ISIS Start-Up and Machine Physics Schedule Cycle 2015/4 : 01 – 14 February 2016 Notes: All equipment to be on and LEBT beam established by 16:30 on Friday 29th Jan. Crew ‘away day’ on 29th Jan – limited MCR functions from 23:30 on 28th to 07:30 on 30th Jan. Search and Interlock checks to be done by 08:30 on 1st Feb. Extraction energy : 800 MeV TS1 ready for MS/32 beam 16:00 on 29th Jan and MS beam 17:00 on 2nd Feb TS2 Ready for beam 08:30 on 12th Feb Beam Current limits: 205 μA on TS-1, 40 μA on TS-2 Operating Modes 4A SRBD 4B TS1 Only 4C TS2 Only 5 TS1 and TS2 Contacts DJA BA SAF ISKG BJ AHK JM AP BGP Dean Adams Bob Anderson Sarah Fisher Ian Gardner Bryan Jones Tony Kershaw John Medland Alex Pertica Ben Pine x6502 x7112 x5526 x6109 x5263 x6646 x5348 X5421 X8294 HVS AS RJM MOM CMW REW DMW Hayley Smith Andy Seville Rob Mathieson MICE Ops Chris Warsop Rob Williamson Di Wright x5524 x5689 x7037 x8188 x6374 x5388 x6267 Date Mode Rep Rate 00:00–08:30 4B MS/32 Crash tests/interlock checks Crew, MA All equip on by 16:00 Friday 29th 08:30–16:30 4B MS/32 Linac setup BJ, HVS Vibration check @ 08:30 16:30–00:00 4B MS/32 Linac setup REW 00:00–08:30 4B MS/32 08:30–16:30 4B MS/32 Linac/HEDS setup DJA 16:30–00:00 4B MS/32 Linac/HEDS setup BJ 03/02/16 00:00–08:30 Wednesday 08:30–16:30 4B MS/32 4B MS/32 Synchrotron setup BGP, HVS 16:30–00:00 4B MS/32 Synchrotron setup BJ 00:00–08:30 4B MS 08:30–16:30 4B MS Synchrotron RF setup AS, RJM 16:30–00:00 4B MS HEDS Optic Studies HVS 00:00–08:30 4B MS 08:30–16:30 4B MS Synchrotron/EPB setup BJ 16:30–00:00 4B MS Synchrotron setup CMW 00:00–08:30 4B MS 08:30–16:30 4B MS Synchrotron setup HVS 16:30–00:00 4B MS High Intensity Beams DJA 00:00–08:30 4B MS 08:30–16:30 4B MS Digital RF Tests AS, DA 16:30–00:00 4B MS Injection Dipole Measurements BJ 01/02/16 Monday 02/02/16 Tuesday 04/02/16 Thursday 05/02/16 Friday 06/02/16 Saturday 07/02/16 Sunday Shift Task Contacts Notes Date Mode Rep Rate 00:00–08:30 4B MS 08:30–16:30 4B MS Phase Space Measurement DJA, BJ, HVS 16:30–00:00 4B MS Synchrotron RF setup AS, DA 00:00–08:30 4B MS 08:30–16:30 4B MS Synchrotron setup REW 16:30–00:00 4B MS Non-linear Motion CMW, DJA, BJ 10/02/16 00:00–08:30 Wednesday 08:30–16:30 4B MS 4B MS RF Beam Comp Test ISKG 16:30–00:00 4B MS Orbit Correction, BPM Tests BJ, HVS 00:00–08:30 4B MS 08:30–16:30 4B MS Beam Transfer Function CMW, BJ, AP 16:30–00:00 4B MS High Intensity Tuning REW 00:00–08:30 5 MS Mode Change Crew 08:30–16:30 5 MS EPB2 Setup BJ, HVS 16:30–00:00 5 MS High Intensity Tuning BGP 00:00–08:30 5 MS 08:30–16:30 5 MS High Intensity Tuning CMW, REW 16:30–00:00 5 MS High Intensity Tuning DJA 00:00–08:30 5 MS 08:30–16:30 5 MS Muon Optic + High Intensity Tuning BJ, HVS 16:30–00:00 5 MS Beamline Surveys Crew, HP 08/02/16 Monday 09/02/16 Tuesday 11/02/16 Thursday 12/02/16 Friday 13/02/16 Saturday 14/02/16 Sunday Shift Task Contacts Notes