NWDA Output Definitions for Single Programme and ERDF Programme 1. Introduction 1.1 It is important that the monitoring of outputs is robust and consistent across all projects and programmes. This document provides definitions for each output and advice on when they should be counted. 1.2 Each output attempts to provide as much detail as possible about which outputs can be counted and gives guidance on the type of verification evidence that should be supplied. 1.3 Where possible the outputs have been made consistent across SP and ERDF, however there are some that are relevant just for Single Programme and some that are additional for ERDF and these are clearly shown. ERDF also requires targets to be set at a results (outcome) level. 1.4 The Appendix provides a summary of some frequently asked questions. 2. General Criteria 2.1 An activity can only be counted as contributing to an output if it fulfils the following criteria: a) Definition – the activity must fall within the scope of activities defined for the output. b) Direct – outputs must be a direct consequence of the NWDA funded project. Subsequent or indirect outputs are defined as outcomes (SP) or results (ERDF) and should be separately identified on Development and Appraisal Forms. c) Counted in the current period – i.e. in the time period they are delivered 2.2 Projects use outputs to measure the progress of the project activities. Outputs therefore have to be capable of being forecast and delivered as part of the project and are monitored and verified during the life of the project. Outputs are a contractual commitment and should, therefore be realistic. 2.3 Projects may produce either a single output or multiple outputs depending on the nature of the project. Outputs forecast and reported must be directly related to project activity and linked clearly to project objectives. 2.4 Total outputs, for both the Single Programme and ERDF, will be recorded on PMS and/or MCIS at contract, forecast and actual as the total gross figure. However, to enable Single Programme outputs to be attributed to the share of NWDA SP funding a new characteristic is available on PMS to allow the % of NWDA to overall public funding to be entered and used to calculate the level of output attribution. 2.5 Projects also generate outcomes/results – the consequences the project is seeking to achieve as set out in its objectives. Outcomes are the results that follow from the project activities as part of the logic chain, and so generally follow after the project has completed and are gathered as part of the evaluation. However, for ERDF some results may need to be forecast and GN PJ_SP309 Page 1 of 49 Issued: June 2009 Version 4.0 Next review: June 2010 counted during the lifetime of the project as part of the monitoring. The relevant data and evidence should be set out in the monitoring and evaluation plan so that it can be collected and assessed at the appropriate stage. 3. Beneficiary Characteristics/Analysis 3.1 In addition to the basic output and result indicators the NWDA has selected a range of requirements to provide a further level of analysis and evidential detail on how the agency investment has been used and the benefits achieved. Targets will be set for sectors and forecasts provided on PMS, however, beneficiary analysis will be used for reporting and not for setting targets. The analysis will be recorded on PMS. Each output definition shows what analysis is appropriate to that output. 3.2 Beneficiary characteristics: Equality Monitoring – four categories are: a) Gender - Male - Female b) Disability c) Age - 16-25 - 26-50 - 51-65 - over 65 d) Race - White - Black or Black British - Asian or Asia British - Mixed Heritage - Chinese - Any other ethnic group - Not stated - Yes - No Disability is defined as a physical impairment or mental health condition which has lasted, or is expected to last, at least 12 months and which has an adverse effect on the individual's ability to carry out normal day-to-day activities. Please note: Although the NWDA is only recording these 6 categories partners will be required to request information using the 16 census categories, which will need to be aggregated for reporting output numbers to the NWDA. Partners will be expected to store the full 16 category information for use by the NWDA if required. The 16 categories are: White - British Irish Other white background Black or Black British - Caribbean African Other black background Asian or Asia British - Indian Pakistani Bangladeshi Other Asian background Mixed Heritage - White and black Caribbean GN PJ_SP309 Page 2 of 49 Issued: June 2009 Version 4.0 Next review: June 2010 - White and black African White and Asian Other mixed background Chinese Any other ethnic Group 3.3 Business Characteristics: Equality Monitoring a) Gender b) Disability - Yes - No A disabled-led business is defined as a company, business or social enterprise in which at least 51% of owners, partners or directors are disabled people. c) Age d) Race - Male - Female A female-led business is defined as a company, business or social enterprise in which at least 51% of owners, partners or directors are female. - 16-25 - 26-50 - 51-65 - over 65 For multi-owner businesses age categorisation will not be possible - BME lead - Non-BME lead A BME-led business is defined as a company, business or social enterprise in which at least 51% of owners, partners or directors are from a BME background (defined as any category in list above other than White-British. Please note: It has support should be monitoring data – i.e. - been decided that certain types of business and/or excluded from the requirement to collect equality very large multi-national businesses; foreign owned companies businesses assisted under universal support definition 3.4 When entering beneficiary characteristics for business into PMS, this should be done against the type of business. 3.5 Sector Analysis: a) b) Priority Sector or Employment Sector Classify as ‘Other’ where it is not known or in other sector Priority Sectors: Biomedical Energy Advanced Engineering Food Digital Business and Professional Employment Sectors: Maritime Construction GN PJ_SP309 Page 3 of 49 Issued: June 2009 Version 4.0 Next review: June 2010 - Visitor Retail Public Health Note: Businesses assisted under universal support definition do not need to be analysed by sector. 4. Monitoring and Verification 4.1 It is important that all data reported to NWDA is accurate and reliable. There are a number of aspects of a project’s systems that need to be checked to ensure monitoring reports are correct, and information will be available when evaluation is undertaken. a) Data Collection Systems Are the appropriate output definitions understood and in use? Is all the necessary output data being collected? What systems are being used to collect data? Are they robust and secure? b) Output Evidence What verification evidence is being collected? Is it acceptable in relation to types of evidence and authenticity? How is this information being stored? Is it easily accessible for checking? Have adequate consents been obtained from the individuals concerned? c) Output Reporting Who completes and checks the Output Monitoring Return? Is it the appropriate people? Are returns submitted on time with the appropriate information? In reviewing the processes and systems for collection/storing and reporting of data and information please note the requirements of Data Protection at 4.3 below. 4.2 Article 13 With the responsibility for the delivery of ERDF being undertaken by the Agency there are monitoring and evaluation functions required by the EU under Article 13 of Regulation 1828/2006. This means there are specific requirements to ensure there is a robust control environment to minimise incorrect and un-supported reporting of achievement. In addition to the ongoing Contract Management and monitoring of partners, including the regular Progress Monitoring Reports, there are 2 types of visits that are required: Project Engagement Visit (PEV) – this must be undertaken by the Contract Manager to all projects. The visit should take place following the agreement and signing of the Offer Letter, ideally before the first claim/progress report is completed by the partner organisation. The visit is to ensure that the team delivering the project fully understand the requirements of the NWDA and the ERDF programme and have in place adequate processes and systems (and understand verification requirements for the outputs they are delivering). The visit must be documented. GN PJ_SP309 Page 4 of 49 Issued: June 2009 Version 4.0 Next review: June 2010 Project Progress and Verification Visit (PAV) – is undertaken by the Programme Office QA team, at least once during the life of the project, to access progress against targets and to verify that any expenditure and outputs claimed are correct and are supported by adequate auditable evidence. The results of this visit must also be fully documented. 4.3 Data Protection Data protection is becoming an increasing sensitive issue, so the Agency must ensure it only requests information about individuals that it really needs and that can be supported by a Business Case. Information is a key asset and its proper use is fundamental to the delivery and evaluation of programmes and projects. Where information is held on individuals, companies or organisations they are entitled to expect that: their privacy will be protected, subject to Freedom of Information requirements; information risks (confidentiality, integrity, availability, storage) will be assessed and mitigated (including incident management) to an acceptable level; the data will be protected, used and handled professionally and only for the purposes it was collected The verification evidence in the following output definition tables is that which should be held by the delivery body. The delivery body is responsible for collecting and storing the data on individual beneficiaries. Where outputs are being reported through the Progress Monitoring Report to the RDA, whether for Single Budget or ERDF, it is only necessary to provide aggregate numbers not the information on individual beneficiaries. However, this means that partner organisations need to ensure they have robust and secure systems for protection of the data on individuals/business owners they collect and they should ensure they obtain agreement that the information can be made available to the Agency and other auditors/consultants we may require to review the data, for example for verification and evaluation purposes. The Grant Funding Agreement now reflects these requirements and Agency staff working with Delivery partners must ensure adequate processes and systems are in place. Data Protection Act The Data Protection Act protects the rights of people about whom data is collected and processed. It is therefore important that the methodology applied conforms to accepted standards. When programmes and projects require the collection of data about a beneficiary, the key principles below should be followed (but it should not be construed as legal advice): Inform: provide information to the individual about why the information is being collected, how it will be used and what will be done to protect confidentiality. Where it is necessary to collect information individual consent forms should be used, or where this is not practicable, individuals should be informed that they may be contacted in the future to provide feedback for verification or evaluation purposes (see example below). Confidentiality: when data is held on paper records it should be locked away in a secure place e.g. a locked cupboard, when not in use. If the records are to be held electronically they should be password protected. When data is held and accessed on ICT systems access should be by GN PJ_SP309 Page 5 of 49 Issued: June 2009 Version 4.0 Next review: June 2010 authentication (user name, password and best commercial practice) avoiding use of removable media e.g. laptops, CDs, USBs etc for storage or access, where possible. On completion the material used to store personal data should be subject to controlled disposal (incineration, pulping, shredding, secure destruction, overwriting, or erasure). Voluntary: completion of equality monitoring forms by individuals is voluntary though care should be taken that this is not overstated as it may encourage non-returns. It is best practice to encourage individuals to provide the information, by explaining the purpose and use of the data. However, do not say or imply that providing the information is compulsory i.e. it should not be a mandatory field in electronic forms. All completed forms should be signed by the individual concerned. Self-classification: wherever possible, self-classification should be used with individuals completing a declaration form. Only in exceptional circumstances should beneficiaries be classified by another individual (other classification). CRE Guidance advises that if the individual absolutely refuses to supply the information, their manager or some other appropriate person should classify them according to what is already known about the person. They should be notified of the classification and given the opportunity to confirm or correct it. The record must show that the information it contains was based on this ‘other classification’ method. Recording: if the beneficiary does not provide the information you should record them as a nil response and in an unknown category. Example A large company is safeguarding 700 jobs as part of the project. An agreement was reached that the company would provide the NWDA with an anonymised list of the 700 jobs to be safeguarded as a baseline. The list would contain the job title, salary band, site/department location and start date of the occupant of the job. The company itself would have the full list which identified the individuals by name. At the end of the 12 month period the company’s external auditors would undertake a random sample check of the list and the individual beneficiaries chosen from the list would be asked to consent to be interviewed. They would then verify that those jobs still existed and were no longer at risk. The Grant Funding Agreement also included a requirement for a similar sampling exercise to be undertaken by the appointed evaluators, when the project evaluation was undertaken. GN PJ_SP309 Page 6 of 49 Issued: June 2009 Version 4.0 Next review: June 2010 Output indicators structure SP and ERDF outputs ERDF Results CITN Ref* R1 Jobs created or safeguarded R5 Individuals who gain employment within 6 months of intervention R1 (a + b) 05 R5 (a + b) 06 R2 Businesses Created R2 R3 Businesses improving their performance 03 (a, c, d + e) R3 People 1 2 3 Jobs created or safeguarded (SP only) People helped to secure employment, education or training (SP/ERDF) People assisted in their skills development (SP/ERDF) Business 4 4a 5 Businesses Created (SP only) Business Creation – pre-start assistance (ERDF only) Businesses Assisted (SP/ERDF) Finance 6 Public and private leverage (SP/ERDF) 07 Place 7 8 9 Brownfield Land reclaimed, redeveloped or regenerated (SP/ERDF) New or upgraded Floorspace (SP only) Public Realm created or improved (SP) 04 R4 New or upgraded Floorspace R4 Tourism/Marketing 10 11 Number of visitors attracted (SP/ERDF) Economic impact from major events and tourism marketing (SP only) n/a R8 Visitor Spend n/a Sustainability 12 13 14 15 Tonnes of Carbon Dioxide generated (SP/ERDF) Environmental Businesses Supported (ERDF only) Environmental products Supported (ERDF only) Number of applications of Low Carbon Technology (ERDF only) n/a n/a n/a n/a * The Technical Note of Combined Indicators for RDA Single Budget and ERDF Programme 2007-13 (CITN) is a national document, produced by OffPAT on behalf of the RDAs and CLG (ERDF programme). The CITN references (in shaded column) should be used in MCIS recording of outputs. For further information the NWOP quantification document can be found on the ERDF website. The CITN provides definitions for common core SP and ERDF outputs and results. However, the Agency has developed this document and guidance for staff which details its own interpretation of the outputs it wishes to collect, and there are some differences. This document references ERDF exclusions and differences as appropriate. GN PJ_SP309 Page 7 of 49 Issued: June 2009 Version 4.0 Next review: June 2010 1. Jobs created or safeguarded PMS codes JC – Jobs created JS – Jobs safeguarded Unit of measurement Number of jobs – counted as FTE (paid work for 30 hrs or more per week) Part time jobs can be converted to FTE on a pro-rata basis or with the EC approach – 2 part time jobs = 1 FTE where no other information is available Counted Created: when a new permanent paid job is created and the post filled. Safeguarded: when a permanent job is forecast as at risk but is no longer at risk of being lost within one year FDI and SPIE jobs can be counted after they have been delivered, but not when they are only anticipated. ERDF requirements Counted as results for ERDF: R1a – jobs created R1b jobs safeguarded As a result they are counted where jobs follow on from a project intervention resulting in the jobs being created or safeguarded. Exclusions Inputs to the project (For example staff who are employed to run the project ) Construction jobs when they are required for the implementation or delivery of a project (e.g. construction of premises), however where construction refers to the sector in which the jobs are located (e.g. created in the region as part of a cluster development project) then the jobs can be counted. Temporary jobs Seasonal jobs where they are incidental to the operation, however if the operation relies on seasonal jobs e.g. tourism they can be included on a pro-rata basis – 3 month job = 0.25 FTE. Refilling of jobs with different people, jobs can only be counted once. Transferred jobs which are a result of a company moving either within the region or from other English regions or UK devolved administrations are not new jobs. These may be included a safeguarded jobs but only where the relocation is part of a rationalisation programme which will safeguard jobs by moving them. Jobs created New: Should not have existed in the Region or seasonal jobs with the employer in the UK before the intervention and should be a direct result of the intervention Permanent: Should have a life expectancy of at least one year from the point it was created Jobs safeguarded Job must be permanent, paid and at risk of being lost within one year, the jobs at risk must be specified, or if sector is in long term decline a longer period may be appropriate (where the project is proposing to undertake pre-emptive action) Verification Job created: Letter from employer (letterhead if possible with name/address of company including post code/tel no.) confirming required details (i.e. start date, permanent job, hours). Evidence of employment of individual e.g. contract, pay slips, employment records + beneficiary data and priority/employment sector. Job safeguarded: Letter of confirmation from employer (letterhead if possible with name/address of company including post code/tel no.) stating why jobs were at risk and how project funding has prevented loss + beneficiary data and priority/employment sector. GN PJ_SP309 Page 8 of 49 Issued: June 2009 Version 4.0 Next review: June 2010 Analysis GN PJ_SP309 Beneficiary by: Gender Age Ethnicity Disability Job by Priority sector/Employment Sector Page 9 of 49 Issued: June 2009 Version 4.0 Next review: June 2010 2. People helped to secure employment, education or training PMS code NEET – People helped (employment/education/training) Unit of measurement 1. Number of individuals who receive assistance 2. Number of individuals who have received assistance through the project who actually secure employment, education or training Counted 1. When an individual has received assistance that is aimed at helping to secure employment, education or training. 2. When the individual secures relevant employment, education or training (as defined below) Individuals must be of working age (16 or over) unemployed, economically inactive or in employment that is at risk ERDF requirements If the subsequent securing of employment is achieved within 6 months this may be able to be counted as a result – see R5 Exclusions Individuals under age of 16 as still covered by statutory education Assistance that is covered under Skills output or assistance for selfemployment (to avoid double counting with output 4). Unemployed Not in work but is actively seeking work ie in receipt of Job Seekers Allowance/Income Support Economically inactive Not in work and not actively seeking work eg non-working parent or someone receiving Incapacity benefits Employment ‘at risk’ Someone in work, but at risk of losing their job eg under threat of redundancy, on a short term/temporary contract, in seasonal work that is coming to an end. Assistance The assistance must be directly helping people secure employment, education or training. Forms of assistance can included: - provision of information, advice and guidance – eg careers advice, CV writing, interview training removing barriers to getting back into the labour market – eg return to work training, providing crèche facilities Voluntary work/work experience Employment To count as secured, employment must be a minimum of 13 weeks and can include Self-employment Full or part time working Education Knowledge and understanding acquired by a gradual process of learning and instruction. To count as secured, the full course must be completed or an accredited or non accredited qualification achieved. Training The acquisition of knowledge, skills and competencies as a result of the teaching of vocational or practical skills. To count as secured, the full course must be completed or an accredited or non accredited qualification achieved. Verification Individual – name, Address incl. post code, date of birth, evidence of being unemployed, economically inactive or in employment that is at risk + beneficiary analysis data GN PJ_SP309 Page 10 of 49 Issued: June 2009 Version 4.0 Next review: June 2010 Assistance – evidence of type of assistance either from individual or organisation providing the assistance Employment – Letter from employer (letterhead if possible with name/address of company including post code/tel no.) confirming required details (i.e. start date, hours etc). Evidence of employment of individual e.g. contract, pay slips, employment records. Education – signed declaration by individual and educational establishment outlining course and attendance record (ie length of course, number of days, final qualification). Training – signed declaration by individual and training establishment outlining course and attendance record (ie length of course, number of days, final qualification). Analysis GN PJ_SP309 Beneficiary by: Gender Age Ethnicity Disability Status (of those receiving assistance): JSA/Income Support claimant Incapacity Benefit claimant Other Securing: Employment Education Training Page 11 of 49 Issued: June 2009 Version 4.0 Next review: June 2010 3. People assisted in their skills development PMS Codes S/T – Skills Development (by learning type) S/SEC – Skills Development (by sector) Unit of measurement Number of individuals Counted When individual has undertaken required amount of development or achieved required qualification. Assistance for the individual can only be counted once per project. The output supports lifelong learning and includes individuals of all ages or employment status (except individuals under 16 and in statutory education – though see count under sub-set 10below). ERDF Requirements The following types of learning are eligible for ERDF: Level 3 qualification Foundation degree or higher Work based training Leadership & Management skills The activity must not be eligible for ESF support and must be in line with the investment frameworks (check with EPE team for any clarification). Exclusions Services as part of legal, statutory obligation on the part of others to provide education up to the age of 16. Anything counted as employment, education or training support in output 2 Skills development The development of an individuals transferable skills, a formal qualification is only required where specified as part of the sub set. Can include: Learning through presentations, demonstrations and instruction Individual learning through coaching Mentoring in the workplace Technology based learning Assisted Assistance should be minimum of 6 hours either as single block or cumulatively. Assistance must be part of the project, where assistance involves capital investment e.g. provision of facilities, it can only be counted if the contract schedule includes a target for individual skills development as a direct result of the project Verification Provider details: Name, address (inc. post code/tel no.) Type of assistance: Type of training, number of hours, start and end dates Individual: Name, address, post code, attendance register/statement, copy of qualifications/certificates (if applicable) + beneficiary data Analysis Beneficiary by: Gender Age Ethnicity Disability Skills development by Priority sector/Employment Sector (where appropriate) GN PJ_SP309 Page 12 of 49 Issued: June 2009 Version 4.0 Next review: June 2010 By type of learning as defined in sub-sets below: 1. Basic skills Individual must achieve one of the following qualifications Literacy, numeracy or ESOL at entry level 3 or above Key Skills in Application of number or communication at levels 1 or 2/GCSE in Maths or English at Grade C or above Only the first qualification attained by an individual counts for this output. 2. Level 2 Qualification Achievement of a National Vocational Qualification (NVQ) at Level 2, or equivalent qualification. Details of equivalent qualifications can be found on the DCSF Qualifications website. 3. Level 3 Qualification Achievement of a National Vocational Qualification (NVQ) at Level 3, or equivalent qualification. Equivalent qualification at this level can include University Certificates. 4. Foundation Degree or Higher Level Qualification Achievement of a National Vocational Qualification (NVQ) at Level 4 or 5, or equivalent qualification 5. Work based training Learning which takes place in the workplace or outside the workplace but is related to a specific job or is paid/provided by the employer. The training can have a direct relationship to the job or could be part of a skills development plan. No formal qualification is required 6. Leadership & Management Training/Development relating to the overall management of a company. This includes accredited or non-accredited provision e.g. taught programmes, action centred learning, mentoring and coaching. Can also include training/development about CSR (Corporate Social Responsibility) 7. Enterprise Skills Training/development relating to the development of entrepreneur skills. Can be accredited or non-accredited provision including generic ‘enterprise‘ skills for employed or unemployed young people or adults. 8. Apprenticeships Training as part of an apprenticeship programme combining learning, paid employment and leads to a qualification i.e. Foundation Apprenticeship at level 2 or Advances Apprenticeship at level 3. 9. Economically inactive completing vocational training Courses to better equip people to obtain sustainable, productive employment. A formal qualification is not required Vocational training courses containing knowledge and skills relevant to particular sectors of industry or occupations. They can be a) general, introducing learners to a broad sectors of industry and business, encouraging understanding, key concepts and theories and may include some basic skills e.g. literacy, numeracy or IT skills; b) specific, return to work, introducing theories, conventional practices, including skills needed for a particular job or occupation; 10. Under 16’s undertaking nonstatutory vocational training GN PJ_SP309 Training or development for young people to prepare them for work. The training does not have to take place within an educational institution, and covers pupils who are still within statutory education. Does not need to lead to a formal qualification Page 13 of 49 Issued: June 2009 Version 4.0 Next review: June 2010 4. Number of Businesses created PMS Code BSU – Number of Businesses Created Unit of measurement Number of businesses Social Enterprises should be identified separately Counted 1. 2. 3. 4. At start up At 12 months survival At 24 months survival At 36 months survival Please note: Other than for ERDF (see below) it is not necessary to have forecast targets for survival rates, these will be used to record actual survival – however, project deliverers will need to have a process in place to follow-up, record and report on business survival ERDF requirements Output not counted for ERDF, but is counted as a result (R2) at stage 2 – 12 month survival, when the business/social enterprise created as a result of an NWDA funded intervention ERDF can also count pre-start assistance – see 4a below Exclusions Businesses that already exist and are relocating or setting up new offices Business The 3 main types of business are Sole Proprietor, Partnerships and Companies and include not for profit, Social and Community Enterprise organisations and Farm businesses Start up When the business starts trading in the region as a direct result of the project intervention. This can be when the business registers for VAT or National Insurance (Class 2) contributions. If these are not available it is acceptable to use the Business Link approach and us the date of the first transaction. Survival When the business is still in operation/trading and is sustained for 12, 24 and 36 months Social Enterprise Social enterprises are defined as businesses with primarily social objectives who’s surpluses are principally re-invested for that purpose in the business or in the community, rather than being driven by the need to maximise profit for shareholders and owners Verification Start up: Name, address (including post code/tel no.) contact details, company registration, VAT registration or NI class 2 registration, or date of 1st transaction where this can be evidenced + beneficiary data and priority/employment sector. Survival: Confirmation at relevant stage that it is still trading, signed declaration by Owner/Director Analysis Business To be analysed by: Priority Employment sector Business type: Social Enterprise Business ownership by: Gender Age Disability Ethnicity GN PJ_SP309 Page 14 of 49 Issued: June 2009 Version 4.0 Next review: June 2010 4a. Businesses creation – pre-start assistance PMS Code Output does not have PMS code – will be recorded for ERDF purposes on MCIS Unit of measurement Number of pre-starts Counted When the pre-start business has received a minimum of 2 days active support, or a minimum £1000 grant or equivalent The pre-starts can only be counted once within a project irrespective of the number of times or forms of assistance received. ERDF requirements Care must be taken to ensure no double counting between this output and output 2 – where assistance is given to individuals that result in self employment Exclusions Travelling time to clients is excluded Pre-start The business must not be trading yet but enquiring about or trying to start up for trading. It can include: Individuals and groups (community, not for profit, other) who are seeking support to start a business HEIs and others seeking to start spin out companies An SME that is less than 12 months and not trading Assistance Support activities may include advice and guidance e.g. to develop business plans, marketing strategies, support for trade fairs, support to develop business skills. This can be provided through: Counselling, mentoring, information provision, training or other non-financial assistance, or Grant or equivalent of at least £1000 Verification Details of the provider of any support (name, address etc). Details of the assistance provided to include a record of hours of assistance, names and addresses of pre-start contacts, activities undertaken. Evidence of status of the pre-start. Copy of receipts for grant or equivalent signed and dated by the recipient. Evidence of business proposal documents – business plan, marketing plan, training undertaken, attendance at trade firs etc. Analysis Business To be analysed by: Priority Employment sector Business ownership by: Gender Age Disability Ethnicity GN PJ_SP309 Page 15 of 49 Issued: June 2009 Version 4.0 Next review: June 2010 5. Number of Businesses assisted PMS Codes BA/T – Businesses Assisted (depth of assistance) BA/S – Businesses Assisted (by type) BA/P – Businesses Assisted (by support product area) BA/SE – Businesses Assisted (by sector) Unit of measurement Number of Businesses Counted When the business has received support covered by the definition for one of the following: 1. Intensive assistance 2. Intermediate support 3. Universal support Within a project a business can only be counted once irrespective of the number of times or forms of assistance it receives. However, it has been agreed that projects (if they opt to) can count all relevant business assists as Universal, but they would be required to do an adjustment to the numbers if the business subsequently receives a higher level of support. This would operate over a 12 month time period. Within a programme a business may be counted each time it receives assistance through a different project or intervention strand. ERDF requirements To count for ERDF assistance must be either intermediate support or intensive assistance (this can be cumulative over a period) For MCIS recording purposes the following outputs should be used: 03 03a 03b 03c 03d 03e Businesses Assisted (intermediate support) Businesses Assisted (intensive support) Collaborations with the Knowledge Base SME assistance Social Enterprise assistance Reduce Industrial and Commercial Waste Anything counted under output 13 for ‘Environmental Businesses’ should be excluded here to avoid double counting – though can be counted towards the cumulative assistance figure if only counted once across the two outputs. Exclusions Distribution of mail shots and brochures (electronic or hard copy). Business can only be counted once in a single project even if it receives more than one piece of support Assistance to individuals to establish a new business should be counted under output 4, however, post start-up support can be counted under this output. Business The 3 main types of business are Sole Proprietor, Partnerships and Companies and include not for profit, Social and Community Enterprise organisations and Farm businesses SME An SME is any enterprise with less than 250 employees and either less than E43m turnover or less than E43 m net assets. If the enterprise is part of a group (more than 25% owned by another enterprise), then the above criteria must be met by the consolidated results of the group. GN PJ_SP309 Page 16 of 49 Issued: June 2009 Version 4.0 Next review: June 2010 Social Enterprise Intensive assistance Social enterprises are businesses with primarily social objectives whose surpluses are primarily reinvested for that purpose in the business or in the community, rather than being driven by the need to maximise profit for shareholders and owners. Businesses are intensively assisted at the point at which they make an investment (significant financial or significant management time) in which their business in partnership with the project, through work with the project team or a brokered third party intermediary eg a relationship with an Account Manager/adviser/consultant. To qualify for the intensive assistance measure there must be a shared agreement to implementing an action plan or other formal framework agreement, developed in partnership between the project and business, including a strategy for improving business performance with the necessary GVA baseline data (previous year) and a specific forecast for change to GVA over a defined period of time (informed by the project intervention and planned actions, but normally 12 months). The plan needs to be signed and dated by a Director. GVA = Total salary/wage costs + pre tax profit + depreciation (evidenced from Annual Report/Company Accounts) The agreement must be auditable ie kept as a tangible document (hard or electronic copy) and have a suitable audit trail that is available on request. An intensive assist is counted at the point the agreed action plan is signed. Intermediate support Minimum level of support is two days consultancy advice or other non financial assistance, grant or equivalent of at least £1,000. Universal support Business must have received support, information or advice by means of individual interaction through face to face, telephone, conference or workshop, networks or web based dialogue. Verification Name, address (inc. post code/tel no.) of business showing ownership + beneficiary data and business type. Assistance should be detailed by depth confirming consultancy support provided and any action plans produced as a result of the support For intensive assistance there should be a formal signed/dated agreement and action plan evidence of a planned meaningful ongoing relationship between the project provider and the business, to include a minimum of 2 planned follow-up activities over the year. These may take place by e-mail/telephone if supported by notes of date/time and point discussed. Collection of GVA data (including baseline) and forecast of GVA to be achieved. For Business Link projects this must include a minimum of 2 hours Adviser time. Evidence for each of the BSSP support projects should ensure relevant specific verification as required – some examples given below Analysis GN PJ_SP309 Business type: Social Enterprise SME Other Page 17 of 49 Issued: June 2009 Version 4.0 Next review: June 2010 Business ownership by: Gender Age Disability Ethnicity - for multi owner business this can be based on ‘majority owned BME business’ Please note some types of business and/or support do not need to be analysed – see guidance notes under section 3.3 Business Characteristics: Equality Monitoring By sector: Priority sector Employment Sector By Business Support Product Area as per BSSP sub-sets below (further information/detail on these Business Support Simplification Product areas can be found on the Process Management Toolkit) 1. Business Creation Helping to overcome barriers to setting up/starting and growing a new business (see exclusions/link to output 4). Includes: Starting a high growth business Intensive start up support for under represented groups Starting a Business – pre-start up advice. Verification: the amount of information may be informed by depth of assistance and product support. Could include details of assistance and information from individuals detailing how assistance has helped overcome barriers to start up (eg development of business plan/marketing plan etc). The intensive start up also requires evidence of belonging to target groups. For High Growth there are also additional criteria required. 2. Local Community Business Coaching Enterprise Coaching helping hard to reach communities to start up in business. This is designed for people for whom other products are not suitable. Verification: the output is aimed at specific target groups, so evidence would need to establish eligibility, as well as details of assistance received 3. Financial Awareness and Capability Providing SMEs with the understanding, skills and expertise to secure private sector funding Verification: details of businesses assisted (including SME status) and how this assistance has helped develop skills/expertise. Further information may be available/appropriate on the subsequent securing of finance. 4. Debt Finance Security and loan finance for SMEs with viable business plans. Includes: Support to lenders (currently limited to the Small Firms Loan Guarantee) Small loans to business for disadvantaged groups Verification: details of businesses assisted and how this assistance has been used to implement business plans. Evidence may also be needed for eligibility in target groups 5. Capital Investment Grants GN PJ_SP309 Grant for Business Investment/SFIE. Help to support capital investment projects either by SMEs or by companies operating in the assisted areas Page 18 of 49 Issued: June 2009 Version 4.0 Next review: June 2010 Verification: details of businesses assisted and how this assistance has helped specific issues/problems. The business must be viable and project must have a good chance of being self-sustaining. 6. Innovation Finance Help to develop and commercially exploit innovative ideas. Includes: Low carbon energy demonstration Grant for Research and Development Verification: details of businesses assisted, activities undertaken and types of products/processes/technologies researched or developed. 7. Risk Capital Targeted at the Equity Gap Finance for business/equity financing for SME businesses unable to raise finance on the commercial market, but which have viable business plans. Verification: details of businesses assisted and SME status. Eligibility for finance by demonstrating failure to secure finance and confirmation of the viability of business plans. and 8. Skills Solutions for Business – Train to Gain Helping businesses to improve the skills of their employees and individuals to improve their skills for business Verification: details of businesses assisted, and how this assistance has helped specific issues/problems, and action/training plans on how advice is to be taken forward to assist employees. 9. Resource Efficiency and Sustainable Waste Management Encourage businesses to adopt measures that reduce the negative impacts of their commercial activities on the environment. Includes ERDF ‘Assistance to reduce industrial waste’ (03e), but to be counted for ERDF purposes should be assistance to provide improvement in processes improve re-cycling, re-use or reduction in waste. Any doubts about fit should be discussed with the EPE. Verification: details of businesses assisted and activity undertaken. Evidence of the waste processes that the intervention targeted. 10. Business Expertise Help to get expert advice for targeted small-medium businesses to grow. Includes: Manufacturing Advisory Service Designing Demand Innovation advice and guidance Coaching for high growth Verification: details of businesses assisted and information from company detailing type of expert advice and how this assistance has helped specific issues 11. Innovation Collaborations Help for companies to work together and with the Knowledge, science and research base to increase collaboration. Includes: Collaborative R+D Networking for Innovation Knowledge Transfer Partnership Innovation Vouchers Includes ERDF ‘Collaborations with the Knowledge Base’ (03b), but for ERDF purposes business to business collaborations do not count. It is only first collaborations by the business which count. For ERDF knowledge base constitutes: UK Public Sector Research Establishments (or equivalents) Research and Development Organisations Research and Technology Organisations Higher Education and Further Education Institutes GN PJ_SP309 Page 19 of 49 Issued: June 2009 Version 4.0 Next review: June 2010 Any doubts about fit should be discussed with the EPE. Verification: details of business assisted and details of any collaboration, including activity and eligibility of organisations involved depending on the product area (eg for ERDF needs confirmation that ‘knowledge base’ is in eligible category). There may be further documentation setting out terms of the collaboration, eg Memorandum of Understanding. 12. Business Collaboration Networks Helping businesses to work together to improve performance and exploit market opportunities and new knowledge Verification: reports/action plans etc of businesses involved in networks and details of assistance/support. Information from individual businesses on benefits/outcomes of collaboration. 13. Shared Business Support Environments Shared business premises and facilities in which businesses develop and grow. Includes: Business Premises Business Growth: Specialist Facilities and Environments Verification: details of businesses assisted and how the use of the new premises/managed workspace has helped business growth. 14. Getting the most from foreign direct investment Maximising the contribution of foreign direct investment to economic activity un the UK. Delivery of inward investment projects is led by UKTI. Verification: details of businesses assisted and how this assistance has helped specific foreign investment projects 15. Preparing to export Developing international trade potential. Help for businesses considering first time exporting or entry into new overseas markets. UKTI will need to endorse suitability for participation. Verification: details of businesses assisted and how this assistance has helped specific issues/problems. 16. Investigating new overseas markets Tailored help for individual companies accessing specific international markets. UKTI will need to endorse suitability for participation. Verification: details of businesses assisted and how this assistance has helped specific issues/problems. 17. Export Credits Guarantee/ Insurance Helping business manage non-payment risks in overseas markets 18. Protecting the Natural Environment Help and incentives to create a low carbon economy and tackle climate change. Includes: Environmental Land Management Funding (part of RDPE) Environmental Land Management Advice Verification: details of businesses assisted and how this assistance has helped specific issues/problems. There must also be a rigorous risk assessment of the exporter and buyer. Verification: details of the business assisted and the form of the assistance. Depending on the assistance may need to confirm eligibility GN PJ_SP309 Page 20 of 49 Issued: June 2009 Version 4.0 Next review: June 2010 6. £ of public and private leverage PMS Code PPL – Public and Private Leverage Unit of measurement £ of Gross matched funding to project (SP) £ of Gross leverage to project (ERDF) Counted When defrayed by the project ERDF requirements ERDF counts leverage not matched funding (including SP). For ERDF purposes FE/HE count as public - see below. Exclusions Any expenditure prior to the contract being signed by both parties, any expenditure after the project has reached practical completion Public Public Sector includes Local Authorities, English Partnerships, ERDF, LSC, Health Trusts and Lottery Private Private sector includes business, registered charities, not for profit organisation, private individual, FE/HE institutions (see exclusion above for ERDF). Leverage Public Sector: SP – The sum of the other public and private investment, including ERDF and matched funding (capital and revenue) but excluding the SP contribution (A). ERDF – The sum of the other public sector investment in the project excluding ERDF and matched funding (B) Private sector: Sum of all the private sector investment in the project, including monetarised in-kind contributions (C) Total value of leverage: SP – A+C ERDF – B+C Verification Public sector: Name/address of organisation and copy of grant letter from contributor Private sector: Name/address of organisation and copy of receipts for contribution In-Kind: Detail of land/building provided with auditable valuation evidence Spend: Evidence of contributions being spent – audits, accounts, invoices etc Analysis GN PJ_SP309 None required Page 21 of 49 Issued: June 2009 Version 4.0 Next review: June 2010 7. Brownfield land reclaimed, redeveloped or regenerated (Ha) PMS Code BL - Brownfield land reclaimed or redeveloped Unit of measurement Area in hectares (ha) Counted At practical completion of the works. Where a site is reclaimed in phases count the hectares when each phase is completed ERDF requirements Green infrastructure is only applicable to Action area 3.2. Green infrastructure on Greenfield land can be counted for ERDF purposes if it is part of the overall project – where this is the case it should be counted as a separate project output (ie not as brownfield land). Exclusions Brownfield Land When only activity is purchase of land, building or site (unless the applicant is obliged to develop the land under the terms of the NWDA Funding Agreement). Any land which does not meet Brownfield’s definition. Land and buildings that are currently in use for agriculture or forestry purposes Land in built up areas not previously developed e.g. parks, recreational grounds, allotments and cemeteries or only shown on the DUN land register as underused or neglected Land previously developed but where the remains of any structure or activity has blended into the landscape in the process of time e.g. amenity use, contribution to nature conservation Includes contaminated, derelict or previously developed land which is or was occupied by a permanent structure (excluding agriculture or forestry buildings) and associated fixed surface, infrastructure within the curtilage of the development. In all cases the RDA activity must comply with the polluter pays principle. Categories include: Previously developed vacant land Vacant buildings unoccupied for 1 year or more Derelict land and buildings on the NLUD database Land or buildings currently in use, allocated for development in the adopted plan or have planning permission, or where it is known there is potential for redevelopment Defence buildings Land used for mineral extraction and/or waste disposal Reclaimed, Redeveloped and Regenerated land GN PJ_SP309 Total number of hectares of Brownfield Land reclaimed, serviced or developed to an acceptable standard/condition Reclaimed: Making land fit for use by: Removing physical constraints to development or improving the land for end use Providing services to open it up for development e.g. provision of utilities and service roads (though please note these are not eligible costs under the state aid land remediation scheme) Activities may include: - dealing with contamination, existing surface and buried structures - Stabilisation - Levelling - Provision of flood defences - Environmental improvements or enhancements Page 22 of 49 Issued: June 2009 Version 4.0 Next review: June 2010 Redeveloped: Development of a site and putting up new building or refurbishing an existing building e.g. construction of premises, new plant and equipment, fitting out of premises Regenerated: Remodelling, enhancement, interpretation or improvement of the site for public benefit and/or its active long term management for that purpose, including: - access - safety - planting Hard End use Land used for physical development/construction Green Infrastructure Physical environments and open spaces that have a management plan in place (e.g. woodland, park, garden, nature reserve, wildlife habitat) which sustain clean air, water and national resources and bring social economical and environmental benefits Verification Photographs, planning consents confirming Brownfield status, land registry records/deeds, local authority/NLUD register details, certificate of practical completion, QS certification. Contaminated Land – completed land condition and remediation complete certificate Green infrastructure management plan Analysis GN PJ_SP309 Hard end use Green Infrastructure Page 23 of 49 Issued: June 2009 Version 4.0 Next review: June 2010 8. New or upgraded floor space PMS Codes F/B – Floorspace (business use) F/C – Floorspace (commercial use) F/V – Floorspace (visitor attractions/leisure) F/E – Floorspace (education use) F/O – Floorspace (other use) Unit of measurement Area m2 Counted On practical completion ERDF requirements New or upgraded floorspace is not an output for ERDF, it an be counted as result for ERDF (R4), however, only floorspace for business use and commercial use can be counted for ERDF (excluding retail) Exclusions Cannot be counted when the only activity is the purchase of an existing building. Residential floorspace should not be included. Floor space Internal floor space – including corridors, lifts, plant rooms, service accomodation New or upgraded New: new building Upgraded: Building refurbished, improved or adapted for productive use. Space that is now lettable or where the actual or potential market value has been increased by the physical improvements Business use Facilities to support business activity but essentially non-commercial in nature e.g. facilities owned or operated by the public sector to promote/support business (such as National Biomanufacturing Centre, Food Technology Centre), advisory services. Commercial use Premises usually owned by the private sector for commercial activity e.g. offices, industrial, retail, hotel. Educational use Premises primarily for educational use e.g. colleges Visitor attraction/leisure Facilities used for tourism or leisure, e.g. museums Verification Building plans showing floor space, address of building, photographs, QS certification and promotional material for sale/letting Analysis By use: Business Commercial Education Visitor attraction/leisure Other By sector (where applicable): Priority sector Employment Sector GN PJ_SP309 Page 24 of 49 Issued: June 2009 Version 4.0 Next review: June 2010 9. Public Realm created or improved PMS Codes PR – Public Realm Unit of measurement Area m² Counted On practical completion ERDF ERDF do not count public realm Exclusions Roads and highways. Private land not open to the public, or not predominantly available to the general public to use at no cost. Anything counted under Brownfield Land output. Public Realm Infrastructure and environmental improvements in towns, cities and villages includes: Cycleways, Footpaths/pavements, and open spaces/areas that are open to the public 24/7 Verification Before/after photographs, QS certification, plans/drawings Analysis None GN PJ_SP309 Page 25 of 49 Issued: June 2009 Version 4.0 Next review: June 2010 10. Number of Visitors attracted PMS Code VA – Visitors Attracted Unit of measurement No of visitors to new or improved venues or attractions Counted Using tourism surveys at appropriate frequency to be agreed. Where the project is undertaking improvements to a venue/attraction the methodology will need to count the increase in visitor numbers. It is therefore essential that a baseline is set to allow this measure. ERDF requirement ERDF requires actual numbers to be counted/evidenced Exclusions Visitors to venues/attractions that have not received NWDA funding Visitor Individual attending an event, venue or attraction. Can be from within or outside the region – there is no minimum visit time or travel distance, but information should be gathered to allow analysis below New or improved venue or attraction A leisure venue or attraction that has been launched or improved through a contribution of funding from the NWDA Verification Evidence to be collected using a standard survey methodology approved by the NWDA Tourism Team Analysis See note re ERDF requirements Analysis by visitor types: a) domestic day visitor from within the region b) domestic day visitor from outside the region c) domestic overnight visitor from within region d) domestic overnight visitor from outside region e) International overnight visitor Note that on PMS, visitor types (a) and (b) are combined GN PJ_SP309 Page 26 of 49 Issued: June 2009 Version 4.0 Next review: June 2010 11. £ economic impact of major events and tourism marketing PMS Code MARK – economic impact of major events, tourism marketing and new and improved visitor attractions Unit of measurement Economic impact in £ of spending by visitors: Attending major events Attracted to the region by tourism marketing Visiting new or improved venues and attractions Counted Using event/marketing surveys at an appropriate frequency to be agreed Where the project is undertaking improvements to a venue/attraction the methodology will need to count the increase in visitor spend. It is therefore essential that a baseline is set to allow this measure. ERDF requirement Output not counted for ERDF, but can count as a result (R8) – Visitor spend ERDF requires actual numbers to be counted/evidenced – STEAM methodology is not accepted as evidence Exclusions Economic impact generated that cannot be directly attributed to NWDA funding, or that is not a result of expenditure by visitors. Major Event An event where NWDA has been involved with funding and/or PR for the event through ‘major event’ funding. Other events that receive funding from the NWDA may be able, or be required, to submit evidence of visitor numbers and their economic impact, at the discretion of the NWDA New or improved venue or attraction A leisure venue or attraction that has been launched or improved through a contribution of funding from the NWDA Verification Evidence to be collected using a standard survey methodology approved by the NWDA Tourism/Marketing Teams Analysis Analysis by: Economic impact of visitors to major event Economic impact of visitors generated by tourism marketing Economic impact of visitors to new or improved venues or attractions GN PJ_SP309 Page 27 of 49 Issued: June 2009 Version 4.0 Next review: June 2010 12. Tonnes of Carbon Dioxide generated PMS Code SCP - Sustainability Unit of measurement Tonnes of Carbon Dioxide Counted The NWDA Carbon Accounting Tool should be used at the project appraisal stage to estimate the carbon footprint of the whole lifetime of the project (ie what the carbon emissions as a result of the project are likely to be). The actual carbon footprint of the project will be calculated and reported regularly throughout the life of the project and at end of project the overall actual carbon footprint will be compared to estimates. Exclusions Anything outside the remit of the Carbon Accounting Tool. Carbon Dioxide generated 1. Energy used by fixed or mobile equipment eg heating in a building, lights, machinery on a construction site 2. Generating and disposing of waste 3. Use or discharge of water 4. Transportation of materials or people The carbon footprint should include only the elements of the projects lifecycle over which the project applicant actually has influence in terms of resulting carbon emissions and can provide data. Further information can be found in the ‘Help’ section of the Carbon Accounting Tool. Verification Copy of the completed Carbon Accounting Tool Analysis None required GN PJ_SP309 Page 28 of 49 Issued: June 2009 Version 4.0 Next review: June 2010 13. Environmental Businesses Assisted PMS Code Output does not have PMS code – will be recorded for ERDF purposes on MCIS Unit of measurement Number of Businesses Counted When business has received a minimum of 2 days consultancy advice or non financial assistance, grant or equipment of at least £1,000. ERDF requirement Exclusions This is an ERDF only output Distribution of mail shots and brochures (electronic or hard copy). Business can only be counted once in a single project even if it receives more than one piece of support – though if the support is under the threshold the support can be counted cumulatively – and can count towards the cumulative assistance in output 5 as long as the business is only counted once. If the support is assisting the business develop an environmental product under output 14 then only one of either environmental business or environmental products output can be claimed for the assistance provided. Assistance Business must have received support, information or advice by means of individual interaction through face to face, telephone, conference or workshop, networks or web based dialogue. Can include mentoring, financial assistance, development of specialist business premises, assistance with promotional or marketing activities. Environmental Business Developers of: environmental/less polluting technologies low carbon technologies environmental products services industries/specialist consultants providing expertise in areas such as flood management, asbestos surveying, waste management and minimisation, efficient energy use and environmental law. Business for this purpose is an establishment with a specific address and post code rather than an enterprise (which may have more than one establishment and whose address and post code may well be the corporate headquarters). Verification Name, address (inc. post code/tel no.) of business showing ownership + beneficiary data. Written company statement or letter signed by Owner, Chief Exec or Finance Director confirming business support received and any action plans produced as a result of the support Analysis GN PJ_SP309 Business ownership by: Gender Age Ethnicity Disability Page 29 of 49 Issued: June 2009 Version 4.0 Next review: June 2010 14. New Environmental Products Assisted PMS Code Output does not have PMS code – will be recorded for ERDF purposes on MCIS Unit of measurement Number of new environmental products assisted as a result of the project Counted When business has received a minimum of 2 days or £1000 of financial assistance towards the development of an environmental product. ERDF requirement Exclusions This is an ERDF only output Assistance provided in the form of mail shots and brochures (electronic or hard copy). Business can only be counted once in a single project even if it receives more than one piece of support. If the business developing the environmental product is an environmental business defined under output 13, then only one of either environmental business or environmental products output can be claimed for the assistance provided. Assistance The number of environmental product(s) supported to improve performance, undertake market testing or provide support to ensure market readiness, accessing further research or funding regardless of whether they succeed in doing so. Business must have received support, information or advice by means of individual interaction through face to face support in attending trade conferences. The activities may include mentoring, financial assistance, promotional or marketing activities, providing links to the HE sector or providing access to further research. Environmental product Environmentally/less polluting goods, energy efficient and resource efficient technologies. Verification Name, address (inc. post code/tel no.) of business and description of environmental product for each ‘environmental product’ supported and how this is classed as an environmental product. Written company statement or letter signed by Owner, Chief Exec or Finance Director confirming support received for the product claimed. Analysis GN PJ_SP309 Business ownership by: Gender Age Ethnicity Disability Page 30 of 49 Issued: June 2009 Version 4.0 Next review: June 2010 15. Number of applications of Low Carbon Technology PMS Code Output does not have PMS code – will be recorded for ERDF purposes on MCIS Unit of measurement Number of new low carbon technology applications as a result of the project Counted When the low carbon technology has: Been demonstrated in a commercial application for an agreed period of time that reflects the ability of the technology to reduce CO2e emissions; Been developed as a prototype and can demonstrate through experimental conditions the ability to reduce CO2e emissions. ERDF requirement Exclusions This is an ERDF only output Assistance provided in the form of mail shots and brochures (electronic or hard copy). If the low carbon technology could also be classed as an environmental product, as defined under output 14, then only one of either environmental products or low carbon technology output can be claimed for the assistance provided. Use of natural systems to store carbon. Application of carbon trading and voluntary offsets Behavioural change processes. Low Carbon Technologies The application of a technology that can demonstrate through its use, an ability to save CO2e over an existing technology or techno. Low carbon technologies cover a broad range of activities relating to energy waste and water including increasing efficiency of fossil fuel and electrical motors, renewable energy technologies, building management controls, substitution of high energy materials and waste/water recovery and minimisation technologies. CO2e Equates to Carbon Dioxide Equivalent – There are six main greenhouse gases with different warming potential and for simplicity they can be calculated to be reported under the one heading CO2e. Verification Name, address (inc. post code/tel no.) of business and description of the low carbon technology, with an independently verifiable report for the technology that demonstrates a step change in technology design, that will provide a reduction in CO2e baseline emissions. Written company statement or letter signed by Owner, Chief Exec or Finance Director confirming support received for the product claimed. Analysis Business ownership by: Gender Age Ethnicity Disability GN PJ_SP309 Page 31 of 49 Issued: June 2009 Version 4.0 Next review: June 2010 ERDF Results Result R1 Jobs created/safeguarded definition is covered under output 1 Result R2 Business Created definition is covered under output 4 Result R4 New or upgraded floorspace definition is covered under output 5 Result R8 Visitor Spend definition is covered under output 11 Result R3 Businesses improving their performance; and Result R5 Individuals who gain employment within 6 months of intervention; are detailed below Result numbers 6 and 7 are not used in this document. R3. Businesses improving their performance PMS Code Output does not have PMS code – will be recorded for ERDF purposes on MCIS Unit of measurement Number of businesses Counted When there is demonstrable proof that a business, assisted through an ERDF project, has had an increase in GVA against the baseline. There is likely to be a delay between the project activities and the realisation of improvements in GVA. Where business improvement was expected to have reduced in the absence of the intervention, an improvement may be recorded if the intervention has resulted in a lesser fall. Exclusions Any business not receiving ERDF support to improve performance Improved performance Measured through increased GVA. GVA = Total salary/wage costs + pre tax profit + depreciation Baseline position (previous year Annual Report/Company Accounts) needs to be evidenced when assistance under output 5 is given and this then needs to highlight that at the end of the assistance (agreed date of calculation) there has been some improvement in the position. Verification Company evidence from output 5. Collection of GVA data (including baseline) and improved measure GVA from Company Accounts. Analysis GN PJ_SP309 Business ownership by: Gender Age Ethnicity Disability Page 32 of 49 Issued: June 2009 Version 4.0 Next review: June 2010 R5. Individuals who gain employment within 6 months of intervention PMS Code Output does not have PMS code – will be recorded for ERDF purposes on MCIS Unit of measurement Number of Individuals who have received assistance through the project and actually secure employment Counted When the individual who received support has gained some form of employment within 6 months following intervention Where the person was in employment at risk and has changed to a more secure job, this may also be counted. Employment Employment may include voluntary and part time work as well as full time employment (paid or self employed) Intervention Support provided to the individual through an ERDF funded project Exclusions Anyone not assisted through an ERDF funded project Verification Name of individual supported Letter from ‘employer’ with name/address of place of employment including post code/tel no, confirming required details (i.e. start date, job details). Evidence of employment of individual e.g. contract, pay slips, employment records + beneficiary data Or Self employment details if appropriate Analysis Beneficiary by: Gender Age Ethnicity Disability For MCIS recording purposes the output should be split: 5a Employment 5b Self-employment GN PJ_SP309 Page 33 of 49 Issued: June 2009 Version 4.0 Next review: June 2010 FREQUENTLY ASKED QUESTIONS Jobs Q. Can a sole trader be counted as a job created as well as a business created? A. Yes, to count as a job they must meet definition criteria – recognising that the employer and employee is in this case the same person. Note sole traders include self-employed and free lance workers. Q. Does the type of business created make a difference to whether we can count a job as well? Does the first job created within a business always get discounted. A. The type of business is not relevant. The first job is not discounted all jobs can be counted. Q. Can helping individuals to obtain voluntary work count as a job? A. Not for output 1 where this is a job is Paid employment. They can be counted under core ouput 2 ‘People helped to secure employment, education or training’ or as an ERDF result under R2 ‘Individuals who gain employment’. Q. In counting the outputs are we expected to collect information on the actual jobs created from inward investment successes? A. There is no reason why inward investment jobs should be treated differently from other RDA interventions that result in jobs created. Q. If we train people in construction skills with the aim of becoming selfemployed, can we count then under jobs created? A. No the project objective is to develop skills so they should be counted under the relevant skills output. Having received the training they may go on to get either a job or become self-employed. These are the outcomes for the project and should be picked up when the project is evaluated. Q. A project focused on corporate social responsibility aims to link companies with local schools. The project will be managed by an individual, whose salary will initially be wholly paid for by the RDA. The intention is that this post will eventually be funded entirely by contributions from the companies involved after 3-4 years. At what point can the post created be counted as an output? Do we have to wait for the contribution from the RDA is zero or can we claim half a job if the private sector is contributing 50%? A. The post is an input to run the project so it cannot be counted as an output at any time. This is not affected by the project objectives or the source of funding contributions. If the post is sustainable and continues after the life of the project then it is an outcome or result not an output and may be counted as such. Q. We are getting conflicting advice from our consultants on whether to count construction jobs as an outcome in our evaluations. If they are a part of a project activity they are an input, but clearly if we do not assess the contribution of activity to project outcomes particularly over large builds (and periods) then we are loosing a swathe of data that cannot be assessed which would be a shame in our assessment of impact. A. The consultants appear to be mixing inputs, outcomes and impacts. They each measure different aspects of a project when the definitions are not applied correctly the risk is that the consultants will try to measure the wrong effects. The simple answer is that if the construction jobs are an input (necessary to make the project happen) and so cannot be counted as an outcome (the result or consequence of the project). Its evaluation should consider to what extent the project success factors have been achieved against its SMART objectives and baseline identified before the project started. A large build has both negative and positive effects during and after its construction phase. Examples might include: GN PJ_SP309 Page 34 of 49 Issued: June 2009 Version 4.0 Next review: June 2010 Negative – additional noise, dust, traffic congestion (impact on health and well being of local community – surveys, incidence of illness reported etc) Positive – contractor takes on/trains local unemployment people to work on the site (impact being a reduction in local unemployment) Other factors might include: Jobs/new businesses that invest on the site on completion Improved confidence of the area reflected in higher land/premises values/rental; further investment by the private sector Improvements in the visual amenity of the area Multiplier effect of spend by site staff in the local community – papers, food, pubs etc. If the project had a direct role in matching job opportunities between the unemployed and the contractor to assist the take up then they could be counted under output 2 ‘People helped to secure employment’ and if the project has ERDF funding and unemployed individuals are employed by the company become permanent employees within at least 6 months then they could be counted as an ERDF result R2 - individuals who gain employment Q. What is the full set of categories used by the census to record ethnicity? A. These are: White British White Irish Other white background Black Caribbean Black African Other black background Indian Pakistani Bangladeshi Other Asian background Chinese White and black Caribbean White and black African White and Asian Other mixed background Any other ethnic Group GN PJ_SP309 Page 35 of 49 Issued: June 2009 Version 4.0 Next review: June 2010 Business Creation Q. Can business link business starts be counted under this output? A. Yes, it is acceptable to include the Business Link start ups. However, measures must be put in place to avoid double counting where Business Link is being used to broker business support through projects. In this case there should be agreement that Business Link will include in their count NOT the project. Q. What can we count if a business relocates from another region and increases the number of people employed? Can we count the additional jobs – even if the jobs were not at risk in their previous location? A. The additional jobs can be counted under core output 1 jobs created, as these are new. The business cannot be counted as it has simply relocated from another region and is not a new business. If it was a first branch of a business that continued in its original location then it could be included as new business attracted to the region. Q. When a project encourages a farm business to diversify e.g. help a farmer start up a bed and breakfast operation, I would regard this as a new business, but the farmer would probably not need to register separately for VAT or Class 2 NICs as a result of starting it up. Please will you confirm that new businesses resulting from diversification of an existing business may be counted and that persuasive evidence of creation will be acceptable where the business owner does not need to register for VAT or Class 2 NICs A. Where public resources are used to assist farmers to diversify from primary production it is essential that there is a transparency between the businesses. As a minimum there must be a separation of accounts between the two to ensure there is no cross-subsidisation between the farm primary production activities and any additional businesses run open the farm to ensure the aid complies with the State Aid rules (agricultural and SME BE etc.) Where this is the case the additional business created may be counted. Q. Can we count businesses that are “Management Buy Outs” as it could be argued that the result is a new business has been created? A. No a “Management buy out” means that there is an existing business hence a new business has not been created and it does not mean the output definition. The buy out price paid reflects the value of the existing business. However, it could be included under Business Support if it relates to agency intervention. Q. Can a business relocating from one side of the border into England from Scotland, Wales or Northern Island be counted? A. A business that simply relocates from one side of the border into England cannot be counted. The same principle applies as to a business relocating from another English region or even within a region. This is displacement with no net benefit to the UK economy hence it cannot be counted. However, where the business remained in Scotland etc. but opened a new branch in the region then it could be counted as a only the first branch in the region. Q. Can franchises be counted as a business created? A. There are 3 basic types of franchises: 1. Where the business set up a branch, owns it and looks for someone to manage it on their behalf (e.g. pubs with independent managers). 2. Where the franchise sets up a business and buys the ‘kit’ (signs, machinery, branding etc.) and then runs as their own business. 3. Where the franchise buys a part share of a business and the rest is owned by the parent company. GN PJ_SP309 Page 36 of 49 Issued: June 2009 Version 4.0 Next review: June 2010 When the franchise is type 1 or 3 then they cannot be counted as a business created, unless they meet ‘the new branch to the region” qualification. When it is a type 2 franchise then it may be counted as a business expansion to the region. However, if an existing franchisee opens a new outlet in the region this may not be counted as it is an expansion of his/her existing business. Q. What is the definition of a definition of a Minority (BME, Female and Disabled) led Business? A. A minority led business is defined as a company or business which has a majority (over 51%) of partner, owner or director ownership or in the case of a social enterprise/other where the majority of the senior management team comprises individuals from BME, women or disabled people. Q. Please could you advise if there are any guidelines to use to forecast the Business Survival outputs at 12, 24 and 36 months. A. We don't have anything definitive and B/L also doesn’t at present. As a guide you should use a reducing 10% drop out - ie 90% at 12 months, 80% at 24 months, and 70% at 36 months - not scientific at all, and probably a bit pessimistic, but given the present climate may be better to err on the side of caution. Unless required for the specific project, it has been decided that survival rates do not need to be set as targets, except for ERDF at 12 months (ie result R2). As we start to see actuals being reported we will be able to update this information and have more evidence based figures. Q. Under the Tasking Framework we could claim Inward Investment under the Business Creation output. Is this now not applicable under the New Output Framework? A. A decision has been taken that we wouldn’t count Inward Investment as this is only applicable to one part of the Agency (Business Relations) and the team concerned keep separate figs for this. GN PJ_SP309 Page 37 of 49 Issued: June 2009 Version 4.0 Next review: June 2010 Business Assistance Q. Does the 2 days consultancy provision include travel time and preparation time on behalf of the client or just the actual time provided by the consultant to the client? A. Travelling time is excluded; it is the actual time delivering the consultancy service to the business that can be outlined. Q. If the assistance involves training the staff of a business; can we also claim output under a skills output? A. Yes where this is part of the project objectives that there is a direct link and it meets the relevant skills output requirements then the individuals whose skills have been developed may also be counted under that output. Q. Does the restriction of counting business assists only once per project lead project managers to disaggregate projects artificially i.e. against the principle of GRADE? A. No. It is a fundamental requirement of public sector projects that these should not be split to keep within financial delegations or achieve higher outputs. This is an inefficient use of RDA resources. It will generally result in less effective projects which are not likely to demonstrate the same value for money as other large projects and so may not be approved when there is a limited budget. Q. Can state schools that receive support on how to manage their budgets be included in the business support output? A. No. State schools are not companies in terms of the definition. Q. A project to give assistance to businesses is designed to run for three years with the contract performance reviewed annually and agree changes to the target/focus area on the basis of the experience of the previous 12 months. Could we claim subsequent assistance given to companies under this project in years two and three? A. No. Where assistance is given to a business within a project the business can only be counted once. As a result of intensive assistance under the project there should be clear outcomes that can be evidenced to demonstrate its value and impact Q. Is there an issue if a company is located in the NW but the Head Office is in another Region? Would this disqualify the Company from receiving support and being counted? A. As long as the benefits from the support to the company (eg jobs) will be retained in the NW then this should not be an issue. Q. Businesses assisted now need to be analysed by depth of assistance. Each business can only be counted once and presumably the majority of assistance would be able to be counted within the 'universal support' definition. However, if a business is counted under universal support this then means they cannot be counted under the other types/definitions if they are then given more indepth assistance. Is it possible to count incrementally and then make adjustments to previously reported figures? A. Businesses should, as far as possible, only be counted once within a project, as it the number of businesses assisted not the number of types of assistance. However, it has been recognised that this could be an issue and to bring the process into line with Business Link practice it has been agreed that all business assists could count as ‘Universal’ on first contact (if they fit the definition) and than an adjustment to the figures could be done if the business subsequently receives a higher level of assistant at ‘Intermediate’ or ‘Intensive’ levels. Adjusting reported figures does cause complications so this will operate over a rolling 12 month period and project deliverers will need to show that they have set up systems to record these GN PJ_SP309 Page 38 of 49 Issued: June 2009 Version 4.0 Next review: June 2010 adjustments. It does mean that there may be some double counting but the arrangements will hopefully keep this to a minimum. [You should also remember that for ERDF the business cannot be counted until it has reached a minimum of intermediate support so any figures recorded for universal support will not be valid for ERDF projects]. Q. For business assistance (universal), what constitutes individual interaction? If a person attends a conference or workshop, is the fact that they attended and it was for longer than 2 hours sufficient, or would there have to be, for example, within the conference/workshop small discussion groups? A. The universal support is wide ranging and there are no specified minimum requirements of this sort. The definition aligns with the Business Link definition so can include anything that is considered to be providing assistance to business, therefore if the example of the conference/workshop was aimed at some sort of assistance for businesses, then it can count. Q. In the transition from the Tasking Framework to the new Outputs Framework when are we counting a business from? Is 01.04.09 the start or if they have previously been assisted under the old output can they/or not be counted under the new one? For example ‘x’ count businesses who have a diagnostic – but they do get repeat business that they know under current rules they cannot count in the future, but if a company requests assistance next financial year that have previously had support, can they now be counted? A. Under the new Outputs Framework it was agreed that if a project classifies a business assist as ‘universal’ and than the business subsequently returns for more intensive assistance then they can be counted again (but the numbers need to be adjusted on a 12 month rolling period). In relation to your query the only time the business should be counted again is if the original support is 'universal' ie would not have already been eligible to be counted as intermediate or intensive. Q. On Intensive assistance to business how vital is GVA and can Intensive be measured in a different way to GVA impact? A. We are using the Business Link national definition for consistency so we cannot change it. If the business cannot provide the necessary information or the assistance will not result in improved GVA you may need to count the assistance under the intermediate definition. A baseline GVA should be set based on certified accounts and then measured again to look at any improvement in GVA after a specified period of time – usually 12 months later. Q. There is no minimum level of time defined for Intensive Assistance, is there any guidance on what this should be. A. The time isn’t specified as it depends on the amount of work with the company. Usually this would include a diagnosis and development of action plan, and then the review of performance/GVA. Business Link benchmark on this is an average of 3 days. We would not really expect the input for this to be less than the Intermediate requirement of 2 days. GN PJ_SP309 Page 39 of 49 Issued: June 2009 Version 4.0 Next review: June 2010 Brownfield Land Q. Could the RDA reclaim the land under one project, and then subsequently redevelop the land under different contract (say a year later). If so could they claim the area of land twice? A. No. To do so would be double counting of the same land – the output measures the land reclaimed and/or remediated. In this case you can count when the land is reclaimed and not wait until the re-development. Value for money on carrying out both elements of the work will no doubt be justified in the project objectives and outcomes, the latter being measured through the project evaluation. Q. If an RDA sells Brownfield Land they own to a developer and have not done any direct reclamation and the contract constrains how it can be developed can the RDA count the land reclaimed as an output? A. Yes. Provided that there is an enforceable contractual condition e.g. a covenant which may relate to the use of the land and/or its subsequent disposal. This is required to protect the RDA’s interests in the use of the land. It must be monitored to ensure compliance. When considering this as an option the RDA will need to assess whether it involves disposal for less than best value or a gift – these require additional BERR approval. Q. Does the property have to be unoccupied for 1 year before the RDA involvement or before the physical start of the works? Can we count an output if the property has been vacant for six months, if we know that work will not start for at least another six months e.g. time taken for planning permissions. A. It is the time the property has been or will have been vacant at the start of the works. Q. The project involves the compulsory purchase and subsequent vesting of 45 parcels of land for development. The site will be sold to the private sector and should result in an estimated 22,000 square metres of new business floor space. Applying the jobs square metre gearing (offPAT) Appraisal Advice Note 1), it is calculated that this floor space would accommodate 825 jobs. The jobs are not part of the project contract as they will be provided by subsequent private businesses who occupy the site. However, it would make little sense not to claim and monitor these 825 jobs as they form a sizeable output for our investment. Can we claim these jobs as an output? A. In this example neither the consequent floorspace nor jobs can be claimed as outputs as they are not a direct result of the projects activities. However, both can be claimed as outcomes as they are a consequence of the project investment. The project should forecast its outcomes as well as its outputs. They should then form part of the vfm assessment during the appraisal and assessing their delivery should form part of the project evaluation plan. If the total project included the purchase/remediation of the land and the subsequent building then the floor space could be counted as outputs. If the building was bespoke for a specified occupant and the jobs were a contractual requirement then they could be counted. The ‘rule of thumb’ should be to include as outputs anything that can be contracted for. GN PJ_SP309 Page 40 of 49 Issued: June 2009 Version 4.0 Next review: June 2010 Public Realm Q. Definitions for the new public realm output state that and highways are excluded, but that footpaths do constitute public realm. Unfortunately, my interpretation is that pavements are highways and therefore out - I take footpaths to have a particular meaning, i.e. public rights of way. Is this correct? A. Under the definition we have agreed that pavements can be classed as footpaths. Highways are defined as the actual roadway (ie laying tarmac etc). GN PJ_SP309 Page 41 of 49 Issued: June 2009 Version 4.0 Next review: June 2010 Premises Q. If I regenerate and old multi-storey building, can I count the area of the floor space? A. Yes. The output includes upgrading premises and counts the floor space produced by the project. Q. Where a project contains a mix of end uses, for example residential and office components, can the project claim all the floorspace being created or should it just be limited to the office component. A. All the floorspace for office and retail can be counted (commercial use) for Single Programme, but not residential. Please note that if ERDF funding is being used the retail component also could not be included in respect of the ERDF expenditure. Q. A developer is currently working up a speculative office development, which they claim has the potential to house up to 200 new jobs. Should these new jobs be included as outputs in the Development and Appraisal Form and subsequent Grant Funding Agreement? A. No, the jobs in this case are not direct and cannot be counted as outputs. The achievement of these jobs would be subject to a tenant/occupier being sought and the developer could not be contracted to deliver these jobs. However, these jobs are outcomes (SP) /results (ERDF) and should be monitored/evaluated. To be claimed as outputs jobs must be a direct (able to be contracted for), for example where the developer pre-lets the development to a specific end user prior to commencing the project. GN PJ_SP309 Page 42 of 49 Issued: June 2009 Version 4.0 Next review: June 2010 Employment, Education or Training Support Q. Is there a minimum level of assistance similar to that for Business Support? A. No there is no minimum assistance intervention value or period. Q. Job is defined as any employment requiring an employment agreement; however sole traders will not have this. Can we still count assisting people to become their own boss? A. Yes as long as the other definitions of people and assistance are met. Q. Can the provision of travel information and subsidised travel to interviews and work by public transport for a short period of time be included under this output as it falls into category of removing barriers to getting back into the labour market. A. Yes. The provision of travel information falls under the information aspect of the output definition. Provision of subsidised travel for individuals to encourage them to go to interviews/start work without financial penalty can form part of Employment Support as long as it does not duplicate Jobcentre responsibilities. Providing support to individuals should not cause any state aid problems but if the aid is to companies then the state aid implications would need to be considered. Q. Can we count assistance to seasonal workers, people on temporary or short term fixed contracts, or individuals on probationary periods or placements as in employment at risk? A. Yes. These groups can be considered to be in “employment at risk” for this output. Q. Can projects claim training outputs for homeless people i.e. those without a permanent address – who are in the project target area? A. Training provided to homeless people could possibly be counted depending on the project objectives and the assistance offered under either Employment Support or Skills if they received a minimum of 6 hours training. The person information here would either be NFA (no fixed abode) or a homeless hostel. Q. With A8 migrants coming to the UK, can we include these in project regardless of how long they have been residents in the country? We have heard that they have to be residents for 3 years first. A. Eastern European Accession 8 (A8) countries joined the European Union in 2004. The UK allowed unfettered access to its Labour Market to new Eastern European member states in 2004. Migrants from these countries are therefore entitled to enter UK to work and there is no residency qualification. See also the Q&A on migrants and basic skills. The 3 years confusion may be in relation to Bulgaria and Romania, which joined the EU in January 2007 but under tougher conditions than the 2004 cohort, which may last for seven years. In their case the UK has imposed restrictions details at http://www.bia.homeoffice.gov.uk/workingintheuk/sbs/bulgariaromainia/eligibility Q. Can we include asylum seekers who are in receipt of National Asylum Support Service (NASS) support whilst awaiting decisions about status, in our NEET and skills outputs? A. Non asylum-seekers are only entitled to limited support whilst waiting for a decision on their status by the UK Border Agency (for more information see Asylum Aid). However, should UK Border Agency decide to i) allow the claim and give them Refugee Status or ii) the legal indefinite Leave to Remain (ILR status) or iii) give permission for them to work as they have been waiting for a decision on their case for more than a year through no fault of their own then they may be included in project activities and counted. GN PJ_SP309 Page 43 of 49 Issued: June 2009 Version 4.0 Next review: June 2010 Skills Q. Can we claim skills outputs when the project involves training individuals who will deliver the project e.g. local authority or partner’s staff? A. No. The training here is for input resources to deliver the project. The only exception would be if one of the stated project objectives is to raise the capacity of delivery in the region. Q. Where does a full ECDL qualification sit in relation to NVQ equivalents? A. Information on qualifications can be found on the Qualifications and Curriculum Authority website http:/www.qca.org.uk Q. Can we count (1) non UK nationals (2) non EC nationals as beneficiaries for skills outputs. A. Yes, if they are resident or working in the region. Q. In a project to provide work experiences to graduates can the individuals be included under the skills output as the work experience opportunity offers a different opportunity for skills development, depending on the company and project requirements? A. Not if the objective of the project is to provide work experience not skills training, it should be counted under output 2 ‘People helped to secure employment, education or training. If the project objective is skills development then the project focus should identify this and relate it to the relevant project objective. Q. Can the six hours training be delivered in modules i.e. not in one day? Can the six hours training be made up of two separate courses i.e. one learner attending two different three hour courses on separate subjects e.g. H&S and First Aid? If a learner does six hours of training with one organisation, and is then referred on to another and they do a different six hours training with them, can each organisation claim one output? A. Assuming the training modules are part of the same project whether by the same or different training organisations. The output unit is the learner and to count the individual has to receive a minimum of 6 hours (there is no maximum figure). In the second example the individual would receive 12 hrs of training but could only be counted once under the project. Q. Can projects claim the skills outputs for learners who have been resident in the UK for less than 3 years? The LSC ESOL can only fund those that have been resident for 3 years plus, hence the question? A. Yes. Skills outputs only require that the person receives a minimum of 6 hours training. Q. There is some confusion over counting individuals assisted in their skills development outputs for under 16’s and what is meant by the following exclusion: ‘Services that are the legal statutory responsibility of other organisations e.g. provision of statutory education to 16’ Does this mean that we can’t count skills that are delivered as part of the national curriculum, or that are delivered in the classroom during normal school hours? A. The principle here is that the core activities for which the delivery body receives funds that are voted from Parliament are not ‘topped up’ by other public bodies. Where a project is additional to those statutory requirements then the individuals assisted can be counted e.g. where the objectives of a project is to encourage pupils to take up science subjects through organising science fairs that compliment the national curriculum then the participants may be counted, if they meet all the other criteria. GN PJ_SP309 Page 44 of 49 Issued: June 2009 Version 4.0 Next review: June 2010 Q. Are ICT skills now part of Basic Skills? A. No. The definition of Basic Skills has not changed; it still refers to “functional literacy and numeracy skills”. The literacy standards cover the skills of speaking and listening, reading and writing. The numeracy standards cover the skills of interpreting, calculating and communicating mathematical information. These basic skills are fundamental to all other learning and skills development. While ICT Skills are an essential skill for life they fall out with the basic skills definition and so cannot be counted under this output. Q. There is a general principle that where a public sector body receives core funding for its activities then other public sector bodies, such as the RDA’s should not fund the same activities. As the LSC is responsible for funding training on basic skills is it appropriate for RDA’s to fund project delivering basic skills? A. Yes. As the original output was agreed as part of the RDA Tasking Framework, the responsible department recognised that while the LSC is the prime funder of basic skills and other skills outputs (Level 2 qualifications etc.) there will be circumstances where RDA investments do lever such outputs, either in joint funding initiatives with LSC’s or where LSC funding is not involved. RDA outputs against these indicators will be relatively small compared to the local LSC outputs, it will be for project appraisals to test for project additionality and ensure that the RDA is not funding something that the LSC should fund. Q. If an individual already has a numeracy qualification but then achieves a literacy qualification can they be counted under this output? A. No, only the first qualification attained by an individual counts for this output. Subsequent basic skills qualifications do not count. Q. Can we count prisoners under the basic skills output? A. Yes. Offenders and ex-offenders are one of the basic skills target groups identified in the Departmental Skills for Life Strategy. Q. Can we count migrant workers, now resident in the region, towards basic skills outputs, if they are attaining basic skills in English as their first qualification in the UK, when they have already have qualifications in their country of origin? A. Acquisitions of functional English Language Skills are included in the ESOL for Work Qualifications. Migrant workers may be counted where they do not have functional English and the project objective is to assist them to attain it. Where the project is using the ESOL for Work Qualification to enable the migrant workers to attain functional English has funding been sought from the LSC in the first instance? Useful websites: Skills for life Network website – http://www.skillsforlifenetwork.com Skills for Life improvement Programme website – http://www.sflip.org.uk Skills benchmarking source http://wwww.isc.gov.uk/providers/data/statistics/success Q. Is one A level classed as an equivalent for a Level 2 qualification? A. DCSF confirmed that this is correct for counting numbers towards the Level 2 PSA target. GN PJ_SP309 Page 45 of 49 Issued: June 2009 Version 4.0 Next review: June 2010 Financial Q. Can we count revenue expenditure as well as capital? A. Yes, revenue funding received that contributes to the project can be counted. However, please note that the ERDF Programme is not counting matched funding , only private sector leverage (over and above matched funding). Q. Can sunk costs included within regeneration infrastructure investment? A. If the sunk costs are an integral part of the development costs to reclaim and redevelop a site then they may be included, along with other surveys or professional design costs. Q. Where HEFCE or LSC provide the funds for a project but channel them through an HE or FE institution to administer them can we count these funds as public sector? A. Yes provided that the funds are not for their statutory functions e.g. undergraduate/post graduate teaching. In this case the funder would be HEFCE or the LSC not the institution. In this scenario the HE or FE institutions are only administering the funds on behalf of the public body providing the funding and are in effect an intermediary not funding body. It is essential to correctly and accurately identify who is the funding body. To maintain the project audit trail such funds should be held in a separate project account by the intermediary and its role and responsibilities clearly identified. (However, where the FE or HE institution contributes to the project costs from its own reserves then that funding is private sector and it is also a beneficiary its contribution may be counted under the private sector induced funding). Q. Can we include money invested by a private sector company if they had to borrow the money to invest in the project for example by the way of a bank loan? A. Yes. The financial statement investment made by the private sector company can be counted as it is the investment and not the source of the funds which is material. Q. Can we include Coalfields Private Sector? A. Yes. The principle that private sector investment in Coalfields projects could be included as leverage was agreed previously under Tier 3 outputs. Q. Can subsequent investment by other public bodies or coalfield sites e.g. Local Authority, be included in the output? A. The subsequent public investment on Coalfields has to be considered against 2 scenarios: i. if the investment is part of the Coalfields project funding with the RDA funding the site remediation and the local authority funding the infrastructure and buildings then the local authority funding can be counted. ii. Where the investment follows after the project to remediate the Coalfield site it is subsequent investment and is an outcome. It is part of the evidence of the impact of the RDA’s investment and may be taken into account in assessing the vfm of the project. Q. I am slightly confused why FE and HE institutions are classed as private sector, when their core funding essentially comes from the Public Sector (LSC and HEFCE respectively), so would appreciate some guidance. A. The Office of National Statistics (ONS) is responsible for the classification as organisations as public or private sector. ONS classifies both FE and HE institutions as private sector as they are bodies corporate FE colleges were designated as corporate bodies under the Further Education Corporations) Order 1992, it came into force 28th September 1992. The statutory FE college sector comprises of a number of different ‘types’ of institutions. Both FE and HE provide statutory services and it is GN PJ_SP309 Page 46 of 49 Issued: June 2009 Version 4.0 Next review: June 2010 these services which are funded from public funds. HEFCE provides the funding for the statutory services to HEIs, which cover a range of institutions – Universities, specialist institutions and general colleges; it also directly funds 135 further education colleges. Most FE colleges get the majority of their income from public sources: on average 78% comes from the LSC, with 9% from fees from employers or individuals. Where FE or HE institutions operate commercially e.g. providing bespoke training for employers, undertaking research for businesses they are operating as an undertaking. It is therefore essential to establish exactly what the funding is for and consider whether they are providing: Statutory educational services (if so they should not be seeking funding from RDA’s but from LSC or HEFCE) therefore are not operating as undertakings or: Commercial services when they are and consider the State aid implications during development For ERDF purposes HE/FE count as public bodies. Q. We are working with a FE College to provide a facility for construction training. The matched funders are the college (presumably we can class this as private sector leverage) and the LSC, presumably Public Sector? A. Yes. The LSC funding is Public Sector leverage as it is an NDPB of DIUS. The college position is more complicated depending on which type of institution it is but should generally be treated in the same way as HEI funding of a project and the same analysis should be taken on the proposed intervention (see answer above). Q. We are involved in the development of a Higher Education Campus, other funders include local authorities and HEFCE (a DIUS NDPB), which are classified by ONS as public sector. The University, is the accountable body, so presumably as an HE Institution we would classify their contribution as Private Sector leverage? A. Yes. The university own funds are private sector as ONS classifies all HEI’s as private sector bodies. The funds for their core activity (under/post graduate) come from the public sector. The assumption is that the project is additional to their core activity otherwise no market failure is being addressed or added value from the RDA intervention which would preclude its investment. Please note that HE/FE count as public bodies when considering leverage for ERDF. GN PJ_SP309 Page 47 of 49 Issued: June 2009 Version 4.0 Next review: June 2010 Tourism Q. For outputs 10 and 11, where the venue or attraction is improved through a project attracting NWDA funding are we counting the total number of visitors or just the increase? A. In these circumstances it is the increase in visitor numbers and spend which needs to be captured. The methodology used by Tourism/Marketing will look at overall numbers, so it is essential that baselines are set in the D+A to ensure increase can be measured. For further information speak to the Tourism Team. GN PJ_SP309 Page 48 of 49 Issued: June 2009 Version 4.0 Next review: June 2010 Changes in Version 4: Page 3 Inclusion of para 3.4 for clarification of PMS entry requirements Page 4 Clarification that businesses assisted under ‘universal’ support do not need to be analysed by sector Page 8 Under exclusions, clarification that inputs to a project should not be counted as a job output Page 12 Skills development – some clarification on eligibility to confirm that the output supports lifelong learning and includes individuals of all ages or employment status. Page 13 Skills development (learning type) – type descriptions for 6 and 8 have been swapped to bring into line with Outputs annex and PMS Page 37 Additional Q + A Page 39 Additional Q + A’s GN PJ_SP309 Page 49 of 49 Issued: June 2009 Version 4.0 Next review: June 2010