EG-Wind Power Development Project Suez Gulf/Samalaut 500 kV OHTL & TA MINISTRY OF ELECTRICITY AND ENERGY EGYPTIAN ELECTRICITY HOLDING COMPANY EGYPTIAN ELECTRICITY TRANSMISSION COMPANY 3rd Update for the Procurement Plan For Suez Gulf/Samalaut 500 kV OHTL & Technical Assistance for Wind Power Commercialization Program Name of the Project: Egypt-Wind Power Development Project Project ID: P113416 Prepared by: Electric Power Systems Engineering Company (EPS) July 2012 3rd update for procurement time plan-Jul 12 Page 1 EG-Wind Power Development Project Suez Gulf/Samalaut 500 kV OHTL & TA UPDATE FOR PROCUREMENT TIME PLAN (JULY 2012) II.1 UPDATED TIME PLAN FOR SUEZ GULF/SAMALAUT 500 KV OHTL II.1.2.1 Completed Activities: Prequalification Stage Preparation of Bid Documents Bidding in 7 February 2012. No. Activity Continue Bidding Stage 1 Bidding Period 2 Evaluation, Envelop (A) Identify clarifications required from Bidders 3 EETC approval to obtain clarifications from Bidderd 4 Notify Bidders and obtain clarifications 5 Evaluate and issue envelope A evaluation report 6 EETC approval of the evaluation report 7 WB approval on the evaluation report 8 EETC issue evaluation report to bidders 9 EETC approval to open envelope B 10 WB no-objection to open envelope B 11 Opening of envelope B, evaluation 12 Final recommendations and Issue Bid's Evaluation and Report 13 WB Clearance 14 EETC Committee approval Contracting Stage 15 Contract Negotiation 16 WB Clearance 17 EETC Board approval 18 Intializing contract 19 Contract Award Construction Stage 20 Start Date 21 Complete Date (27 month) 3rd update for procurement time plan-Jul 12 Updated Time Plan- July 2012 From To 7 Feb 12 4 Jul 12 3 Jul 12 4 Aug 12 5 Aug 12 6 Sep12 23 Sep 12 22 Oct 12 12 Nov 12 12 Dec 12 24 Dec 12 1 Jan 13 9 Jan 13 4 Feb 13 5 Sep 12 20 Sep 12 21 Oct 12 11 Nov 11 Dec 12 23 Dec 12 30 Dec 12 8 Jan 13 3 Feb 13 17 Feb 13 18 Feb 13 18 Mar 13 17 Mar 13 2 Apr 13 3 Apr 13 5 May 13 6 May 13 12 May 13 13 May 13 26 May 13 27 May 13 2 June 13 3 June 13 4 June 13 4 Sept 2014 Page 2 EG-Wind Power Development Project Suez Gulf/Samalaut 500 kV OHTL & TA TA for the Development of Wind Power Program No. Selection of Consultant Inception Report Draft Request for Proposals (RFP) Activity Updated Time PlanJuly 2012 From To Stage I: Preparation and Issue of Bids 1 RFP for developers published 12 Dec 11 10 Sept 12 2 Question from bidders 10 Sept12 8 Oct12 3 Reply to bidders 8 Oct 12 29 Oct12 4 Pre-bid meeting 1 Nov 12 1 Nov 12 5 Consolidated RFP & PPA final 1 Nov 12 15 Nov 12 Stage II:Receive Bids, Evaluation, Contracting 6 Bids from developers due 13 Dec 12 13 Dec 12 7 Evaluation of bids finalized 16 Dec 12 17 Jan13 8 Selected bidder announced Jan13 9 Negotiation starts Feb13 10 Execution of agreements May 13 11 Financial closure achieved Nov 13 Construction Stage Construction time for the 250 MW wind power BOO project is estimated 18 month from signing the Agreements Planned Completion date: May 2015 3