120611 Amoroson JV SFMTS CTS Scope 197KB 06 11 12

advertisement
June 11, 2012
S-08-9322
Amoroso / FCC / Southland JV
390 Bridge Parkway
Redwood Shores, CA 94065
650 654 1900
ATTN: Mr. Jim Benson, JBenson@SJAmoroso.com
RE:
Proposed Scope and bid of Work for SFMTA, Third Street Light Rail Program,
Phase 2 - Central Subway Chinatown Station Contract 1254
Hayward Baker (HB) is pleased to propose on the Compensation Grouting Section 31 43 14 (see attached
Bid Items) of the referenced project. We have visited the site, reviewed the plans, specifications and
addenda (thru #6). The “suggested grout pipe layout schematic” on drawings BP101-103 is the basis of
our costs. The final design is the responsibility of the specialty contractor and upon award discussions
regarding probable settlements from SEM will be needed to finalize the design. Based upon available
information it is anticipated additional holes and monitoring points (drawing BP011) will be needed, and
will be added costs at the unit prices below.
As discussed in the meeting the headhouse excavation will be stopped at approximately El. 90 for the
drilling and grout pipe installation. Utilizing 2 rigs 2 shifts we will need 8 to 10 weeks to complete. A
minimum 8 feet wide “cat walk” working platform along the wall and holes will be needed to complete the
pre-condition and the cavern excavation compensation grouting. Understanding staging area is critical, we
can compact our operations in a minimum area 20 by 30 feet by stacking containers 3 high.
In addition, HB can provide Jet Grouting and Permeation Grouting services as requested for the SEM
work. We can supply either or both cement, microfine or chemical penetration grouting.
Compensation Grouting
Items included in our proposal for this project are as follows:
 All labor, equipment, materials, and supervision to perform the drilling and “sleeve port grout pipe”
(SPGP) installation,
 Procurement, software, and Installation of Liquid Level System (LLS) for heave monitoring (with
integration into global job computer data system),
 All labor, equipment, materials, and supervision to perform the precondition consolidation grouting,
 All labor, equipment, materials, and supervision to perform compensation grouting during SEM
cavern excavation and support work,
 Testing, quality control and quality assurance for the compensation grout work as described in the
contract specifications,
 Submittals and shop drawings required for our work.
California • Colorado • Florida • Georgia • Illinois • Iowa
Maryland • Massachusetts • New Jersey • New York • North Carolina
Tennessee • Texas • Washington • British Columbia • Mexico City, Mexico
www.haywardbaker.com
SFMTA Contract 1254 Chinatown Station
Hayward Baker Grout Proposal
Page 2 of 6
Compensation Grouting Exclusions
Items specifically excluded from this proposal and to be supplied by others, at no cost to HB are as
follows:
 All concrete diaphragm wall knockouts and/or any coring required for SPGP installation,
 Any excavation support to install grout pipes & perform grouting,
 Access buy way of sidewalks and streets by crane service or other means at all times during, drilling,
grout pipe installation, preconditioning grouting and compensation grouting,
 Work platform for performing pre-conditioning and compensation grout injection from SPGP’s,
 Access to surrounding building exterior and interior lower floors for LLS instrumentation installation,
 Provision of a flat, level, stable work platform from which our operations may take place,
 Provision of water at a flow no less than 75 gpm at 50 psi for drilling and/or grouting.
 Provision of electric power up to 400 amp service at 440 volts,
 All lighting, ventilation, and noise control,
 Upon completion, SPGP removal / withdrawal, grout backfilling, & repair/seal of the diaphragm wall,
 Safety and sanitation facilities for workers,
 Any and all traffic control required for the work,
 Inspection, permits, and easements necessary to perform the work
 Additional items as further described in our general terms and conditions.
SUMMARY
HB believes that the compensation grouting process is ideally suited to the particular needs of this project.
HB has successfully utilized this technology for similar projects in the US and Europe on many occasions,
and can provide references and project lists upon request. Additionally, HB has the resources (equipment
and personnel) to adequately handle this work, and as the largest specialty foundation contractor in the
United States, we have the financial backing and bonding capacity necessary to complete this work.
Please find attached a list of HB completed soilfrac compensation projects.
HB includes the LLS monitoring in our proposal because it is critical to the control of our injection. We
have worked with GeTec (designer, manufacturer and setup) on over 8 major compensation projects to
date. Their system is capable of repeatedly providing data to 0.2 millimeters, which allows us not only
real-time settlement but also tells us if the settlement is slowing down or speeding up.
This letter and its attachments constitute HB's proposal and will be made a part of any contract between
yourselves and HB. The acceptance of the price of this Proposal shall evidence the concurrent
acceptance of all terms and conditions recited herein or incorporated by reference.
We have enclosed our Schedule of Prices and our General Terms and Conditions, herein. Our bonding
rate is one percent. If we can be of any assistance in clarifying any points in this proposal, please contact
us by phone or email below.
HAYWARD BAKER INC.
Francis B. Gularte, PE, GE
SVP Special Projects
805 933 1331
Cell 218 7317
Tim S. Avery
Marketing
925 825 5056
Cell 805 218 7307
Gary E. Taylor
VP Special Project
805 933 1331
Cell 218 7313
FBGularte@HaywardBaker.com
TSAvery@HaywardBaker.com
GETaylor@HaywardBaker.com
Hayward Baker
June 4, 2012
Chinatown Station
SFMTA Contract 1254 Chinatown Station
Hayward Baker Grout Proposal
Page 3 of 6
RELEVANT BID ITEMS TO THE GROUTING WORK (Addendum#2)
BID ITEM 1 — FIELD MOBILIZATION & DEMOBILIZATION
BID ITEM 17 — BUILDING PROTECTION
a. The Lump Sum price for Building Protection Work shall be full payment for Work and Materials indicated on
Building Protection BP Drawings and as stated in Sections 01 76 29 Protection of Existing Properties, 31 09 13
Geotechnical Instrumentation and Monitoring and 31 09 15 Structural Instrumentation and Monitoring, except
as provided under other Bid Items. Only those Items that are shown on the Building Protection BP Drawings and
related Specification Sections, will be measured for payment. Any such items required elsewhere shall be
considered Incidental to the Work of for which it is needed.
b. Estimates for progress payment purposes will be made based on the Contractor’s approved Schedule of Values,
which shall include furnishing, installing, maintaining, protecting, making measurements, interpreting, reporting,
removal, and location restoration of items compensable under this Bid Item.
c. The costs for Compensation Grout Holes and Compensation Grouting will be paid under other Bid Items
18 and 19 below.
BID ITEM 18 — COMPENSATION GROUT HOLES
a. The unit price for Compensation Grouting Holes shall be full payment for the cost of Work and Materials necessary
for investigation/surveying, drilling, pre-conditioning, pre-heaving of buildings, de-watering, tie-back cutting,
pre-grouting, and abandoning filled compensation grout holes.
b. Only compensation grout hole work shown on the Building Protection BP Drawings and related Specification
Sections, and as approved by the Engineer will be measured for payment.
c. The cost of re-drilling and casing holes, and temporary changes to driveways, walkways, and landscaping for
Compensation Grout Holes Work shown on the Drawings, is Incidental Work to this Bid Item.
d. The cost of performing compensation grouting is paid under other Bid Items.
e. Estimates for progress payment purposes will be made based on the length of the hole as indicated on the
Drawings, measured by the lineal foot, and multiplied by the unit price bid.
BID ITEM 19 — COMPENSATION GROUTING
a. The unit price for Compensation Grouting Work shall be full payment for the cost of Work and Materials necessary
for injecting compensation grout.
b. Only compensation grouting work injection Work shown on the Building Protection Plans BP Drawings and
related Specification Sections, will be measured for payment. Compensation grouting work required elsewhere
shall be considered incidental to the work of which it is a part.
c. The cost of compensation grout holes is paid under other Bid Items.
d. Estimates for progress payment purposes will be made based on the amount of grout injected, in approved grout
holes, measured by the cubic yard, and multiplied by the unit price bid.
Hayward Baker
June 4, 2012
Chinatown Station
SFMTA Contract 1254 Chinatown Station
Hayward Baker Grout Proposal
Page 4 of 6
SCHEDULE OF PRICES
The following schedule of prices is based the procedures describe herein and as further described in the
general terms and conditions attached.
Item
Item Description
Quantity
Unit
Unit Price
Total Price
BI-1
Field Mob & Demobilization
1
LS
LS
$ 0.00
BI-17
Building Protection
1
LS
LS
$ 0.00
BI-18
Compensation Grout Holes
17,310
LF
$
$ 0.00
Total: Mobilization, LLS Building Monitoring and Pre-condition grouting:
$
000.00
Item BI-1 covers cost of field mobilization-demobilization of men and equipment and jobsite setup. Item
BI-17 covers the cost and installation of the LLS system, grouting and building monitoring data
into the Project Global instrumentation system, and related computer hardware and software
required. Item BI-18 covers drilling installation of SPGP’s, pre-condition grouting to induce heave of
buildings including grout materials.
Item
BI-19
Item Description
Compensation Grouting
(grout material only)
Quantity
Unit
Unit Price
Total Price
4,725
CY
$ 0.00
$ 0.00
BI-19A
Compensation Grouting –
Monitoring 24 hours/day 7
days per week
16?
estimated
MO
$ 0.00
$ 0.00
BI-19B
Compensation Grouting –
HB super, grout engineer &
plant operator
150?
estimated
8 HR
SHFT
$ 0.00
$ 0.00
BI-19C
Compensation Grouting –
HB super, grout engineer,&
plant operator & Labor
100?
estimated
8 HR
SHFT
$ 0.00
$ 0.00
Estimated Total: Materials, Monitoring (LLS), and Compensation grouting:
$
000.00
Item BI-19 covers grout materials (cement, additives, etc.). Item BI-19A covers heave-settlement LLS
(Liquid Level System) monitoring of buildings (starting prior to excavation and continuing thru post
excavation per specifications). Item BI-19B covers standby or compensation grouting as needed utilizing
General Contractors labor (estimate 3 to 5 laborers required to handle / control packers placement,
cleaning etc. of SPGP’s and help batching, mixing and pumping operations). General Contractor provides
their labor for training during pre-conditioning work. All grouting equipment, monitoring equipment,
computer data acquisition and computer monitoring, along with grout materials are included in the above
items. With regard to Item BI-19B and/or C, a total minimum charge of 24 shifts per month applies.
Hayward Baker
June 4, 2012
Chinatown Station
SFMTA Contract 1254 Chinatown Station
Hayward Baker Grout Proposal
Page 5 of 6
GENERAL TERMS AND CONDITIONS
FACILITIES BY OTHERS
The following facilities and services are to be provided to HB by others free of all costs to HB:
Site Access: Unrestricted and uninterrupted access, ventilation, and lighting to the work site / headhouse excavation
during the period of HB's operations suitable for our equipment moving under its own power. Off-loading and
placement of equipment and supplies to and from the working surface in the headhouse.
Work Platform for Drilling: Level floor area of excavation along concrete diaphragm wall of headhouse at 1 st bracing
level as shown on drawings BP102 & BP 103 for diesel hydraulic powered crawler drills for SPGP hole locations
noted on drawing BP 101. A minimum of 25 feet working space from wall is required for drill operation and inserting
SPGP’s.
Work Platform for Grouting: A minimum 8 to 10 feet wide working platform along the headhouse concrete diaphragm
wall to allow workers with long straddle packers, connecting hoses, hose reels, small high pressure pumps, etc. to
perform the pre-condition and compensation grouting. Designed and approved by Cal-OSHA, and designed such
that water and grout runoff is routed to protect workers below.
Waste Control: Containment, removal, and disposal of waste cuttings and wash water from both drilling and grouting
operations.
Utilities: All existing above and below ground utilities, which may be affected by the work, shall be located and
exposed, removed, or relocated. The extent and location of adjacent utilities and services left in place shall be
clearly and accurately marked out on site and shown to an HB representative prior to the commencement of work.
HB cannot accept responsibility for any damage to any such utilities not thus indicated. Furthermore, it is possible
that damage may occur as a result of heave, settlement, and/or intrusion of grout due to unforeseeable condition of
the ground or utility. For this reason HBI cannot accept responsibility for damages thus caused.
Surveying: All survey of all necessary lines and grades from which HBI's work can be easily established.
Permits and Easements: All site permits and easements required to legally perform the work.
Sanitary Facilities: On-site sanitary facilities for the use of HB employees.
Site Yard: A minimum area of 650 square feet to permanently locate our material, batch, mix, pump equipment,
office and supply storage directly adjacent or inside the headhouse and site office.
Electrical: Supply of up to 400amp/440volt power for equipment, shop, office, and headhouse grouting platform.
Water: Adequate supply of suitable clean fresh water supplied to within 100 feet of HBI's operations at the rate of up
to 70 gpm.
Traffic Control: All pedestrian and vehicular traffic control including personal, signs and barricades, if and when
required.
Security: Site security for our personnel and equipment during the duration of work.
PROGRESSION OF WORK
HB's proposal is based upon carrying out the work in a continuous unobstructed manner. Two shift operations are
planned with regard to headhouse horizontal drilling and grouting work, with maintenance work on Saturdays. In the
event that HB's work is interrupted for any reason beyond our control HB shall be compensated at $3,800.00 per
shift for each crew delayed. At this present time, HB anticipates commencing work on-site within 8 weeks of receipt
of a written acceptance and approval of submittals.
Hayward Baker
June 4, 2012
Chinatown Station
SFMTA Contract 1254 Chinatown Station
Hayward Baker Grout Proposal
Page 6 of 6
PAYMENT TERMS
1.
2.
3.
4.
Progress payments will be submitted monthly and shall be payable within 30 days of the invoice date.
All amounts due, including retention (if any), will be paid in full within 45 days of completion of HB's work
regardless of the anticipated project completion date.
An interest charge of 1 percent per month and all costs of collection, including reasonable attorney’s fees
and court costs, will be added to overdue accounts.
In the event payment is withheld for reason not the fault of or within the direct control of HB then payment
shall be made at the time and in the amount originally scheduled.
STANDARD CONDITIONS
Standard Term of Subcontract: Our proposal is based upon a performing the work under a standard form of contract
(either AIA form A401 or AGC form 640) with this proposal as the prevailing contract document.
Changed Conditions: If the ground, structure, or site conditions differ from those offered at the time of bidding and
referred to in this proposal, HB reserves the right to obtain an equitable price adjustment to compensate for extra
work and impacts as a result of the changed condition.
Confidentiality: All specifications, drawings and technical data submitted by HB are to be treated as confidential and
shall not be disclosed to any third party without express written consent of HB. Such information shall remain HB's
property and be returned to HB upon demand.
Hazardous Material: In the event that Hayward Baker encounters any material on the site, as defined in 29CFR1910,
which has not been rendered harmless, HB shall immediately stop work in the area affected and report the condition
in writing to the Owner and Engineer. To the fullest extent permitted by law, the Owner and Contractor shall
indemnify and hold harmless HB, their agents, consultants, and employees from and against all claims, damages,
losses and expenses, including but not limited to attorney fees arising out of or resulting from performance of the
work in the affected area.
Labor: This proposal is based upon using union labor.
Insurance: HB will provide insurance in accordance with the contract documents.
Liability: No liability can be accepted by us, nor shall we accept as in any way our responsibility defects of any kind
whatsoever arising from a cause which is outside our immediate control or knowledge, or for any fault in the junction
between our work and subsequent work carried out by others.
Indemnity: Subject to the terms of the Liability Clause above, and to the correct soil conditions having been provided
to us prior to our work, HBI shall indemnify and insure the Contractor from and against all claims, damages, losses,
and expenses, but only to the extent of the negligence of HBI, and provided that such claim, loss damage or expense
is attributable to 1) bodily injury, sickness, disease or death, or to 2) the injury to or destruction of tangible property
(other than the work itself), and only to the extent such claim is covered under the Commercial General Liability
Policy of HBI.
Liquidated Damages: The Contractor shall not be entitled to any liquidated damage, delay damage or other time
related penalties arising from the work.
Force Majeure: HB cannot accept any liability for default or delay in the completion of the work when caused by
strike, riot, war, or Act of God or other similar circumstances beyond HB's control.
Bonds: The cost of a bond premium is not included in our contract price.
Exclusions: Any items of work not specifically included in this proposal shall not be the responsibility of HB.
Period of Acceptance: This proposal is offered for acceptance for a period of 60 days.
Hayward Baker
June 4, 2012
Chinatown Station