PERFORMANCE EVALUATION REPORT FOR GREATER MAFIKENG BULK WATER SUPPLY SCHEME NORTH WEST CHIEF DIRECTORATE: BULK INFRASTRUCTURE PROGRAMME PERIOD: 01 APRIL 2013 TO 31 MARCH 2014 2 Programme Management: Regional Bulk Infrastructure TABLE OF CONTENTS 1. Introduction 2. Background 2.1 Description of project 2.2 Project history 2.3 Project concept, design and plan 2.4 Start date – duration of the programmer 2.5 Funds previously allocated to project 3. Progress to date 3.1 Implementation of approved business plan 3.2 Schedules of work and phasing of the activities 3.3 Risks taken and management thereof 3.4 Capacities dedicated to the programme 3.5 Key challenges within the project 4. Project result and beneficiaries 4.1 Outcomes and outputs 4.2 Beneficiaries and project results 5. Conclusions / Lessons Learned 5.1 Main successes and failures of the project to date 5.2 Ownership and sustainability of infrastructure works 6. Recommendations ANNEXURE A: ANNEXURE B: ANNEXURE C: ANNEXURE D: ANNEXURE E: Project Implementation Photos List of villages expected to benefit from Phase 1 Details of contracts awarded under Phase 1 Project schedule Details of job opportunities APRIL 2014 3 Programme Management: Regional Bulk Infrastructure 1. APRIL 2014 INTRODUCTION In terms of Section 10(7) (b) of the Division of Revenue Act No 2 of 2013 (DORA) as promulgated in Government Gazette No 36555 dated 10 June 2013, the transferring national officer must submit an annual performance report for Schedule 6 within four months in respect of a province and six months in respect of a municipality after the end of the financial year to the National Treasury. The Regional Bulk Infrastructure Grant (RBIG) is a Schedule 6 indirect conditional grant for the benefit in kind of municipalities. The objective of this Report is to provide an annual performance evaluation report covering the 4th quarter of RBIG funded projects, in compliance with the DORA. The objective of this evaluation was to determine whether the progress on the project is commensurate with the expenditure to date as well as to determine whether the project is still on course in terms of the original planning. This performance evaluation report, covering quarter 4 and the annual report of the 2013/14 fiscal year, is for he Mafikeng Bulk Water Supply Scheme is one of the Regional Bulk Infrastructure Grant projects currently being implemented by the Ngaka Modiri Molema DM in the North West Province, with Department of Water Affairs (DWA) as funder. 2. BACKGROUND 2.1 Description of Project The primary focus is to augment bulk water supply to the City of Mahikeng and its peri-urban villages, within the Mahikeng Local Municipality, located in the Ngaka Modiri Molema District Municipality (NMMDM) in the North West Province. The project aims to increase the capacity of the water treatment works and to improve the bulk water distribution to the region. The City of Mahikeng, capital city of the North West Province, is located some 280 km west of Pretoria. The city has a total estimated population of some 66 400 living within its originally proclaimed (urban) boundaries. The Mahikeng peri-urban villages, located immediately adjacent to the southern, western and north-eastern originally proclaimed boundaries of the city, are home to an additional estimated 172 000 people who presently receive very limited services from the Mahikeng Local and Ngaka Modiri Molema District Municipal Councils, if any. The residents in the periurban villages live very close to the city, make use of its amenities such as offices, shopping facilities, schools and public transport systems, and generally aspire to a similar living standard as the adjacent urban areas. The city’s primary economic base is the business of Government, followed by its functions as commercial and administrative hub for the region. The regional economy also benefits from commercial agriculture, cement manufacture, transport, tourism and mining to a limited degree. The peri-urban villages have been, and still are characterised by significant backlogs in water supply and sanitation, as evidenced by the results of the Census 2011. 4 Programme Management: Regional Bulk Infrastructure APRIL 2014 LEGEN D Urban Mahikeng LM Ngaka Modiri Molema DM Mmabatho WTW Areas Peri-urban Villages Other Villages, not Included in Study Area Mmabath o Mahiken g Figure 1: Locality Plan 2.2 Project history In March 2012, the NMMDM appointed a consultant to undertake a bulk water master plan for the Greater Mahikeng, which had been suffering from systemic water shortages since 2010. The Greater Mafikeng Bulk Water Supply project was subsequently identified by the DWA for potential Regional Bulk Infrastructure Grant (RBIG) funding, the implementation of which was to be advised by the Greater Mafikeng Bulk Water Master Plan (GMBWMP). The GMBWP was completed at the same time as the project implementation readiness report in April 2013. 2.3 Project concept, design and plan The city of Mafikeng originally obtained all of its water supply from the Grootfontein dolomitic compartment, which was supplemented by supply from the Molopo Eye compartment in 1985. In 1996 the Setumo Dam was constructed to the west of the city, half of the yield of which was to comprise natural run-off, and the balance of which would comprise treated sewage effluent from the 2 wastewater treatment works serving the city. The 20 Ml/d Mmabatho water treatment works was constructed together with the Setumo Dam, and commissioned in 1997. The yield of the Grootfontein compartment collapsed in 2010 to approximately one third of its previous yield in 2010, which resulted in regular and systemic water shortages to the city. 5 Programme Management: Regional Bulk Infrastructure APRIL 2014 A condition assessment of the Mmabatho WTW in mid 2012 indicated that as a result of poor maintenance and poor water quality in the Setumo Dam, the WTW’s reliable delivery capacity had deteriorated to approximately 10 Ml/d from its originally designed 20 Ml/d. The GMBWP included a detailed feasibility study, and concluded that the bulk water supply to the Greater Mafikeng’s approximately 238 000 residents (61 800 Households) should be augmented by immediate implementation of the following works:Phase 1 – Emergency Refurbishment and Upgrading of the Mmabatho WTW The purpose of this phase is to refurbish all mechanical and electrical components of the existing Mmabatho WTW, as well as the high lift pump station, the Lokaleng intermediate pump station and pump mains which transmit purified water from the Mmabatho WTW to the Signal Hill reservoirs, which supply the city. It was also to rectify bottlenecks in the WTW treatment process, including the equipping of two filter structures for future utilisation, to bring the existing WTW’s delivery capacity back to its originally rated 20 Ml/d. Phase 2 – Upgrading of the Mmabatho WTW to 30 Ml/d and Associated Bulk Storage and Distribution Infrastructure The GMBWP confirmed that the 98% level of assurance (LoA) yield of the Setumo Dam is in excess of 22 million m3/a, or 60 Ml/d, and recommended that the capacity of the Mmabatho WTW be further upgraded in the second phase of the project to 30 Ml/d, which is projected to be adequate to provide sufficient bulk water supply to the Greater Mafikeng up to approximately 2020. In addition to the existing flocculation, settling and diffused air flotation treatment steps, the upgrading of the WTW will also include the addition of ozonation to deal with excessive Total Organic Carbon (TOC) levels in the water of the Setumo Dam, as well as Granulated Activated Carbon (GAC) filters to deal with taste and odour problems arising from the high algal content of the raw water, which in turn is prevalent as a result of the high nutrient content of the raw water. In addition to the upgrading of the WTW required, it was recommended that a large proportion of the water serving the study area did not need to be pumped all the way to the Signal Hill reservoirs, and the Lokaleng intermediate pump station was in any case inadequate to transmit the extra 10 Ml/d of water which would come from the upgraded Mmabatho WTW. It was therefore recommended that a new 25 Ml prestressed concrete reservoir be constructed at the Lokaleng pump station site, and that gravity led steel pipelines be constructed to deliver the extra water directly from Lokaleng into the city’s reticulation system. This would require the construction of approximately 10.8 km of steel trunk main ranging from 600 – 900 mm in diameter. The villages that are expected to benefit from both phases of the project are listed in Annexure B. 2.4 Start date – duration of the programme The project was initially identified to potentially qualify for RBIG funding by the DWA in March 2012, shortly after the NMMDM commenced its GMBWMP. The DWA commenced contributing to the planning stages of the project in 2012. 6 Programme Management: Regional Bulk Infrastructure APRIL 2014 As stated above, the project IRS and the GMBWMP were completed in April 2013, and the DWA confirmed later in 2013 that it would avail funding to commence Phase 1 of the project during the 2013/14 financial year. Construction of phase 1 of the work however commenced in January 2014, and should be completed by July 2014. Phase 2 of the work is currently scheduled to commence in May 2014, and based on RBIG funding presently indicated in the MTEF, will only be completed by August 2017, with retention to be released a year thereafter. Please refer to Annexure C where the detail of the contracts is reflected. 2.5 Funds previously allocated to project Table 1 below indicates the RBIG funding that was made available to the project to date. Table1: Funding for the past two financial years 2012/13 2013/14 Total Allocation / R 1 536 125 R 21 248 975 R 22 785 100 Spent amount The NMMDM still has to confirm the commitment for counter-funding to the amount of R 110 818 million for the economic component of the costs of the project. 3. PROGRESS TO DATE The performance evaluation was conducted on 22 April 2014 by a team consisting of the following people: 3.1 J Fourie P van der Merwe L Leeuw W Bosman K Tlhagale DWA (RBIG) National Office DWA Regional Office NW NMMDM Bigen Africa Bigen Africa Implementation of the approved business plan In its capacity as Implementing Agent, NMMDM has employed its own staff to manage the project and to provide financial management and administrative support to the project. It has also appointed external professional service providers and contractors in terms of its supply chain management policies and procedures. The NMMDM appointed Bigen Africa Services in March 2012 to undertake the Greater Mafikeng Bulk Water Masterplan and related feasibility studies, which was submitted to NMMDM and DWA in April 2013. This report formed the basis on which more detailed project planning was done. The NMMDM then subsequently extended Bigen Africa’s professional services contract to include for the designs, contract administration and construction supervision of Phases 1 and 2 of the project as describe above, but subject to the availability of adequate funding. In December 2013, the NMMDM awarded Contract NMMDM 12/12/19/PMU for Phase 1 of the work, for the Emergency Refurbishment and Upgrading of the Mmabatho WTW, to HT Pelatona Projects (Pty) Ltd. 7 Programme Management: Regional Bulk Infrastructure Table2: Milestones Product Name of Organization compiling/ developing APRIL 2014 Planned date for completion FS/IRS/Design/EI A April 2013 April 2013 Date FS/IRS/Design/ EIA approved Feasibility Study / GMBWMP Implementation Readiness Study Bigen Africa Services Bigen Africa Services Preliminary Designs EIA (Phase 2) Bigen Africa Services African Environmental Management Services November 2012 July 2013 November 2012 July 2013 WULA African Environmental Management Services July 2014 N/A Operation and Maintenance Plan NMMDM November 2014 N/A Financial Funding Plan Detail Designs: WTW & Lokaleng Reservoir NMMDM Bigen Africa Services November 2014 November 2013 November 2013 3.2 April 2013 April 2013 Schedules of work and phasing of the activities The Scheme comprises a number of components, viz. Phases 1 and 2 of the works as described in Section 2.3 above. Construction work on the first contract awarded under Phase 1 commenced in January 2014, and is expected to be completed in July 2014. A tracked programme for the Project as at 25 March 2014, based on the current MTEF funding available, is shown in Annexure D. The phasing and costs are summarised in Table 3 below. Table 3: Schedule of Dates and Costs per Project Phase Project Phase Planned Date Planned Date for Start for Completion Phase 1:Refurbishment / Upgrading 1/11/2013 25/07/2014 Phase 2A:Mmabatho WTW 1/08/2014 30/06/2016 Phase 2B:Lokaleng Reservoir 15/11/2015 31/05/2017 Phase 2C:Lokaleng Trunk Mains 1/03/2016 31/07/2017 Total 1/11/2013 31/07/2017 3.3 Cost/ Phase (R000s) R 35 621.1 R 142 394.2 R 46 238.1 R 70 965.6 R 295 219.0 Risks taken and management thereof Approximately 50% of the water entering the Setumo Dam, which will be treated by the Mmabatho WTW, is treated wastewater effluent, and water quality in the dam poses a significant risk to the quality of water to be supplied by the plant. In the Project’s Phase 2, a Water Use License would need to be approved by DWA. However for Phase 1 it is currently not required. The NMMDM is in the process of completion of an extensive refurbishment of the Mafikeng and Mmabatho Wastewater Treatment Works (WWTWs) to ensure that the 8 Programme Management: Regional Bulk Infrastructure APRIL 2014 quality of the effluent discharged into the Setumo Dam complies with the special standards prescribed for the Molopo River. In addition, Ozonation and GAC filters will be incorporated into the upgraded Mmabatho WTW to deal with the effects of effluent on the raw water reservoir, viz. excessive TOC contents and taste and odour problems arising as a result of high algal content. The operation and maintenance of the works once complete is essential, and the NMMDM will be required to put a comprehensive operation and maintenance plan in place for the works once complete. It is recommended that NMMDM put in place an Operation and Maintenance contract for the Mmabatho Water Treatment Works until its own internal O&M arrangements can be fully implemented. The O&M Contract would allow for the appointed contractor to undertake all scheduled maintenance on the plant as required by the various plant component manufacturers, as well as to respond to call-outs regarding the Maintenance on the Mmabatho WTW. A clear budget is required to be put in place regarding the available funding for the project. In addition, more effort needs to be made to finalise the counter-funding from NMMDM. 3.4 Capacities dedicated to the programme The capacities dedicated to the programme are as follows: 3.5 Water Services Authority – Ngaka Modiri Molema District Municipality. Water Services Provider – Botshelo Water. Funding – DWA – Regional Bulk Infrastructure Grant (RBIG). Regulator – DWA. Overall Programme and Project Management – Ngaka Modiri Molema District Municipality as Implementing Agent for DWA. Financial management and administrative support – Ngaka Modiri Molema District Municipality. Design, contract administration and construction monitoring – professional service providers appointed by NMMDM: Bigen Africa Services (Pty) Ltd. Construction work – H T Pelatona Services (Pty) Ltd. Please refer to Annexure C where the detail of the contract is reflected. Key challenges within the project Key challenges include the following: Funding for all phases of the Scheme (the current estimated capital shortfall is R 148.4 million, taking into account DWAs MTEF Budget Allocations up to FY16/17 totalling R 150 million. The NMMDM has unofficially indicated that it will provide counter funding for R 110.818 million required for the economic component of the costs, but is yet to provide a council resolution in this regard. Operation and maintenance arrangements for the Mmabatho WTW, which had previously deteriorated significantly, leading to the need for the Phase 1 emergency refurbishment works. The possible delays in approving the Water Use License from the Setumo Dam. 9 Programme Management: Regional Bulk Infrastructure 4. PROJECT RESULTS AND BENEFICIARIES 4.1 Outcomes and outputs APRIL 2014 Currently the expected outcomes and outputs are on track for the phase under Construction. 4.2 Beneficiaries and project results As stated in Section 2.3 above, the purpose of the project is to ultimately supply 30 Ml/day of bulk potable water to a population of 238 400 people in approximately 51 800 households. 4.3 Jobs Created Job creation details are summarized in Annexure E. 5. CONCLUSION / LESSONS LEARNED 5.1 Main successes and failures of the project to date 5.2 Ownership and sustainability of infrastructure works 6. Since 2013, significant progress has been made in the implementation of Phase 1 of the Scheme. The role-players maintain regular contact with each other, and the project team, under the direction of Ngaka Modiri Molema District Municipality, provides the necessary professional input. All contracts under Phase 1 have been awarded. Phase 1 of the project is due for completion towards the middle of 2014. The NMMDM’s project registration and budgeting process requires a commitment from the funding agent for the full funding required for a project before it can award a contract for the works. DWA will need to make a multiyear commitment to the NMMDM for the contracts comprising phase 2 of the project, which will run over consecutive financial years. The NMMDM has been experiencing severe cash flow and financial problems over the last year, and steps will have to be taken to ensure that contracts implemented by it are not disrupted due to delays as a result of non-payment to service providers / contractors. Ownership of all the existing assets included in the bulk water supply system is vested in the NMMDM, and that of the new components to be constructed will be transferred to NMMDM, in its capacity as the Water Services Authority, on completion of construction of the works. The NMMDM has indicated its intention to operate and maintain the bulk water supply system. RECOMMENDATIONS It is recommended that urgent attention be paid to the key challenges listed under Section 3.5 above. Ngaka Modiri Molema District Municipality to ensure sufficient resources are available for operation and maintenance of the project once completed. 10 Programme Management: Regional Bulk Infrastructure APRIL 2014 NMMDM must provide DWA with confirmation for counter funding on the project. DWA to confirm funding for Phase 2 of the project. Pursue the approval of the WUL application 11 Programme Management: Regional Bulk Infrastructure ANNEXURE A: PROJECT IMPLEMENTATION PHOTOS Photo 1: Plant being removed for inspection and refurbishment – February 2014. Photo 2: New Filter floor being cast (March 2014). APRIL 2014 12 Programme Management: Regional Bulk Infrastructure Photo 3: Bubble test being conducted on existing filter floor (March 2014). Photo 4: Existing filters emptied for inspection and assessment (February 2014). APRIL 2014 13 Programme Management: Regional Bulk Infrastructure APRIL 2014 Photo 5: Dosing pump pipework being replaced (March 2014). Photo 6: Filler piece installed to allow rising main isolating valve to be sent for refurbishment Photo 5: (February 2014). 14 Programme Management: Regional Bulk Infrastructure APRIL 2014 ANNEXURE B: LIST OF VILLAGES EXPECTED TO BENEFIT FROM PHASE 1 No. Ward Village / Suburb Name Co-ordinates South East 1 7 Mafikeng 25 o 51 ' 31.92 " 25 o 38 ' 32.44 " 2 8 Mmabatho 25 o 50 ' 16.56 " 25 o 36 ' 3 9 Riviera Park 25 o 51 ' 44.52 " 25 o 39 ' 30.07 " 4 9 Danville 25 o 52 ' 36.23 " 25 o 39 ' 5 8 Montshioa 25 o 50 ' 49.51 " 25 o 37 ' 21.89 " 6 9 Aslaagte 25 o 51 ' 15.56 " 25 o 41 ' 7 30 Dibate 25 o 50 ' 47.29 " 25 o 36 ' 26.32 " 8 16 Motlhabeng 25 o 51 ' 22.84 " 25 o 36 ' 9 20 Ramosadi 25 o 51 ' 51.08 " 25 o 37 ' 13.81 " 10 14 Seweding 25 o 52 ' 12.85 " 25 o 35 ' 42.27 " 11 6 Lokaleng 25 o 47 ' 58.33 " 25 o 34 ' 54.28 " 12 15 Montshioastad 25 o 52 ' 40.25 " 25 o 37 ' 57.50 " 13 9 Lorwaneng 25 o 53 ' 9.31 " 25 o 38 ' 51.90 " 14 21 Majemantsho 25 o 54 ' 16.02 " 25 o 39 ' 58.35 " 15 15 Tloung 25 o 53 ' 8.16 " 25 o 36 ' 49.84 " 16 18 Tlhabologo 25 o 53 ' 31.23 " 25 o 37 ' 30.52 " 17 22 Setlopo 25 o 55 ' 35.61 " 25 o 38 ' 31.34 " 18 19 Magogwe 25 o 54 ' 7.06 " 25 o 35 ' 55.24 " 19 6 Molelwane 25 o 47 ' 56.67 " 25 o 38 ' 15.88 " 20 29 Lonely Park 25 o 50 ' 13.65 " 25 o 39 ' 21 7 Top Village 25 o 50 ' 50.87 " 25 o 39 ' 59.78 " 22 28 Signal Hill 25 o 49 ' 25 o 39 ' 22.67 " 6.03 " 9.20 " 6.49 " 8.55 " 8.82 " 4.26 " 15 Programme Management: Regional Bulk Infrastructure APRIL 2014 ANNEXURE C: DETAILS OF CONTRACTS AWARDED UNDER PHASE 1 CONTRACT CONTRACT PLANNED ACTUAL CONTRACT AWARD / CONTRACTOR VALUE (incl. COMPLETION COMPLETION NO. START VAT) DATE DATE DATE NMMDM 12/12/19/PMU NOTE: HT Pelatona Projects R 27 089 672.31 (Pty) Ltd 15 Jan 2014 Retention monies withheld have been included as expenditure. All figures include 14% VAT. 15 Jul 2014 N/A EXPENDITURE AS AT 31 MAR % 13 COMPLETION (incl. VAT) R 12 789 028.42 33% 16 Programme Management: Regional Bulk Infrastructure APRIL 2014 UPGRADING OF MMABATHO WTW AND ASSOCIATED LINK INFRA STRUCTURE ID Task Name 1 Approval to Proceed 012 Qtr 3, 2012 Qtr 4, 2012 Qtr 1, 2013 Qtr 2, 2013 Qtr 3, 2013 Qtr 4, 2013 Qtr 1, 2014 Qtr 2, 2014 Qtr 3, 2014 Qtr 4, 2014 Qtr 1, 2015 Qtr 2, 2015 Qtr 3, 2015 Qtr 4, 2015 Qtr 1, 2016 Qtr 2, 2016 Qtr 3, 2016 Qtr 4, 2016 Qtr 1, 2017 Qtr 2, 2017 Qtr 3, 2017 Qtr Jun '12Jul '12Aug '12 Sep '12 Oct '12 Nov '12 Dec '12 Jan '13 Feb '13 Mar '13 Apr '13 May '13 Jun '13Jul '13Aug '13 Sep '13 Oct '13 Nov '13 Dec '13 Jan '14 Feb '14 Mar '14 Apr '14 May '14 Jun '14Jul '14Aug '14 Sep '14 Oct '14 Nov '14 Dec '14 Jan '15 Feb '15 Mar '15 Apr '15 May '15 Jun '15Jul '15Aug '15 Sep '15 Oct '15 Nov '15 Dec '15 Jan '16 Feb '16 Mar '16 Apr '16 May '16 Jun '16Jul '16Aug '16 Sep '16 Oct '16 Nov '16 Dec '16 Jan '17 Feb '17 Mar '17 Apr '17 May '17 Jun '17Jul '17Aug '17 Sep '17 Oct '17 N 2 Upgrading Mmabatho WTW Ph1&2 Draft Feasibility Stud y 3 Comments from Stakeholders 4 Upgrading Mmabatho WTW Ph1 & 2 Final Feasibility St udy 5 Upgrading Mmabatho WTW Ph 2 IRS 6 Upgrading Mmabatho WTW Ph1 & 2 EIA 7 Mmabatho WTW Ph 2 License application 8 Mmabatho WTW Ph 2 License approval 9 Strategic & Planning Issues 10 Social Criteria 11 Economic Criteria 12 Technical Criteria 13 Institutional Criteria 14 Financial Criteria 15 Legal Criteria 16 17 18 19 20 Sustainability Criteria Preliminary Designs Water Treatment Works Lokaleng Reservoir Lokaleng Trunkmains 21 Draft IRS Report 22 Comments from Stakeholders 23 Final IRS Report 24 Approval of IRS and Funding 25 Phase 1 (Refurbishment / Upgrade to 20 Ml/d) 26 Update Tender Documents 27 Tender Period 28 Tender Adjudication & Award 29 Refurbishment / Upgrading 30 31 32 23/ 09 Commissioning Phase 2 Upgrading of WTW to 30 Ml/d 33 Detailed Designs 34 Tender Documentation 35 Tender Period 36 Tender Adjudication & Award 37 Construction 38 39 Commissioning 25 Ml Lokaleng Reservoir 40 Detailed Designs 41 Tender Documentation 42 Tender Period 43 Tender Adjudication & Award 44 Construction 45 Commissioning 46 Lokaleng Trunkmains 47 Detailed Designs 48 Tender Documentation 49 Tender Period 50 Tender Adjudication & Award 51 Construction 52 Commissioning Task Milestone Project Summary External Milestone Inactive Milestone Manual Task Manual Summary Rollup Start-only Progress Split Summary External Tasks Inactive Task Inactive Summary Duration-only Manual Summary Finish-only Deadline ANNEXURE D: PROJECT SCHEDULE PHASES 1 AND 2 Project: Mmabatho WTW Ph1&2 25 M Date: Mon 31/03/14 IMPLEMENTATION PROGRAMME Figure 1 17 Programme Management: Regional Bulk Infrastructure APRIL 2014 ANNEXURE E: DETAILS OF JOB OPPORTUNITIES Summary of Decent Job Opportunities Decent job opportunities Decent job opportunities for the financial year 2012/13 for people employed at Adult Men Adult Women various occupational No Person Actual cost No Person Actual cost No levels: Decent = Full time Days on job Days on job for at least 5 months or opportunities opportunities more Clerical Ongoing Clerical New Labourers Ongoing Labourers New Managerial Ongoing Managerial New Semi-Skilled Ongoing Semi-Skilled New Skilled Ongoing Skilled New Supervisor Ongoing Supervisor New Other Ongoing Other New Youth Women Person Actual cost No Days on job opportunities 66 0 148 0 48 0 132 0 R 21,000 R0 R 32,560 R0 R 71,591 R0 R 48,000 R0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 R0 R0 R0 R0 R0 R0 R0 R0 0 0 4 0 1 0 1 0 0 0 90 0 32 0 66 0 R0 R0 R 19,800 R0 R 36,364 R0 R 24,000 R0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 R0 R0 R0 R0 R0 R0 R0 R0 2 132 0 0 0 0 0 0 0 0 0 0 TOTAL Ongoing 13 526 TOTAL New 0 0 Summary of Temporary Job Opportunities R 72,001 R0 R0 R0 R0 R0 R 245,152 R0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 R0 R0 R0 R0 R0 R0 R0 R0 0 0 1 0 1 0 8 0 0 0 132 0 20 0 340 0 R0 R0 R 72,001 R0 R 36,364 R0 R 188,528 R0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 R0 R0 R0 R0 R0 R0 R0 R0 Temporary job opportunities for people employed at various occupational levels: Temporary = Less than 5 months Clerical Ongoing Clerical New Labourers Ongoing Labourers New Managerial Ongoing Managerial New Semi-Skilled Ongoing Semi-Skilled New Skilled Ongoing Skilled New Supervisor Ongoing Supervisor New TOTAL Ongoing TOTAL New 1 0 6 0 2 0 2 0 Youth Men Person Actual cost No Days on job opportunities Disabled Person Actual cost No Days on job opportunities 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 R0 R0 R0 R0 R0 R0 R0 R0 R0 R0 R0 R0 R0 R0 R0 R0 TOTAL Person Actual cost Days on job opportunities 1 0 10 0 3 0 3 0 2 0 1 0 1 0 21 0 66 0 238 0 80 0 198 0 132 0 132 0 20 0 866 0 R 21,000 R0 R 52,360 R0 R 107,954 R0 R 72,001 R0 R 72,001 R0 R 72,001 R0 R 36,364 R0 R 433,680 R0 Temporary job opportunities for the financial year 2013/14 Adult Men Person Actual cost No Days on job opportunities No Adult Women Person Actual cost No Days on job opportunities Youth Men Person Actual cost No Days on job opportunities Youth Women Person Actual cost No Days on job opportunities Disabled Person Actual cost No Days on job opportunities TOTAL Person Actual cost on Days job opportunities 0 0 R0 0 0 R0 0 0 R0 0 0 R0 0 0 R0 0 0 R0 0 0 10 0 0 0 0 0 0 0 0 0 10 0 0 88 0 0 0 0 0 0 0 0 0 88 R0 R0 R 28,088 R0 R0 R0 R0 R0 R0 R0 R0 R0 R 28,088 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 R0 R0 R0 R0 R0 R0 R0 R0 R0 R0 R0 R0 R0 0 0 22 0 0 0 0 0 0 0 0 0 22 0 0 109 0 0 0 0 0 0 0 0 0 109 R0 R0 R 22,799 R0 R0 R0 R0 R0 R0 R0 R0 R0 R 22,799 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 R0 R0 R0 R0 R0 R0 R0 R0 R0 R0 R0 R0 R0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 R0 R0 R0 R0 R0 R0 R0 R0 R0 R0 R0 R0 R0 0 0 32 0 0 0 0 0 0 0 0 0 32 0 0 197 0 0 0 0 0 0 0 0 0 197 R0 R0 R 50,887 R0 R0 R0 R0 R0 R0 R0 R0 R0 R 50,887