SUDAN OPERATIONS CENTRE ANNEXURE IA: SCOPE OF WORKS Introduction – The above construction works at ten recently constructed Primary Schools in Lakes State referred to in the Bills of Quantities and the Technical Specifications is planned under Italian Cooperation project and implemented by United Nations Office for Project Services (UNOPS). Sr. No 1 School Name Aber Primary school 2 Abinajok Primary school 3 Abiriu Girls Primary school 4 Agany Primary school 5 Ager Gum Primary school 6 Cueibet Girls Primary school 7 Comboni Agangrial Primary school County/Payam Work Scope Construction/installation of steel windows/cladding and brick stove on Rumbek Central existing kitchen & standpipes to two /Matangai/Aber existing rain water collection water tanks each at Aber Primary School. Construction/installation of steel windows/cladding and brick stove on Rumbek existing kitchen & standpipes to two Central/Jiir existing rain water collection water tanks each at Abinajok Primary School. Construction/installation of steel windows/cladding and brick stove on Cueibet/Abiriu existing kitchen & standpipes to two existing rain water collection water tanks each at Abiriu Girls Primary School. Construction/installation of steel windows/cladding and brick stove on Yirol existing kitchen & standpipes to two West/Aluakluak existing rain water collection water tanks each at Agany Primary School. Construction/installation of steel windows/cladding and brick stove on Rumbek existing kitchen & standpipes to two Central/Rumbek existing rain water collection water tanks Central each at Ager Gum Primary School. Construction/installation of steel windows/cladding and brick stove on Cueibet/Cueibet existing kitchen & standpipes to two Centre existing rain water collection water tanks each at Cueibet Primary School. Construction/installation of steel windows/cladding and brick stove on existing kitchen & standpipes to two Cueibet/Ngam existing rain water collection water tanks each at Comboni Agangrial Primary School. 2/9/2016 1/2 SUDAN OPERATIONS CENTRE 8 Pacong Primary school Rumbek East/Pacong 9 Panbarkor Primary school Rumbek East/Malengok 10 Yirol Girls Primary school Yirol West/Yirol Town Construction/installation of steel windows/cladding and brick stove on existing kitchen & standpipes to two existing rain water collection water tanks each at Pacong Primary School. Construction/installation of steel windows/cladding and brick stove on existing kitchen & standpipes to two existing rain water collection water tanks each at Panbarkor Primary School. Construction/installation of steel windows/cladding and brick stove on existing kitchen & standpipes to two existing rain water collection water tanks each at Yirol Girls Primary School. Scope of Works – Supply all labour, materials and equipment for the construction/installation of steel windows/cladding and brick stove on existing kitchen & standpipes to two existing rain water collection water tanks all at each of the ten primary schools listed above including all the required finishes to the approval of UNOPS’ Engineer and/or described in Bills of Quantity here with attached. All works should be compliant with the descriptions in the Technical Specifications and Bills of Quantities to meet the following main completion status. Brick Stove – Supply and construction using bricks in clay mortar to be fitted with galvanized grills and chimney as detailed in specification & drawings Masonry Wall – Construction using the concrete cement block to receive the sand cement render with smooth finish as detailed on specification, drawings & BoQ. Countertop - Casting by using reinforced concrete as detailed on drawing Windows and Cladding - Supply and fixing of window units and cladding members made of hard rigid steel on existing cladding as detailed in specification, drawings & BoQ comprising the required approved window hardware and painting to receive the Engineer’s Approval. Finishes - Rendering/plastering and required painting as detailed in specification, drawings and BoQ. Water Tank Fittings - Supply and fixing of HDPE/PPR pipes and push type taps on existing water tanks complete with related accessories as detailed on specification, drawings & BoQ. Site visit: It is recommended that the contractor should visit the site before submitting bid documents. The client will take no liability for contractor’s failure to visit the site. Site cleaning – All excess construction materials on site are to be removed and site left neat and tidy after completion of the works. All debris arising from the construction process shall be disposed as directed by the UNOPS site Engineer. 2/9/2016 2/2