THIRD QUARTER PERFORMANCE EVALUATION REPORT OF GREATER MTHONJANENI REGIONAL BULK WATER SCHEME KWAZULU NATAL CHIEF DIRECTORATE: BULK INFRASTRUCTURE PROGRAMME PERIOD: 01 OCTOBER 2014 TO 31 DECEMBER 2014 2 REGIONAL BULK INFRASTRUCTURE GRANT 31 DECEMBER 2014 TABLE OF CONTENTS 1 INTRODUCTION ........................................................................................................................... 3 2 BACKGROUND ............................................................................................................................. 3 2.1 Project description ................................................................................................... 3 AREA OF SUPPLY ..................................................................................................................................... 3 3 PROJECT CONTRACT AND COST ................................................................................................. 4 3.1 Contract Details and Cost........................................................................................ 4 3.2 Funding Allocated to the Project .............................................................................. 7 4 PROGRESS ON CURRENT PROJECT ............................................................................................. 8 4.1 Progress on UDM/MIG/23/2011: Kwahlokohloko SSA 1: 5.8 km Steel Bulk pipeline, 900 mm dia ........................................................................................................................ 8 4.2 Progress on UDM/MIG/27/2012: Kwahlokohloko SSA 1: Booster Pump stations 1 & 2.5 Mℓ Balancing Reservoir ................................................................................................ 8 4.3 Progress on UDM/MIG/14/2013: Kwahlokohloko SSA 1: Booster Pump stations 2 & 8 Mℓ Balancing Reservoir ................................................................................................... 8 5 RISKS TAKEN AND MANAGEMENT THEREOF ............................................................................. 8 6 PROJECT RESULTS AND BENEFICIARIES...................................................................................... 9 The project beneficiaries are mentioned below: ...................................................................... 9 6.1 Households Beneficiaries ........................................................................................ 9 6.2 Employment during the Implementation of the Project............................................. 9 7 KEY CHALLENGES WITHIN THE PROJECT .................................................................................... 9 8 CONCLUSIONS ........................................................................................................................... 10 8.1 Lessons Learned................................................................................................... 10 9 RECOMMENDATIONS ............................................................................................................... 10 10 PHOTOGRAPHS ON THE IMPLEMENTATION OF THE PROJECT................................................ 11 3 REGIONAL BULK INFRASTRUCTURE GRANT 1 31 DECEMBER 2014 INTRODUCTION In terms of Section 10(7) (b) of the Division of Revenue Act No 10 of 2014 (DORA) as promulgated in Government Gazette No 37595 dated 26 April 2014, the transferring national officer must submit a quarterly performance report for all Programmes funded by a Schedule 6 allocation within 45 days after the end of each quarter, in accordance of the relevant framework to the National Treasury. The Regional Bulk Infrastructure Grant (RBIG) is a Schedule 6 indirect conditional grant for the benefit in kind of municipalities. The objective of this Report is to provide a third quarter performance evaluation report of RBIG funded projects, in compliance with the DORA. The objective of this evaluation was to determine whether the progress on the project is commensurate with the expenditure to date as well as to determine whether the project is still on course in terms of the original planning. This quarterly report covering the third quarter of 2014/15 fiscal year, presents the results of the performance evaluation of Greater Mthonjaneni Regional Bulk Water Supply Project. 2 BACKGROUND In accordance with the Water Service Master Plan (2004), the Goedertrouw Regional Scheme with the Goedertrouw Dam identified as the most viable source will supply water to Greater Mthonjaneni, Kwahlokohloko and Eshowe supply areas. 2.1 Project description The Greater Mthonjaneni Bulk Water Scheme obtains its water from the Goedertrouw Dam. Water gravitates to a new 20 Mℓ Water Treatment Works (WTW) where it is purified. Water is then pumped from the WTW to the north area (Greater Mthonjaneni) into a 2.5 Mℓ Zimele Reservoir approximately 9.5 km from the Water Purification Plant. Another quantity of water will be pumped to the south areas into the 8Mℓ Kwahlokohloko Reservoir and then gravitates into Kwahlokohloko and Eshowe supply areas The components of the project comprise: a) b) c) d) e) 40 Mℓ Water Treatment Works Bulk supply pipelines Concrete and Steel reservoirs Balancing Tanks and Booster Pump stations Reticulation to individual metered connections. AREA OF SUPPLY The regional water supply scheme is the central portion of the uThungulu District Municipality encompassing the whole of Mthonjaneni Local Municipality, and parts of Ntambanana and uMlalazi Local Municipal areas, representing approximately 35% total area and 40% total population residing within uThungulu District Municipality. A list of villages that are expected to benefit from the current phases are listed in Annexure A. 4 REGIONAL BULK INFRASTRUCTURE GRANT 3 31 DECEMBER 2014 PROJECT CONTRACT AND COST The project is managed by the Department of Water and Sanitation, jointly through the Regional Bulk Infrastructure Programme and the Construction Unit of the Department and coordinated by the DWS Regional Office in Region. The capacities dedicated to the project are as follows:- 3.1 Funder: Implementing agent: Operation & Maintenance: Consulting Engineers: Contractors (current): MIG & DWS (RBIG) uThungulu District Municipality uThungulu District Municipality UWP, ZAI, VGC/Ilifa, BKS, Eyethu, Aurecon & PDNA Esorfranki Pipelines, Afriscan Construction and Icon Construction Contract Details and Cost The contract details are mentioned below: a) Contract UDM/MIG/07/2006: Construction of Greater Mthonjaneni Water Works Phase 1&2: (UWP) Contractor : BiWater SA (Pty) Ltd Project Component : Construction of 20ML Greater Mthonjaneni WTW Contract Start date : 14 September 2007 Contract completion : 04 June 2009 Contract Value : R44 804 384.54 (including VAT & Contingencies) Percentage Complete : 100% The contractor has met all financial obligations and has achieved targeted labour components of the project. b) Contract UDM/MIG/17/2006: Supply of ductile iron pipes Phase 1&2: (ZAI) Contractor : DPI Ichweba Project Component : Supply of 10 km ductile iron pipes Contract completion : 11 January 2008 Contract Value : R6 615 079 including VAT & Contingencies) Percentage Complete : 100% c) Bulk Treated Water Rising Main, Pump Stations and Reservoirs: (ZAI) Contract UDM/MIG/01/2007 (ZAI) Contractor : Inhlanhla Civils Project Component : Construction of 10 km rising main Contract Start date : August 2007 Contract completion : 06 October 2008 Contract Value : R14 375 524 (including VAT) Percentage Complete : 100% Contract UDM/MIG/03/2007 (ZAI) Contractor : Africa Civils & Building Construction Project Component : Construction of Buildings, Pump station & Reservoirs Contract Start date : February 2008 5 REGIONAL BULK INFRASTRUCTURE GRANT 31 DECEMBER 2014 Contract completion : 27 November 2008 Contract Value : R12 602 304 (including VAT) Percentage Complete : 100% Contract UDM/MIG/04/2008 (ZAI) Contractor : Inhlanhla Civils Project Component : Electrical and Mechanical Installation Contract Start date : January 2009 Contract completion : 31 August 2009 Contract Value : R13 131 451 (including VAT) Percentage Complete : 100% d) Greater Mthonjaneni phase 1: Reticulation (MIG Programme) (ZAI) Various contracts have been awarded for the implementation of the reticulation projects. The final contract values is R21 403 088 with progress at 100% for this portion of the project. e) UDM/MIG/12/2010: Conversion of Eshowe pipeline (ZAI) Conversion of existing pipeline to Kwahlokohloko and Eshowe, upgrading of booster pumps, refurbishment of raw water reservoirs and all related connections. Contractor : Icon Construction Contract Start date : January 2009 Contract completion : June 2012 Contract Value : R6 792 049.04 (including VAT) Amount spent : R5 636 915 Percentage Complete : 100% f) UDM/MIG/19/2008 & UDM/MIG/18/2011: Greater Mthonjaneni phase 2A&2B: Construction of Bulk water pipeline (VGC) Construction of 19 km of ductile Iron and 12 km uPVC bulk pipeline together with appurtenant works such as scour valves, air valves and control valves. This project was stopped in April 2011 due to poor performance by the Contractor and another contractor was appointed in November 2011 to complete the works but unfortunately they were liquidated in July 2012 before the project was complete. The Liquidator then appointed Afriscan Construction to complete the project. Contractor : Thuthuka Group Limited, Sanyati Civil & Construction and Afriscan Construction Contract Start date : 25 June 2009 Contract completion : 30 June 2013 Contract Value : R45 775 764 (including VAT) Amount spent : R44 591 824 Percentage Complete : 100% 6 REGIONAL BULK INFRASTRUCTURE GRANT g) 31 DECEMBER 2014 UDM/MIG/02/2009: Greater Mthonjaneni phase 2A & 2B: Construction of Bulk Reservoirs (VGC) Construction of 12 concrete reservoirs and elevated tanks together with appurtenant works such as scour valves, air valves and control valves. This project is dependent on the above project for operation. Contractor : Juvansu Trading cc T/A Mazcon Civil & Building Contract Start date : 09 October 2009 Contract completion : 24 November 2010 Contract Value : R10 557 869 (including VAT) Amount spent : R10 085 974 Percentage Complete : 100% h) Greater Mthonjaneni phase 2A & 2B: Reticulation (MIG Programme) (VGC) Various contracts have been awarded for the implementation of the reticulation projects. The total contract value is R18 583 830.92 for this portion of the project with progress at 100%. i) UDM/MIG/13/2010: Greater Mthonjaneni phase 2C & 2D: Construction of Bulk water pipeline & Reservoirs (BKS) Construction of 10.5 km uPVC bulk pipeline and 2 x 400 kℓ Steel Tanks together with appurtenant works such as scour valves, air valves and control valves: Contractor : Hidrotech Infra Contract Start date : 22 September 2011 Contract completion : 22 September 2012 Contract Value : R10 799 113 (including VAT) Amount spent : R9 908 804 Percentage Complete : 100% j) Greater Mthonjaneni phase 2C & 2D: Reticulation (MIG Programme) (BKS) Various contracts have been awarded for the implementation of the reticulation projects. The total contract values are R21 854 750 for this portion of the project and the amount spent up to 31 December 2014 is R14 174 073 with progress at 99%. k) Greater Mthonjaneni SSA 4: Bulk pipeline and Reservoirs Construction of bulk pipeline and 4 x reservoirs together with appurtenant works such as scour valves, air valves and control valves. Contractor Contract Start date Anticipated completion Contract Value Amount spent Percentage Complete : Shula Construction : 14 May 2012 : 11 February 2014 : R22 993 775 (including VAT) : R22 847 240 : 100% 7 REGIONAL BULK INFRASTRUCTURE GRANT l) 31 DECEMBER 2014 Greater Mthonjaneni SSA 4: Reticulation to Zone 1, 2 & 3 Various contracts have been awarded for the implementation of the reticulation projects. The total contract value is R9 686 919 for this portion of the project and the amount spent up to 31 December 2014 is R9 661 260 with progress at 100%. m) Greater Mthonjaneni SSA 5: Bulk pipeline and Reservoirs Construction of bulk pipeline and 4 x reservoirs together with appurtenant works such as scour valves, air valves and control valves. Contractor: Contract Start date Anticipated completion Contract Value Amount spent Percentage Complete n) : Sanyati Civil Engineering & Construction and Afriscan : 13 March 2012 : 28 January 2014 : R29 970000 (including VAT) : R30 930 169 : 99% Kwahlokohloko SSA 1: Bulk pipeline and Reservoirs Construction of 900 mm dia steel bulk pipeline, 2 x pump stations and 2 x reservoirs together with appurtenant works such as scour valves, air valves and control valves. Contractor Contract Start date Anticipated completion Contract Value Amount spent Percentage Complete 3.2 : Esorfranki Pipelines and Icon Construction : 18 May 2012 : 30 November 2015 : R125 084 828.70 (including VAT) : R73 975 641.41 : 59% Funding Allocated to the Project The total project cost is R1 797 364 080 and the planned completion date of the project is at the end of June 2018. Table 1 below indicates the RBIG funding that was made available to the project during the past financial years. Table 1: Funding to date Financial Year 2007/08 2008/09 2009/10 2010/11 2011/12 2012/13 2013/14 2014/15 Total Approved budget R11 000 000 R27 787 000 R1 213 000 R4 743 000 R22 976 500 R35 735 687 R32 164 043 R100 000 000 R 235 619 227 8 REGIONAL BULK INFRASTRUCTURE GRANT 31 DECEMBER 2014 Co-funding streams: 4 District Municipality (MIG) : R248 404 430 PROGRESS ON CURRENT PROJECT The project was visited and the spot check was conducted on 16 January 2015. A team from the uThungulu DM and DWS Officials (Regional) visited the project. Progress was discussed during the site visit. The site was visited by the following people:1. 2. 3. 4.1 Nathaniel Padayachee Kenneth Cezula Mirek Paczynski - Department of Water & Sanitation uThungulu DM (Project Manager) Eyethu Engineers Progress on UDM/MIG/23/2011: Kwahlokohloko SSA 1: 5.8 km Steel Bulk pipeline, 900 mm dia The overall progress on this project is 99%. The overall progress on this project was slow at the beginning but there’s been huge improvement. There have been delays with testing of the pipeline due to the high demand of water in the existing schemes. 4.2 Progress on UDM/MIG/27/2012: Kwahlokohloko SSA 1: Booster Pump stations 1 & 2.5 Mℓ Balancing Reservoir The tender for the construction of the booster pump station and the balancing reservoir was awarded to Esorfranki Construction at the end of July 2013. The progress to date is 80% and the contractor is busy with concrete work and brickwork on the pump station. 4.3 Progress on UDM/MIG/14/2013: Kwahlokohloko SSA 1: Booster Pump stations 2 & 8 Mℓ Balancing Reservoir The tender for the construction of the 2nd booster pump station and 8 Mℓ reservoir was awarded to Icon Construction in June 2014. However, the site has not been handed over to the Contractor due to the Eskom service which was only moved in November 2014 from the reservoir site. 5 RISKS TAKEN AND MANAGEMENT THEREOF At the planning phase of the project there was a risk since the following documents and approvals were not in place: Land ownership/occupation Environmental approval Abstraction permit Confirmation of electricity supply UWP Consulting Engineers, ZAI and Eyethu Consulting Engineers proceeded with the design of the project prior to the above approvals. These applications and processes were undertaken simultaneously with the design. 9 REGIONAL BULK INFRASTRUCTURE GRANT 6 31 DECEMBER 2014 PROJECT RESULTS AND BENEFICIARIES The project beneficiaries are mentioned below: 6.1 Households Beneficiaries The bulk pipeline project is aimed at eradicating water backlogs of 30% of the uThungulu District Municipality communities. When completed, the project will provide water services to over 281 864 people within the service area. The completion of the project will also ensure the delivery of sustainable basic water services, the enhancement of economic development towards achieving the national services target by 2014, the objectives of water for growth and development, employment and redistribution. 6.2 Employment during the Implementation of the Project Due to unrests in the area as a result of people looking for employment, the Implementing Agent laid down a procedure of dealing with unrest on site, including procedures for hiring and laying off workers. The employment created during the implementation of the project is indicated in Annexure B. 7 KEY CHALLENGES WITHIN THE PROJECT The key challenges experienced during the implementation of the project are mentioned below: a) The delay in the power supply connection by Eskom delayed the commissioning of the Water Works. Due to the lack of power supply on the pipeline and booster pump stations no testing could be performed. Application for power supply was submitted in 2005 and Eskom managed to complete the installation by November 2011. b) Contract (Phase 2A & 2B; UDM/MIG/19/2008) terminated due to the Contractors failure to meet deadlines on the construction of the 19 km of ductile iron and 12 km uPVC bulk pipeline together with appurtenant works such as scour valves, air valves and control valves. This caused a delay in all other projects linked to this one. In November 2011, Sanyati Civil Engineering and Construction was appointed to complete this project but in July 2012, they were liquidated without completing the project. This caused further delays to the commissioning of other projects linked to it. c) Greater Mthonjaneni SSA 5 Bulk was also awarded to Sanyati Civil Engineering and Construction in February 2012 and was liquidated in July 2012. This affected the planned expenditure and service delivery. d) Delivery of pipes delayed due to delays in raw material (steel coil) for the raw material suppliers affected progress at Kwahlokohloko SSA 1. e) Local unrest occurred on site due to Labour wage strikes. The local labourers were demanding to be paid according to the Gazetted minimum rates for the Civil Engineering Construction projects instead of the Gazetted Expanded Public Works Programme (EPWP) minimum rates. The construction on Kwahlokohloko SSA 1 was stopped for 28 days. 10 REGIONAL BULK INFRASTRUCTURE GRANT f) 8 31 DECEMBER 2014 Another challenge was caused by the delay in the relocation of the Eskom service at the reservoir site at Kwahlokohloko SSA 1. An application was done in February 2014 and the works were done in November 2014. This caused delays with the Reservoir contractor of 6 months resulting in poor expenditure. CONCLUSIONS The communities in Phases 1 & 2 have started benefiting from the completed reticulation while in other areas they are eagerly awaiting the completion of the project as it will resolve the long standing issues of shortage of potable water within the regional supply areas. 8.1 9 Lessons Learned a) Application for electricity must be done as early as possible to prevent delays in commissioning of completed projects due to delays in electricity installations by Eskom. b) Due diligence must be conducted on all contracts/tenders in excess of R10 m to reduce the risk of liquidation of contractors during construction. c) Whenever a project is started, local labourers as well as local authorities must be informed about the wage rates applicable to each project. RECOMMENDATIONS The implementation of the Greater Mthonjaneni project is successful and there is no need for any recommendations other than those identified in Point 8.1. 11 REGIONAL BULK INFRASTRUCTURE GRANT 31 DECEMBER 2014 10 PHOTOGRAPHS ON THE IMPLEMENTATION OF THE PROJECT The photographs on the implementation of the project are shown below: Photo 1: Kwahlokohloko SSA 1A: Scour outlets Photo 2: Kwahlokohloko SSA 1A: Gabions 12 REGIONAL BULK INFRASTRUCTURE GRANT 31 DECEMBER 2014 Photo 3: Kwahlokohloko SSA 1B: 2.5 Mℓ Balancing Reservoir Photo 4: Kwahlokohloko SSA 1B: Pump station 13 REGIONAL BULK INFRASTRUCTURE GRANT Photo 5: Kwahlokohloko SSA 1B: Pump station Photo 5: Kwahlokohloko SSA 1B: MV Switch room 31 DECEMBER 2014 14 REGIONAL BULK INFRASTRUCTURE GRANT 31 DECEMBER 2014 ANNEXURE A LIST OF VILLAGES TO BENEFIT FROM SCHEME: GREATER MTHONJANENI PHASE 1 &2: Total of 2 762 Households Ekuthuleni Nkunzempunga Matshansundu Nduro Zigagayi Esibhonsweni Dloziyane Memezi Msuthu Nogajuka Siyavuna Emukhindini Mehlamasha Goqozwayo Edubeni Ndundulu Sibayeskhulu Emashobeni Mabhungu Makhasaneni Ezihlabathini Makhothapani Zimele Okhalweni GREATER MTHONJANENI SSA 4: Total of 2 750 Households Hawule Wambaza Enkwenkwe Nomponjwana Makhasaneni Emasangweni GREATER MTHONJANENI SSA 5: Total of 3 754 Households Oqhabiyeni Ongelweni Esikadeni Gobihlahla Mpevu Emfeceni Emkhandlwini KWAHLOKOHLOKO SSA 1: Total of 4 436 Households Mandawe Mbizo 2 Ncemaneni Emaqeleni Isiphezi KwaMpofu Kwahlokohloko Thintumkhaba Mhlathuzana Mtilombo Mbizo 1 ANNEXURE B VUSUMUZI MANDLAKAYISE VELA NTOMBIYENKOSI BUHLE BUYEZA LINDIWE DLOKWAKHE MKHULEKELENI SIBUSISO NSINDISO PHUMLANI NKOSINATHI XOLANI NONHLE SIBONAKALISO BONISIWE GUGU KHANYISILE PHUMELELE NELISIWE PHUMZILEGUGU VS XULU MMN LUTHULI V SISHI NT BUTHELEZI BBM NTULI LC MTHETHWA DE ZUNGU MM MAHAYE S NGIDI NK KHANYILE P GWALA NT XULU X DLUDLA N NDLOVU S MDLETSHE BG MDLETSHE K DLUDLA PN XULU NP MAHAYE PG MAHAYE 8604285512084 8807285680088 5407155740089 6905030839082 7301145352089 6506210447082 6007065875089 8409175743082 8604285841087 9212125623084 9311185459080 9008066350087 9101255919083 8609061043089 8608110654086 8905071221081 9208160593083 7506250592085 8109141264086 7509020690080 DOB dd/mm/yyy y 28/04/1986 28/07/1988 15/07/1957 3/05/1969 14/01/1973 21/06/1965 6/07/1960 17/09/1984 28/04/1986 12/12/1992 18/11/1993 6/08/1990 25/01/1991 6/09/1986 11/08/1986 7/05/1989 16/08/1992 25/06/1975 14/09/1981 2/09/1975 M or F MALE MALE MALE FEMALE MALE FEMALE MALE MALE MALE MALE MALE MALE MALE FEMALE FEMALE FEMALE FEMALE FEMALE FEMALE FEMALE Has Education disability See level Start date codes at dd/mm/yyy Y or N the TOP y 1 11/10/2013 NO 1 11/10/2013 NO 1 11/10/2013 NO 1 11/10/2013 NO 1 11/10/2013 NO 1 11/10/2013 NO 1 11/10/2013 NO 1 11/10/2013 NO 1 11/10/2013 NO 9 11/10/2013 NO 1 11/10/2013 NO 1 11/10/2013 NO 1 11/10/2013 NO 1 11/10/2013 NO 1 11/10/2013 NO 1 11/10/2013 NO 1 11/10/2013 NO 1 11/10/2013 NO 1 11/10/2013 NO 1 11/10/2013 NO 24 0 24 24 24 24 24 24 0 24 24 24 0 0 0 0 0 24 24 0 150 150 150 150 150 150 150 150 150 150 150 150 150 150 150 150 150 150 150 150 3600 0 3600 3600 3600 3600 3600 3600 0 3600 3600 3600 0 0 0 0 0 3600 3600 0 19 0 19 19 0 19 19 19 0 19 19 19 0 0 0 0 0 19 19 0 150 150 150 150 0 150 150 150 150 150 150 150 150 150 150 150 150 150 150 150 2850 0 2850 2850 0 2850 2850 2850 0 2850 2850 2850 0 0 0 0 0 2850 2850 0 9 9 9 9 9 9 9 9 9 9 9 150 150 150 150 0 150 150 150 150 150 150 150 150 150 150 150 150 150 150 150 Total wages paid December Total number of training days I.D. Number Number of labour days for November Daily wage rate for December Last name Dec-14 Total number of training days Initials Total wages paid November First name Number of labour days for October Daily wage rate for November Gender Nov-14 Total number of training days Oct-14 Number of labour days for October Daily wage rate for October 9 Total wages paid October BENEFICIARY INFORMATION PLEASE PROVIDE BENEFICIARY INFORMATION ON THIS SHEET FOR EACH MONTH OF THE YEAR Education Levels – use the codes (1,2,3) on the excel spreadsheet o (1) Unknown o (2) No Schooling o (3) Grade 1-3 (Sub A – Std 1) o (4) Grad 4 (Std 2) ABET 1 o (5) Grade 5-6 (Std 3-4) ABET 2 o (6) Grade 7-8 (Std 5-6) ABET 3 o (7) Grade 9 (Std 7) ABET 4 o (8) Grade 10-11 (Std 8-9) o (9) Grade 12 (Std 10) o (10) Post Matric 1350 0 1350 1350 0 1350 1350 1350 0 1350 1350 1350 0 0 0 0 0 1350 1350 0 2 REGIONAL BULK INFRASTRUCTURE GRANT DUMISANI BHEKISISA NHLANHLA SDUMISILE SINENHLANHLA PHUMELELE SINDISIWE PHILLIP SIYABONGA ZILETHILE THEMBA LAYEZILE BUYILE SENZO NTOMBIYESAZI NTOMBIYENKOSI MUZOMUHLE ZAKHELE ZAMOKUHLE FIKELEPHI BONGINKOSI JABULILE BONISIWE LUNGILE THANDO KHANYISANI KHULEKANI MVELO ZWELITHINI SIBUSISO MLUNGISI ZAMOKWAKHE NKAZIMULO DM ZULU B LUTHULI NP NZUZA SH NXUMALO SS NGEMA PP NGEMA SP NTOMBELA PIM NZUZA S MCINEKA ZT KHANYILE TP MTHETHWA L MPANZA BZ MAGWAZA S XULU NK MKHIZE N NZUZA M KHANYILE ZSL SHANGE Z MKHIZE F MDLETSHE BB MNGADI J ZULU B NZUZA L KHUMALO T.F MPUNGOSE K NZUZA K.H MDLETSHE M BIYELA Z KHUMALO S NTOMBELA M MCHUNU ZZ SHANDU NS MDLETSHE 31 DECEMBER 2014 7210055504086 8507255488088 5207195251083 7807200824085 9007071071084 8309031173088 8805270537081 6201085473088 8008135699085 9002171057083 5501225395088 8906030814081 9403300517080 8705026308086 6907040413080 9307020689089 7604305499081 9412115572081 9106061504056 9001300663084 9003305310083 9202110969084 8709240580082 5/10/1972 25/07/1985 19/07/1952 20/07/1978 7/07/1990 3/09/1983 27/05/1988 8/01/1962 13/08/1980 17/02/1990 22/01/1955 3/06/1989 30/03/1994 2/05/1987 4/07/1969 02/07/1993 30/04/1976 11/12/1994 6/06/1991 30/01/1990 30/03/1990 04/06/2014 24/09/1987 8509150749085 8111135324082 8711106111085 9301096075083 750615558082 8305185543084 9202056022083 6409015480087 9209285873087 15/09/1985 13/11/1981 10/11/1987 09/01/1993 15/05/1975 18/05/1983 05/02/1992 01/09/1964 28/09/1992 MALE MALE MALE FEMALE FEMALE FEMALE FEMALE MALE MALE FEMALE FEMALE FEMALE FEMALE MALE FEMALE FEMALE MALE MALE FEMALE FEMALE MALE FEMALE FEMALE FEMALE FEMALE MALE MALE MALE MALE MALE MALE MALE MALE NO NO NO NO NO NO NO NO NO NO NO NO NO NO NO NO NO NO NO NO NO NO NO NO NO NO NO NO No No No NO NO 1 1 1 1 8 9 10 1 1 1 1 9 1 1 1 1 9 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 14/01/2014 14/01/2014 30/01/2014 30/01/2014 11/10/2013 11/10/2013 11/10/2013 03/04/2014 03/04/2014 03/04/2014 03/04/2014 03/04/2014 03/04/2014 03/04/2014 03/04/2014 03/04/2014 03/04/2014 20/03/2014 20/03/2014 20/03/2014 20/03/2014 04/06/2014 04/08/2014 04/08/2014 06/08/2014 23/10/2014 23/10/2014 23/10/2014 05/06/2014 05/06/2014 05/06/2014 23/10/2014 23/10/2014 24 24 24 24 24 0 0 24 24 24 24 24 24 24 24 0 24 24 24 24 24 24 24 24 24 2 2 2 8 8 8 2 2 150 150 150 150 150 0 185 150 150 150 150 150 150 150 150 150 300 150 150 150 150 150 150 150 150 150 150 150 150 150 150 150 150 3600 3600 3600 3600 3600 0 0 3600 3600 3600 3600 3600 3600 3600 3600 0 7200 3600 3600 3600 3600 3600 3600 3600 3600 300 300 300 1200 1200 1200 300 300 19 19 19 19 19 0 0 19 19 19 19 19 19 19 19 0 19 19 19 19 19 19 19 19 19 19 19 19 19 19 19 19 19 150 150 150 150 150 0 185 150 150 150 150 150 150 150 150 150 300 150 150 150 150 150 150 150 150 150 150 150 150 150 150 150 150 2850 2850 2850 2850 2850 0 0 2850 2850 2850 2850 2850 2850 2850 2850 0 5700 2850 2850 2850 2850 2850 2850 2850 2850 2850 2850 2850 2850 2850 2850 2850 2850 9 9 9 9 9 9 9 9 9 9 9 9 9 0 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 150 150 150 150 150 0 185 150 150 150 150 150 150 150 150 150 300 150 150 150 150 150 150 150 150 150 150 150 150 150 150 150 150 1350 1350 1350 1350 1350 0 0 1350 1350 1350 1350 1350 1350 1350 1350 0 2700 1350 1350 1350 1350 1350 1350 1350 1350 1350 1350 1350 1350 1350 1350 1350 1350