MerC23 Unit Area 3 Checklist

advertisement
Number:
Revision
Page
Meraux Refinery Hurricane Preparedness Plan
Area 3 Checklist
1
2
Actions - Docks
Secure automatic Dock gate in open
position.
Secure oil boom located North of Boat
Platform.
3
Tie down drum for meter prover ball.
4
Secure tool box for meter prover.
5
Secure necessary lube oil drums.
6
Secure all life ring cabinets.
7
8
All hoses on Unloading Dock should be
placed in a lying down position and secure
all cables.
Secure all 350# and 150# fire extinguisher
wheel units.
9
Secure all fire hoses in racks.
10
Place Stretcher at Unloading Dock inside
Sample Room.
11
Secure all trash drums.
12
Tie down portable foam units and hoses.
13
Secure sample box at Loading Dock
structure.
14
Secure shield for Meter Station switch rack.
Place all fire extinguishers inside buildings,
if possible.
Adhere to U.S. Coast Guard regulations on
16 mooring of vessels (tugs, barges, ships,
etc.)
15
Responsible Party
Operations
Supervisor
Operations
Supervisor
Operations
Supervisor
Operations
Supervisor
Operations
Supervisor
Operations
Supervisor
Operations
Supervisor
Operations
Supervisor
Operations
Supervisor
Operations
Supervisor
Operations
Supervisor
Operations
Supervisor
Operations
Supervisor
Operations
Supervisor
Operations
Supervisor
Operations
Supervisor
Operations
Supervisor
Remove all loose material on the dock walk way Operations
18 that can be blown away ( empty oil cans, rags,
Supervisor
17
Pump seal to lowest level.
oil pads, etc)..
19
20
Tie down any ladders are drums on the docks.
Secure the boats at the docks.
Operations
Supervisor
Operations
Supervisor
Initial
MerC23
05/03/2011
1 of 4
Date
Time
Meraux Refinery Hurricane Preparedness Plan
Area 3 Checklist
Number:
Revision
Page
MerC23
05/03/2011
2 of 4
Number:
Revision
Page
Meraux Refinery Hurricane Preparedness Plan
Area 3 Checklist
Actions – All Areas
18
Secure all oil drums and trash containers.
19
Lash down all loading spouts at LPG Tank
Car Loading Rack.
20
Secure all snuffer chains on tank vents.
21
22
23
24
Gravitate similar products from tanks to
empty or low tanks to have adequate
materials in tanks to keep them from
moving.
Start filling empty tanks with water using
crude pumps on Unloading Dock
Note: This would be done only if there is
not sufficient product to maintain safe level
in tanks.
Pump oily separators at the latest possible
time.
Secure fire extinguishers to post in a
fashion that they may be removed easily.
25
Top fuel tanks on all vehicles.
26
Collins pump sump.
27
28
29
30
31
32
33
34
Secure all ladders in the tank farm.
Secure all porter lets and portable signs.
Climb all tanks and remove any loose debris
(piping, rope, flanges, cans, etc).
Secure all empty Chemical totes and hoses.
Secure all Lpg hoses on the Island.
Secure pentane hoses at P-6.
Secure all Portable signs.
Climb all tanks and remove any loose debris
(piping, rope, flanges, cans, etc).
Actions – Waste Water Treatment
Responsible Party
Operations
Supervisor
Operations
Supervisor
Operations
Supervisor
Operations
Supervisor
Operations
Supervisor
Operations
Supervisor
Operations
Supervisor
Operations
Supervisor
Operations
Supervisor
Operations
Supervisor
Operations
Supervisor
Operations
Supervisor
Operations
Supervisor
Operations
Supervisor
Operations
Supervisor
Operations
Supervisor
Operations
Supervisor
Operations
Supervisor
Responsible Party
Initial
MerC23
05/03/2011
3 of 4
Date
Time
Meraux Refinery Hurricane Preparedness Plan
Area 3 Checklist
Actions – Waste Water Treatment
Secure all fire extinguishers, wheel units
27
and hand portables.
28
29
30
31
32
33
34
35
36
37
38
39
40
41
Responsible Party
Operations
Supervisor
Operations
Secure perfume drum at Horseshoe Basin.
Supervisor
Operations
Secure nitrification and anti-foam drums.
Supervisor
Operations
Tie down Bug Supply House.
Supervisor
Operations
Secure lube oil drums.
Supervisor
Hazardous waste drums will be removed or Operations
secured as time permits.
Supervisor
Operations
Tie down all hoses.
Supervisor
Secure all fire extinguishers, wheel units
Operations
and hand portables.
Supervisor
Operations
Secure all portable signs.
Supervisor
Operations
Secure Mercaptan drum.
Supervisor
Operations
Lock Highway gate.
Supervisor
Operations
Secure doors on LPG Building.
Supervisor
Any ladders outside in the unit must be stored in Operations
the chemical room at the WTP control room.
Supervisor
Operations
Climb all structures and remove any loose
debris ( piping, rope, cans flanges, etc).
Supervisor
Start adding fire water to 5-3 and 1-3 if levels
Operations
are not high enough to have adequate material,
Supervisor
to prevent from moving.
42
When unit is shut down isolate tanks 80-14, 8017 and 150-2.
Operations
Supervisor
Number:
Revision
Page
MerC23
05/03/2011
4 of 4