BI-ANNUAL PERFORMANCE EVALUATION REPORT FOR STERKFONTEIN-QWAQWA REGIONAL BULK WATER SUPPLY SCHEME FREE STATE CHIEF DIRECTORATE: BULK INFRASTRUCTURE PROGRAMME PERIOD: 1 APRIL 2014 TO 30 SEPTEMBER 2014 2 PROGRAMME MANAGEMENT: REGIONAL BULK INFRASTRUCTURE TABLE OF CONTENTS 1. Introduction 2. Background 2.1 2.2 2.3 2.4 3. Progress to date 3.1 3.2 3.4 3.6 4. Outcomes and outputs Beneficiaries and project results. Conclusions / Lessons Learned 5.1 5.2 6. Implementation of approved business plan Schedules of work and phasing of the activities 3.3 Risks taken and management thereof Capacities dedicated to the programme Key challenges within the project Project result and beneficiaries 4.1 4.2 5. Description of project Project History Project concept, design and plan Fund previously allocated to project Main successes and failures of the project to date Ownership and sustainability of infrastructure works Recommendations ANNEXURE A: Project Implementation Photos ANNEXURE B: List of villages expected to benefit from Phase 1 & 3 ANNEXURE C: Details of contracts awarded under Phase 1& 3 ANNEXURE D: Project schedule ANNEXURE E: Details of job opportunities SEPTEMBER 2014 3 PROGRAMME MANAGEMENT: REGIONAL BULK INFRASTRUCTURE 1. SEPTEMBER 2014 INTRODUCTION In terms of Section 10(7) of the Division of Revenue Act (DoRA), Act No 5 of 2012 as promulgated in Government Gazette No 36555 dated 10 June 2013, the transferring national officer must submit a quarterly performance report for Schedule 5, 6 and 7 programmes within 45 days after the end of each quarter to the National Treasury. The Regional Bulk Infrastructure Grant (RBIG) is a Schedule 6 indirect conditional grant for the benefit in kind of municipalities. The objective therefore is to provide a quarterly performance report of projects that are funded through the Regional Bulk Infrastructure Grant, in compliance with the Act. The objective of this evaluation was to determine whether the progress on the project is commensurate with the expenditure to date as well as to determine whether the project is still on course in terms of the original planning. This performance evaluation report covers the 1st and 2nd quarter for the 2014/15 fiscal year for the Sterkfontein-QwaQwa Regional Bulk Water Supply Scheme. It is one of the Regional Bulk Infrastructure Grant projects currently being implemented by the Maluti-a-Phofung Local Municipality in the Free State Province, with the Department of Water and Sanitation (DWS) as the funder. 2. BACKGROUND 2.1 Description of the project The primary focus of this project is the sustainable supply and augmentation of potable water to the greater Harrismith and QwaQwa areas including the rural communities of Diyatalawa and Mokgholokweng. 2.2 Project history Maluti-a-Phofung Local Municipality is part of the Thabo Mofutsanyana District Municipality in the Eastern Free State, located along the province’s eastern border with KwaZulu-Natal and Lesotho. In the late 1990's the Maluti-a-Phofung Local Municipality (M-a-P) experienced severe water supply problems in the QwaQwa region due to residential and commercial development and the associated increase in demand for potable water. The Municipality had to consider options to increase the supply to meet the future demand, both in the short and long terms. Before 1994 potable water was supplied to Tshiame and Industriqwa from a temporary water treatment facility at Sterkfontein Dam. After the incorporation of QwaQwa into the Free State Province, the old Sterkfontein pump station to Tshiame was decommissioned, and Tshiame and Industriqwa were incorporated into the Harrismith/Intabazwe potable water supply system from the Wilge River. 4 PROGRAMME MANAGEMENT: REGIONAL BULK INFRASTRUCTURE SEPTEMBER 2014 Over a 20 year time period, this has placed an extreme demand on the Wilge River catchment area and the Wilge Water Treatment Works (WTW) near Harrismith. In 2006 the feasibility of abstracting water for the QwaQwa region from the Sterkfontein Dam, and the re-introduction of supply to Tshiame and Industriqwa from Sterkfontein was investigated. The study recommended constructing a new water treatment facility at Sterkfontein Dam, to supply potable water to QwaQwa with a new pipeline in a southerly direction, and to re-commission the discontinued supply pipeline from Sterkfontein Dam to Tshiame in a westerly direction. During the construction stage of the Sterkfontein-QwaQwa Bulk Water Supply Scheme there was a subsequent growth and additional demand for a higher level of service in the towns of Kestell and Thlolong. The rural communities of Diyatalawa / Mokgholokweng presented a growth towards the agricultural sector resulting in an additional demand in potable water available for the greater community. 2.3 Project concept, design and plan The objective of the project is to ultimately supply of potable water to a population of 170,000 people (approximately 28 800 households). The targeted categories of consumers to be supplied with potable water are domestic water users throughout the Maluti-a-Phofung Local Municipality, and commercial and light industrial users and institutional users mainly within the towns of Tshiame, Mokgolokweng, and Kestell, Tholong and the Northern and Southern areas of the greater QwaQwa. The highest demand for potable water in the QwaQwa area is located in the northern residential areas of Phuthaditjhaba (the central business area), Bluegum Bosch, Mphatlatlatsane and Uniqwa. These areas are expected to be the focal point of both residential and commercial development for the next 20 to 30 years. These areas are the furthest away from the two water sources, the Fika Patso and the Metsi Matsho dams. Metsi Matsho Dam was built in 1972 when the area was a rural homeland area for the South Sotho people, and Fika Patso Dam was constructed in 1985 when QwaQwa was a still a self-governing national homeland in the previous government dispensation. The design of Fika Patso Dam was based on the assumption that the maximum population of the entire QwaQwa area would never exceed 375 000. Today, thirty years later, it is a fact that there are more than 100 000 residential stands in the QwaQwa area. During the design phase of Fika Patso Dam, two alternative dam sites, HaSethunya (Letshalemaduke) and Java, were identified and considered, however both these dam sites are now developed residential areas. At present the Fika Patso Water Treatment Works (WTW) (capacity 36,2 Mℓ/day) and the Metsi Matsho WTW (capacity 5,08 Mℓ/day) cannot meet the Average Annual Daily Demand (AADD) of 41,50 Mℓ/day of the QwaQwa region, and critical 5 PROGRAMME MANAGEMENT: REGIONAL BULK INFRASTRUCTURE SEPTEMBER 2014 water shortages have been experienced during dry winter months and drought periods. During the past few years the Fika Patso Dam level has often been below at less than 50% of its capacity, and water restrictions have had to be implemented on a regular basis. The supply area also includes Kestell and Thlolong, which are presently supplied from Fika Patso Dam via the Uniqwa reservoir. A pipeline also supplies the eastern Golden Gate area from the same reservoir. The Kestell and Golden Gate areas have therefore been included in the feasibility study to secure sustainable water to supply the western and northern supply regions of QwaQwa. The present water consumption in this area is 8,5 Mℓ/day, and is expected to increase to 11,5 Mℓ/day in the 20 year design horizon (2026). The only obvious and solvable solution is to implement a scheme from one of the biggest dams in the country Sterkfontein Dam that will ensure, reliable water source that is treated at a centralised plant, feeding water into a primary and secondary bulk distribution network that is capable of supplying strategically placed bulk reservoirs that supply a number of reticulation networks, so as to provide potable water to a large number of communities. Figure 1: Locality Map The initial feasibility study approved in August 2006 made provision for the implementation and adoption of the following elements namely: 6 PROGRAMME MANAGEMENT: REGIONAL BULK INFRASTRUCTURE SEPTEMBER 2014 Construction of a water treatment works at Sterkfontein Dam Construction of a pipeline from Sterkfontein Dam to the northern region of QwaQwa along Road P65, including pumping facilities Construction of reservoirs to ensure adequate storage capacity in the system Optimisation of the water supply systems from Metsi Matsho Dam and Fika Patso Dam to specific water supply zones in QwaQwa Re-instatement of the water supply to Tshiame, Kalanyoni and Industriqwa from Sterkfontein Dam by re-Commissioning and upgrading an existing pipeline Incorporation of Tshiame into the Sterkfontein-QwaQwa supply system will create capacity in the Greater Harrismith area supply system to accommodate future residential and industrial developments such as Schoonplaatz, the Harrismith Corridor Development, the Greenfields developments, etc. Table 1: Scheme components Item 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 Description Raw water pump station at Sterkfontein Dam Raw water rising main to Sterkfontein Dam WTW New Sterkfontein Dam WTW Rising main from Sterkfontein WTW to new Escol reservoir Escol high lift pump station New 3 Mℓ Escol reservoir New gravity pipeline from Escol reservoir to Seotlong reservoir 9 Mℓ Seotlong reservoir (2x3 Mℓ reservoirs at Uniqw ; 1x3 Mℓ reservoir Seotlong) New gravity pipeline from Seotlong to Bluegum Bosch reservoir New gravity pipeline from Seotlong reservoir to Uniqwa reservoir Tshiame high lift pump station New rising main from Sterkfontein WTW to Tshiame pipeline Re-commissioning of the old Tshiame pipeline New pipeline from Metsi Matsho Dam to Makwane WTW Upgrading of the Makwane WTW New pipeline from Makwane WTW to Matshekgeng reservoir 3 Mℓ Qholaqhwe reservoir The capital value of the project was then (2006) estimated at R130m. Raw water supply system Raw water will be abstracted from the Sterkfontein Dam in 2 ways: Siphon Construction of a siphon to supply raw water from the Sterkfontein Dam to the Sterkfontein WTW (the system includes the re-commissioning of a steel section of the redundant pipeline that used to supply Tshiame) 7 PROGRAMME MANAGEMENT: REGIONAL BULK INFRASTRUCTURE SEPTEMBER 2014 Raw water pump station No.1 Construction of a raw water pump station on the banks of the Nuwejaarspruit situated downstream of the main dam wall, abstracting water from the Nuwejaarspruit and pumping water to the Sterkfontein WTW With influence of the SIP18 and the rural development program there is a possibility to extend the abstraction system to supply raw water to the rural areas of Diyatalawa and Mokgolokweng, alternatively to supply treated water from the WTW. However the project still to be appraised. Water treatment facilities Sterkfontein WTW The construction of Phase 1 of the Sterkfontein WTW with a capacity of 10 Mℓ/day has been completed. This WTW supplies potable water to Tshiame, the northern areas of QwaQwa and the towns of Kestell and Thlolong. Phase 2 for an additional 10 Mℓ/day capacity to a total of 20 Mℓ/day is currently under planning. Makwane WTW The contract for the upgrading of the Makwane WTW from 5 Mℓ/day to 10 Mℓ/day has commenced. This plant will supply potable water to the residential areas of Makwane and Phahameng East. Diyatalawa facility Through the rural development programme a treatment facility with a capacity of 0,5 Mℓ/day treatment plant is being considered to supply potable water to 300 households at the Diyatalawa agricultural village. The project still has to be appraised. Bulk supply pipelines Tshiame supply pipeline Refurbishment of the existing rising main to supply water from Sterkfontein WTW to Tshiame has been completed. Escol pipeline Installation of a new rising main from Sterkfontein Dam to Escol reservoir has been completed. The Tshiame pumping system is presently being used to fill Escol reservoirs, but the installation of the new Escol pump sets is in process. QwaQwa pipeline Installation of a new gravity pipeline to transport potable water from Escol reservoir to the Seotlong, Bluegum Bosch and Uniqwa reservoirs 8 PROGRAMME MANAGEMENT: REGIONAL BULK INFRASTRUCTURE SEPTEMBER 2014 Makwane system pipelines Installation of a new gravity raw water pipeline from Metsi Matsho Dam to the Makwane WTW Installation of new potable transfer pipelines from the Makwane WTW to the Makwane reservoir and from the Makwane reservoir to Matshekgeng reservoir Diyatalawa and Mokgolokweng system pipelines Installation of new rising and gravity mains to supply raw water to the agricultural villages of Diyatalawa and Mokgolokweng, project still to be appraised Kestell/Thlolong pipeline Installation of new gravity pipeline to supply potable water to the towns of Kestell/Thlolong from the newly constructed Uniqwa reservoir, project still to be appraised Distribution pipelines Augmentation of the Fika Patso and Makwane distribution systems by installing interconnecting pipelines in the northern QwaQwa distribution networks. New bulk water storage facilities Escol reservoir Construction of a new 3 Mℓ concrete reservoir at Escol to provide a balancing storage facility for the gravity supply to the northern areas of QwaQwa and Kestell/Thlolong Seotlong and Uniqwa reservoirs Construction of three new 3 Mℓ concrete reservoirs in the northern region of QwaQwa to provide storage for the Bluegum Bosch, Uniqwa and Kestell/Thlolong residential areas Augmentation of bulk water to other supply areas which are currently receiving water from the Fika Patso system will also be accommodated through these facilities Diyatalawa and Mokgolokweng reservoirs Raw water storage facilities to store water for agricultural use, project still to be appraised 9 PROGRAMME MANAGEMENT: REGIONAL BULK INFRASTRUCTURE SEPTEMBER 2014 Figure 2: Layout 2.4 Start date and duration of the programme Construction of the first phases started in February 2009, it is estimated that the project will be completed by 31 March 2016, depending on the availability of funding. After the implementation of the initial scope of works as identified in 2006 commenced it was realised that the towns of Kestell and Thlolong as well as the rural areas of Diyatalawa and Mokgolokweng was in desperate need of additional potable water. This was mainly due to the higher level of sanitation required by the National bucket eradication program and development of the rural communities. 2.5 Funds previously allocated to project The initial total project estimate was R130m in 2006, escalation and additional bulk water supply tendencies (Kestell/Thlolong and Diyatalawa) caused a major increase in the funding required. The total project cost is estimated at R544m and the planned completion date of the project is March 2016, depending on the availability of funds and possible escalation. Table 1 below indicates the RBIG funding that was made available for the project during the past financial years, as well as the projected financial requirements: 10 PROGRAMME MANAGEMENT: REGIONAL BULK INFRASTRUCTURE SEPTEMBER 2014 Table 2: Funding to date and future financial requirements Financial year Approved budget amount Spent budget to date Financial requirements Amount 3. 2008-2011 (R) 2011/12 (R) 2012/13 (R) 2013/14 (R) 2014/15 (R) Total (R) 95,509,725 68,780,000 63,620,000 47,600,000 32,896,000 308,365,725 90,813,677 62,379,127 63,527,719 47,600,233 8,500,000 272,820,756 2014/15 (R) 2015/16 (R) 2016/17 (R) Additional funding required 2014/15/16 (R) 10,000,000 118,000,000 118,000,000 246 000 000 PROGRESS TO DATE The performance evaluation was conducted on 02 April 2014 by following persons (for the sanitation component): 3.1 Mr T Mohapi Mr P Ntili Mr M Manyama Mr A Sichilombe Mr M van Reenen RBIG Coordinator (National) Chief Director Free State Province (DWS) RBIG Coordinator (Province) Maluti-a-Phofung Local Municipality Miletus Consulting Implementation of the approved Business Plan The Business Plan has 4 phases, of which 3 are currently either being implemented and/or completed. All the geotechnical, environmental and land use agreements are in place or in a stage to be completed. In its capacity as Water Services Authority and Implementing Agent, the Maluti-aPhofung Local Municipality has its own Project Management Unit (PMU) that oversees the project. The Municipality also has a contractual agreement with the Water Services Provider (WSP) Maluti-a-Phofung Water (Pty) Ltd to assist with the overseeing of the implementation of the project, and who will be responsible for the future operation of the scheme. Table 3: Milestones Planned date for completion FS/IRS/Design/EIA Date FS/IRS/Design/EI A approved Product Name of organisation compiling/developing Feasibility Study Miletus Consulting Completed 2006 Implementation Readiness Study Miletus Consulting Completed 2008 Preliminary Design Miletus Consulting Completed 2009 EIA EM1/1(I)/06/204 Miletus Consulting Completed 2008 WUL Miletus Consulting Completed 2012 11 PROGRAMME MANAGEMENT: REGIONAL BULK INFRASTRUCTURE Planned date for completion FS/IRS/Design/EIA Date FS/IRS/Design/EI A approved Operation and Maluti-a-Phofung Water Maintenance Plan Available components complete on-going Financial Plan In progress Product 3.2 SEPTEMBER 2014 Name of organisation compiling/developing Funding Maluti-a-Phofung Municipality Design Miletus Consulting Design Kghato Consulting Local as In progress Sterkfontein QwaQwa Bulk Water Supply Scheme, completed for Phases 1, 2 and 3 of the scheme IRS for Kestell pipeline is completed Schedules of work and phasing of the activities The project was divided into the following phases for prioritisation of implementation goals: 3.2.1 Phase 1 This phase entails the construction of the Sterkfontein WTW (Phase 1), the construction of Escol reservoir and the installation of a rising main to Escol reservoir. The components constructed under this phase are completed and functional. Table 4: Projects implemented under Phase 1 Description Status Construction of the Civil & Structural Completed work (capacity 10 Mℓ/day) Installation of the Mechanical & Electrical Completed equipment for the WTW Construction of the Escol reservoir Completed (capacity 3,0 Mℓ) Rising main to Escol reservoir Total cost Completed Cost (R) 48,600,000 26,700,000 10,000,000 35,520,000 R120,820,000 12 PROGRAMME MANAGEMENT: REGIONAL BULK INFRASTRUCTURE SEPTEMBER 2014 3.2.2 Phase 2 This phase entails the installation of a gravity main from Escol Reservoir to storage facilities in the northern water supply region of QwaQwa and the provision of additional storage capacity within the northern water supply regions. Table 5: Projects implemented under Phase 2 Description Cost estimate (R) Status Construction of a 500Ø gravity main from Escol reservoir to Seotlong Completed (14 km to reservoir and connecting pipe work to be commissioned) Uniqwa and Bluegum Bosch reservoirs Provision of bulk storage capacity in the northern supply area of QwaQwa 70 % completed by constructing three 3 Mℓ concrete reservoirs 72,800,000 46,800,000 Total cost estimate R119,600,000 3.2.3 Phase 3 a) This phase entails the construction of new raw water abstraction facilities from the Sterkfontein Dam, outlet canal (Nuwejaarspruit), Dam and the installation of pumps to supply water to QwaQwa. It also includes the installation of a new gravity main from Metsi Matsho Dam to the Makwane WTW, the upgrading of the Makwane WTW from 5 Mℓ/day to 10 Mℓ/day, the partial replacement of the gravity main from Makwane reservoir to Matshekgeng reservoir. b) The installation Kestell/Thlolong. of a new gravity main from Uniqwa reservoirs to Table 6: Projects implemented under Phase 3 Description Status Cost estimate (R) a) Construction of a new raw water abstraction facility at Sterkfontein 95% completed Dam, permanent siphon and pumps to supply water to QwaQwa 25,430,000 a) Makwane Scheme 77,000,000 35% completed b) Upgrading of the Kestell/Thlolong Detail design Bulk Water Supply Total cost estimate 40,000,000 R147,430,000 3.2.4 Phase 4 Phase 4 entails the extension of Sterkfontein WTW, the upgrading and provision of the QwaQwa Rural Bulk Water Supply and the Internal QwaQwa Distribution Connections. 13 PROGRAMME MANAGEMENT: REGIONAL BULK INFRASTRUCTURE SEPTEMBER 2014 Table 7: Projects implemented under Phase 3 Description of element Status Phase 2 of the Sterkfontein WTW to a Detail design capacity of 20 Mℓ/day 57,000,000 QwaQwa rural bulk water supply Awaiting appraisal 50,000,000 Awaiting funding 50,000,000 QwaQwa internal connections distribution and Total cost estimate 3.3 Cost estimate (R) R157,000,000 Risks taken and management thereof As the Scheme comprises new infrastructure, no risks other than those normally encountered on a project of this size and nature have been taken. 3.4 Capacities dedicated to the programme The capacities dedicated to the programme are as follows: 3.5 Water Services Authority (WSA): Maluti-a-Phofung Local Municipality Water Services Provider (WSP): Maluti-a-Phofung Water (Pty) Ltd Funding: DWS Regional Bulk Infrastructure Grant (RBIG) Regulator: DWS Overall Programme and Project Management: Maluti-a-Phofung PMU and Maluti-a-Phofung Water Design, contract administration and construction monitoring: Miletus Consulting (Pty) Ltd. Key challenges within the project Key risk areas and challenges include the following: Funding for all phases of the Scheme (the current estimated capital shortfall is R246m excluding normal escalation) Private property owners delay the construction of the pipeline project from Escol to QwaQwa, final testing and commissioning of the pipeline are underway Cash flow problems of the contractor appointed for the construction of the Northern Bulk Storage emanating termination of the contract and the appointment of a sub-contractor to finish the project Annual RBIG allocations to the project should be increased to ensure continuity of the project and project phasing, especially on the Makwane project to ensure continuity of the system Implementation of the Makwane scheme have commenced in the previous financial year, implementation of the project started with the installation of the new raw water gravity main from Metsi Matso Dam to Makwane WTW, this project will be completed in September 2014. The upgrading of the Makwane 14 PROGRAMME MANAGEMENT: REGIONAL BULK INFRASTRUCTURE SEPTEMBER 2014 WTW from 5 Mℓ/day to 10 Mℓ/day have also been implemented, funding limitations will however force this project to a halt in December 2014 The NUMSA strike had a huge effect on the supply of steel to the industry and hugely affected production in the construction industry (4-6 weeks) Network losses within the water reticulation and beyond municipal control (inside residential sites) should be addressed (as much as 30%) 4. PROJECT RESULTS AND BENEFICIARIES 4.1 Outcomes and outputs At present the expected outcomes and outputs are on track for the phase under construction. 4.2 Beneficiaries and project results As previously stated, the purpose of the project is to ultimately augment and supply additional water to the Northern and Southern areas of QwaQwa, including the towns Kestell/Thlolong, the residential area of Tshiame and the rural agricultural areas of Diyatalawa and Mokgolokweng. 4.3 Jobs created Job creation details are summarized in Annexure E. 5. CONCLUSION / LESSONS LEARNED The communities are eagerly awaiting the completion of the project as it will alleviate the water shortages throughout the Maluti-a-Phofung services area. 5.1 Main successes and failures of the project to date 5.2 Augmentation and commissioning of the old Tshiame water supply scheme from the Sterkfontein Dam scheme brought relief for residents Gaining early permission to access private property is essential and should be done well in advance to prevent unnecessary delays Early Eskom applications for electrical connections at Sterkfontein WTW have insured timeous completion and commissioning of the project Lessons learned, ownership and sustainability of the infrastructure Obtaining a legal opinion before a contractor is appointed may prevent unnecessary legal steps and further project delays. Maluti-a-Phofung Local Municipality will take ownership of the infrastructure and the daily operations of the infrastructure will be incorporated under the hospice of Maluti-a-Phofung Water (Pty) Ltd the service provider to ensure sustainability. Skills transfer was part of the commissioning stage of the Sterkfontein WTW, consultants and service providers are continuously involved in this process. 15 PROGRAMME MANAGEMENT: REGIONAL BULK INFRASTRUCTURE 6. SEPTEMBER 2014 RECOMMENDATIONS It is recommended that: All stakeholders assist in securing adequate funding to complete the total project. A water awareness campaign should be incorporated as part of the scheme to alert the community regarding water losses and scarcity. Diyatalawa and Mokgolokweng must be prioritised as Agricultural growing communities as classified under SIP18. Implementation of the bulk distribution networks is essential to optimise and incorporate the Sterkfontein and Makwane Schemes. 16 PROGRAMME MANAGEMENT: REGIONAL BULK INFRASTRUCTURE ANNEXURE A:PROJECT IMPLEMENTATION PHOTOS STERKFONTEIN WTW: PHASE 1 ESCOL RESERVOIR: PHASE 1 SEPTEMBER 2014 17 PROGRAMME MANAGEMENT: REGIONAL BULK INFRASTRUCTURE QWAQWA PIPELINES: PHASE 2 UNIQWA RESERVOIRS: PHASE 2 SEPTEMBER 2014 18 PROGRAMME MANAGEMENT: REGIONAL BULK INFRASTRUCTURE RAW WATER PUMPSTATION: PHASE 3 RAW WATER SIPHON: PHASE 3 SEPTEMBER 2014 19 PROGRAMME MANAGEMENT: REGIONAL BULK INFRASTRUCTURE SEPTEMBER 2014 ESCOL HIGH LIFT PUMPS AND PIPELINE CONNECTION: PHASE 3 MAKWANE RAW WATER PIPELINE AND CLEAR WATER TANK: PHASE 3 20 PROGRAMME MANAGEMENT: REGIONAL BULK INFRASTRUCTURE SEPTEMBER 2014 ANNEXURE B: LIST OF SCHEME BENEFICIARIES Number of stands Number of beneficiaries per stand Total number of beneficiaries TSHIAME Tshiame A,B,C&D 5 107 6 30 642 Mokgholokweng 1 500 6 9 000 52 6 312 QWAQWA Uniqwa Ha-Rankopane Mphatlatlatsane Phutaditjhaba Phamong Kestell A&B Thlolong De Bult Bluegum Bosch Total 3 074 4 068 2 305 730 989 432 1 573 5 061 6 054 30 945 6 6 6 6 6 6 6 6 6 18444 24408 13830 4380 5934 2592 9438 30366 36324 18 5670 MAKWANE Makwane Matshekgeng Lusaka Tebang Pereng Qholoqhwe Total 2 808 985 3 646 1 886 997 395 10 717 6 6 6 6 6 6 16 848 5 910 21 876 11 316 5 982 2 370 64 302 Village Diyatalawa 21 PROGRAMME MANAGEMENT: REGIONAL BULK INFRASTRUCTURE SEPTEMBER 2014 ANNEXURE C: DETAILS OF CONTRACTS AWARDED UNDER PHASES 1, 2, &3 CONTRACT NO. AND NAME CONTRACT VALUE (R) CONTRACT AWARD / STARTING DATE PLANNED COMPLETION DATE ACTUAL COMPLETION DATE Inzuzo, Hentiq and Umzinyathi JV 25,944,074 Feb 2009 Nov 2012 Nov 2012 25,064,353 100 Nexor 350CCPhello Construction JV 39,186,785 Feb 2009 Nov 2012 Aug 2013 39,066,342 100 Metsi projects CC 22,928,628 Sept 2010 Nov 2012 Jun 2013 22,928,628 100 Tats Electrical (Pty) Ltd 7,909,850 Feb 2009 May 2012 Jun 2012 7,909,850 100 Ruwacon (Pty)Ltd 61,999,582 Jan 2011 Apr 2012 Aug 2013 61,987,910 100 CONTRACTOR EXPENDITURE TO DATE % COMPLETION (R) SCM/BID030/2008 Contract 1.1 : Installation of pipelines SCM/BID019/2008 Contract 1.2a : Sterkfontein WTW (Civil, Structural and associated works) SCM/BID020/2008 Contract 1.2b : Sterkfontein WTW (Mechanical and Electrical installation) SCM/BID031/2008 Contract 1.3 : Construction of Escol reservoir SCM/BID03/2010/11 Contract 2.1 : Construction of Pipelines 22 PROGRAMME MANAGEMENT: REGIONAL BULK INFRASTRUCTURE CONTRACT NO. AND NAME SCM/BID32/2010/11 Contract 2.2 : Northern Regional Bulk Storage SEPTEMBER 2014 CONTRACT VALUE (R) CONTRACT AWARD / STARTING DATE PLANNED COMPLETION DATE Robs Investments Holdings (Pty) Ltd 38,136,650 Oct 2011 Nov 2014 27,050,289 60 Miletus Consulting 25,430,000 Jun 2012 March 2014 24,820,000 95 Miletus Consulting 77,000,000 Jun 2012 March 2016 27,518,423 35 CONTRACTOR ACTUAL COMPLETION DATE EXPENDITURE TO DATE % COMPLETION (R) SCM/FIN02/2011/12 Contract 3.1 : Raw Water Abstraction SCM/FIN03/2011/12 Contract 3.2 : Metsi Matsho Water Supply Notes: Retention money withheld has been included as expenditure All amounts include 14% VAT 23 PROGRAMME MANAGEMENT: REGIONAL BULK INFRASTRUCTURE ANNEXURE D: PROJECT SCHEDULE SEPTEMBER 2014 24 PROGRAMME MANAGEMENT: REGIONAL BULK INFRASTRUCTURE SEPTEMBER 2014 Summary of Decent Job Opportunities (1 April 2014 – 31 August 2014) : Totals Decent job opportunities for people employed at various occupational levels : Decent = Full time for at least 5 months or more Decent Job Opportunities for the 2014/15 financial year Adult Men No Adult Women Person Days Actual cost on job opportuni ties No Person Days Youth Men Actual cost on job opportunit ies No Person Days Youth Women Actual cost on job opportu nities No Disabled Person Days Actual cost on job opportu nities TOTAL No Person Days Actual cost on job opportu nities No Perso n Days Actual cost on job opportu nities Clerical Ongoing 1 115 19 963 1 116 12 083 1 115 18 682 0 0 0 0 0 0 2 346 50 727 Clerical New 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 25 2 577 566 692 3 314 34 305 34 2 691 431 025 4 2 050 60 131 0 0 0 66 7 632 Labourers New 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 1 092 153 0 Managerial Ongoing 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 Managerial New 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 Semi-Skilled Ongoing 1 105 9 923 0 0 0 1 105 15 734 0 0 0 0 0 0 2 210 25 657 Semi-Skilled New 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 15 830 165 096 0 0 0 8 493 66 461 0 0 0 0 0 0 23 1 323 231 557 Skilled New 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 Supervisor Ongoing 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 Supervisor New 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 Other Ongoing 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 Other New 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 11 907 918 4 430 46 388 29 2 032 328 900 2 194 21 195 0 0 0 71 5 096 921 065 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 22 4 415 479 030 Labourers Ongoing Skilled Ongoing TOTAL Ongoing TOTAL New