Totals - AIO IWRM

advertisement
TERMS OF REFERENCE
for
Mid-Term Review of the UNEP/UNDP/GEF project:
Implementing Integrated Water Resource and Wastewater Management in Atlantic and
Indian Ocean SIDS
I. PROJECT BACKGROUND AND OVERVIEW
1.
Project General Information
Project summary
GEF SEC Project ID:
2706
Sub-programme:
n/a
UNEP approval date:
GEF OP #:
October 2010
GEF-4 IW SP3
Project Type:
Expected
Accomplishment(s):
Full Scale Size
Focal Area(s):
International Waters
IW SP3:Balancing over use and
conflicting uses of water
resources in transboundary
surface and groundwater
basins
UNEP: 20 May 2012
UNDP: UNDP Project became
effective on 17 Oct 2012, when
three out of six Government
signatures were secured.
N/A
GEF CEO Endorsement
date:
28 December 2010
GEF Strategic
Priority/Objective:
Expected Start Date:
January 2011
Actual start date:
Planned completion date:
UNEP: May 2016
UNDP: October 2016
Actual completion
date:
Planned project budget at
approval:
US$ 49,707,535
GEF Allocation:
PDF GEF cost:
Expected FSP co-financing:
UNDP: US$ 4,500,000
UNEP: US$ 5,200,000
Total: US$ 9,700,000
US$290,000
$39,422,535
First Disbursement:
UNEP: 23 July 2012
UNDP: July 2012
Date of last Steering
Committee meeting:
2 July 2014
Mid-term review/
evaluation (planned date):
December 2014
PDF co-financing:
US$295,000
Date of financial
closure:
UNEP: 31 December 2016
UNDP: within 12 month after
operational closure
(Operational closure: 17 Oct
2016)
Mid-term review/
evaluation (actual
date):
August – October 2015
2.
Project Rationale
The geographic scope of this regional project covers the Indian and Atlantic Oceans, focusing on six Small Island
Developing States (SIDS); two (2) are in the Atlantic Ocean (Cabo Verde and São Tomé & Principe) and four are
located in the Indian Ocean (Comoros, Maldives, Mauritius and Seychelles). The Small Island Developing States
(SIDS) share geographically similar features and fundamentally similar problems with regard to water management
and conservation, land-based sources of pollution, and issues of environmental flow relating to habitat and
ecosystem protection. In acknowledgment of the vulnerability and the particular needs of SIDS, the project on
implementing integrated water resources and wastewater management in Atlantic and Indian Oceans SIDS (AIO
IWRM) was formulated to address sustainable water management in the six participating SIDS.
The project was designed to contribute to sustainable development in the Atlantic and Indian Oceans Small Island
Developing States (SIDS) through improvements in water resource and environmental management. The project is
consistent with the GEF IV strategic objective for International Waters: (a) ‘to play a catalytic role in addressing
trans-boundary water concerns by assisting countries to utilize the full range of technical assistance, economic,
financial, regulatory and institutional reforms that are needed’, through supporting and building on existing
political commitments and through promoting sustainable water use and improved water management now,
making it easier to address the challenges of the future as climatic variability and change affect water resources
further.
The project will specifically contribute to achievement of the MDG targets for water supply and sanitation as
spelled out in the national sustainable development strategies and specifically the MDG target of setting processes
in motion towards National IWRM Plans. More specifically the project is delivering outcomes under GEF IV
Strategic Program III (SP-3) through working with national governments and communities to address their needs
for safe drinking water and other socio-economic benefits of sustainable and safe water resources, including
balancing environmental requirements with livelihood needs.
3. Project Objectives and Components
The Goal of the project is to ‘contribute to sustainable development in the Indian and Atlantic Ocean Small Island
Developing States through improvements in natural resource and environmental management’. The overall
Objective is to ‘accelerate progress on WSSD targets and IWRM and WUE plans and water supply and sanitation
MDGs for the protection and utilization of groundwater and surface water in the participating countries’. This will
be based on best practices and demonstrations of IWRM approaches.
The project will deliver across a range of MDG targets using IWRM approaches (but with particular focus on MDG 7:
Ensure Environmental sustainability) as the wider development entry point, and will help countries utilize the full
range of technical, economic, financial, regulatory, and institutional measures needed to operationalize
sustainable development strategies for waters and their drainage basins (both surface and ground water).
The project consists of five components:
Component C1 focusing on country-driven and designed demonstration activities focusing on sustainable water
management to utilize Ridge to Reef IWRM approaches to bring significant environmental stress reduction benefits.
Demonstration projects will act as catalysts for replication and scaling-up approaches to improve national water
resources management, and regionally to support the Atlantic and Indian Ocean SIDS in reducing land based
pollutants from entering the ocean.
Component C2 aims to develop an IWRM and WUE Regional and National Indicator Framework for improved
national and regional sustainable development using water as an entry point. It seeks to ensure countries can
monitor IWRM implementation at national level based on improved collection of gender disaggregated data and
indicator feedback and action.
Component C3 focus on Policy, Legislative, and Institutional Reform for IWRM and WUE through supporting
institutional change and re-alignment to enact National IWRM Plans and WUE strategies, including appropriate
financing mechanisms and supporting and building further political will to endorse IWRM policies and plans.
Component C4 provides a Capacity Building and Sustainability Program for IWRM and WUE, including Knowledge
Exchange and Learning and Replication.
Component C5 is the Project Management responsible for the efficient implementation of the project
Each of the components as related outcome and outputs presented in Table 1 below;
Table 1: Expected outcomes and outputs from log frame
Outcomes
Sub-outcomes / Outputs
IWRM and WUE demonstrated
through targeted on ground
projects interventions.
1.1 Outcome 1.1 (Cabo Verde):
Protection
of
groundwater
resources, stabilization of coastal
terrains and promotion of
productive activities at coastal
areas through the integrated
planning and management of
wastewater collection, treatment
and reuse demonstrated in
Tarrafal in the Island of Santiago.
1.1.1
1.2 Outcome
1.2
(Comoros):
Improved
water
source
protection
through
IWRM
Planning and management in
Mutsamudu on the island of
Anjouan.
1.2.1
1.2.2
1.3 Outcome
1.3
(Maldives):
Protection of the freshwater lens
of
Thoddoo
Island
from
salinization and agro-chemical
pollution, with improved drought
season aquifer yield.
1.3.1
1.1.2
1.1.3
1.2.3
1.2.4
1.2.5
1.3.2
1.3.3
1.3.4
1.4 Outcome 1.4 (Mauritius): The
protection
and
sustainable
utilization of the Northern
Aquifer
of
Mauritius
demonstrated
through
the
1.4.1
1.4.2
Improved wastewater management systems, resulting in more
treated wastewater as an alternative water source and reduced
untreated wastewater discharge to the ground;
Increased treated wastewater used for irrigation, resulting in
less groundwater abstraction and increased crop productivity
by the communities;
Awareness raised on water use efficiency for domestic use as
well as tourism sector
Water resource assessment and monitoring systems
Established Water quality improved through solid waste
management and water source protection
Reservoir protected from the effects of small-scale farming
practices
Watershed management plan for Mutsamudu developed
Awareness raised on IWRM and catchment management and
its contribution to MDGs and gender empowerment
Sustainable and innovative groundwater extraction system
(infiltration gallery system) established and operational;
Agricultural practices improved, reducing groundwater
contamination;
Sustainable groundwater extraction systems accepted
nationally as relevant to island potable water supply and
planned for replication nationally;
Groundwater quality monitoring system established and
operational by gender balanced trained locals.
Water Resources Assessment conducted to determine and
monitor the safe yield and water quality of the aquifer;
Improved water quality protection of the groundwater and
lagoon water quality through improved wastewater treatment
and management systems;
integrated
planning
and
management of wastewater
collection, treatment and reuse.
1.4.3
1.4.4
1.5 Outcome 1.5 (São Tomé &
Principe): Integrated River basin
management plan for the Rio
Provaz Basin developed to enable
equitable
water
resources
allocation
and
protection,
contributing
to
sustainable
economic development, public
health and
environmental
protection.
1.5.1
1.5.2
1.5.3
1.5.4
1.6 Outcome
(Seychelles):
Protection of a coastal gravel
aquifer through integrated land
and
water
management
measures
(water
demand
management, land use, flood
management) demonstrated in
the island of La Digue.
2. IWRM and WUE indicators,
baselines, targets and monitoring
protocols discussed, agreed and
adopted
into
long-term
monitoring programs at national
and ‘regional’ levels
3. SIDS employ new plans, policy
tools
and
approaches
in
implementing
IWRM
commitments
1.6.1
1.6.2
Reduced stress on the aquifer through improved water demand
management and dissemination of best practices, aiming for
replication at the national level and beyond;
Capacity strengthened and awareness raised among
government, private sector and civil society for aquifer
protection against over-extraction and contamination with
special focus on climate change and gender empowerment
Quality and quantity of water Resources in the Rio Provaz basin
assessed;
Institutional capacity (cross-sectoral coordination)
strengthened and decentralized (municipal) water management
fostered through the development and implementation of
Basin Water Resources Allocation and Protection Strategy;
Water pollution reduced through improved wastewater
treatment systems (piloting ECOSAN wastewater
management), solid waste collection and disposal and
residential sanitation at the poor communities;
Awareness raised of IWRM at the basin level to strengthen
community participation in IWRM and to ensure sustainability
Water abstraction reduced through water demand
management measures, including rainwater harvesting,
household water tanks to reduce peak water demand,
wastewater reuse, improved metering and tariff reform;
Groundwater availability and quality improved through
improved septic tank management, wastewater collection and
treatment, prevention of seawater intrusion, solid waste
collection, and groundwater recharge.
2.1 Inventories of national monitoring practices related to IWRM, WUE
and environment
2.2 Indicator Framework including process, stress reduction,
environmental and socio-economic status, WUE, catalytic,
governance and cross-cutting indicators; gender disaggregated data
and participatory monitoring protocols agreed nationally and
‘regionally’
2.3 Baselines and Targets established at national and ‘regional’ levels
for Indicator Framework
2.4 Indicator framework and monitoring protocols tested and in use at
demonstration sites, national and ‘regional’ levels
2.5 Institutional capacity for monitoring strengthened
3.1 SIDS IWRM Diagnostic Analyses strengthened and IWRM Road maps
developed
3.2 National IWRM plans and WUE strategies developed and endorsed
with attention to sustainability, financial mechanisms and
replication strategies for demo projects
3.3 Functioning IWRM Partnerships within SIDS at national and other
levels established or strengthened (e.g. national inter-sectoral
committees, apex bodies, catchment committees, water user
4. Strengthened capacity allows
stakeholders and institutions in
SIDS to fulfill their role in local,
national and regional IWRM
processes and exchange best
practices
5. Project implemented
effectively and efficiently to the
satisfaction of partners
4.
groups as relevant) and among SIDS
4.1 Awareness created on roles and responsibilities of IWRM across
governments, civil society, education systems and private sector;
4.2 Targeted trainings and communications platform strengthen
stakeholder groups’ capacity to fulfil mandate in IWRM, including
apex bodies and water champions (men and women)
4.3 Twinning or exchange programmes promote learning and transfer
of experience in support of IWRM implementation
4.4 Replicable practices from demonstration projects and national
IWRM processes identified and promoted
5.1 Capable human resources and efficient systems support project
implementation
5.2 Monitoring, consultation and advisory mechanisms support project
implementation
Executing Arrangements
The project is implemented by UNEP and UNDP and executed by UNOPS, involving two business units of UNOPS.
UNDP is implementing targeted IWRM demonstration projects in all six countries under Component 1 (C1) through
UNOPS Water and Energy Cluster (UNOPS WEC) based in Copenhagen, Denmark. UNEP is implementing the IWRM
Regional and National Indicator Framework, Component 2 (C2), Policy, legislations and water sector reforms,
Component 3 (C3), and regional and National awareness raising, capacity building and networking, Component 4
(C4). The UNEP components are implemented through UNOPS East Africa Hub (UNOPS EAH), formerly Kenya
Operational Hub (KEOH) based in Nairobi, Kenya. Both UNEP and UNDP are jointly responsible for the Project
Management and Coordination, Component 5 (C5). Within UNEP, the Division of Environmental Policy
Implementation (DEPI) is responsible for project implementation under the direct oversight of the UNEP/GEF Task
Manager, Africa. Within UNDP, its Mauritius Country Office has delegated Authority to oversee the
implementation of UNDP component with technical and oversight support provided from the Regional Technical
Advisor for Water and Ocean Governance. The GEF Implementing Agencies, that is UNEP and UNDP, provide
project oversight to ensure that the project meets project goals. Executing Agency, that is UNOPS, ensures the
project will be implemented within the available resources and assumes the over fiducial responsibilities for the
project budget and expenditure.
The Regional Project Coordination Unit (RPCU) is constituted by UNOPS (both the East Africa Hub (EAH) and Water
and Energy Cluster (WEC)). UNOPS, through the Regional Project Coordination Unit (RPCU), provides day to day
operational support and management. The Regional Project Coordination Unit (RPCU) is based in Nairobi, Kenya,
hosted by the UNEP Division of Policy Implementation (DEPI).
The Regional Project Steering Committee (RPSC) provides strategic guidance and direction to the project. It
comprises one representative (the project’s national focal point) from each of the six participating countries and
representatives from UNEP, UNDP and UNOPS. The RPSC reviews progress, provides strategic guidance to the
Project and RPCU, and approves annual work plans and budget.
The diagram below is the Project chart illustrating the project’s structures and arrangements.
1 Regional Steering Committee
COUNTRIES
UNEP
UNDP
National IWRM Focal Points
UNOPS/EAH
UNOPS/WEC
Regional Project
Coordination Unit
Regional Technical
Assistance
Governance Coordination
(Assistant to the IWRM FP)
Demonstration Project
Technical Assistance
Demonstration Project
Manager
National Steering Committee
6 x Country Governance Structure
National IWRM
Governance Activities
National IWRM
Demonstration Project
National Integrated Water Resources Management Stakeholders
Fig. 1: Project Organizational Chart
5.
Project Cost and Financing.
The total project cost at the time of approval is US$ 49,122,535 with GEF allocation being US$ 9,700,000 (20%) and
co-financing US$ 39,422,535 (80%). Table 2 below shows the breakdown per component and agency at CEO
endorsement.
Table 2: Approved Project Cost per Component and Funding Source
Component
GEF Allocation
(US$)
Co-financing
(US$)
4,320,000
(11%)
33,872,881
(89%)
38,192,881
C2 - IWRM and WUE indicators, baselines, targets and
monitoring protocols discussed, agreed and adopted into
long-term monitoring programs at national and ‘regional’
levels (Implemented by UNEP/UNOPS KEOH)
657,300
(59%)
450,000
(41%)
1,107,300
C3 - SIDS employ new plans, policy tools and approaches
in implementing IWRM commitments
(Implemented by UNEP/UNOPS EAH)
1,556,300
(75%)
530,000
(25%)
2,086,300
C1 - IWRM and WUE demonstrated through targeted on
ground projects interventions (Implemented by
UNDP/UNOPS WEC)
Total (US$)
C4 - Strengthened capacity allows stakeholders and
institutions in SIDS to fulfill their role in local, national and
regional IWRM processes and exchange best practices
(Implemented by UNEP/UNOPS EAH)
C5 - Project implemented effectively and efficiently to the
satisfaction of partners
(Implemented by UNEP/UNOPS EAH & UNDP/UNOPS
WEC)
Total
6.
2,206,400
(82%)
483,500
(18%)
2,689,900
UNEP/EAH:
780,000
UNDP/WEC:
180,000
(19%)
9,700,000
(20%)
4,086,154
(81%)
5,046,154
39,422,535
(80%)
49,122,535
Implementation Issues
The project logframe for the overall project has not been revised since the start of the project, also no revisions of
the budget appeared necessary. The logframe for each demonstration project under Component 1 has been
reviewed and necessary adjustments have been proposed and approved by the project steering committee.
The project duration is 48 months, starting on 16 May 2012 (UNEP) and Oct 2012 (UNDP), is expected to be
completed by May 2016 (UNEP) and Oct 2016 (UNDP), respectively. The project start for UNEP-implemented
components was delayed due to changes in the Executing Agency -EA- arrangements (originally UNEP DEPI Marine
and Coastal Division was to be the projects EA.) The UNDP-implemented pilot demonstration activities are
scheduled to close in June 2016 with the Component 1 operational closure scheduled in Oct 2016. Considering
some delays in project delivery in Component 2-4, a review of the project implementation plan for those
Components has taken place at the beginning of 2015 by the current UNEP Task Master with proposals for an
accelerated development of outputs of the UNEP components. Challenges faced to date in the implementation of
components 2 to 4 of this project have resulted in less than 20% of delivery of outputs and considerable loss of
momentum. Besides logistical difficulties (frequent changes of Project managers, incomplete hiring processes of incountry IWRM experts to assist focal points nationally and a change in UNEP Task Manager), there has been a
general delay in the implementation process. Risks and the associated mitigation plan presented in the PIR2014 is
shown in the Table 3 below.
Table 3: The PIR for 2014 contained the following risk mitigation plan:
TOP RISK MITIGATION PLAN
Rank – importance of risk
Risk Statement – potential problem (condition and consequence)
Action to take – action planned/taken to handle the risk
Who – person(s) responsible for the action
Date – date by which action needs to be or was completed
Rank
Risk Statement
Action to Take
Condition
Consequence
1
Delayed recruitment Components 2 and Post
VAs,
where
of GCAs
3 seriously delayed necessary,
for
recruitment
2
Delayed recruitment Various
project Combine VA with webof Communication Component
editor responsibilities
expert
delayed
Who
Date
PM
Mid
2014
September
PM
Mid
2014
September
TOP RISK MITIGATION PLAN
Rank – importance of risk
Risk Statement – potential problem (condition and consequence)
Action to take – action planned/taken to handle the risk
Who – person(s) responsible for the action
Date – date by which action needs to be or was completed
3
Delayed training of Indicator
Recruitment
of PM
Q4
GCAs
framework
consultants
or
delayed, as well as institution to conduct
governance-related training
activities
FY13 rating FY14 rating
Comments/narrative justifying the current FY rating and any changes (positive
or negative) in the rating since the previous reporting period
Medium
Medium
The delays in recruitment and the extended inception period have meant that
there are risks associated with delivery within the expected timeframe. Efforts
must be taken to redress the delays.
The Risk 1 shown in the table has been mitigated at the time of preparation of the current document. One GCA
was recruited in São Tomé and at a later stage the title of the position has been changed into IPSA, IWRM Policy
Support Analyst. Four out of the remaining countries have advertised the position as per April 30th, 2015
II. TERMS OF REFERENCE FOR THE EVALUATION
1.
Objective and Scope of the Evaluation
In line with the implementing agencies guideline (UNEP Evaluation Policy 1 and the UNEP Programme Manual2, and
UNDP Midterm review guidelines3) the Mid-term Review of the Project “Implementing Integrated Water Resources
and Wastewater Management in Atlantic and Indian Ocean SIDS” is undertaken approximately half way through
project implementation to analyze whether the project is on-track, what problems or challenges the project is
encountering, and what corrective actions are required. The MTR will assess project performance to date (in terms
of relevance, effectiveness and efficiency), and determine the likelihood of the project achieving its intended
outcomes and impacts, including their sustainability. The evaluation has two primary purposes: (i) to provide
evidence of results to meet accountability requirements, and (ii) to promote operational improvement, learning
and knowledge sharing through results and lessons learned among UNEP, UNDP, UNOPS and Government partners.
Therefore, the evaluation will identify lessons of operational relevance for project implementation and future
project formulation.
It will focus on the following sets of key questions, based on the project’s intended outcomes, which may be
expanded by the consultants as deemed appropriate:
a.
Quality of project design,
b.
Achievement of main objectives and effectiveness of the programme.
1 http://www.unep.org/eou/StandardsPolicyandPractices/UNEPEvaluationPolicy/tabid/3050/language/en-US/Default.aspx
2 http://www.unep.org/QAS/Documents/UNEP_Programme_Manual_May_2013.pdf
3 http://web.undp.org/evaluation/documents/guidance/GEF/mid-term/Guidance_Midterm%20Review%20_EN_2014.pdf
c.
Efficiency of the implementation
d.
Sustainability of the effects
e.
Key cross-cutting issues
f.
Co-ordination, complementarity and coherence
2.
Overall Approach and Methods
The Mid-term Terminal Evaluation of the Project will be conducted by external and independent consultants to be
recruited and contracted by UNOPS. The MTR will be an in-depth review/evaluation using a participatory approach
whereby key stakeholders are kept informed and consulted throughout the evaluation process. Both quantitative
and qualitative evaluation methods will be used to determine project achievements against the expected outputs,
outcomes and impacts. It is highly recommended that the consultant(s) maintains close communication with the
project team and promotes information exchange throughout the evaluation process in order to increase their
(and other stakeholder) ownership of the review findings.
The MTR must provide evidence based information that is credible, reliable and useful. The MTR will review all
relevant sources of information including documents prepared during the preparation phase (e.g. PIF, the Project
Document, project reports including quarterly progress reports, Annual Project Review/PIRs, project budget
revisions, lesson learned reports), national strategic and legal documents, and any other materials that the
evaluator considers useful for this evidence-based review). The evaluator will review the baseline GEF focal area
Tracking Tool submitted to the GEF at CEO endorsement, and the midterm GEF focal area Tracking Tool which will
be completed before the MTR field mission begins.
The evaluator is expected to follow a collaborative and participatory approach ensuring close engagement with the
implementing and executing agencies, Project Team, government counterparts (including the GEF Operational
Focal Point). Stakeholder involvement should include interviews with stakeholders.
The findings of the evaluation will be based on the following:
(a) A desk review (see also Annex 4) of:
1. Relevant background documentation, inter alia the Diagnostic Analysis report, the Hotspot Analysis
reports;
2. Project design documents (including minutes of the project design review meeting at approval); Annual
3.
4.
5.
6.
7.
8.
Work Plans and Budgets or equivalent, revisions to the project (Project Document Supplement), the
logical framework and its budget;
Engagement Agreement documents, Partner institutions capacity assessment reports, Project
Cooperation Agreements (with Countries for demonstration project implementation)
Project reports including inception phase reports, Inception workshop report, quarterly progress
reports, annual progress reports (Project Implementation Report, PIR), financial reports, consultants
reports, progress reports from collaborating partners, project coordination minutes, National Steering
committee minutes, regional Steering committee minutes, relevant correspondence etc.;
Missions TOR and reports, monitoring reports
Project outputs: Consultancy reports, etc.
Evaluations/reviews of similar projects
An implementation review plan (produced for the 5th June meeting with countries in Nairobi Kenya)
(b) Interviews (individual or in group) with:
1. UNEP Task Manager
2. UNDP Regional Technical Adviser
3. Regional Project Coordination Unit;
4. UNEP Fund Management Officer;
5. UNDP Country Offices in Cabo Verde, Comoros, Maldives, Mauritius, São Tomé & Principe and
Seychelles.
6. UNOPS East Africa Hub
7. UNOPS Water and Energy Cluster
8. Participating beneficiary Government teams and partners in Cabo Verde, Comoros, Maldives, Mauritius,
9.
10.
11.
12.
(c)
(d)
São Tomé and Principe and Seychelles,
National Steering Committees,
Regional steering Committee,
Relevant UNEP Sub-programme Coordinators,
Relevant resource persons;
Field visits: To beneficiary countries and participation in the Regional Steering Committee meeting
Other data collection tools:
The final MTR report should describe the full MTR approach taken and the rationale for the approach making
explicit the underlying assumptions, challenges, strengths and weaknesses about the methods and approach of the
review.
3.
Key Evaluation principles
Evaluation findings and judgements should be based on sound evidence and analysis, clearly documented in the
evaluation report. Information will be triangulated (i.e. verified from different sources) to the extent possible, and
when verification was not possible, the single source will be mentioned. Analysis leading to evaluative judgements
should always be clearly spelled out.
The evaluation will assess the project with respect to a minimum set of evaluation criteria grouped in six
categories: (1) Strategic Relevance; (2) Attainment of objectives and planned result, which comprises the
assessment of outputs achieved, effectiveness and likelihood of impact; (3) Sustainability and replication; (4)
Efficiency; (5) Factors and processes affecting project performance, including preparation and readiness,
implementation and management, stakeholder participation and public awareness, country ownership and drivenness, financial planning and management, UNEP supervision and backstopping, and project monitoring and
evaluation; and (6) Complementarity with the UNEP and UNDP strategies and programmes. The evaluation
consultants can propose other evaluation criteria as deemed appropriate.
Ratings. All evaluation criteria will be rated on a six-point scale. Annex 2 provides guidance on how the different
criteria should be rated and how ratings should be aggregated for the different evaluation criterion categories.
Baselines and counterfactuals. In attempting to attribute any outcomes and impacts to the project intervention,
the evaluators should consider the difference between what has happened with, and what would have happened
without, the project. This implies that there should be consideration of the baseline conditions, trends and
counterfactuals in relation to the intended project outcomes and impacts. It also means that there should be
plausible evidence to attribute such outcomes and impacts to the actions of the project. Sometimes, adequate
information on baseline conditions, trends or counterfactuals is lacking. In such cases this should be clearly
highlighted by the evaluators, along with any simplifying assumptions that were taken to enable the evaluator to
make informed judgements about project performance.
The “Why?” Question. As this is a Mid-term Evaluation particular attention should be given to identifying
implementation challenges and risks to achieving the expected project objectives and sustainability. Therefore, the
“Why?” question should be at the front of the consultants’ minds all through the evaluation exercise. This means
that the consultants need to go beyond the assessment of “what” the project performance was, and make a
serious effort to provide a deeper understanding of “why” the performance was as it was, i.e. of processes
affecting attainment of project results (criteria under category F – see below). This should provide the basis for the
lessons that can be drawn from the project. In fact, the usefulness of the evaluation will be determined to a large
extent by the capacity of the consultants to explain “why things happened” as they happened and are likely to
evolve in this or that direction, which goes well beyond the mere review of “where things stand” at the time of
evaluation.
A key aim of the evaluation is to encourage reflection and learning by Project (staff and key project stakeholders).
The consultant should consider how reflection and learning can be promoted, both through the evaluation process
and in the communication of evaluation findings and key lessons.
Communicating evaluation results. Once the consultant(s) has obtained evaluation findings, lessons and results,
the Evaluation Office will share the findings and lessons with the key stakeholders. Evaluation results should be
communicated to the key stakeholders in a brief and concise manner that encapsulates the evaluation exercise in
its entirety. There may, however, be several intended audiences, each with different interests and preferences
regarding the report. It is therefore planned that the consultant will participate in the Regional steering committee
to interact and provide feedback. If considered necessary, a webinar, conference calls with relevant stakeholders
may be planned.
4.
Evaluation Criteria
i. Strategic Relevance
The evaluation will assess, in retrospect, whether the project’s objectives and implementation strategies were
consistent with global, regional and national environmental issues and needs.
The evaluation will assess whether the project was in-line with the GEF International Waters focal area’s strategic
priorities and operational programme(s).
The evaluation will also assess the project’s relevance in relation to UNEP’s and UNDP’s mandate and its alignment
with their respective policies and strategies at the time of project approval. The magnitude and extent of any
contributions and the causal linkages should be fully described.
The MTR will assess the following four categories of project progress.
5.
Project Strategy
ii. Project Design:
The evaluation will assess, in retrospect, whether the project’s objectives and implementation strategies were
consistent with global, regional and national environmental issues and needs.
The evaluation will assess whether the project was in-line with the GEF International Waters focal area’s strategic
priorities and operational programme(s). The evaluation will also assess the project’s relevance in relation to
UNEP’s and UNDP mandate and its alignment with their respective policies and strategies at the time of project
approval.
Review project design, specifically;




Review the problem addressed by the project and the underlying assumptions.
Review the effect of any incorrect assumptions or changes to the context to achieving the project
results as outlined in the Project Document.
Review the relevance of the project strategy and assess whether it provides the most effective route
towards expected/intended results.
Were lessons from other relevant projects properly incorporated into the project design? Review how
the project addresses country priorities. Review country ownership.




Was the project concept in line with the national sector development priorities and plans of the
country (or of participating countries in the case of multi-country projects)?
Were the executing agencies role well-chosen and developed?
Review decision-making processes: were perspectives of those who would be affected by project
decisions, those who could affect the outcomes, and those who could contribute information or other
resources to the process, taken into account during project design processes?
Review the extent to which relevant gender issues were raised in the project design. See Annex 9 of
Guidance For Conducting Midterm Reviews of UNDP-Supported, GEF-Financed Projects for further
guidelines. If there are major areas of concern, recommend areas for improvement.
Analyze Results Framework/Logframe, specifically;
 Undertake a critical analysis of the project’s logframe indicators and targets,
 Assess how “SMART” the midterm and end-of-project targets are (Specific, Measurable, Attainable,
Relevant, Time-bound), and
 Suggest specific amendments/revisions to the targets and indicators as necessary
 Are the project’s objectives and outcomes or components clear, practical, and feasible within its time
frame?
 Examine if progress so far has led to, or could in the future catalyse beneficial development effects (i.e.
income generation, gender equality and women’s empowerment, improved governance etc...) that
should be included in the project results framework and monitored on an annual basis.
 Ensure broader development and gender aspects of the project are being monitored effectively.
 Develop and recommend SMART ‘development’ indicators, including sex-disaggregated indicators and
indicators that capture development benefits.
iii. Progress towards Results
a.
b.
c.
d.
The project implementation (particularly that of the UNEP components) is heavily delayed due to a number of
factors: A project implementation review for accelerated implementation of project delivery and increased
synergies with the uNDP component was discussed informally with countries on the 5 th June 2015 in UNEP in
Nairobi. The following is a summary of the challenges and remediation actions listed in the project
implementation review (ANNEX for further details)
In its fourth year of operation (since May 2012) the SIDS AIO Project faces a number of delays. Besides
logistical difficulties (frequent changes of Project managers, incomplete hiring processes of in-country IWRM
experts to assist focal points nationally and change in UNEP Task Managers in 2014/2015)), there has been a
general delay in the implementation process.
The proposed implementation review and workplan were developed and discussed informally with
participating countries at an ad hoc meeting in UNEP in Nairobi on 5 th June 2015. The project is 70% into its
total project duration (planned end mid 2016) with less than 20 % of the outputs achieved but with a
remaining 80% of the budget for the implementation of the UNEP components.
Timing being the main limiting factor in succeeding a turnaround of the project and the successful
mainstreaming of IWRM policies and monitoring frameworks into the respective national processes, the
meeting recommended that a one year (no cost) extension would be the basis on which accelerate
implementation would stand a chance of success.
e.
The success of the implementation of UNEP components (2-4) will depend on the support provided to
mainstreaming IWRM into the different national processes, the targeted capacity building to enhance related
policy and monitoring frameworks as well as the necessary inter-ministerial coordination to endorse and
sustain IWRM strategies and Road Maps. An update of the national diagnostic analyses in the six countries will
provide the new baseline reflecting changes in water related policy processes in the last year.
f.
In line a proposal for accelerating the implementation process over the next months was proposed which
include (I) reinforcement of the Regional PCU with a new Project Coordinator and a communication expert, (ii)
accelerating the hiring process for the national IWRM experts to assist the focal points in the implementation
of UNEP components, (iii) hiring of IWRM experts and trainers for sub-regional training workshops, (iv) hiring
of an IWRM monitoring expert to be in charge of the activities under component 2 (IWRM indicator
framework and monitoring national and regional dimensions).
g.
Regarding sustainability of the project outputs and the effective impact of activities it was proposed to build
on the success of the demonstration activities (comp1 UNDP) and for UNEP to continue financing the
demonstration activities along the extension of the project beyond mid 2016 to 2017. This will facilitate the
upscaling of demo activities to the national process, create synergies and cross-fertilisation across project
components and ensure replication of activities.
h.
The question of the role of the Nairobi and Abidjan Convention secretariats will be revisited in order to ensure
optimal integration of the outputs into regional frameworks in the long term (especially in view of
contribution to existing regional monitoring frameworks).
iv. Progress Towards Outcomes Analysis:
Review the logframe indicators against progress made towards the end-of-project targets using the Progress
Towards Results Matrix (shown as Table 4 below), rate the progress using the 6-scale rating, and make
recommendations for the areas marked either marginally unsatisfactory or unsatisfactory (or unlikely achieved or
highly unlikely achieved).
Table 4: Progress Towards Results Matrix (Achievement of outcomes against End-of-project Targets)
Project Strategy
Indicators
Baseline levels
Levels in 1st PIR (self
reported)
Mid-term Targets
End of Project Target
1.1 (Cabo Verde):
Protection of
groundwater
resources,
stabilization of
coastal
terrains and
promotion of
productive activities
at
coastal areas
through the
integrated planning
and
management of
wastewater
collection,
treatment and reuse
demonstrated in
Tarrafal
in the Island of
Santiago
m3 of wastewater
collected for
treatment (or # of
households
connected to WWT
system)
Limited connection to
sewerage system (typically
41%); currently system
operating at 10% capacity
Contractor identified
and on ground;
Extended sewerage system
covering 100% of target
households; system operating
at its 75% capacity
m3 of treated
wastewater used for
irrigation; ha of
farmland under
treated water
number of farmers
trained for the micro
irrigation system with
gender disaggregated
data
number of trees
planted as a natural
barrier against
salinization
number of awareness
raising campaigns
conducted
None,
-estimated to be operating
at 10%
studies on wastewater
facility improvement
have been completed
with draft report and
technical design
details available by
June 2014
not initiated, focus is
to increase the volume
of treated wastewater
Xxx (TBD by dec 2013),
-none, 0 ha under
farming using treated
waste
5ha under drip irrigation
110 farmers currently
cultivating in Colonato
Not initiated by June
2014
130 farmers using micro
irrigation
150 farmers using micro
irrigation
None
a tree nursery
established, to be
planted during the
next rain season.
Major awareness
campaigns have being
undertaken with two
major events captured
by national television.
An awareness raising
strategy was also
developed ( to be
translated and shared
with other countries as
a good example)
There has being
discussion with
different stakeholders
including research
Institutions and
University to be
involved. TOR to
procure services of
Sites identified; 50,000
trees planted
250,000 trees planted, with at
least 70% survival
Awareness raising plan
established,
2 major awareness raising
campaigns every quarter in yr
3, at least 10 major campaigns
by end of project
1.2 (Comoros):
Improved
water source
protection
through IWRM
Planning
and management in
Mutsamudu on the
Water resources
assessed at identified
monitoring points;
Water resource
monitoring
operational
None
No water quality or
quantity monitoring
data collected
Design of sewerage
extension system in
place
At least 1 major
campaign every quarter
Regular water resources
monitoring programme
established
water resources monitoring
programme aopted and
operational
Midterm
Level
&
Assessmen
t
Achievement
Rating
Justification
for Rating
island
of Anjouan
Solid waste collection
system established
and operational.
No collection system;
Volume/weight solid
waste collected
Amount of solid waste in
River Mutsamudu not
Monitored
Volume/area of
monitoring point
covered in solid waste
1.3 (Maldives):
Protection of the
freshwater lens of
Thoddoo Island from
salinization and
agrochemical
Catchment
management
committee
established
Watershed
management plan
No committee Exists
Groundwater quality
baseline established
Limited baseline water
quality data
No plan exists; no data
collection or analysis exists
to provide basis for
management plan
consultant are
developed and
discussed.
There has been
extensive discussion
on the solid waste
collection system with
all stakeholders. A day
has been set aside my
the municipality and
Governor of anjoaun
for Solidwaste
collection in the city of
Anjoaun
several river cleaning
activities have been
undertaken with all
stakeholders with
support of the
Governor of Anjouan
and the Army
An interim multistakeholder
Committee is in place
and actively involved
pending completion of
the water resource
assessment. Interim
water committee
formation is a major
step towards the
establishment of the
watershed
management plan
2014. Several clean up
campaigns have been
undertaken with all
stakeholders. Initial
meeting with farmers
was held and follow up
meetings agreed on
Project design
endorsed by
Government. Vacancy
announcement for
Demonstration Project
Manager advertised
# of households
increased serviced by
solid waste collection
system
A solid waste collection in
place and functional
30% reduction in solid
waste observed at the
monitoring point
upstream of water
supply intake;
50% reduction in solid waste
observed at the monitoring
point upstream of water
supply intake;
Committee established
with clear TORs and
operational
A functional catchment
management committee, with
clear sustainability
arrangements
Consultation with landowners
and catchment s/h completed;
watershed surveys conducted;
watershed zone map
produced; management plan
endorsed by stakeholders
Consultation with
landowners and
catchment s/h initiated;
watershed surveys
conducted; Survey data
available for watershed
zone mapping
50% wells on faming
plots and 50% of
household wells
monitored
pollution, with
improved drought
season
aquifer yields
# of plots receiving
water supply from the
infiltration gallery
system with metering
No water provided from
the system, All
groundwater extracted
from individual wells, no
metering.
Currently elevated salinity
and electrical conductivity
Project design
endorsed by
Government.
50% of agricultural plots
on the island irrigated
from the gallery System
Project design
endorsed by
Government.
Reduced nitrates and
phosphates in GW
Limited data available on
GW quality
Groundwater quality
monitoring system
established
Non existent
Project design
endorsed by
Government.
Project design
endorsed by
Government.
Salinity level below
700μS/cm, 30%
reduction from average
baseline salinity level
30% reduction from the
baseline data
Water Quality
Baseline developed:
Vulnerability of the
aquifer against
pollution and
extraction assessed
Limited Hydrogeological
data on the northern
Aquifer
Increased m3 of
treated wastewater
re-used as alternative
water resources (for
recharge, irrigation,
etc.) (co-fin)
Impact assessment of
the effectiveness of
groundwater recharge
using the treated
wastewater against
saline intrusion.
1500m3 per day injected
in boreholes
Effectiveness of the
current practice unknown
Not initiated by June
2014
Best practices for
water demand
management
captured and
disseminated to % of
stakeholder bodies;
Limited awareness of
policy makers about the
importance to protect
groundwater and lagoon;
Not initiated by June
2014
Reduced groundwater
salinity(%) and
electrical conductivity
1.4 (Mauritius): The
protection and
sustainable
utilization of
the Northern Aquifer
of
Mauritius
demonstrated
through the
integrated
planning and
management of
wastewater
collection,
treatment and reuse
Data collection
ongoing by Water
Resources Unit.
Analysis and
vulnerability maps to
be completed through
consultancy
Gender balanced
training given to
farmers; 20 shallow
boreholes established
for GW quality
monitoring
Required scientific
baseline data agreed
on, and plans for data
collection in place;
hydrogeological data
collection protocols
endorsed
2500m3 per day used as
alternative water
resources (irrigation,
recharge, etc.)
Impact assessment of
the effectiveness of
groundwater recharge
using the treated
wastewater against
saline Intrusion
undertaken and
recommendations made
A plan on dissemination
of best practices on
water demand
management
developed,
10% of public receive
best practice guidance
Scientific baseline reports on
hydrogeological data, land use
and pollution activities
categorized and compiled;
vulnerability map produced;
protection measures in place
at sensitive areas
Aquifer effectively protected
from saline intrusion using the
results of the assessment;
Salinity monitored
35% of public receive best
practice guidance on pollution
prevention and effective water
consumption;
Water demand issues for
communication to policy
makers identified
on pollution prevention
and effective water
consumption;
1.5 (São Tomé &
Principe): Integrated
River basin
management
plan for the Rio
Provaz
Basin developed to
enable equitable
water
resources allocation
and
protection,
contributing to
sustainable
economic
development, public
health and
environmental
protection.
# of briefings
produced by % of
stakeholders on water
resource
management and
climate
change/gender
empowerment
Limited awareness about
saving water and polluting
activities;
Area surveyed and
reported
No formal inventories of
land or water resources or
use exists
Water resources level,
flow and quality data;
GW resources
potential established
No regular data collection
or quality assurance
Basin water
management
committee; Basin
Water Resources
Allocation and
Protection Strategy
No stakeholder
consultations on water
resources management to
date; no catchment
management committee:
no water resources
management strategies at
basin level or national level
# of households using
Ecosan
No Ecosan technology
currently used
Not initiated by June
2014
Plans and approach for
identification of issues
for policy makers
established
50% of IWRM
coordination
mechanism aware of
climate change issues;
100% of IWRM
coordination mechanism
aware of climate change
issues;
system for gender
disaggregated data on
water management
established
Basin zoning
undertaken and data
and information needs
agreed on
Gender disaggregated data on
water management become
available
Data needs and gaps
agreed on; regular data
collection system on
water resources level,
flow and quality
established for both
surface and ground
water;
Robust quantity and quality
data sets collected; all major
risk type assessed for GW
extraction GW resources
potential
established
Stakeholder
consultations started;
Interim committee has
been established.
Stakeholders for
catchment committee
identified and
membership agreed on;
Gender integrated
catchment
management
committees established;
Fact finding for EcoSan
and solid waste
disposal underway in
collaboration with STP
based international
Strategies for
promotion of ecosan
established;
Gender integrated catchment
management committees
established and operational;
water resources management
strategy developed in a
participatory manner and
endorsed by the basin
stakeholders; the process at
the demo basin informs the
national level IWRM process
80% of constructed Ecosan
units still in use at the end of
the project (# of units TBD);
lessons learned produced
aiming for further promotion
Interim Catchment
committee has been
established,
consultancy
recruitment ois
ongoing
Not initiated by June
2014
100% of catchments area
surveyed
1.6 (Seychelles):
Protection of a
coastal
gravel aquifer
through
integrated land and
water
management
measures
(water demand
management, land
use,
flood management)
demonstrated in the
island of La Digue
# of households
business and
community buildings
with rainwater
storage tanks
Rainwater harvesting
practiced only marginally
m3 of re-used effluent
Limited level of
wastewater reuse
practiced
% reduction in peak
water pressure
requirements through
installation of # of
household water
storage tanks
Limited # of households
with potable water storage
tanks
% reduction in
leakage in water
supply distribution
System
2.
IWRM and
No leakage detection and
reduction programme;
bulk metering only at
water treatment plant;
Surface water salinity
in marsh outlets and
GW salinity; aquifer
recharge capacity of
marshland restored
Inflow of seawater at high
tide conditions; no tidal
flaps installed;
Development pressure
reduced natural buffering
capacity of marshland
Volume of waste oils
and batteries
collected
Existing collection
programmes not effective
– no collection
Inadequate monitoring of
water
NGO
wide consultation with
all stakeholders on the
approach for the
rainwater harvesting
and awareness
campaign started
Planning with two
hotels was initiated.
Mandatory installation
have been discussed
with the local office
for planning and the La
Digue advisory
Council.
The project is closely
working with the
Public Utilities
Corporation and data
has been analysed on
mitigation measure
agreed on
2 tidal reverse valves
installed. Project has
been working with
local NGO promoting
conservation and
restoration of the
marshland
site evaluation was
undertaken and
mitigation approach
agreed on. In addition,
communities and
authorities have been
sensitised on the
negative impacts and
mitigation measures
Delayed
-strategy for rainwater
harvesting established;
40% of targeted
buildings using
rainwater at domestic
and commercial levels
Landscape irrigation
schemes using treated
wastewater at two
hotels
Initial discussions and
consultations on
mainstreaming
adoption of potable
water storage tanks for
all new buildings in
progress
A system of leak
identification
established;
40% of leaks fixed; #m
of damaged pipes
replaced 50% reduction
of m3 of water loss (#s
TBD during the
inception)
2 tidal flaps installed;
seawater flows inland
into marshes reduced;
100% of targeted buildings
using rainwater at domestic
and commercial levels
Landscape irrigation schemes
using treated wastewater at 5
hotels, using 100 m3/day
Mandatory installation of
potable water storage tanks
for all new buildings adopted
by the land planning in La
Digue
10% reduction in system peak
pressures
District meters installed and
monitored;
100% of leaks fixed; new leaks
kept at minimum; all damaged
pipes replaced
70% reduction of m3 of water
loss (#s TBD by Dec 2014)
4 tidal flaps installed; no
seawater flows inland into
marshes; reinstatement of
the marshland
Collection system in
place
70% of households using
collection system
Water resources
monitoring plans with
National IWRM monitoring
inventories and capacity
WUE indicators,
baselines, targets
and monitoring
protocols discussed,
agreed and adopted
into long-term
monitoring
programs at national
and ‘regional’ levels
3.
SIDS
employ new plans,
policy tools and
approaches in
implementing IWRM
commitments
4.
Strengthene
d capacity allows
resources levels, flows and
quality
Inadequate land and
catchment
characterization
Poor understanding of
water demands and water
abstraction rates
Delayed
Negligible water pollution
monitoring
Delayed
Poor awareness of IWRM
processes
Delayed
Sectoral policies and
planning
Delayed
Sectoral legislation and
regulation
No integrated resources,
infrastructure and
governance
approaches
Minimal inter-sectoral
coordination
Delayed
No inter-agency
coordination mechanisms
at technical or political
levels
Weak government and
nongovernment
inter-engagement
Delayed
Weak government and
nongovernment
inter-engagement
Little knowledge of
integrated water
and land management
Delayed
Delayed
Delayed
Delayed
Delayed
long-term tracking
indicators established
assessments
Survey, database and
assessment of water
resources
Key stakeholders
trained on monitoring
tools & monitoring plan
implementation
Key stakeholders using
data for water
resources and
infrastructure
management
Development of Indicator
Framework
IWRM integrated into
sectoral policies
and planning
IWRM integrated into
sectoral legislation
and regulation
Development of national and
regional
baseline indicators and targets
Testing of Indicator Framework
IWRM indicator development
and
monitoring capacity building
National IWRM diagnostic
report
baselines strengthened
IWRM integrated into sectoral
policies
and plans
Effective formalized
inter-agency and
inter-sectoral
coordination &
cooperation
Effective government
and civil society
IWRM partnership
National IWRM policies and
plans
Developed
Water resources,
infrastructure and
governance approaches
in all IWRM
approaches
IWRM partnerships established
National IWRM coordination
Completion of IWRM
legislative
reviews and amendments
(Apex)
bodies established
Improved awareness
among stakeholders
on IWRM
IWRM awareness materials
produced
and campaigns delivered
stakeholders and
institutions in SIDS
to fulfill their role in
local, national and
regional IWRM
processes and
exchange best
practices
approaches
Minimal access to external
IWRM
approaches for SIDS
Delayed
Increased stakeholder
IWRM capacity
IWRM training modules and
courses
delivered
Weak networks of local
and national
stakeholders
Delayed
Multi-media IWRM knowledge
base
developed and functional
Little knowledge exchange
and transfer from regional
SIDS and
inter-regional SIDS
Delayed
Multi-media knowledge
resource base
readily available to
IWRM stakeholders
Networks of national
partners exchange
information and
knowledge on IWRM
Delayed
5.
Project
implemented
effectively and
efficiently to the
satisfaction of
partners
Limited in-country capacity
to
manage multi-sectoral
interventions
Limited in-country capacity
to
facilitate multi-stakeholder
governance processes
Delayed
Delayed
Inter-national and interregional SIDS
partnerships sharing
IWRM information
Effective management
and delivery of
demonstration projects
Networking of IWRM partners
Inter-regional SIDS
coordination and
knowledge sharing
Project management training
Effective facilitation of
national IWRM
governance reform
process
Stakeholder engagement
Effective monitoring of
IWRM delivery
Project monitoring and
evaluation, and reporting
In addition to the progress towards outcomes analysis:
 Compare and analyse the GEF Tracking Tool at the Baseline with the one completed right before the Midterm
Review.
 Identify remaining barriers to achieving the project objective in the remainder of the project.
 By reviewing the aspects of the project that have already been successful, identify ways in which the project
can further expand these benefits.
6.












Project Implementation and Adaptive Management
I)
Management Arrangements:
Review overall effectiveness of project management as outlined in the Project Document. Have changes been
made and are they effective? Are responsibilities and reporting lines clear? Is decision-making transparent and
undertaken in a timely manner? Recommend areas for improvement.
Review the quality of execution of the Executing Agency/Implementing Partner(s) and recommend areas for
improvement.
Review the quality of support provided by the GEF Partner Agency (UNDP) and recommend areas for
improvement.
ii)
Work Planning:
Review any delays in project start-up and implementation, identify the causes and examine if they have been
resolved.
Are work-planning processes results-based? If not, suggest ways to re-orientate work planning to focus on
results?
Examine the use of the project’s results framework/ logframe as a management tool and review any changes
made to it since project start.
iii)
Finance and co-finance:
Consider the financial management of the project, with specific reference to the cost-effectiveness of
interventions.
Review the changes to fund allocations as a result of budget revisions and assess the appropriateness and
relevance of such revisions.
Does the project have the appropriate financial controls, including reporting and planning, that allow
management to make informed decisions regarding the budget and allow for timely flow of funds?
Informed by the co-financing monitoring table to be filled out, provide commentary on co-financing: is cofinancing being used strategically to help the objectives of the project? Is the Project Team meeting with all
co-financing partners regularly in order to align financing priorities and annual work plans?
iv)
Project-level Monitoring and Evaluation Systems:
Review the monitoring tools currently being used: Do they provide the necessary information? Do they involve
key partners? Are they aligned or mainstreamed with national systems? Do they use existing information? Are
they efficient? Are they cost-effective? Are additional tools required? How could they be made more
participatory and inclusive?
Examine the financial management of the project monitoring and evaluation budget. Are sufficient resources
being allocated to monitoring and evaluation? Are these resources being allocated effectively?









v)
Stakeholder Engagement:
Project management: Has the project developed and leveraged the necessary and appropriate partnerships
with direct and tangential stakeholders?
Participation and country-driven processes: Do local and national government stakeholders support the
objectives of the project? Do they continue to have an active role in project decision-making that supports
efficient and effective project implementation?
Participation and public awareness: To what extent has stakeholder involvement and public awareness
contributed to the progress towards achievement of project objectives?
vi)
Reporting:
Assess how adaptive management changes have been reported by the project management and shared with
the Project Board.
Assess how well the Project Team and partners undertake and fulfil GEF reporting requirements (i.e. how have
they addressed poorly-rated PIRs, if applicable?)
Assess how lessons derived from the adaptive management process have been documented, shared with key
partners and internalized by partners.
vii)
Communications:
Review internal project communication with stakeholders: Is communication regular and effective? Are there
key stakeholders left out of communication? Are there feedback mechanisms when communication is
received? Does this communication with stakeholders contribute to their awareness of project outcomes and
activities and investment in the sustainability of project results?
Review external project communication: Are proper means of communication established or being established
to express the project progress and intended impact to the public (is there a web presence, for example? Or
did the project implement appropriate outreach and public awareness campaigns?)
For reporting purposes, write one half-page paragraph that summarizes the project’s progress towards results
in terms of contribution to sustainable development benefits, as well as global environmental benefits.
7.
Sustainability
Sustainability is understood as the probability of continued long-term project-derived results and impacts after the
external project funding and assistance ends. The evaluation will identify and assess the key conditions or factors
that are likely to undermine or contribute to the persistence of benefits. Some of these factors might be direct
results of the project while others will include contextual circumstances or developments that are not under
control of the project but that may condition the sustainability of benefits. The evaluation should ascertain to what
extent follow-up work has been initiated and how project results will be sustained and enhanced over time. The
reconstructed ToC will assist in the evaluation of sustainability, as the drivers and assumptions required to achieve
higher-level results are often similar to the factors affecting sustainability of these changes.
The MTR will validate whether the risks identified in the Project Document, Annual Project Review/PIRs and the
ATLAS Risk Management Module are the most important and whether the risk ratings applied are appropriate and
up to date. If not, explain why.
In addition, assess the following risks to sustainability:
i. Financial risks to sustainability:
What is the likelihood of financial and economic resources not being available once the GEF assistance ends
(consider potential resources can be from multiple sources, such as the public and private sectors, income
generating activities, and other funding that will be adequate financial resources for sustaining project’s
outcomes)?
ii. Socio-economic risks to sustainability:
Are there any social or political risks that may jeopardize sustainability of project outcomes? What is the risk
that the level of stakeholder ownership (including ownership by governments and other key stakeholders) will
be insufficient to allow for the project outcomes/benefits to be sustained? Do the various key stakeholders
see that it is in their interest that the project benefits continue to flow? Is there sufficient public / stakeholder
awareness in support of the long term objectives of the project? Are lessons learned being documented by the
Project Team on a continual basis and shared/ transferred to appropriate parties who could learn from the
project and potentially replicate and/or scale it in the future?
iii. Institutional Framework and Governance risks to sustainability:
Do the legal frameworks, policies, governance structures and processes pose risks that may jeopardize
sustenance of project benefits? While assessing this parameter, also consider if the required systems/
mechanisms for accountability, transparency, and technical knowledge transfer are in place.
iv. Environmental risks to sustainability:
Are there any environmental risks that may jeopardize sustenance of project outcomes?
8.
Catalytic Role and Replication
The MTE will assess the catalytic effect already played by the project and methodology. The catalytic role
of interventions is embodied in their approach of supporting the creation of an enabling environment and
of investing in pilot activities which are innovative and showing how new approaches can work. UNEP also
aims to support activities that upscale new approaches to a national, regional or global level, with a view
to achieve sustainable global environmental benefits. The evaluation will assess the catalytic role played
by this project, namely to what extent the project has:
(a)
(b)
(c)
(d)
(e)
(f)
catalyzed behavioural changes in terms of use and application, by the relevant stakeholders, of
capacities developed;
provided incentives (social, economic, market based, competencies etc.) to contribute to catalyzing
changes in stakeholder behaviour;
contributed to institutional changes, for instance institutional uptake of project-demonstrated
technologies, practices or management approaches;
contributed to policy changes (on paper and in implementation of policy);
contributed to sustained follow-on financing (catalytic financing) from Governments, private sector,
donors etc.;
created opportunities for particular individuals or institutions (“champions”) to catalyze change
(without which the project would not have achieved all of its results).
Replication is defined as lessons and experiences coming out of the project that are replicated (experiences are
repeated and lessons applied in different geographic areas) or scaled up (experiences are repeated and lessons
applied in the same geographic area but on a much larger scale and funded by other sources). The evaluation will
assess the approach adopted by the project to promote replication effects and determine to what extent actual
replication has already occurred, or is likely to occur in the near future. What are the factors that may influence
replication and scaling up of project experiences and lessons?
9.
Efficiency
(i) The evaluation will assess the cost-effectiveness and timeliness of project execution. It will describe any cost- or
time-saving measures put in place in attempting to bring the project as far as possible in achieving its results within
its (severely constrained) secured budget and (extended) time. It will also analyse how delays, if any, have affected
project execution, costs and effectiveness. Wherever possible, costs and time over results ratios of the project will
be compared with that of other similar interventions.
ii) The evaluation will give special attention to efforts by the project teams to make use of/build upon pre-existing
institutions, agreements and partnerships, data sources, synergies and complementarities with other initiatives,
programmes and projects etc. to increase project efficiency. For instance, [insert relevant examples for the project
being evaluated].
10.
Factors and Processes Affecting Project Performance
I.
Preparation and readiness. This criterion focuses on the quality of project design and preparation. Were
project stakeholders4 adequately identified and were they sufficiently involved in project development and
ground truthing e.g. of proposed timeframe and budget? Were the project’s objectives and components clear,
practicable and feasible within its timeframe? Are potentially negative environmental, economic and social
impacts of projects identified? Were the capacities of executing agencies properly considered when the project
was designed? Was the project document clear and realistic to enable effective and efficient implementation?
Were the partnership arrangements properly identified and the roles and responsibilities negotiated prior to
project implementation? Were counterpart resources (funding, staff, and facilities) and enabling legislation
assured? Were adequate project management arrangements in place? Were lessons from other relevant
projects properly incorporated in the project design? What factors influenced the quality-at-entry of the
project design, choice of partners, allocation of financial resources etc.? Were any design weaknesses
mentioned in the Project Review Committee minutes at the time of project approval adequately addressed?
II.
Project implementation and management. This includes an analysis of implementation approaches used by
the project, its management framework, the project’s adaptation to changing conditions and responses to
changing risks including safeguard issues (adaptive management), the performance of the implementation
arrangements and partnerships, relevance of changes in project design, and overall performance of project
management. The evaluation will:
(a)
(b)
(c)
(d)
(e)
Ascertain to what extent the project implementation mechanisms outlined in the project document
have been followed and were effective in delivering project milestones, outputs and outcomes.
Were pertinent adaptations made to the approaches originally proposed?
Evaluate the effectiveness and efficiency of project management and how well the management was
able to adapt to changes during the life of the project.
Assess the role and performance of the teams and working groups established and the project
execution arrangements at all levels.
Assess the extent to which project management responded to direction and guidance provided by
the UNEP Task Manager, the UNDP Regional Technical Adviser and project steering including
national and regional steering committees.
Identify operational and political / institutional problems and constraints that influenced the
effective implementation of the project, and how the project tried to overcome these problems.
III. Stakeholder participation, cooperation and partnerships. The Evaluation will assess the effectiveness of
mechanisms for information sharing and cooperation with other UNEP and/or UNDP projects and programmes,
external stakeholders and partners. The term stakeholder should be considered in the broadest sense,
encompassing both project partners and target users of project products. The Theory of Change (TOC) and
stakeholder analysis should assist the evaluator in identifying the key stakeholders and their respective roles,
capabilities and motivations in each step of the causal pathways from activities to achievement of outputs,
4
Stakeholders are the individuals, groups, institutions, or other bodies that have an interest or ‘stake’ in the outcome of the project.
The term also applies to those potentially adversely affected by the project.
outcomes and intermediate states towards impact. The assessment will look at three related and often
overlapping processes: (1) information dissemination to and between stakeholders, (2) consultation with and
between stakeholders, and (3) active engagement of stakeholders in project decision making and activities. The
evaluation will specifically assess:
(a)
(b)
(c)
(d)
(e)
(f)
(g)
the approach(es) and mechanisms used to identify and engage stakeholders (within and outside
UNEP/UNDP) in project design and at critical stages of project implementation. What were the
strengths and weaknesses of these approaches with respect to the project’s objectives and the
stakeholders’ motivations and capacities?
How was the overall collaboration between different functional units of UNEP and/or UNDP involved
in the project? What coordination mechanisms were in place? Were the incentives for internal
collaboration in UNEP/UNDP adequate?
Was the level of involvement of the Regional, Liaison and Out-posted Offices in project design,
planning, decision-making and implementation of activities appropriate?
Has the project made full use of opportunities for collaboration with other projects and programmes
including opportunities not mentioned in the Project Document? Have complementarities been
sought, synergies been optimized and duplications avoided?
What was the achieved degree and effectiveness of collaboration and interactions between the
various project partners and stakeholders during design and implementation of the project? This
should be disaggregated for the main stakeholder groups identified in the inception report.
To what extent has the project been able to take up opportunities for joint activities, pooling of
resources and mutual learning with other organizations and networks? In particular, how useful are
partnership mechanisms and initiatives to build stronger coherence and collaboration between
participating organisations?
How did the relationship between the project and the collaborating partners (institutions and
individual experts) develop? Which benefits stemmed from their involvement for project
performance, for UNEP and for the stakeholders and partners themselves? Do the results of the
project (strategic programmes and plans, monitoring and management systems, sub-regional
agreements etc.) promote participation of stakeholders, including users, in environmental decision
making?
IV. Communication and public awareness. The evaluation will assess the effectiveness of any public awareness
activities that were undertaken during the course of implementation of the project to communicate the project’s
objective, progress, outcomes and lessons. This should be disaggregated for the main stakeholder groups
identified in the inception report. Did the project identify and make us of existing communication channels and
networks used by key stakeholders? Did the project provide feedback channels?
V. Country ownership and driven-ness. The evaluation will assess the degree and effectiveness of involvement
of government / public sector agencies in the project, in particular those involved in project execution and those
participating in project steering committees (regional and/or national levels):
(a)
(b)
(c)
To what extent have Governments assumed responsibility for the project and provided adequate
support to project execution, including the degree of cooperation received from the various public
institutions involved in the project?
How and how well did the project stimulate country ownership of project outputs and outcomes?
[Any other project-specific questions]
VI. Financial planning and management. Evaluation of financial planning requires assessment of the quality and
effectiveness of financial planning and control of financial resources throughout the project’s lifetime. The
assessment will look at actual project costs by activities compared to budget (variances), financial management
(including disbursement issues), and co-financing (see Annex 3). The evaluation will:
(a)
Verify the application of proper standards (clarity, transparency, audit etc.) and timeliness of
financial planning, management and reporting to ensure that sufficient and timely financial
resources were available to the project and its partners;
(b)
(c)
(d)
Assess other administrative processes such as recruitment of staff, procurement of goods and
services (including consultants), preparation and negotiation of cooperation agreements etc. to the
extent that these might have influenced project performance;
Present the extent to which co-financing has materialized as expected at project approval (see Table
1). Report country co-financing to the project overall, and to support project activities at the national
level in particular. The evaluation will provide a breakdown of final actual costs and co-financing for
the different project components (see tables in Annex 3).
Describe the resources the project has leveraged since inception and indicate how these resources
are contributing to the project’s ultimate objective. Leveraged resources are additional resources—
beyond those committed to the project itself at the time of approval—that are mobilized later as a
direct result of the project. Leveraged resources can be financial or in-kind and they may be from
other donors, NGO’s, foundations, governments, communities or the private sector.
VII. Analyse the effects on project performance of any irregularities in procurement, use of financial resources and
human resource management, and the measures taken by implementing and executing agencies to prevent such
irregularities in the future. Determine whether the measures taken were adequate.
VIII. Supervision, guidance and technical backstopping. The purpose of supervision is to verify the quality and
timeliness of project execution in terms of finances, administration and achievement of outputs and outcomes, in
order to identify and recommend ways to deal with problems, which arise during project execution. Such problems
may be related to project management but may also involve technical/institutional substantive issues in which
UNEP has a major contribution to make.
IX. The evaluators should assess the effectiveness of supervision, guidance and technical support provided by the
different supervising/supporting bodies including:
(a)
(b)
(c)
The adequacy of project supervision plans, inputs and processes;
The realism and candour of project reporting and the emphasis given to outcome monitoring
(results-based project management);
How well did the different guidance and backstopping bodies play their role and how well did the
guidance and backstopping mechanisms work? What were the strengths in guidance and
backstopping and what were the limiting factors?
X. Monitoring and evaluation. The evaluation will include an assessment of the quality, application and
effectiveness of project monitoring and evaluation plans and tools, including an assessment of risk management
based on the assumptions and risks identified in the project document. The evaluation will assess how information
generated by the M&E system during project implementation was used to adapt and improve project execution,
achievement of outcomes and ensuring sustainability. M&E is assessed on three levels:
(a)
M&E Design. The evaluators should use the following questions to help assess the M&E design
aspects:
 Arrangements for monitoring: Did the project have a sound M&E plan to monitor results and
track progress towards achieving project objectives? Have the responsibilities for M&E activities
been clearly defined? Were the data sources and data collection instruments appropriate? Was
the time frame for various M&E activities specified? Was the frequency of various monitoring
activities specified and adequate?
 How well was the project logical framework (original and possible updates) designed as a
planning and monitoring instrument?
 SMART-ness of indicators: Are there specific indicators in the logframe for each of the project
objectives? Are the indicators measurable, attainable (realistic) and relevant to the objectives?
Are the indicators time-bound?
 Adequacy of baseline information: To what extent has baseline information on performance
indicators been collected and presented in a clear manner? Was the methodology for the
baseline data collection explicit and reliable? For instance, was there adequate baseline
information on pre-existing accessible information on global and regional environmental status




(b)
and trends, and on the costs and benefits of different policy options for the different target
audiences? Was there sufficient information about the assessment capacity of collaborating
institutions and experts etc. to determine their training and technical support needs?
To what extent did the project engage key stakeholders in the design and implementation of
monitoring? Which stakeholders (from groups identified in the inception report) were involved?
If any stakeholders were excluded, what was the reason for this?
Did the project appropriately plan to monitor risks associated with Environmental Economic and
Social Safeguards?
Arrangements for evaluation: Have specific targets been specified for project outputs? Has the
desired level of achievement been specified for all indicators of objectives and outcomes? Were
there adequate provisions in the legal instruments binding project partners to fully collaborate in
evaluations?
Budgeting and funding for M&E activities: Determine whether support for M&E was budgeted
adequately and was funded in a timely fashion during implementation.
M&E Plan Implementation. The evaluation will verify that:
 The M&E system was operational and facilitated timely tracking of results and progress towards
projects objectives throughout the project implementation period;
 PIR reports were prepared (the realism of the Task Manager’s assessments will be reviewed)
 Half-yearly (and quarterly for UNDP-implemented Component) Progress & Financial Reports
were complete and accurate;
 Risk monitoring (including safeguard issues) was regularly documented
 Information provided by the M&E system was used during the project to improve project
performance and to adapt to changing needs.
11. Evaluation Consultant Role and Specific Tasks
For this evaluation, one international consultant will be hired by UNOPS to carry out the evaluation in line with
UNEP and UNDP guidelines as set out in this terms of reference.. By undersigning Individual Contractor Agreement
(ICA with UNOPS, the consultant certifies that he/she has not been associated with the design and implementation
of the project in any way which may jeopardize their independence and impartiality towards project achievements
and project partner performance. In addition, the consultant will not have any future interests (within six months
after completion of the contract) with the project’s executing or implementing units.
The consultant will be responsible for overall management of the evaluation, in close consultation with the UNEP
and UNDP, and will ensure timely delivery of its outputs as set out in this TORs. . More specifically:
-
Conduct a preliminary desk review and introductory interviews with project staff;
Draft the reconstructed Theory of Change of the project;
Prepare the evaluation framework;
Develop the desk review and interview protocols;
Draft the survey protocols (partner survey and user survey);
In consultation with project Coordination team, plan and develop a review schedule;
Travel and visit countries as well to undertake interviews and data collection. Travel may include meeting
with the national and or Regional steering committee.
Preparation and submission of various deliverables as set out in this terms of reference including
inception report, draft MTR report and final MTR report.
The consultant will ensure timely data collection supported by the PCU, analyse data, and prepare the main report
for the evaluation, and ensure together that all evaluation criteria and questions are adequately covered.
Evaluation Consultant Qualifications and Selection Criteria
The consultant should have extensive evaluation experience, including of large, regional or global programmes and
using a Theory of Change approach; and a broad understanding of large-scale, consultative assessment processes
and factors influencing use of assessments and/or scientific research for decision-making. The required
qualification, experience and competencies include:












Advanced university degree in water resources management, international development, environmental
sciences, monitoring and evaluation, or other relevant fields;
Demonstrated experience in international consulting experience and extensive evaluation experience,
including of large, regional or global programmes and using a Theory of Change approach;
Broad understanding of the Integrated Water Resources Management, its theory, application and
implementation processes;
Excellent understanding of, or experience in, the roles of projects, which aim to catalyse policy and
institutional reforms.
Knowledge of the UN system, and specifically of UNEP, UNDP and GEF on their strategic priorities and
their portfolio;
Past experience in evaluating the UNDP, UNEP or GEF IW portfolio is considered as an advantage;
Excellent writing skills in English;
Proficiency in French and/or Portuguese is considered as an advantage;
Attention to detail and respect for deadlines;
Respect for cultural diversity and appreciation of different political, policy and institutional settings;
Minimum 15 years of professional experience;
An additional 5 years of professional experience in the relevant field can substitute an advanced
university degree.
The fee of the Evaluator will be agreed on a deliverable basis and paid upon acceptance of expected key
deliverables by the UNEP and UNDP.
Evaluation Deliverables:
The following are the key MTR deliverables:
a. Inception report
b. Draft midterm review report
c. Final main report incorporating comments received from evaluation stakeholders as appropriate,
including a “response to comments” annex
d. 2 page bulletin summarising project findings (see template in Annex 2.)
The evaluator’s attention is drawn on the following important notes on the deliverables:
Inception Report:

The evaluator will prepare an inception report containing a thorough review of the project context, project
design quality, a draft reconstructed Theory of Change of the project, the evaluation framework and a
tentative evaluation schedule.

It is expected that a large portion of the desk review will be conducted during the inception phase. It will be
important to acquire a good understanding of the project context, design and process at this stage. The review
of design quality will cover the following aspects (see Annex 5 for the detailed project design assessment
matrix):
1.
2.
3.
4.
5.
6.
Strategic relevance of the project
Preparation and readiness;
Financial planning;
M&E design;
Complementarily with UNEP and UNDP strategies and programmes;
Sustainability considerations and measures planned to promote replication and up-scaling.

The inception report will also include a stakeholder analysis identifying key stakeholders, networks and
channels of communication. This information should be gathered from the Project document and discussion
with the project team.

The evaluation framework will present in further detail the overall evaluation approach. It will specify for each
evaluation question under the various criteria what the respective indicators and data sources will be. The
evaluation framework should summarize the information available from project documentation against each
of the main evaluation parameters. Any gaps in information should be identified and methods for additional
data collection, verification and analysis should be specified. Evaluations/reviews of other large assessments
can provide ideas about the most appropriate evaluation methods to be used.

Effective communication strategies help stakeholders understand the results and use the information for
organisational learning and improvement. While the evaluation is expected to result in a comprehensive
document, content is not always best shared in a long and detailed report; this is best presented in a
synthesised form using any of a variety of creative and innovative methods. The evaluator is encouraged to
make use of multimedia formats in the gathering of information, e.g., videos, photos, sound recordings.
Together with the full report, the evaluator will be expected to produce a 2-page summary of key findings and
lessons

The inception report will also present a tentative schedule for the overall evaluation process, including a draft
programme for the country visit and tentative list of people/institutions to be interviewed. The PCU may
assist developing a proposed travel schedule in the most effective manner in terms of time and costs. The
proposed travel schedule must be approved by UNEP and UNDP before a field mission begins. All financial
matters related to field trips (tickets, DSA and Terminal Expenses) will be made through UNOPS EAH office in
Kenya.

The respective Task Managers (TMs) in UNDP and UNEP will submit the inception report for review and
approval before any further data collection and analysis is undertaken.
The Mid-term Review Report

The Mid-term Review Report should be brief (no longer than 40 pages – excluding the executive summary and
annexes), to the point and written in plain English. The report should follow the annotated Table of Contents
outlined in Annex 1. It must explain the purpose of the evaluation, exactly what was evaluated and the
methods used (with their limitations). The report will present evidence-based and balanced findings,
consequent conclusions, lessons and recommendations, which will be cross-referenced to each other. The
report should be presented in a way that makes the information accessible and comprehensible. Any dissident
views in response to evaluation findings will be appended in footnote or annex as appropriate. To avoid
repetitions in the report, the authors will use numbered paragraphs and make cross-references where
possible.

Submission of the draft MTR report. The evaluator will submit draft report for review by various stakeholders
including UNEP, UNDP, UNOPS and beneficiaries and stakeholders in the participating countries. It is
envisaged that a Regional Project Steering Committee meeting will be organised from 25-28 October 2015 in
Maldives where the evaluator will have a chance to present the draft Mid-Term Review Report and
preliminary findings to the Steering Committee members face-to-face. Steering Committee members can
provide feedback on any errors of facts and may highlight the significance of such errors in any conclusions
either during the meeting, or through a separate bilateral meeting with the evaluator, or through the
submission of written comments before and after the presentation. It is also very important that stakeholders
provide feedback on the proposed recommendations and lessons. Comments would be expected no later than
1 week after the presentation of the draft MTR report by the evaluator at the RPSC meeting. Any comments or
responses to the draft report will be sent to evaluator for consideration in preparing the final draft report,
along with the evaluator’s own views.

Submission of the final MTR report. The final report shall be submitted by Email to the respective Task
managers in UNDP and UNEP and shared with appropriate units. The final evaluation report will be made
available through GEF, UNDP and the UNEP Evaluation Office web-sites (e.g. www.unep.org/eou). The
evaluator will submit the final report no later than 1 week after reception of stakeholder comments. The
evaluator will prepare a response to comments, listing those comments not or only partially accepted by them
that could therefore not or only partially be accommodated in the final report. They will explain why those
comments have not or only partially been accepted, providing evidence as required. This response to
comments will be shared with the interested stakeholders to ensure full transparency.

At the end of the evaluation process, the UNEP and UNDP as the implementing agencies will prepare a
Recommendations Implementation Plan (or Management Response) in the format of a table to be completed
and updated at regular intervals by the agency focal points for the project (UNEP Task Project Manager and
UNDP Regional Technical Adviser). UNEP and UNDP will jointly be responsible for the implementation of the
recommendations.
Schedule of Payment:
Deliverables
Signature of contract
Inception report
Submission and approval of the draft evaluation report
Submission and approval of the final evaluation report
Percentage payment
Travel expenses/DSA
20% of fees
30% of fees
50% of fees
12. Schedule of the Evaluation
Table below presents the tentative schedule for the evaluation.
Timeframe
29 July 2015
7 August 2015
15 August 2015
20 August 2015
1 – 30 September 2015
By 5 October 2015
By 9 October 2015
12-23 October 2015
25-28 October 2015
Activity
Application closes
Select MTR Consultant
Contract issued and the MTR exercise starts.
Preparation and submission of the MTR Inception Report, including
details work plan indicating all mission schedules for approval.
Document review
MTR mission: stakeholder meetings, interviews, field visits.
Mission wrap-up meeting & presentation of initial findings- earliest
end of MTR mission
Submission of the draft report (in English) for circulation for comments.
Translation of the draft report into French and Portuguese for circulation for
comments (arranged by PCU).
Review of the first draft by stakeholders and submission of written
comments directly to the evaluator with copy to PCU
Presentation of the draft report by the consultant at the Regional Project
Steering Committee meeting
By 6 November 2015
By 13 November 2015
By 20 November 2015
By 4 December 2015
By 9 December 2015
Deadline for the submission of comments on the draft report by
stakeholders to the evaluator (in English, French or Portuguese)
Translation of comments, as necessary (A translator arranged by PCU, but
the evaluator to directly deal with the translator).
Submission of the final report (in English), incorporating comments, by the
evaluator to UNEP and UNDP.
Preparation & Issue of Management Response by UNEP and UNDP
Submission of the final MTR report and the Management Response to GEF
(by UNEP)
Final MTR report and Management Response posted online (by UNEP and
UNDP)
Expected date of full MTR completion
13. Logistical Arrangements
This Mid-term Evaluation will be undertaken by one independent evaluation consultant to be contracted by
UNOPS. The consultant will work under the overall guidance provided by the UNEP Task Manager and the UNDP
Regional Technical Advisor. The project team will, where possible, provide logistical support (introductions,
meetings etc.) allowing the consultants to conduct the evaluation as efficiently and independently as possible. It is,
however, the consultant’s individual responsibility to arrange for their travel, visa, obtain documentary evidence,
plan meetings with stakeholders, organize online surveys, and any other logistical matters related to the
assignment.
Annex 1. Annotated Table of Contents of the main evaluation deliverables
Annex 2. Evaluation Ratings
Annex 3. Project costs and co-financing tables
Annex 4. Documentation list for the evaluation to be provided by the UNEP, UNDP and Project Team
Annex 5. Template for the assessment of the quality of project design
Annex 6. Introduction to Theory of Change / Impact pathways, the ROtI Method and the ROtI Results Score sheet
(old version – A new version is under development)
Annex 7. Stakeholder Analysis for the Evaluation Inception Report.
Annex 1. Annotated Table of Contents of the main evaluation deliverables
INCEPTION REPORT
Section
Notes
Data Sources
Max. number of
pages
1
1. Introduction
Brief introduction to the project and
evaluation.
2. Project background
Summarise the project context and
rationale. How has the context of the
project changed since project design?
Background
information on
context
3
3.Stakeholder analysis
See notes in Annex 7
1
4. Review of project
design
Summary of project design strengths
and weaknesses. Complete the
Template for assessment of the quality
of project design (Annex 5 of the Terms
of Reference).
Project document
Project preparation
phase.
TM/PM
Project document and
revisions
5. Reconstructed
Theory of Change
The Theory of Change should be
reconstructed, based on project
documentation. It should be presented
with one or more diagrams and
explained with a narrative (see Annex
6).
The evaluation framework will contain:
 Detailed evaluation questions
(including new questions raised by
review of project design and ToC
analysis) and indicators
 Data Sources
It will be presented as a matrix, showing
questions, indicators and data sources.
Description of the approach and
methods that the consultant will use to
promote reflection and learning
through the evaluation process.
Project document
narrative, logical
framework and
budget tables. Other
project related
documents.
Review of all project
documents.
2 pages of
narrative +
diagram(s)
Review of project
documents,
stakeholder analysis,
discussions with the
Evaluation Manager,
Task Manager and
Project Coordinator
Discussion with
project team on
logistics.
1
6. Evaluation
framework
7. Learning,
Communication and
outreach
8. Evaluation schedule
-
-
Updated timeline for the overall
evaluation (dates of travel and key
evaluation milestones, based on
the indicative schedule included in
the TOR)
Proposed schedule for field visits,
accompanied by a proposed
itinerary and cost estimates
2 + completed
matrix provided in
annex of the
inception report
5
2
9. Annexes
A- Completed matrix of the overall
quality of project design
B- List of individuals and documents
consulted for the inception report
C- List of documents and individuals to
be consulted during the main
evaluation phase
MAIN REPORT
Project Identification Table
An updated version of the Table 1 (page 1) of these TORs
Executive Summary
Overview of the main findings, conclusions and recommendations of the
evaluation. It should encapsulate the essence of the information
contained in the report to facilitate dissemination and distillation of
lessons. The main points for each evaluation parameter should be
presented here (with a summary ratings table), as well as the most
important lessons and recommendations. Maximum 4 pages.
I. Introduction
A very brief introduction, mentioning the name of evaluation and project,
project duration, cost, implementing partners and objectives of the
evaluation.
Objectives, approach and limitations of the evaluation
II. The Project
A. Context
Overview of the broader institutional and country context, in relation to
the project’s objectives, including changes during project implementation.
Factors to address include:

The complexity of the project implication arrangements (no.of
partners/components, geographical scope, ambitiousness of
objective)

The proportion of the Project Managers
time/workplan available to the project

The ease or difficulty of the project’s external operating
environment (climate, infrastructure, political/economic
stability, socio-cultural factors)

Perceived capacity/expertise of executing partners
B. Objectives and components
C. Target areas/groups
D. Milestones/key dates in project
design and implementation
E. Implementation arrangements
F. Project financing
G. Project partners
H. Changes in design during
implementation
I. Reconstructed Theory of Change of
the project
III. Evaluation Findings
Estimated costs and funding sources
and
FMO’s
A. Strategic relevance
B. Achievement of outputs
C. Effectiveness: Attainment of
project objectives and results
This chapter is organized according to the evaluation criteria presented in
section II.4 of the TORs and provides factual evidence relevant to the
questions asked and sound analysis and interpretations of such evidence.
This is the main substantive section of the report. Ratings are provided at
the end of the assessment of each evaluation criterion.
i. Direct outcomes from
reconstructed TOC
ii. Likelihood of impact using
RoTI and based on reconstructed
TOC
iii. Achievement of project goal
and planned objectives
D. Sustainability and replication
E. Efficiency
F. Factors affecting performance
IV. Conclusions and Recommendations
A. Conclusions
This section should summarize the main conclusions of the evaluation,
told in a logical sequence from cause to effect. It is suggested to start with
the positive achievements and a short explanation why these could be
achieved, and, then, to present the less successful aspects of the project
with a short explanation why. The conclusions section should end with
the overall assessment of the project. Avoid presenting an “executive
summary”-style conclusions section. Conclusions should be crossreferenced to the main text of the report (using the paragraph
numbering). The overall ratings table should be inserted here (see Annex
2).
B. Lessons Learned
Lessons learned should be anchored in the conclusions of the evaluation.
In fact, no lessons should appear which are not based upon an explicit
finding of the evaluation. Lessons learned are rooted in real project
experiences, i.e. based on good practices and successes which could be
replicated or derived from problems encountered and mistakes made
which should be avoided in the future. Lessons learned must have the
potential for wider application and use. Lessons should briefly describe
the context from which they are derived and specify the contexts in which
they may be useful.
C. Recommendations
As for the lessons learned, all recommendations should be anchored in
the conclusions of the report, with proper cross-referencing.
Recommendations are actionable proposals on how to resolve concrete
problems affecting the project or the sustainability of its results. They
should be feasible to implement within the timeframe and resources
available (including local capacities), specific in terms of who would do
what and when, and set a measurable performance target. In some cases,
it might be useful to propose options, and briefly analyse the pros and
cons of each option.
It is suggested, for each recommendation, to first briefly summarize the
finding it is based upon with cross-reference to the section in the main
report where the finding is elaborated in more detail. The
recommendation is then stated after this summary of the finding.
Recommendations should be SMART - Specific, Measurable, Achievable,
Result-oriented and Time-bound
Annexes
These may include additional material deemed relevant by the evaluator
but must include:
1. Response to stakeholder comments received but not (fully) accepted by
the evaluators
2. Evaluation TORs (without annexes)
3. Evaluation program, containing the names of locations visited and the
names (or functions) and contacts (Email) of people met
4. Bibliography
5. Summary co-finance information and a statement of project
expenditure by activity (See annex 3 of these TORs)
6. Evaluation findings and lessons. A short and simple presentation of
evaluation findings and lessons ensures that information is easily
accessible to a wide range of audiences. (Use the 2-page template
provided in Annex 2)
7. Any other communication and outreach tools used to disseminate
results (e.g. power point presentations, charts, graphs, videos, case
studies, etc.)
6. Brief CVs of the consultants
Important note on report formatting and layout
Reports should be submitted in Microsoft Word “.doc” or “.docx” format. Use of Styles (Headings etc.), page
numbering and numbered paragraphs is compulsory from the very first draft report submitted. Consultants should
make sure to gather media evidence, especially photographs, during the assignment and insert a sample in the
final report in the appropriate sections. All media collected during the assignment shall become property of the
UNEP and UNDP; which shall ensure that the authors are recognised as copyright owners. The consultant(s) grants
permission to the UNEP and UNDP to reproduce the photographs in any size or quantity for use in official
publications. The consultant(s) shall seek permission before taking any photographs in which persons are
recognisable and to inform them that the photographs may be used in UNEP and UNDP official publications.
Examples of UNEP Mid-term Evaluation Reports are available at www.unep.org/eou.
Annex 2. Evaluation Ratings
The evaluation will provide individual ratings for the evaluation criteria.
Most criteria will be rated on a six-point scale as follows: Highly Satisfactory (HS); Satisfactory (S); Moderately
Satisfactory (MS); Moderately Unsatisfactory (MU); Unsatisfactory (U); Highly Unsatisfactory (HU). Sustainability is
rated from Highly Likely (HL) down to Highly Unlikely (HU).
In the conclusions section of the report, ratings will be presented together in a table, with a brief justification
cross-referenced to the findings in the main body of the report.
Criterion
A. Strategic relevance
B. Achievement of outputs
C. Effectiveness: Attainment of project
objectives and results
1. Achievement of direct outcomes
2. Likelihood of impact
3. Achievement of project goal and planned
objectives
D. Sustainability and replication
1. Financial
2. Socio-political
3. Institutional framework
4. Environmental
5. Catalytic role and replication
E. Efficiency
F. Factors affecting project performance
1. Preparation and readiness
2. Project implementation and management
3. Stakeholders participation and public
awareness
4. Country ownership and driven-ness
5. Financial planning and management
6. UNEP supervision and backstopping
7. Monitoring and evaluation
a. M&E Design
b. Budgeting and funding for M&E
activities
c. M&E pPlan Implementation
Overall project rating
Summary Assessment
Rating
HS  HU
HS  HU
HS  HU
HS  HU
HS  HU
HS  HU
HL  HU
HL  HU
HL  HU
HL  HU
HL  HU
HS  HU
HS  HU
HS  HU
HS  HU
HS  HU
HS  HU
HS  HU
HS  HU
HS  HU
HS  HU
HS  HU
HS  HU
HS  HU
Rating for effectiveness: Attainment of project objectives and results. An aggregated rating will be provided for
the achievement of direct outcomes as determined in the reconstructed Theory of Change of the project, the
likelihood of impact and the achievement of the formal project goal and objectives. This aggregated rating is not a
simple average of the separate ratings given to the evaluation sub-criteria, but an overall judgement of project
effectiveness by the consultants.
Ratings on sustainability. All the dimensions of sustainability are deemed critical. Therefore, the overall rating for
sustainability will be the lowest rating on the separate dimensions.
Ratings on Financial planning and management: An aggregated rating will be provided based on an average of
the various component ratings listed in the table below. Please include this table as an annex in the main report:
GEF projects
Financial management
components
Attention paid to
compliance with
procurement rules and
regulations
Contact/communication
between the PM & FMO
PM & FMO knowledge
of the project financials
FMO responsiveness to
financial requests
PM & FMO
responsiveness to
addressing and
resolving financial
issues
Rating
Evidence/ Comments
HS:HU
HS:HU
HS:HU
HS:HU
HS:HU
Were the
following
documents
provided
to the
evaluator:
A.
B.
C.
D.
An up to
date cofinancing
table
A summary
report on
the projects
financial
management
and
expenditures
during the
life of the
project - to
date
A summary
of financial
revisions
made to the
project and
their
purpose
Copies of
any
Y/N
Y/N
Y/N
Y/N
completed
audits
Availability of project
financial reports and
audits
Timeliness of project
financial reports and
audits
Quality of project
financial reports and
audits
FMO knowledge of
partner financial
requirements and
procedures
Overall rating
HS:HU
HS:HU
HS:HU
HS:HU
Ratings of monitoring and evaluation. The M&E system will be rated on M&E design, M&E plan implementation,
and budgeting and funding for M&E activities (the latter sub-criterion is covered in the main report under M&E
design). M&E plan implementation will be considered critical for the overall assessment of the M&E system. Thus,
the overall rating for M&E will not be higher than the rating on M&E plan implementation.
Overall project rating. The overall project rating should consider parameters ‘A-E’ as being the most important
with ‘C’ and ‘D’ in particular being very important.
Annex 3. Project costs and co-financing tables
Project Costs
Component/subcomponent/output
Estimated cost at design
Actual Cost
Expenditure
ratio
(actual/planned)
Co-financing
UNEP own
Financing
(US$1,000)
Co financing
(Type/Source)
Planne
d

Actua
l
Government
Other*
Total
(US$1,000)
(US$1,000)
(US$1,000)
Planne
d
Actua
l
Planne
d
Actua
l
Planne
d
Total
Disbursed
(US$1,000
)
Actua
l
Grants
Loans
Credits
Equity investments
In-kind support
Other (*)





Total
s
* This refers to contributions mobilized for the project from other multilateral agencies, bilateral development
cooperation agencies, NGOs, the private sector and beneficiaries.
Annex 4. Documentation list for the evaluation to be provided by the UNEP, UNDP and
Project Team













Project design documents (Approved Project Identification Form (PIF), Project Document and Annexes,
minutes from the project validation meeting, GEF IW Tracking Tool completed prior to the GEF CEO
Endorsement, etc.)
GEF IW Tracking Tool completed prior to the MTR process starts, cleared by UNEP and UNDP
Project supervision plan, with associated budget
Correspondence related to project
Supervision mission reports
Steering Committee meeting documents, including agendas, meeting minutes, and any summary reports
Project progress reports, including financial reports submitted
Project Implementation Reviews (PIRs)
Management memos related to project
Other documentation of supervision feedback on project outputs and processes (e.g. comments on draft
progress reports, etc.).
Project revision and extension documentation
Specific project outputs: guidelines, manuals, training tools, software, websites, press communiques,
posters, videos and other advertisement materials etc.
Any other relevant document deemed useful for the evaluation
Annex 5. Template for the assessment of the quality of project design
General guideline:
The original project document, the TOC-D, and the RTOC-D are key sources of information for
completing this assessment.
1. Project Document
Project preparation and readiness
1
Does the project document provide a
description of stakeholder consultation
during project design process?
2
Does the project document include a clear
stakeholder analysis? Are stakeholder needs
and priorities clearly understood and
integrated in project design? (see annex 9)
3
Does the project document entail a clear
situation analysis?
4
Does the project document entail a clear
problem analysis?
5
Does the project document entail a clear
gender analysis?
Relevance
6
Is the project document
i)
clear in terms of relevance
to:
7
8
9
10
Is the project document
i)
clear in terms of relevance
Global,
Regional,
Sub-regional
and National
environment
al issues and
needs?
ii)
UNEP
mandate
iii) the relevant
GEF
focal
areas, strategic
priorities and
operational
programme(s)?
(if appropriate)
iv) Stakeholder
priorities and
needs?
Gender
equity
Addressed
by PRC
Evaluation Comments
Rating
Addressed
by PRC
Evaluation Comments
Rating
11
to cross-cutting issues ii)
12
iii)
Intended
Causality
13
14
15
16
17
18
19
20
21
22
23
24
Results
SouthSouth
Cooperatio
n
Bali
Strategic
Plan
and
Are the outcomes realistic?
Are the causal pathways from project
outputs [goods and services] through
outcomes
[changes
in
stakeholder
behaviour] towards impacts clearly and
convincingly described? Is there a clearly
presented Theory of Change or intervention
logic for the project?
Is the timeframe realistic? What is the
likelihood that the anticipated project
outcomes can be achieved within the stated
duration of the project?
Are activities appropriate to produce
outputs?
Are activities appropriate to drive change
along the intended causal pathway(s)?
Are impact drivers and assumptions clearly
described for each key causal pathway?
Are the roles of key actors and stakeholders
clearly described for each key causal
pathway?
Is the ToC-D terminology (result levels,
drivers, assumptions etc.) consistent with
UNEP definitions (Programme Manual)
Efficiency
Does the project intend to make use of /
build
upon
pre-existing
institutions,
agreements and partnerships, data sources,
synergies and complementarities with other
initiatives, programmes and projects etc. to
increase project efficiency?
Sustainability / Replication and Catalytic
effects
Does the project design present a strategy /
approach to sustaining outcomes / benefits?
Does the design identify social or political
factors that may influence positively or
negatively the sustenance of project results
and progress towards impacts?
Does the design foresee sufficient activities
to promote government and stakeholder
awareness, interests, commitment and
Addressed
by PRC
Addressed
by PRC
Addressed
by PRC
25
26
27
28
29
30
incentives to execute, enforce and pursue
the programmes, plans, agreements,
monitoring systems etc. prepared and
agreed upon under the project?
If funding is required to sustain project
outcomes and benefits, does the design
propose adequate measures / mechanisms
to secure this funding?
Are financial risks adequately identified and
does the project describe a clear strategy on
how to mitigate the risks (in terms of
project’s sustainability)
Does the project design adequately describe
the institutional frameworks, governance
structures and processes, policies, subregional
agreements,
legal
and
accountability frameworks etc. required to
sustain project results?
Does
the
project
design
identify
environmental factors, positive or negative,
that can influence the future flow of project
benefits? Are there any project outputs or
higher level results that are likely to affect
the environment, which, in turn, might affect
sustainability of project benefits?
Does the project design foresee adequate
measures to promote replication and upscaling / does the project have a clear
strategy to promote replication and upscaling?
Are the planned activities likely to generate
the level of ownership by the main national
and regional stakeholders necessary to allow
for the project results to be sustained?
Learning, Communication and outreach
Addressed
by PRC
Has the project identified appropriate
methods for communication with key
stakeholders during the project life?
Are plans in place for dissemination of
results and lesson sharing.
Do learning, communication and outreach
plans build on analysis of existing
communication channels and networks used
by key stakeholders ?
Risk identification and Social Safeguards
31
Are all assumptions identified in the ToC
presented as risks in the risk management
table? Are risks appropriately identified in
both, ToC and the risk table?
Addressed
by PRC
32
33
34
35
36
37
38
39
40
41
42
43
44
Is
the
risk
management
strategy
appropriate?
Are potentially negative environmental,
economic and social impacts of projects
identified?
Does the project have adequate mechanisms
to reduce its negative environmental footprint?
Have risks and assumptions been discussed
with key stakeholders?
Governance and Supervision Arrangements
Is
the
project
governance
model
comprehensive, clear and appropriate?
(Steering Committee, partner consultations
etc. )
Are supervision / oversight arrangements
clear and appropriate?
Management, Execution and Partnership
Arrangements
Have the capacities of partners been
adequately assessed?
Are the execution arrangements clear and
are roles and responsibilities within UNEP
clearly defined?
Are the roles and responsibilities of external
partners properly specified?
Financial Planning / budgeting
Are there any obvious deficiencies in the
budgets / financial planning? (coherence of
the budget, do figures add up etc.)
Has budget been reviewed and agreed to be
realistic with key project stakeholders?
Is the resource utilization cost effective?
How realistic is the resource mobilization
strategy?
Are the financial and administrative
arrangements including flows of funds
clearly described?
Monitoring
Does
the
framework
logical 
capture the
key
elements of
the Theory
of Change
for the
project?
Addressed
by PRC
Addressed
by PRC
Addressed
by PRC
Addressed
by PRC
-
45
46
47
48
49
50
51
52
53
54
55

have
‘SMART’
indicators
for
outcomes
and
objectives?
-

have
appropriate
'means of
verification'
?
-
Are the milestones appropriate and
sufficient to track progress and foster
management
towards
outputs
and
outcomes?
Is there baseline information in relation to
key performance indicators?
How well has the method for the baseline
data collection been explained?
Has the desired level of achievement
(targets) been specified for indicators of
outputs and outcomes?
How well are the performance targets
justified for outputs and outcomes?
Has a budget been allocated for monitoring
project progress in implementation against
outputs and outcomes?
Does the project have a clear knowledge
management approach?
Have mechanisms for involving key project
stakeholder groups in monitoring activities
been clearly articulated?
Evaluation
Addressed
by PRC
Is there an adequate plan for evaluation?
Has the time frame for evaluation activities
been specified?
Is there an explicit budget provision for midterm review and terminal evaluation?
Is the budget sufficient?
2. Project alignment with the Sub programme
Addressed
by PRC
Evaluation Comments
Rating
1
2
3
4
5
6
7
8
9
10
11
12
13
Does the project form a
coherent
part
of
the
programme framework?
Is the relevance of the project
in terms of SP higher level
results clearly described?
How well have linkages with
other projects in the same
Programme Framework been
described?
Where linkages with other SPs
are mentioned, are they well
articulated?
If the project is a pilot, is it
clear why the pilot is relevant
to higher level SP results?
Are the designed activities
relevant
in
terms
of
contributing / producing the
identified PoW Output(s)?
(Based on project design only)
Are
output
indicators
appropriate
to
measure
contribution to / delivery of
the PoW Output(s)?
What is the likelihood that the
project’s contribution towards
PoW output(s) will be
achieved within the duration
of the PoW? (consider also
funding, timing, staffing etc.)
Are the intended results likely
to contribute to the stated
EA? (Based on design only)
Is the pathway from project
outputs to EA contribution
clearly described?
Are the indicators appropriate
to measure contribution to
EA?
What is the likelihood that the
project’s contribution towards
the EA will be achieved within
the duration of the PoW?
(Consider also funding, timing,
staffing etc.)
Do project milestones track
progress to PoW output and
all the way to the EA?
3. Project approval process (specific to the project under review)
Evaluation Comments
1
2
3
What were the main issues raised by PRC that were
addressed?
What were the main issues raised by PRC that were
not addressed?
Were there any major issues not flagged by PRC?
Annex 6. Introduction to Theory of Change / Impact pathways, the ROtI Method and the ROtI Results
Score sheet (old version – A new version is under development)
Terminal evaluations of projects are conducted at, or shortly after, project completion. At this stage it is normally
possible to assess the achievement of the project’s outputs. However, the possibilities for evaluation of the
project’s outcomes are often more limited and the feasibility of assessing project impacts at this time is usually
severely constrained. Full impacts often accrue only after considerable time-lags, and it is common for there to be
a lack of long-term baseline and monitoring information to aid their evaluation. Consequently, substantial
resources are often needed to support the extensive primary field data collection required for assessing impact
and there are concomitant practical difficulties because project resources are seldom available to support the
assessment of such impacts when they have accrued – often several years after completion of activities and
closure of the project.
Despite these difficulties, it is possible to enhance the scope and depth of information available from Terminal
Evaluations on the achievement of results through rigorous review of project progress along the pathways from
outcome to impact. Such reviews identify the sequence of conditions and factors deemed necessary for project
outcomes to yield impact and assess the current status of and future prospects for results. In evaluation literature
these relationships can be variously described as ‘Theories of Change’, Impact ‘Pathways’, ‘Results Chains’,
‘Intervention logic’, and ‘Causal Pathways’ (to name only some!).
Theory of Change (ToC) / impact pathways
Figure 1 shows a generic impact pathway which links the standard elements of project logical frameworks in a
graphical representation of causal linkages. When specified with more detail, for example including the key users
of outputs, the processes (the arrows) that lead to outcomes and with details of performance indicators, analysis
of impact pathways can be invaluable as a tool for both project planning and evaluation.
Figure 1. A generic results chain, which can also be termed an ‘Impact Pathway’ or Theory of Change.
The pathways summarise casual relationships and help identify or clarify the assumptions in the intervention logic
of the project. For example, in the Figure 2 below the eventual impact depends upon the behaviour of the farmers
in using the new agricultural techniques they have learnt from the training. The project design for the intervention
might be based on the upper pathway assuming that the farmers can now meet their needs from more efficient
management of a given area therefore reducing the need for an expansion of cultivated area and ultimately
reducing pressure on nearby forest habitat, whereas the evidence gathered in the evaluation may in some
locations follow the lower of the two pathways; the improved farming methods offer the possibility for increased
profits and create an incentive for farmers to cultivate more land resulting in clearance or degradation of the
nearby forest habitat.
Figure 2. An impact pathway / TOC for a training intervention intended to aid forest conservation.
The GEF Evaluation Office has recently developed an approach to assess the likelihood of impact that builds on the
concepts of Theory of Change / causal chains / impact pathways. The method is known as Review of Outcomes to
Impacts (ROtI)5 and has three distinct stages:
a.
Identifying the project’s intended impacts
b.
Review of the project’s logical framework
c.
Analysis and modelling of the project’s outcomes-impact pathways: reconstruction of the
project’s Theory of Change
The identification of the projects intended impacts should be possible from the ‘objectives’ statements specified
in the official project document. The second stage is to review the project’s logical framework to assess whether
the design of the project is consistent with, and appropriate for, the delivery of the intended impact. The method
requires verification of the causal logic between the different hierarchical levels of the logical framework moving
‘backwards’ from impacts through outcomes to the outputs; the activities level is not formally considered in the
ROtI method6. The aim of this stage is to develop an understanding of the causal logic of the project intervention
and to identify the key ‘impact pathways’. In reality such processes are often complex: they might involve multiple
actors and decision-processes and are subject to time-lags, meaning that project impact often accrues long after
the completion of project activities.
The third stage involves analysis of the ‘impact pathways’ that link project outcomes to impacts. The pathways are
analysed in terms of the ‘assumptions’ and ‘drivers’ that underpin the processes involved in the transformation of
outputs to outcomes to impacts via intermediate states (see Figure 3). Project outcomes are the direct intended
results stemming from the outputs, and they are likely to occur either towards the end of the project or in the
short term following project completion. Intermediate states are the transitional conditions between the project’s
direct outcomes and the intended impact. They are necessary changes expected to occur as a result of the project
outcomes, that are expected, in turn, to result into impact. There may be more than one intermediate state
between the immediate project outcome and the eventual impact. When mapping outcomes and intermediate
states its important to include reference to the stakeholders who will action or be effected by the change.
Drivers are defined as the significant, external factors that if present are expected to contribute to the realization
of the intended impacts and can be influenced by the project / project partners & stakeholders. Assumptions are
5 GEF Evaluation Office (2009). ROtI: Review of Outcomes to Impacts Practitioners Handbook.
http://www.gefweb.org/uploadedFiles/Evaluation_Office/OPS4/Roti%20Practitioners%20Handbook%2015%20June%202009.p
df
6
Evaluation of the efficiency and effectiveness in the use of resources to generate outputs is already a major focus within UNEP
Terminal Evaluations.
the significant external factors that if present are expected to contribute to the realization of the intended impacts
but are largely beyond the control of the project / project partners & stakeholders. The drivers and assumptions
are considered when assessing the likelihood of impact, sustainability and replication potential of the project.
Since project logical frameworks do not often provide comprehensive information on the processes by which
project outputs yield outcomes and eventually lead, via ‘intermediate states’ to impacts, the impact pathways
need to be carefully examined and the following questions addressed:
o
Are there other causal pathways that would stem from the use of project outputs by other potential
user groups?
o
Is (each) impact pathway complete? Are there any missing intermediate states between project
outcomes and impacts?
o
Have the key drivers and assumptions been identified for each ‘step’ in the impact pathway.
Figure 3. A schematic ‘impact pathway’ showing intermediate states, assumptions and impact drivers7 (adapted
from GEF EO 2009)
In ideal circumstances, the Theory of Change of the project is reconstructed by means of a group exercise,
involving key project stakeholders. The evaluators then facilitate a collective discussion to develop a visual model
of the impact pathways using cards and arrows taped on a wall. The component elements (outputs, outcomes,
intermediate states, drivers, assumptions, intended impacts etc.) of the impact pathways are written on individual
cards and arranged and discussed as a group activity. Figure 4 below shows the suggested sequence of the group
discussions needed to develop the ToC for the project.
7
The GEF frequently uses the term “impact drivers” to indicate drivers needed for outcomes to lead to impact. However, in
UNEP it is preferred to use the more general term “drivers” because such external factors might also affect change processes
occurring between outputs and outcomes.
Figure 4. Suggested sequencing of group discussions (from GEF EO 2009)
In practice, there is seldom an opportunity for the evaluator to organise such a group exercise during the inception
phase of the evaluation. The reconstruction of the project’s Theory of Change can then be done in two stages. The
evaluator first does a desk-based identification of the project’s impact pathways, specifying the drivers and
assumptions, during the inception phase of the evaluation, and then, during the main evaluation phase, (s)he
discusses this understanding of the project logic during group discussions or the individual interviews with key
project stakeholders.
Once the Theory of Change for the project is reconstructed, the evaluator can assess the design of the project
intervention and collate evidence that will inform judgments on the extent and effectiveness of implementation,
through the evaluation process. Performance judgments are made always noting that project contexts can change
and that adaptive management is required during project implementation.
The Review of Outcomes towards Impact (ROtI) method requires ratings for outcomes achieved by the project and
the progress made towards the ‘intermediate states’ at the time of the evaluation. According to the GEF guidance
on the method; “The rating system is intended to recognize project preparation and conceptualization that
considers its own assumptions, and that seeks to remove barriers to future scaling up and out. Projects that are a
part of a long-term process need not at all be “penalized” for not achieving impacts in the lifetime of the project:
the system recognizes projects’ forward thinking to eventual impacts, even if those impacts are eventually achieved
by other partners and stakeholders, albeit with achievements based on present day, present project building blocks.”
For example, a project receiving an “AA” rating appears likely to deliver impacts, while for a project receiving a “DD”
this would be very unlikely, due to low achievement in outcomes and the limited likelihood of achieving the
intermediate states needed for eventual impact (see Table 1).
Table 1. Rating scale for outcomes and progress towards ‘intermediate states’
Outcome Rating
Rating on progress toward Intermediate States
D: The project’s intended outcomes were not
delivered
C: The project’s intended outcomes were
delivered, but were not designed to feed into a
continuing process after project funding
B: The project’s intended outcomes were
delivered, and were designed to feed into a
continuing process, but with no prior allocation
of responsibilities after project funding
D: No measures taken to move towards intermediate states.
C: The measures designed to move towards intermediate
states have started, but have not produced results.
B: The measures designed to move towards intermediate
states have started and have produced results, which give no
indication that they can progress towards the intended long
term impact.
A: The project’s intended outcomes were
delivered, and were designed to feed into a
continuing process, with specific allocation of
responsibilities after project funding.
A: The measures designed to move towards intermediate
states have started and have produced results, which clearly
indicate that they can progress towards the intended long
term impact.
Thus a project will end up with a two letter rating e.g. AB, CD, BB etc. In addition the rating is given a ‘+’ notation if
there is evidence of impacts accruing within the life of the project. The possible rating permutations are then
translated onto the usual six point rating scale used in all UNEP project evaluations in the following way.
Table 2. Shows how the ratings for ‘achievement of outcomes’ and ‘progress towards intermediate states
translate to ratings for the ‘Overall likelihood of impact achievement’ on a six point scale.
Highly
Likely
Likely
Moderately
Likely
Moderately
Unlikely
AA AB BA CA
BB+ CB+ DA+
DB+
BB CB DA DB
AC+ BC+
AC BC CC+ DC+
CC DC AD+ BD+
Unlikely
AD BD
DD+
CD+
Highly Unlikely
CD DD
In addition, projects that achieve documented changes in environmental status during the project’s lifetime
receive a positive impact rating, indicated by a “+”. The overall likelihood of achieving impacts is shown in Table 11
below (a + score above moves the double letter rating up one space in the 6-point scale).
The ROtI method provides a basis for comparisons across projects through application of a rating system that can
indicate the expected impact. However it should be noted that whilst this will provide a relative scoring for all
projects assessed, it does not imply that the results from projects can necessarily be aggregated. Nevertheless,
since the approach yields greater clarity in the ‘results metrics’ for a project, opportunities where aggregation of
project results might be possible can more readily be identified.
1.
2.
3.
1.
2.
3.
Rating
justification:
Intermediate states
1.
2.
3.
Rating justification:
Impact (GEBs)
Rati
ng
Ove
(+)
rall
Outcomes
Rati
ng
(D –
A)
Outputs
Rati
ng
(D –
A)
Results rating of
project entitled:
1.
2.
3.
Rating
justification:
Scoring Guidelines
The achievement of Outputs is largely assumed. Outputs are such concrete things as training courses held,
numbers of persons trained, studies conducted, networks established, websites developed, and many others.
Outputs reflect where and for what project funds were used. These were not rated: projects generally succeed in
spending their funding.
Outcomes, on the other hand, are the first level of intended results stemming from the outputs. Not so much the
number of persons trained; but how many persons who then demonstrated that they have gained the intended
knowledge or skills. Not a study conducted; but one that could change the evolution or development of the project.
Not so much a network of NGOs established; but that the network showed potential for functioning as intended. A
sound outcome might be genuinely improved strategic planning in SLM stemming from workshops, training
courses, and networking.
Examples
Funds were spent, outputs were produced, but nothing in terms of outcomes was achieved. People
attended training courses but there is no evidence of increased capacity. A website was developed, but no
one used it. (Score – D)
Outcomes achieved but are dead ends; no forward linkages to intermediate states in the future. People
attended training courses, increased their capacities, but all left for other jobs shortly after; or were not
given opportunities to apply their new skills. A website was developed and was used, but achieved little or
nothing of what was intended because users had no resources or incentives to apply the tools and methods
proposed on the website in their job. (Score – C)
Outcomes plus implicit linkages forward. Outcomes achieved and have implicit forward linkages to
intermediate states and impacts. Collaboration as evidenced by meetings and decisions made among a
loose network is documented that should lead to better planning. Improved capacity is in place and should
lead to desired intermediate outcomes. Providing implicit linkages to intermediate states is probably the
most common case when outcomes have been achieved. (Score - B)
Outcomes plus explicit linkages forward. Outcomes have definite and explicit forward linkages to
intermediate states and impacts. An alternative energy project may result in solar panels installed that
reduced reliance on local wood fuels, with the outcome quantified in terms of reduced C emissions. Explicit
forward linkages are easy to recognize in being concrete, but are relatively uncommon. (Score A)
Intermediate states:
The intermediate states indicate achievements that lead to Global Environmental Benefits, especially if the
potential for scaling up is established.
“Outcomes” scored C or D. If the outcomes above scored C or D, there is no need to continue forward to
score intermediate states given that achievement of such is then not possible.
In spite of outcomes and implicit linkages, and follow-up actions, the project dead-ends. Although
outcomes achieved have implicit forward linkages to intermediate states and impacts, the project deadends. Outcomes turn out to be insufficient to move the project towards intermediate states and to the
eventual achievement of GEBs. Collaboration as evidenced by meetings and among participants in a
network never progresses further. The implicit linkage based on follow-up never materializes. Although
outcomes involve, for example, further participation and discussion, such actions do not take the project
forward towards intended intermediate impacts. People have fun getting together and talking more, but
nothing, based on the implicit forwards linkages, actually eventuates. (Score = D)
The measures designed to move towards intermediate states have started, but have not produced result,
barriers and/or unmet assumptions may still exist. In spite of sound outputs and in spite of explicit forward
linkages, there is limited possibility of intermediate state achievement due to barriers not removed or
unmet assumptions. This may be the fate of several policy related, capacity building, and networking
projects: people work together, but fail to develop a way forward towards concrete results, or fail to
successfully address inherent barriers. The project may increase ground cover and or carbon stocks, may
reduce grazing or GHG emissions; and may have project level recommendations regarding scaling up; but
barrier removal or the addressing of fatal assumptions means that scaling up remains limited and unlikely to
be achieved at larger scales. Barriers can be policy and institutional limitations; (mis-) assumptions may have
to do with markets or public – private sector relationships. (Score = C)
Barriers and assumptions are successfully addressed. Intermediate state(s) planned or conceived have
feasible direct and explicit forward linkages to impact achievement; barriers and assumptions are
successfully addressed. The project achieves measurable intermediate impacts, and works to scale up and
out, but falls well short of scaling up to global levels such that achievement of GEBs still lies in doubt. (Score
= B)
Scaling up and out over time is possible. Measurable intermediate state impacts achieved, scaling up to
global levels and the achievement of GEBs appears to be well in reach over time. (Score = A)
Impact: Actual changes in environmental status
“Intermediate states” scored B to A.
Measurable impacts achieved at a globally significant level within the project life-span. . (Score = ‘+’)
Annex 7. Stakeholder Analysis for the Evaluation Inception Report.
The evaluator should request the project team to provide a list of key stakeholders, and evidence of
stakeholder mapping and analysis. If the project is unable to provide this, or if the evaluation team feels
the information provided is not complete, the evaluator should develop the stakeholder map based on
evidence provided in the project document (and using methods described in the programme manual or
other stakeholder mapping techniques of their choice).
The purpose of stakeholder analysis in the preparation of the evaluation inception report is:
1. To understand which individuals or groups are likely to have been affected by, or to have
affected the activities of the project.
2. To ensure that the evaluation methodology includes mechanisms for the participation of key
stakeholder groups in the process.
3. To enable the evaluation to identify and make use of key channels of communication between
the project and its stakeholders (and between the stakeholders themselves).
In the review of Project design the evaluator should assess whether the project address the following
issues (as specified by UNEP’s Quality Assessment Section8):





Have all stakeholders9 who are affected by or who could affect (positively or negatively) the project
been identified and explained in the stakeholder analysis?
Did the main stakeholders participate in the design stages of the project and did their involvement
influence the project design?
Are the economic, social and environmental impacts to the key stakeholders identified, with
particular reference to the most vulnerable groups10?
Have the specific roles and responsibilities of the key stakeholders been documented in relation to
project delivery and effectiveness?
For projects operating at country level, are the stakeholder roles country specific? Is there a lead
national or regional partner for each country/region involved in the project?
In the review of project outputs and outcomes, the evaluation should consider:
Were outputs accessible to all the relevant stakeholder groups?
Have desired outcomes and impacts occurred amongst all stakeholder groups (and if not, consider why
this might be).
8
See The Quality Assessment Section’s Matrix for Project Review. Information on stakeholder analysis can also be found in
UNEP’s programme manual.
9
Stakeholders can be governmental and non-governmental stakeholders, including business and industry. Project beneficiaries
are often representatives of Civil Society and within UNEP defined as the belonging to the nine Major Groups as defined in the
Agenda 21: Business and Industries, Children & Youth, Farmers, Indigenous People and their communities, Local Authorities,
NGO’s, the Scientific & Technological Community, Women, Workers and Trade Unions.
10
Vulnerable groups such as: women, children, youth, elderly people, indigenous peoples, local communities, persons with
disabilities and below poverty line
Have there been any unanticipated outcomes or impacts with particular reference to the most
vulnerable groups.
In the review of factors affecting performance the evaluation should consider:
 Participation of key stakeholders
 What were the roles and responsibilities of key stakeholders and how did their performance affect
the achievement of project outputs and outcomes.
Download