2013 25kW PV Solar Installation, at Bab Leather Products Incl Off Grid solar power plant Yieldopia Energy Private Limited 29/042013 Yieldopia Team at work Project Description The purpose of this project is to install Solar Photovoltaic (PV) 25 KW off grid solar power plant. This plant may be utilized to serve the needs of the Client 2 Confidential MCS/YEPL/BAB/25KW/VELLORE/2013 Solar Power With the fast depletion of the non-renewable energy resources, there is a tremendous thrust on generating renewable energy. Solar Energy has been identified as one of the driving forces for generating electricity. During the last two decades, the accelerated drop in silicon, which is the feedstock material for most panels, has made it possible for solar panels to move from space-based applications to generation of energy for consumption by the general populace. The solar power industry is growing at a phenomenal rate globally with the US, Germany, Spain and China leading the way. Industry experts predict an annual growth rate of about 40 per cent for several years into the future. With escalating international oil prices and increasing concerns about global warming, solar power represents a strategic energy choice for the future for most of the countries currently dependent on imported energy sources. Similar considerations apply in India as well. Further, there has been a rapid decline in the PV pricing in the last 2-3 months which has made a well designed Solar power solution a better option, environmentally as well as financially to a DG (Diesel Generator Set) power. Due to a massive deficit in the power sector infrastructure and fuel supply use of DG has been growing rapidly in India. This has led to many issues including a rising oil import bill, loss of revenue due to subsidies for diesel and above all, increasing pollution in the country. Solar PV (Photo-Voltaic) Technologies There are two main PV technologies namely Silicon (mono-crystalline or polycrystalline) or thin films (TF). The latter includes amorphous silicon and various chemistries from the CIGS (Cadmium, Indium, Gallium and Selenium) family of elements. Though TF panels have better thermal characteristics then Silicon based panels, their lack of long term record makes them a riskier alternative. Further due to their considerably lower power density requires a higher number of panels resulting in a higher space requirement and BOS costs. Poly-crystalline panels 3 Confidential MCS/YEPL/BAB/25KW/VELLORE/2013 have better thermal characteristics compared to mono-crystalline panels hence are considered more suitable for our needs. Meteorological and System Data (Vellore India) Latitude +12° 99' N Longitude +79° 14’ E System Size 25KW Area of System 5000 square feet Yearly estimated production for the 25 kW Power Plant with battery back up 32,000 KWH Latitude: +12.99 (12°92'02"N) Longitude: +79.14 (79°13'33"E) 4 Confidential MCS/YEPL/BAB/25KW/VELLORE/2013 About Yieldopia Yieldopia is a renewable energy company based in the USA with operations in the US and India. It was founded by Silicon Valley and Indian technology veterans who have served in various executive positions in technology companies such as Cisco Systems and Intel. Yieldopia’s main sphere of activities is as follows: Deliver end-to-end alternative energy projects including solar, wind and cogeneration. This includes project design, development, installation and final commissioning. The range of our projects extends from smaller KW power plants to MW utility class plants. We have pioneered and specialized in co-locating auxiliary projects on PV installations locations to increase the ROI. Provide installation and commissioning of solar module manufacturing. Provide operation and maintenance services for existing plants using the above technologies. Establish enduring partnerships with organizations with a similar mission in the manufacturing and related engineering fields. Promote proliferation of environment-friendly goods and services. Champion renewable energy advancement through the Yieldopia foundation which is involved in numerous projects in the non-profit sector. Project Details 5 Confidential MCS/YEPL/BAB/25KW/VELLORE/2013 Location Vellore, India Latitude 12°99′ N Longitude 79°14′ E Size (KW) 25 KW(DC) Module Type Poly Crystalline High Efficiency Inverters Battery 250 KW. 240vdc/540ah Project Stages The project will be executed in the following stages: Electrical Design A. B. This will be a 25 KW Solar PV system and will be a off Grid system Deliverables will include the following drawings and documentation: a. Site Layout b. Inverter DC Electrical Single Line Diagram c. AC Single Line Diagram and Details d. Electrical Wire and Conduit Schedule and Details e. Inverter Conduit and Wiring Details f. DC String Chart drawings Racking System Installation Once the feasibilities studies are completed, sturdy racking system will be installed on the ground which will be able to support the panels. This is a standard Ground Mount racking system. PV Panels Installation PV Panels will be installed on the racking system at an angle facing the southern direction. 6 Confidential MCS/YEPL/BAB/25KW/VELLORE/2013 Connecting Once the PV Panels have been installed, the system will be completed after adding the inverter and battery the evacuation equipment. Key Project Requirements The following are the key requirements for the project to be developed. Permits All associated permits required for the project will be the responsibility of the project owners and will be provided prior to the project commencement or at a mutually agreed point in time. All Clearance and Permits required for the transmission Line shall be carried out by Client, we have not included cost of the Transmission Line. Project Task Ownership Action Owner 1 Define Requirement Yieldopia 2 Proposal Yieldopia 3 Bill of Materials (BOM) Yieldopia 4 Contract/Finance Client 5 Design Document Yieldopia 6 Procurement Yieldopia 7 Installation Yieldopia 8 Inspection Yieldopia 7 Confidential MCS/YEPL/BAB/25KW/VELLORE/2013 9 Commissioning Yieldopia 10 Operational Handover Yieldopia Project Handover At the end of the commissioning process, the project will be handed over as per the following protocol. Customer will sign-off on all of the following documents to complete the handover based on pre-established criteria in the contract document. - Final KWH output document prepared by Yieldopia. Final Inspection and walk through document prepared by Yieldopia Final BOM and engineering drawings prepared by Yieldopia Final training and operation document prepared by Yieldopia Final sign-off to conclude the project handover by Yieldopia 8 Confidential MCS/YEPL/BAB/25KW/VELLORE/2013 9 Confidential MCS/YEPL/BAB/25KW/VELLORE/2013 Technical Specifications Technical Specifications for a 25KWp (DC) Installation This system will require a space of 5000 SQUARE FEET of land to install. It is imperative that there is no potential for shadows as that will impact the performance of the panels. Solar Photovoltaic (PV) Modules Description Type Manufacturer Green Brilliance/Equivalent Module Type Polycrystalline Module Part Number S6-60 Module Weight 19 Kg Module Dimensions 1960 x 987 x 42 mm Module Nominal Power Number of Modules Ralf, head of our US installation team on a project in California 250 Watts peak Site and Mounting plan dependent Green Brilliance Modules modules are certified to CEI/IEC 61215: 2005 standard and conform to Safety Class IEC 61730 standard for 1000VDC applications and EWG guideline 89/932 (CE). Green Brilliance is in compliance with the International Quality System Standard ISO 9001:2000. 10 Confidential MCS/YEPL/BAB/25KW/VELLORE/2013 Solar Power conditioning Unit PCU TECHNICAL SPECIFICATION Backup Mode Rating(KVA) Output Wave Form DC Input Voltage Array Input Distortion (THDv) Output Frequency Wave form Output voltage Output Regulation Cooling Inverter Type Inverter Efficiency Sleep Mode Protections 25 Sine wave 240VDC 220-400V <3% 50 Hz +/- 0.5 Hz variation Pure Sine 400V AC ± 2% (3phase) ± 2% Fan Forced Bi directional >90% at full load Provided (selectable by switch) Battery over charging, Battery reverse polarity, Over load, Short ckt. & Over heat. <2.5% 150% for 1 minute and 200% for 10 seconds Date & Time, PV Voltage, PV Current, PV Power, Inverter output Volt. , Output Current, Output Power, Solar Accumulated KWh & Grid Volt Inv on, low battery, over load, charging, charged & DC high No Load Consumption Overload Capacity LCD Display . Indication(LED) Grid Mains Mode AC Input Voltage AC Input Frequency 400V ,+20% / -20% 50 Hz ±3 Hz Solar Charge Controller MPPT Charge controller Charging PV Imax (Amp) 60 A Others Others Operating Temperature Storage temperature Enclosure Protection 0 Deg. To + 450 C -25 to 550 C. IP 20 11 Confidential MCS/YEPL/BAB/25KW/VELLORE/2013 Altitude(ASL) Operating Humidity Up 1000M (without de-rating) 95% ,non condensing Electrical Wiring There are various types of wirings that are utilized on site. These vary from low to medium voltage DC and medium to high voltage AC. In each of the cases we use the best all weather and where required UV protected cables. The key is to keep our resistive losses (I2R) to the minimum for maximum efficiency. Fault Protection Our engineer team designs the system with proper grounding including double isolation disconnects where required and fully protected system. Our system includes protection of the AC equipment against lightening using arrestors etc. Monitoring This is an optional feature that we provide. Based on the accessibility many of the metrics related to performance including output and fault logs can be made available remotely. It is possible for people from across the world to monitor the performance and display related graphics on their laptops/desktops or similar device. Product and Performance Warranty 12 Confidential MCS/YEPL/BAB/25KW/VELLORE/2013 Product Guarantee All products guaranteed against manufacturing defects for a period of five years. System Warranty This is provided as follows. Solar Modules 20 years of limited warranty provided by the manufacturer Inverters 5 years Manufacturer Provided Guaranteed Capacity 25 K W under STC/Flash conditions Control panel wiring diagram 13 Confidential MCS/YEPL/BAB/25KW/VELLORE/2013 14 Confidential MCS/YEPL/BAB/25KW/VELLORE/2013 15 Confidential MCS/YEPL/BAB/25KW/VELLORE/2013