Project Costs for Proposed PFC Projects Updated March 18, 2014 In

advertisement
Project Costs for Proposed PFC Projects
Updated March 18, 2014
In accordance with Federal Aviation Regulation Part 158 Passenger Facility Charges, section
158.24, the New Orleans Aviation Board hereby provides notification of its intent to propose a
new Passenger Facilities Charge (PFC) Application at the Louis Armstrong New Orleans
International Airport.
PFC Application 14-11-C-00-MSY
PFC No. 81 - Airfield Pavement Condition Study (reimbursement)
Description: This project will reimburse the sponsor to eligible costs in the field investigation and
preparation of a Pavement Condition Index study that characterizes the condition of relevant paved
section of airfield including runways, taxiways, taxi lanes and apron facilitating aircraft operations
at Louis Armstrong New Orleans International Airport (LANOIA). This study will investigate
and report on degradation in airfield surfaces on the LANOIA campus and make recommendations
for phased master plan to preserve and enhance the airfield pavement.
Justification: This project is needed to preserve and enhance airfield safety. Degraded paved
surfaces can allow for storm water ponding and produce foreign object debris (FOD), which can
damage aircraft and impede efficient surface movement of aircraft.
PFC Level: $3.00
Total PFC Revenue: $127,000
PFC No. 82 - Long Term Planning Study (reimbursement)
Description: This project is to reimburse the sponsor for eligible costs incurred while formulating
a long-term strategic plan for airport development at LANOIA. This airport development study is
a continuation of previous planning efforts to establish a strategically sound program of
development for future investment in the existing campus. The New Orleans Aviation Board
(NOAB) engaged consultant services to perform an “in-depth and robust analysis of the options
for a new airport terminal facility.” This analysis followed on the 2007 Strategic Development
Plan and the 2012 Strategic Development Plan Phase 2 Action Update, focusing weighing multiple
options for developing appropriate and economically viable terminal facilities. The analysis
performed with this project focused on design concepts, costs and environmental impacts.
Justification: This project is needed to address issues revealed in the 2007 Strategic Development
Plan (PFC Project Number – 04-07-C-04-MSY-001), namely the need to craft a long-term
development alternative to address capacity and development needs. The NOAB believes that a
responsive plan will create significant improvements to airport security, increasing competition
among air carriers and reducing anticipated congestion.
PFC Level: $3.00
Total PFC Revenue: $4,801,500
PFC No. 83 - Airfield Electrical
Description: This project is necessary for the design and construction of replacement equipment
enabling the airfield electrical systems serving LANOIA. The FAA has awarded an Airport
Improvement Program (AIP) grant to support a portion of this work; the New Orleans Aviation
Board intends to fund local matching funds with PFC funds and also fund eligible costs if FAA
participation does not fully fund the eligible costs.
Justification: This project will significantly improve air safety by replacing obsolete and failureprone electrical equipment. Several outages have incurred which have interfered with normal
operations at LANOIA.
PFC Level: $4.50
Total PFC Revenue: $6,851,561
PFC No. 84 - Landuse and Development Study (reimbursement)
Description: This project will fund reimbursement of the sponsor for eligible costs associated with
development of a comprehensive land use plan to guide development at LANOIA. This study
reviews existing conditions, identifies potential economic development opportunities and proposes
a series of action steps to realize the identified opportunities. This study is focused on improving
and diversifying Non-Airline Revenue income to the airport so as to reduce carrier costs to operate
at LANOIA and improve competition and air service.
Justification: This project is needed to address issues revealed in the 2007 Strategic Development
Plan (PFC Project Number – 04-07-C-04-MSY-001), namely the need to craft a long-term
development alternative to address capacity and development needs. The NOAB believes that
implementation of a responsive plan will create significant improvements to airport security,
increasing competition among air carriers and reducing anticipated congestion. A land use
development plan will allow the NOAB to focus development efforts on land uses that harmonize
non-aviation and aviation-related development while maximizing non-airline revenue, preserving
and enhancing opportunities for air carrier competition.
PFC Level: $3.00
Total PFC Revenue: $1,000,000
PFC No. 85 - Long Term Development Feasibility Study (reimbursement)
Description: This project will fund reimbursement of the sponsor for eligible costs associated with
studying the feasibility of long term development alternatives at LANOIA. This study evaluates
the financial viability strategic alternatives for airport development of terminal facilities at the
existing airfield campus. This study applies common quantifiable metrics including capital costs,
financing costs, operating and maintenance costs as well as projected revenue streams to establish
a preferred alternative. The analysis examines all reasonable financial factors operative in
selecting a preferred alternative, ranks various common metrics among alternatives, creates a
financial model to assess each alternative’s feasibility, develops benefit/cost analysis for each
development alternative, and presents and affirmatively reports a finding and a preferred
alternative recommendation.
Justification: This project will complement the other planning efforts to support LANOIA’s
strategic development planning process. The 2007 Strategic Development Plan (the SDP - a
master plan document) identified potential alternative for future development and recommended a
common program of needed stabilizing capital projects, all appropriate and useful to any of the
identified development alternatives. The SDP further recommended re-evaluation of alternatives
at a point where activity at the airport had stabilized following the impacts of Hurricane Katrina’s
aftermath in 2005. The SDP recommended 2012 as an appropriate year for that update. LANOIA
acted in 2012 to produce a Phase 2 Action Update, revalidating the work of the 2007 SDP and
identifying a preferred alternative, the Northside option, as the optimum long-term terminal
development solution.
In order to fully evaluate and justify this development alternative to stakeholders, LANOIA
requires objective analysis of the financial viability of the preferred alternative with regard to its
ability to satisfy physical and financial goals established by the Board. Essentially, the NOAB
considers reduction of cost per enplaned passenger with little or no reduction in level of service
during peak demand periods key to preserving and enhancing opportunities for competition among
carriers and associated opportunities for increased service capacity. LANOIA believes this project
is a key element to implementing this necessary program of improvements.
PFC Level: $3.00
Total PFC Revenue: $750,000
PFC No. 86 - Perimeter Fencing Replacement (reimbursement)
Description: This project will reimburse the sponsor for eligible costs incurred to replace nine
mile of perimeter fence and forty-five gates securing the airport’s Air Operations Area.
Deficiencies in the height of the existing fence and gaps allowing wildlife infiltration onto the air
field have impacted safety and required remediation.
Justification: LANOIA produced a Hazardous Wildlife Report which established hazardous
conditions caused by wildlife infiltration onto the airfield. This project is believed to significantly
contribute to safety by correcting degraded sections of fence and preventing wildlife infiltration
onto the active air field.
PFC Level: $4.50
Total PFC Revenue: $492,893
PFC No. 87 - Access Road Improvements (reimbursement)
Description: This project will reimburse the sponsor for eligible costs associated with resurfacing
a combined use (50% airport traffic/50% non-airport traffic) access road connecting the LANOIA
terminal facilities with Interstate 10.
Justification: Sections of pavement and asphalt covering, particularly on the dedicated access
section of the access road were found to be degraded and in need of rehabilitation. This project is
believed to preserve and enhance capacity to access passenger facilities at the LANOIA terminal.
PFC Level: $3.00
Total PFC Revenue: $550,000
PFC No. 88 - Airfield Pavement Rehabilitation
Description: To understand and proactively address the needs of its airfield, LANOIA completed
a Pavement Condition Index Study, which evaluated the current state of the paved airfield surfaces
including runways, taxiways, and apron. The resultant recommendations prioritized needed work
to rehabilitate targeted sections of pavement from most in need of rehabilitation to least in need of
rehabilitation at this time.
Justification: Significant Foreign Object Debris (FOD) has been found in certain degraded
sections of the LANOIA airfield. Ad-hoc repairs have been made to address critical damage. The
NOAB has completed a Pavement Condition Index Study that recommended a prioritized program
of rehabilitation for degraded sections of airfield pavement.
PFC Level: $4.50
Total PFC Revenue: $1,403,479
PFC No. 89 - Airfield Lighting Vault
Description: This project is intended to replace an existing airfield lighting control vault located
in the footprint of future terminal development. The airfield vault will serve as the repository for
dedicated lighting switchgear and other equipment supporting airfield lights.
Justification: This project will preserve and enhance air safety by relocating an essential airfield
equipment station, necessary for safe operation of the airfield. It is believed to be eligible as
discussed in FAA Order 5100.38C, Section 515. LANOIA commissioned a compressive study of
future alternative development scenarios to validate and refine the analysis from the 2007
LANOIA Strategic development Plan. This planning effort encompassed physical, conceptual
planning for long-term passenger and aircraft needs as well as land use and financial feasibility.
The resultant preferred alternative recommends development where the existent airfield lighting
vault is situated; the resultant conflict can be resolved by relocating the existent vault.
PFC Level: $3.00
Total PFC Revenue: $1,116,667
PFC No. 90 - Drainage Pumping Station
Description: This project will fund the design and construction of drainage infrastructure to
mitigate approximately 300 cubic feet per second (cfs) of storm water runoff attributable to
development at LANOIA between 1992 and 2013. A technical report studying this issue
concluded that a pumping station capable of evacuating approximately 300 cfs would properly
mitigate the evaluated impact of impermeable surface improvements accumulated over the period.
Justification: This project will make a significant contribution to air safety by mitigating the
impact of storm events on airport operations. It is believed to be eligible as discussed in FAA
Order 5100.38C, Section 515. The project will mitigate the impact of storm water runoff generated
at LANOIA yet evacuated by the surrounding and inter-connected community of Kenner,
Louisiana.
PFC Level: $3.00
Total PFC Revenue: $1,666,667
PFC No. 91 - Long Term Development Program – Terminal Design
Description: As part of the NOAB’s ongoing commitment to lower operating costs, right-size
the terminal and provide a world class terminal, new terminal facilities are being developed on the
north side of the airport property. This project requests funding for development of the terminal,
including design and construction costs. The terminal is being implemented as a result of a
comprehensive planning process to create a long term infrastructure alternative that provides for
physical infrastructure that adequately serves demand needs while also allowing for more efficient
and secure passenger facilities that reduce costs and foster opportunities for increased competition.
Justification: LANOIA has determined that significant investments will be required to maintain
the existing passenger terminal, which has exceeded its useful life. Additionally, retrofitting the
existing terminal to modern standards, particularly with regard to the inspection and screening of
passengers and checked baggage has been found to be prohibitively expensive. Analysis of
development alternatives has indicated that it is beneficial to develop new modern terminal
facilities on a green field site, which will allow for efficient use of necessary passenger facilities,
proper and timely screening of passengers and checked bags during peak demand periods, and
lower operating costs via more efficient and modern facilities. LANOIA believes this program
will make a significant contribution to security, improvement of opportunities for competition, and
improve capacity during demand periods by implementing a modern terminal facility with
properly-sized passenger areas and security functions.
PFC Level: $4.50
Total PFC Revenue: $400,776,186
PFC No. 92 - Long Term Development Program – Airside
Description: As part of the NOAB’s ongoing commitment to lower operating costs, right-size the
terminal and provide a world class terminal, new terminal facilities are being developed on the
north side of the airport property. This project requests funding for development of adequate
terminal apron and taxiways, including design and construction costs. The terminal is being
implemented as a result of a comprehensive planning process to create a long term infrastructure
alternative that provides for physical infrastructure that adequately serves demand needs while also
allowing for more efficient and secure passenger facilities that reduce costs and foster
opportunities for increased competition. The associated apron and taxiways are a critical element
to the program and needed for effective operation of the facilities.
Justification: LANOIA has determined that significant investments will be required to maintain
the existing passenger terminal, which has exceeded its useful life. Additionally, retrofitting the
existing terminal to modern standards, particularly with regard to the inspection and screening of
passengers and checked baggage has been found to be prohibitively expensive. Analysis of
development alternatives has indicated that it is beneficial to develop new modern terminal
facilities on a green field site, which will allow for efficient use of necessary passenger facilities,
proper and timely screening of passengers and checked bags during peak demand periods, and
lower operating costs via more efficient and modern facilities. LANOIA believes this program
will make a significant contribution to security, improvement of opportunities for competition, and
improve capacity during demand periods by implementing a modern terminal facility with
properly-sized passenger areas and security functions.
PFC Level: $4.50
Total PFC Revenue: $40,199,279
PFC No. 93 - Long Term Development Program – Landside Terminal Design
Description: As part of the NOAB’s ongoing commitment to lower operating costs, right-size the
terminal and provide a world class terminal, new terminal facilities are being developed on the
north side of the airport property. This project requests funding for development of eligible
landside terminal support amenities, such as eligible circulation roads, including design and
construction costs. The terminal is being implemented as a result of a comprehensive planning
process to create a long term infrastructure alternative that provides for physical infrastructure that
adequately serves demand needs while also allowing for more efficient and secure passenger
facilities that reduce costs and foster opportunities for increased competition.
Justification: LANOIA has determined that significant investments will be required to maintain
the existing passenger terminal, which has exceeded its useful life. Additionally, retrofitting the
existing terminal to modern standards, particularly with regard to the inspection and screening of
passengers and checked baggage has been found to be prohibitively expensive. Analysis of
development alternatives has indicated that it is beneficial to develop new modern terminal
facilities on a green field site, which will allow for efficient use of necessary passenger facilities,
proper and timely screening of passengers and checked bags during peak demand periods, and
lower operating costs via more efficient and modern facilities. LANOIA believes this program
will make a significant contribution to security, improvement of opportunities for competition, and
improve capacity during demand periods by implementing a modern terminal facility with
properly-sized passenger areas and security functions.
PFC Level: $4.50
Total PFC Revenue: $17,757,137
Charge Effective Date: August 1, 2003
Estimated Charge Expiration Date: August 1, 2046
Total PFC Revenue to be collected for this application: $477,492,367
Overall PFC Collection Level: $4.50
Louis Armstrong New Orleans International Airport will be receiving public comments. Please
direct comments to Mr. Raymond Anderson before 3:00 pm on Friday, April 18th, 2014.
Mr. Raymond D. Anderson
Deputy Director and Chief Financial Officer
New Orleans Aviation Board
P.O. Box 20007
New Orleans, LA 70141
Download