KING FAHAD UNIVERSITY OF PETROLEUM & MINERALS College of Environmental Design Department of Construction Engineering & Management Master of Engineering Report (CEM-600) Business Process Improvement Case Study at Saudi Electricity Company – Eastern Region Branch "Maintain Support Facilities" For DR. ABDULAZIZ A. BUBSHAIT By Yaser Sulaiman. Al-Jughaiman January, 2004 i TABLE OF CONTENTS CHAPTER 1 ----------------------------------------------- 01 Introduction: ----------------------------------------- 01 1.1 Backgrounds ------------------------------------ 01 1.2 Saudi Electricity Company – Eastern Region Branch ----- 02 1.3 Objectives ------------------------------------- 03 1.4 Report Overview -------------------------------- 04 1.5 Scope Limitation -------------------------------- 04 1.6 Support Services Organization Chart ---------------- 05 CHAPTER 2 ---------------------------------------------- 07 Literature Review -------------------------------------- 07 2.1 Introduction ------------------------------------ 07 2.2 History ---------------------------------------- 08 2.3 Improvement Process Differentiation ---------------- 10 2.4 Relation Between BPR and Information Technology ----- 13 2.5 Davenport and Short BPR Methodology --------------- 15 2.6 Human Resource Factor --------------------------- 16 2.7 Business Process Out Sourcing of Business ------------ 16 2.8 BPR in Small Organization ------------------------- 17 2.9 The Total Plant Paradigm ------------------------- 21 2.10 Why BPI and BPR Projects Fail --------------------- 24 ii CHAPTER 3 ---------------------------------------------- 26 MAINTAIN SUPPORT FACILITY CASE STUDY-------------- 26 3.1 Introduction ------------------------------------ 26 3.2 Why Project Been Selected ----------------------- 28 3.3 Start-up and Preparation Phase -------------------- 32 3.3.1-Selecting a Major Process for BPI ------------- 32 3.3.2-Conducting Interviews ----------------------- 33 3.3.3-Building a Process Model --------------------- 34 3.3.4-Identify Process Boundaries ------------------ 35 3.3.5-Interview the Key People -------------------- 39 3.3.6-Selecting BPI Team Member ----------------- 39 3.3.7- Creating Project Charter -------------------- 40 I. Mission ---------------------------- 41 II. Scope of the Project ----------------- 41 III. Goals and Objectives ----------------- 41 IV. Deliverables ------------------------ 42 V. Roles and Responsibilities -------------- 44 VI. Project Milestone -------------------- 46 VII. Assumption and Risk ------------------ 47 3.3.8-Developing Detailed Work Plan ---------------- 48 3.3.9-Provided Team Over Review and Kick-off Project 48 iii 3.4 3.5 3.6 Current State Phase ----------------------------- 49 3.4.1-Introduction ------------------------------ 49 3.4.2-Process Mapping and Value Analysis ------------ 50 3.4.3-Collecting Detailed Sub-Process Date ---------- 56 3.4.4-Conducting Customer Surveys ----------------- 65 3.4.5-Root Cause Analysis ------------------------ 70 3.4.6-Leading Practices and Site Visits -------------- 77 Future State Phase ------------------------------ 82 3.5.1-Introduction ------------------------------ 82 3.5.2-Conducting Future State Workshops ----------- 84 3.5.3-Creating the Future State Redesign ------------ 90 3.5.4-Develop Business Case for Each Change Recommendation --------------------------- 94 3.5.5-Developing Implementation Plan for each Change Recommendation --------------------------- 100 Implementation Plan Phase ------------------------ 103 3.6.1-Introduction ------------------------------ 103 3.6.2-Mobilizing for Implementation ---------------- 103 3.6.3-Developing Charters and Work Plans ----------- 104 3.6.4-Monitoring and Managing the Status ----------- 105 3.6.5-Measuring Find Results of Implementation ------- 105 iv CHAPTER 4 ---------------------------------------------- 107 Recommendation Improvements Analysis -------------------- 107 4.1 Introduction ------------------------------------ 107 4.1.1-Recommendation Analysis -------------------- 107 Recommendation 1 Utilize Unit Rate Contract ------------------------ 111 Recommendation 2 Maintenance Web Page --------------------------- 121 Recommendation 3 Maintenance Call Center -------------------------- 125 Recommendation 4 Electronic Equipment Repair Shop ------------------- 127 Recommendation 5 Maintenance Free Materials ----------------------- 131 Recommendation 6 Service Level Agreement & Chargeback -------------- 133 Recommendation 7 Predictive Based Maintenance ---------------------- 137 Recommendation 8 Hand Held Data Input Devices --------------------- 139 Recommendation 9 Make CMMS the Standard Database ---------------- 141 Recommendation 10 Improve P.C. Repair and Support Network ------------ 143 CHAPTER 5 ---------------------------------------------- 148 5.1 Introduction -----------------------------------v 148 5.2 Summary of the Project and Conclusion -------------- 148 5.3 Recommendations -------------------------------- 150 References --------------------------------------- vi 153 CONTENTS OF TABLES, FIGURES, AND CHARTS FIGURE 1 SEC Organization Chart ------------------------------- 06 2 Different Improvement Models -------------------------- 11 3 BPI Process Flow ------------------------------------- 27 4 Sub-Process Model ----------------------------------- 35 5 Activities into the Major Process ------------------------ 37 6 Process into the Major Process -------------------------- 38 7 Sub-Process 3 Process Map ---------------------------- 54 8 Sub-Process 5 Process Map ---------------------------- 55 9 Sub-Process 3 Cycle Time ------------------------------ 59 10 NAOSD Department FTE ------------------------------ 62 11 NAOSD Department FTE ------------------------------ 64 12 Sub-Process 3 Root Course Analysis ---------------------- 73 13 Project Implementation Mobilization ---------------------- 102 14 Summary of Costs and Benefits “Utilize Unit Rate Contract” -- 113 1 Comparing TQM with BPR ------------------------------ 11 2 Comparing TQM with BPI ------------------------------ 12 3 Major Macro, and Mega Process at SEC ------------------ 28 4 Project Milestone ------------------------------------- 47 TABLE vii 5 Process Data ---------------------------------------- 57 6 Issues and Improvement Identified by the Customers & the Team ---------------------------------------------- 67 7 Future State Workshop -------------------------------- 86 8 Recommendation #1 “Utilize Unit Rate Contract” ----------- 111 9 Summary of the Benefits “Utilize Unit Rate Contract” ------- 112 10 Cost Worksheet “Utilize Unit Rate Contract” --------------- 114 11 Benefit Worksheet “Utilize Unit Rate Contract” ------------ 115 12 Hard Cost/Benefits – All Figures SRs “Utilize Unit Rate Contracts” ------------------------------------------ 116 117 13 Soft Cost/Benefits – All Figures SRs “Utilize Unit Rate Contracts” ------------------------------------------ 14 Recommendation #2 “Maintenance Web Page” -------------- 121 15 Summary of the Benefits “Maintenance Web Page” ---------- 123 16 Recommendation #3 “Maintenance Call Center” ------------- 125 17 Summary of the Benefits “Maintenance Call Center” --------- 126 18 Recommendation #4 “Electronic Equipment Repair Shops” ----- 127 19 Summary of the Benefits “Repair Shops for all Electronic Equipment” ------------------------------------------ 129 20 Recommendation #5 “Maintenance Free Materials” ---------- 131 21 Summary of the Benefits “Maintenance Free Materials” ------ 132 22 Recommendation #6 “Service Level Agreement & Chargeback” - 133 23 Summary of the Benefits “Service Level Agreement & chargeback” ----------------------------------------- 135 viii 24 Recommendation #7 “Predictive Based Maintenance” --------- 137 25 Summary of the Benefits “Predictive Based Maintenance” ----- 138 26 Recommendation #8 “Hand Held Data Input Devices” -------- 139 27 Summary of the Benefits “Hand Held Data Input Devices” ---- 140 28 Recommendation #9 “Make CMMS the Standard Database” --- 141 29 Summary of the Benefits “Make CMMS the Standard Database” ------------------------------------------ 142 30 Recommendation #10 “Improve P.C. Repair & Support Network” 143 31 Summary of the Benefits “Improve P.C. Repair & Support Network” ------------------------------------------- 144 32 Recommendation #11 “Improve Material Delivery” ----------- 145 33 Summary of the Benefits “Improve Material Delivery” ------- 147 CHART 1 Sub Process 3 Root Cause Analysis ----------------------- 77 2 Implementation Plan “Unit Rate Contracts” ---------------- 119 ix CHAPTER 1 INTRODUCTION 1.1 BACKGROUNDS: Process improvement is not a new concept, although many businesses are now implementing process improvement in order to enhance the effectiveness and efficiency of the business. It was done without intention and not as per the formalities and rules established now. It is widely used term start in the early 1990’s and because so popular for all business seeking for improvements. Hence, since the early 1990’s, Saudi Electricity Company, Eastern Region Branch (SEC-ERB) started gathering information on Total Quality Management (TQM) Philosophies. They signed an agreement with Florida Power Corporation who had successfully implemented TQM and Business Process Improvement (BPI) to assist SEC-ERB in the implementation here. On Corporation November made 1993, presentation representatives to SEC-ERB from Florida Executive Power Management (ERMC) on TQM. ERMC decided to start the implementation of TQM from 1994, though 1996. Florida helped in the implementation of TQM paves the way to prepare to implement Business Process Improvement. Employees of SEC-ERB began discovering what customer needs from 1 them and finding ways of doing their jobs better, faster, and more cost efficiencies. Later SEC-ERB decided to make a much bigger step to provide more substantial change in the way business is conducted by focusing in major business process that cut across the functional corporate structure.(9) In December 1996, ERMC decided to the first step in preparing to implement (BPI). Similarly, the representatives from Florida Power Corporation were invited back to assist SEC-ERB in developing a Business Process model for the Company. The effort identified 446 products and services at the Departmental level. From this list, 70 major business processes, 23 macro processes and 8 mega processes were identified. BPI looks toward improving the 70 major business products that were identified by the Company. A contract was signed with Ernst and Young as a Consultant in the implementation of BPI and first teams were formed in August 1997.The following section gives some background about SEC-ERB. 1.2 Saudi Electricity Company – Eastern Region Branch (SEC-ERB) (12) Saudi Electricity Company was established recently on H1420/09/06 after merging all Electricity Companies in the kingdom and the Company started this business on April 5, 2000. 2 On August 23, 1976 Saudi Consolidated Electricity Company in the Eastern Province was established by joining the small companies in the Eastern Province on in Company. From the Saudi electricity Company annual report, after merging of all electricity companies in the kingdom, the following are the main figure of the Company: Total customers = 3,792,210 Customers Total Generation Capacity = 26,326 MW Maximum Demand Generated = 23,582 MW Total Sold Power = 122,944 GWH Company Capital = 38,287,770,900 Riyal 1.3 Objectives: The objective of this research is to present and summarize the findings of a study carried by the SEC-ERB to improve the "Maintain Support Facilities. The objective will be achieved by reviewing the sequence of step and methods which are implemented and developed in BPI the four phases discussed later (Preparation and Start up, Current State, future State, and Implementation phase). 3 1.4 Report Overview: Report contains mainly three sections: the introduction, the literature, and summary of the BPI report findings carried to improve “Maintain Support Facilities”. The summary section is subdivided and contains the start up and preparation phase, the current state phase, the future state phase and the implementation phase. Separate section for the future state results would be under the recommendation analysis. The start up and preparation show the process from the selection of the subject major process improvement until the kick-off of the project. The current state phase analysis the current situation, while the future state try to find better solutions for improvement after evaluating the findings in the current state. Then, what is the sequence of steps for the implementation phase will be summarized. Finally, the final and approved recommendation by ERMC will be summarized and analyzed. 1.5 Scope Limitation: Even though the research will summarize the BPI phase discussed earlier, the report contains too much and too lengthy details. As a result it was decided to concentrate on one of the sub-processes and to show its related findings only Sub-Process 3 “ Performance Corrective 4 Maintenance “ was selected to be analysed more. This was because it is the heart of the process and became it is usually is associated with the most of the expenditure and it also require most of the resources and it can also affect all the other sub-processes. 1.6 Support Services Organization Chart: The organization chart explains the definition of SEC-ERB support services functions. Even though, in the BPI if other Department other than support services department provide a similar service of the support services it will join the project boundaries and it will be also studied such as the power plants. They are doing them self's the function of support services also Media Department are repairing media equipment. 5 Figure 1: SEC Organization Chart PRESIDENT GENERATION EVP TRANSMISSION EVP INDUSTRIAL SECURITY _ VP FACLITYSUPPPORT – MGR . AREA BUILDING FACILITY SERVICES – SH DIST.CUST SER. EVP GEN. SER. SVP FINANANCE EVP MANAGER PLANNING & BUSINESS COORDINATOR IT & C-VP REAL ESTATE – MGR. HUMAN RESOURCES SVP TECHNICAL SUPPORT – MGR JOAF A.F.M.D. – MGR . . PUB. SHAREHOLDER SVP LEGAL AFFAIR SVP FM-VP FMD – MGR - EAST NORTH A.F.M.D. – MGR . Planning & PROGRAMME SVP INTERNAL AUDITING SVP MATERIAL SUPPLY-VP TRANSPORTATION. VP FMD – MGR. - CENTRAL HASSA A.F.M.D. – MGR. FMD – MGR. - WEST FMD – MGR. - SOUTH . DAMMAM A.F.M.D. – MGR SUPT. & STAFF . GSU – SUP DH & KH -FOREMAN D&Q U - FOREMAN A/C & ELECT - FOREMAN FM UNIT - FOREMAN 6 . SECTI & PP – SEC, ASST. SUPT . GSU & REC.SUP CHAPTER 2 Literature Review 2.1 Introduction Today most business, manufacturing or commercial engineers are considering the changes developed in process improvement techniques. This due of the vast changes developed in the business competition all over the world and specially with the up coming world trade organization coming in business, it becomes vital to all companies to review its strategies and to measure how effective they are. The concept of Business Process Reengineering and Improvement in a new concept started only in early 1990's, however trying to business or trying to discover the cause of un-effective organization stream work or trying to improve the work streamline happened with the start of the establishment of businesses. The rapid Information technology is a key factor affecting many organizations to be more effective. The customer is another key factor to study improving the business since with open world markets; he has many choices and opinion to select. 7 2.2 History Earlier two terms were introduced, one is Total Quality Management and the other is Business Process Improvement and its history especially at SEC-ERB. There are other improvement process such as Business Process Reengineering which was first appeared in 1990 by Michael Hammer(14) in his paper published in the Harvard Business Review called “Re- engineering Work: Don’t automate, obliterate”. He was a former MIT professor and information technology specialist. The issue of BPR includes organizational redesign, process reorganization, and the use of information technology. Hammer and Champy(15) define process re-engineering as “the fundamental rethinking and radical redesign of business processes to achieve dramatic improvements in critical contemporary measures of performance, such as cost, quality, service, and speed…reengineering isn’t about fixing anything…re-engineering a Company means tossing aside old systems and starting over…re-engineering can’t be carried out in small and cautions steps. It is an all-or-nothing proposition…tradition counts for nothing. Hammer also defines BPR as the starting from the very basic issues, reformation of 8 the reengineering process will dramatically improve an organization in terms of its cost, quality, service and speed (14). Re-engineering is a new beginning.” Others also studied BPR Literature (FUglesth and Gronhaug 1997). Caron et. al. (1994)(16) also examined BPR in depth. They offered a set of general guidelines but they failed to mention the importance of systematic methodology. Davenport and Stoddard (1994) also addressed various ideas and studies associated with BPR based on detailed case study analysis of many companies. Duck (1993)(17) considers the adequate management of change to be fundamental in any successful re-engineering project. Management of change involves communicating with the affected by changes, and being aware of the effect of change on the company as a whole. Cyprus says(18) in 1994 that the identification of critical business process is one of the most crucial factors affecting the success or failure of BPR. Davenport & Short (1990)(19) defines business process as "a set of logically related tasks performed to achieve a defined business outcome". And the process is a structured measured set of activities designed to produce a specified output for a particular customer or market. So, processes have two organization that serve them. 9 characteristics: customers and 2.3Improvement Process Differentiation: There are many improvements method, which can be compared, most famous are Total quality Management (TQM), Business Process Improvement (BPI), Business Process Re-engineering (BPR) and Business Process Innovation. TQM usually is a used term for improving small process affecting one or two Departments. BPI looks for incremental step by step continuous improvement to the existing process which usually involves many Departments in many areas which will cross further between organization chart. In the BPR it seeks radical change through designing whole new processes since some process may not be able to improve, hence, a redesign of the whole process from scratch is needed. It is normally deals with Mega process. Where process re-engineering throws everything out and start fresh, process improvement tries to analyze and standardize get every one consistently using the agreed upon procedure and make the process reliable and improve upon the existing procedures. The last term use here is the Business Process Innovation, which deals with some processes that don’t exist so it must be created using the 10 Business Process Innovation and the following figure explains the differences: Figure 2: Different Improvement Models TQM Business Process Re-Engineering BPI Small Processes (9) Business Process Innovation New Process Large Business Processes Streamline the Existing Process Replace Processes Create Processes New Activities Reduce NVA and Improve VA Activities Meet Customer Expectations Many Small Improvements Exceed Customer Expectations Major Improvements Strategic Changes Hence, BPI is in between TQM and BPR. From table 2 it is obvious that TQM is a continuous process but BPR is a one time and since it is cross functional it will affect many areas and departments. So, major differences between TQM and BPR are also listed in the following table: Table 1: Comparing TQM with BPR (10) TQM BPR Level of Change Incremental Radical Start From Existing Process Clean Slate Frequency One-Time/Continuous One-Time Time Required Short Long Participation Bottom-up Top-Down Typical Scope Narrow (within) Cross-functional Risk Moderate High Primary Enabler Statistical Control I.T. Type of Change Cultural Cultural Structural 11 Another table, which can also illustrate the differences between TQM and BPI, similarly, as in the previous table BPI will affect many departments and areas but usually it will not replace major processes. Major differences are in the following table: Table 2: Comparing TQM with BPI ( 9 ) TQM BPI Departmental processes/limited crossfunctional involvement. Major, corporate cross-functional business processes. Many teams functioning at the same time. 2-4 teams functioning at a given time. One hour a week. Full time assignment for 4 months. No computer software necessary. Extensive Database, Spreadsheets & Graphical software experience needed. Modest savings per project. Tactical improvements. Small changes, little stress on organization. Strategic improvements. Large changes, significant stress on org. Quick implementation of improvement. Internal focus for improvement. Improvement of improvements may require years. Improvement is within capability of the Department. Focuses on practices of other Companies. Improvements often require increased Information Technology. 12 2.4 Relation Between BPR and Information Technology Since Hammer himself who is the first references in BPR phenomenon nd a former MIT professor and information technology, he (14) considers IT as the key factor for radical change. He believed that the IT technology is the one to challenge the assumption and believes inherent in the work processes which existed since long before the vast development of modern Computers and Communication technology. Other, such as the IT – economist Paul Strassmann (20) , concluded that there is no relationship whatsoever between Computer expenditure and company performance. Also, Xerox director, Seely Brown(11) , observed that despite investments of over One trillion dollars in technology over two decades, U.S. industry had realized little improvement in the efficiency of its knowledge workers. Devenport & Short(19) argue that BPR requires taking a broader view of both the IT and business activity, and of the relationship between them. IT should be view not only an automating force but fundamentally reshape the way business is done. The development of many systems developed by BPR – Vendors such as SAP or Oracle were expected to provide sharing of data across various business functions. These systems were based on top-down model information strategy implementation and execution, and primarily focused on coordination of companies internal functions. When such systems were 13 implemented in big companies like ARAMCO it streamline some process activities and opened the door widely for process reengineering to be successful. The evolution of the information processing paradigm(11) generally progressed over three phases over the last four decades which changed the business functions and processes are:- 1. Automation : increased efficiency of operations 2. Rationalization of procedures: streamlining of procedures and eliminating obvious bottle necks that are reveled by automation for enhanced efficiency of operations. 3. Re-engineering: radical redesign of business processes that depends upon information technology intensive radical redesign of work flows and work processes. The role of IT is generally that of an enabler rather that a leader of a reengineering effort. Furey, Garlitz & Khelleher (1993) (21) found that the success of the subsequent reengineering was far more dependent on other factors such as management leadership, clear vision, and change management eventhough most reengineering efforts were initiated by the identification of an IT opportunity,. The process owners are encouraged to take the leading role instead of 14 those in charge of IT, as the process owners will have a more complete knowledge of the processes under scrutiny. 2.5 Davenport and Short BPR Methodology: Malhotra, Yogesh in his article " Business Process Redesign : An Overview"(10) he prescribed Davenport Short(19) and five step methodology approach to conduct BPR: First, is to develop the Business Vision and Process objectives such as Cost Reduction, Time Reduction, and output quality improvement. Second, is to identify the processes to be redesigned. Most firms use something called the high impact approach which focuses on the most important processes or those that conflict most with the business vision. Lesser number of firms uses the Exhaustive approach that attempts to identify all the processes within an organization and then prioritize them in order of redesign urgency such as what exists at SEC-ERB as it will be discussed later. Third, understand and measure the existing processes to avoid repeating same mistakes and for providing a baseline for future improvements. Fourth, to identify IT Levers by the awareness of IT capabilities what it can do to influence process design. Last, to design and build a prototype of the new process, the actual design should not be viewed as the end of the BPR process. Rather, it should be viewed as a prototype, with successive iterations. 15 2.6 Human Resources Factor To ensure reengineering of large, complex and also small businesses the employee participation is a key factor for the success or failure of the redesign. There would be a key element in the successful reengineering of especially in large organization. Designed training for human resources support the transition in concert with reengineering management, organizational development, Labor relations and external Consultants. Two steps factor (2) are important in order to fully utilize the human resources effectively. First, is extensive communications by opening meetings for all employees continuously, distributing newsletter to all employees and providing constant updates to reduce the hostility by employees because they could have a sense that their job security or job benefits would be affected. Second, step to successfully managing change is the role of carefully training programs that support the development of streamlined reengineering. Each step has to be done patiently and carefully in order to get employees support and to build knowledge. 2.7 Business Process Outsourcing Instead of Business Process Improvement or Reengineering Business process outsourcing is an act of an organization to transfer the burden of doing an activity or activities to another organization 16 to do instead of them. There are growing a number of companies considering business process outsourcing because of two major factors (7) . First, is the desire of many companies to leave non-core activities to specialist firms that can provide world-class performance in delivering these activities and to focus on core business processes. Second, since BPO firms are specialized, this gives them a significant value proposition. This can include specialized expertise; economies of scale; leverage from investment in high-value processing technologies; the ability practices to and reengineer business meet world-class processes to standards; and incorporate lower costs best from operating selected activities at lower-cost location. It is clear that the use of BPO will grow, and that more supply chain management processes will be considered for outsourcing although business process outsourcing might not be right for all companies. 2.8 BPR in Small Organizations: Although there is no universal methodology for business process reengineering, a number of common components exist within the growing body of literature on BPR. However, that literature is based on 17 experience in larger firms and little has been written for the small firm attempting to gain similar radical gains in performance which have been attributed to successful BPR. In small firms, organizational structure is typically informal, but highly centralized, which provides strength in decision-making and rapid implementation of decisions. This also enables more rapid implementation of change in the organization. Furthermore, it has been empirically confirmed that small businesses differ from large organizations in other matters such as maturity and environmental uncertainty. This indicates that a different set of considerations may be important for BPR in smaller firms. Hammer & Champy(22) provide the only recommendations on attempting BPR especially for the small business. They define the purpose of reengineering as organizing the company so it can best create value for its customers. The emphasis is on the customer and results rather than tasks and procedures. Hammer claims any company can adhere to the principles of reengineering regardless of size. Hammer & Champy recommend keeping the focus on processes and continue improving those processes. 18 On the other hand, Barrier(23) takes the simple meaning of BPR, (i.e. putting the business through radical change), and claims that it is applicable to small businesses as well. Methodology Outlined for Small Firms(4) are as follows: The identification of critical processes within the small firm. The use of IT as a lever for reengineering, and the role played by IT in the project as a whole, The identification of a vision and objectives for the reengineering project, and the degree of planning for BPR conducted, The existence of executive commitment and organizational involvement, the initial motivation for reengineering, and the treatment of those directly affected by any major changes. Again IT was considered as a lever for reengineering, as different ways of harnessing the benefits available from IT were investigated and utilized where possible. IT now plays a significant part in their reengineering process and provides considerable improvements to the firm. As an example, extensive use of email provided improved information flows within the business. Management just looked at the company's long term mission statement, and formulated their plan from that, hence , there was no development of process objectives during the 19 planning for BPR unlike their in complex or large organizations. The role restructuring did not include an initial definition stage, whenever the processes as they existed at that time were analyzed, documented and measured before going ahead with the planned reengineering. This step is important since the effects of the project can not be determined with great certainty, even after implementation, as the situation prior to reengineering was not known. The success appears to be largely attributable to the high level of management support of the project. Their extensive involvement and concern in ensuring that the employees gain a feeling of ownership of the processes that they are responsible for is highly recommended in the literature. Overall, the steps and principles adopted show a high similarity to the recommendations made in the literature. Most likely the reengineering is proven to be extremely beneficial for small firms. But this conclusions can not be generalized to all small firms without further investigation, they indicate little difference in the requirements for small and large firms for successful reengineering of their processes. So, this could be a subject for further study. 20 2.9 The TotalPlant Paradigm TotalPlant is a program called by Honeywell on the industrial automation and control (IAC) which designs, manufactures, and configures the sophisticated control panel called TDC 3000X family of systems (3) . The mission of TotalPlant is to Unify Business and control information to enable global customer satisfaction. The paradigm is based on four principles (3) of success: Process Mapping, Fail-Safing, Team works and Communication. Each principle is critical, so, every team member must be educated in all four major of the principles and the major obstacle to change. This is done to change the employee attitude of things are ok, so why to change. The four paradigm principles are : (a) Process mapping which is tool that allows one model the flow of any business process in a graphical form. This principle consists of eight steps. The first step is to select the process. The second step is to identify the boundary and the third step is to make sure that the team has cross-functional representation from each organization contributing to the process. The fourth step is to develop the "as is" map represents the transformation of inputs into finished products. The fifth step is to identify the cycle time for each step in the process and the sixth step is to identify 21 opportunities for improvement that would not add resources (extra costs). The seventh step is to develop the "should be" map. This map includes a "picture" of the improved processes and projections of their new cycle times. Last step is to develop the process implementation plan, establish confirmation, and implement. (b) Fail-Safing: Fail-safing is a method to identify a defect, analyze it to understand its root cause, and to develop a solution that will prevent that defect from occurring again. Also, there are eight steps in conducting this principle. The first step is to identify the problem (defect) and the second step is to identify the root cause(s) of the problem. The third step is to generate alternative solutions. The fourth step is to evaluate and choose a solution. The fifth step is an implementation plan is created. Step six (Do) is to implement the chosen solution. Step seven (Check) involves checking results. Step eight (Act) is to determine the next steps for continuous improvement. 22 (c) Teamwork To familiarize people (including managers) with what teams are, how they work, and how they will help the company, it takes special effort management support, training, and a nurturing environment to make it work and special training is needed. After training, workers need to "feel" that the work environment is conducive to teams. Creativity, risk taking and innovation are encouraged and viewed as learning experience. People are trusted, respected and empowered to execute their duties. People are not predictable, naturally resist change, and are diverse which become the biggest challenge in dealing with change . People can be trained to effectively map processes and fail-safe defects in a short time. However, getting a diverse workforce to work as a team takes time. The key is the environment. (d) Effective Communication Skills Communication of the TotalPlant vision is key factor in to success. Lack of effective communication is the number one problem in most organizations. Communication of a vision is especially susceptible to conflict because its message is broad and its audience is the enterprise. So, Honeywell provides 23 conflict resolution training to teams to help them deal with conflict in a positive way. One training module concentrates on listening skills. Another module focuses on confronting skills. The key is to develop conflict resolution skills that recognize this tendency and practice these skills in a non-threatening environment until a certain level of mastery is reached. What separates success from failure is execution. Hence, substantial training resources to educate the workforce about the four mechanisms and how they work by top management to be willing to dedicated to the project. Management, behaviors have to change from autocratic to facilitative. Teams have to be rewarded for enterprise value-added activities. Finally, the organizational structure has to change to allow an environment conducive to innovation. 2.10 Why BPI and BPR Projects Fail? Seventy percent of the BPR projects fail because of three main reasons. First, is the lack of sustained management commitment and leadership. Second, is the unrealistic scope and expectations and finally resistance to change. King (1994)(24) views the primary reason of BPR failure as overemphasis on the tactical aspects and the strategic 24 dimensions being compromised. He noted that the process being viewed and applied rather than strategic levels are the most failures reasons of re-engineering. He discusses that there are important strategic dimensions to BPR, notably, developing and prioritizing objectives, defining the process structure and assumptions, identifying trade-offs between processes, identifying new product and market opportunities, coordinating the re-engineering effort, and developing a human resources strategy. He concludes that two things can be the ultimate keys BPR success factors. First, depends on the people who do it and on how well they can be motivated to be creative and to apply their detailed knowledge to the redesign business processes. 25 CHAPTER 3 MAINTAIN SUPPORT FACILITY CASE STUDY 3.1 Introduction: BPI team follows a four phase’s approach strategy with the starts up and preparation phase in the begining. This phase is follows by a current state analysis of the process. Future state design is next, and the methodology ends up with the implementation phases. The last phase since it under implementation up to now. No available information is ready. However, the monitoring and follow up of the implementation phase will be presented, as explained in Figure 3. 26 Figure 3: PBI Process Flow START UP & PREPARATION PHASE CURRENT STATE PHASE FUTURE STATE DESIGN IMPLEMENTATION Selecting a Major Process for BPI Introduction Introduction Introduction Conducting Interview Process Mapping and Value Analysis Conducting Future State Workshops Mobilizing for Implementation Building a Process Model Collecting Detailed Sub-Process Date Creating the Future State Redesign Developing Charters and Work plans Identify Process Boundaries Conducting Customer Surveys Develop Business Case for Each Change Recommendations Monitoring and Managing the Status Interview the Key People Root Cause Analysis Developing Implementation Plan for Each Change Recommendation Measuring find results of implementation Selecting BPI Team & Member Leading Practices and Site Visits Creating Project Charter Developing Detailed Work Plan Providing Team w/ Overview & Kick-Off Project 27 3.2 Why Project been Selected: As stated earlier 70 major business process has been identified, among them 70 BPI project been selected. The following are the 70 major business process: Table 3: Major Macro, and Mega Process at SEC No MAJOR PROCESSES 1 Forecast Energy Demand and Fuel Consumption 2 Plan Future Electrical System (P/P, S/S, Transmission) 3 Plan Distribution Network 4 Plan Support Facilities and Communications Facilities 5 6 MACRO PROCESSES B 7 8 Engineer and Design Power Plants 10 11 12 13 14 15 Plan Electrical System and Support Facilities. I Plan for the future. Prepare and Monitor Operating Plans, Business Plans, and Their Accountability Reports Prepare and Monitor Capital Plans/Budget and Their Accountability Reports and Close Outs Develop and Monitor Engineering, Design, Construction, and Materials Standards 9 A MEGA PROCESSES Engineer and Design TransmissionSubstations & Transmission Lines Engineer and Design Distribution Facilities Engineer and Design Support Facilities Engineer and Design Communications System Prepare & Monitor Budgets & Plans. Engineer & Design C Electrical System & Facilities. II Construct Power Plants Commission Power Plants / Generation Facilities Construct & Commission Transmission-Substations & Transmission Lines D 28 Construct Electrical System and Facilities. Design, modify and construct facilities. 16 17 18 19 20 Construct & Commission Distribution Facilities Construct/Modify & Commission Support Facilities and Communications Facilities Operate Power Plant/Generation Facilities Maintain Power Plant/Generation Facilities Plan and Perform P/P Overhaul/Major Modification activities (T&I) 21 Schedule, Monitor, Operate and Control Electric System 22 Maintain Transmission Substations 23 Maintain Transmission Lines 24 Operate Distribution Network 25 Maintain Distribution Facilities 26 27 28 29 30 31 32 33 34 Operate & Maintain E Power Generation Facilities. III Generate Electric power. Operate and Maintain F Substation and Transmission. G Provide Power Supply to New/Existing Customers Bill Customers and Handle Customer Billing Inquiries Manage Demand and Conserve Energy Operate & Maintain Distribution Deliver electric IV power and serve customers. H Provide Customer Service. Collect Payments From Customers, Provide Disconnection/Reconnection Services and Handle Related Inquiries Recruit and Place Trainees, Employees, and Consultants Provide Organizational Services (incl. Org. Charts, Job Descriptions, Manpower Utilization) I Staff the Business. Administer Labor Relations Matters Provide Employee Training, Education and Career Development Provide Training Facilities & Equipment 35 Administer Employee Benefits, Travel and Lodging Services, and Personnel Matters (Including Contractors) 36 Provide Medical Services 37 Provide Services Related to Cash, Investment and Insurance 38 Provide Shareholders Services 29 J Provide Training and Development K Provide Compensations and Benefits. L Provide Treasury Services. Provide Human V Resources Management. VI Provide Financial Management. 39 Provide Accounting Services 40 Provide Disbursement Services (Invoice Processing/Payment) 41 Administer Payroll 42 Operate Communications System 43 Maintain Communications System 44 45 46 47 48 49 50 51 52 53 54 55 M Provide Comptroller Services. N Provide Communication Services. Plan, Install and Support IT Infrastructure Evaluate/Develop, Maintain/Modify Software Operate Central Computer System (Mainframe) O Provide Information Technology. Prepare, Review and Issue Various Reports (Internal and External) Communicate Company Information/Activities Internally and Externally P Provide Reports and Communications. Q Maintain & Retrieve Information. Retain and Store Records (Paper & Electronic) Provide Information Center/Library Services VI Provide Information I and Communication. Create & Maintain Drawings & Maps Procure Equipment, Materials and Services Store, Control and Issue Medicines, Materials, Tools and Equipment Reclaim Provide Material (Test/Repair/Refurbish/Rework/Man R Services. ufacture) Material, Equipment and Tools Write-off and Dispose-off Excess/Obsolete/Used Materials and Equipment 56 Maintain Support Facilities 57 Provide Office Services 58 Provide Security Services 59 Provide Safety Management 60 Prequalify/Register Vendors/Manufacturers/Contractors 61 Procure Contracts 62 Administer and Manage Contracts 63 Provide Real Estate Services Including Right-of-Way (ROW) 64 Provide Legal Services 65 Provide Auditing Services 30 S Provide Facilities Maintenance & Office. T Provide a Safe Workplace. U Provide Contract Services. V Provide Corporate Support Services. VI Support Business II Activities. 66 Formulate and Administer Procedures, Instructions and Perform Industrial Engineering Services 67 Formulate & Administer Policies 68 Acquire and Assign Transport Fleet 69 Operate Vehicles and Equipment (Including U Drive, Bus Services & Gas/Fuel Services and Supply Water) 70 Maintain Vehicles and Equipment W Provide Transportation Services. The selection of the BPI project to be studied depends mainly on the following: 1. Strategic Impact: Is the process critical to the Company long-term strategic goals. 2. External Customers Impact: Does it affect them directly. 3. Total Resources Consumption: What are the annual expenditure and its percentage to the Company overall budget. Note that a major process is not selected because it is performing badly and needs improvement. Hence, SEC-ERB management at this stage after considering these factors and after evaluation of the importance of the major process and the customers satisfaction SEC-ERB decided its is the time to study “Maintain Support Facilities”. 31 3.3 Start-up and Preparation Phase: There are mainly nine steps in the phase of start up and preparation. Each step will be explained and the results. This phase starts by selecting a major process for BPI to be studied followed by conducting interviews. Then, building a process model and identifying the process boundaries. Fifth step, interviewing the key people followed by the selection of the team members. Creating a process charter is the seventh step, then, developing detailed work plan. Then finally, providing the team with overview and kick-off the project. 3.3.1 Selecting a Major Process for BPI: Earlier it was discussed major, macro and the mega processes developed and identified by SEC-ERB. This begin and end with the customer and independent of organizational structure. Those factors stated earlier lead the Company to decide to select “Maintain Support Services” project to be studied. 32 3.3.2 Conducting Interviews: Core team conducted interviews with Managers involved in the process, customer of the process, key suppliers for the process and people who work within the process. A list of targeting question will help to focus the discussions. It is best always to ask the same question to all being interviewed. The following are some example question use during initial interviews: Why should we consider this Process a project? Why is this project important to you? Why is it important to SEC Eastern Region Branch? What result would you expect from this project? What are the internal and external customers of the process? What are the performance measures used to determine the effectiveness and efficiency of the process? What on-line information is available? Are there any current constraints on the process? (i.e. People’s time, approval levels, budget constraints, etc) It is very important to document these discussions well and create a database of the information for future use in the project. 33 3.3.3 Building a Process Model: The model helps to ensure that the project scope is clear to all and help the project team plan the project activities. The Business Process Model is a decomposition of the Business Process to small sub-process. Input key process steps, output and customers are also identified for each sub-process. The sub-process also was identified from the previous interviews. This model after intensive discussions consisted of six Sub-Processes. It was decided that perform preventive maintenance is a sub-process for the major process. The repair of office equipment such as faxes, copiers, computers, etc. Was decided to be sub-process 2 and each department has its own sub-sub-process such as the repair of media equipment would be sub-process 2.2 and the repair of telecommunication equipment would be sub-process 2.3. Sub- Process 3 is the corrective maintenance for all the equipment and facilities. Facility maintenance (renovation, modification, remodeling, etc.) is sub-process 4 and it was subdivided into three categories such as sub-process 4.2 for Upgrade Landscaping. Sub-Process 5 deals with material delivery process. Finally, sub-process 6 is for all general services activities. 34 The sub process was identified as follows: Fig 4: Sub-Process Model (13) Sub-Process Model Sub-Process 1 Perform Preventive Maintenance (Buildings, Office Equipment & Utilities) Sub Process 2 Repair/Replace Office Equipment (Fax, Copiers, Telephones, Computers, Printers, AV Equip., Cameras, etc) Sub-Process3 Perform Corrective Maintenance on Equipment & Utilities 2.1 Repair/Replace Office Equipment 2.2 Media Equipment maintenance 2.3 Telecom. Equipment Maintenance 2.4 Repair/Replace Computer Hardware/Software & Peripherals. Sub-Process 4 Facility Maintenance (Renovation, Modification, Roofing, Painting, Remodeling, etc.) Sub-Process 5 Acquire Equipment and Materials/Spare Parts Sub-Process 6 Provide General Services (Janitorial/Sanitation, Landscaping/Gardening) 4.1 Sewer system maintenance 4.2 Upgrade Landscaping 4.3 Facility Maintenance 2.4 Identify Process Boundaries: The process Model provides a great picture of the scope of the 3.3.4 Identify Process Boundaries: The process model provides a great picture of the project. In addition to the business Process Model, clearly defining starting and ending points need to be defined. In other words what begins the process and when does the process end. Starting and ending points should also be defined for each sub-process within the Business Process Model. The map will show the inputs and outputs from and to the major seventy processes identified earlier. For example, major process 37 "Procure Contracts" will provide input to the 35 "Maintain Support Services" of contract awarding. And as an output to "Procure Contracts", "Maintain Support Services" will provide three things approved budget, detailed scope of work and contract documents. Figures 5 and 6 show it clearly. 36 Figure 5: Activities into the Major Process (13) The following are the inputs to the process from the other process: 5: Prepare & Monitor Capital Plans/Budgets & their Accountability… 4: Prepare & Monitor Operating Plans and Their Accountability… 70: Create & Maintain Drawing & Maps Guidelines & Procedures Approved Operating Plan Drawing 27:Plan Support Facilities and Communication Facilities Buildings/Facilities Planned Facilities Expenditure Cost Sheet Approved Budget Approved CAD Stationary Training Standards Design Package Project Evaluation Budget 5 Yr. Plan Scheduled of Proposed Plan Safety Standards Safety Tng/Awareness Engineering Standards 63:Communicate Company Information Activities… Annual Monthly Weekly Report Maintenance Status Rep. History Report 62:Prepare, Review and Issue Various Report 30: Maintain Support Facilities Material Expend. Rep. Call for Repair 56: Provide Training Facilities and Equipment Design Package 33: Operate Communication System Test Equipment Telephones, Faxes, Switching Systems, etc. 34: Maintain Communication System Contract Award Space Facilities for Repair Manuals Equipment Trainee Manpower 55: Provide Employee Training Education and… 31: Engineer & Design Communication System Contractors (QC) Vendor Commissioning Inspection Field Rep. Loss Control Training Vehicles Maintenance Drivers Cleaning Equipment Guidelines Instructions Engineering Services Supervision of Project Mgmt. For New Construction Revisions to Safety Equipment 66: Operate Vehicles & Equipment 29: Construct/Modify & Commission Support Facilities and… 28: Engineer & Design Support Facilities Consultation Plant Tag & Maps 69: Provide Safety Management 7:Develop & Monitor Engineering Design, Construction & Material Standards Catering Project Milestone List of Schedule & Expenditure Equip/Tools Pre-Qualified Report Malt. Furniture Satellite & Space Warehouse (Mtrl. Control Unit) List of Products Stationary Petty Cash Availability Supplies & Cost Equip/Tools Malts. 44: Reclaim Material, Equipment and Tools 45: Write off and dispose of Excess/Obsolete/Used materials… 37 42:Procure Equipment, Material & Services 43:Store, Control & Issue Materials, Tools, and Equipment 41: Pre qualify Register Vendors, Manuf. Contractor 40: Provide Office Services 37: Procure Contracts 38:Administrator & Manage Contracts Figure 6: Processes into the Major Process (13) And the following are the output of the process to other major process. 4: Prepare & Monitor Operating Plans and Their Accountability… 70: Create & Maintain Drawing & Maps 69: Provide Safety Management 5: Prepare & Monitor Capital Plans/Budgets & their Accountability… Accountability Report & Justification Updated As-build Drawing Operating Fact Sheet Plan Details Completion Certificate Request for Proposed Drawing Operating & Response to Field Inspection Report Accident Report Vendor Training 63:Communicate Company Information Activities… 62:Prepare, Review and Issue Various Report Project Estimates Business Plan Training Nominees Grans. & Request For Yearly Mileage Driving Test Plan Sheets Driving Conceptual Temporary Design Accommodations Review Coordination Feedback on Standard 5 Yr. Plan Project Punch List Rulings (Exp. Requirement for VR Cap Communication Design & Planning for new Review Systems Materials Approval Design Review (Cabling, Equip. Billing Location) 30: Maintain Support Facilities 56: Provide Training Facilities and Equipment 44: Reclaim Material, Equipment and Tools 45: Write off and dispose of Excess/Obsolete/Used materials… 38 Equipment Installation, Relocation Replacement Cabling Approved BI 33: Operate Communication System 34: Maintain Communication System SOW, Cost Est. Drawings, etc. Contract Documents Contractor Complaints/Claims System Report 55: Provide Employee Training Education and… 31: Engineer & Design Communication System Environment (Cooling, Space, etc. Status Report MIR/Workorder Course Evaluatio Contractor Forecasts Name of n Evaluation MDR Fixed Vendors Asset Form Tech. Spec. OJT Detailed Review Vendor Information Technicians Suggestions Training Morning PRNS/RMC Nominees Report Spare Parts CMR, Custodian Equip. Repairs Materials Release Equipment & Facility Career Dev. Equip/Tools Malts. Management/Repair PCA/CAF Evaluation Requisition Slip Telephony Requirements Exhibitions 29: Construct/Modify & Commission Support Facilities and… 28: Engineer & Design Support Facilities 27:Plan Support Facilities and Communication Facilities Propose Capita Plan Safety Goals & Objective 66: Operate Vehicles & Equipment 7:Develop & Monitor Engineering Design, Construction & Material Standards 37: Procure Contracts Auxiliary Request Contract Document Site Visits & Contractors 42:Procure Equipment, Material & Services 43:Store, Control & Issue Materials, Tools, and Equipment Drawing 41: Pre qualify Register Vendors, Manuf. Contractor 40: Provide Office Services 38:Administrator & Manage Contracts 3.3.5 Interview the key People: The communication is a major part in BPI. After establishing the process model and boundaries, communication again should take place by returning back to the key people to take their comments and support of the models created to make sure of the work. 3.3.6 Selecting BPI Team Member: The BPI project team is responsible for gathering information for process selection, searching for leading practices, identifying technological enablers, identifying the current processes, creating new processes, performing business case analyses and creating implementation plans. The membership of the project team is specified by the Executive Sponsor and Process Manager, and should be composed of team members possessing strong interpersonal, project management, analytical and problem-solving skills, supported with creativity and expertise in important business areas. The best and brightest, the BPI team should consist of and they must be able to work well together for the project to succeed. It is also important at this time to identify several people who have to be candidates to be as a project management skills and could become the implementation project manager upon the conclusion of the project. 39 The team should be cross-functional in its composition. The recommended team size was 13 members. The team should be mix of people, the team should include: Some individuals who actively use the process and work closely with customers (front line employees). Individuals who are well respected by their peers and Department members. Some individuals who intimately understand the current process (experts – could be at any level in the organization) Customers of the process (when possible) and suppliers (those people who are involved with the process at the boundaries). Some technical experts. Some individuals who are completely objective toward the process and outcome (core team can play this role). Some individuals who are not familiar with the process (core team can also play this role). 3.3.7 Creating Project Charter: The key components of the project charter which was developed include mission, scope of project, goals and objectives, deliverables, roles and responsibilities, project milestone and finally assumption 40 and risk. The finding for "Maintain Support Facilities" (13) are as follows: I. Mission: To ensure the following: 1. Reduced cycle time. 2. Efficient and optimum utilization. 3. Timely and appropriate level of service to customer. 4. A moderate and efficient budget. II. Scope of the Project: The staring and ending point of the process. The model and boundaries are components help to define the project scope. III. Goals and Objectives: They were developed as follows: 1. Minimize and optimize time can be enhancing the maintenance process. 2. Reduce Preventive maintenance costs by 15%. 3. Improve response time to customer’s initial request and reduce time to repair equipment by 20% (from customer request to job completed). 41 4. Reduce cost to repair equipment by 10% implement an energy conservation program. 5. Reduce contract cost for Janitorial & Landscaping services by 5%. 6. Clarify and document approved roles and responsibilities for each Department involved in facilities maintenance. 7. Acquire specified good quality materials on time at a competitive price. 8. Utilized the latest technology. 9. Better utilization of existing resources. 10. Proved the best training, (multi-skilling), and latest tools, instruments and equipment to improve employee productivity. 11. Eliminate the duplication of stock numbers for similar/same materials and spare parts. 12. Support qualified Saudization of the process. 13. Assure good quality of maintenance work (Preventive & Corrective) to reduce equipment breakdown. IV. Deliverables: The BPI project Team produced and maintained the following deliverables through the duration of the project. 42 1. Overall project Work plan: Comprehensive schedule of critical project activities including: activity duration, resources and responsibilities, decision point’s required and key milestones. Project Work Plan and Charter. 2. Weekly Status Report (WSR) Weekly updated on project progress and issues will be provided to the Executive Sponsor, Process Manager and the Strategic Development Department (SDD) Manager which the core team came from. Progress status against schedule. 3. Current State Presentation & Work Papers. 4. Leading Practices Report. 5. Future State Presentation & Work Papers. The improvement opportunities offered by this project will lead to a portfolio of change initiatives: BPI team recommendation for major process improvements. Leading Practices from both utility and non-utility Companies to help the team to identify creative 43 practices in the Maintain Support Facilities process. An Express Workshop to identify quick improvements within a key area of the “Maintain Support Facilities” process. Quick Fix action items for obvious quick improvements (outside the scope of this BPI project). 6. Business Cases and Implementation Plans for all BPI Improvement Recommendations. V. Roles and Responsibilities: Four major parties are involved in this study. First is the Executive Sponsor who is the Vice President Support Services. He is responsible for the project vision development, communication of the project vision and purpose, resource allocation, and sustained commitment to completed project. The second is the process Manager. Manager Office Services Department. He was selected since the major parts of the project are functions and responsibilities of OSD. He is responsible for identification of project scope, business process attributes and high-level model and identification of 44 process owners and subject matter expect direction for the project. The third partly, are the project team members who are key individuals selected to participate in the BPI team who are expert in the Maintain Support Facilities process. They are responsible for the following: Commit to the entire project time frame. Participate in the development of the Project Charter. Gather process data. Participate in BPI Team meetings and recommend improvements to the process. Participate in Leading Practices site visits with Companies outside or SEC-ERB. Communicate continually with their management and peers on the status of the BPI project. Participate in Presentations. The fourth party is the BPI Core Team who in responsible for project management, data/information facilitation, supplied by and SEC-ERB evaluation of resources for appropriates, reliability, and reasonableness. Responsible for analysis of date, documentation of assumption, orchestration 45 of communications, facilitation of organizational change management strategies, and preparation of final deliverable. Subject Matter Experts/Past Time Participants (SMEs) those are key people who participate on an as-needed basis to provide information offer their opinions based on experience, so, they are not considered as a major party. VI. Project Milestone: The following table highlights the major phases of the project. Most of the current state require from the team to attend one day per week. For 8 hours. Then team member will be participating full time in last two week in the current state. For the future state the team on average will meet for full time 4 days a week and the remaining one day for 8 hours will be available for the team to collect date and communicate with key people in the Maintain Support Services Process. 46 Table 4: Project Milestone (13) Milestone Event Start Date Finish Date Project Kick-off & Training Finalize & Communicate a “Project Charter” for the project (This document) Current State Process Mapping Workshops & Activity Modeling Customer Interviews 22 Jum. II Oct 2 22 Jum. II Oct 2 18 Raj., Oct 27 18 Raj., Oct 27 29 Jum.II Oct 9 30 Ram., Jan 5 21 Rajab, Oct 30 2 Shaban, Nov. 10 Current State Presentation Workshop 29 Shaw., Feb. 5 29 Shaw., Feb. 5 Current State Final Presentation 3 Dhu-Q., Feb. 9 3 Dhu-Q., Feb. 9 13 Dhu-Q. Feb. 19 17 Dhu-Q., Feb. 23 25 Muh., Apr. 29 25 Muh., Apr. 29 4 Safar, may 8 4 Safar, May 8 12 Safar, May 16 12 Safar, May 16 Future State Design Workshop Sessions Future State Presentation Future State Presentation Sponsor, Process Manager Future State Presentation Workshop to Executive & Invited Guests to SEMC VII. Assumption and Risk: The success of this Project is at risk if the factors that are basic to its development do not exist or cannot be secured. One of the most important techniques of minimizing these risks is the early establishment of clear, quantifiable Objectives and Goals by the Project’s Sponsor. Frequently, a root cause of failure is related to erroneous assumptions about available funding, realistic goals, accomplishments and results, external influences that could negatively impact the Project, and available resources. Therefore, the most critical requirements and factors in this Projects are (13) : 1. A clear understanding of the Mission, Objectives and Goals that is shared by all participants. 47 2. Securing long-term support and commitment, including funding, from all levels of Management. 3. The availability of highly knowledgeable Team Members in all aspects of the Process. 4. Coordination of this Project with other priorities. 5. Successful implementation of any technology enhancements that may apply to this Project. 6. Constant communication and feedback. 3.3.8 Developing Detailed Work plan: The core team is to develop a work plan for the team and for the Project each day activity for the whole project period. It is very difficult to be very accurate in doing such plan but it can be modified each time it needs modifications. 3.3.9 Provided Team with Overview and Kick-off Project: The previews project team member will be invited to share with team their experience and feeling and the team will be provided with an overview of the project. 48 This will end up the first phase, which is the start-up and preparation phase. And the project is ready to start the current state phase. 3.4 Current State Phase: 3.4.1 Introduction Every organization is a collection of processes, both technical and administrative in nature. The nature of processes is the real activities and its related information as data that the Company does in order to perform the final aim or the goals. Hence, current state is the phase where the assessment of the process takes place, which require from the team a lot of analytical thinking. The team will combine their collective knowledge with key process date to develop an understanding of the process. Moreover, rest of the project study there will be explanation of all phases’ detail. However, there would a concentration on one of the six sub-process shown earlier in models, relating the collected dated to that particular sub-process. This will help us to study the affect on each particular sub-process. 49 Finally, the team starts the project by finalizing the project charter “process model, boundaries, etc.” in orders everyone to convinced of the study material. In this report, there would be more concentration of sub-process 3 “Perform Corrective Maintenance”. The reason why it is selected since it is the heart of support services activity, which is also is the main function of the support services. Also, due to the size limitation of the study. 3.4.2 Process Mapping and Value Analysis Also called process mapping, the objective here is to clearly define how the process functions. The major objective of Process flow diagramming is to document the process and get agreement as to who does what in the current business process. A Process Flow Chart is a pictorial representation of a process, using a variety of symbols connected by lines and arrows. A Process Flow Chart provides a clear picture of each stage of a process, the interrelationship between stages of the process, and the direction of the process flow. There are a few basic symbols that should be understood prior to starting the flow charting process. These are (9) rectangle which generally used to identify a process activity, or an 50 action step, in the overall process. Activities such as painting and repairing are examples of activities that could be represented by the rectangle. The diamond is used to indicate a decision required in the process. The information contained in the diamond generally takes the form of a question. Decisions such as "make or buy," "repair or replace," and "ship or stock" are represented by the diamond Most Flow Charts constructed by a BPI team will be done at the activity level. However, sometimes more detail is needed and the Team may decide to work at the task level. Value analysis identifies activities, which are conducted for the benefit of the customer, and activities, which are important for running the business, or rework is necessary. Value added activities (customer importance) focus on meeting customer needs. Non-value added activities (business importance) it is done for ourselves to run the business or to correct problem. Hence, value added criteria: - Activity is important to the customer? - Activity produces a physical change to the product? - Activity is done right the first time? 51 There are three levels of process detail as follows: - Sub-process level: usually is a major part or macro level view of the process. Usually by senior management. - Activity level: usually activity is a major job but falls between macro view and the fine detail of the process. - Task Level: This part where fine or detailed picture of a specific portion of the service process, is usually use by the team to develop the process map. From the process map for sub-process 3, the picture become clearer of how it is alone and to how much detail the team reached. Development of process map took some time since different task and activities and procedures are taken place by different Departments. Hence, incorporating all these differences in one map is not an easy job. The process map explains the sub-process 3 from start up to the end and in between is the activities and tasks performed by each Department in order to perform corrective maintenance. Some activities depend on other processes like here, there is a dependency if the corrective maintenance will be performed need material or not. If there is a need for preparing of the material or ordering material it depends now on sub-process 5 “Acquire Equipment & Material/Spare Parts” which is a lengthy 52 process and if is not done right the material delivery will be late and consequently the corrective maintenance would be also late. The second step is the decision whether task or activity is a value added or non-value added (earlier explained). In the process map for sub-process 3 it was decided by the team that only two activities are value added and the rest are non-value added. The two activities are receiving complaint/request since it will affect directly the customer and executing the requested job or work. The other will not produce any physical change to the customer. 53 Figure 7: Process Map for Sub-Process 3 " Corrective Maintenance" (13) Received Complain/Request Start Is it Emergency? VA Collect Materials Restricted Area Yes No NVA Yes Go To SubProcess 5 NVA Prepare Material Request No Obtained Work Permit? Get Tools Yes Are Materials Required? NVA NVA No No Travel to Site END Execute the Work Requested Close Work Order NVA Input Actual Man-hour in the System NVA High &/or Medium FTE amount Out of Scope Activities Value Added Activity 54 NVA Plan, Manpower and Materials (Estimates) Assign the Work to Technician NVA NVA Found Additional Work Needed? VA NVA Prioritize and schedule work Open Work Order NVA NVA NVA Obtain Work Permit Inspect Complain/Request Travel to Site No Close Work Permit NVA Yes Inform Foreman NVA Figure 8: Process Map for Sub-Process 5 "Acquire Equipment & Material/Spare Parts" (13) High &/or Medium FTE amount Out of Scope Activities Value Added Activity Technical List Material Requirement (Inc. Furniture & Capital Budget) Is a Satelite Warehouse Available Start VA Technician Prepare Dept. Req. Slip & Gain Approval Check Stock Number (Catalog/MMS) NVA NVA Availabile in Dept./Satellite Warehouse Material Man Check for availability Submit to Material Unit/Store VA No NVA Check on CRT SIRS/MIMS System NVA Reorder Again Return/Short Materials Return Material to MMD Warehouse (Only RTI for Short) NVA NVA Follow-up with MMD claim unit for Replacement NVA Correct/ Complete VA NVA Receive Defective/Damage Materials/Spare Parts and Disposae by MDR to MMD Correct/ Complete NVA VA NVA NVA Sign CAF and Give Orig. to Vendor and Process others Payment & Record Y es Sign DRR, Submit Copies to Concerned persons Receive Material and Check for Correctness NVA VA Type/Prepare CAF and Gain Approval Availabile in Dept./Satellite Warehouse No NVA If P.O. Overdue, Follow-up with Expediter NVA Check P.O. in SIRS for Delivery Date, Update Outstanding Matl. Record NVA Evaluate Consumption to Maintain Stock Level Enter Transactions in Dept. Matl. Control PC Program NVA NVA Evaluate and Approve Quotations from Buyer/MCD and Return NVA Follow up with Buyer if no info. On SIRS After Bid Date 55NVA NVA Rush MPR Emergency 20% 95% Gain Approval and Print to MMD Available in PCA Aggreement? Yes NVA NVA 5% Propose to Stock (Dept. Store, MMD, PCA) VA Yes NVA Contact Vendor for Delivery of Material NVA Receive Matl. On DPR and Check Warehouse Clerk Fill Out MIR in SIRS or MIMS on CRT Gain Approval from Approval Authority Print MIR Check PCA Agremennt NVA No Department Pick Up Material from MMD Warehouse were it is Available or MMD Transfer to near Werh. Check if Correct, not Damaged or Short Issue to Technician Receive and Check NVA Complete RVR & Send MMD Claim Unit Make RTI for Wrong, Damage or Short Purchase with Petty Cash Gain Approval (upto 2000 SR) Not Stockable with MMD Evaluate Req. for Emergency or Routine (Judgment by Foreman) NVA Routinewith 80% NVA Full out MPR on MMD SIRS Electrically Yes 3.4.3 Collecting Detailed Sub-Process Data: Every process improvement relies on data to provide a factual basis for making decisions. Data collection enables BPI team to formulate and test working assumptions about process and develop information that will lead to the improvement of the product and services. The first step is to gather data about each department. The team leader will brainstorm the team for defining the data needed to be collected. Hence, each member in each department went back and gather data and constructed a table containing the data such as how much it cost each department to provide the service, number of preventive maintenance, number of customers requests, total copies made, etc. The following table containing those data: 56 Table 5: Process Data (13) Data Description Annual Cost Data Food Allowance Housing Landscaping Plants Tool Repairs Equipments Repairs Maintenance Contracts Safety Gear Tool Replacement Training PM Materials Vehicle Use Landscaping Services Con. Facility Modification Corrective maint. Materials/Spare Parts Contract Labor Cost Equipment replacement Janitorial services Contracts OSD Data Total Data Description 8,000 10,000 16,000 3,000 5,000 33,000 59,000 126,000 94,000 253,000 784,000 2,296,000 3,332,000 3,140,000 4,847,000 3,491,000 9,017,000 27,514,000 OSD Data GD Data PTD Data ITD Data TCD Data RMD Data GPPD Data N/A N/A N/A 12,750 9,300 79,500 59,736 12,000 20,000 10,000 N/A 13,000 10,000 100,000 496,309 140,000 N/A 41,892 35,120 635,000 543,000 300,000 523,616 N/A 780,000 2,131,286 N/A 480,000 2,092,925 4,263,000 437,000 20,000 4,555,790 571,512 26,000 390,000 441,000 GD Data PTD Data ITD Data TCD Data RMD Data GPPD Data 4-5 times per year pc - 2/yr PC printer-2/yr Monitor - 1/yr Mainframe Printed - 4/yr 2,500 36,000 20,000 1,500 6,000 3,000 32,000 292,790 3,500 10,000 Other Data Collected Frequency of breakdown for various types of equipment Number of P.M. Performed Per Year Total Copies Made Average Response Times to Customer Request 6 29,325 20,864,124 1,690 5,554 1 hr 1 day 30 Minutes Inventory Levels (SR Value) # Forms Used 357,000 29 5 N/A 50 # Customer Requests for Maintenance/Repairs 12,985 744 766 Cost of maintenance per customer request # of Short from contracts approved # of Long Form Contracts Approved Average Long Form Contract Duration Average Short Form Contract Duration # of Procurement Contracts (SFC + LFC) # of Telephones Current & Future # of Computers/Peripherals Current and Future Department Breakdown OSD GD PTD ITD 48 9 Const.= 21 wks Service = 4 yrs 3 months 57 3,185 6 2 1,607 1 hr to several days 150,000 3 1284 Hardware 336 Software 900 27,514,000 2,131,286 2,092,925 4,555,790 1-3 hrs 5,107 5 7 More than 2000 Expenditures 40 # PMs Performed 29,325 1,690 5,554 Cust. Request 12,985 744 766 1,620 57 5000/6000 63 300 Total 8,000 10,000 16,000 23,000 65,392 68,120 84,750 181,300 293,500 813,545 936,000 2,328,000 4,267,000 4,512,906 4,847,000 8,211,000 10,667,000 37,332,513 Second step in this section, is measuring the process cycle times for each sub-process. Cycle time is a measure of the actual elapsed time it takes a request to be filled or a job to be done including all queue time, downtime, etc. it is basically stop time minus start time. By averaging the cycle times of a sample measures, the average cycle time for the job can be calculated. Cycle time includes time it takes to complete activity, down time and time between activities or process. By studying Sup-Process 3 "corrective maintenance", it was subdivided into four main areas that are doing the job separately: Generation, Transmission, Headquarters and Operating Area. Then, each area will group main activities they do until they implement the job and putting the time cycle it takes to do the activities under it. .The following is a process cycle time for subprocess 3: 58 Figure 9: Sub-Process 3 Cycle Time (13) General Facilities Receive Complaints/ Request Open Work Order Assign Work to Technician Obtain Matls., Work Permits and Tools Travel to the Site Complete Corrective Maintenance Close Work Order 15.25m 1h-3h 10m-3h 30m-32h A=8h Transmission Facilities Receive Complaints/ Request Open Work Order Assign Work to Technician Obtain Matl., Equipment and Tools Get Work Permit or Permission from Dispatch Travel to the Site Complete Corrective Maintenance Release/Close Work Permit or Permission Close Work Order & Travel Back to Office 20m 60m 35m 32m 45m Headquarter Facilities Receive Complaint Initiate CM Work order Inspection by Technician Obtain Materials Implement Corrective Maint. Work Submission & Work order Closing 15m 2h 15m Operating Area Facilities Receive Complaints/ Request Open Work Order Assign Work to Technician Obtain Matls., Work Permits and Tools Travel to the Site Complete Corrective Maintenance 30m 3h 30m 30hr 59 Close Work Order Last Step in this section, is measuring the Full Time Equivalent (FTE). This is a measurement of manpower costs in terms of man-hours and it is called FTE consumed by each activity or Sub-Process. FTE is equivalent to man power working 8 hours a day for one full week. 1 FTE = 40 hours This amount of man hours consumed in the Major Business Process is done by identifying the number of people who fill positions for that job title. Then by asking as ample of the people who work in the job title to identify the percentage of their time they spend in each SubProcess. By taking Northern Area Office Services Department (NAOSD) as a sample of how the calculation of FTE take place. In the next figure all FTE's documented in away NAOSD list all it job titles and number of employees filling the job tittles. Then, in each SubProcess as discussed earlier to measure how much time they are spending in performing that specific Sub-Process such as in SubProcess 1 it is consuming 2.1 FTE's. So, total FTE's this job title is consuming to serve all the six SubProcess amounted to 4.8 FTE and by dividing each Sub-Process FTE by this figure, the percentage FTE for each Sub-Process is computed and finally by delivering the actual FTE each job title by the total FTE's available for that specific job title and in the case 60 of A/C Technician it completed to be 60%. And by computing all departments FTE's involved as seen in the following figure, the total positions involved in performing all the six Sub-Process amounted to 537 position with a total FTE amounted 413.7 61 Pos % FTE's in Maint. Supp. Facil. % in Maintain Supp. Faci. # of People in Position Figure 10: Northern Area Office Services Department (NAOSD) FTE (13) Sub-Process #1 Perform Preventive Maintenance Sub-Process #2 Sub-Process #2 Sub-Process #2 Sub-Process #2 Repair/Replace Office Equipment Repair/Replace Office Equipment Repair/Replace Office Equipment Repair/Replace Office Equipment Sub-Process #3 Perform Corrective Maintenance 1.0 2.1 2.2 2.3 2.4 3.0 Perform Preventive Maintenance R/R Office Equipment Media Equipment Maintenance Telecommunication Equipment Maintenance Computer & Peripheral Repair Perform Corrective Maintenance on Equipment & Utilities FTE Department/Division FTE % 2.1 2.1 0.8 0.4 0.45 0.45 0.20 0.20 0.3 0.20 0.1 0.05 0.1 0.05 0.7 0.20 0.2 0.05 0.2 0.05 FTE % FTE % FTE % % FTE % 0.1 0.05 1.7 1.7 2.6 1.1 1.0 0.3 0.35 0.35 0.60 0.65 0.85 0.20 0.2 0.05 0.8 0.25 0.2 0.05 0.1 0.5 1.3 0.1 0.3 0.10 0.85 0.75 0.30 0.30 FTE NAOSD 8 8 6 3 2 3 20 1 2 4 0.60 0.60 0.70 0.60 0.60 0.60 0.60 0.2 0.4 3.6 4.8 4.8 4.2 1.8 1.2 1.8 12.0 0.2 0.4 3.6 6 3.0 3.0 1 1 3 1 1 10 0.8 0.6 1.8 0.4 0.9 9.0 0.8 0.6 1.8 0.4 0.9 9.0 A/C Technician Building Electrician Building Maintenance Specialist Building Maintenance Technician Carpenter Clerk Contractor Draftsman Engineer Foreman Gardener Inspector Janitor OSD Manager Painter Plumbers PM Coordinators Superintendent Supervisor 51.3 Sub-Total 80 0.1 0.10 0.3 0.2 0.70 0.20 7 0.1 0.10 0.05 0.05 0.05 0.4 0.05 0 62 0.1 0.3 0.10 0.05 0.4 11.7 Figure 10: Northern Area Office Services Department (NAOSD) "continued" Sub-Process #4 Sub-Process #4 Sub-Process #4 Facility Maintenance Facility Maintenance 4.1 Sewer System Maintenance FTE % 0.1 3.0 0.05 0.25 0.1 0.2 0.15 0.05 Facility Maintenance Sub-Process #5 Acquire Eqp. & Materials/Spare Parts Sub-Process #6 Provide General Services 4.2 4.3 5.0 6.0 Upgrading Landscaping Facility Maintenance Acquire Equipment & Materials/Spare Parts Conduct Landscaping & Janitorial Maintenance Activities FTE % 0.1 1.8 0.1 0.1 0.4 0.05 0.15 0.25 0.3 0.10 0.2 0.05 0.1 0.10 0.1 0.10 0.1 0.05 0.1 0.05 0.9 0.05 0.10 1.4 0.05 0.15 4.5 4.3 FTE 0.3 7.2 0.1 0.2 0.4 % 0.15 0.60 0.75 0.55 0.10 FTE % 1.0 1.0 0.8 0.3 0.2 0.3 0.20 0.20 0.20 0.15 0.15 0.15 0.1 0.05 0.3 0.10 0.2 0.05 1.00 0.90 1.00 FTE 2.6 0.1 0.1 0.10 0.10 8.4 % 0.1 0.1 0.2 0.10 0.15 0.10 0.1 0.05 0.1 0.5 0.10 0.05 0.2 6.2 0.15 0.70 4.9 63 Total 9.4 4.8 4.8 4.2 1.8 1.2 1.8 12.0 0.2 0.4 3.6 3.0 0.8 0.6 1.8 0.4 0.9 9.0 51.3 # of People in Position TE's In Maint. Shop Facil. Figure 11: All Departments FTE's NAOSD 80 51.3 HQOSD 63 52.3 HAOSD 128 111.1 OSD/ERU 11 10.0 DAOSD 75 67.0 MSU 7 7.0 OSD/TSU 9 7.6 OSD Totals 373.0 306.3 DATD 18.4 HATD 16 11.5 NATD 16 11.3 PTD Totals 57 41.2 25 Sub-Process #1 Sub-Process #2 Sub-Process #2 Sub-Process #2 Sub-Process #2 Sub-Process #3 Sub-Process #4 Sub-Process #4 Sub-Process #4 Sub-Process #6 Perform Preventive Maintenance Repair/Replace Office Equipment Repair/Replace Office Equipment Repair/Replace Office Equipment Repair/Replace Office Equipment Perform Corrective Maintenance Facility Maintenance Facility Maintenance Facility Maintenance Provide General Services 1.0 2.1 2.2 2.3 2.4 3.0 4.1 4.2 4.3 6.0 Perform Preventive Maintenance R/R Office Equipment Media Equipment Maintenance Telecommunication Equipment Maintenance Computer & Peripheral Repair Perform Corrective Maintenance on Equipment & Utilities Sewer System Maintenance Upgrading Landscaping Facility Maintenance Conduct Landscaping & Janitorial Maintenance Activities Total 7.0 0.4 0.3 0.4 11.7 4.5 4.3 8.4 9.4 51.3 1.1 1.2 16.9 0.8 4.5 6.9 2.2 52.3 22.5 0.7 1.2 3.9 13.9 111.1 14.1 0.6 55.8 2.6 7.3 19.8 4.5 10.0 28.3 3.2 1.3 0.1 2.7 67.0 7.0 7.6 99.3 12.2 0.6 1.4 1.6 79.4 9.2 11.3 7.6 26.9 28.2 306.3 6.7 5.6 2.9 1.7 18.4 4.3 3.3 1.8 1.1 11.5 4.3 3.4 1.8 1.0 11.3 6.5 3.8 41.2 15.3 0.0 0.0 0.0 0.0 12.3 0.0 0.0 GD 54 17.7 3.4 10.9 17.7 ITD 3 1.2 1.2 1.2 RMD 3 0.5 0.1 47 46.8 8.7 537 Total 413.7 0.4 0.5 TCD 126.8 36.3 12.2 1.0 37.7 46.8 2.8 64 102.6 9.2 11.3 33.4 32.0 413.7 3.4.4 Conducting Customer Surveys: After developing the charter and developing the process maps for each sub process agreed on the beginning of the study, a scheduled meeting with invited guests from different departments. More than 100 employees were invited to share their opinion about the process map and to share with them for their issues and concerns. The whole project depends on discussion and feedback. So, this is only a step in several steps in discussing most of the project results with user of the service and who are implementing the service. The results of these meeting resulted of more than 1,000 issues and concerns. In table 6, the first column is the serial number of the issue or improved recommendation and the second column is the recommendation. The third column concerns the team of identifying where this recommendation is related to which sub process. The fourth deciding whether it is an issue, improvement (I) or it is a recommendation (R). The fifth deals with deciding if this recommendation or issue affects quality (Q), cost (C), cycle time (CT) or safety (S). The last column is the department name that gave the recommendation. The table is arranged in sequences and in order of the sub processes. 65 Understanding customer requirement, values and current level of customer satisfaction are key features in describing the current process. This is a critical aspect because anticipation and exceeding these objectives is a fundamental aspect of BPI. Here only tabulated categorized the issued and concerns about sub-process 3. 66 Table 6: Issues & Improvement Identified by the Customers & the Team SubProcess /Minor Process# Customer & Process Issues/Improvement Issue or Improv. Recom. Quality, Cost, Cycle Time of Safety (13) Department Issues and Recommendation for Sub-Process 3 – Perform Corrective Maintenance on Equipment & Utilities 31 Materials should be available locally for the equipment being purchased 3 I C MMD 39 Some fire station equipment, air, compressor, recharging equipment, generators, etc repairs usually cost more than the replacement of equipment at the generation workshop 3 I C ISD 70 Some duplicate work is being provided by us (ISD) and OSD on fire equipment 3 I C ISD 184 Study the sweet water provision to eliminate water hauling to different SCECO sites 3 I C TD 397 Time and labor cost in obtaining spare pats 3 I C Team 401 No over time available for corrective maintenance 3 I C Team 405 Limitation on petty cash 3 I C Team 413 Lack of power tools 3 I C Team 3 I C HOA 623 5 Not satisfied with the repair of generators when it is sent for repair to CSU. Spare parts and labor was very expensive most of the time. A longer generator must be provided Response time for maintenance is problem 3 I CT MMD 51 Maintenance requires manager approval on the form and it is not necessary to get management approval 3 I CT MMD 62 The lighting system at the office and the gates are not sufficient and it takes one to two weeks of repair 3 I CT ISD 67 There is along process for the repair of A/C unit and there is no replacement unit provided 3 I CT ISD 81 In very remote areas, equipment needs to be transported to a workshop in Dammam which is very far away 3 I CT ISD 89 There are problem with work permit in the process 3 I CT ISD 107 The response time for electrical services is slow. We expect to have same day service 3 I CT ITD 131 Relocation of equipment from building to building or from cars to building takes a lot time and some times you have no one to do it 3 I CT TED 151 OSD should be more initiative rather than waiting for corrective maintenance request 3 I CT SOD 384 Limited O.T. which delays in performing work 3 I CT Preparation 386 Spare parts are unavailable which delays repair 3 I CT Preparation 389 Long procedure to obtain budget item for emergency repairs 3 I CT Preparation 390 Lack of supervision make unawareness of completion tasks by technicians 3 I CT Preparation 395 Obsolete equipment 3 I CT Team 396 Unavailability of spare parts 3 I CT Team 403 No bill of material provided 3 I CT Team Given wrong parts to perform repair 3 I CT Team 410 Delays in repair of equipment 3 I CT Team 411 Distance to equipment needing repair 3 I CT Team 67 412 Lack of transportation 3 I CT Team 415 Delays in obtaining work permits 3 I CT Team 416 Delays in obtaining gate passes 3 I CT Team 417 Difficult to get temporary access for vendors 3 I CT Team 544 When making a request to fix something in HQ clinic conference room, it will take time before the maintenance people do it, such as requesting to change busted lights or fixing the dimmer 3 I CT HSD 614 Repair of window A/C takes too long to receive when it was send to OSD 3 I CT GPPD 23 When a request is sent for maintenance, no response is received and the requestor is not sure who to follow-p with 3 I Q MMD 24 When a request is sent for maintenance, no response is received and the requestor is not sure who to follow-p with 3 I Q MMD 43 No on-call list is available for OSD. OSD says there is no overtime but we work 24 hours in a day 3 I Q ISD 44 No on-call list is available for OSD. OSD says there is no overtime but we work 24 hours in a day 3 I Q ISD 48 When requesting maintenance for A/C it is taken away and not replaced for few days. There should always be a replacement 3 I Q ISD 49 Some time there is not enough air-conditioning to cool the aerator comfortable temperature 3 I Q ISD 50 Air conditioners are installed too low and blow on the guards making them sick. Split A/C should be used 3 I Q ISD 55 There is no clear responsibility for the maintenance of some equipment 3 I Q ISD 57 It is not clear where to send request for design and maintenance 3 I Q ISD 58 Qurrayah PP is having some difficulties with maintenance. OSD does not cover some of the unit. PTD and GD provide courage. Service can not be provided when needed 3 I Q ISD 60 Replacement A/C is not available when the unit goes down 3 I Q ISD 61 Drop gates take one to two months to get repaired 3 I Q ISD 68 Sometimes the department fixes the Air-conditioning unit or removes it for repair because no maintenance crew is available 3 I Q ISD 71 No inspection and calibration is performed for testing / analysis equipment which are very sensitive devices 3 I Q ISD 74 The MORRIS patrolling system which register the patroller during his route has no department assigned for maintenance 3 I Q ISD 82 Ghazlan PP will have an integrated system and it is still not clear who will be responsible for the maintenance and repair 3 I Q ISD 86 No maintenance coverage is available in off hours even for emergencies 3 I Q ISD 91 The toilet should have a good exhaust/ventilation system 3 I Q TRD 68 106 We are getting a good response to the maintenance of specialized A/C equipment used for the maintenance 3 I Q ITD 116 The building and facilities of SECTI is deteriorating and TED feel that they have to point out problem to OSD, such as cracks, curtains are falling, A/C balancing. Etc. TED believes that OSD should take the initiative instead of waiting to be called 3 I Q TED 119 A letter given to OSD to fix the A/C system (hot areas/cold areas and balancing) they came, fixed the manager room and left the rest of the building 3 I Q TED 157 Lighting at PCC is not adequate, we have raised this point so many times but no response from OSD 3 I Q SOD 158 Some of the light tubes are Whitish and others bluish 3 I Q SOD 159 Light tubes are not changed before it fails 3 I Q SOD 172 Don’t leave things to janitorial & landscaping inspectors, OSD inspectors should do the inspection 3 I Q SOD 178 Some of the workshop A/C have no redundancy 3 I Q TD 190 The capability of OSD A/C technicians is questionable 3 I Q GD 199 Windows type A/C unit is frequently breaking down especially the one installed in gas turbine. Even when the defective parts are replaced (several times) the problems reappears after a few days 3 I Q GD 200 The quality of repairs is poor and it is recommended to replace instead of repair 3 I Q GD 201 Water heaters are frequently out of service 3 I Q GD 382 No clear procedures only use our experience 3 I Q Preparation 383 Lack of experienced technicians 3 I Q Preparation 385 Lack of tools and equipment to perform the work 3 I Q Preparation 387 Employee training is not keeping pace with the advances in equipment 3 I Q Preparation 388 No as built drawing provided for equipment 3 I Q Preparation 391 Assignment of improper individuals to execute the task 3 I Q Preparation 392 Improper quality of spare parts 3 I Q Preparation 393 Manuals are not being provided by contractors to maintain new equipment 3 I Q Preparation 394 Manpower limitation and equipment numbers continued to expand 3 I Q Team 398 Shutdowns the customer 3 I Q Team 402 Lack of training on equipment repair & trouble shooting 3 I Q Team 404 Lack of expertise 3 I Q Team 407 Not following the prioritization of the work 3 I Q Team 408 No appraisal for the worker 3 I Q Team 409 No proper supervision or guidance of the work 3 I Q Team 414 Harsh weather 3 I Q Team 418 Repair requires shutdown of equipment 3 I Q Team 3 I Q GDD 530 Turn over of facilities maintenance at Qurayyah PP to OSD was a good decision by management since PP maintenance are dedicated to power plant jobs The managers office and network room has the same duct, however, the cooling requirement for both room is different 3 I Q GDD 536 69 541 No expert personnel to do the water treatment in the R.O plant 3 I Q HSD 542 No correct procedures in hiring R.O. plant personnel 3 I Q HSD 546 The complaint desk at 6323 always mentioned lack of manpower when requesting for service 3 I Q HSD 547 No water in some of the bathroom 3 I Q HSD 548 Lights are always busted, nobody is attending to them except when somebody request them to be fixed 3 I Q HSD 551 No body is repairing water leakage in bathroom which has a bad smell or order 3 I Q HSD 597 Phase III, 2nd floor has climate control problem. It is either too hot or too cold 3 I Q DED 601 Hot water in drinking fountains is rusty 3 I Q DED 615 He is skeptical of the transfer of facilities maintenance to OSD 3 I Q GPPD 633 Problem with the A/C in Jubail & Ghazlan are Substations for the last year 3 I Q TCD 635 Some locations have bad lights and when burnt out they are not changed for a month 3 I Q TCD 73 High voltage testing gloves need to be tested but ISD does not have the equipment. Transmission has the equipment to test the gloves 3 I S ISD 37 Power plant and transportation have workshop which could be used for facilities maintenance 3 R C MMD 584 Entering all facilities equipment in order to request them 3 R CT QPPD 147 HQs. Substation should be improved so that it should have redundancy 3 R Q SOD 559 Cafeteria inspector must be expert on foods, sanitation etc. 3 R Q HSD 583 All SCECO organization should be maintained by one organization 3 R Q QPPD 3.4.5 Root Cause Analysis: All activities that have been identified as Non-Value Added need to be analyzed to understand the underlying reason for their existence. To identify opportunities to reduce the work effort involved this better done by understanding of each activity will allow the team to challenge the need for the activity. The basics of conducting root cause analysis is to always to ask “Why”? That’s the 70 key to finding the root cause (or causes) of an activity. The team identified 22 root causes to respond to any question why? And these are the following: 1. Required by Policy 2. Required by Procedure 3. Rework 4. Lack of Automation 5. Approval Authority 6. Inspection 7. Non-Standardization 8. Paperwork, Report 9. Required by Outside Agency 10. Incomplete Information 11. Inadequate Tools and Equipment 12. Low Skill Level/Limited Resources 13. Coordination 14. Planning Purposes 15. Long Travel Time 16. Poor Quality Material 17. No Operating Manuals 18. Interruptions 71 19. Material no Available/Not Stock Item 20. Weather 21. Training 22. Cost After that in the root cause analysis for each sub-process the activities were listed in the first row end then the second row the importance of this activity for the sub-process to be done and implemented. Then, taking whatever has been agreed on previously in the process map and value analysis and putting for each activity if it’s value added or non-value added. The last rows are listing for each activity the matching root cause listed previously. For example, in sub-process 3 in activity 2 it is of medium importance, Non-Value Added and it has three root causes: 6 – Inspection 12 – Low skill level/Limited Resources 15 – Long Travel Time. As shown in Figure No.12 72 Figure 12: Sub-Process 3 Root Course Analysis (13) Sub-Process 3 Perform Corrective Maintenance on Equipment & Utilities Activity 1 Activity 2 Activity 3 Activity 4 Activity 5 Activity 6 Received Complaint/Request Travel to Site Inspect Complaint/Request Open Work Order Prioritize and schedule work Plan, Manpower and Materials (Estimates) L M L L L M NVA NVA NVA NVA NVA RC: 2 RC: 3 RC: 4 RC: 5 RC: 6 Req. by Procedure Low Skills/Limited Resources VA RC: 1 #N/A Inspection 6 To inspect the work and perform the 14 Planning Purposes Planning Purposes 14 2 To trouble shoot the problem To schedule the job No clear guidelines RC: 3 RC: 4 RC: 5 RC: 6 Req. by Procedure Low Skills/Limited Resources Low Skills/Limited Resources 12 Lack of materials and labor job RC: 1 #N/A RC: 2 Paperwork/Reports 12 Manual Paperwork Incomplete Information 10 2 to document cost, material, labor, To verify the complaint 12 Lacking manpower assigned for this To allocate manpower RC: 6 history, etc RC: 1 RC: 2 #N/A Long Travel Time 15 RC: 3 RC: 4 RC: 5 Planning Purposes Req. by Procedure Lack of Automation 4 Planning Purposes 14 No Bill of Material/availability of Long distance to the site To identify needed material To assign responsibilities Manual process RC: 2 RC: 3 RC: 4 RC: 5 Planning Purposes Approval Authority Material Not Available/non Stock To schedule the work Approval is required Item Hard to get material availability Scheduling is done manually RC: 3 RC: 4 RC: 5 RC: 6 #N/A Low Skills/Limited Resources materials RC: 1 #N/A RC: 1 #N/A #N/A RC: 2 #N/A Unavailability of a PC 5 12 Long Travel Time If far away, need to consider in schedule 73 RC: 6 19 15 Lack of Automation Approval Authority Get approval for costs 4 5 Figure 12: Sub-Process 3 Root Course Analysis "continued" Sub-Process 3 Perform Corrective Maintenance on Equipment & Utilities Activity 7 Activity 8 Activity 9 Activity 10 Activity 11 Activity 12 Assign the Work to Technician Prepare Material Request Collect Materials Obtain Work Permit Get Tools Travel to Site L L M M L M NVA NVA NVA NVA NVA NVA RC: 7 RC: 8 RC: 9 RC: 10 RC: 11 RC: 12 Req. by Procedure Material Not Available/non Stock Req. by Procedure Low Skills/Limited Resources Req. by Procedure 2 Accountability and followup 2 To get materials to do the job 19 Item 2 12 Tools not available with the technicians Safety/procedure/accountability Req. by Procedure 2 To perform the job Not available at the site RC: 7 RC: 8 Low Skills/Limited Resources Material Not Available/non Stock 12 Lack of highly skilled manpower/ RC: 9 19 Material is sometimes not available Long Travel Time 15 RC: 10 RC: 11 RC: 12 Paperwork/ Reports Low Skills/Limited Resources Low Skills/Limited Resources No car is available RC: 12 8 Warehouse far away A lot of paperwork Not enough tools for the technicians RC: 8 RC: 9 RC: 10 RC: 11 Approval Authority Low Skills/Limited Resources 12 specialized skills RC: 7 Planning Purposes 14 5 To get the right person to do the job Need to get approval RC: 7 RC: 8 RC: 9 Planning Purposes Coordination Low Skills? Limited Resources To provide an even distribution of Person not available to sign the work work Request RC: 7 RC: 8 Planning Purposes Planning Purposes To assign equipment to the person 12 #N/A RC: 11 RC: 12 #N/A Req. by Procedure 2 #N/A Each technician is assigned all tools when only a few are needed RC: 9 RC: 10 RC: 11 #N/A #N/A Req. by Procedure Security checks all tools upon entering To estimate the cost doing the work and leaving RC: 7 Training Long Travel Time RC: 10 Takes time to issue materials by MMD 14 14 Long distance to the site Transportation not available 13 Planning Purposes Carry the right tools for the job 21 To do the job the right way the first time 74 RC: 12 1 #N/A 15 Figure 12: Sub-Process 3 Root Course Analysis "continued" Sub-Process 3 Perform Corrective Maintenance on Equipment & Utilities Activity 13 Activity 14 Activity 15 Activity 16 Activity 17 Execute the Work Requested Inform Foreman of new job found Close Work Permit Input Actual Man-hour in the System Close Work Order H L L L L NVA NVA NVA NVA RC: 13 RC: 14 RC: 15 RC: 16 RC: 17 #N/A Coordination Req. by Procedure Foreman not available Safety/procedure/accountability To get labor cost for the work RC: 15 RC: 16 Total VA RC: 13 #N/A RC: 14 Planning Purposes 14 2 #N/A Identify/Record Costs Paperwork/ Reports To reschedule manpower & material 22 Planning Purposes VA: NVA: 14 To finish job RC: 17 8 Identify/ Record Costs 22 to document cost, material, labor, To provide reports history, etc. RC: 13 #N/A RC: 14 RC: 15 RC: 16 Coordination #N/A Planning Purposes To communicate to the foreman RC: 17 14 #N/A for budgeting purposes RC: 13 RC: 14 RC: 15 RC: 16 RC: 17 #N/A #N/A #N/A Cost #N/A Identify cost and experience of equipment RC: 13 #N/A RC: 14 #N/A RC: 15 #N/A RC: 16 RC: 17 #N/A Low Skills/Limited Resources Unavailability of a PC 75 12 2 15 Summarizing these data will result finding out that planning purposes, low skills / limited resources and required by procedures are the main reasons for the non value added activities for subprocess 3 as shown in the following chart: Chart 1: Sub-process 3 Root Cause Analysis Root Cause Analysis (13) Sub-Process 3: Perform Corrective Maintenance in Equipment & Utilities Root Cause Categories Planning Purposes Low/Skills/Limited Resources Req. by Procedure Long Travel Time Approval Authority Material Not Available Stock Item Paperwork/Reports Identify Record Costs Lack of Automation Coordination Inspection Incomplete Information Req. by Policy Rework Training Interruptions Inadequate Tools & Equipment No Operating Manuals for Test Equipment Required by Outside Agency Poor Quality Material Weather Non-Standardization 0 1 2 3 4 5 6 7 8 . # of NVA Activities Identified with Root Cause 77 9 10 3.4.6 Leading Practices and Site Visits Leading Practices is a major function in the business process improvement. It suggests that there are in the world companies or government agencies, which are doing the service better and more efficient. A leading Practice Pursuit focuses on identifying practices that are substantially better than what currently exist in the Company. It stretches beyond the company’s own industry to find common or universal practices. Eighty percent of the effort goes into studying company practices that deliver their higher performance and only 20% of the effort is focused on collecting comparative measures. The first step in this process, is to ask and communicate with others for good service providers and to search by any mean for a better service like searching in the Internet and periodicals in the field related to attributes to be put in mind during searching and communication. These attributes was separated into two categories one for Company attributes such as asking if the company looking for is one the best and fortunate 500 Companies in the world, does it have buildings and facilities scattered, is it a medium to large company and is Janitorial work performed using internal resources or using outsourced measure, etc. The other attribute are related for the process attribute for the future such as, installing low 78 maintenance materials and equipments, is employee moral high, are customers satisfied and they have little company and quality rectified, etc. The following are the Company and the process for the future attributes (13) : Utilizes an advanced maintenance techniques/systems Maintenance activities are centralized Maintenance Activities are decentralized Is it one of the most fortune 500 company in the world Provides a variety of maintenance services Is it a vendor which provides systems, equipment & tools Large company who has outsourced it's maintenance activities Attrition is low Maintains a large landscaped area Buildings and facilities are scattered Is a medium to large sized company Performs Janitorial work using internal resources Janitorial activities are outsourced Maintains a variety of different types of buildings and functions. 79 And the following are the process attributes for the future: Installs low maintenance/durable equipment Simplified customer friendly maintenance process requiring minimal approvals Employee, Technician morale is high Materials process provides prompt delivery Customers have few complaints which are quickly resolved and are highly satisfied Few customer complaints are received Provides fast response to maintenance requests Technicians are highly trained and have a fast learning curve The latest technology is used Uses one ideal maintenance process for all types of maintenance requests Policies and Procedures are clearly defined and well documented Applies a new approach to "Preventive Maintenance" Utilized E-Commerce and Internet/Internet technology Provides cost effective maintenance Utilizes modern tools and equipment Utilized standardized contracts Established low maintenance landscape 80 Process minimizes the storage requirements for materials Electronic requests and responses are used for maintenance services After survey, 51 companies (13) matched the attributes the teams are looking for or at least some of them. Then, two sets of Questionnaire were set up. The first set is simple and easy question to be replied and for general information such as, general information about the company, general information about the services that the team is looking for, etc. 18 of the 51 companies have responded and agreed to participate in the survey. After that there was an agreement by the team and the process manager to fund the visit for the following: - Dubai Airport, Department of Aviation - Dubai Municipality - Dubai Ports Authority - Saudi Aramco After the confirmation with those companies a second set of questionnaire have set up. This questionnaire is a detailed one of how they are doing in detail the service for example. In operation 81 how do you dispatch service, in maintenance describe the maintenance process, etc. and this questionnaire was sent for the companies will be visited so that they will be prepared. Finally, for one week different teams visited each company and get all information they need to be used later for further study in the project. The following are sample of some results from leading practices research For maintenance practices: 1. Equipment Lifetime Management (ELM) 2. Intelligent Buildings 3. Hand-Held Pen Based Computers 4. Reliability Centered Maintenance (RCM) 5. Condition Based Maintenance 6. Periscope Concept For Contracts: 1. Automated Contracting Process 82 2. Service Level Agreement " this would one of the final recommendations" For E-Procurement 1. Electronic Maintenance Materials Ordering Process 2. Electronic Commerce 3.5 Future State Phase: 3.5.1 Introduction During current state phase, the team studied how SEC is doing thing at present during their study. In the future state phase the team is trying to create a better future for the process. During this phase, the actual “redesign” begins. Starting from this phase up to the end the team will attend full time. First, the team will have training in what supposed to do during future state. Most of the time spend is analytical thinking. The continuous communication with others is very important. Sometimes the team would be distributed into two or three teams to conduct certain tasks which does not need the full team to participate in. The team has to review again all current state documents before starting the future state and compile with it the leading practices findings. 83 The first step in the future step is conducting future state workshops as illustrated in the next section. 3.5.2 Conducting Future State Workshops: In this part of the future state, sessions were formed which consist of process experts and customers to take part in the redesign stage. These participants should come from both inside and outside the existing process. This is due so that the inside participant of the process may reveal information about the existing process that was not uncovered in the current state analysis. And having the people who will be the future process owners will help to ensure that the changed process will succeeds once it is implemented. The outside is as important as the inside and its purpose is due the the perspective of someone who will look at the process with a “fresh eye” and raise questions about assumptions that may not be obvious to insider who might be too close to the process to see this. A technology specialist will provide insight as to how technology can be applied to participant prior to their participation in the workshops. Documentation of the session’s ideas is very important. Then, similarly as in the current state the same invited quests previously invited to take part again in the customer improvement ideas for one week. They were also briefed on the current state analysis, and then they start showing their ideas. The 84 key ingredient is to provide an environment free of criticism for creative and unrestricted explanation of options or solutions. Brainstorming will help to break free of old, in effective ideas. The major rules that assist to manage these sessions are set a time limit, clarify the service process to be considered, documentation, clarification of ideas and eliminate duplication. The session should be fun and free from stress. Conducting creative thinking exercises prior to taking business process redesign can improve the innovative mindset of a workshop. Team members should try to make the meetings more fun. Negative statement about ideas should be prevented like it has been tried before or there is no authority to do that ….etc. The result was of more than 1,200 ideas and the following are samples of these ideas and the concentration is on sub-process3: 85 Table 7: Future State Workshop No. Source Brainstorming Idea Category 1 Team Have MMD Deliver materials to the job site Material delivery 2 WS#1 Schedule PM based on counters Material delivery 3 WS#3 Use Express Mail to deliver material Material delivery 4 WS#3 Delivery of material by MMD Material delivery 5 WS#3 Deliver material using DHL Material delivery 6 WS#3 Use DHL to deliver materials from remote warehouses Material delivery 7 WS#3 Materials arriving on site should be delivered to the user by the material man Material delivery 8 WS#3 Make an agreement/partner with Aramco to supply materials Material delivery 9 WS#3 Establish only one user and delivery directly to user by trucks Material delivery 10 WS#3 MMD should deliver only original parts not substituted ones Material delivery 11 WS#3 Provide special boxes to transport sensitive electronic equipment Material delivery 12 WS#3 Create a special card for MIR rush materials to expedite delivery Material delivery 13 Team Provide replacement of equipment which needs repair with stand-by equipment Equipment Utilization/Replacement 14 WS#2 As new models purchased ask about better technology Equipment Utilization/Replacement 15 WS#2 Provide loaner machine during CM Equipment Utilization/Replacement 16 WS#2 provide fax machines for security gates "specially remote areas" Equipment Utilization/Replacement 17 WS#2 Provide mobile telephone for key people Equipment Utilization/Replacement 18 WS#2 Use equipment replacement policy rather than fixing the equipment in site Equipment Utilization/Replacement 19 WS#2 Zero book value equipment to be replaced instead of repair Equipment Utilization/Replacement 20 WS#2 Use portable A/C as back up Equipment Utilization/Replacement 21 WS#3 Jubail warehouses needs A/C Equipment Utilization/Replacement 22 WS#3 Supply computer at security gate Equipment Utilization/Replacement 23 WS#3 Provide pager for each department involved in facility maintenance Equipment Utilization/Replacement 24 Team Establish a database for information based on failure types Troubleshooting 25 Team Train users to troubleshoot minor P.C. problems over the network Troubleshooting 26 Team Implement remote diagnostic capability to resolve P.C. problems over the network Troubleshooting 27 WS#2 Use the latest instruments for trouble shooting (i.e. Infrared) 28 Team Develop good planning to prepare materials Material Planning/Availability 29 Team Allow OSD/ERU to stock fast moving spare parts Material Planning/Availability 30 WS#1 Specify the correct material on the PM sheet Material Planning/Availability 31 WS#1 Store frequently required spare parts in OSD warehouse Material Planning/Availability 32 WS#1 Purchase only high quality material Material Planning/Availability 33 WS#3 Relocation of above storage areas to lower storage areas frequently Material Planning/Availability 34 WS#3 Replenishment of stock should be evaluated by users Material Planning/Availability 35 WS#3 Material installation by the vendor Material Planning/Availability WS#3 Regular status report of ordered material should be submitted to users Material Planning/Availability 36 86 Troubleshooting 37 WS#4 Standardize all materials to all areas Material Planning/Availability 38 WS#4 keep Min/Max of stock furniture in OSD warehouse 39 Team Provide electronic hand held devices for collecting and inputting data Electronic Data Input/Reports 40 WS#1 Computerize all PM sheets Electronic Data Input/Reports Material Planning/Availability 41 WS#1 Provide status repot for same equipment (copy for users) Electronic Data Input/Reports 42 WS#1 Buy equipment locally made Electronic Data Input/Reports 43 WS#2 No more papers to utilize history Electronic Data Input/Reports 44 WS#2 Record work done by video tape as learning tool Electronic Data Input/Reports 45 WS#4 Establish on-line status report Electronic Data Input/Reports 46 Team Provide incentives to the skilled workers to improve quality Worker Recognition/Incentives 47 WS#1 OJT’s should be graded depending on task completion Worker Recognition/Incentives 48 Team Reduce the warranty period for office machines to 1-2 years Warranty of Equipment 49 WS#1 Extend warranty for new equipment Warranty of Equipment 50 WS#1 New equipment or facility should be extended warranty for 5 years Warranty of Equipment 51 WS#2 Increase agent warranty period Warranty of Equipment 52 Team Specify criticality of equipment Maintenance Practices 53 Team Do not perform corrective maintenance on very far areas Maintenance Practices 54 Team Train remote area requestors to perform the job themselves Maintenance Practices 55 Team Assign permanent technicians to particular pieces of equipment Maintenance Practices 56 TED Initiative maintenance instead of requesting it. Maintenance Practices 57 QPPD Allow the customer to open the W.O. Maintenance Practices 58 WS#3 To establish a central fabrication shop to (assemble fabricate) parts Maintenance Practices 59 WS#4 Remove maintenance type project from EDSD & OSD/TSU Maintenance Practices 60 WS#4 Establish a longer planning of maintenance facilities Maintenance Practices 61 WS#4 Remote areas without maintenance should be added to OSD Maintenance Practices 62 WS#4 Standardize all office space & project all relocation Maintenance Practices 63 WS # 1 Lease equipment instead of purchase purchase/Lease 64 WS # 2 EDSE to involve maintenance groups in selection of new equipment purchase/Lease 65 WS # 2 Lease equipment / machine purchase/Lease Team Reduce paper work in the maintenance process Electronic form/Paperwork/Approval Team Status of material should be printed in work orders Electronic form/Paperwork/Approval Team Preparation of department request slips should be done electronically Electronic form/Paperwork/Approval Team Use the intranet to request material electronically Electronic form/Paperwork/Approval Team Computerize the preparation of CAF like MIR/MPR Electronic form/Paperwork/Approval WS # 2 Have all work orders electronically Electronic form/Paperwork/Approval WS # 2 Better initiation of forms Electronic form/Paperwork/Approval 66 67 68 69 70 71 72 73 WS # 2 Electronic form/Paperwork/Approval Create equipment installation forms 74 Team Develop technician to specialize in certain field of expertise Training & Skills 75 HSD Cafeteria inspector must be expert on foods, sanitation etc Training & Skills 76 WS # 2 Include maintenance contractor in the training programs Training & Skills 77 WS # 2 train operator to do minor repair Training & Skills 78 WS # 2 Cross training for technicians Training & Skills 79 WS#3 Any reclaimed materials being requested should be approved by the foreman Approval Authority 80 WS#3 Increase petty cash authority to SR 1000 for superintendents Approval Authority 81 WS#3 Capital equipment less than SR 10,000 should only require manager authority Approval Authority 87 82 WS#3 Provide approval authority for petty cash up to SR 1,000 to unit head Approval Authority 83 WS#4 Eliminate manager approval for project already approved in the operating plant Approval Authority 84 WS#4 Standardize the categories capital project from EDSD Approval Authority 85 WS#4 Lower approval authority to unit head Approval Authority 86 WS#4 Increase authority level Approval Authority 87 WS#4 Single source contact approved by superintendent Approval Authority 88 Team Utilize GPS to locate equipment Automation Tools 89 Team Use robot/cameras for project/site evaluations Automation Tools 90 Team Use the internet to receive customer complaints Automation Tools 91 Team Use a scanner to encode trouble Ticket and Work order Automation Tools 92 Team Allow customer to input complaints electronically in a trouble ticket Automation Tools 93 Team Provide access to Vendor's stock of spare parts to check availability Automation Tools 94 WS#1 Distribute the PM electronically to all technicians Automation Tools 95 WS#1 Use hand held based computers Automation Tools 96 WS#1 Build intelligent in PM program based on perimeters Automation Tools 97 WS#1 Provide robot to do PM in hazard area Automation Tools 98 WS#1 Provide hand based computer to all technician Automation Tools 99 WS#1 Reduce paper by using hand held computer Automation Tools WS # 1 Establish an automation service Automation Tools WS # 1 Make information an easily available to everyone using CMMS. Make available on PC in a customized report Automation Tools WS # 1 Easy to get information from CMMS Automation Tools WS # 1 Provide code to reduce the amount of input into CMMS. Codes will also be used for future analysis Automation Tools WS # 1 Lifetime of major parts of each equipment to be specified on the PM work order so and alarm will be generated automatically if it is replaced prior to its expected life time Automation Tools 106 WS # 1 provide energy conservation programmed Automation Tools 107 WS # 1 Use latest technology Automation Tools WS # 1 system should provide warning when the same CM work is needed two times in a row Automation Tools 109 WS # 2 Receive complaints by email Automation Tools 110 WS # 2 Provide drawing of equipment in the system Automation Tools 100 101 102 103 104 105 108 111 WS # 2 Automate controls to minimize working time of the equipment Automation Tools 112 WS # 2 Use code/task to analyze future problems Automation Tools 113 WS # 2 have all complaints through emails Automation Tools 114 WS # 2 Provide more lamps indicator to specify problems Automation Tools 115 WS # 2 have the system self diagnose it self using internal logic Automation Tools 116 WS # 2 have historical database for each equipment Automation Tools 117 WS # 2 provide pc based system to prioritize request automatically Automation Tools 118 WS # 3 make standard material available through the internet Automation Tools 119 WS # 4 Establish electronic approval for design package Automation Tools 120 WS # 4 All drawing to be generated electronically Automation Tools 121 WS # 4 Provide cad training to all engineer and foreman Automation Tools 122 Team Issue permanent work permits Procedure 123 Team Establish clear guidelines Procedure 124 Team Obtain work permit by phone Procedure 125 Team Contractor should have his own ID Procedure 126 WS # 2 Provide overhauling procedure of the CM Procedure 127 WS # 2 No work orders less than 2 hours Procedure 128 WS # 2 Provide work permit immediately Procedure 88 129 WS # 2 Apposite hours coverage during week ends& holidays Procedure 130 WS # 2 Separate urgent CM from normal CMs Procedure 131 WS # 2 Unscheduled non emergency Procedure 132 WS # 2 Highly repeated problem should be reviewed Procedure 133 WS # 2 Minimize the operation time Procedure 134 WS # 2 use high quality spare parts Procedure 135 WS # 2 Annual PM to be outsourced Procedure 136 WS # 2 Improve the language of communication for manuals Procedure 137 WS # 2 have fixed dates Procedure 138 WS # 2 have the technicians signed for the work done Procedure 139 WS # 2 To install the operating manual in the CMMS Procedure 140 WS # 2 Assign employees to work in the weekends Procedure 141 WS # 2 Equipment retirement date should be printed regularly Procedure 142 WS # 2 Simplify emergency fund Procedure 143 WS # 4 Design package must be reviewed by requestor Procedure 144 WS # 4 Establish a definition what emergency Procedure 145 WS # 4 Define the involvement of the user Procedure 146 WS # 4 All design packages should be completed by 2nd quarter Procedure WS # 4 Categorization of capital project should be done by OSD not by EDSD Procedure WS # 4 Project above 50,000 SR should be implemented otherwise it should be done through unit rate Procedure 149 WS # 4 Total cost of the project must be shouldered by requester Procedure 150 WS # 4 Standardize forms for SFC & LFC Procedure 151 WS # 4 Maintenance of rented building should be done by owner Procedure 152 WS # 4 Limit to 4 contractor for long form contract Procedure WS # 4 Make rotational assignment for department/division involved in reviewing design package Procedure 154 WS # 4 Using one drawing forms for all facilities Procedure 155 WS # 4 Include point of view before submitting to EDSD Procedure 156 WS # 4 Document out of policy request/work order Procedure 157 WS # 4 Locate design engineer in the maintenance organization Procedure 158 WS # 4 Use virtual reality partition Procedure 159 WS # 4 Avoid hiring of unqualified employee Procedure 160 WS # 4 Apply penalty clause for SFC Procedure 161 WS # 4 Award good contractors Procedure WS # 4 No need for any second approval if the project approved in the operating plan Procedure WS # 4 Project below 300,000 SR must be reviewed and approved in the operating plan Procedure 164 WS # 4 Involve OSD from the beginning of all PMD project Procedure 165 WS # 4 For SFC no need to go contracting department Procedure 166 WS # 4 No need for IDs for none restricted areas Procedure 167 WS # 2 Spare parts should be nearest to user Centralization 168 WS # 2 Standardize equipment in remote areas Centralization 169 WS # 2 Satellite work shops in remote areas 170 SOD Establish frequent surveys and services measures Planning & coordination HSD Requester must be informed of the status of his request, if the job cannot be done on time Planning & coordination 172 QPPD Establish a single point of contact for the customer as a planning Planning & coordination 173 HOA A complaint center must be establish Planning & coordination HOA requestor must get feedback form the department concerned when requesting for services Planning & coordination 147 148 153 162 163 171 174 Centralization 89 3.5.3 Creating the Future State Redesign: The list of improvement ideas created during the re-design workshops provides a good base for redesigning the process. The BPI team looked at this list as a collection of improvement ideas thoughts which will help lead the team toward major changes to the process not seeing them as an individual ideas each one separately. Combining these ideas with the leading practices collected form the leading Companies visited also provides another creative stimulus to the team’s process re-design effort. Defining categories that describes the major areas of improvement that were discussed during the re-design workshops or during the leading practices site visits was the first step for the re-design effort is to have. Then, creating a category that best describes each item on the list of ideas generated during the workshops and identify. Sort the list by category. Each category now has a list of similar recommendations for improvement for a particular part of the process. The team used the ideas contained within each category to combine and redefine into larger improvement recommendations. Then, these major improvement ideas were written on sheets of paper using large letters and they posted category title from which 90 them on a large wall under a they were designed. The major improvement ideas posted on the wall represent the changes for the re-designed process. entire re-design and The wall provides a visual picture of the all recommendations can be compared, combined and discussed. The team spent several weeks reviewing the ideas on the wall, looking for interrelationships, combining similar improvements ideas, removing Improvements which do not fit the overall change, resolving conflicts between ideas and developing unique improvements from their discussions. The result will be a list of major improvements. The next step was for the team to conduct a thorough research on each improvement to develop more detail, collect costs and identify benefits, and to learn more about the spirit of the recommendation being proposed. The team started also to developing a business Case for each recommendation During this detailed investigation. The improvements that are obviously a good ideas and are easy to implement requires a small investment of time and money is called Fast Track or Quick Fix actions that can provide immediate benefits and additional momentum for the project. These Quick Fix improvements are listed by the team along with the primary department that should take responsibility for implementation. Examples of quick fix recommendations by the team are as follows (13) : 91 identified Provide fax machines in restricted areas (Telecommunications) Create a standard contract for all contracted work such as repair of equipment, renovation and Janitorial/Landscaping work (FMD). Use female Janitors to clean ladies workroom as part of the health services contract (HSD, QD) which has not been approved. Purchase universal tools and power tools like use of hydraulic lift instead of scaffolding (FMD). Purchase wireless diagrams at sites to be used for technicians. (FMD). Other which need express workshop was formed between Security Department and Facilities Management Department to clear the issue of fire alarm system double responsibilities. It was not clear whose responsibility is it. That is why an express workshop was conducted and the results were as follows (13) : Initial response to an after hour alarm at locations where a security guard is available, will be made by the Security Guard. If the alarm cannot be silenced, then the Shift Supervisor will 92 contact. If it can not be silenced by the Shift Supervisor, he will contact the closes FMD Technician (Until ISD gets resources). Suggestion: to add in the next contract a clause for an additional manpower for responses. o Increase frequency of detector cleaning (PMs). o Revise the existing general instruction (G.I.) for the maintenance of Fire Protection Equipment to include initial response by Security Personnel. o Initial response to fire alarm during working hours will be by FMD. o Provide on call duty Fire Protection Personnel with a mobile phone so he can be contacted easily in case of an emergency. o Place the responsibility of preventive maintenance (PM) and corrective maintenance (CM) for Fire Protection Equipment/System with Industrial Safety Department (ISD). o Develop the basic course and train security operations staff to perform the initial response to fire alarm after working hours 93 Finally, this section the communication comes again as a major factor in which these changes has to be discussed with the involved Departments and customers to have their commitment, feed back and support. 3.5.4 Develop Business Case for Each Change Recommendations: Developing a compelling business case represents an important milestone in the team’s work. An effective business case enables the team to receive funding for the project. A measure of the success of BPI initiative is by prioritizing the solution based on what design elements produce the greatest benefits, and prepare an accurate budget for project implementation. The most obvious reason for putting together a BPI case is to justify the resources necessary to bring a BPI effort into action. The BPI business case is the one place where all relevant facts are documented and linked together into a cohesive story. That mean that the business case should not be only financial document. While all business cases should include financial justification, it should not be the only purpose of the document. The Business Case should answer this question; How much money, people, and time will be needed to deliver the solution and realize the benefits? The writing of the 94 business case forces the BPI team to sit back and reflect on all of the work they have so diligently completed. It is too easy for the team to continue to plug away toward the end result and fail to document the work they’ve already accomplished. This is especially true during the concept and design stages of any BPI effort. Therefore, the business case serves to help the team to capture the knowledge they’ve developed about the BPI project. The major items included in a BPI Business Case are: (13) A completed economic analysis using key indicators and net present Cash Flow over 5 years. Intangible Benefits of Recommendations. Risks associated with implementation. Assumptions and Generalizations. Impact to the strategic direction of SEC Eastern Region. Impact to SEC Eastern Region Plans. Brainstorming is a good tool to for the team to start to develop a business case. The team is subdivided into sub-teams (the team of two) and then they brainstorm the recommendation they are responsible for: 95 following for each All of the costs associated with the recommended improvement. All of the tangible benefits of the recommended improvement. All of the intangible benefits of the recommended improvement. The team considered the following area when they are brainstorming (13) : One time cost and benefits those also known as start-up cost needed to initiate the recommendation and is done only once such as: Plant Equipment: Facilities People Investment: Recruitment and Training New Technologies: Software, Hardware and Telecommunication On going cost, these are annual costs of the improvement such as: Overhead Cost: Telecommunication charges. 96 Charges, Facilities Labor Related Costs: Maintenance, Productivity, On-going Training. Equipment Costs: Material, Engineering, Contactors, Suppliers. Administrations Costs: Marketing, Service Cost, Support Staff. On going benefits, these are the money saving which will occur every year from the point that the recommendation is implemented such as: Material Saving: Equipment, Supplies. Labor Related Saving: Skilled Labor, Productivity, and Maintenance. Capital Saving: Engineering, Contractors, Material. Intangible Benefits: Customer satisfaction, Motivation, Safe working environment, avoided costs. The BPI Team collected as much detail as possible to quantify the costs and benefits. Also, the team developed a high level implementation plan to capture additional implementation costs. Major costs such as full time resources that will be required to 97 manage the implementation (i.e. Implementation Manger, etc.) were identified. Cost and Benefits can be broken into two categories. Hard costs and benefits and Soft costs and benefits. Some main differences between hard cost and soft cost are as follows (13) : Hard Costs are expenses that the Company will pay to implement a recommendation which is over the above what is currently planned in the budget. Some examples could include: Hiring net new positions. Purchasing new Equipment. Buying Materials. Hiring Contractor Service. Soft Costs are expenses that the Company is already paying for even if the recommendation would not be implemented. Some examples could include: Using existing labor for new work. Using existing equipment. Using existing computers. 98 Hard Benefits will provide cost savings that improves the Company’s financial bottom line. These savings may result in reductions in the next budget cycle. Some examples could include: Reduced maintenance. Reduced materials purchase. Fewer filled positions. Less equipment needed. Soft Benefits provide opportunities to reduce workload or prevent expenditures that do not result in an improvement to the Company’s financial bottom line. Some examples could include: Reduced labor hours not resulting in manpower reduction. Improved quality and customer service. Improved utilization of equipment which does nor result in reduction of equipment. The BPI Business Case for each recommendation will compare the “Hard Costs” and “Hard Benefits” only. “Soft Costs” and “Soft Benefits” is included but not considered as a major part of the cost-benefits analysis. Not all BPI Recommendations need to have 99 more hard benefits than costs to be approved. It is important to document the net costs and the intangible benefits that can be achieved. If the intangible benefits are worth more to the Company than the net costs of the recommendation, it may still be approved for implementation. Finally, in this section, teams have to narrow list of improvement to the one that will have the best impact on the process by considering all factors associated with that decision. All the calculations for this section would be shown in the recommendation improvement chapter. 3.5.5 Developing Implementation Plan for Each Change Recommendation: To accurately reflect all of the expected costs, when the expenditures will be spent and when the benefits will be realized, the key implementation information is required by the BPI Business case. The best way to determine this information is to create high level an implementation/work plan for each of the BPI team recommendations. In addition, the team will need to identify other resources that will be required to manage the overall implementation project during the brainstorming stage. An Implementation Project Manger is one additional resource that is needed to assist the implementation of the BPI recommendations. Project management can be thought of as a set of principles and techniques for 100 controlling project risks and capturing opportunities as projects are brought to success. This person is critical to assuring the successful implementation of the BPI recommendations. The role of the project manager in project management is one of great responsibility. It’s the project manager’s job to direct and supervise the project from beginning to end. The project manger must define the project, reduce the project to a set of manageable tasks, obtain appropriate and necessary resources, and build a team or teams to perform the project work. The project manger must set the final goal for the project and must motivate his workers to complete the project on time. Other additional resources were selected to participate during the implementation phase from various support of the BPI recommendations and they came organizations. A full time Information Technology Specialist was selected since the BPI recommendations have a great deal of automation involvement. These additional resources were included as part of the BPI business Case and also were highlighted in the Future State Design presented to management for approval. The implementation plan for each change recommendation will be shown later with completed future state improvement recommendations. 101 But the project implementation mobilization need during the implementation plan for the recommendations is as follows: Figure 13: Project Implementation Mobilization (13) Project Manager FMD (Full Time) 2 years 1 FMD Coordinators TCD Project Coordinators CRD Project Coordinators 2 ITD Project Coordinators (Part Time) 2 years (Part Time 25%) 2 years (Part Time 25%) 2 years (Part Time) 2 years TCD Project Coordinators (Part Time 25%) 2 years This will require the hiring of one full time FMD resources for two years and One ITD resource for one year. The remaining resources will be provided using internal resources. Part Time Members from various participation from various departments such as facility maintenance (FMD), power transmission (PTD), generation (GD), comptroller (CRD), telecommunication (TCD), information technology (ITD), relation & media (R&MD), etc… 102 Finally, again gain consensus on final recommendation to be presented by discussing it with the concerned Department Manger, and Vice President concerned especially some resources will be taken from them for a period like providing manpower for almost two years. In the recommendation improvement analysis chapter, the implementation team member contribution is shown. 3.6. Implementation Plan Phase 3.6.1 Introduction The last phase in the BPI project is the implementation phase. It is mainly implementing the implementation plan previously discussed and it will be presented in the next chapter in developing each recommendation business case model in the recommendation analysis. Executive of a carefully developed change plan separates the high performance from the low successful BPI projects. 3.6.2 Mobilizing for Implementation With the approval of the BPI recommendations by Saudi Electricity Company Executive Management it is time to begin mobilizing for implementation. Executive Management will approve not only the recommendations but also the budget and the resources required for implementing the recommendations. It is very important to begin the 103 implementation very soon after the approval is provided. At this time the momentum and excitement about recommendations and their implementation are very high. Delaying the implementation for more than one (1) month risks losing this momentum making it harder to get the implementation project started and on track. The first and very crucial step in mobilization is for the Executive Sponsor and Process Manager with input form the BPI core team to select an Implementation Project Manager. This person will have full responsibility for the implementation of all BPI recommendations that were approved. It is strongly recommended that a member of the original BPI team be selected to fill this temporary full time and one the team members were selected and was given two years out of his work. His roles include also establishing the implementation project team, arranging for facilities and securing the budget. 3.6.3 Developing Charters and Work plans Some of the BPI recommendations will be interdependent. This means that one recommendation cannot be implemented without another being implemented. Prior to inviting the implementation project team to participate in the project, the Implementation 104 Project Manager should identify these interdependencies and decide how to group similar or interdependent recommendations. 3.6.4 Monitoring and Managing the Status: The charter, work plan and assigned responsibilities for the BPI recommendations because are the basis for managing the implementation project. Process of each recommendation will be monitored by the implementation Project Manager. He will request updates from each of the teams, individuals, and/or departments assigned to implement the recommendations and project work plan will be updated with this information. The Project Implementation Manager will evaluate the project performance by: Analyzing significant variances in schedule and budget Defining and quantifying the problems Analyzing the problem causes Determining the best solutions options 3.6.5 Measuring find results of implementation The implementations Project Manager will report have many reports to monitor the status of the overall project and here are some Sample Management Status Reports 105 Accomplishments for This Week Status Against Work plan Issues and Barriers Lessons Learned Plans for Next Week Morale of Project Team 106 Chapter 04 Recommendation Improvements Analysis 4.1 Introduction Putting what has been discussed earlier in building the business cases, some prove to very much not feasible either it is not cost effective not time saving. After evaluation and analysis of the business case models which was described earlier in chapter three item # 5.4 which explains how it is build up, final recommendations agreed on were 11 recommendations. 4.1.1 Recommendations Analysis The eleven recommendations approved by the team and SEC-ERB management were as follows: 1. Utilize Unit Rate Contracts 2. Maintenance Web Page 3. Maintenance Call Center 4. Electronic Equipment Repair Shops 5. Maintenance Free Materials 6. Service Level Agreement & Chargeback 7. Predictive Based Maintenance 107 8. Hand Held Data Input Devices 9. Make CMMS the Standard Database 10. Improve P.C. Repair and Support Network 11. Improve Material Delivery By analyzing recommendation # 1 " Utilize Unit Rate Contracts" which would be clear about the other recommendations how it was built up. The steps of analyzing the recommendations are as follows: First, the team starts by putting the current situation and the recommended change description and details about the recommendation contents. Second, is the summary of Benefits of Utilize Unit Rate Contracts and summary of all the figures of hard and soft cost benefits, soft costs and benefits, what affect on the goals set in the beginning in the charter and if there are any positions reduced, which all will be calculated next. Third, preparing a cost worksheet, in recommendation # 1 for example there are no hard costs but there are two soft costs. One is 25,000 SR the cost to develop unit rate contract and the other is the implementation plan cost for labor charges which cost 17,000 SR. 108 Fourth, is calculating benefit of Utilizing Unit Rate Contract. For hard benefits 128,178 SR is saved annually. This reduction in cost came mainly from two manpower positions reduction (one engineer and one draftsman). And for soft benefits, a total of 39,082 SR will be saved from time spend by the contract coordinator to oversee the 15 contracts being eliminated. Fifth, preparing hard cost and benefits economic analysis. As discussed earlier it has to be done for five years. This process starts with determining each year how much cash to be spent and cash saved. Adding this will show the net cash every year if it inflow or outflow. Then, there is a factor called discount facts of 7% for the adjustment of how much an amount of money worth for the company in the second, third, fourth and fifth year. A net result show an amount of 434,166 SR will be cash inflow which is positive for the Company. Sixth step in study the recommendation is the economic analyzing of soft costs and benefit. As done earlier cash outflow is calculated from cost and benefit worksheets done earlier. For example, in the fist year there is a cash outflow amounted 42,000 SR the items in the cost worksheet which 109 are the development of the unit rate contract itself and the implementation plan cost. A net cash assessment reveal that a n amounted of 129,459 SR of cash inflow to the company during the five years. Last step in each recommendation, is building the implementation plan. The Plan consists of 6 tasks to be implemented in 10 months to complete this recommendation and it is showing the man hour’s participation in each task. These entire steps are summarized in the summary of costs and benefits worksheet. The following are the Project Final Recommendations which consist of the business case model and the implementation plan (13) : 110 IMPROVEMENT RECOMMENDATIONS Table 8: Recommendation # 1 " Utilize Unit Rate Contracts" 1: Utilize Unit Rate Contracts Current Situation Recommended Change Minor building renovation, modification, expansion, remodeling, demolition, and concreting if performed utilizing short form contracts. It currently takes an average of three months to establish a short form contract and up to one year for a long form contract. Utilize Unit Rate Contracts to reduce the number of Short Form Contracts for non-technical skills such as: Plumbing, Painting, Carpentry, Concreting, Trenching, Backfilling, Demolition. Unit Rate Contract will simplify the process for getting contractor assistance in providing labor for non-technical work. Currently, a short form contract must be established which can take up to one year. Also the cost for labor using a short form contract is usually 5% higher than using a Unit Rate Contract. The Unit Rate contract will drastically reduce the time required to get labor for these non-technical jobs and SEC-ERB will pay less for the work. Examples of the frequent work, which is being conducted over and over again include: 111 Painting of traffic parking lines. Painting of walls. Partition walls. Doors and windows. Concrete work and plastering. Waterproofing. Wood Working. Metal Working. Plumbing. Table 9: Summary of the Benefits "Utilize Unit Rate Contracts" Summary of the Benefits Utilize Unit Rate Contracts Reduce the number of short from contracts by 15 (45 reduced to 30). Reduce paperwork by 25%. Reduce contract preparation. Reduce travel time. Improve the quality of work. Improve customer satisfaction. Provide quick response to customer requests. Better manpower utilization. Reduce maintenance costs. 112 Figure 14: Summary of Costs and Benefits “Utilize Unit Rate Contract” Type of Benefit Cost Cycle Time Quality Impact on Goals High Med. 1 2 3 4 5 6 7 8 9 10 11 12 13 14 Hard Costs and Benefits (SR in Thousands) Annual Impact Economic Analysis (Cash Flow) Net Start Benefit Cost Net Up Costs Year 1 2 3 4 5 5 Yr. Total 128 0 128 0 0 120 112 104 98 434 5 30 5 Yr. Total 129 Low Soft Costs and Benefits (SR in Thousands) Annual Impact Economic Analysis (Cash Flow) Net Start Benefit 39 Cost 0 Net 39 Up Costs 42 Positions Reduced/Avoided OSSD Engineer Draftsman 113 1 1 Year 1 -3 2 36 3 34 4 32 Additional FTE Savings 0.9 FTEs in FMD BENEFIT/COST ANALYSIS COST WORKSHEET Project Description Table 10: COST WORKSHEET "Unit Rate Contract" Description Capital Computer Hardware Computer Software Facilities Hard Soft Assumption Cost to develop a Unit Rate Contract 25,000 SR 25,000 or the same cost as developing one short form contract. Implementation Costs 17,000 See implementation plan for details. 0 42,000 114 BENEFIT/COST ANALYSIS BENEFIT WORKSHEET Project Description Table 11: BENEFIT WORKSHEET "utilize Unit Rate Contracts" Description Hard Quantitative Manpower Reductions One FMD draftsman position reduced. 33,984 Manpower Reductions One FMD Engineer Position Eliminated 56,640 FTE Reductions Better Contract Pricing Paper Work Reduction Transportation Savings Cycle Time Reduction Quality Improvements In-tangible Benefits Contract Coordinator II will have less time needed to oversee and contribute to the 15 contracts being eliminated. The cost of a Unit Rate contract is estimated at 5% less than a Short Form Contract for the same work. Fewer Short Form Contacts with require less paper. Soft Assumption 15 out of the 40 contracts will be eliminated and covered through a Unit Rate Contract. Currently one person can complete 3.42 contracts in a year 10 projects eliminated which require a Scope of work / 3.42 projects per person = 2.92 employees. FTE Time Reduced: This time is reduced in the effort to create 10 contracts which require a Scope of Work 1 Draftsman @ SR 12/hr*2,832hrs/yr = SR 33,984 1 Engineer @ SR 20/hr*2,832hrs/yr = SR 56,640 39,082 1 Contract Coordinator 11 @ SR 15/hr*2,832 hrs/yr = SR 42,480*.92 Assume that the Unit Rate Contract will be 5% less and the value of each of the 15 Short Form Contracts, which will be covered by the Unit Rate Contract, is SR 50,000. 37,500 15*SR 15,000*.05 = SR 37,500 54 10 contracts*30 papers/contract*3 copies* SR .06 Less Travel Time A unit rat contract will reduce the cycle time of assigning work to the contractor from 90 days to 14 days There will be better continuity of work by having the same contractor do the work. We will be sure to get qualified contractor technicians. The contractor manpower will be familiar with the SECERB standards. Better manpower utilization with professional technicians and specialists available. Less time will be devoted to developing short form contracts. 128,178 39,082 115 Hard Costs & Benefits Economic Analysis Table 12: Hard Cost/Benefits – All figures SRs "Utilize Unit Rate Contracts" Year 1421 1422 1423 1424 1425 - - - - - 90,624 90,624 90,624 90,624 37,500 54 37,500 54 37,500 54 37,500 54 Process – incremental cash flows 1. Cash outflows/Costs Capital Items Additional capital equipment 1 Expense Items Operating cost for capital equipment 1 Additional cost 1 Additional cost 2 (materials) Total Expenses Total outflows/cost 2. Cash inflows/savings Reduce 1 Engineer, 1 Draftsman Positions Better price for services (5% savings) Paper Other Total inflows/savings - 128,178 128,178 128,178 128,178 3. Net cash inflow/outflow (1-2) - 128,178 128,178 128,178 128,178 4. 5. Period number Discount factor (@ 7%) 0 1.000 1 0.935 2 0.873 3 0.816 4 0.763 6. Discounted cash flow (3x5) - 119,793 111,956 104,631 97,786 7. Sum of discounted cash flows 434,166 116 Soft Costs & Benefits Economic Analysis Table 13: Soft Cost/Benefits – All figures SRs "Utilize Unit Rate Contracts" Year 1421 1422 1423 1424 1425 -42,000 -42,000 - - - - 39,082 39,082 39,082 39,082 39,082 Total inflows/savings 39,082 39,082 39,082 39,082 39,082 3. Net cash inflow/outflow (1-2) -2,918 39,082 39,082 39,082 39,082 4. 5. Period number Discount factor (@ 7%) 0 1.000 1 0.935 2 0.873 3 0.816 4 0.763 6. Discounted cash flow (3x5) -2,918 36,525 34,135 31,902 29,815 7. Sum of discounted cash flows Process – incremental cash flows 1. Cash outflows/Costs Capital Items Additional Equipment 1 Expense Items Create Unit Rate Contract Implementation Cost Additional Cost 2 (materials) Total Expenses Total outflows/cost 2. -25,000 -17,000 Cash inflows/savings .92 Contract Coord. FTE Time Saving Paper Vehicles Saving 2 (materials) 129,459 117 Chart 2: Implementation Plan "Utilize Unit Rate Contracts" 10. Utilize Unit Rate Contracts to Reduce the Number of SFC on Non-Technical Skills Tasks 1 Start Up and Preparation - Select & Schedule Team - Write Draft Charter - Identify Project Sponsors and Meet 2 Initial Team Meetings - Review Recommendation - Review & Finalize Charter - Discuss with Project Sponsors - Develop Detailed Implementation Plan - Verify Cost-Benefit Analysis - Develop Detailed Cost-Benefit Analysis - Gain approval of Detailed Cost Benefit Analysis Standard Software with All Users 3 Preparation of scope of work for unit rate contracts. 4 Start contract procurement. 1421 1422 Rabi'I Rabi'II Jumada I Jumada II Rajab Sha'ban Ramadan Shawwal Dhu-Al-Qa'dahDhu-Al-Hijja Muharram Safar Rabi-I Rabi-II Duration Responsible Dept. 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 Week Project Manager Project Mgr, 2 Months Implem.Team 5 Awarding contracts. 4 Months Team, FMD 3 Months Team, FMD Team, Contracting, CRD, Contracting 1 Month Mgr., FMD Mgr. SS 6 Mobilization of contractor manpower. 1 Week Team, ITD Cost SR 17, 700 Participants SR 4,680 78 Project Manager SR 6,360 106 Team (3) SR 1,710 40 FMD SR 1,920 32 CD SR 1,920 32 CRD SR 240 2 CD Mgr. SR 720 6 FMD Mgr. SR 150 1 VP. S.S. SR 0 0 Total Hours 297 4 4 4 4 4 4 4 4 4 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 8 8 8 8 8 8 8 8 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 4 4 4 4 3 3 3 3 3 3 3 3 0 0 119 8 8 8 8 8 8 1 2 2 8 8 1 2 1 1422 1423 1424 1425 Table 14: Recommendation # 2 "Maintenance Web Page" Recommendation 2: Maintenance Web Page Current Situation Recommended Change Many maintenance forms and work orders require manual processing. There currently is no single source to get maintenance information and to submit requests electronically. Users have no access to trouble shooting hints and work order status. Create an interactive Web-page for Maintenance of all Support Facilities. Provide a link from the SCECO main webpage to this maintenance web page. No maintenance Website exists today. User friendly access to Maintenance information, simple diagnostic hints and electronic work order request is critical to the future maintenance process. Predictive maintenance and other changes require the availability of data in an efficient and effective manner. It is believed that the establishment of a webpage for Support Facilities Maintenance with the following capabilities and information will provide easy access and utilization of maintenance data. It will also provide an electronic link between the maintenance professionals and their customers. 121 Web Site Capabilities and Information Content: - Hints and New Ideas - Status of Repairs - Link to CMMS data - Equipment List - Self diagnostics of PCs to maximize performance - Equipment Reliability - Cost Update - Software program to calculate economic life - Simple instructions for troubleshooting minor problems and to provide a status report for customer complaints/work order - An electronic library/database of standard contracts, scope of work (SOW), drawings, maintenance design packages and standards. Provide electronic review and approval for contracts, SOW and drawings - One form for all maintenance request/work orders. Automate all maintenance forms, work orders, and work permits into electronic format with electronic routing and approval. Link and combine forms where appropriate. - Create an exchange of information between workshops - Identify tools and test equipment available - Identify catalogs and manuals available 122 - Provide the opportunity to share resources Table 15: Summary of the Benefits "Maintenance Web Page" Summary of the Benefits Maintenance Web Page Improve response time to customer request. Speed up the maintenance process. Better utilization of existing network resources. One reference source for maintenance inquiries. System is available 24 hours a day 7 days a week. Cycle time for work orders is reduced. Eliminate paperwork by automating forms and work orders. Optimize cost by enhancing the maintenance process. 123 Table 16: Recommendation 3 "Maintenance Call Center" 3: Maintenance Call Center Current Situation Recommended Change Currently there are separate telephone numbers for many departments such as TCD and ITD and no specific telephone number for OSD to request maintenance support. Work orders in TCD and OSD are filled manually and transferred by fax or by mail to the technician. Also, the help desk telephones can only receive one telephone call at a time and the phones are often busy. Establish a call center to cover OSD, TCD, & ITD. One simple telephone number will be sued. The call Center shall receive complaints through the following mechanisms: - Web - Computerized Maintenance Management System (CMMS) - Telephone - Fax - E-mail - Voice Mail Then all requests will be integrated through the Web Page. The integration of the above will be done using CTI (Computer Telephone Integrator) and IVR (Interactive Voice Recorder) Many of the companies were manager visited (Dubai Ports Authority, Dubai Municipality, Future plans for ARAMCO) have implemented a single focal point to receive maintenance calls. Customer complains can be received through many channels like telephone, fax, e-mail, etc. The person receiving the complaint has the training and authority to resolve minor problems on the spot. The more complex problems are immediately scheduled with the appropriate maintenance technician using calendaring software and then an electronic work order is forwarded to the appropriate department. The work 125 order is also categorized and prioritized using preset guidelines. The call centers have been fully automated using software packages like Lotus Notes or Support Magic by NAI. The call Center provides a customer friendly and personal approach to assisting customers with their maintenance problems. Table 17: Summary of the Benefits "Maintenance Call Center" Summary of the Benefits Maintenance Call Center Reduce cycle time with the immediate creation of a work order. Reduced time and paperwork. Better reliability of data and a good statistical record (can be used to identify most common maintenance problems). Easy access and filing of complaints. The system is available 24 hours a day. Customers can request status of their work orders. Improve response time. One telephone number to call for all maintenance complaints. Work order is fully managed from beginning to end. The cost of archiving documents will be reduced. 126 Table 18: Recommendation 4 "Electronic Equipment Repair Shops" 4: Electronic Equipment Repair Shops Current Situation Recommended Change Today there are 4 main workshops in HQ under FMD, TCD, ITD and RMD and 3 TCD Service Centers. The equipment and skills for repairing electronic equipment are similar. These resources are spread across many workshops. Also, the workshops are located mostly at HQ. Establish 3 workshops to repair all electronic devises (Copiers, PCs, Telephones, FAX, VCRs, Cameras, etc). The workshops will be located close to the customer. Upgrade technician tools and equipment by providing IC testers, Hand Held monitoring devices, etc. Sensitive electronic equipment will be transported in specially designed containers by qualified technicians. Create groups of multi-skilled technicians as described below: - Multi skilled technicians for the Electronic Workshops to perform repairs on all types of office equipment (PCs, Telephones, FAX, Copiers, VCRs, TVs, etc). Electronic devices are becoming more integrated and simpler in design. Many copiers are being sold today with the capability to be a network printer, fax machine and scanner. Computers have fax modems as part of their standard package. Most of the repair requires the replacement of component parts rather than debugging circuitry logic, which simplifies the repair tasks. 127 It makes sense that in the future aligning the repair capability with these changes in product design. This recommendation combines the separate repair functions for telephone, copiers, PCS, Printers, etc, into one workshop. To significantly reduce the cycle time for these repairs, it was suggested suggest having three of these integrated workshops located close the customers. After significant research with various vendors, it was convinced that it is more cost effective to have this repair capability in-house rather that subcontracting with a vendor. The main reason is that a vendor will only repair their own products and will not repair models from a different vendor. Thos would require SEC-ERB to have vendor contract for each make of equipment in SEC-ERB possession. This was confirmed through visits to the Leading Practice Partner companies where their studies suggested the same and they provide internal resources to provide repairs to electronic equipment. 128 Table 19: Summary of the Benefits "Repair Shops for all Electronic Equipment" Summary of the Benefits Repair Shops for all Electronic Equipment Reduce cycle time of sending the equipment for repair to HQ workshops. Decrease down time since the future workshops will be located closer to the customer. Provide better utilization of maintenance personnel through multi-skilling. Increase equipment efficiency. Reduce the transport utilization cost to deliver/pick-up equipment Provides more knowledge and experience to SEC-ERB employees. Minimize the number of contracts. Enhance the control of materials and Spare Parts. Improve the quality of maintenance work performed. 129 Table 20: Recommendation # 5 " Maintenance Free Materials" 5: Maintenance Free Materials Current Situation Recommended Change Today, most of the equipment, buildings and landscaping utilized little or no maintenance free materials. Most of the building materials are not updated. Establish a group responsible for reviewing the top maintenance problems and recommending maintenance free materials to reduce maintenance repairs. Implement a semi-annual Innovation Workshop to share improvement ideas sponsored by SECTI. Attend Exhibitions to identify the latest maintenance free materials on the market. This practice was implemented at ARAMCO. They stated that maintenance free materials has reduced the need for maintenance and extends the asset life. A system was developed to alert when the same type of repairs are performed frequently. The cause of the problem in investigated and the quality of the material used us checked. A committee was established to investigate the availability free materials to help solve or eliminate these high frequency repairs. This is a continuous look for new products. The initial cost of the new materials is usually higher but you save money with fewer repairs in the long run. It is important to develop a go0d history of statistics to support the higher cost of materials. 131 Table 21: Summary of the Benefits "Maintenance Free Materials" Summary of the Benefits Maintenance Free Materials No maintenance will be required for materials, which are proven to be maintenance free. Materials will have a longer life. Better quality materials will be used. Although the initial cost is higher, the total ownership cost will be less. There will be more uniformity across the Company. Reduction in paperwork. Better utilization of manpower. Reduced cycle time. 132 Table 22: Recommendation # 6 "Service Level Agreement & Chargeback" 6: Service Level Agreement & Chargeback Current Situation Recommended Change There are no legal agreements between services provided Departments and its customers for the type and level of services provided and its cost. Also, there is no chargeback system for these services. This situation does not encourage and environments which requires people to make good business decisions. Customers are requesting higher than needed levels of service and the costs are not being controlled. Establish Service Level Agreements (SLAs) with internal Departments (starting with office equipments) to provide better utilization and control of maintenance resources. Create a Chafgeback system to charge back the maintenance costs for: - Computers & Peripherals Fax Machines Telephones Misc. Office Equipment A.V. Equipment Relocations As per the agreement. service level Service Level Agreements (SLAs) typically have been made between user Company and its suppliers, to specify and regulate the level of performance that is being expected and paid for. But lately, this service contract concept has been used by Companies to establish service level agreements between internal Departments. The main reason this has become an important business tool it that many internally provided services are spiraling out of control, especially in the IT Department. To help control these costs, Departments 133 are being required to make choices on which level of service they need and can justify the cost. Many Companies who have implemented this concept have been able to better manage their costs. Service level Agreement identifies certain levels of performance standards that the service provider must meet or exceed. The SLA also specifies the consequences of failure to achieve one or more service levels. To enforce the commitment to this concept and to help Departments run their functions like a business, many Companies are also establishing a charge back policy. Departments not only will decide what service level they can afford (Prices are part of the Service Level negotiations) but they will budget and pay for these services as they are requested. The Department budget for these services, which are negotiated with the Service Level Agreements and are used for planning purposes by the supplier organization. 134 Table 23: Summary of the Benefits "Service level Agreements & Chargeback" Summary of the Benefits Service level Agreements & Chargeback Allow users to choose the level of service that is appropriate to their needs with consideration to cost of the service. Gives the user a clear description of the level of service they can expect. SLAs help track performance and cost. SLAs provide a business environment to better manage Department requirement and cost. Specifies the service provider’s responsibilities and priorities and optimum utilization of resources. Achieve consistency across the Company. Establish documents clarifying the roles and responsibilities for service provided and customer to consult when there is disagreement. Provide alternatives of different process for different levels of service. Ease the Company budgeting and planning. Provides more detailed statistics related to the services provides by Department, location, requestor, etc. 135 Table 24 : Recommendation # 7 " Predictive Based Maintenance" 7: Predictive Based Maintenance Current Situation HVAC and Rotating Equipment are maintained using Preventive and Corrective maintenance practices. Some equipment is being over-maintained while other piece of equipment is not getting a high enough level of maintenance. Recommended Change Apply Predictive Maintenance Practices appropriate: Based where - Conduct Condition Based Maintenance. - Conduct major P.M. based on manufacturer task recommendation. - Cancel P.M. for equipment which proves not be cost beneficial or doesn’t require P.M. (I.E. Refrigerators, Exhaust Fans, Water Coolers, etc.) Many Companies have changed their maintenance program direction. The typical maintenance philosophy throughout the industry has been a calendar based preventive maintenance program. Maintenance is typically performed without regard for operating conditions and other factors (climate, location, etc.). Technology and information tools have proliferated and have been refined to the point where some very reliable indicators can signal a need for maintenance through remote electronic means or by observation of other indicators. This reinforces a utility industry trend to reduce maintenance costs by implementing smart of intelligent maintenance programs. 137 Condition based maintenance programs take advantage of information about equipment condition (age, location, operations, etc.) for maintenance. New equipment may not require the frequency of maintenance that older devices require. Likewise, equipment located in a slat air environment may need painting more frequently than inland counterparts. This type of approach to maintenance philosophy provides for a targeted approach to budget allocation. Reliability centered maintenance also focuses maintenance budgets. Information must be known about the reliability levels of certain system components. Worst – performing equipment can be targeted for maintenance. These results in a healthy increase of reliability, with maximized results for money spent. Table 25: Summary of the Benefits "Predictive Based Maintenance" Summary of the Benefits Predictive Based Maintenance Reduce maintenance cost and cycle time. Eliminate unnecessary PM activities. Increase productivity and quality of maintenance crews. Reduce equipment downtime and/or breakdown. With detailed date collection, failure analysis and the ability to recognize the true root cause of failures is significantly enhanced. Provide better utilization of manpower. Improve reliability of equipment operation. Decrease P.M. and C.M. work orders. 138 Table 26: Recommendation # 8 " Hand Held Data Input Devices" 8: Hand Held Data Input Devices Current Situation Recommended Change Technicians normally collect data on equipment in writing on a P.M. sheet, which then recorded on paper for a hard copy reference. A computer operator puts some of this information into the current maintenance database. Provide Hand Held Electronic Data Input Devices to Maintenance Technicians for easy and accurate input of Maintenance data at the job site. Our future process will depend on the accurate collection of equipment data. The maintenance scheduled through the utilization predictive maintenance approaches will only be as effective as the database created in CMMS. The automation of data entry has a direct effect on the accuracy of the information being input into the database. The fewer hands involved in inputting information reduce the chances of mistakes. Also, automation can eliminate the need to input all details about a piece of equipment with the ability to recall equipment history data. We recommend the purchase of Hand Held Data Entry Devices for the Maintenance Technicians to directly enter equipment operational data. Equipment history information, PM sheets and maintenance schedules can be 139 downloaded into the devices to provide information to the filed maintenance technician and reduce the effort in recording equipment data. At the end of the day, the new equipment information can be up-loaded directly into CMMS database. These electronic data entry devices will reduce the number of hands required to enter data. Table 27: Summary of the Benefits "Hand Held Data Input Devices" Summary of the Benefits Hand Held Data Input Devices Provide more accurate and reliable data by reducing the opportunity for errors in the recording of data. Reduce Cycle Time for equipment inspection. Increase Maintenance Productivity. Reduce paperwork and forms. Eliminate data entry for updating records. More data can be collected in a short time. 140 Table 28: Recommendation # 9 " Make CMMS the Standard Database" 9: Make CMMS the Standard Database Current Situation Recommended Change Currently TCD and ITD have their own database system while other Departments involved in the Facility Maintenance are using CMMS, which is replacing the MIMS system. Use CMMS as the standard Maintenance Database for all Departments involved in maintenance (ITD, TCD, OSD, PTD, GD, etc). Establish a task team to load the CMMS with information such as; Equipment Operation manuals, Exploded View of the Equipment, As-build Drawings, Failure Types, Major CM Tasks, Video clips of Maintenance Practice and spare parts lists. All Leading Practice Partner Companies have established or are currently implementing CMMS as a database for all of their maintenance information. Having separate databases for the maintenance of different types of equipment increases the cost to the Company and decreases the access to data. Having one common database allows the Company to better manage the data and to keep the system up to date with the latest releases. The current CMMS, which was purchased by SEC-ERB, has the function needed to satisfy all users. 141 Some of our Leading Practice Partners loaded the CMMS with relevant information, which can be utilized by the Technicians. An example of this was found with Saudi Binladen Group who had video clips of their maintenance practices for some of their major equipment available through the CMMS. Also, Dubai Port Authority is planning to establish links with their equipment vendors through the Internet to be able to obtain the exploded view of their equipment. Table 29: Summary of the Benefits "Make CMMS the Standard Database" Summary of the Benefits Make CMMS the Standard Database Make more maintenance related information available electronically and provide easy reference to information by Technicians. Reduce the usage of paper and filing space. Increase Technicians efficiency and quality of maintenance work. Reduce cycle time in the maintenance process. Reduce the number of database systems to upgrade and provide enhancements from three databases to one common database. Will enhance the technician’s capability in troubleshooting and repairing equipment. Will provide quicker service on equipment repairs. Provide as-build drawings in the CMMS and encourage updates. Needed material can be quickly identified. 142 Table 30: Recommendation # 10 "Improve P.C. Repair and Support Network" 10: Improve P.C. Repair and Support Network Current Situation Recommended Change Each Department has a designated Coordinator to solve IT equipment problems in addition to his regular duties and responsibilities. This person may not have the knowledge or experience to solve many of the customer’s problems. Simplify P.C. hardware & software repair and provide better support for the LAN/WAN network by: The current cycle time to repair PC problems is long because the maintenance is performed at the customer site by a technician or the P.C. is delivered to the Central Repair Shop at HQ. - Train the current Department Coordinators to function as Department LAN Administrators who will take full responsibility to maintain LAN connections and P.C. equipment connected to the network. - A diagnostic software package will be purchased to repair software/configure files and hardware problems remotely over the network. SEC-ERB’s computer network infrastructure is almost complete. Maintaining this network will require designated persons who will assist in maintaining the ever-increasing number of P.C. and their peripherals. Remote diagnostic software will provide IT the power to resolve hardware and software problems of PCs, which are remotely located from the IT Department by accessing the PCs over the network. Also, users ca request help on using a software package or creating a chart since IT professionals 143 will have the capability to gain access to a user’s screen and the user’s software application software. Overall response time for resolving user problems will be drastically reduced while simplifying the task of problem resolution for the Maintenance technician. Table 31:Summary of the Benefits "Improve P.C. Repair and Support Network" Summary of the Benefits Improve P.C. Repair and Support Network Quick service will be provided to the customer. Cycle time to repair hardware and software problems will be reduced. Customers can get help on individual software by IT having remote access to a user’s computer. Cost of delivery will be reduced. Standard software will be provided to the customers. 144 Table 32: Recommendation # 11" Improve Material Delivery" 11: Improve Material Delivery Current Situation Recommended Change Department technicians and Material Man are picking up material form the Material Management Department (MMD) warehouse. Increase Availability and Expedite Delivery of material by: - Providing MMD Truck service twice a week on a fixed schedule to FMD at Headquarters (HQ), Training Center (SECTI), Hofuf Operating Area (HOA) and Mansura. Vendors refuse to deliver low value/small quantity of materials under the current Purchase Commitment Agreement (PCA). - Increasing vendor to stocking Facility Maintenance materials and include delivery by quick Express Service. Concerned Departments and MMD Petty Cash Buyers are searching material in market or vendors who are agent and can obtain request items. - We strongly support the MMD study to establish a Communication Link and E-Commerce between SEC-ERB and Vendors using an Internet service. We request that user Departments can have direct access to vendor information. It takes MMD a long time to procure materials under direct charge Material Purchase Request (MPR) in bidding approval of purchase order, receiving and delivery. - Increasing the approval authority: for petty cash purchases of Unit Head to SR 1,000, for PCA of Supervisor to SR 10,000 and for Supt. Authority to SR 50,000. Update the new approval authority in the authority manual. There is limited purchase of items under petty cash due to policy and limited approval authority amount (SR 500 for Div. Head and SR 1,000 for Dept. Head). - Replacing the use of Petty Cash by providing Senior Technicians and Foreman with Corporate Credit Cards/ATM Cards to purchase maintenance materials as authority by the Department Manager. The availability and delivery of material can have a major impact on the maintenance technician’s ability to respond quickly to a customer request. 145 Having the vendor stock some of the materials currently in the SEC-ERB storerooms and requesting the vendor to deliver the materials when required will reduce our costs of storage and will reduce the cycle time for material delivery. Increasing MMD Truck Service to critical delivery points for Support Facilities Maintenance will drastically reduce the cycle time for the deliver of spare parts and materials. This will also reduce the unproductive time Maintenance Technicians spend getting the needed materials. Providing an alternative to petty cash by issuing credit cards or ATM cards to Senior Technicians will provide significant reductions in the time requires purchasing materials for emergency work. The credit card/ATM card will restrict the amount, which can be purchased at the same time. The credit card vendor provides a detailed statement of all purchases made by all credit card holders. This record can be very beneficial for tracking and auditing purposes. Increasing the approval authority for petty cash type transactions will also reduce the time to secure materials needed quickly for an urgent repair. 146 Table 33: Summary of the Benefits "Improve Material Delivery " Summary of the Benefits Improve Material Delivery Better utilization of maintenance personnel to perform maintenance work. Cycle time will be reduced to perform work due to the availability of material. Quick response to user with the ability to quickly search for and obtain materials (Reduction in time for bidding, approval of purchase order). MMD Inventory cost can be reduced as vendors will stock items and deliver those to the user Department. Also transportation costs by MMD will be reduced. Reduced cycle time by increasing the approval authority for petty cash purchases and providing Credit Card/ATM Card. Paper work will be reduced for requesting petty cash, by MMD bidding, Communication with vendor for quotations, etc. 147 Chapter 5 Summary and Conclusion 5.1 Introduction This chapter presents a summary of the study and conclusion on the case study of the Business Process Improvement conducted by Saudi Electricity Company – Eastern Region Branch (SEC-ERB). Recommendations to improve the quality of the BPI or BPR project are presented also. There is no single method that can apply everywhere or considered the ideal methodology. Hence, studying in detail a case study of BPI could pave the path for further studies based on actual practices which eventually led to the improvement of BPI or BPR future projects. 5.2 Summary of the Project and Conclusion The Business Process Improvement (BPI) case study of Saudi Electricity Company – Eastern Region Branch (SEC-ERB) presented in this report is intended to show the BPI methodology in detail of how each process was done and why. During the project preparation, visits to SEC-ERB were done to collect the relevant information and data collected during the excursion of the BPI study "Maintain Support Facility". This report 148 contains mainly three items, introduction, literature about the subject and the case study itself. The case study starts with the introduction of the BPI phases. The phases are the start up & preparation phase, the current state, the future state and finally the implementation phase. Each phase has been summarized and presented the findings that the project team formulated. Since the project data are huge, this forced the concentration of one of the six the sub-processes which is sub-process 3 "Perform Corrective Maintenance". The rest of the subprocesses were conducted in exactly similar methodology as in subprocess 3. Unfortunately, after the BPI project completed SEC-ERB merged with all the electrical companies in the Kingdom to form the Saudi Electricity Company (SEC) which as a result delayed and reduced attention to BPI recommendations implementation. Further, this also made more difficult for the report gathering of information and data since some of the BPI core team were very busy or transferred to other areas to help for merging process. Eleven recommendations are the final result of BPI project and those were presented at chapter 14 "Recommendations Improvement Analysis". Leading practices are implemented at the future state which includes a research of the most advanced practices to conduct the major process and the sub-processes. It included site visit to the companies and businesses which they assume that they are doing the service in a better way. It includes also search 149 in the internet of best practices. Examples of the leading practices were presented in chapter three. Each phase step was presented and analyzed to show how it was implemented. 5.3 Recommendations An excellent recommendation is a mixture of excellent methodology and management support. Hence, all recommendations were supposed to be studied and should not be ignored at any time. All resources should be available fro the team members all the time upon needed such as internet access during all project phases, allocation of resources for leading practices site visits to travel anywhere if needed without any restrictions from neither the executive sponsor nor the process manager for limited resources. This will cause the moral of the team members to drop especially if they are confident that this would be very helpful. Further, taking more accurate measurement to record process data such as the process cycle time and the FTE's. None of recommendation nor from the business case models studied the outsourcing of the entire major process or at least one of the sub-processes to compare the costs between them. investigation. It This was could be noticed an that item after for all further this study and effort, the implementation phase was not done effective. This could be because of two major reasons. One could be due to the merging process with other 150 electrical companies in the kingdom which consumed most of the effort and resources. Or it could be the executive management miscommunications to the subordinated for enforcing the recommendation changes application. This step needs advertisement to all employees to encourage them to apply the new recommendations. I addition, further consideration of the methodology of the cost versus benefits in order to make sure that no recommendation would be eliminated or approved because of hidden factors not considered. The development of a software program of the methodology implemented for future BPI projects execution. Finally, further study of the possibility of simulation program or process to assess more to the possibility of success or failure of a recommendation. 151 References 1. Booth, Report (1995), "Process Mapping", Management Accounting, Vol. 73, No. 3, P. 32. 2. Stein Emily J, Kruger Kenneth F and Siegel Patricia, (1996), " The role of human resources in supporting reengineering", The Health Care Supervisor, Vol. 15, No. 2, P. 8. 3. David J. Paper, James A. Rodger and Parag C. Pendtiarkar (2001), "A BPR Case Study at Honeywell", Business Process Management Journal, Vol. 7, No. 2, PP. 85-99. 4. Analrea, Hale J. & Cragg, Paul B. (1996), "Business Process reengineering in the small firm: A case study", INFOR, Vol. 34, No. 1, P. 15. 5. Clemmer, Jim (1994), "Process re-engineering and process improvement: Not an either or choice", CMA, Vol. 68, No. 5, P. 36. 153 6. Dolon, Tom, (2003), "Best Practices In Process Improvement", Quality Progress, Vol. 36, No. 8, P. 25. 7. Copacino, William C., (2002) "Take a look at business process outsourcing", Logistic Management, Vol. 42, No. 7, P. 70. 8. Yuan Cheng, Min & Hsiu Tsai, Min- (2003), "Reengineering of Construction Management Process", Journal of Construction Engineering and Management, Vol. 129, No. 1, P. 105. 9. Saudi Electricity Company BPI Manual. 10. Malhotra, Yogesh (1998), "Business Process Redesign: An Overview", IEEE Engineering Management Review, Vol. 26, No. 3, P. 10. 11. Malhotra, Yogesh (2000), "Knowledge Management for [E-] Business Performance", Information Strategy: The Executive Journal, Vol. 16, No. 4, P. 5. 12. Saudi Electricity Company Annual Report 2002. 13. BPI "Maintain Support Facilities" report. 154 14. Hammer, M.(1990). "Reengineering work: Don't automate, obliterate." Harvard Business Review, 104-112. 15. Hammer, M., and Champy, J.(1993). Reengineering the corporationA manifesto for business revolution, HarperCollins, New York. 16. Fuglseyh, A.M. and Gronhaug, K.(1997), "IT-enabled redesign of complex and dynamic business processes: the case of bank credit evaluation", Omega, International Journal of Management Sciences, Vol.25, No.1, pp. 93-106. 17. Daniel-Duck, J., "Managing Change: The Art of Balancing", Harvard Business Review, November-December 1993, pp 109-118. 18. Cypress, H. L., " Re-engineering", OR/MS Today, February 1994, 18-29. 19. Davenport, T. H., & Short, James E., "The New Industrial Engineering: Information Technology and Business Process redesign", Sloan Management Review, Summer 19900,pp 11-27. 155 20. Strassmann, P.A. The Squandered Computer: Evaluating the Business Alignment of Information Technologies, 1997, Information Economics press, New Canaan, CT. 21. Furey, T.R., garlitz, J. L. & Kelleher, M. L., "Applying Information Technology to Reengineering", Planning Review, November/December 1993, pp 22-25. 22. Hammer, M. & Champy, J., "Avoiding the Hottest New Management Cure", Inc., 16(4) April 1994, pp 25-26. 23. Barrier, M. " Reengineering your Company", Notion's Business, February 1994, 16-22. 24. King, W.R.(1994 Spring). "Process Reengineering: The Strategic Dimensions", Information System Management, 11(2), pp.71-73. 156