Blast Design; Limestone Quarry CSMM140 Surface Excavation Design Coursework 640046848 Dr A. Wetherelt March 2015 1. Introduction This report details the design for the creation and operation of a limestone quarry, with the primary goal of producing 15,000 tonnes per week of rock for use in the aggregates industry. The site has been specified as ‘greenfield’, with the only prior work conducted being 2 meters of overburden stripping – leaving 58m of workable ground before reaching the maximum specified depth. 1.1. Overall Quarry Layout While the original quarry design would employ benches of a standard size, the detection of a 3.5m weak layer, encountered at a depth of 35m, demands an adaption to ensure the layer is accounted for in blast design to produce a satisfactory blast, taking into account influenced factors such as vibration and flyrock. The bench containing the weak layer has been allocated a height of 11m to provide enough space for additional stemming within the bench to suppress the more unpredictable rock within the weak layer. An alternative overall design has also been outlined - regarding the prospect of using 5 larger benches (3x11m, then 2x12m) which would align the weak layer to the top of the third bench. The unstable weaker rock could then either be excavated via stripping or suppressed using blast covers – however analysing the comparative cost and efficiency of these methods is beyond the scope of this report. It should be noted that this layout would leave a 1m layer of unused rock at the base of the quarry, as bench heights are limited to 12m – potentially incurring a large revenue loss. Each non-critical bench has a specified width of 5m to ensure sufficient capacity to act as a ‘rockfall’ trap, with a 10.5m haul road, to satisfy the requirement of being 3.5 times the width of the largest road vehicle, in this case being a Bell B25E truck – holding a width of 3m. In combination with bench face angles of 71.57o (equal to the 3:1 blast column inclination) this gives an overall slope angle of 47.6o. The Craig Anderson F IGURE 1 – SLOPE GEOMETRY 1 CSMM131 overall slope is shown in Figure X. 1.2. Stereographic Analysis Using the software DIPS 6.0, a stereographic analysis has been conducted to investigate three sets of joints identified from core logging. The results, of which some key cases have been highlighted and are shown in Figure X, indicate that multiple TABLE 1 - PREDICTED FAILURES ; BENCH possible failure modes are likely. Separate analysis FACE have been carried out for both the overall slope angle, X, and the bench face angle, 80o. The angle of friction for the limestone has been assumed as 30o The resultant expected failure mechanisms and the corresponding orientations are shown in Table X. Risk of failure was only found when considering the bench face angle – the overall slope does not appear to incur any failures, however a planar failure is within close proximity, shown in the left diagram of Figure X, and could be possible depending on the actual friction angle. All three failure types; planar, wedge and flexural, have been identified as being likely depending on orientation. While these should not substantially impede progress, they should be monitored – with operations adapted as necessary. Bench slopes have been given a minimum width of 5m to act as rockfall traps should a failure occur on a non-critical bench, however failure of a haul road bench could be critical; reinforcement should then be investigated. While this is outside the scope of this report, it is recommended that the use of dowels or rock bolts, in addition to drainage, should be considered. F IGURE 2 STEREOGRAPHIC A NALYSIS SLOPE ANGLE PLANAR FAILURE ON LEFT , REMAINING ORDERED ACCORDING TO T ABLE X 2. Blast Setup The following sections describes to the setup of a typical column blast for the standard 9m high bench. Data for both 11m bench types (standard and weak layer) have been tabulated at the end of this section. Craig Anderson 2 CSMM131 2.1. Individual Column Geometry The column has been inclined at a ratio of 3:1 (71.56o) to reduce the back break, and the amount of boulders from the upper part of the blast. The blast hole depth used in design has then been extrapolated to accommodate this angle (via trigonometry). Burden has been taken as 3.2m for the two 11m benches, however it has been increased to 3.5m for the 9m benches. While this increase does seem counter intuitive, as there is then less space available for the column charge, the burden is proportional to the column spacing – and thus a larger burden corresponds to a greater amount of limestone blasted. To ensure this assumption is realistic, values for minimum and maximum burden have been derived using the equations below, which give values of 2.63m and 5.3m respectively. Stemming has been taken as equal to the burden. This should consist of sand or gravel, with a particle size of 4 to 9mm for optimal confinement of the explosive gases. πππ₯π √π ππ. π΅π’ππ ππ‘πππππ‘β πππ πππ₯ π΅π’ππππ = 33 (π + 0.05) × 0.95 × πππππππ π΅π’ππππ πππ₯π πππ π΅π’ππππ = βπππ πππ × (2 × + 1.5) πππππ Where dia is the blast hole diameter in mm, and ρ refers to the density of both the explosive (exp - 1.2kg/m3) and the limestone (rock – 2.5kg/m3). C is the rock constant, which has been assumed as 0.4kg/m2. 2.2. Column Layout and Timings Using the tonnage per column (341tonnes) and the required weekly amount (15,000tonnes) – the total number of columns required has been calculated and rounded up to 45. To enable a good grid arrangement, this has been increased to 48 which can then be split into two 24 column blasts each setup in a 3x8 grid. Each column holds two NONEL detonators within a cast pentolite primer to ignite the charge. Each primer is set to a standard 475ms delay utilising surface connectors of interval timings 17, 25, 42 and 67ms delays. A minimal gap of 8ms is maintained between the detonation of each charge, with connecting rows being a minimum of 50ms apart to prevent the creation of volatile fly rock. Full layouts for both standard (two free faces) and front (one free face) blasts can be seen in Appendix A, along with separate setups for specialised situations – which are detailed below. 2.3. Specific Columns 2.3.1. Decked blast It has been specified that a residential property lies 350m from the quarry, and could be affected by blast vibrations. Further detail on this is covered in a later section, however a separate column design has been established to reduce blasting via the inclusion of ‘decking’ within the centre of the column – which has been set to 12 times the 89mm diameter. Requiring an increased burden of 3.7m, the decked blast uses an additional detonator above the decking to fire the charges 25ms apart to reduce the total vibration. This increased burden also allows for less columns to be used – utilising a setup of 2x10 with separate timings for the additional detonators. Craig Anderson 3 CSMM131 2.3.2. Weak Layer bench A separate design has been established to reduce the negative impact the weak layer holds. This includes the stemming of the weak layer, which has been additionally extended to 0.5m above and below the layer. While the layer is outlined as 3.5m thick, this has been extrapolated to 3.69m to account for the incline of the charge passing through more than 3.5m of the layer. The burden has been decreased to allow more space for charge, with the hole diameter subsequently being increased to compliment this. The column grid setup remains the same as standard. 2.4. Explosive As the ground is expected to be below the water table – a typical ANFO explosive would not be appropriate. Instead, the selected explosive, ‘Centra Gold’ - a pumped bulk emulsion from Orica – has been selected for all blast designs - in part due to its specific design for use in wet blast holes, it also holds good strength and VOD values; further details can be seen in Table X. 2.5. Charge Setup TABLE 2 – E XPLOSIVE PROPERTIES The column charge is split into two sections; bottom and column charges. This is to account for the lower amount of constriction to the upper column, and thus the charge concentration has been reduced by half to minimise fly rock chances but still affect the same volume of limestone. The height of the bottom charge is taken as 0.3 times the burden. Sub-drilling has also been included, equal to 0.3 times the maximum burden, to ensure the avoidance of the creation of stumps above the theoretical grade. The amount of explosives in each section can then be derived, via the loading rate – which has been calculated using the equation below – multiplied by the length of the bottom charge section, plus 0.6 times the length of the column charge. πΏππππππ π ππ‘π = 7.85 × ( πππ 2 ) × πππ₯π 100 For the 9m benches, with a diameter of 89mm, the loading rate comes to 7.47kg/m – with the total weight summing to 57.3kg. This is accounting for the column charge being 100% of the initial loading rate, not the reduced concentration to be physically input. As the concentration is reduced under the assumption that the lower concentration will affect the same volume of rock per kg, it should then subsequently be taken as the full concentration in design - i.e. despite having 60% of the concentration, it is expected to affect as much rock as the calculated concentration within the bottom charge and thus included as the 100% value. To check the adequacy of the planned explosive amount, the volume of rock required has been calculated using the blast ratio, derived from dividing the tonnage of limestone per column (spacing x burden x blast hole depth x ρexp ) by the blast hole ratio – taken as 6t/kg Craig Anderson 4 CSMM131 for the medium limestone rock, multiplied before the explosive’s weight strength relative to ANFO; 112%. This produced a requirement of 51kg – indicating an acceptable overcharge of 6.5kg. 2.6. Vibration A residential property has been outlined as being in the proximity of the quarry with regards to which, any blast vibration must remain below 6mm/s as required by UK law. The expected blast from the most shallow 9m benches – which contain the greatest amount TABLE 3 – BLAST VIBRATION DATA of explosive and will be of the nearest proximity – has been analysed to assess the resultant PPV using the equation below. To obtain the coefficients of A and B, data was collected via an assessment by MIST (2003) on the effects of blast vibration from several UK sites. Three limestone sites were identified, with their coefficients averaged as shown in Table X. πππ = π΄ × ( πππππππ‘π¦ π·ππ π‘ππππ (π) √πΈπ₯ππππ ππ£π ππππβπ‘ )π΅ = 498.3 × ( 350π √57.34ππ )−1.34 = 2.89ππ/π The resultant value of 2.89mm/s is then substantially less than the 6mm/s limit, and is deemed sufficient. However, a further analysis of the site-specific coefficients should be conducted before this can be confirmed – utilising the decked blast design if the PPV increases significantly. Re-analysis should also be considered if any factor related to the quarry ground conditions change, or the location of the quarry boundary itself. Aperture. Vibration affected by joint sets; perpendicular & parallel minimum effect, but otherwise would act to lessen vibration 2.7. Rock Fragmentation In order to efficiently process the blasted limestone, the fragments producted must fit within a reasonable size range. A PF Impact Crusher from GALIN has been selected to simulate a reasonable range, working particularly well with limestone due to its lower strength (crusher takes up to 360MPa, as opposed to the rock’s 155MPa). With a maximum feed size of 350mm, the optimal size was taken as 200mm, with fines less than 10mm assumed as being too small to be processed efficiently. The elastic modulus has been taken as 10GPa, as limestone tends to range between 3-17GPa. As with vibration, a specific value should be obtained for a more accurate analysis before the confirmation of any designs. Craig Anderson 5 CSMM131 The fragmentation was predicted using the Kuz-Ram fragmentation analysis model, with the resultant percent passing graph shown in Figure X. The model predicts that 5% of the fragmentation will be above the maximum size of 0.35m, and 0.5% being below the minimum 0.01m. It should be noted that the oversize passing increases to 8% with the two 11m benches – however this is still deemed acceptable as the chosen crusher’s maximum size is specified for up to 360MPa rock. Considering the joint sets , sets 1 and 2 do not hold a particularly significant dip with regards to joint blocking, and though set 3 does have a dip of 49o and low spacing, it’s low persistence suggests that its influence could be significantly lower as it is not as consistently present as the others. Set 2 has then been input into the model as an approximate ‘average’ of the sets. Alternatively, the larger PFW crusher of the 120% 100% Percent Passing 80% 60% 40% 20% 0% 0 0.2 0.4 0.6 0.8 1 1.2 Size (m) F IGURE 3 – KUZ-RAM F RAGMENTATION A NALYSIS same range can take up to 500mm fragments. 3. Production 3.1. Equipment To excavate the blasted rock, an ‘R 970 SME’ crawler excavator from LIEBHERR has been selected. Using a 4.5m3 backhoe bucket meets the specification desired in the brief, and with a 7m mono boom the excavator has a maximum reach of 11.65m with the backhoe bucket – enabling it to sufficiently reach the full height of all benches. Assuming a swell factor of 80%, bucket fill factor of 90%, a cycle time of 40 seconds and excavating 7 hours/day (8 hour shift minutes general time lost), 5 days a week (254 days/year including public holidays) – with mechanical availability and utilisation taken as 85% - a single excavator could move up to 16,500tonne of limestone per week. Calculations are shown below. πππ₯ π‘ππ πππ π βπππ‘ = Craig Anderson πππ’ππ πππππππ‘π¦ (24π‘) × ππππ πππ π βπππ‘ (60 × 7 βππ’ππ ) = 4,536 π‘πππππ πΏππππππ π‘πππ (2 ππππ ) 6 CSMM131 The 4,536 tonnes is then further adapted by multiplying through both the mechanical availability and utilisation of 85% - giving 3277 maximum tonnes per shift and a weekly maximum of just under 16,500 tonnes. To get closer to the 15,000tonne target would require a smaller excavator bucket size, however this setup has been kept to satisfy the original size request while remaining close enough to the target to setup a small stockpile in case of a prolonged operation shut down. The equation used to calculate the excavation time is shown below. ππ€πππππ ππππ π‘ππ ππππ (4013π3 ) π₯ πΆπ¦πππ π‘πππ (30π ) π΅π’ππππ‘ πππππππ‘π¦ (4.5π3 ) πΈπ₯πππ£ππ‘πππ π‘πππ = = 8.23 βππ’ππ π΄π£πππππππππ‘π¦ (0.9) While the brief requests the use of four 80 tonne dump trucks, analysis has proven this to be a substantially inefficient design. Assuming a swell factor of 80%, it would take 14 passes of a 4.5m3 bucket to fill a truck – taking over 8 minutes assuming a cycle time of approximately 35 seconds. Assuming an average travel speed of 20km/h an hour (obeying standards (MiningInfo, 2015) and assuming a 10km/h loaded average speed), in addition to a 90 second dump manoeuvre, the trucks would take approximately 5 minutes to travel the 1.1km round trip, including dumping the material. This would then cause a roughly 3 minute downtime, equivalent to 37.5%, assuming another truck began loading directly upon departure. Considering that only 1 excavator is needed to produce 22,680 tonnes per week (shown below), this would be extremely inefficient both logistically and financially. Instead, an alternative setup utilising smaller articulated dump trucks is recommended – with a Bell B25E suggested, which holds a payload of 24 tonnes. Assuming the same values as before, but with a shortened dump manoeuvre of 1 minute, and a slightly higher mechanical availability of 90%, the amount of trucks required comes to 2.7, implying 3, trucks, due to a overall travel + unload time of 6 minutes with a time to fill from the excavator of 4 passes (2 minutes) aligns the trucks to be constantly in use. While these are timings are on a tight schedule, the setup is deemed acceptable due to the conservative estimations involved – coupled with the expected weekly overproduction of limestone. 4. Conclusions It should be outlined that this report outlines a recommended setup of the proposed open pit quarry. This has been largely designed based on certain assumptions, which should be further investigated before the project is set in motion. The design is also not all encompassing or the only option available – an attempt to allude to possible variations has been included where possible. Craig Anderson 7 CSMM131