PUNJAB ROAD SECTOR PROJECT, PHASE-2 CONSTRUCTION OF ROBs PRE-BID MEETING HELD ON 10.05.2006 Details/record of discussion held in the pre-bid meeting on 10.5.2006 (11:00 AM) in the committee room of Punjab Infrastructure Development Board, SCO 89-90, Sector 34-A, Chandigarh. The following were present in addition to members of the Sectoral Sub Committee (Road Sector): Representatives of Agency 1. Sh. P.P. Arashu, Area Manager, M/s Gammon India Ltd. 2. Sh. M.S. Bhatt, Project Manager, M/s Valecha Engg. Ltd., Mumbai 3. Sh. Pawan Gupta, M/s Amarnath Aggarwal, Panchkula. 4. Praveen Gupta, M/s S.P. Singla Cont. Pvt. Ltd., Panchkula. 5. Sh. Y.R. Bajaj, CE, M/s Brahmaputra Consortium Ltd., 6. Sh. J. Sharma, M/s J.C. Gupta. 7. Sh. R. Goel, Partner, JV, M/s Anil Kumar Gupta, 8. Sh. Jagdeep Singh, Director, M/s R.S. Infrastructure. 9. Sh. S.K. Sharma, M/s U.A.N.R.C. JV, Ltd. 10. Sh. Hardeep Singh, CEO, M/s MSK Projects. 11. Sh. C. Surendran, CEO, M/s MSK Projects. 12. Sh. S.P. Singla, M/s S.P. Singla, Panchkula. 13. Sh. Ashok Kumar, GM, M/s R.S.I. Sr. No. Punjab PWD B&R Branch 1. Sh. T.S. Chahal, EE, Const. Divn. Malerkotla 2. Sh. P.K. Goyal, EE, Provl. Divn. No. 1, Patiala. 3. Sh. Sher Mohd. EE, Provl. Divn. Sangrur. 4. Sh. G.R. Bains, EE, Const. Divn. No. 1, Hoshiarpur. 5. Sh. Anil Gupta, EE (D-II), O/o CE, Patiala. 6. Sh. Vipan Bansal, SDE, Batala. 7. Sh. S.L. Bassi, SDE, Beas. M/s RITES Ltd. 1. 2. 3. 4. Sh. S.K. Aich, JGM. Sh. M. Sridhar, DGM. Sh. O.P. Kapoor. GM. Sh. Sanjay Bhargava, Assistant GM. Question Clarifications M/s GAMMON INDIA LTD. letter dated 09.05.2006 (A) General Technical Specifications (Common) 1. The width of the crash barrier for ROB at Patiala is given as Section shown in the GAD for respective works 0.5m whereas the same for ROBs at Beas & Dhuri is given as shall be adopted. 0.55m. We request that a common width of crash barrier may make applicable for all the ROBs. 2. The height of the electric poles is given as 10.0m for ROB at Height of electric poles above deck slab shall be Patiala and 8.0m for ROB at Dhuri & Beas. Please clarify kept 8.0m in all ROBs. whether all can be considered as 8.0m high. 3. The conditions of expose have been mentioned as severe to Moderate conditions are to be considered. moderate. As Punjab lies in moderate zone we presume the same can be made applicable for design. 4. Please specify whether retaining wall for approaches are RC As per DNIT the option of reinforced earth/RCC retaining wall or RE walls. Also please provide the detailed retaining walls is available. For reinforced earth specifications for reinforced earthwork. work the specification as per MORT&H shall be followed. 5. Please clarify whether the lap lengths can be provided as per As per DNIT IRC:21 instead of 63d, mentioned in the documents. 6. Please provide a detailed sketch of the view cutter mentioned Description of item already detailed on Page 75 in pg. no.75 of ROB at Patiala. (Para-4). Sketch appended and can also be downloaded from website. 7. CI. 1.5 of Technical Specifications: As per code Ludhiana, As per DNIT Bathinda & Patiala are in Zone-III. We presume the horizontal seismic coefficient for all 3 ROBs to be evaluated as per this zone. 8. CI. 5.4 of Technical Conditions Seismic coefficient for The words “seismic coefficient shall be bearings: As the latest amendments to IRC 6-2000 already doubled” at the end of clause 4.5 of Technical take into account the higher seismic coefficient, please clarify Condition stand deleted. whether it is necessary to double the seismic coefficient for bearings. In view of the exte3nsive work involved including the strengthening & widening of roads, etc. we request you to extend the date of tender submission to 13 th June, 2006 i.e. by 3 weeks from 23rd May, 2006. ROB at Dhuri Shall be considered and communicated with the corrigendum. Page 1 of 4 PUNJAB ROAD SECTOR PROJECT, PHASE-2 CONSTRUCTION OF ROBs i) ii) The length of stilt portion shown in drawing is 9 x 20.415 = 193.32m at Sangrur side and in pg72 in the work description it is mentioned as 163.32m. Please clarify. In the Sherpur side arm, the total length as per drawing is 398.28m with 188.92m solid fill whereas as per pg 72 cl. (A) (iii) the total length is 400.58m with 171.23m solid fill. Please clarify. iii) In the longitudinal section of ramp towards Sherpur side the ground levels are in the range of 999m and proposed road levels are in the range of 239m. Please clarify these discrepancies. iv) In the longitudinal section of the main ROB the same discrepancies as in (iii) above are found in the existing ground levels and proposed road levels at the Sangrur end. Please clarify. v) Page 74 cl. (D) (iii): Please furnish the location of the slab type culvert in the drawing and the details of the same. PRE-BID MEETING HELD ON 10.05.2006 Length 163.32m has already been correctly indicated in DNIT. Drawing appended with DNIT are being revised and issued as a corrigendum. Copy of corrigendum/ amendment can also be downloaded from PIDB website. Location has been indicated in DNIT. The span arrangement shall be kept same as of the existing culvert to be widened. ROB at Beas i) The proposed road levels, chainage and existing ground levels are not given in the drawings. Kindly furnish the same. Already correctly indicated in GAD appended with DNIT. ii) In pg. No. 74 cl. (D) of section 4, Contract Data – Diversion Roads, the width of the diversion roads and the position of the same is not furnished in the drawings. Please clarify. The width of the diversion road is to be 5.5 m (Metalled portion) with 1.5m wide earthen shoulders on either side. ROB at Patiala i) Page No. 74 clause (A) first paragraph, construction of service roads, maximum width 7.0/5m mentioned. Please clarify the chainages for 7.0m wide service roads and 5.50m wide service roads. The chainage of service road with respect to width of 7.0/5.5m is already clear in the GAD appended with DNIT. Drawing appended with DNIT are being revised and issued as a corrigendum. Copy of corrigendum/ amendment can also be downloaded from PIDB website. Already clearly indicated in GAD for which reference legend may be seen. Drawing appended with DNIT are being revised and issued as a corrigendum. Copy of corrigendum/ amendment can also be downloaded from PIDB website. As per GAD. ii) Page No. 74 clause (B), second paragraph, widening of leveled portion, width of widened portion s not mentioned. Please clarify the same. Extra widening at `T’ junction for construction of slip road 8.0m wide, improvement of circuit house junction please clarify the area and location in GAD. iii) Page No. 74, third paragraph, strengthening of leveled portion, please clarify the width of the same. iv) Page No. 111 clause No. 13, construction of footpath over drain: Please clarify approximate depth of drains. As indicated in Contract Data at page no. 75. v) Page No. 111 clause no. 14, filling of Rajwaha: Please clarify the area to be filled and depth of filling. vi) In concept plan drawing on Sri Dukh Nivaran Sahib side: Culvert for Rajwaha to be diverted before construction is shown. Please clarify the scope of work for the same. The length of existing Rajwaha also indicated in GAD. Average width and depth are 1.8m and 0.75m respectively which may be verified at site to assess the quantity of filling. Not in the scope of work. vii) ` Page No. 111 clause No. 15, Construction of central verge on both sides of approaches: Please furnish the corresponding detailed sketch for central verge. Already indicated in Contract Data item 9B page 76. M/s MSK Projects (India) Ltd. letter dated 10.05.2006 1. Refer Page No. 72 & 91 of Bid Document While going through the above pages, on Page No. 72 Para-2 it is mentioned that “the solid fill portion shall be retain by reinforced earth/RCC retaining wall adequately anchored in ground”, Clause 5.6.3 of Technical Condition in line 3. “RCC retaining walls” should be read as “Reinforced Earth/RCC retaining wall”. Page 2 of 4 PUNJAB ROAD SECTOR PROJECT, PHASE-2 CONSTRUCTION OF ROBs whereas on Page No. 91 vide clause 5.6.3 it is mentioned that “the solid fill shall be retained by construction of conventional RCC retaining walls”. We request you to please clarify that which type of retaining structure to be provided for solid fill portion. 2. Refer Page No. 92 of Bid Document :Refer Clause 6.6 “Abutment/Dirt Wall” As per this clause the Abutment & Dirt Wall shall be designed for no approach slab condition and have a minimum thickness of 300m. Please clarify that can we provide abutment by using reinforced earth structure? 3. Approval of GAD :We understand that PIDB/PWD Govt. of Punjab will obtain approval of GAD from railway authorities. We request you to clarify the above points and also we understand that the clarifications given by you shall be applicable for all ROBs as per NIT. ROB at Beas PRE-BID MEETING HELD ON 10.05.2006 Abutment and dirt wall shall be conventional R.C.C. Structure. Approval of GAD from Northern Railway has been obtained. i) Slope of 1:35 on Batala side and 1:30 on GT roads As per DNIT. ii) Some plantations on both sides of the road. It is under PWD or Forest ? who will remove it? Shifting of Power line by us or PWD? The site clearance shall be as per provision of DNIT. The site clearance shall be as per provision of DNIT. iv) For Diversion road, whether widening/strengthening of Box culvert over canal is in scope at Baba Batala end? Widening/strengthening of Box envisaged in the scope of work. v) Is there any provision of service Road/approach to existing shops users? As per DNIT vi) Will there be official charges of supervision by PWD? No iii) ROB at Sangrur i) Slope 1:35 OK? ii) Or 1:30 culvert not As per DNIT iv) JBK (Japan Project) Tree plantation. Removal in whose scope. It may call for approval from Delhi. 55.0m Retaining Wall. Purpose? Should we construct (Part-A) – Points levels for end (add in scope of work) OFC shifting involved? Conduits seen at 600 stone The site clearance shall be as per provision of DNIT. As per works specific corrigendum being issued separately. As per DNIT vi) Shifting of electrical line whose scope? As per DNIT iii) vii) Existing culvert at Neat Beas. Dismantling & strengthening viii) Location of Diversion road. ix) Sewerage – Diversion x) Diversion crossing at Railways – Facility of Railways shall be borne by us? 1. As per works specific corrigendum being issued separately. As per works specific corrigendum being issued separately As per DNIT Cost towards making suitable arrangement for providing temporary crossing for Railway portion shall be borne by Railways and/or PWD/PIDB. M/s Valecha letter dated 09.05.2006 We request your good-self to kindly extend the last date for Shall be considered and communicated with the submission of bids from 23.05.2006 to 08.06.2006 (i.e. 15 corrigendum. days) since the scope of work is of design and construct which will take same. M/s S.P. Singla Pvt. Ltd. Commercial Points 1. 2. All Cash Securities deducted from work done bills should be converted into Bank Guarantee from time to time and cash deducted should be released thereby. The Department should remove all over-head and underground utilities whatever to facilitate uninterrupted progress of work. As per DNIT. As per DNIT. Page 3 of 4 PUNJAB ROAD SECTOR PROJECT, PHASE-2 CONSTRUCTION OF ROBs 3. a) b) c) The date start should be considered from the date when the complete site free from all encumbrances is handed over to us. PRE-BID MEETING HELD ON 10.05.2006 As per DNIT M/s Madhava – Brahamputra Consortium Ptd. (JV) The bid security has been asked in the shape of FDR/Deposit As per DNIT at call receipt. It is requested that the Bid Security may please be allowed in the form of Bank Guarantee as the same is being allowed by the GOP/PIDB in other tenders. Reference clause 4.4 on serial page no. 6 of the tender As per DNIT documents: It is stated that in case of consortium, the lead member will have to individually meet the pre-qualification criteria. It is submitted that in a joint venture/consortium the collective experience/financial requirements of the members, simultaneously fixing the minimum requirements of the lead member and other members, may please be allowed. It is submitted that the work involves the total design of the Shall be considered and communicated with the ROBs for which our consultants are likely to take some time. It corrigendum. is requested that the time of submission of the bid may please the extended by fifteen days. Page 4 of 4