BI-ANNUAL PERFORMANCE EVALUATION REPORT OF THE TULBAGH BULK WATER SUPPLY SCHEME WITZENBERG LOCAL MUNICIPALITY WESTERN CAPE CHIEF DIRECTORATE: BULK INFRASTRUCTURE PROGRAMME PERIOD: 01 APRIL 2014 – 30 SEPTEMBER 2014 i REGIONAL BULK INFRASTRUCTURE PROGRAMME SEPTEMBER 2014 TABLE OF CONTENTS 1. 2. 3. 4. 5. 6. INTRODUCTION ............................................................................................................. 1 BACKGROUND .............................................................................................................. 1 2.1 Description of project........................................................................................... 1 2.2 Project history ..................................................................................................... 3 2.3 Project concept, design and plan ........................................................................ 3 2.4 Start date – duration of the programme ............................................................... 5 2.5 Funds allocated to the project ............................................................................. 6 PROGRESS TO DATE ................................................................................................... 7 3.1 Milestones ........................................................................................................... 7 3.2 Implementation of the approved business plan...................................................11 3.3 Schedules of work and phasing of the activities .................................................11 3.4 Risks taken and management thereof ................................................................12 3.5 Capacities dedicated to the programme .............................................................13 3.6 Key challenges within the project .......................................................................13 PROJECT RESULTS AND BENEFICIARIES ............................................................... 13 4.1 Outcomes and outputs .......................................................................................13 4.2 Beneficiaries and project results .........................................................................14 4.3 Jobs created ......................................................................................................14 CONCLUSIONS / LESSONS LEARNED ...................................................................... 14 5.1 Main successes and failures of the project to date .............................................14 5.2 Ownership and sustainability of infrastructure works ..........................................15 RECOMMENDATIONS ................................................................................................. 15 ANNEXURE A: PROJECT IMPLEMENTATION PHOTOS .................................................. 16 ANNEXURE C: DETAILS OF CONTRACTS ....................................................................... 18 ANNEXURE D: PROJECT SCHEDULE .............................................................................. 19 ANNEXURE E: DETAILS OF JOB OPPORTUNITIES......................................................... 20 1 REGIONAL BULK INFRASTRUCTURE PROGRAMME 1. DECEMBER 2014 INTRODUCTION In terms of Section 10(7)(b) of the Division of Revenue Act No 10 of 2014 (DORA) as promulgated in Government Gazette No 37595 dated 26 April 2014, the transferring national officer must submit an annual performance report for Schedule 6 within 45 days after the end of each quarter. The Regional Bulk Infrastructure Grant (RBIG) is a Schedule 6 indirect conditional grant for the benefit in kind of municipalities. The objective of this Report is to provide a performance evaluation report covering the 1st and 2nd quarters of RBIG funded projects, in compliance with the DORA. The objective of this evaluation was to determine whether the progress on the project is commensurate with the expenditure to date as well as to determine whether the project is still on course in terms of the original planning. This performance evaluation report, covering quarters 1 and 2 of the 2014/15 fiscal year, is for the Tulbagh Bulk Water Supply Scheme, funded by inter alia the Regional Bulk Infrastructure Grant, currently being implemented by the Witzenberg Local Municipality in the Western Cape Province. 2. BACKGROUND 2.1 Description of project The Witzenberg Local Municipality (LM), founded in 2000, is classified as a Category B municipality and is responsible for basic service provision to the demarcated municipal area that includes the towns of Ceres, Tulbagh, Prince Alfred’s Hamlet, Wolseley and Op Die Berg. The main municipal office, which serves as a local administrative and commercial capital for the area, is situated in Ceres, in the Western Cape, approximately 130 km North to North east of Cape Town. Regional alternative water resources were evaluated and the long term solutions involve various smaller schemes to be implemented in conjunction with each other. The upgrading involved various sub – projects including the following: TULBAGH New shared bulk pipeline from Klein Berg River Own (municipal) bulk pipeline and bulk storage capacity Upgrade of water treatment facilities and various small bulk infrastructure components Additional water resources from Schalkenbosch tributaries. WOLSELEY Shared Storage capacity Bulk supply pipeline between storage dam and Wolseley New pump station and various upgrades of existing pump stations and water treatment facilities 2 REGIONAL BULK INFRASTRUCTURE PROGRAMME DECEMBER 2014 PA HAMLET Upgrade of existing bulk pipeline in association with Koekedouw Dam management committee New pump station and supply line. Witzenberg LM comprises an area of 2 851 km2 and borders the Bergrivier Municipality in the west, the Breede River Municipality in the east, the Breede Valley Municipality to the south, the Cederberg Municipality to the north and northwest, Drakenstein Municipality to the southwest and the West Coast District Municipality to the west as shown in Figure 1. The projects reported on in this report provide water to all the citizens of Tulbagh, Wolseley and PA Hamlet. In addition, co-funding also allows for the assurance of supply to the farming areas in Tulbagh and PA Hamlet, where infrastructure is shared. Figure 1: Locality: Witzenberg Municipal Area The PAH and Wolseley parts of the project is situated in the Breede-Gouritz water management area, while the Tulbagh part of the project is situated in the Berg-Olifants water management area. The latitude/longitude co-ordinates of the projects are as follows: TULBAGH New shared bulk pipeline from Klein Berg River (19° 09' 17.29'' E; 33° 12' 30.53''S to 19° 08' 54.31'' E; 33° 15' 49.42'' S). Own (municipal) bulk pipeline (19° 08' 54.31'' E; 33° 15' 49.42'' S to 19° 9'53.84"E; 33°17'14.57"S) and bulk storage capacity (19° 09' 12.45''E; 33° 16' 12.10'' S). Upgrade of water treatment facilities and various small bulk infrastructure components (19° 8'47.65"E; 33°17'10.92"S). 3 REGIONAL BULK INFRASTRUCTURE PROGRAMME Additional water 33°18'11.57"S). resources from DECEMBER 2014 Schalkenbosch tributaries. (19°11'53.76"E; WOLSELEY Shared Storage capacity (19° 13' 20.94’’S; 33° 24' 38.72''E). Bulk supply pipeline between storage dam and Wolseley (19° 13' 20.94'' S; 33° 24' 38.72' 'E to 33° 24' 47.14" S; 19° 12' 30.72" E). New pump station and various upgrades of existing pump stations and water treatment facilities (19°12'8.82"E; 33°24'33.15"S). PA HAMLET Upgrade of existing bulk pipeline in association with Koekedouw Dam management committee (33° 21' 45.66'' S; 19° 16' 27.34'' E to 33° 21' 30.76'' S; 19° 16' 57.69'' E) New pump station and supply line. 2.2 Project history The drought experienced during 2004 and 2005 resulted in serious water problems for Tulbagh. A preliminary bulk water study (March 2005) concluded that none of the “local” water resources provide a long term sustainable solution for the future water requirements of Tulbagh specifically. The 2005 study was followed by an investigation in the available water resources for all the towns in the Witzenberg management area. This study (Witzenberg Water Management, June 2008) concluded that not only Tulbagh, but also Wolseley and Prince Alfred Hamlet were not in a situation to allow any further developments due to limited water resources. 2.3 Project concept, design and plan TULBAGH Tulbagh: New shared bulk pipeline from Klein Berg River Taking the technical information into account it is recommended that a low pressure 3 750 m long GRP pipeline with diameters varying between 700 – 400 mmØ be constructed, with associated diversion structures, jointly between the Tulbagh Water Users Association and the Witzenberg Municipality. Tulbagh: Own (municipal) bulk pipeline and bulk storage capacity A pipeline with a diameter of 500 mm and a length of approximately 6 700 m will convey the water from the off-take point provided by the joint pipeline to the existing bulk storage dams of Tulbagh and the water treatment works in Tulbagh. The project will include some upgrade works to the existing diversion structure in the Klein Berg River and an additional bulk storage capacity of 750 000 m3, with a booster pump station. The main purpose of this project is to divert mainly winter flows at a maximum rate of 120 l/s, from the Klein Berg River to the storage dams. 4 REGIONAL BULK INFRASTRUCTURE PROGRAMME DECEMBER 2014 Tulbagh: Upgrade of water treatment facilities and various small bulk infrastructure components This project involves the upgrade of existing sand filters and the construction of an additional filter. Upgrade also needs to be done to existing booster pump stations and infrastructure linking the existing bulk storage capacities with the water treatment facilities. Bulk water meters also need to be installed as part of the upgrade. Tulbagh: Schalkenbosch tributaries As an emergency measure, worked already started in 2006 on the construction of infrastructure to include the water from three tributaries of the Klein Berg River, situated just to the south of Tulbagh. The completion of this project includes the construction and upgrade of two diversion structures and various pipeline sections 200 mm in diameter. Water will be diverted through a number of pipe sections to the existing storage dams at Tulbagh. The project involves the cooperation with a local farmer, who also uses certain sections of the pipeline for his own irrigation purposes. WOLSELEY Wolseley: Storage capacity A bulk storage reservoir with a capacity of 5 Mℓ will be constructed. Wolseley: Bulk supply pipeline between storage dam and Wolseley The project includes the construction of 1630 m long x 355 mm diameter bulk pipeline, linking the storage reservoir with the main distribution network in Wolseley. Wolseley: Pump stations and treatment works The project involves the construction of a new 30 kW pump station with a capacity of 58.8 ℓ/s and the upgrade of an existing pump station at Witbrug. A pipeline, 500 m long, with a diameter of 200 mm and upgrade (new chlorination) to existing treatment facilities is included in this project. PA HAMLET PA Hamlet: Upgrade of bulk supply line Water will be supplied to PA Hamlet from an existing bulk irrigation line which supplies water from the Koekedouw Dam to a number of irrigators near PA Hamlet. The project requires the upgrade of the existing 900 mm diameter pipeline to ensure a safe supply and to ensure a delivery of 54 ℓ/s at the off-take point. 5 REGIONAL BULK INFRASTRUCTURE PROGRAMME DECEMBER 2014 PA Hamlet: Pump station and supply line Water abstracted from the irrigation pipeline will have to be pumped to the treatment facilities at PA Hamlet. The project includes the construction of a 54 ℓ/s pump station as well as the linking pipeline, 200 mm in diameter and approximately 3 800 m long. 2.4 Start date – duration of the programme The construction commenced in January 2010 and is anticipated to be completed by December 2015, later than what was originally anticipated due to delays on the agreement between a developer and Witzenberg on the cost sharing of the Tulbagh storage dam. TULBAGH a) New shared bulk pipeline from Klein Berg River Contract start date : 18 January 2010 Contract completion : 1 July 2012 b) Own (municipal) bulk pipeline Contract start date Contract completion : 15 November 2011 : April 2013 Bulk storage capacity Contract start date Contract completion : 01 June 2012 : December 2015 (planned) c) d) Upgrade of water treatment facilities and various small bulk infrastructure components Contract start date : 11 May 2012 Contract completion : May 2013 e) Link pipeline and various small bulk infrastructure components Contract start date : June 2013 Contract completion : 30 September 2013 f) Schalkenbosch tributaries Contract Start date Contract completion : August 2014 : April 2015 (planned) WOLSELEY a) Storage Capacity Contract start date Contract completion : 04 January 2010 : 30 November 2012 b) Bulk supply pipeline between storage dam and Wolseley, PS and WTW Contract start date : 04 January 2010 Contract completion : May 2011 c) Relining of the Stamper Road Contract start date Contract completion : 04 January 2010 : May and June 2011 6 REGIONAL BULK INFRASTRUCTURE PROGRAMME DECEMBER 2014 PA HAMLET a) b) c) Material Procurement Contract start date Delivery date : 19 January 2012 : June 2012 Pipeline installations PVC Contract start date Contract completion : 14 October 2013 : 30 November 2014 Pipeline installations Steel & Pump Station Contract start date : 24 August 2012 Contract completion : 31 July 2013 See Annexure B of details for contracts awarded. 2.5 Funds allocated to the project The project value is R69 605 000 and is funded as follows: Regional Bulk Infrastructure Grant Witzenberg Local Municipality Tulbagh Water User association R58,000,000 R6,361,000 R5,244,000 Table 1 indicates the funding that was made available to the project during the past financial years. Table 1: Funding 2007/08 2010/11 2011/12 2012/13 2013/14 2014/15 Total Approved RBIG budget amount R16 000 000 R12 000 000 R20 700 000 R8 331 000 R889 000 R57 920 000 Spent RBIG budget amount as at September 2014 R16 000 000 R11 887 767 R20 700 000 R8 331 000 R889 000 R57 920 000 Spent budget other funds R5 110 000 R4 000 000 R0 R0 … R9 110 000 7 REGIONAL BULK INFRASTRUCTURE PROGRAMME 3. DECEMBER 2014 PROGRESS TO DATE The performance evaluation was conducted on the 16 September 2014. A pre-site meeting was held between representatives of Department of Water & Sanitation (DWS), and the Witzenberg Local Municipality. The site was visited by the following representatives: 3.1 Mr D. Cloete Me M Dube Mr L Mditshane Mr N. Jacobs Mr JA. Du Plessis - DWS WP DWS WP DWS HQ Witzenberg Municipality (representing Witzenberg Municipality) Milestones Product Name of Organization compiling/ developing Planned date for completion FS/IRS/Design/EIA Date FS/IRS/Design /EIA approved Feasibility Study PUDJA July 2009 Implementation Readiness Study PUDJA October 2009 TULBAGH Product Name of Organization compiling/ developing Planned date for completion FS/IRS/Design/EIA Date FS/IRS/Design /EIA approved New shared bulk pipeline from Klein Berg River Preliminary Design EIA WUL Operation and Maintenance Plan Financial Funding Plan Design Sarel Bester Civil Engineers Jan 2010 EnviroAfrica March 2010 Sinclair and Associates Nov 2006 Sarel Bester Civil Engineers Dec 2010 July 2012 n/a Sarel Bester Civil Engineers April 2010 Own (municipal) bulk pipeline Preliminary Design EIA WUL Operation and Maintenance Plan Financial Funding Plan WorleyParsons ECOBOUND June 2010 Jan 2011 6 Jan 2012 n/a WorleyParsons n/a Aug 2012 8 REGIONAL BULK INFRASTRUCTURE PROGRAMME Design DECEMBER 2014 WorleyParsons Sept 2010 Bulk storage capacity Preliminary Design Royal Haskoning DHV Nov 2012 EIA Resource Management Services Dec 2012 WUL outstanding Operation and Maintenance Plan outstanding Financial Funding Plan Design n/a Royal Haskoning DHV Dec 2014 Upgrade of water treatment facilities and various small bulk infrastructure components Preliminary Design WorleyParsons EIA n/a WUL n/a Operation and Maintenance Plan Nov 2011 WorleyParsons Financial Funding Plan Design June 2013 n/a WorleyParsons Aug 2012 Link pipeline and various small bulk infrastructure components Preliminary Design WorleyParsons EIA n/a WUL n/a Operation and Maintenance Plan Financial Funding Plan Design June 2012 WorleyParsons n/a WorleyParsons June 2012 Schalkenbosch tributaries Preliminary Design Royal Haskoning DHV EIA WUL Sinclair and Associates Nov 2006 Dec 2010 9 REGIONAL BULK INFRASTRUCTURE PROGRAMME Operation and Maintenance Plan Financial Funding Plan Design DECEMBER 2014 outstanding n/a Royal Haskoning DHV WOLSELEY Product Name of Organization compiling/ developing Planned date for completion FS/IRS/Design/EIA Date FS/IRS/Design /EIA approved Storage Capacity Preliminary Design Aurecon EIA n/a WUL n/a Feb 2010 Operation and Maintenance Plan Financial Funding Plan Design n/a Aurecon Feb 2010 Bulk supply pipeline between storage dam and Wolseley Preliminary Design Aurecon EIA n/a WUL n/a Feb 2010 Operation and Maintenance Plan Financial Funding Plan Design n/a Aurecon Feb 2010 Pump stations and treatment works Preliminary Design Aurecon EIA n/a WUL n/a Operation and Maintenance Plan Financial Funding Plan n/a Feb 2010 10 REGIONAL BULK INFRASTRUCTURE PROGRAMME Design DECEMBER 2014 Aurecon Feb 2010 Relining of the Stamper Road Preliminary Design Aurecon EIA n/a WUL n/a Operation and Maintenance Plan n/a Financial Funding Plan n/a Design Dec 2011 Aurecon Dec 2011 PAH Product Name of Organization compiling/ developing Planned date for completion FS/IRS/Design/EIA Date FS/IRS/Design /EIA approved Material Procurement Preliminary Design Sarel Bester Civil Engineers EIA n/a WUL n/a Operation and Maintenance Plan n/a Financial Funding Plan n/a Design Sarel Bester Civil Engineers Nov 2011 Nov 2011 Berg Steel Pipeline & Pump Station Preliminary Design EIA WUL Operation and Maintenance Plan Financial Funding Plan Design Sarel Bester Civil Engineers Nov 2011 EnviroAfrica n/a outstanding n/a Sarel Bester Civil Engineers May 2012 11 REGIONAL BULK INFRASTRUCTURE PROGRAMME DECEMBER 2014 Link PVC Pipeline Preliminary Design Sarel Bester Civil Engineers Jan 2012 EnviroAfrica Feb 2013 EIA WUL n/a Operation and Maintenance Plan outstanding Financial Funding Plan Design 3.2 n/a Sarel Bester Civil Engineers Jan 2012 Implementation of the approved business plan A pre-feasibility identification report undertaken for Witzenberg municipality in 2005 evaluated the options of bulk water supply augmentation to TULBAGH from various sources. This report was followed by a Water Management report for the full Witzenberg area, completed in June 2008. This report highlighted the need for the augmentation of water sources to Tulbagh, Wolseley and PA Hamlet. The report was followed by a detailed study into the viability of all the different options for all the towns. A report completed in August 2009 recommended the implementation of various projects as highlighted in this report. The budget approval was received in December 2009. The following progress was noted up to 30 September 2014: PA Hamlet Project Berg pipeline: The project has been completed and is operational. Link pipeline: The contractor was appointed and the project started on 14 October 2013, with an anticipated completion date of 14 March 2014. Due to various reasons the project is behind schedule and still in progress. The necessary steps have been implemented to control any further delays, but the new completion date was set for November 2014. The project cost of approximately R4.7 million is however significantly higher than the allocated budget of R1.8 million. DWS indicated that no additional funding will be made available and Witzenberg therefore decided to halt all projects still not awarded. All funding will be reallocated to this project to ensure that the full PAH project will be in operation before for the end of this financial year. 3.3 Schedules of work and phasing of the activities Due to limited funding approved for the implementation of the projects, it was decided to start with the Tulbagh and Wolseley projects immediately and schedule the PA Hamlet projects to start only in June 2012. The implementation of the different components within each project depended on the finalization of water use license 12 REGIONAL BULK INFRASTRUCTURE PROGRAMME DECEMBER 2014 approvals by DWS and EIA application, as well as collaboration agreements with private partnerships in a number of cases. Work on projects where the capacity exists within the municipality started immediately, which included the purchase of pumps and pipe material for the upgrade of existing treatment facilities and specific pipe sections. The tender process for the implementation of the Tulbagh Municipal pipeline started six months after the award of the tender due to the late EIA approval. The tender commenced in November 2012 and was completed in April 2013. The storage licence is still outstanding for the storage dam. The designs for the storage dam has been completed, but additional cost such as grouting for a cut-off toe and the limited capacity of the site resulted in a dam with a cost significantly higher than originally anticipated. Alternative dam sites have been investigated again, but it was decided to stop the tender process until additional funding can be secured for the construction of the dam. This process is in progress. Wolseley reservoir was practically completed in November 2011 and was operational together with the linking bulk pipeline and the pump station. The sealing of the Stamper Road reservoir commenced after the completion of the Wolseley reservoir as both of the reservoirs are used as main storage capacity for Wolseley. The PA Hamlet project was scheduled to be implemented in three phases to maximise the need to employ smaller contractors. The pipe material was purchase as part of a separate contract, while the main Berg pipeline was implemented to be aligned with the shutdown periods of the existing pipeline, which was shared between the farming community and the municipality. The contract for the link pipeline was awarded to a smaller local contractor and the completion of the project was subsequently delayed due to poor site management from the contractor. The project still experience commissioning problems and a practical completion certificate is still outstanding. This is at present the only outstanding contract running. 3.4 Risks taken and management thereof The model used for the estimation of the flows in the Schalkenbosch tributaries was based on the historic information. Re-assessment by an independent professional services provider found that the estimated base flows for the Schalkenbosch Tributaries were not correct. Unfortunately it took a long time for the appointed PSP to access the property of the private owner to verify the results as the owner of the property denied access to the municipality regardless of numerous meetings with the property owner. Based on the outcomes of the re-assessment, the model was re-run with actual results which the PSP measured on site. The results indicated that there was not enough water on the tributaries as was originally estimated and the municipality might need to look for another source. There is still a pending issue on the Tulbagh bulk storage infrastructure, as the site that was identified that the dam is going to be constructed on belongs to the private owner who wants to share the storage facility with the municipality. If the storage facility will be shared between the private owner and the municipality both parties need to contribute towards the construction of the infrastructure. The owner of the property has included the storage dam in his application for the environmental authorization, which was granted in mid-2013. Finally consensus was reached on the split for the costs for the construction of the dam, but the cost is significantly higher than originally anticipated. A revised agreement between the two parties is at present under consideration. 13 REGIONAL BULK INFRASTRUCTURE PROGRAMME 3.5 DECEMBER 2014 Capacities dedicated to the programme The capacities dedicated to the programme are as follows; 3.6 Funding – Regional Bulk Infrastructure Grant (RBIG), Witzenberg Municipality and Tulbagh WUA. Regulator – Department of Water and Sanitation Overall Management – Witzenberg Local Municipality and PUDJA consulting engineers. Site supervision and contract administration – Various Consulting Engineers Construction Contractors Key challenges within the project TULBAGH The measurements by the PSP on the Schalkenbosch tributaries proved that there is not enough flow from the tributaries and the municipality needs to find alternative sources or increased capacity on other storage facilities where there is enough flow from the source. An agreement between the landowner regarding servitude rights and the position of the abstraction point is still under discussion. The RoD for the storage capacity was granted but the agreement regarding the shared storage capacity between the farmer and the municipality is still under discussion. The municipality has exhausted its allocation from the programme but the construction of the dam has not yet started. PA HAMLET The final phase of the project, i.e. the link pipeline is under construction. Due to the local contractor’s management skills, some delays are still experience with the completion of the project. 4. PROJECT RESULTS AND BENEFICIARIES 4.1 Outcomes and outputs No problems are anticipated at this stage, other than normal cost escalations due to the increase in raw products, such as fuel and material since the estimates were done more than four years ago. The additional cost of the Tulbagh dam, following the final geotechnical analysis, resulted into a dam with significant higher cost than what was originally anticipated. This is still unresolved, but under discussion. More water is supplied after the completion of the Tulbagh pipeline which has a positive impact for the municipality i.e. boost economy for the municipality and increase in water security for the municipality. Also the farmers can fill their dams much quicker. 14 REGIONAL BULK INFRASTRUCTURE PROGRAMME 4.2 DECEMBER 2014 Beneficiaries and project results The following communities will benefit from this project. Towns Townships People Wards Tulbagh Witzenville, Helpmekaar, Chris Hani 7200 7 & 11 Wolseley Montana, Pine Valley 8 300 7&2 Prince Alfred Hamlet Kliprug, Phases 4 & 5 4100 4 & 10 Also see Annexure B. The project has benefited the project team and community with the following: 4.3 Provision of water services to the community with population of 7,350, and also catering for future economic and domestic demand. Involvement of trainee personnel in the project whilst gaining experience in all project aspects (design, contract administration, policies). Involvement of local people in the project whilst gaining experience and training on construction and contracting aspects (contract management and various construction methods). Recruitment of local people to work on project. Provision of basic water services to the community, thus catering for future economic and domestic demand. Sourcing of materials from local suppliers and manufactures. Addressing the moratorium put on any further developments in the area due to a lack of water and all the associated social benefits. Jobs created In the period April – September 2014 no new job opportunities was created on the PA Hamlet Link Pipeline project. In total over the project period, a total of 32 jobs have been created. See Annexure E for the list of job opportunities 5. CONCLUSIONS / LESSONS LEARNED 5.1 Main successes and failures of the project to date The water allocations for the farmers proved to be a delicate area that the municipality had to negotiate more frequently with the farmers as the sources predominately run through their farms. A total of 13 contracts emanated from the projects from which 11 projects have been completed. Although two projects are still outstanding, the budget has been exhausted due to escalation and unavoidable incidents during the construction of some of the projects. The extent of the need for additional funding will depend on the final tender cost of the proposed new dam and the final agreement of cost sharing between the developer and 15 REGIONAL BULK INFRASTRUCTURE PROGRAMME DECEMBER 2014 the municipality. The extent of the works needed for the Schalkenbosch tributaries (additional resources for Tulbagh) will also depend on the level of agreement between the land owner and the Municipality, but even more on whether the Municipality decide on the full implementation of the project or only a partial implementation, taking into consideration the reduced base flow available. It however seems inevitable that the Witzenberg municipality will need to submit an application for an additional estimate of approximately R39.4 million taking the escalation in cost for a 2-3 year implementation period into consideration. 5.2 Ownership and sustainability of infrastructure works The Witzenberg Local Municipality is the Implementing Agent and has taken ownership of the infrastructure. The municipality is also responsible for the existing works and will be responsible for the operations and maintenance of the project. The municipality will budget for the O&M. 6. RECOMMENDATIONS The implementation of the Witzenberg Bulk Water Supply Scheme is partially successful, but additional financial support will have to be considered to ensure that the project is implemented to its full extend. DWS will carefully monitor the following issues: The municipality’s commitment to reducing water losses Ensuring that all the necessary EIAs are completed The municipality’s ability and commitment to adequately manage O & M once the project is completed. 16 REGIONAL BULK INFRASTRUCTURE PROGRAMME DECEMBER 2014 ANNEXURE A: PROJECT IMPLEMENTATION PHOTOS 17 REGIONAL BULK INFRASTRUCTURE PROGRAMME DECEMBER 2014 ANNEXURE B: LIST OF VILLAGES EXPECTED TO BENEFIT Towns Townships People Wards Tulbagh Witzenville, Helpmekaar, Chris Hani 7200 7 & 11 Wolseley Montana, Pine Valley 8 300 7&2 Prince Alfred Hamlet Kliprug, Phases 4 & 5 4100 4 & 10 18 REGIONAL BULK INFRASTRUCTURE PROGRAMME DECEMBER 2014 ANNEXURE C: DETAILS OF CONTRACTS CONTRACT CONTRACT NO. AND NAME CONTRACTOR VALUE (incl prof fees) (incl. VAT) TULBAGH: New Shared Bulk JVZ Pipeline from Klein Berg river Construction TULBAGH: Own (Municipal) Bulk Pipeline TULBAGH: Bulk Storage Capacity TULBAGH: Upgrade of Treatment Facilities TULBAGH: Link Pipeline and various small bulk infrastructure TULBAGH: Schalkenbosch Tributaries WOLSELEY: Storage Capacity WOLSELEY: Bulk Supply Pipeline between Storage Dam and Wolseley, PS and WTW WOLSELEY: Relining of the Stamper Road Reservoir PA HAMLET: Material Procurement JVZ Construction None at present NAMEC Construction Dennis Lentoor Civils None at present Nyanga Projects Nyanga Projects EMPA Construction and Agrico R20,000,000 R 6,400,000 R 3,200,000 R 11,000,000 R 6,400,000 R 2,000,000 R 1,500,000 R 5,567,258 (PVC) Nyanga and Pump Station Projects installation R 8,700,000 Robor (Steel) PA HAMLET: Pipeline Installation PA HAMLET: PVC Link pipeline R3,500,00 Dennis Lentoor Civils EXPENDITURE AS CONTRACT PLANNED ACTUAL AWARD / COMPLETION COMPLETION START DATE DATE DATE May 2012 01 July 2012 R 3 540 341.89 100% April 2012 April 2012 R 8,130,000 100% R1,100,000 2% R3,075,000 100% R1,786,000 100% 18 January 2010 15 November 2011 01 June 2012 with final design December 2015 % 2014 COMPLETION (incl. VAT) 11 May 2012 March 2013 17 January September 2013 2013 August 2014 April 2015 N/A R 1,720,00 2% August 2012 November 2012 R 5,766,406 100% May 2011 May 2011 R 1,909,597 100% September May and June May and June 2011 2011 2011 R 1,413,000 100% June 2012 June 2012 R 4,940,000 100% N/A R 12,500,000 100% R 4,374, 415 90% 04 January 2010 04 January 2010 19 January 2012 R12, 500,000 August 2012 May 2013 R 4,740,000 August 2013 2 May 2014 May 2013 AT SEPTEMBER 201 2012 2013 2014 2015 PAH 597 days Thu 12/01/19 Fri 14/05/02 REGIONAL BULK INFRASTRUCTURE PROGRAMME Wolseley 760 days Mon 10/01/04 Fri 12/1 /30 Tulbagh 15 4 days Mon 10/01/18 Thu 15/12/31 Project Duration Start Finish J FMAMJ J A S OND J FMAMJ J A S OND J FMAMJ J A S OND J FMAMJ J A S OND J FMAMJ J A S OND J FMAMJ J A S OND Name 2010 19 DECEMBER 2014 ANNEXURE D: PROJECT SCHEDULE 20 REGIONAL BULK INFRASTRUCTURE PROGRAMME SEPTEMBER 2014 ANNEXURE E: DETAILS OF JOB OPPORTUNITIES PAH Link Pipeline Temporary job opportunities for the 4th Quarter 2014/15 Temporary job opportunities for people employed at various occupational levels: Temporary = Full time for less than 5 months Adult Men Adult Women No Person Days Actual cost on job opportuni ties Clerical Ongoing 0 0 Clerical New 0 Labourers Ongoing Youth Men No Person Days Actual cost on job opportun ities R0 2 41 0 R0 2 0 0 R0 Labourers New 18 313 Managerial Ongoing 4 Managerial New Youth Women No Person Days Actual cost on job opportun ities R 12 300 0 0 41 R 12 300 0 4 63 R 11 592 R 57 592 0 0 82 R 32 800 0 0 0 R0 Semi-Skilled Ongoing 8 150 Semi-Skilled New 8 Skilled Ongoing Disabled No Perso n Days Actual cost on job opportun ities R0 0 0 0 R0 0 0 0 R0 R0 0 0 0 R0 0 0 0 R0 R 30 000 0 0 150 R 30 000 0 3 57 R 13 965 Skilled New 8 170 Supervisor Ongoing 3 Supervisor New TOTAL No Perso n Days Actual cost on job opportu nities No Person Days Actual cost on job opportuniti es R0 0 0 R0 2 41 R 12 300 0 R0 0 0 R0 2 41 R 12 300 0 0 R0 0 0 R0 4 63 R 11 592 R0 0 0 R0 0 0 R0 18 313 R 57 592 0 R0 0 0 R0 0 0 R0 4 82 R 32 800 0 0 R0 0 0 R0 0 0 R0 0 0 R0 R0 0 0 R0 0 0 R0 0 0 R0 8 150 R 30 000 0 R0 0 0 R0 0 0 R0 0 0 R0 8 150 R 30 000 0 0 R0 0 0 R0 0 0 R0 0 0 R0 3 57 R 13 965 R 41 650 0 0 R0 0 0 R0 0 0 R0 0 0 R0 8 170 R 41 650 60 R 18 000 0 0 R0 0 0 R0 0 0 R0 0 0 R0 3 60 R 18 000 1 20 R 6 000 0 0 R0 0 0 R0 0 0 R0 0 0 R0 1 20 R 6 000 Other Ongoing 0 0 R0 1 0 R0 0 0 R0 0 0 R0 0 0 R0 1 0 R0 Other New 0 0 R0 0 0 R0 0 0 R0 0 0 R0 0 0 R0 0 0 R0 TOTAL Ongoing 18 349 R 94 765 7 104 R 23 892 0 0 R0 0 0 R0 0 0 R0 25 453 R 118 657 TOTAL New 35 653 R 135 242 2 41 R 12 300 0 0 R0 0 0 R0 0 0 R0 87 1600 R 384 856 21 REGIONAL BULK INFRASTRUCTURE PROGRAMME SEPTEMBER 2014 Summary of Decent Job Opportunities Decent job opportunities for people employed at various occupational levels: Decent = Full time for at least 5 months or more Decent job opportunities for the 4th Quarter 2013/14 Adult Men Adult Women Youth Men Person Days No Disabled TOTAL No Person Days Actual cost on job opportun ities Clerical Ongoing 0 0 R0 0 0 R0 0 0 R0 0 0 R0 0 0 R0 0 0 R0 Clerical New 0 0 R0 0 0 R0 0 0 R0 0 0 R0 0 0 R0 0 0 R0 Labourers Ongoing 0 0 R0 0 0 R0 0 0 R0 0 0 R0 0 0 R0 0 0 R0 Labourers New 0 0 R0 0 0 R0 0 0 R0 0 0 R0 0 0 R0 0 0 R0 Managerial Ongoing 0 0 R0 0 0 R0 0 0 R0 0 0 R0 0 0 R0 0 0 R0 Managerial New 0 0 R0 0 0 R0 0 0 R0 0 0 R0 0 0 R0 0 0 R0 Semi-Skilled Ongoing 0 0 R0 0 0 R0 0 0 R0 0 0 R0 0 0 R0 0 0 R0 Semi-Skilled New 0 0 R0 0 0 R0 0 0 R0 0 0 R0 0 0 R0 0 0 R0 Skilled Ongoing 0 0 R0 0 0 R0 0 0 R0 0 0 R0 0 0 R0 0 0 R0 Skilled New 0 0 R0 0 0 R0 0 0 R0 0 0 R0 0 0 R0 0 0 R0 Supervisor Ongoing 0 0 R0 0 0 R0 0 0 R0 0 0 R0 0 0 R0 0 0 R0 Supervisor New 0 0 R0 0 0 R0 0 0 R0 0 0 R0 0 0 R0 0 0 R0 Other Ongoing 0 0 R0 0 0 R0 0 0 R0 0 0 R0 0 0 R0 0 0 R0 Other New 0 0 R0 0 0 R0 0 0 R0 0 0 R0 0 0 R0 0 0 R0 TOTAL Ongoing 0 0 R0 0 0 R0 0 0 R0 0 0 R0 0 0 R0 0 0 R0 TOTAL New 0 0 R0 0 0 R0 0 0 R0 0 0 R0 0 0 R0 0 0 R0 No Actual cost on job opport unities Youth Women Person Days Actual cost on job opportuniti es No Person Days Actual cost on job opportuniti es No Person Days Actual cost on job opportun ities No Perso n Days Actual cost on job opportuni ties