1 Chapter 1 INTRODUCTION 1.1. Background Lang Creek dam is an earthfill dam located in Southern California. The dam was constructed to protect the downstream residential areas from high season floods. Floods induced by dam break can cause serious loss of lives and significant economic losses. To recognize the possible causes of dam break, a detailed knowledge of dam breakage processes and flood propagations are required. Performing a sensitivity analysis of dam break parameters helps to study the relationships among the parameters that are involved in dam breach and flood propagation processes. The methods applied in conducting the sensitivity analysis of dam break parameters include hydrologic and hydraulic routing techniques. These techniques help to predict dam-break breaching outflow hydrographs and flood wave propagation, and provide the information regarding the wave front arrival time, inundated area, and flow depth. This study, sensitivity analysis of dam breach parameters using Lang Creek dam as a testing basis, involved estimating the key parameters, time to dam failure, side slope of breach, downstream Manning coefficients, and channel bed slopes. The process of estimating the parameters was done based on literature reviews [12]* and historical data collections [19]*. The influences of parameters on peak flows were analyzed at the specified reaches stations and dam site. Two applications software, the HEC-1 applied in 2 the reservoir components of the study and HEC-RAS applied in unsteady flow routing through the downstream reaches, were utilized to carry out the study. 1.2. Purpose This study was prepared to evaluate the relative effects of dam breach and downstream river parameters on the peak discharges at the dam site and specified locations in the downstream channel. Based on the type of flow routing techniques and parameters used, the objectives of the sensitivity analysis were grouped into two phases. Phase 1: To investigate the sensitivity of maximum discharges for given changes in time to dam failure in hours (TFH), and side slope of dam breach (SS) at the dam site. To evaluate the combined effects of changes in time to dam failure and side slope of breach on maximum discharges and determine the controlling parameter at the dam site. Phase 2: To examine the sensitivity of peak flows for specified Manning coefficients and time to dam failure at specified reach stations; to test the combined effects of changes in Manning coefficients and time to dam failure on peak flows, and determine the controlling parameter at specified reach stations. 3 To study the sensitivity of peak flows for given changes in channel bed slopes. In order to carry out the sensitivity analysis, Lang Creek Dam, reservoir data, and downstream river data were utilized in the study as a testing basis. 4 Chapter 2 GENERAL DESCRIPTION OF STUDY AREA 2.1. Location Lang Creek detention basin is located downstream of Westlake Boulevard, near Lang Ranch, in the city of Thousand Oaks, Ventura County, California. See Figure 2.1 – vicinity map of the Lang Creek Dam. Figure 2.1 - Vicinity map of Lang Creek detention basin [19] 5 The Lang Creek basin dam is an earth fill dam with crest elevation of 1040.8 feet. The study area includes Lang Creek debris and detention basin, the contributing watershed upstream of the basins, and the affected area downstream of the basins. Figure 2.2 – Lang Creek detention basin watershed map [19] 6 2.2. Physical characteristics of Lang Creek dam The physical characteristics of Lang Creek detention basin and dam were summarized in Table 2.2.1. The Table below contains data gathered from previous studies and provided by the dam owner. Table 2.2.1- Lang Creek reservoir and dam characteristics [19] Lang Creek Dam and Reservoir Descriptions Reservoir Characteristics Maximum Water Surface Elevation (ft.) Full Storage Capacity (acre-ft) Maximum Surface Area (Acre) Drainage Area (square miles) Dam Characteristics Type of Dam Height of Dam (ft.) Elevation of Crest (ft.) Length of Crest (ft.) Elevation of Spillway (ft.) Spillway Capacity (cfs) Spillway Width (ft.) Type/Size 1034 345 13.6 3.63 Earth Fill 62.8 1040.8 345 1034 N/A 17 The dam was constructed by the Ventura County Watershed Prevention District with the city of Thousand Oaks in 2004. It was built to relieve the city of Thousand Oaks from flooding during high storm events. The dam is connected to a Lang Creek channel at the downstream side. The channel has an approximate length of 6.49 miles before it joins Arroyo River. 7 Chapter 3 THEORY OF DAM BREACH ANALYSIS 3.1. Historical background Floods resulting from dam failures led to catastrophic and tragic consequences in the past. The catastrophic flooding due to dam failures in the 1960’s and 1970’s brought about the passage of the National Dam Safety Act. Since then [18], a number of state and federal governments have been working to develop robust computer programs that would help to design new dams or evaluate existing dams. The actual failure mechanics of dam failure have not been well understood for either earthen or concrete dams. In earlier attempts to predict downstream flooding due to dam failures, it was usually assumed that the dam failed completely and instantaneously. Some investigators of dam-break flood waves assumed the breach encompasses the entire dam and that it occurs instantaneously. Others, such as Army Corps of Engineers (1960), have recognized the need to assume a partial failure rather than complete breaches. [12] Several researchers have devolved regression equations to estimate breach size, shape, and time to dam failure from historical dam breach information. [9][11][18] A few researchers have tried to develop computer models to simulate the physical breaching process. [8][10][1][2] Since the passage of the “National Dam Safety Act” [18], US Army Corps of Engineers has been proactively working in developing a number of computer models that have capabilities to perform dam breach analysis and river system routing. Such as, HEC-1 and HEC-RAS modeling software, applied in Lang Creek dam breach sensitivity analysis. 8 3.2. Major steps in dam break analysis 3.2.1. Information gathering In this starting step, information on the reservoir, the dam’s structure, and downstream reaches are researched. The following data are required to complete the study: [12] a. Hydrologic information such as precipitation patterns, snow and snowmelt characteristics, watershed characteristics, and topographic data. b. Reservoir characteristics such as storage capacity, surface area, normal and maximum pool elevations, inflows, etc. c. Physical characteristics of the dam and spillway such as construction type, height, crest length, crest elevation, toe elevation, spillway type, spillway width, elevation and capacity, etc. d. Type, size and characteristics of downstream hydraulic structures such as dams, bridges, culverts, railroads or highway crossings, etc. e. The location and type of downstream development such as schools, highways, railroads, parks, etc. 3.2.2. Size and hazard classification of dam Depending on the size and hazard potential, dams can be classified into three categories: small, intermediate, and large. The height of the dam and the volume of the reservoir determine the size category of a certain dam. 9 Table 3.2.1- Classification of dam based on height and reservoir volume [12] Size of dam Small Intermediate Large Dam height (feet) Less than or equal 40 Less than or equal to 100 100 plus Volume of the reservoir (acre-feet) Less than or equal 1000 Less than or equal 50,000 50,000 plus Dams can also be classified according to their hazard potential. This depends on the number of human lives that are threatened, and the economic loss inflicted on the downstream areas in the event of dam failure. There are three categories: low, significant, and high hazard. Table 3.2.2- Classification of dam based on hazard potential [12] Category Low Significant High Loss of life (Extent of development): None expected (no permanent structures for human habitation) Few (no urban developments and no more than a small number of inhabitable structures) More than a few Economic loss: Minimal (undeveloped to occasional structures or agriculture Appreciable (no stable agriculture, industry, or structures) Excessive (extensive community, industry, or agriculture) 3.2.3. Inflow design flood hydrologic analysis The main objective of this step is to estimate the inflow design flood (IDF) to reservoir and to determine the most probable type of failure. Depending on the amount of IDF, different modes of dam failure will be assumed. If the dam is overtopped by the inflow hydrograph, then the failure shall be assumed to be an overtopping failure, otherwise a “sunny day” shall be assumed. The design floods need to be verified and used 10 as IDF hydrographs and routed through the reservoir using HEC-1 to determine the dambreak breaching hydrographs. Table 3.2.3 - Recommended inflow design floods [12] Hazard Size Inflow Design Flood (IDF) Small 50 - 100 year Low Intermediate 100 - 0.5 PMF Large 0.5 PMF - PMF Small 100 - 0.5 PMF Significant Intermediate 0.5 PMF - PMF Large PMF Small 0.5 PMF - PMF High Intermediate PMF Large PMF Where PMF is Probable Maximum Flood 3.2.4. Types of dam failure The types of dam failure include: [12] a. Overtopping failure: the overtopping type of failure is most likely to occur when the reservoir’s water surface elevations exceeds the top of the dam due to significantly large amount of IDF inflows into the reservoir. This commences as a gradual erosion of embankment for earthen dams. Overtopping occurs when there is insufficient flood storage of reservoir, low spillway capacity, or it is modeled by using the broad-crested weir equation. b. Normal pool failure: also referred to as a “sunny day” failure because it occurs independent of rain events, even on sunny days, is initiated by erosion of material due to piping, earthquakes, slope instabilities, foundation weaknesses, or other structural 11 weaknesses. Hydraulically, this type of failure is often modeled as a combination of orifice and weir flow. 3.2.5. Dam breach parameters and analysis The objective of this step is to calculate and verify the outflow breach hydrograph resulting from a dam failure. The most typical breach characteristics are the shape, final depth and width, side slopes, breaching time (failure time) and the rate at which the breach develops. Table 3.2.4 shows the parameters in the development of breach for hypothetical failure of dam. Table 3.2.4 - Dam-break breaching parameters [12] Breaching Parameter Average Width of Breach (BB) Side Slope Saide Slopeofof the Breach the (Z) (1: Breach Z) Time of Failure in Hours (TFH) Values Type of Dam 0.5 HD <BB <3 HD BB = 0.8 * Crest Length BB = Multiple of Monolith Widths BB = Crest Length 0<Z<2 Z= 0 0.25 <Z < 2 1<Z<2 0.1 < TFH <3.0 0.1 < TFH < 0.3 Earthen, Rock fill Slag, Refuse Masonry, Gravity Concrete, Arch All Masonry, Gravity Earthen, Rock fill Slag, Refuse All Masonry, Gravity, Slag, Refuse Earthen, Non Engineered, Poor Construction Earth, Engineered, Conmpacted 0.1 < TFH < 0.5 0.3 < TFH < 3.0 Note: TFH – time to dam failure in hour BB - Average breach bottom width (ft) HD – Dam height (ft) Z or SS – Side slope of the dam breach A. Shape of breach [12] 12 For the hypothetical dam failures the shape of the breach is usually approximated as geometric shape such as rectangle, triangle, trapezoidal or parabola. The shape of the breach is greatly dependent on the type of dam. For earth or rock-fill dams, a trapezoidal shape is common. For concrete arch dams usually the shape of the breach will be the same as the shape of the dam. B. Breach size As the dam breach advances, the dimensions of the breach keep increasing. For an earth fill dam, usually a trapezoidal breach shape, overtopping failure starts as a small breach and progresses at a linear or non-linear rate down the height of the dam as shown in Figure 3.2.1. Figure 3.2.1 - Overtopping breach dimensions [10] For piping failures, the breach starts as a rectangle at some specified elevation from the crest as shown in Figure 3.2.2. The breach width and height grow until the elevation of the top of the breach is the same as the crest elevation, at which point the 13 breach is identical to an overtopping failure. The range of acceptable parameters for both the overtopping and breaching cases are shown in Table 3.2.4. Figure 3.2.2 - Piping breach dimensions [9] ho = the breach top elevation at time t , feet hd = elevation at the top of the dam, feet hb = the breach bottom elevation at time t, feet hbm = lowest breach bottom elevation at time t, feet hf = specified center-line elevation of the pipe, feet b = maximum breach bottom width at time t, feet C. Breaching time Breaching time refers to the time elapsed since the initial breach formation until it reaches its terminal size. The failure time for earth dams ranges from six minutes to three hours. Concrete dam failures are much more rapid, and have a time range of six to 14 eighteen minutes. The time of failure most commonly depends on the size of the dam, types of materials used for construction, and the structural strength of the embankment. D. Rate of failure [12] The rate of breach expansion, increase in depth and width, is called rate of failure. This rate can progress at a linear or non-linear rate. The progress of breach bottom elevation hbt at a rate of P defined by Fread according to this equation: Hbt = hd – [(hd - hbm) (tb / t)p] for 0 < tb < t Where: Hbt = breach bottom elevation at a specified time tb, feet hd = elevation at the top of the dam, feet t = breach formation time, hours hbm = lowest breach bottom elevation at time t, feet p = rate of failure (1 < p < 4) Also, the relationship between the breach bottom width b and its progress rate P is given according to the equation: Bt = bm (tb / t)p Where: Bt = breach bottom width at time tb, feet bm = maximum breach bottom width at time t, feet p = rate of failure (1 < p < 4), most commonly the rate of failure P is assumed to be linear; P is equal to one for both cases. E. Determining outflow hydrograph [12] 15 There are a few recommended computer programs to calculate the breach outflow hydrograph, in addition to manual calculations. Manual calculations are usually the approximate method for calculating the outflow hydrograph. For overtopping failures, the breach outflow hydrograph can be computed by the broad-crested weir flow equation. Neglecting the correction factor for the velocity of approach and downstream submergence effects, the broad-crested weir equation will take the form: Qj = 3.1 bj (hwj – hbj)1.5 + 2.45 Z (hwj – hbj)2.5 Qj = the outflow from the dam (cfs) at time step j bj = the breach bottom width (ft) at time step j hw = water surface elevation in the reservoir (ft, m.s.l) at time step j hbj = the breach bottom elevation at time step j, in feet Z = side slope of the breach; Z: 1 = horizontal: vertical Where: On the other hand, for piping failures, the breach shape is approximated as a rectangle and the following orifice equation can be used: Qj = 9.6 bj (hp – hbj) (hwj – hdj)0.5 Qj = outflow through the breach at time step j, in cubic feet per second bj = breach bottom width in feet at time step j hp = elevation of the vertical centerline of the breach in feet hbj = elevation of the bottom of the breach in feet at time step j hwj = elevation of the water surface elevation in the reservoir in feet at Where: 16 time step j hdj = equal to the pipe center line elevation as long as the downstream tail water elevation is at or lower than the centre line of the pipe. Otherwise it is equal to the downstream tail water elevation at time j. F. Dam-break maximum breaching outflow verification After the analysis is completed and the hydrograph developed, it is necessary to check the reasonableness of the maximum breaching outflow Qmax. There are a few commonly known techniques to check Qmax: historical predictor equations, parametric models, physically based erosion methods, direct comparison techniques, customized prediction equations, classical equations, FERC recommended equations and current OES recommended equations. The rule of the thumb is to check Qmax obtained in one method with the result of the other techniques. 3.3. Streamflow and reservoir routing The process of routing is used to predict the temporal and spatial variations of a flood hydrograph as it moves through a river reach or reservoir. The effects of storage and flow resistance within a river reach are reflected by changes in hydrograph shape and timing as the floodwave moves from upstream to downstream. Figure 3.3.1 shows the major changes that occur to a discharge hydrograph as a floodwave moves downstream. Routing serves the useful purpose of deriving the hydrographs from rainfall distributions, estimating the water yield at a specified point, developing design elevations of flood 17 embankments, studying the effect of a reservoir on the modification of a flood peak, determining the size of spillway, and other flow related objectives. Figure 3.3.1 - Discharge hydrograph routing effects [20] In general, routing techniques may be classified into two categories: hydraulic routing, and hydrologic routing. Hydraulic routing techniques are based on the solution of the partial differential equations of unsteady open channel flow. These equations are often referred to as the Saint Venant equations or the dynamic wave equations. Hydrologic routing employs the Continuity equation and an analytical or an empirical relationship between storage within the reach and discharge at the outlet. 18 3.3.1. Hydrologic routing techniques [7] Hydrologic routing techniques combine the continuity equation with some relationship between storage, outflow, and inflow. These relationships are usually assumed empirical, or analytical in nature. In its simplest form, the Continuity equation can be written as inflow minus outflow equals the rate of change of storage within the reach: I-O= S t Eq. (3.3.1) Where: I = the average inflow to the reach during t O = the average outflow from the reach during t S = storage within the reach For the purpose of this study, the Modified puls reservoir routing method of HEC1 was selected to conduct reservoir routing. The Modified puls method applied to reservoirs consists of a repetitive solution of the Continuity equation. It is assumed that the reservoir water surface remains horizontal, and therefore, outflow is a unique function of reservoir storage. The Continuity equation, Eq. 3.3.1, can be manipulated to get both of the unknown variables on the left-hand side of the equation: ( S1 O2 S2 + )=( 2 t t + I1 I 2 O1 ) - O1 + 2 2 Eq. (3.3.2) 19 Since “I” is known for all time steps, and O1 and S1 are known for the first time step, the right-hand side of the equation can be calculated. The left-hand side of the equation can be solved by trial and error. This is accomplished by assuming a value for either S2 or O2, obtaining the corresponding value from the storage-outflow relationship, and then iterating until Eq. 3.3.2 is satisfied. However, this iterative procedure can be done using a computer program that would produce fast and accurate results. With this premises, HEC-1 hydrologic routing program was used in the Lang Creek Reservoir Routing Study. 3.3.2. Hydraulic routing techniques [7] In hydraulic routing, the flow is described through a set of hydrodynamic differential equations of unsteady-state flow and simultaneous solutions of those equations lead to determination of the outflow hydrograph. Hydraulic routing is based on the principles of hydraulics in which flow is computed as a function of time at several locations along the conveyance system. It involves complexities of varying degrees. The HEC-RAS computer program uses equations that describe 1-D unsteady flow in open channels, the Saint Venant equations consist of the Continuity equation and the Momentum equation. The solution of these equations defines the propagation of a floodwave with respect to distance along the channel and time. The Continuity equation originates from the law of conservation of mass. In figure3.3.2, q is the lateral inflow rate per unit length of channel. Q and A stands for initial discharge and cross-sectional area. All variables are functions of time and space. 20 q Q- Q x . x 2 A Q+ x Q x . x 2 So Figure 3.3.2 - Control volume for the Continuity equation [7] q y q Fg FH FH A Ff x Figure 3.3.3 - Control volume for the Momentum equation [7] 21 Inflow = (Q - Q x . ) t x 2 Outflow = (Q + + qxt Q x . ) t x 2 The rate of change in volume stored within the element is equal to the change in crosssectional area multiplied by the length of section and time, i.e. Storage change = A xt t According to the conservation law: Input – Output = Rate of change in volume Substitute the inflow, outflow and storage change in the conservation law and divide by x , A Q q t x Eq. (3.3.3) For a unit width b of channel with v average velocity, the continuity equation can be written as: y y v q v y t x x b Eq. (3.3.4) 22 The Momentum equation is the x-direction is produced from a force balance on the river element, according to Newton’s second law of motion. The following three main forces are acting on area A as shown in Figure 3.3.3. yA x x Hydrostatic: FH = Gravity: FH = ASox Friction: FH = - ASfx The rate of change of momentum is expressed from Newton’s second law as: F= d mv dt Where the total derivative of v with respect to t can be expressed dv v v v dt t x After equating the sum of the three external forces and make some simplifications for negligible lateral inflow and a wide channel, the equation can be rearranged to yield a complete Momentum equation: Sf So y v v 1 v x g x g t Eq. (3.3.5) 23 Where = specific weight of water y = distance from the water surface to the centroid of the pressure prism Q = inflow A = Cross-sectional flow area v = average velocity of water x = distance along channel b = water surface width y = depth of water t = time q = lateral inflow per unit length of channel Sf = friction slope So = channel bed slope g = gravitational acceleration The Continuity and Momentum equations are considered to be the most accurate and comprehensive solution to 1-D unsteady flow problems in open channels. Nonetheless, these equations are based on specific assumptions, and therefore have limitations. The assumptions used in deriving the 1-D unsteady flow equations are as follows: [3] a. Velocity is constant and the water surface is horizontal across any channel section. 24 b. All flows are gradually varied with hydrostatic pressure prevailing at all points in the flow, such that vertical accelerations can be neglected. c. No lateral secondary circulation occurs. d. Channel boundaries are treated as fixed; therefore, no erosion or deposition occurs. e. Water is of uniform density, and resistance to flow can be described by empirical formulas, such as Manning’s and Chezy’s equation. f. Solution of the full equations is normally accomplished with an explicit or implicit finite difference technique. The equations are solved for incremental times (t) and incremental distances (x) along the waterway. 25 Chapter 4 MODELING AND SENSITIVITY ANALYSIS METHODOLOGIES 4.1. Data gathering and processing Most of the original data gathered and compiled by the dam owner were used in this sensitivity analysis. The main purpose of gathering data in creating a modeling methodology was for defining the size, type, elevation and storage relations of the subject dam, and the geometries of the downstream river reaches. Data gathered for modeling were grouped into the following categories: Reservoir characteristics: The reservoir characteristics consist of reservoir storage elevation curve and reservoir surface area elevation curve (See Figure 4.3.2, Stage – Storage Capacity – Surface Area Curves), reservoir storage capacity in acre-feet at normal water storage pool elevation, surface area in acres at normal water storage pool elevation. The summary of Lang Creek reservoir and dam characteristics were presented in Table 2.2.1. Dam characteristics: This category includes data about name of dam, dam type, dam size, location of the dam, elevation of downstream toe of dam, design water storage pool elevation, maximum flood surcharge elevation, spillway crest elevation, crest of dam elevation, and height of the dam measured from downstream toe to the crest, and category of the dam. See Table 2.2.1, for the detail of Lang Creek reservoir and dam characteristics. General Information: This category of data is for general information purposes. It includes jurisdictions of the dam owner (city, town, and county area), geographic 26 information, watershed boundary, and others. See Chapter Two for detail of geographic information. Downstream Information: Data gathered under this category includes bank stations, reach stations, downstream developments, cross section plots, Manning roughness coefficients, and other pertinent hydrostructures. See appendix B for detail information on river stations and bank stations, and other hydraulic properties. Inflow Hydrograph: The inflow hydrograph data category includes the 10-year 24-hour flood events hydrograph provided by the dam owner. [19] In addition, it includes a modified “sunny day” hydrograph used to breach the Lang Creek Dam. See appendix A – for Lang Creek dam breach HEC-1 inflow data. 4.2. Sensitivity analysis flow chart The analysis of dam breach involved using different computer application software. The software was used to model hydrologic and hydraulics of different waterways that include natural streams, man-made canals, reservoirs and others. Depending on the level of study and extent of expected accuracy, modelers can select appropriate type of modeling software. In this study, two types of application software were used to perform the dam breach sensitivity analysis at the dam site and its downstream reaches. Dam-break analysis assumed in this study caused sever breaching outflow hydrograph at the dam site, this study also incorporated the breaching outflow hydrograph routing through its downstream channel. In order to meet this scope of study, 27 the Lang Creek Dam and its downstream river was used as a testing dam and was modeled in two components, reservoir and river components. The reservoir component of the study was studied using HEC-1. The river component was studied using HEC-RAS. A sensitivity analysis flow chart using the Lang Creek Dam and its downstream river as a testing basis was presented in Figure 4.21. The flow diagram described and presented the overall modeling approaches and assumed scenarios. Also, it showed the matrices used to analyze the relative importance of one or more of the parameters which were thought to have significant influences on the dam-break inundation phenomenon. 4.2.1. HEC-1 modeling As shown in Figure 4.2.1, HEC-1 computer program was used for half of the sensitivity analysis study using the Lang Creek Dam as a testing basis. The model assumes a single inflow to the reservoir of the Lang Creek Dam in addition to defining the physical characteristics of the dam and reservoir. As indicated on the flow diagram, five different scenarios of time to dam failure in hours (TFH) were assumed to evaluate the sensitivity of outflow hydrographs to these changes. See Appendix A for the HEC-1 inputs and outputs data for this part of the study. Additionally, four side slopes of dam breach were assumed to examine their responses of peak outflows at dam for the aforementioned changes. The combined effects of side slope and time to dam failure in hours changes on peak outflows at the dam were also evaluated using HEC-1 hydrologic modeling software. Moreover, the outputs of HEC-1 modeling, combinations of the five time to dam failure in hours (TFH1-5) scenarios and a single side slope of breach (SS3) resulted in five dam-break outflows 28 hydrographs, which were used as input hydrographs to HEC-RAS for studying the relationships among river flow parameters. See Appendix A for the HEC-1 inputs and outputs data for this part of the study. Also, see Chapter five for discussions and summary of multi-plan computer outputs of the modeling. 4.2.2. HEC-RAS modeling As shown in the second half of the flow diagram, the HEC-RAS hydraulic modeling software was used to execute unsteady flow river routing of dam breach hydrographs through the downstream channel. The five dam-break outflow hydrographs generated from HEC-1 were the prime inputs in this modeling. In HEC-RAS modeling, each routing hydrograph was varied with five different Manning’s n values and resulted in twenty five computer runs. The outputs were analyzed to evaluate sensitivity of downstream peak flows to change in Manning’s n values for a given TFH. See Figure 4.2.1 for the testing scenarios matrix, and see Appendix B for the HEC- RAS input and output data for this part of the study. Additionally, three channel bed slopes were tested in the modeling under TFH1 (0.25hr to dam failure) dam-break hydrograph. This matrix resulted in five computer runs. The relationships among peak flows and change in channel bed slope for a specified TFH were investigated for each scenario. See Figure 4.2.1 for the testing scenarios matrix, and see Appendix B for the HEC- RAS inputs and outputs data for this part of the study. 29 Gathering Data Reservoir Routing TFH 1 TFH 2 TFH 3 TFH 4 SS1 TFH 5 SS2 SS3 SS4 Q1&TFH1 – relation, given SS3 Q2&TFH2, relation, given SS3 Q3&TFH3,relation, given SS3 Q4&TFH4,relation, given SS3 Q5&TFH5,relation, given SS3 SS1 (Q1-5TFH1-5) SS2 (Q1-5TFH1-5) SS3 (Q1-5TFH1-5) SS4 (Q1-5TFH1-5) River Routing CHS1 N1 N2 N3 N4 N5 CHS2 CHS0riginal CBS3 Q1-5, & TFH15, - relation, given N1 & SS3 Q1-5, & TFH15,- relation, given N2 & SS3 Q1-5, & TFH15, relation, given N3 & SS3 Q1-5, & TFH15, relation, given N4 & SS3 Q1-5, & TFH15, relation, given N5 & SS3 Notes: Q1-5: Number of hydrographs produced based on a given relation, i.e., outflow hydrograph 1 2 …..5 TFH1-5: Time to dam failure in hours, TFH 1 to 5 = 0.25, 0.5, 1.0, 2.0, and 3.0 hrs respectively SS1-4: Side slope of breach, SS 1 to 4 = 0.25, 1.0, 2.0, & 2.5 respectively Manning coefficient N 1 to 5 = 0.04, 0.035, 0.0375, 0.045 & 0.05 respectively. CBS – channel bed slope CBS 1 to 4 = 0.95So, 0.975So, 1.025So, and 1.05So respectively Figure 4.2.1 – Sensitivity analysis flow chart CBS4 CBS1, (N1, Q1TFH1) CBS2, (N1, Q2TFH1) CBS3, (N1, Q3TFH1) CBS4, (N1, Q4TFH1) CBSoriginal, (N1, Q5TFH1) 30 4.3. Dam breach analysis procedures The parameters of dam breach depend on type of the dam and mode of failure. The shape and duration of the breach, together with the size of the dam and the reservoir, would determine, to a great extent, the characteristics of the breach outflow hydrographs. Overtopping mode of failure was assumed in this study and modeled by using the broadcrested weir equation. The dam-break breaching elevation was assumed at 6 inches above the top of the dam [12]. Hydraulic analysis of dam breach includes two primary tasks, the prediction of the reservoir outflow hydrograph and the routing of that hydrograph through the downstream valley. 4.3.1. Predicting the outflow hydrographs For flood hydrograph estimation, the breach modeled by defining acceptable dam breach parameters was the core of this project. Predicting the outflow hydrographs at the dam location was done using HEC-1 under different scenarios. See Appendix A for HEC1 input data and different scenarios. The process of predicting the outflow hydrograph was a multi-steps approach and began with defining the reservoir characteristics, physical description of Land Creek Dam, and its detailing breach characteristics. 4.3.1.1. Describing reservoir characteristics Description of reservoir geometry was the first step in the analysis of dam breach. The original data taken from the dam owner were input in the HEC-1 model. See Appendix A for input data. Collected data included reservoir surface area rating curves, stage-storage capacity – surface area curves, and spillway rating curve. See following Figure 4.3.1 and Figure 4.3.2. 31 Figure 4.3.1 – Lang Creek spillway rating curve and area-capacity curves [19] Figure 4.3.2 – Stage – storage capacity – surface area curves [19] 32 4.3.1.2. Identifying physical descriptions of dam This step included the identification of dam height, dam crest width, spillway elevation and width, weir flow coefficient, and coefficient of discharge. In this study, data about the physical characterizes of the Lang Creek Dam were imported from the dam owner’s dam inundation mapping report [21] and used as input in HEC-1 modeling. See Table 2.2.1 - Lang Creek Reservoir and Dam Characteristics, and Appendix A – HEC-1 input data. 4.3.1.3. Determining inflow hydrograph to the reservoir This step involved deriving an inflow design flood from a probable maximum precipitation. The inflow design flood is expected to cause the dam to breach in order to analyze the worst case of dam breach analysis. For Lang Creek Dam, the inflow design flood hydrograph provided by the dam owner, 10-year 24 hours flood events, didn’t raise reservoir’s surface water elevation to overtop the dam.[21] As a result, modified hydrograph was used in addition to setting the initial water surface elevation in the reservoir equal to the dam crest elevation. 4.3.1.4. Estimating dam breach characteristics The dam breach core characteristics are: a. Shape of the breach: Since Lang Creek Dam is an earth-fill dam, a trapezoidal shape of breach was assumed in this study. See Table 2.2.1, Lang Creek Dam and reservoir characteristics, and Appendix A for input data and Table 4.3.1 Dam-break Breaching Parameters. b. Breach bottom elevation (Hb): By assuming the possible worst case, the breach 33 bottom elevation was set to be equal to the reservoir minimum elevation. See Appendix A HEC-1 input data. c. Average breach bottom width (b): In this modeling, the breach bottom width was estimated based on empirical formula provided by “DAMBRK Modeling Methodology”. [12] The breach bottom width remained the same in all cases. For well constructed earthen dam “b” is given by: 2Hd b 5Hd Where: Hd: height of the dam. d. Side slope of breach (SS): the slope parameter Z or SS identifies the side slope of the breach, i.e., 1 vertical: Z horizontal. The Z value ranges from 0.25 to 2.0 for earthen dam [8] [12]. Its value depends on the angle of repose of the compacted and wetted materials through which the breach develops. A trapezoidal shape was specified with various combinations of Z values. The four Z values, 0.25, 1.0, 2.0 and 2.5 were used to simulate reservoir routing and examining the relationships between peak breaching outflows and change in Z values at the dam site. For multi-variables or parameters of dam breach sensitivity analysis, the analysis flow chart was presented in Figure 4.2.1 while the inputs and outputs of breaching parameters were presented in Table 4.3.1. e. Time to Failure in hours (TFH): Based upon NWS (National Weather Service) recommendation, the typical TFH for earthen dam is given by: 0.3 TFH 3.0 in hours, 34 Where: TFH = time to dam failure in hours In this study, five different TFH were used to analyze the sensitivity of peak breaching outflows at the dam site due to change in TFH. As shown in the schematic modeling diagram Table 4.3.1, five different TFH: 0.25, 0.5, 1.5, 2.0, and 3.0 hour were used to simulate five breaching scenarios. Additionally, these five TFH were simulated for each Z value and resulted in twenty different peak breaching outflows. The relationship among these three parameters, peak flow, TFH and Z were further analyzed to compare the result with existing condition. See Appendix A for input data. Table 4.3.1 summarized the inputs and outputs of dam-break breaching parameters. Table 4.3.1 - Summary of inputs and outputs of sensitivity analysis Resevoir Inflow TFH t1 t2 t3 IDF t4 t5 Z value SS1 SS2 SS3 SS4 HEC-1 HEC-1 Output - one Output - two (Qsst) (Qsst) Q11 Q21 Q31 Q31 Q41 SS1 SS2 SS3 SS4 Q12 Q22 Q32 Q42 SS1 SS2 SS3 SS4 Q13 Q23 Q33 Q43 SS1 SS2 SS3 SS4 Q14 Q24 Q34 Q44 SS1 SS2 SS3 SS4 Q15 Q25 Q35 Q45 HEC-RAS inflow data (QSSt) Q31 Q32 Q32 Q33 Q33 Q34 Q34 Q35 Q35 Manning n HEC-RAS output - one n1 n2 n3 n4 n5 n1 n2 n3 n4 n5 n1 n2 n3 n4 n5 n1 n2 n3 n4 n5 n1 n2 n3 n4 n5 Q11 Q12 Q13 Q14 Q15 Q21 Q22 Q23 Q24 Q25 Q31 Q32 Q33 Q34 Q35 Q41 Q42 Q43 Q44 Q45 Q51 Q52 Q53 Q54 Q55 HEC-RAS Input data (QSStn) Channel bed Slope (CBS) Q311 CBS0riginal CBS1 CBS2 CBS3 CBS4 Q321 Q331 Q341 Q351 HEC-RAS Output - two (QSStnCBE) Q3110 Q3111 Q3112 Q3113 Q3114 35 4.3.2. Routing breach outflow hydrographs through downstream reaches Dam-break flood hydrograph is a dynamic and unsteady phenomenon. Therefore, the preferred approach is to utilize a fully developed Unsteady State flow routing model. The HEC-1 Flood Hydrograph package provides the capability to compute and route the breaching outflow hydrographs through downstream natural stream, but its channel routing is to hydrologic methods. In order to accurately model the flows, the unsteady flow computer program, HEC-RAS was used to route breaching outflow hydrographs through natural waterways. The implicit formulation of the St. Venant equation is well-suited from the standpoint of accuracy for formulating unsteady flows in a natural channel. Therefore, HEC-RAS was chosen for unsteady state flood routing, and this technique simultaneously computes the discharge, water surface elevation, and velocity throughout the river reach. The following parameters are crucial in running HEC-RAS to perform unsteady flow routing: 4.3.2.1. Defining channel geometry and boundary conditions During modeling of the downstream channel of the Lang Creek Dam using HECRAS, the first step was to establish the external boundary conditions. The upstream boundary was selected at a location such that it was independent of the downstream conditions. The downstream boundary was selected at a location that was independent of flow conditions below the boundary. The last downstream cross section was set at a reasonable distance and a normal depth was chosen to define the downstream boundary conditions. [3] 36 Figure 4.3.3 - Schematic of single river with number After the routing reach was established by the boundary locations, cross sections were obtained to represent the reaches. Cross section locations were measured from upstream to downstream. The cross sections were numbered sequentially from upstream to downstream as shown in Figure 4.3.3. Next, the initial conditions at each cross section were established. For the purposes of this study, default values of expansion and contraction coefficients were used throughout the unsteady state analysis. The program by default assigns a value of 0.3 and 0.1 for expansion and contraction coefficient, respectively. This decision was made due to geometric similarities among cross sections and Manning’s roughness coefficients provided by the dam owner. 4.3.2.2. Selecting Manning coefficients, “n” values 37 Manning’s coefficient n is used to describe the resistance to flow due to channel roughness caused by sand/gravel bed-forms, bank vegetation and obstructions, bend effects, and circulation-eddy losses and so on. The Manning’s coefficient n values provided by the dam owner for the channel reaches between specified cross-sections were used as a reference basis of the sensitivity analysis. In unsteady state river routing simulation, results were often very sensitive to the Manning n values. Selection of the Manning n was aimed to reflect the influence of bank and bed materials, channel obstructions, irregularity of the river banks, especially vegetation, and to minimize potential biasness of the results. Table 4.3.2 – Selected Manning coefficients, “n” values River station (miles) 0 0.91 1.25 1.69 2.06 2.49 3.19 3.76 4.67 5.35 6.49 8.5 Dam owner n – value 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 12.5% decrease 0.035 0.035 0.035 0.035 0.035 0.035 0.035 0.035 0.035 0.035 0.035 0.035 5.0% decrease 0.0375 0.0375 0.0375 0.0375 0.0375 0.0375 0.0375 0.0375 0.0375 0.0375 0.0375 0.0375 5.0% increase 0.045 0.045 0.045 0.045 0.045 0.045 0.045 0.045 0.045 0.045 0.045 0.045 12.5% increase 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 Note: Left, right and main channel are assumed to have the same manning values. Based on field investigations and references for selecting the Manning coefficients, Chow (1959)[15] and Henderson(1966)[14], five “n” values were used to study the relationships among peak flow, time to failure (TFH), and Manning n at two specified locations along the downstream river. 4.3.2.3. Dam-break outflow hydrographs Five different outflow hydrographs derived from five TFH during HEC-1 analysis were used as inflow hydrographs for the downstream river routing. As shown on flow 38 chart Figure 4.3.1 and Table 4.3.1, each breaching outflow hydrographs was in conjunction with five different Manning n values and produced twenty five independent computer runs. See Appendix A for dam-break flood hydrographs. Additionally, the same dam-break breaching outflow hydrographs were used to study the sensitivity of peak flows due to change in channel bed slopes. 4.4. Flood hydrograph routing Flood routing can predict the temporal and spatial variations of a flood wave through a river reach and/or reservoir. This sensitivity analysis consisted of reservoir and downstream channel. The hydrologic routing and hydraulic routing were used to conduct flood routing through the reservoir and downstream channel. 4.4.1. Hydrologic routing The hydrologic routing involved the balancing of inflow, outflow, and storagedischarge relation through use of the continuity equation. This application of hydrologic routing was used for reservoir routing. The reservoir component initiated by receiving upstream inflows and routed these inflows through a reservoir using Storage Routing Methods. [2] Storage Routing Methods in HEC-1 required data that define the storage characteristics of the routing reservoir. The 10-year 24-hour inflow hydrograph to the reservoir provided by the dam owner did not cause the reservoir’s water surface elevation to go above the top of the dam. In order to carry out this project, the IDF was modified and used artificial inflows with the water surface just before failure set to the crest elevation of the dam. In addition 39 to IDF, the shape of breach, average width of breach, side slope of breach, breaching time, and other dam breach parameters were identified and predefined for generating the breaching outflow hydrographs by HEC-1 computer software. Lang Creek Reservoir Dam Dam Reach 1 Distance 0.91mile RC1 Reach 2 Distance 0.34 mile RC2 Figure 4.4.1 – Schematic of Lang Creek reservoir and reaches Figure 4.4.1 is a schematic of Lang Creek reservoir and reaches used in HEC-1 reservoir routing. As shown in Figure 4.4.1, two reaches were defined at the immediate downstream of the dam which helped to increase the accuracy of the breaching outflow hydrographs at the dam site. [3] The HEC-1 hydrologic routing subroutine was applied in modeling and performing the Lang Creek dam-break parameters sensitivity analysis. See Appendix A for detail input parameters and assumptions. 4.4.2. Hydraulic routing 40 Dam-break outflow hydrographs were used as inputs to the river routing through the immediate downstream reaches of dam site. By the very nature, dam-break outflow hydrographs are highly unsteady flows that require a full unsteady flow routing method. In order to fully define an unsteady hydrograph, St. Venant equations should be used to analyze the routing floodwave propagation. Thus, the HEC-RAS hydraulic routing subroutine was adopted to route the dam-break outflow hydrographs though the Lang Creek Channel. In order to carry out the hydraulic routing through the Lang Creek, the downstream cross sections data were imported from the dam owner study that included all cross sections geometries, Manning coefficients, reach lengths and boundary conditions. The boundary conditions included all of the external boundaries of the system, as well as the internal locations and set the initial flow and storage area conditions at the beginning of the simulation. Since the Lang Creek downstream channel was modeled as an open-ended reach, the downstream boundary condition was set as a normal depth. As recommended in HEC-RAS user manual for this option of boundary condition, the last cross section was placed far enough such that any errors it produced would not affect the results at the study reach. [3] See Figure 4.4.2- for the detail information about downstream channel geometries. Lang_Creek_DAMBRK Sensitivity Analysis Plan: 1) S-orig Flow: 8.5 8 7.59 7.25 Legend WS Max WS Ground Bank Sta 6.81 6.44 6.01 5.58 5.31 4.74 3.83 3.15 2.01 0 Figure 4.4.2 – 3D-view of downstream channel geometries 41 42 Chapter 5 RESULTS AND DISCUSSIONS OF SENSITIVITY ANALYSIS The sensitivity analysis using Lang Creek Dam as a testing basis involved testing a number of dam breach parameters. The parameters defined for the reservoir and river component of the analysis were prepared based on existing data and some empirical formulas developed by Fread and Froehlich. With the aid of hydrologic and hydraulic modeling software, reservoir and river flow routings were carried out to establish relationships among the characteristics influencing a peak flow at the dam and specified location in the downstream. The findings were discussed in the following sub-sections. Maximum breach discharge (Qmax), breach development time in hours (TFH), and side slope of breach (SS or 1: Z) were the three principal parameters analyzed at the dam site in the first half of this study, reservoir component. The second half, river component, of sensitivity analysis focused on identifying and analyzing the influences of change in downstream reach parameters, i.e. Manning coefficients and channel bed slopes, on peak flows for a given breaching outflow hydrograph. 5.1. Time to dam failure (TFH) versus maximum breach discharges (Qmax) for a given side slope of breach The HEC-1 dam-break subroutine was used for testing the sensitivity between TFH and Qmax. The results of testing were summarized in Table 5.1.1-2, and appendix A for the detail outputs of HEC-1 dam-break subroutines. 43 Table 5.1.1 – Maximum discharge and time to dam failure at dam site Time of breach development (hr) Side slope of breach (1:Z) Maximum dicharge (cfs) 0.5To To 2To 4To 6To 1 : Zo 1 : Zo 1 : Zo 1 : Zo 1 : Zo 25893 14172 7832 4336 3038 Note: To and Zo represent typical values and equal to 0.5hr and 2 respectively. Table 5.1.2 – Percent change in max discharge and time to dam failure at dam site Time of breach development (hr) Side slope of breach (1:Z) Change in max discharge (%) 0.5To To 2To 4To 6To Zo Zo Zo Zo Zo 82.7 0.0 -44.7 -69.4 -78.6 Note: To and Zo represent typical values and equal to 0.5hr and 2 respectively. In this sensitivity analysis, five different TFH were used for HEC-1 dam-break computer runs and resulted in five dam breaching outflow hydrographs. Figure 5.1.3 – five dam breach hydrographs for a given side slope of breach (1:2) with five different TFH. Also, Appendix A showed the detail of HEC-1 dam-break outputs, and Table 5.1.1 showed the maximum breach discharge varied with TFH with a given side slope Z. Based on results in Table 5.1.1-2, the peak discharge decreased when TFH increased. A 50 % reduction in TFH (To to 0.5To) resulted in 82.7 % increase in peak discharge at the dam site. Whereas, a 500 % increase (To to 6To) in TFH resulted in 78.6 % reduction in peak discharge at the same site. The rate of increase in peak flow relative 44 to change in TFH was very drastic compared to the rate of decrease which was slightly steady as shown in the above table. This trend showed in the following figures and a best fitted equation. Breach Development time and Maximum Discharge Maximum Discharge (cfs) 30000 25000 20000 15000 10000 5000 0 0 0.5 1 1.5 2 2.5 3 3.5 Time to dam failure (hr) Figure 5.1.1 – Time to dam failure and maximum discharge at dam site Percent change in max discharge vs time to dam failure 100.0 Change in max flow (%) 80.0 60.0 40.0 20.0 0.0 -20.0 0 0.5 1 1.5 2 2.5 3 3.5 -40.0 -60.0 -80.0 -100.0 Time to dam failure (hr) Figure 5.1.2 – Percent change in max discharge and time to dam failure at dam site 45 Figure 5.1.1 and 2 depicted graphical relationships between the two parameters. An equation developed based on best fitted trend line showed existence of non-linear function between TFH and Qmax for a given side slope of breach at dam site. Qmax = 7836TFH-0.86 Where: Qmax: maximum discharge at the dam TFH: time to dam failure in hours The equation revealed the qualitative influence of change in dam breach development time on the maximum discharge at dam site. As shown above and mentioned in Chapter Three section 3.2.5, estimation of breaching hydrograph was a multi-variable analysis that involved using empirical formula, historical data and a lot of personal experience. Despite all of these, the above results confirmed that predicting dam breach outflow hydrographs was dependent on and sensitive to a minor change in dam breach development time. The finding of this sensitivity analysis agrees with the dam breach study references such as those written by Fread and Froehlich [9] [11], and this verifies the results. Outflow hydrographs for a given time to dam failure @ dam 30000 25000 Outflow (cfs) 20000 15000 10000 5000 0 0 20 40 60 80 100 120 140 Time (x3mins) 0.5To To 2To 4To 6To Figure 5.1.3 - Five dam breaching outflow hydrographs for a given side slope 46 47 5.2. Side slope of breach (SS) versus maximum breach discharges (Qmax) for a given time to dam failure The HEC-1 dam-break subroutine was applied and resulted in the following summarized data for the two variables, Qmax and SS, at the dam provided that TFH remained the same. Appendix A presented the detail outputs of HEC-1 reservoir routings. Table 5.2.1 – Side slope of breach and maximum discharge at dam site Time of breach development (hr) To To To To Side slope of breach (1:Z) 0.125Zo 0.5Zo Zo 1.25Zo Maximum dicharge (cfs) 14654 14399 14172 14085 Note: To and Zo represent typical values and equal to 0.5hr and 2 respectively. Table 5.2.2 – Percent change in max discharge and side slope of breach at dam site Time of breach development (hr) To To To To Side slope of breach (1:Z) 0.125Zo 0.5Zo Zo 1.25Zo Change in max discharge (%) 3.4 1.6 0.0 -0.6 Note: To and Zo represent typical values and equal to 0.5hr and 2 respectively. The shape parameter (Z) identified the side slope of the breach, i.e., 1 vertical: Z horizontal. For this study a trapezoidal shape of breach was assumed, and breach bottom elevation was set to remain constant in all cases as discussed in Chapter Four section 4.3.1.4. The sensitivity analysis between side slope of breach and maximum discharge was done based on the above mentioned conditions. Results in Table 5.2.1-2 indicated that the maximum discharge increased as the side slope of breach decreased at the dam site. An 87.5% decrease in side of slope of 48 breach (Zo to 0.125Zo) resulted in 3.4% increase in maximum discharge at the dam relative to original data. Whereas, a 25% increase in SS (Zo to 1.25Zo) value produced 0.6% decrease in maximum discharge at the dam site. The rate of increase in peak flow for a given percent change in SS was higher compared to the rate of decrease as shown in the above tables. However, the increments of percent change in peak flow were very small compared to the corresponding percent changes in SS. This observation was further illustrated in Figure 5.2.1-2. Max discharge vs side slope of breach 14700 Max discharge (cfs) 14600 14500 14400 14300 14200 14100 14000 0 0.5 1 1.5 2 2.5 Side slope of breach (1:Z) Figure 5.2.1 – Side slope of breach and maximum discharge at dam site 3 49 Percent change in max discharge vs side slope of breach 4.0 change in max discharge (%) 3.5 3.0 2.5 2.0 1.5 1.0 0.5 0.0 -0.5 0 0.5 1 1.5 2 2.5 3 -1.0 Side slope of breach (1:Z) Figure 5.2.2 – Percent change in max discharge and side slope of breach at dam site Figure 5.2.1 and 2 depict the influence of side slope of breach on maximum discharge at the dam location. As the Z value decreased or the side slope of breach became steeper, the maximum discharge at the dam increased at a steady rate as shown in the above figures. It was obvious that when the Z value increases or breach slope becomes flatter, the area of breach increases. The wider conveyance area means decrease in velocity for a given flow. The rate of increase or decrease in conveyance area with respect to velocity determined the rate of outflow. However, the results of this sensitivity analysis indicated that the maximum discharge at the dam site decreased as the Z values increased under the condition, TFH was remained constant. Further qualitative analysis of the relationship between the two variables is shown in the following equation. The best fit equation developed from Figure 5.2.1-2, and it described the sensitivity of peak discharge to Z values and defined as follows: 50 Qmax = 14339Z-0.0169 With R2 = 0.9724 Where: Qmax: maximum discharge at the dam Z: side slope of dam breach The best fit equation showed estimated non-linear relationship between the two parameters, and this evaluation agreed with the coefficient of determination R2 which indicated the level of the equation’s accuracy. Similarly, many literatures like US Army Crops Engineering Manual 1110-2-1420[18], FLDWAV [10] and DAMBRK [8] manuals consistently agreed with the finding of this study. These literatures confirmed that the aforementioned results and findings are acceptable. 5.3. Relative effects of time to dam failure (TFH) and side slope of breach (SS) on maximum breach discharges (Qmax) The HEC-1 dam-break subroutine was applied to test the sensitivities between TFH and Qmax with given SS, and SS and Qmax with given TFH at the dam site. Appendix A presented detail outputs of HEC-1 dam-break subroutines. The summary results were tabulated – Table 5.3.1 – 2. 51 Table 5.3.1 – Effects of time to dam failure and side slope on peak flows at dam Breach hydrograph based on (hr) 0.125Zo Side slope of breach, SS (1: Z) 0.5Zo Zo 1.25Zo Peak flow (cfs) 0.5To 26704 26285 25893 25747 To 14654 14399 14172 14085 2To 8089 7956 7832 7787 4To 4450 4395 4336 4320 6To 3113 3074 3038 3024 Note: To and Zo represent typical values and equal to 0.5hr and 2 respectively. Table 5.3.2 – Percent change in max discharge for a given time to dam failure and side slope of breach at dam site Breach hydrograph based on TFH (hr) 0.5To To 2To 4To 6To Side slope of breach, SS (1: Z) 0.125Zo 0.5Zo Zo 1.25Zo Change in peak flow (%) relative to typical value 88.4 85.5 82.7 81.7 3.4 1.6 0.0 -0.6 -42.9 -43.9 -44.7 -45.1 -68.6 -69.0 -69.4 -69.5 -78.0 -78.3 -78.6 -78.7 Note: To and Zo represent typical values and equal to 0.5hr and 2 respectively. Table 5.3.1 and 5.3.2 show how the peak discharge at the dam site reacted to change in the two parameters, time to dam failure and side slope of breach. The tables show four conditions of side slope of breaches. Each side slope of breach was combined with five time to dam failure and produced five maximum discharges at the dam site. This analysis was done four times for the four Z values as shown in the above tables. Results in Table 5.3.1 – 2 revealed that the peak discharge increased by 88.4% when the time to dam failure reduced by 50% whereas side slope of breach decreased by 87.5%. On the other hand, a 500% increase in time to dam failure (To to 6To) and 25% increase in side slope of breach (Zo to 1.25Zo) resulted in 78.7% reduction in maximum 52 discharge at the dam site. Similarly, a 50% decrease in time to dam failure and a 25% increase in side slope of breach resulted in 81.7% increase in maximum discharge. Maximum discharge vs time to dam failure for given side slopes of breach 30000 27500 25000 Maximum discharge (cfs) 22500 20000 17500 15000 12500 10000 7500 5000 2500 0 0.00 1.00 2.00 0.125Zo 3.00 Time to dam failure (hrs) 0.5Zo 4.00 Zo 5.00 6.00 1.25Zo Figure 5.3.1 – Effects of time to dam failure and side slope on peak flows at dam site Percent change in peak flow vs time to dam failure for given side slopes of breach 100.0 Change in maximum discharge (%) 80.0 60.0 40.0 20.0 0.0 0.00 -20.0 1.00 2.00 3.00 4.00 5.00 6.00 -40.0 -60.0 -80.0 -100.0 0.125Zo Time to dam failure (hrs) 0.5Zo Zo 1.25Zo Figure 5.3.2 – Percent change in max discharge versus time to dam failure for specified side slopes of breach at dam site 53 Further graphical sensitivity analysis was done to determine a controlling parameter that influenced the maximum discharge at the dam site the most. Figure 5.3.1 and Figure 5.3.2 illustrate the trend existed between the parameters at the dam site. The two figures depicted that the change in side slope of breach resulted in closely spaced graphs for a wide range of change in time to dam failure. This implied that the maximum discharge at the dam site was highly sensitive to the TFH than Z. 5.4. Manning coefficient versus peak flows in existing channel for specified time to dam failure The downstream river routings were carried out by HEC-RAS computer program for five dam-break breaching outflow hydrographs under five TFH scenarios with side slope factor Z equal to two. The HEC-RAS unsteady flow routing was run to investigate the overall impacts of change in time to dam breach on the downstream reach peak flows for given manning coefficients at specified locations between reaches. Appendix B presented the detail inputs and outputs for downstream channel routing. This analysis was executed based on existing Manning coefficients and channel geometries data provided by the dam owner. 54 Table 5.4.1 – Downstream peak flows for five TFH breaching outflow hydrographs River Sta. (miles) 0.5To Qmax (cfs) 25893 20271.23 18709.37 17420.82 15205.26 14000.91 12928.92 12222.29 11761.45 10388.74 8813.7 7942.21 6563.12 0 0.5 0.91 1.25 1.69 2.06 2.49 2.92 3.19 3.76 4.67 5.35 6.49 Assumed time to dam failure for inflow hydrographs To 2To 4To 6To Peak flow (Qmax) Qmax (cfs) Qmax (cfs) Qmax (cfs) Qmax (cfs) 13944 7766 4314.33 3031 12251.44 7337.21 4225.15 3000.67 11928.2 7235.32 4205.49 2991.54 11683.38 7194.03 4194.05 2986.84 11294.61 7070.76 4181.41 2982.24 10994.26 7002.19 4170.12 2978.64 10597.88 6911.79 4156.59 2973.61 10247.64 6830.81 4147.32 2970.12 10002.27 6783.89 4134.38 2966.26 9229.91 6594.76 4080.54 2948.3 8121.33 6238.07 3996.64 2919.48 7409.53 5951.63 3933.75 2886.42 6280.88 5366.47 3710.33 2812.73 Manning coeff. (original value, No) 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 Note : To represents original time to dam failure value equal to 0.5hr. Peak flow profiles vs River Sta. for a given inflow hydrograph 30000 Peak flow (cfs) 25000 20000 15000 10000 5000 0 0 1 2 3 4 5 6 7 River station (miles) 0.5To To 2To 4To 6To Figure 5.4.1 – Peak flow profiles for five TFH breaching outflow hydrographs As shown in Table 5.4.1, five different unsteady flow routings were done using HEC-RAS to produce peak flows at respective river stations. Similarly, Figure 5.4.1 shows the five peak flow profiles generated from five breaching outflow hydrographs that had five different dam breach development times at the dam site. The tabular and 55 graphical analyses of the outputs revealed that the peak flows starting at the dam run in a similar manner all the way to downstream reach end. It was obvious that smaller time to dam failure resulted in a higher dam breach hydrograph as discussed above, and the maximum discharge at the dam sustained its peak throughout the river routing. The second part of this analysis was done to evaluate the relationship between Manning coefficients and peak flows for a given TFH breaching outflow hydrograph. According to the dam owner data, the downstream left, main and right channel sections of the whole reach had the same Manning coefficients. This analysis assumed four additional Manning coefficients based on reasonable assumptions and literature reviews. Appendix B presented HEC-RAS inputs data and outputs for different Manning values. The following tables and figures showed the influence of change in Manning coefficient on the peak flows along the river. As shown in Table 5.4.2 and Figure 5.4.2, the peak flow profiles starting from the dam site down to the downstream end of the channel showed smooth transitions that implied the gradual effects of change in Manning value. The sensitivity analysis results indicated that the HEC-RAS run with a smaller Manning coefficient resulted in higher peak flows for the entire reach length as shown in the Table and Figure 5.4.2. 56 Table 5.4.2 – Peak flows at different river stations for five Manning values Assumed manning coeff. 0.9375No No Peak flow (Qmax) Qmax(cfs) Qmax(cfs) 25893.0 25893.0 20751.1 20271.2 18791.6 18709.4 17692.7 17420.8 15565.0 15205.3 14423.9 14000.9 13401.8 12928.9 12618.6 12222.3 12174.7 11761.5 10877.3 10388.7 9209.7 8813.7 8290.5 7942.2 6862.9 6563.1 5390.4 5152.0 0.875No River Sta. (miles) Qmax(cfs) 25893.0 20678.3 18403.1 17635.6 15740.9 14821.0 13750.3 12769.0 12378.7 11235.6 9592.9 8627.9 7162.3 5634.7 0 0.5 0.91 1.25 1.69 2.06 2.49 2.92 3.19 3.76 4.67 5.35 6.49 8.5 1.125No 1.25No Qmax(cfs) 25893.0 20443.6 18234.8 16934.8 14642.8 13368.3 12130.4 11462.9 10994.8 9622.6 8139.5 7315.8 6018.4 4751.6 Qmax(cfs) 25893.0 20061.4 17632.1 16325.2 13960.7 12674.9 11396.6 10720.6 10291.8 8965.3 7528.3 6780.0 5551.1 4400.4 Note : No represent original manning coeff equal 0.04. Peak flow along river for a given manning value 30000.0 Peak flow (cfs) 25000.0 1.25No 20000.0 1.125No 15000.0 No 0.9375No 10000.0 0.875No 5000.0 0.0 0 1 2 3 4 5 River station (miles) 6 7 8 9 Figure 5.4.2 – Peak flow profiles based on five different Manning values Further analysis was done to investigate the percent change in peak flows for a given change in Manning coefficient relative to baseline flow generated from existing Manning coefficients. Table and Figure 5.4.3 depict the summary of the findings. The 57 results showed a similar trend of increasing in percent change in peak flow down to downstream end of the channel. As shown in Table 5.4.3, a 12.5 % decrease in Manning coefficients resulted in a change in peak flows that ranged from 0% at the upstream and 9.4% at the downstream end of the channel. Whereas, a 25% increase in Manning coefficients resulted in a change in peak flows that ranged from 0% at the upstream and 14.6% at the downstream. Table 5.4.3 – Percent change in peak flows for given Manning values River Sta. (miles) Assumed manning coeff. 0.9375No No Percent change in peak flow @ given sta. Qmax(%) Qmax(%) 0.0 0.0 2.4 0.0 0.4 0.0 1.6 0.0 2.4 0.0 3.0 0.0 3.7 0.0 3.2 0.0 3.5 0.0 4.7 0.0 4.5 0.0 4.4 0.0 4.6 0.0 4.6 0.0 0.875No Qmax(%) 0.0 2.0 -1.6 1.2 3.5 5.9 6.4 4.5 5.2 8.2 8.8 8.6 9.1 9.4 0 0.5 0.91 1.25 1.69 2.06 2.49 2.92 3.19 3.76 4.67 5.35 6.49 8.5 1.125No 1.25No Qmax(%) 0.0 0.9 -2.5 -2.8 -3.7 -4.5 -6.2 -6.2 -6.5 -7.4 -7.6 -7.9 -8.3 -7.8 Qmax(%) 0.0 -1.0 -5.8 -6.3 -8.2 -9.5 -11.9 -12.3 -12.5 -13.7 -14.6 -14.6 -15.4 -14.6 Note : % change relative to original flow data and No represent original manning coeff equal 0.04. Percent change in peak flow along river for a given manning value 15.0 change in peak flow (%) 10.0 5.0 0.0 0 1 2 3 4 5 6 7 8 9 -5.0 -10.0 -15.0 -20.0 River station (miles) 0.875No 0.937No No 1.125No 1.25No Figure 5.4.3 – Change in peak flow profiles based on five different Manning values 58 Figure 5.4.3 shows the profiles of percent change in peak flow for specified Manning coefficients along the river relative to the baseline. The profiles revealed that the change in peak flow became more pronounced at reach stations located away from the dam site. According to the above Figure 5.4.2-3 and Table 5.4.2-3, the peak flow increases as the Manning coefficient value decreases. The relationship between the two parameters have been discussed and studied by researchers such as Chow [15] for years. Based on their finding, the two variables had inverse relationship as indicated in Manning’s equation. This confirmed the consistency of this analysis with literatures. 5.5. Effects of time to dam failure and Manning coefficient on peak flows at specified river stations This part of sensitivity analysis was designed to combine the two scenarios considered in the above sub-section, section 5.4, in order to determine the controlling parameter. Two reach stations were selected to conduct a thorough investigation in identifying the biggest peak flow influencing parameter, Manning value or time to dam breach. Reach station 6.81 and 4.74 were selected and results of different computer runs were tabulated as follows. Table 5.5.1 – Peak flows for different Manning and TFH values @ Sta. 6.81. Breach hydrograph based on TFH (hr) 0.5To To 2To 4To 6To 0.875No 15740.9 11476.6 7194.9 4202.6 2990.3 0.9375No No 1.125No Peak flow (cfs) @ sta. 6.81 15565.0 15205.3 14642.8 11411.7 11294.6 10968.4 7130.2 7070.8 6988.7 4191.0 4181.4 4156.1 2985.7 2982.2 2973.1 1.25No 13960.7 10677.8 6898.8 4131.7 2965.2 Note :No & To represent original manning coeff and time to dam failure, & equal 0.04 and 0.5hr repsectively. 59 Table 5.5.2 – Change in peak flows for different Manning and TFH @ Sta. 6.81 Breach hydrograph based on TFH (hr) 0.5To To 2To 4To 6To 0.875No 3.5 1.6 1.8 0.5 0.3 0.9375No No 1.125No Percent change in peak flow (%) @ sta. 6.81 2.4 0 -3.7 1.0 0 -2.9 0.8 0 -1.2 0.2 0 -0.6 0.1 0 -0.3 1.25No -8.2 -5.5 -2.4 -1.2 -0.6 Note : % change relative to original flow data @ sta. 6.81 and N o & To equal to 0.04 and 0.5hr respectively. Table 5.5.3 – Peak flows for different Manning and TFH values @ Sta. 4.74 Breach hydrograph based on TFH (hr) 0.5To To 2To 4To 6To 0.875No 11235.6 9695.2 6815.1 4123.3 2963.9 0.9375No No 1.125No Peak flow (cfs) @ sta. 4.74 10877.3 10388.7 9622.6 9484.2 9229.9 8687.1 6705.9 6594.8 6433.4 4101.3 4080.5 4038.6 2956.1 2948.3 2929.2 1.25No 8965.3 8218.8 6258.4 3989.2 2913.5 Note :No & To represent original manning coeff and time to dam failure, & equal 0.04 and 0.5hr repsectively. Table 5.5.4 – Change in peak flows for different Manning and TFH @ Sta. 4.74 Breach hydrograph based on TFH (hr) 0.5To To 2To 4To 6To 0.875No 8.2 5.0 3.3 1.0 0.5 0.9375No No 1.125No Percent change in peak flow (%) @ sta. 4.74 4.7 0 -7.4 2.8 0 -5.9 1.7 0 -2.4 0.5 0 -1.0 0.3 0 -0.6 1.25No -13.7 -11.0 -5.1 -2.2 -1.2 Note : % change relative to original flow data @ sta. 4.74 and No & To equal to 0.04 and 0.5hr respectively. As shown in Table 5.5.1 and 2, a decrease in time to dam failure by 50% (To to 0.5To) and 12.5% (No to 0.875No) decrease in Manning coefficient resulted in 3.5% increase in peak flow at reach station 6.8. Similarly, a 500 % increase in time to dam failure and 25% increase in Manning value resulted in 0.6 % reduction in peak flow at the same reach station. Table 5.5.3 and 4 show the same pattern for reach station 4.74. A 50% decrease in time to dam failure and 12.5 % decrease in Manning value resulted in 8.2% increase in peak flow at station 4.74. Overall observation of the results in the above 60 tables indicated that the change in peak flow at the two stations was highly sensitive to a minor change in Manning coefficient than time to dam failure. This finding was further illustrated in the following figures. Peak flow vs time to dam failure for given Manning values @ Sta. 6.81 17500.0 Peak flows (cfs) 15000.0 12500.0 10000.0 7500.0 5000.0 2500.0 0.0 0 0.5 1 0.875No 1.5 2 Time to dam failure (hr) 0.9375No No 2.5 3 1.125No 3.5 1.25No Figure 5.5.1 – Peak flow profiles for given Manning values and TFH @ Sta. 6.81 Percent change in peak flows relative to original flows @ Sta. 6.81 6.0 Change in peak flow (%) 4.0 2.0 0.0 0 0.5 1 1.5 2 2.5 3 -2.0 -4.0 -6.0 -8.0 -10.0 Time to dam failure (hr) 0.875No 0.9375No No 1.125No 1.25No Figure 5.5.2 – Change in peak flow profiles for given Manning values and TFH @ Sta. 6.81 3.5 61 Peak flow vs time to dam failure for given Manning values @ Sta. 4.74 12000.0 Peak flows (cfs) 10000.0 8000.0 6000.0 4000.0 2000.0 0.0 0 0.5 1 0.875No 1.5 2 Time to dam failure (hr) 0.9375No No 2.5 3 1.125No 3.5 1.25No Figure 5.5.3 – Peak flow profiles for given Manning values and TFH @ Sta. 4.74 Percent change in peak flows relative to original flows @ Sta. 4.74 10.0 7.5 Change in peak flow (%) 5.0 2.5 0.0 -2.5 0 0.5 1 1.5 2 2.5 3 3.5 -5.0 -7.5 -10.0 -12.5 -15.0 Time to dam failure (hr) 0.875No 0.9375No No 1.125No 1.25No Figure 5.5.4 – Change in peak flow profiles for given Manning values and TFH @ Sta. 4.74 The above figures demonstrate that as the Manning coefficient and time to dam failure decrease, the peak flow increases at the two reach stations. The controlling parameter between the two variables was shown in the figures. Particularly, the percent 62 change in peak flow profiles at the two reach stations, Figure 5.5.2 and 5.5.4, indicate the influence of a minor change in Manning coefficient on the peak flow. In the analysis of natural waterway, there were a number of unpredictable conditions that prohibited making general conclusions about the river hydraulic parameters. Since the downstream flows changed with time and space, it was difficult to describe the relationships among the three parameters empirically at this level of study. However, the graphical and tabular results at the two stations indicated that the peak flow had inverse relation with Manning coefficient and time to dam failure, i.e., the smaller time to dam failure and Manning value are, the higher the peak flow is. 5.6. Channel bed slope (So) versus peak flows in existing channel under a specified time to dam failure The last part of sensitivity analysis involved studying the reactions of peak flow to change in channel bottom slopes that changed the corresponding downstream channel elevations. As shown in Table 5.6.1, four channel bed slopes were considered in the analysis. Appendix B presented the detail of HEC-RAS inputs and outputs data. 63 Table 5.6.1 – Existing and assumed channel bed slopes Reach Sta. River Sta. (mile) 8.5 8 7.59 7.25 6.81 6.44 6.01 5.58 5.31 4.74 3.83 3.15 2.01 0 0 0.5 0.91 1.25 1.69 2.06 2.49 2.92 3.19 3.76 4.67 5.35 6.49 8.5 Assumed channel bed slopes So - existing S1 = 0.950So S2 = 0.975So S3=1.025So S4 = 1.050So 0.001386 0.001386 0.003064 0.003874 0.003874 0.004405 0.004405 0.004405 0.003323 0.002081 0.002081 0.001661 0.001661 0.001317 0.001317 0.002911 0.003680 0.003680 0.004184 0.004184 0.004184 0.003157 0.001977 0.001977 0.001578 0.001578 0.001351 0.001351 0.002987 0.003777 0.003777 0.004294 0.004294 0.004294 0.003240 0.002029 0.002029 0.001620 0.001620 0.001420 0.001420 0.003140 0.003971 0.003971 0.004515 0.004515 0.004515 0.003406 0.002133 0.002133 0.001703 0.001703 0.001455 0.001455 0.003217 0.004068 0.004068 0.004625 0.004625 0.004625 0.003489 0.002185 0.002185 0.001744 0.001744 Note: So represents existing or baseline channel bed slope provided by dam owner. Similarly, Figure 5.6.1 shows the profiles of the four channel bed slopes considered in the analysis relative to the existing channel bed. Existing and assumed channel bed slopes 1000.00 980.00 960.00 Elevation (ft) 940.00 So 920.00 1.05So 900.00 1.025So 880.00 0.975So 860.00 0.95So 840.00 0 1 2 3 4 5 6 7 8 9 River station (miles) Figure 5.6.1 Profiles of existing and assumed channel bed slopes 64 The existing channel bed slope was used as a baseline to develop four additional bed slopes that helped to investigate the relationship between channel bed slopes and peak flows along the channel. In this analysis, the breaching outflow hydrograph generated by 0.25hr of TFH was used to perform the unsteady flow routing through the downstream reaches. Appendix B showed the detail of inputs and outputs data for this analysis. The summary of computer runs for the assumed channel bed slopes are shown in the following tables. As shown in Table 5.6.2 and 3, the peak flows along the river changed as the channel bed slopes changed. A 5% decrease in channel bed slopes resulted in changes in peak flows that ranged from 0% at the upstream to -24.8% at the downstream. Similarly, a 5% increase in channel bed slopes resulted in changes in peak flows that ranged from 0% at the upstream to 20.0% at the downstream. In order to supplement the tabular results and produce robust findings, the peak flow profiles were created along the river for specified channel bed slopes, shown in Figure 5.6.2 and 5.6.3. Table 5.6.2 – Peak flows for specified channel bed slopes Peak Flow (cfs) Reach Sta. River Sta. (mile) So - existing S1 = 0.950So S2 = 0.975So S3=1.025So S4 = 1.050So 8.5 8 7.59 7.25 6.81 6.44 6.01 5.58 5.31 4.74 3.83 3.15 2.01 0 0 0.5 0.91 1.25 1.69 2.06 2.49 2.92 3.19 3.76 4.67 5.35 6.49 8.5 25893 21142.12 19268.23 18077.92 15957.52 14420.62 13241.21 12408.22 11856.72 9143.9 7539.86 6770.19 5927.17 5296.71 25893 21096.24 19213.05 18078.24 15893.99 14151.29 12676.23 11892.07 11362.94 7575.79 5806.45 5137.23 4455.81 4030.61 25893 21116.71 19228.56 18192.81 15862.62 14253.46 12985.99 12228.94 11700.82 8333.36 6889.69 6111.76 5319.31 4771.15 25893 21153.89 19330.75 18290.26 16109.76 14492.77 13332.29 12460.6 11995.78 10444.5 8314.27 6967.22 6385.12 5374.97 25893 21190.29 19349.76 18380.42 16270.31 14623.59 13438.54 12636.88 12125.22 10791.89 9045.36 7916.52 6702.61 5571.31 Note: So represents existing or baseline channel bed slope provided by dam owner. 65 Table 5.6.3 – Change in peak flows for specified channel bed slopes Reach Sta. 8.5 8 7.59 7.25 6.81 6.44 6.01 5.58 5.31 4.74 3.83 3.15 2.01 0 River Sta. (mile) 0 0.5 0.91 1.25 1.69 2.06 2.49 2.92 3.19 3.76 4.67 5.35 6.49 8.5 So - existing 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 Change in peak flow along river (%) S1 = 0.950So S2 = 0.975So S3=1.025So 0.0 0.0 0.0 -0.2 -0.1 0.1 -0.3 -0.2 0.3 0.0 0.6 1.2 -0.4 -0.6 1.0 -1.9 -1.2 0.5 -4.3 -1.9 0.7 -4.2 -1.4 0.4 -4.2 -1.3 1.2 -17.1 -8.9 14.2 -23.0 -8.6 10.3 -24.1 -9.7 2.9 -24.8 -10.3 7.7 -23.9 -9.9 1.5 S4 = 1.050So 0.0 0.2 0.4 1.7 2.0 1.4 1.5 1.8 2.3 18.0 20.0 16.9 13.1 5.2 Note: So represents existing or baseline channel bed slope provided by dam owner. Figure 5.6.2 and 5.6.3 are the graphical representation of the above two tables. Analysis of the graphs showed that the variation in peak flows was not noticeable at the dam site, but effects of change in channel bed slopes became more prominent at the reach stations distant from the dam site. The influence of change in channel bed slopes were consistent from upstream to downstream end as shown in Figure 5.6.2 and 3. The computation results shown in the above tables and figures revealed that the peak flow along the channel was very sensitivity to a minor change in channel bed slopes, example at river mile 5.0, there was a significant variation in peak flow for a small degree change of So. As indicated in Manning equation [15], the peak flow and channel bed slope have a direct non-linear relation. This implied that as the channel bed slopes increased by certain coefficients, the peak flow increased by certain multiplier which was consistent with the finding of this study. 66 Percent change in peak flows along river for given channel bed slopes 25.0 20.0 Change in peak flow (%) 15.0 10.0 5.0 0.0 -5.0 0 1 2 3 4 5 6 7 8 -10.0 -15.0 -20.0 -25.0 -30.0 River station (miles) So 0.950So 0.975So 1.025So 1.050So Figure 5.6.2 Change in peak flows along the river for given channel bed slopes 9 Peak flow profiles along river for given channel bed slopes 30000 Peak flows (cfs) 25000 20000 15000 10000 5000 0 0 1 2 3 4 5 6 7 8 9 River station (miles) S0 0.95So 0.975So 1.025So 1.050So Figure 5.6.3 – Peak flow profiles along the river for specified channel bed slopes 67 68 Chapter 6 CONCLUSIONS AND RECOMMENDATIONS 6.1. Conclusions The results of Lang Creek Dam breach sensitivity analysis demonstrated that dam breach analysis is a broad subject and requires a large degree of precautions in selecting appropriate parameters and flow routing techniques. Additionally, the study revealed that predicting the pattern of the sensitivity testing outputs becomes more complex as more parameters are incorporated in the analysis. A minor change in dam breach characteristics and downstream river parameters resulted in a significant increment in peak flows at the dam site and specified reach stations in downstream channel. The rates of increments in peak flows were not uniform in the specified sensitivity analyses. This observation indicated that the peak flows were sensitive to changes in time to dam failure, side slope of breach, Manning coefficient, and channel bed at various degrees. Based on the Lang Creek Dam breach sensitivity analyses results, which were obtained through application of HEC-1 and HEC-RAS subroutines, the following conclusions were made on the relationships among the key dam breaching parameters and open channel parameters. A 50 % reduction in TFH resulted in 82.7 % increase in peak discharge at the dam site. Whereas, a 500 % increase in TFH resulted in 78.6 % reduction in peak discharge at the same site. This implied that when the dam collapsed 69 rapidly, the peak discharge became high at the dam site. This concluded that the maximum discharge at the dam site was very sensitive to change in TFH. An 87.5% decrease in SS resulted in 3.4% increase in maximum discharge at the dam site. Whereas, a 25% increase in SS value produced 0.6% decrease in maximum discharge at the dam site. As the side slope of dam breach became steeper or breach area became smaller, the maximum discharge at the dam site became relatively higher. This concluded that maximum discharge at the dam site was slightly sensitive to change in SS. The peak discharge at the dam site increased by 88.4% when the TFH reduced by 50% and SS decreased by 87.5%. Based on the test results, evaluation of the relative influences of the two parameters on the maximum discharge demonstrated that the peak discharge was highly sensitive to a smaller change in TFH than SS at the dam site. The peak flows in the downstream reaches were directly related to maximum dam-break breaching outflow hydrographs. The smaller time to dam failure resulted in a higher dam breaching hydrograph, and the maximum discharge at the dam site sustained its peak throughout the downstream river. A 12.5 % decrease in Manning coefficients resulted in changes in peak flows that ranged from 0% at the upstream and 9.4% at the downstream end of the channel. Whereas, a 25% increase in Manning coefficients resulted in change in peak flows that ranged from 0% at the upstream and -14.6% at the 70 downstream. The results suggested that the peak flows in the channel were highly sensitive to changes in Manning coefficients. A 50% decrease in TFH and a 12.5% decrease in Manning coefficient resulted in 3.5% increase in peak flow at reach station 6.8. Similarly, a 500 % increase in TFH and a 25% increase in Manning value resulted in 0.6 % reduction in peak flow at the same reach station. A similar observation made at a different station, reach station 4.74, showed that a 50% decrease in time to dam failure and 12.5 % decrease in Manning value resulted in 8.2% increase in peak flow. These results indicated the relative influences of the two parameters on the peak flow at the specified reach stations. Based on the results, the peak flows in the channel were highly sensitive to changes in Manning coefficient than time to dam failure. A 5% decrease in channel bed slopes resulted in changes in peak flows that ranged from 0% at the upstream to -24.8% at the downstream. Similarly, a 5% increase in channel bed slopes resulted in changes in peak flows that ranged from 0% at the upstream to 20.0% at the downstream. These results concluded that the peak flows in the channel were highly sensitive to a minor change in channel bed slopes, i.e. as the channel bed slopes became flatter, the peak flows became higher. 71 6.2. Recommendations Sensitivity analysis of dam breach and open channel parameters using Lang Creek as a testing basis involved making a number of assumptions based on literature reviews and historic data. In the real world, there is a large degree of uncertainty associated with the breach parameters and breaching outflow estimation. It would be helpful to minimize the ambiguities associated with breach parameters estimation using different modeling software and analysis techniques for obtaining a wider range of dam and reservoir characteristics and downstream river characteristics data. In this study, only one dimensional unsteady flow routing technique was used to carry out the sensitivity analysis in the downstream river. Similarly, the old version of hydrologic modeling software was applied to perform the reservoir routing. There are a number of limitations and assumptions in the modeling software. It would be helpful to utilize a different version of the software and enhance the findings of this study.