The burden of proof

advertisement
THE SIGNIFICANCE OF THE BURDEN
OF PROOF FOR CONTRACTORS
Key words
Burden of proof, cause of action, evidentiary burden, facts to be proved, proving a negative, building
contracts, building subcontracts, decision to declare a dispute, record keeping.
Introduction
One of the most essential considerations when thinking of initiating dispute resolution procedures as
well as when entering into correspondence on a matter which can lead to a dispute, sometimes long
after completion, is whether you have the evidence that will prove your case. If such evidence is not
available or is not convincing, there is no point to spending good money to chase bad. Contractual
litigation is not about proving a point, it is about economic considerations. Conversely, being
prepared may not only protect you but may also discourage claims against you.
The facts that must be proved
The starting point in all such cases is to establish the
basic matter in dispute. This is not always easy to
determine. Once the issues have been determined the
cause of action probably becomes much clearer
although this may be a chicken and egg situation. The
cause of action tells you what facts are required to be
alleged and proved to be successful and from this is then
extracted what evidence is available to prove the case.
All these stages have specific legal expressions which
help the discussion.
Cause of action was defined in Read v Brown (1888) 22 QBD 1311 as “... every fact which it would
be necessary for a plaintiff to prove, if traversed [asof afsonderlik weerspreek] in order to support his
right to a judgement of the Court. It does not comprise every piece of evidence which is necessary to
prove each fact, but every fact which is necessary to be proved.” It was quoted in SA Law in the case
of McKenzie v Farmer’s Co-operative Meat Industries Ltd 1922 AD 16 at 232. I do not know of many
lay people who understand this definition so it is easier to try to explain it on the basis of the facta
probanda. A cause of action comes into being when all the elements of the claim (see facta
probanda) are present (i.e. a party can sue the other).
1
2
See Christie p. 556
See Potgieter p. 160
Page 1 of 5
The significance of the burden of proof in building contracts and subcontracts
Facta probanda are the facts that need to be proved for an action to succeed. In a claim for damages
for breach of contract these would briefly be the contract, the existence of the term relied on, a
breach of the term and the existence of some prejudice. Within these brief words, lies a multitude of
relevant detail which is generally best dealt with by legal practitioners.
The facta probanda are proved by the evidence that is provided to the trier. This evidence is referred
to as the facta probantia. The detail of the dispute lies in this area.
Within these concepts, which are inter-related, lies the essence of any decision as to the
correspondence and documentation that is essential to guide a dispute to a successful outcome as
well as the potential successful outcome and the limitation of issues in dispute. It is therefore
essential that when dealing with a particular problem, written records be generated that provide a
written source of evidence that supports the facta probanda, provides a good cause of action and
limits the issues in dispute. Obviously this can only take place within a legitimate judicial framework
and it is pointless to attempt to use correspondence to alter a fact which is incontrovertible.
The burden of proof
In any court case, the court uses the principle of the burden of proof, also called the ‘onus’, to assist
it in determining the matter before it3. Schwikkard quotes at p. 559 from Heydon & Ockelton4 in
explaining onus as “the obligation of a party to persuade the trier of facts by the end of the case of
the truth of certain propositions.”
The burden of proof in criminal cases is the ubiquitous ’beyond
reasonable doubt’ of the TV programmes whereas in civil cases it is only
‘on a preponderance of probabilities’,5 subject to any legislation
changing this onus6 in specific situations. Therefore a party who bears
the burden of proof succeeds only if the balance of probability is tipped
in its favour. If the trier is uncertain or in doubt as to whether the
balance has been so tipped then the onus has not been discharged and
the other party is successful7.
Court cases have sometimes been fought virtually exclusively on the basis of the burden of proof
because neither party has sufficient evidence to prove its case so that the party on whom the
burden of proof lay failed to discharge its onus and lost the case.
The principle regarding who bears the burden of proof is contained in the broad statement that he
who avers must prove. In general the plaintiff who seeks an award in his favour must prove his
3
See Schwikkard p. 558
Evidence: Cases and Materials, 4th Edtn, (1996) 15
5
See Ley v Ley’s Executors 1951 3 SA 186 (A)
6
See Schwikkard p. 581
7
See Schwikkard p. 580 who quotes Lord Denning in Miller v Minister of Pensions 1947 2 All ER 372 374: “If the
evidence is such that the tribunal can say ‘we think it more probable than not’, the burden is discharged, but if
the probabilities are equal it is not”. This judgment was adopted in Ocean Accident and Guarantee Corporation
Ltd v Koch 1963 4 SA 147 (A).
4
Page 2 of 5
The significance of the burden of proof in building contracts and subcontracts
entitlement thereto. However, this rule may change depending on the pleadings and the law in
relation to the dispute. For example, in a contract for the hire of goods or property, the tenant bears
the onus of proving that any damage to the hired product during the hire period was not due to his
fault. Similarly, where the pleadings include confession and avoidance, such as an admission of
assault with the avoidance of self-defence, the burden is on the defendant to prove his defence8.
All authors in this subject highlight the fact that the above burden of proof is not the same as the
evidentiary burden which moves between parties as the case progresses. The evidentiary burden lies
on the party who bears the burden of proof until a prima facie case has been built up from the
evidence where after it shifts to the other party who must produce evidence to counter it. This
burden may swing backwards and forwards between the parties during the progress of the dispute.
How the rules affect contractors and subcontractors
Schmidt at para 2.2.1.2 2 (a) to (d) at pp. 2-14 to 2-17 clarifies matters and Schwikkard summarized
it as follows in footnote 6 on p. 572: [note this is not a verbatim quotation]
“Plaintiff has to prove the existence and relevant terms of the contract as well as any prerequisites in
respect of the Defendant’s liability e.g. that he suffered damages or that he performed his own
contractual obligations. If the Defendant denies the existence of a contract between him and the
Plaintiff, the latter will carry the burden of proving the contract because the Defendant’s defence is a
flat denial. The same approach would be followed if the Defendant were to allege that the Plaintiff
never suffered any damages or had failed to perform his own contractual obligations. However, …
the Defendant would carry the burden of proof should he … plead one of the following [special
defences]: (a) that the Plaintiff had released him from the amount due; (b) that the Plaintiff’s claim
has prescribed; or (c) that the contract was unlawful… Interruption of prescription must be proved by
the Plaintiff.”
The law that contracts are enforceable also means that, when making a claim in terms of a contract,
the claimant must prove the existence of the contract and all its terms. The problem faced by a
claimant is that where a defendant denies liability on the basis of an alleged clause excluding
liability, the burden remains on the claimant to prove that the clause does not exist in the contract9.
Similarly, in a contract wherein the contractor alleges he has tendered on the basis of drawings that
did not include a balcony for which the defendant is deducting money from his contract sum, the
burden is on the contractor to prove that the balcony was not shown on the tender drawings. This is
sometimes referred to as ‘proving a negative’. The implications of this requirement can be extremely
onerous and embarking on an action wherein it becomes necessary to prove a negative should be
undertaken with great care. This accentuates the need to ensure that there is proper contract
8
See Mabaso v Felix 1981 3 SA 865 (A). Note that this was a civil case wherein Felix was found liable for
Mabaso’s damages and which followed on a criminal case in which Felix was acquitted because the state failed
to discharge the onus of proving guilt beyond reasonable doubt.
9
See Stocks & Stocks (Pty) Ltd v TJ Daly & Sons (Pty) Ltd 1979 3 SA 754 (A) wherein the respondent alleged a
clause excluding liability for damage and the applicant could not satisfactorily prove to the court that there
was no such clause.
Page 3 of 5
The significance of the burden of proof in building contracts and subcontracts
documentation in place as well as to ensure correspondence comprehensively provides the
additional evidentiary foundation needed to convincingly prove the facta probanda to the trier.
The other effect that must be raised is the need to have relevant documentation available after the
completion of the contract. The effect of presumptions which permeate the law is that when there is
a failure such as a slab collapse, there is a presumption that the slab was incorrectly constructed and
this generally has the practical consequence of placing the contractor in the position of being guilty
unless he can show he is innocent. The typical situations which can arise are shown in the following
two examples:
A slab collapses in a car park. Investigations show that certain reinforcing bars that were shown in
the detailing and bending schedules as having a hook at the one end were installed with no such
hook, thereby causing the collapse. The actual background to the story is that the bars arrived on
site as designed with the hook for the first concrete pour. During the fixing process, the fixer phoned
the engineer to tell him that the hooked bars did not fit into the steel reinforcing cage with the
hooks and the engineer instructed him to cut them off. The instruction is never recorded and repeat
supplies of the bars for the remaining pours are delivered without the hook because the fixer has
diligently told the bar yard to not put a hook in them again. However, when the collapse occurs,
none of the people concerned is working for the respective parties so the engineer pulls out his
drawings which show hooked bars and the contractor cannot prove why he failed to work to the
drawings so the liability for the collapse and its repair rests on his shoulders.
Another example is the case where the contractor and his subcontractor install storm water pipes in
an area adjacent to a library. On studying the drawings they pick up that the pipes are laid very deep
and there appears to be no reason for it. They contact the engineer who agrees and instructs that
the pipes are to be laid to shallower depths. As the work is subject to re-measurement on site,
nobody bothers to record the change. A few years later there is a cloudburst over the area and the
library is flooded. Again there is an investigation and the engineer shows that the pipes were
designed to be laid deeper and that this would have averted the flooding. The contractor has no
evidence to protect him from liability and is held responsible for the flooding and the repairs to the
entire storm water system.
Conclusion
Construction contracts often extend over long periods, often more than a year, and contractors and
subcontractors do not know what potential disputes they will face. Although there are people who
believe an open-ended and vague contract offers more opportunity for claims, that is a matter that
will depend on who bears the burden of proof in the dispute. If a party wants to claim on such a
vague contract, it will potentially face an insurmountable obstacle when it gets to trial and has to
discharge its onus. It is therefore far preferable to ensure the contract is clear and comprehensive. In
addition, early written communications that address issues that will possibly need to be proved can
also come to the assistance of the party who wishes to lay down a solid foundation10.
10
Such correspondence normally excludes any exchanges prior to the agreement of a written contract because
of the parol evidence rule as well as the normal ‘entire contract’ clauses included in most building contracts. It
Page 4 of 5
The significance of the burden of proof in building contracts and subcontracts
Once a potential area of dispute is identified, the cause of action and probable facta probanda
should be outlined because, even if the pleadings alter the process, it is unlikely the essential facts to
be proved will change significantly.
Even if the correspondence results in a dispute as to a fact or the interpretation of a term, this is still
beneficial because it clarifies and can limit the issues which need to be referred for dispute
resolution.
This process may help to eliminate wastage by chasing bad money with good.
The need to have specific records available for protection against future claims is similarly of
extreme importance and few contracting offices ever attach the necessary attention to this risk.
BIBLIOGRAPHY AND REFERENCES USED
Christie: Christie RH, The Law of Contract in South Africa, (5th Edtn), 2006, Butterworths, Durban.
Schwikkard: Schwikkard, PJ, van der Merwe, SE, Principles of Evidence, 3rd Edtn, 2012, Juta & Co,
Claremont.
Schmidt: Schmidt, CWH, Rademeyer, H, Law of Evidence, Issue 11, 2011, LexisNexis Durban
Potgieter: Potgieter, JM, Steynberg, L, Floyd, TB, Visser and Potgieter Law of Damages, 3rd Edtn,
2012, Juta & Co, Claremont.
can also not attempt to alter the contract terms if there is a ‘non-variation’ clause as the prescribed formalities
must then be complied with to vary the terms.
Page 5 of 5
The significance of the burden of proof in building contracts and subcontracts
Download