EDMS Document No. LIU EVM REPORT July 2014 Abstract This is the second EVM report for the LIU project, referred to an extraction of the data made on the 02nd of July 2014. DRAFT 2 Prepared by: Checked by: J. Bobes R. Garoby B. Daudin M. Meddahi Distribution list: Approved by: LIU EVM Report Page 2 of 15 1. EXECUTIVE SUMMARY 3 2. GENERAL OVERVIEW 4 3. LIU MNG (MANAGEMENT) 6 4. LIU PSB 7 5. LIU PS 8 6. LIU SPS 9 ANNEX 1: ABBREVIATIONS AND GENERAL EVM REMARK 10 ANNEX 2: PROGRESS REPORTING 11 LIU-PSB 11 LIU-PS 11 LIU-SPS 11 ANNEX 3: DELIVERABLES TRACKING 12 LIU-PSB 12 LIU-PS 14 LIU-SPS 15 LIU EVM Report Page 3 of 15 1. EXECUTIVE SUMMARY Add Executive summary R. Garoby, Project Leader LIU EVM Report Page 4 of 15 2. GENERAL OVERVIEW The general EVM structure of LIU project is made of 4 sub-projects: Code Description Project Leader Baseline LIU-MNG LIU project management R. Garoby - LIU-PSB PSB Upgrade project K. Hanke Baseline 3.1 May 2014 LIU-PS PS upgrade S. Gilardoni Baseline 2 Feb-2014 LIU-SPS SPS Upgrade B. Goddard Baseline 1 Mar-2014 LIU EVM Report Page 5 of 15 Schedule Variance Comment the project performance in terms of Schedule. Cost Variance Comment the project performance in terms of Cost. LIU EVM Report Page 6 of 15 3. LIU MNG (MANAGEMENT) The LIU MNG project represents the work related to management activities. It has been decided by the project management team to include into this project the expenses derived from the MtoP budget. Include the history of the workunits related to this part. Data not yet ready on the 02nd of July 2014. The image below will be replaced by a proper table. LIU EVM Report Page 7 of 15 4. LIU PSB The current active baseline is “Baseline 3.1”, and it was defined on the 08th of May 2014. LIU EVM Report Page 8 of 15 5. LIU PS The current active baseline “Baseline 2” was defined on the 17th of February 2014. LIU EVM Report Page 9 of 15 6. LIU SPS The current active baseline “Baseline 1” was defined on the 01st of March 2014. LIU EVM Report Page 10 of 15 ANNEX 1: ABBREVIATIONS AND GENERAL EVM REMARK ABBREVIATIONS WP Workpackage WU Workunit LOE Level of Effort EV PV AC Earned Value Planned Value Actual Cost SV CV Schedule Variance Cost Variance SPI CPI Schedule Performance Index Cost Performance Index GENERAL REMARK ON EVM Modelling of PV in the EVM system is linear over the period indicated while progress is strongly linked to visible results which in contracts are showing up only after a start-up phase immediately leading to a latency period with a SV of up to few months. For several reasons also a CV of few months is found: payments are frequently executed only at the end of the WU period, and payments are frequently delayed with respect to delivery and actual acceptance. In this case a positive CV is reported. In some cases materials are purchased with a high expenditure but the actual progress is accounted in the assembly stage and the CV should normalize towards the end of the task. Similarly when reporting is done in full completed units, a variation with respect to linear profiles may appear. In these cases a negative CV is reported. LIU EVM Report Page 11 of 15 ANNEX 2: PROGRESS REPORTING Workunits for which progress reporting has not been done after the month of June. LIU-PSB Workunit Holder WBS Plan Start Plan Finish Last Report 130418 - Transport and Handling C. Bertone (EN-HE-HH) LIU-PSB 23.2.6 01-Jan-2014 31-Dec-2016 - 130428 - Screen+Camera System S. Burger (BE-BI-PM) LIU-PSB 23.7.2 01-Jan-2014 30-Nov-2015 - 130881 - CCI J. Sanchez Quesada (BE-RF-FB) LIU-PSB 4.2 01-Jan-2014 31-Dec-2014 - LIU-PS Workunit Holder WBS Plan Start Plan Finish Last Report 92261 - handling and transport personnel for PS LIU C. Bertone (EN-HE-HH) 92274 - handling studies for PS-LIU C. Bertone (EN-HE-HH) LIU-PS 14.2 01-Jan-2013 31-Dec-2019 10-Mar-2014 LIU-PS 14.2 01-Jan-2013 31-Dec-2019 10-Mar-2014 92278 - handling and transport consumables for PS LIU C. Bertone (EN-HE-HH) LIU-PS 14.2 01-Jan-2013 31-Dec-2019 10-Mar-2014 104207 - PS kicker cavity M. Paoluzzi (BE-RF-IS) LIU-PS 4.2 01-Nov-2012 31-Dec-2016 05-May-2014 104155 - Digital longitudinal coupledbunch feedback H. Damerau (BE-RF-FB) LIU-PS 4.1 30-Jun-2012 30-Jun-2015 26-May-2014 104153 - Install 1-turn feedback systems H. Damerau (BE-RF-FB) LIU-PS 4.1 01-Jan-2012 31-Dec-2015 26-May-2014 LIU-SPS No late reports LIU EVM Report Page 12 of 15 ANNEX 3: DELIVERABLES TRACKING List of the deliverables according to their current states and compare with the baseline. LIU-PSB Late Deliverables (compared to the baseline) More than 3 months LIU-PSB 13 98401 : HVAC for new building Power converter (M. Obrecht Preliminary studies (50%) LIU-PSB 3 112579 : BI Bending (V) magnet (A. Newborough Contract signature (90%) LIU-PSB 4.1 95641 : C02 consolidation study (M. Paoluzzi Tuning power supply studies (5%) LIU-PSB 4.1 95643 : C16 consolidation study (M. Paoluzzi Tuning power supply studies (5%) LIU-PSB 4.3 93319 : 800 W Power amplifier (R. Louwerse Version 2 PCB design (0%) LIU-PSB 4.3 93322 : Control of power equipment (L. Arnaudon Commisionning (80%) LIU-PSB 4.3 93322 : Control of power equipment (L. Arnaudon Write FESA class for PLC (0%) LIU-PSB 5.1 126816 : Booster Injection Corrector Powering (D. Nisbet BI.DHZ.DVT 50/70 Design baseline confirmed and refined (0%) LIU-PSB 5.1 91565 : Booster Injection Septa converters development & procurement (J. Cravero Installation & Commissioning LS1 (0%) LIU-PSB 5.1 91566 : Booster Injection Stripping Foil Chicane converters development & procurement (D. Aguglia Write workpackage description (0%) LIU-PSB 5.1 91568 : Booster Injection Control Electronics (B. Todd PSB Megadiscap FGC3 electronics, chassis and PSU (0%) LIU-PSB 6 113278 : BWS upgrade (B. Dehning drawing office CERN (0%) LIU-PSB 9.2 92155 : Provide BI.SMV magnets (M. Hourican mechanical drawings tank modification (0%) 3 months and less LIU-PSB 17 92068 : BIC Preparation (B. Puccio LAB tests performed (0%) LIU-PSB 2.1 91528 : Performance at low energy (SpaceCharge) (E. Benedetto Analysis and benchmark with 2012-2013 measurements finished (90%) LIU-PSB 2.1 91528 : Performance at low energy (SpaceCharge) (E. Benedetto Curve Emittance vs. Intensity with H- from Linac4 simulated (20%) LIU-PSB 2.1 91529 : Beam Stability (E. Benedetto PSB impedance/wakefields implemented in HEADTAIL and benchmarked (10%) LIU-PSB 23.4 130459 : Dumps (C. Maglioni integration studies (5%) LIU-PSB 23.4 130459 : Dumps (C. Maglioni shielding studies (RP) (5%) LIU-PSB 23.6 130461 : Powerconverters and Transformers for BSW (D. Aguglia Write WU description (0%) LIU-PSB 4.2 95666 : Rf Interlock interface (2 boards) (A. Blas HW test of version 1 (0%) LIU-PSB 4.2 95667 : Motherboard + RTM + firmware (J. Molendijk Version 3 series production (10%) LIU-PSB 4.2 95668 : VXS switch + firmware (J. Molendijk Acceptance tests series (12U) (10%) LIU-PSB 4.2 95668 : VXS switch + firmware (J. Molendijk Cabling series (12U) (0%) LIU-PSB 4.2 95668 : VXS switch + firmware (J. Molendijk PCB version 2 fabrication (12U) (0%) LIU-PSB 4.2 95671 : Beam tests and commissioning of LLRF system with ferrite cavities (M. Angoletta Ring 1-2-3 systems hardware commissining (80%) LIU-PSB 4.2 95671 : Beam tests and commissioning of LLRF system with ferrite cavities (M. Angoletta Ring 4 LLRF hardware commissining (80%) LIU-PSB 4.2 95671 : Beam tests and commissioning of LLRF system with ferrite cavities (M. Angoletta Software (DSP code) development and tests (95%) LIU-PSB 4.3 93319 : 800 W Power amplifier (R. Louwerse Cabling of prototype version 1 amplifier (x2) (0%) LIU-PSB 4.3 93319 : 800 W Power amplifier (R. Louwerse Test 1 amplifiers in final version (0%) LIU-PSB 5.1 126815 : Booster Injection BI.BVT Powering (D. Nisbet Design baseline confirmed and refined (20%) LIU-PSB 6 91544 : H0/H- population measurement at injection dump (F. Roncarolo Mechanical study (50%) LIU-PSB 7 91905 : Head & Tail dumps (C. Maglioni Material procurement dump & ancillaries (20%) LIU-PSB 9.2 92155 : Provide BI.SMV magnets (M. Hourican laminations accessories (0%) LIU-PSB 9.2 92157 : Provide KSW magnets (L. Ducimetiere ceramic vacuum chambers (33%) LIU-PSB 9.2 92157 : Provide KSW magnets (L. Ducimetiere mechanical drawings (90%) LIU-PSB 9.2 92157 : Provide KSW magnets (L. Ducimetiere misc parts procurement (30%) LIU-PSB 9.2 92161 : Provide controls for kickers magnets and generators (E. Carlier design controls system (50%) LIU EVM Report Page 13 of 15 Upcoming Deliverables This month LIU-PSB 23.2.1 130411 : Design office, Supports, Materials, Subcontracting, Fabrication (B. Riffaud) Design and Layout (30%) LIU-PSB 4.3 93321 : Transverse feedback electronics (A. Blas) 5 LHC rf crates + 10 electronic boards (60%) LIU-PSB 5.2 91570 : Provide Booster MPS (F. Boattini) Specification ready for submission (0%) LIU-PSB 4.2 95666 : Rf Interlock interface (2 boards) (A. Blas) Design version 2 (0%) LIU-PSB 4.2 95666 : Rf Interlock interface (2 boards) (A. Blas) Order components for the series of 2 units (0%) LIU-PSB 5.2 130894 : Civil engineering studies for building 245 (L. LopezHernandez) Preliminary studies finished (0%) LIU-PSB 7 91906 : H0/H- dump (C. Maglioni) Detail drawings available (60%) In 2 months Completed Deliverables In the last month LIU-PSB 10.2 91898 : Upgrade and commission Septum BESMH (J. Borburgh) connections installed (100%) LIU-PSB 11 91890 : CO infrastructure for OP (J. Betz) LS1 signals connected and functioning correctly (100%) LIU-PSB 3 Contract signature (100%) LIU-PSB 4.2 112580 : BI Correctors (A. Newborough) 95669 : Hardware reorganisation in BOR and re-cabling (A. Findlay) 95669 : Hardware reorganisation in BOR and re-cabling (A. Findlay) LIU-PSB 4.3 93321 : Transverse feedback electronics (A. Blas) Installation in the PSB (BAT) (100%) LIU-PSB 5.2 130894 : Civil engineering studies for building 245 (L. LopezHernandez) Procurement procedures for studies completed (100%) LIU-PSB 4.2 Acquire interface modules for inputs & outputs (100%) Installation of coaxial cables (100%) In the last 3 months LIU-PSB 10.2 91898 : Upgrade and commission Septum BESMH (J. Borburgh) parts manuafctured (100%) LIU-PSB 1.5 91875 : Integrate Transfer line LINAC4 -> PSB (Y. Muttoni) Installation drawing provided (preliminary integration) (100%) LIU-PSB 1.5 91875 : Integrate Transfer line LINAC4 -> PSB (Y. Muttoni) Preliminary BI line integration completed (100%) LIU-PSB 4 95665 : Master DDS (J. Sanchez Quesada) Test series production (11 MDDS V2) Serge (100%) LIU-PSB 4.1 92599 : Full wideband cavity studies (M. Paoluzzi) Cabling (100%) LIU-PSB 4.1 92599 : Full wideband cavity studies (M. Paoluzzi) Interlocks (100%) LIU-PSB 4.1 92599 : Full wideband cavity studies (M. Paoluzzi) Power converters (100%) LIU-PSB 4.2 95663 : 4 CH ADC + DDC firmware (J. Sanchez Quesada) Test series production (34 ADC V4) Serge (100%) LIU-PSB 4.2 95664 : 4 CH DAC + SDDS firmware (J. Sanchez Quesada) Test series production (27 DAC V2) Serge (100%) LIU-PSB 4.2 95671 : Beam tests and commissioning of LLRF system with ferrite cavities (M. Angoletta) Specification and studies for data processing, data exchange and control layers (100%) LIU-PSB 4.4 95675 : Controls hardware for LLRF (A. Butterworth) Remaing 4 VXS systems installed in BOR (100%) LIU-PSB 4.4 95676 : Controls software for LLRF (A. Butterworth) Software (FESA + synoptic app) final version (100%) LIU-PSB 4.4 95676 : Controls software for LLRF (A. Butterworth) Software (FESA + synoptic app) for Ring 4 tests (100%) LIU-PSB 4.4 95677 : OASIS intergration for LLRF (A. Butterworth) Analogue and digital signal aquistion and observation systems (100%) LIU-PSB 5.2 130894 : Civil engineering studies for building 245 (L. LopezHernandez) Integration studies completed (100%) LIU-PSB 9.2 92155 : Provide BI.SMV magnets (M. Hourican) Magnet Yoke C Frames (100%) LIU EVM Report Page 14 of 15 LIU-PS Late Deliverables (compared to the baseline) More than 3 months LIU-PS 14.2 92278 : handling and transport consumables for PS LIU (C. Bertone renovation loco PS: travaux de finalisation (0%) LIU-PS 21 104279 : Scopes for RF and revolution train (R. Steerenberg Design & Specification completed (20%) LIU-PS 5 113114 : Manufacture and commission Chromaticity Sextupoles Power Converter (G. Le Godec Power converters installed and commissioned (0%) 3 months and less LIU-PS 21 104279 : Scopes for RF and revolution train (R. Steerenberg Oscilloscopes & periph. delivered (0%) LIU-PS 4.1 104153 : Install 1-turn feedback systems (H. Damerau 1-Turn Feedback 10 MHz installed (80%) LIU-PS 4.2 104205 : High-power RF studies (C. Rossi Study released for improved 10 MHz feedback amplifiers (90%) LIU-PS 4.2 104207 : PS kicker cavity (M. Paoluzzi Kicker cavity system installed in the PS (70%) LIU-PS 4.2 104209 : 80 MHz fast ferrite tuner prototype (C. Rossi Study of a 80 MHz fast tuner completed (85%) LIU-PS 4.3 104227 : 5 kW / 100 MHz Power amplifiers (R. Louwerse Cabling of prototype amplifier (0%) LIU-PS 4.3 104227 : 5 kW / 100 MHz Power amplifiers (R. Louwerse PCB design (0%) LIU-PS 6.6 104287 : Longitudinal Profile (L. Soby BI WCM (0%) Upcoming Deliverables This month 104278 : Procurement, installation and commissioning oscilloscopes for last turn BSM logging (R. Steerenberg) Oscilloscopes & periph. commissioned (0%) LIU-PS 21 104279 : Scopes for RF and revolution train (R. Steerenberg) Oscilloscopes & periph. Installed and commissioned (0%) LIU-PS 4.3 104227 : 5 kW / 100 MHz Power amplifiers (R. Louwerse) Test of prototype (0%) LIU-PS 21 In 2 months Completed Deliverables In the last month LIU-PS 5.2 104258 : Manufacture and commission Low Energy Quadrupoles (QN&QSK) Power Converters (S. Pittet) Prototype validated (100%) LIU-PS 5.3 104264 : Manufacture and commission Low Energy Dipoles (DHZ&DVT) Power Converters (S. Pittet) Prototype validated (100%) LIU-PS 6.6 104287 : Longitudinal Profile (L. Soby) Analog front-end electronics (100%) LIU-PS 6.6 104287 : Longitudinal Profile (L. Soby) CO front-end (100%) LIU-PS 6.6 104287 : Longitudinal Profile (L. Soby) DAQ+AXO crate (100%) In the last 3 months LIU-PS 1.1 104144 : Coordinate LIU-PS project (S. Gilardoni) Detailed objectives for 2014 defined (100%) LIU-PS 15 104244 : Main CE works for the shielding of R.Goward (L. Lopez-Hernandez) Construction works completed (100%) LIU-PS 15 104245 : Works supervision for the shielding of R.Goward (L. Lopez-Hernandez) Works supervision completed (100%) LIU-PS 15 104251 : Minor CE works related to the additional PS shielding (L. Lopez-Hernandez) Minor works completed (100%) LIU-PS 4.3 104229 : PS TFB electronic board (A. Blas) 6 boards fully tested (100%) LIU-PS 5.4 127998 : Manufacture and commission Skew Sextupoles Power Converter (S. Pittet) Power converters installed and commissioned (100%) LIU EVM Report Page 15 of 15 LIU-SPS Late Deliverables (compared to the baseline) More than 3 months None. 3 months and less LIU-SPS 4.3 128693 : VME STDL (feedback loop) (W. Hofle VME STDL (feedback loop) (17%) LIU-SPS 4.3 128694 : Analog signal conditioning (W. Hofle Analog signal conditioning/mixing LHC protons (0%) LIU-SPS 4.3 128694 : Analog signal conditioning (W. Hofle Analog signal conditioning/mixing scrubbing beam (0%) LIU-SPS 4.3 128694 : Analog signal conditioning (W. Hofle PU signal distribution crate BPCR (0%) LIU-SPS 4.3 128696 : Provide PCs and Software for Damper (W. Hofle Computers and consoles in BA2 (0%) LIU-SPS 4.3 128696 : Provide PCs and Software for Damper (W. Hofle Provide Expert Software Interface (0%) LIU-SPS 4.3 128696 : Provide PCs and Software for Damper (W. Hofle Provide FESA Classes for Damper (0%) LIU-SPS 4.3 128697 : Optical fiber links BA2-BA3 (W. Hofle Fiber delays (0%) LIU-SPS 4.3 128698 : Clock generation and distribution for BA3 (W. Hofle Clock distribution in BA3 and BA2 (NIM) (0%) LIU-SPS 4.3 128698 : Clock generation and distribution for BA3 (W. Hofle Provide clocks in BA3 (5%) LIU-SPS 4.3 128698 : Clock generation and distribution for BA3 (W. Hofle VME Clock generation in BA2 (0%) LIU-SPS 4.3 128699 : Infrastructure BA2 (W. Hofle Local Infrastructure (50%) LIU-SPS 4.3 128699 : Infrastructure BA2 (W. Hofle Worksite clean-up (50%) LIU-SPS 4.4 128725 : Slotline kicker manufacturing (W. Hofle Slotline kicker electromagnetic design (20%) LIU-SPS 4.4 128725 : Slotline kicker manufacturing (W. Hofle Slotline kicker fabrication (0%) LIU-SPS 4.4 128725 : Slotline kicker manufacturing (W. Hofle Slotline kicker mechanical design (0%) LIU-SPS 6 128844 : Provide electronics for fast BLMs (C. Zamantzas Electronics design (0%) Upcoming Deliverables This month LIU-SPS 4.3 128696 : Provide PCs and Software for Damper (W. Hofle) Provide Application Software and Displays for CCC (0%) LIU-SPS 4.3 128694 : Analog signal conditioning (W. Hofle) Output Signal Combination Chassis (0%) LIU-SPS 4.3 128699 : Infrastructure BA2 (W. Hofle) Rack cabling local in BA2 (33%) In 2 months Completed Deliverables In the last month LIU-SPS 1.1 128095 : Coordinate LIU-SPS project (B. Goddard) Schedule updated (100%) In the last 3 months LIU-SPS 1.1 128095 : Coordinate LIU-SPS project (B. Goddard) Detailed objectives defined (100%) LIU-SPS 1.1 128095 : Coordinate LIU-SPS project (B. Goddard) WU definitions updated (100%) LIU-SPS 4.3 128690 : 7/8-inch cable for LS1 for BA2 (W. Hofle) 7/8-inch cable pulling (100%) LIU-SPS 4.3 128691 : Provide 6 PUs (W. Hofle) BPCR pick-up (BI) (100%) LIU-SPS 4.3 128691 : Provide 6 PUs (W. Hofle) Electrostatic PUs (2 BPH, 2BPV) (BI) (100%) LIU-SPS 4.3 128692 : Provide 6 PUs (W. Hofle) PU integration tunnel (vacuum chambers etc.) (100%) LIU-SPS 4.3 128697 : Optical fiber links BA2-BA3 (W. Hofle) Optical fibers BA2-BA3 links (100%) LIU-SPS 4.3 128697 : Optical fiber links BA2-BA3 (W. Hofle) VME optical RX channel (100%) LIU-SPS 4.3 128697 : Optical fiber links BA2-BA3 (W. Hofle) VME optical TX channel (100%) LIU-SPS 8 128623 : Installation of 4 half cells (pilot) (M. Taborelli) Dipole magnets reinstalled (100%) LIU-SPS 8 128623 : Installation of 4 half cells (pilot) (M. Taborelli) Survey completed (100%) LIU-SPS 9.1 128531 : Perform Extraction protection upgrade activities (J. Borburgh) HighRadMat test set-up inspected (100%)