EDMS Id: 1232723 Minutes of Beam Loss, Protection, Transfer Lines LIU-SPS Working Group Meeting Notes from the meeting held on 18 July 2012 Present: Lene Drøsdal, Lars Jensen, Malika Meddahi, Alessio Mereghetti, Öznur Mete, Helmut Vincke, Jörg Wenninger. Excused: Wolfgang Bartmann, Brennan Goddard, Verena Kain, Fausto Lorenzo Maciariello, Yannis Papaphilippou, Helga Timko. 1- Comments and Matters Arising – All The minutes of the previous meeting were approved. 2- SPS beam scraping: more on observations/ measurements and outcomes for the LIU operation – Lene Drøsdal The beam scraping test results were updated with the addition of new scans (slides). Lene reminded that during the LHC beam injection process, if the losses at the transfer line collimators are above the LHC-BLM thresholds, the beams are dumped. The high losses are mostly correlated to large tails of the SPS beams. In order to prevent these losses, high intensity LHC beams are scraped in the SPS before the injection, typically to 1-3%. Assuming that the SPS beam is stable, the scraper jaws should be set at a fixed position. However, as the beam position is varying in the SPS, the scraper jaw position has to be adjusted very regularly, and the operators cannot rely on a fixed scraping procedure. Therefore the investigation of the SPS beam stability is essential for the correct setting up of the beam scraper jaws as well as their important outcomes for the LIU operation. This stability study is in progress (Lene). Weekly beam scraping tests are performed to investigate the SPS beam stability and tails. During the scraping tests, the jaw in one plane was retracted to decouple the contribution from scraping in both planes, while the other jaw was moved stepwise towards the beam centre. The beam size and the centre can be extracted from the Gaussian fit of the measured tail distribution up to 30% of the beam. According to the tail scans over the period of May/June 2012, the beam centre has moved by ~0.7 mm. However, further investigations are necessary to determine how much the beam centre measurements are biased by the tail population. Performing beam scraping closer to the beam core –up to 60% of the distribution- reveals the presence of large tail population. Using these data, a better fit could be made. The beam size measurements were correlated with the wirescanner measurements. The tests showed that scraping only 30% of the beam leads to an overestimation of the beam size in case of large tail population. In this case, only full beam scans are sufficient to determine the beam centre and the size. More full scans will be done in the upcoming tests in order to better characterize the beam stability and sizes. Meanwhile an orbit stability crosscheck with the BPM readings will provide important information. The full beam scan method will be improved by analyzing the measured distribution as a double Gaussian, defining the beam core and the tails as different Gaussian distributions. 3- Update on Fluka studies – Alessio Mereghetti 1 Previously, the beam impact at 5σ onto the jaw of the TCDIH.NEW1 collimator in TI8 under Q20 optics was investigated. Despite the fact that the nominal LIU case results in the higher peak energy deposition (per impacting particle), it is the maximum LIU case which causes a higher temperature increase on the impacted collimator jaw. In the update, the difference in the temperature increase was correlated with the compensation between the beam size and the bunch population provided by different beam parameters (Nominal or Maximum LIU) (slides). From nominal to maximum LIU parameters the beam spot area increases by a factor of 2.5. This is consistent with the previous findings where increasing beam dimension compensates for the increasing bunch population and yields higher values of the temperature increase. A parametric study was performed and presented in order to further investigate the case. A slab of graphite with the same composition as the TCDIx collimators was taken into account. The peak energy deposition and the temperature increase were computed for the same simulation settings used for TCDIx collimators (the same scoring mesh). The nominal LIU parameters were considered as the reference case for the computations. A search was conducted in order to determine the bunch population resulting with the same temperature increase with the reference case as the beam dimension increases. As a result, for the relatively low dispersion values where the beam size is dominated by the emittance, the increase in the bunch population may lead to a higher increase in the temperature at the location of the peak energy deposition. 4- Status of the TCDI Ansys studies – Fausto Maciariello This contribution was postponed for the next meeting. 5- Update on Scraper Studies including Orbit Effects – Oznur Mete The LIU scraper system studies were updated taking into account orbit effects (slides). The resulting orbit deviations due to the misalignment of the SPS quadrupoles were calculated. Misalignment errors (Gaussian distribution 1σ = 200μm) were assigned randomly to all SPS quadrupoles. A thousand different seeds were used within the 6σ reach of the distribution. In the current design, in order to move the beam to the point of interception with the fixed scraper, a negative and a positive local orbit bump are used for H and V plane respectively. Consequently, a 3σ deviation of 19 mm and -16 mm, in the H and V planes were considered as the worst cases for further analysis. Additional local orbit bumps were used to correct the orbit in its worst case. The same knobs as used for the scraping bumps were utilized and required bumper strengths for the correction were calculated. The resulting orbit in the SPS was calculated for each plane, considering the components of 3σ deviated orbit, correction bumps at the location of the scrapers and the bumps to move the beam further onto the scrapers. The resulting case was analyzed in terms of the total required magnet strengths and the beam clearance. For the scenario where both a correction and the bump are involved in their worst cases the amount of possible scraping for H and V planes were found to be 5σ and 6σ of the beam, respectively. The horizontal bumpers in the LSS6 were found to be sufficiently strong to provide the required kicks. However, MPSH.62199 might constitute a bottleneck for the LIU operation due to the necessity of usage of 99% of its capacity for the worstcase correction and full scraping. The existing bumpers for the vertical plane are not strong enough to provide needed strengths. Therefore four new bumpers were proposed with the determined strengths to be utilized both for worst-case orbit correction and the full beam scraping plus a tolerance of 20%. The beam clearance of the horizontal plane is larger than 3σ when the errors and both bumps are switched on. However, the clearance is not sufficient for the vertical plane. It 2 was suggested to use in the simulation only half of the maximum errors (20 mm offset have been used, as 10 mn could be considered – in regular operation the orbit is corrected to about 3-4 mm). 6- A.O.B. None. 7- List of Actions Actions for SPS beam tests: Karel Cornelis, Lene Drøsdal, Verena Kain, Öznur Mete - Beam tests: Scraping the full beam away (low Intensity) –(to be concluded in two weeks) Beam loss location measurements during the ramp, with high and low intensity (Helga Timko) (to be scheduled) Actions depending on the discussions: Confirm the reliability of the acquisition from BPV.60508. Investigation of the scraper scans considering a model of double Gaussian distribution to better explain the tails. Crosscheck the orbit stability with the BPM readings. - Tests in the SPS on the cycle without beam: Timing of the bumpers (switch of the polarity) (to be finalized) Actions for FLUKA studies: Alessio Mereghetti. Short term: TED Dump Energy deposition / thermal load on TED dumps and upstream vacuum window, for the smallest beam size / highest beam intensity; considered dumps: TED.29133 and TED.87765. Medium-long term: TI2/TI8, Energy deposition on the LHC magnets due to full beam impact on a TCDIx collimator, close to LHC, for both Q20 and Q26: TI2: impact on the TCDIH.29050 collimator (i.e. the last collimator in the upgraded collimation scheme), with special attention to Q8 and Q7 (Left of Point 2). TI8: impact on the TCDIH.87904 collimator, with special attention to Q7 and Q6 (Right of Point 8), TI8: impact on the TCDIH.88121 and TCDIV.88123 collimators, with special attention to Q5 (Right of Point 8). Medium-long term: SPS Scrapers Energy deposition / thermal load on the scraper, and loss pattern around the SPS ring, for horizontal and vertical scraping, focusing on LSS6; priority to Q20 optics; tool: coupling of Fluka to SixTrack. Worthwhile to consider all the cases, in order to correctly identify the key parameters ruling the patterns to be found. Actions arising during the discussions The situation with the MSI magnets in the TI2 to be checked; Taking into consideration the LHC BLMs, when computing the effect on LHC magnets; For the Fluka and SixTrack coupling, a realistic beam profile to be obtained with the contribution from Yannis Papaphilippou. – Effect on the downstream elements induced by a full beam dump on the TED; Get in contact with O. Aberle for first feedbacks about results on the TED. (done) – Provide Oliver with the energy deposition maps. (done) Actions for studies on LIU scraper: Öznur Mete Simulations (ongoing): 3 Feasibility of the LIU scraping system, in the presence of the orbit effects: consider decreasing the misalignment error and repeat the same investigation. Search for the possibility of flat interception of the beam with the scraper instead of the current tilted case. Actions for dose rate estimations: Helmut Vincke. – Estimation of the doses in the LSS6 considering a possible future scraping activity in the area (when final location will be confirmed). Actions for ANSYS studies: Fausto Maciariello. – TCDI Ansys simulations. – Explore the possibility of a beam-based test to identify the reliability and robustness of the concerned graphite material. (Timing for the test and the required beam properties will be discussed with Malika Meddahi, Verena Kain, Oliver Aberle). Next meeting: Wednesday 1st August 2012 (TBC), from 10:30 to 11:30, in 865-1D17. The agenda will be communicated in due time. Öznur Mete 4