Duffany, Fountain, Julian Optimizing Nitrogen Removal in a Sequencing Batch Reactor CEE 453 Findings Report: Optimizing Nitrogen Removal in a Sequencing Batch Reactor PI’s: Matthew Duffany Matthew Fountain Timothy Julian 5/11/04 Version 1.0 5/11/04 Page 1 of 25 Duffany, Fountain, Julian Optimizing Nitrogen Removal in a Sequencing Batch Reactor CEE 453 Table of Contents: Topic Page Abstract ............................................................................................... 3 Introduction ......................................................................................... 3 Objectives ............................................................................................ 4 Methods ............................................................................................... 4 Nitrate Probe Analysis ........................................................................ 6 Nitrogen Removal Discussion............................................................ 13 Appendix 1: Plant Setup ..................................................................... 17 Appendix 2: Reactor Setups .............................................................. 18 Appendix 3: Waste Characteristics ................................................... 19 Appendix 4: Academic / Industrial Designs ...................................... 20 Appendix 5: Nitrate Probe Calibration ............................................... 22 Appendix 6: Aeration Level ................................................................ 23 Works Cited ......................................................................................... 25 Version 1.0 5/11/04 Page 2 of 25 Duffany, Fountain, Julian Optimizing Nitrogen Removal in a Sequencing Batch Reactor CEE 453 Abstract: The initial goal of this project was to establish a system for optimized nitrogen and BOD removal from a wastewater stream in an activated sludge batch reactor. The plan for optimization included the implementation of online nitrate measurement combined with Process Controller V2 LabView software to manage reactor state changes. However, initial testing of the nitrate probe (an Analytical Sensors Inc gel filled LogIT ion selective electrode) suggested that the device was unsuitable for the current project intentions. At this point experiments were run to confirm probe difficulties and research was begun to establish industry and academic criteria for nitrification and denitrification in process. This report presents a summary of findings into the difficulties encountered with the online probe (ranging from voltage fluctuations under varying conditions to ionic interference in different conditions) and condenses the state of the art on nitrogen (biological and chemical aspects, sensitivities, kinetics and processes) removal as it pertains to lab tested small scale batch reactors. Introduction: Much ongoing research is focused on the analyses of varied waste water treatment strategies. One of the increasingly important criteria is nitrogen concentrations in waste effluent. The major sources of nitrogen in municipal wastewater are urea and fecal matter. Nitrogen is important to treat as ammonia nitrogen is a serious fish poison even in small concentrations1, nitrate nitrogen can lead to eutrophication of coastal (nitrogen limited) ecosystems even in low effluent concentrations2, and nitrite creates human health concerns by causing blue baby syndrome in children (nitrite in concentrations of 1 mg/L). The nitrogen can be present as any of these species due to the bacterial pathways: Nitrosomonas 2 NH 4 3O2 2 NO2 2H 2 O 4 H Nitrobacter 2 NO2 O2 2 NO3 To this extent, drinking water is regulated by the EPA at 1 mg/L for nitrite-nitrogen and 10 mg/L for nitrate-nitrogen. However, while the nitrification cycle is simply described, its biological kinetics forms a slightly more complicated process. To begin with, a typical nitrogen removal in bio-solids is the volatilization of ammonia, this method is difficult to achieve in wastewater treatment as very small amounts of gaseous ammonia will be lost at pH values less than 8.5 as hydrogen ions are a component in the equilibrium3: [ NH 4 ] [ NH 3 ] [ H ] 1 Mogens Henze [et al.]. Water Pollution Control Federation. Task Force on Nutrient Control 3 ibid 2 Version 1.0 5/11/04 Page 3 of 25 Duffany, Fountain, Julian Optimizing Nitrogen Removal in a Sequencing Batch Reactor CEE 453 Therefore, the ammonia must instead be oxidized and taken through the reactions shown above to nitrate so that denitrification can later be used to remove the nitrogen to a harmless form of diatomic nitrogen gas. Nitrification is a relatively specialized process that will only be accomplished through the Nitrosomonas and Nitrobacter species of bacteria. These bacteria are obligate aerobes (their populations will only grow under aerobic conditions) but they can survive long periods of anaerobic conditions. They are both autotrophs that oxidize ammomia to provide energy for cell synthesis, but Nitrosomonas kinetics is the limiting rate in the process, leading to solutions typically low in nitrite compared to ammonia or nitrate concentrations4. Once the nitrogen has all been converted to nitrate the next step is to induce the action of denitrifying bacteria. These bacteria come from a range of diverse species including Pseudomonas, Micrococus, Archromobacter, Thiobacillus, and Bacillus. These species are mostly facultative (able to use either oxygen or nitrate as the terminal electron acceptor in respiration), and thus oxygen concentrations must be kept low as oxygen provides greater energy and is thus preferred by the organisms (oxygen respiration of glucose yields 686 Kcal / mol while nitrate yields only 570 Kcal / mol).5 More specific analyses of these processes follow below. Objectives: The initial goal for this project consisted of establishing an online control of an activated sludge batch reactor to optimize both nitrogen and BOD removal. To this aim funding was requested and received for an online nitrate probe. However, the nitrate probe proved unsuitable due to extreme fluctuations for the online control of the plant. At this point the project was shifted to an analysis of effects on the nitrate probe and what factors may be causing these variations, and whether or not they were correctable. The experimental studies on the probe also led us to delve into the literature surrounding the difficulties with both nitrification and denitrification, and the eventual report became a combination of analysis on the probe and a study on applying industrial and academic techniques of nitrogen removal in a sequencing batch reactor in the hopes that future groups would be able to advance our work into a fully functional model. Methods: An activated sludge sequencing batch reactor was set up to simulate the activity in an activated sludge single tank treatment plant. While treating waste as a batch process is unlikely in an industrial or municipal setting where extremely large volumes would be neccessary, the approximation served adequately to experiment with nitrogen removal as 4 5 ibid Halling-Sørensen, B. Version 1.0 5/11/04 Page 4 of 25 Duffany, Fountain, Julian Optimizing Nitrogen Removal in a Sequencing Batch Reactor CEE 453 it related to oxygen and timing. If specific methods were to be devised, a model of a continuous flow reactor would need to be constructed and tested as well. The details of the plant design can be found in Appendix 1: Plant Setup, and the precise volumes, timings, and alternative inputs of the multitude of experiments run in this project can be found in Appendix 2: Reactor Setups. The characteristics of the waste flows can be found in tables provided in Appendix 3: Waste Characteristics. In a general sense the plant was constructed, tested for structural integrity and leaking, and then run continuously (other than a 2 day downtime due to computer virus infection of the lab) for a six week period. During this period the different reactor setups were tested to determine different information about the nitrate probe and BOD levels. The reactor was run according to Process Controller v2 software developed by Monroe Weber-Shirk, as a piece of LabView code which controlled different states of the reactor as shown in the appendix through a series of solenoid valves controlling waste input and air input. Oxygen was introduced to the reactor through a ceramic diffuser to maximize dissolution into the waste solution. The reactor was also brought into effectiveness by the introduction of 4 L of activated sludge from the Ithaca Waste Water Treatment Facility. It was also important to refrigerate the waste so that no degradation would occur in the waste bottle which would falsely serve as a “pretreatment.” Furthermore, it was necessary to load the waste into the tank before the water so that the water could be used to flush the pipes that were outside the refrigerator and prevent a bioaccumulation from growing on the waste in the piping and possibly blocking future flow. The different states run in the reactor can be summarized as the following: Add Waste: input of 140 mL of 20x concentration stock waste from the refrigerator; controlled through flowrate of the peristaltic pump. Add Water: input water (with stock 2 and 3) into the reactor until 4 L of total volume is recorded by a pressure sensor (calibrated to account for altered density of water due to waste and sludge). Aerate: air pumped into the ceramic diffuser at air rate controlled by solenoid valves while the reactor is stirred by a stirbar on a stir plate set at 8. Operated on a timer system. Anaerobic: no aeration occurs but stirring continues at setting number 8. Operated on a timer system. Settling: ceasing of aeration and stirring, sludge allowed to settle to the bottom of the tank. Operated on a timer system. Discharge: with no stirring or aeration the water is removed from the top of the settled sludge though a port at 1.2 L height in the tank, along with wasted sludge that allows mass balance with growth to retain constant sludge volume. Controlled by pressure sensor recording minimum volume. Repetition of steps above Version 1.0 5/11/04 Page 5 of 25 Duffany, Fountain, Julian Optimizing Nitrogen Removal in a Sequencing Batch Reactor CEE 453 Nitrate Probe Analysis: The nitrate probe was calibrated as shown in Appendix 5. The nitrate probe was first soaked in water for 15 minutes, then a diluted nitrate solution for 2 hours. At this point the probe was washed clean and placed into distilled water with different concentrations of nitrate in order to measure the corresponding voltages. The probe values show a distinctively curved calibration line, implying a similar voltage to interpreted value ratio as a pH meter. This result seems sensible as both meters use voltage from the diffusion of a solution through a membrane. One of the major problems with the nitrate probe is that the calibration was accomplished in distilled water with only nitrate ions present. In the activated sludge reactor there are many other chemicals present. The probe will suffer from interference in solutions with high ionic strength, and this was one issue that had to be tested in the reactor. The initial testing of the nitrate probe consisted of measuring the voltage output from the probe while it was immersed in the tank during our standard reactor cycle of adding waste and water, aerating, letting sit anaerobically, settling, and discharging effluent. By applying the calibration curve to the voltage received from the probe while it was immersed in the reactor, the nitrate concentration can, hypothetically, be determined. This concentration is inversely related to the voltage received. This relationship is shown in Figure 1, where nitrate voltage is measured during one complete cycle and is converted into nitrate concentration. The two graphs are mirror images of each other due to the inverse relationship between voltage and nitrate concentration. In addition, variations in the voltage of approximately 0.02 volts correspond to variations in nitrate concentration of roughly 0.18 ppm/100. This demonstrates the magnification effect that occurs when converting from voltage to concentration of nitrate. Version 1.0 5/11/04 Page 6 of 25 Duffany, Fountain, Julian Optimizing Nitrogen Removal in a Sequencing Batch Reactor CEE 453 Concentration / Voltage vs Tim e Over One Period Discharge Anaerobic Fill 0.7 0.18 Aerate Settle 0.16 0.6 0.14 0.5 0.4 0.1 volts concentration 0.12 4/30 0.08 0.3 Nitrate (ppm/100) Nitrate (Volts) 0.06 0.2 0.04 0.1 0.02 0.34 0.33 0.31 0.29 0.27 0.25 0.23 0.22 0.2 0.18 0.16 0.14 0.13 0.11 0.09 0.07 0.05 0.04 0 0 0.02 0 tim e (day fraction) Figure 1: This figure shows the voltage read by the nitrate probe and corresponding nitrate concentration over the period of one wastewater treatment cycle. This demonstrates the indirect relationship between voltage output by the probe and nitrate concentration in the reactor. Once the relationship between the voltage and the nitrate concentration was determined, the nitrate concentration could be constantly measured and monitored in the reactor. This was a vital component of our proposed research as our initial goal was to use the nitrate probe as a real-time feedback monitor of conditions in the reactor (online reactor control). However, the measurements provided by the nitrate probe were not always accurate. The magnitude that the nitrate concentration wavered, as measured by the probe, inhibited its use as a real-time feedback monitor of conditions in the tank. While the reactor was run for multiple cycles under the typical Wuhrman Configuration conditions of aerobic, anaerobic, settle, discharge / fill, the nitrate was measured. The results were then compared to expected results and it was discovered that the nitrate probe was displaying wavering concentrations of nitrate that did not follow the expected conditions. This is demonstrated in Figure 2, which shows the nitrate concentrations in two complete cycles, along with idealized expected nitrate concentrations and dissolved oxygen in the tank. Version 1.0 5/11/04 Page 7 of 25 Duffany, Fountain, Julian Optimizing Nitrogen Removal in a Sequencing Batch Reactor CEE 453 Actual Nitrate Vs. Predicted Nitrate Over Two Cycles Discharge / Fill Discharge / Fill 1.2 2 Settle Anaerobic Aerobic Aerobic Anaerobic Settle 1.8 1 1.4 DO (mg/L) 0.8 1.2 0.6 1 0.8 0.4 0.6 Nitrate (ppm/100) 1.6 0.4 0.2 0.2 0.8 0.78 0.76 0.74 0.72 0.71 0.69 0.67 0.65 0.63 0.61 0.57 0.59 0.56 0.54 0.5 0.52 0.48 0.46 0.44 0.42 0.41 0.39 0.37 0.33 0.35 0.31 0.29 0.27 0.26 0.24 0.2 0.22 0.18 0 0.16 0 Time (day fraction) DO (mg/L) Expected Nitrate Actual Nitrate (ppm/100) Figure 2: This figure shows the expected nitrate concentration along with the actual nitrate and dissolved oxygen concentrations as demonstrated by the nitrate and oxygen probes. While the oxygen probe is demonstrating expected results, the nitrate probe wavers significantly throughout the cycle with only small correlation to the expected nitrate concentration trends. This demonstrates that the nitrate probe is not yielding expected results. The project direction (of the laboratory module) was now devoted to discerning the cause for the wavering nitrate readings so that the probe could be used to in conjunction with the rest of the reactor to optimize waste treatment. To understand whether the nitrate probe was recognizing nitrate concentration or it was recognizing concentration of ion interference, a burst of nitrate (0.971 g NaNO3) was added to the tank while the wastewater treatment was in the anaerobic state. The concentration of nitrate was meanwhile measured using the probe. A nitrate concentration spike was demonstrated, as expected, by the probe as shown in Figure 3 while the reactor was being aerated. A burst of dextrose (10 g) was then added to the tank two hours after the nitrate was added. The purpose of this was to provide the activated sludge with a source of chemical oxygen demand that would increase the rate of denitrification. The expected result of this would be a sharp decline in the concentration of nitrate. Version 1.0 5/11/04 Page 8 of 25 Duffany, Fountain, Julian Optimizing Nitrogen Removal in a Sequencing Batch Reactor CEE 453 Nitrate and Dextrose Spikes Aerobic 8 9 Anaerobic Aerobic Anaerobic 8 7 6 DO (mg/L) 5 Nitrate Added Dextrose Added 5 4 4 3 Nitrate (ppm/100) 7 6 DO (mg/L) Nitrate (ppm/100) 3 2 2 1.147 1.137 1.126 1.116 1.105 1.095 1.084 1.074 1.064 1.053 1.043 1.032 1.022 1.012 1.001 0.991 0.980 0.970 0.959 0.949 0.939 0.928 0.918 0.907 0.897 0.887 0.876 0 0.866 0 0.855 1 0.845 1 Time (day fraction) Figure 3: This figure shows the nitrate concentration in the reactor after a spike of 0.971 g of sodium nitrate (NaNO3) and 10 g dextrose were added to the tank two hours apart. The concentration of nitrate spikes, and then slowly declines while in the anaerobic state. As soon as the dextrose is added, the nitrate concentration drops dramatically and remains low even when the reactor switches to the aerobic stage. The results demonstrated that the nitrate probe was recognizing changes in nitrate concentration. However, the nitrate concentration that was being measured by the probe must clearly not have been the only contributor to the measurement because, as shown above, the nitrate probe was not giving expected results in the full cycle controlled situation. Because this experiment was run in only in aerobic / anaerobic conditions, it was postulated that electrical interference caused by the complete cycle run through may have caused the wavering nitrate readings. At this point, further experiments were run. To test this electrical hypothesis, the nitrate probe was removed from the tank and placed in a separate beaker with a steady diluted nitrate concentration while the wastewater reactor was run. If the nitrate concentration changed even slightly over the period of one cycle, this would demonstrate that state changes were causing electrical interference. Because the nitrate concentration remained steady over the period of one cycle, electrical interference was ruled out as the cause for error. However, as stated, the nitrate concentration in the beaker was composed entirely of distilled water and sodium nitrate, with no other ionic interference present. The next possible source of error examined was the ionic or electrical interference created from the dissolved oxygen probe which was measuring dissolved oxygen only a few centimeters from the nitrate probe, as shown in the lab set-up in Appendix 1. The dissolved oxygen probe was removed from the tank in order to determine any difference in the nitrate probe readings, but there was no change in the nitrate readings. The dissolved oxygen concentration displayed by the DO probe equilibrated, but the nitrate Version 1.0 5/11/04 Page 9 of 25 Duffany, Fountain, Julian Optimizing Nitrogen Removal in a Sequencing Batch Reactor CEE 453 probe reading did not change. This demonstrates that the proximity to the working dissolved oxygen probe did not influence the nitrate probe. Because the nitrate probe was carefully calibrated using a solution of diluted nitrate, we determined that the activated sludge (or other compounds) in the wastewater tank was a possible source of interference. In order to test this hypothesis, we ran four separate sets of cycles while measuring nitrate, slowly removing different aspects of the wastewater treatment plant. If the removal of one of the components in the reactor resulted in expected unwavering results, we could rule that it was the cause of interference. The first cycle tested was the normal running mode of the tank, in which every aspect of the reactor was included: water, waste, and activated sludge. The second cycle tested removed the activated sludge and ran the reactor with only water and waste. The third cycle tested consisted of running only water with a nitrate spike added at the beginning. The results are shown as follows, where Figures 4, 5 and 6 demonstrate the results from water – water and nitrate spike -- water and waste – and -- water, waste and activated sludge respectively. Nitrate Spike Added to Water / Cycle Run Discharge Fill Water 12 8 Aerobic Anaerobic Settle 7 DO concentration (mg/L) 10 6 8 5 6 4 3 4 2 2 1 0 0. 95 0 0. 96 7 0. 98 5 1. 00 2 1. 01 9 1. 03 7 1. 05 4 1. 07 1 1. 08 9 1. 10 6 1. 12 4 1. 14 1 1. 15 8 1. 17 6 1. 19 3 1. 21 0 1. 22 8 1. 24 5 1. 26 2 0 Day Fraction Nitrate Spike DO (mg/L) Nitrate (ppm/100) Figure 4: This figure demonstrates the results from running through a cycle with water after a spike of nitrate was added. Because there is no activated sludge in the tank to treat the nitrate, the concentration should remain relatively stable. Though this is true for the aerobic state, the measured nitrate spikes in the anaerobic state and remains high. Version 1.0 5/11/04 Page 10 of 25 Duffany, Fountain, Julian Optimizing Nitrogen Removal in a Sequencing Batch Reactor CEE 453 The nitrate spike shown at the beginning of Figure 4 corresponds with the results demonstrated in Figure 3 that the nitrate probe recognizes an increase in nitrate level. However, the nitrate level is supposed to slowly increase in the aerobic stage, and then decrease in the anaerobic stage as expected in Figure 2. Clearly, the multiple spikes that occur in the anaerobic stage do not conform to this projection. After the multiple spikes occur, the nitrate concentration remains high until the reactor discharges the waste and is refilled. As the only components present in the tank are water and the initial spike of nitrate, the switch to anaerobic conditions should have no effect on the nitrate levels whatsoever. This, however, was not demonstrated by Figure 4. Next, the waste was added to the cycle as shown in Figure 5. The waste provided a source of chemical oxygen demand, but did not provide any nitrate. Again, because there was no activated sludge included in the tank, the nitrate levels should have remained steady at close to zero (since the majority of the previous spike of nitrate was discharged). This was not demonstrated, however, as the nitrate was measured to be wavering around 0.4 ppm / 100. Clearly, a problem with the nitrate probe is demonstrated in Figure 5. Cycle with Water and Waste Only Fill Discharge 12 0.7 Anaerobic Anaerobic Settle 0.6 10 0.5 DO mg/L 8 0.4 6 0.3 4 Nitrate (ppm/100) Aerobic 0.2 2 0.1 0 0. 50 6 0. 52 0 0. 53 4 0. 54 7 0. 56 1 0. 57 5 0. 58 9 0. 60 3 0. 61 7 0. 63 1 0. 64 5 0. 65 9 0. 67 2 0. 68 6 0. 70 0 0. 71 4 0. 72 8 0. 74 2 0. 75 6 0. 77 0 0. 78 4 0. 79 7 0. 81 1 0 Time (day fraction) DO (mg/L) Nitrate (ppm/100) Figure 5: This figure shows the results for nitrate and dissolved oxygen levels as obtained in the reactor running with the water and waste running without the activated sludge. In the aerobic stage, just after waste was added, the nitrate level spikes and slowly decays but still remains high. In the anaerobic stage, however the nitrate again spikes and slowly decays. Because there is no activated sludge in the tank, the cause of the spike / decay in the anaerobic stage is not understood. Version 1.0 5/11/04 Page 11 of 25 Duffany, Fountain, Julian Optimizing Nitrogen Removal in a Sequencing Batch Reactor CEE 453 Though a clear problem is shown in the attempt to measure nitrate in a reactor containing only water, we added the activated sludge to the tank to repeat the previous experiment of running a complete cycle and measuring the nitrate. Unsurprisingly, results similar to Figure 2 were measured as shown in Figure 6. Those results show a spike of nitrate during the discharge / fill stage, and then show a wavering line around a constant concentration. What was surprising, however, was that the concentration of the nitrate was lower (around 0.08 ppm / 100) and that the nitrate concentration did not waver as much as it previously had. Though these two experiments were identical, except that Figure 2 demonstrates an experiment that had been running for a couple of days while Figure 6 was re-added activated sludge. A possible cause for this was that the activated sludge may have been less active than their predecessors because they had been sitting un-aerated and without waste for a period of two days. Fill Cycle with Water, Waste, and Activated Sludge Discharge 9 1 Aerobic Settle Anaerobic 0.9 8 0.8 7 DO (mg/L) 0.6 5 0.5 4 0.4 3 0.3 2 0.2 6 0 5 9 3 8 2 2 0. 64 0. 62 0. 61 0. 59 0. 57 0. 56 0. 54 7 0. 53 5 0 4 8 3 7 2 1 0. 51 0. 50 0. 48 0. 47 0. 45 0. 43 0. 42 0. 40 0. 39 0. 37 0. 36 0. 34 6 0 0 0 5 0.1 9 1 0. 32 Nitrate (ppm/100) 0.7 6 Time (day fraction) DO (mg/L) Nitrate (ppm/100) Figure 6: The activated sludge was re-added to the system of water and waste and was run through a complete cycle. The nitrate results shown are more consistent than the first measurements obtained , but are lower in magnitude and still do not follow the expected trend. This is most likely due to less active sludge. Though the cause of the nitrate probe’s inability to function appropriately was never determined, we postulate that interference from ions in the water, waste, and activated sludge are possible sources. The nitrate probe seemed to work best in distilled water / sodium nitrate mixtures. For this reason, we do not recommend using this nitrate probe in the future for work in an activated sludge reactor due to the high concentration of impurities. Version 1.0 5/11/04 Page 12 of 25 Duffany, Fountain, Julian Optimizing Nitrogen Removal in a Sequencing Batch Reactor CEE 453 Though our original goal was to use the nitrate probe as a real-time feedback monitor that enabled us to change reactor states based on nitrate levels, the high fluctuation in nitrate measurements made this task impossible. A possible suggestion for the future would be to test other nitrate probes available on the market, and rely on this nitrate probe only for pure concentrations of nitrate. Nitrogen Removal Discussion: As explained in the introduction, the removal of nitrogen from the wastewater effluent requires both nitrification and denitrification. There are a number of difficulties that must be overcome to make these processes dominant in a reactor designed to remove BOD from waste. The first difficulty in nitrogen removal occurs in the oxidation of ammonia into first nitrite then later nitrate. The microorganisms that oxidize the ammonia are obligate aerobes, so for growth must be exposed to oxygenated waters with concentrations of nitrogen. However, with the raw waste that is input into the reactor, the same aeration cycle will also provide oxygen for the heterotrophic microorganisms that degrade the organic carbon. These two groups of organisms are in direct competition with each other for the available dissolved oxygen, and those that decompose organic carbon have growth kinetics that allow them a higher actual growth rate than the maximum possible growth rate for the nitrifying bacteria. This disparity in rates means that no matter how unbalanced the growth becomes, the carbon utilizing bacteria will dominate the population of the reactor as long as any significant quantities of organic carbon remain. This order means that nitrification will not occur until after the degradation of carbonaceous oxygen demand, and thus when oxygen levels begin to rise, the nitrogen may not have been oxidized as of yet. This significant lag time in nitrification has been observed this year by the work done in Rudi Sheck’s laboratory group. The lag time occurs not only because the nitrifiers must wait for oxygen to be available for their processes, but also must wait once that oxygen is available for a significant increase in their population for them to impact the tank environment. The nitrifier’s population kinetics can be modeled as a dual form of the Monod equation6. This lag means that the reactor management must account for an increase in dissolved oxygen levels before nitrification and not mistakenly identify the increase of dissolved oxygen to imply that all oxygen demand has been met by the aeration step. Finally, due to diffusion not only into the water, but also from heterotrophic biomass inhibiting diffusion from the water into the floc, oxygen levels must be kept at greater than 3 mg/L for nitrification whereas COD reactions require a mere 0.5 mg / L.7 6 7 Henze, et al., 1986 T.J. Casey. Version 1.0 5/11/04 Page 13 of 25 Duffany, Fountain, Julian Optimizing Nitrogen Removal in a Sequencing Batch Reactor CEE 453 The next difficulty when removing nitrogen comes in the sensitivity of nitrifying bacteria to heavy metals and synthetic organic chemicals (to a much greater extent than the heterotrophic bacteria). Some of the metals that these bacteria are sensitive to are cobalt in concentrations of less than 0.08 ppm, as well as copper and zinc, all of which are included at small concentrations in the water stream added to the reactor (reference Appendix 3: Waste Characteristics).8 Even if these concentrations are not high enough to cause acute toxicity (near instant death of a population) they may over time lead to chronic toxicity with bioaccumulation of heavy metals inhibiting nitrification. The impact of chronic toxicity depends on both concentrations in the waste water as well as the sludge retention age.9 The concept of sludge retention age is one of the most important controls on nitrification and denitrification of a waste. In order for microbial populations to reach sufficient biomass, literature shows that it is proven necessary for the sludge age in a reactor to be approximately 9-12 days.10 Sludge age is related to hydraulic retention time in that it is simply the measure of: Mass Sludge In System SRT Mass Sludge Leaving System Per Day Another difficulty in the process of nitrification arises in pH control. Nitrifying bacteria become inhibited at pH below 7, with optimal pH values of approximately 8.311 However, the nitrification reaction produces hydrogen ions, thus decreasing the pH: NH 4 2O2 NO3 2 H H 2 O In fact, if pH is to remain balanced, 7.14 mg of CaCO3 alkalinity will be destroyed per 1 mg of NH4+-N oxidized. Therefore it is important to ensure that sufficient alkalinity exists in the reactor to control pH levels. After the troubles of nitrification, denitrification seems a relatively straightforward process. Where there are only a few specialized bacteria that can act as nitrifiers, denitrifiers have a much larger possible grouping of species as discussed in the introduction. The main concern with denitrification is that most of these microorganisms are facultative denitrifiers, and thus will prefer to use oxygen if it is available. Therefore oxygen concentrations must be kept as close as possible to zero for maximum denitrification rates. To some extent this pH change can be cancelled by using a high enough aeration rate that CO2 is stripped from the solution. One of the most difficult factors of denitrification to deal with in a batch reactor is the demand of denitrifiers for organic carbon. This need is a problem since as discussed above, the oxidation of the ammonia to provide the nitrate needed for denitrification first eliminated the organic carbon from the waste. As a result, many municipal waste water treatment plants will add methanol to stimulate denitrification at concentrations of 3 kg of 8 Mogens Henze, et al. Randy Junkins, et al. 10 Halling-Sørensen, B. 11 ibid 9 Version 1.0 5/11/04 Page 14 of 25 Duffany, Fountain, Julian Optimizing Nitrogen Removal in a Sequencing Batch Reactor CEE 453 methanol: 1 kg NO3—N.12 This addition can become very expensive as well as tedious. Some wastewater treatment facilities have tried to reintroduce raw waste to later parts of the reactor to provide this carbon without incurring additional cost, but this often leads to lower quality effluent, or the need for further aeration steps. If too many cycles are used, microorganisms that have an assimilatory nitrate reduction (they reduce nitrate to ammonium for use in protein synthesis) may become a concern. Appendix 4: Academic / Industrial Designs, details some of the proposed methods for a treatment of a single waste stream (nitrate and oxygen demand treated in same process) with an activated sludge system. The Wuhrmann configuration tries to defeat the need for adding organic carbon that was discussed earlier by utilizing the death of microorganisms to provide the necessary carbon. However, this process will proceed extremely slowly as a result of low growth rates and therefore not produce substantial nitrogen removal without very long residence times. The Ludzack Ettinger configuration partially joins an anoxic tank with an aerobic tank. Mixing occurs between these two tanks providing both nitrification and denitrification in environments with plenty of organic carbon. The main problem with this tank is that the unpredictable partial mixing creates varied results with waste output and carbonaceous oxygen demand may come to dominate the aerobic tank. The modified Ludzack Ettinger process recycles mixed liquor from an aerobic environment back into an anoxic tank that is the first step in the reactor. By using an anoxic environment first there is plenty of organic carbon for denitrification to occur. However, without an initial aerobic step, there will be significant quantities of ammonia that are unaffected by the first reactor and move directly into the second reactor where they are oxidized into nitrate. The problem with this reactor setup is that with CSTR tanks, there will be significant flow that is not recycled after being oxidized, and thus nitrate will be present in the discharge at significant levels. The final process this report will examine is the Bardenpho model. This model provides nearly 100% removal of nitrate from the effluent when successfully implemented (with any CSTR process some influent will immediately become untreated effluent, so perfection is impossible with this general model type). The configuration consists of an anoxic tank followed by an aerobic tank, with another anoxic tank, and finally a reaeration tank. Mixed liquor transport occurs from the aerobic tank into the first anoxic tank. This setup excels in that it provides initial anoxic denitrification of any nitrate in the original waste water, then an aerobic step allows nitrification and the new nitrate proceeds into a tank of anoxic conditions for further denitrification. A final pass through a reaeration tank brings dissolved oxygen levels of the effluent up to acceptable standards and aids in stripping CO2 from the effluent to increase pH levels. The recycle of mixed liquor from the first aerobic tank to the first anoxic tank is also important in that 12 Water Pollution Control Federation. Task Force on Nutrient Control Version 1.0 5/11/04 Page 15 of 25 Duffany, Fountain, Julian Optimizing Nitrogen Removal in a Sequencing Batch Reactor CEE 453 it allows sufficient quantities of nitrifying bacteria to accumulate by providing longer residence times. The only real problem with the Bardenpho model is that it is very difficult to modify into a sequencing batch reactor design. The recycle of aerobic liquor to an anoxic state that contains raw waste could be attempted with “mini-cycles” of fresh effluent brought into the reactor, but at this point mass balance becomes very difficult if you want to preserve effluent quality. The intermediate anoxic state is easy in that once the first two tanks have been simulated it is simply a true sequencing batch reactor. The final reaeration step would be a simple matter of setting the ceramic diffuser for a very high airflow rate temporarily. It would be a valuable experiment to modify this process to different setups of a SBR and see what specific configuration provides the best results, and if they approach that from a true Bardenpho model. Of all possible offshoots from the research of this report this is the avenue that provides the most interest to the authors of this report and with a functional nitrate probe may have been the path they would have taken. Version 1.0 5/11/04 Page 16 of 25 Duffany, Fountain, Julian Optimizing Nitrogen Removal in a Sequencing Batch Reactor CEE 453 Appendix 1: Plant Setup Laboratory Setup Key to Laboratory Setup = 100 kPa input airline = solenoid valve controlling air entering accumulator = accumulator = solenoid valve controlling air leaving accumulator = needle valve to fine-tune airflow rate = peristaltic pump = concentrated waste/tap stock input = stirrer with 6 L tank = dissolved oxygen probe = Fisher Scientific Student Nitrate Probe = 1.2 L of activated sludge mixed with 2.8 L of tap stock Key to More Laboratory Setup = refrigerator at 5 degrees Celsius = solenoid valve to control waste leaving diluted waste bottle = solenoid valve to control entering water with metals mixture = 1 L bottle containing 1 part 100X concentrated waste and 4 parts tap water = 1 L bottle containing 100X concentrated waste Environment for Lab Setup • Wastewater Treatment Plant run at 22 degrees Celsius • Stir-bar set to the 8th setting when running Version 1.0 5/11/04 Page 17 of 25 Duffany, Fountain, Julian Optimizing Nitrogen Removal in a Sequencing Batch Reactor CEE 453 Appendix 2: Reactor Setups Click to open attached PowerPoint Presentation on Reactor Setups: Version 1.0 5/11/04 Page 18 of 25 Duffany, Fountain, Julian Optimizing Nitrogen Removal in a Sequencing Batch Reactor CEE 453 Appendix 3: Waste Characteristics Molecular Chemical Weight Concentration Compound Formula g/mol mg/L Starch 84.40 40,000 Casein 125.00 30,000 Sodium acetate C2H3O2Na3H20 136.1 31.90 Capric acid C10H20O2 172.3 11.60 Ammonium chloride NH4Cl 53.5 75.33 Potassium phosphate K2HPO4 174.2 6.90 Sodium hydroxide NaOH 40.0 175.00 Figure 1. Synthetic feed composition of the refrigerated waste stock (stock 1). Figure courtesy of CEE 453 website: “Introduction to NRP”. Molecular Chemical Weight Concentration Compound Formula g/mol mg/L Magnesium sulfate MgSO47H2O 246.5 69.60 Sodium molybdate NaMoO42H2O 241.9 0.15 Manganese sulfate MnSO4H2O 169.0 0.13 Cupric sulfate CuSO44H2O 249.7 0.08 Zinc suflate ZnSO47H2O 287.5 0.48 Calcium chloride CaCl22H2O 147.0 22.50 Iron chloride FeCl36H2O 270.3 18.33 Figure 2. Metals and their concentrations that are added to tap water for the purpose of diluting the synthetic waste (combination of stock 2 and stock 3). Figure courtesy of CEE 453 website: “Introduction to NRP”. Version 1.0 5/11/04 Page 19 of 25 Duffany, Fountain, Julian Optimizing Nitrogen Removal in a Sequencing Batch Reactor CEE 453 Appendix 4: Academic / Industrial Designs13 Ludzack-Ettinger Configuration (1962) influent anoxic aerobic Wuhrmann Configuration (1964) influent 13 aerobic anoxic Halling-Sørensen, B. Version 1.0 5/11/04 Page 20 of 25 Duffany, Fountain, Julian Optimizing Nitrogen Removal in a Sequencing Batch Reactor CEE 453 Modified Ludzack-Ettinger Process Mixed Liquor influent anoxic aerobic Bardenpho Model Mixed Liquor anoxic Version 1.0 aerobic anoxic 5/11/04 aerobic Page 21 of 25 Duffany, Fountain, Julian Optimizing Nitrogen Removal in a Sequencing Batch Reactor CEE 453 Appendix 5: Nitrate Probe Calibration water volume std concentration 100 1000 amount std (ml) test solution concentration (ppm) 10.0 20.0 35.0 50.0 1.0 2.0 3.5 5.0 ml ppm voltage (volts) 0.15 0.129 0.11 0.1 60.0 NO3- (ppm) 50.0 y = 0.0061x -3.9256 R2 = 0.9961 40.0 30.0 20.0 10.0 0.0 0.1 0.11 0.12 0.13 0.14 0.15 voltage Appendix 5: Nitrate Probe Calibration Curve for use in converting raw sensor data to nitrate concentrations. Calibrated in distilled water with a known nitrate solution at 1000 ppm. Version 1.0 5/11/04 Page 22 of 25 Duffany, Fountain, Julian Optimizing Nitrogen Removal in a Sequencing Batch Reactor CEE 453 Appendix 6: Aeration Level As experimental conditions changed throughout the course of our Nutrient Removal Project, oxygen uptake and utilization did as well. The Aeration Lab was referenced frequently to obtain the equations necessary to determine various airflow rates into our system. An example calculation to determine airflow rate is as follows: Wastewater BOD: 325 mg/L C*: 8 mg/L Wastewater Flow Rate: 16 L/day C: 2 mg/L dC ˆ k v ,l (C * C ) dt dC dt 0.015 325 eq. 1 mg L *16 mg L day 1300 4L L day mg mg kˆv ,l (6 ) Ls L eq. 3 kˆv,l 0.00251 / s Where: eq. 2 eq. 4 C* is the equilibrium dissolved oxygen concentration C is the target dissolved oxygen concentration kv,l is the overall volumetric gas transfer coefficient The kv,l value found above corresponds to an airflow rate found through interpolation of the experimental data in Figure 3 of approximately 450 μM / s. Other airflow rates can be found using the same method. A value of 1000 μM / s was used throughout our experimentation in order to provide certainty that sufficient aeration occurred to meet NOD and not merely COD. Version 1.0 5/11/04 Page 23 of 25 Duffany, Fountain, Julian Optimizing Nitrogen Removal in a Sequencing Batch Reactor CEE 453 0.012 0.01 Kvl (1/s) 0.008 0.006 Kvl 0.004 0.002 0 0 2000 4000 6000 8000 10000 flowrate ( μM/s ) Figure 3: Kvl vs Flowrate Note: Figure 3 taken from CEE 453 Aeration Lab by Matthew Fountain, Timothy Julian, and Matthew Duffany, Spring 2004 Figure 3 shows the asymptotic relationship between kv,l and the flowrate. As flowrate increases, the kv,l initially increases as more air bubbles are created. However, as flowrate increases, the air bubble size increases, thus reducing their surface area until the bubbles eventually resemble a column of air that is the upper limit of surface area. Because kv,l is a function of interfacial surface area, kv,l must also have an upper limit. This relationship of bubble diameter to flow rate helps to explain the asymptotic nature of the graph. Version 1.0 5/11/04 Page 24 of 25 Duffany, Fountain, Julian Optimizing Nitrogen Removal in a Sequencing Batch Reactor CEE 453 Works Cited: Task Force on Nutrient Control under the direction of the Municipal Subcommittee of the Technical Practice Committee, Biological and chemical systems for nutrient removal Alexandria, VA : Water Environment Federation, 1997. B. Halling-Sørensen and S.E. Jørgensen, The removal of nitrogen compounds from wastewater, Amsterdam ; New York : Elsevier, 1993. Clair N. Sawyer, Harry E. Wild, Jr. and Thomas C. McMahon, representing Metcalf & Eddy, inc. Nitrification and denitrification facilities: wastewater treatment. Washington] Environmental Protection Agency, Technology Transfer, 1973 [i.e. 1974] Task Force on Nutrient Control ; Orris E. Albertson, chairman. Nutrient control Washington, D.C. : Water Pollution Control Federation, 1983 John Roberts, Bubble aeration and an assessment of biochemical reactor performance. New Castle, Australia : University of New Castle, [Dept. of Chemical Engineering], 1978. Poduska, Richard Alan, Nitrogen removal from wastewaters by combining controlled activated sludge nitrification and anaerobic filter denitrification. [Ithaca, N.Y.] 1969 Harman David Stensel, Biological kinetics of the suspended growth denitrification process, [Ithaca, N.Y.] 1971. T.J. Casey, Unit treatment processes in water and wastewater engineering Chichester ; New York : Wiley, c1997. Randy Junkins, Kevin Deeny, Thomas Eckhoff, The activated sludge process : fundamentals of operation, Boston : Butterworth, c1983. Mogens Henze ... [et al.], Wastewater treatment : biological and chemical processes, Berlin ; New York : Springer, c2002. Version 1.0 5/11/04 Page 25 of 25