ITEM ITEM EROSION TO BANKS OF THE RIVER ERME, IVYBRIDGE Report of Head of Community Services Statutory Powers:- Land Drainage Act 1991 Water Resources Act 1991 Budgetary Implications: Possible capital expenditure of up to £30,000 for works and fees (no current budget allocation) Introduction 1. Over the last eighteen months erosion has occurred to a section of the left bank of the River Erme fronting the public open space between Marjorie Kelly Way and the A38 Trunk Road. This land is in the ownership of the Council. Action is required to prevent further erosion of this land. Responsibilities and Liabilities 2. This stretch of the River Erme is “Main River” for which the Environment Agency exercise control. The section of bank that has been eroded was faced with a near vertical blockstone wall to control erosion. The Environment Agency advise that responsibility for this wall and the bank rests with the riparian owner (the Council). Any repairs would require Environment Agency consent in accordance with the relevant legislation. 3. A popular public footpath runs adjacent to the river linking the town centre with the open spaces and playing fields on the south side of the A38. For a length of approximately 40 metres the river bank has been eroded back a distance of up to 3 metres. The resulting top of the bank is now therefore adjacent to the public footpath (a temporary fence has been erected between the footpath and the area of erosion). The Problem 4. The erosion has occurred around the outside of a moderately sharp bend in the river. The bank to this bend had at some time been provided with a man-made near vertical blockstone wall. Erosion has removed the majority of this blockstone wall and the bank has been graded out to an angle of repose of approximately 45°. By its location on the bend in the river there is an inherent risk of further significant erosion at times of flood flows. 5. Any further lateral erosion would remove sections of the public footpath continuing erosion downstream could have an impact on existing sewer outfalls to the river. 6. Repairs to the blockstone wall at this location following previous erosion were carried out some ten years ago. These works were arranged by the Environment Agency Direct Labour Organisation and subject to a financial contribution from the Council. Remedial Works 7. To control any further erosion at this location works will be required. Subject to Environment Agency approval, work would involve the bank being protected with blockstone laid to the existing batter of 45° rather than re-construction of the vertical wall that previously existed. 8. Access to this site for construction plant and supply of the appropriate size blockstone is difficult, possibly requiring a temporary access off Marjorie Kelly Way – this will have a significant impact on the cost of the work. A preliminary estimate for the total cost, including design fees, is in the region of £30,000. 9. No provision exists for this expenditure within existing budgets. 10. This report has been presented in advance of the overall capital programme to ensure that Members are aware of this issue. The Way Forward 11. Preliminary design works are being undertaken in liaison with the Environment Agency. Firm costings will be prepared and these may then be considered in the forthcoming review of the Council’s Capital Programme. Recommendation That the Executive RESOLVES that the report be noted and that any decision be deferred until the whole Capital Programme is reviewed. W.R. Lawrence Principal Engineer J Barrett Head of Community Services Background Papers: Location plan Executive 31 January 2002