GZA GeoEnvironmental, Inc. Engineers and Scientists August 26, 2015 File No. 01.0025623.10 The Honorable Sefatia Romeo Theken Mayor of Gloucester 9 Dale Avenue Gloucester, Massachusetts 01930 Re: 249 Vanderbilt Avenue Norwood Massachusetts 02062 781-278-3700 FAX 781-278-5701 http://www.gza.com Richard Sagall, Chairperson Board of Health 3 Pond Road Gloucester, Massachusetts 01930 Notification of Phase IV Remedy Implementation Plan Submittal Former Gloucester Manufactured Gas Plant (MGP) Harbor Loop, Gloucester, Massachusetts Release Tracking Number (RTN) 3-25126 Dear Mayor Theken and Mr. Sagall: Per the requirements of the Massachusetts Contingency Plan (MCP), specifically 310 CMR 40.1403(3)(a) and (e), this letter is intended to notify you that a Phase IV Remedy Implementation Plan (RIP) for the above-referenced Site is being submitted to the Massachusetts Department of Environmental Protection (MassDEP), and that associated field activities will be initiated shortly thereafter. The Phase IV RIP describes Comprehensive Remedial Actions (CRAs) that will be conducted to achieve a condition of No Significant Risk (NSR) at the Site. Related field activities will be conducted over a period of two to three construction seasons beginning on or after September 8, 2015. As required by the MCP, the following sections of the Phase IV RIP are attached: a description and conceptual plan of the activities; and a discussion of the measures that will be implemented to limit or mitigate impacts to environmental receptors and natural resource areas. A schedule for the proposed Phase IV Remedy Implementation is also attached. A copy of the Phase IV RIP submittal can be viewed after August 28, 2015 under RTN 3-35126 at the MassDEP website: http://db.state.ma.us/dep/cleanup/sites/search.asp. Copies of the report can also be obtained by contacting Mr. Kenneth Lento at (781) 907-3655 or the undersigned. If you have any questions concerning this letter, please contact the undersigned at 781-278-3805. Very truly yours, GZA GEOENVIRONMENTAL, INC. Matthew J. Barvenik, LSP Senior Principal cc: MassDEP – NERO Kenneth E. Lento, National Grid Attachments: Description of the Comprehensive Remedial Actions J:\25,000-26,999\09.0025623.00\Phase IV - RIP\Phase IV Report\Appendices\Appendix Q - Public Notices\BOH & City Notice of Phase IV RIP Submittal.docx DESCRIPTION OF REMEDIAL ACTIONS 1.00 INTRODUCTION On behalf of Massachusetts Electric Company d/b/a National Grid (National Grid), GZA GeoEnvironmental, Inc. (GZA) and Anchor QEA, LLC (Anchor QEA) have prepared this Phase IV Remedy Implementation Plan (RIP) for the Gloucester Gas Light Company (GGLC) Manufactured Gas Plant (MGP) facility (the Site). The Site is located off Harbor Loop and Rogers Street in Gloucester, Massachusetts and has been assigned Release Tracking Number (RTN) 3-25126 by the Massachusetts Department of Environmental Protection (MassDEP). 1.10 PROJECT SUMMARY Response actions are being conducted at the Site to meet the requirements of the Massachusetts Contingency Plan (MCP, 310 CMR 40.0000). A Locus Map is included as Figure 1, and an Aerial View of the Site showing properties within the disposal site boundary is presented as Figure 2. As shown on Figure 2, the Site extends across upland and in-water (marine) areas of multiple properties, which are owned by various commercial and governmental entities. To facilitate assessment and remedial activities, the Site has been divided into Marine and Upland Areas. The Upland Area has been further subdivided into the Southern Area and Northern Area based on historical and present-day ownership and land uses. The MCP Phase IV Comprehensive Remedial Alternatives (CRAs) described in this report have been designed to address the Southern and Marine Areas1 of the Site, collectively designated as the Project Area. Property owners within the Project Area include the United States Coast Guard (USCG), the City of Gloucester (City), National Grid, Maritime Gloucester; and Kristensen Realty, LLC (KRLLC); additional information about each of the properties is provided in Section 2.00. Selected CRAs at these properties and in Gloucester Inner Harbor will include excavation and capping of MGP-impacted soils, removal of coal tar in the form of dense non-aqueous phase liquid (DNAPL), removal of MGP-impacted sediment, off-Site treatment and/or disposal of remediation waste, and post-dredging placement of backfill and a sub-aqueous porewater cap. This will involve removal and replacement of waterfront pile-supported structures, construction of interim docking structures, construction and/or replacement of seawalls, excavation and construction of an engineered barrier, dredging across approximately 7 acres of Gloucester Inner Harbor, and placement of sub-aqueous fill material in the harbor for seawall stability and porewater control purposes. Permits for the project have been sought from multiple local, State, and Federal agencies. The timing of the project will be affected by Division of Marine Fisheries (DMF) Time of Year (TOY) restrictions (for in-water work) and the requirements of property owners. The project is anticipated to begin in September 2015, and given its technical, regulatory, and logistical complexity, will extend over a period of up to three years. Work will be sequenced so as to limit impact to operations at each of the properties. 1 Separate MCP submittals have been and/or will be made for the properties within the Northern Area; see Section 2.30 for additional information. 3 7.00 DESCRIPTION AND CONCEPTUAL PLAN OF REMEDIAL ACTIVITIES, INCLUDING RELEVANT DESIGN PARAMETERS (310 CMR 40.0874(3)(B)(5) AND (6)) The following sections provide a conceptual plan and description of how the CRAs outlined in Section 4.00 will be implemented during the Phase IV. Additional information regarding the proposed sediment dredging, backfilling, and capping, soil excavation, seawall construction, and marine structure removal and replacement activities is provided in the Specifications included in Appendix D. A listing of the key elements of the work, cross-referenced to the relevant Specification sections, is provided in Specification Section 01 10 00 – Summary of Work. 7.10 MARINE AREA SITE PREPARATION To provide access for in-water remediation equipment, piers and floating docks at the USCG, City of Gloucester, National Grid, and Maritime Gloucester properties will have to be removed. As a consequence, interim structures will be constructed to allow some inwater operations at the USCG and Maritime Gloucester properties to continue during the remedial efforts. In addition, measures to augment structure stability will be implemented at the USCG and Maritime Gloucester seawalls prior to dredging. The in-water structure removal and construction activities that will be implemented at the various properties are described below. 7.10.1 USCG Floating Docks During each remediation work season, USCG vessels will be temporarily re-located from their existing floating docks. The existing gangway, steel braces, and timber float at the Northern Floating Dock will be removed to provide access for dredge equipment, and will be replaced prior to the end of each work season. The existing gangway and timber float at the Southern Floating Dock will be used in the construction of the interim floating dock system described below, and will similarly be replaced prior to the end of each work season. To limit disruption to USCG operations during the remediation, an interim floating dock system for up to three vessels will be constructed adjacent to Pier 2 at 17 Harbor Loop (see Drawing S-14). To accommodate the interim system, the Pier 2 substructure will be repaired by replacing timber fender piles and cross-bracing elements that are in poor condition, and reinforcing additional timber piles with fiber reinforced polymer (FRP) jackets to enhance their strength and longevity. The interim system will consist of a timber pile-supported landing, two timber floating docks, and an aluminum gangway. Temporary fuel, lighting, water, and electrical services for the USCG vessels will be provided at this location. This interim location, while suitable for USCG access, is not sheltered from wind and wave surges. Therefore, a temporary bottom-anchored floating breakwater will be installed as shown on Drawing S-14. The breakwater will consist of two bottom-anchored concrete floats, each approximately 13 feet by 41 feet in dimension. These floats will extend over the 2004 Harbor Commissioner’s line into a Federal anchorage area, under permit approval from the United States Army Corps of Engineers (USACE) and a 10A Permit issued by the Gloucester Harbormaster. 4 Following the completion of the remediation project, the interim floating dock system and breakwater will be removed from Pier 2, and the Northern and Southern floating docks will be re-located to their existing locations at the USCG property. 7.10.2 National Grid Pier and City of Gloucester Floating Docks As described in Section 2.20, a wooden pile-supported pier owned by National Grid extends over both the National Grid property at 19 Harbor Loop and City of Gloucester property at 19R Harbor Loop. The pier is in poor condition, and an approximately 1,300-square foot (sf) section of it was removed in July 2012 as a safety measure at the request of the Gloucester Harbormaster. To facilitate in-water equipment access to the seawalls and Nearshore Area, the pier will be removed in its entirety at the start of the remediation project as described in Specification Section 02 40 00 – Demolition and Structure Moving. At the end of the first work season, in accordance with an agreement with the City of Gloucester, National Grid will install an array of steel guide piles to support a new City of Gloucester floating dock system that will also extend over both properties. The guide piles will consist of 18-inch-diameter concrete-filled coated steel pipe piles, which will be drilled into the bedrock beneath the harbor to withstand tidal and wave action. Between work seasons, i.e., during the summer of 2016, these piles will be used to support an interim City of Gloucester floating dock system. Following completion of the project, the piles will support a new City of Gloucester floating dock system, which is described under Site Restoration activities in Section 7.80 of this Phase IV RIP. 7.10.3 Maritime Gloucester Piers, Floating Docks and Gangway The anticipated sequence of remediation at Maritime Gloucester includes construction of a vertical barrier (Section 7.70.2, below) during the first work season and dredging in the Nearshore Area to remove impacted sediments during the second work season. This will require temporary re-location of some Maritime Gloucester operations during the first work season, and removal and replacement of the piers at the property during the second work season, as described below. During the first work season, the gangway and floating docks currently attached to the southern edge of the Main Pier will be temporarily re-located to an alternate location on the Maritime Gloucester property, and will be restored to existing conditions when access to the slip is restored. An interim timber landing will be constructed at the Northern Hauling Pier to provide access for the gig rowers club, which currently accesses the water via the southern landing at the Main Pier. During the second work season, the gangway and floating docks at the Main Pier and the two hauling piers will be removed from their supports and stored. It is anticipated that the Maritime Gloucester Main Pier decking, and all but the most landward set of piles, will be removed, unless the contractor’s approach allows for sediment remediation objectives to be achieved with some portions of the pier remaining in place. Similarly, all or a select portion of the hauling piers will be removed; where possible, select timber piles may be left in place, and sediment removed around the piles during dredging. Once dredging and backfilling has been completed, the Main Pier and hauling piers will be reconstructed in kind and the floating docks and gangway will be restored. 5 7.10.4 Maritime Gloucester Boat House Seawall Stability Enhancement The Maritime Gloucester Boat House Seawall (Drawing EC-1) was constructed in the late 19th century, and does not meet current design factors of safety. Therefore, when the Maritime Gloucester Main Pier is removed, the existing row of wooden piles closest to the seawall will be left in place, to improve seawall stability during dredging. These piles will be augmented with seven steel H-piles and plates driven along the toe of the wall in front of the boat house. Concrete will be tremie poured between the piles/plates and the seawall, to provide additional stability specific to the boat house area (Drawing S-21). As an additional stabilization measure during dredging in front of the boat house, the top courses of the granite block seawall section will be temporarily removed, and the soil behind it will be excavated to an elevation of +5 feet NGVD. This will reduce the effective surcharge load on the wall and thus increase the overturning factor of safety during dredging in front of the boat house. Impacted sediment seaward of the steel plates will be removed by interval dredging, following which the mudline will be brought back to existing grade with material providing similar strength to that removed (See Section 5.80). Once in-water backfilling has been completed, the granite blocks will be replaced and the excavation behind the seawall in the upland area will be filled with concrete. Four of the H-piles will be cut to elevation -2 feet NGVD; the remaining three will be left in place to support an approximately 8-foot-wide wooden walkway (Drawing S-29) providing waterfront access. The soil removed from the upland excavation will be managed under a Release Abatement Measure (RAM) Plan to be developed for the Maritime Gloucester property prior to the initiation of this phase of work. 7.10.5 Debris Removal and Pre-Dredge Bathymetric Survey Following removal/re-location of structures as described above, and prior to the removal of sediments, a visual debris survey will be performed at each of the areas where dredging is to be conducted. Industrial debris related to marine activities has been identified within the Marine Area, including old piles, tires, bricks, cables, lines, and timber and scrap metal debris. The remnants of the abandoned marine railway at Maritime Gloucester will also be removed during this phase of work. Proposed debris management is described in Section 9.30 of this Phase IV and in Specification Section 02 61 00 – Removal and Disposal of Excess Materials. The debris survey will be coordinated with a pre-dredge bathymetric survey to establish baseline conditions prior to the start of remediation. This pre-dredge survey represents one of a series of surveys that will be conducted throughout the Phase IV in accordance with Specification Section 02 21 00 – Surveys. The baseline survey will be compared to post-dredge surveys to verify dredge depths reached and volumes removed in each area. The survey results will be used to prepare Final Conditions plans that will be submitted as part of the Phase IV Final Inspection Report (FIR). 7.10.6 Installation of Marine Resuspension Controls As described in Specification Section 01 57 30 – Marine Resuspension Controls, a number of in-water controls will be installed prior to the initiation of in-water or waterfront activities that may generate silt (i.e., turbidity) or sheens. These controls, which will be 6 deployed as shown on Drawings C-3 and C-4, will generally consist of the following elements as shown on Drawing C-7: A Mobile Resuspension Control System will be installed prior to dredging in the Nearshore and/or Offshore Areas. This system will be comprised of an enclosed moon pool surrounded by permeable turbidity curtains. Reefing lines will be used to accommodate varying water depths due to tidal fluctuations, and to maintain the curtains between one and three feet above the sediment surface. Billow controls will be used to limit drifting of the curtain due to tidal currents. Sorbent booms will be secured to the inner and outer edge of the system to absorb potential sheens that may be released during the work. A Modified Mobile Resuspension Control System will be installed prior to dredging in portions of the Nearshore Area where the system described above cannot be used due to access limitations associated with the system geometry or shallow water depths. The modified system includes the same components (i.e., turbidity curtain, reefing lines, billow controls, and sorbent booms) as described above. Work will be conducted off the back of the modified system, with additional permeable turbidity curtains installed from the mobile system to the shoreline as shown on Drawing C-4. Stand-alone permeable turbidity curtains will be anchored around the work area during suction dredging at USCG Pier 2 and steel pile installation for the City of Gloucester floating dock system (Drawing C-3). Both stand-alone impermeable turbidity curtains and stand-alone permeable turbidity curtains will be anchored around the work area during seawall removal and construction activities at Solomon Jacobs Park, National Grid, and Maritime Gloucester (Drawing C-3). When left in place overnight, the marine resuspension controls will be lit to warn boaters in accordance with USCG and Harbormaster requirements. The marine resuspension controls will be inspected at least twice daily, and will be modified as necessary to meet Site-specific conditions and the requirements of the Water Quality Certification (WQC). The controls will remain in place until sheen-generating and silt-producing activities are complete, and will then be decontaminated and disposed of in accordance with Specification Sections 02 51 29 – Surface Cleaning and Decontamination and 02 61 00 – Removal and Disposal of Excess Materials. 7.20 UPLAND AREA SITE PREPARATION Site preparation in the upland areas will be initiated with the installation of fencing around the work areas at each of the properties, as shown on Drawings C-13 and C-14 and in accordance with Specification Section 01 56 00 – Temporary Enclosures and Barriers. This will be followed by the installation of Erosion and Sedimentation Controls, as shown on C-3 and C-4 and discussed in Section 8.40 of this Phase IV RIP. 7 Existing features within Solomon Jacobs Park will then be removed as shown on Drawing CD-3, and the park will be cleared in anticipation of temporary construction features such as a containment area for temporary stockpiling of impacted materials, a staging area for clean materials, and a wheel wash station. Also during this stage of work, select monitoring wells in the Southern Area will be decommissioned in accordance with Specification Section 33 29 00 – Well Abandonment and Drawing R-9. These wells were selected based on routine monitoring efforts conducted during IRA activities; new DNAPL recovery wells will be installed at key locations as described below in Section 7.70.3. In accordance with the terms of access agreements between National Grid and the property owners, limited areas of the USCG and Maritime Gloucester properties may be used for temporary staging of clean materials or equipment (Drawings G-5 and G-6). No remediation waste will be stockpiled at the USCG property. At the Maritime Gloucester property, excess soil generated during the Boat House Seawall Stability Enhancement process described in Section 7.10.4 may be temporarily stored pending characterization and off-Site disposal. The soil will be managed as described in Section 9.20.2. Granite blocks removed during the Boat House Seawall Stability Enhancement may also be temporarily stored at the property pending their re-use following dredging and backfill placement. 7.30 DREDGING Dredging to remove sediments with VOT and/or TPAH16 concentrations greater than 135 mg/kg will be conducted over approximately 7 acres of the Marine Area as shown on Drawings C-17 through C-19. The proposed dredge depths range from approximately 1.0 feet to 6.5 feet below the existing mudline, including an anticipated overdredge allowance of 6 inches. The deeper dredge depths are located in the Nearshore Area. Approximately 30,000 cy of sediment containing VOT and/or TPAH16 concentrations greater than 135 ppm will be removed during the Phase IV Remedy. Additional sediment volume may need to be removed based on visual observation of the nature and extent of OHM during dredging implementation. Dredging equipment and procedures are described in Specification Section 35 01 50.51 – Marine Dredging, and are summarized below. 7.30.1 Mechanical Dredging Dredging across most of the Offshore Area, seaward of the Gloucester Harbor Line, will be performed using an excavator mounted on a barge. The barge will be fitted with hydraulic spuds and configured with a moon pool (as described above in Section 7.10.6) within which the dredging operations will be performed. A hydraulically actuated environmental clamshell bucket will be used to reduce sediment loss during dredging. Dredging will be conducted within a Mobile Resuspension Control System designed to maintain the dispersion of turbidity, sheens, floating oil and/or tar within the limits of work. Dredging in the Nearshore Area, landward of the Gloucester Harbor Line, will be performed using one or more excavators mounted on shallow draft barges. These barges will be similarly equipped with hydraulic spuds and an excavator with environmental 8 clamshell bucket, but without a moon pool. This configuration is required to allow dredging to be performed up against existing structures. The barge and work area will also be surrounded by resuspension controls throughout the work. Dredging adjacent to the USCG, City of Gloucester, National Grid, and Maritime Gloucester seawalls will be performed in narrow linear segments followed immediately by backfilling to maintain stability, a process referred to as interval dredging. The technique involves excavating one narrow “slot” or “interval” perpendicular to the length of the structure to limit the amount of material removed from the toe of the structure at any given time. “Slots” or “intervals” will be immediately backfilled to existing, or otherwise specified grade following excavation. A hopscotch approach will be used to excavate subsequent “slots” or “intervals” so that no two adjacent slots are excavated and open at the same time; i.e., the width of any individual open excavation will not exceed the prescribed slot width. 7.30.2 Dredging at the Maritime Gloucester Marine Railway Dredging around the active Marine Railway at Maritime Gloucester will be conducted in the dry within a temporary sheet pile cofferdam. The approximately 16-footwide by 208-foot-long cofferdam will be constructed of inter-locking steel sheet piles. The footprint of the cofferdam will encompass the end of the railway, estimated to be at -14.29 feet NGVD. Closure of the landward side of the cofferdam will require removal of approximately 10 feet of railway and framing timbers. Final closure will be performed as close to low tide as possible to reduce the amount of water remaining within the closed cofferdam. Pumping to remove water within the cofferdam will be performed from the water surface to limit the suction and suspension of sediment from the mud line. As described in Section 9.40, this water will be treated as necessary prior to discharge within the limits of the work, in accordance with the WQC. A mini-excavator will be placed into the cofferdam to remove sediment. In conjunction with the mini-excavator, laborers will use hand tools to remove impacted sediment from beneath and around the railway components. Excavated sediment removed from the cofferdam will be transferred to a material scow and managed with other dredged materials from the Site, as described in Section 9.10. 7.30.3 Suction Dredging Diver-assisted suction dredging will be conducted in localized areas where access is limited, such as under USCG Pier 2. This dredging will be performed by a dive crew to control the location and depth of the suction head around the existing infrastructure. Suction dredging may also be used in the area of the active Marine Railway as an alternate to the cofferdam approach. 7.40 MARINE BACKFILL PLACEMENT Backfill will be placed in areas of the dredge footprint to manage dredge residuals and to reestablish benthic habitat following dredging activities. Additional factors, including the need for structural stability near existing marine structures and design elevations within the 9 Federal navigation channel, were also evaluated prior to developing specifications for backfilling at the Site. The resulting backfilling plan is graphically depicted on Drawing C-21, and the materials to be used for backfill in different areas of the Site are specified in Section 31 05 13 – Soils and Aggregates for Earthwork. 7.40.1 Nearshore Area Following dredging, backfill will be placed in the Nearshore Area at the USCG, City of Gloucester, National Grid, Maritime Gloucester, and KRLLC properties as described below. USCG, City of Gloucester, and National Grid properties Outside the porewater cap area (described below in Section 7.50), a minimum 6inch-thick layer of clean backfill will be placed within the Nearshore Area at the USCG, City of Gloucester, and National Grid properties to reestablish benthic habitat and/or to manage dredge residuals. The grain size characteristics of the backfill will generally be similar to existing materials. Maritime Gloucester Following dredging and placement of an initial 6 inches of backfill material, a confirmatory sediment core sample will be collected from each of four quadrants in the Nearshore Area at the Maritime Gloucester property. The samples will be submitted for laboratory analysis of TPAH16 by EPA Method 8270D, and the results will be compared to the remedial objective of 135 mg/kg. As necessary, an additional dredge pass of at least 12 inches in depth will be conducted prior to final placement of backfill to grades shown on Drawing C-21. Within the cofferdam at the active Marine Railway, backfill material will be placed under and around the railway and timber framing to existing grades as shown on Drawing C-21. Upon completion of backfilling, the cofferdam elements (internal bracing and the sheet piles) will be removed and decontaminated over an intermodal container. Marine railway rails/timbers that were removed to close the sheeting will be replaced. KRLLC property Sufficient backfill will be placed to restore mudline to the grade shown on Drawing C-21 at the KRLLC property. 7.40.4 Offshore Area The majority of the Offshore Area is located within a Federal navigation channel, which has an authorized elevation. Although the proposed dredging will extend below that elevation, placement of backfill material after dredging poses the potential risk of overfilling to an elevation at or above the authorized elevation. To evaluate the need for backfilling after dredging, as associated with potential dredge residuals, confirmatory sediment samples will be collected from a representative “test” area and analyzed for OHM concentrations. If OHM concentrations are consistent with remedial objectives, backfill will not be placed within the area tested and backfill placement will not be 10 recommended for the Offshore Area. If OHM concentrations are not consistent with remedial objectives, 6 inches of backfill material will be placed in the “test” area. Then, confirmatory sediment samples will be collected from another “test” area, and the process mentioned above repeated. Under either circumstance, the objective is to maintain the post-remediation mudline within the Federal navigation channel at or below the authorized elevation. Upon completion of this work, this area will not be subject to restrictions on future dredging. 7.50 MARINE CAPPING The objective of the sub-aqueous porewater cap to be constructed in the Nearshore Area adjacent to the USCG property, Solomon Jacobs Park, and the National Grid property is to address impacted sediment porewater that has the potential to present a future risk to ecological receptors. The extent of the cap is based on the porewater studies described in Section 5.20 and Appendix F, and will cover approximately 10,000 sf (Drawing C-21). The cap design, which is based on the modeling described in Appendix F, will include a chemical isolation layer overlain by an erosion protection layer designed to protect the material within the chemical containment layer from propeller scour and erosion. The cap materials will be placed using one of two methods: 1) placement of custom Triton® Marine Armor Mattresses (MAMs) fabricated by Tensar® International Corporation (Tensar) or equivalent or 2) placement of individual layers of granular material. Both placement methods provide the same chemical containment as well as provide adequate erosion protection. MAMs were selected for placement on the USCG property to accommodate potential future operational changes on this Federal property, and will also be used in a small application on the National Grid property to provide increased erosion protection near the seawall. The MAMs will comprise dual-layer polymeric (i.e., non-metallic) compartmental structures. The bottom layer of each MAM will be 12 inches thick, wrapped in geotextile, and filled with a mixture of sand and CETCO PM-199 organoclay to attenuate upwelling porewater. The 8-inch-thick upper compartment will be filled with stone to protect the underlying sand-organoclay layer from damage due to scour and propeller wash. As shown on Drawing C-22, a rip rap buttress will be placed above the MAMs, adjacent to the USCG seawall stability wedge. This buttress will be located below Mean Low Water, and will provide additional stability for the USCG seawall. The rip rap buttress and MAMs can be removed and replaced as necessary to accommodate future USCG operational changes or infrastructure improvements. The MAMs will also better withstand scour associated with Harbormaster operations in the shallow draft areas of the National Grid property. At the rest of the National Grid property, and on the City of Gloucester property, the porewater cap will consist of a multi-layer Granular Marine Cap with the following layers: A 6- to 12-inch-thick chemical containment layer consisting of a mixture of 50% sand and 50% CETCO PM-199 organoclay to attenuate upwelling porewater, overlain by a 6- to 12-inch-thick layer of filter material, overlain by 11 a 9- to 15-inch-thick layer of armor stone to protect the underlying layers from damage due to scour and prop wash. Typical cross-sections of the granular cap and MAM cap are shown in Drawing C-22. The top of cap elevation will be no higher than the existing mudline. Following the completion of remediation activities, the integrity of the cap will be monitored over time and maintenance will be conducted as needed, in accordance with the AUL, or AUL-like instrument, required to reach a Permanent Solution under the MCP. It is anticipated that the AUL will allow pre-existing activities, i.e., activities consistent with the current uses of the properties using current operational procedures, but will require notification to National Grid prior to future changes in operating conditions or invasive activities (e.g., dredging, pile driving) within the footprint of the cap. Post-construction conditions surveys of the porewater cap will be conducted by National Grid as described in Section 13.30. Note that as shown on Drawing C-21, the porewater cap will be placed entirely within the nearshore portions of the properties listed above, and it will in all cases be located more than 100 feet away from the Harbor Commissioner’s Line. As such, the cap will have no impact on the Federal navigation channel, its side-slope design, or future maintenance dredging activities. 7.60 USCG STABILITY WEDGE CONSTRUCTION To enhance the stability of the USCG seawall in order to facilitate dredging of impacted sediments, a stability wedge of concrete will be constructed along the toe of the seawall. The wedge will be constructed by interval dredging, matched with intervals of concrete placement, to alleviate potential stability issues associated with dredging immediately adjacent to the seawall. The extent of the stability wedge, and a profile view, are presented in Drawings C-21 and C-22. Note that the wedge will be an integral part of the porewater cap at the USCG property. The stability wedge will also create additional intertidal resource area at this location. In accordance with recommendations made by MassDEP during the EENF review for this project, at least 18 inches of select fill (see Section 31 05 13 – Soils and Aggregates for Earthwork) will be placed above the concrete to provide habitat following remediation. A layer of granite blocks or equivalent will be placed along the seaward edge of the wedge to create a berm that will limit future scouring and loss of the habitat layer. 7.70 SOUTHERN AREA REMEDIAL RESPONSE ACTIONS As summarized in Section 4.00, NAPL-impacted fill material behind the granite block seawalls along the waterfront at the Solomon Jacobs Park and National Grid properties has been identified as an ongoing source of impact to the environment. In addition, presumed source material exists behind the National Grid Existing Building Seawall, in an area that cannot be directly investigated due to the presence of a building partially founded on the seawall. In support of a Permanent Solution at the park and National Grid properties, source material will be excavated where accessible. This will entail removal and replacement of seawalls at Solomon Jacobs Park and a portion of the National Grid property. For the remainder of the National Grid property, where the existing building is 12 supported on the seawall, a concrete vertical barrier (i.e., a new seawall) will be installed seaward of the existing seawall for source control. Further, to address the conditions described in Section 4.00 and achieve a Permanent Solution in the Southern Area, an automated DNAPL Recovery System will be installed at the USCG, Solomon Jacobs Park and National Grid properties, and an engineered barrier will be constructed in the park. The following sub-sections describe each of these CRAs. 7.70.1 Source Removal The granite block seawalls designated as the Solomon Jacobs Park Seawall, the National Grid Pier Seawall and the National Grid Access Ramp Seawall on Drawing EC-1 enclose fill material emplaced in the late 19th century during operation of the MGP. During the Phase IV, these seawalls will be removed to facilitate access to soil impacted by coal tar (source material), and will be re-built along a straighter alignment which will also provide additional water sheet for the City of Gloucester Harbormaster and the public. The excavation and construction efforts are described in Specification Sections 31 00 00 – Earthwork through 31 50 00 – Support of Excavation (SOE) and 35 31 16.40 – Stone Seawalls and select S-series Drawings between S-1 and S-10, and are summarized below. A temporary support of excavation system will be installed landward of the existing seawalls to support upland excavation (Drawing S-1). The SOE system will consist of drilled mini piles, with wood lagging used down to MLW, followed by steel sheets below MLW. The system was designed based on the lithologic and geotechnical data collected during the Phase II CSA, as well as subsequent investigations described in Section 5.00. Once the SOE system has been installed, the National Grid Pier Seawall and the land it encloses (approximately 1,000 cy of fill) will be removed. The Solomon Jacobs Park Seawall and National Grid Pier Access Ramp Seawall will then be removed, and coal tar-containing soil behind the seawalls will be excavated to an elevation of approximately 11.5 feet NGVD. This will result in the removal of approximately 2,000 cy of source material. Additional soil volume may need to be removed based on visual observation of nature and extent of OHM at depth during source removal activities. Following source removal, a 6-foot-thick tremie concrete foundation will be installed below water, and a replacement seawall will be constructed and finished to a surface elevation of +10.5 feet NGVD. It is anticipated that the granite blocks reclaimed during removal of the existing seawalls will be cleaned as necessary (to remove coal tar staining) and re-used to construct the granite block seawalls. Additional granite blocks reclaimed from the seawall demolition will be placed at the toe of the rebuilt seawalls for aesthetics and scour protection. A vertical layer of adsorbent CETCO PM-199 organoclay mixed with sand will be placed landward of the granite walls. This layer is designed to adsorb residual hydrocarbons if present, thus limiting potential future impact associated with groundwater drainage to the harbor. As a conservative supplement to source removal, the seawall design also includes installation of a horizontal 4-inch-diameter perforated PVC pipe at the base of the organoclay layer, which is accessed through a number of 4inch-diameter solid PVC vertical risers (Drawing S-7). This supplementary system will facilitate manual collection of DNAPL from the base of the seawall if there is postremediation lateral migration of DNAPL from fill material left in place landward of the excavated areas. 13 Concurrent with the organoclay and PVC pipe installation, a geosynthetic wrapped face wall will be constructed behind the organoclay, as shown on Drawing S-7 and S-8. This seawall design – geosynthetic wall, organoclay layer, and granite block wall - has been selected to allow for later removal and replacement of the organoclay if necessary, while meeting current design standards and maintaining the historical appearance of the waterfront. Following seawall construction, the lagging between the mini-piles will be removed to the extent feasible and the tops of the mini-piles will be cut off at 3 feet below finished grade. Much of the above described source removal and seawall reconstruction work will be conducted in the wet in conjunction with the tidal cycles at this location. 7.70.2 Vertical Barrier Construction at National Grid and Maritime Gloucester The objective of the vertical barrier (concrete seawall) to be constructed adjacent to the National Grid building is to limit the potential migration of source material. This material is presumed to be located under the building, with potential migration into the harbor and sediment through the National Grid Existing Building Seawall (see Drawing EC-1 for location). Given the building location relative to the seawall, it is not feasible to excavate the presumed source soils without significantly impacting the building. Therefore, to achieve source control, a low-permeable barrier (i.e., concrete seawall) will be constructed approximately 10 feet seaward of the current seawall to limit the potential migration of coal tar toward the harbor. The barrier will extend approximately 5 feet onto the Maritime Gloucester property to provide additional control of presumed source and additional stability to the existing Maritime Gloucester seawall at this location. This work will consequently create approximately 450 sf of new land behind the new seawall, designated as the National Grid Building Seawall. Construction of the vertical barrier will include interval dredging in front of the National Grid Existing Building Seawall to remove unsuitable sediments, constructing a low-permeability reinforced concrete seawall, and backfilling behind the new seawall with clean granular material. Due to anticipated soil conditions, the new seawall will be supported by steel piles driven to refusal. Steel plates will be placed between the piles closest to the seawall to limit undermining of existing seawall during excavation, and between the outermost row of piles. Additional steel sheets will be placed between the remaining piles to facilitate interval dredging adjacent to the existing wall. Following dredging to remove impacted and structurally unsuitable soils, the new seawall will be constructed in the wet. The new seawall will have a granite façade to match the appearance of other seawalls along the waterfront, and granite blocks will be placed at the toe to provide scour protection. Sand-gravel fill will be placed behind the seawall on the National Grid property to facilitate the flow of groundwater toward the National Grid access ramp seawall, where the organoclay layer will be in place to adsorb residual dissolved hydrocarbons. Concrete fill will be placed behind the seawall at the Maritime Gloucester property (Drawings S-7 and S-8). The upper surface behind the wall will be completed with an approximately 45-linear-foot-long publicly accessible concrete walkway along the water’s edge, with a gangway to the City floating dock system for Harbormaster access. 14 7.70.3 Automated DNAPL Recovery System The Phase IV Remedy in the Southern Area will include installation of an automated recovery system to remove DNAPL from well GZ-4C at the USCG Property as well as locations at the park and National Grid property where residual DNAPL may be present at depth. Installation of this system will be integrated with seawall reconstruction efforts as described below. Following seawall construction, three new 4-inch-diameter stainless steel DNAPL recovery wells, RW-1 through RW-3, will be installed just seaward of the geosynthetic wall at the locations shown on Drawing C-23. The wells will be screened to approximately 55 feet below grade to remove DNAPL from the base of the till layer (see Specification Section 33 20 00 – Extraction and Monitoring Wells). These wells, as well as existing GZ-8B (which will be re-built if damaged during construction), will be completed with precast concrete vaults at each location. The vaults, each with a hinged steel cover, will be finished to match final grade. The wells will be monitored routinely following their installation to evaluate whether residual DNAPL is present at depth at any of these locations. Automated downhole pumps, similar to that used for the DNAPL recovery pilot test system under the IRA described in Section 5.60, will be installed in wells with recoverable DNAPL. DNAPL storage units and control panels for the pumps will be housed at 19 Harbor Loop (Drawing C-24), and will be connected to the wells by dualcontained DNAPL recovery piping consisting of nylon tubing with secondary PVC piping for containment. The piping will extend aboveground from well GZ-4C along the landside of the USCG seawall toward the park, and will then continue belowground at the park and National Grid properties. The DNAPL recovery system will be operated in accordance with the provisions of an MCP Phase V (Operation, Maintenance and/or Monitoring (OMM) of Comprehensive Response Actions) until DNAPL with Micro-Scale Mobility has been removed to the extent feasible in support of a Permanent Solution in the Southern Area. 7.70.4 Engineered Barrier at Solomon Jacobs Park Soils with petroleum hydrocarbon concentrations exceeding UCLs are present within an approximately 3,600-square-foot area in Solomon Jacobs Park. As discussed in Section 5.50 and the memorandum in Appendix I, an engineered barrier will be constructed by excavating soil in this area (Drawing C-16) to between 4 and 6 feet bgs. The excavation will be coordinated with tidal cycles to limit the volume of water that is generated; such water will be containerized and properly managed for off-Site disposal. Given the absence of surface structures at the park and the limited depth of excavation, no shoring or support of excavation is anticipated. Approximately 800 cy of soil will be removed from the excavation and will be managed as described in Section 9.20. Following soil removal, a defining layer consisting of horizontal chain-link fencing will be placed at a minimum of 4 feet bgs and will be overlain with clean fill. In addition, as a further conservative measure, a second demarcating layer of snow fence will be placed at 3 feet bgs to provide an advance visual warning and limit future penetration of the engineered barrier. The finished grade of the 15 engineered barrier will match existing grade, therefore there will be no change in the elevation of the park, and there will be no net loss in pervious surface due to the barrier. The park will be landscaped and restored to its current use, and an AUL will be implemented for inspection and maintenance of the engineered barrier as required by the MCP. 7.80 RESTORATION Following the completion of remedial activities, conditions will be restored at each of the properties as shown on Drawings R-2, R-5 and R-6 and as described below. 7.80.1 Solomon Jacobs Park Following the completion of remedial activities, the park will be re-graded as shown on Drawing R-6, resulting in an approximately 1/2-foot increase in grade toward the parking area and no change in grade along the harborfront. New landscaping, benches, and planters will be installed, and existing monuments (e.g., the Harbor Walk granite monument and the Captain Solomon Jacobs plaque) that were temporarily removed to facilitate remedial activities will be replaced. The final design of the park has been approved by the City of Gloucester. In the Nearshore Area adjacent to the park, the new City of Gloucester-owned floating dock system will include three shallow-draft concrete floats, three deep-draft concrete floats, and four adjoining finger floats (Drawing R-2). The floating docks have been designed to surround Harbor Rock on three sides, reducing the navigational hazard posed by this natural feature. A new aluminum gangway will provide public access from Solomon Jacobs Park to the floating dock system. The gangway will be mounted to the top edge of the new park seawall, and will be compliant with the provisions of the Americans with Disabilities Act. 7.80.2 National Grid Property The strip of land to the south of the National Grid building, adjacent to Solomon Jacobs Park, is currently paved. Much of this area will be excavated during remediation either as part of the SOE for the new seawalls, to install utilities for the City floating dock system, and/or to construct a Utility Corridor along the National Grid driveway for future subsurface work (Drawing C-16). Following the excavation and off-Site removal of soil from the Utility Corridor trench, orange filter fabric will be placed along the extent of the trench to serve as a demarcation layer, the sewer force main for the marine sewerage pump out and spare conduits for future utilities will be installed, and the trench will be backfilled with compacted sand fill (Drawing C-20). Upon completion, the grade at the seaward edge of this area will be raised to match the grade within the park, and the surface will be finished with either bituminous pavement or concrete to match surrounding areas. As stated earlier, the control panels and storage units for the DNAPL recovery system will be housed within the building on the National Grid property. This will require some alterations to the building, such as construction of internal walls or installation of additional doorways, which will be performed by National Grid during the remediation project. The building will continue to be occupied by the Gloucester Harbormaster following the completion of Phase IV activities. 16 The vertical barrier in front of the National Grid Existing Building Seawall will result in the creation of a publicly accessible concrete walkway along the waterfront, with signage as required by MassDEP Waterways department. A second gangway will provide access for the Gloucester Harbormaster from this walkway to the City floating dock system. A telescoping davit (winch) will be installed near the National Grid access ramp seawall for operation by the Harbormaster to facilitate moving materials to and from boats. In addition, a marine sewage pump-out station will be installed at the property for use by the Harbormaster’s office to service vessels. 7.80.3 Maritime Gloucester The portions of the Main Pier and hauling piers at Maritime Gloucester that were removed to accommodate dredging efforts will be reconstructed in kind, and the floating docks and gangways will be replaced. The area in front of the Maritime Gloucester boat house, as well as any temporary staging and material storage areas at this property, will be restored to existing conditions. As described in Section 7.10.4., a timber walkway will be constructed to provide waterfront pedestrian access between the new land and the existing land at this property. 7.80.4 USCG Property The interim docking structure at Pier 2 will be removed, and the USCG floating docks will be re-located to their existing locations. The dredging operations and MAM installation will not result in adverse impact to in-water operations at this facility. No significant remedial response actions are planned in the upland area, but conditions at the temporary staging and material storage area will be restored to existing conditions. 7.80.5 Marine Area With the exception of an approximately 10-foot zone along certain seawalls (i.e., the USCG stability wedge, the vertical barrier at National Grid and Maritime Gloucester, and the Maritime Gloucester Boat House Seawall Stability Enhancement), postremediation mudline elevations within most of the Nearshore Area will be at or below existing conditions. The porewater cap at the USCG, City of Gloucester and National Grid properties will be subject to post-remediation inspection and maintenance requirements as described in Section 13.00, but will not adversely impact in-water operations at any of the properties. The post-remediation mudline in the approximately 5 acres that comprise the Offshore Area, including the Federal navigation channel and anchorage areas, will be at or below existing grades, and will not be subject to restrictions on future dredging. 10.00 INTERACTION OF REMEDIAL ACTION WITH SITE FEATURES, AND IMPACT ON ENVIRONMENTAL RECEPTORS (310 CMR 40.0874(3)(B)(9) AND (10)) 10.10 RELATIONSHIP TO EXISTING ACTIVITIES OR OPERATIONS As described in Section 2.00, the Phase IV Remedy will be implemented across properties with different ownership and uses, including the USCG Gloucester station; the City of 17 Gloucester Solomon Jacobs Park and Public Landing; a commercial property owned by National Grid and occupied by the Gloucester Harbormaster; and the Maritime Gloucester marine educational facility. National Grid has worked with each of the property owners to sequence work such that impact to their operations is limited to the extent possible, and to provide interim facilities for those operations that must continue during remediation. Work at each of the properties will be conducted in accordance with the terms of access agreements between National Grid and the property owners as described in Specification Section 01 14 00 – Work Restrictions and Sequence. The access agreements include property-specific restrictions on the periods during which the project contractor may conduct work in the upland and/or marine area(s) of each property. A graphical representation of these restrictions is provided on Drawings G-5 and G-6. 10.10.1 USCG Property Remediation activities in the upland portions of the USCG property will be limited to installation of DNAPL piping and well vault at GZ-4C and staging of some clean materials. However, extensive remediation is planned in the Nearshore Area at and adjacent to this property. This work will be coordinated with the temporary re-location of the USCG vessels to an alternate docking system at Pier 2, as described in Section 7.10. This will allow USCG operations to continue throughout the remediation efforts at the Site. 10.10.2 Solomon Jacobs Park In accordance with the terms of the agreement between the City of Gloucester and National Grid, work at Solomon Jacobs Park will not be initiated until after Labor Day, when there are fewer visitors and less use of the park and public landing compared to the summer months. The park will be closed to the public between Labor Day and Memorial Day during each work season. These short-term restrictions are necessary for public safety. However, on a long-term basis, the project will enhance public use of, and waterfront access at, Solomon Jacobs Park by restoring infrastructure that is currently in need of rehabilitation. 10.10.3 National Grid Property The National Grid building at 19 Harbor Loop will serve as a project office for the contractors and National Grid’s construction oversight team during the remediation. Office space will also be provided to the City of Gloucester Harbormaster, whose in-water operations will be relocated to an alternate location within the harbor during each work season in accordance with an agreement between National Grid and the City of Gloucester. Following completion of the project, the Harbormaster will have continued use of the building and direct access to the City floating dock system, as described in Section 7.80. In addition, the public will be afforded increased waterfront access along the new land constructed behind the vertical barrier. 10.10.4 Maritime Gloucester Under the terms of the access agreement with Maritime Gloucester, a portion of their property near the boat house will be cordoned off for public safety at the beginning of 18 each season of remediation. During the first remediation work season, when the vertical barrier construction will restrict access to the area south of the Main Pier, National Grid will construct an interim landing at the Northern Hauling Pier to allow a gig rowers’ club access to the waterfront. During the second remediation work season, the piers at the property will be removed and replaced, and areas along the seawall and driveway will be used for staging materials and providing access to land-based equipment. Dredging to remove MGPrelated sediment will be coordinated with dredging to remove sediments impacted by Maritime Gloucester (RTN 3-3341), which will be documented under separate submittals to MassDEP. 10.10.5 KRLLC The extent of remediation at KRLLC is anticipated to be limited to approximately six cy of dredging along the in-water property line with Maritime Gloucester. This work will be conducted in accordance with the terms of the access agreement between the property owner and National Grid. 10.20 RELATIONSHIP TO DRAINAGE FEATURES AND NATURAL RESOURCE AREAS, AND IMPACTS TO ENVIRONMENTAL RECEPTORS As required by the MCP, this section provides a discussion of the measures that have been incorporated into the design, construction and operation of the selected CRA to avoid deleterious impact on drainage features, environmental receptors and natural resource areas (including surface water or wetland), or where it is infeasible to avoid such impact, a discussion of measures to limit or mitigate impacts. 10.20.1 Identification of Natural Resource Areas In support of a Notice of Intent filing with the Gloucester Conservation Commission for implementation of the Phase IV Remedy, the following coastal resource areas were identified within the project boundaries, and were assessed to characterize existing conditions and potential impacts associated with the proposed remediation activities. Both temporary and permanent alterations to these resource areas are anticipated with the implementation of the proposed remedial activities and associated mitigation. Modification of the resource areas has been limited to the extent practical, while still allowing the project remediation goals to be accomplished. As demonstrated below, the remediation has been designed to be protective of the resource areas such that there should be no adverse impacts to these areas following the completion of the remediation work. Designated Port Area (DPA) The Project Area is located within a developed harbor that is a DPA, described in Section 301 CMR 25.00 of the Coastal Zone Management (CZM) Regulations for Massachusetts (Massachusetts 1994). DPAs are a coastal resource area under the Massachusetts Wetlands Protection Act (WPA; M.G.L Chapter 131, Section 40)). The WPA is administered on the local level by the Conservation Commission, which implements the Massachusetts Wetlands Regulations (310 CMR 10.00). 19 The Phase IV Remedy is expected to both temporarily and permanently alter coastal resource areas located within the DPA; however, the functions of the DPA will not be significantly impacted by the project. Temporary impacts will include short-term interference with navigation when remediation work is being performed in the navigational and anchorage areas. Long-term impacts will benefit the DPA based on a net deepening of some navigational and anchorage areas. The project has received regulatory approval from the Conservation Commission (Section 14.20) and from the Massachusetts Office of CZM, which is tasked with reviewing Federal actions2 affecting coastal uses and/or resources to ensure that such actions are consistent with the state’s enforceable program policies. Land Under the Ocean, Land Containing Shellfish and Coastal Beach Overall, the project will provide a net benefit to these coastal resource areas because MGP-related impacts, including sediment in the harbor and source material behind the seawalls, will be removed or contained. However, dredging to remove the sediment, and excavation/seawall construction associated with source removal and control, will have the following impacts. Dredging, backfilling and porewater cap placement will result in both permanent and temporary impacts to these resource areas because sediment will be removed, new clean material will be placed in some of the dredged areas, and the harbor bottom elevation and water depth will be changed in portions of the resource areas. The change in harbor bottom elevation and water depth is not expected to significantly adversely impact the resource areas. Backfilling to reestablish benthic habitat, manage residuals, and provide structural stability is not anticipated to have significant impacts to the resource areas as the clean material is generally similar to existing material in portions of the Land Under the Ocean, Land Containing Shellfish, and Coastal Beach. Porewater cap placement will result in an alteration to Coastal Resource Areas in the Nearshore Area because the cap materials are expected to be larger or of a different material type (e.g marine armor mattresses) than existing materials in portions of the Land Under the Ocean and Land Containing Shellfish. Benthic recolonization is expected to occur following dredging activities whether dredged areas are backfilled/restored or not, and the quality of benthic habitat will be improved as described in Section 10.20.5. Seawall Removal and Reconstruction will result in a permanent increase of Land Under the Ocean because a portion of the previously built land and enclosing seawall (National Grid Pier Seawall) will be removed and will not be replaced. The total area of the Land Under the Ocean will be increased in this area by approximately 1,150 square feet. At the same time, construction of the vertical barrier for source control will result in an approximately 450 square-foot reduction in the area of Coastal Beach seaward of the National Grid and Maritime Gloucester properties. Mitigation for this alteration is discussed later in this section. 2 CZM review was triggered by the submittal of permit applications to the USACE, and included review of the project in terms of the State’s Coastal Hazards and Habitat policies as well as applications filed with MassDEP Wetlands and MassDEP Waterways programs. CZM issued a letter on April 6, 2015 concluding that the activity (i.e. remediation) as proposed is consistent with their enforceable policies. 20 Coastal Bank, Land Subject to Coastal Storm Flowage, and Buffer Zones Seawall Removal and Reconstruction: The reconstruction of the seawalls at Solomon Jacobs Park and National Grid will permanently impact Coastal Bank, Land Subject to Coastal Storm Flowage, and Buffer Zones. Some Coastal Banks such as the seawall associated with Solomon Jacobs Park and National Grid will be removed and relocated, with a loss of approximately 50 linear feet of Coastal Bank due to the removal of land in front of Solomon Jacobs Park and the Existing National Grid Seawall. The location of the Coastal Bank (i.e. seawall) at a portion of the National Grid and Maritime Gloucester properties will move approximately 10 feet seaward as a result of vertical barrier construction. Soil Excavation and Construction of Engineered Barrier: Work associated with soil excavation and placement of the engineered barrier will take place entirely within the Land Subject to Coastal Storm Flowage and the 100-foot and 200-foot Buffer Zones to Coastal Bank, Coastal Beach, and Land Under the Ocean (relevant under Bylaw). There will be no permanent changes to the characteristics of the land surface related to the soil removal work because the area will be returned to pre-remediation grades and there will be no increase in impervious surface in this area. Due to the removal of previously built land, there will be a reduction in total impervious Buffer Zone. 10.20.2 Best Management Practices to Limit Impacts The Phase IV Remedy will be conducted in accordance with the terms of WQC X255073 issued by the MassDEP Wetlands Program, and two Orders of Conditions (OOC #28-2369 for the remediation project, and OOC #28-2371 for the City floating dock system) issued by the Gloucester Conservation Commission, each of which includes conditions designed to limit the impacts of the project on the natural resource areas and environmental receptors of Gloucester Inner Harbor. In addition, as described earlier in this Phase IV RIP, a number of Best Management Practices (BMPs) will be employed during the work, including the use of erosion and sedimentation controls in the vicinity of catch basins and drainage areas (Section 8.40) and marine resuspension controls around inwater silt-generating activities (Section 7.10.6). 10.20.3 In-Kind Mitigation - Creation of Compensatory Tidal Area As a result of the vertical barrier construction, 450 square feet of Coastal Beach and Land Subject to Tidal Action in front of the National Grid and Maritime Gloucester properties will be converted to upland in order to control MGP-impacted source material. The Coastal Beach/Land Subject to Tidal Action in this area consists largely of fill material emplaced during seawall construction, with cobbles and boulders and some miscellaneous debris material exposed along the base of the wall at low tide. Because the Project Area is located within a DPA, these Coastal Beaches and Land Subject to Tidal Action, are categorically “not likely to be significant to marine fisheries, storm damage prevention, or flood control” (310 CMR Section 10.206). Nevertheless, the project design includes the compensatory creation of approximately 750 square feet of Coastal Beach/Land Subject to Tidal Action on top of the Stability Wedge in front of the USCG Seawall. This voluntary in-kind mitigation element results in a net gain of approximately 300 square feet of this resource within the Project Area. The surface, which is designed to provide both scour protection and habitat, will consist of approximately 18 inches of 21 materials similar to the Coastal Beach material currently present in front of the National Grid seawall, with a surface elevation above MLW (-3.79 feet NGVD 29). 10.20.4 In-Kind Mitigation - Increase In Subtidal Habitat Area to Benefit Protected Fishery Resources and the Environment In addition to the compensatory in-kind mitigation described above, the project will result in the removal of 1,150 square feet of land behind the National Grid Pier Seawall that will not be replaced. Combined with the 750 square feet of Land Under the Ocean that will be converted to Coastal Beach at USCG property, this will result in a net increase of 400 square feet of Land Under the Ocean. The creation of this new Land Under the Ocean, in conjunction with the remedial actions to be undertaken at the Project Area, will benefit two important local species, American lobster (Homarus americanus) and winter flounder (Pseudopleuronectes americanus). Gloucester Harbor waters continue to support a productive lobster population, and winter flounder is a key recreational and commercial fish for the area. 10.20.5 Mitigation - Habitat Enhancement in Existing Areas Another aspect of the proposed mitigation involves enhancing existing habitat to improve conditions for biota of the area. Following implementation of the Phase IV Remedy, a condition of NSR to the environment will be achieved, representing a significant enhancement of habitat conditions within the harbor. Additional habitat enhancement for benthic invertebrate and fisheries species will be provided by elements of the project that will be implemented prior to, during, and following the proposed remedial dredging within the harbor. A key example is the removal of intertidal and subtidal debris from within the dredge prism area, which will benefit benthic invertebrate production. Debris such as bricks, rip-rap, grout, cables, chains, line, and broken piles has been observed within the Project Area and will be removed as part of the dredging remediation activities. In addition, habitat features for fishery species are factored into the design and will benefit American lobster and winter flounder, as well as other fisheries species. The increased cobble, gravel, pebble, mud, sand, and flat rock substrates to be placed after completing remediation are appropriate habitat enhancement features for lobster. A gravel or cobble habitat will be created in the newly created Land Subject to Tidal Action, and material that may range from gravel to larger cobble sizes will be placed in areas in front of the USCG, Solomon Jacobs Park, and National Grid properties where an erosion protection layer is necessary to mitigate the effects of propeller scour. Flat rock substrates, consisting of re-used granite block materials from the existing walls to the extent practicable, will be present along the toe of the newly constructed/rehabilitated seawalls. For winter flounder, habitat features that will be created or enhanced in the project vicinity include sand and mud substrates. The removal of impacted sediments and the placement of the 6-inch layer of backfill in the Nearshore Area, including in the newly created Land Under the Ocean, will result in habitat enhancement for winter flounder spawning grounds and will benefit other fishery and benthic species within the Project Area. In conclusion, the removal of impacted sediments from the Inner Harbor, removal of debris from the substrate, the post-dredging increase in total area of Waters of the U.S. 22 and Land Under Ocean, and the use of habitat enhancing backfill will result in an overall net benefit to the American lobster, winter flounder and general fisheries resources in the Gloucester Inner Harbor. 10.30 RELATIONSHIP TO LOCAL PLANNING AND DEVELOPMENT ISSUES 10.30.1 Short-Term Impacts to Local Infrastructure The primary short-term impact to local infrastructure is associated with the transport of equipment and materials to and from the Site. As described earlier, the shipment of remediation waste via barge instead of by land will greatly reduce anticipated impacts to local roadways during the project. Land-based transport of materials and equipment cannot be entirely eliminated, but as shown on Drawing C-1, truck traffic associated with the project will avoid the downtown areas and will be routed along Rogers Street and East Main Street (Route 127), connecting to Route 128. It is not anticipated that street closures will be necessary to implement the proposed work, however, as necessary, traffic details will be utilized. The project will also have short-term impacts on waterways within Gloucester Inner Harbor associated with dredging activities and the concurrent barge or scow transportation of dredged sediments. As part of the Chapter 91 permitting process, a Sitespecific Marine Boating Coordination Plan was requested and approved by MassDEP Waterways Program, and notifications to local waterways users and Site abutters will be made in accordance with the plan. There will be a decrease in the ability of watercraft to access certain portions of the Site during work on and adjacent to seawalls and during dredging; however, accommodations will be made for safe alternate watercraft passage. Note that the changes in remediation waste shipment discussed above will also reduce potential inner harbor traffic congestion, because far fewer transport trips are required with the much larger scows. 10.30.1 Long-Term Impacts to Local Infrastructure The long-term impacts to local infrastructure are anticipated to be overwhelmingly positive. Currently, the wooden pier and concrete landing in front of Solomon Jacobs Park are in poor condition, and portions are closed to the public. The granite block seawalls in this area date back to the late 19th century, and do not meet current design standards. The new seawalls designed as part of source removal and control efforts will meet current engineering standards and accommodate projected sea level rises over the coming years. The walls will visually match the existing granite walls along the harborfront to retain the historical appearance of the harbor. The stability of other seawalls, such as the USCG seawall and the Maritime Gloucester Boat House Seawall, will also be enhanced as a result of the project. Following remediation, Solomon Jacobs Park and the adjacent parking area will be restored to provide waterfront views and access for local residents and visitors. The new land at the National Grid and Maritime Gloucester properties will provide additional public access to the waterfront in this area. The project is also being coordinated with, and materially contributes to, the City of Gloucester efforts to install a new floating dock system to provide upgraded landing facilities and facilities for Harbormaster use. 23 Within the harbor, commercial and private boaters will benefit from increased water depth within the navigation channel following the completion of the project. 10.40 SOIL CHARACTERISTICS AND GROUNDWATER CHARACTERISTICS The remediation efforts will result in removal of MGP-impacted soil from Solomon Jacobs Park and the National Grid property, and its replacement with clean fill within an engineered barrier in the central portion of the park, and as part of a geosynthetic wrapped face wall behind the granite block seawalls. The replacement fill material will be more suitable than the granular fill material it replaces. For example, some of the existing fill, particularly proximate to the seawalls, is open-worked, which can result in collapse of surface pavements. In addition, the replacement fill is anticipated to be more permeable than the silty clay material encountered in some areas to be excavated. Thus the replacement fill will promote drainage via infiltration, rather than surface runoff, of precipitation. Removal of the MGP-impacted soil is also anticipated to result in lower dissolved hydrocarbon concentrations in the groundwater beneath the park. Decreasing dissolved phase hydrocarbons in groundwater will result in lower concentrations discharging to the harbor. The organoclay layer placed behind the new granite block seawalls will adsorb residual hydrocarbons, further reducing dissolved concentrations potentially discharging through the seawalls. Groundwater quality beneath the National Grid building will not be directly improved by the remediation activities. However, the fill material placed behind the new vertical barrier will be significantly more permeable than existing fill, and in combination with the impermeable wall, will channel groundwater flow from impacted soils beneath the building toward the organoclay barrier behind the new granite block walls, thus also further reducing impacts to the harbor. 12.20 DESIGN AND CONSTRUCTION SCHEDULE Design efforts and specification preparation for the project have been completed, the specifications were put out to bid, bids were received and analyzed, and a contractor was selected with Notice to Proceed awarded to Charter Contracting Company, LLC (Charter) of Boston, Massachusetts in June 2015. Construction is planned to occur over two to three construction seasons starting in September 2015. The following restrictions apply to this project: Silt-producing in-water work will be subject to TOY restrictions established by the DMF, which restricts activities between February 15 and June 30 to avoid effects on Winter Flounder (Pseudopleuronectus americanus) spawning activities. In accordance with the terms of agreements between National Grid and the property owners, there will be restrictions on remediation activities between Memorial Day and Labor Day to reduce impacts on public access to Solomon Jacobs Park, the public landing, and the Maritime Gloucester facility during the summer. The primary silt-producing activities during this project will include the dredging of sediments, backfilling, porewater cap installation, removal of the existing seawalls, 24 excavation of associated coal tar-impacted soils/sediment, and installation of piles to support the replacement of waterfront structures after remediation. To comply with TOY restrictions, the project schedule calls for dredging and backfilling to be completed prior to February 15 of each year. Similarly, it is anticipated that removal of the existing seawalls and the excavation of soils/sediment will also be completed prior to February 15 of each work season. Every effort will be made to coordinate and expedite activities such that inwater piles can be installed prior to February 15; however, a variance from TOY restrictions may be requested to allow for the completion of pile installation in some localized sections of the Project Area. BMPs and environmental controls will be used throughout the remediation work to limit adverse impacts to environmental receptors. Subsequent wall re-building activities (including construction of the granite block walls, organoclay installation, and construction of the geosynthetic wrapped face walls) are not silt producing; therefore, these activities will continue past February 15, but will be completed in accordance with property-specific timing restrictions. The following general remediation sequence is anticipated: Season 1 (Year 1, September 2015 – May 2016): Installation of interim docking facility/gig rower access at the USCG and Maritime Gloucester properties Source removal/control and seawall rehabilitation at the Solomon Jacobs Park, National Grid and Maritime Gloucester seawalls Nearshore remedial activites in portions of the USCG, City of Gloucester, and National Grid properties Upland remedial activities (e.g., engineered barrier construction, and DNAPL recovery system installation) activities at the City of Gloucester and National Grid properties Remedial activities in the offshore portion of the marine area Season 2 (Year 2, currently anticipated to be July 2016 to May 2017): Completion of remedial activities in the offshore portion of the marine area Removal and rebuilding of the Maritime Gloucester in-water structures (to the extent required) Completion of nearshore remedial activities at the Maritime Gloucester, National Grid, City of Gloucester, and USCG properties Completion of upland remedial activities Re-installation of waterfront structures, and restoration of upland areas to pre-construction conditions. 25 Note that, although the schedule calls for project completion in two work seasons, work may extend into a third season in areas of the Site due to the logistical complexities and TOY restrictions applicable to the Site. 26