CIMS CR 3 - Business Requirements

advertisement
CIMS MAINTENANCE
Business Requirements for CR – 003 and Nov/Dec 2005 JAD
Client:
Date:
Revision:
Ministry of Forests and Range
Compliance and Enforcement Branch
Dec 19, 2005
1
Vivid Solutions Inc.
Suite #1A, 2328 Government St.
Victoria, BC V8T 5G5
Phone: (250) 385-6040
Fax: (250) 385-6046
Website: www.vividsolutions.com
Ministry of Forests and Range
CIMS Maintenance Business Requirements
Document Change Control
REVISION NUMBER
1
DATE OF ISSUE
AUTHOR(S)
DESCRIPTION
Original draft
Page 2 of 23
Ministry of Forests and Range
CIMS Maintenance Business Requirements
Table of Contents
1. INTRODUCTION ..................................................................................................................... 5
1.1
PROJECT VISION...................................................................................................... 5
2. APPROACH .......................................................................................................................... 6
3. USER CLASSES ...................................................................................................................... 7
3.1
PRIMARY USERS ...................................................................................................... 7
3.2
SECONDARY USERS ................................................................................................... 7
4. CONCEPTUAL MODEL .............................................................................................................. 8
4.1
CONTEXT DIAGRAM .................................................................................................. 8
5. BUSINESS PROCESSES .............................................................................................................. 9
5.1
TMTR INSPECTIONS .................................................................................................. 9
5.2
INVALIDATE AND COPY .............................................................................................. 9
5.3
SUPERVISORS TO VIEW SCHEDULES ................................................................................ 9
5.4
PRICING INSPECTIONS ............................................................................................... 10
5.5
PRICING RISK AND PRIORITY ........................................................................................ 10
5.6
MULTI SITE INSPECTIONS FOR ROAD AND SILVICULTURE ....................................................... 10
5.7
SCHEDULING: SITE PRIORITY AND INSPECTION IMPLICATIONS ................................................. 11
5.8
LINKS TO MAPVIEW .................................................................................................. 11
5.9
LINKS TO CUT_BLOCK_OPEN_ADMIN/FTA DATA MODEL CHANGES ............................................ 11
5.10
CIMS MOBILE .......................................................................................................... 11
5.11
LINKS FROM ERA (COMPLIANCE ACTION) .......................................................................... 12
5.12
CIMS PORTAL ......................................................................................................... 12
5.13
FOLLOW UP ........................................................................................................... 13
5.14
INSPECTION ADDENDUM ............................................................................................. 13
5.15
HARVEST COMPLIANCE SUMMARY .................................................................................. 14
5.16
COMPLIANCE SUMMARY ............................................................................................. 14
5.17
RISK ASSESSMENT COPY ............................................................................................. 14
5.18
INSPECTION COPY .................................................................................................... 15
5.19
SPELL CHECKER ...................................................................................................... 15
6. DATA REQUIREMENTS.............................................................................................................. 16
6.1
TMTR INSPECTIONS .................................................................................................. 16
6.2
INVALIDATE AND COPY .............................................................................................. 16
Page 3 of 23
Ministry of Forests and Range
6.3
CIMS Maintenance Business Requirements
PRICING INSPECTIONS ............................................................................................... 17
7. INTERFACE REQUIREMENTS ....................................................................................................... 18
7.1
TMTR INSPECTIONS .................................................................................................. 18
7.2
PRICING INSPECTIONS ............................................................................................... 19
8. PERFORMANCE REQUIREMENTS .................................................................................................. 21
9. INFRASTRUCTURE REQUIREMENTS ............................................................................................... 22
10. DOCUMENT SIGN-OFF ............................................................................................................ 23
Page 4 of 23
Ministry of Forests and Range
CIMS Maintenance Business Requirements
1. INTRODUCTION
1.1
PROJECT VISION
The Compliance and Enforcement Branch (C&E) of the Ministry of Forests of Range (MoFR)
has an existing production application called the Compliance Information Management
System (CIMS). A CIMS working group has been formed and has come up with a number of
enhancements to the CIMS application. This document is intended to capture and describe
the Business Requirements associated with the application enhancements.
Page 5 of 23
Ministry of Forests and Range
CIMS Maintenance Business Requirements
2. APPROACH
The approach taken to identify the requirements is to describe each of the requirements as
a process in the Business Processes section. Where more detail was required, additional
information about a particular requirement has been detailed in the Data Requirements and
Interface Requirements sections.
Page 6 of 23
Ministry of Forests and Range
CIMS Maintenance Business Requirements
3. USER CLASSES
3.1
PRIMARY USERS
The primary users of the CIMS application are:
1. Inspectors – Create Inspections, create Risk Evaluations, assign Site
Priorities, and create Commencement Notices.
2. Supervisors – All of the functions of an Inspector, plus create District
Inspection Plans and manage Inspection Site Assignments.
3. Administrators – Have super user privileges in the application
4. Assessors – Create Risk Evaluations and Assign Site Priorities.
3.2
SECONDARY USERS
The secondary users of the CIMS application are:
1. Viewers – Only view information in the application.
2. Non C&E Assessors – Create Risk Evaluations.
3. Commencement – Create Commencement Notices.
Page 7 of 23
Ministry of Forests and Range
CIMS Maintenance Business Requirements
4. CONCEPTUAL MODEL
4.1
CONTEXT DIAGRAM
This is a simple, high-level diagram of the system boundaries and interactions with
other systems. It forms the basis for further decomposition.
ESF
CIMS
Commencement
Notice
FTA
Risk Evaluation
District
Inspection Plan
ERA
Site Priority
RESULTS
Inspection
Figure 1 - CIMS Overview
Page 8 of 23
Ministry of Forests and Range
CIMS Maintenance Business Requirements
5. BUSINESS PROCESSES
5.1
TMTR INSPECTIO NS
A new inspection type for Timber Marking and Transport Regulation (TMTR) is
needed by C&E. The TMTR Inspection will be used by inspectors to record inspection
information about the transport of logs within the province of BC. TMTR Inspections
can be done at a Region or District level and will consist of inspecting one or more
vehicles or vessels. For each vehicle/vessel inspected, one or more load slips for
that vehicle/vessel will be inspected.
5.2
INVALIDATE AND COPY
In a number of situations, a change is required to a completed inspection (one
reason for the change is a rename of the site that the inspection is for), however
since the inspection is already completed, a change is not allowed to the inspection.
To allow for changes to be made to completed inspections, an Invalidate and Copy
process will be used. The Invalidate and Copy process will be available to the
inspector that originally did the inspection, a FOS, or a CIMS Administrator.
The Invalidate part of the process will take the existing completed inspection and
invalidate it. The Invalidate will also require a Invalidate Rationale be entered to
indicate why the inspection is being invalidated. The Copy part of the process will
copy the now invalidated inspection, assign a new inspection number, and give it a
status of incomplete, so that the copied inspection can be modified. The invalid
inspection should display the text “This inspection was replaced by: {new inspection
id}” on both the inspection web page and printed Inspection reports. The copied
inspection should display the text “This inspection replaces: {original inspection id}”
on both the inspection web page and printed Inspection reports.
To support the above process the following changes are also required:



5.3
Invalid Inspections can be viewed by anyone with view inspection privileges.
When printing Invalid inspections, display ‘Invalid’ as a watermark on the
inspection.
Inspection searches can now return Invalid inspections (default is to not show
invalid inspections).
SUPERVISORS TO VIEW SCHEDULES
In order to better manage their inspectors, supervisors need the ability to view the
schedules for the inspectors in the districts assigned to the supervisor.
The
supervisor will need to identify the inspector’s schedule that the supervisor would
like to view. In the instance where an inspector has a schedule in more that one
district, the supervisor will have to choose a single district to view.
Page 9 of 23
Ministry of Forests and Range
5.4
CIMS Maintenance Business Requirements
PRICING INSPECTIONS
A new inspection type of Pricing is needed by C&E. The Pricing Inspection is typically
done after harvesting is completed. It is used to check that the information provided
in the ECAS submission is correct and that the obligations/actions required by the
licensee relating to stumpage were satisfactorily completed by the licensee. Any
CIMS user with the privilege of Edit Inspections can create a Pricing Inspection.
5.5
PRICING RISK AND PR IORITY
With the new Pricing inspection, a Pricing Risk and Priority are also needed. The
calculated value for the Pricing Risk will be used by both C&E inspectors in CIMS and
staff in the Revenue branch.
The Revenue branch staff will use some other
application (to be defined by Revenue branch) to access the value for Pricing Risk.
The calculation of Pricing Risk will be done using information from ECAS submissions.
The specifics of the calculations still need to be finalized, but will be provided by
Revenue branch staff.
A Pricing Risk will automatically be calculated at the time the ECAS submission is first
accepted/received by MoFR staff. Since the creation of a Pricing Risk will cause a
Risk Site to be created in CIMS, the site will be assigned to an inspector and will be
automatically put on the inspector’s Active schedule. Subsequently, after the rate
status is confirmed, a new Pricing Risk will be calculated. Each time a Pricing Risk is
calculated, a Priority will also be automatically entered for the site. The automatic
Priority will always be set to the same value as the Risk. At any time after the first
Pricing Risk is created for a site, an assessor will be able to go into CIMS and add a
new Priority for that site.
5.6
MULTI SITE INSPECTIO NS FOR ROAD AND SILVICU LTURE
The site for a Road and Silviculture inspection are currently either a single road
section or opening/block respectively. Changes to the site for Road and Silviculture
inspections have been requested and are detailed below.
For a Road Inspection, the inspection site will be one or more road sections on the
same Road (File). If a Non-Compliance or Follow Up is included in the inspection,
the inspector will need to indicate, by way of comments, which road section the NonCompliance or Follow Up pertains to. For the purposes of counting inspections, each
road section included in an inspection will count as a single inspection. For example:
if an inspection includes three road sections, this will count as 3 inspections.
For a Silviculture Inspection, the inspection will still consist of an opening/block. For
an opening/block there are one or more Standards Units (SU) contained in the
opening/block. For the purposes of a Silviculture Inspection, the inspector will be
able to indicate that one or more of the SUs where inspected as part of the
inspection. For the purposes of counting inspections, an opening/block will still count
as a single inspection. In the future, there may be a request to create a separate
report that will show the number of SUs that were inspected.
Page 10 of 23
Ministry of Forests and Range
5.7
CIMS Maintenance Business Requirements
SCHEDULING: SITE PRIORITY AND INSPECTION
IMPLICATIONS
Add the values of Site Priority and Inspection Implications to the Scheduling
Preferences list of items displayed. These values will be available for all inspection
types. When selected in Data Selection, columns for Site Priority and Inspection
Implications will be displayed in the Active and Inactive pages of the Scheduling tool.
5.8
LINKS TO MAPVIEW
From within the CIMS application, links to Mapview have been requested. The links
to Mapview should be available from inspections, risk, and priority for the Harvest,
Road, Silviculture, Recreation, and Range business areas. The link will take the user
into Mapview.
Using the Enforcement view, Mapview display the site of the
inspection, risk, or priority that was linked from.
For the content in Mapview, Priority information from CIMS will be replicated to the
LRDW on a periodic basis (daily or weekly) into the LRDW. The Mapview project will
build a Priority layer for the Priority information from CIMS. This layer will form the
basis of the Enforcement view. The Priority information in the LRDW should only be
accessible to Ministry staff. That is, no one outside of the Ministry should be able
access either the raw Priority data in the LRDW, or the Enforcement view within
Mapview.
5.9
LINKS TO CUT_BLOCK_OPEN_AD MIN/FTA DATA MODEL
CHANGES
The FTA application Data Model is changing with the release of FTA 4, which is to be
released sometime in Spring/Summer 2006. The Changes to the FTA data model will
impact such things as the CUT_BLOCK and TIMBER_MARK entities. This may have a
substantial impact on CIMS. Meetings will need to be scheduled to get more
information on the proposed changes. Additionally, the FTA application team has
requested that CIMS change its referential integrity from linking to the CUT_BLOCK
table to linking to the CUT_BLOCK_OPEN_ADMIN table. This will allow FTA more
flexibility when changing block labels. After the meetings are held with the FTA
team, an approach for dealing with these changes can be developed for CIMS.
5.10 CIMS MOBILE
The CIMS Mobile application allows inspectors to document inspections in the field
and the upload them the CIMS system when the inspector returns to the office. The
CIMS Mobile application requires a number of third party components to be installed
on laptops in order for the software to be available in the field. Reducing the number
of third party components required for the application is very desirable. The CIMS
Page 11 of 23
Ministry of Forests and Range
CIMS Maintenance Business Requirements
application is also going thru a rebranding at the moment, which will result in a
completely new interface for the application. CIMS and CIMS Mobile share a very
similar interface, so CIMS Mobile will also require a rebranding.
In order to accommodate the above two items, the following changes can be made
to the CIMS Mobile application:
 Apply the interface style of CIMS after rebranding to CIMS Mobile. Only the
Inspection module (not including Gov’t Statutory Obligations) will be included
in CIMS Mobile. All code not part of the Inspection module (for example: Risk
Module) will be removed for the CIMS Mobile source.
 Remove the MSDE component. CIMS Mobile will be modified to use XML files
as the persistent data store mechanism. Currently, inspections are uploaded
and downloaded using XML files, so the XML schema already exists for the
different inspection types.
 Remove the Crystal Reports component. For the printing of Inspection
Reports from CIMS Mobile, an HTML print employing CSS (cascading style
sheets) will be used.
Additionally, to support other changes made to the inspection module in CIMS the
following changes to CIMS Mobile are also required.
 Include the new Pricing Inspection.
 Include the new TMTR Inspection to CIMS Mobile.
 Any changes in CR2 or CR4 that apply to the Inspection Module should be
reflected in CIMS Mobile.
5.11 LINKS FROM ERA (COMPLIANCE ACTION)
Currently, the ERA application has the ability to create an Incident Inspection in
CIMS when the outcome of Compliance Action is selected for a Contravention. This
functionality works well and will continue to be required in the future. However, it is
possible that an inspection related to the Compliance Action may already exist in
CIMS. In this case an Incident Inspection should not be created, but a link between
the ERA case and the CIMS inspection should be created.
The user interface for the ERA application will need to be changed so that when an
outcome of Compliance Action is selected for a Contravention, the user will be
provided with a choice of either creating a new inspection, or linking to an existing
Completed inspection. If the choice is to create a new inspection, the inspection will
be created as it is today. If the choice is to link to an existing inspection, the user
will need to pick an inspection with the same site as the Contravention. Once the
inspection is chosen, a link between CIMS and ERA will be created and a Follow Up
Summary Closure entry will be created on the CIMS inspection for the Compliance
Action.
5.12 CIMS PORTAL
The following items have been requested for the CIMS Portal Page
Page 12 of 23
Ministry of Forests and Range


CIMS Maintenance Business Requirements
Include a count of Compliance Actions Requiring Reinspection. The
count will include all inspections that were created with a Compliance Action
by the inspector, but where another inspection to verify that the Compliance
Notice has been complied with, has not yet been completed. The second
inspection does not necessarily have to be completed by the inspector of the
first inspection. Note: this is related to a change in the Inspection Addendum
section.
Include a count of New Risk Sites Assigned. The count will include all the Risk
Sites that have been assigned to the inspector within the last x number of
days. The x will be an application configurable variable.
5.13 FOLLOW UP

For Follow Up the following changes have been requested:
 When adding a follow-up include a mandatory Follow-Up Reason that will
consist of selecting on of the following values: Weather Conditions, Time,
More Information Required, Expertise.
 Modify the label text Comment/Notice to read Notice. This applies to both
web pages and reports.
Remove Notice from label “Comment/Notice”
5.14 INSPEC TION ADDENDUM
For the Inspection Addendum the following changes have been requested:
 When the value of Site Priority is undefined, change the text to read one of
two values. No Risk Defined – will be displayed when there is no risk for
the inspection’s site. No Priority Defined – will be displayed when there is a
risk for the inspection’s site, but no priority has been set for the site. When
No Priority Defined is displayed, make the test a hotlink that will go the
Site Priority page for the inspection’s site.
 Rename label Satisfactorily Complete to Remediation Satisfactorily
Complete.
 Rearrange Inspection Reasons on the Addendum:
o Switch reasons 5. Verification of compliance notice or other order
fulfilment and 12. Licensee request
o Move reason 2. Re-inspection recommendation (from a previous
inspection)/Inspection Trigger Identified to the bottom of the
list.
o When Re-inspection recommendation is selected, provide the
ability to link to an inspection on the same site that had a Compliance
Notice.
 Provide a method (button/checkbox) to set the status of a site to Complete
within the scheduler, when the inspection is Completed. This will mainly be
used when the inspection is being done as a final inspection, however there
may be other reasons for the setting the scheduler status to Complete.
Page 13 of 23
Ministry of Forests and Range
CIMS Maintenance Business Requirements
5.15 HARVEST COMPLIANCE S UMMARY
For the Harvest Compliance Summary the following changes have been requested:
 For all General Requirement descriptions the part(s) of the description in
brackets should be removed. This applies to both any web pages, and
reports.
For example: Soil conservation (disturbance, etc.) would
become Soil conservation.
 Detailed explanations for each of the General Requirements should be added
to the Robo-Help documentation.
 General Requirement Item 8 should be split into 2 items Forest Health and
Fire Protection. This will require that current requirements 9 – 11 be
renumbered 10 – 12.
5.16 COMPLIANCE SUMMARY
For the Compliance Summary for all inspection types the following changes have
been requested:
 When a General Requirement is assigned a Compliance Status of Yes or Not
Inspected, provide the ability to add an optional comment for the General
Requirement. (This may be accomplished by moving all of the General
Requirements to a detail page.)
 Continue to be able to attach documents at the inspection level and, now, be
able to attach documents at the General Requirement level. Note: it has
been requested that the documents be printed as part of the inspection
report, however, this may not be possible due to the different types of
documents that may be attached to the General Requirement.
5.17 RISK ASSESSMENT COPY
Sometime after a Risk Evaluation has completed on a site, it may be necessary to
revisit that site and update the Risk Evaluation. After a Risk Evaluation has been
completed on a site there may be other sites in the surrounding area that have
similar risk values. For the above two reasons, a Risk Evaluation Copy function is
required for CIMS.
The Risk Evaluation Copy function will be provided on all Completed Risk Evaluations.
The copy function will first prompt the user to select a site for the Evaluation (the
site from the copied evaluation will be provided as a default), the individual that
completed the evaluation, and the date of the evaluation. Once the previous three
pieces of information have been entered, the Risk Evaluation will be copied. All
information from the original Risk Evaluation with the exception of the site,
completed by, evaluation date, licensee, and evaluation status will be copied to the
new Evaluation. The values for the site, completed by, and evaluation date will be
set to the values that were entered.
The value for the licensee will be set
appropriately for the site, based on the same rules used when creating a new
evaluation. The status of the evaluation will be set to Incomplete. Once the
evaluation has been copied, it will be treated as any other Incomplete evaluation.
Page 14 of 23
Ministry of Forests and Range
CIMS Maintenance Business Requirements
5.18 INSPEC TION COPY
The Inspection Copy function is to be provided on all Completed Inspections. The
copy function will first prompt the user to select a site for the inspection (the site
from the copied inspection will be provided as a default), and the date of the
inspeciton. Once the previous three pieces of information have been entered, the
Inspection will be copied. All information from the original Inspection with the
exception of the site, inspection date, licensee, general requirements, and inspection
status will be copied to the new Inspection. The values for the site and inspection
date will be set to the values that were entered. The value for the licensee will be
appropriately for the site, based on the same rules used when creating a new
inspection. The values for the General Requirements will be set to NA. The status of
the inspection will be set to Incomplete. Once the inspection has been copied, it
will be treated as any other Incomplete inspection.
5.19 SPELL CHECKER
A very useful feature for users of the CIMS application would be to have a
checker available on comment boxes in the application.
Currently, the
application is investigating an approach to be used to provide such a feature for
Once a spell checker has been implemented in ERA, the same approach can be
in CIMS to provide spell checker functionality.
spell
ERA
ERA.
used
Page 15 of 23
Ministry of Forests and Range
CIMS Maintenance Business Requirements
6. DATA REQUIREMENTS
6.1
TMTR INSPECTIO NS
A TMTR














Inspection will consist of the following information:
Inspection ID (M)
Inspection status (M)
Location (O)
Inspection Date (M)
Inspection Start Time (M)
Inspection End Time (M)
In Attendance (O)
Inspector (M)
Agency (Multiple Agencies can be added) (O)
Initiative (Provincial, Regional, or District) (M)
Purpose of Checks (Education, Compliance, Enforcement) (all three could be
selected – at least one must be selected)
File # 1 (Arcs/Orcs) format (M)
File # 2 (Arcs/Orcs) format (O)
Vehicle/Vessel Details (can be multiple – must be at least one)
 Operator/Markholder (should be linked to an entry in the Client
system) (O)
 Vehicle (M)
 Vehicle Driver (O)
 Load Slip (can be multiple per Vehicle/Vessel – must be at least one)
Load Slip Number (O)
Timber Mark (O)
Timber Brand (O)
Non-Compliant (M)
Follow-up (M)
Additional information that can be recorded for a TMTR Inspection will include:
 Non Compliance Information when a Load Slip is marked as Non-Compliant.
 Follow-Up information when a Load Slip is marked as Follow-Up.
 Images for the Inspection. Images will be stored at the Inspection level.
However, C&E would like the ability to store inspections against individual
Load Slips as well. While this is possible, it is unlikely to be included in the
first release of the TMTR Inspection.
 Follow-Up Closure information for items requiring Follow-Up.
 Inspection Notes after the inspection is Complete.
6.2
INVALIDATE AND COPY
Invalidate and Copy will require the additional information to be added to an
inspection:
 Link to Copy inspection from Invalid inspection.
 Link to Invalid inspection from Copy inspection.
 Invalidate Rationale (Mandatory whenever an inspection is Invalidated).
Page 16 of 23
Ministry of Forests and Range
6.3
CIMS Maintenance Business Requirements
PRICING INSPECTIONS
A Pricing Inspection will consist of the following information:
 Inspection ID (M)
 Inspection status (M)
 Timber Mark (M)
 Road Section (only for Timber Mark for a Road Permit, in this case at least
one must be present, but can be more than one for the same Road Permit)
 Licensee (M)
 Inspection Date (M)
 Inspection Start Time (M)
 Operator/Contractor (O)
 In Attendance (O)
 Inspection Method (one of Ocular, Recce, Detailed Survey, File)
 Location Inspected Text (M)
 Location Inspected (one of Partial, Complete)
 Conformance Items (Yvonne and Mark still need to provide list)
 Conformance to each Conformance Item (one of N/A, Not Inspected,
Consistent, Inconsistent)
 Comment for each Conformance Item.
 Non-Compliant (M)
 Follow-Up (M)
 Inspector (M)
 Digital Image (O)
 Additional Checklist (O)
 Other Checklist (O)
 Email (O)
 Fax (O)
 Mail (O)
 Hand Delivered (O)
 Received By (O)
 File # 1 (Arcs/Orcs) format (M)
 File # 2 (Arcs/Orcs) format (O)
Additional information that can be recorded for a Pricing Inspection will include:
 Non Compliance Information when the inspection is marked as NonCompliant.
 Follow-Up information when the inspection is marked as Follow-Up.
 Images for the Inspection. Images will be stored at the Inspection level.
 Follow-Up Closure information for items requiring Follow-Up.
 Inspection Notes after the inspection is Complete.
Page 17 of 23
Ministry of Forests and Range
CIMS Maintenance Business Requirements
7. INTERFACE REQUIREMEN TS
7.1
TMTR INSPECTIO NS
Client and Operator /
Markholder
to
be
removed from this
section.
MOFR label to be
changed to inspector.
Initiative to include
choices for Provincial,
Regional, District, or
Single Stop.
Purpose of Checks to
be Check Boxes.
Load Slips to be surrounded
by Vehicle/Vessel details.
Details
are
Operator/
Markholder that will map to
a client, vehicle, and vehicle
driver.
Rename
button to Add
Load Slip.
Figure 2 - TMTR Inspection
Page 18 of 23
Ministry of Forests and Range
7.2
CIMS Maintenance Business Requirements
PRICING INSPECTIONS
Add “file” as
an inspection
method.
Remove
Activity
Status Section and
Replace
with
location Inspected
Section.
Page 19 of 23
Ministry of Forests and Range
CIMS Maintenance Business Requirements
Allow a comment
for
each
conformance item.
Figure 3 – Pricing Inspection
Page 20 of 23
Ministry of Forests and Range
CIMS Maintenance Business Requirements
8. PERFORMANCE REQUIREMENTS
Typical performance requirements for the Ministry of Forests and Range apply.
Page 21 of 23
Ministry of Forests and Range
CIMS Maintenance Business Requirements
9. INFRASTRUCTURE REQUI REMENTS
Describe any infrastructure requirements for the system
Webade 4.x
Jrun 4.x
Crystal Reports 10
Oracle 9i
Page 22 of 23
Ministry of Forests and Range
CIMS Maintenance Business Requirements
10. DOCUMENT SIGN-OFF
The undersigned have read and agree with the content of this document.
Yvonne Roslin-White
Systems and Training Coordinator
Compliance and Enforcement Branch
Ministry of Forests and Range
Date
Mark Ismay
Information Management Group
Ministry of Forests and Range
Date
David Simpson
Project Manager – Vivid Solutions Inc.
Date
Page 23 of 23