Sp 2014 Office Relocation Project Proposal College of Business EBTM 450 Role of Associate Dean Played by Eric Akindana, Timothy McDowell, and Ritu Dangol EBTM 450 Professor Neeraj Parolia 5/18/2014 Executive Summary In order to prepare a preliminary project plan for the office relocation project the Associate Dean was assigned to develop a proposal to be submitted to Dean Edwards for approval. In our groups role as the Associate Dean we determined the necessary deliverables and activities that must be completed in order to have a successful project outcome. The earliest reasonable start date was May 15, 2015, with project duration of 48 days and an estimated cost of $10,900. By having the new department faculty offices grouped together it would provide synergies and necessary support for a successful launch. It was determined 11 faculty offices would be needed to house the new BA&T department. We began by identifying Dean Edwards concern, which was the cost and logistics required to bring the BA&T faculty offices together in the financial department office suite. In order to identify the costs related to specific activities we analyzed our resources as well as potential contractors and were able to determine reasonable estimates of expenses. After analyzing the cost we proceeded to develop a logistical method of executing all the required task and activities, including predecessors when necessary. 1|Page Statement of Scope After analyzing the project parameters and requirements we developed a prioritized objective of cost, time, and performance of the project. The scope of our project was to provide a synergistic environment for faculty to launch the new department by August 10, 2015 with a budget of $15,000 or less. The key limitations and parameters used to establish the scope and identify necessary activities of this proposal can be viewed below The project must be completed by the second Monday of August when faculty report to campus for the fall semester. The vacated offices in the Finance Department suite would need to be painted and the floors striped/waxed Office telephone numbers and room numbers would need to be updated in the university directory Desk chairs which are long overdue for replacement Offices are assigned based on tenure Faculty would need to determine the office furniture configuration On-campus facilities personnel can move the furniture into the proper position for each office Two offices will require construction of framed walls with doors. Faculty libraries and research documents which will need to be packed and moved No renovation work can begin until the spring semester ends the third Friday in May 2|Page Project Justification The project for office relocation is centered on identifying and solving the faculty members concerns about the physical location of their offices. The current office locations were arranged in suites based on the faculty member’s department assignment. A recent relocation of seven campus support staff from Van Alstyn to a new facility across campus made offices available in the Finance Department suite, where 11 faculty offices needed to house the new BA&T department. The faculty preferred to have their own office suite area but unfortunately there were currently no unoccupied suites large enough for all 11 faculty member. However, allocation of physical office space was not part of the initial proposal to start the new department; the Dean agreed that having the new department faculty offices grouped together would provide synergies and identity necessary to support their successful launch. Thus it became necessary for our team to take on the role of the Associate Dean, Dr. Stephens. We understood the importance of locating academic faculty offices together and took the lead in developing the proposal. 3|Page Project Estimates and Plan When we began developing this proposal our team identified that the major objective was the staff relocation process for the new department. We created a work breakdown structure using the following activities vacated offices, frame walls, frame door, offices assigned, strip floor, paint, determined furniture placement, replaced chairs, update room numbers, update phone number, set up furniture, and wax floor to develop a plan with realistic estimates for the project duration and cost. After identifying each activity needed to complete the project, research was conducted determining duration as well as the cost of each activity to be completed. The total project duration is 48 days at a cost of $10,900. The duration and cost of each activity can be viewed in the table below Task Name Duration Entire Project Allocate Specific Offices Office Assigned Vacated Offices Carpentry Frame Walls Frame Doors Finishes Paint Stripe Floor Wax Floor Office Equipment Determine Furniture Placement Replace Chairs Set Up Furniture 48 days 2 days 10 days 10 days 2 days 5 days 3 days 6 days 3 days 5 days 10 days University Directory Upgrade Cost $10,900.00 $0.00 $0.00 $1000.00 $4,500.00 $3,000.00 $1,500.00 $2,500.00 $700.00 $1,200.00 $600.00 $2,650.00 $0.00 $1,650.00 $1000.00 $250.00 Update Phone Numbers 1 day $125.00 Update Room Numbers 1 day $125.00 4|Page Our two primary resources for project completion were Barton Marlow construction (outsourced) and Internal Employees. Estimated budget calculations are below. Barton Marlow Flooring Striping and Waxing the floor are divided into two sections. To strip the floor, Cost of good totaled at $250.00. For 6 employees, labor cost is $52.78 day for 3 days totaling $1,200.00. Waxing the floor cost of gold sold is $150.00. For 2 employees, labor cost $37.50 a day for 6 days totaling $600.00. The grand total is $1,800.00 Painting Painting Cost of goods totaled at $100.00. Barton Marlow will supply 2 workers at $50.00 per day for 5 days. The grand total is $600.00. Framing Framing Walls and Doors are calculated into one price. 4 employees will work 12 days at $66.67 per hour. In addition, Cost of goods totaled at $1,300.00 bring the grand total to $4,500.000 Internal Employees Facilities will provide 2 employees to for 4 hours per day at $25 dollars an hour for 10 days at a total cost of $2,000.00.Graduate Student, Nick Sutton will be paid $25.00 per hour, working 5 hours for 2 days costing a total of $250.00. Dr. Stephens will work 4 hours for 2 days costing the project zero dollars. Faculty will three days for eight hours also costing the project zero. These costs will be included in the school budget. 5|Page Gantt Chart Task Name Duration Entire Project 48 days Allocate Specific Offices Office Assigned 2 days Vacated Offices 10 days Carpentry Frame Walls 10 days Frame Doors 2 days Start Finish Predecessors Resource Names Fri 5/15/15 Thu 7/23/15 $10,900.00 $1,000.00 Wed Thu 6/18/15 8 6/17/15 Fri 5/15/15 Fri 5/29/15 Mon 6/1/15 Mon 6/15/15 Fri 6/12/15 5 Tue 6/16/15 7 Dr. Stephens Facilities Barton Marlow Barton Marlow Finishes , 5 days Stripe Floor 3 days Wax Floor 6 days Office Equipment Determine Furniture 3 days Placement 5 days Set Up Furniture 10 days University Directory Upgrade Update Phone 1 day Numbers Update Room 1 day Numbers 6|Page $0.00 $1,000.00 $4,500.00 $3,000.00 $1,500.00 $2,500.00 Paint Replace Chairs Cost Mon 6/22/15 Wed 6/17/15 Thu 7/16/15 Fri 6/26/15 7,8,11 Fri 6/19/15 8 Thu 7/23/15 16 Barton Marlow Barton Marlow Barton Marlow $700.00 $1,200.00 $600.00 $2,650.00 Fri 6/19/15 Tue 6/23/15 4 Faculty $0.00 Wed 6/24/15 Tue 6/30/15 14 Mark Downs Office Furniture $1,650.00 Wed 7/1/15 Wed 7/15/15 15 Facilities $1,000.00 $250.00 Thu 6/25/15 Wed 6/24/15 Thu 6/25/15 19 Nick Sutton $125.00 Wed 6/24/15 4 Nick Sutton $125.00 Network Diagram 4: Office Assigned Milestone: Wed 6/17/15 5: Vacated Offices 5/15/15-5/29/15 10 Days 8: Frame Doors 6/15/15-6/16/15 2 Days 14: Determine Furniture Placement 6/19/15-6/3/15 3 Days 19: Update Room Numbers 6/24/15 1 Days 7: Frame Walls 6/1/15-6/12/15 10 Days 11: Stripe Floor 6/17/15-6/19/15 3 Days 15: Replace Chairs 6/24/15-6/30/15 5 Days 10: Paint 6/22/15-06/26/15 5 Days 18: Update Phone Numbers 6/25/15 1 Day 12: Wax Floor 7/16/15-7/23/15 6 Days 7|Page 16: Set-Up Furniture Milestone 7/1/15 1 Day Cash Flow Statement $3,000.00 $2,500.00 $2,000.00 $1,500.00 $1,000.00 $500.00 $0.00 May May May May May June June June June July July July 3, 10, 17, 24, 31, 7, 14, 21, 28, 5, 12, 19, 2015 2015 2015 2015 2015 2015 2015 2015 2015 2015 2015 2015 8|Page Recommendations Based on the estimated cost and duration to complete this project we believe this proposal will be the most efficient and cost-effective. We feel our project proposal will place the new department in a position to achieve its goal of synergy and identity necessary for a successful launch. We also believe that it is critical for the project to begin as soon as feasibly possible to ensure that there is time for unexpected and unforeseen delays. In addition because of resource constraints we strongly believe that the project should cost no more than $15,000 to complete. Many factors have been taken into consideration to develop the proposal including time, cost, scope, feasibility, and project purpose/objective. So we are confident in recommending Dean Edwards to go forward with the approval process for our project proposal. 9|Page