THE GROUNDWATER REMEDIATION SYSTEM (GRS) MONITORING AND OPERATIONS PROGRAM SEMI-ANNUAL ENGINEERING REPORT FOR THE PERIOD JANUARY 1, 2007 THROUGH JUNE 30, 2007 AT LUVATA GRENADA LLC (OEM PLANT) GRENADA, MISSISSIPPI PURSUANT TO MISSISSIPPI DEPARTMENT OF ENVIRONMENTAL QUALITY (MDEQ) AGREED ORDER 2875-94 DATED JULY 19, 1994 FOR LUVATA GRENADA LLC GRENADA, MISSISSIPPI HAZCLEAN Report No. 07.0306.52 October, 2007 THE GROUNDWATER REMEDIATION SYSTEM (GRS) MONITORING AND OPERATIONS PROGRAM SEMI-ANNUAL ENGINEERING REPORT FOR THE PERIOD JANUARY 1, 2007 THROUGH JUNE 30, 2007 AT LUVATA GRENADA LLC (OEM PLANT) GRENADA, MISSISSIPPI PURSUANT TO MISSISSIPPI DEPARTMENT OF ENVIRONMENTAL QUALITY (MDEQ) AGREED ORDER 2875-94 DATED JULY 19, 1994 FOR LUVATA GRENADA LLC GRENADA, MISSISSIPPI ___________________________________ E. Corbin McGriff, Ph.D., P.E. President and Director of Operations _________________________________ State of Mississippi Registered Professional Engineer No. 5690 ___________________________________ Michael A. Noone, RPG Geological Services Manager _________________________________ State of Mississippi Registered Professional Geologist No. 0162 Prepared by HAZCLEAN ENVIRONMENTAL CONSULTANTS, INC. P. O. Box 16485 Jackson, Mississippi 39236-6485 (601) 922-0766 HAZCLEAN Report No. 07.0306.52 October, 2007 TABLE OF CONTENTS Page 1.0 INTRODUCTION ................................................................................................... 1 1.1 Background................................................................................................ 1 1.2 Remedial System Review and Modification ............................................... 2 2.0 GROUNDWATER REMEDIATION SYSTEM (GRS) DESIGN SUMMARY ........... 4 3.0 OPERATIONS, MAINTENANCE AND MONITORING ACTIVITIES ..................... 6 3.1 Operations and Maintenance ..................................................................... 6 3.2 GRS Performance Summary ..................................................................... 6 3.3 NPDES Influent and Effluent Sampling Summary ..................................... 7 4.0 GROUNDWATER SAMPLING SUMMARY .......................................................... 8 4.1 Monitoring Well Sampling Activities Summary ........................................... 8 4.2 Groundwater Levels and Vacuum Readings............................................ 12 5.0 SITE RESPONSE TO TREATMENT .................................................................. 13 5.1 Total TCE Mass Removed (Vapor and Groundwater) ............................ 13 5.2 TCE Mass Removed from Groundwater .................................................. 13 5.3 TCE Mass Removed as Vapor ................................................................ 14 5.4 GRS Treatment Summary ....................................................................... 14 6.0 REMEDIAL PROGRESS EVALUATION ............................................................. 15 6.1 Operations Summary ............................................................................... 15 6.2 Findings ................................................................................................... 16 TABLES: Table 1: Table 1-1: Table 1-2: Table 1-3: Table 1-4: Groundwater Elevation Summary Monitoring and Recovery Wells (June, 2007) ........................................................ 17 Groundwater Elevation Summary Monitoring and Recovery Wells (Stratigraphic Layer 1) (June, 2007) .................................................................................. 24 Groundwater Elevation Summary Monitoring and Recovery Wells (Stratigraphic Layer 2) (June, 2007) .................................................................................. 26 Groundwater Elevation Summary Monitoring and Recovery Wells (Stratigraphic Layer 3) (June, 2007) .................................................................................. 29 Groundwater Elevation Summary Monitoring and Recovery Wells (Stratigraphic Layer 4) (June, 2007) .................................................................................. 32 i TABLE OF CONTENTS (Continued) Page Table 1-5: Table 2: Table 2-1: Table 2-2: Table 2-3: Table 2-4: Table 2-5: Table 3: Table 3-1: Table 3-2: Table 3-3: Table 3-4: Table 3-5: Table 4: Table 4-1: Table 4-2: Table 4-3: Table 4-4: Table 4-5: Table 5: Groundwater Elevation Summary Monitoring and Recovery Wells (Stratigraphic Layer 5) (June, 2007) .................................................................................. 35 Laboratory Analytical Report Summary Argus Analytical, Inc. (June, 2007)................................................ 37 Laboratory Analytical Report Summary (Stratigraphic Layer 1) (June, 2007).............................................. 44 Laboratory Analytical Report Summary (Stratigraphic Layer 2) (June, 2007).............................................. 46 Laboratory Analytical Report Summary (Stratigraphic Layer 3) (June, 2007).............................................. 49 Laboratory Analytical Report Summary (Stratigraphic Layer 4) (June, 2007).............................................. 52 Laboratory Analytical Report Summary (Stratigraphic Layer 5) (June, 2007).............................................. 55 Historical (Original to Current) TCE Groundwater Analytical Summary - All Wells ..................................................... 57 Historical (Original to Current) TCE Groundwater Analytical Summary (Stratigraphic Layer 1) .................................. 65 Historical (Original to Current) TCE Groundwater Analytical Summary (Stratigraphic Layer 2) .................................. 67 Historical (Original to Current) TCE Groundwater Analytical Summary (Stratigraphic Layer 3) .................................. 70 Historical (Original to Current) TCE Groundwater Analytical Summary (Stratigraphic Layer 4) .................................. 73 Historical (Original to Current) TCE Groundwater Analytical Summary (Stratigraphic Layer 5) .................................. 76 Composite Historical TCE Groundwater Analytical Summary Monitoring and Recovery Wells - All ............................................. 78 Composite Historical TCE Groundwater Analytical Summary Monitoring and Recovery Wells (Stratigraphic Layer 1) ................ 86 Composite Historical TCE Groundwater Analytical Summary Monitoring and Recovery Wells (Stratigraphic Layer 2) ................ 89 Composite Historical TCE Groundwater Analytical Summary Monitoring and Recovery Wells (Stratigraphic Layer 3) ................ 92 Composite Historical TCE Groundwater Analytical Summary Monitoring and Recovery Wells (Stratigraphic Layer 4) ................ 96 Composite Historical TCE Groundwater Analytical Summary Monitoring and Recovery Wells (Stratigraphic Layer 5) .............. 100 GRS Operational Summary (March, 2000 through June, 2007) .............................................. 102 ii TABLE OF CONTENTS (Continued) Page GRAPH: Graph 1: Cumulative Volatile Organic Compounds (VOCs) Removed (March, 2000 to June, 2007) ....................................................... 111 FIGURES: Figure 1: Figure 2-1: Figure 2-2: Figure 2-3: Figure 2-4: Figure 2-5: Figure 3-1: Figure 3-2: Figure 3-3: Figure 3-4: Figure 3-5: Figure 4: Site Layout .................................................................................. 113 Groundwater Elevation Contour Map (Stratigraphic Layer 1) ...... 115 Groundwater Elevation Contour Map (Stratigraphic Layer 2) ...... 117 Groundwater Elevation Contour Map (Stratigraphic Layer 3) ...... 119 Groundwater Elevation Contour Map (Stratigraphic Layer 4) ...... 121 Groundwater Elevation Contour Map (Stratigraphic Layer 5) ...... 123 TCE Concentration Map (Stratigraphic Layer 1) ......................... 125 TCE Concentration Map (Stratigraphic Layer 2) ......................... 127 TCE Concentration Map (Stratigraphic Layer 3) ......................... 129 TCE Concentration Map (Stratigraphic Layer 4) ......................... 131 TCE Concentration Map (Stratigraphic Layer 5) ......................... 133 System Recovery Well(s) Vacuum Readings (Stratigraphic Layers 1 and 2, June, 2007) ................................. 135 APPENDICES: Appendix A: GRS Monthly Laboratory Analytical Reports (Effluent and Influent) (January through June, 2007) Appendix B: Argus Analytical, Inc. Laboratory Reports, Semi-Annual Groundwater Sampling Event (June, 2007) iii HAZCLEAN REPORT NO. 07.0306.52 1.0 INTRODUCTION 1.1 Background PAGE 1 As part of a Comprehensive Groundwater Investigation (pursuant to Mississippi Department of Environmental Quality [MDEQ] Agreed Order 2875-94, dated July 19, 1994), presently ongoing at the Luvata Grenada LLC (OEM Plant) facility, Grenada, Mississippi, HAZCLEAN ENVIRONMENTAL CONSULTANTS, INC. (HAZCLEAN), has prepared a Groundwater Remediation System (GRS) monitoring and operations program semi-annual engineering report for the facility for the second semi-annual period of the seventh year of operation (January 1, 2007 – June 30, 2007). This semi-annual report was compiled from HAZCLEAN’s field and operations/maintenance data and from laboratory analytical data reported to HAZCLEAN by Argus Analytical, Inc., Ridgeland, Mississippi. Initial assessment activities at the OEM facility were conducted from 1989 – 1992. Assessment activities were requested by the Mississippi Department of Environmental Quality (MDEQ) pursuant to the discovery of elevated levels of Trichloroethene (TCE) in the groundwater monitoring wells (GWMWs) located on the east adjoining property (Koppers Industries, Inc.). Luvata contracted HAZCLEAN to prepare a Work Plan (Report No. 93.1.306.20.256; December 7, 1993) for a preliminary groundwater investigation and to develop a report on historical waste management practices (Report No. 93.1.306.20.286; December 14, 1993) as part of the Work Plan. Initial assessment activities were completed in 1995 and in November, 1997, a “Groundwater Remediation System and Monitoring Program Design for the Comprehensive Groundwater Investigation Program (Revised)”; Report No. 96.1.306.27.447, was submitted to the MDEQ. From November, 1999 through February, 2000, installation of monitoring wells, recovery wells, and the groundwater remediation system were completed. The GRS was initially started in March, 2000. Except for periods of adjustments and maintenance to improve the recovery efficiency, the system has operated continuously. The following report incorporates a summary of the GRS monthly Operations and Maintenance (O&M), semi-annual groundwater sampling event and reporting activities for the second semi-annual period of the seventh year of operation (January 1, 2007 – June 30, 2007). OCTOBER, 2007 HAZCLEAN REPORT NO. 07.0306.52 PAGE 2 The site has been characterized as consisting of five (5) identified water-bearing layers and referred to as Stratigraphic Layers: 1, 2, 3, 4 and 5. Notably, after careful review of historical data, Stratigraphic Layer 3/4, which had only one (1) well (MW-52-30) placed within this layer, will no longer be recognized as a distinct layer. This well has been placed in Stratigraphic Layer 3. 1.2 Remedial System Review and Modification Lennox International, Heatcraft’s former parent company, initiated a voluntary project review in November 2003 to evaluate all phases of the overall program including site characterization, system efficacy, system operational components, and system efficiency. Available site characterization and remediation system documentation was reviewed and evaluated to determine the extent to which the objectives stated in the Order/Voluntary Agreement between MDEQ and Heatcraft OEM had been and were being met. In an effort to more quantitatively evaluate the current GRS groundwater capture zone and, thus, system effectiveness a numerical groundwater modeling assessment was conducted. After successful quantitative statistical calibration of the steady-state groundwater flow model, the finite element grid was modified to accommodate the addition of pumping nodes so that, in addition to evaluating current system effectiveness, a variety of alternative scenarios could be evaluated. Results of the simulations demonstrated that complete capture has not been achieved. However, aggregate site data do show that natural processes, including dispersion, diffusion, sorption, and intrinsic biological processes, have attenuated downgradient plume migration. The results of that review recommended retaining the current system’s concept and objectives, but re-designing the mechanical aspects of the system. MDEQ concurred with this recommendation and the groundwater extraction-and-treatment system is being reconfigured to provide better capture of the more highly contaminated portions of the plume and by separating the SVE system to help ensure capture of the vapor plume and more efficient removal of contaminant mass from the vadose zone. The modified groundwater remediation system has been designed to contain the source zone and to prevent further migration of the plume (greater than or equal to 1 mg/L) off site. Based on hydrogeologic modeling, high concentration plume capture will be achieved with 30 wells, and eight of these wells will be existing GRS recovery or monitoring wells the others are newly drilled wells. These well locations were selected through groundwater modeling performed on data from a series of slug tests performed on existing deep and shallow wells. These locations are designed to provide capture of the dissolved-phase plume and protect against off-site migration. OCTOBER, 2007 HAZCLEAN REPORT NO. 07.0306.52 PAGE 3 The SVE system will utilize a dedicated blower rather than the existing liquid ring pump; this is expected to result in improved efficiency and the ability to better control and monitor the system. The SVE system will also use dedicated extraction wells to accommodate collection of accurate vapor-flow measurements, accurate measurement of contaminant concentrations in the vadose, and accurate vacuum measurements. With this information, resources can be reassigned and the vadose source can be more aggressively attacked and more quickly treated. Installation of the new groundwater extraction-and-treatment and SVE system is currently underway and is to be completed in the fall of 2007. OCTOBER, 2007 HAZCLEAN REPORT NO. 07.0306.52 2.0 PAGE 4 GROUNDWATER REMEDIATION SYSTEM (GRS) DESIGN SUMMARY The GRS was installed and started operations in March, 2000. The system is a Dual Phase Vapor Extraction (DPVE) type and was manufactured by Ejector Systems, Inc., Addison, Illinois. The GRS incorporates a 50 horsepower Travaini Liquid Ring Vacuum Pump (LRVP) to produce a vacuum to recover Volatile Organic Compounds (VOCs), specifically, Trichloroethene (TCE) impacted groundwater from a system of 27 recovery wells. Extracted groundwater and soil vapors are drawn into the GRS’s primary air-water separator (knock-out tank) which separates vapors from recovered groundwater. The vapors are drawn though the LRVP and a secondary air/moisture separator prior to discharge to the atmosphere. The groundwater is pumped from the primary knockout tank, utilizing a pump which has been designed to operate under vacuum conditions, for treatment through a series of three (3) separate air stripper units. The GRS utilizes a central four-inch (4") Schedule 40 PVC piping network to apply a vacuum to the vadose and saturated zones surrounding the recovery wells. Soil vapors and groundwater are delivered to the GRS via a single four-inch (4") piping network. In order to produce groundwater from deeper wells (greater than 30 feet in depth), a dedicated one-inch (1") PVC air line delivers compressed air to each applicable well. By utilizing vacuum assisted air-lift, downhole mechanical pumps are eliminated, thereby, reducing maintenance and/or replacement costs. Influent piping, effluent piping and GRS components are routed as illustrated on Figure 1, Site Layout. The GRS major system components include the following: a. A series of three (3) separate air strippers consisting of one (1) 2-tray air stripper system and two (2) separate 4-tray air stripper systems rated for up to 50 gallons per minute (gpm) liquid influent. Each tray contains approximately twelve (12) aeration tubes for water treatment. Each stripper discharges the residual Volatile Organic Compound (VOC) vapors through separate exhaust stacks. b. One (1) – fifty (50) horsepower Liquid Ring Vacuum Pump (LRVP). The GRS has been designed in order to combine maximum groundwater recovery and maximize vapor recovery at the facility. By combining both, the overall time required for remediation of the facility is minimized. c. Hour run-time meter (wired to the LRVP). d. Remote telemetry system with restart and monitoring capabilities. OCTOBER, 2007 HAZCLEAN REPORT NO. 07.0306.52 PAGE 5 e. Phase reversal monitor and relay to protect electrical hardware from spontaneous phase reversals, utility maintenance errors, etc. f. Voltage overload protection relays to protect electrical hardware from voltage spikes due to lightning strikes, etc. g. Air/water and air/air heat exchanger. h. Ten (10) horsepower rotary screw air compressor with 110 psi capacity for continuous duty operation with filtration system and gauges to provide air lift in the deeper recovery wells (RW-2-60, RW-2-118, RW-4-60, RW-5-60, RW-13-60, RW-14-60, RW-15-60, RW-19-60, and RW-20-60). i. 8.5' W x 28.5' L x 9.5' H aluminum hull building with removable walls. The GRS unit and components are enclosed in a cyclone fenced compound to protect the unit and components from vandalism, damage from traffic and to protect the general public in accordance with MDEQ regulations. OCTOBER, 2007 HAZCLEAN REPORT NO. 07.0306.52 3.0 OPERATIONS, MAINTENANCE AND MONITORING ACTIVITIES 3.1 Operations and Maintenance PAGE 6 HAZCLEAN visits the facility a minimum of two (2) times per month for scheduled O&M activities, to collect system influent and effluent water samples under the National Pollutant Discharge Elimination System (NPDES) permit and to record the groundwater remediation system (GRS) data. System data to be recorded consists of the following: ▪ ▪ ▪ ▪ ▪ ▪ Runtime hours; Stripper blower values; Totalizing flowmeter gallons; AWS-1 vacuum; AWS transfer and other pump readings; Liquid ring exhaust and liquid ring pump temperatures. O&M activities for the semi-annual period include maintenance on the flow meter totalizer, installation of various system gauges, scheduled lubrication of all motors, cleaning of the AWS-1 and AWS-2 tanks and conductance probes, repairs to Blowers 1 and 2, replacement of drop tubes in recovery wells, repair leaking make-up water pump, cleaning of air strippers and other routine GRS maintenance activities. HAZCLEAN conducts unscheduled visits as needed. 3.2 GRS Performance Summary During this performance period (January 1, 2007 – June 30, 2007), the GRS processed a combined total volume of 1,126,731 gallons of groundwater and make-up waters. The ratio of make-up water to groundwater has never been determined, but a ratio of 1:4 is reasonable, based on previous meter readings. The GRS operated a total of 3,716 of 4,344 hours for an operating efficiency of 85.5 percent (%). Since the GRS start-up in March, 2000, the GRS has extracted approximately 42,526,840 gallons of groundwater and make-up water (Note: groundwater plus make-up waters will be referred to as groundwater throughout this report). The GRS has operated a total of 54,340 hours of 64,032 calendar hours for an operating efficiency of 84.9 percent (%). OCTOBER, 2007 HAZCLEAN REPORT NO. 07.0306.52 3.3 PAGE 7 NPDES Influent and Effluent Sampling Summary Since system start-up and monthly thereafter, National Pollutant Discharge Elimination System (NPDES) groundwater permit sampling has been conducted. The NPDES Permit No. MS0001368 was issued in 1998, re-issued September 16, 2003, and expires August 31, 2008. The permit requires bimonthly monitoring of: a. b. c. d. e. f. g. Flow Rate Biochemical Oxygen Demand (5-Day) Total Suspended Solids Trichloroethene (TCE) Vinyl Chloride Oil and Grease pH As required by the NPDES Permit, on a monthly basis, all influent and effluent samples are analyzed for certain Volatile Organic Aromatics (VOAs), - specifically targeting: Benzene; Carbon Disulfide; 1,1-Dichloroethene (1,1-DCE); CIS-1,2-Dichloroethene (CIS-1,2-DCE); Trans-1,2-Dichloroethene (Trans-1,2-DCE); Ethylbenzene, Styrene; Toluene; Trichloroethene (TCE), Vinyl Chloride and Xylenes (Total). Additionally, once per month, the effluent system discharge water is analyzed for Oil and Grease and Total Suspended Solids (TSS). The effluent water pH is field measured and provided to the laboratory (see Appendix A, GRS Monthly Laboratory Analytical Reports [Effluent and Influent]). In September, 2003, the NPDES Permit was modified and BOD 5 was removed from the analysis criteria. During the course of the GRS start-up evaluation (March 8 through July 1, 2000), the GRS was subjected to several operating scenarios to determine the optimal removal and treatment of VOC impacted soils and groundwater. Discharged TCE ranged from below method detection limits (BMDL) to a maximum of 0.082 milligrams per liter (mg/l). Upon receipt and review of analytical results yielding TCE effluent concentrations above the method detection limit, the GRS was adjusted to reduce TCE effluent concentrations. During portions of April, 2000 and May, 2000, the GRS discharged TCE in concentrations above method detection limits (0.006 mg/l - 0.082 mg/l); however, the levels were within the discharge limitations (no stated permit levels) in the MDEQ, NPDES Permit Number MS0001368. Since May, 2000, all monitored effluent chemicals of concern concentrations have been in compliance with the NPDES Permit. OCTOBER, 2007 HAZCLEAN REPORT NO. 07.0306.52 PAGE 8 4.0 GROUNDWATER SAMPLING SUMMARY 4.1 Monitoring Well Sampling Activities Summary Sampling of groundwater monitoring/recovery wells for the second semi-annual period (January 1, 2007 – June 30, 2007) of the seventh year of operations was performed in June, 2007, in accordance with Quality Assurance Protocols detailed in the United States Environmental Protection Agency (USEPA), Region IV, Environmental Investigations Standard Operating Procedure and Quality Assurance Manual (EISOPQAM) (November, 2001). Polyethylene-Based Equilibrator Passive Diffusion Bag (PDB) disposable samplers and disposable bailers were used to obtain groundwater samples which were submitted for laboratory analysis for Volatile Organic Compound (VOC) concentrations. PDB samplers are suitable for obtaining concentrations of VOCs in groundwater and are a suggested method for long-term monitoring of VOCs in groundwater monitoring wells at wellcharacterized sites. The effectiveness of the use of a single PDB sampler in a monitoring well is dependent upon horizontal flow through the well screen and that the quality of the water is representative of the groundwater in the aquifer directly adjacent to the well screen. A typical PDB sampler consists of a low-density polyethylene lay-flat tube closed at both ends which is filled with deionized water prior to installation within the monitored well. The sampler is positioned within the well bore, approximately 8” – 12” from the well bottom. The amount of time that the PDB sampler is left in the monitoring well prior to recovery depends on the time required by the PDB sampler to equilibrate with localized groundwater and the time required for the environmental disturbance caused by sampler deployment to return to ambient conditions. The rate that the deionized water within the PDB sampler equilibrates with localized groundwater depends on multiple factors, including the type of compounds being sampled and the water temperature. The samplers are left in place long enough for the localized groundwater, contaminant distribution, and flow dynamics to restabilize following PDB sampler deployment. Laboratory, field data and pilot studies support that a minimum of two to three (2-3) weeks is adequate time for equilibration for VOCs. From May 30 – 31, 2007, the PDB samplers were installed in monitoring wells located at the following stations: MW-1-29 MW-5-40 MW-7-57 MW-10-20 MW-12-31 MW-15-40 OCTOBER, 2007 MW-2-60 MW-5-60 MW-8-19 MW-10-34 MW-12-47 MW-15-60 MW-2-118 MW-6-24 MW-8-119.5 MW-10-45 MW-13-36 MW-16-43 MW-3-29 MW-6-59.5 MW-9-19 MW-11-17 MW-13-58 MW-16-57 MW-4-43 MW-7-19 MW-9-34 MW-11-35 MW-14-36 MW-17-30 MW-4-60 MW-7-42 MW-9-48 MW-12-20 MW-14-57 MW-17-48 HAZCLEAN REPORT NO. 07.0306.52 MW-18-20 MW-20-50 MW-26-25 MW-28-118 MW-31-30 MW-34-30 MW-37-30 MW-40-30 MW-44-50 MW-48-20 PZ-3-19 MW-55-60 MW-58-60 MW-18-40 MW-21-30 MW-26-40 MW-29-25 MW-31-39 MW-34-50 MW-37-60 MW-40-57 MW-45-30 MW-49-20 MW-53-30 MW-56-30 MW-59-30 MW-18-60 MW-22-30 MW-26-57 MW-29-40 MW-32-30 MW-35-30 MW-38-30 MW-41-30 MW-45-50 MW-50-20 MW-53-60 MW-56-60 MW-59-60 PAGE 9 MW-19-40 MW-23-30 MW-27-25 MW-29-64 MW-32-40 MW-35-50 MW-38-60 MW-42-30 MW-46-30 MW-51-30 MW-54-30 MW-57-30 MW-19-60 MW-24-30 MW-27-40 MW-30-30 MW-33-30 MW-36-30 MW-39-30 MW-43-30 MW-46-50 MW-52-30 MW-54-60 MW-57-60 MW-20-28.5 MW-25-30 MW-27-57 MW-30-50 MW-33-40 MW-36-50 MW-39-60 MW-44-30 MW-47-50 PZ-1-29A MW-55-30 MW-58-30 Following the initial equilibration period, the PDB samplers maintain equilibrium concentrations with the localized groundwater until recovery. Recovery of the PDB samplers consists of retrieving the PDB samplers from the well and immediately transferring the enclosed water into two (2) laboratory supplied 40-milliliter (ml) sampling vials with Hydrochloric Acid (HCL) preservative and placing in a cooler with ice to chill the samples to four degrees Centigrade (4oC) awaiting transport to Argus Analytical, Inc., Ridgeland, Mississippi, an approved National Environmental Laboratory Accreditation Program (NELAP) laboratory for analysis. All retrieved groundwater samples were analyzed according to EPA Method 8260B for Volatile Organic Compounds. Since PDBs are too large and drop-tubes prevent the placement of PDBs within the casing of recovery wells, disposable bailers were utilized to obtain samples from the recovery wells and Piezometer Well PZ-2-19. Groundwater samples were collected from May 30 - 31, 2007, from the following locations: MW-1-29 MW-5-40 MW-7-57 MW-10-20 MW-12-31 MW-15-40 MW-18-20 MW-20-50 MW-26-25 MW-29-40 MW-32-30 MW-35-30 MW-38-30 MW-41-30 MW-45-50 MW-50-20 RW-18-38 OCTOBER, 2007 MW-2-60 MW-5-60 MW-8-19 MW-10-34 MW-12-47 MW-15-60 MW-18-40 MW-21-30 MW-26-40 MW-29-64 MW-32-40 MW-35-50 MW-38-60 MW-42-30 MW-46-30 MW-51-30 RW-20-59 MW-2-118 MW-6-24 MW-8-119.5 MW-10-45 MW-13-36 MW-16-43 MW-18-60 MW-22-30 MW-26-57 MW-30-30 MW-33-30 MW-36-30 MW-39-30 MW-43-30 MW-46-50 MW-52-30 RW/MW-02-29 MW-3-29 MW-6-59.5 MW-9-19 MW-11-17 MW-13-58 MW-16-57 MW-19-40 MW-23-30 MW-27-40 MW-30-50 MW-33-40 MW-36-50 MW-39-60 MW-44-30 MW-47-50 PZ-01-29A RW/MW-05-24 MW-4-43 MW-7-19 MW-9-34 MW-11-35 MW-14-36 MW-17-30 MW-19-60 MW-24-30 MW-28-118 MW-31-30 MW-34-30 MW-37-30 MW-40-30 MW-44-50 MW-48-20 PZ-2-19 RW/MW-13-20 MW-4-60 MW-7-42 MW-9-48 MW-12-20 MW-14-57 MW-17-48 MW-20-28.5 MW-25-30 MW-29-25 MW-31-39 MW-34-50 MW-37-60 MW-40-57 MW-45-30 MW-49-20 PZ-3-19 RW/MW-14-20 HAZCLEAN REPORT NO. 07.0306.52 RW/MW-15-20 MW-53-60 MW-56-60 MW-59-60 RW/MW-16-28 MW-54-30 MW-57-30 RW/MW-19-20 MW-54-60 MW-57-60 PAGE 10 RW/MW-4-29 MW-55-30 MW-58-30 RW-18-59 MW-55-60 MW-58-60 MW-53-30 MW-56-30 MW-59-30 For Quality Assurance/Quality Control (QA/QC) purposes, 12 duplicate groundwater samples and one (1) trip blank were collected and submitted for the same analysis as the groundwater samples. The 12 duplicates are identified by the alphabet letters A-L with the actual well in parenthesis: Duplicate A (MW-53-30), B (MW-9-19), C (MW-50-20), D (MW-32-40), E (MW-46-50), F (MW-44-30), G (MW-58-60), H (MW-29-25), I (MW-2-118), J (MW-26-40), K (MW-28-118), and L (MW-20-50). All samples were analyzed for the following site specific target Volatile Organic Compounds (VOCs): Trichloroethene (TCE), Vinyl Chloride, Cis-1,2 Dichloroethene, Trans-1,2Dichloroethene, 1,1-Dichloroethene, Benzene, Toluene, Ethylbenzene, Xylenes (Total), Carbon Disulfide and Styrene. Groundwater levels were measured using a Solinst®, Inc., Model 122 Light Non-Aqueous Phase Liquids (LNAPL)/Dense Non-Aqueous Phase Liquids (DNAPL)/water interface probe. Neither LNAPLs nor DNAPLs were encountered in any measured groundwater or recovery well. Following each measurement, the interface probe was thoroughly cleaned using the following procedure; first with a Liqui-nox® detergent solution, then rinsed with deionized water, then rinsed with pesticide grade isopropanol, and a final rinse with distilled water. Elevations are determined to an accuracy of 0.01 feet from the top of each monitoring well casing elevation. All groundwater measurements are made from the north side of the top of riser pipe casing to ensure consistency in a reference point. The direction of groundwater flow varies for each identified stratigraphic layer. Layer 1: For this monitoring period, the groundwater flow had a predominate westerly direction from PZ-3-19 toward RW/MW-14-20 and continuing a westward direction toward MW-18-20, except in the southeast portion. In the southeast area, the direction changes to a southeasterly flow. The overall flow pattern somewhat mimics the surface topography. Also, during this period, in the months of March and April, RW/MW-13-20 and RW/MW-19-20 were disconnected from the recovery system and RW/MW-15-20 was unable to be located (possibly destroyed). Depths to groundwater ranged from 8.94 feet to 19.84 feet below top of casing (TOC) for this period. Layer 2: Groundwater flow is mainly to the north and east. RW/MW-04-29 did not encounter groundwater this sampling period. RW/MW-02-29 has been disconnected from the treatment system and MW-27-25 was unable to be located. Depths to groundwater range from 14.41 feet below top of casing (TOC) to 25.69 feet below TOC. OCTOBER, 2007 HAZCLEAN REPORT NO. 07.0306.52 PAGE 11 Layer 3: Groundwater flow direction underlying the site is mainly towards the north and east, which has been the general direction for most of the reporting periods. Depths to groundwater have remained about the same as compared to the December, 2006 depths. Depths to groundwater ranges from 9.77 feet to 26.34 feet below top of casing (TOC). Layer 4: Groundwater flow for Stratigraphic Layer 4 has a west to east flow pattern in the direction of Jack Creek, which is located to the southeast and circumvents the site from the southeast to a northerly route and enters Batupan Bogue River. Current (June, 2007) depths compared to December, 2006 depths did not indicate much change; therefore, little recharge/discharge is occurring. RW-18-59 has a depth to groundwater of 7.79 feet below top of casing (TOC). This well compares favorably to Piezometer Well PZ-2-19, which has a depth to groundwater of 8.94 feet below top of casing (TOC). This well’s depth to groundwater implies that it is located within a confined bed, separate and distinct from other wells identified to be in Stratigraphic Layer 4. As a result, it was not utilized in constructing the groundwater flow maps. Depths to groundwater range from 12.98 feet to 28.11 feet below top of casing (TOC). Layer 5: A determination of the groundwater flow is based on only three (3) control points. This layer is similar to Layer 4 in that recharge/discharge does not vary much. Groundwater flow direction is from south to north across the site toward the Batupan Bogue River. Depths to groundwater range from 20.71 feet to 26.21 feet below top of casing (TOC). The groundwater elevations for this sampling event were only slightly different than the December, 2006 sampling event. Table 1, Groundwater Elevation Summary Monitoring and Recovery Wells, presents the groundwater elevations measured from June 27 - 29, 2007, for all wells and by stratigraphic layers. Tables 1-1 through 1-5 present the groundwater elevations for the wells within the respective Stratigraphic Layers 1, 2, 3, 4, and 5. Disposable nitrile gloves were worn during the purging and sampling activities of all wells. Gloves were changed between groundwater purging activities and between sample acquisition of each sampled well. Groundwater samples collected for VOC analysis were placed into two (2) laboratory supplied 40 ml, amber glass sample vials with Teflon® caps. All samples were preserved with Hydrochloric Acid (HCL). After sample collection, the samples were double-bagged in Ziploc™ freezer bags to prevent cross-contamination and then placed in a cooler with ice to be cooled to 4° C. All samples were submitted within the allowed holding time to Argus Analytical, Inc., Ridgeland, Mississippi, for laboratory analysis. OCTOBER, 2007 HAZCLEAN REPORT NO. 07.0306.52 PAGE 12 Table 2, Laboratory Analytical Report Summary, Argus Analytical, Inc., presents the analytical results for all sampled wells. Tables 2-1 through 2-5, Laboratory Analytical Report Summary, detail the analytical results of all sampled wells as applicable for each stratigraphic layer for the June, 2007 sampling event. For the complete analytical report, see Appendix B, Argus Analytical, Inc. Laboratory Reports, Semi-Annual Groundwater Sampling Event. Table 3, Historical (Original to Current) TCE Groundwater Analytical Summary – All Wells, presents and compares the original to the most current TCE concentrations. Tables 3-1 through 3-5 compare the original (1994/1995 data) to the June, 2007 TCE groundwater analytical results for each stratigraphic layer. 4.2 Groundwater Levels and Vacuum Readings For each semi-annual event, groundwater level measurements are only taken in system effectiveness and boundary control wells. Groundwater levels are used to monitor the movement and direction of groundwater flow for all Stratigraphic Layers (1 – 5). A review of site data indicates that only a limited area of the facility is subject to the influence of the GRS unit. The areas showing influence are the areas of major concern, specifically in the areas of monitoring wells 13, 14, 15 and 16. Vacuum readings are taken on all recovery wells to determine their working efficiency. Vacuum readings are measured at the wellhead while the system is operating at vacuum with a permanently mounted vacuum gauge at the wellhead. The normal vacuum operating range by the liquid ring vacuum pump (LRVP) is between 15 – 17 inches of Mercury. OCTOBER, 2007 HAZCLEAN REPORT NO. 07.0306.52 5.0 PAGE 13 SITE RESPONSE TO TREATMENT Monitoring activities, including the measurement of VOC exhaust concentrations, exhaust temperatures, pressure gauge and control panel readings, groundwater influent and effluent concentrations, groundwater treated volumes, system repairs, and other criteria required to maintain the GRS have been conducted. As discrepancies and malfunctioning items and/or equipment are identified, repairs are made and adjustments to the system are made. Major repairs, such as upgrading the system, were not conducted since a new treatment system and recovery well arrangement is being implemented. On a monthly basis, exhaust (air) VOC emission concentrations are measured with a Photovac MicroFID, handheld Flame Ionization Detector (FID) Meter capable of detecting VOCs in a range from 0.5 to 50,000 parts per million (ppm). Prior to collecting each vapor reading, the HVM is calibrated in accordance to manufacturer’s instructions. By correlating analytical data with measured VOC concentrations, monitoring exhaust gas velocities and concentrations, the vapor mass of VOCs as TCE being removed is calculated. The GRS is recovering vadose zone soil vapors from the facility’s recovery well system at a rate of approximately 277 cubic feet per minute for this semi-annual period. 5.1 Total TCE Mass Removed (Vapor and Groundwater) For the second semi-annual period of the seventh year of operation (January 1, 2007 – June 30, 2007), the GRS has extracted a combined total of 1,644.89 pounds (0.82 tons) of TCE in vapor form and from groundwater. 5.2 TCE Mass Removed from Groundwater For the semi-annual period (January 1, 2007 – June 30, 2007), the GRS treated 1,126,731 gallons of groundwater in 3,716 operational hours for an average of 5.05 gallons per minute (gpm). The decrease (343,560 gallons) in groundwater processed this period versus last period (1,126,731 gallons vs. 1,470,291 gallons) relates to the decrease in VOCs removed (5.05 pounds vs. 5.16 pounds). For the period, the GRS has removed 3.74 pounds of VOCs from the groundwater. OCTOBER, 2007 HAZCLEAN REPORT NO. 07.0306.52 5.3 PAGE 14 TCE Mass Removed as Vapor For the semi-annual period (January 1, 2007 – June 30, 2007), the GRS removed 1,641.15 pounds (0.82 tons) as vapor this period resulting in a decrease (279.31 pounds) over the previous period (1,641.15 pounds vs. 1,920.46 pounds and 0.82 tons vs. 0.96 tons). The system’s actual exhaust volumetric flow rate (Q)1 was calculated at an average 277 cubic feet per minute (cfm) based on six (6) measurements during the semiannual period. 1 The actual volumetric flow rate (Q) for the system was determined utilizing the following equation: Q=VA Where Velocity (V): V=1096(VP/) ½ and VP= velocity pressure in the exhaust stack (inches of Water) = density of the stack gas (pounds per cubic foot) A= the cross sectional area of the stack (square feet). The exhaust velocity pressure (VP) was measured utilizing a Dwyer Pitot Tube and a digital manometer traversed perpendicular across the diameter of the exhaust stack as given in Dwyer Instruments Inc., Bulletin No. H-11. The stack gas density was determined by measuring the stack gas dry bulb, wet bulb temperatures and relative humidity and using a psychometric air properties calculator to find the specific volume, which is the reciprocal of the density. 5.4 GRS Treatment Summary For the second semi-annual period of the seventh year of operation (January 1, 2007 June 30, 2007), the GRS has operated in compliance with NPDES Permit No. MS0001368. Since the start-up of the system in March, 2000, the GRS has removed a total of 51,348 pounds (25.67 tons) of VOC/TCE in vapor form and a total of 1,346 pounds (0.67 tons) of VOC/TCE from groundwater. A total of 52,695 pounds (26.35 tons) of VOCs have been removed from the subsurface by the GRS in 54,340 operating hours. Table 5, GRS Operational Summary, details GRS applied vacuum, runtime, total effluent discharge, groundwater influent and effluent concentrations, GRS vapor effluent concentrations, and GRS vapor velocities. Monthly influent and effluent laboratory analytical reports are attached in Appendix A. OCTOBER, 2007 HAZCLEAN REPORT NO. 07.0306.52 6.0 REMEDIAL PROGRESS EVALUATION 6.1 Operations Summary PAGE 15 Dense Non-Aqueous Phase Liquids (DNAPLs) were not detected or measured by the interface probe in any monitoring well at the facility. DNAPLs have not accumulated within any component of the GRS. The GRS has proved to be an effective means of remediation for the site. From a review of the historical analytical data, a number of groundwater monitoring wells in each stratigraphic unit show a decrease in TCE concentration over time. TCE concentrations at the start of operations March, 2000 to the June, 2007 analytical results for each stratigraphic layer are summarized as follows (see Tables 3-1 through 3-5): Layer 1: This layer continues to show substantial lowering of contamination from original high levels in many wells. Although down from their original 19941995 values, monitoring wells MW-7-19, MW-9-19, MW-18-20, MW-49-20, and MW-50-20 had increases. The largest increase occurred in MW-50-20 (188 mg/l vs. 136 mg/l). As stated in previous reports, this monitoring well is most likely being contaminated from spillage of untreated and/or partially treated waters from the old treatment system. Additionally, recovery well RW/MW-14-20 increased from 22.6 mg/l to 28.5 mg/l. Three (3) recovery wells (RW/MW-13-20, RW/MW-15-20, and RW/MW-19-20) were disconnected and/or destroyed during this semi-annual monitoring period; therefore, no sampling was conducted for these wells. For the remaining wells in this layer, contamination levels ranged from <0.002 to 1.24 mg/l. Layer 2: This layer continues to show decreases in contamination in the majority of wells. Increases were noted for monitoring wells MW-1-29, MW-3-29, MW-16-43, MW-17-48, MW-23-30, MW-37,30, PZ-1-29A and recovery well RW/MW-16-28. The highest concentrations are found in MW-18-40 (14.1 mg/l); RW/MW-05-24 (17.2 mg/l) and RW/MW-16-28 (6.47 mg/l). While these wells are the highest in concentration, they have been reduced from levels ranging upwards to 238 mg/l. The remaining wells in Layer 2 range from <0.002 mg/l to 17.2 mg/l. MW-27-25 was unable to be located (UTL). RW/MW-2-29 was disconnected in April and RW/MW-4-29 did not encounter groundwater (GWNE). OCTOBER, 2007 HAZCLEAN REPORT NO. 07.0306.52 PAGE 16 Layer 3: For this semi-annual sampling event, Layer 3 had little change from the previous (December 2006) sampling event. The higher concentration wells (MW-02-60, MW-05-40, MW-07-42, MW-09-34, MW-13-36, MW-14-36, MW-15-40 and MW-20-50), which are within the suspect source areas, remained mostly stable in concentration levels (see Table 3-3, Historical [Original to Current] TCE Groundwater Analytical Summary [Stratigraphic Layer 3] for results). Layer 4: Layer 4 has 31 wells being monitored. The highest concentration is still in MW-14-57 but is down from its highest concentration of 317 mg/l to 219 mg/l. Based on the June, 2007 analytical results, this layer appears to be stabilizing in its vertical and horizontal migration for the most part, with the exception of MW-4-60 and MW-14-57. MW-4-60 increased from 14.5 mg/l to 43.6 mg/l and MW-14-57 increased from 119 mg/l to 219 mg/l. Layer 5: This layer, which has only three (3) monitoring wells, has remained stable with concentration levels ranging from <0.002 mg/l to 0.045 mg/l. The effects of a downward migration into this layer are not apparent. Continued groundwater sampling data aids in determining the horizontal and vertical movement of the TCE plume(s) at the facility. 6.2 Findings 1. The GRS has been an effective mechanism for the extraction of VOCs from the groundwater and vadose zone. To date, approximately 54,340 pounds (26.35 tons) of VOCs have been extracted and treated due to vapor extraction and/or groundwater treatment. 2. DNAPLs and LNAPLs were not detected in any measured groundwater monitoring well or groundwater recovery well during the June, 2007 sampling event. 3. During the past semi-annual period, the groundwater influent flow rate, based on gallons processed, ranged from 2.0 gallons per minute (gpm) to 9.3 gpm. The average groundwater GRS influent flow rate is approximately 4.7 gpm into the AWS-1 knockout tank. 4. A number of groundwater monitoring wells in each stratigraphic unit show a decrease in TCE concentration over time. 5. The use of Equilibrator Passive Diffusion Bag (PDB) Samplers is cost effective and maintains the necessary data quality objectives for sampling TCE concentrations. OCTOBER, 2007 HAZCLEAN REPORT NO. 07.0306.52 PAGE 17 TABLE 1 GROUNDWATER ELEVATION SUMMARY MONITORING AND RECOVERY WELLS JUNE, 2007 OCTOBER, 2007 HAZCLEAN REPORT NO. 07.0306.52 PAGE 18 INSERT TABLE 1 PAGE 1 OCTOBER, 2007 HAZCLEAN REPORT NO. 07.0306.52 PAGE 19 INSERT TABLE 1 PAGE 2 OCTOBER, 2007 HAZCLEAN REPORT NO. 07.0306.52 PAGE 20 INSERT TABLE 1 PAGE 3 OCTOBER, 2007 HAZCLEAN REPORT NO. 07.0306.52 PAGE 21 INSERT TABLE 1 PAGE 4 OCTOBER, 2007 HAZCLEAN REPORT NO. 07.0306.52 PAGE 22 INSERT TABLE 1 PAGE 5 OCTOBER, 2007 HAZCLEAN REPORT NO. 07.0306.52 PAGE 23 INSERT TABLE 1 PAGE 6 OCTOBER, 2007 HAZCLEAN REPORT NO. 07.0306.52 PAGE 24 TABLE 1-1 GROUNDWATER ELEVATION SUMMARY MONITORING AND RECOVERY WELLS STRATIGRAPHIC LAYER 1 JUNE, 2007 OCTOBER, 2007 HAZCLEAN REPORT NO. 07.0306.52 PAGE 25 INSERT TABLE 1-1 OCTOBER, 2007 HAZCLEAN REPORT NO. 07.0306.52 PAGE 26 TABLE 1-2 GROUNDWATER ELEVATION SUMMARY MONITORING AND RECOVERY WELLS STRATIGRAPHIC LAYER 2 JUNE, 2007 OCTOBER, 2007 HAZCLEAN REPORT NO. 07.0306.52 PAGE 27 INSERT TABLE 1-2 PAGE 1 OCTOBER, 2007 HAZCLEAN REPORT NO. 07.0306.52 PAGE 28 INSERT TABLE 1-2 PAGE 2 OCTOBER, 2007 HAZCLEAN REPORT NO. 07.0306.52 PAGE 29 TABLE 1-3 GROUNDWATER ELEVATION SUMMARY MONITORING AND RECOVERY WELLS STRATIGRAPHIC LAYER 3 JUNE, 2007 OCTOBER, 2007 HAZCLEAN REPORT NO. 07.0306.52 PAGE 30 INSERT TABLE 1-3 PAGE 1 OCTOBER, 2007 HAZCLEAN REPORT NO. 07.0306.52 PAGE 31 INSERT TABLE 1-3 PAGE 2 OCTOBER, 2007 HAZCLEAN REPORT NO. 07.0306.52 PAGE 32 TABLE 1-4 GROUNDWATER ELEVATION SUMMARY MONITORING AND RECOVERY WELLS STRATIGRAPHIC LAYER 4 JUNE, 2007 OCTOBER, 2007 HAZCLEAN REPORT NO. 07.0306.52 PAGE 33 INSERT TABLE 1-4 PAGE 1 OCTOBER, 2007 HAZCLEAN REPORT NO. 07.0306.52 PAGE 34 INSERT TABLE 1-4 PAGE 2 OCTOBER, 2007 HAZCLEAN REPORT NO. 07.0306.52 PAGE 35 TABLE 1-5 GROUNDWATER ELEVATION SUMMARY MONITORING AND RECOVERY WELLS STRATIGRAPHIC LAYER 5 JUNE, 2007 OCTOBER, 2007 HAZCLEAN REPORT NO. 07.0306.52 PAGE 36 INSERT TABLE 1-5 OCTOBER, 2007 HAZCLEAN REPORT NO. 07.0306.52 PAGE 37 TABLE 2 LABORATORY ANALYTICAL REPORT SUMMARY ARGUS ANALYTICAL, INC. JUNE, 2007 OCTOBER, 2007 HAZCLEAN REPORT NO. 07.0306.52 PAGE 38 INSERT TABLE 2 PAGE 1 OCTOBER, 2007 HAZCLEAN REPORT NO. 07.0306.52 PAGE 39 INSERT TABLE 2 PAGE 2 OCTOBER, 2007 HAZCLEAN REPORT NO. 07.0306.52 PAGE 40 INSERT TABLE 2 PAGE 3 OCTOBER, 2007 HAZCLEAN REPORT NO. 07.0306.52 PAGE 41 INSERT TABLE 2 PAGE 4 OCTOBER, 2007 HAZCLEAN REPORT NO. 07.0306.52 PAGE 42 INSERT TABLE 2 PAGE 5 OCTOBER, 2007 HAZCLEAN REPORT NO. 07.0306.52 PAGE 43 INSERT TABLE 2 PAGE 6 OCTOBER, 2007 HAZCLEAN REPORT NO. 07.0306.52 PAGE 44 TABLE 2-1 LABORATORY ANALYTICAL REPORT SUMMARY ARGUS ANALYTICAL, INC. STRATIGRAPHIC LAYER 1 JUNE, 2007 OCTOBER, 2007 HAZCLEAN REPORT NO. 07.0306.52 PAGE 45 INSERT TABLE 2-1 OCTOBER, 2007 HAZCLEAN REPORT NO. 07.0306.52 PAGE 46 TABLE 2-2 LABORATORY ANALYTICAL REPORT SUMMARY ARGUS ANALYTICAL, INC. STRATIGRAPHIC LAYER 2 JUNE, 2007 OCTOBER, 2007 HAZCLEAN REPORT NO. 07.0306.52 PAGE 47 INSERT TABLE 2-2 PAGE 1 OCTOBER, 2007 HAZCLEAN REPORT NO. 07.0306.52 PAGE 48 INSERT TABLE 2-2 PAGE 2 OCTOBER, 2007 HAZCLEAN REPORT NO. 07.0306.52 PAGE 49 TABLE 2-3 LABORATORY ANALYTICAL REPORT SUMMARY ARGUS ANALYTICAL, INC. STRATIGRAPHIC LAYER 3 JUNE, 2007 OCTOBER, 2007 HAZCLEAN REPORT NO. 07.0306.52 PAGE 50 INSERT TABLE 2-3 PAGE 1 OCTOBER, 2007 HAZCLEAN REPORT NO. 07.0306.52 PAGE 51 INSERT TABLE 2-3 PAGE 2 OCTOBER, 2007 HAZCLEAN REPORT NO. 07.0306.52 PAGE 52 TABLE 2-4 LABORATORY ANALYTICAL REPORT SUMMARY ARGUS ANALYTICAL, INC. STRATIGRAPHIC LAYER 4 JUNE, 2007 OCTOBER, 2007 HAZCLEAN REPORT NO. 07.0306.52 PAGE 53 INSERT TABLE 2-4 PAGE 1 OCTOBER, 2007 HAZCLEAN REPORT NO. 07.0306.52 PAGE 54 INSERT TABLE 2-4 PAGE 2 OCTOBER, 2007 HAZCLEAN REPORT NO. 07.0306.52 PAGE 55 TABLE 2-5 LABORATORY ANALYTICAL REPORT SUMMARY ARGUS ANALYTICAL, INC. STRATIGRAPHIC LAYER 5 JUNE, 2007 OCTOBER, 2007 HAZCLEAN REPORT NO. 07.0306.52 PAGE 56 INSERT TABLE 2-5 OCTOBER, 2007 HAZCLEAN REPORT NO. 07.0306.52 PAGE 57 TABLE 3 HISTORICAL (ORIGINAL TO CURRENT) TCE GROUNDWATER ANALYTICAL SUMMARY – ALL WELLS OCTOBER, 2007 HAZCLEAN REPORT NO. 07.0306.52 PAGE 58 INSERT TABLE 3 PAGE 1 OCTOBER, 2007 HAZCLEAN REPORT NO. 07.0306.52 PAGE 59 INSERT TABLE 3 PAGE 2 OCTOBER, 2007 HAZCLEAN REPORT NO. 07.0306.52 PAGE 60 INSERT TABLE 3 PAGE 3 OCTOBER, 2007 HAZCLEAN REPORT NO. 07.0306.52 PAGE 61 INSERT TABLE 3 PAGE 4 OCTOBER, 2007 HAZCLEAN REPORT NO. 07.0306.52 PAGE 62 INSERT TABLE 3 PAGE 5 OCTOBER, 2007 HAZCLEAN REPORT NO. 07.0306.52 PAGE 63 INSERT TABLE 3 PAGE 6 OCTOBER, 2007 HAZCLEAN REPORT NO. 07.0306.52 PAGE 64 INSERT TABLE 3 PAGE 7 OCTOBER, 2007 HAZCLEAN REPORT NO. 07.0306.52 PAGE 65 TABLE 3-1 HISTORICAL (ORIGINAL TO CURRENT) TCE GROUNDWATER ANALYTICAL SUMMARY STRATIGRAPHIC LAYER 1 OCTOBER, 2007 HAZCLEAN REPORT NO. 07.0306.52 PAGE 66 INSERT TABLE 3-1 OCTOBER, 2007 HAZCLEAN REPORT NO. 07.0306.52 PAGE 67 TABLE 3-2 HISTORICAL (ORIGINAL TO CURRENT) TCE GROUNDWATER ANALYTICAL SUMMARY STRATIGRAPHIC LAYER 2 OCTOBER, 2007 HAZCLEAN REPORT NO. 07.0306.52 PAGE 68 INSERT TABLE 3-2 PAGE 1 OCTOBER, 2007 HAZCLEAN REPORT NO. 07.0306.52 PAGE 69 INSERT TABLE 3-2 PAGE 2 OCTOBER, 2007 HAZCLEAN REPORT NO. 07.0306.52 PAGE 70 TABLE 3-3 HISTORICAL (ORIGINAL TO CURRENT) TCE GROUNDWATER ANALYTICAL SUMMARY STRATIGRAPHIC LAYER 3 OCTOBER, 2007 HAZCLEAN REPORT NO. 07.0306.52 PAGE 71 INSERT TABLE 3-3 PAGE 1 OCTOBER, 2007 HAZCLEAN REPORT NO. 07.0306.52 PAGE 72 INSERT TABLE 3-3 PAGE 2 OCTOBER, 2007 HAZCLEAN REPORT NO. 07.0306.52 PAGE 73 TABLE 3-4 HISTORICAL (ORIGINAL TO CURRENT) TCE GROUNDWATER ANALYTICAL SUMMARY STRATIGRAPHIC LAYER 4 OCTOBER, 2007 HAZCLEAN REPORT NO. 07.0306.52 PAGE 74 INSERT TABLE 3-4 PAGE 1 OCTOBER, 2007 HAZCLEAN REPORT NO. 07.0306.52 PAGE 75 INSERT TABLE 3-4 PAGE 2 OCTOBER, 2007 HAZCLEAN REPORT NO. 07.0306.52 PAGE 76 TABLE 3-5 HISTORICAL (ORIGINAL TO CURRENT) TCE GROUNDWATER ANALYTICAL SUMMARY STRATIGRAPHIC LAYER 5 OCTOBER, 2007 HAZCLEAN REPORT NO. 07.0306.52 PAGE 77 INSERT TABLE 3-5 OCTOBER, 2007 HAZCLEAN REPORT NO. 07.0306.52 PAGE 78 TABLE 4 COMPOSITE HISTORICAL TCE GROUNDWATER ANALYTICAL SUMMARY MONITORING AND RECOVERY WELLS – ALL OCTOBER, 2007 HAZCLEAN REPORT NO. 07.0306.52 PAGE 79 INSERT TABLE 4 PAGE 1 OCTOBER, 2007 HAZCLEAN REPORT NO. 07.0306.52 PAGE 80 INSERT TABLE 4 PAGE 2 OCTOBER, 2007 HAZCLEAN REPORT NO. 07.0306.52 PAGE 81 INSERT TABLE 4 PAGE 3 OCTOBER, 2007 HAZCLEAN REPORT NO. 07.0306.52 PAGE 82 INSERT TABLE 4 PAGE 4 OCTOBER, 2007 HAZCLEAN REPORT NO. 07.0306.52 PAGE 83 INSERT TABLE 4 PAGE 5 OCTOBER, 2007 HAZCLEAN REPORT NO. 07.0306.52 PAGE 84 INSERT TABLE 4 PAGE 6 OCTOBER, 2007 HAZCLEAN REPORT NO. 07.0306.52 PAGE 85 INSERT TABLE 4 PAGE 7 OCTOBER, 2007 HAZCLEAN REPORT NO. 07.0306.52 PAGE 86 TABLE 4-1 COMPOSITE HISTORICAL TCE GROUNDWATER ANALYTICAL SUMMARY MONITORING AND RECOVERY WELLS (STRATIGRAPHIC LAYER 1) OCTOBER, 2007 HAZCLEAN REPORT NO. 07.0306.52 PAGE 87 INSERT TABLE 4-1 PAGE 1 OCTOBER, 2007 HAZCLEAN REPORT NO. 07.0306.52 PAGE 88 INSERT TABLE 4-1 PAGE 2 OCTOBER, 2007 HAZCLEAN REPORT NO. 07.0306.52 PAGE 89 TABLE 4-2 COMPOSITE HISTORICAL TCE GROUNDWATER ANALYTICAL SUMMARY MONITORING AND RECOVERY WELLS (STRATIGRAPHIC LAYER 2) OCTOBER, 2007 HAZCLEAN REPORT NO. 07.0306.52 PAGE 90 INSERT TABLE 4-2 PAGE 1 OCTOBER, 2007 HAZCLEAN REPORT NO. 07.0306.52 PAGE 91 INSERT TABLE 4-2 PAGE 2 OCTOBER, 2007 HAZCLEAN REPORT NO. 07.0306.52 PAGE 92 TABLE 4-3 COMPOSITE HISTORICAL TCE GROUNDWATER ANALYTICAL SUMMARY MONITORING AND RECOVERY WELLS (STRATIGRAPHIC LAYER 3) OCTOBER, 2007 HAZCLEAN REPORT NO. 07.0306.52 PAGE 93 INSERT TABLE 4-3 PAGE 1 OCTOBER, 2007 HAZCLEAN REPORT NO. 07.0306.52 PAGE 94 INSERT TABLE 4-3 PAGE 2 OCTOBER, 2007 HAZCLEAN REPORT NO. 07.0306.52 PAGE 95 INSERT TABLE 4-3 PAGE 3 OCTOBER, 2007 HAZCLEAN REPORT NO. 07.0306.52 PAGE 96 TABLE 4-4 COMPOSITE HISTORICAL TCE GROUNDWATER ANALYTICAL SUMMARY MONITORING AND RECOVERY WELLS (STRATIGRAPHIC LAYER 4) OCTOBER, 2007 HAZCLEAN REPORT NO. 07.0306.52 PAGE 97 INSERT TABLE 4-4 PAGE 1 OCTOBER, 2007 HAZCLEAN REPORT NO. 07.0306.52 PAGE 98 INSERT TABLE 4-4 PAGE 2 OCTOBER, 2007 HAZCLEAN REPORT NO. 07.0306.52 PAGE 99 INSERT TABLE 4-4 PAGE 3 OCTOBER, 2007 HAZCLEAN REPORT NO. 07.0306.52 PAGE 100 TABLE 4-5 COMPOSITE HISTORICAL TCE GROUNDWATER ANALYTICAL SUMMARY MONITORING AND RECOVERY WELLS (STRATIGRAPHIC LAYER 5) OCTOBER, 2007 HAZCLEAN REPORT NO. 07.0306.52 PAGE 101 INSERT TABLE 4-5 OCTOBER, 2007 HAZCLEAN REPORT NO. 07.0306.52 PAGE 102 TABLE 5 GRS OPERATIONAL SUMMARY MARCH, 2000 THROUGH JUNE, 2007 OCTOBER, 2007 HAZCLEAN REPORT NO. 07.0306.52 PAGE 103 INSERT TABLE 5 PAGE 1 OCTOBER, 2007 HAZCLEAN REPORT NO. 07.0306.52 PAGE 104 INSERT TABLE 5 PAGE 2 OCTOBER, 2007 HAZCLEAN REPORT NO. 07.0306.52 PAGE 105 TABLE 5 PAGE 3 OCTOBER, 2007 HAZCLEAN REPORT NO. 07.0306.52 PAGE 106 TABLE 5 PAGE 4 OCTOBER, 2007 HAZCLEAN REPORT NO. 07.0306.52 PAGE 107 TABLE 5 PAGE 5 OCTOBER, 2007 HAZCLEAN REPORT NO. 07.0306.52 PAGE 108 TABLE 5 PAGE 6 OCTOBER, 2007 HAZCLEAN REPORT NO. 07.0306.52 PAGE 109 TABLE 5 PAGE 7 OCTOBER, 2007 HAZCLEAN REPORT NO. 07.0306.52 PAGE 110 TABLE 5 PAGE 8 OCTOBER, 2007 HAZCLEAN REPORT NO. 07.0306.52 PAGE 111 GRAPH 1 CUMULATIVE VOLATILE ORGANIC COMPOUNDS (VOCs) REMOVED MARCH, 2000 TO JUNE, 2007 OCTOBER, 2007 HAZCLEAN REPORT NO. 07.0306.52 PAGE 112 INSERT GRAPH 1 OCTOBER, 2007 HAZCLEAN REPORT NO. 07.0306.52 PAGE 113 FIGURE 1 SITE LAYOUT OCTOBER, 2007 HAZCLEAN REPORT NO. 07.0306.52 PAGE 114 INSERT FIGURE 1 OCTOBER, 2007 HAZCLEAN REPORT NO. 07.0306.52 PAGE 115 FIGURE 2-1 GROUNDWATER ELEVATION CONTOUR MAP (STRATIGRAPHIC LAYER 1) OCTOBER, 2007 HAZCLEAN REPORT NO. 07.0306.52 PAGE 116 INSERT FIGURE 2-1 OCTOBER, 2007 HAZCLEAN REPORT NO. 07.0306.52 PAGE 117 FIGURE 2-2 GROUNDWATER ELEVATION CONTOUR MAP (STRATIGRAPHIC LAYER 2) OCTOBER, 2007 HAZCLEAN REPORT NO. 07.0306.52 PAGE 118 INSERT FIGURE 2-2 OCTOBER, 2007 HAZCLEAN REPORT NO. 07.0306.52 PAGE 119 FIGURE 2-3 GROUNDWATER ELEVATION CONTOUR MAP (STRATIGRAPHIC LAYER 3) OCTOBER, 2007 HAZCLEAN REPORT NO. 07.0306.52 PAGE 120 INSERT FIGURE 2-3 OCTOBER, 2007 HAZCLEAN REPORT NO. 07.0306.52 PAGE 121 FIGURE 2-4 GROUNDWATER ELEVATION CONTOUR MAP (STRATIGRAPHIC LAYER 4) OCTOBER, 2007 HAZCLEAN REPORT NO. 07.0306.52 PAGE 122 INSERT FIGURE 2-4 OCTOBER, 2007 HAZCLEAN REPORT NO. 07.0306.52 PAGE 123 FIGURE 2-5 GROUNDWATER ELEVATION CONTOUR MAP (STRATIGRAPHIC LAYER 5) OCTOBER, 2007 HAZCLEAN REPORT NO. 07.0306.52 PAGE 124 INSERT FIGURE 2-5 OCTOBER, 2007 HAZCLEAN REPORT NO. 07.0306.52 PAGE 125 FIGURE 3-1 TCE CONCENTRATION MAP (STRATIGRAPHIC LAYER 1) OCTOBER, 2007 HAZCLEAN REPORT NO. 07.0306.52 PAGE 126 INSERT FIGURE 3-1 OCTOBER, 2007 HAZCLEAN REPORT NO. 07.0306.52 PAGE 127 FIGURE 3-2 TCE CONCENTRATION MAP (STRATIGRAPHIC LAYER 2) OCTOBER, 2007 HAZCLEAN REPORT NO. 07.0306.52 PAGE 128 INSERT FIGURE 3-2 OCTOBER, 2007 HAZCLEAN REPORT NO. 07.0306.52 PAGE 129 FIGURE 3-3 TCE CONCENTRATION MAP (STRATIGRAPHIC LAYER 3) OCTOBER, 2007 HAZCLEAN REPORT NO. 07.0306.52 PAGE 130 INSERT FIGURE 3-3 OCTOBER, 2007 HAZCLEAN REPORT NO. 07.0306.52 PAGE 131 FIGURE 3-4 TCE CONCENTRATION MAP (STRATIGRAPHIC LAYER 4) OCTOBER, 2007 HAZCLEAN REPORT NO. 07.0306.52 PAGE 132 INSERT FIGURE 3-4 OCTOBER, 2007 HAZCLEAN REPORT NO. 07.0306.52 PAGE 133 FIGURE 3-5 TCE CONCENTRATION MAP (STRATIGRAPHIC LAYER 5) OCTOBER, 2007 HAZCLEAN REPORT NO. 07.0306.52 PAGE 134 INSERT FIGURE 3-5 OCTOBER, 2007 HAZCLEAN REPORT NO. 07.0306.52 PAGE 135 FIGURE 4 SYSTEM RECOVERY WELL(S) VACUUM READINGS (STRATIGRAPHIC LAYERS 1 AND 2) OCTOBER, 2007 APPENDIX A GRS MONTHLY LABORATORY ANALYTICAL REPORTS EFFLUENT AND INFLUENT JANUARY THROUGH JUNE, 2007 APPENDIX B ARGUS ANALYTICAL, INC. LABORATORY REPORTS SEMI-ANNUAL GROUNDWATER SAMPLING EVENT JUNE, 2007