Kay Environmental Services / Kayode Okesanjo Gamma-Omega 765 kV transmission line Pedology Report PROPOSED 765 kV TRANSMISSION LINE GAMMA TO OMEGA PEDOLOGY REPORT Prepared by Kayode Okesanjo Kay Environmental Services P.O. Box 1533 Paulshof 2056 Prepared for: PBA International February 2002 533569566 -1- Kay Environmental Services / Kayode Okesanjo Gamma-Omega 765 kV transmission line Pedology Report EXECUTIVE SUMMARY Kay Environmental Services (KES) was approached by PBA to undertake pedological study of the proposed Gamma – Omega 765 kV transmission line. The proposed 765 kV Transmission line forms a part of the wider Cape Strengthening Programme being undertake by Eskom’s Transmission. The motivation for the programme is set out in the report, however it sets out to address two key requirements: To strengthen the transmission networks to the Western Cape such that reliability of the supply is improved. To enhance the capacity of the network such that predicted future demand may be met. To comply with regulatory requirements of the Environmental Conservation Act (Act 73 of 1989 and associated regulations), and to apply internationally acknowledged best management practice in its activities, Eskom Transmission Group have undertaken this Environmental Impact Assessment (EIA) process. The aim of this study is: To improve the reliability of the exiting transmission network to the Western Cape, and To upgrade the electricity transmission capacity of the network in the short-term whilst providing for the longer-term requirement. This report is primarily comprised of a desktop study of the corridor supplemented by site visits and feedback from I&APs. The primary sources of information were the Institute of Soil, Water and Climate maps and land-type memoirs, and Eskom. The environmental impacts of the construction phase would be particularly sensitive to the management and sensible planning. These impacts include soil erosion and soil pollution. The issues and activities connected to the construction phase include: Clearing of vegetation for the installation of the transmission towers. Clearing of areas for campsites. Construction of access roads. Soil erosion. The soil types along the entire route are generally stable, though all are sensitive to disturbance. The areas in section 2 are very sensitive and due to the position of the soil on the steep slopes along the mountain range. Evidence of gully, water and wind erosion is present in the landscape. In sections 3 to 5 there is evidence of erosion throughout the area, primarily due to infrastructure such as road crossings of watercourses. Construction activities should be carefully monitored to ensure compliance with the EMP. The EMP should limit construction activities to those that are acceptable in preventing environmental damage. No scarring of 533569566 -2- Kay Environmental Services / Kayode Okesanjo Gamma-Omega 765 kV transmission line Pedology Report such areas would be allowed and proper rehabilitation would ensure recovery without any problems. Erosion prevention measures should be taken right from inception of the construction process. The proposed transmission line will have very little impact on the soil within the study corridor. However there are some sensitive areas within the study corridor especially the areas within section 2 were the terrain shows extensive evidence of gully and sheet erosion. Special attention needs to be giving to this area during the construction of the proposed transmission line. 533569566 -3- Kay Environmental Services / Kayode Okesanjo TABLES OF CONTENTS 1. 2. 3 4 Gamma-Omega 765 kV transmission line Pedology Report Page INTRODUCTION...................................................................................................... 5 BACKGROUND AND BRIEF ............................................................................... 5 STUDY APPROACH .............................................................................................. 5 STUDY AREA .......................................................................................................... 6 4.1 SOILS .................................................................................................................... 6 5. IDENTIFICATION OF RISK SOURCES ............................................................ 7 5.1 CONSTRUCTION .................................................................................................. 7 5.2 MAINTENACE DURING OPERATION ................................................................. 7 5.3 CRITERIA AGAINST WHICH EXPECTED IMPACTS ARE EVALUATED .......... 9 6. IMPACT DESCRIPTION AND ASSESSMENT .............................................. 11 7 GENERIC MANAGEMENT AND MITIGATION MEASURES .................... 21 7.1 MITIGATION ....................................................................................................... 21 7.2 MAINTENANCE .................................................................................................. 21 7.3 REHABILITATION OF FERTILE SOIL ............................................................... 22 8 ALTERNATIVES.................................................................................................... 22 9 CONCLUSION........................................................................................................ 23 10. REFERENCES ................................................................................................... 24 533569566 -4- Kay Environmental Services / Kayode Okesanjo 1. Gamma-Omega 765 kV transmission line Pedology Report INTRODUCTION The proposed 765 kV Transmission line forms a part of the wider Cape Strengthening Programme being undertake by Eskom’s Transmission. To comply with regulatory requirements of the Environmental Conservation Act (Act 73 of 1989 and associated regulations), and to apply internationally acknowledged best management practice in its activities, Eskom Transmission Group have undertaken this Environmental Impact Assessment (EIA) process. Although the new transmission line will only be brought into operation at the time when growth and demand requires it, it is necessary to secure the corridor (servitude) that will accommodate the proposed 765 kV well in advance. The study route is a 10km corridor centred on a preferred alignment for the new transmission line. The length of the study corridor is some 520km. It may cross the Western/Northern Cape provincial border at a number of locations, but the bulk of the route lies in the Western Cape province. 2. BACKGROUND AND BRIEF The Cape Strengthening Programme comprises a number of individual projects with the collective aim of improving the reliability of electricity supply to the southern areas of the country, and to the Western Cape in particular. The primary aims of the Cape Strengthening Programme are: To improve the reliability of the exiting transmission network to the Western Cape, and To upgrade the electricity transmission capacity of the network in the short-term whilst providing for the longer-term requirement. 3 STUDY APPROACH This report is primarily comprised of a desktop study supplemented by site visits and feedback from I&APs. The primary sources of information are the Institute of Soil, Water and Climate (ISWC) and Soil map produce from the Environmental Impact Assessment software package. The approach to this study was to review all soil land-type maps, from ISWC and topographical information from 1: 50,000 maps. No soil mapping was conducted but site visits were undertaken at locations along the route.. The erosion hazard criteria consists of two sub-criteria, namely slope gradient and soil erodibility group. Both criteria need to be met for the land to qualify for a particular erodibility class. 533569566 -5- Kay Environmental Services / Kayode Okesanjo 4 Gamma-Omega 765 kV transmission line Pedology Report STUDY AREA The study route is a 20km corridor centred on a preferred alignment for the new transmission line. The length of the study corridor is some 520km. It may cross the Western/Northern Cape provincial border at a number of locations, but the bulk of the route lies in the Western Cape province. The pedology for the route was reviewed. Critical and/or sensitive areas along the corridor were identified and mitigation factors area discussed. Refer to Map 5a – Soils. 4.1 SOILS Section 1 soils are dominate by soils with a marked clay accumulation also common within this section is soils with minimal development (lime present) and greyish-sandy excessively drained soil, with some soils with minimal development with lime rare in the landscape. Section 2 of the study corridor is dominate by soils with minimal development with lime present and soils with minimal development with lime rare in the landscape, also common is the landscape is rocks with limited soils and soils with marked clay accumulation strong and reddish colour. Section 3 soils are dominated by soils with marked clay accumulation strong and reddish with Red-massive or weak structured soils with high base status and rock with limited soils. Section 4 soils include both soils with minimal development (shallow on hard or weathering rock) with lime present and rocks with limited soils. Section 5 soils are dominated by soils with minimal development (shallow on hard or weathering rock) with lime present, also present are rocks with limited soil, Red massive or weak structured with high base status. Present in limited parts greyish-sandy excessively drained soils and soils with negligible to weak profile development –usually on recent flood plains. Erosion is seen to be a potential problem for the whole study area. The flatter terrain and extensive agricultural practices in Section 1 result in the soils being highly disturbed, but largely protected and therefore at lower risk. However, Sections 2 to 5 are seen to be very sensitive to disturbance, resulting in a high erosion potential. Indeed, at locations in these Sections, erosion due to the existing lines is evident, and this has been confirmed by repeated complaints from stakeholders along the route. However it is understood that this erosion is largely due to poor maintenance of the access roads. 533569566 -6- Kay Environmental Services / Kayode Okesanjo 5. Gamma-Omega 765 kV transmission line Pedology Report IDENTIFICATION OF RISK SOURCES This section presents the various biophysical impacts that may result from the construction of the transmission line. The biophysical impacts are discussed in terms of the various project stages and the activities connected to each stage. The project stages include construction and maintenance. 5.1 CONSTRUCTION The environmental impacts of the construction phase would be particularly sensitive to the management and sensible planning. These impacts include soil erosion and soil pollution. The issues and activities connected to the construction phase include: Clearing of vegetation for the installation of the transmission towers. Clearing of areas for campsites. Construction temporary access roads. Disturbance of geological fossil sites. Soil erosion. 5.2 MAINTENACE DURING OPERATION As with disturbance to any soils, the potential problem of subsequent erosion is seldom solved by initial rehabilitation after construction. A long-term maintenance programme needs to be established. Such a programme will need to be drawn up prior to construction. 533569566 -7- Kay Environmental Services / Kayode Okesanjo Gamma-Omega 765 kV transmission line Pedology Report Summary of potential risk of each activity per description area Table 1 Activity Impact Clearing of vegetation for installation of Soil erosion foundation and towers Loss of arable land Loss of wetland related soils Soil pollution Clearing for campsite Soil erosion Soil pollution Soil Loss Construction temporary road Soil erosion Soil pollution Loss of arable land Wetland related soils 533569566 Magnitude of impact High High High High High High High High High High High -8- Duration of impact Medium to long term Medium to long term Medium to long term Medium to long term Medium to long term Long term Long term Medium to long term Long term Short to long term Medium to long term Kay Environmental Services / Kayode Okesanjo 5.3 Gamma-Omega 765 kV transmission line Pedology Report CRITERIA AGAINST WHICH EXPECTED IMPACTS ARE EVALUATED Nature of the impact Extent of the impact Description of impact Describe whether the impact will be : local extending only as far as the development site; or limited to the site and immediate surroundings; or will have an impact on the region, or will have an impact on a national scale or across international borders Duration of the impact Intensity Short term (0-5 years) Medium term (5-15 years) Long term (f16-30 years) Permanent The specialist should establish whether the impact is destructive or benign and should be qualified as low, medium or high. The specialist study must attempt to quantify the magnitude of the impacts and outline the rationale used. Probability of occurrence Improbable, where the possibility of the impact to materialise is very low Probable, where there is a distinct possibility that the impact will occur Highly probable, where it is most likely that the impact will occur Status of the impact Definite, where the impact will definitely occur The specialist should determine whether the impacts are negative, positive or neutral (“cost – benefit” analysis). The impacts are to be assessed in terms of their effect on the project and the environment. For example, an impact that is positive for the proposed development may be negative for the environment. It is important that this distinction is made in the analysis. Accumulative impact Consideration must be given to the extent of any accumulative impact that may occur due to the proposed development. Such impacts must be evaluated with an assessment of similar developments already in the environment. Such impacts will be either positive or negative, and will be graded as being of negligible, low, medium or high impact. 533569566 -9- Kay Environmental Services / Kayode Okesanjo 6. Gamma-Omega 765 kV transmission line Pedology Report IMPACT DESCRIPTION AND ASSESSMENT The soils along the entire route are stable. However, the areas within section 2 are the most sensitive and critical areas along the entire route. This is due to the position of the soil on the steep slopes along the mountain range. Evidence of gully, water and wind erosion is present in the landscape. Sections 1 to 5 Theme Nature of Impact Legal requirements Stage Extent of impact Duration of impact Intensity Probability of Occurrence Status of impact Accumulative Impact Level of Significance Mitigation measures Clearing of vegetation for installation of foundation and towers Soil Erosion Conservation of Agriculture Resources Act (No. 43 of 1983) Construction and Decommission Operation Local NA Potentially long term NA Medium NA Definite NA Negative NA Negative NA Potentially high on steep slopes, Moderate in NA valleys Construction to be done in dry season. Work from top of slope downward. Clearing of vegetation should be kept to a minimum. If possible construction should happen without vegetation removal. Level of significance after mitigation EMP requirements Avoid pristine area. Moderate to low The rehabilitation of any dongas will be necessary in this area. Erosion control will be necessary in this section of the proposed transmission line. 533569566 - 11 - Kay Environmental Services / Kayode Okesanjo Gamma-Omega 765 kV transmission line Pedology Report Long-term monitoring and maintenance requirements to be identified. EMP to control construction to ensure that the best method is used. Discussion The steeper slopes long the route of the proposed transmission line are the most sensitive and critical area to be crossed by the line. These soils are highly susceptible to erosion. Construction activities will either disturb the vegetation cover or breach the protective topsoil is likely to result in severe soil loss. However, it is understood that limited vegetation clearing takes place during construction. Unless the vegetation is high or comprises large trees, it is merely driven over within the working area around the pylon. Nevertheless, some damage to the vegetation will occur and rehabilitation and long-term monitoring will be necessary, particularly in the Karoo areas where vegetation regeneration is slow. 533569566 - 12 - Kay Environmental Services / Kayode Okesanjo Section: 1, 2, 3, 4, and 5 Theme Nature of Impact Legal requirements Stage Extent of impact Duration of impact Intensity Probability of Occurrence Status of impact Accumulative Impact Level of Significance Mitigation measures Gamma-Omega 765 kV transmission line Pedology Report Clearing of vegetation for installation of foundation; towers and access roads Loss of Wetland related soils Conservation of Agricultural Resources Act (No 43 of 1983), Environmental conservation Act (No 73 of 1989) Construction and Decommissioning Operation Local Local Potentially long – term Potentially long-term Moderate to high Moderate Highly probable Probable Negative Negative Moderate Moderate Moderate Moderate Ensure ongoing, regular monitoring and Wetland areas should be avoided at all cost maintenance. during the installation of towers Level of significance after mitigation EMP requirements Low Wetlands should be avoided in planning access roads for construction. Any damage to wetlands must be rehabilitated before the site is abandoned. Self-supporting tower should be installed in wetland area and pans. No dumping of refuse and waste around wetlands. While working in an area efforts should made to reduce compaction of soil. Temporary road crossing wetland should not be compacted and must be remove after construction is finished. 533569566 For more site specific mitigation measures - 13 - Low Set out monitoring and maintenance programme for each wetland. Kay Environmental Services / Kayode Okesanjo Gamma-Omega 765 kV transmission line Pedology Report refer to Eskom’s Environmental Management Plan Report (EMPR) to the construction Phase of this project. Discussion Wetlands are highly sensitive habitats being home to a group of highly specialized species, particularly bird species. Gaining access to construct this proposed powerline has the potential to impact heavily the wetlands in this study area. These wetlands must be avoided, as it is unacceptable to route roads through wetlands. The presence of wetlands along the study area is relatively low, and are all of a small scale. As such they can be avoided by careful placing of pylons and access roads in the bird area. Also included in the area are river crossings, particularly the smaller watercourses where formal roads or crossing points are not near to the route of the line. The same construction and management principles apply, though avoidance is seldom possible. The protection and rehabilitation of these points will be important. 533569566 - 14 - Kay Environmental Services / Kayode Okesanjo Section 1 Theme Nature of Impact Legal requirements Stage Extent of impact Duration of impact Intensity Probability of Occurrence Status of impact Accumulative Impact Level of Significance Mitigation measures Gamma-Omega 765 kV transmission line Pedology Report Construction of access roads Soil Erosion Conservation of Agricultural Resources Act (No 43 of 1983), Environmental conservation Act (No 73 of 1989) Construction Operation Local Local Long-term Long-term Low Low Probable Probable Negative Negative Negative Negative Low to moderate but potentially high on the Low to moderate but potentially high on the Southern Alternative Southern Alternative During construction of access road track All rehabilitation and re-vegetation based vehicle should be used especially in wetland surroundings. Compaction should minimised Any foreign material used to maintain the temporary road programmes must be monitored. must be Existing access road should be used were ever possible. remove after construction, unless used to improve the road and for erosion control Level of significance after mitigation EMP requirements Low During vegetation construction removal and site the preparation, erection of buildings must happen simultaneously, to ensure that no large tracts of land are left exposed at any point in time. Vegetation clearance should be kept to the dry season. 533569566 - 15 - Low All access roads must be maintained and storm water drainage system implemented. Vegetation removal must be kept to a minimum. Kay Environmental Services / Kayode Okesanjo Gamma-Omega 765 kV transmission line Pedology Report Discussion This section of the proposed transmission has a low erosion rating as much of the land has been “improved” by agriculture and access is generally well established. Although the erosion rating is low the activities involved in the construction of access road could course erosion. Utilisation of existing access road is a must. Avoid pristine area. However, an area of concern will be the Southern Alternative where the line will pass through the Elandsberg Private Nature Reserve. This area is undisturbed with the exception of the existing lines and, with the steeper slopes, soil erosion risk is much higher than the surrounding area of Section 1. 533569566 - 16 - Kay Environmental Services / Kayode Okesanjo Section 3 - 5 Theme Nature of Impact Legal requirements Stage Extent of impact Duration of impact Intensity Probability of Occurrence Status of impact Accumulative Impact Level of Significance Mitigation measures Gamma-Omega 765 kV transmission line Pedology Report Construction of access roads Soil Erosion Conservation of Agricultural Resources Act (No 43 of 1983), Environmental conservation Act (No 73 of 1989) Construction and Decommissioning Operation Local Local Potentially long-term Potentially long-term Low to high Low to high Probable Probable Negative Negative Moderate to high Moderate to high Moderate to high Moderate to high Utilise existing access roads where possible. All rehabilitation and re-vegetation Address existing erosion problems. Construction to be done in dry season. Work from top of slope downward. During construction of the proposed programmes must be monitored. Existing access road should be used were ever possible. transmission line areas with fertile soil present this should removed and stored. Level of significance after mitigation EMP requirements Low EMP to control construction to ensure that the Low Clear monitoring and maintenance plan to be best method is used. During vegetation set out, including responsibilities. construction removal and site the preparation, erection of buildings must happen simultaneously, to storm water drainage system implemented. ensure that no large tracts of land are left exposed at any point in time. Vegetation clearance should be kept to the dry season. 533569566 - 17 - All access roads must be maintained and Vegetation removal must be kept to a minimum. Burning along the entire route should be avoided if possible. Burning will leave the Kay Environmental Services / Kayode Okesanjo Gamma-Omega 765 kV transmission line Pedology Report topsoil exposed, which increases the chances of soil erosion. If possible, the veld along the entire route should be cut mechanically to prevent soil exposure. Discussion Their is evidence of soil erosion along this section of the line on both sides of the study area, most of the erosion along this section occurs at river crossings this will affect the water quality in the river, because of the sediment load eroding into the river. Utilisation of existing access road is a must. Avoid pristine area. It is evident that erosion associated with the existing lines is problematic, and in some cases severe. The repeated complaint from landowners is that rehabilitation and maintenance of the existing access roads is not undertaken by Eskom Transmission. It its therefore considered that two opportunities exist by running the new line adjacent to the existing lines; a) the same access roads can be used in most circumstances, thereby limiting new impacts elsewhere, and b) there is opportunity for existing erosion to be addresses as part of the construction of the new line. It is vital, however, that a formal procedure of long-term monitoring and maintenance of erosion in these areas is established prior to construction. This procedure must identify responsibilities of Eskom Transmission (Regional and National) as well as the landowner. 533569566 - 18 - Kay Environmental Services / Kayode Okesanjo Section 2 Theme Nature of Impact Legal requirements Stage Extent of impact Duration of impact Intensity Probability of Occurrence Status of impact Level of Significance Mitigation measures Gamma-Omega 765 kV transmission line Pedology Report Construction of access roads Soil Erosion Conservation of Agricultural Resources Act (No 43 of 1983), Environmental conservation Act (No 73 of 1989) Construction Operation Local Local Potentially long-term Potentially long Term High Low Definite Highly Probable Negative Negative High in mountain areas, moderate to low in valleys High in mountain areas, moderate to low in valleys Utilise existing access roads where possible. Access by foot on steep slopes and mountain ridges. Utilise helicopter construction on mountain slopes and ridges. Construction to be done in dry season. Work from top of slope downward. Clearing of vegetation should be kept to a The rehabilitation of dongas will be necessary in this area. Erosion control will be necessary in this section of the proposed transmission line. minimum. Level of significance after mitigation EMP requirements Moderate in mountain areas, low in valleys The rehabilitation of donga will be necessary Low Clear monitoring and maintenance plan to be in this area. set out, including responsibilities. Erosion control will be necessary in this section of the proposed transmission line. Erosion must be monitored in the section of storm water drainage system implemented. the transmission line All access roads must be maintained and Vegetation removal must be kept to a minimum. EMP to control construction to ensure that the best method is used. All rehabilitation and re-vegetation programmes must be regularly checked and monitored with reseeding of any bare soil 533569566 - 19 - Kay Environmental Services / Kayode Okesanjo Gamma-Omega 765 kV transmission line Pedology Report patches. Burning along the entire route should be avoided if possible. Burning will leave the topsoil exposed, which increases the chances of soil erosion. If possible, the veld along the entire route should be cut mechanically to prevent soil exposure. Erosion should be monitored during the maintenance of the proposed transmission line. Discussion This section of the proposed transmission line is the most sensitive and critical area to be crossed by the proposed line. These soils are highly susceptible to erosion. Construction activities will either disturb the vegetation cover or breach the protective topsoil is likely to result in severe soil loss. In general, the concerns are similar to those raised for Sections 3 to 5 and the same mitigation and management requirements will apply. 533569566 - 20 - Kay Environmental Services / Kayode Okesanjo 7 Gamma-Omega 765 kV transmission line Pedology Report GENERIC MANAGEMENT AND MITIGATION MEASURES Objectives: To reduce the erosion potential when soils are denuded of vegetation or otherwise disturbed. To maximise the use of suitable topsoil for rehabilitation. Control and suitable dispersion of runoff on slopes. Minimise the potential for soil pollution. 7.1 MITIGATION During construction site preparation, vegetation removal and the erection of buildings must happen simultaneously, to ensure that no large tracts of land are left exposed at any point in time. Vegetation clearance should be kept to the dry season. Construction camps should not be sited on steep slopes or near wetland, as this will increase soil erosion. It is advisable to locate construction camps near watershed in order to minimise run-off and erosion. Re-vegetation will prevent erosion after closure. Catch water drains or berms must be constructed above embankments and cuttings to prevent runoff from flowing down and across the slopes. This is especially important while slopes are still bare. For optimum control of soil erosion on embankments and cuttings, vegetation must be established. All topsoil removed from an area during site preparation and construction must be stockpiled for use during rehabilitation. The rehabilitation of the site must occur immediately after construction phase, and should not be left until the end of the project. Construction activities should be carefully monitored to ensure compliance with the EMP. The EMP should limit construction activities to those that are acceptable in preventing environmental damage. No scarring of such areas would be allowed and proper rehabilitation would ensure recovery without any problems. Erosion prevention measures should be taken right from inception of the construction process. 7.2 MAINTENANCE Objective: To ensure that rehabilitation measures are effective. Mitigation: 533569566 - 21 - Kay Environmental Services / Kayode Okesanjo Gamma-Omega 765 kV transmission line Pedology Report All rehabilitation and re-vegetation programmes must be regularly checked and monitored with reseeding of any bare soil patches. Burning along the entire route should be avoided if possible. Burning will leave the topsoil exposed, which increases the changes of soil erosion. If possible, the veld along the entire route should be cut mechanically to prevent soil exposure. Although soil erosion is very extensive in some areas along the proposed transmission line route due to bad management practice or neglects Eskom should look at improving the land practices along this route because this will help slow down a lot of the erosion currently taking place. 7.3 REHABILITATION OF FERTILE SOIL In all areas disturbed by construction activities, the topsoil must be removed and stockpiled close to the site for use during rehabilitation. This may involve separating the 0 and A Horizon, depending on the nature of the soil profile. In cases where these horizons are separated, the material must be stored in different stockpiles. This material should not be stockpiled in natural drainage channels, even during the dry season, as this will leave it exposed to the processes of water erosion. Stockpiles should be placed in areas where they are not susceptible to wind erosion. For more site specific mitigation measures refer to Eskom’s Environmental Management Plan Report (EMPR) to the construction Phase of this project. 8 ALTERNATIVES The assessment given above addresses the issues that are representative of the study corridor as a whole. The preferred line and alternatives identified do not differ significantly such that different levels of impact will emerge. It is considered that, in all cases erosion can be avoided or mitigated and the need for rehabilitation, monitoring and maintenance is equally important. However, preference may be awarded to the routes in the different sections of the study area as follows: Section 1: Preference is given to the Central Route as this avoids the higher erosion risk areas on the Southern Alternative. Section 2: All of the routes identified will be very sensitive to erosion. However, the Southern Alternative passes over the high and complex terrain of the Skurweberg and Witsenberg, which is seen to be more sensitive than the other mountain ridges considered in this Section. Erosion problems in this area have taken many years to resolve. In comparison, the Northern Alternative is relatively pristine, though the narrow valley on the eastern sections of this route (near Section 3) already exhibits erosion. It is considered preferable to leave each 533569566 - 22 - Kay Environmental Services / Kayode Okesanjo Gamma-Omega 765 kV transmission line Pedology Report of these routes alone and give preference to either the Central Route or the Central Alternative, where erosion risk and accessibility is seen to be better. Sections 3 to 5: It is considered that there is significant benefit in following either of the existing 400kV lines through these areas. Many of the existing access roads may be used as a result and current erosion problems may therefore be addressed. No particular preference can be given to which of the existing lines the new line should follow. Deviation away from the existing lines raises concern for the spread of erosion impacts. 9 CONCLUSION It is considered that, overall, the impact of a new 765kV Transmission line through the study area may be mitigated and managed to an overall rating of low. There are areas where careful planning of construction will be required, particular the mountain ridges. However, of particular concern is the need for long-term monitoring and maintenance of the access roads and constructions sites. It is recommended that clear management plans, with responsibilities, are set out and approved prior to construction. Maintenance agreements with landowners may offer reasonable solutions to this issue. 533569566 - 23 - Kay Environmental Services / Kayode Okesanjo 10. Gamma-Omega 765 kV transmission line Pedology Report REFERENCES Satellite Application Centre Division of Information and Communication Technology, CSIR Institute of Soil Climate and Water Maps and type Memoirs. Institute of Soil Climate and Water Data centre for Weather. 533569566 - 24 -