Soil Investigation work Proposed Director`s Bungalow at

advertisement
EE/2015-16/
Dt. 07.08.2015
COURIER
NOTICE FOR INVITING QUOTATION
To,
Dear Sir(s),
The wax sealed quotation is invited on Item rate basis with following condition by the Office of the Executive
Engineer, NITIE, Mumbai – 400 087. Telephone No. 28035377 Without the wax sealed quotation will be summarily
rejected.
This notice is also available on web-site : www.nitie.edu.
Name of work
Earnest Money Deposit
Period of contract
Last date of submission of quotation
Date of opening of quotations
Validity period of
Quotation for acceptance
Place of submission of quotation
: Soil Investigation work Proposed Director's
Bungalow at NITIE, Mumbai
: Rs.8000.00 (Pay order or DD to be attached in
favour of "NITIE Mumbai 87"
: One month
: 25.08.2015 up to 11.00 A.M
: 25.08.2015 at 11.30A.M.
: 90 days from date of submission
: Quotation Box kept in front of the Office of
Registrar, Admn. Building, NITIE
NITIE reserves the right to reject any or all tenders without assigning any reason thereof.
Thanking you,
Yours faithfully
EXECUTIVE ENGINEER
CC : D R (A & A)/ CPSC/Notice Board IIT
Notice Board NITIE
Name of Work: - Soil Investigation work Proposed Director’s Bungalow at NITIE,
Mumbai.
BRIEF SPECIFICATIONS AND SCOPE OF WORK
1. GENERAL
1.1 All soil investigation work must be carried as per relevant Indian Standards for subsurface investigations (IS
1892), classification of soils (IS 1498), determination of bearing pressures for shallow foundations (IS 6403),
pile foundations (IS 2911) and various other Standards specified for the sampling, tests and recommendations.
For laboratory testing of rock samples, methods suggested by International Society of Rock Mechanics (ISRM)
shall be followed.
1.2 All levels shall be recorded from a fixed bench mark identified by the Architects.
1.3 Tentative locations of the boreholes are marked on the enclosed drawing.
1.4 Soil Investigation Agency shall keep the structural consultants informed about the progress of work at site and
shall furnish clarifications if required.
1.5 The time limit for completing soil investigation work is three weeks from the date of receipt of the Work-Order.
2. SCOPE OF INVESTIGATION
Total number of boreholes will be 5 Nos. as shown in the drawing.
The scope of Soil Investigation work shall definitely include (but shall not be limited to) the following:
2.1 Drilling all 5 bore holes up to at least 20.0m depth below the existing ground level or 10m depth below weathered
rock level – whichever is more and collecting disturbed and undisturbed samples at suitable intervals (and at
change of strata) and recording Standard Penetration Test results.
2.2 Carrying out laboratory tests on the 5 samples collected to determine Engineering Properties of Soil as directed
by the Consulting Engineers.
2.3 Carrying out chemical analysis of one sample of the ground water and two samples of the soil to determine
chloride and sulphate contents and pH value.
2.4 Recording existing ground water table and the extent of fluctuation, if any, in ground water table level.
2.5 Indicating the permeability of soil to determine the feasibility of carrying out open excavation up to 10m depth,
if required.
3. RECOMMENDATIONS
3.1 The Soil Investigation Agency is expected to make recommendations on each type of Foundation, Depth of
Foundation and Net Allowable Bearing Pressure on the soil at different levels. The expected short-term and longterm settlements for the recommended bearing pressures shall be clearly spelt out.
3.2 In case of piled foundations, load carrying capacities of driven as well as bored & cast in situ piles taking into
account the structural capacity of the pile shaft as well as the resistance offered by surrounding soils by means
of side friction and the tip resistance shall be calculated. The report should mention the capacities of piles in
relation to their diameters and the length of piles.
3.3 For all recommendations, the formulae in Indian Standards shall be used or any established literature can be
consulted. The Soil Investigation agency shall give complete calculations to the structural consultants showing
the basis of the recommendations on field and laboratory tests. The criteria for determination of quality of
acceptable strata shall be clearly defined in a manner, which will assist the supervisory staff at site during the
progress of work.
3.4 The investigation agency shall recommend values of suitable ‘spring constants’ to be adopted in the analysis to
determine the soil structure interaction. Similarly values of approximate ‘horizontal spring constants’ shall be
recommended.
3.5 The investigation agency shall visit the site atleast twice during the initial stages of actual construction work of
the project, whenever it is taken up, to confirm the acceptance of the founding strata as well as its load carrying
capacity, in accordance with the results of soil investigation it has submitted.
3.6 The investigating agency shall include in the report, the safe slope of excavation needed to be maintained
throughout the work for different depths of excavation from 1m upto 12m depending on the soil properties in
different layers.
3.7 The report should also indicate the need to install a soil retention system including dewatering, if required, and
the recommended type of such a system keeping in view if excavation levels may reach a depth of 12m.
3.8 A cross section of soil profile covering the bore holes along both the axes shall be included in the report.
_______________
CONTRACTOR
NITIE, Mumbai - 87
________________________
EXECUTIVE ENGINEER
SCHEDULE
Name of Work:- Soil Investigation work Proposed Director’s Bungalow at NITIE , Mumbai.
Sr No
Item
Quantity Unit
Rate
Amount
I
FIELD WORK
1-a
Mobilization of all required equipment ,
plant , instruments and its subsequent
demobilization
etc.
complete
on
satisfactory completion of the soil
investigation jobs
Setting & shifting of rig at bore hole/test
location including 1st one
Drilling exploratory bore holes of not more
than 150mm diameter, in all types of soil,
including clay, as per specification . (Soil
where SPT “N” equal or less than 50)
Drilling NX size exploratory bore holes in
weathered rock / hard rock with T.C./with
diamond drill bit with core run not more
than 1.5 m & collecting rock samples using
double tube core barrels , preserving rock
samples in wooden core boxes all as per the
specifications including gravity grouting if
necessary in water loss zones & providing
cement (soft rock is defined SPT “N” equal
or more than 50)
Conducting standard penetration tes (SPT)
@1.5m interval and collecting /preserving
SPT samples , as per specifications
Collecting undisturbed soil samples(UDS)
with thin alled sampling tube and
conforming to the specifications
Collecting ground water samples for
chemical analysis
Collecting of soil samples for chemical
analysis
Providing wooden core box for preserving
soiul/rock samples conducting following
tests on various soil , water & rock samples
UDS/DS samples collected thereon , as per
specifications & determining
Field density of soil / water samples to be
noted
Specific gravity / unit weight
1-b
2
3
4
5
6
7
8
9.
10.
11.
i)
Rock core inclusive of cutting / grinding /
polishing
With saturation
L.S.
Job
5
P.No.
100
R.M.
100
R.M.
5
P.No
5
P.No.
2
P.No.
2
P.No.
1
Job
4
P.No.
5
P.No.
5
P.No
ii)
Without saturation
5
P.No
II
Laboratory Tests
1
5
P. No
2
Natural moisture content (NMC) of soils by
oven drying method
Atterbert limits of soil i.e.
5
P. No.
i.
Liquid Limit (LL)
5
P. No.
ii.
Plastic Limit
5
P. No.
iii.
Shrinkage Limit(SL)
5
P. No.
3
5
P. No.
4
Grain size analysis (GSA) of various soil
samples by both mechanical sieve &
hydrometer analysis
In situ dry density of soil samples
5
P. No.
5
Tri – axial drained and un – drained test
5
P. No.
6
5
P. No.
5
P. No.
5
P. No.
9
Chemical analysis of soil to determine
chloride sulphate
Chemical analysis of ground water to
determine chloride, Sulphate, Ph 7. Organic
Content
Unconfined compressive strength of soaked
rock samples
Porosity of rock sample
5
P. No.
10
Dry density of rock sample
5
P. No.
11
Point load index of soaked rock sample
5
P. No.
12.
Water absorption of soil
5
P. No.
13.
Consolidation Test
5
P. No.
7
8
Total Rs.
Total in Words -
_______________
CONTRACTOR
Seal & Addresses
________________________
EXECUTIVE ENGINEER
Download