About Yieldopia

advertisement
2013
25kW PV Solar
Installation, at Bab
Leather Products Incl
Off Grid solar power plant
Yieldopia Energy Private Limited
29/042013
Yieldopia Team at work
Project Description
The purpose of this project is to install Solar Photovoltaic (PV) 25 KW off grid
solar power plant. This plant may be utilized to serve the needs of the Client
2
Confidential
MCS/YEPL/BAB/25KW/VELLORE/2013
Solar Power
With the fast depletion of the non-renewable energy resources, there is a
tremendous thrust on generating renewable energy. Solar Energy has been
identified as one of the driving forces for generating electricity. During the last
two decades, the accelerated drop in silicon, which is the feedstock material for
most panels, has made it possible for solar panels to move from space-based
applications to generation of energy for consumption by the general populace.
The solar power industry is growing at a phenomenal rate globally with the US,
Germany, Spain and China leading the way. Industry experts predict an annual
growth rate of about 40 per cent for several years into the future. With escalating
international oil prices and increasing concerns about global warming, solar
power represents a strategic energy choice for the future for most of the
countries currently dependent on imported energy sources.
Similar considerations apply in India as well. Further, there has been a rapid
decline in the PV pricing in the last 2-3 months which has made a well designed
Solar power solution a better option, environmentally as well as financially to a
DG (Diesel Generator Set) power. Due to a massive deficit in the power sector
infrastructure and fuel supply use of DG has been growing rapidly in India. This
has led to many issues including a rising oil import bill, loss of revenue due to
subsidies for diesel and above all, increasing pollution in the country.
Solar PV (Photo-Voltaic) Technologies
There are two main PV technologies namely Silicon (mono-crystalline or polycrystalline) or thin films (TF). The latter includes amorphous silicon and various
chemistries from the CIGS (Cadmium, Indium, Gallium and Selenium) family of
elements.
Though TF panels have better thermal characteristics then Silicon based panels,
their lack of long term record makes them a riskier alternative. Further due to
their considerably lower power density requires a higher number of panels
resulting in a higher space requirement and BOS costs. Poly-crystalline panels
3
Confidential
MCS/YEPL/BAB/25KW/VELLORE/2013
have better thermal characteristics compared to mono-crystalline
panels hence are considered more suitable for our needs.
Meteorological and System Data (Vellore India)
Latitude
+12° 99' N
Longitude
+79° 14’ E
System Size
25KW
Area of System
5000 square feet
Yearly estimated production for the 25
kW Power Plant with battery back up
32,000 KWH
Latitude: +12.99 (12°92'02"N)
Longitude: +79.14 (79°13'33"E)
4
Confidential
MCS/YEPL/BAB/25KW/VELLORE/2013
About Yieldopia
Yieldopia is a renewable energy company based in the USA with operations in the
US and India. It was founded by Silicon Valley and Indian technology veterans
who have served in various executive positions in technology companies such as
Cisco Systems and Intel.
Yieldopia’s main sphere of activities is as follows:







Deliver end-to-end alternative energy projects including solar, wind and
cogeneration. This includes project design, development, installation and
final commissioning. The range of our projects extends from smaller KW
power plants to MW utility class plants.
We have pioneered and specialized in co-locating auxiliary projects on PV
installations locations to increase the ROI.
Provide installation and commissioning of solar module manufacturing.
Provide operation and maintenance services for existing plants using the
above technologies.
Establish enduring partnerships with organizations with a similar mission in
the manufacturing and related engineering fields.
Promote proliferation of environment-friendly goods and services.
Champion renewable energy advancement through the Yieldopia
foundation which is involved in numerous projects in the non-profit sector.
Project Details
5
Confidential
MCS/YEPL/BAB/25KW/VELLORE/2013
Location
Vellore, India
Latitude
12°99′ N
Longitude
79°14′ E
Size (KW)
25 KW(DC)
Module Type
Poly Crystalline High Efficiency
Inverters
Battery
250 KW.
240vdc/540ah
Project Stages
The project will be executed in the following stages:
Electrical Design
A.
B.
This will be a 25 KW Solar PV system and will be a off Grid system
Deliverables will include the following drawings and documentation:
a. Site Layout
b. Inverter DC Electrical Single Line Diagram
c. AC Single Line Diagram and Details
d. Electrical Wire and Conduit Schedule and Details
e. Inverter Conduit and Wiring Details
f. DC String Chart drawings
Racking System Installation
Once the feasibilities studies are completed, sturdy racking system will be
installed on the ground which will be able to support the panels. This is a
standard Ground Mount racking system.
PV Panels Installation
PV Panels will be installed on the racking system at an angle facing the southern
direction.
6
Confidential
MCS/YEPL/BAB/25KW/VELLORE/2013
Connecting
Once the PV Panels have been installed, the system will be completed after
adding the inverter and battery the evacuation equipment.
Key Project Requirements
The following are the key requirements for the project to be developed.
Permits
All associated permits required for the project will be the responsibility of the
project owners and will be provided prior to the project commencement or at a
mutually agreed point in time. All Clearance and Permits required for the
transmission Line shall be carried out by Client, we have not included cost of the
Transmission Line.
Project Task Ownership
Action
Owner
1
Define Requirement
Yieldopia
2
Proposal
Yieldopia
3
Bill of Materials (BOM)
Yieldopia
4
Contract/Finance
Client
5
Design Document
Yieldopia
6
Procurement
Yieldopia
7
Installation
Yieldopia
8
Inspection
Yieldopia
7
Confidential
MCS/YEPL/BAB/25KW/VELLORE/2013
9
Commissioning
Yieldopia
10
Operational Handover
Yieldopia
Project Handover
At the end of the commissioning process, the project will be handed over as per
the following protocol. Customer will sign-off on all of the following documents to
complete the handover based on pre-established criteria in the contract
document.
-
Final KWH output document prepared by Yieldopia.
Final Inspection and walk through document prepared by Yieldopia
Final BOM and engineering drawings prepared by Yieldopia
Final training and operation document prepared by Yieldopia
Final sign-off to conclude the project handover by Yieldopia
8
Confidential
MCS/YEPL/BAB/25KW/VELLORE/2013
9
Confidential
MCS/YEPL/BAB/25KW/VELLORE/2013
Technical Specifications
Technical Specifications for a 25KWp (DC)
Installation
This system will require a space of 5000 SQUARE FEET of land to install. It is
imperative that there is no potential for shadows as that will impact the
performance of the panels.
Solar Photovoltaic (PV) Modules
Description
Type
Manufacturer
Green Brilliance/Equivalent
Module Type
Polycrystalline
Module Part Number
S6-60
Module Weight
19 Kg
Module Dimensions
1960 x 987 x 42 mm
Module Nominal Power
Number of Modules
Ralf, head of our US installation team on a project in California
250 Watts peak
Site and Mounting plan dependent
Green Brilliance Modules modules are certified to CEI/IEC 61215: 2005 standard
and conform to Safety Class IEC 61730 standard for 1000VDC applications and
EWG guideline 89/932 (CE). Green Brilliance is in compliance with the
International Quality System Standard ISO 9001:2000.
10
Confidential
MCS/YEPL/BAB/25KW/VELLORE/2013
Solar Power conditioning Unit
PCU TECHNICAL SPECIFICATION
Backup Mode
Rating(KVA)
Output Wave Form
DC Input Voltage
Array Input
Distortion (THDv)
Output Frequency
Wave form
Output voltage
Output Regulation
Cooling
Inverter Type
Inverter Efficiency
Sleep Mode
Protections
25
Sine wave
240VDC
220-400V
<3%
50 Hz +/- 0.5 Hz variation
Pure Sine
400V AC ± 2% (3phase)
± 2%
Fan Forced
Bi directional
>90% at full load
Provided (selectable by switch)
Battery over charging, Battery
reverse polarity, Over load,
Short ckt. & Over heat.
<2.5%
150% for 1 minute and 200% for
10 seconds
Date & Time, PV Voltage, PV
Current, PV Power,
Inverter output Volt. , Output
Current, Output Power,
Solar Accumulated KWh & Grid
Volt
Inv on, low battery, over load,
charging, charged & DC high
No Load Consumption
Overload Capacity
LCD Display
.
Indication(LED)
Grid Mains Mode
AC Input Voltage
AC Input Frequency
400V ,+20% / -20%
50 Hz ±3 Hz
Solar Charge Controller
MPPT Charge controller
Charging PV Imax (Amp)
60 A
Others
Others
Operating Temperature
Storage temperature
Enclosure Protection
0 Deg. To + 450 C
-25 to 550 C.
IP 20
11
Confidential
MCS/YEPL/BAB/25KW/VELLORE/2013
Altitude(ASL)
Operating Humidity Up
1000M (without de-rating)
95% ,non condensing
Electrical Wiring
There are various types of wirings that are utilized on site. These vary from low to
medium voltage DC and medium to high voltage AC. In each of the cases we use
the best all weather and where required UV protected cables. The key is to keep
our resistive losses (I2R) to the minimum for maximum efficiency.
Fault Protection
Our engineer team designs the system with proper grounding including double
isolation disconnects where required and fully protected system. Our system
includes protection of the AC equipment against lightening using arrestors etc.
Monitoring
This is an optional feature that we provide. Based on the accessibility many of the
metrics related to performance including output and fault logs can be made
available remotely. It is possible for people from across the world to monitor the
performance and display related graphics on their laptops/desktops or similar
device.
Product and Performance Warranty
12
Confidential
MCS/YEPL/BAB/25KW/VELLORE/2013
Product Guarantee
All products guaranteed against manufacturing defects for a period of five years.
System Warranty
This is provided as follows.
Solar Modules
20 years of limited warranty provided by the
manufacturer
Inverters
5 years Manufacturer Provided
Guaranteed Capacity
25 K W under STC/Flash conditions
Control panel wiring diagram
13
Confidential
MCS/YEPL/BAB/25KW/VELLORE/2013
14
Confidential
MCS/YEPL/BAB/25KW/VELLORE/2013
15
Confidential
MCS/YEPL/BAB/25KW/VELLORE/2013
Download