SECTION 01 7418
WATER POLLUTION CONTROL
EDIT NOTES:
A. THE GUIDE SPECIFICATIONS LISTS THREE SECTIONS FOR WATER
POLLUTION PREVENTION. THESE SECTIONS SHOULD BE USED AS
INDICATED BELOW. TOTAL LAND DISTURBANCE SHOULD INCLUDE
PROJECT, STOCKPILE AND STAGING AREAS.
1.
PROJECTS WITH LAND DISTURBANCE OF ONE ACRE OR MORE
SHALL INCLUDE SPECIFICATION SECTION 01_7416, STORM
WATER POLLUTION PREVENTION PLAN, UNLESS IT MEETS THE
REQUIREMENTS OF CONDITION # 2 LISTED BELOW.
2.
SITES WITH LAND DISTURBANCE WITHIN ONE TO FIVE ACRES
WITH WAIVER SUBMITTED THROUGH SMARTS AND APPROVED
BY THE WATER BOARD SHOULD USE SPEC SECTION 01_7417, BMP
IMPLEMENTATION PLAN.
3.
SITES WITH LAND DISTURBANCE OF LESS THAN ONE ACRE:
a.
IF SITE IS PART OF A LARGER DEVELOPMENT OF ONE ACRE
OR MORE, OR IF SWPPP/NOI IS REQUIRED TO OBTAIN
CHPS/LEED CERTIFICATION, USE SECTION 01_7416, STORM
WATER POLLUTION PREVENTION PLAN.
b. IF PROJECTS MAINTAINS ORIGINAL LINE & GRADE,
HYDRAULIC CAPACITY, AND ORIGINAL PURPOSE OF THE
FACILITY (I.E. MINOR TRENCHING PROJECTS, HVAC, FIRE
ALARM PROJECTS, ETC.), SECTION 01_7418, WATER
POLLUTION CONTROL, MAY BE USED.
c.
NON-MAINTENANCE PROJECTS, USE SPECIFICATION
SECTION 01_7417, BMP IMPLEMENTATION PLAN.
PART 1 - GENERAL
1.01
SUMMARY
A.
Section Includes:
1.
Control runoff and pollutants from the site during construction activities.
EDIT NOTE: ADD RELATED SECTIONS AS APPLICABLE TO PROJECT.
B.
Related Requirements:
1.
PROJECT NAME
SCHOOL NAME
Division 01 – General Requirements.
12/09/2013
WATER POLLUTION CONTROL
01 7418-1
1.02
ACRONYMS AND DEFINITIONS
1.03
BMP
Best Management Practice.
CAN
Corrective Action Notice.
CASQA
California Stormwater Quality Association.
CGP
NPDES General Permit for Storm Water Discharges Associated
with Construction Activities.
DWQ
Division of Water Quality.
LARWQCB
Los Angeles Regional Water Quality Control Board.
NPDES
National Pollutant Discharge Elimination System.
OEHS
LAUSD Office of Environmental Health and Safety.
SWPPP
Storm Water Pollution Prevention.
SWRCB
State Water Resources Control Board.
REQUIREMENTS
A.
B.
CONTRACTOR shall:
1.
Implement Good Site Management "Housekeeping".
2.
Install and maintain BMPs. Insure that BMPs are designed to protect all
exposed portions of the site, including:
a.
Erosion, Sediment, Tracking, and Wind Erosion Control BMPs.
b.
Non--storm Water Control BMPs.
c.
Waste Management BMPs.
3.
Incorporate BMP activities into the Project Schedule.
4.
Inform CONTRACTOR and Subcontractors personnel on the BMP
procedures to prevent pollutants from entering the storm drain system,
before the start of construction activities. Keep personnel informed of the
BMP implementation process and of changes to the procedures. Provide
record to OAR of Storm Water Topics discussed.
5.
Pay fines and penalties from regulatory agencies against OWNER due to
CONTRACTOR’S non-compliance with storm water regulations.
OWNER shall recover costs of fines and penalties by appropriate
OWNER assessment. Review of the BMPs by OAR shall not relieve
CONTRACTOR from liabilities arising from non-compliance of storm
water pollution regulations.
Project Inspector and OEHS Inspector will conduct inspection and examination of
site storm water regulation compliance.
PROJECT NAME
SCHOOL NAME
12/09/2013
WATER POLLUTION CONTROL
01 7418-2
1.04
SUBMITTALS
A.
1.05
BMP material quality, grade, type as specified in the CASCA BMP Handbook.
QUALITY ASSURANCE
A.
Regulatory Requirements: Comply with the following requirements:
1.
National Pollutant Discharge Elimination System (NPDES) General
Permit for Storm Water Discharges Associated with Construction and
Lands Disturbance Activities; ORDER NO. 2009-0009-DWQ; NPDES
NO. CAS000002, adopted by the State Water Resources Control Board.
2.
Regulations of the California Environmental Protection Agency, State
Water Resources Control Board; Los Angeles Regional Water Control
Board, and local ordinances.
3.
CASQA Stormwater Best Management Practice Handbook
Construction Activity (BMP Handbook) current adopted edition.
for
EDIT NOTE: IF PROJECT IS LOCATED WITHIN JURISDICTION
WITH SWPPP ORDINANCES, ADD NEW PARAGRAPH # 4 BELOW
LISTING AGENCY NAME.
1.06
STORAGE AND PROTECTION
A.
Provide proper storage of materials and equipment to prevent rain and storm
water runoff to come in contact with pollutants, such as soil stabilizers, paint or
fluids from vehicles.
PART 2 – PRODUCTS
NOT USED
PART 3 – EXECUTION
3.01
IMPLEMENTATION
A.
Install perimeter controls prior to starting Work at the Project site.
B.
Implement BMP plan to contain on-site storm water on the Project site. Provide
storm drain inlet protection. Do not drain on-site water directly into the storm drain
without proper BMP in place.
C.
Prevent pollutant discharges into the storm drain system. Prevent storm water from
coming into contact with pollutants, such as sediment, material spills, or leakage
PROJECT NAME
SCHOOL NAME
12/09/2013
WATER POLLUTION CONTROL
01 7418-3
from storage tanks, waste containers or transfer areas. In the event contamination is
found CONTRACTOR shall immediately notify OAR who will contact the OEHS.
D.
Protect exposed dirt, such as stockpiles, landscaping areas, and hillsides.
E.
Properly manage non-storm water discharges such as ground water, broken utility
lines and fire hydrant testing per BMP Implementation Plan.
F.
Adjust BMP’s locations and layouts in accordance to construction progress to assure
compliance to regulations.
G.
Conduct inspections of pollution prevention controls and provide Site Monitoring
Report to OAR immediately if pollutants are discharged into the site runoff.
CONTRACTOR shall remediate contaminated water.
H.
Upon Substantial Completion: Maintain and leave post-construction storm water
pollution prevention controls in place and remove those that are not needed as
determined by the OAR.
3.02
CLOSEOUT
A.
Verify the following prior to Substantial Completion:
1.
Final stabilization of site has been demonstrated.
2.
There is no potential for construction related storm water pollutants to be
discharged into site runoff.
3.
Construction related equipment and temporary BMP have been removed
from site.
4.
Rubbish, debris, and waste materials have been removed and legally
disposed of off the Project site.
5.
OEHS CAN items have been closed and signed-off.
END OF SECTION