24
(See regulations for exceptions)
Page 5 of 7
Revised: December 2013
Gas Operations and
Maintenance Manual
P-192.319
Installation of Pipe in a Ditch
12. Ensure each buried Distribution Line is provided with adequate cover in accordance with
49 CFR 192.327.
a) Except as provided in paragraph (b) of this section, each buried main must be installed with
at least 24 inches of cover.
b) Where an underground structure prevents the installation of a transmission line or main
with the minimum cover, the transmission line or main may be installed with less cover if it
is provided with additional protection to withstand anticipated external loads.
Installation of Service Lines
1. Plastic pipe installed within town systems must be installed below ground level with a minimum
of 12 inches of cover on private property and at least 18 inches in streets and roads.
2. Plastic pipe that is installed in a vault or below grade enclosures must be completely encased
in a gas-tight metal pipe and fittings that are adequately protected from corrosion.
3. Plastic pipe that is not encased must have some type of electrically conductive wire or other
means of locating the pipe while it is underground.
4. Plastic pipe that is being encased must be inserted into the casing pipe in a manner that will
protect the plastic. The leading end of the plastic pipe must be closed before insertion.
Pipe Clearance: Transmission and Mains
1. Ensure there is appropriate clearance between the pipe and underground structures in
accordance with 49 CFR 192.325.
a) At least 12 inches of clearance from any other underground structure not associated with
the transmission line.
b) Enough clearance from any other underground structure to allow proper maintenance and
to protect against damage that might result from proximity to other structures.
c) Plastic pipe must have sufficient clearance, or must be insulated, from any source of heat
so as to prevent the heat from impairing the serviceability of the pipe.
Page 6 of 7
Revised: December 2013
Gas Operations and
Maintenance Manual
P-192.319
Installation of Pipe in a Ditch
THIS PAGE INTENTIONALLY LEFT BLANK.
Page 7 of 7
Revised: December 2013
Download