Nitrogen Management Practice
Grant Agreement - Part A
BACKGROUND
The Department has agreed to provide Grant Funding to NQ Dry Tropics for payment to the Proponent to undertake
various activities to improve nitrogen use management practices to meet the Project Objectives.
The Proponent is strongly encouraged to seek independent professional agronomic advice to best suit the unique
circumstances and needs of its farming system.
The parties wish to record the terms and conditions of their Agreement.
HOW THIS AGREEMENT WORKS
This Agreement is comprised of:
(a) Part A – these specific Project Activity details, including:





The execution page
Schedule 1 - Grant Contract Details
Schedule 2 - Payment Details
Schedule 3 - Deliverables
Schedule 4 - Farm Details
(b) Part B – Grant Contract terms and conditions Version 1.0 September 2015 which is available
at https://goo.gl/aLuOX7
DEFINED TERMS
Unless the contrary intention is expressed, capitalised terms in this Part A are defined in clause 3 of Part B.
RTS15-XXXX - Nitrogen Management Practice
Page 2 of 8
Grant Agreement - Part A
EXECUTED AS AN AGREEMENT
NQ DRY TROPICS EXECUTION
EXECUTED for and on behalf of NQ Dry Tropics LTD, ACN 101 770 601 pursuant to Section 126 or 127 of the Corporations Act 2001 (Cth)
______________________________________________________
(Signature of Authorised Signatory)
______________________________________________________
(Name of Authorised Signatory)
In the presence of:
______________________________________________________
(Signature of witness)
______________________________________________________
(Name of witness)
______________________________________________________
(Date)
PROPONENT EXECUTION
EXECUTED for and on behalf of the Proponent by its representative who has full power of authority to enter into, perform and observe its
obligations under this agreement.
Entity name, ABN xxxx
______________________________________________________
(Signature of Authorised Signatory)
______________________________________________________
(Name of Authorised Signatory)
In the presence of:
______________________________________________________
(Signature of witness)
______________________________________________________
(Name of witness)
______________________________________________________
(Date)
RTS15-XXXX - Nitrogen Management Practice
Page 3 of 8
Grant Agreement - Part A
SCHEDULE 1 - GRANT CONTRACT DETAILS
NQ Dry Tropics
Organisation name:
ABN/ACN:
GST Registered:
Phone:
Key Contact:
Key Contact Email:
Mailing Address line 1:
Mailing Suburb:
Mailing State:
Mailing Postcode:
NQ Dry Tropics Ltd
18 101 770 601
Yes
07 4724 3544
Peter Gibson
peter.gibson@nqdrytropics.com.au
PO Box 1466
Townsville
QLD
4810
Proponent
Organisation name:
ABN/ACN:
GST Registered:
Phone:
Email:
Key Contact:
Key Contact Email:
Address line 1:
Suburb:
State:
Postcode:
Project Activity Description
Proponent will perform the Project Activity to achieve the Proposed Nitrogen Application of <INSERT PROPOSED
TARGET VALUE> as outlined in Schedule 4.
Proponent will receive payments of Grant Funding as specified in Schedule 2 (Payment Schedule) to improve its
nitrogen management practice as set out in Schedule 3.
Completion Date
30/06/2018
Special Contract Conditions
Nothing to display.
RTS15-XXXX - Nitrogen Management Practice
Page 4 of 8
Grant Agreement - Part A
SCHEDULE 2 - PAYMENT SCHEDULE
Title
1. Sign and return the Agreement and Deliverables to NQ Dry Tropics
Amount
20% of grant
amount
Due Date
On signing the
contract
2. Carry out the project as per Project Activity Description and complete
2016/2017 Milestone activities, as described in Schedules 3 and 4
40% of grant
amount
28/02/2017
3. Carry out the project as per Project Activity Description and complete
2017/2018 Milestone activities, as described in Schedules 3 and 4
40% of grant
amount
28/02/2018
TOTAL FUNDING GST Excluded
$xxxxx
RTS15-XXXX - Nitrogen Management Practice
Page 5 of 8
SCHEDULE 3 – DELIVERABLES
Project Activity
Description:
To improve nitrogen and irrigation management practices on the Farm (or Farms). [For projects with more than 1 Farm insert additional
tables at Schedule 4]
Project Activity ID:
RTS15- XXX
Project Activity
Name:
Farmers last name – Nitrogen and irrigation management project
Activities
Deliverable(s)/Output code(s)
2015 / 2016
Milestones
Provision, and acceptance (by NQ Dry Tropics), of the following documents and/or data for the Farm
(or Farms):
Development of
Agreement
Completion Date
Payments
(GST excl)
On Signing of Grant
Contract
20% of
Grant
Funding
28 February 2017
40% of
Grant
Funding
 Grant Contract signed;
 Evidence of the amount of fertiliser applied to the cane crops for the calendar years 2013,
2014 and 2015;
 Records of mill by-product application in the past 3 - 5 years (if applicable);
 Completed practice survey form as provided by NQ Dry Tropics;
 Signed consent form for WILMAR to provide NQ Dry Tropics with yield data from harvest
years 2013 to 2018; and
 A valid tax invoice.
2016 / 2017
Milestones
Provision, and acceptance (by NQ Dry Tropics), of the following documents and/or data for the Farm
(or Farms):

Receipts of purchase as evidence of the amount of fertiliser purchased and applied to the
cane crops for the calendar year 2016;

Delivery receipts and / or purchase receipts for calendar year 2016 regarding other sources
of nitrogen (e.g. mill by-products and legume crop seeds);

Receipts of drip or overhead irrigation equipment and installation invoices (if applicable);

Completed fertiliser activity form and practice change survey for the Farm (or Farms) as
provided by NQ Dry Tropics for calendar year 2016; and

A valid tax invoice.
RTS15-XXXX - Nitrogen Management Practice
(This date may vary
depending on the
specific project
proposal)
Page 6 of 8
SCHEDULE 3 – DELIVERABLES
Submission of:
 A warranty declaring that all Minimum Standards of Management Practice are in place on
the Farm (or Farms) and will be in place for the duration of the Agreement (Minimum
Standards are defined in Part B); and
1 year from
Commencement
Date
Nil
payment
28 February 2018
40% of
Grant
Funding
 A certificate or acknowledgment from Queensland Canegrowers Organisation Ltd that the
three Smartcane BMP modules have been completed.
2017 / 2018
Milestones
Provision and verification (by NQ Dry Tropics) of the following documents and/or data for the Farm
(or Farms):

Receipts of purchase as evidence of the amount of fertiliser purchased and applied to the
cane crops for the calendar year 2017;

Delivery receipts and / or purchase receipts for calendar year 2017 regarding other sources
of nitrogen (e.g. mill by-products and legume crop seeds);

Receipts of drip or overhead irrigation equipment and installation invoices (if applicable);

Completed fertiliser activity form and practice change survey for the Farm (or Farms) as
provided by NQ Dry Tropics for calendar year 2017; and

Completed nutrient management plan using the Six Easy Steps program.

A valid tax invoice.
Provision of the following documents and/or data for the Farm (or Farms):
(This date may vary
depending on the
specific project
proposal)
30 June 2018
Nil
payment
Total (GST excl.)
$
Total GST amount
$
Total (GST incl.)
$
 Receipts of purchase as evidence of the amount of fertiliser purchased and applied to the
cane crops for the year to date for calendar year 2018;
 Delivery receipts and / or purchase receipts for the year to date for calendar year 2018
regarding other sources of nitrogen (e.g. mill by-products and legume crop seeds); and
 Completed fertiliser activity form for the Farm (or Farms) as provided by NQ Dry Tropics for
calendar year 2018.
Proponents must obtain, keep and provide necessary reports and/or Records to meet requirements
of the Agreement. The Proponents are obliged to keep such Records for a period of no less than 7
years after the end of the Agreement.
RTS15-XXXX - Nitrogen Management Practice
Page 7 of 8
SCHEDULE 4 – FARM DETAILS
[to be extracted from information provided by the Department and inserted at contract creation]
Item
number
Description
1.
Farm name
2.
Project Activity Area
ha
3.
Baseline Nitrogen applied
Kg Nitrogen / year
4.
Proposed Nitrogen application
Kg Nitrogen / year
5.
Proposed area to be converted to drip irrigation
ha
6.
Proposed area to be converted to overhead irrigation
ha
7.
Map of farm location
Details
Attach an additional table for each Farm addressed in this Project
RTS15-XXXX - Nitrogen Management Practice
Page 8 of 8
Download