SECTION 01 7418 WATER POLLUTION CONTROL EDIT NOTES: A. THE GUIDE SPECIFICATIONS LISTS THREE SECTIONS FOR WATER POLLUTION PREVENTION. THESE SECTIONS SHOULD BE USED AS INDICATED BELOW. TOTAL LAND DISTURBANCE SHOULD INCLUDE PROJECT, STOCKPILE AND STAGING AREAS. 1. PROJECTS WITH LAND DISTURBANCE OF ONE ACRE OR MORE SHALL INCLUDE SPECIFICATION SECTION 01_7416, STORM WATER POLLUTION PREVENTION PLAN, UNLESS IT MEETS THE REQUIREMENTS OF CONDITION # 2 LISTED BELOW. 2. SITES WITH LAND DISTURBANCE WITHIN ONE TO FIVE ACRES WITH WAIVER SUBMITTED THROUGH SMARTS AND APPROVED BY THE WATER BOARD SHOULD USE SPEC SECTION 01_7417, BMP IMPLEMENTATION PLAN. 3. SITES WITH LAND DISTURBANCE OF LESS THAN ONE ACRE: a. IF SITE IS PART OF A LARGER DEVELOPMENT OF ONE ACRE OR MORE, OR IF SWPPP/NOI IS REQUIRED TO OBTAIN CHPS/LEED CERTIFICATION, USE SECTION 01_7416, STORM WATER POLLUTION PREVENTION PLAN. b. IF PROJECTS MAINTAINS ORIGINAL LINE & GRADE, HYDRAULIC CAPACITY, AND ORIGINAL PURPOSE OF THE FACILITY (I.E. MINOR TRENCHING PROJECTS, HVAC, FIRE ALARM PROJECTS, ETC.), SECTION 01_7418, WATER POLLUTION CONTROL, MAY BE USED. c. NON-MAINTENANCE PROJECTS, USE SPECIFICATION SECTION 01_7417, BMP IMPLEMENTATION PLAN. PART 1 - GENERAL 1.01 SUMMARY A. Section Includes: 1. Control runoff and pollutants from the site during construction activities. EDIT NOTE: ADD RELATED SECTIONS AS APPLICABLE TO PROJECT. B. Related Requirements: 1. PROJECT NAME SCHOOL NAME Division 01 – General Requirements. 12/09/2013 WATER POLLUTION CONTROL 01 7418-1 1.02 ACRONYMS AND DEFINITIONS 1.03 BMP Best Management Practice. CAN Corrective Action Notice. CASQA California Stormwater Quality Association. CGP NPDES General Permit for Storm Water Discharges Associated with Construction Activities. DWQ Division of Water Quality. LARWQCB Los Angeles Regional Water Quality Control Board. NPDES National Pollutant Discharge Elimination System. OEHS LAUSD Office of Environmental Health and Safety. SWPPP Storm Water Pollution Prevention. SWRCB State Water Resources Control Board. REQUIREMENTS A. B. CONTRACTOR shall: 1. Implement Good Site Management "Housekeeping". 2. Install and maintain BMPs. Insure that BMPs are designed to protect all exposed portions of the site, including: a. Erosion, Sediment, Tracking, and Wind Erosion Control BMPs. b. Non--storm Water Control BMPs. c. Waste Management BMPs. 3. Incorporate BMP activities into the Project Schedule. 4. Inform CONTRACTOR and Subcontractors personnel on the BMP procedures to prevent pollutants from entering the storm drain system, before the start of construction activities. Keep personnel informed of the BMP implementation process and of changes to the procedures. Provide record to OAR of Storm Water Topics discussed. 5. Pay fines and penalties from regulatory agencies against OWNER due to CONTRACTOR’S non-compliance with storm water regulations. OWNER shall recover costs of fines and penalties by appropriate OWNER assessment. Review of the BMPs by OAR shall not relieve CONTRACTOR from liabilities arising from non-compliance of storm water pollution regulations. Project Inspector and OEHS Inspector will conduct inspection and examination of site storm water regulation compliance. PROJECT NAME SCHOOL NAME 12/09/2013 WATER POLLUTION CONTROL 01 7418-2 1.04 SUBMITTALS A. 1.05 BMP material quality, grade, type as specified in the CASCA BMP Handbook. QUALITY ASSURANCE A. Regulatory Requirements: Comply with the following requirements: 1. National Pollutant Discharge Elimination System (NPDES) General Permit for Storm Water Discharges Associated with Construction and Lands Disturbance Activities; ORDER NO. 2009-0009-DWQ; NPDES NO. CAS000002, adopted by the State Water Resources Control Board. 2. Regulations of the California Environmental Protection Agency, State Water Resources Control Board; Los Angeles Regional Water Control Board, and local ordinances. 3. CASQA Stormwater Best Management Practice Handbook Construction Activity (BMP Handbook) current adopted edition. for EDIT NOTE: IF PROJECT IS LOCATED WITHIN JURISDICTION WITH SWPPP ORDINANCES, ADD NEW PARAGRAPH # 4 BELOW LISTING AGENCY NAME. 1.06 STORAGE AND PROTECTION A. Provide proper storage of materials and equipment to prevent rain and storm water runoff to come in contact with pollutants, such as soil stabilizers, paint or fluids from vehicles. PART 2 – PRODUCTS NOT USED PART 3 – EXECUTION 3.01 IMPLEMENTATION A. Install perimeter controls prior to starting Work at the Project site. B. Implement BMP plan to contain on-site storm water on the Project site. Provide storm drain inlet protection. Do not drain on-site water directly into the storm drain without proper BMP in place. C. Prevent pollutant discharges into the storm drain system. Prevent storm water from coming into contact with pollutants, such as sediment, material spills, or leakage PROJECT NAME SCHOOL NAME 12/09/2013 WATER POLLUTION CONTROL 01 7418-3 from storage tanks, waste containers or transfer areas. In the event contamination is found CONTRACTOR shall immediately notify OAR who will contact the OEHS. D. Protect exposed dirt, such as stockpiles, landscaping areas, and hillsides. E. Properly manage non-storm water discharges such as ground water, broken utility lines and fire hydrant testing per BMP Implementation Plan. F. Adjust BMP’s locations and layouts in accordance to construction progress to assure compliance to regulations. G. Conduct inspections of pollution prevention controls and provide Site Monitoring Report to OAR immediately if pollutants are discharged into the site runoff. CONTRACTOR shall remediate contaminated water. H. Upon Substantial Completion: Maintain and leave post-construction storm water pollution prevention controls in place and remove those that are not needed as determined by the OAR. 3.02 CLOSEOUT A. Verify the following prior to Substantial Completion: 1. Final stabilization of site has been demonstrated. 2. There is no potential for construction related storm water pollutants to be discharged into site runoff. 3. Construction related equipment and temporary BMP have been removed from site. 4. Rubbish, debris, and waste materials have been removed and legally disposed of off the Project site. 5. OEHS CAN items have been closed and signed-off. END OF SECTION PROJECT NAME SCHOOL NAME 12/09/2013 WATER POLLUTION CONTROL 01 7418-4