M/s. SAI MAATARINI TOLLWAYS LIMITED, HYDERABAD Name of Project: Four Laning of Panikoili - Rimuli Section of NH215 from Km 0+000 – 163+000 (Design Length 166+173 Kms) in the State of Orissa under NHDP Phase-III as BOT (Toll) Basis on DBFOT pattern. MONTHLY PROGRESS REPORT for MARCH-2015 CLIENT NATIONAL HIGHWAYS AUTHORITY OF INDIA (MINISTRY OF SHIPPING, ROAD TRANSPORT & HIGHWAYS) (Government of India) Independent Engineer Project Management Consultant SAI CONSULTING ENGINEERS PVT. LTD, SHELADIA ASSOCIATES INC., USA, Ahmedabad Hyderabad EPC Contractor M/s. GAYATRI PROJECTS, LTD., Hyderabad SAI MAATARINI TOLLWAYS LIMITED Four Laning of Panikoili – Rimuli Road Section of NH215 from Km 0+000 – 163+000 (Design Length 166+173 Kms) in the state of Odisha under NHDP Phase-III as BOT (Toll) Basis. Monthly Progress Report : March - 2015 Table of Contents 2. SCOPE OF THE PROJECT ................................................................................................................................... 4 3. PROCUREMENT OF THE SITE IN TERMS OF LENGTH OF PROJECT HIGHWAY (KM).................. 6 4. PRECONSTRUCTION ACTIVITIES ..................................................................................................................... 20 5. STATUS OF DESIGNS & DRAWINGS ................................................................................................................ 23 6. PHYSICAL PROGRESS ..................................................................................................................................... 24 6.1. 6.2. 7. PHYSICAL PROGRESS (TO BE UPDATE)....................................................................................................................24 FINANCIAL PROGRESS (AS PER REVISED PROGRAMME) TO BE UPDATE .........................................................................25 STRIP CHART OF WORK PROGRESS ................................................................................................................ 27 7.1. 7.2. 7.3. 7.4. 7.5. 7.6. 7.7. 8. PROGRESS OF MAJOR BRIDGES ............................................................................................................................57 PROGRESS OF MINOR BRIDGES ............................................................................................................................59 PROGRESS OF ROBS ..........................................................................................................................................60 PROGRESS OF FLYOVER.......................................................................................................................................60 PROGRESS OF VEHICULAR UNDER PASSES (VUPS): ..................................................................................................61 PROGRESS OF PEDESTRIAN UNDER PASSES (PUPS):.................................................................................................61 PROGRESS OF CULVERTS (PIPE/BOX/SLAB): ...........................................................................................................62 CONSTRUCTION CONSTRAINTS: .................................................................................................................... 66 9. A) ADDITIONAL SCOPE: 31 IRRIGATION CULVERTS ARE BEING TAKEN UP UNDER ADDITIONAL SCOPE AS DEPOSIT WORKS OF IRRIGATION DEPARTMENT, GOVT. OF ODISHA ...................................................................... 68 10. CLAIMS: ..................................................................................................................................................... 69 11. DISPUTES................................................................................................................................................... 69 12. NON CONFORMING PRODUCT NOTIFICATIONS (NCPNS). .......................................................................... 71 13. CORRESPONDENCE .................................................................................................................................... 72 14. ENVIRONMENTAL REGULATIONS & CLEARANCES: .................................................................................... 74 15. STATEMENT SHOWING ROAD ACCIDENT CASES FOR THE MONTH: ........................................................... 76 16. EVICTION OF ENCROACHMENTS:............................................................................................................... 76 17. APPENDIX - CONCESSIONAIRE STAFF ......................................................................................................... 78 18. SUMMARY OF TEST RESULTS ..................................................................................................................... 83 19. APPENDIX 3 - LIST OF PLANT AND EQUIPMENT ....................................................................................... 100 23. APPENDIX 4 - LIST OF LAB EQUIPMENT & CALIBRATION STATUS............................................................. 102 24. APPENDIX 5 - CALIBRATION STATUS OF PLANTS ..................................................................................... 106 25. APPENDIX 5 - WEATHER REPORT ............................................................................................................. 107 26. APPENDIX 6 – PHOTOGRAPHS ................................................................................................................. 108 M/s. SAI MAATARINI TOLLWAYS LIMITED Page 2 SAI MAATARINI TOLLWAYS LIMITED Four Laning of Panikoili – Rimuli Road Section of NH215 from Km 0+000 – 163+000 (Design Length 166+173 Kms) in the state of Odisha under NHDP Phase-III as BOT (Toll) Basis. Monthly Progress Report : March - 2015 1. Project Location Map The Project Site of the Four-Lane divided Project Highway comprises the section of National Highway No 215 commencing from Km 0.000 to Km 163.000 i.e. Panikoili – Rimuli section in the State of Odisha. The present carriageway of the Project Highway is an intermediate lane/twolane/single carriageway. PROJECT ROUTE M/s. SAI MAATARINI TOLLWAYS LIMITED Page 3 SAI MAATARINI TOLLWAYS LIMITED Four Laning of Panikoili – Rimuli Road Section of NH-215 from Km 0+000 – 163+000 (Design Length 166+173 Kms) in the state of Odisha under NHDP Phase-III as BOT (Toll) Basis. Monthly Progress Report : March - 2015 2. Scope of the Project S.NO. 1 2 3 4 DESCRIPTION 5 6 7 8 i) ii) iii) iv) iv) 9 a) b) c) d) e) f) g) Project Design Stretch Project Cost (INR) Construction Period Concession Period : : : : Appointed Date Financial Close Scheduled Date of Completion Details of Project Highway Carriageway Length Bypasses Length Realignment Length Sub Total Service/Slip Roads Built-up Area Details of Project Structures Flyovers / Elevated Structures ROBs Major Bridges RUBs Minor Bridges PUPs/Cattle Crossings VUPs : : : : : : : : : : : : : : : : : : M/s. SAI MAATARINI TOLLWAYS LIMITED REAMRKS Km 0+000 to Km 166+200 (Design Length: 166.173 KM) 1,410 Cr. VGF Rs.548.49 Cr. 910 Days 24 Years including Construction Period 02/05/2013 04/09/2013 29/10/2015 Existing 163.000 Km 163.000 Km Existing 2 Nos 5 Nos 1 No 32 Nos - Proposed 127.807 Km 32.800 Km 5.566 Km 166.173 Km 42.336 Km 5.400 Km Proposed 1 No 2 Nos 6 Nos 30 Nos 21 Nos 15 Nos Page 4 SAI MAATARINI TOLLWAYS LIMITED Four Laning of Panikoili – Rimuli Road Section of NH-215 from Km 0+000 – 163+000 (Design Length 166+173 Kms) in the state of Odisha under NHDP Phase-III as BOT (Toll) Basis. Monthly Progress Report : March - 2015 h) i) j) k) l) m) 10 i) ii) iii) iv) v) vi) Animal Underpasses Elephant Underpasses Reptile Underpasses Slab Culverts Box Culverts Pipe Culverts Sub Total Project Facilities / Miscellaneous Grade Intersections Grade Separated Intersections Bus Bays Truck Lay Bays Toll Plazas Wayside Amenities Sub Total M/s. SAI MAATARINI TOLLWAYS LIMITED : : : : : : : : : : : : : : 202 Nos 4 Nos 48 Nos 294 Nos 6 Nos 2 Nos 50 Nos min. 04 Nos 256 Nos 38 Nos 431 Nos 12 Nos 1 No 43 Nos 4 Nos 3 Nos 2 Nos 65 Nos Page 5 SAI MAATARINI TOLLWAYS LIMITED Four Laning of Panikoili – Rimuli Road Section of NH-215 from Km 0+000 – 163+000 (Design Length 166+173 Kms) in the state of Odisha under NHDP Phase-III as BOT (Toll) Basis. Monthly Progress Report : March - 2015 3. Procurement of the Site in terms of Length of Project Highway (Km). 3.1 Fragile Working Fronts of Land Available impeding mobilization of Manpower & Machinery: Continuous Stretch Land Available Length <0.500 >0.5 to <1 >1 to <2 >2 to <3 >3 to < 4 >4 to <5 >5 to <6 >6 to <7 >7 to <8 >8 to <9 >9 to <10 >10 Total M/s. SAI MAATARINI TOLLWAYS LIMITED 17.297 14.253 27.757 12.965 20.380 0.000 0.000 0.000 0.000 0.000 0.000 0.000 92.652 Minor Hindrance Length 7.389 4.720 1.141 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 13.250 Full Hindrance Length 3.21 6.085 10.930 8.95 3.18 0.000 0.000 0.000 0.000 0.000 0.000 0.000 32.355 Reserve Forest Length 5.091 3.610 19.225 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 27.926 Total 32.987 28.668 59.053 21.915 23.560 0.000 0.000 0.000 0.000 0.000 0.000 0.000 166.183 Page 6 SAI MAATARINI TOLLWAYS LIMITED Four Laning of Panikoili – Rimuli Road Section of NH-215 from Km 0+000 – 163+000 (Design Length 166+173 Kms) in the state of Odisha under NHDP Phase-III as BOT (Toll) Basis. Monthly Progress Report : March - 2015 3.2 Fragile Working Fronts of Land Available impeding mobilization of Manpower & Machinery: Bar Chart Land Available Length Minor Hindrance Length Full Hindrance Length Reserve Forest Length 30.000 25.000 20.000 15.000 10.000 5.000 0.000 Stretch (kKM) <0.500 >0.5 to <1 >1 to <2 >2 to <3 >3 to < 4 >4 to <5 >5 to <6 >6 to <7 >7 to <8 >8 to <9 >9 to <10 >10 1. Continuous stretch of land to be available in possession with Concessionaire for efficient mobilization is at least 10 Kms. 2. Continuous stretch of land to be available in possession with Concessionaire for general mobilization is at least 5 Kms. 3. Any length of land in bits less than the above parameters if available in possession with Concessionaire creates problem for mobilization & efficient execution. The execution in these types of bits shall cause a serious impediment / hindrance to Concessionaire M/s. SAI MAATARINI TOLLWAYS LIMITED Page 7 SAI MAATARINI TOLLWAYS LIMITED Four Laning of Panikoili – Rimuli Road Section of NH-215 from Km 0+000 – 163+000 (Design Length 166+173 Kms) in the state of Odisha under NHDP Phase-III as BOT (Toll) Basis. Monthly Progress Report : March - 2015 3.3. Chainage wise Land Stretches Available: 1 2 Alatiri 3 Alatiri, Patharapada, M.D Jamalpur, Ouapada, Dhanpur, Aliya, 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 JAJPUR BY-PASS Village Name 19 Aliya Aliya, Ghikoili, Benapur Benapur Benapur, Talugaon Benapur, Talugaon Benapur, Talugaon Benapur, Talugaon Benapur, Talugaon Benapur, Talugaon Sanapatuli, Badapatuli, Tentulikhunta Tentulikhunta, Dandakiri Dandakiri Chainage From To 00+000 00+120 00+120 00+140 MA YA A A 0.12 0.02 G Y Available Structure under Arbitration case 00+140 03+350 ME E 3.21 G Available 03+350 03+360 04+200 04+230 05+470 05+500 05+670 05+920 06+340 06+440 06+700 06+820 03+360 04+200 04+230 05+470 05+500 05+670 05+920 06+340 06+440 06+700 06+820 06+880 YA MB YA MC YA MA YA MA YA MA MA YA A B A C A A A A A A A A 0.01 0.84 0.03 1.24 0.03 0.17 0.25 0.42 0.10 0.26 0.12 0.06 Y G Y G Y G Y G Y G G Y Temple Available Diary Form Available Compound wall Available Land under 3A notification & Temple Available Structure under Arbitration case Available Available Maruti Show room 06+880 09+490 MD D 2.61 G Available 09+490 09+820 09+820 10+300 YA MA A A 0.33 0.48 Y G 10+300 10+440 YA A 0.14 Y Land under 3A notification & Temple Available Land acquisition Problem due to non acceptance of compensation by land owner (Internal Problem) Available Land acquisition Problem due to non acceptance of compensation by land owner (Internal Problem) Available Land acquisition Problem due to non acceptance of compensation by land owner (Internal Problem) Available Land acquisition Problem due to non acceptance of compensation by land owner (Internal Problem), Buiral ground & Pvt Pond code Length Land Status 20 Dandakiri, Baladia 10+440 10+580 MA A 0.14 G 21 Baladia, Chandama, Santarapur 10+580 10+673 YA A 0.09 Y 22 10+673 10+790 MA A 0.12 G 23 10+790 11+100 YA A 0.31 Y 11+100 11+400 MA A 0.30 G 11+400 11+695 YA A 0.30 Y 24 25 Chandama, Santarapur M/s. SAI MAATARINI TOLLWAYS LIMITED GOVT Land (Hect) PVT FOREST TOTAL Length 06.45 KM. Sl No. Page 8 SAI MAATARINI TOLLWAYS LIMITED Four Laning of Panikoili – Rimuli Road Section of NH-215 from Km 0+000 – 163+000 (Design Length 166+173 Kms) in the state of Odisha under NHDP Phase-III as BOT (Toll) Basis. Monthly Progress Report : March - 2015 Sl No. Village Name 26 27 28 30 31 Kuanarda, Nayagarh, Naguan Nayagarh, Naguan Naguan, Itapur, Talagarh 32 Talagarh 29 33 34 35 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 Talagarh, Uparagarh, Mangarajpur Talagarh, Uparagarh, Mangarajpur Talagarh, Uparagarh, Mangarajpur, Manjuri, Ragadi Ragadi Ragadi, Korabandi, Kadama, Andhari Andhari Andhari, Jarda Jarda Ramachandrapur Ramachandrapur, Badapadana, Padanpur, Suanpada Suanpada Chainage From To 11+695 12+370 12+370 12+950 12+950 13+150 MB YB MA B B A 0.68 0.58 0.20 G Y G Available Alignment Problem Available 13+150 14+380 MC C 1.23 M Available 14+380 14+490 14+490 15+620 YA MC A C 0.11 1.13 Y G 15+620 15+640 YA A 0.02 Y Land under 3A notification Available Land acquisition Problem due to non acceptance of compensation by land owner (Internal Problem) 15+640 15+930 MA A 0.29 G Available 15+930 16+080 YA A 0.15 Y School building 16+080 19+200 ME E 3.12 G Available 19+200 20+800 FC C 1.60 F Ragadi Reserve Forest 20+800 22+800 MC C 2.00 G Available 22+800 23+000 23+150 23+250 23+350 23+400 24+010 24+680 24+730 24+770 24+930 25+250 26+100 26+200 23+000 23+150 23+250 23+350 23+400 24+010 24+680 24+730 24+770 24+930 25+250 26+100 26+200 26+620 YA MA YA MA YA MB YB GA YA GA YA MB YA MA A A A A A B B A A A A B A A 0.20 0.15 0.10 0.10 0.05 0.61 0.67 0.05 0.04 0.16 0.32 0.85 0.10 0.42 Y G Y G Y G Y G Y G Y G Y G Govt building (Forest dept), School Available Pvt building Available Temple Available Shops, School, P.S, Bank, Market Area Available Structure under Arbitration case Available Market, BSNL building, Hospital Available Encroachments, Shops, Houses Available 26+620 27+150 YB B 0.53 Y Encroachments, Houses 27+150 27+300 MA A 0.15 G Available M/s. SAI MAATARINI TOLLWAYS LIMITED code Length Land Status GOVT Land (Hect) PVT FOREST TOTAL 4.80 Page 9 SAI MAATARINI TOLLWAYS LIMITED Four Laning of Panikoili – Rimuli Road Section of NH-215 from Km 0+000 – 163+000 (Design Length 166+173 Kms) in the state of Odisha under NHDP Phase-III as BOT (Toll) Basis. Monthly Progress Report : March - 2015 YA MA A A 0.08 0.22 Y G 27+600 27+960 YA A 0.36 Y 32 27+960 28+240 MA A 0.28 G 33 28+240 28+350 YA A 0.11 Y 28+350 28+480 MA A 0.13 G 28+480 28+580 YA A 0.10 Y 28+580 28+830 29+000 28+830 29+000 29+250 MA YA MA A A A 0.25 0.17 0.25 G Y G 29+250 29+290 YA A 0.04 Y 29+290 29+500 30+200 30+800 30+940 31+280 29+500 30+200 30+800 30+940 31+280 31+400 MA YB MB YA MA YA A B B A A A 0.21 0.70 0.60 0.14 0.34 0.12 G Y G Y G Y Big Pond Available Land acquisition Problem due to non acceptance of compensation by land owner (Internal Problem) Available Land acquisition Problem due to non acceptance of compensation by land owner (Internal Problem), GP building Available Land acquisition Problem due to non acceptance of compensation by land owner (Internal Problem) Available Houses Available Land acquisition Problem due to non acceptance of compensation by land owner (Internal Problem) Available Sainkula market, PS Available Land under 3A notification Available Temple, Market, Houses Village Name 29 30 31 34 Suanpada, Nuagaon Nuagaon 35 36 37 38 39 RA G 40 41 42 43 44 45 Nuagaon, Gointhagodi Gointhagodi Gointhagodi, Khalana Khalana Khalana, agarda, Sainkula Khalana, agarda, Sainkula Sainkula code Length Land Status 46 Sainkula, Machala,Rudranarayanapur, Bamphidi 31+400 33+100 MC C 1.70 G Available 47 Rudranarayanapur 33+100 33+160 YA A 0.06 Y Land acquisition Problem due to non acceptance of compensation by land owner (Internal Problem) 48 Rudranarayanapur, Bamphidi, Hasanpur 33+160 33+430 MA A 0.27 G Available 49 Hasanpur 33+430 33+670 YA A 0.24 Y 50 51 Hasanpur Hasanpur, Salapada, 33+670 34+050 34+050 37+000 MA MD A D 0.38 2.95 G G M/s. SAI MAATARINI TOLLWAYS LIMITED Land acquisition Problem due to non acceptance of compensation by land owner (Internal Problem) Available Realignment & Major Bridge GOVT Land (Hect) PVT FOREST TOTAL Le ng th 02 .9 5 K M. Chainage From To 27+300 27+380 27+380 27+600 Sl No. Page 10 SAI MAATARINI TOLLWAYS LIMITED Four Laning of Panikoili – Rimuli Road Section of NH-215 from Km 0+000 – 163+000 (Design Length 166+173 Kms) in the state of Odisha under NHDP Phase-III as BOT (Toll) Basis. Monthly Progress Report : March - 2015 Sl No. Village Name Chainage From To 37+000 37+120 38+120 38+400 38+600 38+800 39+800 39+900 40+330 40+650 41+900 42+800 43+400 44+000 44+100 44+480 45+100 46+400 47+580 50+700 52+800 53+400 55+000 55+650 55+700 57+700 58+500 59+000 60+250 62+060 64+900 66+800 69+150 69+300 70+500 74+400 37+120 38+120 38+400 38+600 38+800 39+800 39+900 40+330 40+650 41+900 42+800 43+400 44+000 44+100 44+480 45+100 46+400 47+580 50+700 52+800 53+400 55+000 55+650 55+700 57+700 58+500 59+000 60+250 62+060 64+900 66+800 69+150 69+300 70+500 74+400 74+900 code Length Land Status GOVT Land (Hect) PVT TOTAL FOREST Salapada Salapada Salapada, Sudusudia, Janra Janra Khaparakhai Ghasipura Kainpura Sailong Sailong 65 Morabali 66 67 68 69 70 71 72 73 74 75 Indupura Gohira Talagaon Biragobindapur Bhalukuma Dhakota Amaranga Bandha Nahaguna Kanto 76 Kolimati 77 Kamonda 78 Darkhola Melana 81 Balijodi G H AT G A O N BY PA SS 79 80 82 Balijodi M/s. SAI MAATARINI TOLLWAYS LIMITED MA MB MA YA MA FB MA MA MA MC MB MB MB YA GA GB MC MC ME MD MB MC RB MA RC RB RA RC FC GD FC RD GA FC GE FA A B A A A B A A A C B B B A A B C C E D B C B A C B A C C D C D A C E A 0.12 1.00 0.28 0.20 0.20 1.00 0.10 0.43 0.32 1.25 0.90 0.60 0.60 0.10 0.38 0.62 1.30 1.18 3.12 2.10 0.60 1.60 0.65 0.05 2.00 0.80 0.50 1.25 1.81 2.84 1.90 2.35 0.15 1.20 3.90 0.50 G G G Y G F G G G G G G G Y G G G G G G G G R G R R R R F G F R G F G F Available Available Available Govt Structure Available Salapada Reserve Forest Available Available Available Available Available Available Available Shops, Market Complex & Junctions Available Available Available Available Available Available Available Available Compensation is in process Available Compensation is in process Compensation is in process Compensation is in process Compensation is in process Atai Reserve Forest Available Atai Reserve Forest Compensation is in process Available Atai Reserve Forest Available Atai Reserve Forest 3.788 7.444 11.232 3.000 Length 03.50 KM. Barigaon 1.947 1.129 - 3.076 9.814 5.354 3.448 1.574 - 13.262 6.928 5.430 19.603 2.323 5.700 - 21.926 1.800 5.610 Le ng th 04 .6 0 K M. ANANDAPUR BY-PASS Belabahali, Barigaon 52 53 54 55 56 57 58 59 60 61 62 63 64 Page 11 SAI MAATARINI TOLLWAYS LIMITED Four Laning of Panikoili – Rimuli Road Section of NH-215 from Km 0+000 – 163+000 (Design Length 166+173 Kms) in the state of Odisha under NHDP Phase-III as BOT (Toll) Basis. Monthly Progress Report : March - 2015 Village Name 83 Uperdiha 84 85 86 Kusunpur Kusunpur Golabandha 87 Bataharichandanpur 88 Sanamasinabila 89 90 91 92 93 94 95 96 Sanabarabeda Tikira Nangalkanti Dhenkikote Khantaghar KhajuriJuani Katrabeda Chikinia 97 Pipilia 98 Bankapatuli 99 Gopalapur 100 Gopalapur, Badaposi 101 Badaposi 102 103 104 105 106 Badaposi Jamunalia Tolankbahal 107 108 109 Tulashichaura, Sirispal Chainage From To 74+900 76+520 76+520 78+400 78+400 79+000 79+000 79+400 79+400 81+000 81+000 82+980 82+980 83+600 83+600 84+700 84+700 86+400 86+400 88+380 88+380 89+500 89+500 89+900 89+900 90+500 90+500 92+600 92+600 93+800 93+800 96+100 96+100 98+300 98+300 101+480 101+480 101+980 101+980 102+700 102+700 103+200 103+200 103+800 103+800 107+580 107+580 108+180 108+180 109+200 109+200 110+050 110+050 111+430 111+430 112+900 112+900 113+776 113+776 114+080 114+080 114+194 114+194 114+440 114+440 114+615 114+615 116+615 FC RC RB RA RC RC RB RC FC GC RC GA RB RD GC RD RD RE RA RB GA FB GE GB GC FB GC FC FC MA FA GA FA FC C C B A C C B C C C C A B D C D D E A B A B E B C B C C C A A A A C 1.62 1.88 0.60 0.40 1.60 1.98 0.62 1.10 1.70 1.98 1.12 0.40 0.60 2.10 1.20 2.30 2.20 3.18 0.50 0.72 0.50 0.60 3.78 0.60 1.02 0.85 1.38 1.47 0.88 0.304 0.114 0.246 0.175 2.000 F R R R R R R R F G R G R R G R R R R R G F G G G F G F F G F G F F Atai Reserve Forest Compensation is in process Compensation is in process Compensation is in process Compensation is in process Compensation is in process Compensation is in process Compensation is in process Masinabila Reserve Forest Available Compensation is in process Available Compensation is in process Compensation is in process Available Compensation is in process Compensation is in process Compensation is in process Compensation is in process Compensation is in process Available Pipila Reserve Forest Available Available Available Naranapur Reserve Forest Available Naranapur Reserve Forest Naranapur Reserve Forest Available Sabik Jungle Available Sabik Jungle Village Forest 116+615 116+640 GA A 0.025 G Available 116+640 116+680 116+680 116+850 MA GA A A 0.040 0.170 G G Due to family dispute Available M/s. SAI MAATARINI TOLLWAYS LIMITED code Length Land Status GOVT Land (Hect) PVT TOTAL FOREST 12.040 3.634 8.681 4.180 - 20.721 7.815 7.883 13.254 2.202 2.214 - 10.085 15.467 6.682 6.058 2.493 1.566 5.100 - 6.246 11.934 5.994 10.858 11.344 16.317 4.464 2.177 1.704 3.298 2.695 4.945 18.102 3.577 - 9.174 7.624 10.710 14.112 7.697 14.156 14.039 21.263 21.679 0.900 2.550 7.560 Length 15.65 KM Keonjhar By-pass Sl No. - Page 12 SAI MAATARINI TOLLWAYS LIMITED Four Laning of Panikoili – Rimuli Road Section of NH-215 from Km 0+000 – 163+000 (Design Length 166+173 Kms) in the state of Odisha under NHDP Phase-III as BOT (Toll) Basis. Monthly Progress Report : March - 2015 110 111 112 113 114 115 116 117 118 119 120 121 122 123 124 125 126 127 128 129 130 131 132 133 134 135 136 137 138 139 140 141 142 143 144 145 146 Village Name Sirispal Sidhmath Nizgarh Nizgarh Maligaon Gopinathpur Nuagaon Nuagaon Dhurpada Dhurpada Raisuan Raisuan & Gopinathpur Chainage From To 116+850 117+100 117+100 117+400 117+400 117+710 117+710 120+960 120+960 121+150 121+150 121+380 121+380 121+400 121+400 121+750 121+750 121+821 121+821 123+500 123+500 124+100 124+100 124+300 124+300 125+075 125+075 125+100 125+100 127+080 127+080 127+100 127+100 127+300 127+300 128+840 128+840 128+860 128+860 129+000 129+000 129+020 129+020 129+420 129+420 129+460 129+460 129+650 129+650 129+670 129+670 129+900 129+900 130+340 130+340 130+640 130+640 131+400 131+400 131+420 131+420 132+000 132+000 132+200 132+200 132+260 132+260 132+277 132+277 132+300 132+300 132+337 132+337 132+369 M/s. SAI MAATARINI TOLLWAYS LIMITED code RA GA FA GE FA GA FA GA FA GC FB YA MB GA MC YA MA MC FA MA FA MA GA MA YA RA MA MA YB YA MB FA GA FA YA FA YA Length A A A E A A A A A C B A B A C A A C A A A A A A A A A A B A B A A A A A A 0.250 0.300 0.310 3.250 0.190 0.230 0.020 0.350 0.071 1.679 0.600 0.200 0.775 0.025 1.980 0.020 0.200 1.540 0.020 0.140 0.020 0.400 0.040 0.190 0.020 0.230 0.440 0.300 0.760 0.020 0.580 0.200 0.060 0.017 0.023 0.037 0.032 Land Status R G F G F G F G F G F Y G G G Y G G F G F G G G Y R G G Y Y G F G F Y F Y GOVT Land (Hect) PVT FOREST TOTAL Compensation is in process Available Village Forest Available Village Forest Available Village Forest Available Sabik Jungle Available Village Forest King Fort wall Available Available Available Land Acquation (3A & 3D Missing) Available Available Sabik Jungle Available Sabik Jungle Available Available Available Structure Compensation is in process Available Available Electrical & RWSS Pipe Line Land Acquation (3A & 3D Missing) Available Sabik Jungle Available Sabik Jungle Land Acquation (3A & 3D Missing) Sabik Jungle Land Acquation (3A & 3D Missing) 1.350KM RAG Sl No. Page 13 SAI MAATARINI TOLLWAYS LIMITED Four Laning of Panikoili – Rimuli Road Section of NH-215 from Km 0+000 – 163+000 (Design Length 166+173 Kms) in the state of Odisha under NHDP Phase-III as BOT (Toll) Basis. Monthly Progress Report : March - 2015 179 Silisuan Banajodi Banajodi Banajodi, Padmapur Padmapur, Putulia Putulia Keshpank Jadichatra Jhumpur a ByPass 180 181 182 Bankamarani Chainage From To 132+369 132+515 132+515 132+565 132+565 132+600 132+600 133+420 133+420 133+450 133+450 133+505 133+505 133+580 133+580 134+010 134+010 134+180 134+180 134+475 134+475 134+575 134+575 134+675 134+675 134+890 134+890 134+910 134+910 134+970 134+970 134+980 134+980 135+249 135+249 135+450 135+450 136+010 136+010 136+200 136+200 136+600 136+600 136+900 136+900 136+929 136+929 137+300 137+300 137+343 137+343 137+400 137+400 137+600 137+600 137+920 137+920 138+420 138+420 138+480 138+480 138+500 138+500 138+523 FA MA FA GB YA GA FA GA FA GA FA GA FA GA FA GA FA GA FB GA YA GA FA MA FA GA GA GA GA GA GA FA A A A B A A A A A A A A A A A A A A B A A A A A A A A A A A A A 0.146 0.050 0.035 0.820 0.030 0.055 0.075 0.430 0.170 0.295 0.100 0.100 0.215 0.020 0.060 0.010 0.269 0.201 0.560 0.190 0.400 0.300 0.029 0.371 0.043 0.057 0.200 0.320 0.500 0.060 0.020 0.023 F G F G Y G F G F G F G F G F G F G F G Y G F G F G G G G G G F Sabik Jungle Available Sabik Jungle Available Electrical Available Village Forest Available Village Forest Available Village Forest Available Village Forest Available Village Forest Available Village Forest Available Village Forest Available RWSS Pipe Line Structure Sabik Jungle Available Sabik Jungle Structure Available Available Available Available Available Sabik Jungle 138+523 138+943 FA A 0.420 F Village Forest 138+943 138+963 FA A 0.020 F Sabik Jungle 138+963 139+000 GA A 0.037 G Available 139+000 139+037 FA A 0.037 F Sabik Jungle M/s. SAI MAATARINI TOLLWAYS LIMITED code Length Land Status GOVT Land (Hect) PVT TOTAL FOREST 0.85 KM 147 148 149 150 151 152 153 154 155 156 157 158 159 160 161 162 163 164 165 166 167 168 169 170 171 172 173 174 175 176 177 178 Village Name 1.560 1.170 0.110 0.390 1.670 1.560 Length 3.80 KM RAG Sl No. - Page 14 SAI MAATARINI TOLLWAYS LIMITED Four Laning of Panikoili – Rimuli Road Section of NH-215 from Km 0+000 – 163+000 (Design Length 166+173 Kms) in the state of Odisha under NHDP Phase-III as BOT (Toll) Basis. Monthly Progress Report : March - 2015 Sl No. 183 184 185 186 187 188 189 190 191 192 193 194 195 196 197 198 199 200 201 202 203 204 205 206 207 208 209 210 211 212 213 214 215 216 217 218 219 Village Name Bankamarani, Hundla Jamudiha, Palasponga Palasponga Palasponga, Murusuan Tangarani Jamuposhi ,Spongepatna Jhumpura Jhumpura, Bhaluka & Arsala Arsala Sundhimursuan, Balabhadrapur Chainage From To 139+037 139+469 139+469 139+632 139+632 140+200 140+200 141+310 141+310 142+120 142+120 142+195 142+195 142+205 142+205 142+540 142+540 143+400 143+400 143+465 143+465 144+615 144+615 145+200 145+200 145+210 145+210 145+270 145+270 145+295 145+295 147+760 147+760 148+650 148+650 149+300 149+300 149+620 149+620 149+649 149+649 149+660 149+660 149+680 149+680 149+770 149+770 149+779 149+779 149+800 149+800 149+823 149+823 150+000 150+000 150+042 150+042 150+115 150+115 150+286 150+286 150+430 150+430 150+460 150+460 150+600 150+600 150+800 150+800 152+260 152+260 152+350 152+350 152+380 M/s. SAI MAATARINI TOLLWAYS LIMITED code GA FA GB FC GB GA FA GA RB MA FC RB FA RA FA GD MB RB YA FA MA FA MA FA MA FA MA FA MA FA MA FA MA FA GC GA GA Length A A B C B A A A B A C B A A A D B B A A A A A A A A A A A A A A A A C A A 0.432 0.163 0.568 1.110 0.810 0.075 0.010 0.335 0.860 0.065 1.150 0.585 0.010 0.060 0.025 2.465 0.890 0.650 0.320 0.029 0.011 0.020 0.090 0.009 0.021 0.023 0.177 0.042 0.073 0.171 0.144 0.030 0.140 0.200 1.460 0.090 0.030 Land Status G F G F G G F G R M F R F R F G G R Y F G F G F G F G F G F G F G F G G G Available Sabik Jungle Available Tangarani Reserve Forest Structure Available Village Forest Available Compensation is in process Available Tangarani Reserve Forest Compensation is in process Village Forest Compensation is in process Village Forest Available Available Compensation is in process Structure & RWSS Pipe Line Sabik Jungle Available Sabik Jungle Available Sabik Jungle Available Sabik Jungle Available Sabik Jungle Available Sabik Jungle Available Sabik Jungle Available Sabik Jungle Available Available Available GOVT 2.030 Land (Hect) PVT TOTAL FOREST 1.150 3.180 1.665 1.360 0.250 1.610 5.510 2.470 7.980 2.830 2.830 1.630 1.630 Page 15 SAI MAATARINI TOLLWAYS LIMITED Four Laning of Panikoili – Rimuli Road Section of NH-215 from Km 0+000 – 163+000 (Design Length 166+173 Kms) in the state of Odisha under NHDP Phase-III as BOT (Toll) Basis. Monthly Progress Report : March - 2015 220 221 222 223 224 225 226 227 228 229 230 231 RAG 232 233 234 235 236 237 238 239 240 241 242 243 244 245 246 247 248 249 250 251 Village Name Balabhadrapur Balabhadrapur, Patabila Balaibandh,Mursuan Mursuan Mursuan,Parsala, Sijukala 252 Chainage From To 152+380 152+430 152+430 152+510 152+510 153+040 153+040 153+140 153+140 153+200 153+200 153+530 153+530 153+600 153+600 154+900 154+900 155+000 155+000 155+180 155+180 155+700 155+700 156+200 156+200 156+460 156+460 157+090 157+090 158+405 158+405 158+415 158+415 159+400 159+400 159+415 159+415 159+590 159+590 159+618 159+618 159+690 159+690 159+890 159+890 160+110 160+110 160+380 160+380 160+445 160+445 160+573 160+573 160+675 160+675 160+728 160+728 161+085 161+085 161+099 161+099 162+240 162+240 162+270 162+270 163+000 GA RA GB RA YA RA GA FC GA RA GB RA YA GB FC FA GB FA GA FA GA FA GA FA GA FA GA FA GA FA GC FA MB A A B A A A A C A A B A A B C A B A A A A A A A A A A A A A C A B 0.050 0.080 0.530 0.100 0.060 0.330 0.070 1.300 0.100 0.180 0.520 0.500 0.260 0.630 1.315 0.010 0.985 0.015 0.175 0.028 0.072 0.200 0.220 0.270 0.065 0.128 0.102 0.053 0.357 0.014 1.141 0.030 0.730 G R G R Y R G F G R G R Y G F F G F G F G F G F G F G F G F G F G Available Compensation is in process Available Compensation is in process Structure Compensation is in process Available Balibandha Reserve Forest Available Compensation is in process Available Compensation is in process RWSS Pipe Line Available Balibandha Reserve Forest Village Forest Available Sabik Jungle Available Sabik Jungle Available Sabik Jungle Available Sabik Jungle Available Sabik Jungle Available Sabik Jungle Available Sabik Jungle Available Village Forest Available 163+000 164+715 MC C 1.715 G Available 164+715 165+010 FA A 0.295 F Village Forest code Length Land Status GOVT Land (Hect) PVT TOTAL FOREST 3.250 3.250 3.900 1.80 KM Sl No. 9.740 Parsala, Sijukala 253 M/s. SAI MAATARINI TOLLWAYS LIMITED Page 16 SAI MAATARINI TOLLWAYS LIMITED Four Laning of Panikoili – Rimuli Road Section of NH-215 from Km 0+000 – 163+000 (Design Length 166+173 Kms) in the state of Odisha under NHDP Phase-III as BOT (Toll) Basis. Monthly Progress Report : March - 2015 Sl No. 254 Village Name Rimuli Chainage From To 165+010 166+173 code MC Length C 1.173 Land Status G Description Type A. Vacant access & ROW Available Length (KM) G B. Land available with missing bits / serious hindrances at Jajpur Dist. G C. Land available with missing bits / serious hindrances at Keonjhar G Dist. Land available (A+B+C) refer Lr. No. 375 dt: 25-09-14 after deliberations in review meeting on 3-9-14 &I.E. Lr. No. 401 dt:16-914 Minor Hindrance Length (KM) Y Compensation Not Paid R Full Hindrance Length (KM) Reserve Forest (151.94 Hec.) F Total Length (KM)>>> GOVT Land (Hect) PVT TOTAL FOREST Available Total Length 40.332 19.532 (%) 24.27% 11.75% 37.115 22.33% 97.143 58.46% 9.103 32.275 27.652 166.173 5.48% 36.06% 27.652 40.332 G Y 32.275 19.532 R F 37.115 9.103 100% Note: RAG - Realignment M/s. SAI MAATARINI TOLLWAYS LIMITED Page 17 SAI MAATARINI TOLLWAYS LIMITED Four Laning of Panikoili – Rimuli Road Section of NH-215 from Km 0+000 – 163+000 (Design Length 166+173 Kms) in the state of Odisha under NHDP Phase-III as BOT (Toll) Basis. Monthly Progress Report : March - 2015 Jajpur District: 1. Missing Bits about 517 bits from Appointed Date for which compensation is to be paid for these obstacle pockets between Km 0+000 & 24+000 2. Govt. / Religious Structures: 07 Nos. Thasil Name Govt. Structures Vysanagar 6 Length (M) Religious Structures 410 1 Length (M) Total Structures 50 7 Total Length (M) 460 3. HT lines at Km 7+010 & Km 7+670 (between Km 6+750 & Km 8+000 = 1.250) 4. Irrigation Canals – 9 Nos. (Ch: 23+500, 23+500, 20+280, 19+850, 18+490, 16+330, 7+300, 5+610 & 0+850) Keonjhar district: 1. Realignment at Major Bridge at Km 35+315 - 5Kms 2. Govt. / Religious Structures: 159 Nos. Thasil Name Govt. Structures A Ghasipura & Anandapur Ghatgaon Sadar JHUMPURA CHAMPUA Total 3. 4. 5. 6. 7. 8. B 49 24 44 18 3 138 Length (M) C 7520 4930 6288 2167 423 21328 Religious Structures D 13.00 5.00 3.00 21 Length (M) E 750 457 323 1530 Total Structures F=B+D 62 24 49 18 6 159 Total Length (M) G=C+E 8270 4930 6745 2167 746 22858 Hindrance created by Amarang villagers in Km 53+000 to Km 54+000 - 1Km Irrigation Canals – 22 Nos. Obstruction of Siba temple @ Km 113+400 in Jamunalia Left out structures of 18 villages of Sadar, Champuva & Jumpura thasils Stalemate in Arshala Village Km 149+300 to 150+500 = 1.20 Kms Demolition of Boundary wall of OSIL at Km 144+900 to 145+600 =0.700 Km M/s. SAI MAATARINI TOLLWAYS LIMITED Page 18 SAI MAATARINI TOLLWAYS LIMITED Four Laning of Panikoili – Rimuli Road Section of NH-215 from Km 0+000 – 163+000 (Design Length 166+173 Kms) in the state of Odisha under NHDP Phase-III as BOT (Toll) Basis. Monthly Progress Report : March - 2015 9. Missing plots in the Keonjhar District (Km 24+000 to Km 166+173) : the list of missing bits were communicated to PD vide this office Lr. No. 503 dated 30-12-2014 Sl. No. 1 2 Name of Thasil Ghatagaon Ghasipura No of left out plots 54 86 Additional Area (Acre) 3.940 3.850 19 1.050 3 Anandapur 4 Champua 4 1.100 5 6 Sadar Jhumpura 25 6 2.095 0.560 194 12.595 Total : 10. Minor Bridges at KM 148+457 & Km 149+027 (2 Nos) in Jumpura Bypass at Bhaluka village = 1.50 Kms Prevention of execution in between Km 166+000 to Km 166+173 by villagers for higher compensation = 0.173 Km M/s. SAI MAATARINI TOLLWAYS LIMITED Page 19 SAI MAATARINI TOLLWAYS LIMITED Four Laning of Panikoili – Rimuli Road Section of NH-215 from Km 0+000 – 163+000 (Design Length 166+173 Kms) in the state of Odisha under NHDP Phase-III as BOT (Toll) Basis. Monthly Progress Report : March - 2015 [ 4. Preconstruction Activities A. Shifting of Electrical Poles Sl. No Erection: 1 2 3 4 a) b) c) d) e) f) g) h) i) 5 a) b) c) d) 6 7 8 9 10 11 12 13 14 15 16 17 18 Description Unit Concreting of Poles 9m PSC Poles (300 KG) Sub-Total >>> Electrical Sub-Stations Transformers 250 KVA 11/0.4 KV 150 KVA 11/0.4 KV 100 KVA 11/0.4 KV 100 KVA 11/0.23 KV 63 KVA 11/0.4 KV 25 KVA 11/0.4 KV 16 KVA 11/0.4 KV 16 KVA 11/0.23 KV 10 KVA 11/0.23 KV Sub-Total >>> RS Joist A) 150/150 18M B) 150/150 15M C) 150/150 13M D) 150/150 11M 8 m Joist Poles 8m PSC Poles 200 Kgs. 9m PSC Poles Kgs. 11m Joist Poles Sub-Total >>> 3PH 4W LT Line 1PH 4W LT Line 3x50+1x35+1x16 sq.mm. AB Cable 3x50+1x35 sq.mm. AB Cable 3x35+1x25 sq.mm. AB Cable 1x35+1x25 sq.mm. AB Cable 33 KV HT Line 33KV 3Ph. 3W with 1002mm AAA conductor 11KV 3Ph. 3W with 802mm AAA Conductor Nos Nos Nos Nos Nos Nos Nos Nos Nos Nos Nos Nos Nos Nos Nos Nos Nos Nos Nos Nos Nos Km Km Km.0+000 to Km.24+000 Total Done Balance 352 91 443 14 1 218 75 293 1 1 1 1 5 3 1 2 28 1 5 3 1 2 14 12 40 222 85 148 23 3 533 4 0 20 155 17 192 4 0 Km.24+000 to Km.113+000 Total Done Balance 134 16 150 14 0 0 0 0 0 0 0 0 0 0 14 0 12 0 20 67 85 148 6 3 341 0 0 1107 456 1563 61 693 350 1043 31 90 11 9 48 23 12 194 3 1 979 354 1333 61 0 2 0 6 0 9 13 2 11 7 111 0 0 46 521 0 9 0 0 0 576 0 0 566 13.7 136 8.3 0 0 0 0 0 20.5 1.1 3 9 0.51 7.212 7.21 0.51 20.5 1.1 3 9 0 2 0 13 0 10 15 2 11 8 122 1 46 611 11 18 48 23 12 770 3 1 128 102 230 7 1 2 1 11 1 Km Km Km Km Km 0 Km 21 1 20 20.5 8.1 12.4 Km 12 12 0 17.9 0.3 17.6 M/s. SAI MAATARINI TOLLWAYS LIMITED Km.113+000 to Km.163+000 Total Done Balance 264 274 538 1 1 6 4 10 1 6 2 62 0 26 540 0 1 1 136 16.8 22 3.38 Km.0+000 to Km.163+000 Total Done Balance 429 76 505 31 0 1 1 6 0 3 10 1 6 2 61 0 0 26 404 0 0 0 0 0 430 5.4 0 2152 897 3049 106 1 3 1 20 0 15 30 6 18 12 212 0 13 72 1191 233 103 196 46 15 1869 20.7 1 610 451 1061 0 1 0 0 8 0 3 7 3 1 3 26 0 1 0 246 166 9 48 40 12 522 15.3 1 1542 446 1988 106 0 3 1 12 0 12 23 3 17 9 186 0 12 72 945 67 94 148 6 3 1347 5.4 0 0 0 0 0 16.8 27.71 1.1 3 9 17.31 7.212 0 0 0 0.51 20.5 1.1 3 9 16.8 0 41.5 9.1 32.4 18.62 51.9 15.68 36.22 Remarks Page 20 SAI MAATARINI TOLLWAYS LIMITED Four Laning of Panikoili – Rimuli Road Section of NH-215 from Km 0+000 – 163+000 (Design Length 166+173 Kms) in the state of Odisha under NHDP Phase-III as BOT (Toll) Basis. Monthly Progress Report : March - 2015 [ Sl. No Description Unit Km.0+000 to Km.24+000 Total Done Balance Km.24+000 to Km.113+000 Total Done Balance Km.113+000 to Km.163+000 Total Done Balance Km.0+000 to Km.163+000 Total Done Balance Remarks 1002mm 19 20 Dismantling: 21 22 23 24 25 26 27 28 29 11KV 3Ph. 3W with AAA Conductor 11KV 3Ph. 3W HT Lines Sub-Total >>> Km Km 55 sq.mm AAA Conductor 80 sq.mm AAA Conductor 100 sq.mm AAA Conductor 34 mm2 AAA Conductor 11 KV Line 33 KV Line LT Line Electrical poles removing BSNL poles Sub-Total >>> Km Km Km Km Km Km Km Nos Nos Km 12 49 12 29 12 12 21 8 1 2 5 0 48 2 5 0 20 0 0 20 8.47 1.5 86.48 0 0 20 8 0 0 0 0 0 28 90 59 53.4 1.53 21.5 1.8 1.61 70 5 303.8 1.5 14.41 90 1.53 1.2 1.8 1.61 70 5 171.1 8.47 0 72.07 0 59 53.4 0 20.3 0 0 0 0 132.7 22 81.71 4.71 23.6 73 7.29 23.5 17.55 6.2 11.7 0 0 132 0 0 7.29 0 17.29 58.11 8.47 35.5 217.2 0 18.21 67.01 8.47 17.29 150.18 65.71 0 23.5 0 17.55 6.2 11.7 0 0 124.66 175 59 97.9 9.53 39.05 8 15.31 75 5 483.8 109.3 0 1 1.53 1.2 1.8 3.61 75 5 198.4 65.71 59 96.9 8 37.85 6.2 11.7 0 0 285.36 B. Tree Felling Sl. No. A 1 2 3 4 5 Chainage (Km) From To B C 0+000 24+000 24+000 58+000 58+000 107+000 104+600 113+100 113+300 143+000 143+000 163+000 Total Length D 24 34 49 8.50 29.90 20 D.F.O. Estimate Lr. No. E 1171 1171 1520 1520 M/s. SAI MAATARINI TOLLWAYS LIMITED No of Trees as per Estimate DL. Revised Estimate sanction (Rs.) at Site Felled Balance No. DFO PIU / RO Authority F 1054 1197 4848 1027 4458 2501 15085 G 1054 1197 4771 164 4338 2415 13939 H=F-G 77 863 120 86 1146 I 36 J 1185875 2535000 22330839 K L 2091000 Approved 22330839 Approved 39 9284356 9284356 35 8088566 43424636 8088566 Approved 43424636 - Page 21 SAI MAATARINI TOLLWAYS LIMITED Four Laning of Panikoili – Rimuli Road Section of NH-215 from Km 0+000 – 163+000 (Design Length 166+173 Kms) in the state of Odisha under NHDP Phase-III as BOT (Toll) Basis. Monthly Progress Report : March - 2015 [ C. RWS&S & PH Estimates: Status of revised estimates “RWS&S and PH pipe lines & Tube Wells shifting” Description Revised Estimate Amount Sanction from Authority a Km 0+000 to Km 24+000 Rs. 9,80,483 Yet to be received Work in Progress b Km 24+000 to Km 163+000 Rs. 2,10,19,000 Yet to be received Work in Progress Sl. No. Sub Total : (+/-) Remarks Rs. 2,19,99,483 These estimates which were prepared based on SSR 2007-08 were revised with current SSR (2013-14) by Line department; are to be got sanctioned by PIU from authority. a) RWS&S Tube Wells Shifting SL No. District 1 2 3 4 5 6 7 Jajpur Keonjhar Keonjhar Keonjhar Keonjhar Keonjhar Keonjhar Tahasil Jajpur Anandapur Ghasipura Ghatgaon Keonjhar Jhumpura Champura Total No of Tube Wells to be Shifted 6 6 8 17 20 8 4 69 No of Tube Wells Shifted 4 3 1 8 No of Tube Wells to be Shifted 5 3 8 77 No of Tube Wells Shifted 0 8 Percentage Progress (%) Remarks 66.67% 0.00% 0.00% 0.00% 15.00% 0.00% 25.00% 11.59% Estimate dated 24-10-2013 Percentage Progress (%) Remarks b) PH Tube Wells Shifting SL No. District 1 2 Keonjhar Keonjhar Tahasil Anandapur Keonjhar Total Grand Total: M/s. SAI MAATARINI TOLLWAYS LIMITED 0 10.39% Page 22 SAI MAATARINI TOLLWAYS LIMITED Four Laning of Panikoili – Rimuli Road Section of NH-215 from Km 0+000 – 163+000 (Design Length 166+173 Kms) in the state of Odisha under NHDP Phase-III as BOT (Toll) Basis. Monthly Progress Report : March - 2015 5. Status of Designs & Drawings A. Plan & Profile : From Km 0+000 to Km 166+173: finalized in conformance of the provisions of C.A. & IRC Codes. B. Structures: The Structural drawings are being confirmed as is consistent with the phased requirement for execution of work. i. Major Bridges : 06 Nos. ii. Minor Bridges : 30 Nos. iii. Flyover : 01 No. iv. ROBs : 02 Nos. v. VUPs : 15 Nos. vi. PUPs : 21 Nos. vii. AUPs : 06 Nos. viii. EUPs : 02 Nos. ix. Box/Slab/Pipe Culverts : 295 Nos. x. RUPs : 50 Nos. min. M/s. SAI MAATARINI TOLLWAYS LIMITED Page 23 SAI MAATARINI TOLLWAYS LIMITED Four Laning of Panikoili – Rimuli Road Section of NH215 from Km 0+000 – 163+000 (Design Length 166+173 Kms) in the state of Odisha under NHDP Phase-III as BOT (Toll) Basis. Monthly Progress Report : March - 2015 6. Physical Progress 6.1. Physical Progress Project Length Km =163+173 Bill No. A I III B I II III IV V VI VII VIII IX X C I II III IV V VI VII a b VIII Description Pre Construction Activity Site Clearance Dismantling of Structures Road Works Widening Side Existing Side Service Roads LHS Service Roads RHS Bypass LHS Bypass RHS Drainage & Protective Works Highway Lighting Road Appaurantances Toll Plaza Structures ROB Flyover Underpass (VUP,PUP,AUP&EUP) Major Bridges Minor Bridges Pipe Culverts Box & Slab Culverts (i) Culvert Area between 0 & 10 (ii) Culvert Area between 10 & 20 (iii) Culvert Area Above 20 (c) Rehabilitation Repair / Widening of Culverts Retaining / Toe wall Total : Material procured as on date: Grand Total : % Completion % weightage of Contract Value Upto Date Till Previous Month For this Month 0.704% 0.091% 0.453% 0.083% 0.431% 0.082% 0.022% 0.001% 23.826% 16.258% 2.526% 2.526% 8.327% 8.327% 8.990% 0.190% 1.208% 1.651% 8.795% 0.501% 0.033% 0.014% 2.381% 2.310% 0.000% 0.000% 0.000% 0.000% 7.340% 0.185% 0.031% 0.009% 1.798% 1.838% 0.000% 0.000% 0.000% 0.000% 1.455% 0.316% 0.003% 0.005% 0.584% 0.473% 0.000% 0.000% 0.000% 0.000% 0.695% 0.158% 4.528% 1.716% 3.370% 0.054% 0.253% 0.091% 2.762% 0.379% 1.286% 0.031% 0.237% 0.080% 2.592% 0.340% 1.148% 0.026% 0.016% 0.010% 0.170% 0.039% 0.138% 0.005% 7.821% 1.112% 0.431% 2.974% 0.705% 0.114% 2.769% 0.700% 0.092% 0.205% 0.005% 0.022% 0.144% 0.000% 0.000% 0.000% 5.347% 100.00% 2.564% 25.730% 2.062% 21.760% 0.502% 3.969% 2.270% 28.000% 3.447% 25.208% -1.177% 2.792% M/s. SAI MAATARINI TOLLWAYS LIMITED Page 24 SAI MAATARINI TOLLWAYS LIMITED Four Laning of Panikoili – Rimuli Road Section of NH215 from Km 0+000 – 163+000 (Design Length 166+173 Kms) in the state of Odisha under NHDP Phase-III as BOT (Toll) Basis. Monthly Progress Report : March - 2015 6.2. Financial Progress (As per Revised Programme) Sl. No. A B C D Description Target (Rs. in Cr.) Achieved (Rs. in Cr.) Percentage (B vs A) % wrt TCC** (Rs. 2020 Cr.) Cum. Upto (Dec’14) *1322.80 *918.22 69.41 45.46 Month (Jan’15) *115.88 69.23 59.74 3.43 Cumulative (Jan’15) 1438.68 987.45 68.64 48.88 * Includes mobilization fee 20% of contract price as per Cl 7.3(b) of EPC Agreement. * *TCC – Total Contract Cost M/s. SAI MAATARINI TOLLWAYS LIMITED Page 25 SAI MAATARINI TOLLWAYS LIMITED Four Laning of Panikoili – Rimuli Road Section of NH-215 from Km 0+000 – 163+000 (Design Length 166+173 Kms) in the state of Odisha under NHDP Phase-III as BOT (Toll) Basis. Monthly Progress Report : March - 2015 PROJECT COMPLETION SCHEDULE (PCS) AS PER SCHEDULE-G OF C.A. Appoint Date : Description 02-05-13 May'13 Jun'13 As per C.A. Achieved in Cr. Cum. in Cr. Percentage (%) Description As per C.A. Achieved in Cr. Cum. in Cr. Percentage (%) Sep'14 Oct'14 27.52 694.32 34.37% 23.57 717.89 35.54% Project Cost (Rs. In Cr.): Milestone-1 (A.D.: 29-10-13 ; G.P.: 26-01-14) Jul'13 Aug'13 Sep'13 Oct'13 Nov'13 202 404.00 404.00 20.00% Milestone-3 (A.D.: 10-02-15; G.P.: 11--05-15) Nov'14 Dec'14 Jan'15 Feb'15 Mar'15 1414 29.56 47.73 64.43 60.75 69.23 747.45 795.18 859.61 920.36 987.45 37.00% 39.37% 42.55 45.56 48.88 A.D.: Well within time as set forth in Schedule-G Dec'13 Jan'14 Feb'14 18.13 422.13 20.90% 31.08 453.21 22.44% 34.52 487.73 24.15% Apr'15 May'15 Jun'15 2,020 Milestone-2 (A.D.: 05-06-14; G.P.: 03-09-14) Mar'14 Apr'14 May'14 Jun'14 Jul'14 606 29.48 33.37 31.10 30.23 21.40 517.21 550.58 581.68 611.91 633.31 25.60% 27.26% 28.80% 30.29% 31.35% COD (A.D.: 28-10-15) Jul'15 Aug'15 Sep'15 2020 G.P.: Within grace period of 90 days pursuant to Cl. 12.4.2 of C.A. Aug'14 33.49 666.80 33.01% Oct'15 Beyond the grace period Milestone – I: Occurred within the grace period pursuant to Cl. 12.4.2 of C.A.; as acquiesced by I.E. vide Lr. No. SAI-3521-2014 dated 03-09-2014 Milestone–II: Occurred within the grace period pursuant to Cl. 12.4.2 of C.A.; which is to be acquiesced by I.E. after furnishing the Company’s Statutory Auditor’s Certificate by Concessionaire. M/s. SAI MAATARINI TOLLWAYS LIMITED Page 26 SAI MAATARINI TOLLWAYS LIMITED Four Laning of Panikoili – Rimuli Road Section of NH-215 from Km 0+000 – 163+000 (Design Length 166+173 Kms) in the state of Odisha under NHDP Phase-III as BOT (Toll) Basis. Monthly Progress Report : March - 2015 7. Strip chart of work progress BC DBM WMM-Top WMM-1st GSB SG-Top SG-IInd SG-Ist EMB-6th EMB-5th EMB-4th EMB-3rd EMB-2nd Exc. Upto Emb. Top LHS EMB-Top EMB-1st OGL Record OGL FDD C&G Chainage 0.000 0.050 0.100 0.150 0.200 0.250 0.300 0.350 0.400 0.450 0.500 0.550 0.600 0.650 0.700 0.750 0.800 0.850 0.900 0.950 1.000 1.050 1.100 1.150 1.200 1.250 1.300 1.350 1.400 1.450 1.500 1.550 1.600 1.650 1.700 1.750 1.800 1.850 1.900 1.950 2.000 2.050 2.100 2.150 2.200 2.250 2.300 2.350 2.400 2.450 2.500 2.550 2.600 2.650 2.700 2.750 2.800 2.850 2.900 2.950 3.000 3.050 3.100 3.150 3.200 3.250 3.300 3.350 3.400 3.450 3.500 3.550 3.600 3.650 3.700 3.750 3.800 3.850 3.900 3.950 4.000 4.050 4.100 4.150 4.200 4.250 4.300 4.350 4.400 4.450 4.500 4.550 4.600 4.650 4.700 4.750 4.800 4.850 4.900 4.950 5.000 OGL Samp. Testing OGL Samp. Testing C &G OGL FDD OGL Record EMB-1st EMB-2nd EMB-3rd RHS EMB-4th EMB-5th EMB-6th EMB-Top SG-Ist SG-IInd SG-Top GSB WMM-1st WMM-Top DBM BC M/s. SAI MAATARINI TOLLWAYS LIMITED Page 27 SAI MAATARINI TOLLWAYS LIMITED Four Laning of Panikoili – Rimuli Road Section of NH-215 from Km 0+000 – 163+000 (Design Length 166+173 Kms) in the state of Odisha under NHDP Phase-III as BOT (Toll) Basis. Monthly Progress Report : March - 2015 BC DBM WMM-Top WMM-1st GSB SG-Top SG-IInd SG-Ist LHS EMB-Top EMB-6th 8 EMB-5th EMB-4th EMB-3rd EMB-2nd EMB-1st OGL Record OGL FDD C&G Chainage 5.000 5.050 5.100 5.150 5.200 5.250 5.300 5.350 5.400 5.450 5.500 5.550 5.600 5.650 5.700 5.750 5.800 5.850 5.900 5.950 6.000 6.050 6.100 6.150 6.200 6.250 6.300 6.350 6.400 6.450 6.500 6.550 6.600 6.650 6.700 6.750 6.800 6.850 6.900 6.950 7.000 7.050 7.100 7.150 7.200 7.250 7.300 7.350 7.400 7.450 7.500 7.550 7.600 7.650 7.700 7.750 7.800 7.850 7.900 7.950 8.000 8.050 8.100 8.150 8.200 8.250 8.300 8.350 8.400 8.450 8.500 8.550 8.600 8.650 8.700 8.750 8.800 8.850 8.900 8.950 9.000 9.050 9.100 9.150 9.200 9.250 9.300 9.350 9.400 9.450 9.500 9.550 9.600 9.650 9.700 9.750 9.800 9.850 9.900 9.950 10.000 OGL Samp. Testing OGL Samp. Testing C &G OGL FDD OGL Record EMB-1st EMB-2nd EMB-3rd RHS EMB-4th EMB-5th EMB-6th 9 EMB-Top SG-Ist SG-IInd SG-Top GSB WMM-1st WMM-Top DBM BC M/s. SAI MAATARINI TOLLWAYS LIMITED Page 28 RHS EMB-6th Chainage EMB-6th 10.000 10.050 10.100 10.150 10.200 10.250 10.300 10.350 10.400 10.450 10.500 10.550 10.600 10.650 10.700 10.750 10.800 10.850 10.900 10.950 11.000 11.050 11.100 11.150 11.200 11.250 11.300 11.350 11.400 11.450 11.500 11.550 11.600 11.650 11.700 11.750 11.800 11.850 11.900 11.950 12.000 12.050 12.100 12.150 12.200 12.250 12.300 12.350 12.400 12.450 12.500 12.550 12.600 12.650 12.700 12.750 12.800 12.850 12.900 12.950 13.000 13.050 13.100 13.150 13.200 13.250 13.300 13.350 13.400 13.450 13.500 13.550 13.600 13.650 13.700 13.750 13.800 13.850 13.900 13.950 14.000 14.050 14.100 14.150 14.200 14.250 14.300 14.350 14.400 14.450 14.500 14.550 14.600 14.650 14.700 14.750 14.800 14.850 14.900 14.950 15.000 LHS SAI MAATARINI TOLLWAYS LIMITED Four Laning of Panikoili – Rimuli Road Section of NH-215 from Km 0+000 – 163+000 (Design Length 166+173 Kms) in the state of Odisha under NHDP Phase-III as BOT (Toll) Basis. Monthly Progress Report : March - 2015 BC DBM WMM-Top WMM-1st GSB SG-Top SG-IInd SG-Ist EMB-Top EMB-5th 7 M/s. SAI MAATARINI TOLLWAYS LIMITED 9 EMB-4th EMB-3rd EMB-2nd EMB-1st OGL Record OGL FDD C&G OGL Samp. Testing OGL Samp. Testing C&G OGL FDD OGL Record EMB-1st EMB-2nd EMB-3rd EMB-4th EMB-5th EMB-Top 7 SG-Ist SG-IInd SG-Top GSB WMM-1st WMM-Top DBM BC Page 29 RHS EMB-6th Chainage 15.000 15.050 15.100 15.150 15.200 15.250 15.300 15.350 15.400 15.450 15.500 15.550 15.600 15.650 15.700 15.750 15.800 15.850 15.900 15.950 16.000 16.050 16.100 16.150 16.200 16.250 16.300 16.350 16.400 16.450 16.500 16.550 16.600 16.650 16.700 16.750 16.800 16.850 16.900 16.950 17.000 17.050 17.100 17.150 17.200 17.250 17.300 17.350 17.400 17.450 17.500 17.550 17.600 17.650 17.700 17.750 17.800 17.850 17.900 17.950 18.000 18.050 18.100 18.150 18.200 18.250 18.300 18.350 18.400 18.450 18.500 18.550 18.600 18.650 18.700 18.750 18.800 18.850 18.900 18.950 19.000 19.050 19.100 19.150 19.200 19.250 19.300 19.350 19.400 19.450 19.500 19.550 19.600 19.650 19.700 19.750 19.800 19.850 19.900 19.950 20.000 LHS SAI MAATARINI TOLLWAYS LIMITED Four Laning of Panikoili – Rimuli Road Section of NH-215 from Km 0+000 – 163+000 (Design Length 166+173 Kms) in the state of Odisha under NHDP Phase-III as BOT (Toll) Basis. Monthly Progress Report : March - 2015 BC DBM WMM-Top WMM-1st GSB SG-Top SG-IInd SG-Ist EMB-Top EMB-5th 9 7 M/s. SAI MAATARINI TOLLWAYS LIMITED 7 9 EMB-4th EMB-3rd EMB-2nd EMB-1st OGL Record OGL FDD C&G OGL Samp. Testing OGL Samp. Testing C&G OGL FDD OGL Record EMB-1st EMB-2nd EMB-3rd EMB-4th EMB-5th EMB-6th EMB-Top SG-Ist SG-IInd SG-Top GSB WMM-1st WMM-Top DBM BC Page 30 RHS Chainage EMB-4th EMB-3rd EMB-2nd EMB-1st OGL Record OGL FDD OGL FDD OGL Record EMB-1st EMB-2nd EMB-3rd EMB-4th M/s. SAI MAATARINI TOLLWAYS LIMITED EMB-5th 9 10th Layer 8th Layer Exc. Upto Emb. Top 14 Exc. Upto Emb. Top Exc. Upto Emb. Top 14 EXC upto Emb Top EMB-6th 20.000 20.050 20.100 20.150 20.200 20.250 20.300 20.350 20.400 20.450 20.500 20.550 20.600 20.650 20.700 20.750 20.800 20.850 20.900 20.950 21.000 21.050 21.100 21.150 21.200 21.250 21.300 21.350 21.400 21.450 21.500 21.550 21.600 21.650 21.700 21.750 21.800 21.850 21.900 21.950 22.000 22.050 22.100 22.150 22.200 22.250 22.300 22.350 22.400 22.450 22.500 22.550 22.600 22.650 22.700 22.750 22.800 22.850 22.900 22.950 23.000 23.050 23.100 23.150 23.200 23.250 23.300 23.350 23.400 23.450 23.500 23.550 23.600 23.650 23.700 23.750 23.800 23.850 23.900 23.950 24.000 24.050 24.100 24.150 24.200 24.250 24.300 24.350 24.400 24.450 24.500 24.550 24.600 24.650 24.700 24.750 24.800 24.850 24.900 24.950 25.000 LHS SAI MAATARINI TOLLWAYS LIMITED Four Laning of Panikoili – Rimuli Road Section of NH-215 from Km 0+000 – 163+000 (Design Length 166+173 Kms) in the state of Odisha under NHDP Phase-III as BOT (Toll) Basis. Monthly Progress Report : March - 2015 BC DBM WMM-Top WMM-1st GSB SG-Top SG-IInd SG-Ist EMB-Top 14 C&G OGL Samp. Testing OGL Samp. Testing C&G EMB-5th EMB-6th EMB-Top SG-Ist SG-IInd SG-Top GSB WMM-1st WMM-Top DBM BC Page 31 RHS EMB-6th Chainage 25.000 25.050 25.100 25.150 25.200 25.250 25.300 25.350 25.400 25.450 25.500 25.550 25.600 25.650 25.700 25.750 25.800 25.850 25.900 25.950 26.000 26.050 26.100 26.150 26.200 26.250 26.300 26.350 26.400 26.450 26.500 26.550 26.600 26.650 26.700 26.750 26.800 26.850 26.900 26.950 27.000 27.050 27.100 27.150 27.200 27.250 27.300 27.350 27.400 27.450 27.500 27.550 27.600 27.650 27.700 27.750 27.800 27.850 27.900 27.950 28.000 28.050 28.100 28.150 28.200 28.250 28.300 28.350 28.400 28.450 28.500 28.550 28.600 28.650 28.700 28.750 28.800 28.850 28.900 28.950 29.000 29.050 29.100 29.150 29.200 29.250 29.300 29.350 29.400 29.450 29.500 29.550 29.600 29.650 29.700 29.750 29.800 29.850 29.900 29.950 30.000 LHS SAI MAATARINI TOLLWAYS LIMITED Four Laning of Panikoili – Rimuli Road Section of NH-215 from Km 0+000 – 163+000 (Design Length 166+173 Kms) in the state of Odisha under NHDP Phase-III as BOT (Toll) Basis. Monthly Progress Report : March - 2015 BC DBM WMM-Top WMM-1st GSB SG-Top SG-IInd SG-Ist EMB-Top EMB-5th 7 EMB-4th EMB-3rd EMB-2nd EMB-1st OGL Record OGL FDD C&G OGL Samp. Testing OGL Samp. Testing C&G OGL FDD OGL Record EMB-1st EMB-2nd EMB-3rd EMB-4th EMB-5th EMB-6th EMB-Top SG-Ist SG-IInd SG-Top GSB WMM-1st WMM-Top DBM BC M/s. SAI MAATARINI TOLLWAYS LIMITED Page 32 RHS Chainage 30.000 30.050 30.100 30.150 30.200 30.250 30.300 30.350 30.400 30.450 30.500 30.550 30.600 30.650 30.700 30.750 30.800 30.850 30.900 30.950 31.000 31.050 31.100 31.150 31.200 31.250 31.300 31.350 31.400 31.450 31.500 31.550 31.600 31.650 31.700 31.750 31.800 31.850 31.900 31.950 32.000 32.050 32.100 32.150 32.200 32.250 32.300 32.350 32.400 32.450 32.500 32.550 32.600 32.650 32.700 32.750 32.800 32.850 32.900 32.950 33.000 33.050 33.100 33.150 33.200 33.250 33.300 33.350 33.400 33.450 33.500 33.550 33.600 33.650 33.700 33.750 33.800 33.850 33.900 33.950 34.000 34.050 34.100 34.150 34.200 34.250 34.300 34.350 34.400 34.450 34.500 34.550 34.600 34.650 34.700 34.750 34.800 34.850 34.900 34.950 35.000 LHS SAI MAATARINI TOLLWAYS LIMITED Four Laning of Panikoili – Rimuli Road Section of NH-215 from Km 0+000 – 163+000 (Design Length 166+173 Kms) in the state of Odisha under NHDP Phase-III as BOT (Toll) Basis. Monthly Progress Report : March - 2015 BC DBM WMM-Top WMM-1st GSB SG-Top SG-IInd SG-Ist EMB-Top EMB-6th EMB-5th 14 M/s. SAI MAATARINI TOLLWAYS LIMITED 10 14 15 8 EMB-4th EMB-3rd EMB-2nd EMB-1st OGL Record OGL FDD C&G OGL Samp. Testing OGL Samp. Testing C &G OGL FDD OGL Record EMB-1st EMB-2nd EMB-3rd EMB-4th EMB-5th EMB-6th EMB-Top SG-Ist SG-IInd SG-Top GSB WMM-1st WMM-Top DBM BC Page 33 RHS Chainage EMB-3rd EMB-4th EMB-5th M/s. SAI MAATARINI TOLLWAYS LIMITED 6TH Layer 7th Layer 10th Layer 10 TH Layer 7th Layer EMB-6th 8th Layer EMB-3rd 7th Layer EMB-4th 7th Layer EMB-5th 35.000 35.050 35.100 35.150 35.200 35.250 35.300 35.350 35.400 35.450 35.500 35.550 35.600 35.650 35.700 35.750 35.800 35.850 35.900 35.950 36.000 36.050 36.100 36.150 36.200 36.250 36.300 36.350 36.400 36.450 36.500 36.550 36.600 36.650 36.700 36.750 36.800 36.850 36.900 36.950 37.000 37.050 37.100 37.150 37.200 37.250 37.300 37.350 37.400 37.450 37.500 37.550 37.600 37.650 37.700 37.750 37.800 37.850 37.900 37.950 38.000 38.050 38.100 38.150 38.200 38.250 38.300 38.350 38.400 38.450 38.500 38.550 38.600 38.650 38.700 38.750 38.800 38.850 38.900 38.950 39.000 39.050 39.100 39.150 39.200 39.250 39.300 39.350 39.400 39.450 39.500 39.550 39.600 39.650 39.700 39.750 39.800 39.850 39.900 39.950 40.000 LHS SAI MAATARINI TOLLWAYS LIMITED Four Laning of Panikoili – Rimuli Road Section of NH-215 from Km 0+000 – 163+000 (Design Length 166+173 Kms) in the state of Odisha under NHDP Phase-III as BOT (Toll) Basis. Monthly Progress Report : March - 2015 BC DBM WMM-Top WMM-1st GSB SG-Top SG-IInd SG-Ist EMB-Top 9 EMB-2nd EMB-1st OGL Record OGL FDD C&G OGL Samp. Testing OGL Samp. Testing C&G OGL FDD OGL Record EMB-1st EMB-2nd EMB-6th EMB-Top SG-Ist SG-IInd SG-Top GSB WMM-1st WMM-Top DBM BC Page 34 RHS EMB-6th Chainage EMB-6th 40.000 40.050 40.100 40.150 40.200 40.250 40.300 40.350 40.400 40.450 40.500 40.550 40.600 40.650 40.700 40.750 40.800 40.850 40.900 40.950 41.000 41.050 41.100 41.150 41.200 41.250 41.300 41.350 41.400 41.450 41.500 41.550 41.600 41.650 41.700 41.750 41.800 41.850 41.900 41.950 42.000 42.050 42.100 42.150 42.200 42.250 42.300 42.350 42.400 42.450 42.500 42.550 42.600 42.650 42.700 42.750 42.800 42.850 42.900 42.950 43.000 43.050 43.100 43.150 43.200 43.250 43.300 43.350 43.400 43.450 43.500 43.550 43.600 43.650 43.700 43.750 43.800 43.850 43.900 43.950 44.000 44.050 44.100 44.150 44.200 44.250 44.300 44.350 44.400 44.450 44.500 44.550 44.600 44.650 44.700 44.750 44.800 44.850 44.900 44.950 45.000 LHS SAI MAATARINI TOLLWAYS LIMITED Four Laning of Panikoili – Rimuli Road Section of NH-215 from Km 0+000 – 163+000 (Design Length 166+173 Kms) in the state of Odisha under NHDP Phase-III as BOT (Toll) Basis. Monthly Progress Report : March - 2015 BC DBM WMM-Top WMM-1st GSB SG-Top SG-IInd SG-Ist EMB-Top EMB-5th 10 10 12 EMB-4th EMB-4th 7 9 12 M/s. SAI MAATARINI TOLLWAYS LIMITED 7 15 8 14 9 15 8 13 12 13 11 EMB-3rd 17 12 EMB-2nd EMB-1st OGL Record OGL FDD C&G OGL Samp. Testing OGL Samp. Testing C&G OGL FDD OGL Record EMB-1st EMB-2nd EMB-3rd EMB-5th 17 12 EMB-Top 7 SG-Ist SG-IInd SG-Top GSB WMM-1st WMM-Top DBM BC Page 35 RHS Chainage OGL FDD OGL Record EMB-1st EMB-2nd EMB-3rd EMB-4th EMB-5th EMB-6th M/s. SAI MAATARINI TOLLWAYS LIMITED OGL Record OGL FDD Exc upto Emb Top 8 Exc upto Emb Top EMB-1st Exc upto Emb Top EMB-2nd 9 Exc upto Emb Top EMB-3rd 7 EXC upto Emb Top EMB-4th 9 EXC upto Emb Top EMB-5th EXC upto Emb Top EMB-6th 45.000 45.050 45.100 45.150 45.200 45.250 45.300 45.350 45.400 45.450 45.500 45.550 45.600 45.650 45.700 45.750 45.800 45.850 45.900 45.950 46.000 46.050 46.100 46.150 46.200 46.250 46.300 46.350 46.400 46.450 46.500 46.550 46.600 46.650 46.700 46.750 46.800 46.850 46.900 46.950 47.000 47.050 47.100 47.150 47.200 47.250 47.300 47.350 47.400 47.450 47.500 47.550 47.600 47.650 47.700 47.750 47.800 47.850 47.900 47.950 48.000 48.050 48.100 48.150 48.200 48.250 48.300 48.350 48.400 48.450 48.500 48.550 48.600 48.650 48.700 48.750 48.800 48.850 48.900 48.950 49.000 49.050 49.100 49.150 49.200 49.250 49.300 49.350 49.400 49.450 49.500 49.550 49.600 49.650 49.700 49.750 49.800 49.850 49.900 49.950 50.000 LHS SAI MAATARINI TOLLWAYS LIMITED Four Laning of Panikoili – Rimuli Road Section of NH-215 from Km 0+000 – 163+000 (Design Length 166+173 Kms) in the state of Odisha under NHDP Phase-III as BOT (Toll) Basis. Monthly Progress Report : March - 2015 BC DBM WMM-Top WMM-1st GSB SG-Top SG-IInd SG-Ist EMB-Top 17 22 12 9 C&G OGL Samp. Testing OGL Samp. Testing C &G EMB-Top SG-Ist SG-IInd SG-Top GSB WMM-1st WMM-Top DBM BC Page 36 RHS EMB-3rd EMB-2nd EMB-1st OGL Record OGL FDD Chainage 13 7 OGL FDD OGL Record EMB-1st EMB-2nd EMB-3rd EMB-4th M/s. SAI MAATARINI TOLLWAYS LIMITED 10 Exc upto Emb. Top 18 Exc upto Emb. Top EMB-4th Exc upto Emb. Top EMB-6th 50.000 50.050 50.100 50.150 50.200 50.250 50.300 50.350 50.400 50.450 50.500 50.550 50.600 50.650 50.700 50.750 50.800 50.850 50.900 50.950 51.000 51.050 51.100 51.150 51.200 51.250 51.300 51.350 51.400 51.450 51.500 51.550 51.600 51.650 51.700 51.750 51.800 51.850 51.900 51.950 52.000 52.050 52.100 52.150 52.200 52.250 52.300 52.350 52.400 52.450 52.500 52.550 52.600 52.650 52.700 52.750 52.800 52.850 52.900 52.950 53.000 53.050 53.100 53.150 53.200 53.250 53.300 53.350 53.400 53.450 53.500 53.550 53.600 53.650 53.700 53.750 53.800 53.850 53.900 53.950 54.000 54.050 54.100 54.150 54.200 54.250 54.300 54.350 54.400 54.450 54.500 54.550 54.600 54.650 54.700 54.750 54.800 54.850 54.900 54.950 55.000 LHS SAI MAATARINI TOLLWAYS LIMITED Four Laning of Panikoili – Rimuli Road Section of NH-215 from Km 0+000 – 163+000 (Design Length 166+173 Kms) in the state of Odisha under NHDP Phase-III as BOT (Toll) Basis. Monthly Progress Report : March - 2015 BC DBM WMM-Top WMM-1st GSB SG-Top SG-IInd SG-Ist EMB-Top EMB-5th 13 7 9 C&G OGL Samp. Testing OGL Samp. Testing &G C EMB-5th EMB-6th EMB-Top SG-Ist SG-IInd SG-Top GSB WMM-1st WMM-Top DBM BC Page 37 RHS EMB-3rd Chainage EMB-6th 7 M/s. SAI MAATARINI TOLLWAYS LIMITED 56.700 56.750 56.800 56.850 56.900 56.950 57.000 57.050 57.100 57.150 57.200 57.250 57.300 57.350 57.400 57.450 57.500 57.550 57.600 57.650 57.700 57.750 57.800 57.850 57.900 57.950 58.000 58.050 58.100 58.150 58.200 58.250 58.300 58.350 58.400 58.450 58.500 58.550 58.600 58.650 58.700 58.750 58.800 58.850 58.900 58.950 59.000 59.050 59.100 59.150 59.200 59.250 59.300 59.350 59.400 59.450 59.500 59.550 59.600 59.650 59.700 59.750 59.800 59.850 59.900 59.950 60.000 EMB-4th 9th layer 18th layer 17th layer EMB-5th 55.000 55.050 55.100 55.150 55.200 55.250 55.300 55.350 55.400 55.450 55.500 55.550 55.600 55.650 55.700 55.750 55.800 55.850 55.900 55.950 56.000 56.050 56.100 56.150 56.200 56.250 56.300 56.350 56.400 56.450 56.500 56.550 56.600 56.650 LHS SAI MAATARINI TOLLWAYS LIMITED Four Laning of Panikoili – Rimuli Road Section of NH-215 from Km 0+000 – 163+000 (Design Length 166+173 Kms) in the state of Odisha under NHDP Phase-III as BOT (Toll) Basis. Monthly Progress Report : March - 2015 BC DBM WMM-Top WMM-1st GSB SG-Top SG-IInd SG-Ist EMB-Top EMB-6th 7 EMB-2nd EMB-1st OGL Record OGL FDD C&G OGL Samp. Testing OGL Samp. Testing C&G OGL FDD OGL Record EMB-1st EMB-2nd EMB-3rd EMB-4th EMB-5th EMB-Top 30 17 11 13 SG-Ist SG-IInd SG-Top GSB WMM-1st WMM-Top DBM BC Page 38 RHS Chainage 65.000 65.050 65.100 65.150 65.200 65.250 65.300 65.350 65.400 65.450 65.500 65.550 65.600 65.650 65.700 65.750 65.800 65.850 65.900 65.950 66.000 66.050 66.100 66.150 66.200 66.250 66.300 66.350 66.400 66.450 66.500 66.550 66.600 66.650 66.700 66.750 66.800 66.850 66.900 66.950 67.000 67.050 67.100 67.150 67.200 67.250 67.300 67.350 67.400 67.450 67.500 67.550 67.600 67.650 67.700 67.750 67.800 67.850 67.900 67.950 68.000 68.050 68.100 68.150 68.200 68.250 68.300 68.350 68.400 68.450 68.500 68.550 68.600 68.650 68.700 68.750 68.800 68.850 68.900 68.950 69.000 69.050 69.100 69.150 69.200 69.250 69.300 69.350 69.400 69.450 69.500 69.550 69.600 69.650 69.700 69.750 69.800 69.850 69.900 69.950 70.000 LHS SAI MAATARINI TOLLWAYS LIMITED Four Laning of Panikoili – Rimuli Road Section of NH-215 from Km 0+000 – 163+000 (Design Length 166+173 Kms) in the state of Odisha under NHDP Phase-III as BOT (Toll) Basis. Monthly Progress Report : March - 2015 BC DBM WMM-Top WMM-1st GSB SG-Top SG-IInd SG-Ist EMB-Top EMB-6th EMB-5th EMB-4th EMB-3rd EMB-2nd EMB-1st OGL Record OGL FDD C&G OGL Samp. Testing OGL Samp. Testing C&G OGL FDD OGL Record EMB-1st EMB-2nd EMB-3rd EMB-4th EMB-5th EMB-6th EMB-Top SG-Ist SG-IInd SG-Top GSB WMM-1st WMM-Top DBM BC M/s. SAI MAATARINI TOLLWAYS LIMITED Page 39 RHS Chainage 75.000 75.050 75.100 75.150 75.200 75.250 75.300 75.350 75.400 75.450 75.500 75.550 75.600 75.650 75.700 75.750 75.800 75.850 75.900 75.950 76.000 76.050 76.100 76.150 76.200 76.250 76.300 76.350 76.400 76.450 76.500 76.550 76.600 76.650 76.700 76.750 76.800 76.850 76.900 76.950 77.000 77.050 77.100 77.150 77.200 77.250 77.300 77.350 77.400 77.450 77.500 77.550 77.600 77.650 77.700 77.750 77.800 77.850 77.900 77.950 78.000 78.050 78.100 78.150 78.200 78.250 78.300 78.350 78.400 78.450 78.500 78.550 78.600 78.650 78.700 78.750 78.800 78.850 78.900 78.950 79.000 79.050 79.100 79.150 79.200 79.250 79.300 79.350 79.400 79.450 79.500 79.550 79.600 79.650 79.700 79.750 79.800 79.850 79.900 79.950 80.000 LHS SAI MAATARINI TOLLWAYS LIMITED Four Laning of Panikoili – Rimuli Road Section of NH-215 from Km 0+000 – 163+000 (Design Length 166+173 Kms) in the state of Odisha under NHDP Phase-III as BOT (Toll) Basis. Monthly Progress Report : March - 2015 BC DBM WMM-Top WMM-1st GSB SG-Top SG-IInd SG-Ist EMB-Top EMB-6th EMB-5th EMB-4th EMB-3rd EMB-2nd EMB-1st OGL Record OGL FDD C&G OGL Samp. Testing OGL Samp. Testing C&G OGL FDD OGL Record EMB-1st EMB-2nd EMB-3rd EMB-4th EMB-5th EMB-6th EMB-Top SG-Ist SG-IInd SG-Top GSB WMM-1st WMM-Top DBM BC M/s. SAI MAATARINI TOLLWAYS LIMITED Page 40 RHS Chainage 80.000 80.050 80.100 80.150 80.200 80.250 80.300 80.350 80.400 80.450 80.500 80.550 80.600 80.650 80.700 80.750 80.800 80.850 80.900 80.950 81.000 81.050 81.100 81.150 81.200 81.250 81.300 81.350 81.400 81.450 81.500 81.550 81.600 81.650 81.700 81.750 81.800 81.850 81.900 81.950 82.000 82.050 82.100 82.150 82.200 82.250 82.300 82.350 82.400 82.450 82.500 82.550 82.600 82.650 82.700 82.750 82.800 82.850 82.900 82.950 83.000 83.050 83.100 83.150 83.200 83.250 83.300 83.350 83.400 83.450 83.500 83.550 83.600 83.650 83.700 83.750 83.800 83.850 83.900 83.950 84.000 84.050 84.100 84.150 84.200 84.250 84.300 84.350 84.400 84.450 84.500 84.550 84.600 84.650 84.700 84.750 84.800 84.850 84.900 84.950 85.000 LHS SAI MAATARINI TOLLWAYS LIMITED Four Laning of Panikoili – Rimuli Road Section of NH-215 from Km 0+000 – 163+000 (Design Length 166+173 Kms) in the state of Odisha under NHDP Phase-III as BOT (Toll) Basis. Monthly Progress Report : March - 2015 BC DBM WMM-Top WMM-1st GSB SG-Top SG-IInd SG-Ist EMB-Top EMB-6th EMB-5th EMB-4th EMB-3rd EMB-2nd EMB-1st OGL Record OGL FDD C&G OGL Samp. Testing OGL Samp. Testing C&G OGL FDD OGL Record EMB-1st EMB-2nd EMB-3rd EMB-4th EMB-5th EMB-6th EMB-Top SG-Ist SG-IInd SG-Top GSB WMM-1st WMM-Top DBM BC M/s. SAI MAATARINI TOLLWAYS LIMITED Page 41 RHS Chainage EMB-6th 85.000 85.050 85.100 85.150 85.200 85.250 85.300 85.350 85.400 85.450 85.500 85.550 85.600 85.650 85.700 85.750 85.800 85.850 85.900 85.950 86.000 86.050 86.100 86.150 86.200 86.250 86.300 86.350 86.400 86.450 86.500 86.550 86.600 86.650 86.700 86.750 86.800 86.850 86.900 86.950 87.000 87.050 87.100 87.150 87.200 87.250 87.300 87.350 87.400 87.450 87.500 87.550 87.600 87.650 87.700 87.750 87.800 87.850 87.900 87.950 88.000 88.050 88.100 88.150 88.200 88.250 88.300 88.350 88.400 88.450 88.500 88.550 88.600 88.650 88.700 88.750 88.800 88.850 88.900 88.950 89.000 89.050 89.100 89.150 89.200 89.250 89.300 89.350 89.400 89.450 89.500 89.550 89.600 89.650 89.700 89.750 89.800 89.850 89.900 89.950 90.000 LHS SAI MAATARINI TOLLWAYS LIMITED Four Laning of Panikoili – Rimuli Road Section of NH-215 from Km 0+000 – 163+000 (Design Length 166+173 Kms) in the state of Odisha under NHDP Phase-III as BOT (Toll) Basis. Monthly Progress Report : March - 2015 BC DBM WMM-Top WMM-1st GSB SG-Top SG-IInd SG-Ist EMB-Top EMB-6th EMB-5th 9 EMB-4th EMB-3rd Exc upto Emb. Top EMB-2nd EMB-1st OGL Record OGL FDD C&G OGL Samp. Testing OGL Samp. Testing C&G OGL FDD OGL Record EMB-1st EMB-2nd EMB-3rd EMB-4th EMB-5th EMB-Top 9 7 M/s. SAI MAATARINI TOLLWAYS LIMITED 11 10 SG-Ist SG-IInd SG-Top GSB WMM-1st WMM-Top DBM BC Page 42 RHS EMB-3rd EMB-4th EMB-5th M/s. SAI MAATARINI TOLLWAYS LIMITED Layer EMB-6th 11th EMB-2nd Layer Layer Layer EMB-3rd 8th 10th 7th EMB-4th 7th Layer EMB-5th 9thLayer Chainage 90.000 90.050 90.100 90.150 90.200 90.250 90.300 90.350 90.400 90.450 90.500 90.550 90.600 90.650 90.700 90.750 90.800 90.850 90.900 90.950 91.000 91.050 91.100 91.150 91.200 91.250 91.300 91.350 91.400 91.450 91.500 91.550 91.600 91.650 91.700 91.750 91.800 91.850 91.900 91.950 92.000 92.050 92.100 92.150 92.200 92.250 92.300 92.350 92.400 92.450 92.500 92.550 92.600 92.650 92.700 92.750 92.800 92.850 92.900 92.950 93.000 93.050 93.100 93.150 93.200 93.250 93.300 93.350 93.400 93.450 93.500 93.550 93.600 93.650 93.700 93.750 93.800 93.850 93.900 93.950 94.000 94.050 94.100 94.150 94.200 94.250 94.300 94.350 94.400 94.450 94.500 94.550 94.600 94.650 94.700 94.750 94.800 94.850 94.900 94.950 95.000 9th Layer 12th Layer 8th Layer EMB-2nd EMB-1st OGL Record OGL FDD OGL Record Exc. Upto Emb. Top LHS SAI MAATARINI TOLLWAYS LIMITED Four Laning of Panikoili – Rimuli Road Section of NH-215 from Km 0+000 – 163+000 (Design Length 166+173 Kms) in the state of Odisha under NHDP Phase-III as BOT (Toll) Basis. Monthly Progress Report : March - 2015 BC DBM WMM-Top WMM-1st GSB SG-Top SG-IInd SG-Ist EMB-Top EMB-6th 11 C&G OGL Samp. Testing OGL Samp. Testing C&G OGL FDD EMB-1st Hardrock Rock EMB-Top SG-Ist SG-IInd SG-Top GSB WMM-1st WMM-Top DBM BC Page 43 RHS EMB-3rd EMB-2nd EMB-1st OGL Record OGL FDD OGL Samp. Testing Chainage EMB-2nd EMB-3rd EMB-4th EMB-5th M/s. SAI MAATARINI TOLLWAYS LIMITED Exc. upto E. Top EMB-4th Exc. Upto Emb. Top Exc. Upto Emb. Top EMB-5th 95.000 95.050 95.100 95.150 95.200 95.250 95.300 95.350 95.400 95.450 95.500 95.550 95.600 95.650 95.700 95.750 95.800 95.850 95.900 95.950 96.000 96.050 96.100 96.150 96.200 96.250 96.300 96.350 96.400 96.450 96.500 96.550 96.600 96.650 96.700 96.750 96.800 96.850 96.900 96.950 97.000 97.050 97.100 97.150 97.200 97.250 97.300 97.350 97.400 97.450 97.500 97.550 97.600 97.650 97.700 97.750 97.800 97.850 97.900 97.950 98.000 98.050 98.100 98.150 98.200 98.250 98.300 98.350 98.400 98.450 98.500 98.550 98.600 98.650 98.700 98.750 98.800 98.850 98.900 98.950 99.000 99.050 99.100 99.150 99.200 99.250 99.300 99.350 99.400 99.450 99.500 99.550 99.600 99.650 99.700 99.750 99.800 99.850 99.900 99.950 100.000 LHS SAI MAATARINI TOLLWAYS LIMITED Four Laning of Panikoili – Rimuli Road Section of NH-215 from Km 0+000 – 163+000 (Design Length 166+173 Kms) in the state of Odisha under NHDP Phase-III as BOT (Toll) Basis. Monthly Progress Report : March - 2015 BC DBM WMM-Top WMM-1st GSB SG-Top SG-IInd SG-Ist EMB-Top EMB-6th C&G OGL Samp. Testing C &G OGL FDD OGL Record EMB-1st EMB-6th EMB-Top SG-Ist SG-IInd SG-Top GSB WMM-1st WMM-Top DBM BC Page 44 RHS EMB-3rd EMB-1st OGL Record OGL FDD OGL Samp. Testing Chainage OGL FDD OGL Record EMB-1st EMB-2nd EMB-3rd EMB-4th EMB-5th Exc. Upto Emb. Top Exc. Upto Emb. Top EMB-2nd Exc. Upto Emb. Top EMB-4th 9th Layer EMB-5th 100.000 100.050 100.100 100.150 100.200 100.250 100.300 100.350 100.400 100.450 100.500 100.550 100.600 100.650 100.700 100.750 100.800 100.850 100.900 100.950 101.000 101.050 101.100 101.150 101.200 101.250 101.300 101.350 101.400 101.450 101.500 101.550 101.600 101.650 101.700 101.750 101.800 101.850 101.900 101.950 102.000 102.050 102.100 102.150 102.200 102.250 102.300 102.350 102.400 102.450 102.500 102.550 102.600 102.650 102.700 102.750 102.800 102.850 102.900 102.950 103.000 103.050 103.100 103.150 103.200 103.250 103.300 103.350 103.400 103.450 103.500 103.550 103.600 103.650 103.700 103.750 103.800 103.850 103.900 103.950 104.000 104.050 104.100 104.150 104.200 104.250 104.300 104.350 104.400 104.450 104.500 104.550 104.600 104.650 104.700 104.750 104.800 104.850 104.900 104.950 105.000 LHS SAI MAATARINI TOLLWAYS LIMITED Four Laning of Panikoili – Rimuli Road Section of NH-215 from Km 0+000 – 163+000 (Design Length 166+173 Kms) in the state of Odisha under NHDP Phase-III as BOT (Toll) Basis. Monthly Progress Report : March - 2015 BC DBM WMM-Top WMM-1st GSB SG-Top SG-IInd SG-Ist EMB-Top EMB-6th C&G OGL Samp. Testing C &G EMB-6th EMB-Top M/s. SAI MAATARINI TOLLWAYS LIMITED 12 8 SG-Ist SG-IInd SG-Top GSB WMM-1st WMM-Top DBM BC Page 45 RHS OGL Samp. Testing C&G OGL FDD OGL Record EMB-1st EMB-2nd EMB-3rd EMB-4th EMB-5th EMB-6th EMB-Top SG-Ist SG-IInd SG-Top GSB WMM-1st WMM-Top KERB DBM BC M/s. SAI MAATARINI TOLLWAYS LIMITED 13th layer 13th layer 11th layer 11th layer 9th layer 8th layer 8th layer 20th layer 13th layer 15th layer 21th layer Page 46 9th layer 15th layer 10th layer 11th layer 9th layer 8th layer Minor Bridge Compensation not paid 7th layer Minor Bridge Chainage Temple 8thLayer 15th layer 10th layer 11th layer 8th layer 8th Layer Minor Bridge Compensation not paid Minor Bridge 21th layer 12th layer 7th layer 11th layer 17th layer 17th layer 8th layer 11th Layer 11th Layer 8th Layer Excavation upto Emb. Top Layer 8th Layer Temple BC DBM KERB WMM-Top WMM-1st GSB SG-Top SG-IInd SG-Ist EMB-Top EMB-6th EMB-5th EMB-4th EMB-3rd EMB-2nd EMB-1st OGL Record OGL FDD C&G OGL Samp. Testing 113+000 113+050 113+100 113+150 113+200 113+250 113+300 113+350 113+400 113+450 113+500 113+550 113+600 113+650 113+700 113+750 113+800 113+850 113+900 113+950 114+000 114+050 114+100 114+150 114+200 114+250 114+300 114+350 114+400 114+450 114+500 114+550 114+600 114+650 114+700 114+750 114+800 114+850 114+900 114+950 115+000 115+050 115+100 115+150 115+200 115+250 115+300 115+350 115+400 115+450 115+500 115+550 115+600 115+650 115+700 115+750 115+800 115+850 115+900 115+950 116+000 116+050 116+100 116+150 116+200 116+250 116+300 116+350 116+400 116+450 116+500 116+550 116+600 116+650 116+700 116+750 116+800 116+850 116+900 116+950 117+000 117+050 117+100 117+150 117+200 117+250 117+300 117+350 117+400 117+450 117+500 117+550 117+600 117+650 117+700 117+750 117+800 117+850 117+900 117+950 118+000 LHS SAI MAATARINI TOLLWAYS LIMITED Four Laning of Panikoili – Rimuli Road Section of NH-215 from Km 0+000 – 163+000 (Design Length 166+173 Kms) in the state of Odisha under NHDP Phase-III as BOT (Toll) Basis. Monthly Progress Report : March - 2015 RHS OGL Samp. Testing C&G OGL FDD OGL Record EMB-1st EMB-2nd EMB-3rd EMB-4th EMB-5th EMB-6th EMB-Top SG-Ist SG-IInd SG-Top GSB WMM-1st WMM-Top KERB DBM BC M/s. SAI MAATARINI TOLLWAYS LIMITED Page 47 10th layer Excavation upto Emb Top Layer Excavation upto Emb Top layer Excavation upto Subgrade Top layer 13th layer 7th layer 7th layer 12th layer 11th layer 12th layer 15th layer 12th layer 13th layer Chainage 118+000 118+050 118+100 118+150 118+200 118+250 118+300 118+350 118+400 118+450 118+500 118+550 118+600 118+650 118+700 118+750 118+800 118+850 118+900 118+950 119+000 119+050 119+100 119+150 119+200 119+250 119+300 119+350 119+400 119+450 119+500 119+550 119+600 119+650 119+700 119+750 119+800 119+850 119+900 119+950 120+000 120+050 120+100 120+150 120+200 120+250 120+300 120+350 120+400 120+450 120+500 120+550 120+600 120+650 120+700 120+750 120+800 120+850 120+900 120+950 121+000 121+050 121+100 121+150 121+200 121+250 121+300 121+350 121+400 121+450 121+500 121+550 121+600 121+650 121+700 121+750 121+800 121+850 121+900 121+950 122+000 122+050 122+100 122+150 122+200 122+250 122+300 122+350 122+400 122+450 122+500 122+550 122+600 122+650 122+700 122+750 122+800 122+850 122+900 122+950 123+000 10th layer 8th layer Excavation upto Emb Top Layer 7th layer 8th layer 7th layer 10th layer 9th layer 14th layer 11th layer 12th layer 15th layer 14th layer 13th layer 11th layer BC DBM KERB WMM-Top WMM-1st GSB SG-Top SG-IInd SG-Ist EMB-Top EMB-6th EMB-5th EMB-4th EMB-3rd EMB-2nd EMB-1st OGL Record OGL FDD C&G OGL Samp. Testing 11th layer LHS SAI MAATARINI TOLLWAYS LIMITED Four Laning of Panikoili – Rimuli Road Section of NH-215 from Km 0+000 – 163+000 (Design Length 166+173 Kms) in the state of Odisha under NHDP Phase-III as BOT (Toll) Basis. Monthly Progress Report : March - 2015 RHS Chainage OGL Samp. Testing C&G OGL FDD OGL Record EMB-1st EMB-2nd EMB-3rd EMB-4th EMB-5th EMB-6th EMB-Top SG-Ist SG-IInd SG-Top GSB WMM-1st WMM-Top KERB DBM BC 123+000 123+050 123+100 123+150 123+200 10th layer 123+250 8th layer 123+300 123+350 123+400 123+450 Excavation Upto Emb Top Layer123+500 123+550 123+600 123+650 Excavation Upto Emb Top Layer123+700 123+750 123+800 123+850 123+900 123+950 15th layer 124+000 124+050 124+100 124+150 124+200 124+250 124+300 124+350 Excavation Upto Emb Top Layer 124+400 124+450 124+500 Excavation Upto Emb Top Layer124+550 124+600 124+650 124+700 124+750 124+800 124+850 124+900 124+950 125+000 125+050 125+100 125+150 125+200 125+250 125+300 125+350 125+400 125+450 125+500 125+550 125+600 125+650 11th layer 125+700 125+750 125+800 125+850 18th layer 125+900 125+950 126+000 16th layer 126+050 126+100 126+150 15th layer 126+200 126+250 126+300 126+350 126+400 126+450 7th layer 126+500 126+550 8th layer 126+600 126+650 126+700 126+750 126+800 126+850 126+900 126+950 127+000 127+050 127+100 127+150 10th layer 127+200 127+250 127+300 127+350 17th layer 127+400 127+450 127+500 127+550 127+600 13th layer 127+650 127+700 127+750 127+800 Excavation upto Emb Top Layer 127+850 127+900 127+950 128+000 M/s. SAI MAATARINI TOLLWAYS LIMITED Excavation Upto Emb Top Layer Excavation Upto Emb Top Layer 8th layer 10 th layer 12th layer BC DBM KERB WMM-Top WMM-1st GSB SG-Top SG-IInd SG-Ist EMB-Top EMB-6th EMB-5th EMB-4th EMB-3rd EMB-2nd EMB-1st OGL Record OGL FDD C&G OGL Samp. Testing 12th layer LHS . . . . . . . . . . . . Fly-over Area 12th layer 18th layer 17th layer 12th layer 7th layer 8th layer 7th layer 8th layer 14th layer 14th layer SAI MAATARINI TOLLWAYS LIMITED Four Laning of Panikoili – Rimuli Road Section of NH-215 from Km 0+000 – 163+000 (Design Length 166+173 Kms) in the state of Odisha under NHDP Phase-III as BOT (Toll) Basis. Monthly Progress Report : March - 2015 Fly-over Area Page 48 RHS OGL Samp. Testing C&G OGL FDD OGL Record EMB-1st EMB-2nd EMB-3rd EMB-4th EMB-5th EMB-6th EMB-Top SG-Ist SG-IInd SG-Top GSB WMM-1st WMM-Top KERB DBM BC 7th layer EXCAVATION 15th layer Electrical Line VUP Structure RWSS Pipe line, 12th layer 10th layer 8th layer 10th layer 11 th layer 8th layer 9th layer 7th layer 11th layer VUP Structure 13th layer 13th layer 8th layer Excavation Upto Emb Top Layer Compensation Not Paid Excavation Upto Emb Top Layer EXCAVATION Excavation upto Emb Top Layer 8th layer M/s. SAI MAATARINI TOLLWAYS LIMITED 8th layer 7th layer 10th layer 12th layer 8th layer 11th layer Chainage 8th layer BC DBM KERB WMM-Top WMM-1st GSB SG-Top SG-IInd SG-Ist EMB-Top EMB-6th EMB-5th EMB-4th EMB-3rd EMB-2nd EMB-1st OGL Record OGL FDD C&G OGL Samp. Testing 128+000 128+050 128+100 128+150 128+200 128+250 128+300 128+350 128+400 128+450 128+500 128+550 128+600 128+650 128+700 128+750 128+800 128+850 128+900 128+950 129+000 129+050 129+100 129+150 129+200 129+250 129+300 129+350 129+400 129+450 129+500 129+550 129+600 129+650 129+700 129+750 129+800 129+850 129+900 129+950 130+000 130+050 130+100 130+150 130+200 130+250 130+300 130+350 130+400 130+450 130+500 130+550 130+600 130+650 130+700 130+750 130+800 130+850 130+900 130+950 131+000 131+050 131+100 131+150 131+200 131+250 131+300 131+350 131+400 131+450 131+500 131+550 131+600 131+650 131+700 131+750 131+800 131+850 131+900 131+950 132+000 132+050 132+100 132+150 132+200 132+250 132+300 132+350 132+400 132+450 132+500 132+550 132+600 132+650 132+700 132+750 132+800 132+850 132+900 132+950 133+000 LHS SAI MAATARINI TOLLWAYS LIMITED Four Laning of Panikoili – Rimuli Road Section of NH-215 from Km 0+000 – 163+000 (Design Length 166+173 Kms) in the state of Odisha under NHDP Phase-III as BOT (Toll) Basis. Monthly Progress Report : March - 2015 Page 49 RHS OGL Samp. Testing C&G OGL FDD OGL Record EMB-1st EMB-2nd EMB-3rd EMB-4th EMB-5th EMB-6th EMB-Top SG-Ist SG-IInd SG-Top GSB WMM-1st WMM-Top KERB DBM BC 133+000 133+050 133+100 133+150 133+200 133+250 10th layer 133+300 133+350 133+400 133+450 133+500 Excavation was done but RFI was not raised 133+550 133+600 133+650 133+700 133+750 133+800 133+850 133+900 133+950 134+000 134+050 134+100 134+150 134+200 134+250 134+300 134+350 134+400 10th layer 134+450 134+500 134+550 134+600 9th layer 134+650 134+700 134+750 134+800 Excavation upto Emb Top Layer 134+850 134+900 134+950 135+000 135+050 135+100 135+150 135+200 135+250 135+300 135+350 135+400 135+450 135+500 135+550 135+600 135+650 135+700 135+750 135+800 135+850 135+900 135+950 136+000 136+050 136+100 136+150 136+200 136+250 136+300 136+350 136+400 136+450 136+500 PUP Structure 136+550 136+600 136+650 136+700 136+750 136+800 136+850 136+900 136+950 137+000 137+050 137+100 137+150 137+200 137+250 137+300 137+350 137+400 137+450 137+500 137+550 137+600 137+650 137+700 137+750 137+800 137+850 137+900 137+950 138+000 Chainage 15th layer LHS BC DBM KERB WMM-Top WMM-1st GSB SG-Top SG-IInd SG-Ist EMB-Top EMB-6th EMB-5th EMB-4th EMB-3rd EMB-2nd EMB-1st OGL Record OGL FDD C&G OGL Samp. Testing 9th layer 10th layer M/s. SAI MAATARINI TOLLWAYS LIMITED 7th layer 8th layer 7th layer 10th layer 8th layer 12th layer 10th layer 11th layer SAI MAATARINI TOLLWAYS LIMITED Four Laning of Panikoili – Rimuli Road Section of NH-215 from Km 0+000 – 163+000 (Design Length 166+173 Kms) in the state of Odisha under NHDP Phase-III as BOT (Toll) Basis. Monthly Progress Report : March - 2015 Page 50 RHS OGL Samp. Testing C&G OGL FDD OGL Record EMB-1st EMB-2nd EMB-3rd EMB-4th EMB-5th EMB-6th EMB-Top SG-Ist SG-IInd SG-Top GSB WMM-1st WMM-Top KERB DBM BC M/s. SAI MAATARINI TOLLWAYS LIMITED 12th layer Major Bridge Area 8th layer 7th layer 9th layer Chainage 9th layer Major Bridge Area 12th layer 9th layer 8th layer BC DBM KERB WMM-Top WMM-1st GSB SG-Top SG-IInd SG-Ist EMB-Top EMB-6th EMB-5th EMB-4th EMB-3rd EMB-2nd EMB-1st OGL Record OGL FDD C&G OGL Samp. Testing 138+000 138+050 138+100 138+150 138+200 138+250 138+300 138+350 138+400 138+450 138+500 138+550 138+600 138+650 138+700 138+750 138+800 138+850 138+900 138+950 139+000 139+050 139+100 139+150 139+200 139+250 139+300 139+350 139+400 139+450 139+500 139+550 139+600 139+650 139+700 139+750 139+800 139+850 139+900 139+950 140+000 140+050 140+100 140+150 140+200 140+250 140+300 140+350 140+400 140+450 140+500 140+550 140+600 140+650 140+700 140+750 140+800 140+850 140+900 140+950 141+000 141+050 141+100 141+150 141+200 141+250 141+300 141+350 141+400 141+450 141+500 141+550 141+600 141+650 141+700 141+750 141+800 141+850 141+900 141+950 142+000 142+050 142+100 142+150 142+200 142+250 142+300 142+350 142+400 142+450 142+500 142+550 142+600 142+650 142+700 142+750 142+800 142+850 142+900 142+950 143+000 LHS 8th layer 6th layer 12th layer 12th layer 12th layer 11th layer 7th layer 8th layer Govt Structure (Temple, School & Club) 9th layer 12th layer 10th layer 9th layer 7th layer 8th layer 8th layer 11th layer SAI MAATARINI TOLLWAYS LIMITED Four Laning of Panikoili – Rimuli Road Section of NH-215 from Km 0+000 – 163+000 (Design Length 166+173 Kms) in the state of Odisha under NHDP Phase-III as BOT (Toll) Basis. Monthly Progress Report : March - 2015 Page 51 RHS OGL Samp. Testing C&G OGL FDD OGL Record EMB-1st EMB-2nd EMB-3rd EMB-4th EMB-5th EMB-6th EMB-Top SG-Ist SG-IInd SG-Top GSB WMM-1st WMM-Top KERB DBM BC M/s. SAI MAATARINI TOLLWAYS LIMITED 8th layer 7th layer exc upto emb top 9th layer 9th layer 9th layer 6th layer exc upto emb top Excavation upto emb top Tangarani Reserve Forest Exc upto emb top Chainage exc upto emb top BC DBM KERB WMM-Top WMM-1st GSB SG-Top SG-IInd SG-Ist EMB-Top EMB-6th EMB-5th EMB-4th EMB-3rd EMB-2nd EMB-1st OGL Record OGL FDD C&G OGL Samp. Testing 143+000 143+050 143+100 143+150 143+200 143+250 143+300 143+350 143+400 143+450 143+500 143+550 143+600 143+650 143+700 143+750 143+800 143+850 143+900 143+950 144+000 144+050 144+100 144+150 144+200 144+250 144+300 144+350 144+400 144+450 144+500 144+550 144+600 144+650 144+700 144+750 144+800 144+850 144+900 144+950 145+000 145+050 145+100 145+150 145+200 145+250 145+300 145+350 145+400 145+450 145+500 145+550 145+600 145+650 145+700 145+750 145+800 145+850 145+900 145+950 146+000 146+050 146+100 146+150 146+200 146+250 146+300 146+350 146+400 146+450 146+500 146+550 146+600 146+650 146+700 146+750 146+800 146+850 146+900 146+950 147+000 147+050 147+100 147+150 147+200 147+250 147+300 147+350 147+400 147+450 147+500 147+550 147+600 147+650 147+700 147+750 147+800 147+850 147+900 147+950 148+000 LHS SAI MAATARINI TOLLWAYS LIMITED Four Laning of Panikoili – Rimuli Road Section of NH-215 from Km 0+000 – 163+000 (Design Length 166+173 Kms) in the state of Odisha under NHDP Phase-III as BOT (Toll) Basis. Monthly Progress Report : March - 2015 9th layer Page 52 RHS OGL Samp. Testing C&G OGL FDD OGL Record EMB-1st EMB-2nd EMB-3rd EMB-4th EMB-5th EMB-6th EMB-Top SG-Ist SG-IInd SG-Top GSB WMM-1st WMM-Top KERB DBM BC M/s. SAI MAATARINI TOLLWAYS LIMITED Major Bridge Area 7th layer 11th layer 12th layer 8th layer Excavation upto Emb top BC DBM KERB WMM-Top WMM-1st GSB SG-Top SG-IInd SG-Ist EMB-Top EMB-6th EMB-5th EMB-4th EMB-3rd EMB-2nd EMB-1st OGL Record OGL FDD C&G OGL Samp. Testing IOCl Petrol Pump Chainage 148+000 148+050 148+100 148+150 148+200 148+250 148+300 148+350 148+400 148+450 148+500 148+550 148+600 148+650 148+700 148+750 148+800 148+850 148+900 148+950 149+000 149+050 149+100 149+150 149+200 149+250 149+300 149+350 149+400 149+450 149+500 149+550 149+600 149+650 149+700 149+750 149+800 149+850 149+900 149+950 150+000 150+050 150+100 150+150 150+200 150+250 150+300 150+350 150+400 150+450 150+500 150+550 150+600 150+650 150+700 150+750 150+800 150+850 150+900 150+950 151+000 151+050 151+100 151+150 151+200 151+250 151+300 151+350 151+400 151+450 151+500 151+550 151+600 151+650 151+700 151+750 151+800 151+850 151+900 151+950 152+000 152+050 152+100 152+150 152+200 152+250 152+300 152+350 152+400 152+450 152+500 152+550 152+600 152+650 152+700 152+750 152+800 152+850 152+900 152+950 153+000 LHS SAI MAATARINI TOLLWAYS LIMITED Four Laning of Panikoili – Rimuli Road Section of NH-215 from Km 0+000 – 163+000 (Design Length 166+173 Kms) in the state of Odisha under NHDP Phase-III as BOT (Toll) Basis. Monthly Progress Report : March - 2015 Minor Bridge Page 53 RHS OGL Samp. Testing C&G OGL FDD OGL Record EMB-1st EMB-2nd EMB-3rd EMB-4th EMB-5th EMB-6th EMB-Top SG-Ist SG-IInd SG-Top GSB WMM-1st WMM-Top KERB DBM BC 9th layer M/s. SAI MAATARINI TOLLWAYS LIMITED Minor Bridge Area Govt Structure (School) 7th layer Minor Bridge Area 7th layer 7th layer 8th layer 12th layer 7th layer 7th layer 11th layer Exc upto Emb top BC DBM KERB WMM-Top WMM-1st GSB SG-Top SG-IInd SG-Ist EMB-Top EMB-6th EMB-5th EMB-4th EMB-3rd EMB-2nd EMB-1st OGL Record OGL FDD C&G OGL Samp. Testing 7th layer 7th layer Chainage 153+000 153+050 153+100 153+150 153+200 153+250 153+300 153+350 153+400 153+450 153+500 153+550 153+600 153+650 153+700 153+750 153+800 153+850 153+900 153+950 154+000 154+050 154+100 154+150 154+200 154+250 154+300 154+350 154+400 154+450 154+500 154+550 154+600 154+650 154+700 154+750 154+800 154+850 154+900 154+950 155+000 155+050 155+100 155+150 155+200 155+250 155+300 155+350 155+400 155+450 155+500 155+550 155+600 155+650 155+700 155+750 155+800 155+850 155+900 155+950 156+000 156+050 156+100 156+150 156+200 156+250 156+300 156+350 156+400 156+450 156+500 156+550 156+600 156+650 156+700 156+750 156+800 156+850 156+900 156+950 157+000 157+050 157+100 157+150 157+200 157+250 157+300 157+350 157+400 157+450 157+500 157+550 157+600 157+650 157+700 157+750 157+800 157+850 157+900 157+950 158+000 LHS SAI MAATARINI TOLLWAYS LIMITED Four Laning of Panikoili – Rimuli Road Section of NH-215 from Km 0+000 – 163+000 (Design Length 166+173 Kms) in the state of Odisha under NHDP Phase-III as BOT (Toll) Basis. Monthly Progress Report : March - 2015 Reserve Forest Page 54 RHS OGL Samp. Testing C&G OGL FDD OGL Record EMB-1st EMB-2nd EMB-3rd EMB-4th EMB-5th EMB-6th EMB-Top SG-Ist SG-IInd SG-Top GSB WMM-1st WMM-Top KERB DBM BC M/s. SAI MAATARINI TOLLWAYS LIMITED SAND FILLING EXCAVATION 8th layer Excavation Upto Top Layer 9th layer 8th layer 7th layer 9th layer 10th layer 14th layer 12th layer EXCAVATION 7th layer 8th layer Box Culvert Gap 9th layer 13th layer BC DBM KERB WMM-Top WMM-1st GSB SG-Top SG-IInd SG-Ist EMB-Top EMB-6th EMB-5th EMB-4th EMB-3rd EMB-2nd EMB-1st OGL Record OGL FDD C&G OGL Samp. Testing 16th layer 15th layer 12th layer 10th layer Box Culvert Gap Reserve Forest Chainage 158+000 158+050 158+100 158+150 158+200 158+250 158+300 158+350 158+400 158+450 158+500 158+550 158+600 158+650 158+700 158+750 158+800 158+850 158+900 158+950 159+000 159+050 159+100 159+150 159+200 159+250 159+300 159+350 159+400 159+450 159+500 159+550 159+600 159+650 159+700 159+750 159+800 159+850 159+900 159+950 160+000 160+050 160+100 160+150 160+200 160+250 160+300 160+350 160+400 160+450 160+500 160+550 160+600 160+650 160+700 160+750 160+800 160+850 160+900 160+950 161+000 161+050 161+100 161+150 161+200 161+250 161+300 161+350 161+400 161+450 161+500 161+550 161+600 161+650 161+700 161+750 161+800 161+850 161+900 161+950 162+000 162+050 162+100 162+150 162+200 162+250 162+300 162+350 162+400 162+450 162+500 162+550 162+600 162+650 162+700 162+750 162+800 162+850 162+900 162+950 163+000 LHS SAI MAATARINI TOLLWAYS LIMITED Four Laning of Panikoili – Rimuli Road Section of NH-215 from Km 0+000 – 163+000 (Design Length 166+173 Kms) in the state of Odisha under NHDP Phase-III as BOT (Toll) Basis. Monthly Progress Report : March - 2015 Page 55 RHS OGL Samp. Testing C&G OGL FDD OGL Record EMB-1st EMB-2nd EMB-3rd EMB-4th EMB-5th EMB-6th EMB-Top SG-Ist SG-IInd SG-Top GSB WMM-1st WMM-Top KERB DBM BC M/s. SAI MAATARINI TOLLWAYS LIMITED 9th layer Minor Bridge 11th layer 9th layer 7th layer 9th layer 8th layer PUP Structure 8th layer 10th layer 11th layer Excavation Upto Emb Top 8th layer Minor Bridge Minor Bridge 10th layer 9th layer 11th layer 12th layer 14th layer 15th layer 18th layer PUP Structure 7th layer 10th layer 7th layer 9th layer Chainage 163+000 163+050 163+100 163+150 163+200 163+250 163+300 163+350 163+400 163+450 163+500 163+550 163+600 163+650 163+700 163+750 163+800 163+850 163+900 163+950 164+000 164+050 164+100 164+150 164+200 164+250 164+300 164+350 164+400 164+450 164+500 164+550 164+600 164+650 164+700 164+750 164+800 164+850 164+900 164+950 165+000 165+050 165+100 165+150 165+200 165+250 165+300 165+350 Layer165+400 165+450 165+500 165+550 165+600 165+650 165+700 165+750 165+800 165+850 165+900 165+950 166+000 166+050 166+100 166+150 166+200 BC DBM KERB WMM-Top WMM-1st GSB SG-Top SG-IInd SG-Ist EMB-Top EMB-6th EMB-5th EMB-4th EMB-3rd EMB-2nd EMB-1st OGL Record OGL FDD C&G OGL Samp. Testing Minor Bridge LHS SAI MAATARINI TOLLWAYS LIMITED Four Laning of Panikoili – Rimuli Road Section of NH-215 from Km 0+000 – 163+000 (Design Length 166+173 Kms) in the state of Odisha under NHDP Phase-III as BOT (Toll) Basis. Monthly Progress Report : March - 2015 Page 56 SAI MAATARINI TOLLWAYS LIMITED Four Laning of Panikoili – Rimuli Road Section of NH-215 from Km 0+000 – 163+000 (Design Length 166+173 Kms) in the state of Odisha under NHDP Phase-III as BOT (Toll) Basis. Monthly Progress Report : March - 2015 7.1. Progress of Major Bridges Foundation Sl. No. Chainage 1 35+342 Sub-str Super-str Side Scope Complete (%) Scope Complete (%) 2 0.46 23.23% Not Started due to resistance / deadlock created by adjacent Belbahali Villagers LHS RHS COMPLETED Sl. No. 1 IN PROGRESS Foundation Chainage Sub-str Super-str Side A1 P1 P2 P3 P4 A2 A1 P1 P2 P3 P4 A2 LHS 0 0 0 0 0 0 0 0 0 0 0 0 RHS 1 1 1 1 1 1 0.6 0.85 0.85 0.85 1 1 A1P1 P1P2 P2-P3 56+800 COMPLETED Chainage 1 83+568 Side P4-A2 Girder casting in progress Girder Casted IN PROGRESS Foundation Sl. No. P3-P4 23.23% Sub-str Super-str A1 P1 P2 P3 P4 A2 A1 P1 P2 P3 P4 A2 LHS 0 0 0 0 0 0 0 0 0 0 0 0 RHS 1 1 1 1 1 1 1 1 0.9 0.8 0.9 1 COMPLETED M/s. SAI MAATARINI TOLLWAYS LIMITED A1P1 P1P2 P2-P3 P3-P4 P4-A2 Scope Complete (%) 2 0.48 24.17% IN PROGRESS 24.17% Page 57 SAI MAATARINI TOLLWAYS LIMITED Four Laning of Panikoili – Rimuli Road Section of NH-215 from Km 0+000 – 163+000 (Design Length 166+173 Kms) in the state of Odisha under NHDP Phase-III as BOT (Toll) Basis. Monthly Progress Report : March - 2015 Sl. No. Chainage 1 108+058 Foundation Side Sub-str Super-str A1 P1 P2 P3 A2 A1 P1 P2 P3 A2 LHS 0 0 0 0 0 0 0 0 0 0 RHS 1 1 1 1 1 0.9 0.3 0.85 0.9 1 A1-P1 COMPLETED Chainage 1 139+495 Sub-str A1 P1 P2 P3 P4 P5 A2 A1 P1 P2 P3 P4 P5 A2 LHS 1 1 1 1 1 1 1 0.45 0.8 1 1 1 1 1 RHS 1 1 1 1 1 1 1 0.35 0.9 1 1 1 1 1 1 151+200 Scope Complete (%) 2 0.45 22.38% 22.38% A1P1 P1-P2 P2P3 Scope Complete P3P4 P4-P5 2 0.95 47.32% 47.32% Sub-str Side A1 P1 P2 P3 P4 P5 P6 P7 P8 P9 A2 A1 P1 P2 P3 P4 P5 P6 P7 P8 P9 A2 LHS 0 0 0.65 0.65 0 1 1 1 1 1 0 0 0 0 0 0 1 1 1 1 0 0 RHS 0.1 1 1 0.85 0.15 1 1 1 0.15 1 1 0 0.2 0.2 0 0 1 1 1 0.2 0 0.4 COMPLETED M/s. SAI MAATARINI TOLLWAYS LIMITED IN PROGRESS (%) P5-A2 IN PROGRESS Foundation Chainage P3-A2 Super-str Side COMPLETED Sl. No. P2-P3 IN PROGRESS Foundation Sl. No. P1-P2 A1P1 P1P2 P2P3 P4P5 Super-str P5P6P6 P7 P7P8 P8P9 Scope Complete (%) 2 0.51 25.63% P9A2 25.63% Page 58 SAI MAATARINI TOLLWAYS LIMITED Four Laning of Panikoili – Rimuli Road Section of NH215 from Km 0+000 – 163+000 (Design Length 166+173 Kms) in the state of Odisha under NHDP Phase-III as BOT (Toll) Basis. Monthly Progress Report : March - 2015 7.2. Progress of Minor Bridges Sl. No Chainage 1 17+100 2 22+017 3 Foundation Sub structure Super structure Scope Completed (%) BANDI RIVER 2 1.00 50.00% ANDHARI RIVER 2 1.00 50.00% 24+818 GHAGIA NALLA 2 0.50 25.00% 4 25+543 KALLAPAL JORE 2 1.00 50.00% 5 31+982 2 0.85 42.50% 6 33+672 2 0.85 42.50% 7 36+512 SASAN RIVER DHANAGHARA NALLAH KANNADIAPATA RIVER 2 1.00 50.00% 8 40+071 2 0.10 5.00% 9 44+400 JHADESWAR RIVER 2 1.13 56.25% 10 49+422 MUHAN 2 1.00 50.00% 11 57+322 2 1.00 50.00% 12 67+297 2 1.00 50.00% 13 82+625 SAGADIA NALLAH 2 1.50 75.00% 14 95+410 SITA RIVER 2 0.50 25.00% 15 97+913 ANIADHAR 2 0.13 6.25% 16 106+926 RIVER 2 0.65 32.50% 17 111+551 KHALIGHAT 2 0.13 6.25% 18 116+160 New construction 2 0.95 47.50% 19 117+074 New construction 2 0.85 42.50% 20 143+235 New construction 2 0.85 42.50% 21 146+697 New construction 2 0.85 42.50% 22 148+547 New construction 2 0.45 22.50% 2 0.00 0.00% (km) Identification LHS RHS LHS RHS LHS RHS These structures are not started due to impasse created by villagers of Jhumpura since long time. 23 149+027 New construction 24 151+990 New construction 2 0.70 34.75% 25 153+843 New construction 2 0.70 34.75% 26 155+467 2 0.95 47.50% 27 156+771 New construction New construction 2 2.00 100.00% 2 0.15 7.50% 2 0.85 42.50% 2 1.00 50.00% Average 39.36% 28 158+252 29 163+037 30 166+003 New construction New construction New construction COMPLETED M/s. SAI MAATARINI TOLLWAYS LIMITED IN PROGRESS Page 59 SAI MAATARINI TOLLWAYS LIMITED Four Laning of Panikoili – Rimuli Road Section of NH-215 from Km 0+000 – 163+000 (Design Length 166+173 Kms) in the state of Odisha under NHDP Phase-III as BOT (Toll) Basis. Monthly Progress Report : March - 2015 7.3. Progress of ROBs Sl. No. Chainage 1 9+233 Sl. No. Chainage 1 115+636 Foundation Side Sub-str Super-str A1 P1 P2 A2 A1 P1 P2 A2 LHS 1 1 1 1 0.9 0.7 0.8 0.9 RHS 1 1 1 1 0.7 0.8 0.8 0.9 Foundation Side A1 P1 Sub-str A2 LHS RHS A1 P1 0.15 0.9 0.35 A1-P1 P1-P2 P2-A2 Super-str A2 A1 P1 A2 0.8 COMPLETED Scope Complete (%) 2 0.91 45.31% Scope Complete (%) 2 0.55 27.50% 36.41% IN PROGRESS 7.4. Progress of Flyover Sl. No. 1 CHAINAGE 125+284.500 SIDE Foundation Sub Structure Super-Str (Girders) A1 P1 P2 P3 A2 A1 P1 P2 P3 A2 LHS 1 1 1 1 1 1 1 1 1 1 RHS 1 1 1 1 1 1 1 1 1 1 Weg. Actual Avg. 25.00% 25.00% 25.00% 25.00% A1-P1 P1-P2 P2-P3 Super-Str (Deck slab) P3-A2 A1-P1 P1-P2 P2-P3 P3-A2 0.25 1 30.00% 3.75% 20.00% 0.00% 53.75% COMPLETED M/s. SAI MAATARINI TOLLWAYS LIMITED IN PROGRESS Page 60 SAI MAATARINI TOLLWAYS LIMITED Four Laning of Panikoili – Rimuli Road Section of NH-215 from Km 0+000 – 163+000 (Design Length 166+173 Kms) in the state of Odisha under NHDP Phase-III as BOT (Toll) Basis. Monthly Progress Report : March - 2015 7.5. Progress of Vehicular Under Passes (VUPs): Sl. No. Design chainage 1 10+673 2 Size Foundation Sub structure Super structure Scope Completed (%) 1 x 12.00 x 5.50 2 2.000 100.00% 20+038 1 x 12.00 x 5.50 2 2.000 100.00% 3 23+544 1 x 12.00 x 5.50 2 2.000 100% 4 29+857 1 x 12.00 x 5.50 2 1.000 50.00% 5 38+783 1 x 12.00 x 5.50 2 1.000 50.00% 6 42+133 1 x 12.00 x 5.50 2 2.000 100.00% 7 45+448 1 x 12.00 x 5.50 2 0.000 0.00% 8 53+382 1 x 12.00 x 5.50 2 2.000 100.00% 9 77+950 1 x 12.00 x 5.50 2 1.650 82.50% 10 90+500 1 x 12.00 x 5.50 2 0.750 37.50% 11 115+118 1 x 12 x 5.50 2 2.000 100.00% 12 117+685 1 x 12 x 5.50 2 2.000 100.00% 13 122+926 1 x 12 x 5.50 2 2.000 100.00% 14 128+846 1 x 12 x 5.50 2 2.000 100.00% 15 131+412 1 x12 x 5.5 2 2.000 100.00% LHS RHS LHS RHS LHS RHS DELETED COMPLETED 81.33% IN PROGRESS 7.6. Progress of Pedestrian Under Passes (PUPs): Sl. No. Design Chainage Size 1 05+665 2 Foundation Sub structure Super structure Scope Completed (%) 1x5x3 2 2.000 100.00% 09+630 1 x 5.00 x 3.00 2 2.000 100.00% 3 15+838 1 x 5.00 x 3.00 2 1.350 67.50% 4 22+705 1 x 5.00 x 3.00 2 1.000 50.00% 5 24+505 1 x 5.00 x 3.00 2 0.000 0.00% 6 37+187 1x5x3 2 1.850 92.50% 7 40+838 1x5x3 2 2.000 100.00% 8 51+512 1x5x3 2 2.000 100.00% 9 76+800 1 x 5.0 x 3.0 2 0.000 0.00% 10 94+254 1 x 5.0 x 3.0 2 1.000 50.00% 11 109+676 1 x 5.0 x 3.0 2 2.000 100.00% 12 114+576 1x5x3 2 2.000 100.00% 13 118+272 1x5x3 2 2.000 100.00% 14 120+680 1x5x3 2 2.000 100.00% 15 126+981 1x5x3 2 2.000 100.00% 16 127+632 1x5x3 2 2.000 100.00% 17 136+518 1x5x3 2 2.000 100.00% 18 142+651 1x5x3 2 2.000 100.00% LHS RHS LHS M/s. SAI MAATARINI TOLLWAYS LIMITED RHS LHS RHS Page 61 SAI MAATARINI TOLLWAYS LIMITED Four Laning of Panikoili – Rimuli Road Section of NH215 from Km 0+000 – 163+000 (Design Length 166+173 Kms) in the state of Odisha under NHDP Phase-III as BOT (Toll) Basis. Monthly Progress Report : March - 2015 Sl. No. Design Chainage Size 19 149+792 20 21 Foundation Sub structure Super structure Scope Completed (%) 1x5x3 2 0.750 37.50% 156+099 1x5x3 2 2.000 100.00% 164+267 1x5x3 2 2.000 100.00% LHS RHS LHS RHS LHS COMPLETED RHS IN PROGRESS 80.83% 7.7. Progress of Culverts (Pipe/Box/Slab): Sl. No. Chainage 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 01+177 02+115 03+051 03+452 03+871 04+363 05+069 05+956 08+556 09+140 11+370 11+600 12+376 13+060 13+266 13+952 14+240 14+700 15+680 16+382 17+375 17+563 18+300 19+901 20+627 20+783 21+070 21+224 21+692 21+852 23+015 23+430 23+925 25+956 26+360 27+075 27+494 27+753 28+147 28+732 28+927 30+105 30+307 30+646 31+295 32+319 32+460 32+646 33+125 34+252 Structure Type Box Culvert HP Culvert HP Culvert HP Culvert HP Culvert HP Culvert HP Culvert HP Culvert HP Culvert Box Culvert HP Culvert HP Culvert HP Culvert Box Culvert HP Culvert HP Culvert HP Culvert Box Culvert HP Culvert HP Culvert HP Culvert HP Culvert HP Culvert HP Culvert HP Culvert Box Culvert HP Culvert HP Culvert HP Culvert Box Culvert Box Culvert Box Culvert Box Culvert Box Culvert Box Culvert Box Culvert Slab Culvert Box Culvert Box Culvert Box Culvert Box Culvert Box Culvert Box Culvert Box Culvert HP Culvert Box Culvert Box Culvert Box Culvert Box Culvert Box Culvert Foundation LHS RHS Sub Structure LHS RHS M/s. SAI MAATARINI TOLLWAYS LIMITED Super Structure LHS RHS Scope Completed (%) 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 1 2 1.75 1.5 1.125 1.125 1 0.25 0.5 0.45 2 2 2 2 1 2 2 2 50.00% 100.00% 87.50% 75.00% 56.25% 56.25% 50.00% 12.50% 25.00% 22.50% 100.00% 100.00% 100.00% 100.00% 50.00% 100.00% 100.00% 100.00% 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 1 1 1.125 2 1.5 1.125 1.125 1 0.45 1 1 1 1 1 1 1 1 1 0.35 1 1 0.125 1 1 1 1 0.25 100.00% 100.00% 100.00% 100.00% 50.00% 50.00% 56.25% 100.00% 75.00% 56.25% 56.25% 50.00% 22.50% 50.00% 50.00% 50.00% 50.00% 50.00% 50.00% 50.00% 50.00% 50.00% 17.50% 50.00% 50.00% 6.25% 50.00% 50.00% 50.00% 50.00% 12.50% DELETED Page 62 SAI MAATARINI TOLLWAYS LIMITED Four Laning of Panikoili – Rimuli Road Section of NH215 from Km 0+000 – 163+000 (Design Length 166+173 Kms) in the state of Odisha under NHDP Phase-III as BOT (Toll) Basis. Monthly Progress Report : March - 2015 Sl. No. Chainage 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66 67 68 69 70 71 72 73 74 75 76 77 78 79 80 81 82 83 84 85 86 87 88 89 90 91 92 93 94 95 96 97 98 99 100 101 102 103 104 105 106 107 108 109 110 111 112 36+119 36+201 39+101 39+920 40+195 41+245 42+965 43+155 43+577 43+882 44+612 44+941 45+091 45+820 46+135 46+747 47+024 47+235 47+359 47+705 47+870 48+080 49+066 49+260 51+883 52+135 53+798 54+101 54+101 55+243 55+438 55+723 57+825 58+230 58+877 59+401 60+529 62+305 62+734 63+371 64+478 77+470 77+640 79+587 80+954 85+493 86+550 91+602 91+817 92+402 93+362 94+166 96+112 96+604 96+697 96+807 99+676 100+042 100+656 100+920 100+983 101+060 Structure Type Box Culvert Box Culvert Box Culvert Box Culvert Box Culvert Box Culvert HP Culvert Box Culvert Box Culvert Box Culvert HP Culvert Box Culvert Box Culvert Box Culvert Box Culvert Box Culvert Box Culvert Box Culvert Box Culvert Box Culvert Box Culvert Box Culvert Box Culvert Box Culvert Box Culvert Box Culvert Box Culvert Box Culvert Box Culvert Box Culvert Box Culvert Box Culvert Box Culvert Box Culvert Box Culvert Box Culvert Box Culvert Box Culvert Box Culvert Box Culvert Box Culvert Box Culvert Box Culvert Box Culvert Box Culvert HP Culvert Box Culvert Box Culvert Box Culvert Box Culvert Box Culvert Box Culvert Box Culvert Box Culvert Box Culvert Box Culvert Box Culvert Box Culvert Box Culvert Box Culvert Box Culvert Box Culvert Foundation LHS RHS Sub Structure LHS RHS M/s. SAI MAATARINI TOLLWAYS LIMITED Super Structure LHS RHS Scope Completed (%) 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 0.125 1 0.125 2 2 2 2 1.75 1.75 1.35 1.125 1.25 1.125 1 1 1.125 1 1 1 1 1 1 1 1 2 1 1 1 1 1 1 1 0.125 1 2 1 2 2 2 2 2 0.25 0.25 0.35 0.35 1 1 1.5 1.5 1 1 1 1 1 1 2 1 1 1 1 0.125 1 6.25% 50.00% 6.25% 100.00% 100.00% 100.00% 100.00% 87.50% 87.50% 67.50% 56.25% 62.50% 56.25% 50.00% 50.00% 56.25% 50.00% 50.00% 50.00% 50.00% 50.00% 50.00% 50.00% 50.00% 100.00% 50.00% 50.00% 50.00% 50.00% 50.00% 50.00% 50.00% 6.25% 50.00% 100.00% 50.00% 100.00% 100.00% 100.00% 100.00% 100.00% 12.50% 12.50% 17.50% 17.50% 50.00% 50.00% 75.00% 75.00% 50.00% 50.00% 50.00% 50.00% 50.00% 50.00% 100.00% 50.00% 50.00% 50.00% 50.00% 6.25% 50.00% Page 63 SAI MAATARINI TOLLWAYS LIMITED Four Laning of Panikoili – Rimuli Road Section of NH215 from Km 0+000 – 163+000 (Design Length 166+173 Kms) in the state of Odisha under NHDP Phase-III as BOT (Toll) Basis. Monthly Progress Report : March - 2015 Sl. No. Chainage 113 114 115 116 117 118 119 120 121 122 123 124 125 126 127 128 129 130 131 132 133 134 135 136 137 138 139 140 141 142 143 144 145 146 147 148 149 150 151 152 153 154 155 156 157 158 159 160 161 162 163 164 165 166 167 168 169 170 171 172 173 174 101+557 101+980 103+187 104+282 104+577 105+255 105+395 105+633 105+765 105+872 106+062 106+332 109+724 113+877 114+137 114+927 115+322 115+850 116+420 116+687 117+222 117+397 117+817 118+103 118+437 118+677 118+982 119+197 119+457 119+697 119+797 120+087 120+677 120+770 120+907 121+117 121+297 121+467 121+937 122+109 122+237 122+597 122+883 123+117 123+677 123+857 124+487 124+887 125+447 126+262 126+417 127+327 127+470 128+567 128+707 129+540 130+091 130+457 130+896 130+990 131+500 131+540 Structure Type Box Culvert Box Culvert Box Culvert Box Culvert Box Culvert Box Culvert Box Culvert Box Culvert Slab Culvert Box Culvert Box Culvert Box Culvert Box Culvert Box Culvert Box Culvert Box Culvert Box Culvert Box Culvert Box Culvert Box Culvert Box Culvert Box Culvert Box Culvert Box Culvert Box Culvert Box Culvert Box Culvert Box Culvert Box Culvert Box Culvert Box Culvert Box Culvert Box Culvert Box Culvert Box Culvert Box Culvert Box Culvert Box Culvert Box Culvert Box Culvert Box Culvert Box Culvert Box Culvert Box Culvert Box Culvert Box Culvert Box Culvert Box Culvert Box Culvert Box Culvert Box Culvert Box Culvert Box Culvert Box Culvert Box Culvert HP Culvert Box Culvert Box Culvert Box Culvert Box Culvert Box Culvert Box Culvert Foundation LHS RHS 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 Sub Structure LHS RHS 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 M/s. SAI MAATARINI TOLLWAYS LIMITED 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 Super Structure LHS RHS 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 Scope Completed (%) 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 0.125 0.125 1 1 0.35 1 0.65 1 1.125 1 0.25 1 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 1 2 2 1 1 1 1 6.25% 6.25% 50.00% 50.00% 17.50% 50.00% 32.50% 50.00% 56.25% 50.00% 12.50% 50.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 50.00% 100.00% 100.00% 50.00% 50.00% 50.00% 50.00% Page 64 SAI MAATARINI TOLLWAYS LIMITED Four Laning of Panikoili – Rimuli Road Section of NH215 from Km 0+000 – 163+000 (Design Length 166+173 Kms) in the state of Odisha under NHDP Phase-III as BOT (Toll) Basis. Monthly Progress Report : March - 2015 Sl. No. Chainage 175 176 177 178 179 180 181 182 183 184 185 186 187 188 189 190 191 192 193 194 195 196 197 198 199 200 201 202 203 204 205 206 207 208 209 210 211 212 213 214 132+645 133+827 134+472 135+554 139+853 140+593 140+877 141+365 141+647 141+764 142+237 145+898 146+572 147+107 147+317 147+477 150+113 151+677 152+445 152+835 153+175 154+276 154+515 155+000 155+998 158+592 158+971 159+323 160+421 160+896 161+259 161+588 161+920 163+331 163+801 164+036 164+191 164+521 164+631 165+104 Structure Type Box Culvert Box Culvert Box Culvert Box Culvert Box Culvert Box Culvert Box Culvert Box Culvert Box Culvert Box Culvert Box Culvert Box Culvert Box Culvert Box Culvert Box Culvert Box Culvert Box Culvert Box Culvert Box Culvert Box Culvert Box Culvert Box Culvert Box Culvert Box Culvert HP Culvert Box Culvert HP Culvert Box Culvert Box Culvert Box Culvert Box Culvert Box Culvert Box Culvert Box Culvert Box Culvert Box Culvert Box Culvert Box Culvert Box Culvert Slab Culvert Foundation LHS RHS 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 Sub Structure LHS RHS 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 COMPLETED M/s. SAI MAATARINI TOLLWAYS LIMITED 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 Super Structure LHS RHS 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 IN PROGRESS Scope Completed (%) 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 0.125 1 1 1 2 1 1 1 1 1 1 2 2 0.65 0.25 0.25 1.5 1 1 1 1 1 1 2 1 1 1 1 2 2 2 1 2 2 2 2 2 2 2 1 6.25% 50.00% 50.00% 50.00% 100.00% 50.00% 50.00% 50.00% 50.00% 50.00% 50.00% 100.00% 100.00% 32.50% 12.50% 12.50% 75.00% 50.00% 50.00% 50.00% 50.00% 50.00% 50.00% 100.00% 50.00% 50.00% 50.00% 50.00% 100.00% 100.00% 100.00% 50.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 50.00% 66.93% Page 65 SAI MAATARINI TOLLWAYS LIMITED Four Laning of Panikoili – Rimuli Road Section of NH215 from Km 0+000 – 163+000 (Design Length 166+173 Kms) in the state of Odisha under NHDP Phase-III as BOT (Toll) Basis. Monthly Progress Report : March - 2015 8. Construction Constraints: Concessionaire has communicated Constraints vide its Lr. No. 375 dated 25-09-2014 which is as follows A. Land Acquisition: (a) Jajpur District (Km 0+000 to Km 24+000) : Impediments (b) HT lines at Km 7+010 & Km 7+670 : (1.) OPTCL has been prepared the estimate of 220KV & 132 KV HT Lines and submitted to Project Director vide their Lr. No. Tech/TL-2/140(9) dt. 16-01-15 & Tech/TL7/141(9) dt. 16-01-15 to a tune of Rs. 1,05,31,667/- & Rs. 36,27,296/- respectively. (2.) Project Director vide their Lr. No. 7116 dated 18-03-2015 addressed GM(Electrical), OPTCL, Jajpur Road to clarify 8 points before placing the funds (c) Irrigation Culverts - 9 Nos (Lr. No. 416 dt: 20-09-14) Ch: 23+500, 23+500, 20+280, 19+850, 18+490, 16+330, 7+300, 5+610 & 0+850 Based on the basic parameters received from PIU, the details were furnished immediately to Sheladia on 25-03-2015 for preparation of GADs and Tentative estimates (d) Govt./Religious Structures: 7 Nos. (Lr. No. 424 dt: 21-09-14,488 dt: 02-12-14 Lr. No. 500 dt:25-12-14) Ch. 04+380, 14+600, 15+060, 15+960, 22+940, 23+005, 23+005 The guidelines on execution of Govt. / Religious Structures which are within PROW were not given by PIU even by 31-01-2015 despite several requests for the last more than 1 year. The obstacles shown above to an extent of 17 nos. irrespective of their length are adversely affecting the performance of Concessionaire in the entire 24Kms length. Keonjhar District (Km 24+000 to Km 166+173): Impediments (a) Realignment (2Kms) of Major Bridge at Km 35+315 (Lr. No. 524 dated 31-01-2015): Belbahali villagers are fiercely or violently opposing the approved alignment despite acceptance by Govt. of Odisa. The stalemate is yet to be resolved, though PD addressed District Magistrate & Collector, Keonjhar vide Lr. No. 6888 dated 23-01-2015 to give police protection to Concessionaire in the back drop of recommendation of 3 Member committee constituted by Govt. of Odisha finalizing the alignment no-01 (as per C.A.) but the Police force couldn’t stall violent mob fiercely sitting across the PROW objecting the commencement execution of the realignment by Gayatri Projects Ltd., EPC Contractor. (b) Govt./Religious Structures: 157 Nos. (Lr. No. 488 dt: 02-12-14 & Lr. No. 500 dt:25-12-14) These structures affect the execution over a length of 26.50 KMs scattered over a length of 142.173 Kms. i.e., 1 structures hinders at every 905meters on an average. No guidelines were given on methodology to be adopted for new construction of these structures till now, causing serious impediment within PROW for execution. (c) Acquisition of left out plots in the earlier 3D notification for following stretches requested for direct purchase (Lr. No. 503 dt: 30-12-2014) Sl. No. 1 Name of Thasil No of left out plots Ghatagaon M/s. SAI MAATARINI TOLLWAYS LIMITED 54 Additional Area (Acres) 3.940 Page 66 SAI MAATARINI TOLLWAYS LIMITED Four Laning of Panikoili – Rimuli Road Section of NH215 from Km 0+000 – 163+000 (Design Length 166+173 Kms) in the state of Odisha under NHDP Phase-III as BOT (Toll) Basis. Monthly Progress Report : March - 2015 Sl. No. Name of Thasil No of left out plots Additional Area (Acres) 2 Ghasipura 86 3.850 3 4 Anandapur Champua 19 4 1.050 1.100 5 Sadar 25 2.095 6 Jhumpura 6 0.560 194 12.595 Total : (d) Irrigation Culvert - 22 Nos Based on the basic parameters received from PIU, the details were furnished immediately to Sheladia on 25-03-2015 for preparation of GADs and Tentative estimates. (e) Change of Scope Notice for VUP at KM 115+118 (Lr. No. 500 dt:25-12-14) (f) Obstruction of Siba temple @ Km 113+400 in Jamunalia (Lr. No. 500 dt:25-12-14) (g) Left out structures in 46 locations in Keonjhar District (Lr. No. 500 dt:25-12-14) (h) Stalemate in Arshala Village Km 149+300 to 150+500 (Lr. No. 500 dt:25-12-14) (i) Minor Bridges at KM 148+457 & Km 149+027 (2 Nos) in Jumpura Bypass at Bhaluka village (Lr. No. 500 dt:25-12-14) (j) Prevention of execution in between Km 166+000 to Km 166+173 by villagers for higher compensation. (This issue was discussed in Review Meeting on 03-09-14 & 24-09-2014, Lr. No. 500 dt:25-12-14). B. Forest Land Diversion Proposal: Obtained from MoEF vide Order No. F.No. 8-01/2014-FC, GOI, MoEF, FC – Division, New Delhi, dated 06-05-2014 for Stage-I clearance. In regard the Stage-II Forest Clearance, the user agency is permitted vide MoEF & CC order No. F.NO. 11-306/2014-FC, GOI, FC Division, New Delhi on 08-08-2014 to fell the forest trees and use the land for the purpose of executing the project irrespective of issuance of Stage-II clearance provided the user agency (NHAI) paid the requisite costs as mentioned in the conditions laid down in stage-I forest clearance which was issued to this project. NHAI has deposited levies to a greater extent but still to deposit some more funds to obtain tree felling permission in forest area ( “608 days time” from stipulated date vide Cl. 10.3.4 of C.A. is lapsed by 31-03-2015). C. Eviction of Encroachments: Eviction of encroachments has been mostly completed in the entire project stretch except in Arsala Village (Km149+300 to 151+150) & Gopinathpur to an extent of 250meters. D. Govt. Land Alienation: Jajpur District: 59 cases were filed with Vyasanagar Tahasil Keonjhar District: 305 cases (Ghasipura-78, Anandpur-30, Ghatgaon-60, Sadar-97, Bansapal (new)-3, Champua-10, Jhumpura (New) 27) were filed. The alienation may take some time for official transfer of land to Authority by way of mutation. Project Director has to take expeditious steps on the matter. E. Court cases, Arbitration cases: There are about 217 Arbitration cases in Keonjhar District and a dozen cases in Jajpur District. M/s. SAI MAATARINI TOLLWAYS LIMITED Page 67 SAI MAATARINI TOLLWAYS LIMITED Four Laning of Panikoili – Rimuli Road Section of NH215 from Km 0+000 – 163+000 (Design Length 166+173 Kms) in the state of Odisha under NHDP Phase-III as BOT (Toll) Basis. Monthly Progress Report : March - 2015 9. a) Additional Scope: 31 Irrigation culverts are being taken up under additional scope as deposit works of irrigation Department, Govt. of Odisha b) Change of Scope: 1. 31 Nos. New Culverts pertaining to Irrigation Department: Project Director has communicated in principle approval of these additional culverts vide Lr. No. 6067, dated 24-04-2014 for which Change of Scope Notice has to be issued for all 31 culverts as I.E. vide Lr. No. 123 dated 30-05-2014 has communicated to PD, a comprehensive proposal on the matter. Project Director has been requested vide Concessionaire’s Lr. No. 384, dated 28-07-2014 to address irrigation wings between Km 0+000 to Km 113+000 to request the latter to support GPL for joint survey of 21 Irrigation Culverts falling within the area to exactly locate the crossing points on NH215, decide upon invert levels, exact size of vents etc., in order to communicate to Sheladia for preparation of design & drawings with estimate at an early date, as GPL found that the Jr. level officers are not cooperating for joint survey passing out the time. The stalemate still continues. Therefore, the EPC Contractor proceeding ahead with Four-Laning unmindful on execution of Irrigation culverts in the back drop of inordinate apathy of Irrigation department. However PD has called for a meeting with irrigation department vide Lr. No.6325 & 6326 dt. 12-01-215 and consequent joint visit, but the ultimate solution is yet to emerge. Estimates for 11 nos culverts, upon approval of GADs, were prepared and submitted to P.D. in turn I.E. scrutinized and submitted to P.D. vide their Lr. No. 217 dated 25-12-2014. PD. has to take action to get the funds obtained from line department and 20% advance payment to be deposited to Concessionaire pursuant to Cl. 16.3.1 of C.A. 2. VUP at KM 115+189 (MDR-Tulasichunura): The Cost comparison between Single & Double cell VUP at Km 115+189 has been furnished to I.E. vide this office Lr. No. 402 dated 14-11-2014. I.E., has verified the same and furnished to P.D. vide their Lr. No. SAI/IC/02/200/2014, dated 21-11-2014. PD vide Lr. No. 6719 dated 11-12-14 addressed I.E. to submit comprehensive report along with details justification for provision of double cell VUP at Km 115+189 under change of scope under ARTICLE-16 of C.A. The Concessionaire vide Lr. No. 524 dated 31-01-2015 addressed to P.D. with a request to issue “Change of Scope Notice” without further delay. 3. Additional box culvert size 2.5m x 2.5m: Where genuine demands of public in different locations of project highway for providing PUPs are raised, it has been decided by Manager(Tech.,), NHAI, TL, I.E., & EPC Contractor during their joint inspection to site on 23-02-2014, to provide 2.5m X 2.5m size of Box Culverts to included in Change of Scope in due course. Concessionaire vide Lr. No. 536 dated 26-02-2015 has notified the same to PIU, providing comprehensive estimate to initiate for in principle approval from Authority in respect of such box culvert pertaining to Section-2, GPL. M/s. SAI MAATARINI TOLLWAYS LIMITED Page 68 SAI MAATARINI TOLLWAYS LIMITED Four Laning of Panikoili – Rimuli Road Section of NH215 from Km 0+000 – 163+000 (Design Length 166+173 Kms) in the state of Odisha under NHDP Phase-III as BOT (Toll) Basis. Monthly Progress Report : March - 2015 10. Claims: a. Extension of Time (EOT) for achieving Mile stones & Scheduled 4-Laning Date: 1. Letter No. SMTL/P-R/NH-215/TSN-CGM/I.E./2013-14/023, dated 21-09-2013 addressed to I.E. for E.O.T. – Delay in acceptance of Designs & Drawings by 1 year 3 months & accessibility of land of 72 Kms (43.37%) for Project Work. 2. Letter No. SMTL/P-R/NH-215/TSN-CGM/I.E./2013-14/025, dated 22-09-2013 addressed to I.E. for E.O.T. of 5 months – Delay in permissions / approvals for electrical utility shifting. 3. Letter No. SMTL/P-R/NH-215/TSN-CGM/I.E./2013-14/055, dated 11-11-2013 addressed to I.E. indicating the facts of delay on the obligation of NHAI before commencement of execution of 4laning pursuant to Cl. 12.4.1 of C.A. 4. Letter No. SMTL/P-R/NH-215/TSN-CGM/I.E./2013-14/071, dated 23-11-2013 addressed to I.E. for E.O.T. of 7 Month – Delay in Tree felling. 5. Letter No. SMTL/P-R/NH-215/TSN-CGM/I.E./2013-14/075, dated 26-11-2013 addressed to I.E. for E.O.T. of 7 Months.– Delay for shifting of RWSS & PH Pipe lines 6. Letter No. SMTL/P-R/NH-215/TSN-CGM/I.E./2013-14/076, dated 26-11-2013 addressed to I.E. for E.O.T. of 7 Months. – Delay in Tree felling. 7. Letter No. SMTL/P-R/NH-215/TSN-CGM/I.E./2013-14/183, dated 10-03-2014 addressed to I.E. for E.O.T. – Determination of extension of Time for all Milestones or the Scheduled Four Laning Date and amendment for them as stipulated in Cl. 6 of Schedule-G and Cl. 12.4.2 of Concession Agreement for the reasons of delay in obligations attributable to Authority / Independent Engineer – Requested. 8. Lr. No. SAI/IC/03/241/2014, dated 27-03-2014 – I.E. has stated that the extension of time is not justified and untenable without calling for verifying relevant documents, records of evidence from either NHAI / Concessionaire. Thus the action of IE is arbitrary & indiscreet. 9. Lr. No. SMTL/P-R/NH-215/TSN-CGM/I.E./2013-14/309, dated 21-06-2014 addressed to I.E. substantiating its claim for occurrence of Milestone-I with a detailed substance. 11. Disputes a) Letter No. SMTL/P-R/NH-215/TSN-CGM/I.E./2013-14/182, dated 10-03-2014 addressed to I.E. for E.O.T. – Review of Design & Drawings by Independent Engineer pursuant to Cl. 12.3 of C.A. – Abnormal delay in review of about 10 months from Appointed Date after submission of Design & Drawings – Determination of Extension of Time for Project Milestones & Scheduled Four Laning Date pursuant to Cl. 12.4.2 of C.A. and Cl. 3.1 (vii) & Cl. 8.2 Schedule-Q of C.A. – Requested. b) Letter No. SMTL/P-R/NH-215/TSN-CGM/I.E./2013-14/183, dated 10-03-2014 addressed to I.E. for E.O.T. – Determination of extension of Time for all Milestones or the Scheduled Four Laning Date and amendment for them as stipulated in Cl. 6 of Schedule-G and Cl. 12.4.2 of Concession Agreement for the reasons of delay in obligations attributable to Authority / Independent Engineer – Requested. c) In Lr. No. SAI/IC/03/247/2014, dated 01-04-2014 I.E. has rejected the plea of Concessionaire for EOT for 10 months which was demanded vide Lr. No. 183 dated 10-03-2014. d) In Lr. No. SMTL/P-R/NH-215/TSN-CGM/I.E./2013-14/211, dated 01-04-2014 Concessionaire has informed I.E. that it would go for “Dispute Resolution” vide Cl. 44 of C.A. for the rejection made vide Lr. No. 247 dated 01-04-2014. e) Concessionaire vide its Lr. No. SMTL/P-R/NH-215/TSN-CGM/NHAI/2014-15/309, dated 18-042014 addressed to P.D. requesting him to restrain from imposing damages for Non-occurrence of M/s. SAI MAATARINI TOLLWAYS LIMITED Page 69 SAI MAATARINI TOLLWAYS LIMITED Four Laning of Panikoili – Rimuli Road Section of NH215 from Km 0+000 – 163+000 (Design Length 166+173 Kms) in the state of Odisha under NHDP Phase-III as BOT (Toll) Basis. Monthly Progress Report : March - 2015 f) g) h) i) j) k) l) m) n) o) p) q) r) s) t) u) Milestone-1 as recommended by IE. vide their letter No. 1399 dated 04-04-2014, the contents of which are not agreed to by Concessionaire who requested to maintain status quo until EOT case under dispute is settled. Concessionaire vides its Lr. No. SMTL/P-R/NH-215/TSN-CGM/I.E./2013-14/238, dated 21-04-2014 notified I.E. with a request to mediate and assist the parties to dispute for arriving at an amicable settlement pursuant to Cl. 44.2 (conciliation) of C.A. I.E. vide their Lr. No. SAI/IC/02/110/2014, dated 29-04-2014 informed P.D. on the intention of Concessionaire for dispute resolution and narrated the provisions in Cl. 44.2 of C.A. with a copy to Concessionaire. Concessionaire vide its Lr. No. SMTL/P-R/NH-215/TSN-CGM/I.E./2014-15/254, dated 06-05-2014 requested IE to take up dispute resolution in consonance with Cl. 44.2 of C.A. through conciliation. Concessionaire vide its Lr. No. REF: SMTL/P-R/NH-215/TSN-CGM/NHAI/2013-14/325, dated 0905-2014 addressed to PD for EOT for 10 months Concessionaire vode its Lr. No. SMTL/P-R/NH-215/TSN-CGM/NHAI/2013-14/326, dated 11-052014 addressed to PD for EOT for 10 months. Concessionaire vide its Lr. No. SMTL/P-R/NH-215/TSN-CGM/I.E./2013-14/274, dated 17-05-2014 addressed to I.E. requested for EOT of 365 days for project milestones under various reasons. Concessionaire vide its Lr. No. SMTL/P-R/NH-215/TSN-CGM/I.E./2013-14/278, dated 23-05-2014 addressed to I.E. requested for EOT of 365 days for project milestones under various reasons. IE vide their Lr. No. SAI/IC/02/120/2014, dated 26-05-2014 addressed to P.D. asked to provide details and documents related to action taken by PIU under Cl. 10.3 of C.A. As a reply to PDs Lr. No. NHAI/11011/1/PKR(SMTPL)/2012/PIU/KJR/6162, dated 29-05-2014, Concessionaire vide its Lr. No. SMTL/P-R/NH-215/TSN-CGM/NHAI/2013-14/342, dated 31-052014 has replied with its legitimate demand of EOT for 365 days as on 31-05-2014. IE vide their Lr. No. SAI/IC/02/163/2014, dated 01-09-2014 addressed to P.D. asked to provide details in letters shown in item (j) & (K) by Concessionaire (addressed to PD) and item no. (l) & (m) by Concessionaire (addressed to I.E.) for taking necessary further action on conciliation. COO, IE vide their Lr. No. SAI/4801/2014, dated 19-12-2014 requested Concessionaire to provide comprehensive information on Dispute Resolution on EOT pursuant Cl. 44.2 of C.A. for finalizing the scope of mediation. Concessionaire vide Lr. No.446 dated 30-12-2014 addressed COO, IE has furnished the total information in respect of EOT. Concessionaire vide Lr. No. 503 dated 03-01-2015 addressed to PD with a copy to I.E. maintained that they have right to claims under C.A. Project Director vide their Lr. No. 6841 dated 13-01-2015 addressed COO, IE has given the latter his opinion in the three bullet points. I.E. vide Lr. No. 631 dated 18-02-2015 has communicated to Project Director & Concessionaire the 1st Conciliation Meeting to be held on 05-03-2015 at 2:30 PM in I.E.’s office, Ahmadabad. Concessionaire, after discussions and taking opinion of the Project Director, PIU, NHAI, Keonjhar addressed Chief Operating Officer, I.E., Ahmadabad requesting him vide Lr. No. 497 dt: 25-2-15 to change the Venue to Bhubaneswar for holding the conciliation meeting on any convenient dated mutually agreed by all parties. M/s. SAI MAATARINI TOLLWAYS LIMITED Page 70 SAI MAATARINI TOLLWAYS LIMITED Four Laning of Panikoili – Rimuli Road Section of NH215 from Km 0+000 – 163+000 (Design Length 166+173 Kms) in the state of Odisha under NHDP Phase-III as BOT (Toll) Basis. Monthly Progress Report : March - 2015 12. Non Conforming Product Notifications (NCPNs). Sl. No. NCPN No I.E.'s Lr. No. 1 2 SAI/IC/03/178/ 2013 Dt.08-022014 2 3 SAI/IC/03/179/ 2014 Dt.10-022014 4 SAI/IC/03/188/ 2014 Dt.14-022014 3 4 5 SAI/IC/03/196/ 2014 Dt.17-022014 5 11 SAI/IC/03/223/ 2014 Dt.0803-2014 6 14 SAI/IC/03/283/ 2014 dt.0105-2014. 7 16 SAI/IC/03/374/ 2014 8 18 SAI/IC/03/377/ 2014 9 20 SAI/IC/03/431/ 2014 Description PMC Lr. No. & Date SMTL Lr. No. & Date Compliance Major Bridge at Km 56+800 (A2). Since the Design related issues (Founding Level) has not resolved/settled for Major Bridge at Km 56+800, the Concessionaire has constructed the Raft (A2) without submission of compliance report, as IE designer's commented on submitted design and drawings of aforementioned structure. Fly Over at Km 125+284.5 (A2&P3). Since the Design related issues (Overlapped pressure bulbs of Abutment & adjacent pier is not considered in the design) has not resolved/settled for Fly Over at Km 125+284.5, the Concessionaire has constructed the Raft (A2&P3) without submission of compliance report, as IE designer commented on submitted design and drawings of aforementioned structure. Km 146 (Batching Plant). Without Calibration of Admixture at Km 146 Batching Plant, Production of Concrete started. SMTL/P-R/NHSheladia/PMC/ 215/TSNNH-215/2013CGM/I.E./201414/97 Dt. 15/520 18-02-2014 dt.28-03-2015 Major Bridge at Ch. 56+800. 1st lift of Abutment/Return Wall: A2 1. Haunch not provided as shown in the Drgs 2. Dowels for lap is very SMTL/P-R/NHless (500mm to 1500mm instead of two layers as shown in the Sheladia/PMC/ 215/TSNdrawings). 3. Vertical bars in Abutment wall are fixed in one layer NH-215/2013CGM/I.E./2013instead of two layer as shown in the drawings. 4. RFIs are not 14/122 Dt. 14/197 submitted but the Concessionaire for casting footing and 1st lift of 19-03-2014 Dt.19-03-2014 wall. 5. 1st lift of wall (Abutment & Return) is casted after all NCR has been issued to Concessionaire. AT Km 56+800 Major Bridge: As per IE designer comments, concessionaire has to furnish the data of RQD, UCS and core recovery for all abutments and piers for conformity of hard rock, but without submission of aforesaid data PCC for P4 has been done and further reinforcement has been placed for concrete (Raft) works. Hence it is considered as non-conformity of work till submission of required of necessary data. Safety during Construction: At Km 56+800 MAJOR BRIDGE: Foundation & walls of Pier P2, Pier P3 and Pier P4 are completed without submitting the confirmatory Boring details and laboratory test results for IE’s review & comments. Wherever the GSB laying is in progress thickness provided is not uniform under the main carriageway, shoulders & median. GSB thickness under median and shoulders is less than that of the main carriageway. Locations: LHS – 113+600 – 113+880, 114+020 – 114+550, 114+590 – 114+770, 119+000 – 119+400, 119+580 120+080, 121+200 – 121+930, 122+000 – 122+090, 122+120 – 122+470, 123+380 – 123+600, 128+250 – 128+550, 130+600 – 130+900, 131+800 – 132+300, 132+960 – 133+300, 134+340 – 134+900, 135+060 – 135+560, 135+800 – 136+020, 137+320 – 137+560, 137+980 – 138+930,140+880 – 141+140, 160+740 – 160+800. RHS – 113+600 – 113+880, 114+020 – 114+550, 114+590 – 114+770, 118+690 – 118+930, 119+000 – 120+380, 121+200 – 121+930, 122+000 – 122+090, 122+120 – 122+240, 122+280 – 122+470, 123+380 – 123+600, 126+450 – 126+640, 128+250 – 128+550, 129+440 – 129+800, 129+960 – 130+300, 132+960 – 133+300, 138+460 – 139+120, 158+400 – 158+570, 158+620 – 158+960, 159+000 – 159+300, 159+700 – 159+840, 160+610 – 160+700, 162+220 – 162+360. Since the composition of crust thickness of road has not yet been finalized. The Concessionaire has been carried out the DBM laying operations with 90mm thickness and completed between Km 13+800 to Km 15+520 LHS & Km 16+110 to Km 19+500 (LHS). The executed said work is being considered as a un concurred by I.E. until the finalization pavement crust. M/s. SAI MAATARINI TOLLWAYS LIMITED Page 71 SAI MAATARINI TOLLWAYS LIMITED Four Laning of Panikoili – Rimuli Road Section of NH215 from Km 0+000 – 163+000 (Design Length 166+173 Kms) in the state of Odisha under NHDP Phase-III as BOT (Toll) Basis. Monthly Progress Report : March - 2015 Sl. No. NCPN No I.E.'s Lr. No. 10 23 SAI/IC/03/438/ 2014 11 24 SAI/IC/03/445/ 2014 12 25 SAI/IC/03/456/ 2015 13 26 SAI/IC/03/492/ 2015 14 27 SAI/IC/03/493/ 2015 15 28 SAI/IC/03/494/ 2015 16 29 SAI/IC/03/495/ 2015 PMC Lr. No. & Date Description SMTL Lr. No. & Date Compliance Km 151+200 (Major Bridge) – The GFC drawing of Major Bridge at ch.151+200 has not been submitted to IE. But the work has been started. Km 119+020 to 119+060 (LHS) – The DBM layer has been laid whereas pavement design and mix design is yet to be finalized. Km10+673, 20+038, 23+544, 29+857, 42+133 – Without submission of retaining wall design & drawings, the work is under progress at above mentioned locations. Until the submission of said drawings, the executed work is being considered as non-concurrence by IE. VUP at Km 53+382 & 77+950 : Drawings & Design details of retaining walls at above maintained VUP locations have not yet been submitted to IE for review, but it is seen at site the aforesaid work is under progress without having any GFC certification from IE. Until submission of such required details, the executed work is being considered as a non-acceptance from IE. ECW: The BBD report along with pavement design details an ECW (Existing Carriage Way) in pursuant to IRC 81 have not been submitted IE for review. But it is seen at site all road works operations are being carried out without approval of a plan and profile and overlay design detail over existing road carriage way. Hence the executed work has been considered as non-concurrence from IE. DBM work: The compliance report as sought by IE Pavement Design Engineer for final acceptance of pavement crust composition for New Carriage Way and use of VG-40 grade Bitumen in the Project Highway have not yet been furnished to IE. It is evident at site more than 35 Km DBM has already been constructed without concurrence from IE. Km.115+118, Km.117+658, Km.122+926, Km.128+846, Km.131+412: Drawings and Designs details of retaining walls at above maintained VUP locations have not yet been submitted to IE for review, but it is seen at site the aforesaid work is under progress without having any GFC certification from IE. Until submission of such required details, the executed work is being considered as a non-acceptance from IE. 13. Correspondence INCOMING CORRESPONDENCE Sl. No. 1 Letter No. Date Subject Encl: Address To CC: SAI/IC/03/216/2014 03-Mar-14 Observation on portal type Minor Bridge Yes CGM, SMTL PD, NHAI, Keonjhar, AVP, SAI, 2 SAI/IC/03/217/2014 03-Mar-14 Observation on RCC Super Structure for Major Bridge at Ch.139+565. Yes CGM, SMTL PD, NHAI, Keonjhar, AVP, SAI, 3 SAI/IC/03/218/2014 06-Mar-14 Submission of Expenditure Statement. Nil CGM, SMTL PD, NHAI, Keonjhar, AVP, SAI, 4 SAI/IC/03/219/2014 06-Mar-14 NCPN. No-09 Ch.140+600 to Ch.140+750. Yes CGM, SMTL PD, NHAI, Keonjhar, AVP, SAI, 5 SAI/IC/03/220/2014 06-Mar-14 NCPN-IO Ch.l35+060 to 135+250 Yes CGM, SMTL PD, NHAI, Keonjhar, AVP, SAI, 6 SAI/IC/03/221/2014 08-Mar-14 Identification of Sub Grade Borrow Areas. Nil CGM, SMTL PD, NHAI, Keonjhar, AVP, SAI, 7 SAI/IC/03/222/2014 08-Mar-14 Deployment of HM plants. Nil CGM, SMTL PD, NHAI, Keonjhar, AVP, SAI, 8 SAI/IC/03/223/2014 08-Mar-14 Yes CGM, SMTL PD, NHAI, Keonjhar, AVP, SAI, 9 SAI/IC/03/224/2014 08-Mar-14 Nil CGM, SMTL PD, NHAI, Keonjhar, AVP, SAI, 10 SAI/IC/03/225/2014 08-Mar-14 Yes CGM, SMTL PD, NHAI, Keonjhar, AVP, SAI, 11 SAI/IC/03/226/2014 10-Mar-14 Major Bridge at Km.56+800 -P4 Arrangement for factory visit for verification of SHYAM and SRMB steel. Non Comformity of Executed Embankment work at Km.23+100 to 23+380 LHS Observation on Fly Over at Ch.125+281 Yes CGM, SMTL PD, NHAI, Keonjhar, AVP, SAI, 12 SAI/IC/03/227/2014 10-Mar-14 Review of Borrow Areea No.44,48,49,50 & 54. Nil CGM, SMTL PD, NHAI, Keonjhar, AVP, SAI, 13 SAI/IC/03/228/2014 10-Mar-14 Review of NCPN Closure Nil CGM, SMTL PD, NHAI, Keonjhar, AVP, SAI, 14 SAI/IC/03/229/2014 10-Mar-14 Review of Mix Designs M-15 & M-25. Nil CGM, SMTL PD, NHAI, Keonjhar, AVP, SAI, 15 SAI/IC/03/231/2014 14-Mar-14 Nil CGM, SMTL PD, NHAI, Keonjhar, AVP, SAI, 16 SAI/IC/03/232/2014 14-Mar-14 Nil CGM, SMTL PD, NHAI, Keonjhar, AVP, SAI, 17 SAI/IC/03/233/2014 19-Mar-14 Road maintainance Work. Methodology of Dynamic pile load test for intial pile at Km.151+200 - Furnished for review & acceptance. Permeability report. Nil CGM, SMTL Nil PD, NHAI, Keonjhar PD, NHAI, Keonjhar, AVP, SAI, CGM(T),RO, NHAI, Odisha, CGM, SMTL , TL, SAI, Keonjhar Nil CGM, SMTL PD, NHAI, Keonjhar, AVP, SAI, Nil CGM, SMTL PD, NHAI, Keonjhar, AVP, SAI, Nil CGM, SMTL PD, NHAI, Keonjhar, AVP, SAI, 18 SAI/IC/1084/2014 19-Mar-14 19 SAI/IC/03/234/2014 21-Mar-14 20 SAI/IC/03/235/2014 21-Mar-14 21 SAI/IC/03/236/2014 22-Mar-14 Delay in finalizing the various design issues Submission of Revised Design & Drawings for PUP, AUP, VUP & Major Bridge at Km.151+101 Structures. Submission of Compliance report and revised Plan & Profile-Review and acceptance in comformance with C.A. Obsevation on MPR submitted during month of Dec'13, Jan'14 & Feb'14 on the financial progress. M/s. SAI MAATARINI TOLLWAYS LIMITED Page 72 SAI MAATARINI TOLLWAYS LIMITED Four Laning of Panikoili – Rimuli Road Section of NH215 from Km 0+000 – 163+000 (Design Length 166+173 Kms) in the state of Odisha under NHDP Phase-III as BOT (Toll) Basis. Monthly Progress Report : March - 2015 Sl. No. Letter No. Date Subject Encl: Address To CC: Nil CGM, SMTL PD, NHAI, Keonjhar, AVP, SAI, Nil CGM, SMTL PD, NHAI, Keonjhar, AVP, SAI, Nil CGM, SMTL PD, NHAI, Keonjhar, AVP, SAI, Nil CGM, SMTL PD, NHAI, Keonjhar, AVP, SAI, Nil CGM, SMTL CGM(Tech),RO Odisha, Bhubaneswar, PD, NHAI,Keonjhar, AVP, SAI, 22 SAI/IC/03/237/2014 22-Mar-14 23 SAI/IC/03/238/2014 25-Mar-14 24 SAI/IC/03/239/2014 26-Mar-14 25 SAI/IC/03/240/2014 26-Mar-14 26 SAI/IC/03/241/2014 27-Mar-14 27 SAI/IC/03/242/2014 27-Mar-14 Change of Location certain structures during site visit of I.E. & NHAI representatives along with Concessionaire representative-Detailed furnished for concurrence. Correction of Letter No. Submission of Revised Design & Drawings for PUP, AUP, VUP & Major Bridge at Km.151+101 Structures. Targets from April 2014 to March 2015. Review of Design & Drawings by I.E. pursuant to Cl.12.3 of C.A.Abnormal delay in review of about 10 months from appointed date after submission of Design & Drawings-Determination of Extension of Time for Project Milestone & Scheduled Four lanning date pursuant to Cl.12.4.2 of C.A. and Cl.3.1(vii) & Cl.8.2 schedule-Q of C.A. Review of Borrow Area No.48 Ext., 65, 66, & 66A. Nil CGM, SMTL PD, NHAI, Keonjhar, AVP, SAI, 28 SAI/IC/03/243/2014 27-Mar-14 Review of Borrow Area No.01. Nil CGM, SMTL PD, NHAI, Keonjhar, AVP, SAI, 29 SAI/IC/03/244/2014 27-Mar-14 Review of Borrow Area No.03. Nil CGM, SMTL PD, NHAI, Keonjhar, AVP, SAI, 30 SAI/IC/03/245/2014 27-Mar-14 Review of Borrow Area No.52,57,62,73 & 75. Nil CGM, SMTL PD, NHAI, Keonjhar, AVP, SAI, 31 SAI/IC/03/246/2014 28-Mar-14 Dumping of GSB material without compacting the subgrade top. Nil CGM, SMTL PD, NHAI, Keonjhar, AVP, SAI, OUTGOING CORRESPONDENCE Sl. No. 1 2 3 4 5 Letter No. SMTL/P-R/NH-215/TSNCGM/I.E./2014-15/499 SMTL/P-R/NH-215/TSNCGM/I.E./2014-15/500 SMTL/P-R/NH-215/TSNCGM/I.E./2014-15/501 SMTL/P-R/NH-215/TSNCGM/I.E./2014-15/502 SMTL/P-R/NH-215/TSNCGM/I.E./2014-15/503 Date 04-03-2015 04-03-2015 03-03-2015 10-03-2015 10-03-2015 6 SMTL/P-R/NH-215/TSNCGM/I.E./2014-15/504 14-03-2015 7 SMTL/P-R/NH-215/TSNCGM/I.E./2014-15/505 14-03-2015 8 SMTL/P-R/NH-215/TSNCGM/I.E./2014-15/506 14-03-2015 9 SMTL/P-R/NH-215/TSNCGM/I.E./2014-15/507 14-03-2015 10 11 12 13 14 15 16 SMTL/P-R/NH-215/TSNCGM/I.E./2014-15/508 SMTL/P-R/NH-215/TSNCGM/I.E./2014-15/509 SMTL/P-R/NH-215/TSNCGM/I.E./2014-15/510 SMTL/P-R/NH-215/TSNCGM/I.E./2014-15/511 SMTL/P-R/NH-215/TSNCGM/I.E./2014-15/512 SMTL/P-R/NH-215/TSNCGM/I.E./2014-15/513 SMTL/P-R/NH-215/TSNCGM/I.E./2014-15/514 14-03-2015 14-03-2015 17-03-2015 19-03-2015 23-03-2015 23-03-2015 24-03-2015 17 SMTL/P-R/NH-215/TSNCGM/I.E./2014-15/515 25-03-2015 18 SMTL/P-R/NH-215/TSNCGM/I.E./2014-15/516 28-03-2015 19 SMTL/P-R/NH-215/TSNCGM/I.E./2014-15/517 28-03-2015 20 SMTL/P-R/NH-215/TSNCGM/I.E./2014-15/518 28-03-2015 21 SMTL/P-R/NH-215/TSNCGM/I.E./2014-15/519 28-03-2015 Subject Submission of test results for barrow areas no. 193, 199, 202, 203, 208 to 210, 213, 214, 216, 220, 222 to 225, 227 to 230 & 233 – Proposal for source Approval for minor minerals furnished by section-2, Gayatri Projects Ltd., - Review and acceptance in conformance with C.A. – Requested – Reg. Agreement copies of Stone Quarry & Crusher located at Bandho Monthly Progress Report for the month of Feb-15 pursuant to Cl.13.1 of CA Issuance of GFC drawings Submission of test results of Barrow Areas – Review & Acceptance in conformance with CA – Requested – reg. Conducting of BBD survey for the existing highway – Raw survey data along with existing subgrade soil classification and moisture content there in – furnished – Reg. Conciliation of dispute on EOT pursuant to Cl.44.2 under Article-44 (Dispute Resolution) of CA – Statement of issues included in the scope of mediation based on which claim of EOT for Project Milestone & Scheduled Four-Laning Date is sought - Submitted Furnishing of particulars for information / documents as required by Vigilance Division, NHAI, New Delhi – Reg. Submission of revised design & drawings for major Briodge at Km 56+800 along compliances – Review & Acceptance of IERequested-Reg. Source approval of Bharati Cement from M/s Vicat Sagar Pvt. Ltd., Hyderabad – Review and acceptance of IE Submission of test results of Barrow Areas – Review & Acceptance in conformance with CA – Requested – reg. Source approval for Geo-Green Blanket from Sri Venkateswara Fibre Udyog Pvt. Ltd., Bangalore – Review and acceptance of IE – Compliances-Furnished-Reg. Submission of typical drawings for miscellaneous items – Review & Acceptance of IE-Requested – Reg. Source approval for PC strands of Tata Steel – Review and acceptance of IE – Requested-Reg. Submission of test results of Barrow Areas – Review & Acceptance in conformance with CA – Requested – reg. Compliance on observations of IE on pavement design report for NCW & ECW – Furnished – Reg. Monthly return on (a) MIS, Form – I, Form – II & ROB/RUB Status and (b) Proforma – I, Proforma-II & Proforma-III as on 25th March-15-Furnsihed-Reg. Conducting of BBD survey for the Existing Highway – Survey data along with existing subgrade soil classification and moisture content-Reg. Submission of revised hydraulic report for MJB at Km 35+803 along compliances –Review & acceptance of IE – RequestedReg. Submission of revised shop drawings & design calculations for POT-cum-PTFE bearings for (i) Flyover at Km 125+281, (ii) MJB at Km 56+800, Km 83+566, Km 109+072, Km 108+062 & 139+482 Km (iii) Mnior Bridges at Km 96+105, Km98+965 & 116+160 (iv) EUP at Km 62+652 & 95+137 – Review & Acceptance – Requested – Reg. Source aaproval for Monnet Ispat & Energy Ltd. Steel TMT Bars – Review and acceptance of IE – Requested – Reg. M/s. SAI MAATARINI TOLLWAYS LIMITED Encl: Address To CC: PD, NHAI, Keonjhar Yes TL, Keonjhar Yes TL, Keonjhar Yes TL, Keonjhar No TL, Keonjhar Yes TL, Keonjhar Yes TL, Keonjhar PD, NHAI, Keonjhar Yes COO, SAI PD, NHAI, Keonjhar Yes TL, Keonjhar PD, NHAI, Keonjhar Yes TL, Keonjhar PD, NHAI, Keonjhar Yes TL, Keonjhar Yes TL, Keonjhar Yes TL, Keonjhar Yes TL, Keonjhar Yes TL, Keonjhar Yes TL, Keonjhar Yes TL, Keonjhar Yes TL, Keonjhar PD, NHAI, Keonjhar No TL, Keonjhar PD, NHAI, Keonjhar Yes TL, Keonjhar PD, NHAI, Keonjhar Yes TL, Keonjhar PD, NHAI, Keonjhar Yes TL, Keonjhar PD, NHAI, Keonjhar PD, NHAI, Keonjhar PD, NHAI, Keonjhar PD, NHAI, Keonjhar PD, NHAI, Keonjhar PD, NHAI, Keonjhar PD, NHAI, Keonjhar PD, NHAI, Keonjhar PD, NHAI, Keonjhar PD, NHAI, Keonjhar PD, NHAI, Keonjhar PD, NHAI, Keonjhar Page 73 SAI MAATARINI TOLLWAYS LIMITED Four Laning of Panikoili – Rimuli Road Section of NH215 from Km 0+000 – 163+000 (Design Length 166+173 Kms) in the state of Odisha under NHDP Phase-III as BOT (Toll) Basis. Monthly Progress Report : March - 2015 Sl. No. Letter No. Date Subject 22 SMTL/P-R/NH-215/TSNCGM/I.E./2014-15/520 28-03-2015 23 SMTL/P-R/NH-215/TSNCGM/I.E./2014-15/521 29-03-2015 24 SMTL/P-R/NH-215/TSNCGM/NHAI/2013-14/539 03-03-2015 25 SMTL/P-R/NH-215/TSNCGM/NHAI/2013-14/540 03-03-2015 26 SMTL/P-R/NH-215/TSNCGM/NHAI/2013-14/541 04-03-2015 27 28 SMTL/P-R/NH-215/TSNCGM/NHAI/2013-14/542 SMTL/P-R/NH-215/TSNCGM/NHAI/2013-14/543 23-03-2015 23-03-2015 29 SMTL/P-R/NH-215/TSNCGM/NHAI/2013-14/544 25-03-2015 30 SMTL/P-R/NH-215/TSNCGM/NHAI/2013-14/545 26-03-2015 31 SMTL/P-R/NH-215/TSNCGM/NHAI/2013-14/546 26-03-2015 32 SMTL/P-R/NH-215/TSNCGM/NHAI/2013-14/547 26-03-2015 33 34 35 SMTL/P-R/NH-215/TSNCGM/NHAI/2013-14/548 SMTL/P-R/NH-215/TSNCGM/NHAI/2013-14/549 SMTL/P-R/NH-215/TSNCGM/NHAI/2013-14/550 26-03-2015 30-03-2015 31-03-2015 Encl: Closure of NCPN No – 04 – Requested – Reg. Pavement design calculations with MR values obtained from tests along with input & output matrix with 2600 (BC) and 2900 (DBM) replacing cut off value of 2400 – Furnished – Reg. Reluctance of Sri Shaikanta Mishra to vacate the structure (Dhaba) constructed on Govt. Land at Km 78+600 (RHS) – Support from Administration to get the person vacated from the structure – Requested – Reg. Obstruction by Arsala villagers for executing the work between Km 149+000 & Km 151+000 – Stalling the work of PUP at Km 149+500 on 01-03-2015 under the pre text of non payment of compensation for Mosque – Immediate intervention to resolve the deadlock – Requested – Reg. Stalemate of execution due to existence of fisheries pond affecting a length of 0.310 Kms (between Km 116+810 & Km 117+100) on account of delay in finalization of compensation – Expeditious action – Solicited – Reg. Submission of RA Bill No-02 for Electrical Utility Shifting from Ch.0+000 to Ch.24+000 & Ch.24+000 to Ch.113+000 – Reg. Renewal of Explosive license no.5/2012 in Keonjhar District for subject project – Requested-Reg. Submission of Financial Data – Reg. CC: TL, Keonjhar PD, NHAI, Keonjhar Yes TL, Keonjhar PD, NHAI, Keonjhar No PD, NHAI, Keonjhar TL, Keonjhar No PD, NHAI, Keonjhar TL, Keonjhar No PD, NHAI, Keonjhar TL, Keonjhar Yes Yes Yes Construction of additional culverts (deposit works) pertaining to irrigation departments of Jajpur & Keonjhar district on NH215 in between Km 0+000 to Km 166+173 – Inordinate delay in finalization of scheme & GAD – Notified – Reg. Obstruction in executing Minor Bridge at Km 149+019 by Minority community in Arsala village – Resolution – Requested – Reg. Fabrication of Steel Girders for ROBs at Km 9+233 in Jajpur Bypass & Km 115+789 in Keonjhar Bypass – Methodology of Fabrication and Quality Assurance Plan – Furnished for onward submission to East Coast Railways – Reg. Lodging of FIRs in Police Stations in respect of chronic problems in site – Difficulty – Notified – Reg. Release of 2nd tranche of Grant pursuant Cl.25.2.3 of CA – Requested-Reg. Land involved in Court Cases – 16 cases on the project site in the Honbl’e High Court of Odisha – Reg. Address To Yes PD, NHAI, Keonjhar PD, NHAI, Keonjhar Manager (F&A), RO, BBSR, Odisha TL, Keonjhar TL, Keonjhar PD, NHAI, Keonjhar Yes PD, NHAI, Keonjhar TL, Keonjhar Yes PD, NHAI, Keonjhar TL, Keonjhar Yes PD, NHAI, Keonjhar TL, Keonjhar Yes Yes Yes PD, NHAI, Keonjhar PD, NHAI, Keonjhar PD, NHAI, Keonjhar TL, Keonjhar TL, Keonjhar TL, Keonjhar 14. Environmental Regulations & Clearances: APPLICABLE PERMITS (Cl. 4.1.3 (d) and Schedule-E of C.A. SEC-II (Km.0 – Km.113) Manjuri Km. 18+500 Sl No. a b Description of Permission / License Permission of the state Government for extraction of boulders from quarry Permission of Village Panchayata and Pollution Control Board for installation of WMM Plant Manjuri (Km. 19+000) Hasanpur Km. 33+000 Batching Plant Hot Mix Plant HSD Pump Stone Quarry Crusher Ostapura (Km. 42+000) NA NA NA Approved (Part payment deposited for renewal) NA NA NA Approved (Valid up to 31-12-015) M/s. SAI MAATARINI TOLLWAYS LIMITED Bandha / Arjun Bania (Km. 58+000) Stone Quarry Crusher Batching Plant HM Plant WMM Plant HSD Pump Langalakanthi (92+000) Khajirijiani (Km. 94+000) Stone Quarry Crusher Stone Quarry Crusher WMM Plant HM Plant Batching Plant HSD Pump FDP under Process To be applied for Permission Approved (25% Part payment deposited for renewal) Approved (Valid up to 31-12-015) To be applied for Permission Approved (Valid up to 31-12-015) Page 74 SAI MAATARINI TOLLWAYS LIMITED Four Laning of Panikoili – Rimuli Road Section of NH215 from Km 0+000 – 163+000 (Design Length 166+173 Kms) in the state of Odisha under NHDP Phase-III as BOT (Toll) Basis. Monthly Progress Report : March - 2015 Manjuri Km. 18+500 Sl No. Description of Permission / License WMM Plant Manjuri (Km. 19+000) Hasanpur Km. 33+000 Batching Plant Hot Mix Plant HSD Pump Ostapura (Km. 42+000) Stone Quarry Crusher Bandha / Arjun Bania (Km. 58+000) Stone Quarry Crusher Batching Plant HM Plant WMM Plant HSD Pump Langalakanthi (92+000) Khajirijiani (Km. 94+000) Stone Quarry Crusher Stone Quarry Crusher WMM Plant HM Plant Batching Plant HSD Pump Approved Approved (Renewed up to 31-03-2015) NA Not Applied NA Approved (Renewed up to 31-03-2015) crushers c d e f g h i j Approved Approved License for use of NA NA NA (Renewed up (Renewed up to explosives to 31-12-014) 31-12-014) Permission of the state Government for Approved for total stretch (Km. 00+000 to 163+000) drawing water from river / reservoir License from Inspector of factories or other Under Process (Plan competent NA In Process NA NA Approved but not Authority for applied for licence) setting up Batching Plant Clearance of Approved Pollution Control In Process Approved NA NA (Renewed up to 31Board for setting 03-2015) of Batching Plant Clearance of Village Panchayats and In Process NA Approved NA Approved Pollution Control Board for Asphalt Plant Permission of Village Panchayat and State Government for borrow earth Permission of State Government for cutting of trees Any other permits or clearance required under Applicable Laws NA In Process In Process Labour License - Done SEC-II (Km.113 – Km.163) Sl. No. DESCRIPTION A Permission of the State Government for extraction of boulders from quarry Permission of Village Panchayat B C D E State Pollution Control Board for installation of Crushers State Pollution Control Board for Crushing of Granite Stone Chips License for use of explosives Permission of the State Government for drawing water from river/reservoir License from Inspector of factories or other competent authority for setting up Batching Plant GPL @ 115 (Ramachandrapur) 1.Permission for quarry obtained through auction at Km. 115 Tulasichoura Stone Quarry -3, Tulasichoura Village of 12 Aces for long term Memo NO. 8028 dated 21.12.2013 for 3 years. Environmental Clearance is pending with /SEIAA.office Completed Order No GP/2012-13/1209 & 0703-2013 Completed Order No 943/IND-I-NOC/242 & 15-05-2012 @ 135 (Raisuan) 1.Permission for quarry obtained through auction at Km. 135 Tikarpada Stone Quarry No-1,Tikarpada Village of 12 Aces on dated 01.04.2014. To be renew by 31-03-2015 Environmental Clearance is pending with /SEIAA.office -NA-NA- Completed order no 220/APC & 05-04-2014 -NA- Completed (Tulasichoura) Order No 5/2013 & 01-01-2014 Completed (Tikarpada) Order No 14/2012 & 01-012014 -NA- -NA- Completed (Order No 595/210061200110 & 06-03-2012) -NA- M/s. SAI MAATARINI TOLLWAYS LIMITED Page 75 SAI MAATARINI TOLLWAYS LIMITED Four Laning of Panikoili – Rimuli Road Section of NH215 from Km 0+000 – 163+000 (Design Length 166+173 Kms) in the state of Odisha under NHDP Phase-III as BOT (Toll) Basis. Monthly Progress Report : March - 2015 Sl. No. F G H GPL DESCRIPTION @ 115 (Ramachandrapur) Clearance of Pollution Control Board for setting up Batching Plant Clearance of Village Panchayats and Pollution Control Board for Asphalt Plant Permission of Village Panchayat and State Government for borrow earth I Permission Government trees. of State for cutting of J Any other permits or clearances required under Applicable Laws. @ 135 (Raisuan) Completed ( Order No 347/IND-I-NOC/240 & 19-03-2012) -NA- Completed, Village Panchayat Order No 87 & 19-12-2012, Pollution Control Board Order No 347-IND-NOC/240 & 19-03-2012 -NA- Completed -NA- Completed Order No 3196/Lease on dated, Keonjhar the 24-04.2013 for DL-39, & Order No 8478/Lease on dated, Keonjhar the 2011.2013 for DL-35 (Only for Non forest & Govt land) WMM Plant Completed 15. Statement showing Road Accident cases for the month: Feb '15 Stretch / NH Sl. No. State PIU/CMU 1 Odisha Keonjhar NH No. From (Km) 215 Panikoili TOTAL Detail of Accident To (Km) Remuli Length Fatal Grievous Minor Total 0 0 0 0 2 2 2 2 163 No. of Animals Killed (If Any) Nil Nil Remarks 16. Eviction of Encroachments: Sl No Name of the Village Sadar Tahasil 1 Jamunalia 2 Tolankbahal 3 Sirispal 4 Nizgarh 5 Maligaon Gopinathpur 6 Nuagaon 7 Dhrupada 8 Raisuan 9 Gopinathpur 10 Khuntapada 11 Silisuan 12 Banajodi 13 Padmapur 14 Putulia 15 Keshpank 16 Jadichatara 17 Bankamaruni 18 Hundula 19 Jamudiha 20 Palaspanga 21 Mursuan 22 Spongepatna 23 Tangarani Sub Total Sadar Tahasil Jhumpura Tahasil 1 Bhaluka 2 Arsala Private Building Compensation Dismantle Total no of encroachments No of Balance to Dismantle Notices Issue Completed Balance Issued Notices Total Nos Paid Balance Complete Balance Total Nos 2 1 2 13 1 1 1 2 13 1 1 0 0 0 0 1 1 2 10 1 0 0 0 3 0 5 0 0 11 3 5 0 0 11 3 0 0 0 0 0 4 4 0 4 0 0 0 0 2 26 22 0 3 8 20 32 3 0 2 0 18 20 2 0 4 2 22 22 0 2 5 19 30 2 0 1 0 10 18 1 0 4 0 4 0 0 1 3 1 2 1 0 1 0 8 2 1 0 0 2 20 20 0 2 5 19 20 2 0 0 0 10 18 0 0 2 0 2 2 0 0 0 0 10 0 0 1 0 0 0 1 0 2 0 16 21 0 16 21 9 18 17 2 9 18 17 2 1 9 5 6 27 1 34 1 5 4 3 17 1 0 0 0 0 0 0 0 0 0 0 4 1 3 10 0 34 0 185 160 25 139 21 185 3 27 0 3 3 0 0 3 0 0 M/s. SAI MAATARINI TOLLWAYS LIMITED 133 52 0 0 11 Govt. Structure Total Dismantle Balance 1 1 0 1 7 4 1 1 3 6 12 0 14 18 2 3 8 9 14 17 2 0 4 0 0 1 1 7 0 1 0 2 4 12 1 86 9 37 5 Page 76 SAI MAATARINI TOLLWAYS LIMITED Four Laning of Panikoili – Rimuli Road Section of NH215 from Km 0+000 – 163+000 (Design Length 166+173 Kms) in the state of Odisha under NHDP Phase-III as BOT (Toll) Basis. Monthly Progress Report : March - 2015 Sl No 3 4 5 6 7 Name of the Village Sundhimursuan Balabhadrapur Katalposi Balibandh Mursuan Sub Total Jhumpura Tahasil Champua Tahsil 1 Sijukala 2 Parsala 3 Rimuli Sub Total Champua Tahasil Grand Total Private Building Compensation Dismantle Total no of encroachments No of Balance to Dismantle Notices Issue Completed Balance Issued Notices 2 2 11 7 3 Total Nos Paid Balance Complete Balance Total Nos 0 7 16 27 5 0 6 11 16 2 0 1 5 11 3 0 0 8 12 0 0 6 3 4 2 2 2 11 7 3 85 38 23 23 15 25 0 25 0 0 3 12 4 2 2 1 1 10 3 2 2 1 0 0 0 9 13 9 13 0 0 9 13 19 289 5 203 14 62 5 167 0 36 22 232 22 155 0 77 22 108 M/s. SAI MAATARINI TOLLWAYS LIMITED Govt. Structure Total Dismantle Balance 22 0 0 0 0 0 9 7 2 0 9 9 68 7 13 2 14 1 14 2 Page 77 SAI MAATARINI TOLLWAYS LIMITED Four Laning of Panikoili – Rimuli Road Section of NH215 from Km 0+000 – 163+000 (Design Length 166+173 Kms) in the state of Odisha under NHDP Phase-III as BOT (Toll) Basis. Monthly Progress Report : March - 2015 STAFF OF SPV & Its TEAM 17. Appendix - Concessionaire Staff S. No. 1 2 3 Name Mr. T. Suryanarayana Mr. U. Anil Kumar Mr. Gopal Mandal Designation Chief General Manager (Tech.) Sr. Planning Engineer / Quantity Surveyor Office Asst. Project Management Consultants Team Staff S. No. Name Designation 1 2 3 Mr. P. G. Kulkarni M D Rami Reddy Mr. C K S Marar Team Leader Cum Senior Highway Engineer Senior Material Engineer Senior Planner 4 V. Nageswar Rao Resident Highway Engineer - I 5 Ranjit Kumar Resident Highway Engineer - III 6 Sanjay Kumar Acharya Bridge Engineer - I 7 S. K. Singh Bridge Engineer - III 8 Mangulu Charan Panda Field Engineer (Highways) - I 9 Field Engineer (Bridges) - I 10 Laxman Rao V D. V. Suryanarayana 11 Mahaboob Subhani Field Engineer (Bridges) - II 12 Satya Ranjan Mohapatra Quality Control Engineer - I 13 Bikash Kumar Behera Quality Control Engineer - II 14 Mayadhara Behera Lab Technician - I 15 Saroj Kumar Padhi Lab Technician - I 16 Chitaranjan Pattanaik Surveyor - I 17 Shashikanta Sahoo QS – I 18 P. Venkateswar Rao QS – II 19 R. K. Nayak Office Manager Field Engineer (Highways) - II M/s. SAI MAATARINI TOLLWAYS LIMITED Page 78 SAI MAATARINI TOLLWAYS LIMITED Four Laning of Panikoili – Rimuli Road Section of NH-215 from Km 0+000 – 163+000 (Design Length 166+173 Kms) in the state of Odisha under NHDP Phase-III as BOT (Toll) Basis. Monthly Progress Report : March - 2015 11.0 Appendixes Appendix – 1 Concessionaire’s EPC Contractor’s Staff M/s. SAI MAATARINI TOLLWAYS LIMITED Page 79 SAI MAATARINI TOLLWAYS LIMITED Four Laning of Panikoili – Rimuli Road Section of NH215 from Km 0+000 – 163+000 (Design Length 166+173 Kms) in the state of Odisha under NHDP Phase-III as BOT (Toll) Basis. Monthly Progress Report : March - 2015 SEC – I KEY PERSONAL STAFF LIST SL. NO. NAME OF EMPLOYEE 1 BVU BHASKAR 2 S. Venkata Reddy 3 D.S.R. Ratnakar 4 D V V Satyanarayana 5 B Satyanarayna ADMIN & LIAISIONING 1 B. Pattanaik 2 Manoranjan Patra 3 Siba Prasad Mohapatra 4 P P K Kar 5 N Apanna Babu 6 C H Ganesh ACCOUNTS 1 P Nagendra 2 S P Mohapatra 3 S Madhusudan 4 K V V Satyanarayan PLANNING & BILLING 1 V. Sunil Kumar 2 N Satish 3 S. Mahapatra 4 G C Senapati 5 Ram Chandra Sahoo HIGHWAYS 1 G Padmanabham 2 Vijay Bhatia 3 A Bheemudu 4 G V S N Murthy 5 D Venkateswara Rao STRUCTURES 1 Mohd. Akhtar 2 Sai Prasad 3 Pradhan 4 Venkatesh QA & AC 1 B Suresh 2 Tirupati Reddy 3 B Umashankar SURVEY 1 Rakesh Kumar Sahoo 2 Tapas Kumar Behra 3 Ch S Chakrabathy 4 M Malliah 5 Chhabi Mahalik 6 Sesha Sai 7 Sisir Kumar Patra 8 Jyoti Ranjan Mahapatra STORES 1 P.RAMU 2 Ravi kiran MECHANICAL DIVISION 1 Y. Venkataramaih 2 K. Vijay Kumar 3 K. Basava Raj M/s. SAI MAATARINI TOLLWAYS LIMITED DESIGNATION REMARKS General Manager Project Manager Project Manager Project Manager (Roads) Project Manager CM (HR & Admin) PRO Dy. Manager, HR/Admin HR & IT Executive Health Visitor Health Visitor AGM (F & A) Asst. Manager Accounts Accountant Accountant Sr.PE (Planning) Sr. Project Engineer Project Engineer Planning & Billing Asst. Asst. QS DPM DPM DPM Roads Project Engineer Paving In-charge DGM Structures P.E Site Engineer Site Engineer DPM Lab Material Engineer Material Engineer Surveyor Surveyor Sr Engineer Survey Sr Surveyor Sr Surveyor Surveyor Surveyor Surveyor Manager Asst. Manager DGM (P&M) Manager, Plants Crusher In-charge Page 80 SAI MAATARINI TOLLWAYS LIMITED Four Laning of Panikoili – Rimuli Road Section of NH-215 from Km 0+000 – 163+000 (Design Length 166+173 Kms) in the state of Odisha under NHDP Phase-III as BOT (Toll) Basis. Monthly Progress Report : March - 2015 M/s. SAI MAATARINI TOLLWAYS LIMITED Page 81 SAI MAATARINI TOLLWAYS LIMITED Four Laning of Panikoili – Rimuli Road Section of NH-215 from Km 0+000 – 163+000 in the state of Odisha under NHDP Phase-III as BOT (Toll) Basis. Monthly Progress Report : March -2015 SEC – II KEY PERSONAL STAFF LIST Sl. No 1 Name of Employee Designation KV.Saikrishna Rao General Manager B.S.N.Murthy 2 PLANNING & Q.S Remarks Additional General Manager 1 Ishwari Prasad Nath Planning Engineer 2 Surajit Mohanta Planning Assistant 3 P.Siva Sankar Quantity Assistant 4 Mukut Chandra Choudhury Quantity Assistant ADMIN & STORE 1 S.Maruthakasi Senior Manager (Stores) 2 Asish Kumar Swain Manager (Liasioning) 3 M.Arunakar Reddy Manager (Liasioning) 4 Sankarsan Mohanty Admin Asst. FINANCE /ACCOUNT N.Tirupathi Rao Asst. Manager (F & A) Shibu.P Accounts Officer 1 Dinesh Chandra Seth Deputy General Manager 2 Bijay Kumar Behera Material Engineer K S Akhil Asst Material Engineer B.Krishana Rao Senior Surveyor Krishna Lal Surveyor 1 K.Ravi Kumar Construction Manager 2 Koteswar Rao DPM (Highways) Kanak Raju Sr Engineer 1 B. P. Jain Deputy General Manager 2 A. Klayana Raju Sr. DPM (Structure) 3 Kanchu Simhadri Construction Manager 4 Ganesh Singha Manager (Structure) 1 2 QA & QC 2 SURVEY 1 2 HIGHWAY 3 STRUCTURE Mitresh Kumar Gautam 5 MECHANICAL & PLANTS Bridge Engineer 1 N.Srinivasa Rao Dy. General Manager (Mechanical) 2 D.N.Raju Dy. General Manager (Plants) 3 L.Srinivasa Rao Foreman M/s. SAI MAATARINI TOLLWAYS LIMITED Page 82 SAI MAATARINI TOLLWAYS LIMITED Four Laning of Panikoili – Rimuli Road Section of NH-215 in the state of Odisha under NHDP Phase-III as BOT (Toll) Basis. Monthly Progress Report : March -2015 18. Summary of test Results QC Test Summary – Section-I (Km 0.000 to Km 40.000) Executed Quantity Sl. No A i ii iii iv v vi vii B i ii iii iv v vi vii viii ix C i ii iii iv v vi vii viii D I ii iii iv v vi vii viii E 1 i ii 2 i ii iii Name of Test Testing Method Frequency of Test OGL (Ref. MORTH Section 305 & 900) (1 sample to be collected for every 250 m on either side) Gradation/Sieve Analysis IS:2720 (Part 4) 1 test/Sample Liquid Limit & PI IS:2720 (Part 5) 1 test/Sample Max. Dry Density & OMC IS:2720 (Part 8) 1 test/Sample Moisture Content IS :2720 (Part 2) 1 test/Sample CBR IS:2720 (Part 16) If sample in SG level Free Swell Index IS:2720 (Part 40) 1 test/Sample Field Density Compaction for OGL IS:2720 (Part 28) 1 Set Test Per 1000 m2 EARTHWORK (Ref. MORTH Section 305 & 900) Gradation/Sieve Analysis IS:2720 (Part 4) 1 test/3000 m3 Liquid Limit & PI IS:2720 (Part 5) 1 test/3000 m3 Max. Dry Density & OMC IS:2720 (Part 8) 1 test/3000 m3 Moisture Content IS :2720 (Part 2) 1 test/250 m2 CBR IS:2720 (Part 16) 1 test/3000 m3 Free Swell Index IS:2720 (Part 40) 1 test/3000 m3 Sulphate Content BS:1377(tests 9/10) As & when Required Field Density Compaction for Embankment IS:2720 (Part 28) 1 Set Test Per 1000 m2 Field Density Compaction for Subgrade IS:2720 (Part 28) 1 Set Test Per 500 m2 GSB (Ref. MORTH Section 401 & 900) Gradation/Sieve Analysis IS: 2386-Part 1 1 test/200 m3 Liquid Limit & PI IS:2720 (Part 5) 1 test/200 m3 Moisture Content IS :2720 (Part 2) 1 test/250 m2 Field Density Compaction IS:2720 (Part 28) 1 test/500 m2 CBR IS:2720 (Part 16) 1 test/ source and as when required Max. Dry Density & OMC IS:2720 (Part 8) Initially one, as and when required by the Engineer Water Absorption IS:2386 (Part 3) 1 test/ source and as when required 10% Fines Value BS:812(Part111) Initially one, as and when required by the Engineer WMM (Ref. MORTH Section 406 & 900) Aggregate Impact Value IS:2386 (Part 4) 1 test/500 m3 IS:2720 (Part 4) & Gradation/Sieve Analysis 1 test/200 m3 of aggregate IS: 2786-Part 1 Combined Flakiness Index & Elongation Index IS:2386 (Part 1) 1 test/500 m3 Atterberg Limits (Passing 0.425 mm) IS:2720 (Part 5) 1 test/200 m3 Field Density Compaction IS:2720 (Part 28) 1 test/500 m2 Max. Dry Density & OMC IS:2720 (Part 8) Initially one, as and when required by the Engineer Abrasion value IS:2386 (Part 4) Initially one, as and when required by the Engineer Water Absorption IS:2386 (Part 3) Initially one, as and when required by the Engineer BITUMINOUS COURSES PRIME COAT / TACK COAT (Ref. MORTH Section 502, 503 & 900) Quality of binder IS: 73, 217& 8887 1 test/lot One test per 500sq.m and not less than two tests per Rate of spread of Binder day DBM / BC (Ref. MORTH Section 507, 509 & 900) Quality of binder IS: 73 1 test/lot IS:2386 Part 4 & Aggregate Impact Value / Los Angles Abrasion Value One test per 350 cum. of aggregate IS: 2386-Part 3 Flakiness Index & Elongation Index IS:2386 Part 1 One test per 350 cum. of aggregate M/s. SAI MAATARINI TOLLWAYS LIMITED Upto Previous Month Present Month Cumulative m2 m2 m2 1114807 54919 1169726 m3 m3 m3 2079000 246000 2325000 4769408 1065157 490389 178135 5259797 1243292 m3 45,733.2 m3 9,791.2 m3 55,524.4 228,671 48,956 277,627 m3 m3 m3 Number of Tests Conducted In This Month Previous Month Total to Date Passed Failed Total Passed Failed Total Passed Failed Total 496 491 496 3245 19 537 3146 0 0 0 24 6 8 24 496 491 496 3269 25 545 3170 5 5 5 268 5 5 223 0 0 0 0 0 0 0 5 5 5 268 5 5 223 501 496 501 3513 24 542 3369 0 0 0 24 6 8 24 501 496 501 3537 30 550 3393 1285 1285 1285 21946 238 1285 4 15412 5028 0 0 0 240 10 0 0 262 70 1285 1285 1285 22186 248 1285 4 15674 5098 82 82 82 3748 30 82 0 1947 1445 0 0 0 0 0 0 0 33 12 82 82 82 3748 30 82 0 1980 1457 1367 1367 1367 25694 268 1367 4 17359 6473 0 0 0 240 10 0 0 295 82 1367 1367 1367 25934 278 1367 4 17654 6555 255 250 995 944 3 2 1 2 1 0 9 15 0 0 0 0 256 250 1004 959 3 2 1 2 52 52 201 194 0 0 0 0 0 0 0 6 0 0 0 0 52 52 201 200 0 0 0 0 307 302 1196 1138 3 2 1 2 1 0 9 21 0 0 0 0 308 302 1205 1159 3 2 1 2 220 0 220 23 0 23 243 0 243 366 0 366 29 0 29 395 0 395 220 339 1483 2 1 1 0 0 0 0 0 0 220 339 1483 2 1 1 23 29 209 0 0 0 0 0 0 0 0 0 23 29 209 0 0 0 243 368 1692 2 1 1 0 0 0 0 0 0 243 368 1692 2 1 1 36029.2 5115.5 41144.7 288235 40924 329159 m2 m2 m2 9 0 9 1 0 1 10 0 10 259776 44722 304498 581 0 581 99 0 99 680 0 680 m3 m3 m3 11020 2106.9 13126.9 95 0 95 17 0 17 112 0 112 204 0 204 20 0 20 224 0 224 204 0 204 20 0 20 224 0 224 Page 83 SAI MAATARINI TOLLWAYS LIMITED Four Laning of Panikoili – Rimuli Road Section of NH-215 in the state of Odisha under NHDP Phase-III as BOT (Toll) Basis. Monthly Progress Report : March -2015 [ Executed Quantity Sl. No Name of Test Testing Method iv Specific Gravity & Water absorption of aggregate IS:2386 Part 3 v Soundness (Magnesium and sodium sulphate) IS:2386 Part 5 vi vii Sand equivalent test for fine aggregate Stone Polish Test viii Mix grading ix Stability of mix x Water sensitivity of mix (Retained tensile strength) xi Control of temperature of binder in boiler, aggregate in the dryer and mix at the time of laying and rolling. xii Control of binder content and grading of the mix. xiii Rate of spread of mixed material xiv xv F 1 i ii iii iv v vi vii viii Density of compacted layer Coating and stripping of bitumen aggregate mixtures MATERIAL FOR STRUCTURES COARSE AGGREGATE (MORTH 1007) Moisture Content Specific Gravity Gradation/Sieve Analysis Aggregate Impact Value/Los Angles Abrasion Value Flakiness Index Water absorption of Aggregate Soundness (Magnesium and sodium sulphate) Alkali-Aggregate reactivity ix Petrographic Analysis x xi 2 i ii iii iv v vi vii viii ix Chloride & Sulphate Deleterious Material FINE AGGREGATE (MORTH 1008) Silt Content Moisture Content Clay Lumps Specific Gravity Gradation/Sieve Analysis, Fineness Modulus Water absorption of Aggregate Chloride & Sulphate Deleterious Material Soundness (Magnesium and Sodium Sulphate) IS:2720 Part 37 (BS 812 Part – 114) IS:2720 (Part 4) Asphalt Institute Manual MS-2 AASHTO T 283 Frequency of Test Upto Previous Month Present Month Cumulative Initially one test of 3 representative specimens for each source of supply. Subsequently when warranted by changes in the quality of aggregates. Initially, one determination by each method for each source of supply, then as warranted by change in the quality of the aggregates. Initially one, as and when required by the Engineer Initially one, as required, for Bituminous Concrete. One set of tests on individual constituents and mixed aggregate from the drier for each 400 tones of mix subject to a minimum of two tests per plant per day. For each 400 tones of mix produced, a set of 3 Marshall specimens to be prepared and tested for stability, flow value, density and void content subject to a minimum of two sets being tested per plant per day. Initially one test of 3 representative specimens for each source of supply. Subsequently when warranted by changes in the quality of aggregates (if required) At regular close interval Asphalt Institute Manual MS-2 IS:6241 IS:383,IS:2386 P-III IS:383, IS:2386 - Part III IS:383,IS:2386 – Part 1 IS:383, IS:2386 Part IV IS:383,IS:2386 P-1 IS383,IS:2386 P-III IS:383,IS:2386 -V IS:383,IS:2386 P-VII IS:383, ASTM 295, IS:2386 Part VIII IS:383,IS:SP-23 IS:383, IS:2386 P-II IS:383,IS2386 Part II (IS:383,IS:2386) (IS:383, IS:2386 Part II) (IS:383,IS:2386P-III) (IS:383,IS:2386 – Part III) IS:383,IS:2386 P-III (IS:383,IS:SP -23) (IS383,IS:2386 Part II) IS:383,IS:2386 P-V M/s. SAI MAATARINI TOLLWAYS LIMITED One test for each 400 tones of mix subject to a minimum of two tests per day per plant. Regular control through checks on the weight of mixed material and layer thickness 1 test / 700 sq.m area Initially one, as and when required by the Engineer Number of Tests Conducted In This Month Previous Month Total to Date Passed Failed Total Passed Failed Total Passed Failed Total 3 0 3 0 0 0 3 0 3 4 0 4 0 0 0 4 0 4 4 0 0 0 4 0 0 0 0 0 0 0 4 0 0 0 4 0 234 0 234 20 0 20 254 0 254 149 0 149 20 0 20 169 0 169 4 0 4 0 0 0 4 0 4 874 0 874 170 0 170 1044 0 1044 99 0 99 20 0 20 119 0 119 0 0 0 0 0 0 0 0 0 126720 24878 151598 438 3 0 0 438 3 35 0 0 0 35 0 473 3 0 0 473 3 m3 m3 m3 26422.2 3625.5 30047.7 350 20 370 165 146 20 4 4 0 0 0 0 0 0 0 0 350 20 370 165 146 20 4 4 24 1 24 5 4 1 0 0 0 0 0 0 0 0 0 0 24 1 24 5 4 1 0 0 374 21 394 170 150 21 4 4 0 0 0 0 0 0 0 0 374 21 394 170 150 21 4 4 One per source 4 0 4 0 0 0 4 0 4 One per source One per source 4 4 0 0 4 4 0 0 0 0 0 0 4 4 0 0 4 4 358 350 0 20 358 20 1 1 1 0 0 0 0 0 0 0 0 0 358 350 0 20 358 20 1 1 1 24 24 0 1 24 1 0 0 0 0 0 0 0 0 0 0 0 0 24 24 0 1 24 1 0 0 0 382 374 0 21 382 21 1 1 1 0 0 0 0 0 0 0 0 0 382 374 0 21 382 21 1 1 1 Daily/at every day of concreting One per source & there after every month. one test per day One per source & there after once in a week. One per source & there after once in a week . One per source & there after every month. One per source One per source Daily Daily/at every day of concreting At every day of concreting One per source & there after every month. Daily One per source & there after every month. One per source One per source One per source m3 m3 m3 26422.2 3625.5 30047.7 Page 84 SAI MAATARINI TOLLWAYS LIMITED Four Laning of Panikoili – Rimuli Road Section of NH-215 in the state of Odisha under NHDP Phase-III as BOT (Toll) Basis. Monthly Progress Report : March -2015 [ Executed Quantity Sl. No Name of Test Testing Method 3 i ii iii iv 43 GRADE ORDINARY PORTLAND CEMENT (Ref. IS: 8112 & MoRTH 1006) Initial Setting Time Final Setting Time (IS:4031) Soundness by Le-Chatlier’s method (%) Fineness by dry sieve method 90micron v Compressive strength vi vii viii ix x xi xii xiii xiv 4 i ii iii iv v vi vii viii ix x xi xii xiii xiv 5 i ii iii iv v vi vii viii ix 6 i ii iii iv Chemical Tests Loss on Ignition Insoluble residue Alumina Iron Oxide ratio Lime Saturation factor Magnesia Sulphuric anhydride Alkalies Chlorides WATER (MORTH 1010) Volume of 0.02N NaOH required to neutralize 100 ml sample of water using phenolphthalein as an indicator Volume of 0.02N H2SO4 required to neutralize 100 ml sample of water using methyl orange as an indicator Solids Organic Inorganic Sulphates (SO4) Chlorides (CI) Suspended matter pH ADMIXTURE (MORTH 1012) Chloride Content Dry Material content Ash content Relative density Upto Previous Month Present Month Cumulative Bags Bags Bags 48473 10930 59403 Bags Bags Bags 159667 18680 178347 One test per week no. and once per source 3rd party testing MTC for each supply and one per source 3rd party testing One test per week and once per source 3rd party testing IS 516 (IS:8112) MTC for each supply and one per source 3rd party testing (IS:3025) (IS:3025) (IS:456,IS:3025) (IS:9103, IS:6925) (IS:9103) (IS:9103) (IS:9103) M/s. SAI MAATARINI TOLLWAYS LIMITED (As per IRC SP 84,8.6ii) Water from each source shall be tested before start of work and there afterevery 3 months and after every monsoon till the completion of work. Once per source and as when required Once per source and as when required Once per source and as when required Once per source and as when required Number of Tests Conducted In This Month Previous Month IS 516 Chemical Tests Loss on Ignition Insoluble residue Alumina Iron Oxide ratio Lime Saturation factor (IS:4032) Magnesia Sulphuric anhydride Alkalies Chlorides 53 GRADE ORDINARY PORTLAND CEMENT (Ref. IS: 12269, MoRTH 1006) Initial Setting Time Final Setting Time (IS:4031) Soundness (by Le-Chatlier’s method) by Autoclave (%) Fineness by dry sieve method 90micron Compressive strength Frequency of Test MT MT MT 93.4 24.75 118.15 Total to Date Passed Failed Total Passed Failed Total Passed Failed Total 6 6 6 6 18 18 18 7 7 7 7 7 7 7 7 7 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 6 6 6 6 18 18 18 7 7 7 7 7 7 7 7 7 1 1 1 1 3 0 0 1 1 1 1 1 1 1 1 1 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 1 1 1 1 3 0 0 1 1 1 1 1 1 1 1 1 7 7 7 7 21 18 18 8 8 8 8 8 8 8 8 8 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 7 7 7 7 21 18 18 8 8 8 8 8 8 8 8 8 22 22 15 22 66 66 63 24 24 24 24 24 24 24 24 24 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 22 22 15 22 66 66 63 24 24 24 24 24 24 24 24 24 2 2 2 2 6 6 3 2 2 2 2 2 2 2 2 2 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 2 2 2 2 6 6 3 2 2 2 2 2 2 2 2 2 24 24 17 24 72 72 66 26 26 26 26 26 26 26 26 26 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 24 24 17 24 72 72 66 26 26 26 26 26 26 26 26 26 10 0 10 0 0 0 10 0 10 10 0 10 0 0 0 10 0 10 10 10 10 10 10 10 10 0 0 0 0 0 0 0 10 10 10 10 10 10 10 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 10 10 10 10 10 10 10 0 0 0 0 0 0 0 10 10 10 10 10 10 10 3 3 3 3 0 0 0 0 3 3 3 3 0 0 0 0 0 0 0 0 0 0 0 0 3 3 3 3 0 0 0 0 3 3 3 3 Page 85 SAI MAATARINI TOLLWAYS LIMITED Four Laning of Panikoili – Rimuli Road Section of NH-215 in the state of Odisha under NHDP Phase-III as BOT (Toll) Basis. Monthly Progress Report : March -2015 [ Executed Quantity Sl. No Name of Test Testing Method 7 CONCRETE (MORTH 1716.2.5) i Sample of cube (A sample means a set of 3 cubes) ii Workability (Slump) iii Cube Strength of Concrete (IS:10262,IS:456, IRC:21) IS : 516 COMPRESSIVE STRENGTH (MIX DESIGN CUBES) No. Of Cubes a Frequency of Test : 1/Design Mix (or) 1/Change of Source COMPRESSIVE STRENGTH (SITE CUBES) No. Of Cubes b Frequency of Test : MORTH Sec.1700 Table:1700-8 IS 516 IS 516 IS 516 IS 516 IS 516 IS 516 IS 516 IS 516 IS 516 IS 516 IS 516 IS 516 IS 516 IS 516 IS 516 IS 516 IS 516 IS 516 IS 516 IS 516 IS 516 IS 516 IS 516 IS 516 IS 516 IS 516 IS 516 IS 516 10 i ii iii iv 11 i NP4 HUME PIPES Cube Strength of Concrete Dimensions, Workmanship & Finish Hydrostatic test pressure Three edge Bearing test STEEL MTC ii SAMPLING IS 1786 CHEMICAL UTS YIELD STRESS ELONGATION BEND TEST REBEND TEST UNIT WEIGHT IS 1786 IS 1786 IS 1786 IS 1786 IS 1786 IS 1786 IS 1786 iii iv v vi vii viii ix IS :516 IS : 458 -2003 IS : 458 -2003, IS:3597 IS : 458 -2003, IS:3597 M/s. SAI MAATARINI TOLLWAYS LIMITED Frequency of Test Every concrete spread over entire period of concreting Every batch of concrete at dispatch as well as delivery point As per requirement M15 7days M15 28 days M20 7days M20 28 days M25 7days M25 28 days M30 7days M30 28 days M35 7days M35 28 days M40 7days M40 28 days M20Kerb 7days M20Kerb 28 days M15 7days M15 28 days M20 7days M20 28 days M25 7days M25 28 days M30 7days M30 28 days M35 7days M35 28 days M40 7days M40 28 days M20Kerb 7days M20Kerb 28 days Upto Previous Month m3 Present Month m3 Cumulative Total to Date Passed Failed Total Passed Failed Total Passed Failed Total 3869 0 3869 797 0 797 4666 0 4666 10174 0 10174 1274 0 1274 11448 0 11448 39 66 33 66 21 42 45 93 21 42 21 36 12 24 753 1263 261 255 51 42 2040 5241 90 282 33 48 231 456 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 39 66 33 66 21 42 45 93 21 42 21 36 12 24 753 1263 261 255 51 42 2040 5241 90 282 33 48 231 456 0 0 0 0 0 0 0 0 0 0 0 0 0 0 75 204 39 57 12 72 399 1416 9 18 0 6 30 54 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 75 204 39 57 12 72 399 1416 9 18 0 6 30 54 39 66 33 66 21 42 45 93 21 42 21 36 12 24 828 1467 300 312 63 114 2439 6657 99 300 33 54 261 510 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 39 66 33 66 21 42 45 93 21 42 21 36 12 24 828 1467 300 312 63 114 2439 6657 99 300 33 54 261 510 3 3 3 3 0 0 0 0 3 3 3 3 0 0 0 0 0 0 0 0 0 0 0 0 3 3 3 3 0 0 0 0 3 3 3 3 m3 2419.6 277.5 2697.1 478.7 34.5 513.2 417.8 369.5 787.3 20620.1 2719 23339.1 1501.5 99.0 1600.5 55.5 4.0 59.5 929 122 1051.0 As per requirement As per requirement 2% of the pipes As per requirement Each Delivery FOR BELOW 100 TONS UNDER 10-MM - 1/25TON; 10-MM TO 16 MM - 1/35TON; OVER 16-MM 1/45TON Number of Tests Conducted In This Month Previous Month MT MT MT 111 0 111 7 0 7 118 0 118 2218.46 112.58 2331.04 120 0 120 9 0 9 129 0 129 40 40 40 40 40 40 120 0 0 0 0 0 0 0 40 40 40 40 40 40 120 3 3 3 3 3 3 9 0 0 0 0 0 0 0 3 3 3 3 3 3 9 43 43 43 43 43 43 129 0 0 0 0 0 0 0 43 43 43 43 43 43 129 Page 86 SAI MAATARINI TOLLWAYS LIMITED Four Laning of Panikoili – Rimuli Road Section of NH-215 in the state of Odisha under NHDP Phase-III as BOT (Toll) Basis. Monthly Progress Report : March -2015 [ Executed Quantity Sl. No x Name of Test DIAMETER Testing Method IS 1786 Frequency of Test Upto Previous Month Present Month Number of Tests Conducted In This Month Previous Month Cumulative Total to Date Passed Failed Total Passed Failed Total Passed Failed Total 120 0 120 9 0 9 129 0 129 Each Consignment QC Test Summary – Section-I (Km 40.000 to Km 80.000) Executed Quantity Sl. No Name of Test Testing Method A i ii iii iv v vi vii B i ii iii iv v vi vii viii ix C i ii iii iv v OGL (Ref. MORTH Section 305 & 900) (1 sample to be collected for every 250 m on either side) Gradation/Sieve Analysis IS:2720 (Part 4) Liquid Limit & PI IS:2720 (Part 5) Max. Dry Density & OMC IS:2720 (Part 8) Moisture Content IS :2720 (Part 2) CBR IS:2720 (Part 16) Free Swell Index IS:2720 (Part 40) Field Density Compaction for OGL IS:2720 (Part 28) EARTHWORK (Ref. MORTH Section 305 & 900) Gradation/Sieve Analysis IS:2720 (Part 4) Liquid Limit & PI IS:2720 (Part 5) Max. Dry Density & OMC IS:2720 (Part 8) Moisture Content IS :2720 (Part 2) CBR IS:2720 (Part 16) Free Swell Index IS:2720 (Part 40) Sulphate Content BS:1377(tests 9/10) Field Density Compaction for Embankment IS:2720 (Part 28) Field Density Compaction for Subgrade IS:2720 (Part 28) GSB (Ref. MORTH Section 401 & 900) Gradation/Sieve Analysis IS: 2386-Part 1 Liquid Limit & PI IS:2720 (Part 5) Moisture Content IS :2720 (Part 2) Field Density Compaction IS:2720 (Part 28) CBR IS:2720 (Part 16) vi Max. Dry Density & OMC IS:2720 (Part 8) vii Water Absorption IS:2386 (Part 3) viii 10% Fines Value BS:812(Part111) D I WMM (Ref. MORTH Section 406 & 900) Aggregate Impact Value ii Gradation/Sieve Analysis iii iv v Combined Flakiness Index & Elongation Index Atterberg Limits (Passing 0.425 mm) Field Density Compaction vi Max. Dry Density & OMC IS:2720 (Part 8) vii Abrasion value IS:2386 (Part 4) viii Water Absorption IS:2386 (Part 3) E 1 IS:2386 (Part 4) IS:2720 (Part 4) & IS: 2786-Part 1 IS:2386 (Part 1) IS:2720 (Part 5) IS:2720 (Part 28) Frequency of Test Upto Previous Month Present Month Number of Tests Conducted In This Month Previous Month Cumulative Total to Date Passed Failed Total Passed Failed Total Passed Failed Total 123 123 123 31 0 127 777 0 0 0 0 0 0 0 123 123 123 31 0 127 777 0 0 0 0 0 0 82 0 0 0 0 0 0 0 0 0 0 0 0 0 82 123 123 123 31 0 127 859 0 0 0 0 0 0 0 123 123 123 31 0 127 859 299 299 299 164 77 299 0 8404 2286 0 0 0 0 0 0 0 0 0 299 299 299 164 77 299 0 8404 2286 22 22 22 176 18 22 0 548 428 0 0 0 0 0 0 0 12 9 22 22 22 0 0 22 0 560 437 321 321 321 340 95 321 0 8952 2714 0 0 0 0 0 0 0 12 9 321 321 321 340 95 321 0 8964 2723 116 111 427 433 6 0 0 0 0 0 116 111 427 433 6 31 31 25 112 0 0 0 0 3 0 0 0 25 115 0 147 142 452 545 6 0 0 0 3 0 147 142 452 548 6 6 0 6 0 0 0 6 0 6 6 0 6 0 0 0 6 0 6 6 0 6 0 0 0 6 0 6 1 test/500 m3 80 0 80 28 0 28 108 0 108 1 test/200 m3 of aggregate 249 0 249 126 0 126 375 0 375 80 127 436 0 0 0 80 127 436 28 38 118 0 0 0 28 38 118 108 165 554 0 0 0 108 165 554 6 0 6 0 0 0 6 0 6 1 0 1 0 0 0 1 0 1 8 0 8 0 0 0 8 0 8 1 test/Sample 1 test/Sample 1 test/Sample 1 test/Sample If sample in SG level 1 test/Sample 1 Set Test Per 1000 m2 1 test/3000 m3 1 test/3000 m3 1test/3000 m3 1 test/250 m2 1 test/3000 m3 1 test/3000 m3 As & when Required 1 Set Test Per 1000 m2 1 Set Test Per 500 m2 1 test/200 m3 1 test/200 m3 1 test/250 m3 1 test/500 m2 1 test/ source and as when required Initially one, as and when required by the Engineer 1 test/ source and as when required Initially one, as and when required by the Engineer 1 test/500 m3 1 test/200 m3 1 test/500 m2 Initially one, as and when required by the Engineer Initially one, as and when required by the Engineer Initially one, as and when required by the Engineer 305397 72780 378177 568500 66000 634500 379000 231000 568500 44000 54000 66000 423000 285000 634500 1986282 358356 540705 206605 19,653.0 6,200 25,853 50,965 149,230 98,265.0 18781 99176 7104 55504 2526987 564961 25885 154680 BITUMINOUS COURSES PRIME COAT / TACK COAT (Ref. MORTH Section 502, 503 & 900) M/s. SAI MAATARINI TOLLWAYS LIMITED Page 87 SAI MAATARINI TOLLWAYS LIMITED Four Laning of Panikoili – Rimuli Road Section of NH-215 in the state of Odisha under NHDP Phase-III as BOT (Toll) Basis. Monthly Progress Report : March -2015 [ Executed Quantity Sl. No Name of Test Testing Method i ii iii Quality of binder Temperature of Binder for application (TACK COAT) iv Rate of spread of Binder(prime coat) 2 i DBM / BC (Ref. MORTH Section 507, 509 & 900) Quality of binder ii Aggregate Impact Value / Los Angles Abrasion Value iii Flakiness Index & Elongation Index iv Stripping value v Water absorption of aggregate IS:2386 Part 3 vi Soundness (Magnesium and sodium sulphate) IS:2386 Part 5 vii Sand equivalent test for fine aggregate IS:2720 Part 37 viii Plasticity Index ix Stone Polish Test x Percentage of fractured faces xi Mix grading IS:2720 (Part 4) xii Stability of mix Asphalt Institute Manual MS-2 xiii Water sensitivity of mix (Retained tensile strength) xiv Control of temperature of binder in boiler, aggregate in the dryer and mix at the time of laying and rolling. xv Control of binder content and grading of the mix. xvi Rate of spread of mixed material xvii Density of compacted layer xviii Coating and stripping of bitumen aggregate mixtures F 1 i MATERIAL FOR STRUCTURES COARSE AGGREGATE (MoRTH 1007) Moisture Content ii Specific Gravity IS: 73, 217& 8887 Frequency of Test IS:6241 (IS:2720 Part 5 (BS 812 Part – 114) AASHTO T 283 Present Month Cumulative 63140 IS:6241 IS:383,IS:2386 P-III IS:383, IS:2386 - Part III M/s. SAI MAATARINI TOLLWAYS LIMITED Total to Date Passed Failed Total Passed Failed Total Passed Failed Total 0 0 110 0 0 0 0 0 110 0 0 47 0 0 0 0 0 47 0 0 157 0 0 0 0 0 157 140 0 140 55 0 55 195 0 195 46244 16896 66500 24904 91404 26 0 26 0 0 0 26 0 26 One test per 350 cum. of aggregate 3282 1677 4959 21 0 21 6 0 6 27 0 27 One test per 350 cum. of aggregate Initially one test of 3 representative specimens for each source of supply. Subsequently when warranted by changes in the quality of aggregates. Initially one test of 3 representative specimens for each source of supply. Subsequently when warranted by changes in the quality of aggregates. Initially, one determination by each method for each source of supply, then as warranted by change in the quality of the aggregates. Initially one, as and when required by the Engineer Initially one, as and when required by the Engineer Initially one, as required, for Bituminous Concrete. When gravel is used, one test per 50 cum of aggregate. One set of tests on individual constituents and mixed aggregate from the drier for each 400 tones of mix subject to a minimum of two tests per plant per day. For each 400 tones of mix produced, a set of 3 Marshall specimens to be prepared and tested for stability, flow value, density and void content subject to a minimum of two sets being tested per plant per day. Initially one test of 3 representative specimens for each source of supply. Subsequently when warranted by changes in the quality of aggregates (if required) 3282 1677 4959 21 0 21 6 0 6 27 0 27 2 0 2 5 0 5 7 0 7 8 0 8 4 0 4 12 0 12 2 0 2 0 0 0 2 0 2 3 0 3 0 0 0 3 0 3 0 0 0 0 0 0 0 0 0 3 0 3 0 0 0 3 0 3 0 0 0 0 0 0 0 0 0 1 test/lot 7876 4042 11918 30 0 30 12 0 12 42 0 42 7876 4042 11918 38 0 38 12 0 12 50 0 50 2 0 2 0 0 0 2 0 2 At regular close interval Asphalt Institute Manual MS-2 Number of Tests Conducted In This Month Previous Month 1 test/lot At regular close interval One test per 500sq.m and not less than two tests per day IS: 73 IS:2386 Part 4 & IS: 2386-Part 3 IS:2386 Part 1 Upto Previous Month One test for each 400 tones of mix subject to a minimum of two tests per day per plant. Regular control through checks on the weight of mixed material and layer thickness 1 test / 700 sq.m area Initially one, as and when required by the Engineer 7876 4042 11918 23848 24464 48312 Daily/at every day of concreting One per source & there after every month. 14947 Ton 7971 Ton 14947 Ton 0 0 0 0 0 0 0 0 0 30 0 30 12 0 12 42 0 42 74 0 74 50 0 50 124 0 124 34 0 34 37 0 37 71 0 71 3 0 3 2 0 2 5 0 5 177 0 177 25 0 25 202 0 202 5 0 5 0 0 0 5 0 5 Page 88 SAI MAATARINI TOLLWAYS LIMITED Four Laning of Panikoili – Rimuli Road Section of NH-215 in the state of Odisha under NHDP Phase-III as BOT (Toll) Basis. Monthly Progress Report : March -2015 [ Executed Quantity Sl. No Name of Test iii Gradation/Sieve Analysis iv Aggregate Impact Value/Los Angles Abrasion Value v vi vii viii Flakiness Index Water absorption of Aggregate Soundness (Magnesium and sodium sulphate) Alkali-Aggregate reactivity ix Petrographic Analysis x xi 2 i ii Chloride & Sulphate Deleterious Material FINE AGGREGATE (MORTH 1008) Silt Content Moisture Content iii Clay Lumps iv Specific Gravity v Gradation/Sieve Analysis, Fineness Modulus vi vii Water absorption of Aggregate Chloride & Sulphate viii Deleterious Material ix 3 i ii iii iv v Soundness (Magnesium and Sodium Sulphate) 43 GRADE ORDINARY PORTLAND CEMENT (Ref. IS: 8112 & MoRTH 1006) Initial Setting Time Final Setting Time Soundness by Le-Chatlier’s method (%) Fineness by dry sieve method 90micron Compressive strength 3 Days 7 Days 28 Days Chemical Tests Loss on Ignition Insoluble residue Alumina Iron Oxide ratio Lime Saturation factor Magnesia Sulphuric anhydride Alkalies Chlorides 53 GRADE ORDINARY PORTLAND CEMENT (Ref. IS: 12269, MoRTH 1006) Initial Setting Time Final Setting Time Soundness (by Le-Chatlier’s method) by Autoclave (%) Fineness (by Blaine’s air permeability method) Compressive strength 3 Days 7 Days vi vii viii ix x xi xii xiii xiv 4 i ii iii iv v Testing Method IS:383,IS:2386 – Part 1 IS:383, IS:2386 Part IV IS:383,IS:2386 P-1 IS383,IS:2386 P-III IS:383,IS:2386 -V IS:383,IS:2386 P-VII IS:383, ASTM 295, IS:2386 Part VIII IS:383,IS:SP-23 IS:383, IS:2386 P-II IS:383,IS2386 Part II (IS:383,IS:2386) (IS:383, IS:2386 Part II) (IS:383,IS:2386P-III) (IS:383,IS:2386 – Part III) IS:383,IS:2386 P-III (IS:383,IS:SP -23) (IS383,IS:2386 Part II) IS:383,IS:2386 P-V Frequency of Test Upto Previous Month Present Month Cumulative Total to Date Passed Failed Total Passed Failed Total Passed Failed Total one test per day 177 0 177 25 0 25 202 0 202 One per source & there after once in a week. 32 0 32 4 0 4 36 0 36 One per source & there after once in a week . One per source & there after every month. One per source One per source 32 4 0 0 0 0 0 0 32 4 0 0 4 0 0 0 0 0 0 0 4 0 0 0 36 4 0 0 0 0 0 0 36 4 0 0 One per source 0 0 0 0 0 0 0 0 0 One per source One per source 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 177 177 0 0 177 177 25 25 0 0 25 25 202 202 0 0 202 202 At every day of concreting 0 0 0 0 0 0 0 0 0 One per source & there after every month. 4 0 4 0 0 0 4 0 4 177 0 177 25 0 25 202 0 202 One per source & there after every month. One per source 1 0 0 0 1 0 0 0 0 0 0 0 1 0 0 0 1 0 One per source 0 0 0 0 0 0 0 0 0 One per source 0 0 0 0 0 0 0 0 0 6 6 0 6 0 18 18 15 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 6 6 0 6 0 18 18 15 0 0 0 0 0 0 0 0 0 1 1 0 1 0 3 6 3 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 1 1 0 1 0 3 6 3 0 0 0 0 0 0 0 0 0 6 7 0 7 0 21 24 18 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 7 7 0 7 0 21 24 18 0 0 0 0 0 0 0 0 0 7 7 0 7 0 0 0 0 7 7 0 7 2 2 0 2 0 0 0 0 2 2 0 2 9 9 0 9 0 0 0 0 9 9 0 9 9 9 0 0 9 9 6 6 0 0 Daily Daily/at every day of concreting Daily 9075.59Ton 3777 Ton 9075.59 Ton (IS:4031) One test per week and once per source 3rd party testing IS 516 36695 (IS:4032) MTC for each supply and one per source 3rd party testing (IS:4031) One test per week and once per source 3rd party testing IS 516 One test per week and once per source 3rd party testing M/s. SAI MAATARINI TOLLWAYS LIMITED Number of Tests Conducted In This Month Previous Month 141480 23080 29450 59775 170930 6 6 15 15 0 0 15 15 Page 89 SAI MAATARINI TOLLWAYS LIMITED Four Laning of Panikoili – Rimuli Road Section of NH-215 in the state of Odisha under NHDP Phase-III as BOT (Toll) Basis. Monthly Progress Report : March -2015 [ Executed Quantity Sl. No vi vii viii ix x xi xii xiii xiv 5 i ii iii iv v vi vii viii ix 6 i ii iii iv 7 i Name of Test 28 Days Chemical Tests Loss on Ignition Insoluble residue Alumina Iron Oxide ratio Lime Saturation factor Magnesia Sulphuric anhydride Alkalies Chlorides WATER (MORTH 1010) Volume of 0.02N NaOH required to neutralize 100 ml sample of water using phenolphthalein as an indicator Volume of 0.02N H2SO4 required to neutralize 100 ml sample of water using methyl orange as an indicator Solids Organic Inorganic Sulphates (SO4) Chlorides (CI) Suspended matter pH ADMIXTURE (MORTH 1012) Chloride Content Dry Material content Ash content Relative density CONCRETE (MORTH 1716.2.5) Testing Method (IS:8112) ii Workability (Slump) Cube Strength of Concrete M-15(7 days) M-15 28 Days M-20(7 days) M-20 28 Days M-20 Kerb(7 days) M-20 Kerb 28 Days M-25(7 days) M-25 28 Days M-30(7 days) M-30 28 Days M-35(7 days) M-35 28 Days M-40(7 days) M-40 28 Days Upto Previous Month Present Month Cumulative MTC for each supply and one per source 3rd party testing (IS:3025) (IS:456,IS:3025) (As per IRC SP 84,8.6ii) Water from each source shall be tested before start of work and there afterevery 3 months and after every monsoon till the completion of work. (IS:9103, IS:6925) (IS:9103) (IS:9103) (IS:9103) Once per source and as when required Once per source and as when required Once per source and as when required Once per source and as when required (IS:10262,IS:456, IRC:21) Every concrete spread over entire period of concreting Every batch of concrete at dispatch as well as delivery point IS : 516 M/s. SAI MAATARINI TOLLWAYS LIMITED As per requirement 87365 25750 113115 2273.0 m3 229.0 m3 2502.0 M3 382.5 m3 147.5 m3 530.0 m3 11.5m3 17309.5 m3 474m3 72.0m3 Number of Tests Conducted In This Month Previous Month (IS:3025) Sample of cube (A sample means a set of 3 cubes) iii Frequency of Test 0 0 5629.0 m3 23.5 m3 57.5 m3 22938.5 m3 497.5 m3 129.5 m3 Failed Total Passed Failed 18 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 18 0 0 0 0 0 0 0 0 0 3 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 3 0 0 0 0 0 0 0 0 0 21 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 21 0 0 0 0 0 0 0 0 0 2 0 2 2 0 2 4 0 4 2 0 2 2 0 2 4 0 4 2 2 2 2 2 2 2 0 0 0 0 0 0 0 2 2 2 2 2 2 2 2 2 2 2 2 2 2 0 0 0 0 0 0 0 2 2 2 2 2 2 2 4 4 4 4 4 4 4 0 0 0 0 0 0 0 4 4 4 4 4 4 4 3 3 3 3 0 0 0 0 3 3 3 3 1 1 1 1 0 0 0 0 1 1 1 1 4 4 4 4 0 0 0 0 4 4 4 4 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 171 501 0 0 75 87 0 0 930 2562 0 0 18 12 69 0 0 0 42 102 0 0 402 687 0 0 6 27 69 111 0 0 42 102 0 0 402 687 0 0 6 27 240 612 0 0 117 189 0 0 1332 3249 6 39 24 39 0 0 0 0 0 0 0 0 0 0 0 0 0 0 240 612 0 0 117 189 0 0 1332 3249 6 39 24 39 171 501 0 0 75 87 0 0 930 2562 6 39 18 12 0 0 0 0 0 0 0 0 0 0 0 0 0 0 Total Total to Date Passed Passed Failed Total Page 90 SAI MAATARINI TOLLWAYS LIMITED Four Laning of Panikoili – Rimuli Road Section of NH-215 in the state of Odisha under NHDP Phase-III as BOT (Toll) Basis. Monthly Progress Report : March -2015 [ QC Test Summary – Section-I (Km 80.000 to Km 113.000) Executed Quantity SI. No. Type of Test Test Method A i ii iii iv v vi vii B Frequency of Test OGL (Ref. MORTH Section 305 & 900) (1 sample to be collected for every 250 m on either side) Gradation/Sieve Analysis IS:2720 (Part 4) 1 test/Sample Liquid Limit & PI IS:2720 (Part 5) 1 test/Sample Max. Dry Density & OMC IS:2720 (Part 8) 1 test/Sample Moisture Content IS :2720 (Part 2) 1 test/Sample CBR IS:2720 (Part 16) If sample in SG level Free Swell Index IS:2720 (Part 40) 1 test/Sample Field Density Compaction for OGL IS:2720 (Part 28) 1 Set Test Per 1000 m2 EARTHWORK / BORROW MATERIAL (Ref. MORTH Section 305 & 900) 2 tests/8000 m3 (As per IRC 36i Gradation/Sieve Analysis IS:2720 (Part 4) 1970 & IRC SP 11-1988) 2 tests/8000 m3 (As per IRC 36ii Liquid Limit & PI IS:2720 (Part 5) 1970 & IRC SP 11-1988) 2 tests/8000 m3 (As per IRC 36iii Max. Dry Density & OMC IS:2720 (Part 8) 1970 & IRC SP 11-1988) iv Deleterious Content IS:2720 (Part 27) As Required v Moisture Content IS :2720 (Part 2) 1 test/250 m2 vi CBR IS:2720 (Part 16) 1 test/3000 m3 vii Free Swell Index IS:2720 (Part 40) 1 test/3000 m3 viii Sulphate Content BS:1377(tests 9/10) As and when required ix Field Density Compaction for Embankment IS:2720 (Part 28) 1 Test Per 1000 m2 1 Test Per 500 -1000 m2 (As per IRC x Field Density Compaction for Subgrade IS:2720 (Part 28) 36-1970) Note: Original Ground-OG, Embankment-E, Subgrade-SG, Earthen Shoulder-ES, Backfill - BF C GSB (Ref. MORTH Section 401 & 900) i Gradation/Sieve Analysis IS: 2386-Part 1 1 test/200 m3 ii Liquid Limit & PI IS:2720 (Part 5) 1 test/200 m3 iii Moisture Content IS :2720 (Part 2) 1 test/250 m3 iv Field Density Compaction IS:2720 (Part 28) 1 test/500 m2 1 test/ source and as when v CBR IS:2720 (Part 16) required Initially one, as and when required vi Max. Dry Density & OMC IS:2720 (Part 8) by the Engineer 1 test/ source and as when vii Water Absorption IS:2386 (Part 3) required Initially one, as and when required viii 10% Fines Value BS:812(Part111) by the Engineer D WMM (Ref. MORTH Section 406 & 900) 1 test/500 m3 (As per IRC 109i Aggregate Impact Value IS:2386 (Part 4) 1997) IS:2720 (Part 4) & 1 test/200 m3 of Aggregate (As per ii Gradation/Sieve Analysis IS: 2786-Part 1 IRC 109-1997) Combined Flakiness Index & Elongation 1 test/500 m3 of Aggregate (As per iii IS:2386 (Part 1) Index IRC 109-1997) iv Atterberg Limits (Passing 0.425 mm) IS:2720 (Part 5) 1 test/200 m3 (As per IRC 109-97) v Field Density Compaction IS:2720 (Part 28) 1 test/500 m2 Initially one, as and when required vi Max. Dry Density & OMC IS:2720 (Part 8) by the Engineer Initially one, as and when required vii Abrasion value IS:2386 (Part 4) by the Engineer M/s. SAI MAATARINI TOLLWAYS LIMITED Upto Previous Month Present Month Number of Tests Conducted In This Month Upto Previous Month Cumulative Total to Date Passed Failed Total Passed Failed Total Passed Failed Total 280 280 280 955 0 280 955 0 0 0 0 0 0 4 280 280 280 955 0 280 959 0 0 0 97 0 0 97 0 0 0 0 0 0 0 0 0 0 97 0 0 97 280 280 280 1052 0 280 1052 0 0 0 0 0 0 4 280 280 280 1052 0 280 1056 471,949 27,025 498,974 978,000 84,000 1,062,000 572 0 572 33 0 33 605 0 605 978,000 84,000 1,062,000 568 0 568 33 0 33 601 0 601 978,000 84,000 1,062,000 568 0 568 33 0 33 601 0 601 0 2,280,909 945,000 978,000 1,682,535 0 321,185 78,000 84,000 196,515 0 2,602,094 1,023,000 1,062,000 1,879,050 0 10045 164 568 0 5737 0 0 29 0 0 138 0 10045 193 568 0 5875 0 1617 28 33 0 717 0 0 0 0 0 0 0 1617 28 33 0 717 0 11662 192 601 0 6454 0 0 29 0 0 138 0 11662 221 601 0 6592 685,659 124,670 810,329 4070 100 4170 900 0 900 4970 100 5070 31,961 31,961 159,805 159,805 7,684 7,684 38,420 38,420 39,645 39,645 198,225 198,225 177 173 480 474 0 0 0 6 177 173 480 480 45 45 132 130 0 0 0 2 45 45 132 132 222 218 612 604 0 0 0 8 222 218 612 612 - - - 2 0 2 0 0 0 2 0 2 - - - 2 0 2 0 0 0 2 0 2 - - - 2 0 2 0 0 0 2 0 2 - - - 2 0 2 0 0 0 2 0 2 26,053 5,700 31,753 135 0 135 32 0 32 167 0 167 26,053 5,700 31,753 226 0 226 45 0 45 271 0 271 26,053 5,700 31,753 135 0 135 32 0 32 167 0 167 26,053 204,824 5,700 45,600 31,753 250,424 200 612 0 6 200 618 45 190 0 0 45 190 245 802 0 6 245 808 - - 2 0 2 0 0 0 2 0 2 - - 0 0 0 0 0 0 0 0 0 Page 91 SAI MAATARINI TOLLWAYS LIMITED Four Laning of Panikoili – Rimuli Road Section of NH-215 in the state of Odisha under NHDP Phase-III as BOT (Toll) Basis. Monthly Progress Report : March -2015 [ Executed Quantity SI. No. viii Type of Test Water Absorption E 1 i ii BITUMINOUS COURSES PRIME COAT (Ref. MORTH Section 502 & 900) Quality of binder Temperature of Binder for application iii Rate of spread of Binder 2 i ii TACK COAT (Ref. MORTH Section 503 & 900) Quality of binder Temperature of Binder for application iii Rate of spread of Binder 3 i DBM (Ref. MORTH Section 507 & 900) Quality of binder Aggregate Impact Value / Los Angles Abrasion Value ii Test Method IS:2386 (Part 3) IS: 73, 217& 8887 IS: 73, 217& 8887 IS: 73 IS:2386 Part 4 & IS: 2386-Part 3 iii Flakiness Index & Elongation Index IS:2386 Part 1 iv Stripping value v Water absorption of aggregate IS:2386 Part 3 vi Soundness (Magnesium and sodium sulphate) IS:2386 Part 5 vii Sand equivalent test for fine aggregate IS:2720 Part 37 viii Plasticity Index IS:2720 Part 5 ix Percentage of fractured faces x Mix grading & Individual xii Stability of mix IS:6241 IS:2720 (Part 4) Asphalt Institute Manual MS-2 Frequency of Test Initially one, as and when required by the Engineer 1 test/lot At regular close interval One test per 500sq.m and not less than two tests per day 1 test/lot At regular close interval One test per 500sq.m and not less than two tests per day 1 test/lot One test per 350 cum. of aggregate (As per IRC 111-2009) One test per 350 cum. of aggregate (As per IRC 111-2009) Initially one test of 3 representative specimens for each source of supply. Subsequently when warranted by changes in the quality of aggregates. Initially one test of 3 representative specimens for each source of supply. Subsequently when warranted by changes in the quality of aggregates. Initially, one determination by each method for each source of supply, then as warranted by change in the quality of the aggregates. Initially one, as and when required by the Engineer Initially one, as and when required by the Engineer When gravel is used, one test per 50 cum of aggregate. One set of tests on individual constituents and mixed aggregate from the drier for each 400 tones of mix subject to a minimum of two tests per plant per day. For each 400 tones of mix produced, a set of 3 Marshall specimens to be prepared and tested for stability, flow value, density and void content subject to a minimum of two sets being tested per plant per day. M/s. SAI MAATARINI TOLLWAYS LIMITED Upto Previous Month Present Month - 59,664 55,528 Cumulative 9,152 Total to Date Passed Failed Total Passed Failed Total Passed Failed Total 2 0 2 0 0 0 2 0 2 4 20 0 0 4 20 2 5 0 0 2 5 6 25 0 0 6 25 127 0 127 32 0 32 159 0 159 3 23 0 0 3 23 0 4 0 0 0 4 3 27 0 0 3 27 64,680 132 0 132 19 0 19 151 0 151 - 15,224 Number of Tests Conducted In This Month Upto Previous Month 74,888 36 7 43 36 0 36 7 0 7 43 0 43 4,354 1,053 5,407 21 0 21 5 0 5 26 0 26 4,354 1,053 5,407 21 0 21 5 0 5 26 0 26 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 9,932 2,294 12,226 215 0 215 50 0 50 265 0 265 9,932 2,294 12,226 43 0 43 10 0 10 53 0 53 Page 92 SAI MAATARINI TOLLWAYS LIMITED Four Laning of Panikoili – Rimuli Road Section of NH-215 in the state of Odisha under NHDP Phase-III as BOT (Toll) Basis. Monthly Progress Report : March -2015 [ Executed Quantity SI. No. Type of Test Test Method Frequency of Test xiii Water sensitivity of mix (Retained tensile strength) AASHTO T 283 Initially one test of 3 representative specimens for each source of supply. Subsequently when warranted by changes in the quality of aggregates (if required) xiv Control of temperature of binder in boiler, aggregate in the dryer and mix at the time of laying and rolling. IRC 111 (2009) At regular close interval xv Control of binder content and grading of the mix. xvi Rate of spread of mixed material xvii Density of compacted layer Asphalt Institute Manual MS-2 F 1 i Coating and stripping of bitumen aggregate mixtures MATERIAL FOR STRUCTURES COARSE AGGREGATE (MoRTH 1007) Moisture Content ii Specific Gravity IS:383, IS:2386 - Part III iii Gradation/Sieve Analysis Aggregate Impact Value/Los Angles Abrasion Value IS:383,IS:2386 – Part 1 xviii iv IS:6241 IS:383,IS:2386 P-III IS:383, IS:2386 Part IV v Flakiness Index IS:383,IS:2386 P-1 vi Water absorption of Aggregate IS383,IS:2386 P-III viii Soundness (Magnesium and sodium sulphate) Alkali-Aggregate reactivity ix Petrographic Analysis x xi 2 i ii iii Chloride & Sulphate Deleterious Material FINE AGGREGATE (MORTH 1008) Silt Content Moisture Content Clay Lumps iv Specific Gravity v Gradation/Sieve Analysis, Fineness Modulus vi Water absorption of Aggregate vii viii Chloride & Sulphate Deleterious Material Soundness (Magnesium and Sodium Sulphate) CONCRETE (MORTH 1716.2.5) vii ix 5 One test for each 400 tones of mix subject to a minimum of two tests per day per plant. Regular control through checks on the weight of mixed material and layer thickness 1 test / 700 sq.m area (As per IRC 111-2009) Initially one, as and when required by the Engineer Daily/at every day of concreting One per source & there after every month. one test per day One per source & there after once in a week. One per source & there after once in a week . One per source & there after every month. Upto Previous Month Present Month Cumulative 0 0 9,932 Number of Tests Conducted In This Month Upto Previous Month Total to Date Passed Failed Total Passed Failed Total Passed Failed Total 0 0 0 0 0 0 0 0 0 0 2,294 12,226 497 0 497 115 0 115 612 0 612 9,932 2,294 12,226 43 0 43 10 0 10 53 0 53 9,932 2,294 12,226 99 0 99 23 0 23 122 0 122 55,528 11,704 67,232 86 0 86 19 0 19 105 0 105 0 0 0 0 0 0 0 0 0 0 0 0 479 0 479 64 0 64 543 0 543 6 0 6 3 0 3 9 0 9 479 0 479 64 0 64 543 0 543 95 0 95 5 0 5 100 0 100 95 0 95 5 0 5 100 0 100 7 0 7 3 0 3 10 0 10 IS:383,IS:2386 -V One per source 0 0 0 0 0 0 0 0 0 IS:383,IS:2386 P-VII IS:383, ASTM 295, IS:2386 Part VIII IS:383,IS:SP-23 IS:383, IS:2386 P-II One per source 0 0 0 0 0 0 0 0 0 One per source 0 0 0 0 0 0 0 0 0 One per source One per source 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 283 283 0 0 0 0 283 283 0 28 28 0 0 0 0 28 28 0 311 311 0 0 0 0 311 311 0 IS:383,IS2386 Part II (IS:383,IS:2386) (IS:383, IS:2386 Part II) (IS:383,IS:2386P-III) (IS:383,IS:2386 – Part III) IS:383,IS:2386 P-III (IS:383,IS:SP -23) (IS383,IS:2386 Part II) IS:383,IS:2386 P-V Daily Daily/at every day of concreting At every day of concreting One per source & there after every month. Daily One per source & there after every month. One per source One per source One per source M/s. SAI MAATARINI TOLLWAYS LIMITED 2 0 2 1 0 1 3 0 3 283 0 283 28 0 28 311 0 311 153 0 153 1 0 1 154 0 154 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 Page 93 SAI MAATARINI TOLLWAYS LIMITED Four Laning of Panikoili – Rimuli Road Section of NH-215 in the state of Odisha under NHDP Phase-III as BOT (Toll) Basis. Monthly Progress Report : March -2015 [ Executed Quantity SI. No. Type of Test i Sample of cube (A sample means a set of 3 cubes) ii Workability (Slump) iii Cube Strength of Concrete COMPRESSIVE STRENGTH (MIX DESIGN CUBES) No. Of Cubes Frequency of Test : 1/Design Mix (or) 1/Change of Source COMPRESSIVE STRENGTH (SITE CUBES) No. Of Cubes Frequency of Test : MORTH Sec.1700 Table:1700-8 Test Method (IS:10262,IS:456, IRC:21) IS : 516 IS 516 IS 516 IS 516 IS 516 IS 516 IS 516 IS 516 IS 516 IS 516 IS 516 IS 516 IS 516 IS 516 IS 516 IS 516 IS 516 IS 516 IS 516 IS 516 IS 516 IS 516 IS 516 IS 516 IS 516 IS 516 IS 516 IS 516 IS 516 Frequency of Test Every concrete spread over entire period of concreting Every batch of concrete at dispatch as well as delivery point As per requirement M15 7days M15 28 days M20 7days M20 28 days M25 7days M25 28 days M30 7days M30 28 days M35 7days M35 28 days M40 7days M40 28 days M20Kerb 7days M20Kerb 28 days M15 7days M15 28 days M20 7days M20 28 days M25 7days M25 28 days M30 7days M30 28 days M35 7days M35 28 days M40 7days M40 28 days M20 Kerb 7days M20 Kerb 28 days Upto Previous Month Present Month Number of Tests Conducted In This Month Upto Previous Month Cumulative 1,342.0 123.0 1,465.0 26.0 0.0 26.0 0.0 0.0 0.0 7,502.5 1,203.5 8,706.0 43.0 22.0 65.0 129.5 148.0 277.5 389.5 125.0 514.5 Total to Date Passed Failed Total Passed Failed Total Passed Failed Total 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 240 465 6 9 0 0 762 1821 9 21 15 27 108 156 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 240 465 6 9 0 0 762 1821 9 21 15 27 108 156 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 27 49 0 0 0 0 114 417 3 9 24 36 48 84 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 27 49 0 0 0 0 114 417 3 9 24 36 48 84 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 267 514 6 9 0 0 876 2238 12 30 39 63 156 240 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 267 514 6 9 0 0 876 2238 12 30 39 63 156 240 QC Test Summary – Section-II (Km 113.000 to Km 166.173) Executed Quantity Sl. No A i ii iii iv v vi vii B i ii iii Name of Test Testing Method Frequency of Test OGL (Ref. MORTH Section 305 & 900) (1 sample to be collected for every 250 m on either side) Gradation/Sieve Analysis IS:2720 (Part 4) 1 test/Sample Liquid Limit & PI IS:2720 (Part 5) 1 test/Sample Max. Dry Density & OMC IS:2720 (Part 8) 1 test/Sample Moisture Content IS :2720 (Part 2) 1 test/Sample CBR IS:2720 (Part 16) If sample in SG level Free Swell Index IS:2720 (Part 40) 1 test/Sample Field Density Compaction for OGL IS:2720 (Part 28) 1 Set Test Per 1000 m2 EARTHWORK (Ref. MORTH Section 305 & 900) Gradation/Sieve Analysis IS:2720 (Part 4) 1 test/3000 m3 Liquid Limit & PI IS:2720 (Part 5) 1 test/3000 m3 Max. Dry Density & OMC IS:2720 (Part 8) 1 test/3000 m3 M/s. SAI MAATARINI TOLLWAYS LIMITED Upto Previous Month Present Month Cumulative _ _ _ _ _ _ 277166.67 _ _ _ _ _ _ 39,167 1963500 1957500 1962000 138000 138000 138000 Number of Tests Conducted In This Month Previous Month Total to Date Passed Failed Total Passed Failed Total Passed Failed Total _ _ _ _ _ _ 316,333 222 222 222 0 2 222 1508 0 0 0 0 0 0 155 222 222 222 0 2 222 1663 0 0 0 0 0 0 235 0 0 0 0 0 0 0 0 0 0 0 0 0 235 222 222 222 0 2 222 1743 0 0 0 0 0 0 155 222 222 222 0 2 222 1898 2101500 2095500 2100000 1282 1282 1285 27 23 23 1309 1305 1308 46 46 46 0 0 0 46 46 46 1328 1328 1331 27 23 23 1355 1351 1354 Page 94 SAI MAATARINI TOLLWAYS LIMITED Four Laning of Panikoili – Rimuli Road Section of NH-215 in the state of Odisha under NHDP Phase-III as BOT (Toll) Basis. Monthly Progress Report : March -2015 [ Executed Quantity Sl. No Name of Test iv v vi vii viii ix C i ii iii iv v Moisture Content CBR Free Swell Index Sulphate Content Field Density Compaction for Embankment Field Density Compaction for Subgrade GSB (Ref. MORTH Section 401 & 900) Gradation/Sieve Analysis Liquid Limit & PI Moisture Content Field Density Compaction CBR Testing Method IS :2720 (Part 2) IS:2720 (Part 16) IS:2720 (Part 40) BS:1377(tests 9/10) IS:2720 (Part 28) IS:2720 (Part 28) IS: 2386-Part 1 IS:2720 (Part 5) IS :2720 (Part 2) IS:2720 (Part 28) IS:2720 (Part 16) vi Max. Dry Density & OMC IS:2720 (Part 8) vii Water Absorption IS:2386 (Part 3) viii 10% Fines Value BS:812(Part111) D I WMM (Ref. MORTH Section 406 & 900) Aggregate Impact Value ii Gradation/Sieve Analysis iii iv v Combined Flakiness Index & Elongation Index Atterberg Limits (Passing 0.425 mm) Field Density Compaction vi Max. Dry Density & OMC IS:2720 (Part 8) vii Abrasion value IS:2386 (Part 4) viii Water Absorption IS:2386 (Part 3) E i ii BITUMINOUS COURSES PRIME COAT / TACK COAT (Ref. MORTH Section 502, 503 & 900) Quality of binder Temperature of Binder for application iii Rate of spread of Binder 1 iii DBM / BC (Ref. MORTH Section 507, 509 & 900) Quality of binder Aggregate Impact Value / Los Angles Abrasion Value Flakiness Index & Elongation Index iv Stripping value 2 i ii IS:2386 (Part 4) IS:2720 (Part 4) & IS: 2786-Part 1 IS:2386 (Part 1) IS:2720 (Part 5) IS:2720 (Part 28) IS: 73, 217& 8887 IS: 73 IS:2386 Part 4 & IS: 2386-Part 3 IS:2386 Part 1 IS:6241 Frequency of Test Upto Previous Month 48250 771000 1942500 _ 2738333.3 370083 Number of Tests Conducted In This Month Previous Month Present Month Cumulative 0 33000 138000 _ 275333 52833 88,400 85,600 40,250 481,000 _ Total to Date Passed Failed Total Passed Failed Total Passed Failed Total 48250 804000 2080500 _ 3013667 422917 193 247 1268 0 15661 4170 0 10 27 0 769 271 193 257 1295 0 16430 4441 30 11 46 0 1598 606 0 0 0 0 54 28 30 11 46 0 1652 634 223 258 1314 0 17259 4776 0 10 27 0 823 299 50 268 1341 0 18082 5075 21,600 21,600 6,250 85,000 0 110,000 107,200 46,500 566,000 _ 428 428 161 866 43 14 0 0 96 0 442 428 161 962 43 108 108 25 155 0 0 0 0 15 0 108 108 25 170 0 536 536 186 1,021 43 14 0 0 111 0 550 536 186 1,132 43 _ 0 _ 4 0 4 0 0 0 4 0 4 _ 0 _ 5 0 5 0 0 0 5 0 5 _ 0 _ 8 0 8 0 0 0 8 0 8 1 test/500 m3 75200 14400 89600 376 0 376 53 0 53 429 0 429 1 test/200 m3 of aggregate 62900 15400 78300 629 0 629 77 0 77 706 0 706 1 test/500 m3 1 test/200 m3 1 test/500 m2 Initially one, as and when required by the Engineer Initially one, as and when required by the Engineer Initially one, as and when required by the Engineer 75200 62600 675500 14400 15400 130500 89600 78000 806000 376 626 1241 0 0 110 376 626 1351 53 77 249 0 0 12 53 77 261 429 703 1490 0 0 122 429 703 1612 _ _ 0 2 0 2 0 0 0 2 0 2 _ 1 0 2 0 2 0 0 0 2 0 2 _ 1 0 2 0 2 0 0 0 2 0 2 1 test/lot At regular close interval One test per 500sq.m and not less than two tests per day 0 0 0 0 0 0 5 36 0 0 5 36 2 25 0 0 2 25 7 61 0 0 7 61 101500 60000 161500 203 0 203 120 0 120 323 0 323 1 test/250 m2 1 test/3000 m3 1 test/3000 m3 As & when Required 1 Set Test Per 1000 m2 1 Set Test Per 500 m2 1 test/200 m3 1 test/200 m3 1 test/250 m2 1 test/500 m2 1 test/ source and as when required Initially one, as and when required by the Engineer 1 test/ source and as when required Initially one, as and when required by the Engineer 1 test/lot 0 0 0 34 0 34 3 0 3 37 0 37 One test per 350 cum. of aggregate 3900 4213 8113 78 0 78 25 0 25 103 0 103 One test per 350 cum. of aggregate Initially one test of 3 representative specimens for each source of supply. Subsequently when warranted by changes in the quality of aggregates. 3900 4213 8113 78 0 78 25 0 25 103 0 103 0 0 0 6 0 6 2 0 2 8 0 8 M/s. SAI MAATARINI TOLLWAYS LIMITED Page 95 SAI MAATARINI TOLLWAYS LIMITED Four Laning of Panikoili – Rimuli Road Section of NH-215 in the state of Odisha under NHDP Phase-III as BOT (Toll) Basis. Monthly Progress Report : March -2015 [ Executed Quantity Sl. No Name of Test Testing Method v Water absorption of aggregate IS:2386 Part 3 vi Soundness (Magnesium and sodium sulphate) IS:2386 Part 5 vii Sand equivalent test for fine aggregate IS:2720 Part 37 viii Plasticity Index (IS:2720 Part 5 ix Stone Polish Test x Percentage of fractured faces xi Mix grading xii Stability of mix xiii Water sensitivity of mix (Retained tensile strength) xv Control of binder content and grading of the mix. xvi Rate of spread of mixed material xvii F 1 i Density of compacted layer MATERIAL FOR STRUCTURES COARSE AGGREGATE (MoRTH 1007) Moisture Content (BS 812 Part – 114) IS:2720 (Part 4) Asphalt Institute Manual MS-2 AASHTO T 283 Asphalt Institute Manual MS-2 IS:383,IS:2386 P-III ii Specific Gravity IS:383, IS:2386 - Part III iii Gradation/Sieve Analysis Aggregate Impact Value/Los Angles Abrasion Value IS:383,IS:2386 – Part 1 iv IS:383, IS:2386 Part IV v Flakiness Index IS:383,IS:2386 P-1 vi Water absorption of Aggregate IS383,IS:2386 P-III Frequency of Test Initially one test of 3 representative specimens for each source of supply. Subsequently when warranted by changes in the quality of aggregates. Initially, one determination by each method for each source of supply, then as warranted by change in the quality of the aggregates. Initially one, as and when required by the Engineer Initially one, as and when required by the Engineer Initially one, as required, for Bituminous Concrete. When gravel is used, one test per 50 cum of aggregate. One set of tests on individual constituents and mixed aggregate from the drier for each 400 tones of mix subject to a minimum of two tests per plant per day. For each 400 tones of mix produced, a set of 3 Marshall specimens to be prepared and tested for stability, flow value, density and void content subject to a minimum of two sets being tested per plant per day. Initially one test of 3 representative specimens for each source of supply. Subsequently when warranted by changes in the quality of aggregates (if required) One test for each 400 tones of mix subject to a minimum of two tests per day per plant. Regular control through checks on the weight of mixed material and layer thickness 1 test / 250 sq.m area Daily/at every day of concreting One per source & there after every month. one test per day One per source & there after once in a week. One per source & there after once in a week . One per source & there after every month. M/s. SAI MAATARINI TOLLWAYS LIMITED Upto Previous Month Present Month Cumulative 0 0 0 Number of Tests Conducted In This Month Previous Month Total to Date Passed Failed Total Passed Failed Total Passed Failed Total 0 5 0 5 0 0 0 5 0 5 0 0 1 0 1 0 0 0 1 0 1 0 0 0 1 0 1 0 0 0 1 0 1 0 0 0 20 0 20 3 0 3 23 0 23 0 0 0 1 0 1 0 0 0 1 0 1 0 0 0 0 0 0 0 0 0 0 0 0 12000 18000 30000 56 0 56 45 0 45 101 0 101 12000 18000 30000 60 0 60 45 0 45 105 0 105 0 0 0 6 0 6 0 0 0 6 0 6 0 0 0 56 0 56 45 0 45 101 0 101 0 0 0 0 0 0 0 0 0 0 0 0 36500 28000 64500 146 0 146 112 0 112 258 0 258 _ _ _ 871 0 871 248 0 248 1119 0 1119 _ _ _ 13 0 13 0 0 0 13 0 13 _ _ _ 781 0 781 92 0 92 873 0 873 _ _ _ 78 0 78 3 0 3 81 0 81 _ _ _ 77 0 77 3 0 3 80 0 80 _ _ _ 8 0 8 0 0 0 8 0 8 Page 96 SAI MAATARINI TOLLWAYS LIMITED Four Laning of Panikoili – Rimuli Road Section of NH-215 in the state of Odisha under NHDP Phase-III as BOT (Toll) Basis. Monthly Progress Report : March -2015 [ Executed Quantity Sl. No Name of Test vii viii Soundness (Magnesium and sodium sulphate) Alkali-Aggregate reactivity ix Petrographic Analysis x xi 2 i ii iii Chloride & Sulphate Deleterious Material FINE AGGREGATE (MORTH 1008) Silt Content Moisture Content Clay Lumps iv Specific Gravity v Gradation/Sieve Analysis, Fineness Modulus vi Water absorption of Aggregate vii viii ix Chloride & Sulphate Deleterious Material Soundness (Magnesium and Sodium Sulphate) 43 GRADE ORDINARY PORTLAND CEMENT (Ref. IS: 8112 & MoRTH 1006) Initial Setting Time Final Setting Time Soundness by Le-Chatlier’s method (%) Fineness by dry sieve method 90micron Compressive strength Chemical Tests Loss on Ignition Insoluble residue Alumina Iron Oxide ratio Lime Saturation factor Magnesia Sulphuric anhydride Alkalies Chlorides 53 GRADE ORDINARY PORTLAND CEMENT (Ref. IS: 12269, MoRTH 1006) Initial Setting Time Final Setting Time Soundness (by Le-Chatlier’s method) by Autoclave (%) Fineness (by Blaine’s air permeability method) Compressive strength Chemical Tests Loss on Ignition Insoluble residue Alumina Iron Oxide ratio Lime Saturation factor Magnesia Sulphuric anhydride Alkalies Chlorides 3 i ii iii iv v vi vii viii ix x xi xii xiii xiv 4 i ii iii iv v vi vii viii ix x xi xii xiii xiv IS:383,IS:2386 -V IS:383,IS:2386 P-VII IS:383, ASTM 295, IS:2386 Part VIII IS:383,IS:SP-23 IS:383, IS:2386 P-II IS:383,IS2386 Part II (IS:383,IS:2386) (IS:383, IS:2386 Part II) (IS:383,IS:2386P-III) (IS:383,IS:2386 – Part III) IS:383,IS:2386 P-III (IS:383,IS:SP -23) (IS383,IS:2386 Part II) IS:383,IS:2386 P-V (IS:4031) One per source One per source One per source _ _ _ 3 0 3 0 0 0 3 0 3 One per source One per source _ _ _ _ _ _ 1 3 0 0 1 3 0 0 0 0 0 0 1 3 0 0 1 3 Daily Daily/at every day of concreting At every day of concreting One per source & there after every month. Daily One per source & there after every month. One per source One per source One per source _ _ _ _ _ _ _ _ _ 37 792 0 0 0 0 37 792 0 3 124 0 0 0 0 3 124 0 40 916 0 0 0 0 40 916 0 _ _ _ 12 0 12 0 0 0 12 0 12 _ _ _ 552 0 552 46 0 46 598 0 598 _ _ _ 10 0 10 0 0 0 10 0 10 _ _ _ _ _ _ _ _ _ 0 3 0 0 0 0 0 3 0 0 0 0 0 0 0 0 0 0 0 3 0 0 0 0 0 3 0 _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ 41 41 11 41 132 5 3 3 3 3 3 3 3 3 0 0 0 0 0 0 0 0 0 0 0 0 0 0 41 41 11 41 132 5 3 3 3 3 3 3 3 3 3 2 2 2 9 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 3 2 2 2 9 0 0 0 0 0 0 0 0 0 44 43 13 43 141 5 3 3 3 3 3 3 3 3 0 0 0 0 0 0 0 0 0 0 0 0 0 0 44 43 13 43 141 5 3 3 3 3 3 3 3 3 _ _ _ _ _ _ 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 _ _ _ 0 0 0 0 0 0 0 0 0 _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ 0 0 3 3 3 3 3 3 3 3 3 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 3 3 3 3 3 3 3 3 3 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 Frequency of Test One test per week and once per source 3rd party testing IS 516 (IS:4032) MTC for each supply andone per source 3rd party testing (IS:4031) One test per week and once per source 3rd party testing IS 516 (IS:8112) Number of Tests Conducted In This Month Upto Previous Month _ _ Testing Method MTC for each supply and one per source 3rd party testing M/s. SAI MAATARINI TOLLWAYS LIMITED Previous Month Present Month Cumulative _ _ Total to Date Passed Failed Total Passed Failed Total Passed Failed Total _ _ 3 3 0 0 3 3 0 0 0 0 0 0 3 3 0 0 3 3 0 0 0 0 0 0 0 0 0 Page 97 SAI MAATARINI TOLLWAYS LIMITED Four Laning of Panikoili – Rimuli Road Section of NH-215 in the state of Odisha under NHDP Phase-III as BOT (Toll) Basis. Monthly Progress Report : March -2015 [ Executed Quantity Sl. No 5 i ii iii iv v vi vii viii ix 6 Name of Test Testing Method WATER (MORTH 1010) Volume of 0.02N NaOH required to neutralize 100 ml sample of water using phenolphthalein as an indicator Volume of 0.02N H2SO4 required to neutralize 100 ml sample of water using methyl orange as an indicator Solids Organic Inorganic Sulphates (SO4) Chlorides (CI) Suspended matter pH ADMIXTURE (MORTH 1012) (IS:3025) (IS:3025) (IS:456,IS:3025) i Chloride Content ii Dry Material content (IS:9103) iii Ash content (IS:9103) iv Relative density (IS:9103) 7 CONCRETE (MORTH 1716.2.5) Sample of cube (A sample means a set of 3 cubes) i ii Workability (Slump) iii Cube Strength of Concrete COMPRESSIVE STRENGTH (MIX DESIGN CUBES) No. Of Cubes 1 Frequency of Test : 1/Design Mix (or) 1/Change of Source COMPRESSIVE STRENGTH (SITE CUBES) No. Of Cubes 2 Frequency of Test : MORTH Sec.1700 Table:1700-8 Frequency of Test (IS:9103, IS:6925) (IS:10262,IS:456, IRC:21) IS : 516 IS 516 IS 516 IS 516 IS 516 IS 516 IS 516 IS 516 IS 516 IS 516 IS 516 IS 516 IS 516 IS 516 IS 516 IS 516 IS 516 IS 516 IS 516 IS 516 IS 516 IS 516 IS 516 IS 516 (As per IRC SP 84,8.6ii) Water from each source shall be tested before start of work and there afterevery 3 months and after every monsoon till the completion of work. Once per source and as when required Once per source and as when required Once per source and as when required Once per source and as when required Every concrete spread over entire period of concreting Every batch of concrete at dispatch as well as delivery point As per requirement M15 7days M15 28 days M20 7days M20 28 days M25 7days M25 28 days M30 7days M30 28 days M35 7days M35 28 days M40 7days M40 28 days M45 7days M45 28days M15 7days M15 28 days M20 7days M20 28 days M25 7days M25 28 days M30 7days M30 28 days M35 7days M/s. SAI MAATARINI TOLLWAYS LIMITED Upto Previous Month Present Month Cumulative _ _ _ Number of Tests Conducted In This Month Previous Month Total to Date Passed Failed Total Passed Failed Total Passed Failed Total _ 2 0 2 1 0 1 3 0 3 _ _ 2 0 2 1 0 1 3 0 3 _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ 2 2 2 2 2 2 2 0 0 0 0 0 0 0 2 2 2 2 2 2 2 1 1 1 1 1 1 1 0 0 0 0 0 0 0 1 1 1 1 1 1 1 3 3 3 3 3 3 3 0 0 0 0 0 0 0 3 3 3 3 3 3 3 _ _ _ 2 0 2 1 0 1 3 0 3 _ _ _ 2 0 2 1 0 1 3 0 3 _ _ _ 2 0 2 1 0 1 3 0 3 _ _ _ 2 0 2 1 0 1 3 0 3 _ _ _ 9972 0 9972 1800 0 1800 11772 0 11772 _ _ _ 17799 0 17799 2500 0 2500 20299 0 20299 _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ 5387.5 489 5876.5 0 0 0 19 21 15 14 0 2 19 21 13 14 9 13 7 6 538 931 0 0 11 8 2185 4533 155 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 19 21 15 14 0 2 19 21 13 14 9 13 7 6 538 931 0 0 11 8 2185 4533 155 0 0 0 0 0 0 0 0 0 0 0 0 0 0 62 74 0 0 0 4 255 595 22 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 62 74 0 0 0 4 255 595 22 19 21 15 14 0 2 19 21 13 14 9 13 7 6 600 1005 0 0 11 12 2440 5128 177 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 19 21 15 14 0 2 19 21 13 14 9 13 7 6 600 1005 0 0 11 12 2440 5128 177 62 0 62 42380 4629 47009 3611 736 4347 Page 98 SAI MAATARINI TOLLWAYS LIMITED Four Laning of Panikoili – Rimuli Road Section of NH-215 in the state of Odisha under NHDP Phase-III as BOT (Toll) Basis. Monthly Progress Report : March -2015 [ Executed Quantity Sl. No Name of Test Testing Method IS 516 IS 516 IS 516 IS 517 IS 518 IS 516 IS 516 Upto Previous Month Present Month M40 7days M40 28 days M45 7days M45 28 days M20Kerb 7days M20Kerb 28 days STEEL MTC ii SAMPLING IS 1786 CHEMICAL UTS YIELD STRESS ELONGATION BEND TEST REBEND TEST UNIT WEIGHT DIAMETER IS 1786 IS 1786 IS 1786 IS 1786 IS 1786 IS 1786 IS 1786 IS 1786 Each Delivery FOR BELOW 100 TONS UNDER 10MM - 1/25TON; 10-MM TO 16 MM - 1/35TON; OVER 16-MM 1/45TON Each Consignment M/s. SAI MAATARINI TOLLWAYS LIMITED Number of Tests Conducted In This Month Previous Month Cumulative M35 28 days 8 i iii iv v vi vii viii ix x Frequency of Test Total to Date Passed Failed Total Passed Failed Total Passed Failed Total 314 39 51 3 0 70 124 0 0 0 0 0 0 0 314 39 51 3 0 70 124 56 8 30 4 11 10 31 0 0 0 0 0 0 0 56 8 30 4 11 10 31 370 47 81 7 11 80 155 0 0 0 0 0 0 0 370 47 81 7 11 80 155 424 147 571 97 193 290 786.5 258 1044.5 _ _ _ 216 0 216 33 0 33 249 0 249 _ _ _ 205 0 205 18 0 18 223 0 223 _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ 84 84 84 84 84 84 216 216 0 0 0 0 0 0 0 0 84 84 84 84 84 84 216 216 6 6 6 6 6 6 33 33 0 0 0 0 0 0 0 0 6 6 6 6 6 6 33 33 90 90 90 90 90 90 249 249 0 0 0 0 0 0 0 0 90 90 90 90 90 90 249 249 Page 99 SAI MAATARINI TOLLWAYS LIMITED Four Laning of Panikoili – Rimuli Road Section of NH-215 from Km 0+000 – 163+000 in the state of Odisha under NHDP Phase-III as BOT (Toll) Basis. Monthly Progress Report : March -2015 19. Appendix 3 - List of Plant and Equipment 20. Section (0-113) Sl. Description of P&M No. PLANTS 1 Crusher 2 Crusher 3 Crusher 4 Batching Plant 5 Batching Plant 6 Batching Plant 7 Wet Mix Plant 8 Wet Mix Plant 9 Wet Mix Plant 10 Hot Mix Plant 11 Hot Mix Plant 12 Hot Mix Plant MACHINERY 1 JCB 2 Hire JCB 3 Excavator 4 Hire excavator 5 Loader-3036 6 Hire loader 7 Soil compactors 8 Grader cat120k 9 Sensor- Paver 10 Crane hydra 11 Hire hydra crane 12 Dumper 13 BT Sprayer 14 Hire dumpers 15 Boom Placer 16 Bolero 17 Camper Genio 18 Diesel tanker 19 Dozer 20 Concrete Pump (mcp/12) 21 Dewatering Pump 22 DG Sets (5 Kva – 500 Kva) 23 Kerb Laying 24 Water Tanker 25 Transit Mixer 26 Trailers 27 PTR 28 Concrete Pump 29 Kerb Cutting Make/Brand Capacity Available at Site Remarks Metso Metso Puzzolana Schwing Stetter Schwing Stetter Schwing Stetter Apollo MAXMECH Apollo Apollo Speco Speco 240 TPH 240 TPH 200 TPH 30 CPH 60 CPH 30 CPH 160 TPH 200 TPH 250 TPH 160 TPH 160 TPH 160 TPH 1 1 1 1 1 1 1 1 1 1 1 1 KM-42 KM-58 KM-94 KM-19 KM-58 KM-94 KM-18 KM-58 KM-94 KM-32 KM-58 KM-94 0.3 m3 0.3 m3 1 m3 1 m3 1.7 m3 1.7 m3 8-10 Ton 200 Cum/hr Cum/Hr/40/30 5-16 T 10-20T 20 MT 2.4 – 6 Mtr 20 MT 12 KL 60Cum/Hr (Max) 0.75 – 2.5 HP 5 Kva 80 Rmt/hr 12 KL 6 m3 - 4 4 5 17 9 7 13 7 4 2 6 34 3 50 1 11 17 3 2 6 2 33 3 16 13 5 1 6 1 Make/Brand Capacity Available at Site Remarks Puzzolana Puzzolana 200 TPH 240 TPH 1 1 @ Ch 115+000 @ Ch 116+000 Vogele MCP/9,12 21. Section (113-166) Sl. No. A 1 2 Name of P&M Plant Crusher Crusher M/s. SAI MAATARINI TOLLWAYS LIMITED Page 100 SAI MAATARINI TOLLWAYS LIMITED Four Laning of Panikoili – Rimuli Road Section of NH-215 from Km 0+000 – 163+000 in the state of Odisha under NHDP Phase-III as BOT (Toll) Basis. Monthly Progress Report : March -2015 [ Sl. No. Name of P&M 3 Batching Plant 4 5 6 7 B 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 WMM PLANT WMM PLANT HM Plant HM Plant Machinery Excavator Excavator Dumper Tipper WMM Paver Dozer (D80) Grader Grader Escort Roller JCB Roller Tandom Roller PTR Roller Water Tanker JCB Transit Mixer Transit Mixer Transit Mixer Loader BT Sprayer Tractor Broomer Kerb Casting Machine Plate Earth Compacter – 1 24 25 26 27 Concrete Pump Electrical Vibrator 3 Phase - 1 Petrol Vibrator – 1 DG Set 28 29 30 31 32 33 34 35 36 DG Set DG Set DG Set Silent DG Set Silent DG Set Silent DG Gen Set DG Gen Set DG Gen Set Trolley Based Search Light Air Compressor with Patch Heater Welding Transformer 450 Amp – 1 Welding Machine – 2 Weigh Bridge 80/100 Hydra Crane Trailors (40 feet Length x 9.0 m width) Kerb Cutter Rock Breaker 37 38 39 40 41 42 43 44 Make/Brand Capacity Available at Site SchwingStetter 30 cum/Hr 3 Appolo Condequip Appolo Appolo 160 TPH 200 TPH 200 TPH 160 TPH 1 1 1 1 TATA-210 L&T Ashok Leyland TATA Vogele Hindustan CAT Sany Escort JCB Dynapac Dynapac Ashok Leyland CAT Asia Motors Ashok Leyland Ashok Leyland Hindustan Ashok Leyland Ford Appolo Appolo Testwell Greaves Cotton Ltd. KillicEng Killic Caterpillar Greaves Cotton Ltd. Caterpillar Kirloskar Kirloskar Kirloskar Kirloskar Kirloskar Kirloskar Sigma 1m3 1 m3 14m3 - 12 KL 0.3 m3 6 m3 6 m3 4 m3 1.7 m3 - 22 11 116 9 2 12 6 5 13 3 3 1 17 10 6 9 2 6 2 3 1 1 1 500 KVA 5 4 1 3 400 KVA 250 KVA 160 KVA 125 KVA 100 KVA 63 KVA 40 KVA 20 KVA 5 KVA 1 1 1 1 1 1 1 1 3 N/A 3 PHASE 1 Shaketech Rama Vishwakarma Ashok Leyland 3 PHASE 3 PHASE 80MT - 1 1 3 3 Ashok Leyland Appolo - - 3 1 2 M/s. SAI MAATARINI TOLLWAYS LIMITED - Remarks 1-@ Ch 115+400, 2- @ Ch 148+800 & 3- @ Ch 151+200 @ Ch 115+000 @ Ch 134+200 @ Ch 116+000 @ Ch 134+200 Page 101 SAI MAATARINI TOLLWAYS LIMITED Four Laning of Panikoili – Rimuli Road Section of NH-215 from Km 0+000 – 163+000 in the state of Odisha under NHDP Phase-III as BOT (Toll) Basis. Monthly Progress Report : March -2015 [ Sl. No. 45 46 22. Name of P&M Make/Brand Capacity Cruller Drill with Compressor Tata 407 HSD Distributer TATA 3 KL Available at Site 2 1 Remarks Appendix 4 - List of Lab Equipment & Calibration Status Lab at Km 19 Sl. No. 1 2 3 4 5 6 7 8 9 10 11 12 14 16 17 18 19 20 21 22 23 24 25 26 27 29 31 32 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 Name of Equipment / Instrument 300o Thermostatic Controlled Oven ( 0 to Capacity) Big Thermostatic Controlled Oven ( 0 to 300o Capacity) Medium Water Bath, Capacity-50 Litre Electronic balance (30 kg ) 1 gm accuracy Electronic balance (30 kg ) 1 gm accuracy Electronic balance (30 kg ) 1 gm accuracy Electronic balance (30 kg ) 5 gm accuracy Electronic balance (1000 gm ) 0.1 gm accuracy Electronic balance (15 kg) 1.0 gm accuracy Electronic balance (15 kg) 0.5 gm accuracy Electronic balance (15 kg) 0.5 gm accuracy Electronic balance (600 gm ) 0.01 gm accuracy Rapid Moisture Meters 100,75,63,53,50,45,40,37.5,31.5,26.5,25,22.4,20,19,16,14,13.2,12.5,11.2 ,10,9.5,6.3,5.6,4.75 mm (450 mm dia IS Sieves) 4.75,2.36,2.8,2,1.4,1.18,1,0.710,0.600,0.500,0.425,0.355,0.300,0.180,0.1 50,0.090,0.075 mm & Pan (200 mm dia Brass Is Sieves) Casagrande Liquid limit testing device Casagrande Liquid limit testing device CBR Testing Machine Cone penetro meter Proctor mould 2250 cc with 4.9kg rammer Proctor mould 2250 cc with 4.9kg rammer Proctor mould 2250 cc with 4.9kg rammer Proctor mould 2250 cc with 4.9kg rammer Proctor mould 1000 cc with2.6kg rammer Proctor mould 1000 cc with2.6kg rammer Sand Pouring Cylinders with complete set (100mm dia) Sand Pouring Cylinders with complete set (150mm dia) Sand Pouring Cylinders with complete set (200mm dia) CBR moulds Aluminium containers Proving Ring (50 KN) No-980 Proving Ring (50 KN) No-239 Proving Ring (50 KN) No-945 Vicat Needle Apparatus ( with dash pot) Cement Mortar Cube Moulds (7.06x7.06x7.06 cm) Aggregate Impact Value Test Apparatus Flakiness Gauge Elongation Gauge Concrete Cube moulds ( 150x150x150 mm) Concrete beam moulds ( 150x150x700 mm) Slump cone with rod Compressive Testing Machine (2000 kn) (CTM) Cement mortar cube vibrating machine Aggregate Crushing Value M/s. SAI MAATARINI TOLLWAYS LIMITED 1 1 1 1 1 1 1 1 1 1 1 1 1 Last Date of Calibration 11.11.14 11.11.14 22.07.14 11.11.14 11.11.14 11.11.14 11.11.14 11.11.14 11.11.14 11.11.14 11.11.14 11.11.14 16.02.15 Due Date of Calibration 10.11.15 10.11.15 21.07.15 10.11.15 10.11.15 10.11.15 10.11.15 10.11.15 10.11.15 10.11.15 10.11.15 10.11.15 15.08.15 50 11.11.14 10.11.15 43 11.11.14 10.11.15 1 1 1 1 1 1 1 1 1 1 1 1 1 56 150 1 1 22.07.14 22.07.14 22.07.14 13.11.14 24.06.14 24.06.14 24.06.14 24.06.14 24.06.14 24.06.14 10.02.15 10.02.15 10.02.15 10.11.14 24.12.14 14.11.14 14.10.14 14.10.14 13.11.14 11.11.14 11.11.14 13.11.14 13.11.14 11.11.14 28.02.15 22.07.14 30.06.14 13.11.14 22.07.14 21.07.15 21.07.15 21.07.15 12.11.15 23.06.15 23.06.15 23.06.15 23.06.15 23.06.15 23.06.15 09.05.15 09.05.15 09.05.15 09.11.15 23.06.15 13.11.15 14.10.15 14.10.15 12.11.15 10.11.15 10.11.15 12.11.15 12.11.15 10.11.15 27.02.16 21.07.15 30.06.15 12.11.15 21.07.15 Quantity 1 15 1 3 3 93 19 5 1 1 2 Remarks Page 102 SAI MAATARINI TOLLWAYS LIMITED Four Laning of Panikoili – Rimuli Road Section of NH-215 from Km 0+000 – 163+000 in the state of Odisha under NHDP Phase-III as BOT (Toll) Basis. Monthly Progress Report : March -2015 [ Sl. No. 50 51 52 53 54 55 58 59 60 61 62 63 Name of Equipment / Instrument Soundness apparatus Bitumen Penetro meter Ring & ball apparatus electrically operated Ductility Test apparatus (Complete Set) Tar Visco meter Digital Water Bath,Accuracy- 1 deg C Saybolt Visco meter Modified Marshall Rammers Modified Marshall Moulds Standard Marshall Rammers Standard Marshall Moulds Core cutting machine with entire assembly Quantity 5 1 1 1 1 1 1 4 15 4 30 1 Last Date of Calibration 13.11.14 22.07.14 22.07.14 22.07.14 22.07.14 22.07.14 22.07.14 05.08.14 05.08.14 05.08.14 05.08.14 22.07.14 Due Date of Calibration 12.11.15 21.07.15 21.07.15 21.07.15 21.07.15 21.07.15 21.07.15 04.08.15 04.08.15 04.08.15 04.08.15 21.07.15 Last Date of Calibration 04-06-2014 04-06-2014 04-06-2014 04-06-2014 04-06-2014 04-06-2014 04-06-2014 04-06-2014 10-01-2015 09-01-2015 20-02-2015 04-06-2014 04-06-2014 04-06-2014 04-06-2014 04-06-2014 06-01-2015 11-02-2015 06-01-2015 11-02-2015 25-03-2015 06-01-2015 21-02-2015 21-02-2015 21-02-2015 04-06-2015 01-07-2014 01-07-2014 04-06-2014 06-06-2015 04-06-2014 04-06-2014 06-06-2015 06-06-2015 03-06-2015 04-06-2014 04-06-2014 04-06-2014 04-06-2014 06-06-2015 06-06-2015 Due Date of Calibration 03-06-2015 03-06-2015 03-06-2015 03-06-2015 03-06-2015 03-06-2015 03-06-2015 03-06-2015 09-01-2016 08-07-2015 19-08-2015 03-06-2015 03-06-2015 03-06-2015 03-06-2015 03-06-2015 05-04-2015 10-05-2015 05-04-2015 10-05-2015 24-06-2015 05-04-2015 20-02-2016 20-02-2016 20-02-2016 04-12-2015 01-07-2015 01-07-2015 06-06-2015 04-12-2015 06-06-2015 06-06-2015 04-12-2015 04-12-2015 02-12-2015 06-06-2015 06-06-2015 06-06-2015 06-06-2015 04-12-2015 04-12-2015 Remarks Lab at Km 55+000 SI. No. 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 Name of Equipment / Instrument Thermostatic Controlled Oven ( 0 to 300o Capacity) Big Thermostatic Controlled Oven ( 0 to 300o Capacity) Medium Digital Water Bath, Capacity-50 Liter Plateform balance (300 kg ) 100 gm accuracy Electronic balance (30 kg )5 gm accuracy Electronic balance (10kg ) 1.0 gm accuracy Electronic balance (15 kg) 1.0 gm accuracy Electronic balance (600 gm ) 0.01 gm accuracy Digital Thermometer, (0 to +300°C) Rapid Moisture Meter - 01 Rapid Moisture Meter - 03 IS Sieves (100 mm to 4.75 mm 450 mm Dia GI ) IS Sieves (4.75 mm to 0.075 mic Dia Brass ) Casagrande Liquid limit testing device Cone penetro meter Proctor mould & rammer(small & big) Sand Pouring Cylinders with complete set (100mm dia)-2 & 3 Sand Pouring Cylinders with complete set (100mm dia)-1 Sand Pouring Cylinders with complete set (150 mm dia)-2 Sand Pouring Cylinders with complete set (150 mm dia)-3 Sand Pouring Cylinders with complete set (200mm dia)-1 Sand Pouring Cylinders with complete set (200mm dia)-2 CBR moulds Surcharge weight (2.5 Kg) Perforated plates Aluminum containers Proving Ring (50 KN) Proving Ring (25 KN) Vicat Needle Apparatus ( with dash pot) Cement Mortar Cube Moulds (7.06x7.06x7.06 cm) Aggregate Impact Value Test Apparatus Flakiness & Elongation Gauge Concrete Cube moulds ( 150x150x150)mm Slump cone with rod Cement mortar cube vibrating machine Ductility Test apparatus (Complete Set) Ring & ball apparatus electrically operated Bitumen Penetro meter Saybolt Visco meter Modified Marshall Rammers Modified Marshall Moulds M/s. SAI MAATARINI TOLLWAYS LIMITED Quantity 3 1 1 1 4 2 1 2 5 1 1 45 48 4 4 10 5 5 5 5 3 3 30 30 15 200 1 1 1 12 2 5 140 10 1 1 1 1 1 3 15 Remarks Page 103 SAI MAATARINI TOLLWAYS LIMITED Four Laning of Panikoili – Rimuli Road Section of NH-215 from Km 0+000 – 163+000 in the state of Odisha under NHDP Phase-III as BOT (Toll) Basis. Monthly Progress Report : March -2015 [ SI. No. 42 43 44 45 46 47 48 Name of Equipment / Instrument Standard Marshall Rammers Standard Marshall Moulds WMM Plant Concrete Batch mix Plant Hot Mix Plant Standard Measurement Cylinders (5,15&30 Lt capacity) Thin Film Oven Quantity 3 18 1 1 1 3 1 Last Date of Calibration 06-06-2015 06-06-2015 30-12-2014 30-12-2014 08-01-2015 04-06-2014 04-06-2014 Due Date of Calibration 04-12-2015 04-12-2015 29-03-2015 29-03-2015 07-04-2015 06-06-2015 06-06-2015 Last Date of Calibration 23-01-15 23-01-15 23-01-15 23-01-15 23-02-15 23-02-15 25-01-15 23-02-15 23-01-15 21-10-14 03-11-14 28-08-14 29-11-14 29-11-14 18-06-14 06-06-14 02-02-15 07-02-15 03-02-15 03-02-15 06-06-14 06-06-14 29-11-14 24-10-14 16-01-14 27-02-14 18-06-14 06-06-14 20-10-14 20-10-14 23-01-15 23-01-15 23-01-15 23-01-15 23-01-15 23-12-14 23-01-15 23-01-15 23-01-15 23-01-15 21-10-14 23-01-15 Due Date of Calibration 22-01-16 22-01-16 22-01-16 22-01-16 22-02-16 22-02-16 24-01-16 22-02-16 22-01-16 20-04-15 02-05-15 27-08-15 28-11-15 28-11-15 17-06-15 05-06-15 01-05-15 06-05-15 02-05-15 02-05-15 05-06-15 05-06-15 28-11-15 23-04-15 16-07-15 26-08-15 17-06-15 05-06-15 19-04-15 19-04-15 22-01-16 22-01-16 22-01-16 22-01-16 22-01-16 22-12-15 22-07-15 22-07-15 22-07-15 22-07-15 20-10-15 22-01-16 Last Date of Calibration Due Date of Calibration Remarks Lab at Km 94+300 SI. No. 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 Name of Equipment / Instrument Thermostatic Controlled Oven ( 0 to 300o Capacity) Big Thermostatic Controlled Oven ( 0 to 300o Capacity) Medium Digital Water Bath, Capacity-50 Liter Digital Water Bath, Capacity-25 Liter Electronic balance (60 kg ) 5 gm accuracy Electronic balance (30 kg ) 1 gm accuracy Electronic balance (5 kg) 0.1 gm accuracy Electronic balance (600 gm ) 0.01 gm accuracy Digital Thermometer, (-40 to +300°C) Rapid Moisture Meter - 01 Rapid Moisture Meter - 03 IS Sieves (450,300 & 200 mm Dia) Casagrande Liquid limit testing device Cone penetro meter CBR Testing Machine Proctor mould & rammer(small & big) Sand Pouring Cylinders with complete set (100mm dia)-1 Sand Pouring Cylinders with complete set (100mm dia)-2 Sand Pouring Cylinders with complete set (200mm dia)-1 Sand Pouring Cylinders with complete set (200mm dia)-2 CBR moulds Surcharge weight (2.5 Kg) Perforated plates Aluminum containers Proving Ring (50 KN) Proving Ring (30 KN) Aggregate Impact Value Test Apparatus Flakiness & Elongation Gauge Concrete Cube moulds ( 150x150x150)mm Slump cone with rod Ductility Test apparatus (Complete Set) Ring & ball apparatus electrically operated Bitumen Penetro meter Saybolt Visco meter Tar Visco meter Cannonmanning U tube visco meter (13mm u Tube) Modified Marshall Rammers Modified Marshall Moulds Standard Marshall Rammers Standard Marshall Moulds Standard Measurement Cylinders (3,15&30 Lt capacity) Thin Film Oven Quantity 2 1 1 1 1 2 1 1 5 1 1 24 1 1 1 7 1 1 1 1 54 69 32 126 1 1 1 2 45 2 1 1 1 1 1 1 3 15 5 18 3 1 Remarks Lab at Km 115+500 SI. No. Name of Equipment / Instrument M/s. SAI MAATARINI TOLLWAYS LIMITED Quantity Remarks Page 104 SAI MAATARINI TOLLWAYS LIMITED Four Laning of Panikoili – Rimuli Road Section of NH-215 from Km 0+000 – 163+000 in the state of Odisha under NHDP Phase-III as BOT (Toll) Basis. Monthly Progress Report : March -2015 [ SI. No. 1 Name of Equipment / Instrument Thermostatic Controlled Oven ( 0 to 300o Capacity) Big 300o Capacity) Medium 1 Last Date of Calibration 23-02-15 Due Date of Calibration 23-02-16 Quantity 2 Thermostatic Controlled Oven ( 0 to 1 21-12-14 21-12-15 3 Digital Water Bath, Capacity-50 Liter 1 28-09-14 25-09-15 4 Electronic balance (30 kg ) 2 13-11-14 13-11-15 5 Electronic balance (75 kg ) 1 17-11-14 17-11-15 6 Electronic balance (20 kg ) 1 14-11-14 14-11-15 7 Electronic balance (5 kg) 2 14-11-14 13-11-15 8 Electronic balance (200 kg) 1 17-11-14 16-11-15 9 Electronic balance (600 gm ) 1 14-11-14 14-11-15 10 Digital Thermometer, Accuracy-1°C 2 22-10-14 22-10-15 11 IS SIEVES (450,300 & 200 MM Dia) 1 Set 23-02-15 23-02-16 12 CBR Testing Machine 1 24-12-14 23-12-15 13 Proctor mould & rammer(small & big) 3 19-12-14 19-06-15 14 Sand Pouring Cylinders with complete set (200mm dia) 2 26-11-14 25-05-15 15 CBR moulds 18 19-12-14 19-06-15 16 Surcharge weight (2.5 Kg) 16 19-12-14 19-06-15 17 Perforated plates 16 20-12-14 20-05-15 18 Aluminum containers 226 19-12-14 19-06-15 19 Proving Ring (50 KN) 1 11-09-14 11-09-15 20 Vicat Needle Apparatus ( with dash pot) 1 23-02-15 23-08-15 21 Cement Mortar Cube Moulds (7.06x7.06x7.06 cm) 9 23-02-15 23-08-15 22 Aggregate Impact Value Test Apparatus 1 17-12-14 17-05-15 23 Flakiness & Elongation Gauge 1 23-02-15 23-08-15 24 Concrete Cube moulds ( 150x150x150)mm 95 23-02-15 23-08-15 25 Slump cone with rod 10 23-02-15 23-08-15 26 Cement mortar cube vibrating machine 1 21-11-14 20-05-15 27 Soundness apparatus 1 11-12-14 11-12-15 28 Ductility Test apparatus (Complete Set) 1 25-09-14 24-09-15 29 Ring & ball apparatus electrically operated 1 25-12-14 25-12-15 30 Bitumen Penetro meter 1 27-09-14 26-09-15 31 Modified Marshall Rammers 2 17-12-14 17-06-15 32 Modified Marshall Moulds 15 17-12-14 17-06-15 33 Standard Marshall Rammers 2 20-11-14 20-05-15 34 Standard Marshall Moulds 21 20-11-14 20-05-15 M/s. SAI MAATARINI TOLLWAYS LIMITED Remarks Page 105 SAI MAATARINI TOLLWAYS LIMITED Four Laning of Panikoili – Rimuli Road Section of NH-215 from Km 0+000 – 163+000 in the state of Odisha under NHDP Phase-III as BOT (Toll) Basis. Monthly Progress Report : March -2015 [ 23. Appendix 5 - Calibration Status of Plants Sl. No. Description of Equipment / Instrument MAKE / BRAND Last Date of Calibration Calibration Frequency Due Date of Calibration Apollo 200TPH 05-03-15 3 Months 04-06-15 Schwing Stetter, CP30 06-12-14 3 Months 05-03-15 1 WMM Plant @ 17+860 LHS 2 Concrete Batch mix Plant @ 18+500 LHS 3 Hot Mix Plant @ Km 32+300 LHS Apollo ANP 200 05-01-15 3 Months 04-04-15 4 Hot Mix Plant @ Km 55+400 Sepco 160TPH 08-01-15 3 Months 07-04-15 5 Concrete Batch mix Plant @ 55+400 LHS Schwing Stetter, CP60 30-12-14 3 Months 29-03-15 6 WMM Plant @ 55+400 LHS Maxmech 200TPH 30-12-14 6 Months 29-03-15 7 Concrete Batch mix Plant @ 93+600 LHS Schwing Stetter, CP30 29-12-14 3 Months 28-03-15 8 WMM Plant @ Km 93+600 Apollo 250TPH 02-03-15 6 Months 01-06-15 9 Hot Mix Plant @ Km 93+600 Apollo 160TPH 05-01-15 3 Months 04-04-15 10 WMM Plant @ Km 115+200 Apollo 200TPH 08-02-15 3 Months 08-05-15 10 Concrete Batch mix Plant @Km 115+000 Schwing Stetter (Delta) 01-03-15 3 Months 01-06-15 11 Hot Mix Plant @ Km 116+280 Apollo 200TPH 25-03-15 3 Months 25-06-15 12 WMM Plant @ Km 133+200 Condequip-200TPH 08-03-15 3 Months 08-06-15 13 Concrete Batch mix Plant @ Km 151+000 Schwing Stetter (Delta) 15-01-15 3 Months 16-04-15 M/s. SAI MAATARINI TOLLWAYS LIMITED REMARKS Page 106 SAI MAATARINI TOLLWAYS LIMITED Four Laning of Panikoili – Rimuli Road Section of NH-215 from Km 0+000 – 163+000 in the state of Odisha under NHDP Phase-III as BOT (Toll) Basis. Monthly Progress Report : March -2015 [ 24. Appendix 5 - Weather Report Section-I (Km.19+000) DD-MM-YY Section-I (Km.55+000) Min Temp (˚C) Max Temp (˚C) Average Rainfall 26-Feb-14 22.50 27-Feb-14 Section-I (Km.94+000) Max Temp (˚C) Average Rainfall (in mm) Min Temp (˚C) Min Temp (˚C) Max Temp (˚C) Average Rainfall 30.20 - 25.10 28.70 30.90 20.40 - 22.50 31.10 - 25.40 29.40 31.40 21.00 - 28-Feb-14 23.50 33.40 - 25.80 30.00 30.80 20.40 - 1-Mar-14 25.00 33.10 - 25.40 30.40 30.20 19.90 - 2-Mar-14 24.40 32.30 - 25.80 29.20 29.70 22.60 - - 21.40 35.30 12.00 25.70 30.00 30.80 22.40 7.00 29.60 - 24.20 31.30 - 25.10 29.10 31.40 21.60 - 25.20 30.00 - 24.30 32.50 - 24.80 29.50 30.80 21.90 - 6-Mar-14 25.00 28.90 - 26.70 34.20 - 24.10 28.80 28.90 20.20 - 7-Mar-14 25.00 28.90 - 23.90 35.10 - 23.90 28.80 29.40 22.60 - 8-Mar-14 25.40 29.90 - 25.40 36.90 - 24.50 27.00 30.10 18.90 - 9-Mar-14 26.30 29.90 - 21.40 34.50 - 25.40 30.10 31.20 23.50 - 10-Mar-14 26.80 30.20 - 24.50 35.50 - 26.50 31.10 32.20 22.80 - 11-Mar-14 26.60 30.20 - 24.60 34.70 - 26.50 31.00 32.20 22.60 - 12-Mar-14 26.50 30.30 - 23.60 35.40 - 26.50 31.20 32.20 21.60 - 13-Mar-14 27.30 30.30 - 26.10 35.00 - 26.80 31.60 31.80 20.40 - 14-Mar-14 27.40 30.50 - 25.70 35.40 - 26.80 31.80 32.00 21.20 - 15-Mar-14 27.50 31.90 - 26.10 35.50 - 27.20 31.80 32.40 22.20 - 16-Mar-14 26.80 30.30 - 25.10 36.50 - 27.20 31.30 32.90 23.00 - 17-Mar-14 25.00 32.20 - 26.70 35.00 - 27.80 31.60 33.30 24.40 - 18-Mar-14 26.80 31.20 - 25.50 35.10 - 27.30 31.50 32.50 23.50 - 19-Mar-14 27.00 30.50 - 25.20 34.70 - 27.10 31.70 32.50 22.60 - 20-Mar-14 27.30 31.90 - 25.10 32.60 - 26.60 31.30 32.20 22.10 - 21-Mar-14 27.50 31.90 - 26.10 35.40 - 27.00 31.80 31.90 22.00 - 22-Mar-14 27.50 31.90 - 25.10 35.70 - 27.50 32.30 32.20 22.60 - 23-Mar-14 28.30 32.10 - 26.20 36.10 - 28.20 33.00 33.60 24.00 - 24-Mar-14 28.90 31.90 - 27.30 28.80 - 29.80 33.80 34.90 25.10 - 25-Mar-14 28.50 31.80 - 28.20 36.80 - 28.20 33.40 34.70 24.60 1.00 (in mm) Min Temp (˚C) Max Temp (˚C) 28.70 - 25.10 25.40 29.40 - - 25.80 30.00 29.80 - 23.10 26.40 33.10 - 3-Mar-14 26.70 30.20 4-Mar-14 25.80 5-Mar-14 M/s. SAI MAATARINI TOLLWAYS LIMITED Average Rainfall Section- II (Km.115) (in mm) 5.00 4.00 (in mm) Page 107 SAI MAATARINI TOLLWAYS LIMITED Four Laning of Panikoili – Rimuli Road Section of NH-215 from Km 0+000 – 163+000 in the state of Odisha under NHDP Phase-III as BOT (Toll) Basis. Monthly Progress Report : March -2015 [ 25. Appendix 6 – Photographs DBM top completed Km 17+60 BS DBM top completed at Km 18+000 RHS M/s. SAI MAATARINI TOLLWAYS LIMITED Page 108 SAI MAATARINI TOLLWAYS LIMITED Four Laning of Panikoili – Rimuli Road Section of NH-215 from Km 0+000 – 163+000 in the state of Odisha under NHDP Phase-III as BOT (Toll) Basis. Monthly Progress Report : March -2015 [ DBM top completed at Km 58+300 RHS DBM top completed from Km113+500 to Km114+500 BS M/s. SAI MAATARINI TOLLWAYS LIMITED Page 109 SAI MAATARINI TOLLWAYS LIMITED Four Laning of Panikoili – Rimuli Road Section of NH-215 from Km 0+000 – 163+000 in the state of Odisha under NHDP Phase-III as BOT (Toll) Basis. Monthly Progress Report : March -2015 [ DBM top completed from Km121+100 to Km122+650 BS DBM top completed from Km 129+480 to Km 129+900 RHS DBM top completed from Km133+375 To Km133+940 LHS M/s. SAI MAATARINI TOLLWAYS LIMITED Page 110 SAI MAATARINI TOLLWAYS LIMITED Four Laning of Panikoili – Rimuli Road Section of NH-215 from Km 0+000 – 163+000 in the state of Odisha under NHDP Phase-III as BOT (Toll) Basis. Monthly Progress Report : March -2015 [ WMM in progress at Km 79+640 RHS and at Km 138+500 GSB top in progress at Km 37+950 LHS and at Km 127+700 (Hard rock area) Earthwork in progress at Km40+300 RHS and at Km153+000 BS M/s. SAI MAATARINI TOLLWAYS LIMITED Page 111 SAI MAATARINI TOLLWAYS LIMITED Four Laning of Panikoili – Rimuli Road Section of NH-215 from Km 0+000 – 163+000 in the state of Odisha under NHDP Phase-III as BOT (Toll) Basis. Monthly Progress Report : March -2015 [ Work in Progress MNB at Km 44+400 and Major Bridge at Km 56+803 (RHS) Major Bridge progress at Km 83+568 (RHS) Flyover Girder Casting @ Ch 125+284 M/s. SAI MAATARINI TOLLWAYS LIMITED Page 112 SAI MAATARINI TOLLWAYS LIMITED Four Laning of Panikoili – Rimuli Road Section of NH-215 from Km 0+000 – 163+000 in the state of Odisha under NHDP Phase-III as BOT (Toll) Basis. Monthly Progress Report : March -2015 [ Work in progress ROB @ Ch 116+636 and Major Bridge @ Ch 139+485 Girder casting in progress at Ch.151+200 (Major Bridge) Work in progress Minor Bridge at ch 116+163 9. M/s. SAI MAATARINI TOLLWAYS LIMITED Page 113 SAI MAATARINI TOLLWAYS LIMITED Four Laning of Panikoili – Rimuli Road Section of NH-215 from Km 0+000 – 163+000 in the state of Odisha under NHDP Phase-III as BOT (Toll) Basis. Monthly Progress Report : March -2015 [ Work in progress Minor Bridge at ch 163+037 Safety barricading near VUP at ch @ 115+118 Diversion M/s. SAI MAATARINI TOLLWAYS LIMITED Page 114