Investment Projects of Major Industries of Fujian Province

advertisement
Investment Projects of Major
Industries of Fujian Province
Fujian International Investment Attraction
Office
January 2013
Contents
Electronic Information Industry ................................................................................ 1
1. Fuqing Optoelectronic Science and Technology Park (Phase II) ...................... 1
2. Zhangzhou Changshan LED Display Project .................................................... 1
3. Quanzhou Nan’an Organic Light Emitting Diode (OLED) Production Line .... 2
4. Putian Large LCD End Products ........................................................................ 3
5. Investment Project of LED Energy-saving Lighting and Supporting Industrial
Chain of Zhangzhou Lantian Economic Development .......................................... 4
6. Quanzhou Anxi LED Chip and Epitaxy Manufacturing and LED Packaging
Application Project ................................................................................................ 4
7. Sapphire Substrate Cutting Project of Quanzhou Taiwanese Investment Zone . 5
8. Sapphire Epitaxial Wafer Project of Quanzhou Taiwanese Investment Zone ... 6
9. Quanzhou Nan’an High-power Special LED Lamp Production Line ............... 7
10. Quanzhou Nan’an LED Epitaxial Wafer and Chip Manufacturing and
Packaging Production Line .................................................................................... 7
11. Putian LED Epitaxial Wafer and Chip Production Project .............................. 8
12. Sanming Qingliu Electronic Industrial Park Project ........................................ 9
13. Introduction to the Construction Project of Pucheng Industrial Park LED
Incubation Base, Nanping .................................................................................... 10
14 Longyan liancheng Sapphire Substrate and Epitaxial Wafer Production
Project .................................................................................................................. 10
15. Longyan Changting Rare Earth Luminescent Materials and Application
Project .................................................................................................................. 11
16. Ningde Zhouning Longguang High-efficiency LED Lighting Lamp Project 11
17. Zhangzhou Dongshan Thin-film Solar Cells ................................................. 12
18. Zhangzhou Hua’an Energy-saving Opto-electronics Industry....................... 13
19. Zhangzhou Dongshan Battery Separator Project ........................................... 13
20. Quanzhou Nan’an Photovoltaic and Electronic Information Industrial Base 14
21. Quanzhou Nan’an Solar Photovoltaic System Battery Production Line ....... 15
22. Sanming Qingliu Photovoltaic Solar Energy Industrial Park Project ............ 16
23. Fujian (Pucheng) Jimin Photovoltaic and Electronic Technology Park ........ 16
24. Northern Fujian Environment-friendly Lead Crystal Battery Production
Project, Nanping .................................................................................................. 17
25. Longyan Liancheng Monocrystalline Silicon and Solar Cell Module
Production Project ................................................................................................ 18
26. Fuqing Light Control Industry Project ........................................................... 18
27. Investment Project of Fuzhou Electromechanical Industrial Park ................. 19
28. Mechanical and Electronic Industrial Park Project of Lianjiang Economic
Development Zone,Fuzhou ............................................................................... 20
29. Zhangzhou Changshan Micro-electronics and Electronic Component Project
.............................................................................................................................. 21
30. Zhangzhou Dongshan Glass Deep Processing Project .................................. 21
31. Zhangzhou zhangpu High-tech Electronic Industrial Park Project................ 22
32. Opto-electronics Industrial Park of Quanzhou Taiwanese Investment Zone . 23
33. Quanzhou Nan’an Automotive Electronics Product Development and
Production Project ................................................................................................ 23
34. Longyan Shanghang 500t Optical Fiber Perform Production Line ............... 24
35. Quanzhou Anxi High-quality Bathroom Plumbing and Mechanical and
Electrical Valve Production Project ..................................................................... 25
36. Quanzhou Software Park ............................................................................... 25
37. Quanzhou Fengze Haixi Electronic Information Industry Incubation Base .. 26
38. Quanzhou Anxi Service Outsourcing Project of China International
Information Technology (Fujian) Industrial Park ................................................ 27
39. Construction of Putian Anfu Online Trade City ............................................ 28
40. Introduction to Wuyi New District Software Industrial Park, Nanping......... 29
Mechanical Equipment Industry .............................................................................. 30
41. Fuzhou Fuqing Jiangyin Metallurgical Machinery Industry Project ............. 30
42. Fuzhou Luoyuan Bay Stainless Steel Deep Processing Industrial Park ........ 30
43. Quanzhou Nan’an Special Casting Mold and Bearing Manufacturing Project
.............................................................................................................................. 31
44. Quanzhou Hui’an Steel Structure Chunking Construction Project ................ 32
45. Sanming Mingxi High-Strength Light-Duty Steel Wheel Project ................. 33
46. Sanming Haixi (Datian) Mechanical Casting and Forging Concentration Area
Development Project ............................................................................................ 34
47. Sanming Jiangle Project on Continuous Casting and Rolling of Stainless
Steel Composite Plate and Strip ........................................................................... 34
48. Longyan Wuping Precision Stainless Steel Rolling and Product Project ...... 35
49. Electronics, Photoelectric and Electro-Mechanical Projects of Fuzhou
Municipal Electro-Mechanical Industrial Park .................................................... 36
50. Mechanical and Electronic Industrial Park, Lianjiang Economic
Development Zone Project, Fuzhou .................................................................... 37
51. Industrial Projects of Fuzhou Taiwanese Investment Zone ........................... 37
52. Industrial Projects of Xiang’an Industrial Park,Xiamen ............................. 38
53. Zhangzhou Advanced Equipment Manufacturing Industry Project Hua’an .. 38
54. Zhangzhou Nanjing Dehe Mechanical Industrial Park .................................. 39
55. High-end Equipment Manufacturing Industrial Park project of Quanzhou
Taiwanese In vestement Zone .............................................................................. 39
56. Quanzhou Nan’an Binjiang Mechanical Equipment Manufacturing Base
Project .................................................................................................................. 40
57. Petrochemical Mechanical Equipment Manufacturing Project of Quanzhou
Taiwanese Investment Zone ................................................................................. 41
58. Sanming Qingliu Longxiang Industrial Park Mechanical Manufacturing
Project .................................................................................................................. 42
59. Fujian CREC Qianda Equipment Manufacturing Project .............................. 42
60. Rail Equipment Industry Auxiliary Project of Quanzhou Taiwanese
Investment Zone................................................................................................... 43
61. Longyan Engineering Machinery and Automotive Tire Production Line
Project .................................................................................................................. 44
62. Longyan Excavator-Dedicated High-Pressure Cylinder project .................... 44
63. Longyan Xinluo Mine Emergency Equipment Manufacturing Production
Project .................................................................................................................. 45
64. Longyan Rail Transit Material and Equipment Manufacturing Industrial Park
.............................................................................................................................. 45
65. Fuzhou Lianjiang Kemen Port Automotive Industrial Park Project .............. 46
66. Fuzhou Qingkou Investment Zone Automotive Engine Project .................... 47
67. Zhangzhou Hua’an Automobile and Parts Industry ....................................... 47
68. Zhangzhou Automotive Auxiliary Industrial Chain Project on Automotive
Bearing etc . ......................................................................................................... 48
69. Quanzhou Nan’an Automotive Rear-View Detector Project ......................... 48
70. Quanzhou Nan’an AMT Project .................................................................... 49
71. Project with Annual Capacity of 200,000 Engines,Sanming ...................... 50
72. Sanming Jiangle Semi-Solid Rapid Prototyped Automotive Engine Casting
Project .................................................................................................................. 50
73. Nanping Minbei Lead-Crystal Environmental-Protection Battery Production
Project .................................................................................................................. 51
74. Longyan Truck Crankshaft Production Project.............................................. 52
75. Longyan Wuping Automotive Stainless Steel Muffler Production Line Project
.............................................................................................................................. 52
76. Longyan Mini-car Production Project with Annual Capacity of 300,000
Mini-cars .............................................................................................................. 53
77. Longyan Luxury Coach Production Project .................................................. 54
78. Longyan Heavy-Duty Truck Production Project ........................................... 54
79. Longyan Automotive Engine Production Project .......................................... 55
80. Longyan Aerial Ladder Fire Truck Production Project.................................. 55
81. Longyan Changting RE Hydrogen-Storage Alloy Powder and NI-MH
Electric-Vehicle Battery Production Line ............................................................ 56
82. Ningde Fu’an Tiger Electric Car Industrial Park Project ............................... 57
83. Ningde Fu’an Hybrid Power Assembly with Annual Capacity of 10,000 Sets
of New-Energy Passenger Cars ........................................................................... 57
84. Ningde Fu’an Zhenzhong New-Energy Electric Car and Hybrid Electric
Yacht Project ........................................................................................................ 58
85. Ningde Fu’an Zhenzhon New-Energy Electric Car Project .......................... 59
86. Xiamen Baoda Yacht Industrial Park Project ................................................. 60
87. Zhangzhou Dongshan Yacht Manufacturing and Auxiliary Project .............. 60
88. Zhangzhou 100,000-Tonnage Shipyard Project ............................................. 61
89. Shipbuilding Project of Quanzhou Shipyard ................................................. 61
90. Quanzhou Hui’an Marine Intermediate-Speed Diesel Engine Project .......... 62
91. Quanzhou Hui’an Ship Deck Mechanical Manufacturing Project ................ 63
92. Putian Port Mechanical Manufacturing Base Auxiliary Project .................... 63
93. Nanping Marine Special Cable Project .......................................................... 64
94. Ningde Haixi Industrial Area Ocean Engineering Equipment Manufacturing
Base Project ......................................................................................................... 65
95. Zhangzhou Nanjing Project on Basic Parts of CNC Machine Tool ............... 66
96. Zhangzhou Nanjing CNC Floor-Type Milling and Boring Machine, CNC
Plane Milling and Boring Machine and Machining Center ................................. 66
97. Zhangzhou Nanjing Large High-Speed Precision Compound CNC Machine
Tool and Machining Center ................................................................................. 66
98. CNC High-Speed Machine Tool Project of Quanzhou Taiwanese Investment
Zone ..................................................................................................................... 67
99. Quanzhou Hui’an CNC Machine Tool Automatic Production Line Project .. 67
100. Sanming Mingxi Pneumatic Precision Mechanical Parts Processing Project
.............................................................................................................................. 68
101. Zhangzhou Large-Tonnage Container Fork Truck....................................... 69
102. Zhangzhou Nanjing Project of Food Mechanically-Processing Industrial
Park ...................................................................................................................... 69
103. Longyan Bearing Production Project ........................................................... 70
104. Longyan Changting Textile Machinery Production Project ........................ 70
105. Quanzhou An’xi Haixi Tea-making Equipments Industrial Base Auxiliary
Service Project ..................................................................................................... 71
Petrochemical Industry ............................................................................................. 73
106. Xiamen New Eco-Friendly Lyocell Long Fiber .......................................... 73
107. Zhangzhou Oil Refinery Project of Annual Output of 15 Million Tons, and
Ethylene Project of Annual Output of 2 Million Tons ......................................... 73
108. Zhangzhou Fine Chemical Production Project ............................................ 73
109. Quanzhou Quangang 1,3- Propylene Glycol ............................................... 74
110. Quanzhou Quangang ABS Resin ................................................................. 74
111. Quanzhou Quangang Aniline ....................................................................... 75
112. Quanzhou Quangang Phenol Acetone .......................................................... 75
113. Quanzhou Quangang Phthalic Anhydride .................................................... 76
114. Quanzhou Quangang SM ............................................................................. 77
115. Quanzhou Quangang Acrylonitrile .............................................................. 77
116.Quanzhou Quangang Acrylonitrile-Butadiene-styrene Copolymer .............. 78
117. Quanzhou Quangang CPP ............................................................................ 78
118. Quanzhou Quangang Butyl Rubber ............................................................. 79
119. Quanzhou Quangang Butanol-octanol ......................................................... 79
120. Quanzhou Quangang Super Absorbent Resin .............................................. 80
121. Quanzhou Quangang Epoxy Resin .............................................................. 81
122. Quanzhou Quangang Ethylene Oxide/Glycol .............................................. 81
123. Quanzhou Quangang Adipate: ..................................................................... 82
124. Quanzhou Quangang CPL ........................................................................... 82
125. Quanzhou Quangang MMA ......................................................................... 83
126. Quanzhou Quangang MTBE........................................................................ 84
127. Quanzhou Quangang Methane Chloride ...................................................... 84
128. Quanzhou Quangang MEK .......................................................................... 85
129. Quanzhou Quangang Acrylic Fiber ............................................................. 85
130. Quanzhou Quangang PTA ........................................................................... 86
131. Quanzhou Quangang PAM .......................................................................... 86
132. Quanzhou Quangang PTT............................................................................ 87
133. Quanzhou Quangang PBT ........................................................................... 87
134. Quanzhou Quangang PTMEG ..................................................................... 88
135. Quanzhou Quangang PC .............................................................................. 89
136. Quanzhou Quangang PVA ........................................................................... 89
137. Quanzhou Quangang Nylon 66 Salt ............................................................ 90
138. Quanzhou Quangang Petroleum Resin ........................................................ 90
139. Quanzhou Quangang Bisphenol A ............................................................... 91
140. Quanzhou Quangang MA ............................................................................ 91
141. Quanzhou Quangang DMC.......................................................................... 92
142. Quanzhou Quangang Nitrobenzene ............................................................. 93
143. Quanzhou Quangang Isopropanol................................................................ 93
144. Hui’an PTA .................................................................................................. 94
145. Hui’an PET .................................................................................................. 94
146. Hui’an Unsaturated Polyester Resin ............................................................ 95
147. Putian Meizhou Bay Petrochemical Downstream Industrial Base (Fine
Industry) ............................................................................................................... 96
148. Sanming Series Nanometer Calcium Carbonate Products of Annual
Capacity of 50,000 Tons ...................................................................................... 96
149. Nanping Brief Introduction to Organic Silicon Rubber Project .................. 97
150. Long’an Synthetic Resin and Additive of An Annual Capacity of 150,000
Tons ...................................................................................................................... 98
151. Quanzhou Quangang Salt Production Project through Seawater Desalination
.............................................................................................................................. 98
152. Sanming Oleoresin Base and Series Rosin Fine and In-Depth Processing
Project .................................................................................................................. 99
153. Nanping Lithium Hexafluorophosphate
and Electrolysis liquid for
Lithium Battery Production Project ................................................................... 100
154. Nanping Activated Carbon In-depth(Fine) Processing Project of An Annual
Capacity of 50,000 Tons .................................................................................... 100
155. Fuzhou New Chemical Materials Industrial Chain Project ....................... 101
156. Putian Relevant Supplementary Downstream Industrial Chain for Propane
Dyhydrogenation................................................................................................ 102
157. Sanming Organic Silicon Monomer and Downstream Product Processing
Project of An Annual Capacity of 100,000 Tons ............................................... 102
158. Sanming Fluorite Chemical Products In-Depth Processing Project .......... 103
159. Nanping Brief Introduction to Development Project of Series Fluorite
Chemical Products ............................................................................................. 103
160. Zhangzhou Crude Oil Warehouse Base Project ......................................... 104
161. Zhangzhou Leather Park Supplementary Industrial Zone ......................... 104
162. Putian Supplementary Reserve Oil Base Project on Northern Bank of
Meizhou Bay ...................................................................................................... 105
163. Sanming Fluorine Chemical Industrial Park Project ................................. 105
164. Brief Introduction to Light Textile Chemical New Material Park
Development Project of Nanping Industrial Park .............................................. 106
165. Fu’an Chemical Industrial Park ................................................................. 106
Biological Pharmaceutical Industry ............................. Error! Bookmark not defined.
166.Projects in Fuzhou Biological Pharmaceutical Industrial Park..............Error!
Bookmark not defined.
167. Biopharmaceutical Park of Lianjiang Economic Development Zone ..Error!
Bookmark not defined.
168. Haicang Biopharmaceutical Park:................ Error! Bookmark not defined.
169. Biopharmaceutical Industrial Park ............... Error! Bookmark not defined.
170. Zhangpu Biopharmaceutical Industrial BaseError! Bookmark not defined.
171. Yongchun Biopharmaceutical Industrial ParkError!
defined.
Bookmark
not
172 . Yongchun Biopharmaceutical Industrial Incubation and Public Service
Platform(Phase I) ................................................. Error! Bookmark not defined.
173. Biopharmaceutical Industrial Park of Mingxi CountyError! Bookmark not
defined.
174. Zherong Haixi Pharmaceutical Valley ......... Error! Bookmark not defined.
175. Chinese traditional medicine and processing base in Nanjing county of
Zhangzhou city..................................................... Error! Bookmark not defined.
176. Construction of Sanming Municipal Modern Chinese Patent Drugs and
Natural Vegetable Drugs Industrial Park ............. Error! Bookmark not defined.
177. Marine Biochemical Health-Care Product ... Error! Bookmark not defined.
178. Zhao’an Jindu Marine Biological Industrial ParkError!
defined.
Bookmark
not
179. Quanzhou Investment Zone of Marine and Biological Technology .....Error!
Bookmark not defined.
180. Wuping County Planting and In-depth Processing of TCM Herbs .......Error!
Bookmark not defined.
181. TCM Herbs Planting and Processing ProjectError!
defined.
Bookmark
not
182. Anoectochilus Formosanus Hayata Planting and Development in Anyuan
County .................................................................. Error! Bookmark not defined.
183. Coix Chinensis Planting and In-Depth Processing ProjectError! Bookmark
not defined.
184. In-depth Processing of Radix PseudostellariaeError!
defined.
Bookmark
not
185. GAP Planting of Officinal magnolia Bark and Extracting of Magnolol in
Mingxi County ..................................................... Error! Bookmark not defined.
186. Magnolol Abstraction and Preparation ProductionError! Bookmark not
defined.
187. Taxane and Taxol Anti-Cancer Drugs Extraction ProjectError! Bookmark
not defined.
188. Cultivation and extracting of Cephalotaxus and Homoharringtonine
Pharmaceutical ..................................................... Error! Bookmark not defined.
189. Rose Essence Oil Extraction and ProcessingError!
defined.
190. In-depth Processing of Cosmetic Camellia OilError!
defined.
Bookmark
Bookmark
not
not
191. Refined Processing of Tea Seed Oil ............. Error! Bookmark not defined.
192. Sanming Biological Active Substances Extraction and Industrial
Development with Bamboo Resources ................ Error! Bookmark not defined.
193. Green Foods and Biopharmaceutical Development in Jianing County Error!
Bookmark not defined.
194. Manufacturing of Soapberry Biological Diesel Products with Annual Output
of 100,000 Tons.................................................... Error! Bookmark not defined.
195. Biopharmaceutical Manufacturing Project .. Error! Bookmark not defined.
196. Land Levelling Project of Xinling Biopharmaceutical Industrial Park Error!
Bookmark not defined.
Services...................................................................................................................... 128
197. Songxia Food Logistics Park in Changle City ........................................... 128
198. Fuzhou Large-Scale Logistics Trading Center .......................................... 128
199. Huangshi Commercial Logistics Park in Putian ........................................ 129
200. Putian Marine Products Refrigeration and Cold Chain Logistics .............. 130
201. Tianbao Commerce Park in Zhangzhou ..................................................... 130
202. Quanzhou Strait Luggage Logistics Mall .................................................. 131
203. Construction Project of Ninghua County Modern Logistics Center between
Fujian and Jiangxi .............................................................................................. 132
204. Gui’an Central Hot Spring Tourism Project in Lianjiang County ............. 133
205. Tourism Resource Development Project of Xianyou County .................... 133
206. Development Project of Heping Ancient Town Scenic Area in Shaowu City
............................................................................................................................ 134
207. Bar Corridor Project in Wuyi Mountain .................................................... 135
208. Development Project of Zhuzi Garden in Wuyi Mountain ........................ 136
209. Comprehensive Coastal Tourism Development Project in Dongshan County
............................................................................................................................ 136
210. Sandu'ao Coastal Tourism Development Project ....................................... 137
211. Tianxing Mountain National Forest Park in Pingnan County-Tourism
Development Project of Longjing Bridge Scenic Spot ...................................... 138
212. Comprehensive Development Project of Minhu Lake Scenic Spot in Youxi
County ................................................................................................................ 139
213.Huangchao Ecological Leisure & Tourism Resort in Nanan City .............. 139
214. Creative Industries Center of Cross-strait Marine Culture in Meizhou Island,
Putian ................................................................................................................. 140
215. Taxus Chinensis Cultural Creative Industrial Park Project in Mingxi County,
China .................................................................................................................. 141
216. Longyan Central Soviet Areas Park Construction Project ......................... 141
217. Third Affiliated Hospital of Fujian Medical University ............................ 142
218. General Hospital in Gaokan New Town, Yongding County ...................... 143
219. Second-Phase Real Estate Project in Mazu Town, Putian City ................. 143
220. Longyan Exhibition City............................................................................ 144
221. Auto Parts Industrial Park in Changting County........................................ 144
222. Building Material Market of Industry and Trade Zone on the West Bank of
Taiwan Straits,Wuyi Mountain ....................................................................... 145
223. Construction Project of Sanming Old-age Nursing Center........................ 146
224. National Basketball Training Base in Nan’an City .................................... 146
Infrastructure Projects ............................................................................................ 148
225. Highway Project in Meilie Industrial Park, Sanming ................................ 148
226. Putian Urban Rapid Transit System ........................................................... 149
227. Putian Airport Construction ....................................................................... 149
228. “Dry Port” Construction Project in Longyan ............................................. 150
229. Construction Project of Outer Ring Roads in Longyan Downtown Area .. 151
230. Mt. Wuyi Passenger Terminal .................................................................... 151
231. Construction Project of Northern Section of Jiangjun Avenue of Yunxiao 152
232. Construction Project of Yunxiao County Section (Phase II) of Zhangzhou
Coastal Avenue................................................................................................... 153
233. Shacheng Central Fishing Port in Ningde City .......................................... 153
234. Ningde Xinan Harbor Railway Byline ....................................................... 154
235. Storage and Wharf Construction of Operation Zone of Hougang Village,
Shacheng Town,Ningde ..................................................................................... 154
236. Ningde-Gutian Expressway of Expressway Network on the West Bank of
Taiwan Straits,Ningde ........................................................................................ 155
237. Xinan-Shugang Expressway of Expressway Network on the West Bank of
Taiwan Straits,Ningde ........................................................................................ 156
238. Zherong-Chengguan Transit Expressway in National Highway G104...... 156
239. Creativity Highway Project of Nan’an City............................................... 157
240. New Construction of Provincial Road 307 in Nan’an ............................... 157
241. Xiaocuo-Shugang Branch Line of Quangang Expressway Network on the
West Bank of Taiwan Straits .............................................................................. 158
242. Marine Reclamation Construction Project in Sanyu Village, Ningde City 159
243. Huaxun Asia-Pacific International Incubation Base in Changle City ........ 160
244. Xiamen Aosino Chateau ............................................................................ 160
245. Xiamen Aviation Logistics Operation Service Center ............................... 161
246. Jimei Logistics Park ................................................................................... 162
247. Xiamen Financial Center across Taiwan Straits......................................... 162
248. Business Office Project of Xiang’an New Town CBD .............................. 163
249. Haicang Bonded Port ................................................................................. 164
Electronic Information Industry
1. Fuqing Optoelectronic Science and Technology Park (Phase II)
I. Project content and construction scale: Introduce such projects as the upstream
key parts and components and upstream raw materials of intelligent and
multifunctional TFT-LCD panel and LCD as well as new type LED and OLED
backlight and so on to National Fuqing Rongqiao Economic and Technological
Development Zone.
II. Reasons and conditions for project construction: National Fuqing Rongqiao
Economic and Technological Development Zone is the LCD end products
manufacturing base with the largest scale, most concentrated layout and highest
international market share in China, and has great advantages for industrial
development in terms of location, technical conditions and industrial base.
III. Total project investment: over RMB10 billion (determined according to the
actual project scale). Way of cooperation: sole proprietorship or joint venture.
IV. Preliminary work progress: It has been included in the development plan of
opto-electronics industry of Fuqing City and it is basically complete with
infrastructures.
V. Unit for the project: Management Committee and Economic Development
Board of National Fuqing Rongqiao Economic and Technological Development Zone
VI. Contact person: Lin Lixiu, Zhang Wen
Tel: 0591-85377720, 13850148143, 0591-85377885, 13950494715
E-mail: rongqiaojingfa@163.com
2. Zhangzhou Changshan LED Display Project
I. Project construction scale and content: LED display is a display device
composed by lined light emitting diodes. Driven by low voltage scanning, it is
featured by low power consumption, long service life, low cost, high brightness, less
fault, large visual angle and long view distance.
II. Reasons and conditions for project construction: There are now manufacturers
of computer connectors, electronic parts and components, computer mainboards,
1
video cards, industrial computers and laptops in the Notebook Industrial Park of
Changshan Huaqiao Economic Development Zone. By introducing supporting
industries like LED display manufacturers, it will complete the industrial chain.
III. Total project investment: USD50 million. Way of cooperation: sole
proprietorship.
IV. Project economic benefit analysis: New breakthroughs have been constantly
made in LED technology in recent years. As the most widely used display, it also sees
an increase in different fields. The laptops in 2010 only demanded 6 billion LEDs.
Especially, when it becomes a supporting industry in the Notebook Industrial Park, it
will have a large market, a broad market prospect and significant economic benefits.
V. Preliminary work progress: The overall planning and site selection of the
project have been completed, and the water, electricity, road, communication and
drainage are available and the land for use is flattened.
VI. Unit for the project: Management Committee of Changshan Huaqiao
Economic Development Zone of Zhangzhou City
VII. Contact person: Lin Rongyi
Tel: 0596-8626398
E-mail: cskfq457@163.com
3. Quanzhou Nan’an Organic Light Emitting Diode (OLED) Production
Line
I. Project content and construction scale: The project is located in Xiamei Town
Photovoltaic and Electronic Information Industrial Base, Nan’an. It is planned to
introduce a production line with an annual output of 360,000 glass substrates (scale:
370mm×470mm and 730mm×920mm).
II. Reasons and conditions for project construction: The outstanding properties of
OLED in terms of feature, structure and manufacturing process lay a foundation for
its application in flat-panel and soft-screen displays, which can make the displays
lighter, thinner, brighter, high-definition, lower in voltage, highly effective and lower
in cost and respond more rapidly (compared to LCD), thus greatly saving space and
making it easy to carry along.
III. Total project investment: RMB520 million, including RMB485 million fixed
asset investment. Way of cooperation: sole proprietorship to establish factories.
IV. Project economic benefit analysis: After the project is completed, it is
2
estimated that its annual sales revenue will be RMB800 million and create a tax
revenue of RMB240 million.
V. Preliminary work progress: Currently, they are acquiring and flattening the
land for the project.
VI. Unit for the project: Nan’an Innovation, Investment and Development Co.,
Ltd.
VII. Contact person: Mr. Lin
Tel: 13905066391
4. Putian Large LCD End Products
I. Project content and construction scale: It is planned to acquire a 200mu land to
construct a packaging, electronic assembly, welding and debugging production line.
After it is completed, it will have a production capacity of 2 million sets of LCDs a
year, making it an important LCD industrial base in China.
II. Reasons and conditions for project construction: Putian High-tech Industrial
Park is a national LCD production base. With strong scientific research ability, Putian
High-tech Industrial Park has attracted many leading enterprises in the industry such
as Sunway International Holdings Ltd., Tak Shun Technology Group Limited,
Xinying LCD, China New Century Communication Electronics Company Limited
and Fujian Angstrem Semiconductor Co., Ltd., taking a leading position in Fujian
Province in industrial level. The upstream and downstream supporting facilities of the
industrial chain are complete and the information and technology can be shared
locally.
III. Total project investment: RMB600 million, including RMB550 million of
fixed investment and RMB50 million of startup and working capital. Way of
cooperation: joint venture, cooperation, holding or sole proprietorship.
IV. Project economic benefit analysis: The construction period of the project is 1
year. The annual output is expected to be 2 million sets of LCDs. With full capacity,
its average annual sales revenue is expected to reach RMB800 million, and average
annual profits, RMB150 million. The return on investment is 25% and the period for
recovery of investment is 5 years.
V. Preliminary work progress: Putian High-tech Industrial Park has formed five
functional areas including communication industrial park, science and technology
industrial park, electronic information park, mechanical and electrical industrial park
and light industrial park, and has gathered three major industries, electronic
information industry, mechanical manufacturing industry and shoe leather and
3
clothing industry.
VI. Unit for the project: Putian Hanjiang Foreign Trade & Economic
Cooperation Bureau
VII. Contact person: Chen Chunlin
Tel: 0594-3596100
E-mail: chenchunlin0708@163.com
5. Investment Project of LED Energy-saving Lighting and Supporting
Industrial Chain of Zhangzhou Lantian Economic Development
I. Project content and construction scale: The planning land area is 600mu and it
is planned to build a LED lighting product manufacturing base.
II. Reasons and conditions for project construction: An electronic information
industrial cluster focused on LED has taken an initial shape in Lantian Economic
Development Zone. Currently there are LED display, LED lighting and relevant
photoelectricity supporting projects in the Zone, as well as key enterprises and
postdoctoral workstations with national energy-saving lighting high-tech
industrialization basis, showing certain industrial advantages.
III. Total project investment: RMB3 billion
IV. Preliminary work progress: It has entered the land approval and land
acquisition process.
V. Unit for the project: Management Committee of Lantian Economic
Development Zone
VI. Contact person: Chen Jingyu
Tel: 13906959124
6. Quanzhou Anxi LED Chip and Epitaxy Manufacturing and LED
Packaging Application Project
I. Project content and construction scale: 50 LED chip and epitaxy
manufacturing equipments; a LED packaging application project with an annual
output of 100KK.
II. Reasons and conditions for project construction: The opto-electronics industry
is an emerging high-tech industry of innovation of interdisciplinary integrated
technology and is the industry with high growth potential, rapid development speed,
4
strong permeability, wide scope of application and great influence on the society and
economy. The construction of Fujian Quanzhou (Hutou) Opto-electronics Industrial
Park is another major measure Fujian Province takes to make the private economy of
Fujian bigger and stronger and it is of great strategic significance in accelerating the
transformation of the development mode of Fujian, adjusting and optimizing
industrial structure, seizing international high-end position in opto-electronics and PV
industry, promoting the cooperation and interaction in the opto-electronics industry
between Fujian and Taiwan at a higher level and in a broader range and better serving
the development of Western Taiwan Straits.
III. Total project investment: about RMB3.3 billion. Way of cooperation: sole
proprietorship, joint venture or cooperation.
IV. Project economic benefit analysis: After the project is completed, its annual
output value will be RMB2 billion including RMB700 million of profits. The period
for recovery of investment is about 4 years.
V. Preliminary work progress: The overall land planning of the project has been
completed. All of the land for use has been flattened and the infrastructures are under
construction.
VI. Unit for the project: Management Committee of Fujian Quanzhou (Hutou)
Opto-electronics Industrial Park
VII. Contact person: Lin Zhihuang
Tel: 13505039288
Fax: 0595-23405533
E-mail: hu3401091@163.com
7. Sapphire Substrate Cutting Project of Quanzhou Taiwanese Investment
Zone
I. Project content and construction scale: High-brightness LED sapphire substrate
production line
II. Reasons and conditions for project construction: To accelerate the
concentration of opto-electronics industry, Quanzhou Taiwanese Investment Zone
plans to build a 6-square-kilometer opto-electronics industrial park and equip it with
complete infrastructures, which will provide favorable conditions for the development
of opto-electronics industry and electronic communication industry as well as the
transfer of Taiwan PV industry.
5
III. Total project investment: about RMB600 million. Way of cooperation: sole
proprietorship, joint venture or cooperation.
IV. Preliminary work progress: The regulatory plan for the park has been
completed, the road network has taken an initial shape and the park can provide
complete supporting facilities and services.
V. Unit for the project: Technological and Economic Development Bureau of
Quanzhou Taiwanese Investment Zone
VI. Contact person: Miss Zhuang, Miss He
Tel: 13808529689, 0595-27395529, 15159751058, 0595-27308666
E-mail: qz27308666@163.com
8. Sapphire Epitaxial Wafer Project of Quanzhou Taiwanese Investment
Zone
I. Project content and construction scale: Sapphire epitaxial wafer production
line
II. Reasons and conditions for project construction: To accelerate the
concentration of opto-electronics industry, Quanzhou Taiwanese Investment Zone
plans to build a 6-square-kilometer opto-electronics industrial park and equip it with
complete infrastructures, which will provide favorable conditions for the development
of opto-electronics industry and electronic communication industry as well as the
transfer of Taiwan PV industry.
III. Total project investment: about RMB600 million. Way of cooperation: sole
proprietorship, joint venture or cooperation.
IV. Preliminary work progress: The regulatory plan for the park has been
completed, the road network has taken an initial shape and the park can provide
complete supporting facilities and services.
V. Unit for the project: Technological and Economic Development Bureau of
Quanzhou Taiwanese Investment Zone
VI. Contact person: Miss Zhuang, Miss He
Tel: 13808529689, 0595-27395529, 15159751058, 0595-27308666
E-mail: qz27308666@163.com
6
9. Quanzhou Nan’an High-power Special LED Lamp Production Line
I. Project construction content and site selection: The project is located in
Quanzhou Nan’an Photovoltaic and Electronic Information Industrial Base. It is
planned to introduce a high-power special LED lamp production line to especially
produce high-power LED landscape lamps, solar street lamps, solar garden lamps,
traffic lights, miner's lamps, illuminating lamps, power LEDs and drive and so on.
II. Project construction reasons and market analysis: Compared to the current
lighting sources of its kind, LED (light emitting diode) has many advantages such as
long service life, high brightness, low voltage drive, small power for lighting on,
small content of infrared light and ultraviolet light, dimmable control, dynamic
distinguishing, light weight, directional light and excellent applicability in severe
environment.
III. Total project investment: about RMB50 million. Way of cooperation: sole
proprietorship to establish factories.
IV. Project economic benefit analysis: It is estimated that the annual sales
revenue can reach up to RMB150 million and create a tax revenue of about RMB30
million.
V. Preliminary work progress: The planning of Nan’an Photovoltaic and
Electronic Information Industrial Base has been completed. The standard factories in
the startup area are under construction.
VI. Unit for the project: Nan’an Innovation, Investment and Development Co.,
Ltd.
VII. Contact person: Lin Rongdui
Tel: 13905066391
Fax: 0595-86766908
10. Quanzhou Nan’an LED Epitaxial Wafer and Chip Manufacturing and
Packaging Production Line
I. Project content and construction scale: The project is located in Xiamei Town
Photovoltaic and Electronic Information Industrial Base. It is planned to introduce a
production line that can produce 200,000 square inches of LED epitaxial wafers
(including 30,000 square inches of GaN-based LED epitaxial wafers), 6 billion LED
chips (including 200 million GaN-based LED chips), 600 million LED components
7
(including 200 million chip LED components) on a yearly basis and its packaging
production line.
II. Reasons and conditions for project construction: Compared to the current
lighting sources of its kind, LED (light emitting diode) has many advantages such as
long service life, high brightness, low voltage drive, small power for lighting on,
small content of infrared light and ultraviolet light, dimmable control, dynamic
distinguishing, light weight, directional light and excellent applicability in severe
environment.
III. Total project investment: about USD38 million. Way of cooperation: sole
proprietorship to establish factories.
IV. Project economic benefit analysis: It is estimated that the annual sales
revenue can reach up to USD60 million and create a tax revenue of USD16 million.
V. Preliminary work progress: Currently, they are acquiring and flattening the
land for the project.
VI. Unit for the project: Nan’an Innovation, Investment and Development Co.,
Ltd.
VII. Contact person: Mr. Lin
Tel: 13905066391
Fax: 0595-86766908
11. Putian LED Epitaxial Wafer and Chip Production Project
I. Project content and construction scale: construct ten LED epitaxial wafer and
chip production lines and construct LED research & development center.
II. Reasons and conditions for project construction: The application of LED
lighting, as the fourth generation lighting source, is looming ahead. As it adopts
semiconductor lighting, it has low power consumption and can save 80% energy
compared to incandescent filament lamps, and 60% to fluorescent lamps. In addition,
it has many colors and doesn’t contain any mercury, silver, poisonous gas or
radioactive element, making it true green lighting.
III. Total project investment: RMB380 million. Way of cooperation: joint venture
or sole proprietorship.
IV. Project economic benefit analysis: With full capacity, the project can create
an annual output value of over RMB3 billion. It is estimated that the investment can
8
be recovered in three to five years.
V. Preliminary work progress: Compile the project proposal.
VI. Unit for the project: Chengxiang Investment Project Service Center
(Business Investment Bureau)
VII. Contact person: Hong Leiming
Tel: 13607539551
Fax: 0594-2826628
E-mail: cxqtz2008@163.com
12. Sanming Qingliu Electronic Industrial Park Project
I. Project content and construction scale: The planning area is 500mu. It is
planned to introduce 10 to 15 supporting electronics manufacturing enterprises and
construct electronics series projects with an annual production of 500 million energy
saving lamps, 1 billion magnetic coils, 500 million PCS magnetic rings, 500 million
PCS inductances and LED, electronic components and lighting source and so on.
II. Reasons and conditions for project construction: Conveniently located in the
south of the urban area, Qingliu Longxiang Industrial Park adjoins the Yongning
Section of Quanzhou-Nanning Expressway. Abundant in such production factors as
water and electricity, it provides foundation advantages for the electronic industry of
Qingliu County. A 500mu industrial land has been mapped out in the industrial park to
build an electronic products processing park focusing on electronic products.
III. Total project investment: RMB500 million. Way of cooperation: sole
proprietorship, joint venture or cooperation.
IV. Project economic benefit analysis: It is estimated that the investment can be
recovered in three to five years.
V. Preliminary work progress: The project proposal has been completed.
VI. Unit for the project: Management Committee of Qingliu Economic
Development Zone
VII. Contact person: Yang Shengfa
Tel: 18950994733
E-mail: qljxgwh@163.com
9
13. Introduction to the Construction Project of Pucheng Industrial Park
LED Incubation Base, Nanping
I. Project content and construction scale: It is planned to build the LED light
source packaging and application lamp laboratory and equip 3D light distribution
testing system and so on.
II. Reasons and conditions for project construction: As an important strategic
emerging industry supported by the state - new energy industry as well as an industry
that the state encourages, the project is an upgrade and update of traditional industry.
With energy-saving and efficient products, the project has great benefits but little
pollution.
III. Total project investment: RMB200 million. Way of cooperation: joint
venture.
IV. Preliminary work progress: An agreement has been signed with Fujian
Daming Electronics Co., Ltd. to settle in the industrial park.
V. Unit for the project: Management Committee of Pucheng Industrial Park
VI. Contact person: Zhou Zhijun
Tel: 13950670088
E-mail: fjpcgyyq@163.com
14 Longyan liancheng Sapphire Substrate and Epitaxial Wafer Production
Project
I. Project content and construction scale: It is planned to construct a project with
an annual output of 200,000 2-inch sapphire substrates, 150,000 4-inch sapphire
substrates and 150,000 4-inch sapphire epitaxial wafers in Phase I.
II. Reasons and conditions for project construction: Sapphire substrates, as
important technical crystalline materials, are widely applied in the windows and
reflectors of lasers, the semiconductor silicon epitaxial substrates, the integrated chips
with insulating substrates, the infrared transmitting materials in the aerospace industry,
the epitaxial substrate materials of gallium nitride and a series of high-tech fields, as
well as in the civil industry. Sapphire wafers are still the most economical, maturest
and mostly used substrate materials of gallium nitride.
III. Total project investment: USD126.98 million. Way of cooperation: sole
proprietorship.
10
IV. Preliminary work progress: The land use planning of the project has been
completed.
V. Unit for the project: Liancheng Business Investment Bureau
VI. Contact person: Luo Liqin
Tel: 13959067228 E-mail: lc8922851@163.com
15. Longyan Changting Rare Earth Luminescent Materials and Application
Project
I. Project content and construction scale: It is planned to construct a project with
an annual output of 4,000kg LED fluorescent powder, 400,000 energy-saving LED
luminaires and 60 million energy-saving rare earth lamps.
II. Reasons and conditions for project construction: With such advantages as high
luminous efficiency, excellent color rendering index, energy conservation and long
service life, fluorescent lamps have a great market, and the conditions for large-scale
energy-saving lamp production have been met. In addition, Changting is the only
county in Fujian Province with rare earth separation enterprises, whose separation
capacity in 2010 was 7,000 tons, which can meet the raw material supply of the
project.
III. Total project investment: RMB520 million. Way of cooperation: joint venture
or sole proprietorship.
IV. Project economic benefit analysis: After the project is completed, its annual
output value will reach RMB2.5 billion, including 340 million of benefit.
V. Preliminary work progress: The project assessment has been completed.
VI. Unit for the project: Changting Rare Earth Industry Office
VII. Contact person: Zhong Keliang
Tel: 13600996699
16. Ningde Zhouning Longguang High-efficiency LED Lighting Lamp
Project
I. Project content and construction scale: The planning area is about 50mu. It is
11
planned to build standard plants, introduce advanced domestic and overseas technical
equipments and develop Zhouning Longguang high-efficiency LED lighting series
products.
II. Reasons and conditions for project construction: Currently, most of the
high-end LED lighting lamp manufacturers are foreign manufacturers. Therefore, with
the broad LED application area around the corner, the project is very promising.
III. Total project investment: RMB120 million. Way of cooperation: sole
proprietorship.
IV. Preliminary work progress: It has been included in the high-tech industry
planning of the Twelfth Five-year Plan of Zhouning County. Such preliminary work
as feasibility study plan preparation has been completed.
V. Unit for the project: Zhouning Development and Reform Bureau
VI. Contact person: Chen Xinyuan
Tel: 0593-5665739
17. Zhangzhou Dongshan Thin-film Solar Cells
I. Project construction scale and content: a land area of 100mu and an annual
output of 200MW thin-film solar cells.
II.Reasons and conditions for project construction: Dongshan Photovoltaics and
New Glass Materials Industrial Park is a project to be implemented as specified in the
outline of the Twelfth Five-year Plan of Fujian Province and one of the two PV glass
and solar cell industrial bases that Fujian Provincial Party Committee and the People’s
Government of Fujian Province have decided to build in the west coast of the Taiwan
Straits (Zhangzhou). The Industrial Park focuses mainly on projects related to PV and
new materials such as thin-film solar cell modules, online and offline low-emissivity
coated glasses, low-e glasses and automotive glasses. After it is completed, it will
realize an annual output value of RMB20 billion and create a tax revenue of RMB2
billion, becoming an important national industrial base of PV and new glass materials.
III. Total project investment: RMB126 million.
IV. Preliminary work progress: The overall planning and site selection of the
project have been completed, and the water, electricity, road, communication and
drainage are available and the land for use is flattened.
12
V. Unit for the project: Dongshan Economic and Technological Development
Zone
VI. Contact person: Lin Wanquan
Tel: 0596-5885007
E-mail: dsetdz@163.com
18. Zhangzhou Hua’an Energy-saving Opto-electronics Industry
I. Project content and construction scale: the planning land is 3,000mu.
II. Reasons and conditions for project construction: The opto-electronics industry
in Hua’an Economic Development Zone has grown substantially. With Fortune 500
enterprises settling in, it has preliminarily set the new light source, new energy and
new material industries represented by semiconductor lighting and solar photovoltaics
as its development orientation. The industrial chain has taken an initial shape and the
industrial cluster is basically formed.
III. Total project investment: RMB1.8 billion
IV. Preliminary work progress: Currently a batch of leading enterprises in the
industry such as Lisheng Electronic & Lighting (Xiamen) Co., Ltd., Xiamen
Faratronic Co., Ltd., Zhangzhou Tongtian Electronic Co., Ltd. and Yueqing AnKong
Electrical Co., Ltd. has settled in the Development Zone.
V. Unit for the project: Hua’an Economic Development Zone
VI. Contact person: Huang Laixing
Tel: 0596-7362212
19. Zhangzhou Dongshan Battery Separator Project
I. Project content and construction scale: Construct modern standard plants and
expand the scale of production to meet the increasing demand in AGM separators for
the development of different domestic industries.
II. Reasons and conditions for project construction: It solves the problems such
as easy short circuit of battery separators, high self-discharge rate, insufficient active
ion substance and low recombination efficiency and so on, which provides better
insulating effects, longer service life and more environmental-friendly products. The
comprehensive technical level of the products has reached the advanced level of
13
foreign similar products and they can substitute imported products and be exported to
earn foreign exchange.
III. Total project investment: RMB400 million
IV. Preliminary work progress: The maintenance-free lead-acid battery separator
- AGM separator project has settled in the Development Zone.
V. Unit for the project: Kony Battery Separator Co., Ltd.
VI. Contact person: Lin Congquan
Tel: 13960015567
20. Quanzhou Nan’an Photovoltaic and Electronic Information Industrial
Base
I. Project content and construction scale: It is planned to complete the
construction of the Base by 2020 in three phases and focus on the development of PV
and electronic information industrial cluster such as PV and LED. It is estimated that
the Base will form a 300MW, 600MW and 1,000MW PV cell industrial chain by 2011,
2015 and 2020, becoming a National Torch Program characteristic industrial base and
a national PV and electronic information industrial park.
II. Reasons and conditions for project construction: Solar power generation has
the advantages that other conventional energy resources don’t have such as full
cleanness, absolute safety, more universal and sufficient resources, long service life
and free maintenance and so on. Experts predict that photovoltaic power generation
will surpass nuclear power and become one of the most important basic energies in
the first half of the 21th century.
III. Total project investment: RMB600 million. Way of cooperation: joint venture
and cooperation in site development, construction of standard plants or investment in
plants.
IV. Project economic benefit analysis: It is estimated that the three phases of the
base will be completed in 2020. By then, a 1,000MW PV cell industrial chain will be
formed, realizing a production value of RMB100 billion and creating a tax revenue of
RMB2.5 billion.
V. Preliminary work progress: Currently, the planning for the base has been
completed and the construction of Phase I municipal works has been partly completed.
Currently, 15 projects have settled in, of which, 6 projects have settled in the
14
incubation base and are operating, while the other projects are under construction.
VI. Unit for the project: Nan’an Photovoltaic and Electronic Investment and
Development Company
VII. Project responsible person: Mr. Lin
Tel: 13905066391
21. Quanzhou Nan’an Solar Photovoltaic System Battery Production Line
I. Project content and construction scale: The project is located in Xiamei Town
Photovoltaic and Electronic Information Industrial Base. It is planned to introduce a
high-power and large-capacity battery production for solar photovoltaic system that
can produce 2 million pieces annually.
II. Reasons and conditions for project construction: Solar power generation has
the advantages that other conventional energy resources don’t have such as full
cleanness, absolute safety, more universal and sufficient resources, long service life
and free maintenance and so on. With the fast development of world photovoltaic
industry, the demand of high-power and large-capacity batteries will also increase
significantly. Therefore, the market of large-capacity batteries for solar photovoltaic
system will have a promising future.
III. Total project investment: about USD15 million. Way of cooperation: sole
proprietorship to establish factories.
IV. Project economic benefit analysis: After it is completed, it is estimated that
its annual sales revenue can reach up to USD40 million and create a tax revenue of
about USD8.5 million.
V. Preliminary work progress: Currently, they are acquiring and flattening the
land for the project.
VI. Unit for the project: Nan’an Innovation, Investment and Development Co.,
Ltd.
VII. Contact person: Mr. Lin
Tel: 13905066391
Fax: 0595-86766908
15
22. Sanming Qingliu Photovoltaic Solar Energy Industrial Park Project
I. Project content and construction scale: Covering an area of 1,000mu, the
Photovoltaic Solar Energy Industrial Park of Qingliu Economic Development Zone
plans to introduce six to eight relevant enterprises and focus on the development of
solar cells and modules, special production equipments for solar cells, TCO
conducting glasses, coating equipments of TCO conducting glasses, laser equipments,
solar photovoltaic off-grid power generation system and solar lamps.
II. Reasons and conditions for project construction: As an important carrier of the
development of Fujian PV industry and the development platform of application base
of the photovoltaic solar industry, Qingliu presents great development opportunities
and broad development prospect in supporting the photovoltaic solar industry.
III. Total project investment: RMB6 billion. Way of cooperation: sole
proprietorship.
IV. Project economic benefit analysis: The investor may set the investment scale
itself and implement the project by stages. It is estimated the investment will be
recovered in three to five years.
V. Preliminary work progress: The project proposal has been completed.
VI. Unit for the project: Management Committee of Qingliu Economic
Development Zone
VII. Contact person: Zhang Shengqun
Tel: 15860853066
E-mail: qljxgwh@163.com
23. Fujian (Pucheng) Jimin Photovoltaic and Electronic Technology Park
I. Project content and construction scale: It is planned to build a thin-film solar
cell production line and engage in the research and development of such technologies
as solar photovoltaic conversion.
II. Reasons and conditions for project construction: Located in Fujian Pucheng
Industrial Park, Fujian Jimin Electronic Technology Co., Ltd., is only 2.5 kilometers
from the county town center. Covering a land area of 120mu, it currently has 50,000
square meters of standard factories. The industrial park is a Sino-foreign park
specialized in electronic technology.
III. Total project investment: RMB1 billion. Way of cooperation: cooperation,
16
joint venture or sole proprietorship.
IV. Preliminary work progress: The overall planning, feasibility research, project
approval procedures and environmental impact assessment of the project have been
completed. Most plants have been completed.
V. Unit for the project: Fujian Jimin Electronic Technology Co., Ltd.
VI. Contact person: Xu Shiting
Tel: 13950690979
24. Northern Fujian Environment-friendly Lead Crystal Battery Production
Project, Nanping
I. Project content and construction scale: The total land area is 300mu, of which
106,000 square meters will be used to to build manufacturing shops, office and
research and development complex buildings and other subsidiary rooms. It is
planned to build a new electric vehicle battery and UPS battery production line with
an annual production of 3 million sets of electric vehicle batteries and 1 million sets
of UPS batteries.
II. Reasons and conditions for project construction: The lead crystal batteries
manufactured with new technology and process have different electrolyte than general
electrolyte, which are crystal form without any leakage, which makes them green
batteries. The new type environmentally friendly products are rapidly entering the
lives of consumers of different fields.
III. Total project investment: RMB560 million. Way of cooperation: joint venture
or sole proprietorship.
IV. Project economic benefit analysis: After the project is completed, it can
achieve an annual sales revenue of RMB880 million, including RMB267.68 million
of profit. The return on investment is 47.8% and the profit after tax is RMB200.76
million. The period for recovery of investment after income tax is 2.8 years.
V. Preliminary work progress: The feasibility research is under progress.
VI. Unit for the project: Business Investment Bureau of Management Committee
of Northern Fujian Economic Development Zone
VII. Contact person: Fang Dongjie
Tel: 0599-5671266, 13950689985 E-mail: zsjggyx@163.com
17
25. Longyan Liancheng Monocrystalline Silicon and Solar Cell Module
Production Project
I. Project content and construction scale: The project land is 1,000mu. It is
planned to build two monocrystalline silicon polish lines with an annual output of 30
million 8 to 10-inch semiconductor monocrystalline silicons and twelve production
lines with an annual output of 300MW crystalline silicon solar cell modules.
II. Reasons and conditions for project construction: The project can provide
monocrystalline silicon pieces needed by the semiconductor chip industry, which is
good for the development of the semiconductor industry. It can also provide
crystalline silicon solar cell modules for the photovoltaic industry, which is good for
the development of the photovoltaic industry.
III. Total project investment: RMB890 million. Way of cooperation: sole
proprietorship.
IV. Project economic benefit analysis: After the project is put into operation, it
can achieve an annual sales revenue of RMB15 billion (including tax), and the profit
after tax will be RMB215.5518 million. The period for recovery of investment after
tax is 6.06 years.
V. Preliminary work progress: The project feasibility report has been completed.
VI. Unit for the project: Liancheng Economic and Trade Bureau
VII. Contact person: Chen Xing
Tel: 13507501896
26. Fuqing Light Control Industry Project
I. Project construction content and scale: to introduce light control industry
projects such as photochromic glass to achieve a production scale of over RMB1
billion a year.
II. Reasons and conditions for project construction: National Fuqing Rongqiao
Economic and Technological Development Zone, a national economic and
technological development zone approved by the State Council, is dominated by
opto-electronics industry. Complete with infrastructures, the Development Zone is
also in a favorable location. Currently, most light control materials are employed in
18
such fields as optical information storage, light control, optical switch, optical device
materials, optical information gene materials and modifier gene chip materials and so
on, showing a great market prospect.
III. Total project investment: RMB300 million. Way of cooperation: sole
proprietorship or joint venture.
IV. Project economic benefit analysis: The market demand is stable and shows
growth trend and the economic benefit is good.
V. Preliminary work progress: All kinds of preparatory work are under way.
VI. Unit for the project: Management Committee and Economic Development
Board of National Fuqing Rongqiao Economic and Technological Development Zone
VII. Contact person: Zhang Wen;
Tel: 13950494715
E-mail: rongqiaojingfa@163.com
27. Investment Project of Fuzhou Electromechanical Industrial Park
I. Project construction content and scale: Fuzhou Electromechanical Industrial
Park, covering an area of 321.79 hectares (or 4,827mu), mainly introduces enterprises
of complete equipment manufacturing, precision machinery, optoelectronics,
electronics and relevant industrial chains.
II. Reasons and conditions for project construction: With convenient transport
and rich landscape resources, the Park shows a broad space for development and
mature development conditions.
III. Total project investment: The enterprise raises the funds by itself according
to the actual condition of the project. Way of cooperation: investment by domestic
enterprises, total foreign investment, joint venture and cooperation.
IV. Project economic benefit analysis: after its completion, Fuzhou
Electromechanical Industrial Park will promote the industrial development in Fuzhou
City and even in Fujian Province, strengthen regional economy, create jobs and
increase state tax revenue, showing great economic and social benefits.
V. Preliminary work progress: All kinds of preparatory work are under way.
VI. Unit for the project: Management Committee of Fuzhou Jinshan Industrial
Zone
19
VII. Contact person: Shi Jianhui, Guo Xiaoxia
Tel: 0591-83856888, 0591-83856188
Fax: 0591-83856588 E-mail: 373362187@qq.com
28. Mechanical and Electronic Industrial Park Project of Lianjiang
Economic Development Zone,Fuzhou
I. Project content and construction scale: Shangang Industrial Concentration Area
of Fujian Lianjiang Economic Development Zone is dominated by mechanical and
electronic industry. The planed land for use for Phase II Project is 2,270mu (about
1,513,333.33m2), of which 1,800mu (equal to 1,200,000m2) is industrial land.
Currently, about 500mu (about 333,333.33m2) is developed and it is planned to
introduce 3 to 9 mechanical and electronic industry projects.
II. Reasons and conditions for project construction: Located in the “Half-hour
Economic Circle” of Fuzhou City, Fujian Lianjiang Economic Development Zone
enjoys convenient transportation; and inside it is completed with infrastructures such
as road, tap water, electricity and pollution discharge system and so on. Currently, the
Zone has introduced some 50 small and large electromechanical projects including
generator set, transformer, cable, motor bearing component, locomotive component
and hardware, forming an initial electromechanical supporting industry cluster.
III. Total project investment: The total investment for a single project is over
USD10 million. Way of cooperation: sole proprietorship or joint venture.
IV. Preliminary work progress: As the land for use for Phase I and II Project
complies with the state land policy, the land acquisition has been completed and
relevant procedures have been completed. The land for Phase I has been leveled and
the leveling of the land for Phase II is expected to be completed by the end of 2012.
V. Unit for the project: Management Committee of Fujian Lianjiang Economic
Development Zone
VI. Contact person: Wang Jinhai (mobile phone number: 13805071308)
Tel: 0591-26251899, 26158893
Fax: 0591-26231580
E-mail: lj26131166@qq.com
20
29. Zhangzhou Changshan Micro-electronics and Electronic Component
Project
I. Project content and construction scale: manufacture of micro-electronics and
electronic components, mainly referring to the development and manufacture of
integrated circuits and packaging, thin-film vacuum fluorescent displays, power
electronic devices, artificial intelligence components and sensing elements.
II. Reasons and conditions for project construction: By introducing
manufacturers of micro-electronics and electronic components to support other
industries in the industrial park, it will complete the industrial chain, and the project
will have a large market, a broad market prospect and significant economic benefits.
III. Total project investment: RMB63 million. Way of cooperation: joint venture
or sole proprietorship.
IV. Preliminary work progress: The planning of the High-tech Industrial Park
(Notebook Industrial Park) Changshan Huaqiao Economic Development Zone has
been completed.
V. Unit for the project: Management Committee of Changshan Huaqiao
Economic Development Zone of Zhangzhou City
VI. Contact person: Lin Rongyi
Tel: 0596-8626398 E-mail: cskfq457@163.com
30. Zhangzhou Dongshan Glass Deep Processing Project
I. Project content and construction scale: The project covers an area of 100mu
and is about the production of low-e coated glasses, bent toughened glasses, laminated
glasses and hollow glasses.
II. Reasons and conditions for project construction: The Development Zones has
such advantages as silica sand resources, coastline ports, market location and talents
of glass technology and gathers powerful technology stream, logistics, information
stream and business flow, constructing a complete multifunctional and outward sales
logistics network.
III. Total project investment: RMB283.5 million. Way of cooperation: joint
venture or sole proprietorship.
IV. Preliminary work progress: The overall planning and site selection of the
21
project have been completed, and the water, electricity, road, communication and
drainage are available and the land for use is flattened.
V. Unit for the project: Dongshan Economic Development Zone
VI. Contact person: Lin Wanquan
Tel: 0596-5885007
E-mail: dsetdz@163.com
31. Zhangzhou zhangpu High-tech Electronic Industrial Park Project
I. Project content and construction scale: The planning land area of the High-tech
Electronic Industrial Park is 500mu. It is planned to build a manufacturing base of IT
products, high-tech electronic products and electronic components related to
automatic control, household appliances, communication, network and PC.
II. Reasons and conditions for project construction: Located favorably in
Zhangpu County, Jinpu Industrial Park is 119km from Xiamen Port, 140km from
Shantou, 15km from Zhangpu Interchange of Zhangzhou-Zhaoan Expressway, 1.5km
from Zhangpu Station of Xiamen-Shenzhen High-speed Rail which is under
construction and with National Road 324 on its north side. With convenient
transportation, it is also complete with water and power supply and road system. As
an emerging industrial park in Zhangpu, Jinpu Industrial Park has advantages in
location, land price, service, policy and facilities and so on. To meet the requirements
of “overall planning, implementation by step and high-standard construction”, it will
create an ideal investment environment for domestic and overseas businessmen.
III. Total project investment: RMB315 million. Way of cooperation: joint venture
or sole proprietorship.
IV. Preliminary work progress: The project planning and project assessment have
been completed. Some land has been flattened. The enterprise can start construction
after settling.
V. Unit for the project: Zhangpu Jinpu Industrial Park
VI. Contact person: Li Chunyue
Tel: 0596-3182066
22
32. Opto-electronics Industrial Park of Quanzhou Taiwanese Investment
Zone
I. Project content and construction scale: The planning area is 6 square
kilometers. It is planned to mainly introduce LED, photovoltaic industry, digital
microchip semiconductor, electronic component and communication equipment
industries.
II. Reasons and conditions for project construction: Opto-electronics Industrial
Park has a beautiful environment, convenient traffic and complete infrastructures,
providing favorable conditions for developing opto-electronics industry and electronic
communication industry and undertaking the transfer of Taiwan PV industry.
III. Total project investment: about RMB30 billion. Way of cooperation: sole
proprietorship, joint venture or cooperation.
IV. Preliminary work progress: The regulatory plan for the park has been
completed, the road network has taken an initial shape and the park can provide
complete supporting facilities and services.
V. Unit for the project: Technological and Economic Development Bureau of
Quanzhou Taiwanese Investment Zone
VI. Contact person: Miss Zhuang, Miss He
Tel: 13808529689, 0595-27395529, 15159751058, 0595-27308666
E-mail: qz27308666@163.com
33. Quanzhou Nan’an Automotive Electronics Product Development and
Production Project
I. Project content and construction scale: The project is located in Nan’an
Binjiang Mechanical Equipment Manufacturing Base. It is planned to introduce world
advanced technology and equipments to establish an automotive electronics product
production line. The project mainly develops and produces: 1. auto audiovisual
entertainment system; 2. auto computer information integration system; 3. car body
electronic intelligence integration system; and 4. ignition coils, wiring harness and
CAN bus and so on.
II. Reasons and conditions for project construction: With the widespread use and
rapid development of electronic information technology, electronic technology and
products take a larger and larger proportion in the application in automotive,
23
providing a broader market space for the development of automotive electronics.
There are over 1,000 auto parts and engineering machinery enterprises in Quanzhou
with an annual output value of about RMB10 billion, showing a cluster competitive
advantage in Fujian Province and even in China. Currently 41 auto parts and
engineering machinery enterprises have settled in Nan’an Binjiang Mechanical
Equipment Manufacturing Base, with a total investment of up to RMB3.6 billion.
Settling in this base, the project can have relatively complete supporting industries,
which is good for product promotion and enterprise development.
III. Total project investment: about USD30 million. Way of cooperation: sole
proprietorship to establish factories.
IV. Project economic benefit analysis: After the project is completed, it can
realize an annual sales revenue of USD50 million and create a tax revenue of USD15
million.
V. Preliminary work progress: The lot for the project has been reported to Fujian
Office of Land and Resources for review and approval.
VI. Unit for the project: Nan’an Binjiang Investment and Development Co., Ltd.
VII. Contact person: Mr. Huang
Tel: 13905076187
34. Longyan Shanghang 500t Optical Fiber Perform Production Line
I. Project content and construction scale: It is planned to build an optical fiber
perform production line with an annual output of 500 tons.
II. Reasons and conditions for project construction: Abundant in mineral
resources, Shanghang County provides sufficient raw materials of the project. In
addition, the industrial park is conveniently located and the supporting facilities in it
are well developed.
III. Total project investment: USD182.54 million. Way of cooperation: sole
proprietorship.
IV. Preliminary work progress: The feasibility study report of the project has
been completed.
V. Unit for the project: Fujian Shanghang Industrial Park Office
VI. Contact person: Yuan Guiquan
24
Tel: 13950831453
E-mail: 1473948077@qq.com
35. Quanzhou Anxi High-quality Bathroom Plumbing and Mechanical and
Electrical Valve Production Project
I. Project content and construction scale: The project covers a land area of
1,300mu. It is planned to construct manufacturing enterprises and enterprise
headquarters that integrate the production, processing, scientific research, display,
sales and warehouse logistics of hardware products such as bathroom plumbing and
mechanical and electrical valves and business and residence.
II. Reasons and conditions for project construction: The project is less than three
kilometers from China Water Heating City in Nan’an. The project products can
complement each other’s advantages with the sanitary product industries in China
Water Heating City. By making full use of the businessmen resources gathering in
China Water Heating City, it will produce great scale effect.
III. Total project investment: RMB1 billion. Way of cooperation: sole
proprietorship or cooperation.
IV. Project economic benefit analysis: After the project is completed, its annual
output value will be over RMB500 million, including RMB80 million net profits. The
period for recovery of investment is 6 years.
V. Preliminary work progress: The land planning of the project has been
completed and special service agencies have been established.
VI. Unit for the project: Fujian Longdu Construction and Development Co., Ltd.
VII. Contact person: Wu Yixiong
Tel: 13805931111
E-mail: 13805931111@139.com
36. Quanzhou Software Park
I. Project content and construction scale: The planning land area of the Park is
1,085mu and it is planned to divide it into two major functional areas: research &
development and incubation area and business service area. In Phase I Project, the
complex building, research & development office building, apartments and cultural
and recreational center will be completed, and in Phase II Project, Haixi (Quanzhou)
Cloud Computing Industrial Park will be built.
25
II. Reasons and conditions for project construction: Located in the site that is
reasonably selected for the project, Quanzhou Software Park has obvious location
advantage and is also complete in construction conditions. In addition, the excellent
talent development and exchange environment of Quanzhou create very favorable
conditions for the construction and development of the Software Park.
III. Total project investment: about RMB2.27 billion.
IV. Project economic benefit analysis: Quanzhou Software Park project can
accelerate the informatization of Quanzhou private enterprises, promote the
optimization and upgrading of the manufacturing industry and enhance the
comprehensive economic strength of the central urban area of Quanzhou, showing
great economic and social benefits.
V. Preliminary work progress: The 500mu land for Phase I Project of the
Software Park has been flattened and the infrastructures such as municipal roads have
been completed; currently the land requisition and relocation work for Phase II
Project is in progress.
VI. Unit for the project: Quanzhou Software Park Construction and Development
Co., Ltd.
VII. Project responsible person: Wang Wei
Tel: 0595-22899618
E-mail: fjqzrjy@163.com
37. Quanzhou Fengze Haixi Electronic Information Industry Incubation
Base
I. Project content and construction scale: Phase I Project covers a land area of
53mu, including one 13-floor comprehensive research & development building, five
standard plants and two apartment buildings, equipped with public service facilities
such as high-tech product exhibition halls, multifunctional lecture halls and training
rooms.
II. Reasons and conditions for project construction: Relying on the comparative
advantages and solid foundation of Quanzhou in microwave technique and wireless
communication industry, the project gives full play to the resource superiority and
driving role of Fujian Mobile Communication Industrial Alliance, which accelerates
the formation of industrial chain, promotes the base to become an important growth
pole in regional economy and drive the upgrading of the regional industrial structure.
III. Total project investment: about RMB1 billion. Way of cooperation: The base
26
mainly introduces microwave and digital interphone industries and their extended
industries. Enterprises settle in the base by renting standard plants or research and
development sites or through project cooperation.
IV. Project economic benefit analysis: After the project is completed, it will form
a public service platform that integrates research and development, test, talent training,
marketing, planning for company listing and investment and financing services,
becoming a scientific and technological service center for the electronic
communication industry, an important base for the transformation of high-tech
achievements, a cradle of high-tech enterprises and a place to cultivate technical
entrepreneurs.
V. Preliminary work progress: Such works in Phase I Project as the plants, the
comprehensive research & development building and the apartment buildings have
been completed.
VI. Unit for the project: Fujian Yucheng Scientific and Technological Service
Co., Ltd.
VII. Contact person: Wang Jianming
Tel: 13960390707
E-mail: 13960390707@139.com
38. Quanzhou Anxi Service Outsourcing Project of China International
Information Technology (Fujian) Industrial Park
I. Project content and construction scale: The total land area of the industrial park
is about 10,000mu, of which the land area of Phase I Project is about 1,500mu. The
total building area of Phase I Project is about 900,000 square meters, which is mainly
used to construct the core business area and comprehensive service area.
II. Reasons and conditions for project construction: In the development strategy
of Western Taiwan Straits Economic Zone, informatization and digitization are not
only effective ways to promote new industrialization but also important guarantee of
the security of national strategy.
III. Total project investment: It is planned to complete Phase I Project within
three years in three phases, with a total investment of about RMB10 billion. Way of
cooperation: joint venture or partnership.
IV. Project economic benefit analysis: After it is completed, it will be a global
platform for the structural upgrading of information-based industry and for the
application and promotion of information technology, and also the largest information
27
technology service outsourcing base in Eastern China.
V. Preliminary work progress: Currently, the overall planning for Phase I Project
of the park has been completed. The data disaster recovery room, a core business
content, is currently under pile foundation construction.
VI. Unit for the project: Management Committee of China International
Information Technology (Fujian) Industrial Park
VII. Contact person: Xu Qishu
Tel: 13805933833
Fax: 0595-36119555
E-mail: 13805933833@qq.com
39. Construction of Putian Anfu Online Trade City
I. Project content and construction scale: To construct an online trading platform,
including third party payment platform, network foundation platform, network
management platform and supporting physical facilities.
II. Reasons and conditions for project construction: 1) it complies with industrial
policy; 2) it meets economic development needs; and 3) it has superior basic
conditions.
III. Total project investment: 1) RMB300 million for the e-commerce platform
project, of which RMB210 million is used for the construction of electronic network
platform and website promotion and marketing; 2) RMB600 million for supporting
service projects. Way of cooperation: sole proprietorship, joint venture or cooperation.
IV. Project economic benefit analysis: After the project is completed, it can
realize an annual output value of RMB10 billion and create a tax revenue of RMB3
billion.
V. Preliminary work progress: The project has been included in the development
planning of Twelfth Five-year Plan of Putian City.
VI. Unit for the project: Putian Chengxiang Longqiao Street Committee
VII. Contact person: Zheng Youhong
Tel: 15160238401
E-mail: 644071876@qq.com
28
40. Introduction to Wuyi New District Software Industrial Park, Nanping
I. Project content and construction scale: The planning land area is 1,000mu. It is
planned to divide the industrial park into two major functional areas, an 800mu
research and development and incubation area and a 200mu business service area, and
to construct it according to the planning layout following the principles of high
starting point, high standard, high level and high grade.
II. Reasons and conditions for project construction: The construction and
implementation of the project will accelerate the informatization of private enterprises
in northern Fujian Province, promote the upgrading of the manufacturing industry and
optimize the industrial structure. Located in the site that is reasonably selected for the
project, it has obvious location advantage and is also basically complete in
construction conditions. In addition, the excellent talent training and exchange
environment of Wuyi University nearby provides a steady flow of talents for the
construction of the software industrial park.
III. Total project investment: RMB1 billion. Way of cooperation: sole
proprietorship, joint venture or cooperation.
IV. Preliminary work progress: The location of the project has been determined,
the land acquisition work is basically completed and the underpass works of
bidirectional four-lane Daofeng-South have been completed.
V. Unit for the project: Business Investment Bureau of Nanping Wuyi New
District Management Committee
VI. Contact person: Fang Dongjie
Tel: 0599-5671266 E-mail: zsjggyx@163.com
29
Mechanical Equipment Industry
41. Fuzhou Fuqing Jiangyin Metallurgical Machinery Industry Project
I. Project content and construction scale: in compliance with the requirements of
national environmental –protection policies and latest industrial orientation; in
compliance with the industrial function orientation of Jiangyin Development Zone;
have a comparatively well-developed industrial chain and capable of promoting the
development of upstream and downstream industries; a metallurgical machinery
manufacturing industry project with high technical contents and high added value.
II. Reasons and conditions for project construction: project’s location –
Jiangyin industrial concentration district is located on the southeast coast of Fuqing
with abundant port resources and broad industrial hinterland. An all-purpose berth is
planned to be constructed in the east port with the maximum tonnage of 250,000. A
railway byline and a highway dedicated for port congestion alleviation directly reach
the edge of the industrial area. The water and power supply capacity guarantees
large-scale project.
III. Total project investment: the investment intensity is not lower than RMB 1.5
million /Mu. Cooperation ways: sole proprietorship or joint venture
IV. Preliminary work progress: the industrial area has passed the general regional
environmental impact assessment; Outline of General Planning of Fujian Provincial
Coastal Iron and Steel Base has been formulated.
V. Unit for the project: Jiangyin Industrial Concentration Area
VI. Contact person: Chen Ziyu
Tel: 0591-85966262
42. Fuzhou Luoyuan Bay Stainless Steel Deep Processing Industrial Park
I. Project content and construction scale: the planned area is about 10, 018 Mu.
Based on BaoSteel Group, it intends to introduce downstream deep-processing
enterprises on stainless steel cold rolling, wire drawing, tube, standard part,
non-standard part, kitchen ware, decoration and complete equipment manufacturing
etc.
30
II. Reasons and conditions for project construction: Stainless steel industry has
developed into one of the advantageous industries of Luoyuan Bay Development
Zone. It has preliminarily shaped an industrial chain with the complete range of
smelting, hot rolling, cold rolling, plate and wire and other products. Besides,
Luoyuan Bay Development Zone has a convenient transportation, which can meet the
demand of goods collecting and distributing of stainless steel industry.
III. Total project investment: RMB 13 billion. Cooperation ways: sole
proprietorship, joint venture or cooperative enterprise.
IV. Analysis on project’s economic benefits: after the Park is constructed, it will
be able to have the annual stainless steel deep-processing capacity of 4 million tons
and the annually-increased industrial output value of about RMB 50 billion.
V. Preliminary work progress: the auxiliary facilities such as water supply, power
supply and road have been constructed.
VI. Unit for the project: Administration Committee of Luoyuan Bay
Development Zone
VII. Contact person: Wang Wenbin
Tel: 13706972912
Fax: 0591-26982650
43. Quanzhou Nan’an Special Casting Mold and Bearing Manufacturing
Project
I. Project content and construction scale: the project plans to introduce a
modernized production line, mainly producing common civil-use casting and
high-grade industrial special casting equipments. It’s capable of producing 20,000
tons of castings of different kinds.
II. Reasons and conditions for project construction: Nan’an mechanical
manufacturing industry has the annual output value of RMB 5.3 billion. It’s one of the
important national production bases on plumbing and firefighting equipments. With
the development of plumbing and firefighting equipment industries, the demand on
precision of casting mold rises. The increasing demand on precision casting directly
promotes the development of special casting equipments. Hence, the project enjoys a
great market prospect.
III. Total project investment: Total Investment is USD 75 million. Cooperation
ways: joint venture or cooperative enterprise.
31
IV. Analysis on project’s economic benefits: the construction period of the
project is 1 year. The 4-year sales or operational revenue is RMB 28.75 million. The
investment payback period is 4 years and rate of return on investment (ROI) is 23%.
V. Preliminary work progress: the arterial roads of Binjiang industrial
concentration district have all been put into use. The land of over 70 hectares for
enterprise use in the starting area has been prepared for construction.
VI. Unit for the project: Nan’an Binjiang Mechanical Equipment Manufacturing
Base
VII. Contact person: Huang Zhehuai
Tel: 13905076187
Fax: 0595-86759288, 86768553
44. Quanzhou Hui’an Steel Structure Chunking Construction Project
I. Project content and construction scale: the project has a planned land area of
800 Mu and constructs steel structure material processing factory building, steel
structure chunking factory building, pipe and pressure container processing and
manufacturing factory building and outdoor chunking field. It will also construct a
5,000-tonnage ship dock, two 10,000-tonnage docks and one 30,000-tonnage public
pier for bulk cargo as support.
II. Reasons and conditions for project construction: Steel structure chunking
construction project caters to the demand of development of ocean engineering, steel
engineering and petrochemical engineering. According to national development
planning, in the future it will make great efforts to develop steel bridge construction
technology, including urban overpass and passenger footbridge etc, so the demand on
steel and iron will greatly increase. From the perspective of petrochemical
engineering developing trend, it will refer to ocean engineering chunking technologies,
and make chunking assembly and shipping of the steel structure and pipeline projects
of large-scale petrochemical projects to greatly improve specialization level and
reduce the difficulty of field installation projects and field management. Hence, the
project has a great developing prospect.
III. Total project investment: RMB 800 million. Cooperation ways: sole
proprietorship, joint venture or cooperative enterprise.
IV. Analysis on project’s economic benefits: the annual output value is RMB 3
billion and the annually-paid tax is RMB 400 million.
V. Unit for the project: Hui’an Project Development Center, Hui’an Huidong
32
Industrial Area
VI. Contact person: Zhuang Zhaoxu
Tel: 0595-87391181
0595-87878568
Fax: 0595-87391177
0595-87876568
45. Sanming Mingxi High-Strength Light-Duty Steel Wheel Project
I. Project content and construction scale: the project has a planned total floor area
of 52, 200 square meters, including a steel structure workshop of 44,000 square
meters, office and production auxiliary facilities of 8, 416 square meters and sewage
treatment plant of 356 square meters. It will introduce domestic and international
advanced production equipments to annually produce 3 million pieces of
high-strength light-duty steel wheel products.
II. Reasons and conditions for project construction: the project is located in
Mingxi Industrial Park, less than 60 kilometers away from Yong’an Motor City where
SinoTruck Haixi automobile project settles. It’s a new highlight to further extend
automotive industrial chain, build automotive industrial cluster, and construct Haixi
modernized Motor City with the annual capacity of 300,000 cars and output value of
over RMB 100 billion.
III. Total project investment: RMB 200 million
Cooperation ways: sole proprietorship, joint venture or cooperative development.
IV. Analysis on project’s economic benefits: after the project is put into
production, it will have an annual sales revenue of RMB 30 million, total benefits of
RMB 27 million (in the first year of production) and sales tax and surcharges of RMB
36.1906 million (including added-value tax).
V. Unit for the project: Fengxi Town, Mingxi County, Sanming City
VI. Contact person: Yan Feng
Tel: 0598--2750003
33
46. Sanming Haixi (Datian) Mechanical Casting and Forging Concentration
Area Development Project
I. Project content and construction scale: the project has a total planned area of
6.81 square kilometers, with developable construction land of 4.53 square kilometers
and ecological greening land of 2.28 square kilometers. It will set different areas for
casting, mechanical processing, precision mechanical manufacturing and construction
material production projects.
II. Reasons and conditions for project construction: Datian County has had a
30-year developing history on mining machinery and artificial board machinery. At
present, there have been 29 casting enterprises with the annual capacity of 160,000
tons of castings and the annual output value of over RMB 2 billion. Datian County
takes the development and strengthening of casting and forging industry as a main
developing direction. It plans to attract some casting and forging enterprises to settle
here, build an industrial park oriented on casting and mechanical processing, and
shape a mechanical casting industrial cluster of certain scale.
III. Total project investment: RMB 550 million. Cooperation ways: sole
proprietorship or joint venture.
IV. Preliminary work progress: the general planning on the industrial
concentration district has been formulated and reviewed by experts. The land of 0.87
square kilometers has been leveled.
V. Unit for the project: Datian Shangjing People’s Government
VI. Contact person: Chen Xiuda
Tel: 13960550666
47. Sanming Jiangle Project on Continuous Casting and Rolling of Stainless
Steel Composite Plate and Strip
I. Project content and construction scale: the project plans to acquire a land of
500 square kilometers and construct production lines on continuous cold and hot
rolling mill, hot wide strip rolling mill, plate mill and continuous casting and rolling
mill. After the project is put into use, it will annually produce 200, 300 and 400 series
stainless steel billet of 250,000 tons, stainless steel bar of 150,000 tons and cold and
hot-rolled plate of 100,000 tons.
II. Reasons and conditions for project construction: the project is in preliminary
stage. As it’s been the only enterprise that mass produces stainless steel composite
34
plate and strip billet and produces plate and strip in continuous rolling method in the
world, it has an absolute technological monopoly. After the project is put into use, it
can take full advantage of the abundant raw materials of this area and purchase and
produce locally. It will extend industrial chain, save transportation and sales
expenditure and reduce production cost.
III. Total project investment: Total Investment is RMB 1.7 billion. Cooperation
ways: joint venture
IV. Preliminary work progress: Preliminary feasibility study report has been
formulated to construct a globally first-class professional enterprise in stainless steel
plate and strip product production.
V. Project site: Jishan Industrial Park, Fujian Jiangle Economic Development
Zone
VI. Unit for the project: Project Management Office, Jiangle Development and
Reform Bureau
VII. Contact person: Lin Qu
Tel: 0598-2333091
48. Longyan Wuping Precision Stainless Steel Rolling and Product Project
I. Project content and construction scale: it will annually produce 100,000 tons of
precision stainless steel rolling and products. The 200~400 Serial Products have the
thickness of 0.08~1.2mm. It will annually produce stainless steel band of 100, 000
tons (including 60,000 tons used for different kinds of products).
II. Reasons and conditions for project construction: stainless steel is featured
with nice look, corrosion resistance, abrasion resistance and high strength. It’s widely
applied in different fields of industrial manufacturing and daily life. Wuping County
is located in the intersection of Fujian, Guangdong and Jiangxi, so it enjoys a
convenient transportation and advantageous location. The stainless steel industrial
development platform has been increasingly perfecting. The existing stainless steel
piping and industrial gas manufacturing enterprises in the Park can support the project
and a complete industrial chain will thus take shape.
III. Total project investment: RMB 560 million. Cooperation ways: sole
proprietorship.
IV. Analysis on project’s economic benefits: the annual sales revenue is
35
estimated to be RMB 157.5 million and the paid tax will be RMB 393.75 million.
V. Preliminary work progress: the project proposal has been formulated.
VI. Unit for the project: Wuping Investment Promotion Bureau
VII. Contact person: Wen Quan
Tel: 15880615720
49. Electronics, Photoelectric and Electro-Mechanical Projects of Fuzhou
Municipal Electro-Mechanical Industrial Park
I. Project content and construction scale: The Electro-Mechanical Industrial Park
occupies a land of 321.79 hectares (4,827 Mu). It focuses on the introduction of
enterprises engaged in complete equipment manufacturing, precision machinery,
photo-electricity, electronics and the related industrial chains.
II. Reasons and conditions for project construction: The Park is located in the
west bank of Wulongjiang, central downtown of Fuzhou. It’s 14 kilometers away from
the central downtown of Fuzhou, 30 kilometers away from Mawei Port and 44
kilometers away from Changle Airport. The transportation is convenient and
landscape resources are abundant. It has a broad developing space and mature
conditions for development.
III. Total project investment: The enterprises will self- raise capitals according to
the actualities of the projects. Cooperation ways: domestically-funded, wholly
foreign-funded, joint venture or cooperation.
IV. Preliminary work progress: the preliminary preparation work is ongoing.
V. Unit for the project: Administration Committee of Fuzhou Jinshan Industrial
Concentration District
VI. Contact person:
Shi Jianhui
Tel: 0591-83856888
Fax: 0591-83856588
Guo Xiaoxia Tel: 0591-83856188
Fax: 0591-83856588
36
50.Mechanical and Electronic Industrial Park, Lianjiang Economic
Development Zone Project, Fuzhou
I. Project content and construction scale: Shangang industrial concentration
district of Lianjiang Economic Development Zone takes mechanical and electronic
industry as the leading industry, and is intended to introduce 3-9 mechanical and
electronic industry projects.
II. Reasons and conditions for project construction: The project is located in the
“Half-Hour Economic Circle” of Fuzhou. It takes 30 minutes to Fuzhou International
Airport by car. It is 25 kilometers away from Mawei Port and 24 kilometers away
from Kemen Port. The transportation is very convenient; at present, the Development
Zone has introduced nearly 50 electro-mechanical projects on generator set,
transformer, electric cable and motor bearing parts. An electro-mechanical auxiliary
industrial concentration park has preliminarily taken shape.
III. Total project investment: the total investment for single project is above USD
10 million. Cooperation ways: sole proprietorship or joint venture.
IV. Preliminary work progress: The lands for Phase 1 and 2 are compliant with
state land policies. Land acquisition has been finished and the application for
transferring farmland to project land has been approved. Land for Phase 1 project has
been prepared for construction and a part of the land for Phase 2 project will be
prepared by the end of 2012.
V. Unit for the project: Administration Committee of Fujian Lianjiang Economic
Development Zone
VI. Contact person: Wang Jinhai
Mobile: 13805071308
Tel: 0591-26251899, 26158893
Fax: 0591-26231580
Email: lj26131166@qq.com
51. Industrial Projects of Fuzhou Taiwanese Investment Zone
I. Project contents and construction scales: In January, 2012, the State Council
approved Fuzhou Taiwanese Investment Zone’s expansion to the south and north
banks of Luo Bay, with the expanded area of 11.46 square kilometers. The Area
focuses on metal and metallurgy and deep processing, mechanical equipment
manufacturing, shipbuilding, new material processing and energy industries.
II. Reasons and conditions for project construction: 1. It enjoys a geographic
37
advantage as it’s close to Taiwan. Luoyuan bay, where the projects are located, has
been the best deep-water port closest to Keelung Port of Taiwan. 2. It enjoys the
advantage of harbor. Luoyuan Bay is one of the six natural deepwater harbors in
Fujian Province, which is rare in China. 3. The land cost is comparatively low. As
Daguanban Reclamation Area is polder reclamation area, its land use class is sea area
whose application and approval cost is lower than that of farmland, so the land cost is
lower. 4. Great space for development. The south bank of Luoyuan Bay is located in
Daguanban reclamation area, with an area of 27 kilometers. It mainly contains beach
lands and hilly lands and the lands are flat, so it can be developed by plot. In later
phase, it can be extended to Matou Plain for development, with the area of over 100
square kilometers. It’s an ideal option for large-scale port-centered industrial projects.
III. Cooperation ways: plant set-up
IV. Unit for the project: Administration Committee of Fuzhou Taiwanese
Investment Zone
V. Contact person: Lin Yuzhou
Tel: 0591-86292147
Fax: 0591-86292145
52. Industrial Projects of Xiang’an Industrial Park,Xiamen
I. Project content and construction scale: the planned area of the Park is 40.59
square kilometers. It’s an ecology and environmental-protection-oriented park as
planned. It focuses on introducing comprehensive light industries such as food
production, royal incense, photo-electricity, electronics, chemical fiber, textile,
costume, packaging and plastics industries.
II. Project Cooperation ways: sole proprietorship.
III. Unit for the project: Xiang’an District Economy and Trade Bureau
IV. Contact person: Chen Yaohui
Tel: 0592-7889832
53. Zhangzhou Advanced Equipment Manufacturing Industry Project
Hua’an
I. Project content and construction scale: The planned land area for the project is
20,000.
38
II. Total Investment: RMB 2.38 billion
III. Preliminary work progress: it has introduced many enterprises such as
Langyao Equipment, Hengfeng Machinery, Sailing Precision Hardware and Zhangjun
Heavy-Duty Machinery etc.
IV. Unit for the project: Hua’an Economic Development Zone
V. Contact person: Huang Laixing, Hua’an Economy and Trade Bureau
Tel: 0596-7362212
54. Zhangzhou Nanjing Dehe Mechanical Industrial Park
I. Project content and construction scale: It covers a total land area of 800 Mu.
II. Total Investment: RMB 200 million
III. Unit for the project: Shancheng Town, Nanjing County
IV. Contact person: Jian Huangxi
Tel: 13906953578
55. High-end Equipment Manufacturing Industrial Park project of
Quanzhou Taiwanese Investment Zone
I. Project content and construction scale: the planned land area is 8 square
kilometers. It focuses on the basic equipments on marine engine, precision processing,
environmental-protection, medical care, intelligent devices and CNC machine tool
etc.
II. Reasons and conditions for project construction: Quanzhou equipment
manufacturing industry enjoys a good industrial base. It has preliminarily shaped an
equipment manufacturing industrial system cored on automotive parts, textile
machinery, shoe-making machinery, engineering machinery, shipbuilding industry and
parts. At present, Quanzhou Taiwanese Investment Zone has introduced many leading
projects such as China CNR Corporation’s project and has had great developing
conditions and advantages; meanwhile, Quanzhou equipment manufacturing industry
has enriched resources in senior and intermediate technical talents and skilled workers,
with great HR support.
39
III. Cooperation ways: sole proprietorship, joint venture or cooperative enterprise
IV. Preliminary work progress: the park planning has been finished and the
infrastructure network has preliminarily taken shape. It’s able to provide
well-developed auxiliary facilities and services.
V. Unit for the project: Technical and Economic Development Bureau of
Quanzhou Taiwanese Investment Zone
VI. Contact person: Ms. Zhuang and Ms.He
Tel: 0595-27395529,13808529689
Tel: 0595-27308666,15159751058
Email: qz27308666@163.com
56. Quanzhou Nan’an Binjiang Mechanical Equipment Manufacturing Base
Project
I. Project content and construction scale: the project has three phases as planned.
It focuses on the introduction of automotive and engineering mechanical parts project,
component and precision mechanical equipment manufacturing project, and
conventional industrial projects transformed with high and new-technology such as
automotive electronic control system, security system and new-energy automotive
auxiliary parts etc.
II. Reasons and conditions for project construction: the project is located in
Xiamei Town, which is only 3 kilometers away from Entry of Quanzhou-Sanming
Highway, 20 kilometers away from Jinjiang Airport and 13 kilometers away from
Quanzhou Station of Fuzhou-Xiamen High-speed Rail. Xiamen Town and Fengzhou
Town started early in the development of mechanical (automotive parts) industry and
have a lot of personnel engaged in automotive parts marketing. They can provide
talent, capital and information support for the construction of industrial base.
III. Total project investment: Planned Total Investment is RMB 800 million.
Cooperation ways: plant set-up.
IV. Preliminary work progress: At present, the arterial road in the base has been
basically constructed. In the starting area, there have been 38 enterprises under
construction and over 20 ones partially put into use. The phase two project is in
planning.
40
V. Unit for the project: Nan’an Binjiang Investment and Development Co., Ltd.,
VI. Contact person: Mr. Huang
Tel: 13905076187
Fax: 0595-86759288 86768553
57. Petrochemical Mechanical Equipment Manufacturing Project of
Quanzhou Taiwanese Investment Zone
I. Project content and construction scale: special petrochemical mechanical
equipments include complete equipment, tank accessory series, pipe accessory series,
steel structure series, heating furnace fitting series, tower and tank internals series,
and other non-standard parts.
II. Reasons and conditions for project construction: Quanzhou has established
Quangang Petrochemical Park and Quanhui Petrochemical Park. The industrial
development has been of certain scale. As petrochemical industry’s mid-stream and
downstream industrial chain develops, the demand on petrochemical mechanical
equipments grows. Quanzhou Taiwan Businessmen Investment Area has planned 8
square kilometers as Mechanical Equipment Manufacturing Park. The auxiliary
infrastructure has been well-developed and is able to meet the construction demand of
the project.
III. Cooperation ways: sole proprietorship, joint venture or cooperative
enterprise.
IV. Preliminary work progress: the park planning has been finished and the
infrastructure network has preliminarily taken shape. It’s able to provide
well-developed auxiliary facilities and services.
V. Unit for the project: Technical and Economic Development Bureau of
Quanzhou Taiwanese Investment Zone
VI. Contact person: Ms. Zhuang and Ms.He
Tel: 0595-27395529,13808529689
Tel: 0595-27308666,15159751058
Email: qz27308666@163.com
41
58. Sanming Qingliu Longxiang Industrial Park Mechanical Manufacturing
Project
I. Project content and construction scale: the project has a planned area of 0.33
square kilometers and is intended to introduce 10-15 enterprises. It will focus on
mechanical production projects such as automotive parts mechanical processing and
engineering mechanical parts processing etc.
II. Reasons and conditions for project construction: mechanical manufacturing
industry has been one of the key industries planned by Jinxing Processing Park,
Qingliu Economic Development Zone. Qingliu County has many mechanical
processing enterprises such as Farming Machinery Plant, Hardware Plant and Air Gun
Plant, and their workers have certain advantage in conventional skills. Qingliu County
can be based on the great automotive and engineering mechanical industrial
foundation of Sanming and Yong’an and support Yong’an Heavy Truck, Sanming
Heavy-Duty Machinery, XGMA Machinery and other engineering mechanical
processing enterprises in Quanzhou.
III. Total project investment: RMB 600 million
IV. Analysis on project’s economic benefits: the investment payback period is
expected to be 3-5 years.
V. Preliminary work progress: the project proposal has been formulated.
VI. Unit for the project: Administration Committee of Qingliu Economic
Development Zone
VII. Contact person: Yang Shengfa
Tel: 18950994733
Email:qljxgwh@163.com
59. Fujian CREC Qianda Equipment Manufacturing Project
I. Project content and construction scale: Fujian CREC Qianda Equipment
Manufacturing Co., Ltd. is a high-end heavy-duty equipment manufacturing
enterprise invested by the stated-owned enterprise “China Railway Engineering
Corporation” in Fujian that ranks among both Global Top 500 Enterprises and Global
Top 500 Brands. To improve its products, especially the brand, technology and
management level of tunnel boring machine and expand the production scale, the
Company sincerely invites well-known international mechanical equipment
enterprises to discuss for set-up of cooperative enterprise or joint venture.
42
II. Reasons and conditions for project construction: Based on CREC’s advanced
shield technologies, CREC Qianda has constructed the first key laboratory on shield
technology and shield tunneling equipment in China, and taken up many “863”
projects of China. The TBM serial products developed and manufactured by the
company have fully independent intellectual property right. As China’s transportation
industry especially rail transportation industry develops, TBM and the related
products will enjoy a better market prospect.
III. Cooperation ways: set-up of cooperative enterprise or joint venture
IV. Unit for the project: Fujian CREC Qianda Equipment Manufacturing Co.,
Ltd.
V. Contact person: Cheng Jianying
Tel: 13905022802
Tel: 0591-22917312/22917965 (Fax)
Email: jianying.cheng@vip.163.com
60. Rail Equipment Industry Auxiliary Project of Quanzhou Taiwanese
Investment Zone
I. Project content and construction scale: the planned land area is 4,000 Mu. It
will introduce Quanzhou Strait Rail Vehicle Project’s auxiliary projects on seat, lamp,
windshield, vehicle door and window, floor, lower and grooved parts of vehicle,
electricity box, wallboard, top plate, side top, end plate, air-duct, grab rail
cold-resistance and transportation and logistics.
II. Reasons and conditions for project construction: China CNR Corporation
invested to construct Strait Rail Transportation Vehicle Project in Quanzhou Taiwan
Businessmen Investment Area in 2010. The project is capable of producing 300 rail
vehicles, in-plant repairing 500 urban rail vehicles and un-wheeling repairing 80
urban rail vehicles after it’s put into use. To build a rail transportation industrial chain,
and create a good developing environment for rail transportation auxiliary enterprises,
the area plans green intelligent transportation industrial base. It has a great
development prospect.
III. Cooperation ways: sole proprietorship, joint venture or cooperative enterprise
IV. Preliminary work progress: the park planning has been finished. It’s able to
provide well-developed auxiliary facilities and services.
V. Unit for the project: Technical and Economic Development Bureau of
43
Quanzhou Taiwanese Investment Zone
VI. Contact person: Ms. Zhuang and Ms.He
Tel: 0595-27395529,13808529689
Tel: 0595-27308666,15159751058
Email: qz27308666@163.com
61. Longyan Engineering Machinery and Automotive Tire Production Line
Project
I. Project content and construction scale: it will annually produce 1.5 million sets
of engineering machineries and different kinds of auto tires.
II. Total project investment: USD 238.1 million. Cooperation ways: sole
proprietorship
III. Preliminary work progress: Preliminary feasibility study report has been
formulated.
IV. Unit for the project: Administration Committee of Longyan New Area,
Longyan Municipal Key Project Management Office
V. Contact person: Zhang Siyuan, Lin Shengwen
Tel: 0597-3212151/0597-3229629, 13806996815
62. Longyan Excavator-Dedicated High-Pressure Cylinder project
I. Project content and construction scale: it will annually produce 200,000 pieces
of excavator-dedicated high-pressure cylinders.
II. Total project investment: USD 104.76 million. Cooperation ways: sole
proprietorship
III. Preliminary work progress: Preliminary feasibility study report has been
formulated.
IV. Unit for the project: Longyan Xinluo Investment Promotion Bureau
44
V. Contact person: Qiu Zhidong
Tel: 0597-2338889
63. Longyan
Production Project
Xinluo
Mine
Emergency
Equipment
Manufacturing
I. Project content and construction scale: it will annually produce 2,000 sets of
stationary shelters and mobile escape hatches.
II. Reasons and conditions for project construction: mine emergency shelter is a
confined space set in dangerous operational areas under mine. It’s usually excavated
from lane wall with great air tightness and certain resistance to impact of external
forces. By testing the parameters in emergency shelter and operating internal
life-saving systems, miners can form a good internal environment for survival and
gain time for lifesaving purpose.
III. Total project investment: RMB 812.25 million. Cooperation ways: sole
proprietorship.
IV. Analysis on project’s economic benefits: after the project is put into
production, in normal condition, it will have the annual sales revenue of RMB 2
billion. ROI will be 28.1%, profit and tax investment ratio will be 35.5% and the
investment payback period is 10.56 years.
V. Preliminary work progress: Preliminary feasibility study report has been
formulated and the project land is being applied.
VI. Unit for the project: Xinluo Economic and Technical Development Center.
VII. Contact person: Qiu Zhidong
Tel: 0597-2338889,13600987787
64. Longyan Rail Transit Material and Equipment Manufacturing
Industrial Park
I. Project content and construction scale: it’s mainly a large high-speed rail
material and equipment manufacturing industrial park including projects on internal
decoration of vehicle and equipments, steel-core and copper-sheet & copper-steel
composite material, track board of ballast-less track system, high-speed rail fastener,
CA mortar and special asphalt emulsion, PU sleeper and high-speed rail sound barrier
45
etc.
II. Reasons and conditions for project construction: as a strategic and rising
industry, high-speed rail is featured with high speed, large traffic volume, land and
energy saving and environmental protection. It has a far-reaching significance on
accelerating economic development method transfer, building modern integrated
transportation system, implementing sustainable strategy implementation and
promoting sound and fast economic and social development.
III. Total project investment: RMB 5 billion. Cooperation ways: sole
proprietorship by domestic large-scale enterprises.
IV. Preliminary work progress: the project proposal has been formulated.
V. Unit for the project: Longyan Municipal Project Development Center
VI. Contact person: Wu Hongkui
Tel: 0597-3212126,13959478254
65. Fuzhou Lianjiang Kemen Port Automotive Industrial Park Project
I. Project content and construction scale: the park has a planned area of 10,000
Mu. It will be constructed to a professional “One-Stop” automotive market cored with
finished automobile and parts manufacturing and integrating sales, storage and
inspection services as planned.
II. Reasons and conditions for project construction: Daguanban Section of
Fuzhou Lianjiang Kemen Port Economic Development Zone is a state-level
Taiwanese investment area, with a planned area of 6 square kilometers. It enjoys
exceptional port advantage. The port is all-weather open to large vessels of
100,000—300,000 tonnage. Fuzhou automotive industry will gather the automotive
industrial clusters led by Southeast Motors. Lianjiang County will be based on the
excellent port resources and deepen cooperation in design, R&D and component
upgrading. It’s expected to form an industrial cluster system with the annual capacity
of 100,000 cars and involving the auxiliary components and parts.
III. Total project investment: RMB 10 billion. Cooperation ways: sole
proprietorship, joint venture.
IV. Preliminary work progress: The Park’s preliminary planning has been
finished.
46
V. Unit for the project: Lianjiang Bureau of Foreign Trade and Economic
Cooperation
VI. Contact person: Xue Nan
Tel: 0591-26153193
26232339
Fax: 0591-26233966
66. Fuzhou Qingkou Investment Zone Automotive Engine Project
I. Project content and construction scale: construction of an automotive engine
production line with the annual capacity of 500,000 sets of engines.
II. Reasons and conditions for project construction: Qingkou Investment Zone
enjoys an favorable geographical location, well-developed infrastructure and
advantageous labor cost. It has been an important automotive production base in
Fujian Province, but it lacks automotive engine manufacturing enterprises now.
III. Total project investment: USD 200 million. Cooperation ways: joint venture
or sole proprietorship.
IV. Preliminary work progress: The infrastructure has been equipped such as land
that is required by the project construction.
V. Unit for the project: Administration Committee of Qingkou Investment Zone,
Fuzhou
VI. Contact person: Chen Qinan
Tel: 0591-22761310, 13705982615
Fax: 0591-22765053
Email: qinkou@sina.com
67. Zhangzhou Hua’an Automobile and Parts Industry
I. Project content and construction scale: the planned land area is 20,000 Mu.
II. Total Investment: RMB 1.33 billion
III. Preliminary work progress: It has introduced over ten enterprises such as
Zhengxing Wheel and Longxi Bearing etc.
47
IV. Unit for the project: Hua’an Economic Development Zone
V. Contact person: Lin Hong
Tel: 0596-7369979
68. Zhangzhou Automotive Auxiliary Industrial Chain Project on
Automotive Bearing etc .
I. Project content and construction scale: Automotive Auxiliary Industrial Park
has a planned land area of about 1000 Mu.
II. Total Investment: RMB 4 billion
III. Preliminary work progress: The north new area is in planning. The land
application and acquisition work will start in the first half of 2012.
IV. Unit for the project: Administrative Committee of Lantian Economic
Development Zone
V. Contact person: Kang Jianshun
Tel: 0596-2106009
69. Quanzhou Nan’an Automotive Rear-View Detector Project
I. Project content and construction scale: the project plans to adopt first-class
equipments and techniques such as liquid crystal display (LCD) and 1/3
high-resolution infrared CCD camera and construct automotive rear-view detector
with the annual capacity of 600,000 sets.
II. Reasons and conditions for project construction: automotive rear-view
detector is comprised of CDOS micro visual fluorescent screen and the related
supporting circuits. After installing the product, driver can clearly observe the full rear
view through the fluorescent screen in cab. The infrared camera of the product has
150-degree rear view that has no dead zone. The product solves the rear view’s dead
zone problem for lifting and transportation equipments and vehicles and enjoys a
great market prospect.
III. Total project investment: RMB 200 million. Cooperation ways: sole
proprietorship.
48
IV. Analysis on project’s economic benefits: after the project is put into use, it
will enjoy a annual sales revenue of RMB 137.5 million, the profits of RMB 49.25
million and the tax of RMB 14.31 million.
V. Preliminary work progress: the land for the project has been planned and the
application for transferring farmland to project land has been submitted to Provincial
Department of Land and Resources.
VI. Unit for the project: Nan’an Binjiang Investment and Development Co., Ltd.
VII. Contact person: Mr. Huang
Tel: 13905076187
Fax: 0595-86759288, 86768553
70. Quanzhou Nan’an AMT Project
I. Project content and construction scale: the project plans to introduce advanced
AMT production technology and equipments to construct AMT production line with
the annual capacity of 100,000 sets of AMT.
II. Reasons and conditions for project construction: AMT is a device that
achieves automated shift operation through the microcomputer-controlled automatic
operating mechanism without changing the original structures of mechanical
transmission and clutch. The project has independent intellectual property right, high
technical contents and added value. It enjoys a great market prospect.
III. Total project investment: RMB 80 million. Cooperation ways: plant set-up.
IV. Analysis on project’s economic benefits: after the project is put into use, it
will have a annual output value of RMB 280 million and the profits of RMB 30
million. The investment payback period is 2.7 years.
V. Preliminary work progress: at present, the arterial roads in the Base have been
basically constructed, the land for the project has been planned and the application for
transferring farmland to project land has been submitted to Provincial Department of
Land and Resources.
VI. Unit for the project: Nan’an Binjiang Investment and Development Co., Ltd.
VII. Contact person: Mr. Huang
Tel: 13905076187
Fax: 0595-86759288, 86768553
49
71. Project with Annual Capacity of 200,000 Engines,Sanming
I. Project content and construction scale: the project covers a land of 0.13 square
kilometers and constructs whole assembly, test, painting and packaging production
lines with the annual capacity of 200,000 sets of engines.
II. Reasons and conditions for project construction: Fujian Sanming Puling
Automotive Industrial Park is jointly developed by Sanming and Yong’an. It has the
planned area of 20 square kilometers, with the developed area of 2.7 square
kilometers. SinoTruck Fujian Haixi Automobile Co., Ltd. is a finished car
manufacturing enterprise in core area. It’s planned to annually produce 200,000
finished automobiles by 2015 and thus become an important commercial vehicle
production and export base in Fujian and even in the whole China. The Park plans to
construct an engine project to support Haixi Automobile. It will have a lot of car types
to match and a wide range of application.
III. Total project investment: Total project investment is RMB 2 billion.
Cooperation ways: sole proprietorship or cooperative enterprise.
IV. Economic benefit analysis: Total project investment is RMB 2 billion. The
annual sales revenue is RMB 7 billion. The investment payback period is 4 years.
V. Preliminary work progress: the preliminary work of the project is ongoing.
VI. Unit for the project: Fujian Sanming Puling Automotive Industrial Park
VII. Contact person: Liu Jiao
Tel: 0598-3815986
72. Sanming Jiangle Semi-Solid Rapid Prototyped Automotive Engine
Casting Project
I. Project content and construction scale: it plans to construct two production
lines on aluminum alloy automotive engine casting and annually produce 1 million
sets of engine castings for different car types.
II. Reasons and conditions for project construction: it adopts the advanced
semi-solid rapid prototyping technology to produce high-quality and low-energy
consumption automotive engine casting and enjoys a great market prospect. Fujian
Provincial RheoMet Light Metal Co., Ltd. owns the exclusive use right of light metal
semi-solid rapid prototyping patent technology in Asia and has developed a series of
light metal alloy products to put into production. It provides a great support for the
50
raw material source and the related technologies of the project. Meanwhile, the
project has low energy consumption, small pollution, no environmental-protection
pressure and mature construction conditions.
III. Total project investment: RMB 500 million. Cooperation ways: sole
proprietorship or joint venture.
IV. Analysis on project’s economic benefits: after the project is put into
production, it will have an annual sales revenue of RMB 1.2 billion and the benefits
of RMB 280 million. The ROI is 40% and investment payback period is 3.6 years
(including 1-year construction period).
V. Preliminary work progress: Preliminary feasibility study report has been
formulated.
VI. Unit for the project: Jiangle Development and Reform Bureau
VII. Contact person: Li Keming
Tel: 0598-2333091,13860595382
73. Nanping Minbei Lead-Crystal Environmental-Protection Battery
Production Project
I. Project content and construction scale: the project has a total land area of 0.2
square kilometers and will construct workshops, office and R&D building and other
auxiliary buildings of 106,000 square meters; it will construct electric vehicle battery
and UPS battery production lines and annually produce 3 million sets of electric
vehicle batteries and 1 million sets of UPS batteries.
II. Reasons and conditions for project construction: the project’s products have
many features superior to lead-acid battery: long service life, basically two times that
of lead-acid battery; good low-temperature resistance, common lead-acid battery’s
capacity release will be obviously influenced at minus 0℃, while lead-crystal battery
can still release over 80% capacity at minus 20 ℃ ; this new-type
environmental-protection product is rapidly entering into the lives of consumers in
different fields and being accepted by a increasing number of organizations and
individuals.
III. Total project investment: RMB 560 million. Cooperation ways: joint venture
or sole proprietorship.
IV. Analysis on project’s economic benefits: after the project is put into
51
production, it will have an annual sales revenue of RMB 880 million, an average
annual total benefits of RMB 267.68 million. Its IRO is 47.8%, after-tax benefits are
RMB 200.76 million and the after-income-tax investment payback period is 2.8 years.
V. Preliminary work progress: feasibility study work is ongoing.
VI. Unit for the project: Investment Promotion Bureau, Administration
Committee of Minbei Economic Development Zone
VII. Contact person: Fang Dongjie
Tel: 0599-5671266 Email: zsjggyx@163.com
74. Longyan Truck Crankshaft Production Project
I. Project content and construction scale: it will annually produce 300,000 pieces
of crankshafts, including 150,000 pieces of heavy-duty truck crankshafts and 150,000
pieces of light-duty truck crankshafts.
II. Total project investment: USD 71.43 million. Cooperation ways: sole
proprietorship
III. Preliminary work progress: the feasibility survey on the project has been
done.
IV. Unit for the project: Longyan Xinluo Investment Promotion Bureau
V. Contact person: Qiu Zhidong
Tel: 0597-2338889
75. Longyan Wuping Automotive Stainless Steel Muffler Production Line
Project
I. Project content and construction scale: the project covers a land area of 20,000
square meters with total floor area of 18,300 square meters, including workshops of
9,000 square meters, two warehouses of 4,500 square meters, office building of 4,500
square meters and auxiliary buildings of 300 square meters
II. Total project investment: USD 17.94 million. Cooperation ways: sole
proprietorship
52
III. Preliminary work progress: the project’s feasibility study report has been
formulated.
IV. Unit for the project: Wuping Urban & Rural Planning and Construction
Bureau
V. Contact person: Zhong Wenguang
Tel: 13859567668
76. Longyan Mini-car Production Project with Annual Capacity of 300,000
Mini-cars
I. Project content and construction scale: the project will annually produce
300,000 mini-cars. Phase 1 project will annually produce 150,000 mini-cars,
including 100,000 FJ6390 Series mini-buses and 50,000 FJ1020JA Series mini-trucks.
Phase 2 project will annually produce 300,000 mini-cars.
II. Reasons and conditions for project construction: As an important
manufacturing base on agricultural vehicles, passenger cars, special vehicles and truck,
Longyan has had a good base on automotive manufacturing. It has 11 automotive
manufacturing enterprises and over 80 automotive parts production enterprises.
Longyan has a wide market radiation, convenient transportation conditions of
products, raw materials and parts and low labor and shipping cost, so it has great
market competitiveness.
III. Total project investment: RMB 2.395 billion. Cooperation ways: set up joint
venture with domestic large-scale enterprises.
IV. Analysis on project’s economic benefits: after the project is put into
production, it will have the total benefits of RMB 410.22 million and net benefits of
RMB 307.66 million. The investment payback period is 7.25 years.
V. Preliminary work progress: the construction of Phase 1 project has started.
VI. Unit for the project: Longyan Municipal Economy&Trade Commission
VII. Contact person: Lai Shuimei
Tel: 0597-3293206, 13507539189
53
77. Longyan Luxury Coach Production Project
I. Project content and construction scale: the project will construct a production
line with the annual capacity of 5,000 luxury coaches. The Total Investment is
planned to be RMB 600 million.
II. Reasons and conditions for project construction: As an important
manufacturing base on agricultural vehicles, passenger cars, special vehicles and truck,
Longyan has had a good base on automotive manufacturing. It has 11 automotive
manufacturing enterprises and over 80 automotive parts production enterprises.
Longyan has a wide market radiation, convenient transportation conditions of
products, raw materials and parts and low labor and shipping cost, so it has great
market competitiveness.
III. Total project investment: RMB 1.28 billion. Cooperation ways: set up joint
venture or cooperative enterprise with domestic large-scale enterprises.
IV. Preliminary work progress: the project proposal has been formulated.
V. Unit for the project: Long Yan Municipal Economy& Trade Commission
VI. Contact person: Lai Shuimei
Tel: 0597-3293206, 13507539189
78. Longyan Heavy-Duty Truck Production Project
I. Project content and construction scale: the project will construct a production
line with the annual capacity of 30,000 medium and heavy-duty trucks.
II. Reasons and conditions for project construction: As an important
manufacturing base on agricultural vehicles, passenger cars, special vehicles and truck,
Longyan has had a good base on automotive manufacturing. It has 11 automotive
manufacturing enterprises and over 80 automotive parts production enterprises.
Longyan has a wide market radiation, convenient transportation conditions of
products, raw materials and parts and low labor and shipping cost, so it has great
market competitiveness.
III. Total project investment: RMB 1 billion. Cooperation ways: set up
cooperative enterprise with domestic large-scale enterprises.
IV. Preliminary work progress: the project proposal has been formulated.
V. Unit for the project: Longyan Municipal Economy & Trade Commission
54
VI. Contact person: Lai Shuimei
Tel: 0597-3293206, 13507539189
79. Longyan Automotive Engine Production Project
I. Project content and construction scale: the project will construct 5 production
lines on vehicle body, cylinder head mechanical processing, whole assembly, testing
and painting and packaging and R&D center.
II. Reasons and conditions for project construction: as domestic highway
network perfects and economic society speedily develops, the domestic demand on
high-power engines of medium and heavy-duty truck, high-speed luxury bus and
high-power engineering machinery grows, especially heavy-duty vehicles of over 360
horsepower and 16 tonnage, which has a great market demand potential.
III. Total project investment: RMB 2.5 billion. Cooperation ways: sole
proprietorship by domestic large-scale enterprises.
IV. Analysis on project’s economic benefits: the sales revenue is estimated to be
RMB 3.8 billion.
V. Preliminary work progress: the project proposal has been formulated.
VI. Unit for the project: Longyan Municipal Project Development Center
VII. Contact person: Wu Hongkui
Tel: 13959478254
80. Longyan Aerial Ladder Fire Truck Production Project
I. Project content and construction scale: it will introduce advanced production
techniques and equipments and construct a production line with the annual capacity of
500 aerial ladder fire trucks.
II. Reasons and conditions for project construction: Longyan has been the
manufacturing base of cargo truck and special vehicles with the widest range and
largest scale and important mechanical equipment industrial base. It has developed
leading enterprise groups, technical R&D power and professional worker teams on
engineering machinery, special vehicle, hydraulic equipment and water pump
manufacturing, so it has had the industrial base for aerial ladder fire truck R&D and
55
production.
III. Total project investment: RMB 1.2 billion. Cooperation ways: sole
proprietorship.
IV. Analysis on project’s economic benefits: after the project is put into
production, it will have an annual sales revenue of RMB 2 billion, the paid tax of
RMB 180 million and net benefits of RMB 220 million.
V. Preliminary work progress: it has finished the preliminary work including
project investment opportunity analysis, construction site comparison and selection
and product market survey.
VI. Unit for the project: Longyan Municipal Project Development Center
VII. Contact person: Chen Kaiwu
Tel: 0597-3212161, 13859566518
81. Longyan Changting RE Hydrogen-Storage Alloy Powder and NI-MH
Electric-Vehicle Battery Production Line
I. Project content and construction scale: it will annually produce 3,000 tons of
high-performance RE hydrogen-storage alloy powder and 100,000 sets of NI-MH
electric-vehicle batteries.
II. Reasons and conditions for project construction: Changting County has
abundant rare earth resources. The County Party Committee and County Government
take rare earth as the leading industry. This project can give a full play to Changting’s
advantage on rare earth, transfer the advantage to economic industrial advantage, and
extend the deep processing industrial chain on rare earth.
III. Total project investment: RMB 1.02123 billion. Cooperation ways: sole
proprietorship or joint venture.
IV. Analysis on project’s economic benefits: the annual sales revenue will be
RMB 2.5304 billion and the benefits will be RMB 250 million.
V. Preliminary work progress: the project’s feasibility study report has been
formulated and the land has finished three supplies and one leveling.
VI. Unit for the project: Changting Rare Earth Industrial Office
VII. Contact person: Zhong Keliang
56
Tel: 13600996699
82. Ningde Fu’an Tiger Electric Car Industrial Park Project
I. Project content and construction scale: the project has a planned land area of
0.13 square kilometers and will annually produce 500,000 electric vehicles of
different kinds, with the output value of RMB 1.5 billion.
II. Reasons and conditions for project construction: Fujian Tiger Power Machine
Group Co., Ltd. has been engaged in electric machine production for many years. In
recent years, the Company has been dedicated to the R&D of electric cars. At present,
the Company has acquired different technologies on electric car production and has
owned certain customer groups. The conditions for the construction of Tiger Electric
Car Industrial Park and launching of the production project have been mature.
III. Total project investment: RMB 300 million. Cooperation ways: joint venture
or cooperative enterprise
IV. Analysis on project’s economic benefits: the project’s investment payback
period is estimated to be 5.6 years (including construction period), IRR will be 18.8 %
and ROI will be 15.78%.
V. Preliminary work progress: The preliminary planning has been examined and
reviewed.
VI. Unit for the project: Fujian Tiger Power Machine Group Co., Ltd.
VII. Contact person: Huang Huatang
Tel: 0593-6379555
83. Ningde Fu’an Hybrid Power Assembly with Annual Capacity of 10,000
Sets of New-Energy Passenger Cars
I. Project content and construction scale: the project plans to construct a
new-energy passenger-car hybrid power assembly production center and a drive
motor manufacturing center etc. The project occupies a land of 0.33 square kilometers
with the general floor area of 316,667 square meters.
II. Reasons and conditions for project construction: the products have been
supplied in great quantity to automobile companies such as Xiamen Golden Dragon
Bus Co., Ltd, King Long Motor Group, Higer Bus Company Limited, Shanghai
57
Sunlong Bus Co., Ltd and Zhengzhou Yutong Group Co., Ltd.. At present, the
products have finished testing and model operation and will be put into
commercialized operation and mass production.
III. Total project investment: RMB 1.08 billion. Cooperation ways: joint venture
or cooperative enterprise.
IV. Analysis on project’s economic benefits: after the project is put into
production, it will finally have the annual capacity of 10,000 sets of new-energy
passenger-car hybrid power assemblies, achieve the sales revenue of RMB 3.01
billion, the benefits (pre-tax) of RMB 511 million and the sales tax and surcharges of
RMB 167 million, and increase the employment of 2,600 people.
V. Preliminary work progress: the project has been approved by governmental
department for setup and the land acquisition has been implemented; the
infrastructure in Wanwu Harbor Industrial Park has been well-prepared and the
constructions of water, power, road and pipeline facilities have been finished, so it’s
able to meet the construction and production demand of the project; the products of
the project have passed R&D and pilot-scale testing stages, and have entered into pilot
production and small-lot production. The mass production conditions have been well
prepared.
VI. Unit for the project: Fujian Yueda Motor Group Co., Ltd.
VII. Contact person: Lin Shigong
Tel: 13509578059
84. Ningde Fu’an Zhenzhong New-Energy Electric Car and Hybrid Electric
Yacht Project
I. Project content and construction scale: the project will build the factory
building of 160,000 square meters, and the testing and inspection center of 12,000
square meters. It will construct over 600 pieces (sets) of special apparatus and
equipments and 5 dedicated production lines with the annual capacity of 300, 000 sets
(pieces) of new-energy automobiles and hybrid power yachts.
II. Reasons and conditions for project construction: in the next five to ten years,
China will give policy support to the development of electric car. Electric car has been
included in the top seven strategic and rising industries that will be supported and
developed with focus by China. Zhenzhong Company is an enterprise engaged in the
production of special cranes, electric motors and generators with the annual capacity
of 1 million sets (pieces) of products. It has had unique conditions and advantages on
58
the production of new-energy electric car and hybrid power yacht.
III. Total project investment: RMB 1.5 billion. Cooperation ways: joint venture
or cooperative enterprise.
IV. Analysis on project’s economic benefits: the project’s investment payback
period is estimated to be 8.7 years (including construction period), IRR will be
15.70 % and ROI will be 17.53%.
V. Preliminary work progress: It has developed 0.8KW-30KW electric
car-dedicated brushless RE permanent-magnet motor and developed 0.8KW-30KW
electric car controller with National University of Defense Technology. It has
developed two 2-4-seat low-speed sample electric cars.
VI. Unit for the project: Fu’an Municipal Zhenzhong Electric Manufacture Co.,
Ltd.
VII. Contact person: Lin Zhenzhong
Tel: 13905033562
85. Ningde Fu’an Zhenzhon New-Energy Electric Car Project
I. Project content and construction scale: the project will build the factory
building of 160,000 square meters, and the testing and inspection center of 12,000
square meters. It will construct over 600 pieces (sets) of special apparatus and
equipments and 5 dedicated production lines with the annual capacity of 300, 000
new-energy electric cars of different kinds.
II. Reasons and conditions for project construction: New-energy electric car has
been included in the top seven strategic and rising industries of China. Zhenzhong
Company is an enterprise engaged in the production of special cranes, electric motors
and generators with the annual capacity of 1 million sets (pieces) of products. It has
had unique advantages on the production of new-energy electric cars.
III. Total project investment: RMB 1.5 billion. Cooperation ways: joint venture
or cooperative enterprise.
IV. Analysis on project’s economic benefits: the project’s investment payback
period is estimated to be 8.7 years (including construction period), IRR will be
15.70 % and ROI will be 17.53%.
V. Preliminary work progress: It has developed 0.8KW-30KW electric
59
car-dedicated brushless Rare Earth permanent-magnet motor and developed
0.8KW-30KW electric car controller with National University of Defense Technology.
It has developed two 2-4-seat low-speed sample electric cars.
VI. Unit for the project: Fu’an Municipal Zhenzhong Electric Manufacture Co.,
Ltd.
VII. Contact person: Lin Zhenzhong
Tel: 13905033562
86. Xiamen Baoda Yacht Industrial Park Project
I. Project content and construction scale: yacht manufacturing and construction
of Yacht Industrial Park with the land of over 100 Mu for use
II. Total project investment: RMB 300 million. Cooperation ways: joint venture,
cooperative enterprise.
III. Preliminary work progress: the project’s feasibility study report has been
formulated.
IV. Unit for the project: Xiamen Baoda Yacht Co., Ltd.
V. Contact person: Wang Yun
Tel: 13306069888
87. Zhangzhou Dongshan Yacht Manufacturing and Auxiliary Project
I. Project content and construction scale: The yacht project has a land area of 100
Mu and the annual capacity of 100 yachts and the related auxiliary projects.
II. Total Investment: RMB 63 million
III. Preliminary work progress: The project has finished general planning and site
selection. The land has had “five supplies and one leveling”.
IV. Unit for the project: Dongshan Economic and Technical Development Zone
V. Contact person: Lin Wanquan
60
Tel: 0596-5885007
88. Zhangzhou 100,000-Tonnage Shipyard Project
I. Project content and construction scale: It covers a land area of about 1000 Mu
with the shoreline of about 800 meters. It can contain a 100,000-tonnage dock and
auxiliary facilities for shipbuilding.
II. Total Investment: RMB 1.2 billion
III. Preliminary work progress: The project land has been prepared.
IV. Unit for the project: Investment Promotion Bureau of Zhangzhou
Development Zone
V. Contact person: Gan Chaowei
Tel: 0596-6852325
89. Shipbuilding Project of Quanzhou Shipyard
I. Project content and construction scale: The total planned area of the project is
about 4,462 Mu, including the land area of 931 Mu and the marine area of 3,531 Mu.
After the project is constructed, it will have the annual capacity of 2.6 million dead
weight tonnage. Its representative products are 100,000-tonnage ship,
170,000-tonnage ship and 8000 TEU container vessel. It will try to build
globally-advanced luxury cruise, conventional and high-speed ferryboat, container
vessel, chemical tanker and marine service platform as soon as possible.
II. Reasons and conditions for project construction: With a temperate climate,
broad land area, good geological conditions, long deep-water shoreline, great
shielding conditions, Douwei harbor district on the south bank of Meizhou Bay enjoys
exceptionally advantageous natural developing conditions. The project will fill in the
gap that Fujian coastal area and Taiwan Strait are unable to repair or build large
vessels and is beneficial for perfection of auxiliary system of shipbuilding industry.
III. Total project investment: RMB 4.7 billion
IV. Preliminary work progress: the infrastructure of the project’ location
including water supply, power supply, transportation, dock, communication and
aerodynamic source has been well prepared in advance the construction conditions of
the project has been prepared.
61
V. Unit for the project: Quanzhou Development and Reform Commission
VI. Contact person: Ye Qingshan
Tel: 0595-22199229
Zhong Jianfeng
Fax: 0595-22980551
Email: qz22199229@126.com
90. Quanzhou Hui’an Marine Intermediate-Speed Diesel Engine Project
I. Project content and construction scale: the project will be located in Fujian
Quanzhou Shipbuilding Auxiliary Industrial Park or Hui’an Huidong Industrial Park.
The project has a planned land area of 300 Mu and the annual capacity of 10 million
KW marine diesel engines.
II. Reasons and conditions for project construction: Marine intermediate-speed
diesel engine can be used as auxiliary engine for large vessel, main engine of small
vessel, fishing boat and AHTS vessels, or prime motor of mobile power station. The
engine has a wide range of application and great market demand. As Quanzhou
Shipbuilding Industrial Base gradually takes shape, it will provide a broad market
space for the project.
III. Total project investment: RMB 1.2 billion.
proprietorship, joint venture or cooperative enterprise.
Investment way: sole
IV. Project benefit analysis: the annual output value is RMB 2 billion and
annually-paid tax is RMB 400 million.
V. Preliminary work progress: The industrial layout planning and project
proposal have been formulated.
VI. Unit for the project: Hui’an Project Development Center, Hui’an Huidong
Industrial Area
VII. Contact person: Zhuang Zhaoxu
Tel: 0595-87391181
0595-87878568
Fax: 0595-87391177
0595-87876568
62
91. Quanzhou Hui’an Ship Deck Mechanical Manufacturing Project
I. Project content and construction scale: the project has a planned land area of
200 Mu. It will construct the factory building of 40,000 square meters and annually
produce 300 sets of deck machines of different kinds including anchoring machine,
hoisting machines, steering machine, and different kinds of winches, capstans and
hatch-cover controlling gears.
II. Reasons and conditions for project construction: Quanzhou has planned and
constructed Quanzhou Shipbuilding Industrial Base in Hui’an Douwei Harbor District.
It has the planned shipbuilding capacity of 3 million deadweight tons and the repair
dock has the capacity of 700,000 deadweight tons (including ocean engineering etc).
It will become one of the national top 4 shipbuilding & repair bases. At present, the
shipbuilding and repair project of Quanzhou Shipyard and the project of Baiyuan Ship
have been constructed and out into use here. As Quanzhou Shipbuilding Industrial
Base gradually takes shape, it will provide broad market space for the project.
III. Total project investment: RMB 200 million. Cooperation ways: sole
proprietorship, joint venture or cooperative enterprise.
IV. Analysis on project’s economic benefits: the project will have the annual
output value of RMB 120 million and the annually-paid tax of RMB 25 million.
V. Preliminary work progress: the industrial layout planning and project proposal
have been formulated.
VI. Unit for the project: Hui’an Project Development Center, Hui’an Huidong
Industrial Area
VII. Contact person: Zhuang Zhaoxu
Tel: 0595-87391181
0595-87878568
Fax: 0595-87391177
0595-87876568
92. Putian Port Mechanical Manufacturing Base Auxiliary Project
I. Project content and construction scale: it’s intended to construct two projects:
one produces port equipment on container loading and unloading and bulk cargo
delivery, the other repairs and builds large vessel and marine equipments.
II. Reasons and conditions for project construction: the rear land area of Xiuyu
Harbor District is open and mainly contains short hills and red clay platform. It
63
provides a good geological condition for projects and has a great carrying capacity, so
it can be used as the land of large-scale port mechanical and vessel repair industrial
projects. The project’s location is close to port, which is convenient for the
transportation of raw materials and finished products. And it’s also close to steel and
iron production base and original mechanical manufacturing parks, which helps
acquire raw material and provides a good industrial foundation.
III. Total project investment: RMB 2.92 billion Cooperation ways: joint venture,
sole proprietorship or cooperative enterprise.
IV. Analysis on project’s economic benefits: for Project one, the annual sales
revenue is RMB 360 million, the total profits are RMB 31 million, the total amount of
paid tax is RMB 50 million, internal rate of return (IRR) (after-tax) is 14.65% and
investment payback period is 7.63 years. As for Project two, the sales revenue is RMB
6.55 billion, the total amount of paid tax is RMB 570 million and internal rate of
return (IRR) (after-tax) is 11.56% and investment payback period is 11.5 years.
V. Preliminary work progress: Project one has formulated the project planning
now. Project two has finished the hydrological and geological prospecting on the
marine and land areas of the harbor district and the preliminary work such as the
planning of the shipbuilding and repair project.
VI. Unit for the project: Putian Xiuyu Foreign Economy and Trade Bureau
VII. Contact person: Li Yuqing
Tel: 13959576202
93. Nanping Marine Special Cable Project
I. Project content and construction scale: it will annually produce different kinds
of marine cable and wire of 100,000 kilometers and newly construct production and
auxiliary building of 30,000 square meters; purchase production and testing
equipment; construct auxiliary public service, environmental-protection, firefighting
and OSHA facilities.
II. Reasons and conditions for project construction: As the largest cable
producing area in Fujian, Nanping has had well-prepared production elements such as
talent and technology. Its produced cable equipments are sold to different places. In
the next 10 years, China’s export volume on marine cable will be increased by 5%
every year. It provides a broad developing space for special cable manufacturers.
III. Total project investment: RMB 300 million. Cooperation ways: sole
64
proprietorship.
IV. Analysis on project’s economic benefits: after the project is put into
production, it will have an annual sales revenue of RMB 350 million, total benefits of
RMB 34.51 million and the total amount of paid tax of RMB 51.03 million. The
project’s IRR (before income tax) is 24.54%, the investment payback period is 5.53
years (including construction period) and the break-even point (capacity utilization
rate) is 62.18%.
V. Preliminary work progress: Preliminary feasibility study report has been
formulated by Beijing Mechanical Planning Institute
VI. Unit for the project: Nanping Yanping Project Planning Center
VII. Contact person: Cao Chuanpu
Tel: 0599-6161825
Email: npfgj@163.com
94. Ningde Haixi Industrial Area Ocean Engineering Equipment
Manufacturing Base Project
I. Project content and construction scale: the project covers a land area of 2
square kilometers and mainly produces marine mobile drilling platform (vessel),
floating production system, ocean engineering workboat and auxiliary ships as well as
auxiliary equipments and systems. It’s aimed at building an ocean engineering
equipment manufacturing base of modern technical level.
II. Reasons and conditions for project construction: Ningde has abundant
shoreline resources and enriched deep-water docks. The project can make a full use of
Ningde’s advantageous harbor resources and give a full play to the respective
advantages of CNOOC and COSCO Shipyard.
III. Total project investment: RMB 3 billion. Cooperation ways:
or sole proprietorship
joint venture
IV. Preliminary work progress: The general planning of Haixi Ningde Industrial
Park has been formulated, the marine reclamation project of the initiation project of
the initiation base has been finished, and the 1000 cubic meter crude oil reserve
project has started.
V. Unit for the project: Haixi Ningde Industrial Area Development Co., Ltd.
VI. Contact person: Du Juan
65
Tel: 0593-2910188
95. Zhangzhou Nanjing Project on Basic Parts of CNC Machine Tool
I. Project content and construction scale: two production lines of wire rail,
magazine tool, tool changer, bearing and rotary spindle head.
II. Unit for the project: Nanjing Bureau of Foreign Trade and Economic
Cooperation
III. Contact person: Jiang Guoshun
Tel: 13607551099
96. Zhangzhou Nanjing CNC Floor-Type Milling and Boring Machine, CNC
Plane Milling and Boring Machine and Machining Center
I. Project content and construction scale: 2 production lines of CNC floor-type
milling and boring machine and CNC plane (bridge-type, overhead-type and double
gantry-type) milling and boring machine
II. Unit for the project: Nanjing Bureau of Foreign Trade and Economic
Cooperation
III. Contact person: Jiang Guoshun
Tel: 13607551099
97. Zhangzhou Nanjing Large High-Speed Precision Compound CNC
Machine Tool and Machining Center
I. Project content and construction scale: 2 production lines of large high-speed
precision compound CNC machine tool
II. Unit for the project: Nanjing Bureau of Foreign Trade and Economic
Cooperation
III. Contact person: Jiang Guoshun
Tel: 13607551099
66
98. CNC High-Speed Machine Tool Project of Quanzhou Taiwanese
Investment Zone
I. Project content and construction scale: CNC high-speed machine tool
production line
II. Reasons and conditions for project construction: As international capital and
technology-intensive heavy chemical industry gradually moves to China, the 16 key
fields of China’s equipment manufacturing industry keep a great and long-term
demand on high-speed, precision, efficient and special CNC machine tools such as
high-speed machining tool. Quanzhou Taiwanese Investment Area has planned 8
square kilometers as Mechanical Equipment Manufacturing Park. The auxiliary
infrastructure has been well-developed and project construction conditions have been
prepared.
III. Cooperation ways: sole proprietorship, joint venture or cooperative enterprise
IV. Preliminary work progress: the park planning has been finished and the
infrastructure network has preliminarily taken shape. It’s able to provide
well-developed auxiliary facilities and services.
V. Unit for the project: Technical and Economic Development Bureau of
Quanzhou Taiwanese Investment Zone
VI. Contact person: Ms. Zhuang and Ms.He
Tel: 0595-27395529,13808529689
Tel: 0595-27308666,15159751058
Email: qz27308666@163.com
99. Quanzhou Hui’an CNC Machine Tool Automatic Production Line
Project
I. Project content and construction scale: the project is located in Hui’an
Huidong Industrial Area. It has a planned land area of 200 Mu and is intended to
construct intermediate and high-grade CNC machine tool production lines with the
annual capacity of 1,000 sets of intermediate and high-grade CNC machine tools of
different types.
II. Reasons and conditions for project construction: the domestic market demand
67
on CNC machine tool is over 200,000 sets. The provincial demand is about 10,000
sets. In the next 10 years, CNC machine tool will replace the existing conventional
machine tool. In recent years, Hui’an harbor-centered heavy chemical industries are
rising such as petrochemical, shipbuilding and equipment manufacturing industries.
Hence, in Hui’an, the projects on CNC machine tool will have a great developing
prospect.
III. Total project investment: RMB 200 million. Cooperation ways: sole
proprietorship, joint venture or cooperative enterprise.
IV. Analysis on project’s economic benefits: after the project is put into use, it
will have an annual output value of RMB 400 million and the tax of RMB 70 million.
V. Preliminary work progress: the industrial layout planning has been formulated,
and the auxiliary infrastructure required by the project including water, power and
road etc. have been preliminarily prepared.
VI. Unit for the project: Hui’an Huidong Industrial Area
VII. Contact person: Zhuang Zhaoxu
Tel: 0595-87878568
Fax: 0595-87876568
100. Sanming Mingxi Pneumatic Precision Mechanical Parts Processing
Project
I. Project content and construction scale: it will annually produce 10 million sets
of pneumatic precision mechanical parts such as jackhammer, gun-drill, hand riveter
and extension tube etc.
II. Reasons and conditions for project construction: Pneumatic tool industry is
one of the key industries of Mingxi County that has a group of backbone enterprises
and has had certain industrial development base. Pneumatic precision driving
component processing is still blank in Chinese mainland. After the project is put into
use, it will become a new processing and manufacturing center on precision tool’s
driving components and a supporting enterprise of pneumatic tool industry and its
products will be sold to Chinese mainland, Taiwan, Japan and Thailand. Hence, it
enjoys a great market prospect.
III. Total project investment: RMB 75 million. Cooperation ways: sole
proprietorship or joint venture.
IV. Analysis on project’s economic benefits: after the project is put into
68
production, it will have an annual sales revenue of RMB 63 million and the benefits
of RMB 18.7 million. The investment payback period is 4 years (not including
construction period).
V. Unit for the project: Sanming Mingxi Investment Promotion Bureau
VI. Contact person: Lin Zengyun
Tel: 13850876357
101. Zhangzhou Large-Tonnage Container Fork Truck
I. Project content and construction scale: 3 production lines of fork truck for
large-tonnage container of 40 feet and over 60 tons
II. Unit for the project: Zhangzhou Development Zone
III. Contact person: Gan Chaowei
Tel: 0596-6852325
102. Zhangzhou Nanjing Project of Food Mechanically-Processing
Industrial Park
I. Project content and construction scale: The plant covers a land of 100,000
square meters with the floor area of 60,000 square meters. It will annually produce
300 sets of food processing machines such as high-temperature and high-pressure
sterilization machine, pasteurized machine and vacuum accelerated freeze dryer.
II. Total Investment: RMB 200 million
III. Unit for the project: Nanjing Bureau of Foreign Trade and Economic
Cooperation
IV. Contact person: Jiang Guoshun
Tel: 13607551099
69
103. Longyan Bearing Production Project
I. Project content and construction scale: the project will construct a production
line with the annual capacity of 200,000 sets of bearings for heavy-duty cargo trucks
and engineering machineries, 80,000 sets of bearings for high-speed passenger cars
and 20,000 sets of bearings for precision rolling mill and related auxiliary mechanical
facilities etc.
II. Reasons and conditions for project construction: Mechanical industry has
been Longyan’s pillar industry. It has shaped the mechanical industrial cluster cored
with engineering machineries and environmental-protection machineries. It owns a
group of technicians with mechanical processing and production experiences and has
abundant labor resources. The project’s location has increasingly perfecting
infrastructure. A modern 3D transportation network supported by an airport, 4
railways, 4 highways and 8 state and provincial roads has taken shape.
III. Total project investment: RMB 550 million. Cooperation ways: sole
proprietorship.
IV. Analysis on project’s economic benefits: after the project is put into
production, the project will have the annual sales revenue of RMB 1 billion and the
paid tax of RMB 250 million.
V. Preliminary work progress: Preliminary feasibility study report has been
formulated.
VI. Unit for the project: Longyan Municipal Project Development Center
VII. Contact person: Wu Hongkui
Tel: 13959478254
104. Longyan Changting Textile Machinery Production Project
I. Project content and construction scale: it will annually produce 3,000 sets of
spinning frames and auxiliary post-processing equipment.
II. Reasons and conditions for project construction: Changting County and its
surrounding area have a lot of textile enterprises, but there hasn’t been any textile
machinery manufacturing enterprise. Changting has well-developed infrastructure
such as transportation and great mechanical processing capacity. The County has the
casting capacity of over 20,000 tons. All of these are favorable for the settlement of
large-scale textile machinery enterprises.
70
III. Total project investment: RMB 300 million. Cooperation ways: sole
proprietorship.
IV. Analysis on project’s economic benefits: after the project is put into
production, the project will have the annual output value of RMB 600 million and the
annual benefits of RMB 60 million.
V. Preliminary work progress: the project proposal has been formulated.
VI. Unit for the project: Changting Textile Industrial Development Bureau
VII. Contact person: Lan Youhao
Tel:13605924179
105. Quanzhou An’xi Haixi Tea-making Equipments Industrial Base
Auxiliary Service Project
I. Project content and construction scale: the project covers a land area of 210
Mu, with the floor area of 200,000 square meters and the total investment of RMB
500 million. It plans to construct a tea-making equipment industrial base integrating
R&D, production, exhibition, information, storage, sales, distribution and service.
II. Reasons and conditions for project construction: Haixi Tea-making
Equipments Industrial Base investment project is located beside Provincial Road 308
and 5 kilometers away from entry of Shenyang-Haikou Highway and neighbors China
Tea Capital and Tea Expo. It enjoys a geographic advantage and convenient
transportation.
III. Total project investment: the total Investment is RMB 100 million
IV. Analysis on project’s economic benefits: it’s expected to have the annual
operating revenue of RMB 30 million and the net profit of RMB 15 million. The
investment payback period is about 6 years.
V. Preliminary work progress: At present, the land application, acquisition and
preparation is ongoing and conceptual design is being optimized. It’s planned to be
constructed and put into use in 2013. A special development, construction and
administration institution has been established.
VI. Unit for the project: Administration Committee of Anxi Urban Industrial
Park
VII. Contact person: Li Zhimin
71
Tel: 0595-23280631,13959934199
Email: 240631204@qq.com
72
Petrochemical Industry
106. Xiamen New Eco-Friendly Lyocell Long Fiber
I. Scale and contents: Land area of the project is 43,000 square meters. Public,
recycled and warehouse land have been planned.
II. Cooperation mode: Joint venture, cooperation
III. Project organizer: Xiamen JLD Company
IV. Contact Person: He Wenfeng
Tel: 13306018369
107. Zhangzhou Oil Refinery Project of Annual Output of 15 Million Tons,
and Ethylene Project of Annual Output of 2 Million Tons
I. Scale and contents: mainly construct oil refinery project of annual output of 15
million tons, ethylene device of annual output of 2 million tons and petrochemical
downstream products of alkene derivations.
II. Project organizer: Fujian Gulei Development Zone Management Committee
III. Contact person: Guo Shubin
Tel: 13709310966
108. Zhangzhou Fine Chemical Production Project
I. Scale and contents: Land area is 300 mu for constructing fine chemical
production base for 160,000-ton acrylic acid and 160,000-ton butyl acrylate with the
annual revenue of 20 billion Taiwan dollars.
II. Total investment: 1800 mllion yuan
III. Project organizer: Zhangpu County Foreign Economic and Trade Bureau
IV. Contact person: Wu Mingzhi
73
Tel: 0596-3291792
109. Quanzhou Quangang 1,3- Propylene Glycol
I. Scale and contents: 20,000-ton 1,3- Propylene Glycol per year
II. Construction reasons and conditions: The major uses of Propylene Glycol are
for production of polymers such as unsaturated polyester, polyether and polyurethane
etc., and for solvent and food additives. At present, there is a large deficiency in
propylene glycol market.
III. Analysis of economic benefits: The annual average sales revenue is 260
million yuan after completion, and the annual average total profit and tax will be 60
million yuan with the value-added being 80 million yuan.
IV. Total investment: 300 million yuan. Cooperation mode: exclusive foreign
investment, sino-foreign joint venture or cooperation.
V. Preliminary work: The site selection has been preliminarily completed.
VI. Project organizer: Quangang Petrochemical Industrial Zone Construction &
Development Co. Ltd.
VII. Contact person: Zhuang Minfang
Tel: 0595-27728271
110. Quanzhou Quangang ABS Resin
I. Scale and contents: ABS resin of 300,000-ton per year
II. Construction reasons and conditions: ABS resin is a thermal plastic compound
resin produced through synthesizing and mixing three monomer AN, BTA and SM.
The three monomers can supplement each other with their own advantages through
combination. It is easy to process; thus it is a thermal plastic engineering plastic with
quite extensive purposes.
III. Analysis of economic benefits: The annual average sales revenue is 3450
million yuan, and the annual average profit and tax will be 527.6 million yuan with
the annual average profit being 378.3 million yuan after the project is put into
production. The profit and tax rate is 21.4%, and the profit rate is 15.3%.
74
IV. Total investment: 2,471.2 million yuan. Cooperation mode: exclusive
investment or joint venture.
V. Preliminary work: Site selection has been preliminarily completed.
VI. Contact organization: Quangang District Economic and Trade Bureau
VII. Contact person: Zhuang Tao Zhong Yunfeng
Tel: 0595-87993100
Fax: 0595-87987653
111. Quanzhou Quangang Aniline
I. Scale and contents: Aniline(80,000 tons per year)
II. Construction reasons and conditions: Aniline is an important chemical raw
material and organic intermediate, through which over three hundreds of chemical
products can be produced. Demands for aniline have risen rapidly in recent years.
Especially, there is a great deficiency in MDI-level Aniline.
III. Analysis of economic benefits: The annual average sales revenue will be 880
million yuan, and the total annual average profit and tax will be 300 million yuan with
the value-added being 350 million yuan after project completion.
IV. Total investment: 97 million yuan. Cooperation mode: exclusive investment
or joint venture.
V. Preliminary work: Site selection has been preliminarily completed.
VI. Project organizer: Quangang Petrochemical Industrial Zone Construction&
Development Co. Ltd.
VII. Contact person: Zhuang Minfang
Tel: 0595-27728271
112. Quanzhou Quangang Phenol Acetone
I. Scale and contents: Produce 200,000 tons of phenol acetone annually
II. Construction reasons and conditions: Phenol is an important organic chemical
raw material that ranks first in the secondary products of domestic benzene. Acetone
75
is an important organic solvent that is mutually soluble with water, and can be solved
in several organic solvents such as alcohol, ether, oil and hydrocarbon etc. The
demands for it rise by 6% annually on average in recent years, thus there is a huge
deficiency and it shall be imported in large quantities.
III. Total investment: 1200 million yuan. Cooperation mode: exclusive
investment or joint venture.
IV. Analysis of economic benefits: The annual average sales revenue is 1520
million yuan after completion, and the annual average total profit and tax will be 140
million yuan with the value-added being 210 million yuan.
V. Preliminary work: Site selection has been preliminarily completed.
VI. Project organizer: Quangang District Economic and Trade Bureau
VII. Contact person: Zhuang Tao Zhong Yunfeng
Tel: 0595-87993100
Fax: 0595-87987653
113. Quanzhou Quangang Phthalic Anhydride
I. Scale and contents: 40,000 tons of phthalic anhydride per year
II. Construction reasons and conditions: Phthalic anhydride is an important basic
organic raw material, and is the major raw material to produce plasticizer, polyester
resin and alkyd resin. The demands in 2015 are estimated to be about 1.65 million
tons.
III. Total investment: 316 million yuan. Cooperation mode: exclusive investment
or joint venture.
IV. Analysis of economic benefits: The estimated annual sales revenue is 312
million yuan, and the annual profit will be 41.2 million yuan with the investment
profit rate being 13.0%.
V. Preliminary work: Site selection has been preliminarily completed.
VI. Project organizer: Quangang Petrochemical Industrial Zone Construction&
Development Co. Ltd.
VII. Contact person: Zhuang Minfang
Tel: 0595-27728271
Fax: 0595-27728270
76
114. Quanzhou Quangang SM
I. Scale and contents: 500,000 tons of SM
II. Construction reasons and conditions: SM is mainly used for producing PS,
ABS/SAN resin, styrene butadiene rubber, latex and thermal plastic elastomers etc. At
present, there is serous deficiency in domestic supply, thus the domestic
manufacturing capacity of SM shall be increased urgently.
III. Total investment: 1200 million yuan. Cooperation mode: exclusive
investment or joint venture.
IV. Analysis of economic benefits: The annual sales revenue is estimated to be
450 million yuan.
V. Preliminary work: Site selection has been preliminarily completed.
VI. Project organizer: Quangang District Economic and Trade Bureau
VII. Contact person: Zhuang Tao Zhong Yunfeng
Tel: 0595-87993100
Fax: 0595-87987653
115. Quanzhou Quangang Acrylonitrile
I. Scale and contents: 250,000 tons of acrylonitrile per year
II. Construction reasons and conditions: Acrylonitrile is flammable and deadly
poisonous, and it is mutually soluble with most of organic solvents. It is quite
important in high polymer materials such as synthetic fiber and synthetic resin etc.
There is a huge deficiency in domestic acrylonitrile market. The demands for it have
taken on great growth momentum.
III. Total investment: 1900 million yuan. Cooperation mode: exclusive
investment or joint venture.
IV. Analysis of economic benefits: The estimate annual average sales revenue is
3030 million yuan, and the total annual average profit and tax is 560 million yuan
with the value-added being 690 million yuan after the project is put into production.
V. Preliminary work: Site selection has been preliminarily completed.
77
VI. Project organizer: Quangang District Economic and Trade Bureau
VII. Contact person: Zhuang Tao Zhong Yunfeng
Tel: 0595-87993100
Fax: 0595-87987653
116.Quanzhou Quangang Acrylonitrile-Butadiene-styrene Copolymer
I. Scale and contents: 300,000 tons of Acrylonitrile-Butadiene-styrene
Copolymer per year
II. Construction reasons and conditions: ABS is one of the thermal engineering
plastics with good comprehensive properties, and the thermal deformation
temperature is higher than that of polystyrene and pvc. It is extensively applied in
industrial and daily goods such as machinery, electronic, electrical appliances,
automobiles, plane, ship and agricultural machinery.
III. Total investment: 2470 million yuan. Cooperation mode: exclusive
investment or joint venture.
IV. Analysis of economic benefits: The annual average sales revenue is 3450
million yuan after completion, and the annual average total profit and tax will be 530
million yuan with the value-added being 700 million yuan.
V. Preliminary work: Site selection has been preliminarily completed.
VI. Project organizer: Quangang Petrochemical Industrial Zone Construction&
Development Co. Ltd.
VII. Contact person: Zhuang Minfang
Tel: 0595-27728271
117. Quanzhou Quangang CPP
I. Scale and contents: 1.2 million tons of CPP per year
II. Construction reasons and conditions: CPP technology takes heavy oil as raw
material, and produces low-carbon alkene through catalytic pyrolysis, and enjoys
quite desirable industrial prospect in production of ethylene and propene etc.
III. Total investment: 2150 million yuan. Cooperation mode: exclusive
78
investment or joint venture.
IV. Analysis of economic benefits: The estimated annual average sales revenue is
3080 million yuan after the project is put into production, and the annual average
profit is 422.5 million yuan with the profit rate being 19.7%;
V. Preliminary work: Site selection has been preliminarily completed.
VI. Project organizer: Quangang District Economic and Trade Bureau
VII. Contact person: Zhuang Tao Zhong Yunfeng
Tel: 0595-87993100
Fax: 0595-87987653
118. Quanzhou Quangang Butyl Rubber
I. Scale and contents: 40,000 tons of Butyl Rubber per year
II. Construction reasons and conditions: Butyl rubber has properties such as
excellent air tightness, heat resistance, and resistance to aging, ozone and solvent,
electrical insulation, vibration reduction and low water absorption etc. Butyl rubber is
an important raw material for auto industry and tire manufacturing industry.
III. Total investment: 1470 million yuan
IV. Analysis of economic benefits: The annual average sales revenue is estimated
to be 800 million yuan after completion, and the annual average total profit and tax
will be 250 million yuan with the value-added being 360 million yuan.
V. Preliminary work: Site selection has been preliminarily completed.
VI. Project organizer: Quangang District Economic and Trade Bureau
VII. Contact person: Zhuang Tao Zhong Yunfeng
Tel: 0595-87993100
Fax: 0595-87987653
119. Quanzhou Quangang Butanol-octanol
I. Scale and contents: 290,000 tons of Butanol-octanol per year
II. Construction reasons and conditions: Butanol and octanol are colorless,
79
transparent and flammable oily liquids with special smells. Both of them are medium
poisonous, and are important raw materials for synthetic refined chemical products.
At present, the total capacity of butanol-octanol device in China has reached 900,000
tons per year, including 330,000 tons of butanol per year, and 570,000 tons of octanol
per year.
III. Total investment: 1078.70 million yuan. Cooperation mode: exclusive
investment or joint venture.
IV. Analysis of economic benefits: The annual average sales revenue is 2,111
million yuan and annual average profit is 149.80 million yuan with the profit rate
being 13.9%.
V. Preliminary work: Site selection has been preliminarily completed.
VI. Project organizer: Quangang Petrochemical Industrial Zone Construction&
Development Co. Ltd.
VII. Contact person: Zhuang Minfang
Tel:0595-27728271
120. Quanzhou Quangang Super Absorbent Resin
I. Scale and contents: 30,000 tons of super absorbent resin per year.
II. Construction reasons and conditions: Super absorbent resin is a new
functional polymer material, which has super function of absorbing water of several
hundreds to thousands times its own weight, and is widely applied in daily use, oil,
chemical industry, light industry, building, medical health and agriculture etc.
III. Total investment: 402.50 million yuan. Cooperation mode: exclusive
investment or joint venture.
IV. Analysis of economic benefits: The annual sales revenue is estimated to be
510 million yuan, and the annual profit is 65.7 million yuan with the investment profit
rate being 16.3%.
V. Preliminary work: Site selection has been preliminarily completed.
VI. Project organizer: Quangang District Economic and Trade Bureau
VII. Contact person: Zhuang Tao Zhong Yunfeng
80
Tel: 0595-87993100
Fax: 0595-87987653
121. Quanzhou Quangang Epoxy Resin
I. Scale and contents: 50,000 tons of epoxy resin per year
II. Construction reasons and conditions: At present, the manufacturing capacity
of epoxy resin of the world is about 1.4 million tons per year, and the consumption is
about 1.3 million tons. Along with the rapid development of automobiles, electronic
and ship building industry, there is a huge development prospect for epoxy resin
product in China.
III. Total investment: 480 million yuan. Cooperation mode: exclusive investment
or joint venture.
IV. Analysis of economic benefits: The annual sales revenue is 1 billion yuan,
and the investment profit rate is 17.0%.
V. Preliminary work: Site selection has been preliminarily completed.
VI. Project organizer: Quangang Petrochemical Industrial Zone Construction&
Development Co. Ltd.
VII. Contact person: Zhuang Minfang
Tel: 0595-27728271
122. Quanzhou Quangang Ethylene Oxide/Glycol
I. Scale and contents: 250,000 tons of ethylene oxide and 300,000 tons of glycol
per year
II. Construction reasons and conditions: At present, there are about a decade of
ethylene oxide/glycol manufacturers in China. However, due to insufficient
newly-added device of ethylene oxide in recent years in China, the production thereof
has not been increased greatly, thus such product shall be still imported in a large
quantity.
III. Total investment: 1750 million yuan. Cooperation mode: exclusive
investment or joint venture.
IV. Analysis of economic benefits: The annual average sales revenue is 200
81
million yuan, and the total annual average profit and tax is 300 million yuan.
V. Preliminary work: Site selection has been preliminarily completed.
VI. Project organizer: Quangang District Economic and Trade Bureau
VII. Contact person: Zhuang Tao Zhong Yunfeng
Tel: 0595-87993100
Fax: 0595-87987653
123. Quanzhou Quangang Adipate
I. Scale and contents: 70,000 tond of adipate per year
II. Construction reasons and conditions: Adipate is the most important aliphatic
dibasic acid, and the technology of producing alcohol ketone through cyclohexene
with benzene being the raw material is recommended for the project, and nitric acid
oxidation technology is recommended for adipic acid manufacturing process.
III. Total investment: 979.1 million yuan. Cooperation mode: exclusive
investment or joint venture.
IV. Analysis of economic benefits: The annual average sales revenue is estimated
to be 1050 million yuan, the annual average profit and tax is 196.8 million yuan, and
the annual average profit is 138.05 million yuan with the profit and tax rate being
20.1% and profit rate being 14.1%.
V. Preliminary work: Site selection has been preliminarily completed.
VI. Project organizer: Quangang District Economic and Trade Bureau
VII. Contact person: Zhuang Tao Zhong Yunfeng
Tel: 0595-87993100
124. Quanzhou Quangang CPL
I. Scale and contents: 100,000 tons of CPL per year
II. Construction reasons and conditions: CPL is mainly used for polymerizing
polyamide sections, and then processing nylon-6 fibers and nylon-y engineering
plastics etc. It is widely applied in automobiles, electronic and electrical appliances,
82
package, machinery and daily goods etc.
III. Total investment: 2378.9 million yuan. Cooperation mode: exclusive
investment or joint venture.
IV. Analysis of economic benefits: The annual sales revenue is estimated to be
1820 million yuan, and the total annual profit is 34,494 million yuan with the
investment profit rate being 14.5% after the project is put into production.
V. Preliminary work: Site selection has been preliminarily completed.
VI. Contact organization: Quangang District Economic and Trade Bureau
VII. Contact person: Zhuang Tao Zhong Yunfeng
Tel: 0595-87993100
Fax: 0595-87987653
125. Quanzhou Quangang MMA
I. Scale and contents: 70,000 tons of MMA per year
II. Construction reasons and conditions: MMA is a colorless volatile liquid, and
an important organic chemical product, which is mainly used to produce PMMA, and
other resins and plastic modifiers etc.
III. Analysis of economic benefits: The annual sales revenue is estimated to be
1114.08 million yuan, and the total annual profit is 190.57 million yuan with the
investment profit rate being 20.2% after the project is put into production.
IV. Total investment: 732.54 million yuan. Cooperation mode: exclusive
investment or joint venture.
V. Preliminary work: Site selection has been preliminarily completed.
VI. Contact organization: Quangang District Economic and Trade Bureau
VII. Contact person: Zhuang Tao Zhong Yunfeng
Tel: 0595-87993100
Fax: 0595-87987653
83
126. Quanzhou Quangang MTBE
I. Scale and contents: 70,000 tons of MTBE per year
II. Construction reasons and conditions: MTBE is a transparent and colorless
liquid of a high octane value, and is an ideal blending component to produce leadless
oxygenated gasoline with a high octane value, which can not only effectively improve
automobile properties, but also lower the manufacturing cost of gasoline.
III. Total investment: 60 million yuan. Cooperation mode: exclusively foreign
investment, sino-foreign joint venture or cooperation.
IV. Analysis of economic benefits: The annual average sales revenue is 250
million yuan after completion, and the value-added is 20 million yuan.
V. Preliminary work: Site selection has been preliminarily completed.
VI. Project organizer: Quangang Petrochemical Industrial Zone Construction&
Development Co.Ltd.
VII. Contact person: Zhuang Minfang
Tel: 0595-27728271
127. Quanzhou Quangang Methane Chloride
I. Scale and contents: 80,000 tons of methane chloride per year
II. Construction reasons and conditions: The demands for dichloromethane will
maintain growth momentum in recent 10 years. The new refrigerant HFC32 produced
with dichloromethane as the raw material is the final substitute of Freon refrigerant
due to excellent eco-friendly properties thereof.
III. Total investment: 400 million yuan. Cooperation mode: exclusive investment
or joint venture.
IV. Analysis of economic benefits: The annual sales revenue is estimated to be
450 million yuan, and the total annual profit is 123.18 million yuan with the
investment profit rate being 26.6% after the project is put into production.
V. Preliminary work: Site selection has been preliminarily completed.
VI. Project organizer: Quangang Petrochemical Industrial Zone Construction &
Development Co. Ltd.
84
VII. Contact person: Zhuang Minfang
Tel: 0595-27728271
128. Quanzhou Quangang MEK
I. Scale and contents: 30,000 tons of MEK per year
II. Construction reasons and conditions: MEK is also called 2-butanone, and is
mainly used as coating solvent, and adhesive solvent. And it is widely applied in tape,
printing ink, and dewaxing of lubrication oil.
III. Total investment: 229 million yuan. Cooperation mode: exclusive investment
or joint venture.
IV. Analysis of economic benefits: The annual average sales revenue is estimated
to be 296 million yuan with the profit and tax being 66.76 million yuan after the
project is put into production.
V. Preliminary work: Site selection has been preliminarily completed.
VI. Contact organization: Quangang District Economic and Trade Bureau
VII. Contact person: Zhuang Tao Zhong Yunfeng
Tel:0595-87993100
Fax: 0595-87987653
129. Quanzhou Quangang Acrylic Fiber
I. Scale and contents: 150,000 tons of acrylic fiber per year
II. Construction reasons and conditions: Acrylic fiber has excellent properties,
and the finished acrylic fiber has good fluffiness and heat retention as well as a soft
hand feel and good climate endurance, anti mildew and anti-moth, and it is also the
raw material of a high-tech product, i.e. carbon fiber.
III. Total investment: 1.6 billion yuan
IV. Analysis of economic benefits: The annual average sales revenue is estimated
to be 2400 million yuan after completion, and the annual average total profit and tax
will be 400 million yuan with the value-added being 510 million yuan.
85
V. Preliminary work: Site selection has been preliminarily completed.
VI. Contact organization: Quangang District Economic and Trade Bureau
VII. Contact person: Zhuang Tao Zhong Yunfeng
Tel: 0595-87993100
Fax: 0595-87987653
130. Quanzhou Quangang PTA
I. Scale and contents: 900,000 tons of PTA per year
II. Construction reasons and conditions: PTA is one of important staple organic
raw materials, and is mainly used to produce polyester fiber and is widely used in
chemical fiber, light industry, electronic and building etc.
III. Total investment: 3.56 billion yuan. Cooperation mode: exclusive investment
or joint venture.
IV. Analysis of economic benefits: The annual average sales revenue is 5850
million yuan after completion, and the annual average total profit and tax will be1360
million yuan with the value-added being 1600 million yuan.
V. Preliminary work: Site selection has been preliminarily completed.
VI. Project organizer: Quangang Petrochemical Industrial Zone Construction&
Development Co. Ltd.
VII. Contact person: Zhuang Minfang
Tel: 0595-27728271
131. Quanzhou Quangang PAM
I. Scale and contents: 20,000 tons of PAM per year
II. Construction reasons and conditions: PAM is the general term of AM
homopolymer and various copolymers. PAM is a low poisonous substance, and has
excellent properties such as flocculation, thickening, resistance reduction, scale
inhibition and glue stabilization etc.. PAM is widely applied in water treatment, paper
making, oil exploitation, mine and metallurgical industry etc.
86
III. Total investment: 375 million yuan. Cooperation mode: exclusive investment
or joint venture.
IV. Analysis of economic benefits: The annual average sales revenue is 400
million yuan and the annual average profit is 62.90 million yuan with the profit rate
being 16.8% after the project is put into production.
V. Preliminary work: Site selection has been preliminarily completed.
VI. Contact organization: Quangang District Economic and Trade Bureau
VII. Contact person: Zhuang Tao Zhong Yunfeng
Tel:0595-87993100
Fax: 0595-87987653
132. Quanzhou Quangang PTT
I. Scale and contents: 40,000 tons of PTT per year
II. Construction reasons and conditions: PTT resin has good processing
properties, electrical properties, mechanical properties and dimensional stability, and
is mainly used in clothing material, carpet material, engineering plastic, film material
and other fields.
III. Total investment: 400 million yuan
IV. Analysis of economic benefits: The annual average sales revenue is estimated
to be 290 million yuan after completion, and the annual average total profit and tax
will be 70 million yuan with the value-added being 90 million yuan.
V. Preliminary work: Site selection has been preliminarily completed.
VI. Project organizer: Quangang Petrochemical Industrial Zone Construction&
Development Co. Ltd.
VII. Contact person: Zhuang Minfang
Tel: 0595-27728271
133. Quanzhou Quangang PBT
I. Scale and contents: PBT device with a capacity of 40,000 ton per year
87
II. Construction reasons and conditions: PBT resin is an important engineering
plastic, and is widely applied in electronics, electrical, office machine, and automobile
industry etc., and can produce excellent fiber products.
III. Total investment: 300 million yuan. Cooperation mode: exclusive foreign
investment, sino-foreign joint venture or cooperation.
IV. Analysis of economic benefits: The annual average sales revenue is 640
million yuan after completion, and the annual average total profit and tax will be 80
million yuan with the value-added being 100 million yuan.
V. Preliminary work: Site selection has been preliminarily completed.
VI. Project organizer: Quangang Petrochemical Industrial Zone Construction&
Development Co. Ltd.
VII. Contact person: Zhuang Minfang
Tel: 0595-27728271
134. Quanzhou Quangang PTMEG
I. Scale and contents: PTMEG device with a capacity of 30,000 tons per year
II. Construction reasons and conditions: PTMEG is a linear polyether diol, and is
white and waxy solid under normal temperature. It is mainly used for producing
polyurethane elastomer, spandex, ester and ether copolymer elastomer. At present,
domestic supply of PTMEG basically depends on import.
III. Total investment: 750 million yuan. Cooperation mode: exclusive foreign
investment, sino-foreign joint venture or cooperation.
IV. Analysis of economic benefits: The annual average sales revenue is 900
million yuan after completion, and the annual average total profit and tax will be 240
million yuan with the value-added being 290 million yuan.
V. Preliminary work: Site selection has been preliminarily completed.
VI. Project organizer: Quangang Petrochemical Industrial Zone Construction&
Development Co. Ltd.
VII. Contact person: Zhuang Minfang
Tel: 0595-27728271
88
135. Quanzhou Quangang PC
I. Scale and contents: 100,000 tons PC per year
II. Construction reasons and conditions: PC is a transparent counterbalance
plastic with a high plasticity and can be used under high temperature from 135 to
145 ℃ . It has excellent electrical insulation, extension, dimensional stability,
resistance to chemical erosion, and is mainly used as high-grade insulation, electrical
appliances, electronics and automobiles etc. The domestic demands rises about 10%
annually on average.
III. Total investment: 3.05 billion yuan. Cooperation mode: exclusive investment
or joint venture.
IV. Analysis of economic benefits: The annual average sales revenue is estimated
to be 4400 million yuan after completion, and the annual average total profit and tax
will be 720 million yuan with the value-added being 940 million yuan.
V. Preliminary work: Site selection has been preliminarily completed.
VI. Contact organization: Quangang District Economic and Trade Bureau
VII. Contact person: Zhuang Tao Zhong Yunfeng
Tel: 0595-87993100
Fax: 0595-87987653
136. Quanzhou Quangang PVA
I. Scale and contents: 70,000 tons of PVA per year
II. Construction reasons and conditions: PVA is the only water soluble polymer
discovered at present, and is produced through alcoholysis and polyaddition of VAM.
The application fields cover textile, foods, medicine, building, woods processing,
paper making, printing, agriculture and metallurgical field etc.
III. Total investment: 730 million yuan. Cooperation mode: exclusive investment
or joint venture.
IV. Analysis of economic benefits: The annual average sales revenue is 910
million yuan after completion, and the annual average total profit and tax will be 190
million yuan with the value-added being 250 million yuan.
89
V. Preliminary work: Site selection has been preliminarily completed.
VI. Contact organization: Quangang District Economic and Trade Bureau
VII. Contact person: Zhuang Tao Zhong Yunfeng
Tel:0595-87993100
Fax: 0595-87987653
137. Quanzhou Quangang Nylon 66 Salt
I. Scale and contents: 100,000 tons of nylon 66 salt per year
II. Construction reasons and conditions: Nylon 66 salt is the major raw material
to produce polyamide (nylon) fiber and resin. It is estimated that production of
polyamide fiber in China will grow by about 5% annual on average in several years to
come, and the project enjoys a favorable market prospect.
III. Total investment: 476 million yuan. Cooperation mode: exclusive investment
or joint venture.
IV. Analysis of economic benefits: The annual average sales revenue is 1800
million yuan, and the annual average profit is 83.7 million yuan with the profit rate
being 17.6%.
V. Preliminary work: Site selection has been preliminarily completed.
VI. Project organizer: Quangang Petrochemical Industrial Zone Construction&
Development Co. Ltd.
VII. Contact person: Zhuang Minfang
Tel: 0595-27728271
138. Quanzhou Quangang Petroleum Resin
I. Scale and contents: 50,000 tons of petroleum resin per year
II. Construction reasons and conditions: Petroleum resin is characteristic of low
acid value, good mixing property, low melting point, waterproof, resistance to alcohol
and chemicals etc., which is mainly used in coating industry, rubber industry and is
also used to produce hot-melt adhesive, traffic road sign paint, printing ink and paper
hydrophobic etc. The demands are estimated to reach about 300,000 ton in 2015.
90
III. Total investment: 530 million yuan. Cooperation mode: exclusive investment
or joint venture.
IV. Preliminary work: Site selection has been preliminarily completed.
V. Contact organization: Quangang District Economic and Trade Bureau
VI. Contact person: Zhuang Tao Zhong Yunfeng
Tel:0595-87993100
Fax: 0595-87987653
139. Quanzhou Quangang Bisphenol A
I. Scale and contents: 100,000 tons of Bisphenol A per year;
II. Construction reasons and conditions: Bisphenol A is an important
intermediate chemical, and is the key raw material to produce PC, epoxy resin and
polyester. It is widely used in improving the properties of resin such as PVC, PE, PP
and PS etc. At present, the domestic manufacturing capacity cannot meet the market
demands.
III. Total investment: 645 million yuan. Cooperation mode: exclusive investment
or joint venture.
IV. Analysis of economic benefits: The annual average sales revenue is 1.3
million yuan after completion, and the annual average total profit and tax will be 205
million yuan with the value-added being 255 million yuan.
V. Preliminary work: Site selection has been preliminarily completed.
VI. Contact organization: Quangang District Economic and Trade Bureau
VII. Contact person: Zhuang Tao Zhong Yunfeng
Tel: 0595-87993100
Fax: 0595-87987653
140. Quanzhou Quangang MA
I. Scale and contents: 50,000 tons of MA per year
II. Construction reasons and conditions: MA is currently one of the three major
anhydrides, which ranks only after benzoic anhydride and acetic anhydride, and it is
91
mainly used to produce UPR and alkyd resin. It has found wide applications in
pesticides, medicine, coating, ink, lubrication oil additive, paper-making chemicals,
textile modifier, food additive and surface active agent.
III. Total investment: 450 million yuan. Cooperation mode: exclusive investment
or joint venture.
IV. Analysis of economic benefits: The annual average sales revenue is estimated
to be 450 million yuan, and the total annual average profit and tax is 50 million yuan.
The device construction period is 1.5 years.
V. Preliminary work: Site selection has been preliminarily completed.
VI. Contact organization: Quangang District Economic and Trade Bureau
VII. Contact person: Zhuang Tao Zhong Yunfeng
Tel: 0595-87993100
Fax: 0595-87987653
141. Quanzhou Quangang DMC
I. Scale and contents: 30,000 tons of DMC per year
II. Construction reasons and conditions: DMC is an important organic synthetic
intermediate, and can replace deadly poisonous phosgene and DMS as carbonylation
agent and methylating agent to produce many kinds of chemicals. Meanwhile, it can
be used as gasoline additive, organic solvent and can be used to produce
polycarbonate and isocyanate etc.
III. Total investment: 250 million yuan. Cooperation mode: exclusive investment
or joint venture.
IV. Analysis of economic benefits: The annual average sales revenue is estimated
to be 230 million yuan after completion, and the annual average total profit and tax
will be 50 million yuan with the value-added being 70 million yuan.
V. Preliminary work: Site selection has been preliminarily completed.
VI. Contact organization: Quangang District Economic and Trade Bureau
VII. Contact person: Zhuang Tao Zhong Yunfeng
Tel: 0595-87993100
Fax: 0595-87987653
92
142. Quanzhou Quangang Nitrobenzene
I. Scale and contents: 110,000 tons of nitrobenzene
II. Construction reasons and conditions: Nitrobenzene is colloquially called bitter
almond oil, and is almost dissoluble in water, and is compatible in solution with
alcohol and ether. It can be used for making dyes, explosives, drugs and organic
solvent etc. It is mainly used to produce aniline in industry.
III. Total investment: 80 million yuan. Cooperation mode: exclusive investment
or joint venture.
IV. Analysis of economic benefits: The annual average sales revenue is 700
million yuan after completion, and the annual average total profit and tax will be 300
million yuan with the value-added being 350 million yuan.
V. Preliminary work: Site selection has been preliminarily completed.
VI. Project organizer: Quangang Petrochemical Industrial Zone Construction&
Development Co. Ltd.
VII. Contact person: Zhuang Minfang
Tel: 0595-27728271
143. Quanzhou Quangang Isopropanol
I. Scale and contents: 100,000 tons of isopropanol per year
II. Construction reasons and conditions: Isopropanol is an important chemical
product and raw material, and is mainly used to make drugs, cosmetics, plastics,
spices, coatings and dehydrate and detergent in electronic industry. The demands of
isopropanol in China are estimated to be 360,000 tons in 2015.
III. Total investment: 432 million yuan. Cooperation mode: exclusive investment
or joint venture.
IV. Analysis of economic benefits: The annual sales revenue is estimated to be 1
billion yuan, and the annual total cost is 903.8 million yuan, and the annual profit is
64.5 million yuan with the investment profit rate being 14.9%.
V. Preliminary work: Site selection has been preliminarily completed.
93
VI. Project organizer: Quangang Petrochemical Industrial Zone Construction&
Development Co. Ltd.
VII. Contact person: Zhuang Minfang
Tel: 0595-27728271
144. Hui’an PTA
I. Scale and contents: The project is sited in Quanhui petrochemical industrial
zone of Fujian Meizhou Bay Petrochemical base, and the annual manufacturing
capacity is 1.5 million tons of PTA.
II. Construction reasons and conditions: PTA is one of the important raw
materials to produce polyester, and the demands for PTA in China are estimated to
reach about 23.85 million tons in 2015. The domestic demands for PTA will further
rise to about 28.74 million tons in 2020.
III. Total investment: 5.56 billion yuan. Cooperation mode: exclusive investment
or joint venture.
IV. Analysis of economic benefits: The annual average sales revenue is 10.63
billion yuan, and the annual profit is 860 million yuan with the investment profit rate
being 15.5%. The investment recovery period (pre-income tax) is 7.86 years.
V. Preliminary work: The project planning has been approved for implementation
by Fujian Provincial Government.
VI. Project organizer : Quanhui Petrochemical Base Development and
Construction Co. Ltd.
VII. Contact person: Chen Chaoyang
Tel: 0595-87861678
Fax: 0595-87860678
Email: cnqhpc@qq.com
145. Hui’an PET
I. Scale and contents: The project is sited in Quanhui petrochemical industrial
zone of Fujian Meizhou Bay Petrochemical base, and the annual manufacturing
capacity is 0.6 million tons of PET.
II. Construction reasons and conditions: PET belongs to linear saturated
94
polyester resin, and is mainly used in polyester fiber, and has more and more
applications in non-fiber fields such as packing, electronic, and medical health. The
annual average demands will grow by 4.1% in 5 years.
III. Total investment: 1.91 billion yuan. Cooperation mode: exclusive investment
or joint venture.
IV. Analysis of economic benefits: The annual average sales revenue is 5.88
billion yuan, and the annual profit is 240 million yuan with the investment profit rate
being 12.6% and the investment recovery period (pre-income) is 9.09 years.
V. Preliminary work: The project planning has been approved for implementation
by Fujian Provincial Government.
VI. Project organizer: Quanhui Petrochemical Industrial Base Construction&
Development Co. Ltd.
VII. Contact person: Chen Chaoyang
Tel: 0595-87861678
Fax: 0595-87860678
Email: cnqhpc@qq.com
146. Hui’an Unsaturated Polyester Resin
I. Scale and contents: The project is sited in Quanhui petrochemical industrial
zone of Fujian Meizhou Bay Petrochemical base, and the annual manufacturing
capacity is 100,000 tons of unsaturated polyester resin.
II. Construction reasons and conditions: Unsaturated polyester resin is one of
the major varieties of heat convertible resin. Due to its excellent mechanical
properties, electrical properties and resistance to chemical erosion, it is mainly used in
production of glass fiber reinforcement products. Moreover, it is also used to produce
non-reinforced products such as buttons, coating and artificial agate.
III. Total investment: 270 million yuan. Cooperation mode: exclusive investment
or joint venture.
IV. Analysis of economic benefits: The annual average sales revenue is 1020
million yuan, the annual profit is 45 million yuan with the investment recovery period
(pre-income tax) being 7.4 years.
V. Preliminary work: The project planning has been approved for implementation
by Fujian Provincial Government.
VI. Project organizer: Quanhui Petrochemical Industrial Base Construction&
95
Development Co. Ltd.
VII. Contact Person: Chen Chaoyang
Tel: 0595-87861678
Fax: 0595-87860678
Email: cnqhpc@qq.com
147. Putian Meizhou Bay Petrochemical Downstream Industrial Base (Fine
Industry)
I. Construction reasons and conditions: It mainly undertakes the radiation by two
petrochemical industrial zones such as Quangang and Quanhui, and mainly cultivate
six fields such as water-saving improved materials with light pollution and a high
value-added, in-depth processing of polyurethane, plastic products, synthetic fiber and
in-depth processing, supplementary raw materials, and plastics recycle etc.
II. Scale and contents: Thermal plastic polyolefin elastomer of annual capacity of
20,000 tons, plastic alloy project of an annual capacity of 50,000 tons, and
polyurethane sole material is to be constructed in Xianyou Petrochemical Industrial
Park.
III. Total investment: Estimated total investment: 7.2 billion yuan Cooperation
mode: joint venture or exclusive investment.
IV. Preliminary work: The project proposal has been completed.
V. Contact person: Li Xiangyang
Tel: 13860928666
148. Sanming Series Nanometer Calcium Carbonate Products of Annual
Capacity of 50,000 Tons
I. Construction reasons and conditions: Compared with ordinary calcium
carbonate, nanometer calcium carbonate has completely improved physical and
chemical properties such as magnetism, catalytic activity, optical and thermal
resistance, melting point, dispersion and compatibility etc. It is mainly applied in
petrochemical, plastic, rubber industry, paper making industry, coating industry, food
industry and pharmaceutical industry etc.
II. Scale and contents: It occupies a land of 200 mu, and nanometer calcium
carbonate production line of annual capacity of 50,000 tons is to be constructed.
96
III. Total investment: 100 million yuan. Cooperation mode: exclusive
investment.
IV. Analysis of economic benefits: The annual sales output value is 70 million
yuan, and the annual profit is 260 billion yuan with the estimated investment recovery
period being 5 years.
V. Preliminary work: The feasibility study report has been completed.
VI. Project organizer: Datian County Reform and Development Bureau
VII. Contact person:
Su Huadong
Tel & Fax: 0598-7321509
149. Nanping Brief Introduction to Organic Silicon Rubber Project
I. Construction reasons and conditions: Organic silicon rubber compound is
mainly used to produce keys, insulation for electronic and electrical products, cables
and wires and other fields. 40% of the raw material to produce organic silicon rubber,
i.e. silica, is available in Shaowu, thus the raw materials can be obtained in local areas
to reduce investment cost.
II. Scale and contents: make use of the current silica raw materials in Shaowu;
produce 20,000 tons of organic silicon rubber annually.
III. Total investment: 130 million yuan. Cooperation mode: exclusive
investment.
IV. Analysis of economic benefits: The annual sales revenue will be 451.2
million yuan and the profit is 70.50 million yuan after project completion with the
investment recovery period of being 3.8 years.
V.
Preliminary work: The project proposal has been completed.
VI. Project organizer: Shaowu Municipal Reform and Development Bureau
VII. Contact Person: You Lishou
Tel: 0599-6220526
97
150. Long’an Synthetic Resin and Additive of An Annual Capacity of
150,000 Tons
I. Construction scale and content: covering an area of 100 mu
II. Construction reasons and conditions: Waterborne resin is an eco-friendly and
economic new product which takes water as solvent in place of DMF. The project will
be a significant reform in synthetic leather industry.
III. Analysis of economic benefits: The product is eco-friendly, and has a low
cost, a promising market prospect and good economic benefits.
IV. Total investment: 110 million yuan. Cooperation mode: exclusive investment.
V. Preliminary work: The planning and approval of land use have been
completed.
VI. Project organizer: Long’an Development Zone Management Committee
VII. Contact person: Chen Shixiao, Zhang Dehe
Tel:
0593-7283366 l5259328866
Tel:
0593-7285828 l3599189996
Fax: 0593-7995733
151. Quanzhou Quangang Salt Production Project through Seawater
Desalination
I. Scale and contents: Seawater desalination device with a capacity of handling
50,000 ton of seawater per day, salt production device with a capacity of 35,000 tons
per year, and production device of bromine, potassium chloride, magnesium chloride
and magnesium sulfate.
II. Construction reasons and conditions: Construction of the phase II project of
State Grid Nanpu Power Plant, i.e. the combined thermal power project (2×670MW)
is being accelerated, and the residual heat of the power generation project and some
low-grade steam and original seawater have been utilized to put out high-purity pure
fresh water and concentrated seawater through several effective evaporation and
condensing. The concentrated seawater is introduced into salt production project in
the salt yard on the hillside. The salt-making mother liquor enters into the salt
chemical production process to produce chemical products such as bromine,
potassium chloride, magnesium chloride and magnesium sulfate etc. which are in
98
short supply in the market.
III. Total investment: 500 million yuan
IV. Analysis of economic benefits: The project is estimated to product output
value of 300 million yuan after project completion.
V. Preliminary work: Site selection has been preliminarily completed.
VI. Project organizer: Quangang District Reform and Development Bureau
VII. Contact person: Zhang Zhangshui
Tel:0595-87978796
152. Sanming Oleoresin Base and Series Rosin Fine and In-Depth
Processing Project
I. Construction reasons and conditions: Qingliu boasts exploitable area of pine
trees of 0.8 million mu and produces 12,000 tons of oleoresin annually, which is
mainly composed of resin acids and terpene. Rosin has many properties such as
anti-corrosion, anti-humidity, insulation, adhesion, and softening etc.
II. Scale and contents: Construct 100,000 mu of raw material woods for oleoresin
industry, and fine rosin production line of an annual output of 10,000 tons.
III. Total investment: 120 mllion yuan
IV. Analysis of economic benefits: The output value of the project is 150 million
yuan after completion. The annual profit can reach 30 million yuan with the
investment recovery period of being 4 years.
V. Preliminary work: The preliminary feasibility study has been completed.
VI. Project organizer: Qingliu County Forestry Bureau
VII. Contact person: Huang Shulong
Tel: 13950925569
99
153. Nanping Lithium Hexafluorophosphate
Lithium Battery Production Project
and Electrolysis liquid for
I. Construction reasons and conditions: The annual consumption of Lithium
Hexafluorophosphate will exceed 1,000 tons in 2015, and there is obvious insufficient
manufacturing capacity of Lithium Hexafluorophosphate in China, thus it is urgent to
vigorously develop high-quality product.
II. Scale and contents: Lithium Hexafluorophosphate for lithium battery of an
annual capacity of 500 tons, and 5,000 tons of electrolysis liquid.
III. Total investment: 150 million yuan. Cooperation mode: exclusive
investment.
IV. Analysis of economic benefits: The estimated annual sales revenue will be
550 million yuan, and the investment recovery period is 2.36 years.
V. Preliminary work: The preliminary project planning has been completed.
VI. Project organizer: Shaowu Municipal Reform and Development Bureau,
Jintang Industrial Park
VII. Contact person: You Lishou
Tel: 0599-6220526
154. Nanping Activated Carbon In-depth(Fine) Processing Project of An
Annual Capacity of 50,000 Tons
I. Construction reasons and conditions: Jian’ou boasts 631 bamboo processing
enterprises of various scales, and the annual residuals of forestry processing industry
exceeds 200,000 tons.
II. Scale and contents: The construction period is 3 years, and the 4th technology
and production line with wooden activated carbon and phosphoric acid method, and
the fine (in-depth) processing scale of activated carbon of an annual capacity of
50,000 tons has formed. The yield of the first phase of the project is 20,000 tons.
III. Total investment: 200 Million yuan
IV. Analysis of economic benefits: The estimated annual newly-added sales
revenue is 450 million yuan, and the net profit is 61.45 million yuan with the
investment recovery period of being 3.25 years.
100
V. Preliminary work: All the compensation funds for land requisition have been
paid, and the project has been submitted for approval together with the environmental
impact assessment. The relevant formalities for use of land and woods have been
completed.
VI. Project organizer: Fujian Jian’ou Zhixing Activated Carbon Co. Ltd.
VII. Contact person: Wei Anguo
Tel:0599-3850888, 13706012339
Fax: 0599-3838328
Email: joaczx@126.com
155. Fuzhou New Chemical Materials Industrial Chain Project
I. Scale and contents: Western new chemical materials industrial chain project
mainly depends on CPP united device with annual output of 1 million tons to
construct about 8 in-depth petrochemical projects. Recent project construction scale is
2.71 million tons per year.
II. Construction reasons and conditions: Jiangyin industrial zone enjoys the
geographical advantages of being adjacent to the sea and Taiwan. At present, the total
investment that has settled down in western new chemical materials industrial zone
has exceeded 70 billion yuan.
III. Total investment: 20 billion yuan. Cooperation mode: joint venture or
cooperation.
IV. Analysis of economic benefits: The annual average sales revenue is 29.5
billion yuan, and the annual profit and tax is 5.1 billion yuan with the annual profit
being 3.1 billion yuan.
V. Preliminary work: The overall regional environmental impact assessment of
the industrial zone has been approved, and the land used for projects such as CPP and
Polypropylene etc. have been approved.
VI. Project organizer: Jiangyin Industrial Concentration Zone
VII. Contact person: Zheng Xingdong
Tel: 0591-85966275
101
156. Putian Relevant Supplementary Downstream Industrial Chain for
Propane Dyhydrogenation
I. Construction reasons and conditions: The polypropylene and propylene oxide
projects to be constructed etc. are the supplementary projects of propane
dyhydrogenation project, and there is sufficient supply of raw materials in the park.
The polypropylene and propylene oxide etc. can be directly used for production of
color coated steel plate in the park.
II. Scale and contents: Propylene oxide project with an annual capacity of
300,000 million tons, and by-product propanediol project with a capacity of 6,000
tons are to be constructed. And propylene prjoect of an annual capacity of 350,000
tons, acrylic acid project of an annual capacity of 80,000 tons and propylene synthetic
paper project of an annual capacity of 150,000 tons are to be constructed as well.
III. Preliminary work: The preliminary design has been completed.
IV. Contact person: Li Yuqing
Tel: 13959576202
157. Sanming Organic Silicon Monomer and Downstream Product
Processing Project of An Annual Capacity of 100,000 Tons
I. Construction reasons and conditions: Organic silicon material is a new
artificially synthetic chemical material which is widely used in textile, electronics,
electrical appliances, oil, chemical, light industry, building, metallurgical, machinery,
military industry, traffic and transport, medical care etc. The annual growth rate of
domestic demands for organic silicon monomer is 26%, and the domestic market
demands for organic silicon grows rapidly by 15 to 20%.
II. Scale and contents: produce organic silicon monomer of annual capacity of
100,000 tons, organic silicon of an annual capacity of 45,000 ton per year, including
20,000 tons of silicon oil, and 10,000 tons of silicon rubber, and 6,000 tons of silicon
resin, 6,000 tons of silane coupling agent and 3,000 tons of other products per year.
III. Total investment: The estimated Total investment is 1 billion yuan, including
800 million yuan of fixed assets investment. Cooperation mode: exclusive investment.
IV. Analysis of economic benefits: The annual sales value is 2 billion yuan, and
the annual average profit is 460 million yuan with the estimated investment recovery
period being 4 years.
102
V. Preliminary work: The project proposal has been completed.
VI. Project organizer Datian County Reform and Development Bureau
VII. Contact person:
Su Huadong
Tel & Fax: 0598-7321509
158. Sanming Fluorite Chemical Products In-Depth Processing Project
I. Construction reasons and conditions: Qingliu county boasts exploitable reserve
of fluorite of over 12 million tons, and the county has introduced several fluorite
chemical enterprises of a certain scale, and has formed annual manufacturing
capacities of 250,000 tons of fine fluorite powder, 130,000 tons anhydrous
hydrofluoric acid, 30,000s ton of fluoride salt, and 10,000 tons of fluorinated
ammonia, and 10,000 tons of hydrogen fluoride ammonia. The mining and dressing
scale ranks first in the province.
II. Scale and contents: The planned area is 3,000 mu; Mainly develop series
fluorite chemical products;
III. Total investment: 2 billon yuan. Cooperation mode: exclusive investment
IV. Preliminary work: The project proposal has been completed.
V. Project organizer: Qingliu Economic Development Zone Management
Committee
VI. Contact person: Jiang Dingrong
Tel: 13328583956
159. Nanping Brief Introduction to Development Project of Series Fluorite
Chemical Products
I. Construction reasons and conditions: The extractable reserve of fluorite in
Jianyang city exceeds 10 million tons. The area can produce 130,000 tons of
hydrofluoric acid annually.
II. Scale and contents: mainly develop and produce fluorine-containing pesticide
intermediate such as 2-choloride-5-tri-hydrocholride methyl pyridine etc.; textile
modifier of an annual capacity of 1,000 tons; 1,000 tons of trifluoroethanol, and 6,000
103
tons of F12 refrigerant;
III. Total investment: 350 million yuan. Cooperation mode: exclusive investment
IV. Analysis of economic benefits: The investment recovery period is 4 years.
V. Preliminary work: Market investigation and project feasibility study report
have been completed.
VI. Project Project organizer: Jianyang Municipal Investment Bureau
VII. Contact person: Zhang Wenlu
Tel: 0599-5822973
160. Zhangzhou Crude Oil Warehouse Base Project
I. Scale and contents: crude oil warehouse with the annual handling capacity of 5
million tons. The project can be constructed by phases. The annual handling capacity
of crude oil will exceed 1 million tons after construction of the first phase.
II. Total investment: 718.20 million yuan
III. Preliminary work: The land leveling for the project has been completed.
IV. Project organizer: Economic and Technological Development Zone
Management Committee of Zhangzhou Investment Bureau
V. Contact person: Liu Wei
Tel: 0596-6856100
161. Zhangzhou Leather Park Supplementary Industrial Zone
I. Scale and contents: Planned land area is 2,000 mu
II. Total investment: 5,400 nillion yuan
III. Preliminary work: Overall planning has been completed.
IV. Project organizer: Zhangpu Chihu Industrial Zone
104
V. Contact person:
Wu Shaopu
Tel: 0596-3718886
162. Putian Supplementary Reserve Oil Base Project on Northern Bank of
Meizhou Bay
I. Construction reasons and conditions: The water and air of Meizhou Bay are
strong in dilution, and it is appropriate to construct oil processing project there.
Meizhou Bay will provide supply transfer interface for energy and chemical raw
materials for Fujian Province and other provinces after completion of Panyu
commercial reserve oil base of an area of 5 million cubic meters, to form regional
petrochemical industrial concentration zone of Meizhou Bay.
II. Scale and contents: Panyu commercial reserve oil base of an area of 5 million
cubic meters; phase I project of oil processing project on northern bank of Meizhou
Bay;
III. Preliminary work: The preliminary approval is being carried out.
IV. Contact person: Wu Fenggui
Tel: 13850235723
163. Sanming Fluorine Chemical Industrial Park Project
I. Construction reasons and conditions: The reserve of exploitable fluorite inside
Qingliu County exceeds 10 million tons, and the prospective reserve exceeds 30
million tons. Qingliu County enjoys convenient traffic conditions and abundant
resources, which can provide sufficient raw materials and auxiliary materials for
production.
II. Scale and contents: The planned land area is 3,000 mu, and 8-12 fluorine
chemical enterprises are planned for the park, with focus on fine and in-depth
processing of series fluorite products.
III. Total investment: 2 billion yuan
IV. Analysis of economic benefits: Investment recovery period 3 to 5 years.
V. Preliminary work: The project proposal has been completed.
105
VI. Project organizer: Qingliu Economic Development Zone Management
Committee
VII. Contact person: Yang Shengfa
Tel: 18950994733
Email:
qljxgwh@163.com
164. Brief Introduction to Light Textile Chemical New Material Park
Development Project of Nanping Industrial Park
I. Construction reasons and conditions: The park is a hub connecting Changjiang
Delta on the north, and southeastern Fujian Province on the south, and an industrial
concentration zone in the green inland area of the economic zone on the western bank
of Taiwan Strait. It boasts sufficient water and power supply, and perfect
infrastructure.
II. Scale and contents: Light textile and chemical new material industrial park
with a planned area of 1,500 mu. It is intended to carry out strategic cooperation and
high-level grafting with large enterprises inside and outside the province and the
500-best enterprises in the world. Investment direction: light textile and new chemical
material industry.
III. Total investment: 1 billion yuan. Cooperation mode: exclusive investment,
joint venture or BT.
IV. Preliminary work: A batch of medium and small light textile and new
chemical material enterprises have concentrated in the park, which has laid down a
good foundation for development of light textile and new chemical material industrial
park.
V. Project organizer: Fujian Nanping Jiangnan New Area Management
Committee
VI. Contact person: Zhang Guozhi Wu Ruitong
Tel: 0599-8616117
0599-8615183
165. Fu’an Chemical Industrial Park
I. Project location: Fu’an Xiabaishi Town
II. Scale and contents: Construct LNG liquefied gas industrial park; Land area
106
requisitioned: 6, 000 mu.
III. Construction reasons and conditions: The city has introduced liquefied gas
reception station project, and has ports qualified for liquefied gas reception project.
Meanwhile, there is abundant freshwater resource and convenient traffic conditions
with a large inland area, thus it enjoys unique favorable project construction
condition.
IV. Total investment:
or joint venture.
45 billion yuan,Cooperation mode: exclusive investment
V. Analysis of economic benefits: The economic benefit and expenses ratio of the
project is 2.78. The economic internal rate of return is 26.66% with the economic
recovery cycle of 8.32 years. The total rate of return on investment of the project is
14.98%, with the financial recovery period of 7 years.
VI. Preliminary work: The demonstration and assessment of preliminary
planning have been completed.
VII. Project organizer: Fu’an Xiabaishi Town Government
VIII. Contact person: Xue Shuming
Tel: 0593-6877366
107
Biological Pharmaceutical Industry
166. Projects in Fuzhou Biological Pharmaceutical Industrial Park
I. Content and scale: The biological industrial park occupies a land area of
167.86 hectares(2,518mu), and it intends to introduce biological engineering,
biochemical pharmacy, modern TCM and medical instruments manufacturing
enterprises.
II. Description: Lying on the west bank of Wulongjiang River of downtown
Fuzhou, the Park is a picturesque place, which is 14 kms away from downtown
Fuzhou, 30kms away from Mawei Port and 44 kms away from Changle International
Airport.
III. Intended Total investment: subject to companies’ individual conditions.
IV. Progress: being in preparation for the preliminary phase.
V. Project coordinator: Fuzhou Jinshan Industrial Concentrated Zone
Management Committee
VI. Contact: Shi Jianhui, Guo Xiaoxia
Tel:0591-83856888
Fax:0591-83856588
Tel:0591-83856188
Fax:0591-83856588
167. Biopharmaceutical Park of Lianjiang Economic Development Zone
I. Content and scale: Lianjiang Biopharmaceutical Park lies in Dongpu Industrial
Zone of Lianjiang Economic Development Zone. The area is planned to reach 2.2
square kms, and it is divided into the east and west sections. Area of focus includes
genetic engineering drugs, modern TCM, biochemical medicine, and
biopharmaceutical service outsourcing and biomedical engineering etc..
II. Description: Fujian Lianjiang Economic Development Zone lies in the
“half-hour economic circle” of Fuzhou City and enjoys convenient traffic conditions.
At present, it has successfully introduced a number of companies like Fucheng
Biochemical, NEPTUNUS Fuyao, Jinshan Pharmaceutical, etc with investment
amount to over 100 million yuan. New companies will enjoy ready industrial
equipment.
108
III. Investment requirement: 10 million USD for each project, Means of
cooperation: wholly owned or joint ventured;
IV. Progress: The general planning of Dongpu industrial zone is approved, and
the land use complies with the state’s land policies. The land requisition in the
western section has been completed, and the formalities for converting agricultural
field into development land have been submitted for approval. The land in the eastern
section can be leveled by the end of 2012.
V. Project coordinator: County Foreign Trade and Economic Cooperation Bureau
VI. Contact: Xue Nan
Tel: 0591-26153193, 26232339
Fax: 0591-26233966
168. Haicang Biopharmaceutical Park:
I. Content and scale: The recent planned land area for use is 384.20 hectare, and
the future land area for use is 1,000 hectare. It is divided into R&D zone, industrial
zone, storage zone and living zone. Production of genetic engineering drugs, vaccine
products, chemical active pharmaceutical ingredients, diagnostic reagent products,
medical instruments products and health-care products, and food reinforcement
products are its focus. Efforts are being made to develop the Park into a state-level
biopharmaceutical industrial base, to speed up the construction of the biological
pharmaceutical incubation and the platforms for the commercialization of
intermediate experiments and to improve the construction of the industrial zones.
II. Description: The industrial park is granted policy and financial support. The
Park lies in Haicang. Companies will find a solid industry development foundation,
convenient traffic, sophisticated masterplan and will enjoy tailored service there.
III. Intended total investment: 6.6 Billion yuan; Means of Cooperation: joint
ventured and cooperative;
IV. Progress: 75 biopharmaceutical enterprises have concentrated in the
biopharmaceutical zone in Haicang District, of which 20 are large scale ones. 1
post-doctorate workstation and 6 enterprise technical centers of provincial or
municipal level are set up. Moreover, “Fujian-Taiwan (Xiamen) Biopharmaceutical
Cooperation and Exchanges Base” and “Xiamen Haicang District Biopharmaceutical
Feature Industrial Base under State Torch Plan” is established.
V. Project coordinator: Haicang District Investment Promotion Bureau
109
VI. Contact: Xi Yunwen
Tel:0592-6058083, 13459020047
Email: tzcjj@haicang.gov.cn
169. Biopharmaceutical Industrial Park
I. Content and scale: The Park will occupy a land of 3,000 mu, of which 1000mu
belong to Huaren Pianzaihuang Pharmaceutical Industrial Park. It is designed to have
Huaren Pianzaihuang Pharmaceutical Industrial Park playing a leading role and build
the park into a large-scaled, diversified and brand-known park.
II. Description: To the south of the park, there lies a Jingcheng Avenue, which is
connected to the Jingcheng Bridge on the east of the avenue. To the east of the park,
there lies Zhangzhou freight transport station of Longxia railway. In addition,
Jingcheng New Area has smooth water, electricity supply and drainage, power supply
and telecommunication, which will be instrumental in future development.
III. Intended total project investment: 625 million yuan; Means of Cooperation:
own development by enterprises;
IV. Progress: Huaren Pianzaihuang Pharmaceutical Co., Ltd. been set up in the
park, and a level of 500 mu is available. The roads, water drainage and power
facilities are being constructed and perfected.
V. Project coordinator: Jingcheng New Area of Nanjing County
VI. Contact: Yu Zhiyong
Tel: 13960009288
Email: fjnjyzy@163.com
170. Zhangpu Biopharmaceutical Industrial Base
I. Content and scale: The Park is planned to cover an area of about 1,000 mu for
the manufacturing of modern TCM, Chinese traditional patent medicines, biological
drugs, marine drugs, genetic engineering drugs, enzyme preparation, feature chemical
pharmaceutical raw materials, new drug preparations, vaccines and etc..
II. Description: The park lies in the urban suburb of Zhangpu County, Fujian
Province, and is only about 100 kms away from Xiamen and Shantou special
economic zones. It has easy access to state highway 324, Xiamen-Shenzhen Railway,
110
the provincial highway line, Zhangdong highway line and Tongshan Expressway, thus
a convenient traffic. Its management committee, in conjunction with Customs, Exit
and Entry Inspection and Quarantine Bureau, State and Local Taxation Bureau, can
provide tailored service from projects approval, environment supervising, land use,
construction approval, trading, and etc. At present, companies will find it is easy to
access water supply, electricity, communication and other services. 2 pharmaceutical
enterprises have entered into the park.
III. Intended total project investment: The aim is to attract a total 164 million
USD with the actual paid-in capital reaching 164 million USD. The intended means
foreign capital: sole proprietorship.
IV. Progress: The land and the feasibility analysis is completed.
V. Project coordinator: Zhangpu County Sui’an Industrial Zone Development
Company
VI. Contact: Lu Jinshou
Tel: 0596-3206828
Fax: 0596-3299777
Email: zpsa3299528@163.com
171. Yongchun Biopharmaceutical Industrial Park
I. Content and scale: The Park is planned to cover an area of over 320 hectares,
of which 158.3 hectares are set aside for the first phase, which include 95.6 hectares
for industrial development with the employment of 8000 persons and 62.7 hectares
for residence with a population of 20000.
II. Description: Yongchun County is rich in ecological and medicine resources.
Its prospect of cultivating and developing biological pharmacy as its priority has been
enshrined and endorsed by “The Eleventh Five-Year Planning for Pharmaceutical
Industry of Fujian Province”.
III. Intended total project investment: 16 Million USD; Means of Cooperation:
joint ventured, cooperative or solely foreign-owned company
IV. Progress: The construction of the Park is approved by the expert panel. A
1,300 mu of land is requisited for the first phase and infrastructures such as roads,
water supply, drainage, power and telecommunication fall into place. At present,
enterprises such as Zihongyuan, Meijin Technology and Xiangye Biological, etc. are
approved to be set up.
V. Project coordinator: Yongchun County Economic and Trade Bureau
111
VI. Contact: Liu Liangshui, Zheng Yingzi
Tel: 13600725191, 0595-23891358
172. Yongchun Biopharmaceutical Industrial Incubation and Public Service
Platform(Phase I)
I. Content and scale: A 24,012 square metres is set aside for the first phase,
which include a R&D experiment and testing center and an industrial incubation
center.
II. Description: The construction of the platforms are important measures for
Yongchun County to take in order to push forward the development of
biopharmaceutical industry. It will speed up the commercialization of research fruits
by consolidating policy, technology, talents and funds.
III. Intended total project investment: 98 million yuan is intended for the first
phase. Means of cooperation: Institutes of higher education and R&D institutions are
welcome to carry out R&D, intermediate test and inspection and testing business.
IV. Progress: The construction of industrial incubation center is completed with
the affiliated projects practically ended. The main body of the R&D building is
completed.
V. Project Coordinator: Yongchun County Technological R&D Center
VI. Contact: Wang Dagen
Tel: 0595-23899612
173. Biopharmaceutical Industrial Park of Mingxi County
I. Content and scale: The Park covers an area of 500 mu with a total building
area of 488,000 square metres. Functional zones such as a trading centre of biological
pharmacy and Chinese medicines, standard breeding plants, production and
processing zone, storage and logistic center, R&D office building and residential
zones and medicinal botanic garden will be built.
II. Description: Mingxi County put forth the idea of cultivating and developing
biological pharmacy into a leading industry by taking advantage of its ecological
environment and abundant medicinal plants. Mingxi county is one of the Pilot
counties of Biological Pharmacy by using recycling techniques. It is honored with
112
“Hometown of Chinese American Yew” and has been enlisted as a model country of
circular biological pharmacy of Fujian Province. The plan of the Park is compiled by
experts from Fudan University, or Yale in China.
III. Intended total project investment: RMB 560 million yuan with the annual
trading and distribution volume estimated to reach 1.3 billion yuan after completion
of the project. Means of cooperation: solely foreign owned company, joint ventured or
cooperative.
IV. Progress: “Planning for Pharmaceutical Town on the West Bank of Taiwan
Strait” has been complied, and preliminary feasibility study of the project has been
completed.
V. Project coordinator: Mingxi County Investment Bureau of Sanming City
VI. Contact: Lin Zengyun
Tel: 13850876357
Email: mxqhlzy@163.com
174. Zherong Haixi Pharmaceutical Valley
I. Content and scale: The total land area of the project is 2,000 mu, and it is
mainly on planting, research and appreciation of medicinal plants; health preservation
culture, recreational medical treatment, processing and production of TCM herbs, and
a grand function zone for shopping and experience of herbal medicines.
II. Description: The development of Haixi pharmaceutical valley is a symbolic
project to construct “Haixi Pharmaceutical Town”, and is a supplementary project of
the pharmaceutical park and an “urban forest” landscape characteristic of harmonious
coexistence between human and nature that demonstrates the development features of
pharmaceutical industry of Zherong, creates the times charms of “Chinese Hometown
of Radix Pseudostellariae”, and displays profound geological culture of “Haixi
Pharmaceutical Town” and “Construct State Ecological County” .
III. Intended total project investment: About 1 billion yuan; Means of
cooperation: BOT; Term of franchised operation: 30 Years;
IV. Progress: At present, mapping of topographic maps, project planning, and
surrounding control planning program etc. have been completed.
V. Project coordinator: Zherong Pharmaceutical Management Center
VI. Contact: Yuan Jiduan
113
Tel: 0593-8366611, 13959314856
Email: zryjd@126.com
175. Chinese traditional medicine and processing base in Nanjing county of
Zhangzhou city
I. Content and scale: to establish a 10,000-mu processing base for breeding of
improved varieties of TCM materials such as Chinese yam, Eletteria cardamomum
Maton, morinda root, and Andrographis paniculata, processing and production base,
and circulation market with the annual sales volume of Chinese herbal medicines of
10,000 tons.
II. Description: Nanjing of Zhangzhou lies in subtropical monsoon climate, with
the annual average air temperature of 21℃, and annual rainfall of 1,700 mm and
340-day frost-free period. The climate is suitable for planting Chinese herbal
medicines, and there are many peasant planters.
III. Intended total project investment: 150 Million yuan
IV. Progress: The project proposal and land-use plan have been finished.
V. Project coordinator: Nanjing County Foreign Economic & Trade Bureau
VI. Contact: Jian Guoshun
Tel: 13607551099
Email: njjgs@163.com
176. Construction of Sanming Municipal Modern Chinese Patent Drugs and
Natural Vegetable Drugs Industrial Park
I. Content and scale: to construct a 5,000 mu of modern Chinese patent drugs and
natural vegetable drugs industrial park;
II. Description: Sanming is a key area for developing biological industry in
Fujian Province and boasts favorable ecological environment and rich biological
resources. It has been preliminarily found out that there are 1,713 kinds of herbal
materials in the area. The planting scale and product quality of herbal materials of
Sanming enjoy a high reputation in the industry, and Sanming is the first “State
Forestry Biological Industrial Base” entitled by State Forestry Administration.
III. Intended total project investment: Total investment: 5 billion yuan, which is
partly or wholly funds raised from outside the area. Means of cooperation: Sole
proprietorship or joint venture.
IV. Progress: Complete land-use planning and “five linkages(water, power, road,
114
communication, cable TV), two drainages(water and sewage) and one leveling(land
leveling) have been completed.
V. Project coordinator: Sanming Municipal Forestry Bureau, Sanming Municipal
Biopharmaceutical Office
VI. Contact: Zhang Yunmao
Tel: 0598-8266625, 13950951009
Email: swyycy@163.com
177. Marine Biochemical Health-Care Product
I. Content and scale: The development zone covers a land area of 100 mu for
manufacturing marine health-care products, capsules, oral liquids and tablets.
II. Description: The development zone lies in Dongshan Island, an island on the
southern tip of FUJIAN. It is between Xiamen and Shantou special Economic Zones,
and is within easy reach to HK and Macao. Its superb geographical condition and rich
aquatic resources provide sufficient raw materials for the processing of marine
biological health care products.
III. Intended Total investment: 63 Million Yuan;
IV. Progress: The overall planning and selection of site are approved. Companies
will have easy access to water, electricity, communication, gas and land.
V. Project coordinator: Dongshan Economic& Technical Development Zone
VI. Contact: Sun Huosheng Tel: 0596—5885007
178. Zhao’an Jindu Marine Biological Industrial Park
I. Content and scale: The Park covers an area of 18 square kms, and it is the
National Pilot Base of Building a Prosperous Marine Industry in the Guidance of
Science and Technology. The area of focus includes marine biological products,
marine biological pharmaceutical materials, marine biological breeding and healthy
cultivation, marine biological service industry, and marine biological comprehensive
supplementary facilities etc..
II. Description: Zhao’an county is rich in marine biological resources and the
traditional marine industry is prosperous. The Park is on the fringe of Fujian and
Guangdong, and benefits from the scientific research resources from two provinces.
115
III. Intended total project investment:1.5 billion yuan; Means of Cooperation: to
be discussed face to face.
IV. Progress: a total amount of 520 million yuan has been invested on the
infrastructure of the Park since it was set up 3 years ago. The infrastructure facilities
such as power supply, road network, communication, water supply, drainage system,
sewage treatment, etc. fall into place.
V. Project coordinator:
Management Committee
Zhao’an Jindu
Industrial
Concentration Zone
VI. Contact: Zhang Cuiyan
Tel: 13960102280
Email: jinduzsj@163.com
179. Quanzhou Investment Zone of Marine and Biological Technology
I. Content and scale: to foster a large scale marine extracting, separating and
manufacturing of natural compound, to develop sea water comprehensive utilization
pilot zone by applying sea water desalination, sea water circular cooling technology
industrialization, etc, to build the largest biological and new pharmaceutical industrial
base in the province; area of focus include marine drugs and health-care products such
as series polysaccharidies drugs and drugs separated and extracted from alga etc..
II. Description: Quanzhou Investment Zone lies in the eastern suburb of
Quanzhou, and is opposite to downtown Quanzhou across a lake. Quanzhou is trying
to turn it into a new economic growth engine. The area boasts of 25-km coastal line
and has sufficient marine resources. It also has, superior geological advantages and
perfect supplementary facilities for developing high-level marine biological
technology.
III. Intended total project investment: 30 Million USD; Means of Cooperation:
sole proprietorship, joint venture or cooperation;
IV. Preliminary work progress: Complete compilation of planning and
supplementary facilities fall into place;
V. Project coordinator: Technological and Economic Development Bureau of
Quanzhou Taiwan Merchant Investment Zone
VI. Contact: Miss Zhuang, Miss He
Tel:13808529689, 0595-27395529
116
Tel:15159751058, 0595-27308666
180. Wuping County Planting and In-depth Processing of TCM Herbs
I. Content and scale:to plant a 15,000 mu of TCM herbs, including 4,000 mu of
Melaleuca alternifolia, 2,000 mu of radices, 2,000 mu of Anoectochilus roxburghii,
2,000 mu of Platycodon grandiflorum, and 5,000 mu of Chinese yew; processing and
production of TCM herbs.
II. Description: Wuping County lies in central subtropical zone, and the climate,
soil and natural conditions thereof are suitable for growth of various TCM herbs.
Wuping County has made preferential policies to support development of TCMB herb
industry, and provides hilly field for lease, supplies seedlings, market information and
technical service to planters.
III. Intended total project investment: 71.43 Million USD; Means of Cooperation:
Sole proprietorship;
IV. Progress: Feasibility study report has been completed;
V. Project coordinator: Wuping County Forestry Bureau
VI. Contact: Zhong Defa
Tel: 13959077470
181. TCM Herbs Planting and Processing Project
I. Content and scale: Select high-quality herbal varieties to plant a land of 5000
mu with modern technical equipment and processing technology to introduce in-depth
processing of TCM herbs.
II. Description: The climate and soil of Gutian County are suitable for growth of
herbs, and there are many wild herbs with a high quality. The high-quality herbal
varieties have been selected in the project for planting and processing and developing
medicinal resources, thus there is a promising market prospect.
III. Total project investment: Total investment: RMB 100 Million; Means of
cooperation: Sole proprietorship, joint venture and cooperation;
IV. Progress: The preliminary feasibility study report has been completed.
117
V. Project coordinator: Gutian County Agricultural Bureau
VI. Contact: Ye Duanyun
Tel: 0593-3803858
Fax: 0593-3882172
182. Anoectochilus Formosanus Hayata Planting and Developmentin
Anyuan County
I. Content and scale: a 2,000 mu for planting of Anoectochilus Formosanus
Hayat and construct production lines for developing series drinks and health-care
products of Anoectochilus Formosanus Hayat;
II. Description: The geological and climatic conditions of Anyuan Township of
Ninghua County are suitable for growing Anoectochilus Formosanus Hayat, and the
planting techniques has been have matured in recent years, which bring about a
promising planting prospect.
III. Intended total project investment: The estimated total project investment is
156 million yuan, and will be totally foreign capital. Means of cooperation: solely
foreign owned or cooperative
IV. Progress: feasibility study and analysis of the project are completed;
V. Project coordinator: Anyuan Township People’s Government of Ningyuan
County
VI. Contact: Mr. Zeng, Liao Fuping
Tel: 13459890666,0598-6731006
183. Coix Chinensis Planting and In-Depth Processing Project
I. Content and scale:to plant a 5,000 mu of coix chinensis and to build a
processing plant, which will occupy a land area of 100 mu with the total building area
of 47,000 square meters.
II. Description: Coix chinensis has a uniquely excellent ecological adaptability,
and has long been planted in Ninghua. Coix chinensis kernel is a valuable herbal
medicine for both medicinal and edible purposes accredited by State Ministry of
Health.
118
III. Intended total project investment:Total project investment: 1.5 billion
yuan(totally foreign capital); Means of cooperation: sole proprietorship, joint venture.
IV. Progress: Part of the planting bases has been constructed, and feasibility
study report has been compiled.
V. Project coordinator: Ninghua County Agricultural Bureau
VI. Contact: Chen Jiangang
Tel: 0598-6822677
184. In-depth Processing of Radix Pseudostellariae
I. Content and scale: to build a production line of Radix Pseudostellariae that
meets GMP standards with annual output of 5,000 tons to realize output value of 1
billion yuan;
II. Description: Zherong is dubbed “Hometown of Radix Pseudostellariae” in
China , and it has a 26,000 mu of Radix Pseudostellariae, with its yield and sales
volume accounting for over two thirds of those of the whole country. It is the largest
and most active Radix Pseudostellariae production and sales zone in China. The
nutritious and health-care value of Radix Pseudostellariae are attracting attention with
its market share gradually rising with a broad market prospect.
III. Intended total project investment:200 Million yuan; Means of cooperation:
solely foreign owned or joint ventured;
IV. Progress: Zherong has 26,000 mu of Radix Pseudostellariae with its yield and
sales volume accounting for over two thirds of those of the whole country.
V. Project coordinator: Zherong County Economic and Trade Bureau
VI. Contact: Wei Guogan
Tel: 13905038731
Email: zrxjmj@163.com
185. GAP Planting of Officinal magnolia Barkand Extractingof Magnolol in
Mingxi County
I. Content and scale: to build Magnolol(total content≥50%) production line with
annual output of 200 tons with a supplemented 50,000 mu of officinal magnolia
119
Barker base;
II. Description: Farmers in Hufang Town began to plant Officinal magnolia Bark
since the end of the 1970s and acquired mature planting techniques for the industry
and are formed into a certain scale. At present, more farmers than ever before are
willing to plant officinal magnolia bark, which provide sufficient workforce for the
project.
III. Intended total project investment: Total investment: 80 Million Yuan; Means
of Cooperation: solely foreign-owned , joint ventured.
IV. Progress: 30,000 mu of land is planted with magnolia bark. The preliminary
feasibility study report for Magnolol extraction and processing project.
V. Project coordinator: Hufang Township People’s Government, Mingxi County,
Fujian Province
VI. Contact: Xiao Xianqi
Tel: 13850858596
Email: mxfh@163.com
186. Magnolol Abstraction and Preparation Production
I. Content and scale: The project is planned to cover a land of 50 mu to develop
magnolol and magnolol abstraction and preparations production to form
manufacturing capacity of 500 tons annually.
II. Description: Honored with a provincial “mangnolia officinalis bark
production and agricultural standardization pilot zone”, a 4,500-mu of mangnolia
officinalis bark pilot base has been constructed in Guangze county. In addition,
“Agricultural Standard Regulations of Guangze County(mangnolia officinalis variety
NGZ/T001-2010) has been set up and compiled. The planting area of mangnolia
officinalis bark in the whole county will reach at around 100,000 mu by 2015, which
can provide raw materials for sustainable development of biological pharmaceutical
enterprises.
III. Intended total project investment: 50 Million yuan, Means of Cooperation:
Solely foreign owned
IV. Progress: Feasibility study is being carried out;
V. Project coordinator: Guangze County Scientific Technological Bureau
VI. Contact: Lu Fusheng
120
Tel: 0599-8373156
187. Taxane and Taxol Anti-Cancer Drugs Extraction Project
I. Content and scale: To develop a 10,000 mu of Taxus Media cultivation base
and 300-mu seedling breeding base, to build a 500-mu Taxus media recreational
center, to set up a Taxane and Taxol TCM patent prescription R&D production base
and substances supplying base.
II. Description: Qingliu county lies in the west of Fujian Province, and has
tropical monsoon climate of central Asia and is suitable for large-scale planting of
Taxus Media culti. Various parts of Taxus Media contain Taxol, and the content of
Taxol in the branches and leaves exceeds the level of 0.03%, in the root, 0.06%. The
whole plant can be used to extract Taxol with a high utilization rate. The
comprehensive economic value thereof is higher through in-depth processing.
III. Intended total project investment:RMB 100 Million; Means of cooperation:
cooperation or sole proprietorship;
IV. Preliminary work progress: Preliminary feasibility study of the project has
been completed.
V. Project coordinator: Qingliu County Forestry Bureau;
VI. Contact: Liu Rihui
Tel: 13950925569
Email: qlxxmb@163.com
188. Cultivationandextracting of Cephalotaxus and Homoharringtonine
Pharmaceutical
I. Content and scale: to build a 500-mu breeding base of improved varieties of
Cephalotaxus and a 10,000-mu planting base, to build a production line for extracting
of pharmaceutical materials of Homoharringtonine with annual output of 500 tons,
and to produce 500 million formula injection liquid preparations.
II. Description: Qingliu County boasts of abundant and extensive distribution of
wild Cephalotaxus resources, which have not been effectively and comprehensively
developed and utilized. The leaves, branches, seeds and roots, etc. can be used to
extract several alkaloids to cure cancer(mainly for abstracting Homoharringtonine to
cure acute myeloblastic leukemia). Most of the domestic distribution areas of
121
Cephalotaxus have been excessively utilized, which has led to drastic decrease of
resources and endangered such resources.
III. Intended total project investment:RMB 150 Million, including: 50 million
yuan for cultivation base, and 100 million yuan for abstraction of pharmaceutical raw
materials, and a production line for formula injection liquid preparations; Means of
cooperation: sole proprietorship or cooperation;
IV. Progress: Survey of the resources conditions of the whole county and
feasibility study of the project have been completed;
V. Project coordinator: Qingliu County Forestry Bureau
VI. Contact: Liu Rihui
Tel: 13950925569
Email: qlxxmb@163.com
189. Rose Essence Oil Extraction and Processing
I. Content and scale:to build a biological extraction workshop, which introduces
10 sets of imported rose essence oil extraction device and 1 dedicated production line
for rose extract; to guide farmers to plant a 20,000 mu of imported roses.
II. Description: Qingliu County is the largest planting base of cut flowers in
Fujian Province. At present, rose planting takes on vigorous development momentum
there, and can provide sufficient raw material for the project construction.
III. Intended total project investment: RMB 150 Million
IV. Progress: Survey of the resources conditions of the whole county and
feasibility study of the project have been completed;
V. Project coordinator: Qingliu County Forestry Bureau
VI. Contact Person: Liu Rihui
Tel: 13950925569
Email: qlxxmb@163.com
190. In-depth Processing of Cosmetic Camellia Oil
I. Content and scale:to develop in-depth camellia oil cosmetic skin-care products
through utilizing the rich vitamins and unsaturated fatty oil in the camellia oil;
122
Construct two large-scaled industrial production lines with an annual output of 1,000
tons of cosmetic camellia oil;
II. Description: Camellia oil belongs to a high-grade plant health-care oil with
quite high nutritious value and medicinal value. Qingliu enjoys superior natural
conditions, mild and humid climate and fertilized soil, which are suitable for the
growth of tea-oil trees. Moreover, it has a long history of planting tea-oil trees, thus
being entitled “Chinese Hometown of Tea-oil Trees” by Chinese Economic Woods
Association in 2008.
III. Intended total project investment: RMB 80 Million
IV. Progress: The feasibility study report on the project construction has been
completed.
V. Project coordinator: Qingliu County Forestry Bureau
VI. Contact: Liu Rihui
Tel: 13950925569
Email: qlxxmb@163.com
191. Refined Processing of Tea Seed Oil
I. Content and scale: 150,000 mu of tea-oil tree for technical upgrading, to build
tea seed oil production line with an annual output of 5,000 tons;
II. Description: Tea seed oil is a high-quality edible oil with pure color, fragrant
tastes and rich nutrition. It is effective in lowering blood pressure, blood fat and soften
blood vessels etc, and human immunity can be improved through long-term intake of
such oil. In addition, it can be processed into high-grade skin-care cosmetic products.
Thus tea seed oil has many physiological and health-care functions for human body,
and is in compliance with the requirements of modern people such as advocating
nature, striving for health, and improving living quality, thus it is a premium product
in current edible oil.
III. Intended total project investment: 150 Million yuan; Means of cooperation:
joint venture or sole proprietorship;
IV. Progress: At present, there are over 300,000 mu of tea-oil trees with an
annual output of 1,600 tons of tea oil. The total output value of tea-oil trees broke
through 100 billion yuan, with the planting area and yield ranking the first in the
whole province.
123
V. Project coordinator: Shangbaishi Town Government of Fu’an City
VI. Contact: Lin Qingyun
Tel: 0593-6698001, 13950563536
192. Sanming Biological Active Substances Extraction and Industrial
Development with Bamboo Resources
I. Content and scale: To build a comprehensive processing production line for
biological active substances such as flavone, polysaccharide and xylitol etc. from
bamboo leaves and bamboo shaving residuals, which will produce1,000 tons of
flavone abstract from bamboo leaves, 100 tons of polysaccharide from bamboo leaves
and 2,000 tons of xylitol from bamboo materials annually. Sanming is an important
forestry zone in south China, and current it has over 4 million mu of bamboos with
380 million pieces of bamboos. It produces 80 million pieces of bamboos annually,
and there are many bamboo processing enterprises in the area.
II. Description: There are rich natural health-care elements and nutritious
substances in the bamboo leaves, which are natural treasury for developing green
foods, health-care products and drugs.
III. Total project investment: The total investment is 3 million yuan, which is
partly or wholly investment funds invited from outside the area. Means of cooperation:
Solely foreign owned and joint ventured.
IV. Progress: The feasibility study report on the project construction has been
completed.
V. Project coordinatore: Sanming Forestry Bureau
VI. Contact :Huang Shangcai
Tel: 0598-8288036, 13178078839
193. Green Foods and Biopharmaceutical Developmentin Jianning County
I. Content and scale: to build 5 agricultural products production lines with an
annual output of 20,000 tons, which include a production line of functional
polysaccharide Jian lotus seeds nutrition powder with annually output of 5500tons, a
production line of in-depth of liensinine(pharmaceutical raw materials) with an annual
output of 1,000 tons, a production line of oil tea camellia with annual output of 3,000
124
tons, a production line of lotus root processing line with an annul output of 10,000
tons, a production line for extracting flavone from lotus leaves with an annul output of
500 tons.
II. Description: Jianning has a tropical oceanic monsoon climate of central Asia
with appropriate ecological environment, and is extremely suitable for growth of
green crops. The desirable ecological environment, high-quality water resources and
agriculture with distinct features make it an ideal place to develop processing of Jian
lotus, bamboo shoots products, fruits, vegetables, oil tea and water resources etc..
III. Intended total project investment: Total investment is 250 million
yuan(totally foreign capital); Means of cooperation: sole proprietorship;
IV. Progress: Compilation of feasibility study report of the project has been
completed.
V. Project coordinator: Fujian Jianning Economic Development Zone
Management Committee
VI. Contact: Su Jiansheng
Tel: 0598-8721331, 13950929317
194. Manufacturing of Soapberry Biological Diesel Products with Annual
Output of 100,000 Tons
I. Content and scale: to build a biological diesel production line with
soapberry(Annual output: 100,000 Tons)
II. Description: Shunchang county boasts of rich forest land and forest resources.
And cultivation techniques have been developed there. It is renowned “hometown of
Chinese bamboo ” and “ hometown of Chinese fir”. The 30,000-mu pilot base for
cultivating of soapberry as tree species for biological energy is being constructed. At
present, 4,000-mu pilot soapberry model base, and 9-km highway afforestation for
soapberry base have been finished.
III.Intended total project investment: 150 Million yuan;
IV. Progress: Development and utilization research of soapberry biomass energy
has been carried out for years. Shunchang County has been determined to be a model
county for soapberry biomass industrial development, and the construction project of
30,000-mu model cultivation base for soapberry as tree species for biomass energy
will be completed soon.
125
V. Project coordinator: Shunchang County Forestry Bureau
VI. Contact : Zhou Shaoping
Tel: 13509530568
195. Biopharmaceutical Manufacturing Project
I. Content and scale: to build a production line of injection Thymosin with
annual output of 20 million pieces, a production line for Monocomponent Insulin with
annual output of 5 million bottles(pieces), a production line for hemin pharmaceutical
raw materials with an annual output of 6,000 kgs and a production line for hemin
chewable tablets with annual output of 500 million tablets, a production line of
paclitaxel with an annual output of 5 million boxes, to build 20,000-mu Chinese yew
base.
II. Description: Develop and product several kinds of highly active biochemical
rugs and reagents from the internal organs of pigs and rare plants such as Chinese yew
etc; For example, produce oral preparations such as injection Thymosin, insulin,
Heparin sodium and taxinol oral preparations etc.. Longyan boasts of abundant animal
raw materials, which is beneifical to great development of biopharmaceutical industry.
The agricultural fields and hilly land in the marginal zones in core area of Longyan
Shangkeng Meihuashan Natural Reserve and Wuping State Natural Researve are
suitable for artificial planting of plants such as Chinese yew. Moreover, the techniques
for factory-based seedling cultivation for plants such as Chinese yew etc. and
high-yield raw material woods have matured, which can guarantee supply of raw
materials such as Chinese yew etc..
III. Intended total project investment: 73.49 Million USD; Means of cooperation:
sole proprietorship and cooperation;
IV. Progress: Project proposal has been completed;
V. Project coordinator: Fujian Senbao Food Group Co., Ltd., Longyan Key
Project Office
VI. Contact: Lai Youhui
Tel: 0597-2316710, 0597-2316729
126
196. Land Levelling Project of Xinling Biopharmaceutical Industrial Park
I. Content and scale: The total planned land area is 5,000 mu, and the investor is
required to adopt BT mode to level land in accordance with the design.
II. Description: The northern areas of Fujian province enjoy superior geological
advantages, and are suitable for planting herbal plants. In the park, there is Mt. Wuyi
snake scientific training base, pilot base of Jianyang vegetable herbs, Houttuyniae,
yam, Jianou Alisma orientale, Jian lotus, Songxi Magnolia etc., and model improved
varieties breeding base of Chinese yew, yam, kudzu vine root and Tripterygium
Wilfordii. The regular planting area of the TCM herbs exceeds that of 100,000 mu,
and can provide various and rick herbal resources for the enterprises in the park.
III. Intended total project investment: RMB 750 Million yuan
IV. Progress: Land requisition has been basically completed.
V. Project coordinator: Investment Bureau of Nanping Wuyi New Area
Management Committee
VI. Contact: Fang Dongjie
Tel: 0599-5671266
127
Services
197. Songxia Food Logistics Park in Changle City
I. Project description: it is planned to build a comprehensive industrial park of
food processing.
II. Construction reasons and conditions: Songxia Harbor District is one of four
harbor districts of Fuzhou Port, an important junction of the project “sending grain
from the north to the south” determined by the Ministry of Transport of the People’s
Republic of China, the processing, collecting and distribution center of grain and oil
in the southeast coastal area and an port for international grain import/export as well
as the port with direct voyage route to Taiwan. Therefore, it is quite necessary to build
a comprehensive industrial park of grain processing.
III. Total investment: RMB 1 billion.
IV. Preliminary work: overall planning has been completed.
V. Project organizer: Songxia Town Government of Changle
VI. Contact person: Chen Xiaoyin
Tel: 13805051225
Fax: 0591-28763002
198. Fuzhou Large-Scale Logistics Trading Center
I. Project description: 200mu land in the southwest of Langqi Island of Fuzhou is
proposed to be requisitioned. It is planned to build a large-scale comprehensive
commercial logistics trading center integrating five major trading centers including
textile & garment, leather ware, electronics, hardware& chemical and plastic product
and steel & building materials and providing the services of exhibition, storage,
distribution and the like.
II. Construction reasons and conditions: convenient transportation of Langqi
Island is to be developed in near future. Fuzhou Loop Expressway under planning
makes Langqi Island a part of the rapid transit network. Langqi Island is merely 5
minutes’ drive from Shenyang-Haikou Expressway, thus Langqi Island is an ideal
place for building a large-scale logistics trading center. Furthermore, no similar
project has been built in Fujian Province. The Project can not only radiate the whole
128
province but also connect Taiwan and the area on the west coast of Taiwan Straits
such as the south area of Zhejiang and the east area of Guangdong.
III. Total investment: USD 200 million
IV. Analysis of economic benefits: the annual rate of return is planned to be 13%
and the payback period is estimated to be 8 years.
V. Preliminary work: functional planning has been completed.
VI. Project organizer: Administrative Committee of Langqi Economic Zone of
Fuzhou
VII. Contact person: Jiang Xu
Tel: 0591-83909863,13075966993
Fax: 0591-83602018 E-mail: j3x001@163.com
199. Huangshi Commercial Logistics Park in Putian
I. Project description: the Project is planned to cover an area of 11,000mu. It is
proposed to build an arts and handicrafts town, a shoes & garment town, a Straits
International Trade Town, a 4s motor town, a building materials & home furnishing
town, a distribution center of SINOPHARM Group and Zhongmin Medicine Trade
Co., Ltd., a comprehensive logistics center, a commercial office cluster, a theme
commercial area and the like.
II. Construction reasons and conditions: the Project enjoying favorable
geographic location is planned to be built into a modern commercial logistics park
mainly integrating commercial exhibition and selling and logistics & distribution,
equipped with residence and public service. The Project will build distinct functional
zones and complete supporting public utilities in a beautiful and convenient living
environment.
III. Total investment: RMB 10 billion. Cooperation mode: exclusive investment,
joint venture or cooperation.
IV. Analysis of economic benefits: after the Project is put into production, the
annual trading volume will reach RMB 100 billion.
V. Preliminary work: within the Park, China Putian Arts and Handicrafts Town
and the shoes & garment town have formally started to operate; the Straits
International Trade Town is under construction; the auto park, building materials &
129
home furnishing town, the logistics center of Luyan Pharmaceutical, the storage &
logistics center of SINOPHARM Group and Zhongmin Medicine Trade Co., Ltd., Jin
Jiang Hotel and the like are to be constructed. Besides, ancillary facilities such as
roads are gradually being improved.
VI. Project organizer: Licheng District Service Center for Investment Projects
VII. Contact person: Huang Meifang
Tel: 0594-2388110, 13950745658
Fax: 0594-2336359 Email: Lctz2388110@163.com
200. Putian Marine Products Refrigeration and Cold Chain Logistics
I. Project description: it is planned to build a collective transaction center and
cold chain logistics base for marine products like abalone, kelp, etc.
II. Construction reasons and conditions: Xiuyu District has rich marine resources
with the total costal cultivating area of 54,283.96 hectares producing marine products
like fish, shrimp, crab, kelp, etc. To promote the healthy and long-term development
of marine product market in Xiuyu District, it is urgent to build a marine products
refrigeration and cold chain logistics project in Xiuyu District. And it is planed to
adopt the LNG cold energy construction and cold chain logistics base.
III. Total investment: RMB 200 million. Cooperation mode: joint venture,
cooperation or exclusive investment.
IV. Preliminary work: initial design has been completed.
V. Project organizer: Xiuyu District Service Center for Investment Projects
(Investment Promotion Bureau)
VI. Contact person: Huang Xiaozhi
Tel: 0594-5857733
Fax: 0594-5870135
Email: 5857733@163.com
201. Tianbao Commerce Park in Zhangzhou
I. Project description: with an overall planned area of 6,000mu, of which 1,500
130
for Phase I, the project plans to introduce professional market of trade and logistics or
construct the urban commercial complex.
II. Construction reasons and conditions: the Commerce Park adjoins western
intersection of Zhangzhou-Longhai Expressway and Xiangcheng interaction of
Fuzhou-Guangzhou Expressway, with No.319 National Road passing through it. It is
13km, and 70km away from downtown area of Zhangzhou and Xiamen respectively
and 55km away from Zhangzhou Port. Therefore, it boasts superior geographic
location and convenient transportation.
III. Total investment: RMB 3 billion. Cooperation mode: exclusive investment.
IV. Analysis of economic benefits: it is expected that the annual tax revenue will
reach RMB 100 million.
V. Preliminary work: regulatory plan has been completed.
VI. Project organizer: People’s Government of Tianbao Town
VII. Contact person: Cai Qinglong
Tel: 0596-2542277, 13806931964
202. Quanzhou Strait Luggage Logistics Mall
I. Project description: in the first phase, the project covers an area of 137mu, and
the total construction area is 220,000m2, in which, the stores cover 105,000m2,
markets 21,000m2, underground malls 58,000m2 and hotel-style apartments 36,000m2.
II. Construction reasons and conditions: currently, Quanzhou has more than
1,000 luggage manufactures with an annual output value of over 10 billion, being the
main production base of the whole province, even for the entire country. Once
completion, the modern Quanzhou Strait Luggage Logistic Mall will become the
biggest wholesale mall for raw and auxiliary materials of luggage in southeast of
China.
III. Total investment: RMB 1.2 billion. Cooperation mode: using rents or sales to
introduce related cooperates to run business such as wholesales of raw and auxiliary
materials for luggage, finished products exhibition, research and training and the like
in the mall.
IV. Analysis on expected economic benefits: it is estimated that more than 3,000
businesses come from the whole country (including Taiwan) will be introduced upon
131
completion of the project.
V. Preliminary work: the procedures such as project identification, planning
scheme, environmental impact assessment and the like have been submitted and
approved, and the land using in first phase has conducted “bidding, auction and
listing” after resettlement. The pile foundation construction is carried out now.
VI. Project organizer: Quanzhou Strait Luggage Logistic Mall Co., Ltd.
VII. Contact person: Du Xuhui
Tel: 0595-22508529, 13358585805
203. Construction Project of Ninghua County Modern Logistics Center
between Fujian and Jiangxi
I. Project description: covering an area of 1,000mu and total construction area of
500,000m2, it is planned to build seven functional areas with the annual cargo handing
capacity of 12 million tons, which includes integrated office, information center,
storage area, intermodal transportation area, processing and distribution area, vehicle
maintenance service area, supporting service area.
II. Construction reasons and conditions: among the six counties along the borders
between Fujian and Jiangxi, Ninghua County, which is located in the middle of the
this border, has the widest area and the largest populations, so it becomes the
intersection point of the economic zones between the west of Fujian and south of
Jiangxi, and becomes one of the important material distribution center. Along with the
shaping of the completed frame system of Ninghua transport network, it is necessary
to build a modern logistic center in Ninghua County, which shows a good market
prospects.
III. Total investment: RMB 1 billion.
IV. Analysis on expected economic benefits: the annual revenue will be RMB 1.3
billion, the profit will be RMB 120 million and the investment will be recovered in
8.3 years after the Project being completed and putting into operation.
V. Preliminary work: the feasibility report has been compiled.
VI. Project organizer: Economic and Trade Bureau of Ninghua County
VII. Contact person: Zhang Fahua
Tel: 0598-6824651, 13507552016
132
204. Gui’an Central Hot Spring Tourism Project in Lianjiang County
I. Project description: the Project covers an area of 5,000mu (1mu≈666.67m2). It
is planned to build a hot spring center, a physical therapy center, a high-end
conference center, a specialty restaurant, a hot spring villa, an outdoor recreation
ground and other functional areas.
II. Construction reasons and conditions: the area where the Project is located is
endowed with convenient transportation and rich high-quality hot spring resource
with reasonable daily exploitation amount of 6,700t. In the area, ecology is well
protected. In addition, Aojiang River, the sixth largest river of Fujian Province, is the
artery of the water system in the tourist area. Within the river basin, environment is
well protected with high-quality water. Furthermore, the area is rich in diversified
animals and plants and the forestation rate reaches 85%.
III. Total investment: RMB 7 billion. Cooperation mode: exclusive investment or
joint venture..
IV. Analysis of economic benefits: according to Overall Planning of Gui’an Hot
Spring Tourist Area, daily tourist number of Gui’an tourist area will be 1,800 in 2015,
4,000 in 2020 and 7,400 in 2030.
V. Preliminary work: at present, overall planning of the area has been completed
and regulatory plan is now being made. Besides, infrastructures such as water/power
supply, flood control and road have been preliminarily completed.
VI. Project organizer: Administrative Committee of Gui’an Hot Spring Tourist
Area of Lianjiang County
VII. Contact person: Zheng Defeng
Tel: 13850181210
205. Tourism Resource Development Project of Xianyou County
I. Project description: it is planned to build a place for dream praying ceremony
as Xianyou is named as “China Dream Town”. Meanwhile, it is also proposed to
develop Caixiyan Scenic Spot, Xianshuiyang Tourism Region, Tianmashan Scenic
Spot and Xianyou Jinzhong Hot Spring Tourism Region and construct Maixieyan
Sports & Leisure Park and Linan Hot Spring Business & Leisure Village.
133
II. Construction reasons and conditions: Xianyou possesses rich tourism
resources and has four major scenic spots including Jiuli Lake, Maixieyan Scenic
Spot, Caixiyan Scenic Spot and Tianma Mountain, thus being of outstanding
development advantages and great development potential. It will build up the tourism
brand of “Fantasy Xianyou, Dream Town on the west bank of Taiwan Straits”, create
the tourism development pattern of “Mazu on the sea and Nine Immortals on the
mountain” based on the three major resources, namely ecology, hot spring and culture,
to develop itself into an outstanding tourism county of China.
III. Total investment: RMB 1,825 million. Cooperation mode: cooperation, joint
venture or exclusive investment. Separate investment in single engineering is also
allowed.
IV. Preliminary work: planning and site selection has been completed.
V. Project organizer: Investment Invitation Bureau of Xianyou County
VI. Contact person: Zhu Weicai
Tel: 18760528263
Fax: 0594-8261234
Email:fjxytz@163.com
206. Development Project of Heping Ancient Town Scenic Area in Shaowu
City
I. Project description: including restoration of watchtower in east and north gates,
Heping Academy and Government Office of County Magistrate Assistant, facade
repair of Heping Street and Dongmen Street, construction of Beimen Service Center,
etc.; further planning projects such as removal, construction and façade repair of
Nanmen Tourism Service Center; development of 16 major attractions in Heping
Town; construction of a 500mu international resort integrating leisure, vacation and
shopping 1km away from Heping expressway intersection.
II. Construction reasons and conditions: established over 4,000 years ago,
Heping Ancient Town in Shaowu City is considered as the most well-preserved and
unique ancient residential buildings discovered so far in China with unique tourism
resource for development. Moreover, as the birthland of 42 million Chinese in the
world whose first name is Huang, it possesses rich cultural tourism resources. As a
result, the market prospects for the project are bright.
III. Total investment: RMB 217 million.
134
IV. Analysis of economic benefits: the annual sales revenue will be RMB 110
million, the profit will be RMB 33 million and in the payback period will be 7 years
upon completion of the Project.
V.Preliminary work: Protection and Renovation Plan for Heping Ancient Town
has been drawn up by Ruan Yishan, the director of National Research Center of
Historic City and the professor of Tongji University, and feasibility study and
environmental evaluation report of the project has been prepared. In addition, other
preliminary works like land acquisition, housing survey, house removal and takeover
of key ancient buildings have been completed.
VI. Project organizer: Tourism Bureau of Shaowu City
VII. Contact person: Zhang jinhua
Tel: 13706013018
207. Bar Corridor Project in Wuyi Mountain
I. Project description: build a commercial block which will be an integrated place
merging Chinese and Western cultures for relaxation and entertainment, including
music bar, business bar, teahouse and café.
II. Construction reasons and conditions: tourism in Wuyi Mountain, which is an
international tourist resort, is developing rapidly. In 2011, the whole City received
7.11 million person-times of tourist and the annual sale income reached RMB 12.26
billion, which ranked first in national 5A-class scenic area. However, the lack of large
western restaurant, night club and bar makes it hard to meet the rising demand of
high-grade consumption of tourists.
III. Total investment: RMB 600 million. Cooperation mode: exclusive
investment or joint venture.
IV. Analysis of economic benefits: it is estimated that the sale revenue will be
RMB 420 million and the payback period will be 5 years upon completion of the
Project.
V. Preliminary work: site selection of the project has been completed.
VI. Project organizer: Project Office of Wuyishan City
VII. Contact person: Hu Bijiang
Tel: 0599-5302117, 13905994766
135
Fax: 0599-5317866
E-mail: 5134xmb@163.com
208. Development Project of Zhuzi Garden in Wuyi Mountain
I. Project description: the Project is planned to cover an area of 207,000mu,
including functional areas like Zhuzi cultural cooperation center, Fujian and Taiwan
tea culture cooperation center, demonstration base of lotus industry on the west bank
of Taiwan Straits, Ailian Island resort, sports and health center, and comprehensive
management service center.
II. Construction reasons and conditions: with numerous historical sites and
profound cultural heritage, Wufu Town has always enjoyed a reputation for its
flourishing culture. Zhu Xi, the master of Neo-Confucianism, who spent more than 40
years here on study, writing and education, has influenced a lot in the history and
culture of Wufu Town. It’s a famous historical and cultural town in China as well as
an important part of world cultural heritage of Wuyishan city..
III. Total investment: RMB 1 billion. Cooperation mode: exclusive investment or
joint venture.
IV. Analysis of economic benefits: it is estimated that the sale revenue will reach
RMB 380 million and the payback period will be 6 years upon completion of the
project.
V. Preliminary work: conceptual planning of the Project has been completed.
VI. Project organizer: People's Government of Wufu Town, Wuyishan City
VII. Contact person: Zhou Jianping
Tel: 0599-5406168, 13706010646
209. Comprehensive Coastal Tourism Development Project in Dongshan
County
I. Project description: it is planned to develop 5 to 8 high-star hotels along the
coastal line of the Dongshan Island with waters in the front and a hill at the back
according to its local conditions. The hotels share a total planned area of 2,000 mu
with total building area of 180,000m2 and accommodate 2,500 rooms. In addition, a
series of ancillary facilities is about to be built: coastal vocation corridors (including
landscape parks and business facilities), coastal roads for tourism, training bases of
136
sailing activities, marine tourism lines (piers and onshore facilities), yacht piers, yacht
clubs and so on.
II. Construction reasons and conditions: the Project will hugely enhance the
tourist reception capacity of Dongshan, contribute to the upgrading of tourism
industry structure, lift the tourism brand and favor the construction of coastal leisure
and tourism zones of Fujian Province.
III. Total investment: RMB 11.8 billion. Cooperation mode: BT or BOT.
IV. Preliminary work: at present, manors are in their existence, the Maryland
Hotel is being built and also the foundation of Haijing and Honji Hotels has been laid.
V. Project organizer: Construction Headquarters of Dongshan Star Hotel Project
VI. Contact person: Lin Xilu
Tel: 13806908376
210. Sandu'ao Coastal Tourism Development Project
I. Project description: it is planned to construct Jiaotou Tourist Service Center
and Central Pier, Sandu Island Ancient Relics Scenic Spot, Doumu Island Scenic Spot,
Qingshan Island Tourist Resort; Jigongshan Island Scenic Spot, Ganlan Island Scenic,
seafood fishing city, real estates of coastal landscape, luxurious marine cruises,
marine fishing recreation areas, Qingshan Island Holiday Resort, Ganlan Island Yacht
Club, Jigongshan Island Mariners' Club and the like.
II. Construction reasons and conditions: Sandu’ao, the only “Marine Lake” in
China, possesses beautiful seascape, unique landscape of marine abrasion, mysterious
military harbor feelings and long history of opening, forming its richly exquisite
resources of touring, recreation and vocational tourism. And with the gradual advance
of touristic traffic lines in the eastern part of Fujian and the lifted touristic reputation ,
the tourist development conditions of Sandu’ao are getting mature.
III. Total investment: RMB 2.2 billion. Cooperation mode: exclusive investment
or cooperation.
IV. Analysis of economic benefits: upon its completion, the annual tourist
reception will be about 300,000 person-times, the income of each item will be more
than RMB 300 million and the payback period will proximately be eight years.
V. Preliminary work: Tourism Development Plan of Jiaocheng District and
137
Regulatory Plan of Concept of Tourism Scenic Plots of Jiaocheng District.
VI. Project organizer: Tourism Bureau of Jiaocheng District
VII. Contact person: Gong Qingtuan
Tel: 0593-2826122, 13950596066
211. Tianxing Mountain National Forest Park in Pingnan County-Tourism
Development Project of Longjing Bridge Scenic Spot
I. Project description: it is planned to expand the tourist highway 20km longer
and construct service facilities such as a tour trail with 32km, pavilions, terraces,
buildings, pavilions, public toilets, tourism villas and the like.
II. Construction reasons and conditions: with an area of 1,152 Hectare, Longjing
Bridge Science Spot covers more than 50 natural landscapes such as Tianxing
Mountain, Liancui Ridge, Pinus Taiwanensis Forest, Daxian Rock, Huoshao River
and the like, forming a beautiful scenic picture with unique mountain, river, forest and
spring landscapes enhancing each other’s beauty.
III. Total investment: RMB 303.48 million. Cooperation mode: joint
development.
IV. Analysis of economic benefits: the annual business income of the project
under normal operation is estimated to be RMB 66,084,400, and the annual profits
will be RMB 22,198,400 (after income tax).
V. Preliminary work: State Forestry Bureau has approved to build the Tianxing
Mountain National Forest Park; the preparation of General Plan of National Forest
Park has been complied, the approval and detailed plan of which is underway; and
other works are being arranged.
VI. Project organizer: Fujian Dachang Hydropower Group Co., Ltd.
VII. Contact person: Lin Wei
Tel: 0593-3322468, 13959339933
138
212. Comprehensive Development Project of Minhu Lake Scenic Spot in
Youxi County
I. Project description: the science spot consists of a dynamic zone and a static
zone as classified by resource characteristics and conditions: the former is composed
of a national training base for white-water kayaking and kayaking, and a recreation
and tourism zones for public; while the later is a high-end area for conference, leisure
and health promotion.
II. Construction reasons and conditions: National Water Conservancy Scenic
Spot of Minhu Lake in Youxi County is located in the area of Jiemian Hydropower
Station whose reservoir area is 36.7 square kilometer and the maximum width of the
reservoir is 2.5 km, being the biggest artificial lake of Youxi County. Besides, the
scenic spot is located in the heartland of Fujian Province, so it has obvious
geographical advantage to reach each area of Fujian.
III. Total investment: RMB 1.07 billion. Cooperation mode: exclusive
investment or joint venture.
IV. Analysis of economic benefits: after construction, if the annual tourists are
400,000, the annual revenues will be RMB 245.20 million and the net profit (after
income tax) will be RMB 112.03 million, which means the profit rate of investment
will be 10.47% and the payback period will be 9.6 years.
V. Preliminary work: the general plan of science spot has been complied, and
some works such as road constructions of some tourist attractions in Minhu Lake,
Minhu Lake Tablet, and infrastructure constructions of Minxin Park have been
finished. Besides, the purchase of water tourism facilities, the initial constructions of
some water leisure and tourism projects and water entertainment districts, and some
constructions of integrated service area of Minhu Lake have been finished.
VI. Project organizer: Tourism Bureau of Youxi County
VII. Contact person: Zhang Qijing
Tel: 13067003689
213.Huangchao Ecological Leisure & Tourism Resort in Nanan City
I. Project description: the Project plans to build and develop a Huangchao
tourism scenic spot, a sports park and a tourism holiday villa with an area of
168,000m2.
139
II. Construction reasons and conditions: the Project aims at promoting the
tourism industry development of Nanan City by further making full play of the
location advantage of Dongtian Town adjacent to Xiamen and rich mountainous
natural biological landscapes and rich humanistic historical cultural resources.
III. Total investment: RMB 900 million. Cooperation mode: joint development.
IV. Project organizer: Nanan Development and Reform Commission
V. Contact person: Li Changqing
Tel: 13959865858
214. Creative Industries Center of Cross-strait Marine Culture in Meizhou
Island, Putian
I. Project description: the Project covers an area of 2,900mu, including 1,000mu
reclaim land. The Project plans to build cross-strait artistic creation base, Mazu belief
museum, music making workshop, Mazu cultural museum park, cross-strait marine
hairdressing and health preservation hall, international cruise terminal, yacht club,
finishing household folk tour, sea fishing center, island botanic gardens, Meizhou
island impression art center, etc.
II. Construction reasons and conditions: Meizhou Island is a national tourism
resort, the birth land of Mazu culture and the world intangible cultural heritage site of
Mazu belief, attracting more than 1.5 million tourists every year. The Creative
Industries Center of Cross-strait Marine Culture aims at inheriting and promoting the
Mazu culture by communication and service and building up the world Mazu culture
center. At the same time, cultural and recreational tourism projects are assorted to rich
the tourism products of Meizhou Island and promote its tourism development.
III. Total investment: RMB 2.3 billion. Cooperation mode: cooperation, joint
venture or exclusive investment. Separate investment in single engineering is also
allowed.
IV. Preliminary work: planning and site selection have been completed.
V. Project organizer: Meizhou Island Administrative Commission
VI. Contact person: Zheng Wengui
Tel: 0594-5094335
Fax: 0594-5092031
140
Email:zlfpt@126.com
215. Taxus Chinensis Cultural Creative Industrial Park Project in Mingxi
County, China
I. Project description: covering a building area of 54,600m2, the Project plans to
build a historical museum, a library, a theater, a cultural activation center and other
cultural facilities.
II. Construction reasons and conditions: Mingxi County is the only “Taxus
Chinensis Town in China”. It has built up near 50,000 mu taxus chinensis bases and
achieved near RMB 1 billion output value in 2011. The Project aims at building up a
Taxus Chinensis Cultural Creative Industrial Park at the north of the Yingbin Road to
further display the taxus chinensis cultural results and turn Mingxi County into a
collecting and distributing center of serial products of taxus chinensis industry inside
and beyond Fujian Province.
III. Total investment: RMB 500 million.
IV. Analysis of economic benefits: upon completion and operation, the Project
will achieve an annual rate of return of 18% and the pay back period (static) will be
5-6 years.
V. Preliminary work: the pre-project planning has been completed with
30,000mu taxus chinensis var mairel bases built up and 1 million bonsais planted.
VI. Project organizer: Forestry Bureau of Mingxi County
VII. Contact person: Lin Baoyun
Tel: 13605969191
216. Longyan Central Soviet Areas Park Construction Project
I. Project description: covering an area of 1,308 hectares, the Project takes the
central soviet areas spirit as connotation and the red culture as the mainline,
composites red culture, Hakka culture and folk culture, and builds up a
comprehensive cultural park integrating ecotourism, mountain leisure and cultural
experience as a whole.
II. Construction reasons and conditions: by modeling the central soviet areas
theme culture and implanting of leisure industrial economy, the Project aims at
building up a comprehensive park representing urban humanistic spirit, beautiful
ecological environment and good economic format to comprehensively promote the
urban cultural image, perfect the urban function and promote the urban industrial and
141
economic development.
III. Total investment: RMB 800 million.
IV. Project organizer: Longyan Municipal Development Group Co., Ltd.
V. Contact person: Lin Jie
Tel: 0597-2991219, 18906070105
217. Third Affiliated Hospital of Fujian Medical University
I. Project description: the hospital is planned to cover an area of 276mu with
total building area of 240,000m2, providing 2,000 beds. In addition, it is planned to
build a comprehensive outpatient, emergency & medical technology building with
supporting facilities, ward building, comprehensive administration building, logistics
system and rehabilitation center. The departments will be set in accordance with the
fundamental requirements for AAA hospitals.
II. Construction reasons and conditions: the Project can improve medical
treatment and provide health care service and has received the vigorous support from
Wu Mengchao, an academician who is the founder of liver surgery in China and has
won the national top science and technology award. Meanwhile, Fujian Provincial
Department of Finance and Fujian Provincial Department of Health have issued a
joint document to nominate the Project as a provincial medical reform pilot hospital.
It is planned to develop a mode inheriting the public non-commercial nature while
absorbing social capital in building of public hospital.
III. Total investment: RMB 2,172 million.
IV. Analysis of economic benefits: annual outpatient service is planned to be 800
thousand - 1 million person-time, annual patient number of hospitalization
40,000-50,000 person-time and annual surgical volume 30,000 person-time.
V. Preliminary work: the Project (the first-phase engineering) is listed as a
provincial key construction project. The foundation was laid in May 2011. At present,
the first-phase engineering is under construction. The Proposal of second-phase
engineering has been approved by Fujian Development and Reform Commission and
the feasibility study report has been submitted for approval.
VI. Project organizer: Fujian Medical University
VII. Contact person: Xu Xiaoqing
142
Tel: 13959115313
Fax: 0591-22862286
Email:fsyy@mail.fjmu.edu.cn
218. General Hospital in Gaokan New Town, Yongding County
I. Project description: the Project plans to build up a balanced and fully
developed general hospital in all strengths by building a general ward building,
outpatient service building, medical laboratory & office building and introducing
excellent medical scientific talents and advanced equipment with 400 designed
sickbeds and 5 ambulances.
II. Total investment: RMB 80 million. Cooperation mode: exclusive investment
or joint venture.
III. Preliminary work: planning and site selection have been completed.
IV. Project organizer: Urban Construction & Development Co., Ltd. in Gaopo
Town, Yongding County
V. Contact person: Chen Shenghu
Tel: 13906976110
219. Second-Phase Real Estate Project in Mazu Town, Putian City
I. Project description: it is planned to develop a project covering 1,500mu for
commercial residence, office, club, hotel and public facilities with building area of
2,000,000m2 based on the land reclamation around the sea in the first-phase
engineering of Mazu Town (core area of Mazu Town).
II. Construction reasons and conditions: the development of Mazu Town is of
great significance for promoting Mazu Culture, creating communication center with
Taiwan and improving the communication and cooperation between Fujian and
Taiwan. Meanwhile, Mazu Town is characterized by “Mazu” culture and “aquatic
town”, thus it will certainly be developed into a bright pearl on the west coast of
Taiwan Straits.
III. Total investment: RMB 5 billion. Cooperation mode: exclusive investment or
joint venture..
IV. Analysis of economic benefits: upon the advantage of hometown of Mazu,
143
Mazu Temple on the Meizhou Island can attract over 2 million person-times for
pilgrimage, sightseeing and tourism every year.
V. Project organizer: Department Bureau of North Bank Economic Development
Zone
VI. Contact person: Guo Qingxing
Tel: 13905043008
Fax: 0594-5952956
Email: ba5952968@163.com
220. Longyan Exhibition City
I. Project description: the planned area of the Project is 900 mu, including 380mu
for the first-phase engineering with total building area of 213,000m2, and 520mu for
the second-phase engineering.
II. Construction reasons and conditions: Longyan Exhibition City is a key project
of Longyan City. It is of great significance for improving the level of the Cross-Straits
Machinery Industry Expo, increasing the grade of the center of Longyan, developing
modern service of Longyan and fostering new areas of economic growth.
III. Total investment: RMB 1.3 billion. Cooperation mode: BT or cooperation.
IV. Preliminary work: woodland vetting procedures of Fujian Forest Department
and the land approval procedures of Fujian Provincial Government have been handled
for the planned first-phase land of the exhibition city. The Project designer has been
selected and the design plan is now being improved. Meanwhile, site leveling and bid
inviting for supervisory unit have been completed.
V. Project organizer: Longyan Exhibition Co., Ltd.
VI. Contact person: Ou Wenlong
Tel: 13906070892
221. Auto Parts Industrial Park in Changting County
I. Project description: the planned area of the Project is 5,000mu. Main products
include: axle, gear box, interior trim parts of auto, auto mould, auto diverter, auto
lighting, auto instrument and the like. It is proposed to be developed into a production
base for domestic and overseas market of complete vehicle accessories and auto parts.
144
II. Construction reasons and conditions: at present, there are more than 100
enterprises producing special vehicles, cargo truck and light/heavy truck in Fujian.
Due to immature industrial chain, most accessories are imported from other areas.
Therefore, the auto accessories manufacture park has promising prospect.
III. Total investment: RMB 600 million. Cooperation mode: cooperation.
IV. Analysis of economic benefits: the annual output value will be RMB 1.8
billion and the profit will be RMB 180 million.
V. Preliminary work: the planning and design have been completed.
VI. Project organizer: Changting Bureau of Machinery and Electronics Industry
VII. Contact person: Lai Honglu
Tel: 13806995192
222. Building Material Market of Industry and Trade Zone on the West
Bank of Taiwan Straits,Wuyi Mountain
I. Project description: the Project is planned to cover an area of 130mu with total
building area of 90,000m2. It consists of building slab market, steel market, hardware
market, ceramics market and the like.
II. Construction reasons and conditions: Wuyi New District has convenient
transportation and outstanding location advantages. Meanwhile, seven connections
and one leveling have been completed in the forest product industry and trade zone on
the west bank of Taiwan Straits. Thus, the Project site enjoys smooth information
transmission and optimized resources. A product supply chain integrating business
flow, information flow, cash flow and material flow can be built up.
III. Total investment: RMB 260 million.
IV. Analysis of economic benefits: the annual sales revenue will be RMB 1.6
billion, the annual profits will be RMB 50 million and payback period will be 8 years
upon completion of the Project.
V. Preliminary work: bidding, auction and listing of the land have been carried
out.
VI. Project organizer: Project Department of Forest Product Industry and Trade
Zone on West Bank of Taiwan Straits
145
VII. Contact person: Wu Fajian
Tel: 18960698969
Fax: 0599-8259910
Email:mblcyq@163.com
223. Construction Project of Sanming Old-age Nursing Center
I. Project description: the planned land area is 100 Mu with a construction area
of 10,000 m2 and 1500 beds.
II. Construction reasons and conditions: currently, most of the private institutions
for old-age nursing in Sanming are small apartments with small scale, low level and
imperfect functions, showing a shortage of high-grade old-age nursing intuitions in
the urban. Hence, a new old-age apartment can not only bring nursing services for the
aged who live here, but also play its specialty continually.
III. Total investment: RMB 150 million.
IV. Analysis of economic benefits: The annual sales revenue will be RMB 34.39
million, the profit will be RMB 14.80 million and the investment will be recovered in
12 years upon completion of the project.
V. Preliminary work: the feasibility report has been compiled.
VI. Project organizer: People’s Government of Chenda Town, Meilie District.
VII. Contact person: Wu Anxiong
Tel: 13960516518
224. National Basketball Training Base in Nan’an City
I. Project description: the planning area is 53.5 hectares. Base construction
includes the competition hall, training hall and supporting facilities such as ground
track field, outdoor basketball court, tennis court, swimming pool, athlete’s apartment,
sports hotel, office building, body quality training hall and group construction center
and so on.
II. Construction reasons and conditions: basketball is a traditional and
advantageous sport event in Nan’an, which has more than 200 thousand basketball
athletes. Nan’an City has long been the major competition field course of Fujian
146
Women Basketball Team, and it has held the basketball game of the 8th National
Farmers' Sports Meeting. After completion of the “National Basketball Training Base”,
the national team and sports teams of other provinces will be attracted here for
training.
III. Total investment: RMB 647 million. Cooperation mode: exclusive
investment, joint venture or cooperative construction and stadium operation.
IV. Preliminary work: planning and design of the project are underway. 746mu
land has been acquired and leveling of partial plots has been completed. Nan’an
Sports School is under construction.
V. Project organizer: Bureau of Culture and Sports of Nan’an City
VI. Contact person: Chen Xinxin
Tel: 13506037297
147
Infrastructure Projects
225. Highway Project in Meilie Industrial Park, Sanming
I. Project description: the highway project in Melie Industrial Park has a total
route length of 6.86371 km (11.539 m long-chain). It’s designed in accordance with
the second class highway standard formulated by the ministry, with the designed
driving speed of 60 km/h and width of roadbed of 18m. The full-width concrete
pavement is 15m wide, the net width above bridge floor is 18 m, and culvert and
roadbed are of the same width. The main construction works include: 1,665,450m3 of
roadbed earthwork excavation, 1,906,690m3 of roadbed rock excavation, 8204.23m3
of drainage works, 15681.5m3 of protection works and pavement works of 95663.5 m2.
As for bridge works, it’s planned to construct 2 long bridges with 494m length in total
and 1 short bridge of 18m. The newly built reinforced concrete slab culvert has 16
channels, with a total length of 376m.
II. Construction reasons and conditions: the highway in Meilie Industrial Park to
be built is planned to connect Meilie Economic Development Zone (Xiaojiao Village),
Sanming Urban Logistics Park (Wengdun Village) and the north interchange of
Sanming Expressway. After completion, the distance from Xiaojiao Village to the
north interchange will be shortened by 10km, which is convenient for transportation
between Xiaojiao Industrial Park and Sanming Urban Logistics Park. Besides, driving
on the highway at the north interchange can avoid passing the crowded road and
reduce transportation cost.
III. Total investment: RMB 325.8 million. Cooperation mode: exclusive
investment or joint venture.
IV. Analysis of economic benefits: the ENPV is RMB 72.79 million, EBCR
1.2659, EIRR 10.1%, Payback Period EN 18.83 years and the Payback Period 18
years.
V. Preliminary work: the proposal of the project has been submitted for approval,
and the feasibility study report and Phase-II preliminary design have been approved in
the review.
VI: Project organizer: Construction Headquarters of Meilie Industrial Park
Highway of Sanming City.
VII. Contact person: Liu Lan
148
226. Putian Urban Rapid Transit System
I. Project description: the line is planned to be about 70km in length.
II. Construction reasons and conditions: the urban population of Putian City in
2015 is estimated to be over 2 million, meeting the conditions for building up the
rapid transit system in the No. 81 Document of State Council in 2003 Circular on
Strengthening Urban Rail Rapid Transit Construction and Management. Putian
Station is related to the Fuzhou-Xiamen Railway and Xiangtang-Putian Railway with
the short-term target of 3.5million person-time/a and long-term target of 5million
person-time/a. Within the first year of opening up, the passenger flow of single line
has reached near 80% of the short-term target.
III. Total investment: RMB 25 billion. Cooperation mode: joint venture,
cooperation or entrusted management, etc.
IV. Analysis of economic benefits: the public transport travel people of Putian
are predicated to be 2,093,000 person-time/d, including 837,200 person-time/d for
railway transport and 1,005,000 person-time/d for railway passenger flow. Therefore,
the Project has good economic and social benefits.
V. Preliminary work: planning has been completed.
VI. Project organizer: Putian Development & Reform Commission
VII. Contact person: Cai Yunying
Tel: 0594-2382311, 13905049316
Fax: 0591-2298744
E-mail: j3x001@163.com
227. Putian Airport Construction
I. Project description: Putian Airport is planned to be a route airport being
available for A320 and B737 series aircrafts. 4C is applied in recent construction
while 4D is reserved for the future construction. The track is designed to be Class I
two-way, with length of 2,400m×45m. The airport terminal is planned to be 10,000m2,
in which 10 seats will be available in recent period and 20 in the future. The airport is
planed to cover an area of 3,300mu in recent period and 3,750mu in the future.
II. Construction reasons and conditions: Putian Airport is quite necessary for
promoting coordinated development of the region on the west bank of Taiwan Straits,
149
for perfecting Fujian comprehensive transportation system, for carrying forward Mazu
Culture in order to promote the work in Taiwan, for improving the characteristic
economy in Putian, for integrating Putian tourism into “tourism on the west bank of
Taiwan Straits”, and for strengthening national defense capacity.
III. Total investment: RMB 850 million. Cooperation mode: exclusive
investment, joint venture or cooperation.
IV. Preliminary work: Site Selection Report of Airport in Putian, Fujian, Design
Plan of Flight Procedure during Site Selection of Airport in Putian, Fujian, Necessity
Analysis on Airport Construction in Putian, Fujian and Study on Development
Strategy of Airport in Putian, Fujian have been completely prepared.
V. Project organizer: Putian Development & Reform Commission
VI. Contact person: Cai Yunying
Tel: 0594-2382311, 13905049316
Fax: 0594-2298744
E-mail: j3x001@163.com
228. “Dry Port” Construction Project in Longyan
I. Project description: the planned area and construction area of the Project will
be 10,157mu and 8,733mu respectively. The 10 key construction projects in the first
phase aiming at realizing the basic functions of dry port include bonded logistics
center, port inspection base, container evacuation center, international purchasing
center, comprehensive service center and the like with a planned area of 1,104mu.
II. Construction reasons and conditions: the construction of “dry port” in
Longyan can effectively expand economic hinterland of port, and make the wide
central and western regions as the important potential market for the expansion of
supply of goods along coastal port.
III. Total investment: RMB 10.6 billion. Cooperation mode: exclusive
investment or joint venture.
IV. Preliminary work: the first phase project has been started.
V. Project organizer: Longyan International Logistics Center Construction Co.,
Ltd.
VI. Contact person: Liao Xu
150
Tel: 18959096868
229. Construction Project of Outer Ring Roads in Longyan Downtown Area
I. Description: The outer ring roads consist of north, south, east and west parts,
with a full length of 54 kilometers.
II. Total investment: RMB 5.5 billion
III. Preliminary work: The land acquisition and demolition work in the north
section of east outer ring road. The south and west outer ring roads are both in the
process of conceptual planning. In addition, the request of land for connecting
Yongchun-Yongding Highway and the north section of Longyan is submitted to a
higher level for examination and approval.
IV. Project organizer: Longyan Municipal Development Group Co., Ltd.
V. Contact person: Ruan Xuejun
Tel: 18959050488
230. Mt. Wuyi Passenger Terminal
I. Description: The implementation of main project design and construction shall
be in accordance with national second-class standard, and it should include the
complex building integrated with hotel and restaurant, waiting building, office
building and public park, long-distance, short-distance, countryside and public
transportation and taxi in the station ground, and a second-class bus station which is
an effective auxiliary to the planned hub of railway passenger transport.
II. Reasons and conditions: With Pucheng-Nanping, Wyi-Shaowu, Ningde-Wuyi
and Songxi-Jian’ou highway being open to traffic, the expansion of Mt. Wuyi Airport,
especially the construction of Jingfu high-speed rail which will expand to the section
between Fuzhou and Mt. Wuyi, the external traffic condition of Mt. Wuyi can, to a
large extent, be improved and make it become a key transportation hub to bridge the
south and the north.
III. Total investment: RMB150 million.Cooperation form: Exclusive investment
or joint venture.
IV. Analysis on economic benefits: It is estimated that the income will increase
by RMB 100 million annually after the project is completed and put into operation,
151
and the profit will be RMB 50 million and the investment will be paybacked in 3
years.
V. Preliminary work: The site selection and pre-feasibility study have been done.
VI. Project organizer: Project Office of Wuyi City
VII. Contact person: Hu Bijiang
Tel:1390599476
Fax: 0599-5317866
Email: 5134xmb@163.com
231. Construction Project of Northern Section of Jiangjun Avenue of
Yunxiao
I. Project description: the two-way avenue to be constructed is 4,532m in length
and 40m in width (with eight lanes, the road surface covering 8×3.5m, the marginal
strip 4×0.5m, the central reserve area 4.0m and the green belts covering 2×3.0m on
both sides). The construction of supporting facilities such as greening, lighting,
transportation projects and bus stations will be conducted at the same time. The pipe
place for rain water, waste water, electricity, telecommunication, water supply, and
gas will be reserved.
II. Reasons and conditions: the northern section of Jiangjun Avenue is the artery
connecting Yunxiao County and Huotian intersection of Guwu Expressway in the
planning of Yunxiao County. The construction of the Project will further improve the
transportation between Yunxiao County and Huotian Town, accelerate the
development of Huotian Town, bring benefits to the development of tourism resources
of Zhangjiang River, and promote the Kaizhang culture of Yunxiao County.
III. Total investment: RMB 269.05 million. BT mode is planned to be adopted
for attracting investment.
IV. Preliminary work: survey and design have been carried out.
V. Project organizer: Construction Bureau of Yunxiao County
VI. Contact person: Lin Zhenkun
Tel: 13505039228;
Fax: 0595-23405533
152
232. Construction Project of Yunxiao County Section (Phase II) of
Zhangzhou Coastal Avenue
I. Project description: the designed length is 14.15km and the width of subgrade
is 24.5m. The whole Avenue is constructed according to the Class I highway standard
with the designed speed of 80km/h.
II. Reasons and conditions: the construction of the Project plays an important
role in taking advantages of tourism resources and port resources along the avenue,
speeding up the development of port resources, perfecting transportation network,
optimizing investment environment, developing port economy and fully
implementing the strategies of “Port in City” and “Port in County”. The conditions are
ripe for the construction project.
III. Total investment: RMB 380 million. BT mode is planned to be adopted for
attracting investment. BT mode is adopted to tender for the construction.
IV. Progress of preliminary work: all the preliminary work has been completed
and has been approved with the Document No. MFJT [2010]928. The preparation,
examination and approval of preliminary design drawing of two phases and the
preparation of working drawing have been completed.
V. Project organizer: Yunxiao County Luda Road Construction Co., Ltd
VI. Contact person: Wu Wenxian
Tel: 13605048008
233. Shacheng Central Fishing Port in Ningde City
I. Project description: construction of 1,500mu fishing port wharf and supporting
facilities.
II. Construction reasons and conditions: Shacheng port is deep and wide with
convenient transportation and rich fish resources, making it the ideal place for
constructing a fishing port. Shacheng Central Fishing Port will reserve 48,800 m2 of
land area as the fishing port work zone, shoreline of 707m and wharf of 625m. In
addition, there will be 2 places of shelter anchorage, which can cope with fish and
goods distribution and ship windshield safety.
III. Total investment: RMB 80 million.
IV. Analysis of economic benefits: BT investment will be adopted and the
153
investment payback period will be 6 years.
V. Preliminary work: the First-Class Fishing Port in Shacheng Town has been
completed and it is now declared for project approval of national center fishing port.
VI. Project organizer: People’s Government of Shacheng Town
VII. Contact person: Chen Xiaolong
Tel: 0593-7581436, l3950561719
Fax: 0593-7581154
234. Ningde Xinan Harbor Railway Byline
I. Project description: the Xinan Harbor Railway Byline is planned to be
constructed according to Class II Highway Standard with total length of 29km and
designed speed of 80km/h.
II. Construction reasons and conditions: the Project aims at connecting the Xinan
Industrial Zone to the Wenzhou-Fuzhou Railway with great significance to
developing the Xinan Peninsula, improving the infrastructure and railway network
construction of Xinan Industrial Zone, improving its investment environment, etc.
III. Total investment: RMB 2 billion. Cooperation mode: BT and BOT.
IV. Preliminary work: the Byline Project has been listed into the medium and
long-term plan of Fujian railway network with route planning and pre-feasibility
preparation being completed.
V. Project organizer: The Railway Construction Preparation Office of Ningde
VI. Contact person: Yang Weijia
Tel: 13859686588
235. Storage and Wharf Construction of Operation Zone of Hougang Village,
Shacheng Town,Ningde
I. Project description: a wharf apron is planned to be arranged near the -20 to
-30m soundings. The container wharf is planned to be 1,000m in water front with 3
berths for 4th generation container ocean vessel (and 2 berths for 5th or 6th generation
154
container ocean vessel) and trafficability of about 1 million TEU.
II. Construction reasons and conditions: the Shacheng Harbor is of superior
geographic conditions and convenient transportation. Located in the south bank of the
Shacheng Harbor and about 10km away from its entrance, the operation zone of
Hougang Village is one of the 6 harbor & wharf operating areas in the general plan of
the Shacheng Harbor. It is embraced on three sides by mountains and has
1,000m-deep and 1,500mu land area with good apron and sounding conditions and
flat and wide land area at back.
III. Total investment: RMB 1 billion.
IV. Analysis of economic benefits: The annual output value will be RMB 2.5
billion and the profit and tax will be RMB 200 million.
V. Preliminary work: being planned.
VI. Project organizer: People’s Government of Shacheng Town
VII. Contact person: Chen Xiaolong
Tel: 0593-7581436, l3950561719
Fax: 0593-7581154
236. Ningde-Gutian Expressway of Expressway Network on the West Bank
of Taiwan Straits,Ningde
I. Project description: the Expressway is planned to be a doubly-way four-lane
expressway, with total length of 73km, designed speed of 80km/h, and total width of
subgrade of 24.5m.
II. Construction reasons and conditions: the Project is one of the important
regional interconnections of “three horizontals, eight verticals, three rings and
thirty-three joints” of expressway network in the Economic Zone on the West Bank of
Taiwan Straits. The Project is of significant practical importance to the perfection of
regional expressway network arrangement, enhancement of mountainous areas and
costal areas, expansion of harbor hinterland in Santuao, strengthening of national
defense and transportation construction, etc.
III. Total investment: RMB 5.568 billion. Cooperation mode: BT and BOT.
IV. Preliminary work: route planning has been completed already.
V. Project organizer: Expressway Construction Headquarters of Ningde City
155
VI. Contact person: He Fengbing
Tel: 13509564866
237. Xinan-Shugang Expressway of Expressway Network on the West Bank
of Taiwan Straits,Ningde
I. Project description: the Expressway is designed to be constructed according to
four lane expressway standard, with total length of 18.36km and designed speed of
100km/h.
II. Construction reasons and conditions: Xinan-Shugang branch line is one of the
important expressways in Shugang of “thirty-three joints” of expressway network
planning of Economic Zone on the west bank of Taiwan Straits. Crossing
Shenyang-Haikou Expressway, and connecting with Ningde-Wuyishan Expressway
via Wanwu Hub Interchange. Xinan-Shugang Expressway is a significant supporting
project for infrastructure of Development Planning of Santuao in Economic Zone on
the West Bank of Taiwan Straits.
III. Total investment: RMB 1.9 billion. Cooperation mode: BT and BOT.
IV. Preliminary work: pre-approval projects of feasibility of the Project have
been completed, and feasibility report has been prepared and reviewed in Fujian
Province.
V. Project organizer: The Expressway Construction Preparation Office of Ningde
VI. Contact person: He Fengbing
Tel: 13509564866
238. Zherong-Chengguan Transit Expressway in National Highway G104
I. Project description: the Expressway is planned to be 6.431km in length and
12m in full road width.
II. Construction reasons and conditions: the Project will greatly relieve the traffic
pressure in old district of Zherong County, improve living and transportation safety
for the public there, improve regional transportation conditions and investment
environment and promote the economic development of Zherong County, especially
the expansion of export-oriented economy.
156
III. Total investment: BT method will be adopted, and corresponding area of land
will be circled for operation in Plot B of new district in the east of Zherong County.
IV. Preliminary work: the feasibility report of the Project has been completed,
and project approval and preliminary work are under process.
V. Project organizer: Transportation Bureau of Zherong County
VI. Contact person: Chen Hui
Tel: 0593-8363001, 13950562988
Fax: 0593-2272270
E-mail: j3x001@163.com
239. Creativity Highway Project of Nan’an City
I. Project description: the highway under planning is 20km in length and 42m in
width.
II. Total investment: RMB 640 million. Cooperation mode: BT.
III. Analysis of economic benefits: this Project is proposed to be constructed in
“builder and transfer” (BT) way, in which the Project investor is selected through
public offering. The investor can get reasonable return on investment by investing in
this Project.
IV. Preliminary work: the feasibility study report has been complied.
V. Project organizer: Nan'an City Transportation Bureau
VI. Contact person: Huang Wenjiao
Tel: 13505065828
Fax: 0595-86366901
240. New Construction of Provincial Road 307 in Nan’an
I. Project description: the road under planning is 45km in length and 30m in
roadbed width.
II. Total investment: RMB 120 million. Cooperation mode: BT.
III. Analysis of economic benefits: this Project is proposed to be constructed in
157
“builder and transfer” (BT) way, in which the Project investor is selected through
public offering. The investor can get reasonable return on investment by investing in
this Project.
IV. Preliminary work: the feasibility study report has been complied.
V. Project organizer: Nan'an City Transportation Bureau
VI. Contact person: Huang Wenjiao
Tel: 13505065828
Fax: 0595-86366901
241. Xiaocuo-Shugang Branch Line of Quangang Expressway Network on
the West Bank of Taiwan Straits
I. Project description: the branch line is planned to be 9.59km in total length,
80km/h of designed speed and 24.5m of width of sub-grade. And the Project will
adopt the Double Carriage Expressway Standard and other technical standards
according to the Technical Standard of Highway Engineering (JTGB01-2003).
II. Construction reasons and conditions: the construction of the Project will
perfect the expressway network arrangement in Fujian Province and Quanzhou City,
enhance comprehensive transportation junction and connection on the west bank of
Taiwan Straits, get through the collecting and distributing channels from the
Quangang Harbor to the interior provinces and expand the economic hinterland of
harbor groups on the west bank of Taiwan Straits. Agreement on project construction
has been reached through several coordination and verifications by the People’s
Government of Quangang District with related departments, who will actively engage
in and support the Project.
III. Total investment: RMB 1.201 billion.
IV. Analysis of economic benefits: the financial internal rate of return will be
5.89%, financial net present value RMB 300,805,400, return on investment 7.6%,
payback period 16.35 years and loan repayment period of project debt (including the
construction period) 13.85 years.
V. Preliminary work : in November, 2011, the People’s Government of
Quangang District organized and held the primary examination meeting on
engineering feasibility; in January, 2012, the design unit provided the revised draft
and submitted it to the Quanzhou Municipal Higher Advisory Committee and
Quanzhou Development and Reform Commission; and in February, 2012, the
Quanzhou Development and Reform Commission transmitted the engineering
feasibility report of the Project to the Fujian Development and Reform Commission
158
for application and review.
VI. Project organizer: Traffic & Transportation Bureau of Quangang District,
Quanzhou City.
VII. Contact person: Lin Jiaqiang and Lin Mingjian
Tel: 0595-68110209, 13960339876, 13959972001
Fax: 0595-87996200
Email: qgqjtjgcg@163.com
242. Marine Reclamation Construction Project in Sanyu Village, Ningde
City
I. Project description: 8,000mu marine area along 3,200m sea wall will be
reclaimed in the Project, mainly for the development of emerging industries and
cultural creative industries, the former of which include new energy, new materials,
new energy vehicles, energy conservation and environmental protection, information
technology, biotechnology, etc., and the latter of which include advertisement, design,
film, TV interactive leisure software, audio and book publication, animation
production, etc.
II. Construction reasons and conditions: the Sanyu new district is located
between Sanyu Village, Qidu Town and Yundan Village, Badu Town, with estuary of
Huotong Stream and of Qidu to the north and south respectively. National Highway
104 lies on the west of the new district, Shenyang-Haikou Expressway passes it on the
west and Wenzhou-Fuzhou Expressway passes it on the east. It is 1.3km away from
the north shore line of Zhangwan Harbor in the south, where wharfs bearing
10,000-30,000t berths can be constructed. All the above provide the city with
convenient land and water transportation.
III. Total investment: RMB 1.2 billion
IV. Analysis of economic benefits: the investment payback period will be 8
years.
V. Preliminary work: Planning on Regional Sea Areas Utilization for
Construction has been prepared, and the use right of national sea area has been
officially approved.
VI. Project organizer: Investment Promotion Center of Jiaocheng District
VII. Contact person: Zheng Lixin
159
Tel: 13950572668
243. Huaxun Asia-Pacific International Incubation Base in Changle City
I. Project description: the planned land area is 500mu with a floor area of
833,000 m2.
II. Construction reasons and conditions: make use of internationalization
advantage of Huaxun Group and foster ecological environment for innovative
enterprise growth and cluster. The Project is to develop international cooperation
channel in Asia-Pacific areas, establish technological innovation union and investment
union in Asia-Pacific areas, and build technical cooperation and discussion platform,
software and information service outsourcing platform, public technology support
platform and scientific achievements trading platform.
III. Total investment: RMB 3 billion. Cooperation mode: share investment.
IV. Analysis of economic benefits: the newly increased annual revenue will be
RMB 4 billion, with tax revenue being RMB 150 million.
V. Preliminary work: approval procedures of Huaxun Asia-Pacific International
Incubation Base are underway, and key provincial project has been declared.
VI. Project organizer: Huaxun (Fujian) Venture Capital Co., Ltd.
VII. Contact person: Lin Shen
Tel: 13509376626
Fax: 0591-88033633
244. Xiamen Aosino Chateau
I. Project description: the Project is planned to cover an area of 13,000m2 and the
building area of 40,000m2. The second and third floors underground will serve as
warehouse and garage, and the third and fourth floors aboveground will serve as
exhibition hall and place for trade office.
II. Construction reasons and conditions: at present, there is no specialized
distribution center of significant scale for imported goods in Fujian Province or even
in the whole South China. Relying on the convenient transportation network and
abundant tourism resource in Xiamen, the Project can provide merchants with
efficient logistics distribution service and make itself known by the public in next to
no time. Besides, supported by the special bonded policy, the Project will help
160
merchants improve the fund utilization efficiency, so as to enhance market
competitiveness.
III. Total investment: RMB 200 million.
IV. Analysis of economic benefits: the total rate of return on investment will be
28.25%, the ROE 56.43%, the FNPV RMB 578.27 million and the static payback
period on investment 7-8 years (including construction period).
V. Preliminary work: Project planning has been submitted for approval, and the
Project is estimated to be commenced at the end of June 2012.
VI. Project organizer: Aosino (Xiamen) International Wine Co., Ltd.
VII. Contact person: Que Juxuan
Tel: 13799252501
Fax: 0595-5618187
E-mail: quejuxuan0902@163.com
245. Xiamen Aviation Logistics Operation Service Center
I. Project description: the total building area is about 120,000m2, and part of the
office buildings will be available for renting and selling.
II. Construction reasons and conditions: Aviation Logistics Operation Service
Center belongs to comprehensive aviation logistics operation service center
integrating joint inspection and customs clearance service on port, administrative
management of modern logistics park, logistics enterprise operation and business
supporting service.
III. Total investment: RMB 350 million.
IV. Analysis of economic benefits: the financial internal rate of return will be
9.5%, the profit rate of investment 10.8% and the static payback period on investment
10.2 years.
V. Preliminary work: roof capping of building was completed in December 2011,
and at present, construction of curtain wall and internal/external decoration are in
process. The Project will be completed in the second half of 2013.
VI Project organizer: Xiamen Free Trade Zone Aviation Logistics Park
Construction Co., Ltd.
161
VII. Contact person: Lin Yimei
Tel: 13606079872, 0592-5707579
Fax: 0592-5706660-6589
E-mail:lym@iport.com.cn
246. Jimei Logistics Park
I. Project description: Jimei Logistics Park, located in Guankou Town of Jimei
District, occupies 2,966mu (1mu=666.67m2), and it is estimated to be completed in
2014.
II. Construction reasons and conditions: logistics industry is a pillar industry of
Xiamen. As the critical part of Qianchang Motor-Rail Logistics Center, Jimei Logistic
Park will serve as a collection and distribution of goods by railway in southwest of
Fujian Province, with the service area covering the whole economic zone on the west
coast of Taiwan Straits.
III. Total investment: RMB 550 million.
IV. Analysis of economic benefits: the total revenue from trade service, financial
service, lease of office and storage equipment, transportation outsourcing, stamp tax
and land use tax will reach RMB 360 million after the Project is put into production
and increases to RMB 640 million in 5 years.
V. Preliminary work: land acquisition and prophase construction procedures are
underway.
VI. Project organizer: Jimei State-owned Property Investment Co., Ltd.
VII. Contact person: Lin Huihong
Tel: 13950011788, 0592-6253258
247. Xiamen Financial Center across Taiwan Straits
I. Project description: the Project is planned to cover an area of 8.6km2 in Siming
District and 10.5km2 in Huli District. The institutions involving finance, background
service, intermediary service, equity investment funds and the like are invited for
investment.
II. Construction reasons and conditions: in 2010, Several Opinions of the State
162
Council of the PRC on Supporting Fujian Province to Accelerate the Building of the
Economic Zone on the West Coast of the Taiwan Straits was issued, and “Establishing
regional financial service center across Taiwan Straits, and pre-implementing and
pre-testing some significant reform measures in financial application” was formally
approved. In 2011, construction of economic zone on the west coast of Taiwan Straits
was specially put forwarded in Outline of the “12th Five-Year Plan”, facilitating the
construction of the regional financial service center across Taiwan Straits in Xiamen.
III. Total investment: RMB 175 billion.
IV. Analysis of economic benefits: a national grade regional financial service
center across Taiwan Straits will be established.
V. Preliminary work: some plots have been exploited for construction, and part
of projects introduced is undergoing listing procedures.
VI. Project organizer: Xiamen Siming Investment Promotion and Service
Agency and Xiamen Huli Investment Promotion Bureau
VII. Contact person: Wang Yanyu and Feng Guangyu
Tel: 0592-2667376, 5722382
Fax: 0592-266714, 0592-5722385
E-mail: wangruru@126.com, zsj@huli.gov.cn
248. Business Office Project of Xiang’an New Town CBD
I. Project description: the Project, located in Xindian Town of Xiang’an District,
covers an area of 1,000mu. In this project, the planned public service facilities include
business office and city complex, SOHO, large scale business and five-star hotels, bus
stops, parking lots, citizen event plaza and supporting center for business office and
entertainment and so on.
II. Construction reasons and conditions: Xiang’an possesses unique advantages
of location and economic development in the progress of construction of western
coast of Taiwan Straits and integrative development of Xiamen, Zhangzhou and
Quanzhou. In the future development, Xiang’an has got promising potential of real
estate appreciation.
III. Total investment: RMB 1.6 billion.
IV. Analysis of economic benefits: land revenue of the Project will be about
163
RMB 1.6 billion.
V. Preliminary work: three supplies (supply of water, electricity and road), and
one leveling and urban facilities are under construction.
VI. Project organizer: Xiamen Xiang’an Construction and Development Co.,
Ltd.
VII. Contact person: Luo Mingqing
Tel: 13860108688, 0592-7889892
Fax: 0592-7889078
Email:xmxacdc@vip.163.com
249. Haicang Bonded Port
I. Project description: the Project occupies 9.5092 km2 and integrates modern
port, bonded logistics park and export processing zones.
II. Construction reasons and conditions: this Project was approved by the State
Council on Jun.5, 2008. It covers an area of 9.5092 km2 and integrates modern port,
bonded logistics park and export processing zones. It’s presently one of the areas
under special customs supervision in China, with the greatest degree of trade
openness, most complete functions, most preferential policies, most convenient
customs clearance and largest area.
III. Total investment: RMB 5 billion.
IV. Analysis of economic benefits: according to national policies, settled
enterprises are entitled to enjoy relevant preferential policies and foreign exchange
policies in the bonded area, export processing zones and bonded logistics park.
V. Preliminary work: operation in customs - closing status of the first and second
phase Project, and the third phase Project is being under construction.
VI. Project organizer: Haicang District Government and Haicang Bonded Port
Administrative Committee
VII. Contact person: Xie Jin’e
Tel: 0592-6896675, 13950010212
Fax: 0592-6895998
Email: xieje@haitou.cn
164