50 schools for expansion and rehabilitation

advertisement
E4515 V5
REPUBLIC OF GHANA
MINISTRY OF EDUCATION
SECONDARY EDUCATION IMPROVEMENT
PROJECT (SEIP)
ENVIRONMENTAL AND SOCIAL
MANAGEMENT PLAN FOR 50 SELECTED
SCHOOLS FOR EXPANSION AND
REHABILITATION
FEBRUARY 2015
50 SCHOOLS FOR EXPANSION AND REHABILITATION
ENVIRONMENTAL AND SOCIAL MANAGEMENT PLAN
EXECUTIVE SUMMARY
The Government of Ghana, through the Ministry of Education, proposes to construct 200 new
Senior High Schools under a Secondary Education Improvement Project (SEIP). The proposed
SEIP with funding from the World Bank would support the implementation of the government’s
Community Day Senior High School Project (CSHSP) through two components: (i) Support to
Increase Access with Equity and Quality in Senior High Schools; and (ii) Management, Research
and Monitoring and Evaluation.
The SEIP is expected to finance results which demonstrate increased access in targeted districts,
increased enrolment of poorest students and improved learning outcomes for selected low
performing senior high schools. The Government of Ghana plans to achieve these results through
the construction of new senior secondary schools in underserved areas, rehabilitation and
expansion of existing low performing schools and support for Senior High School (SHS)
attainment for disadvantaged students. In addition, activities are planned to improve the quality
of selected low performing schools with a focus on mathematics and science education. The
Government plans to do this by: providing 23 new senior high schools in mostly underserved
areas; expanding and upgrading support for 125 existing low performing SHSs; providing threeyear scholarship support for at least 10,400 needy and qualified SHS students especially girls,
and; providing school performance partnerships in selected 125 schools to improve quality and
connectivity to the internet. In order to achieve and report on the results attained under the
project, the SEIP will provide funding and technical assistance to the implementing agencies and
the third party validation agencies. The development of a research program to better understand
constraints and challenges in secondary education while formulating a national secondary
strategy would also be included under the project. The introduction of a web platform for school
reporting and real time monitoring would increase social accountability and information sharing
on the performance of the sector.
Activities under SEIP are: (i) the construction of new senior secondary schools in 14 districts
which currently have no senior secondary schools; (ii) new construction in 9 selected districts
based on district criteria for population demand, poverty indicators, etc; and (iii) upgrading,
expansion and rehabilitation (E&R) of existing selected low performing schools. The
rehabilitation and expansion aspect of the project is to occur in two separate batches, the first for
50 selected senior high/technical schools across the 10 administrative regions, and the second
for another set of 75 existing senior high/technical schools. The E&R aspect is to occur on existing
schools that have seen increased demand for intake of junior high school graduates, or have weak
and dilapidated infrastructure that need to be replaced or rehabilitated. Thus, the subprojects are
GSEIP/ESMP
Page ii
50 SCHOOLS FOR EXPANSION AND REHABILITATION
ENVIRONMENTAL AND SOCIAL MANAGEMENT PLAN
not being developed on newly acquired lands, but are part of the schools’ existing land take.
Hence, there are no issues of displacement or involuntary resettlement, and of compensation to
any persons, as these lands have been previously vested in the State.
This ESMP covers E&R activities in the first 50 selected schools across the 10 regions of Ghana.
Selection of beneficiary schools has been based on need for additional classroom space at the
senior high school level, triggered by overarching population of junior high school graduates
within the selected localities. Some of the beneficiary schools will benefit from one category of
works or the other, while other schools will benefit from both categories. These activities trigger
the application of World Bank environmental and social assessment and safeguard tools in order
to preserve the natural and human environment within the project localities (OP 4.01
Environmental Assessment, and OP 4.12 Involuntary Resettlement).
Between November 21 and 28, 2014, the MOE team of environmental consultants screened all
the sites for the 50 existing schools earmarked for expansion and rehabilitation using checklists
provided in the approved ESMF and RPF for their suitability to the project and compliance with
World Bank guidelines. The site screening criteria for the 50 sites for expansion and rehabilitation
under SEIP are designed to minimize impact on environment and natural resources due to
expansion and rehabilitation works.
This ESMP has been prepared to guide the implementation of the expansion and rehabilitation
works for the selected 50 existing schools. It provides a project background, baseline
environmental and social conditions at the subproject locations, and defines the regulatory
framework within which the project is to be implemented. The methodology for identifying and
assessing potential environmental and social impacts of the project has been outlined, and an
impact matrix employed in assessing and quantifying the impacts that could arise across the
project implementation phases. Table ES 1 presents the potential impacts, with their proposed
mitigation measures.
GSEIP/ESMP
Page iii
50 SCHOOLS FOR EXPANSION AND REHABILITATION
Table ES.1
ENVIRONMENTAL AND SOCIAL MANAGEMENT PLAN
Rapid Impact Matrix (Scale: +ve impact=+5; -ve impact= -5)
ENVIRONMENTAL IMPACT
IMPACT
SCALE
Removal, handling and disposal of
asbestos (Risk of asbestos pollution)
MITIGATION MEASURES
Pre-Construction Phase
-3
An asbestos removal specialist will be engaged to
safely remove and dispose of asbestos materials.
Loss of Vegetative cover
-1
150% of felled trees will be replanted and as part of
Contractor’s deliverables
Dust generation
-1
Sections of site to be excavated will be doused with
water prior to commencement of work
Exposure of soil surface to erosion
-1
Clearing of vegetation will be staggered, to be cleared
only when construction is to begin
Construction Phase
-1
Dust generation from digging and excavation will
attenuate naturally.
Air quality issues
Noise
Construction equipment will be regularly serviced,
construction activity will be restricted to daylight
hours.
Delivery of construction materials and equipment will
be timed to coincide with off-peak traffic hours
Traffic impacts
-2
Occupational Health and Safety
-2
Personal Protection Equipment will be provided and
their use strictly enforced
Public safety and Health
-3
Solid waste generation
-1
Liquid waste generation
-3
Employment and Income generation
+3
Project site will be cordoned off. Excavations and pits
will be marked with appropriate signage. HIV/AIDS
and STDs awareness sessions will be organized for
construction workers. Free condoms will be supplied.
Excess earth material will be used in landscaping,
reusable waste materials will be sorted on-site for
reuse, organic wastes will be disposed off through
municipal waste disposal system.
Effluent from equipment washout will be disposed on
dry land away from water courses, mobile toilets will
be provided for construction workers’ ablution
Positive impact (enhancement) that requires no
mitigation.
Occupation and Maintenance Phase
Demographic changes and increased
demand on transport infrastructure
-2
District Assembly will take measures to enhance local
transport infrastructure, if needed
Solid waste generation
-1
Solid waste will be disposed off through municipal
waste system
Liquid waste generation
-2
Cesspits will be constructed to contain liquid wastes
for future de-sludging
Security and safety
-2
Security personnel will be engaged by District
Assembly to protect school property
Run-off management
-2
Rain water harvesting devices have been incorporated
into design to trap rain water and reduce run-off
Groundwater depletion
-2
Abstraction rates will be monitored to stay within
sustainable limits.
*Impacts are objectively assessed and quantified based on magnitude, extent, duration and reversibility.
GSEIP/ESMP
Page iv
50 SCHOOLS FOR EXPANSION AND REHABILITATION
ENVIRONMENTAL AND SOCIAL MANAGEMENT PLAN
A monitoring plan (Table ES 2) presents a summary of project impacts to be monitored
throughout the project implementation, and an Environmental Management and Mitigation Plan,
as presented in Table ES 3, outlines the steps to be taken to ensure the sound and sustainable
implementation. The ESMP assigns responsibilities for the various actions and activities, and
provides a cost estimate for its implementation.
Table ES 2
Monitoring Plan
Parameter
Frequency
Responsibility
Remarks
Pre-Construction Phase
Removal, handling and
One-off
Project Contractor/Environmental
This should be
disposal of asbestos (Risk of
activity
and Social Safeguards Coordinator
completed before
asbestos pollution
works begin
Construction Phase
Air quality (Dust and Exhaust
Weekly
Project Contractor
Weekly
Project Contractor
Daily
Project Contractor
Monthly
Project Contractor
emissions)
Noise generation
Traffic impacts
Occupational health and Safety
Public Safety
Daily
Project Contractor/ Project
Implementation Team
Solid waste generation and
Weekly
management
Implementation Team
Liquid waste generation and
Daily
management
Employment
Project Contractor/ Project
Project Contractor/ Project
Implementation Team
and
Income
Monthly
Project Implementation Team
generation
Occupancy and Maintenance Phase
GSEIP/ESMP
Page v
50 SCHOOLS FOR EXPANSION AND REHABILITATION
Demographic changes and
ENVIRONMENTAL AND SOCIAL MANAGEMENT PLAN
Yearly
increased demand on
transportation infrastructure
Solid waste generation and
Monthly
management
Liquid waste generation and
Quarterly
School Management Team
Quarterly
School Management Team
management
Groundwater depletion
It is noteworthy that all the sites for construction works are on existing school lands, and nobody’s
lands, crops or properties are affected in any manner.
The ESMP appoints the contractor to fell affected trees, chop them into sizeable pieces and hand
them over to the District Assembly for onward distribution to community members to use as fuel
wood. If the school has boarding facilities, then the wood could preferably be used in cooking the
students’ meals. The contractor is further, obliged to plant one-and-a half times the number of
trees felled, using native species in the locality, to replace the felled trees.
GSEIP/ESMP
Page vi
50 SCHOOLS FOR EXPANSION AND REHABILITATION
Table ES 3
ENVIRONMENTAL AND SOCIAL MANAGEMENT PLAN
Environmental and Social Impact Management and Mitigation Table
POTENTIAL
PROJECT ACTIVITY
ENVIRONMENTAL
LOCATION
IMPACTS/ACTIVITY
Some rehabilitation
project sites
Specific Asbestos
removal methods
installed
Project contractor
Vegetation and tree
clearing
All new construction
project sites
Selective and staggered
vegetation will be done
only when construction
is ready to begin.
Project Contractor
Air quality
CONSTRUCTION
RESPONSIBLE PARTY
Removal of asbestos
roofing material
PRE-CONSTRUCTION
PHASE.
PROPOSED
MITIGATION MEASURE
(S)
Noise
PHASE
Project site and
vicinity
Project site and
vicinity
Construction areas will
be doused with water to
minimize dust emissions.
Dust nets shall be hung
on buildings undergoing
rehabilitation
Regular maintenance of
machinery and
equipment.
NET EFFECTS
Elimination of risk
of asbestos
pollution
Avoidance of
exposure of land
surface to erosion
Project Contractor
Project Contractor
GSEIP/ESMP
Restriction of delivery of
materiel to site to offpeak traffic hours. Use of
Part of
Contractors’
costs
No cost
Controlled dust
generation;
Part of
Contractors’
costs
Reduced noise
impacts
Part of
Contractors’
costs
Restriction of
construction activity to
daylight hours
Traffic impacts
ESTIMATED
BUDGET
(USD)
PMT/Project
Contractor
Reduced traffic
impacts
Part of
Contractors’
costs
Page vii
50 SCHOOLS FOR EXPANSION AND REHABILITATION
ENVIRONMENTAL AND SOCIAL MANAGEMENT PLAN
Roads serving
immediate project
area
Occupational Health
and Safety issues
Project site
Public safety and
health
Project site and
vicinity
Solid waste
management
Liquid waste
management
GSEIP/ESMP
Project site
Project site
traffic wardens to
coordinate traffic flow
Proper site sanitation
and housekeeping.
Provision and enforced
use of PPE. Strict
adherence to safety
precautions as per
Factories, Offices and
Shops Act, 1970 (Act
328)
Cordoning off of pits and
excavations with
physical barriers and
appropriate signage.
HIV/AIDS and STDs
awareness programs for
hired labour. Supply of
condoms to labourers
Excess earthen material
will be used in
landscaping. Waste skips
will be provided to
collect wastes for
appropriate disposal at
municipal disposal site.
Equipment washout will
be discharged away from
water courses; chemical
or pit toilets will be
PMT/Project
Contractor
PMT/Project
Contractor
Reduced incidence
of accidents and
injuries.
Reduced risk of
accidents and
injuries to students
and general public.
Reduced risk of
spread of HIV/AIDS
and STDs
Part of
Contractors’
costs
Part of
Contractors’
costs
Project Contractor
Safe disposal of
generated solid
waste
Part of
Contractors’
costs
Project Contractor
Safe disposal of
generated liquid
waste
Part of
Contractors’
costs
Page viii
50 SCHOOLS FOR EXPANSION AND REHABILITATION
Employment and
Income
Increased demand on
transport
infrastructure
OCCUPANCY AND
MAINTENANCE
PHASE
Solid waste generation
provided for
construction workers.
Project Management
Team/District
Assembly
Project site
Hired hands will earn
some regular income to
support themselves and
their families.
Project site and
environs
DA will ensure that
transport facilities and
infrastructure are
improved.
DA/Project
Environmental Team
Waste skips will be
provided for waste
collection, to be
evacuated by DA waste
management facilities
periodically.
Provision and
maintenance of suitable
toilet facilities on school
compound
School
authorities/DEMC
School site
Liquid waste
generation
School site
GSEIP/ESMP
ENVIRONMENTAL AND SOCIAL MANAGEMENT PLAN
SEIP/School
authorities
Income generation
Adequate transport
facilities and
infrastructure.
Proper sanitary
conditions on school
compound.
Proper sanitary
conditions on school
compound.
DA to bear
cost
DA to bear
cost
DA to bear
cost
Page ix
50 SCHOOLS FOR EXPANSION AND REHABILITATION
ENVIRONMENTAL AND SOCIAL MANAGEMENT PLAN
Consultations have been held with the heads of the beneficiary school in identifying and
evaluating the proposed subproject locations or structures to be rehabilitated in order to predict
the potential environmental and social impacts. Consultations will continue with these
institutions throughout the implementation period to ensure the success of the project. Table ES
4 below is a summary of concerns raised by school heads.
Tables ES 4 Summary of Issued raised by School Heads
No.
Comment/Concern/Question
Mitigation/Action to be Taken
1
We have some uncompleted projects
on the school compound, and will
prefer that the project funds are
utilized to complete such projects.
The World Bank funding will be utilized to
undertake any project from start to finish. It
will be used as supplement funding for any
existing project.
2
Why is the project fund not given to the There is the need for fund accountability, and
schools to implement as they deem fit? the schools cannot be given the funds to
implement as they choose. The FPMU has come
round to collate schools’ prioritized list of
projects, and has selected those the funds can
start and finish.
It is noteworthy that the MOE had started stakeholder engagements long before the Consultants
went to the field, so most issues of concern had already been raised and discussed. Annex B
attached is Minutes/Reports of Workshops with DCEs
Disclosure
All reasonable efforts must be made to disclose/display this ESMP to the public at strategic
points within the project’s area of influence so as to allow all stakeholders read and understand
how they stand to be affected by the project.
It should also be disclosed at the Environmental Protection Agency and the World Bank Info
Shop.
Public Consultation Plan
A key element of sustaining stakeholders’ support in any project execution is to consult and
communicate with the stakeholders effectively and to engage them as early as possible with the
project which has been done in the course of preparation of the intervention work and further
enhanced during the preparation of this ESMP. Like any other business function, stakeholder
engagement needs to be managed and driven by a well-defined strategy. A Stakeholder
GSEIP/ESMP
Page x
50 SCHOOLS FOR EXPANSION AND REHABILITATION
ENVIRONMENTAL AND SOCIAL MANAGEMENT PLAN
engagement plan has been designed to guide the Stakeholder Engagement and Communication
Process
Grievance Redress Mechanism
During the implementation of the intervention work, a redress mechanism which is in line with
the ESMF, RPF, and PIM has been developed as detailed in the stand alone RAP for the proposed
site to address situations of conflicts or disagreements about some of the project activities. Thus
the ARAP should be referred to for further details on this grievance redress mechanism.
Suffice it to say that it is a localized mechanism that takes account of the specific issues, cultural
context, local customs and project conditions and scale.
Summary and Recommendations
The study has indicated that the establishment of the proposed project will not severely impact
negatively on the existing environmental, social and health as well as safe conditions of the
people, locally, or nationally.
It is expected that multiplier effects such as employment opportunities, poverty reduction,
enhanced national reputation and cultural promotion, among others, will be enhanced. On the
other hand, there are also some negative impacts that were identified.
The ESMP has revealed the followings with appropriate recommendations:

The proposed intervention work is most desirable because of the obvious socio-economic
benefits. These far out-weigh the negative impacts that could arise in the course of
implementation.

Priority should be given to local workers in the recruitment of unskilled labour

There is the need to carry along the community during project implementation.

Mitigation measures and management plans have been suggested and developed for the
negative impacts.

Appropriate institutional framework has been drawn up to implement the mitigation
measures and environmental management plan while the proposed monitoring
programmes shall be set in motion as soon as possible.
GSEIP/ESMP
Page xi
50 SCHOOLS FOR EXPANSION AND REHABILITATION
ENVIRONMENTAL AND SOCIAL MANAGEMENT PLAN
TABLE OF CONTENT
1.0
PAGE
INTRODUCTION …………………………………………………………………………………………….. 1
1.1
Background ……………………………………………………………………………………………………….
2
1.2
Description of Project ……………………………………………………………………………………….
3
1.3
Objectives of the Environmental and Social Mitigation Plan……………………………….
9
1.4
Legal, Regulatory and Administrative Frameworks ……………………………………………
9
2.0
METHODOLOGY …………………………………………………………………………………………….
11
2.1
Approach …………………………………………………………………………………………………………
11
2.2
Impact Identification and Evaluation Methodology ……………………………………………
11
3.0
BASELINE ENVIRONMENTAL AND SOCIAL CONDITIONS ...……………………………
13
3.1
Biophysical Environment …………………………………………………………………………………
13
3.1.1
Sudan Savannah Zone …………………………………………………………………………
13
3.1.2
Guinea Savannah Zone ………………………………………………………………………..
15
3.1.3
The Forest Savannah (Transition) Zone .………………………………………………
16
3.1.4
Semi-Deciduous Rain Forest Zone .………………………………………………………
16
3.1.5
High Rain Forest Zone ………………………………………………………………………….
17
3.1.6
Coastal Savannah Zone ………………………………………………………………………..
18
Socio-economic and Cultural Environment ………………………………………………………
19
3.2.1
Sudan Savannah Zone …………………………………………………………………………
19
3.2.2
Guinea Savannah Zone ………………………………………………………………………..
21
3.2.3
The Forest Savannah (Transition) Zone .………………………………………………
22
3.2.4
Semi-Deciduous Rain Forest Zone .………………………………………………………
22
3.2.5
High Rain Forest Zone ………………………………………………………………………….
23
3.2.6
Coastal Savannah Zone ………………………………………………………………………..
24
3.2
GSEIP/ESMP
Page xii
50 SCHOOLS FOR EXPANSION AND REHABILITATION
ENVIRONMENTAL AND SOCIAL MANAGEMENT PLAN
4.0
SIGNIFICANT ENVIRONMENTAL AND SOCIAL IMPACTS ...………………………………
27
4.1
Pre-Construction Phase Impacts …………………………………………………………………………
27
4.2
Construction Phase Impacts ……………………………………………………………………………….. 28
4.3
Occupancy and Maintenance Phase Impacts ………………………………………………………..
5.0
MITIGATION OF IDENTIFIED IMPACTS …………………………………………………………… 33
5.1
Pre-Construction Phase Mitigation ……………………………………………………………………..
33
5.2
Construction Phase Mitigation ……………………………………………………………………………
34
5.3
Occupancy and Maintenance Phase Mitigation ……………………………………………………. 35
6.0
MONITORING ………………………………………………………………………………………………… 36
6.1
Pre-Construction Phase Monitoring ……………………………………………………………………. 36
6.2
Construction Phase Monitoring ………………………………………………………………………….
36
6.3
Occupancy and Maintenance Monitoring ……………………………………………………………
38
7.0
ENVIRONMENTAL AND SOCIAL MANAGEMENT PLAN ……..…………………………….
41
7.1
Environmental Management Structure ………………………………………………………………
41
7.2
General Health and Safety Procedures ……………………………………………………………….
46
7.3
Pollution Control ………………………………………………………………………………………………
46
7.4
Waste Disposal ………………………………………………………………………………………………..
48
7.5
Trainings and Capacity Building ……………………………………………………………………….
48
7.6
Allocation of Resources for Environmental Management ……………………………………
48
8.0
CONSULTATIONS ……………………………….…………………………………………………………... 54
8.1
Objectives of Consultation ………………………………………………………………………………….. 54
8.2
Stakeholder Consultations ……………………………………………………………………..………….
54
8.3
Disclosures and Public Consultation Plan …………………………………………………………..
57
9.0
CONCLUSION AND RECOMMENDATIONS ……………………………………………………….
59
GSEIP/ESMP
32
Page xiii
50 SCHOOLS FOR EXPANSION AND REHABILITATION
ENVIRONMENTAL AND SOCIAL MANAGEMENT PLAN
Bibliography
Dickson, Kwamina B., Benneh, George, Essah, R. R., A New Geography of Ghana (revised edition;.
Harlow, Longman, 1988.
www.microsfere.org, (Microsfere Fund for People and Nature)
Adu, S. V., (1992) Soils of the Kumasi Region, Ashanti Region, Ghana: Memoir No.8 Ghana Soil
Research Institute.
Ghana Population and Housing Census, 2010 (PHC 2010).
Annexes/Attachments
Annex A
List of Stakeholders and Persons Consulted
Annex B
Minutes/Reports of Workshops with DCE
Annex C
Photographs of Proposed Construction Sites
List of Tables
Table 1.1
Descriptions of Subproject Locations
Table 1.2
Interventions
Table 4.1
Rapid Impact Matrix
Table 6.1
Monitoring Plan
Table 7.1
Institutional Arrangement/Responsibilities for Environmental Assessment and
Resettlement
Table 7.2
Organisations and Focal Persons for ESMP
Table 7.3
Environmental and Social Impact Management and Mitigation Table
Table 8.1
Summary of Issues raised at Consultation Meetings.
GSEIP/ESMP
Page xiv
50 SCHOOLS FOR EXPANSION AND REHABILITATION
1.0
ENVIRONMENTAL AND SOCIAL MANAGEMENT PLAN
INTRODUCTION
The Government of Ghana, through the Ministry of Education, proposes to construct 200 new
Senior High Schools under a Secondary Education Improvement Project (SEIP). The proposed
Secondary Education Improvement Project (SEIP) with funding from the World Bank would
support the implementation of the government’s Community Day Senior High School Project
(CSHSP) through two components: (i) Support to Increase Access with Equity and Quality in
Senior High Schools; and (ii) Management, Research and Monitoring and Evaluation.
The SEIP is expected to finance results which demonstrate increased access in targeted districts,
increased enrollment of poorest students and improved learning outcomes for selected low
performing senior high schools. The Government of Ghana plans to achieve these results through
the construction of new senior secondary schools in underserved areas, and rehabilitation and
expansion of existing low performing schools, among other interventions.
The project development objective of the SEIP under this aspect is to increase access to upper
secondary education in underserved school districts and improve quality in low-performing
senior high schools in Ghana. The project’s two components will: (i) provide support to increase
access with equity and quality in senior high schools using results-based financing; and (ii)
strengthen capacity of Ministry of Education, Ghana Education Service to monitor, coordinate,
evaluate and analyze policies for the first component. A matrix of indicators has been developed
to measure performance of Component 1 annually and to monitor the results achieved as
reflected in the results framework. Component 1 will support and monitor key activities to
accomplish these goals through construction of new schools, quality improvement and expansion
of existing schools where demand is high and in areas where schools have the potential to absorb
and retain students, and through scholarships to girls and low income students.
Activities this phase of the SEIP that trigger the use of the ESMF are: (i) the construction of new
senior secondary schools in 14 districts which currently have no senior secondary schools; (ii)
new construction in 9 selected districts based on district criteria for population demand, poverty
indicators, etc; and (iii) upgrading, expansion and rehabilitation of existing selected low
performing schools. This ESMP covers E&R activities in the first 50 selected schools across the 10
regions of Ghana under the third category. Selection of beneficiary schools has been based on
need for additional classroom space at the senior high school level, triggered by overarching
population of junior high school graduates within the selected localities. Some of the beneficiary
schools will benefit from one category of works or the other, while other schools will benefit from
both categories. These activities trigger the application of World Bank environmental and social
GSEIP/ESMP
Page 1
50 SCHOOLS FOR EXPANSION AND REHABILITATION
ENVIRONMENTAL AND SOCIAL MANAGEMENT PLAN
assessment and safeguard tools in order to preserve the natural and human environment within
the project localities (OP 4.01 Environmental Assessment, and OP 4.12 Involuntary
Resettlement).
1.1
Background
An Environmental and Social Management Framework (ESMF) and a Resettlement Policy
Framework (RPF) have been developed to provide environmental and social safeguards guidance
for the Secondary Education Improvement Project (SEIP) being prepared for IDA support of
US$155million (one hundred and fifty five million United States dollars). Both framework
documents having been approved and disclosed by both the Ghana Environmental Protection
Agency (EPA) and the World Bank, they will provide guidance to project implementation
operatives, districts, institutions, contractors, and other stakeholders including beneficiaries of
the senior secondary school rehabilitation and construction under the project. The ESMF and the
RPF are mainstreaming environment and social safeguards into the design and planning of the
SEIP. The choice of ESMF (instead of EIA) was made for the project because of the following
reasons:

Wide geographical spread – 23 selected districts where new construction will be
undertaken , in all the ten (10) administrative regions of Ghana;

Implementation duration – will be over five years from 2014 - 2019;

Cross sectoral involvement and scope – Ministries, Departments, Agencies and Schools at
national, regional and district levels;

Site specific activities – which may cover a range of different components e.g. classroom
block, sanitation, borehole, solar energy, staff residential facilities - the level of site
specific project being determined by the situation at each location.
The land ownership system in Ghana is governed by a complex operation of customary, statute,
and common law resulting in a rather uniquely complicated land ownership structure. There are
three principal land ownership patterns in Ghana namely:

Customary-owned;

State-owned;

Customary-owned but state-managed lands also known as vested lands.
Vested lands are lands owned by a Stool but managed by the state on behalf of the land-owning
Stool. Under such ownership, the legal rights to sell, lease, manage, and collect rent is taken away
from the customary landowners by the application of specific law to that land and vested in the
state. The landowners retain the equitable interest in the land (i.e., the right to enjoy the benefits
GSEIP/ESMP
Page 2
50 SCHOOLS FOR EXPANSION AND REHABILITATION
ENVIRONMENTAL AND SOCIAL MANAGEMENT PLAN
from the land). This category of land is managed in the same way as state lands. Unlike state lands,
however, the boundaries are not cadastral surveyed and they are usually larger in size, covering
wide areas. Vested lands are often the lands used for social infrastructure, such as the secondary
schools to be supported under the project.
1.2
Description of Project
Fifty existing senior high schools across the 10 regions of Ghana are to benefit from the
rehabilitation of existing structures and/or the construction of additional school structures,
depending on what was selected and prioritized by the FPMU for each beneficiary school. The
scope of activity is presented in Table 1.1 below, which shows the selected works on each
beneficiary school in the administrative district or municipality across the 10 regions.
All of the sub-projects will be constructed on existing school land, some of which are green fields
that have never had any civil construction activities on them. These have grasses, vegetation
brush and some ornamental trees on them (average 15 matured trees) that need to be cleared
and/or felled to make way for the construction activity.
Historically, asbestos roofing materials have been used in the coastal areas of Ghana in preference
over aluminium and zinc roofing material. This is because aluminium and zinc roofing materials
rust easily in the salt-laden sea breeze. However, asbestos is a carcinogenic material, the use of
which has been restricted in many jurisdictions, including Ghana. For instance, the main water
utility company in Ghana has long replaced asbestos pipes in water transmission and distribution
pipelines across the country. The two subprojects in Accra Metropolis, Osu Presbyterian High
School and Holy Trinity Cathedral Senior High School are located in close proximity to the sea,
and have therefore used asbestos roofing material in their construction. Their removal will be
guided by specific safety methods outlined under Section 5.1.1 below.
Table 1.2 below lists the special interventions required for the implementation of the subprojects.
GSEIP/ESMP
Page 3
50 SCHOOLS FOR EXPANSION AND REHABILITATION
Table 1.1
S/N
REGION
1
ASHANTI
REGION
Descriptions of Subproject Locations and Scope of Works
DISTRICT
SEKYEDOMASE SENIOR HIGH SCHOOL
ESAASE BONTEFUFUO SEC. TECHNICAL
SCHOOL
OFFINSO MUNICIPAL
ST. JEROME SENIOR HIGH SCHOOL
ADANSI NORTH DISTRICT
FOMENA T.I AHMADIYYA SENIOR HIGH
SCHOOL
BOSOME SENIOR HIGH TECHNICAL
SCHOOL-ASIWA
NKENKAASU SECONDARY HIGH SCHOOL
OFFINSO NORTH
ADANSI NORTH
AMANSIE CENTRAL
BRONG
AHAFO
GSEIP/ESMP
SCHOOL
EJURA SEKYEDOMASE
AMANSIE WEST
BOSOME FREHO
2
ENVIRONMENTAL AND SOCIAL MANAGEMENT PLAN
PRU
BODWESANGO SENIOR HIGH SCHOOL
JACOBU SECONDARY/TECHNICAL
SCHOOL
PRANG SENIOR HIGH SCHOOL
PRU
YEJI SECONDARY/TECHNICAL SCHOOL
SCOPE OF WORKS








REHABILITATION
NEW CONSTRUCTION
2-Storey Classroom Block
Old Library block
Technical School Block
3-Unit Classroom Block
Agric Block
Assembly Hall
Library
Home Economic
2-Store Classroom
2NO. 3-Unit Classroom Block
3-Unit Classroom Block
 5-Unit Classroom
 4-Unit Classroom block
 3-Unit Classroom block
N/A
N/A
 4-Unit Classroom BlockMain Block
 4-Unit Classroom BlockNyako Block
 Water distribution from
existing borehole
 Staff common room
3-Unit Classroom Block
2No. 3-Unit Classroom
2No. 3-Unit Classroom Block
3-Unit Classroom Block
2No. 3-Unit Classroom Block
2No. 3-Unit Classroom Block
N/A
2No.3-Unit Classroom block
Page 4
50 SCHOOLS FOR EXPANSION AND REHABILITATION
3
CENTRAL
REGION
4
EASTERN
REGION
5
GREATER
ACCRA
6
NORTHERN
REGION
GSEIP/ESMP
ENVIRONMENTAL AND SOCIAL MANAGEMENT PLAN
BANDA
BANDAMAN SENIOR HIGH TECHNICAL
SCHOOL
JAMAN NORTH
TAIN
DORMAA WEST
TAIN
TWIFO HEMANG
UPPER DENKYIRA
GOKA SECONDARY/TECHNICAL SCHOOL
BADU SECONDARY/TECHNICAL SCHOOL
NKRANKWANTA SEC/TECH
MENJI AGRICULTURAL SENIOR HIGH
SCHOOL
OBRACHIRE SHS
SENYA SHS
ODOBEN SHS
NYANKUMASI SHS
ASSIN NORTH SENIOR HIGH TECH.
SCHOOL
JUKWA SHS
DIASO SHS
ASSIN SOUTH
KWAHU NORTH
ASSIN NSUTA AGRIC SHS
ST. FIDELIS SENIOR HIGH SCHOOL
ACCRA METRO
HOLY TRINITY CATH. SENIOR HIGH
SCHOOL
ACCRA METRO
PRESBYTERIAN SENIOR HIGH SCHOOLOSU
TUNA SENIOR HIGH SECONDARY TECH.
SCHOOL
AWUTU/EFUTU/SENYA
AWUTU/EFUTU/SENYA
ASIKUMA/ODOBEN/BRAKWA
ASSIN SOUTH
ASSIN NORTH
SAWLA-TUNA-KALBA
DISTRICT
 Administration/Library
 5-Unit Classroom Block
N/A
N/A
 6-Unit Classroom Block
N/A
2No. 3-Unit Classroom Block
2No. 3-Unit Classroom Block
2No. 3-Unit Classroom Block
2No. 3-Unit Classroom Block
 2-Unit Classroom Block
N/A
N/A
N/A
N/A
3-Unit Classroom Block
2No. 3-Unit Classroom Block
2No. 3-Unit Classroom Block
2No. 3-Unit Classroom Block
6-Unit Classroom Block
N/A
 2-Unit Science block
 4-Unit business Block
 1-Unit Computer /1-Unit
Agric Block
 1-Unit Home Economics
Block
N/A
 2-Unit Home Economic
block
 4-Unit Art block
 4-Unit business/Agric block
 4-Unit classroom block
 2-Unit home economics
block (with Library)
N/A
2No. 3-Unit Classroom Block
N/A
 2-Unit Classroom block
6-Unit Toilet Block
6-Unit Classroom Block
2No. 3-Unit Classroom Block
2No. 6 Seater toilet facility
6-Unit Classroom block
N/A
Page 5
50 SCHOOLS FOR EXPANSION AND REHABILITATION
7
UPPER
EAST
SABOBA
E/P SENIOR HIGH SCHOOL, SABOBA
EAST GONJA DISTRICT
T.I AHMADIYYA SENIOR HIGH SCHOOL
CENTRAL GONJA DISTRICT
BUIPE SECONDARY TECHNICAL
KASSENA NANKANA EAST
AWE SENIOR SECONDARY/TECHNICAL
SCHOOL
BONGO
BONGO SENIOR HIGH SCHOOL
BONGO
GOWRIE SECONDARY/TECHNICAL
SCHOOL
KASSENA NANKANA EAST
OUR LADY OF LOURDES
SECONDARY/TECH
ZORKOR SENIOR HIGH SCHOOL
BONGO
GSEIP/ESMP
ENVIRONMENTAL AND SOCIAL MANAGEMENT PLAN
 3-Unit form 3 Classroom
block
 6-Unit Classroom block
 Computer lab
 Library block
 3-Unit Classroom block
 Science block
 Mechanised Boreholes
 2-Unit Classroom block (a)
 2-Unit Classroom block (b)
 3-Unit Classroom block
 4-Unit Classroom block
(general art)
 4-Unit Classroom block
(science)
 2No. 3-Unit Classroom
Block
 1-Unit Classroom block
with office
 2-Unit Classroom block
 3-Unit Classroom block
with
 2-Unit Classroom block
 6-Unit Classroom block
 Library block
 General Office
 3-Unit Classroom block
 Science block
N/A
2No.3-Unit Classroom block
N/A
2No.3-Unit Classroom block
N/A
N/A
N/A
N/A
N/A
N/A
Page 6
50 SCHOOLS FOR EXPANSION AND REHABILITATION
8
9
10
UPPER
WEST
VOLTA
REGION
WESTERN
REGION
GSEIP/ESMP
ENVIRONMENTAL AND SOCIAL MANAGEMENT PLAN
DAFFIAMA/BUSSIE/ISSA
DAFFIAMA SENIOR HIGH SCHOOL
NADOWLI-KALEO DISTRICT
KALEO SECONDARY/TECHNICAL
JIRAPA DISTRICT
ULLO SENIOR HIGH SCHOOL
WA EAST DISTRICT
KETU
NKWANTA SOUTH
ADAKLU ANYIGBE
Agortime Ziope
NORTH TONGU (NEW)
KETU
PRESTEA HUNI VALLEY
FUNSI SENIOR HIGH SCHOOL
KLIKOR SECONDARY/TECH SCHOOL
NTRUBOMAN SENIOR SEC/TECH.
ADAKLU SENIOR HIGH SCHOOL
AGOTIME SENIOR HIGH SCHOOL
DORFOR SENIOR HIGH SCHOOL
SOME SENIOR HIGH SCHOOL
ST. AUGUSTINE'S SENIOR SECONDARY
SEC. BOGOSO
 1- Unit classroom block (a)
 1- Unit classroom block (b)
 2- Unit home economics
block
 3- Unit classroom block (a)
 4- Unit classroom block (b)
 2-Unit classroom block
 3-Unit Home economics
classroom block
 ICT laboratory
 Science blocks
 Workshop
 3- Unit classroom block
(business)
 3- Unit classroom block
(general art)
 6- Unit classroom block
N/A
 Science Laboratory
N/A
N/A
N/A
N/A
 3-Unit Science Laboratory
 6-Unit classroom block
(General Arts Block)
 3-Unit classroom block (
Business)
 4-Unit classroom block
(Vocational Block)

N/A
N/A
N/A
2No. 3-Unit classroom block
3-Unit classroom block
2No. 3-Unit classroom block
2No. 3-Unit classroom block
2No. 3-Unit classroom block
2No. 3-Unit classroom block
3-Unit classroom block
2No. 3-Unit classroom block
Page 7
50 SCHOOLS FOR EXPANSION AND REHABILITATION
BODI
SEFWI AKONTOMBRA
AOWIN
WASSA AMENFI EAST
GSEIP/ESMP
ENVIRONMENTAL AND SOCIAL MANAGEMENT PLAN
BODI SENIOR HIGH SCHOOL
AKONTOMBRA SENIOR HIGH SCHOOL
NANA BRENTU SENIOR HIGH
TECHNICAL SCHOOL
DABOASE SENIOR HIGH TECHNICAL
SCHOOL



2No. 3-Unit classroom block
2No. 3-Unit classroom block
2No. 3-Unit classroom block

2No. 3-Unit classroom block
Page 8
50 SCHOOLS FOR EXPANSION AND REHABILITATION
Table 1.2
Special Interventions
S/No
1.
ENVIRONMENTAL AND SOCIAL MANAGEMENT PLAN
Intervention
Removal of asbestos roofing sheets
Location
Osu Presby SHS, Holy Trinity
SHS (Accra Metropolitan)
2.
Felling of trees and clearing of vegetation to make way All other remaining sites
for construction activities
A qualified and competent building contractor will be selected through a competitive bidding
process, to undertake the construction of each sub-project.
1.3
Objectives of the Environmental and Social Mitigation Plan
The site screening assisted in categorizing the sub-projects under the SEIP into the appropriate
Environmental Category under the World Bank Operational Guidelines, i.e. whether under
Category A, B or C, depending on scope severity and complexity of identified impacts. All the subprojects are deemed to be Category C projects, likely to have minimal to insignificant
environmental impacts.
The objective of the Environmental and Social Mitigation Plan is to:
1. Identify, evaluate and quantify all the potential environmental and social impacts that
could arise from the implementation of the project,
2. Design and propose appropriate mitigation measures and activities that will minimize or
offset the identified impacts,
3. Assign responsibilities for the implementation of the mitigation measures, time and actual
place of implementation, and projected cost of implementing the mitigation measures.
4. Define a monitoring mechanism and identify monitoring parameters to ensure that all
mitigation measures are completely and effectively implemented; and
5. Identify training requirements at various levels and provide a plan for implementation.
1.4
Legal, Regulatory and Administrative Frameworks
A thorough review of the legal, regulatory and administrative frameworks governing the ESMF
was done in that document, and is summarized here in this Environmental and Social Screening
Report.
The environmental policies and legal framework and procedures considered in preparation of the
SEIP ESMF include the following:

Ghana’s National Environmental Policy;
GSEIP/ESMP
Page 9
50 SCHOOLS FOR EXPANSION AND REHABILITATION
ENVIRONMENTAL AND SOCIAL MANAGEMENT PLAN

The Environmental Protection Agency Act of 1994 (Act 490);

The Environmental Assessment Regulations (LI 1652), and EIA procedures;

Laws and Regulations pertaining to the protection of the environment and health;

National Sanitation Policy;

Town and Country Planning Ordinance 1951 (Cap84);

Factories, Offices and Shops Act, 1970 (Act 328)and

The Local Government Act 462 of 1993.
Additionally, the relevant World Bank’s Safeguard policies which include guidance on
Environmental Assessment requirements - Environmental Assessment (OP4.01), has been
brought into effect. Because no new land acquisition and displacement is involved in this project,
the World Bank safeguard policy on Involuntary Resettlement (OP/BP 4.12), is not triggered.
2.0
METHODOLOGY
GSEIP/ESMP
Page 10
50 SCHOOLS FOR EXPANSION AND REHABILITATION
ENVIRONMENTAL AND SOCIAL MANAGEMENT PLAN
Under this section we outline the approach and methodology employed in identifying and
evaluating the potential environmental and social impacts that could arise from the
implementation of the project.
2.1
Approach
In identifying and quantifying the potential environmental and social impacts that could arise
from the implementation of the SEIP project, the following steps were employed:
i.
Review of project brief and documents - the ESMF and RPF as approved by the Ghana
EPA and the World Bank were reviewed to get a good understanding of the project
scope and details.
ii.
Technical site visits were undertaken to all proposed sub-project site to appraise the
sites and their immediate vicinities, with regard to the natural environment, presence
of sensitive environmental resources such as water bodies, natural habitats of plant
and animal species, lay of land (with reference to steep slopes, liability to floods, etc.,)
presence of community cultural properties such as sacred groves, shrines, cemeteries,
etc., as well as for the current occupation and/or use of the land parcels.
iii.
Further consultations with heads of beneficiary schools. Heads of the beneficiary
schools pointed out which existing structures are to be rehabilitated and the actual
sites where the new structures to be constructed are to be located. Earlier on,
consultations had been held between the MoE and the District Chief Executives of the
beneficiary communities, as well as the respective District Directors of Education. ,
2.2
Impact Identification and Evaluation Methodology
Identified potential environmental and social impacts have been quantified and categorized
under the various project phases, as Pre-construction phase impacts, Construction Phase impacts
and Operation and Maintenance Phase impacts.
The identified impacts are presented graphically in a Rapid Impact Matrix. Impacts/issues have
been evaluated using a numerary scale ranging from -5 through 0 (zero) to +5, (i.e. negative
through nil effect to positive or beneficial), and are as explained below:
-5
-
Extremely adverse
+1
-
Minimally beneficial
-4
-
Very adverse
+2
-
Very beneficial
-3
-
Adverse
+3
-
Beneficial
-2
-
Slightly adverse
+4
-
Slightly beneficial
GSEIP/ESMP
Page 11
50 SCHOOLS FOR EXPANSION AND REHABILITATION
-1
-
Minimally adverse
0
-
zero or No impact
ENVIRONMENTAL AND SOCIAL MANAGEMENT PLAN
+5
-
Extremely beneficial
Impacts are objectively assessed and quantified based on factors such as:

their magnitude,

scope or extent,

sensitivity and value of the affected resource or receptor,

duration, and

reversibility.
3.0
BASELINE ENVIRONMENTAL AND SOCIAL CONDITIONS
This section presents the
GSEIP/ESMP
Page 12
50 SCHOOLS FOR EXPANSION AND REHABILITATION
ENVIRONMENTAL AND SOCIAL MANAGEMENT PLAN
A clear understanding of the project environment is necessary In order to identify and evaluate
the potential impacts of the proposed project. The biophysical and socio-cultural background of
the subproject sites across Ghana has been collected from the official Ghana government website
for local government authorities, www.ghanadistricts.gov, as well as from a published source.
(see Bibliography), consultations with local government officials, local people and also from first
hand, personal observation during site visits. This section presents a brief description of the biophysical and socio-economic environment of the project area, focusing on the potential
environmental and social impacts of the proposed project as a result of interactions between the
project activities and the subproject location and surrounding natural environment. A vegetation
map of Ghana showing the indicative locations of the subprojects have been attached above as
Figure 3.1 Overlain Vegetation Zones on Regional Map of Ghana Showing Subproject Sites.
3.1
Biophysical Environment
The locations for the 50 subprojects are spread across the 10 administrative regions of Ghana
(reference Table 1.1 above), and can be categorized into 6 different vegetation zones; namely
Sudan Savannah (1), Guinea Savannah (2), Forest Savannah (3), Semi-deciduous Rain Forest (4),
the High Rain Forest (5) and the Coastal Savannah (6). The categorization is largely based on
climatic factors, notably rainfall and temperature. Figure 3.1 below shows the spatial distribution
of the subprojects across the various vegetation zones of Ghana. The zones are marked by the
figures in brackets after each zone.
A brief description of each vegetation zone is presented below, referencing the subprojects
located within each zone.
3.1.1
Sudan Savannah (1)
The Sudan Savannah type of vegetation has vast grasslands separating deciduous trees and
comprises open fire-swept grasslands and clusters of deciduous trees. Some of the most densely
vegetated parts can be found along river basins and forest reserves. However, anthropogenic
activities over the years have affected the original (virgin) vegetation cover. Common trees found
are African locust bean plant (Parkia biglobosa), locally known as dawadawa, baobab (Adansonia
digitata) sheanut (Vitellaria paradoxa) and mangos (Mangifera indica).
Figure 3.1 Regional Map of Ghana overlain with Vegetation Zones Showing 50 Subproject Locations.
GSEIP/ESMP
Page 13
50 SCHOOLS FOR EXPANSION AND REHABILITATION
GSEIP/ESMP
ENVIRONMENTAL AND SOCIAL MANAGEMENT PLAN
Page 14
50 SCHOOLS FOR EXPANSION AND REHABILITATION
ENVIRONMENTAL AND SOCIAL MANAGEMENT PLAN
The zone straddles most of the Upper East Region, a small segment of the northeastern part of
the Northern Region and almost a third of the Upper West Region. The climate conditions are
characterized by the dry and wet seasons, which are influenced mainly by two (2) air masses –
the North-East Trade winds and the South-Westerlies (Tropical Maritime). The Harmattan air
mass (North-East Trade Winds) is usually dry and dusty as it originates from the Sahara Desert
between early December and early February. During such periods, rainfall is virtually absent due
to low relative humidity, which rarely exceeds 20 per cent and low vapour pressure less than
10millibars. Day temperatures are high recording 42° Celsius (especially February and March)
and night temperatures are as low as 18° Celsius. It experiences the tropical maritime air mass
between May and October. This brings rainfall averaging 950mm per annum.
Five subprojects are located in this eco-zone, namely AWE SENIOR SECONDARY/TECHNICAL
SCHOOL, BONGO SENIOR HIGH SCHOOL, GOWRIE SECONDARY/TECHNICAL SCHOOL, OUR LADY
OF LOURDES SECONDARY/TECHNICAL SCHOOL and ZORKOR SENIOR HIGH SCHOOL.
3.1.2
Guinea Savannah (2)
The Guinea Savannah region, the driest area of Ghana, covers approximately two thirds of the
country’s land surface. It encompasses about two-thirds of the Upper West Region, almost all of
the Northern Region, the central northern part of the Brong Ahafo Region, the northern parts of
the Ashanti, Eastern and Volta Regions. The vegetation zone has two distinct seasons – a wet
season that runs from May to October and a long dry season that stretches from October to April;
with hardly any rains. Mean annual rainfall is 950mm while maximum temperature is 45°C in
March and April with a minimum of 12°C in December. The Guinea savannah woodland consists
of short deciduous trees widely spaced and a ground flora, which gets burnt by annual fires or
scorched by the sun during the long dry season. The most common economic trees are the shea
nut, dawadawa, baobab and acacia. Most of the productive agriculture in Ghana occurs in this
zone, especially along the corridors of the Volta Lake, where irrigation and fertile soils facilitate
all year round cultivation. Agriculture is the economic mainstay in this zone, although fishing,
trading and commerce as well as some industrialization (agro-processing) occurs here. The zone
encompasses “the Mole National Park, a 4,840 km2 protected area of undulating terrain with steep
scarps, pristine Guinea savanna vegetation with gallery forests along the rivers and streams. Over
90 mammal species including elephants, buffalo, roan, kob, hartebeest, 4 primate species and
over 300 bird species are found in the park” (Source: www.microsfere.org). The Digya National
Park, occupying about 3,478 km2 of undulating terrain with sandstone inselbergs is situated on
the western shores of the Volta Lake. Guinea savanna woodland predominates with gallery forest
along the major lines.
GSEIP/ESMP
Page 15
50 SCHOOLS FOR EXPANSION AND REHABILITATION













3.1.3
ENVIRONMENTAL AND SOCIAL MANAGEMENT PLAN
Thirteen subprojects are located in this zone, namely;
DAFFIAMA SENIOR HIGH SCHOOL,
KALEO SECONDARY/TECHNICAL. ULLO SENIOR HIGH SCHOOL.
FUNSI SENIOR HIGH SCHOOL
TUNA SENIOR HIGH SECONDARY TECH. SCHOOL
E/P SENIOR HIGH SCHOOL, SABOBA
T.I AHMADIYYA SENIOR HIGH SCHOOL
BUIPE SECONDARY TECHNICAL
PRANG SENIOR HIGH SCHOOL
YEJI SECONDARY/TECHNICAL SCHOOL
BANDAMAN SENIOR HIGH TECHNICAL SCHOOL
NTRUBOMAN SENIOR SEC/TECHNICAL, and
ST. FIDELIS SENIOR HIGH SCHOOL.
The Forest Savannah (Transition) Zone (3)
The Forest Savannah transition zone is a narrow band with constantly shifting boundaries, as
epitomized by the constant battle between man and nature. While “sahelization” seeks to press
southward as a result of changing climatic and anthropogenic factors, human efforts are also
being made to reverse this trend through afforestation. It lies between the Savannah zone and
the Semi-deciduous Rain Forest Zone, and has seen considerably reduction with the insidious
southward creeping of the Guinea Savannah and the gradual deforestation in the Semi-Deciduous
Rain Forest to the south. It has however, marked a clear boundary between the generally dry
northern part of Ghana and the forested southern sections.
It cuts across four administrative regions in a characteristic V-shaped manner; The Brong Ahafo,
Ashanti, Eastern and the Volta Regions. The Bui National Park, an area of about 1,821km²,
bisected by the Black Volta, lies in this zone. It has spectacular gallery forests along rivers courses
and noted for its resident hippopotamus population in the Black Volta.
Four subprojects are located within this zone.




3.1.4
GOKA SECONDARY/TECHNICAL SCHOOL
BADU SECONDARY/TECHNICAL SCHOOL
MENJI AGRICULTURAL SENIOR HIGH SCHOOL, and
SEKYEDOMASE SENIOR HIGH SCHOOL
Semi-deciduous Rain Forest (4)
The semi-deciduous rain forest zone of Ghana contains some of the most productive soils of the
country. The zone covers some 48,000 square kilometers, and receives adequate annual rainfall
levels to support large scale plantation crops such as cocoa (Theobroma cacao), oil palm (Elaias
guineensis) and citrus species, as well as annual crops such as maize (Zea mays) Cassava (Manihot
GSEIP/ESMP
Page 16
50 SCHOOLS FOR EXPANSION AND REHABILITATION
ENVIRONMENTAL AND SOCIAL MANAGEMENT PLAN
utilissima)and plantain (Musa sapientum), (Adu, 1992). It cuts across parts of the Brong Ahafo,
Ashanti, Western, Eastern and Central Regions.
The vegetation zone is characterized by a double maxima rainy season, which reaches its peak
period in May – July, and the minor season occurs in the period of September – November. Annual
rainfall usually starts in April with the peak month in June and ends in November. The dry season
starts in November – December and ends in March. The annual rainfall is between 67m and
1130mm; temperatures are warm throughout t the year with maximum monthly mean of 37.2ºC
and a minimum of 21.0ºC. Relative humidity is generally high ranging from the highest of 98% in
June to 31% in January. The annual rainfall is between 67-1130 millimetres and maximum
temperature is 37.2 degrees Celsius. Relative humidity is generally high; ranging from 98% in
June to 31% in January. The Bia National Park and Bia Resource Reserve constitute a twin
conservation area covering a total area of 305.62km² in the moist semi-deciduous forest types. It
is the only Biosphere Reserve in Ghana. The Kyabobo National Park (359.8 km²) is also found in
the Dry semi-deciduous forest zone, and has both forest and savanna species of plants and
animals.
Fourteen subprojects are located in this vegetation zone, namely ,

NKENKAASU SECONDARY HIGH SCHOOL













ST. JEROME SENIOR HIGH SCHOOL
NKRANKWANTA SEC/TECH
ESAASE BONTEFUFUO SEC. TECHNICAL SCHOOL
JACOBU SECONDARY/TECHNICAL SCHOOL
FOMENA T.I AHMADIYYA SENIOR HIGH SCHOOL
BODWESANGO SENIOR HIGH SCHOOL
BOSOME SENIOR HIGH TECHNICAL SCHOOL-ASIWA
DIASO SHS
ASSIN NORTH SENIOR HIGH TECH. SCHOOL
ASSIN NSUTA AGRIC SHS
DABOASE SENIOR HIGH TECHNICAL SCHOOL
NANA BRENTU SENIOR HIGH TECHNICAL SCHOOL
AKONTOMBRA SENIOR HIGH SCHOOL, and

BODI SENIOR HIGH SCHOOL
3.1.5
High Rain Forest (5)
The High Forest zone, in the southern zone of Ghana, consists of forests ranging from wet
evergreen to dry semi-deciduous. It is the region with the highest precipitation in the country,
where rainfall may even reach 2300 mm in the wettest parts (wet evergreen zone). The High
Forest Zone falls within the Biodiversity Hotspot of the Guinean forests of West Africa , one of the
36 most important biodiversity areas in the world (www.microsfere.org).
GSEIP/ESMP
Page 17
50 SCHOOLS FOR EXPANSION AND REHABILITATION
ENVIRONMENTAL AND SOCIAL MANAGEMENT PLAN
One of the subprojects is located in this zone.
3.1.6
Coastal Savannah
The zone is characterized by two rainy seasons. The average annual rainfall is about 730mm,
which falls primarily during the two rainy seasons; the first begins in May and ends in mid-July.
The second season begins in mid-August and ends in October. Rainfall is usually in short but
intensive storms, and gives rise to local flooding where drainage channels are obstructed. There
is very little variation in temperature throughout the year. The mean monthly temperature
ranges from 24.7°c in August (the coolest) to 28°c in March (the hottest) with annual average of
26.8°c. As the area is close to the equator, the daylight hours are practically uniform during the
year. Relative humidity is generally high varying from 65% in the mid-afternoon to 95% at night.
There is evidence to suggest the vegetation of the zone has been altered in the more recent past
century by climatic and other factors. Much of the zone is believed to have been covered by dense
forest in the past, of which a few remnant trees survive. A climatic change combined with the
gradient of the plains and cultivation has imposed vegetation structures similar to those of the
southern shale, Sudan and Guinea Savannahs all of which lie north of the zone.
There are three broad vegetation zones in the coastal savannah zone, namely shrub land,
grassland and coastal lands. The shrub land occurs more commonly in the western outskirts and
in the central northern sections. It consists of dense clusters of small trees and shrubs, which
grow, to an average height of five metres. The grasses are a mixture of species found in the
undergrowth of forests. They are short, and rarely grow beyond one metre. Ground herbs are
found on the edge of the shrub. They include species, which normally flourish after fire. The
coastal zone comprises two vegetation types, wetland and dunes. The coastal wetland zone is
highly productive and an important habitat for marine and terrestrial-mainly bird life.
Mangroves, comprising two dominant species (Avicennia sp. and Rhizophora sp), are found in the
tidal zone of all estuaries sand lagoons. Salt tolerant grass species cover substantial low-lying
areas surrounding the lagoons. These grasslands have an important primary production role in
providing nutrients for prawns and juvenile fish in the lagoon systems. In recent times, wetlands
are however being encroached upon. Protection of the coastal wetland zone is very important to
the long-term sustainability of the fish industry, which is predominant in the Coatal Savannah.
The dune lands have been formed by a combination of wave action and wind. They are most
unstable but stretch back inland several kilometers in places. There are several shrub and
grassland species, which grow and play an important role in stabilizing dunes. Coconuts and
palms grow well in this zone, providing soil protection, and also as an economic crop.
GSEIP/ESMP
Page 18
50 SCHOOLS FOR EXPANSION AND REHABILITATION
ENVIRONMENTAL AND SOCIAL MANAGEMENT PLAN
In addition to the natural vegetation zones, a number of introduced trees and shrubs thrive in the
zone. Neems, mangoes, cassias, avocados, and palms are prominent. Introduced shrubs like
bougainvillea are also very prominent. These are, however, being damaged from residential
encroachment, bush fire, sand collection and illegal tree felling.
The extensive coastal area of Ghana hosts a variety of wetlands, including the Anlo-Keta lagoon
complex, Muni-Pomadze Lagoon, Sakumo Lagoon, Songor Lagoon. Apart from mangroves and salt
marsh grasses, which grow in the intertidal zone, sea grasses or attached algae also occur mainly
in rocky areas and wave cut platforms. These areas have increased as a result of erosion exposing
the underlying bedrock - especially to the southeastern sections. They have an important role in
the coastal ecosystem because of their high rate of primary production in the provision of food
and shelter for the survival of shrimps, prawns and many species of fin fishes. Ocean floor sea
gases are confined to a few sheltered areas of the coastline and the lagoons. The ocean floor
regime is too unstable to support large areas of sea grass.












3.2
Eleven subprojects are located here, namely
KLIKOR SECONDARY/TECH SCHOOL
SOME SENIOR HIGH SCHOOL
ADAKLU SENIOR HIGH SCHOOL
AGOTIME SENIOR HIGH SCHOOL
DORFOR SENIOR HIGH SCHOOL
PRESBYTERIAN SENIOR HIGH SCHOOL
HOLY TRINITY CATH. SENIOR HIGH SCHOOL
OBRACHIRE SHS
SENYA SHS
ODOBEN SHS and
NYANKUMASI SHS.
Socio-economic and Cultural Environment
This section presents an overview of the baseline socio-economic and cultural environment
within the beneficiary districts, which have been categorized along the vegetation zones
described under Section 3.1. Information presented here has been gleaned from the official
website for local government in Ghana, www. ghanadistricts.com.
3.2.1
Sudan Savannah
Population and Demography: The Sudan Savannah zone has a relatively low population density
with respect to its land mass. Communities tend to cluster around fertile land tracts and water
bodies, and are separated by long and large swathes of bare land. About 80% of the population
lives in rural communities scattered in dispersed settlements. Yearly southward migration during
GSEIP/ESMP
Page 19
50 SCHOOLS FOR EXPANSION AND REHABILITATION
ENVIRONMENTAL AND SOCIAL MANAGEMENT PLAN
the long dry season also accounts for the low population density, as some of the migrants tend to
stay longer in the south than the next farming season, especially if they find lucrative jobs.
Social Amenities: Apart from the regional capitals and a few urban centers that have access to
pipe-borne water, most of the smaller communities depend on boreholes and wells for drinking
water. There are a few hundreds of kilometers of tarred roads, while the rest remain un-tarred.
The tarred roads link the major towns and regional capitals, mainly. The rest of the roads are untarred, which makes movement of humans and cargo difficult within the zone, especially during
the rainy season. Health facilities are spread thin over the zone, with two regional hospitals at Wa
and Bolgatanga, the capitals for the Upper West and Upper East Regions respectively. There are
a number of clinics and Community Health Posts (CHPs) compounds distributed across the zone,
but usually poorly resourced or lack basic medicaments.
Education: As with most parts of Ghana, basic education is widely available across the zone. The
Government’s School Feeding Program at the basic level has gone to increase enrolment and
attendance. Secondary education is available to a lower extent (Annex 3 of the ESMF for SEIP
provides details). There is a polytechnic at Wa, and a few public teacher training colleges, at Tumu
and Gambaga. There is a university campus at Wa.
Economic activity: The major economic activity in the zone is agriculture. Crops grown include
corn, millet, peanuts, okra, shea butter, and rice. s, goats, chickens, pigs and guinea fowl are raised
for meat and eggs. Because the region's dry season is long, stretching from extending roughly
from October to May, many people leave the region to work in the southern part of Ghana for at
least part of the year. Brewing of pito, a mildly alcoholic beverage derived from millet, is also
common trade.
The two subproject locations within the zone are Binduri (Binduri District) and Zulugu (Pusiga
District), both to the north-eastern end of the zone. Both are newly created districts hived off from
the erstwhile Bawku District. Both are yet to attain their full complements of administrative
infrastructure. Extended farming is restricted to the areas along river basins and forest reserves.
Examples are the Sissili and Asibelika basins, and Kologo and Naaga forest reserves. Dams,
dugouts and impoundments are used to supplement agriculture during the dry season, but these
also depend on the amount of captured or retained water during the rainy season. Poverty levels
are therefore generally high.
3.2.2
Guinea Savannah
This zone encompasses a wide variety of populations and economic activities, as a result of its
varied biomes. While the northern part is dry and vast, the southern sections and areas along the
GSEIP/ESMP
Page 20
50 SCHOOLS FOR EXPANSION AND REHABILITATION
ENVIRONMENTAL AND SOCIAL MANAGEMENT PLAN
banks of the Volta Lake and the Black Volta to the west are considerably forested, have fertile
soils and have comparatively higher rainfall volumes. This promotes more profitable and varied
agriculture (farming and fishing) as well as agro-processing.
Population and Demography: The northern sections, especially the Northern Region, is subject
to long dry spells of drought, and short, heavy rains, often resulting in floods during the rainy
season. Southward migration during the dry season occurs here, but the return rates are higher
than in the Sudan Savannah. The more populated southern section of the zone is attributable to
more fertile soils, better rainfall regime and hence better agriculture. The Northern Region is
sparsely populated, although has vast stretches of land (35 persons per square kilometer).
Social Amenities: The zone has about 5 major development nodes, mainly Wa (Upper West
Regional capital), Tamale metropolis, Yendi Municipality, Bole (capital for Bole District) and
Atebubu (capital for Atebubu-Amantin District) to the south. In and around these habitations,
amenities and facilities such as electricity, pipe-borne water, road infrastructure and health
facilities are evenly spread out. An airstrip in Tamale is currently being upgraded into an
international airport to serve the northern section of Ghana as well as the northern Sahelian
neighbouring countries. Water transport along the Volta Lake is prominent, although fatalities
from boat accidents are frequent, due to submerged tree stumps that often break wooden boats
and canoes apart on impact.
Education: Basic education availability is quite high, reducing as one goes higher on the academic
ladder. There is a polytechnic, a teacher training school and nurses’ training college in Tamale.
The University of Development Studies is based in Tamale, with a campus in Wa. The Savannah
Agricultural Research Institute is located in Nyankpala, near Tamale.
Economic Activity: These are as varied as the biomes in the eco-zone are. Agriculture is
predominant, followed by fishing along the banks of the Volta Lake and its tributary rivers.
Common foodstuffs here are cereals (maize, millet, sorghum and rice) legumes, and yams. Animal
rearing is also very common, especially of sheep, goats and cattle.
Because of the relative urbanization, trade, industry and commerce as well as the services sector
are all quite developed. Agro-processing, particularly of shea and cashew is significantly on the
increase, providing some impetus for enhanced cultivation. Food markets are common, as food
merchants travel from the south to purchase fresh food in bulk quantities for sale in the southern
parts of the country.
3.2.3
Forest Savannah (Transition)
GSEIP/ESMP
Page 21
50 SCHOOLS FOR EXPANSION AND REHABILITATION
ENVIRONMENTAL AND SOCIAL MANAGEMENT PLAN
The socio-economic profile of this zone is not much different from that of the Guinea Savannah,
except that more trade in foodstuffs go on here, as the frontier between the generally dry and less
populated north, and the forested and densely populated south. Trade and commerce are next to
agriculture in the zone.
Population and Demography: As earlier indicated, the zone is home to brisk business in
foodstuffs and other merchandise across the zone. This is especially so across the central and
northwestern sections of the zone. Thus, the population in the zone comprises a fairly stable
majority that engages in food production, and a significant minority engaged in trading,
commerce and the services sector.
Social Amenities: In a southerly direction, development and urbanization in Ghana progressively
increases. Thus, the transition zone enjoys a lot more social amenities than the northern
neighbours. Road networks are generally better and motorable all year round, water and
electricity supply services are more accessible, and health facilities are within easy reach.
Education: Basic education facilities are available in every rural community, as access
progressively reduces towards the secondary and tertiary levels. However, students in the Forest
Savannah have options of secondary education in the Northern sector (Upper East, Upper West
and Northern Regions) where secondary education is free, and the more resourced and endowed
secondary schools in the south.
Economic Activity: Agriculture is the main economic activity, followed by trade and commerce,
and the services sector. The largely urbanized zone presents a number of business and
investment opportunities in transport, retailing and food processing. Poverty levels are generally
lower here than in the Guinea and Sudan Savannah eco-zones.
3.2.4
Semi Deciduous Rain Forest
This zone encompasses three regional capitals, namely Sunyani for Brong Ahafo Region, Kumasi
for Ashanti Region and Koforidua for the Eastern Region. The Ashanti Region is the most populous
region and the nerve centre for business and commerce in Ghana. Strategically located between
the north and the south, it is a transit point for most goods from the north to the south, and vice
versa.
Population and Demography: The second biggest eco-zone after the Guinea Savannah, the
Semi-deciduous rain forest is about the most populated eco-zone in Ghana. The most populous
region, the Ashanti Region lies across the Guinea Savannah, the Forest Savannah Transition zone
and the Semi-deciduous zone, likewise the Brong Ahafo and the Eastern Regions. While mainly
GSEIP/ESMP
Page 22
50 SCHOOLS FOR EXPANSION AND REHABILITATION
ENVIRONMENTAL AND SOCIAL MANAGEMENT PLAN
occupied by the indigenous Akan ethnic group, this zone is also home to people from almost all
the regions in the country, and beyond.
Social Amenities: The Transition Zone is about one of the most endowed zones in Ghana in terms
of availability of social amenities and infrastructure. Roads networks are among the best, and
interconnect all other regions and zones. Thus, accessibility is high. There are two local airports
in Kumasi and Sunyani, within the zone. Amenities like electricity and pipe-borne water are
largely available. Medical facilities are easily accessible, from primary through secondary to
tertiary or referral facilities. There are modern referral hospitals in Sunyani and Koforidua, while
the second largest teaching hospital, the Komfo Anokye Teaching Hospital is in Kumasi. These are
beside a number of district and regional hospitals, polyclinics and private health facilities.
Education: The zone remains the most endowed in terms of educational facilities, from basic
level to the tertiary level, and both public and private owned.
Employment: Employment opportunities abound in the Semi Deciduous Rain Forest zone,
ranging from agriculture (farming and fishing) through agro-processing, trading and commerce,
goods and services, transport business, timber and milling to petty trading. The presence of the
rain forest affords the availability of timber for construction.
3.2.5
High Rain Forest Zone
The High Rain Forest is located in the southern section of the Western Region. Heavily forested
with high rainfall regimes, the zone is noted for food production, timber and mining industries.
Roads are generally in poor nature due to the heavy rainfall which causes severe soil erosion.
Population and Demography: Populations are concentrated in the urban centres where
employment opportunities in the mining, timber and commercial sectors are common. Trade and
commerce, as well as the services industries also attract considerable numbers. Farming is mainly
in cocoa, oil palm, rubber and in foodstuffs. The rural – urban split in this zone is approximately
50 percent – 50 percent (2010 PHC). The few urban centres are therefore highly populated while
the remaining larger rural habitations are sparsely populated.
Social Amenities: The population spread in rural areas means that smaller towns and villages
have very low populations, and spread over a wide area. This makes it uneconomical and
expensive for social amenities to be provided. Most of the rural communities are located in the
heavily wooded forests. Extension of electricity has been done under Self Help Electrification
Projects over the past decade. However, the lines are frequently overgrown with bushes, and
falling trees interrupt services. Coupled with the fact that electricity is mainly used for lighting,
GSEIP/ESMP
Page 23
50 SCHOOLS FOR EXPANSION AND REHABILITATION
ENVIRONMENTAL AND SOCIAL MANAGEMENT PLAN
the power utility company serving the area does not deem the service very profitable. Roads are
poorly developed, and are mainly dusty, dirt roads. This is because vehicular traffic is usually low,
except in the cocoa season, where haulage trucks move in to haul cocoa to the ports. The heavy
and long rainfall regime erodes the roads often, and so they are periodically graded and aligned.
Boreholes and hand-dug wells provide drinking water in most of the rural areas, heavily
supplemented by harvested rain water. Small rural communities are separated by large swathes
of forests, so transportation is mainly by bicycles and motorcycles, as well as the occasional and
often overloaded commercial vehicles.
The urban centers, however, enjoy electricity, pipe-borne water and good roads. They are mainly
interconnected by surfaced roads that go to emphasize the stark difference between the rural and
urban populations.
Education: Access to basic education is restricted, not by availability, but by reach. Many pupils
walk between 1.5 to 3 kilometres to attend school. Often, some have to use canoes and makeshift
boats or weak bridges to reach school. Junior and senior secondary education is more restricted,
and many students are unable to commute, and rather relocate to live with relatives in bigger
towns where school facilities exist. Senior secondary schools are predominantly found in the
urban centres. There is a polytechnic in Takoradi, in Sekondi Takoradi Metropolis, and a teacher
training colleges at Sefwi Wiawso.
Employment: The major employment avenues are in food cropping, (mainly of rice, plantain,
cassava. vegetables and fruits), plantation farming, especially of cocoa, oil palm, rubber,
processing of oil palm, copra, mining and lumber processing. Illegal, small-scale gold is a common
occurrence that is ravaging the ecology of the zone. It entails open cast mining that uses nearby
rivers, streams and rivulets to wash the soil for alluvial gold. The use of mercury is widespread,
and the government is struggling to control illegal mining.
3.2.6 Coastal Savannah
The coastal savannah stretches from southern section of the Central Region and spreads
eastwards across the Greater Accra Region to the Volta Region. It encompasses
Population and Demography: The Coastal Savannah has the most populous cities in Ghana.
Accra, the national capital, as well as Tema, the leading industrial city are both located in this
zone. The other major city is Cape Coast, an ancient city noted for its castles, forts and other
heritage sites. It also has a high concentration of the leading senior secondary school and tertiary
institutions in Ghana. This zone has been a major destination for rural urban drift, especially
Accra and Tema. Thus, the population is concentrated around these two nodes, where many rural
GSEIP/ESMP
Page 24
50 SCHOOLS FOR EXPANSION AND REHABILITATION
ENVIRONMENTAL AND SOCIAL MANAGEMENT PLAN
people flood to in search of work opportunities. Accra alone is estimated to have about 1.8 million
people commuting daily in and out of the city for business, trade and other activities (2010-2013
Medium Term Development Plan, Accra Metropolitan Assembly).
Social Amenities:
Benefitting from their occupation by colonial administrators in pre-
independence days, this zone is home to many of the major administrative and political
structures. Cape Coast used to be the colonial capital before it was relocated to Accra in 1877.
Historically, the Volta Region also encountered German and Swiss missionaries who established
schools and churches, some of which are still in existence. Thus, the Coastal Savannah zone saw
development and modernity ahead of the rest of Ghana. Road networks, electricity supply, pipeborne water and drainage have been available since the 1940s. As home to the national capital,
the Greater Accra Region has the best of social amenities and infrastructure, including road
network, electricity, potable water supply, public transport system and telecommunications.
These facilities are, however, are constantly being stretched by the constantly increasing
population and attendant urban sprawl.
Education: Cape Coast is touted as the “cradle of education” in Ghana, since formal education in
Ghana started there. Following the coming of Europeans to the then Gold Coast missionary
schools were started in Cape Coast, and then spread to Accra. The Volta Region also saw German
and Swiss missionaries setting up schools and institutions of learning. Thus, the zone has some of
the oldest and reputed basic and secondary schools in Ghana. Basic education is highly available
and accessible, with reduced access in the northern sections of the zone. Even then, availability
and accessibility are higher than most parts of the other eco-zones. Secondary education is also
very available and accessible. In this zone, tertiary education is strongly represented. The highest
concentration of tertiary institutions is found in the zone, both public and private. The University
of Cape Coast, the University of Ghana, Legon, the University of Professional Studies and
Accountancy, Ghana Technology University College and the University of Allied Health Sciences
are among the public tertiary institutions here. A number of private universities are also found,
prominent among them are Ashesi University, and Zenith University College. Religious
organizations have over the past two decades, also set up many universities, including Central
University College, Methodist University College, and Pentecost University College. Other tertiary
institutions include polytechnics at Accra, Cape Coast and Ho.
Employment: The Coastal Savannah zone is the business and economic centre of Ghana; hence it
offers various employment opportunities ranging from the formal sector to the private, small and
medium scale businesses. Ministries, government institutions and agencies, banking and financial
institutions, schools and the service industry present employment avenues for university and
GSEIP/ESMP
Page 25
50 SCHOOLS FOR EXPANSION AND REHABILITATION
professional graduates.
ENVIRONMENTAL AND SOCIAL MANAGEMENT PLAN
Food markets for the teeming population offers brisk business
opportunities in the food sector, where traders haul raw food items from the forest zones to the
Coastal Savannah for sale. As in most cosmopolitan areas, medium, small and micro scale
businesses abound, as every individual is striving to make a living in the melting pot of urban
living.
4.0
SIGNIFICANT ENVIRONMENTAL AND SOCIAL IMPACTS
The various phases of the proposed SEIP sub-projects would potentially present issues of
environmental concern. These concerns have been identified from various sources, including site
visits and inspections, consultations with primary stakeholders and project literature review.
The potential environmental and social impacts of the proposed project have been categorized
GSEIP/ESMP
Page 26
50 SCHOOLS FOR EXPANSION AND REHABILITATION
ENVIRONMENTAL AND SOCIAL MANAGEMENT PLAN
under the various project phases, as Pre-Construction phase impacts, Construction Phase impacts
and Occupation and Maintenance Phase impacts.
4.1
Pre-construction Phase Impacts
Pre-construction phase activities would comprise land acquisition, vegetation clearing and land
preparation, as well as delivery of construction materials to site. Potential impacts at the preconstruction phase will include:

Removal, handling and disposal of asbestos roofing materials

Loss of vegetative cover,

Dust generation,

Exposure of soil surface to erosion,
These are described in detail below.
4.1.1
Removal, handling and disposal of Asbestos
Most buildings constructed in Accra and most coastal dwellings in Ghana prior to 1980 may
contain asbestos. Even some buildings constructed after 1980 may contain some asbestos, most
likely as roofing material. Asbestos is considered a carcinogenic material. When broken, they
release asbestos fibres, which when inhaled can lead to serious and fatal lung ailments. This will
be a major risk which, when not properly managed, could become an adverse impact (-3).
4.1.2
Loss of Vegetative Cover
As described above under Section 1.2 Description of Project, the locations of some sub-projects are
currently covered by grasses, vegetation brush and an average of about 15 trees of different sizes
and at different levels of maturity. These will have to be cleared for the project to commence. This
could lead to loss of vegetative cover, and is considered a minimally adverse impact (-1), because
the vegetation type is available in adjoining areas. No rare, threatened or endangered plant
species was identified on any of the sub-project sites. Felled trees will be cut into sizeable logs
and handed over to the beneficiary school for use as fuel wood at the dining halls.
4.1.3
Dust Generation
For the construction of new facilities, the removal of vegetative cover at the construction sites
will be done using machinery (bulldozers and graders). This activity will generate dust as the
vegetation is cleared from the soil surface. This will be a slightly adverse impact (-2), since, in
almost all cases, the sub-project sites are on school compounds already occupied by students and
staff..
GSEIP/ESMP
Page 27
50 SCHOOLS FOR EXPANSION AND REHABILITATION
4.1.4
ENVIRONMENTAL AND SOCIAL MANAGEMENT PLAN
Exposure of Soil Surface to Erosion
Clearing of vegetation prior to construction could expose the soil surface to erosion, especially
during the rainy season. The soil in several sections of the area is made up of loose,
unconsolidated material that is susceptible to erosion, especially by run-off. This is a minimally
adverse impact (-1) since the sub-project sites have been selected to avoid steep areas liable to
run-off carrying away sediments.
4.2
Construction Phase Impacts
Construction phase impacts will comprise the following:

Air quality impacts (Dust and Exhaust emissions)

Noise generation

Traffic Impacts

Occupational Health and Safety

Public Safety and Health

Community and Local Economics

Community Perception and Attitudes

Distortion of Social Processes

Solid Waste management

Liquid waste management

Employment and Income opportunities
These are briefly described below, with their proposed mitigation measures:
4.2.1
Air Quality Impacts
Dust generation from excavation and construction activities could compromise air quality in the
project area, especially during the dry season. Exhaust emissions from construction machinery
could also affect air quality via their exhaust emissions. This will be a minimally adverse impact
(-1)
4.2.2
Noise generation
Construction activity could generate noise from machinery and equipment that will disturb
teaching and learning. This will be a slightly adverse impact (-2)
GSEIP/ESMP
Page 28
50 SCHOOLS FOR EXPANSION AND REHABILITATION
4.2.3
ENVIRONMENTAL AND SOCIAL MANAGEMENT PLAN
Traffic Impacts
Haulage trucks delivering building materials to site could generate traffic impacts by adding to
vehicular traffic on roads serving the project area. This will be a minimally adverse impact (-1)
4.2.4
Occupational Health and Safety
Construction site workers will be exposed to risks of accidental collisions with moving vehicles,
strains from repeated movements or from lifting and heaving of heavy objects, slips and falls,
including falls from heights. Accidental cuts from tools and machines are also safety risks. Wet
cement as a construction material is corrosive on contact to with human skin. This will be a
minimally adverse impact (-2)
4.2.5
Public Safety and Health
Excavations, pits and heaps of unconsolidated material will be left overnight at the end of a
working day at the construction site. These would make the construction site dangerous to stray
animals and vagrants who might walk across the site at night.
It will be captured in the Contractors’ Clauses for selected contractors to recruit local labour as
much as it is available and practicable. However, the possibility of other skilled personnel coming
into the subproject location to work on the construction project cannot be ruled out. That will
bring in risks of increased incidence of HIV/AIDS and Sexually Transmitted Diseases (STDs). The
expected cash liquidity in the locality could increase social vices such as prostitution. These are
risks that need to be managed to prevent them from occurring. The identified impact will be an
adverse impact (-3).
4.2.6
Solid Waste Generation
Construction activity will generate considerable amount of solid waste, include earth material,
wood cut-offs, wood shavings, plastic cut-offs, empty cement sacks, paint cans etc. These would
need to be appropriately disposed of. This will be a minimally adverse impact (-1)
4.2.7
Liquid Waste Generation
Liquid waste streams will include equipment wash-out after daily construction activity, and
human wastes from construction workers. An estimated 30 persons will be engaged per subproject site. This will be an adverse impact (-2)
4.2.8
Sources of Raw Materials
Raw materials such as laterite and sand are won from engineered borrow pits where these
materials are naturally available. Permits are required from regulatory agencies for accessing
GSEIP/ESMP
Page 29
50 SCHOOLS FOR EXPANSION AND REHABILITATION
ENVIRONMENTAL AND SOCIAL MANAGEMENT PLAN
these materials, which also require some remediation works to be done at the borrow pits in
order to mitigate environmental damage after winning the material. It will be the selected
Contractors’ responsibility to acquire the relevant permits for borrows sites, from where laterite
and other earth materials for the construction activity will be won. This responsibility will be
captured in Contractors’ Clauses as part of the contract document. This will be a zero (0) impact,
since the permitting process requires that the permit holder backfills or remediates any impact
arising from the winning of construction materials.
4.2.9
Community and Local Economics
At the Construction phase, the project will generate opportunities for increased employment
(local artisans and laborers in the district where facilities will be built) and business growth for
local communities (boost in trade of construction materials and goods and services for the
contractor and contractor’s employees). While this additional employment and economic growth
may be limited to the construction stage, the project will contribute to an increase in diversified
skills base through skills and technology transfer and collective business acumen of the locality,
which will have secondary benefits in the long term. Failure to maximize local employment and
business opportunities may result in negative perceptions within the community and may fuel
opposition and potential conflict.
An estimated 15 labourers will be employed at each subproject location. Employment and
incomes for these people could have ramifying positive effects. There will also be opportunities
for food vendors who will sell cooked food to these workers on a daily basis
This will be a beneficial impact (+3).
4.2.10 Increased Pressure on Community Amenities
The construction (rehabilitation or expansion) phase will see the aggregation of workers in a
common locality or section of the community. This could put communal facilities such as public
toilet facilities and drinking water. Migrant workers could create congestion in small
communities by way of rented accommodation, and create social tensions. This would be an
adverse impact (-2)
Table 4.1
Rapid Impact Matrix (Scale: +ve impact=+5; -ve impact= -5)
ENVIRONMENTAL AND SOCIAL
IMPACT
GSEIP/ESMP
IMPACT
SCALE
Pre-Construction Phase
IMPACT DESCRIPTION
Page 30
50 SCHOOLS FOR EXPANSION AND REHABILITATION
ENVIRONMENTAL AND SOCIAL MANAGEMENT PLAN
Asbestos handling
-3
Risk of inhalation of asbestos fibres, which can lead to
serious health implications.
Loss of Vegetative cover
-1
The site will be cleared of vegetation (trees and
underbrush) prior to construction.
Dust generation
-1
Vegetation clearing will generate dust on and around
the project site
Exposure of soil surface to erosion
-1
Clearing of vegetation will expose soil surface to
elements of the weather (erosion)
Construction Phase
-1
Dust generation from digging and excavation activities,
exhaust emissions from construction machinery.
Air quality issues
Noise
-2
Construction equipment and related activities will
generate noise. This could disrupt teaching and
learning on school compounds.
Delivery of construction materials and equipment
could impede vehicular movements on trunk roads
serving sub-project areas
Traffic impacts
-2
Occupational Health and Safety
-2
Risks of injury from accidents, collisions trips and falls
at the construction site, exposure to corrosive action of
wet cement
Public safety and health
-3
Solid waste generation
-1
Risks of humans or animals falling into excavations.
Increased risk of HIV/AIDS and STDs
Excess earth material, packaging materials, empty
cement sacks, paint containers, etc., will be generated.
Liquid waste generation
-3
Equipment washout after daily operation, ablution
facilities for construction workers.
Community and local economies
+3
Some local artisans will be employed; some
construction material will be sourced locally. Food
vendors and other services will also generate revenue.
Increased pressure on existing
community amenities
-2
Migrant workers will increase pressure on facilities
such as public toilets and water sources.
Occupation and Maintenance Phase
Demographic changes and increased
demand on transport infrastructure
-2
Enhanced school infrastructure, safer and larger school
structures will mean increased student populations
Solid waste generation
-1
Waste paper will be generated from the offices and
classrooms; food packaging wastes from canteen.
Liquid waste generation
-2
Wastewater from washrooms and science laboratories
*Impacts are objectively assessed and quantified based on magnitude, extent, duration and reversibility.
4.3
Occupancy and Maintenance Phase Impacts
Occupancy and Maintenance phase impacts would include:
GSEIP/ESMP
Page 31
50 SCHOOLS FOR EXPANSION AND REHABILITATION

ENVIRONMENTAL AND SOCIAL MANAGEMENT PLAN
Demographic changes and increased demand on social infrastructure in host
communities

Traffic Impacts

Solid Waste generation

Liquid Waste generation

Employment opportunities
These are briefly described below.
4.3.1
Demographic changes and increased demand on social infrastructure
One of the key qualifying criteria is for a beneficiary school to have a minimum population
capacity of about 1,000 students. The rehabilitation and/or expansion of school facilities enhance
the school’s intake capacity. The influx of such a population will affect the population dynamics
of the host community and potentially impinge on community infrastructure and services,
especially on transport facilities. Students from the surrounding communities will need to
commute to and from school. Initially, this could create inadequacy and then opportunities for
investors in the transport sector. This will be a slightly adverse impact (-2)
4.3.2
Solid Waste Generation
Paper wastes, food packaging and residues will comprise the bulk of solid wastes to be generated
from the school. This will be a minimally adverse impact (-1)
4.3.3
Liquid Waste Generation
Liquid waste will comprise washroom wastes, as well as wastes from the science laboratories.
With a projected student population in excess of 1,000, this will be a slightly adverse impact (-2)
Table 4.1 above summarizes the identified environmental and social impacts and their detailed
description at the various phases of the project.
5.0
MITIGATION OF IDENTIFIED IMPACTS
Under this section, the proposed mitigation measures for the identified environmental and social
impacts are presented under the various project phases.
GSEIP/ESMP
Page 32
50 SCHOOLS FOR EXPANSION AND REHABILITATION
5.1
ENVIRONMENTAL AND SOCIAL MANAGEMENT PLAN
Pre-Construction Phase Mitigation
Identified impacts at the Pre-Construction Phase will be mitigated as follows.
5.1.1
Asbestos Removal
If the presence of asbestos is suspected, a registered asbestos consultant or other qualified health
and safety specialist should be consulted to determine whether or not asbestos is present. If,
however, the Contractor has capacity to safely handle it, then it should be removed and disposed
of appropriately.
The use of appropriate Personal Protection Equipment prior to handling asbestos is mandatory.
This should include safety gloves, nose mask of appropriate type, and coveralls. The asbestos
material should first be sprinkled with water to make it wet and less likely to break. If removed
from a height, they should not be dropped. Rather, they should be carried or held in a net or
appropriate material, and lowered gently either by a crane or by ropes onto the ground or into a
waiting disposal truck. Removed asbestos pieces should be disposed of at a landfill site, to be
buried immediately and separately from other wastes.
5.1.2
Mitigation of Vegetative Cover Loss
As part of the Contractor’s obligations, one hundred and fifty percent (150%) of the total number
of trees felled in clearing the site for construction will be replanted on and around the school
compound as part of the construction activity, and will be deemed to be a deliverable from the
contractor. If there is inadequate space around the school to plant all the seedlings, another
location will be demarcated for the contractor to plant the seedlings and ensure that they are
established.
5.1.3
Dust Generation
This is an impact that requires no mitigation. Natural wind dispersion in the sub-project area will
attenuate generated dust.
5.1.4
Exposure of Soil Surface to Erosion
Vegetation clearing will be staggered; it will be done only at sites where construction work is
ready to begin. This will limit the exposure of the soil surface to erosion and other factors.
5.2
Construction Phase Mitigation
Under the Construction Phase, identified impacts will be mitigated as follows:
5.2.1
Dust and Exhaust Emission Mitigation
GSEIP/ESMP
Page 33
50 SCHOOLS FOR EXPANSION AND REHABILITATION
ENVIRONMENTAL AND SOCIAL MANAGEMENT PLAN
Areas to be excavated will be doused with water to minimize dust emissions. Construction
equipment and machinery will be serviced regularly to reduce excessive exhaust emissions.
5.2.2
Noise generation
Construction equipment and machinery will be serviced regularly to reduce excessive noise
generation. As much as possible, construction activity will be restricted to daylight hours, when
background din masks noise from construction activities. Regarding disruption of teaching and
learning, this will be a residual impact after machinery and equipment have been maintained.
Construction workers will be required to avoid unnecessary noise, shouting and horsetrading.
5.2.3
Traffic Impact Mitigation
As much as possible, delivery of materiel to site will be restricted to off-peak traffic hours. Traffic
wardens (flagmen) will be engaged to coordinate traffic flow
5.2.4 Occupational Health and Safety
Proper site sanitation and housekeeping will be maintained on construction sites. Contractors
will be required to provide and enforce the use of Personal Protection Equipment (PPE). Strict
adherence to local safety regulations and safety precautions as per Factories, Offices and Shops
Act, 1970 (Act 328) will be enforced.
5.2.5
Public Safety and Health Enhancement
The construction site will be appropriately fenced or cordoned off to prevent stray animals and
vagrant persons, including students, from straying on to the site. All pits and excavations that
will be left overnight will be cordoned with physical barriers and appropriate signage. HIV/AIDS
and STDs awareness programmes will be held for hired labour, particularly non-indigenous
workers, and condoms will be made available to them.
5.2.6
Solid Waste management
Excess earthen material will be used in landscaping at the project site. Waste skips will be
provided to collect wastes for appropriate disposal at municipal disposal site.
5.2.7
Liquid Waste management
Equipment washout will be discharged away from water courses to avoid contaminating natural
water bodies. The contractor will be required to provide separate toilet and ablution facilities for
construction workers. These will be either chemical toilets or pit latrines that will be chemically
treated and sealed after the construction phase..
5.2.8
Community and Local Economics
GSEIP/ESMP
Page 34
50 SCHOOLS FOR EXPANSION AND REHABILITATION
ENVIRONMENTAL AND SOCIAL MANAGEMENT PLAN
This will be a positive impact (social enhancement) that requires no mitigation.
5.2.9
Increased Pressure on Communal Facilities
Selected contractors will be required to construct work camps away from the beneficiary
community, and provide ablution and drinking water facilities specifically for their use.
5.3
Occupancy and Maintenance Phase Mitigation
At the operational phase of the school, the identified potential impacts will be addressed as
follows:
5.3.1
Demographic Changes and Increased Demand on Transport Infrastructure
The District Assemblies (DAs) will ensure that transport facilities and infrastructure are
improved. Measures in this direction could include the extension of the services of the stateowned Metro Mass Transport Limited to facilitate the movement of students to and from school
on a daily basis. Another alternative will be for the DAs to grade and maintain the service roads
to the school locations to encourage private transport providers to ply those roads and offer
transport services to students.
5.3.2
Solid Waste management
The DAs will provide waste skips for waste collection. These will be evacuated by DA waste
management facilities periodically.
5.3.3
Liquid Waste management
Suitable toilet facilities will be provided on the school compound. The classroom block design
includes water closet (WC) facilities to serve the ablution needs of students and staff. These will
be evacuated of sludge periodically by the DAs.
6.0
MONITORING
Monitoring of project activities will ensure that the environmental and social management and
mitigation plans installed for the project implementation are working as planned. It will also
indicate how close indicated paper intentions are to reality, and offer opportunities for prompt
GSEIP/ESMP
Page 35
50 SCHOOLS FOR EXPANSION AND REHABILITATION
ENVIRONMENTAL AND SOCIAL MANAGEMENT PLAN
review and redress of any systemic failures or weaknesses. Monitoring will be done throughout
the project implementation, from Pre-Construction phase, through Construction phase to
Occupancy and Maintenance phase. Table 6.1 is a proposed monitoring plan showing monitoring
activities, responsible persons and budgeted costs.
6.1
Pre-Construction Phase Monitoring
At the Construction phase, the major activity that will require monitoring is the involuntary
resettlement of project affected persons.
6.1.1 Removal, Handling and Disposal of Asbestos
The identification of asbestos on any of the subproject locations will be reported and documented
by the relevant contractor. The removal, handling and disposal shall be supervised by the
Environmental Consultant and the Environmental and Social Safeguards Coordinator, both of
whom should be wearing the appropriate PPEs. The entire process of removal and disposal shall
be documented, possibly with video records, and filed as part of the periodic reporting process to
the World Bank Environmental Safeguards Specialist.
6.2
Construction Phase Monitoring
This monitoring plan will be implemented during the Construction phase, and will cover the
following:

Air quality (Dust and Exhaust emissions)

Noise generation

Traffic impacts

Occupational health and Safety

Public Safety and Health

Solid waste generation and management

Liquid waste generation and management, and

Employment and Income generation.
6.2.1
Air quality (Dust and Exhaust emissions)
Dust emissions from the Construction phase will be monitored on a daily basis, and when
required, the site doused with water to control dust.
6.2.2
Noise
GSEIP/ESMP
Page 36
50 SCHOOLS FOR EXPANSION AND REHABILITATION
ENVIRONMENTAL AND SOCIAL MANAGEMENT PLAN
Though the recorded levels are well within the EPA guideline limits, noise levels will continue to
be monitored through the Construction phase, on a weekly basis.
6.2.3
Traffic Impacts
Service roads in the sub-project locations could be congested due to construction activities.
Traffic impact at the construction phase of the project will be monitored on a daily basis.
Collisions, near-misses and incidence of traffic build-ups will be logged daily, and investigated to
determine how best they could be prevented from recurring.
6.2.4
Occupational Health and Safety
While personnel will be provided with all the appropriate PPE and their use enforced, the
possibility of accidents and personal injuries at the construction sites cannot be downplayed. OHS
incidents will be monitored on a daily basis. PPE will include safety boots, gloves, nose masks,
safety goggles, hard hats and ear muffs. Any accident, near miss or injury will be recorded and
investigated to determine the cause so as to avoid their recurrence.
6.2.5
Public Safety and Health
While measures will be taken to prevent any breaches of public safety, incidents that could
compromise safety of non-construction workers and the general public will be monitored on a
daily basis, and documented as they happen for prompt amelioration and review.
The selected contractors will be required, as part of their deliverables, to offer HIV/AIDS
awareness programmes to their hired hands, both local and in-migrated. These programmes
should be frequent; one before commencement of works, and repeated at least once every three
months. They will be documented in both hard and soft version. The free or subsidised supply of
condoms to hired hands, especially in-migrated ones will also be required.
6.2.6
Solid waste generation and management
Volumes of solid wastes generated will be monitored on a weekly basis. This will provide a guide
as to whether or building materials are being used judiciously.
6.2.7
Liquid Waste generation and management
The proper disposal of generated liquid waste is critical in ensuring that no natural water body
or course is contaminated with faecal matter of liquid construction wastes. The de-sludging and
disposal of the mobile toilets at the construction sites will be monitored on a daily basis.
GSEIP/ESMP
Page 37
50 SCHOOLS FOR EXPANSION AND REHABILITATION
6.2.8
ENVIRONMENTAL AND SOCIAL MANAGEMENT PLAN
Employment and Income Generation
The construction phase of the 50 sub-projects under the SEIP is estimated to last over 5 years.
During the period, about 1,500 people are expected to be employed. The selected contractors will
employ quantity surveyors, civil engineers, building technicians, construction engineers and
other construction professionals. Low-skill workers such as masons, carpenters and construction
workers will also be engaged. Other employment avenues will include supply of local building
materials as sand and stones, as well as food vendors who will sell food to construction workers
on site. This would significantly impact the local economies as well as the overall national
economy.
6.3 Occupancy and Maintenance Phase Monitoring
Monitoring at the Operations phase will cover the following:
The parameters to be monitored at the Occupancy and Maintenance Phase will be:

Demographic changes and Increased demand on Transport Infrastructure

Solid waste generation

Liquid waste generation

Groundwater depletion
These are explained in detail below.
6.3.1
Demographic Changes and Increased Demand on Transport Infrastructure
This parameter will be monitored quarterly by the DAs, to determine how the operations of the
Community Day Secondary School will be impacting on the local transport sector. The outcome
will determine the necessary steps to be taken by the DA to rectify the situation.
6.3.2
Solid Waste Generation and Management
Generated solid waste will comprise mainly wastepaper, packaging material and other organic
matter that could be potentially raw material (biofuel) for energy generation should the
quantities be significant and consistent. Generated volumes and frequency of evacuation will be
monitored to determine if there is a suitable trend. Monitoring records will be kept by the DA or
the waste collection contractor.
6.3.3
Liquid Waste generation and Management
GSEIP/ESMP
Page 38
50 SCHOOLS FOR EXPANSION AND REHABILITATION
ENVIRONMENTAL AND SOCIAL MANAGEMENT PLAN
Cess pits with soak-away systems will be installed to contain liquid waste from the washrooms
and laboratories. These will be de-sludged periodically as they get filled up. The School
Management Team will monitor the systems for their integrity and continued utility.
Table 6.1 below is a Monitoring Plan
Table 6.1 Monitoring Plan
Parameter
Monitoring
Responsibility
Remarks
Frequency
Pre-Construction Phase
Construction Phase
Air quality (Dust and
Weekly
Project Contractor
Exhaust emissions)
Weekly air quality monitoring analysis
will determine dust control measures to
be implemented.
Noise generation
Weekly
Project Contractor
Weekly noise monitoring analysis will
determine noise control measures to be
implemented.
Traffic impacts
Daily
Project Contractor
Daily traffic analysis will determine traffic
control measures to be implemented.
Occupational
health
Daily
Project Contractor
and Safety
Daily HSE meetings will be organized by
the Site Safety Officer, that will address
HSE management issues and provide a a
forum for the SEIP PIT to interface with
Contractor and construction activity, and
address public safety concerns and review
of incidents and near-misses, while
providing Opportunities for Improvement
(OFI).
Public
Safety
Health
and
Daily
Project Contractor/
Site security and safety will be monitored
Project
twice a day, before commencement of
Implementation
work and after close of work, to ensure
Team
that the site is secured from intruders and
vagrants, and that all excavations and
equipment on site are secured and
properly cordoned off. Tool box meetings
will address public safety concerns and
Opportunities for Improvement (OFI).
GSEIP/ESMP
Page 39
50 SCHOOLS FOR EXPANSION AND REHABILITATION
Solid
generation
management
waste
and
Weekly
Liquid
generation
management
waste
and
Weekly
Employment
and
Income generation
Monthly
ENVIRONMENTAL AND SOCIAL MANAGEMENT PLAN
Project
Implementation
Team/District
Waste Management
Department
Project
Implementation
Team
The District WMD will be engaged to
empty waste collection skip on site
regularly
Project
Implementation
Team/DA
PIT and the District Assembly will ensure
that workers are paid regularly and on
time
Chemical and/or pit latrines to be
provided by contractors for their
labourers will be inspected.
Occupancy and Maintenance Phase
Demographic
changes and
increased demand on
transportation
infrastructure
Quarterly
District Assembly
Planning
Department
The Planning Office will monitor local
demographic changes and economic
trends
Solid
generation
management
waste
and
Monthly
District Assembly
Waste
Management
Department
WMD will keep track of volumes, types
and characteristics of generated solid
waste
Liquid
waste
Quarterly
School
School Management Team will monitor
septic tanks and inform District Waste
Management Department when full or
near full
generation
and
management
6.4
Management Team
Reporting Schedule
The Environmental and Social Safeguards Coordinator at the Ministry of Education will be
responsible for furnishing the World Bank with reports and updates. On a monthly basis, the
Coordinator will furnish the Ghana office of the World Bank with progress reports. However,
should it be necessary for a report to be sent in the intervening periods that will also be done.
7.0
ENVIRONMENTAL AND SOCIAL MANAGEMENT PLAN
This section describes the environmental and social management plan and the environmental
guidelines for avoiding and or preventing the adverse environmental and social impacts of the
project activities. Institutional setup for implementing the ESMP, roles and responsibilities of the
focal persons, monitoring mechanisms, and training and capacity building programs have also
been detailed in this section.
Qualified contractors will be selected through a competitive bidding process to implement the
construction of the sub-projects. Contractors will undertake the construction of the subprojects
GSEIP/ESMP
Page 40
50 SCHOOLS FOR EXPANSION AND REHABILITATION
ENVIRONMENTAL AND SOCIAL MANAGEMENT PLAN
at the approved locations, delivering according the approved project design details. Construction
phase environmental and social management and mitigation measures will be spelt out clearly
for contractors under a Contractors’ Clauses document, to be issued as part of the contract
documents that contractors will sign off. The Project Management Team has the role and
responsibility of ensuring compliance with the relevant local and World Bank safeguard policies.
The World Bank has the role of reviewing and approving safeguards documents regarding this
project, while Ghana EPA will ensure that all compliance standards and measures are met.
The World Bank has the role of reviewing and approving safeguards documents regarding this
project, while Ghana EPA will ensure that all compliance standards and measures are met.
7.1
Project Management and Oversight Structure
Oversight of the SEIP implementation will be in the Ministry of Education (MOE) with the
Ghana Education Service providing their mandated implementation role for service delivery.
This section deals with the relevant institutional arrangements–existing and proposed –which
would facilitate environmental and social soundness and sustainability.
7.1.1
Project Oversight
A Steering Committee and Project Management Team of the MOE will be established to
coordinate and oversee implementation.
The Project Steering Committee (PSC) will:

Provide guidance on strategic, policy and implementation issues;

Coordinate activities of the ministries, agencies and other stakeholders involved in the
project implementation;

Review and approve annual work plans, budget and annual reports;

Review and discuss quarterly and annual project progress reports and make necessary
recommendations; and

Assess the progress towards achieving the project’s objectives and take corrective action if
necessary.

Resolving cross-sectoral and issues above the Project Management Team.
The PSC will be chaired by the minister of MOE or his/her designee. The PSC will include
representatives at the chief director level for the ministries and at the director levels for the
agencies of relevant ministries and institutions and civil society organizations, including:
(i)
Ministries of Finance; and Ministry of Local Government and Rural Development;
GSEIP/ESMP
Page 41
50 SCHOOLS FOR EXPANSION AND REHABILITATION
ENVIRONMENTAL AND SOCIAL MANAGEMENT PLAN
Ghana Statistical Service; Environmental Protection Council; and West African
(ii)
Examination Council;
Civil Works Contractors Associations; and Ghana National Education Campaign
(iii)
Coalition. The PSC will meet quarterly to assess the project implementation progress
on the ground and undertake site visits as necessary.
7.1.2
Functions of the Project Management Team
The Project Management Team will derive from the Project Implementation Committee at the
national level (see figure). The PMT’s main functions are to
(i)
assume project control,
(ii)
monitor the actual construction of work executed in the four (4) zones of the country
namely: Zone 1- Northern, Upper East and Upper West regions; Zone 2- Ashanti and
Brong Ahafo regions; Zone 3- Central, Western and Greater Accra regions; and Zone
4- Volta and Eastern regions;
(iii)
review reports submitted by the supervising consultant on a zonal basis and bring up
issues to the Project Implementation Committee for resolution;
(iv)
liaise with the District Assemblies to ensure their full participation in the supervision
of the project;
(v)
prepare and update the schedule of activities/procurement plans to be executed
under the project;
(vi)
vetting claims submitted by the consultants on behalf of the contractors;
(vii)
vetting consultancy claims submitted by the supervising consultants;
(viii)
agree on design modification to suit topography of the land;
(ix)
prepare bi-monthly briefs to the Ministerial leadership;
(x)
follow up and ensure that contractors and consultants are paid for properly prepared
claims;
(xi)
review any recommendations for the payment of fluctuations/variations and for
advice to the PSC;
(xii)
take over completed structures and commission them for usage by the schools; and
(xiii)
accompany Ministerial leadership on monitoring in the respective zones.
The PMT will include the following:

2 environmental and social safeguards consultants

1 procurement specialist (MOE)

1 technical advisor (MOE)

4 architects (FPMU + 3 others)
GSEIP/ESMP
Page 42
50 SCHOOLS FOR EXPANSION AND REHABILITATION
ENVIRONMENTAL AND SOCIAL MANAGEMENT PLAN

4 quantity surveyors (FPMU, GETFund and 2 others)

4 civil engineers (FPMU + 3 others)

1 electrical engineer (on retainer basis)

Project management consultancy firm (providing the others)
Figure 7.1 below is a tabular arrangement of the institutional arrangements and responsibilities
for environmental assessment and resettlement.
Figure 7.1:
Institutional Arrangements/Responsibilities for Environmental
Assessment and Resettlement
Institutional Responsibilities Task
Institution(s) Responsible
Project coordination and
management
- Project Steering Committee (PSC)
- Project Management Team
- District Education Oversight Committee
- School Management
Implementation and monitoring of
ESMF and RPF
Determination of affected persons
and compensation levels
- PMT (E&S Consultants)
- DEOC (including Land Valuation Division)
- Environmental Protection Agency (EPA)
- PSC
- PMT
- DEOC
Payment of compensation
- PMT
- DEOC
Dispute resolutions
- DEOC
District Level: District Assemblies (DAs) are empowered under Act 462 of 1993 to be responsible
for development, improvement and management of human settlements and the environment in
their districts. In order to facilitate the work of the DAs in this regard, the District Education
Oversight Committee (DEOC) which includes the (i) MCE or DCE; (ii) District Director of
Education; (iii) District Engineer; (iv) District Planner; (v) District Environmental/Social Officer;
and (vi) representative from the Land Valuation Division of the Lands Commission will have
responsibility for the project implementation in collaboration with the beneficiary communities.
The District Environmental/Social Officer will be responsible for site screening and reporting to
the DEOC. There will be the need for capacity building at the DEOC level. The District Engineer
will lead in the monitoring and supervision of contractors and recommend the signing of work
certificates against work done.
GSEIP/ESMP
Page 43
50 SCHOOLS FOR EXPANSION AND REHABILITATION
ENVIRONMENTAL AND SOCIAL MANAGEMENT PLAN
Role of DEOC
The key functions envisaged for the DEOCs with regard to environmental issues are:

Responsible for liaising with EPA and other relevant agencies

Work with project environmental consultants (PM Consultancy) when required

Responsible for registering all project components within the zones with the EPA,
including completing Form EA1, any other documentation, and/or the attached project
environmental screening checklist.

Ensure compliance with all recommendations by EPA and other regulatory agencies

Play a lead role in site selection for relevant SEIP components within the district and
initiating collation of baseline data
Figure 7.2 below illustrates the organizational structure of the DEOC.
STEERING
COMMITTEE
PROJECT
MANAGEMENT
TEAM
MCE/DCE
DEOC

DISTRICT
DIRECTOR
InspectingFORand
EDUCATION
DISTRICT
ENGINEER.
DISTRICT
PLANNING
OFFICER.
DISTRICT
ENVIRONMENTAL
OFFICER
LAND
VALUATION
DIVISION
REPRESENTATI
Monitoring of environmental components of pre-constructional,
constructional and operational stages and providing the PMT with reports on a regular
basis.
Additionally, the DEOC will receive and seek to address any grievances that may arise at the local
level, as outlined in the RPF.
Table 7.2 below outlines the institutional setup for timely identification and reporting of the
environmental issues relating to the SEIP and for taking necessary preventive or corrective
measures at the national and district levels of responsibility under the ESMF:
Table 7.2
GSEIP/ESMP
Organizations and Focal Persons for ESMP Implementation
Page 44
50 SCHOOLS FOR EXPANSION AND REHABILITATION
ENVIRONMENTAL AND SOCIAL MANAGEMENT PLAN
Organization/Entity
Project
Management
Team
Role
Responsible for
implementing various
activities required for
safeguard compliance
under the ESMF and
RPF.
Focal Person
Environmental and
Social Safeguards
Consultants (to be
recruited)
Jurisdiction
Ministry of
Education
District Education
Oversight
Committee (of
District
Assembly)
Responsible for project
implementation in
collaboration with the
beneficiary
communities as well as
site screening and
reporting to the DEOC.
District
Environmental/
Social Officer
Respective
District
Assemblies
Project
Construction
Contractors
Responsible for
physical construction of
project structures
according to project
design and
specifications, site and
construction workers’
Health and Safety
Site Engineer and
Site Manager
Subproject
Construction
sites
World Bank
Has monitoring roles
for compliance with
World Bank
Environmental and
Social Safeguards
regulations
Task Team
Leader/members
Subproject
Construction
sites
7.2
General Health and Safety Procedures
The guidelines provided in the Factories, Offices and Shops Act, 1970 (Act 328) given below shall
be strictly complied with at the Construction phase of the project. These regulations cover the
major safety areas. Further details of the safety sections relating to this project are also outlined
below.
 General Safety Rules for workers engaged in construction.
 Safety guidelines related to the use of tools and equipment
 Safety procedures associated with the transportation and of personnel and materials, and
 Safety procedures for materials handling, storage and disposal
GSEIP/ESMP
Page 45
50 SCHOOLS FOR EXPANSION AND REHABILITATION
7.3
ENVIRONMENTAL AND SOCIAL MANAGEMENT PLAN
Pollution Prevention
In addition to the operational guidelines relating to health and safety, strict pollution prevention
guidelines shall also be enforced during all phases to the project. Most pollution incidents are
avoidable if careful planning and management procedures are instituted. Pollution prevention
measures are much cheaper to implement than costly clean up after the incident. For the
prevention measures to be effective it is important that the construction gangs first are
adequately trained in pollution prevention for this expansion project.
Some of the important pollution prevention guidelines to be followed for this project shall include
the following:
7.3.1
Planning and Preparation
Careful planning can reduce the risk of pollution significantly. As a first step environmental site
meetings will be organized with the construction gangs by the Project Management Team prior
to commencement and during construction operations. These meetings will help increase the
awareness levels of construction workers and supervisors on what environmental, health and
safety measures are required at the project site.
7.3.2
Site Offices
A common cause of pollution is through acts of theft and vandalism. The sub-project construction
areas will be cordoned off and adequately protected by fences and locked accesses where
possible. Security personnel are engaged at the nearby site offices and yard where construction
materials are kept. Care will be taken to ensure that no contaminated drain water is allowed to
flow into the public drains traversing the area.
Fire precautions to be observed at site offices include:
 Provision of adequate and suitable portable fire extinguishers
 Adequate ventilation for storage rooms containing flammable chemicals
7.3.3
Storage, Handling and Disposal of Materials / Oils / Chemicals
The Factories, Offices and Shops Act requirements regarding the above shall be strictly adhered
to. In addition, the following guidelines shall also be followed in the handling of materials, oils
and chemicals.
GSEIP/ESMP
Page 46
50 SCHOOLS FOR EXPANSION AND REHABILITATION
ENVIRONMENTAL AND SOCIAL MANAGEMENT PLAN
 Materials shall be stored in an orderly manner and in safe stacks, tiers or piles. Materials shall
be stored so as not to obstruct passageways. Where necessary warning signals, lights and
barricades shall be provided.
 Most chemicals used in construction operations such as oils, cement, cleaning materials, and
paint have potential pollution hazards. All such materials shall be stored on an impervious
base within a bund wall to contain any spillages.
 Leaking or empty oil / paint/ chemical drums shall be removed from the site and safely
disposed of.
 Contents of all tanks / drums containing chemicals shall be clearly marked.
 Disposal of all tanks and drums shall be done safely. All contents of tanks/drums to be
disposed shall be emptied and perforated by competent personnel before final safe disposal.
 Fuelling of project equipment (trucks, bulldozers etc.) and vehicles may constitute the greatest
spillage risks. This shall be done in designated areas with impermeable surfaces located away
from existing public drains on site. Drip trays and spill kits shall be kept on-hand. Fuel hoses
and valves shall be regularly checked for leakages and wear and tear.
 Emergency spillage procedures shall be clearly outlined and posted conspicuously. Absorbent
materials for containing spillages shall be readily available on site. These shall include
sawdust, sand, cotton rags, etc.
7.3.4
Concrete Works.
The construction of the building foundations and the superstructures themselves at the site shall
involve concrete works. Concrete and cement are very alkaline and corrosive and can have
serious pollution impacts on water. Therefore all concrete preparation and mixing shall be
located away from drains, and will be carefully monitored to ensure that such material do not get
into the public drains to contaminate any streams and water bodies.
7.4
Waste Disposal
For the proposed construction works, the major sources of waste would be from the vegetation
clearing, plastic scraps, empty cement sacks, metal scraps etc. Those that can be recovered and
used such as empty cement sacks and wood waste will be recovered for reuse. Dealers in the
relevant waste materials will be invited to cart them away, while the non-reusable ones will be
gathered in appropriate waste bins to be provided at the site for collection and disposal through
public waste disposal system.
GSEIP/ESMP
Page 47
50 SCHOOLS FOR EXPANSION AND REHABILITATION
7.5
ENVIRONMENTAL AND SOCIAL MANAGEMENT PLAN
Trainings and Capacity Building
The principal objective of the trainings is to ensure the sound and sustainable
implementation of the ESMP. Social conflict can best be addressed by bringing all
stakeholders on board through sustained and regular consultations. The training will equip
project personnel for effective communication and be a means of empowering the
community, for social conflict resolution.
7.5.1 District Level Training
It is recommended to hold one-day training workshops at the District level for DEOCs. These
workshops will focus on identifying and discussing environmental and social issues that will
arise during the implementation of the ESMP. These will also sensitize participants about
environmental and social obligations under the ESMP, managing the site relevant problems,
and strategizing implementation of the ESMP activities.
7.5.2 National Level Training
Similarly, a one-day workshop will be held at the national level every quarter during which
key stakeholders involved in SEIP field implementation will focus primarily on policy issues
and share ideas and experiences. The Environmental and Social Safeguard consultants in the
PMT will be responsible for organizing and reporting on these quarterly trainings. At the
national level, it is also recommended that contractors working in the various districts are
trained. The training of contractors will focus on their responsibilities toward complying
with the ESMP requirements.
7.6
Allocation of Resources for Environmental and Social Management
Apart from the human resources to be made available under Section 6.1 above, financial provision
would be required to ensure that mitigation, monitoring and training programmes are effectively
implemented. The estimated cost of implementing this ESMP is about US$ 26,500. The details
are provided in Table 7.3 below, which is a composite Environmental and Social Impact
Mitigation and Management Table that outlines how identified impacts will be mitigated,
managed and monitored during the implementation of the 50 existing schools for expansion and
rehabilitation under SEIP.
Some of the costs will be part of selected Contractors’ obligations, while the beneficiary Municipal
District Assemblies will bear the costs of some aspects. The contractors will be required to quote
for these activities as part of their tender processes.
GSEIP/ESMP
Page 48
50 SCHOOLS FOR EXPANSION AND REHABILITATION
GSEIP/ESMP
ENVIRONMENTAL AND SOCIAL MANAGEMENT PLAN
Page 49
50 SCHOOLS FOR EXPANSION AND REHABILITATION
Table 7.3
ENVIRONMENTAL AND SOCIAL MANAGEMENT PLAN
Environmental and Social Impact Management and Mitigation Table
POTENTIAL
PROJECT PHASE
ENVIRONMENTAL
LOCATION
PROPOSED MITIGATION
MEASURE (S)
RESPONSIBLE PARTY
NET EFFECTS
IMPACTS/ACTIVITY
Removal, handling and
disposal of asbestos
Some subproject
sites
Vegetation clearing
Project site
PRE-CONSTRUCTION
PHASE.
Air quality
Project site and
vicinity
A qualified asbestos
contractor will be
engaged to remove,
handle and appropriately
dispose of asbestos
material.
Project Contractor/
Project Management
Team
Selective and staggered
vegetation will be done
only when construction
is ready to begin.
Project Contractor
Areas to be excavated
will be doused with
water to minimize dust
emissions
Safe removal and
disposal of asbestos
Avoidance of
exposure of land
surface to erosion
Project Contractor
Controlled dust
generation; Reduced
exhaust emissions
Project Contractor
Reduced noise
impacts
ESTIMATED
BUDGET
(USD)
5,000
Part of
Contractor’s
costs
“
CONSTRUCTION
PHASE
Traffic impacts
GSEIP/ESMP
Project site and
vicinity
Regular maintenance of
machinery and
equipment.
Roads serving
immediate project
area
Restriction of
construction activity to
daylight hours
Noise
PMT/Project Contractor
Reduced traffic
impacts
Page 50
50 SCHOOLS FOR EXPANSION AND REHABILITATION
ENVIRONMENTAL AND SOCIAL MANAGEMENT PLAN
Restriction of delivery of
materiel to site to offpeak traffic hours. Use of
traffic wardens to
coordinate traffic flow
Project site
Occupational Health and
Safety issues
Proper site sanitation
and housekeeping.
Provision and enforced
use of PPE. First aid kits
will be provided to
manage minor accidents
Strict adherence to
safety precautions as per
Factories, Offices and
Shops Act, 1970 (Act
328)
Project site and
vicinity
Public safety and health
PMT/Project Contractor
Reduced incidence
of accidents and
injuries.
2,000
PMT/Project Contractor
Cordoning off of pits and
excavations with physical
barriers and appropriate
signage. HIV/AIDS and
STDs awareness program
for contractor’s staff,
Project Contractor
provision of condoms as
prophylaxis.
Project site
Solid waste management
GSEIP/ESMP
Excess earthen material
will be used in
landscaping. Waste skips
Project Contractor
Reduced risk of
accidents and
injuries to public
Safe disposal of
generated solid
waste
1,500
DA to dispose
of wastes
Page 51
50 SCHOOLS FOR EXPANSION AND REHABILITATION
ENVIRONMENTAL AND SOCIAL MANAGEMENT PLAN
will be provided to
collect wastes for
appropriate disposal at
municipal disposal site.
Safe disposal of
generated liquid
waste
Project site
Equipment washout will
be discharged away from
water courses;
Liquid waste
management
Increased pressure on
community amenities
Project host
community
Separate toilet and
drinking water facilities
will be provided for
construction crew
Project Contractor
Project Management
Team
Reduced risk of
conflict from stress
on community
amenities
through
municipal
waste
disposal
system
No cost
implications
6,000
Income generation
Employment and Income
Project Monitoring
GSEIP/ESMP
Project site
All sub project sites
Hired hands will earn
some regular income to
support themselves and
their families.
PMT members and
Consultants will visit all
project sites to ensure
compliance with country
and World Bank
requirements in ESMP
DA/Project
Management Team
Project Management
Team
No cost
implications
Compliance with
World Bank and
Ghana EPA
requirements
12,000
Page 52
50 SCHOOLS FOR EXPANSION AND REHABILITATION
ENVIRONMENTAL AND SOCIAL MANAGEMENT PLAN
Increased demand on
transport infrastructure
Project site and
environs
DA will ensure that
transport facilities and
infrastructure are
improved.
DA/Project
Management Team
Solid waste generation
School site
Waste skips will be
provided for waste
collection, to be
evacuated by DA waste
management facilities
periodically.
School
authorities/DEMC
OCCUPANCY
AND MAINTENANCE
PHASE
Liquid waste generation
GSEIP/ESMP
School site
Provision and
maintenance of suitable
toilet facilities on school
compound.
School
authorities/DEMC
Adequate transport
facilities and
infrastructure.
Proper sanitary
conditions on school
compound.
Proper sanitary
conditions on school
compound.
To be borne
by DA
To be borne
by DA
To be borne
by DA
Page 53
50 SCHOOLS FOR EXPANSION AND REHABILITATION
8.0
ENVIRONMENTAL AND SOCIAL MANAGEMENT PLAN
CONSULTATIONS
Stakeholder engagement and consultation is very important aspect of the project, as it affords the
administrative heads of the beneficiary schools the opportunity to contribute input and feedback
information aimed at strengthening the development project and avoiding negative impacts or
mitigating them where they cannot be avoided. Public participation and involvement
demonstrates to all stakeholders, that fairness and transparency has been integrated to all
aspects of the project. The involvement of stakeholders is to demonstrate the openness of the
selection process, and enriches the project value, acceptance and participation by all
stakeholders.
8.1
Objectives of Consultation
The main objectives include but are not limited to the following:

Provision of relevant and timely information about the project;

Optimizing the potential benefits of the project to the beneficiary schools;

Elimination or minimization of future long term liabilities;

Identification of probable mitigation to potential negative impacts by the affected people;

Avoidance of conflicts by addressing issues promptly;
In fulfilment of the above objectives, consultations have been held with the relevant stakeholders
to facilitate the identification of key environmental concerns associated with proposed project.
Stakeholder identification and mapping entailed a process of identifying all interest groups and
institutions that could be impacted upon by the project, and determining their interest levels,
involvement and impact on the project success.
For the SEIP, consultations began in February 2014, and will continue throughout the
implementation phase to the occupancy and maintenance phase.
8.2
Stakeholder Consultations
At this stage, consulted institutional stakeholders include:
 Heads of Beneficiary Schools
 District Chief Executives
 Environmental Protection Agency (EPA).
A list of stakeholders and persons consulted is presented as Annex A. The statuses of engagement
with these institutions are presented below.
8.2.1
Heads of Beneficiary Schools
GSEIP/ESMP
Page 54
50 SCHOOLS FOR EXPANSION AND REHABILITATION
ENVIRONMENTAL AND SOCIAL MANAGEMENT PLAN
Following the drawing up of the selection criteria for beneficiary communities, the Ministry of
Education has engaged the administrative heads of the beneficiary schools in a series of
workshops and consultations. They were informed of the financial allocation of $200,000.00 per
beneficiary school, and that they should generate a prioritized wish list of project that they need
to be executed on their school compounds. The consultants’ consultation meetings with the
school heads were only confirming what the teachers had been informed about already. Annex B
is minutes and Workshop reports.
8.2.2
District Chief Executives
The DAs, as the local government authorities, have administrative jurisdiction over the various
metropolises, municipalities and districts. Their administrative heads, known as District Chief
Executives (DCEs), have been engaged in a number of workshops by the MOE, where the steps
and activities, as well as obligations and responsibilities required of them were explained. Annex
B is minutes and Workshop reports.
They will continue to participate in the implementation of SEIP in their respective jurisdictions.
8.2.3
Environmental Protection Agency
The EPA has reviewed and approved the ESMF and RPF for the SEIF, and have published the two
documents on their website (www.epa.gov.gh). The approval has resulted in the site screening
process and the drafting of this ESMP to guide the actual implementation of the ESMF.
The implementation of SEIP also requires that individual subprojects are registered with the EPA,
using their standard Form EA 1. The EPA will then screen each individual site and give direction
as to whether or not any further assessment will be required. This registration process has been
complied with, and the subprojects are currently awaiting screening by the EPA.
Table 8.1 below is a summary of issues raised and discussed at the various locations during
consultations.
GSEIP/ESMP
Page 55
50 SCHOOLS FOR EXPANSION AND REHABILITATION
Table 8.1
No.
ENVIRONMENTAL AND SOCIAL MANAGEMENT PLAN
Summary of Issues Raised at Consultation Meetings
Comment/Concern/Question
Mitigation/Action to be Taken
1
We have some uncompleted projects on the school compound, The World Bank funding will be utilized to undertake any project from start to
and will prefer that the project funds are utilized to complete such finish. It will be used as supplement funding for any existing project.
projects.
2
Why is the project fund not given to the schools to implement as There is the need for fund accountability, and the schools cannot be given the
they deem fit?
funds to implement as they choose. The FPMU has come round to collate
schools’ prioritized list of projects, and has selected those the funds can start
and finish.
GSEIP/ESMP
Page 56
50 SCHOOLS FOR EXPANSION AND REHABILITATION
8.3
ENVIRONMENTAL AND SOCIAL MANAGEMENT PLAN
Disclosures and Public Consultation Plan
After this ESMP is approved, the PIU will ensure that it is disclosed by the World Bank on its
infoshop, by the Ghana EPA on its website and also by the Ministry of Education on its website.
Additionally, hard copies of the report will be made available at designated locations for review
by members of the general public. This will include the EPA Library at its head office in Accra and
the various EPA Regional offices, the District Assembly offices of the beneficiary metropolises,
municipalities and districts. This will enable all interested stakeholders read and understand
how they stand to be affected by the project.
A key element of sustaining stakeholders’ support in any project execution is to consult and
communicate with the stakeholders effectively and to engage them as early as possible with the
project which has been done in the course of preparation of the intervention work and further
enhanced during the preparation of this ESMP. Like any other business function, stakeholder
engagement needs to be managed and driven by a well-defined strategy. Table 8.2 below provides
a Summary of the stakeholder engagement plan.
Table 8.2: Summary of Planned Stakeholder Engagement Schedule
Activity
Stakeholders / Community
Frequency / Timeline
Pre-Construction / Prior to Project Commencement
Project email, postal address
and contact details
Fact Sheet and FAQ sheets
All stakeholders
Once-off establishment
All stakeholders
Briefings
District Assemblies,
Community members World
Bank
All stakeholders
As required, subject to any updates
on the Project
As required, subject to the
approvals process
Newsletters, Media and
Advertising
Site tours
Personal meetings
Community Sessions
Develop and disseminate
Feedback and Complaints
Mechanism and
communications procedures
Briefings, Site Tours and
Community Sessions - for
development of the
GSEIP/ESMP
Government authorities,
District Assemblies,
community, World Bank, etc.
Targeted stakeholders
Residents of affected areas/
Community and interest
groups
As required, subject to any updates
on the Project
As required
As required
As required, subject to approvals
route and feedback from the
community
All stakeholders
As required, subject to any updates
on the Project
Government authorities, Local
communities,
Prior to Work Plan approval
Page 57
50 SCHOOLS FOR EXPANSION AND REHABILITATION
ENVIRONMENTAL AND SOCIAL MANAGEMENT PLAN
Rehabilitation and Closure
• Additional relevant
Plan
stakeholders
Advertising / media release
All stakeholders
(update on milestones)
Project launch
All stakeholders
Construction and operations
Regular
Before civil works
Ongoing community liaison
Local community
Ongoing
Project updates
All stakeholders
Monthly
Responding to issues and
All stakeholders
Ongoing / as required
inquiries as per Feedback
and Complaints Mechanism
Annual reporting
All stakeholders
Annually
Personal meetings
All stakeholders
Ongoing / as required
* Budget to be determined based on profile of stakeholders, duration, location and size
GSEIP/ESMP
Page 58
50 SCHOOLS FOR EXPANSION AND REHABILITATION
9.0
ENVIRONMENTAL AND SOCIAL MANAGEMENT PLAN
CONCLUSION AND RECOMMENDATIONS
This ESMP has critically evaluated the individual sub-projects under the SEIP, having reviewed
the project documents, and taken the project location environmental and social characteristics
into account. The potential environmental and social impacts have been assessed, and are all
considered to have minimal environmental impacts, and are thus classified as Category B
projects. Appropriate mitigation measures have been designed for these impacts.
The ESMF and RPF approved by the Ghana EPA and the World Bank sets the stage for the
implementation of the project, and this ESMP is set to guide the implementation process.
The ESMP has revealed the followings with appropriate recommendations:

The proposed intervention work is most desirable because of the obvious socio-economic
benefits. These far out-weigh the negative impacts that could arise in the course of
implementation.

Priority should be given to local workers in the recruitment of unskilled labour

There is the need to carry along the community during project implementation.

Mitigation measures and management planshave been suggested and developed for the
negative impacts.

Appropriate institutional framework has been drawn up to implement the mitigation
measures and environmental management plan while the proposed monitoring
programmes shall be set in motion as soon as possible.
GSEIP/ESMP
Page 59
50 SCHOOLS FOR EXPANSION AND REHABILITATION
Annex A
S/N
1
List of Stakeholders and Persons Consulted
REGION
2
DISTRICT
EJURA SEKYEDOMASE
AMANSIE WEST
ASHANTI
3
OFFINSO MUNICIPAL
4
ADANSI NORTH DISTRICT
5
BOSOME FREHO
6
OFFINSO NORTH
7
ADANSI NORTH
8
AMANSIE CENTRAL
9
ENVIRONMENTAL AND SOCIAL MANAGEMENT PLAN
BRONG
AHAFO
PERSONS MET
ARTHUR-MANU
JOSEPH
DESIGNATION
HEADMASTER
CONTACTS
0277833519
SETH BOADU
KWAKYE
ZAINAB ADAMS
HEAD OF
SCHOOL
HEAD OF
SCHOOL
HEAD OF
SCHOOL
HEAD OF
SCHOOL
HEAD OF
SCHOOL
HEAD OF
SCHOOL
0244077713
0244513255
ANTHONY ASANTE
BABA I. SEIDU
JOSEPH OBI
FRANCIS Y.
AGORSOR
FAISAL SULEIMAN
0243721411
0244599159
0208226232
0244029861
0244248447
10
PRU
YEJI SECONDARY/TECHNICAL
SCHOOL
ALEXANDER
OPPONG-BAAH
HEAD OF
SCHOOL
HEAD OF
SCHOOL
11
BANDA
JAMAN NORTH
EMMANUEL
SAMMOR-DUAH
KYEREH-DIABOUR
AUGUSTINE
HEAD OF
SCHOOL
HEAD OF
SCHOOL
0243984552
12
13
TAIN
CECILIA J.
POGREBAH
HEAD OF
SCHOOL
0244810640
14
DORMAA WEST
BANDAMAN SENIOR HIGH
TECHNICAL SCHOOL
GOKA
SECONDARY/TECHNICAL
SCHOOL
BADU
SECONDARY/TECHNICAL
SCHOOL
NKRANKWANTA SEC/TECH
ADZAH GODWIN
MAWUENA
HEAD OF
SCHOOL
0245875409
GSEIP/ESMP
PRU
SCHOOL
SEKYEDOMASE SENIOR HIGH
SCHOOL
ESAASE BONTEFUFUO SEC.
TECHNICAL SCHOOL
ST. JEROME SENIOR HIGH
SCHOOL
FOMENA T.I AHMADIYYA
SENIOR HIGH SCHOOL
BOSOME SENIOR HIGH
TECHNICAL SCHOOL-ASIWA
NKENKAASU SECONDARY
HIGH SCHOOL
BODWESANGO SENIOR HIGH
SCHOOL
JACOBU
SECONDARY/TECHNICAL
SCHOOL
PRANG SENIOR HIGH SCHOOL
0540752358
0243022398
Page 60
50 SCHOOLS FOR EXPANSION AND REHABILITATION
15
16
WESTERN
REGION
TAIN
MENJI AGRICULTURAL SENIOR
HIGH SCHOOL
NAA F. SIGDE
ACTING
DIRECTOR
0248379602
PRESTEA HUNI VALLEY
ST. AUGUSTINE'S SENIOR
SECONDARY SEC. BOGOSO
BODI SENIOR HIGH SCHOOL
MARY YAMSON
0208154310
AKONTOMBRA SENIOR HIGH
SCHOOL
NANA BRENTU SENIOR HIGH
TECHNICAL SCHOOL
DABOASE SENIOR HIGH
TECHNICAL SCHOOL
TUNA SENIOR HIGH
SECONDARY TECH. SCHOOL
E/P SENIOR HIGH SCHOOL,
SABOBA
T.I AHMADIYYA SENIOR HIGH
SCHOOL
BUIPE SECONDARY
TECHNICAL
AWE SENIOR
SECONDARY/TECHNICAL
SCHOOL
BONGO SENIOR HIGH SCHOOL
AMOAH P.
KOBINA
DAVID YAW
OPOKU
ANTHONY IL
ISSAKA A.
MAHAMUD
GARIBA RAZAK
IBRAHIM
HEAD OF
SCHOOL
HEAD OF
SCHOOL
HEAD OF
SCHOOL
HEAD OF
SCHOOL
HEAD OF
SCHOOL
HEAD OF
SCHOOL
HEAD OF
SCHOOL
HEAD OF
SCHOOL
HEAD OF
SCHOOL
HEAD OF
SCHOOL
AZITARIGA GAAGA
A.
MARGARET L.
AKPARIBO
HEAD OF
SCHOOL
HEAD OF
SCHOOL
0203321520
REV. SR. AGNES B.
ADONGO
SEIDU TAHIRU
ANYAGRI
HEAD OF
SCHOOL
HEAD OF
SCHOOL
0267706428
17
BODI
18
SEFWI AKONTOMBRA
19
AOWIN
20
WASSA AMENFI EAST
21
22
SAWLA-TUNA-KALBA
DISTRICT
SABOBA
23
EAST GONJA DISTRICT
24
CENTRAL GONJA DISTRICT
25
NORTHERN
REGION
UPPER EAST
KASSENA NANKANA EAST
26
BONGO
27
BONGO
28
KASSENA NANKANA EAST
29
BONGO
GSEIP/ESMP
ENVIRONMENTAL AND SOCIAL MANAGEMENT PLAN
GOWRIE
SECONDARY/TECHNICAL
SCHOOL
OUR LADY OF LOURDES
SECONDARY/TECH
ZORKOR SENIOR HIGH
SCHOOL
JOSEPH ARTHUR
EMMANUEL
BOKUMA
NDEEGO J.
MATHEW
DIMBIE M.I.
0503630348
0242314962
0246665093
0243051894
0246750721
0244848567
0244795069
0202301378
0243322600
0247936644
0200334878
Page 61
50 SCHOOLS FOR EXPANSION AND REHABILITATION
30
31
NADOWLI-KALEO DISTRICT
32
JIRAPA DISTRICT
DAFFIAMA SENIOR HIGH
SCHOOL
KALEO
SECONDARY/TECHNICAL
ULLO SENIOR HIGH SCHOOL
33
WA EAST DISTRICT
FUNSI SENIOR HIGH SCHOOL
BEGYIL LUKE
AWUTU/EFUTU/SENYA
OBRACHIRE SHS
KWAMI ALORVI
35
AWUTU/EFUTU/SENYA
SENYA SHS
36
ODOBEN SHS
37
ASIKUMA/ODOBEN/BRAKW
A
ASSIN SOUTH
MENSAH ERIC
NANA
PATRICIA A. KLU
38
ASSIN NORTH
39
TWIFO HEMANG
ASSIN NORTH SENIOR HIGH
TECH. SCHOOL
JUKWA SHS
40
UPPER DENKYIRA
DIASO SHS
41
ASSIN FOSSU
ASSIN NSUTA AGRIC SHS
KETU
KLIKOR SECONDARY/TECH
SCHOOL
NTRUBOMAN SENIOR
SEC/TECH.
ADAKLU SENIOR HIGH
SCHOOL
AGOTIME SENIOR HIGH
SCHOOL
DORFOR SENIOR HIGH
SCHOOL
34
42
UPPER WEST
CENTRAL
REGION
VOLTA
REGION
DAFFIAMA/ISSA BUSSIE
ENVIRONMENTAL AND SOCIAL MANAGEMENT PLAN
43
NKWANTA
44
ADAKLU ANYIGBE
45
ADAKLU ANYIGBE
46
NORTH TONGU
GSEIP/ESMP
NYANKUMASI SHS
MARTHA R.
FUGLUU
PATRICIA G.
DIANON
GUO KILIAN
ISAAC A. K.
AMISSAH
J. N. QUAYASONFORSON
ERNEST E. A.
NOYE
PHYLLIS D. A.
ARTHURSAMPTON
AGATHA HARRY
MATHEW
KUDROHA
MICHAEL DEI
ADZIMAH
GODWIN
DRAPHOR SYLVIA
E.
AKPABLI JOSEPH
K.
HEAD OF
SCHOOL
HEAD OF
SCHOOL
HEAD OF
SCHOOL
HEAD OF
SCHOOL
HEAD OF
SCHOOL
HEAD OF
SCHOOL
HEAD OF
SCHOOL
HEAD OF
SCHOOL
HEAD OF
SCHOOL
HEAD OF
SCHOOL
HEAD OF
SCHOOL
0248666180
HEAD OF
SCHOOL
HEAD OF
SCHOOL
HEAD OF
SCHOOL
HEAD OF
SCHOOL
HEAD OF
SCHOOL
HEAD OF
SCHOOL
0244766087
0266463728
0243582757
0208914421
0542393754
0208197298
0243229791
0244025683
0242888898
0244997093
0233997093
0208172742
0208160283
0208319081
0246444116
0202930928
0248156719
0249407462
0543888583
Page 62
50 SCHOOLS FOR EXPANSION AND REHABILITATION
47
48
GREATER
ACCRA
49
50
KETU
SOME SENIOR HIGH SCHOOL
K. K. AHAFIA
ACCRA METRO
HOLY TRINITY CATH. SENIOR
HIGH SCHOOL
PRESBYTERIAN SENIOR HIGH
SCHOOL
ST. FIDELIS SENIOR HIGH
SCHOOL
WILLIAM D.
ADJAYE
BARBARA B.
PUPULAMPO
MATHIAS
ATTIMAH
ACCRA METRO
EASTERN
REGION
GSEIP/ESMP
ENVIRONMENTAL AND SOCIAL MANAGEMENT PLAN
KWAHU NORTH
HEAD OF
SCHOOL
HEAD OF
SCHOOL
HEAD OF
SCHOOL
HEAD OF
SCHOOL
0244105546
024467556
0244042214
0208528459
Page 63
50 SCHOOLS FOR EXPANSION AND REHABILITATION
Annex B
ENVIRONMENTAL AND SOCIAL MANAGEMENT PLAN
Minutes of Meetings/Workshop Reports
50 BENEFICIARY DISTRICTS AND HEADS OF SCHOOLS MEETING
Meeting Summary
Education Village
Tuesday, October 21, 2014
Pillar 1 of the Secondary Education Improvement Project (SEIP) is to increase access with equity in
senior secondary education in underserved districts. Under this pillar, intermediate result indicator
two is to increase the seats created and utilised within low performing beneficiary SHS schools.
Specifically, 50 senior high schools (SHSs) are targeted to receive facilities improvements. These
schools are also included among the 125 schools in pillar 2 that will receive quality improvements.
To begin this process, the Ministry of Education (MoE) organised a meeting with Heads of the 50
schools and the district Directors of Education for the districts where these schools are located.1 The
meeting lasted for half a day and was held on October 21, 2014 at the Education Village in East Legon,
Accra. In attendance were 44Heads of schools and 41 District Directors, as well as Ministry officials.2
The objective of the meeting was to brief the schools on the different components of their
involvement and to begin the process to collect information on which facilities needed to be upgraded.
After the opening prayer and welcome address, Mr. Wilson gave a presentation on the selection
criteria that the schools had to meet to qualify as one of the 50 schools, and stressed the importance
of a needs assessment for facilities. Mrs. Dorothy Glover followed this presentation with a briefing on
the scholarship scheme and on the School Performance Partnership Plans (SPPP). Finally, Dr.Tawiah
gave a brief on management and leadership and talked about the training that principals would
receive.3 After each presentation, any questions that participants had were addressed.4
1
See Annex I for the programme.
2
See Annex II for a list of attendees.
3
See Annex III for the presentations.
4
See Annex IV for a full list of questions and answers.
GSEIP/ESMP
Page 64
50 SCHOOLS FOR EXPANSION AND REHABILITATION
ENVIRONMENTAL AND SOCIAL MANAGEMENT PLAN
District Directors Attendees
Region
Ashanti
Ashanti
Ashanti
Ashanti
Ashanti
Ashanti
Ashanti
BrongAhafo
BrongAhafo
BrongAhafo
BrongAhafo
BrongAhafo
Central
Central
Central
Central
Eastern
Greater
Accra
Northern
Northern
Northern
Northern
Upper East
Upper East
Volta
Volta
Volta
Volta
Western
Western
Western
District
ADANSI NORTH
AMANSIE CENTRAL
AMANSIE WEST
BOSOME FREHO
EJURA SEKYIDOMASE
OFFINSO MUNICIPAL
OFFINSO NORTH
BANDA
DORMAA WEST
JAMAN NORTH
PRU
TAIN
ASIKUMA-ODOBEN-BRAKWA
ASSIN NORTH MUNICIPAL
ASSIN SOUTH
TWIFO HEMANG-LOWER DENKYIRA
AFRAM PLAINS (KWAHU NORTH)
ACCRA METROPOLITAN
District Director
PAUL ANTWI OPPONG
JOSEPH K. AGYEMANG
SAMUEL KENA
GEORGINA ENYAH
JOSEPH K. APPIAH
FRANK YAW MUSAH
SIMON ODEI NYARKO
EMIL ASIEDU-BOACHIE
ISAAC NSIAH EDWARDS
ASUBONTENG KWASI
EMML EFFAH-SAKYI
NAA F. SIGDE
MARTHA ACQUAH
PHIL A.A. BAIDOO
ANNA B. BAIDOO
NANA S.A.B. AIDOO
ELIZABETH AMANKWA
ANGELA TENA MENSAH
CENTRAL GONJA
EAST GONJA
SABOBA
SAWLA-TUNA-KALBA
BONGO
KASSENA-NANKANA MUNICIPAL
AGORTIME ZIOPE
KETU SOUTH
NKWANTA SOUTH
NORTH TONGU (NEW)
AOWIN
BODI
PRESTEA HUNI VALLEY
ALICE A. NAWURI
ADAM SEIDU DAUDA
GEORGINA ANABA-N.
FRANK AFLAMPUI
MBELA PADMORE
AUGUSTINE G. AYIREZANG
REV. SEVOR SAMUEL
FRED P.K. DUNYOH
MAXWELL H. GBAKAH
ALEX GODZI
ALHAJI A. SOPHINA
JOHN OPPONG ACKAH
KYERE BOATENG
Heads of Schools Attendees
Region
District
School Name
Ashanti
ADANSI NORTH
Ashanti
ADANSI NORTH
Ashanti
AMANSIE CENTRAL
BODWESANGO SENIOR HIGH
SCHOOL
FOMENA T.I AHMADIYYA SENIOR
HIGH SCHOOL
JACOBU SECONDARY/TECHNICAL
SCHOOL
GSEIP/ESMP
Head of
School
JOSEPH OBI
ZAINAB
ADAMS
FRANCIS Y.
AGORSOR
Page 65
50 SCHOOLS FOR EXPANSION AND REHABILITATION
ENVIRONMENTAL AND SOCIAL MANAGEMENT PLAN
Ashanti
AMANSIE WEST
Ashanti
BOSOME FREHO
Ashanti
Ashanti
EJURA
SEKYIDOMASE
OFFINSO
MUNICIPAL
OFFINSO NORTH
BrongAhafo
BANDA
BrongAhafo
DORMAA WEST
NKRANKWANTA SEC/TECH
BrongAhafo
JAMAN NORTH
BrongAhafo
PRU
GOKA SECONDARY/TECHNICAL
SCHOOL
PRANG SENIOR HIGH SCHOOL
BrongAhafo
PRU
YEJI SECONDARY/TECHNICAL
SCHOOL
BrongAhafo
TAIN
Central
ASIKUMA-ODOBENBRAKWA
ASSIN NORTH
MUNICIPAL
BADU SECONDARY/TECHNICAL
SCHOOL
ODOBEN SENIOR HIGH SCHOOL
Ashanti
Central
ESAASE BONTEFUFUO SEC.
TECHNICAL SCHOOL
BOSOME SENIOR HIGH TECHNICAL
SCHOOL-ASIWA
SEKYEDOMASE SENIOR HIGH
SCHOOL
ST. JEROME SENIOR HIGH SCHOOL
NKENKAASU SECONDARY HIGH
SCHOOL
BANDAMAN SENIOR HIGH
TECHNICAL SCHOOL
ASSIN NORTH SENIOR HIGH
TECHNICAL SCHOOL
Central
ASSIN SOUTH
Central
ASSIN SOUTH
Central
AWUTU-SENYA
ASSIN NSUTA AGRIC. SENIOR HIGH
SCHOOL
NYANKUMASI AHENKRO SENIOR
HIGH SCHOOL
OBRACHIRE SECONDARY/TECHNICAL
Central
AWUTU-SENYA
SENYA SENIOR HIGH SCHOOL
Central
UPPER DENKYIRA
WEST
DIASO SENIOR HIGH SCHOOL
Eastern
AFRAM PLAINS
(KWAHU NORTH)
ACCRA
METROPOLITAN
ACCRA
METROPOLITAN
CENTRAL GONJA
S.T. FIDELIS SENIOR HIGH TECH.
SCHOOL
HOLY TRINITY CATH. SENIOR HIGH
SCHOOL
PRESBYTERIAN SENIOR HIGH
SCHOOL-OSU
BUIPE . SECONDARY TECHNICAL
SCHOOL
Greater
Accra
Greater
Accra
Northern
GSEIP/ESMP
K. A. OPOKU
ANTHONY
ASANTE
ARTHURMANU JOSEPH
SETH BOADU
KWAKYE
BABA I. SEIDU
EMMANUEL
SAMMORDUAH
ADZAH
GODWIN
MAWUENA
KYEREHDIABOUR
FAISAL
SULEIMAN
ALEXANDER
OPPONGBAAH
CECILIA J.
POGREBAH
PATRICIA A.
KLU
J.N.
QUAYSONFORSON
AGATHA
HARRY
ISAAC A.K.
AMUSSAH
KWAMI
ALORVI
MENSAH ERIC
NANA
PHYLLIS D.A.
ARTHURSAMPTON
MATHIAS
ATTIMAH
WILLIAM D.
ADJAYE
BARBARA B.
PUPLAMPU
ISSAKA A.
MAHAMUD
Page 66
50 SCHOOLS FOR EXPANSION AND REHABILITATION
ENVIRONMENTAL AND SOCIAL MANAGEMENT PLAN
Northern
EAST GONJA
Northern
SABOBA
T. I. AHMADIYYA SENIOR HIGH
SCHOOL
E/P SENIOR HIGH SCHOOL, SABOBA
Northern
Upper East
SAWLA-TUNAKALBA
BONGO
TUNA SENIOR HIGH SECONDARY
TECHNICAL SCHOOL
BONGO SENIOR HIGH SCHOOL
Upper East
BONGO
Upper East
BONGO
GOWRIE SECONDARY/TECHNICAL
SCHOOL
ZORKOR SENIOR HIGH SCHOOL
Upper East
KASSENA-NANKANA
MUNICIPAL WEST
OUR LADY OF LOURDES
SECONDARY/TECHNICAL
Upper East
Volta
KASSENA-NANKANA
WEST MUNICIPAL
ADAKLU
AWE SENIOR
SECONDARY/TECHNICAL SCHOOL
ADAKLU SENIOR HIGH SCHOOL
Volta
AGORTIME ZIOPE
AGOTIME SENIOR HIGH SCHOOL
Volta
KETU SOUTH
Volta
Volta
Volta
Western
KETU SOUTH
NKWANTA SOUTH
NORTH TONGU
(NEW)
AOWIN
KLIKOR SECONDARY/TECHNICAL
SCHOOL
SOME SENIOR HIGH SCHOOL
NTRUBOMAN SENIOR HIGH SCHOOL
DORFOR SENIOR HIGH SCHOOL
Western
BODI
NANA BRENTU SENIOR HIGH
TECHNICAL SCHOOL
BODI SENIOR HIGH SCHOOL
Western
PRESTEA HUNI
VALLEY
ST. AUGUSTINE'S SENIOR
SECONDARY SEC. BOGOSO
Western
SEFWI
AKONTOMBRA
AKONTOMBRA SENIOR HIGH
SCHOOL
GSEIP/ESMP
DIMBIE M. I.
NDEEGO J.
MATTHEW
EMMANUEL
BOKUMA
AZITARIGA
GAAGA A.
MARGARET L.
AKPARIBO
SEIDU TAHIRU
ANYAGRI
REV. SR.
AGNES B.
ADONGO
GARIBA RAZAK
I.
ADZIMAH
GODWIN
DRAPHOR
SYLVIA E.
MATTHEW
KUDROHA
K. K. AHAFIA
MICHAEL DEI
AKPABLI
JOSEPH K.
DAVID YAW
OPOKU
JOSEPH
ARTHUR
PETER
DICKSON
MENSAH
AMOAH P.
KOBINA
Page 67
50 SCHOOLS FOR EXPANSION AND REHABILITATION
ENVIRONMENTAL AND SOCIAL MANAGEMENT PLAN
50 + 23 BENEFICIARY DISTRICTS AND HEADS OF SCHOOLS ORIENTATION
Orientation Report
Education Village, Accra
Friday, November 7, 2014
Pillar 1 of the Secondary Education Improvement Project (SEIP) is to increase access with equity in
senior secondary education in underserved districts. Under this pillar, intermediate result indicator
two is to increase the seats created and utilised within low performing beneficiary SHS schools.
Specifically, 50 senior high schools (SHSs) are targeted to receive facilities improvements. These
schools are also included among the 125 schools in pillar 2 that will receive quality improvements.
Pillar 2 of the Secondary Education Improvement Project (SEIP) is to improve quality in low performing
senior high schools. These quality improvements come in the form of teacher training in Math and
Science, increasing completion rates, creating School Performance Partnership Plans (SPPPs) for
learning, and implementing ICT packages. Specifically, 125 senior high schools (SHSs) are targeted to
receive facilities improvements broken down into two groups: 75 schools receive only quality
improvements, while 50 schools receive both quality improvements and facilities improvements.
To begin this process, the Ministry of Education (MoE) organised an orientation with Heads of the 50
schools and the district Directors of Education for the districts where these schools are located.5 The
meeting was held on November 7, 2014 at the Education Village in East Legon, Accra. In attendance
were 41 Heads of schools and 17 District Directors, as well as District Chief Executives and Municipal
Chief Executives, and Ghana Education and MoE officials.6
The objective of the meeting was to brief the schools on the different components of their
involvement for both facilities upgrades and quality improvements. After the opening prayer and
welcome address7, presentations were given on the overview of the project, selection of beneficiaries,
iCampus and ICT based instruction, the school profile website and online monitoring tool, Math and
Science curriculum, the results framework and disbursement linked indicators, disbursement
guidelines, procurement, leadership, safeguards issues, and guidelines for new construction.8 After
each presentation, any questions that participants had were addressed.9
5
See Annex I for the programme.
6
See Annex II for a list of District Director and school Head attendees.
7
See Annex III for the welcome address.
8
See Annex V for the presentations.
9
See Annex IV for a full list of questions and answers.
GSEIP/ESMP
Page 68
50 SCHOOLS FOR EXPANSION AND REHABILITATION
ENVIRONMENTAL AND SOCIAL MANAGEMENT PLAN
: Attendees: District Directors Attendees
Region
District
District Director - name
Ashanti
Ashanti
BrongAhafo
BrongAhafo
Central
Central
Central
Eastern
Greater
Accra
Northern
Upper West
Upper West
Volta
Volta
Volta
Western
Western
AMANSIE CENTRAL
OFFINSO NORTH
DORMAA WEST
TAIN
ASSIN NORTH MUNICIPAL
ASSIN SOUTH
TWIFO HEMANG-LOWER DENKYIRA
AFRAM PLAINS (KWAHU NORTH)
ACCRA METROPOLITAN
JOSEPH K. AGYEMANG
SIMON ODEI NYARKO
ISAAC NSIAH EDWARDS
NAA F. SIGDE
PHIL A.A. BAIDOO
ANNA B. BAIDOO
NANA S.A.B. AIDOO
ELIZABETH AMANKWA
ANGELA TENA MENSAH
SABOBA
JIRAPA
NADOWLI
ADAKLU
AGOTIME ZIOPE
NORTH TONGU (NEW)
AOWIN
SEFWI AKONTOMBRA
GEORGINA ANABA-N.
DOMINICA DASSAH
VALENTINE D SHERIFF
SAMUEL A DORFE
REV. SEVOR SAMUEL
ALEX GODZI
ALHAJI A. SOPHINA
DAVID AKOLWIN AGATIBA
Heads of Schools Attendees
Region
District
Ashanti
Ashanti
ADANSI NORTH
ADANSI NORTH
Ashanti
AMANSIE
CENTRAL
BOSOME FREHO
Ashanti
Ashanti
EJURA
SEKYIDOMASE
Ashanti
OFFINSO
MUNICIPAL
Ashanti
OFFINSO NORTH
BrongAhafo BANDA
BrongAhafo
BrongAhafo
BrongAhafo
BrongAhafo
BrongAhafo
GSEIP/ESMP
DORMAA WEST
JAMAN NORTH
PRU
PRU
TAIN
School Name
BODWESANGO SENIOR HIGH SCHOOL
FOMENA T.I AHMADIYYA SENIOR HIGH
SCHOOL
JACOBU SECONDARY/TECHNICAL
SCHOOL
BOSOME SENIOR HIGH TECHNICAL
SCHOOL-ASIWA
SEKYEDOMASE SENIOR HIGH SCHOOL
Head/Assistant Head of
School
JOSEPH OBI
ZAINAB ADAMS
FRANCIS Y. AGORSOR
ANTHONY ASANTE
ARTHUR-MANU JOSEPH
ST. JEROME SENIOR HIGH SCHOOL
SETH BOADU KWAKYE
NKENKAASU SECONDARY HIGH SCHOOL
BANDAMAN SENIOR HIGH TECHNICAL
SCHOOL
NKRANKWANTA SEC/TECH
GOKA SECONDARY/TECHNICAL SCHOOL
PRANG SENIOR HIGH SCHOOL
YEJI SECONDARY/TECHNICAL SCHOOL
BADU SECONDARY/TECHNICAL SCHOOL
BABA I. SEIDU
EMMANUEL SAMMORDUAH
ADZAH GODWIN MAWUENA
KYEREH-DIABOUR
FAISAL SULEIMAN
ALEXANDER OPPONG-BAAH
CECILIA J. POGREBAH
Page 69
50 SCHOOLS FOR EXPANSION AND REHABILITATION
BrongAhafo TAIN
Central
Central
ASIKUMAODOBENBRAKWA
ASSIN NORTH
MUNICIPAL
ASSIN SOUTH
Central
ASSIN SOUTH
Central
Central
AWUTU-SENYA
TWIFO
HEMANGLOWER
DENKYIRA
UPPER
DENKYIRA WEST
AFRAM PLAINS
(KWAHU
NORTH)
ACCRA
METROPOLITAN
ACCRA
METROPOLITAN
CENTRAL GONJA
EAST GONJA
SABOBA
SAWLA-TUNAKALBA
BONGO
BONGO
Central
Central
Eastern
Greater
Accra
Greater
Accra
Northern
Northern
Northern
Northern
Upper East
Upper East
Upper East
Upper East
Upper East
Volta
Volta
Volta
Volta
Volta
GSEIP/ESMP
BONGO
KASSENANANKANA
MUNICIPAL
WEST
KASSENANANKANA WEST
MUNICIPAL
ADAKLU
AGORTIME
ZIOPE
KETU SOUTH
KETU SOUTH
NKWANTA
SOUTH
ENVIRONMENTAL AND SOCIAL MANAGEMENT PLAN
MENJI AGRICULTURAL SENIOR HIGH
SCHOOL
ODOBEN SENIOR HIGH SCHOOL
NAA F. SIGDE (Director
Acting)
PATRICIA A. KLU
ASSIN NORTH SENIOR HIGH TECHNICAL
SCHOOL
ASSIN NSUTA AGRIC. SENIOR HIGH
SCHOOL
NYANKUMASI AHENKRO SENIOR HIGH
SCHOOL
OBRACHIRE SECONDARY/TECHNICAL
JUKWA SENIOR HIGH SCHOOL
J.N. QUAYSON-FORSON
DIASO SENIOR HIGH SCHOOL
PHYLLIS D.A. ARTHURSAMPTON
MATHIAS ATTIMAH
S.T. FIDELIS SENIOR HIGH TECH. SCHOOL
AGATHA HARRY
ISAAC A.K. AMISSAH
KWAMI ALORVI
ERNEST E.A. NOYE
HOLY TRINITY CATH. SENIOR HIGH
SCHOOL
PRESBYTERIAN SENIOR HIGH SCHOOLOSU
BUIPE . SECONDARY TECHNICAL SCHOOL
T. I. AHMADIYYA SENIOR HIGH SCHOOL
E/P SENIOR HIGH SCHOOL, SABOBA
TUNA SENIOR HIGH SECONDARY
TECHNICAL SCHOOL
BONGO SENIOR HIGH SCHOOL
GOWRIE SECONDARY/TECHNICAL
SCHOOL
ZORKOR SENIOR HIGH SCHOOL
OUR LADY OF LOURDES
SECONDARY/TECHNICAL
WILLIAM D. ADJAYE
AWE SENIOR SECONDARY/TECHNICAL
SCHOOL
GARIBA RAZAK I.
ADAKLU SENIOR HIGH SCHOOL
AGOTIME SENIOR HIGH SCHOOL
ADZIMAH GODWIN
DRAPHOR SYLVIA E.
KLIKOR SECONDARY/TECHNICAL SCHOOL
SOME SENIOR HIGH SCHOOL
NTRUBOMAN SENIOR HIGH SCHOOL
MATTHEW KUDROHA
K. K. AHAFIA
MICHAEL DEI
BARBARA B. PUPLAMPU
ISSAKA A. MAHAMUD
DIMBIE M. I.
NDEEGO J. MATTHEW
EMMANUEL BOKUMA
AZITARIGA GAAGA A.
MARGARET L. AKPARIBO
SEIDU TAHIRU ANYAGRI
REV. SR. AGNES B. ADONGO
Page 70
50 SCHOOLS FOR EXPANSION AND REHABILITATION
Volta
Western
Western
GSEIP/ESMP
NORTH TONGU
(NEW)
BODI
PRESTEA HUNI
VALLEY
ENVIRONMENTAL AND SOCIAL MANAGEMENT PLAN
DORFOR SENIOR HIGH SCHOOL
AKPABLI JOSEPH K.
BODI SENIOR HIGH SCHOOL
ST. AUGUSTINE'S SENIOR SECONDARY
SEC. BOGOSO
JOSEPH ARTHUR
PETER DICKSON MENSAH
Page 71
Download