MANAGEMENT CONTROL POLICY:LEGIONELLA UWE _______________________________________________________________________________________________________________________________ MANAGEMENT CONTROL POLICY FOR THE MINIMISATION OF RISK FROM LEGIONELLOSIS AND LEGIONNAIRES’ DISEASE THIS DOCUMENT UAS BEEN FORMALLY APPROVED BY THE UNIVERSITY OF WEST OF ENGLAND AS PART OF THE HEALTH AND SAFETY MANAGEMENT PLAN DATE NAME POSTION Mr Phillip Kearns Estates Operations Manager / Responsible Person SIGANATURE Page 1 of 79 MANAGEMENT CONTROL POLICY:LEGIONELLA UWE _______________________________________________________________________________________________________________________________ POLICY INDEX Section Sub Section 1 Content Page Nos 1.1 1.2 Document Control Amendment Status Distribution record 2.1 2.2 2.3 2.4 2.5 Policy Definitions and Responsibilities Policy Statement Scope of policy Applicable Legislation Responsibilities Management Flowchart 3.1 3.2 3.3 3.4 3.5 3.6 Legionella Risk Management Plan Legionella Risk Assessment System Design Control Methods Legionellosis Maintenance Tasks Control Parameters and Interpretation of Results Control Documentation for Physical,Analytical and Microbiological Test Data 2 3 4 Legionella Outbreak Action Plan 5 5.1 5.2 5.3 5.4 Appendices - Technical Legionella Management and Control tasks Technical Test Data Record Sheets Closing/Opening of Building / Area Documents Out of Specification Water Quality 6.1 6.2 Appendices - Documentary Policy Receipt Document Responsibilities Notification 7.1 Appendices - Estate Estate Schedule 6 7 Page 2 of 79 MANAGEMENT CONTROL POLICY:LEGIONELLA UWE _______________________________________________________________________________________________________________________________ SECTION 1 – DOCUMENT CONTROL Page 3 of 79 MANAGEMENT CONTROL POLICY:LEGIONELLA UWE _______________________________________________________________________________________________________________________________ 1. AMENDMENT STATUS Amendment Detail Issue Date Doc Draft 1 for approval by N Cooper Sept 07 Doc Doc Draft 2 N Cooper Modifications Draft 3 31.10.07 04.08.09 Doc Draft 4 review and update Doc Issued – Modified 20 August 2012 Page Ref Page 4 of 79 Aug 2012 MANAGEMENT CONTROL POLICY:LEGIONELLA UWE _______________________________________________________________________________________________________________________________ 1.2 Distribution record This Policy Document has a controlled circulation and should not be copied without the permission of the Responsible Person. The following hold authorised copies: COPY No. AUTHORISED COPY HOLDER Each copy issued is to be signed and this is to be recorded as per the documentation contained in appendix 6.1 Page 5 of 79 MANAGEMENT CONTROL POLICY:LEGIONELLA UWE _______________________________________________________________________________________________________________________________ SECTION 2 POLICY DEFINTIONS AND RESPONSIBILITIES Page 6 of 79 MANAGEMENT CONTROL POLICY:LEGIONELLA UWE _______________________________________________________________________________________________________________________________ 2. POLICY STATEMENT It is the University of West of England Management (hereafter referred to as UWE) Policy to manage the operation and maintenance of its Domestic and Process Water in line with current best practice, complying with all current and relevant guidelines and legislation relating to the management and control of Legionellosis including Legionnaires’ Disease. Measures to be taken to attain this objective include: The appropriate selection, design, installation and maintenance of plant. The appointment and suitable training of “Responsible Person” competent to: o Liaise with all other organisations that supply UWE with services pertaining to either; Legionellosis Management and Control and/or Management & Control of Hot Water, whether accommodation, facilities management, water treatment, consultancy etc. o Identify and assess the risk of Legionellosis resulting from work activities to include breakdowns and abnormal situations. o Develop, implement and maintain appropriate and suitable Management Systems, Personnel Training Programmes and plant treatment procedures. o Develop and maintain adequate records in order to demonstrate compliance with best practice and fulfil legal obligations. o Ensure compliance with this Policy. The regular monitoring of all implemented Management Systems, Training Programmes and treatment procedures, to establish and ensure their continuing efficacy and legislation compliance. The UWE Approved Working Systems, which are to be held within this Document, have been prepared in consultation with competent persons on the interpretation and understanding and practical application of guideline and legal requirements described in current relevant guidelines and legislation relating to the management and control of Legionellosis including Legionnaires’ Disease. Responsible Person: Name: …………… Signature:……….…………………..Date: …………… Duty Holder: Name: …………… Signature:……….…………………..Date: …………… Page 7 of 79 MANAGEMENT CONTROL POLICY:LEGIONELLA UWE _______________________________________________________________________________________________________________________________ Page 8 of 79 MANAGEMENT CONTROL POLICY:LEGIONELLA UWE _______________________________________________________________________________________________________________________________ 2.2 Scope of Policy UWE attaches the greatest importance to the health, safety and welfare of staff and visitors to the site. In this regard UWE has in operation a Management Programme to minimise, as far as is practicable, the risk from Legionella bacteria. The following sections outline the approach to be adopted for the prevention of colonisation of water systems by Legionella bacteria and details a design and maintenance schedule for water systems, which may be subject to such, at the UWE sites. UWE recognises and accepts its responsibility under the Health and Safety at Work Act. This Policy applies to: 1. All Cold Water Systems: Including Mains (boosted or otherwise) or tank fed supplies, distribution systems and outlets. 2. Domestic Showers: Including tank fed showers, Mains fed showers with direct electrical heaters, emergency dowsing showers and eye wash stations. 3. Domestic Hot Water Systems: Including all direct and indirect calorifiers (primary heating coil, electric immersion heater or otherwise), cistern-type water heaters and instant water heaters (plate heat exchanges, electric or otherwise). 4. Ancillary Plant: Process and any other plant which is liable to encourage Legionella growth and/or create an aerosol. It is the Policy of UWE that: a) All new water systems shall be designed, installed and operated in such a way as to minimise, avoid or prevent the risk of Legionellosis. b) All existing water and air systems shall be operated and maintained in such a way as to minimise or control the risk of Legionellosis. No new water systems shall be introduced and no changes shall be made to water systems unless they have first been authorised by the Responsible Person. Undertakings UWE recognises its responsibility to implement in full, all requirements described in current relevant guidelines and legislation relating to the management and control of Legionellosis including Legionnaires’ Disease, particularly, the Health and Safety Commission's Approved Code of Practice – L8. UWE will undertake to: Appoint an UWE Responsible Person to enable the implementation of the requirements of this Policy. The Responsible Person will in turn appoint in writing Engineering Support Staff (Estates) for all the UWE sites: Identify and assess sources of risk from all water and ventilation systems found within all the buildings of the Estate Maintain a “Written Scheme” for preventing, reducing or controlling the risk. Page 9 of 79 MANAGEMENT CONTROL POLICY:LEGIONELLA UWE _______________________________________________________________________________________________________________________________ 1 2.2.2 Implement and manage precautions. Keep records of the precautions implemented of the premises within UWE control. The Estate For the purposes of this Policy, the Estate comprises all the buildings currently occupied, and maintained by The UWE sites. (under a full maintenance lease or otherwise). For a current list of the Estate, see Appendix 7 – UWE Estate. Other sites/buildings may, from time-to-time, be included and incorporated within the scope of this Policy. The UWE Responsible Person shall notify all landlords of leased buildings of their requirements under this Policy. 2.2.3 UWE SERVICE PROVIDERS For the purposes of this Policy, the Service Providers are organisations that supply The UWE with services pertaining to Legionellosis Management & Control, whether accommodation, and or Facilities Management, Water Treatment, equipment, Consultancy, etc. At the time of this Policy the main Service Providers for the site Legionella Programme are: Pure Group: -: Legionella Consultancy services Risk Assessment and Review Auditing, Training Remedial Work following Risk Assessment Programme Monitoring, Sampling, Reporting Chlorine Dioxide Dosing Systems Page 10 of 79 MANAGEMENT CONTROL POLICY:LEGIONELLA UWE _______________________________________________________________________________________________________________________________ 2.3 Applicable Legislation UWE, in implementing this Policy, will use, as a general source of practical help, the documents listed below: HSE ACoP L8 – The Control of Legionella bacteria in water systems – Approved Code of Practice & Guidance 2001. Health and Safety at Work etc. Act 1974, Sections 2, 3 and 4 (HSW). Control of Substances Hazardous to Health Regulations 2002, Regulation 6 (COSHH). The Public Health (Infectious Diseases) Regulations 1988. The Water Supply (Water fittings) Regulations 1999. The Water Supply (Water Quality) Regulations 2000. BS 6700:1997 - Specification for Design, installation, testing and maintenance of services supplying water for domestic use within buildings and their curtilages. Food Act 1990. Page 11 of 79 MANAGEMENT CONTROL POLICY:LEGIONELLA UWE _______________________________________________________________________________________________________________________________ 2.4 GENERAL RESPONSIBILITIES 2.4.1 EMPLOYERS DUTIES UWE as employers, have a general duty under The Health and Safety at Work Act etc. 1974 to ensure so far as is reasonably practicable, the health, safety and welfare of all their employees. HSWA 2(1) requires employers to: Provide and maintain plant and systems of work that are safe and free from health risks, Make arrangements for ensuring safety and the avoidance of health risks in connection with the use, handling, storage and transportation of articles and substances (HSWA 2(2)b), Provide such information, instruction, training and supervision to ensure the health and safety at work of their employees [HSWA 2(2)c], Provide a safe working environment [HSWA 2(2)e], Those in control of premises must ensure that they are safe and that any plan or substance do not endanger health of all persons at work and the general public (HSWA 4). Employees have a duty under Section 7 of the Health and Safety at Work Act etc. 1974 to take reasonable care for their own health and safety and of that of others who may be affected by their acts or omissions at work. Towards this end, employees should use correctly all work items provided by their employers, in accordance with their training and their instructions they receive to enable them to use the items safely. Employees' duties under Section 7 also include co-operating with their employer to enable the employer to comply with statutory duties for health and safety. Employers or those they appoint (e.g. under Regulation 6) to assist them with health and safety matters therefore need to be informed without delay of any work situation which might present a serious and imminent danger. The danger could be to the employee concerned or, if it results from the employee's work, to others. Employees should also notify any shortcomings in the health and safety arrangements, even when no immediate danger exists, so that employers in pursuit of their duties under the HSWA Act and other statutory provisions can take such remedial action as may be needed. 2.4.2 PERSONNEL TRAINING In order to allow the associated persons to act as effectively and cost-effectively as possible, all relevant and associated members of staff should be offered scheduled and appropriate training. In addition, the Institute Responsible Person, with the assistance of others, will provide as necessary inhouse training for all managers so that the procedures adopted to cope with high hazard units on their site is understood. All the appropriate Institute members of staff shall receive “Refresher” training every two-years or when there have been changes to the relevant legislation. Page 12 of 79 MANAGEMENT CONTROL POLICY:LEGIONELLA UWE _______________________________________________________________________________________________________________________________ The training should cover relevant topics such as: General knowledge on the Management and Control of Legionellosis Legal responsibilities. UWE Policy on legionella. COSHH. Monitoring Tasks. System design Cleaning and disinfection operations Inspection and auditing Recording of test data Staff with specific responsibilities for actions to control the “Risk” should be given additional training in how to carry out those particular tasks. In addition, persons who deputise should receive equivalent training to the person whose function they are covering. The training required will vary from individual to individual according to their background and responsibilities. Individual records should be kept for these staff, and staff should not be allowed to perform their duties without supervision until their training is completed. Training records should be signed by the Institute Responsible Person, except for the UWE Responsible Person themselves which should be signed by the Duty Holder. The level of knowledge should be regularly assessed and should be programmed and continuous rather than sporadic. A Qualified-Persons Register shall be drawn-up and maintained by the Responsible Person. 2.4.3 SPECIFIC TRAINING All those involved with the site Legionella Programme should undergo general Legionella Awareness Training. This should be certificated. The Responsible Person should have an extended Awareness Session to explain their roles and consequent responsibilities. The named Responsible Person need also a more theoretical qualification. The Legionella City and Guilds, or similar, is appropriate for this . Page 13 of 79 MANAGEMENT CONTROL POLICY:LEGIONELLA UWE _______________________________________________________________________________________________________________________________ 2.5 MANAGEMENT FLOWCHART 2.5.1 GENERAL It is the responsibility of any person employed by UWE (in whatsoever capacity) to comply with the requirements of this Policy. Advice on the requirements of the Policy can be obtained at any time from the Responsible Person. The person ultimately responsible for all matters relating to Legionellosis Management & Control, within the scope of this Policy, is the Duty Holder. However, the operational responsibility is delegated to UWE Responsible Person. The UWE Responsible Person is he/she with delegated specific actions, tasks and responsibilities under the Legionellosis Management & Control Programme. The UWE Responsible Person and Engineering Support Staff (Estates) are to be made aware of their responsibilities under this Policy, in writing. All service providers involved in the Legionellosis Management & Control Programme will need to demonstrate and provide evidence of training appropriate to their activities. Where there is any change in the personnel listed in the UWE Responsible Person section of this Policy, the new employee must be made aware, in writing, of the type and extent of their responsibility in relation to the Institute’s Legionellosis Management & Control Programme and receive appropriate training where necessary. Page 14 of 79 MANAGEMENT CONTROL POLICY:LEGIONELLA UWE _______________________________________________________________________________________________________________________________ 2.5.2 MANAGEMENT STRUCTURE FOR THE CONTROL OF LEGIONELLA The following flowchart defines the inter relationship between all parties responsible for the implementation and control of legionella. Page 15 of 79 MANAGEMENT CONTROL POLICY:LEGIONELLA UWE _______________________________________________________________________________________________________________________________ DUTY HOLDER Assistant Vice Chancellor John Rushforth RESPONSIBLE PERSON Estates Operations Manager Phillip Kearns Depty Responsible Person Mechanical Maintenance Engineer Nigel Cooper Maintenance Term Contractor Mitie TFM Water Treatment/Hygiene Contractor Mitie Water Staff will be properly trained and competent to carry out the appropriate measures, and UWE shall facilitate such training as is necessary. Maintenance staff who come into direct contact with potable water or structures and pipes which store or convey potable water will be appropriately trained in the principles of water supply hygiene. Page 16 of 79 MANAGEMENT CONTROL POLICY:LEGIONELLA UWE _______________________________________________________________________________________________________________________________ 2.5.3 DUTY HOLDER SHALL Have Overall Responsibility for all aspects of Legionellosis Management & Control within UWE Estate. Nominate, or cause to be nominated, in writing, a "Legionella and Risk Management Steering Committee" whose duties will be to advise on and monitor the implementation and efficacy of all Legionellosis Management & Control Programmes across all sites constituting the Estate. The Committee should consist of the Estates and Contract Management with Health & Safety Representation, and the appointed Legionellosis Management & Control Consultants and should be chaired by the Duty Holder. Appoint, in writing, the UWE Responsible Person (letters of appointment and acceptance are included in Appendix 6.2). Authorise the ratification of this Policy Document detailing the scope of Legionellosis Management & Control within UWE. 2.5.4 RESPONSIBLE PERSON SHALL Have Overall Responsibility for the Implementation of the Legionellosis Management & Control Programmes, on their site. Facilitate suitable and sufficient Risk Assessments to identify the Risk of Legionellosis on all buildings under their control and review these assessments on, at least, a two-yearly basis or when there have been major alterations to a system. Have Overall Responsibility for provision of Auditing the Legionellosis Management & Control Programmes across the Institute, and reporting all findings to the "Legionella Risk Management Steering Committee". Ensure notification for all 3rd parties who maintain water facilities to buildings and or areas occupied by UWE, of their requirements under this Policy. Ensure that all new buildings purchased and or leased by the UWE under a full maintenance lease are subjected to the scope of this Policy prior to coming on-line. Assess the training needs for training of staff involved in the Legionellosis Management & Control Management Programme and select suitable training establishments to provide approved Training Courses. Ensure personal training records are kept up to date. Carry out a Tender Process and select suitable Water Treatment/Hygiene Contractors and Consultants for the provision of services pertaining to Legionellosis Management & Control for buildings under their control. Advise the Duty Holder, via an Annual Report of the status of the Legionellosis Management & Control Programme across the UWE. Page 17 of 79 MANAGEMENT CONTROL POLICY:LEGIONELLA UWE _______________________________________________________________________________________________________________________________ 2.5.5 LEGIONELLA RISK MANAGEMENT STEERING COMMITTEE SHALL Ratify all appointments of positions of “Responsibility”. Ratify this Policy including all other relevant Documentation, Works Specifications, PPM Programmes, etc. Conduct an annual review of this Policy and issue amendments as required by the review. Consider the efficacy of all contractors commissioned on Legionellosis Management & Control and Management related projects. Monitor the efficacy of all training Programmes implemented for associated staff. Maintain a uniform Legionellosis Management & Control Programme across the UWE Estate Provide a forum of discussion and sharing of information pertaining to Legionellosis Management & Control across the UWE Estate. Put in place arrangements for reporting an outbreak or suspected outbreak of Legionella. Note: The Committee should meet at intervals necessary to reflect the work load in-hand, but at least 6-monthly. 2.5.6 UWE SERVICE PROVIDERS Carry out remedial work as indicated by UWE following Legionella Risk Assessment and further inspections. Carry out specific monitoring, sampling and testing duties and supply of chlorine dioxide as per contract and as outlined for the site Legionella Programme within this document Page 18 of 79 MANAGEMENT CONTROL POLICY:LEGIONELLA UWE _______________________________________________________________________________________________________________________________ SECTION 3 – LEGIONELLA RISK MANAGEMENT PLAN Page 19 of 79 MANAGEMENT CONTROL POLICY:LEGIONELLA UWE _______________________________________________________________________________________________________________________________ 3.1 LEGIONELLA RISK ASSESSMENTS A suitable and sufficient assessment, shall be carried out on all buildings which are owned and/or occupied by UWE under a “full repairing lease”, in order to identify and assess the risk of Legionellosis from work activities and water sources on the premises and organise any necessary precautionary measures. The Risk Assessments shall be carried out by specialists who can demonstrate they are competent and capable of carrying out this work. The specialists shall be registered with the Legionella Control Association. Systems which are susceptible to colonisation by Legionellae sp., and which incorporate means for creating and disseminating water droplets, shall be identified, and the risk they present will be assessed. Risks shall be assessed not just for the routine operation of the system, but also in unusual circumstances, breakdown, abnormal operation, and commissioning. The main objective of the Risk Assessment shall be to institute management procedures to ensure that compliance is continuing and not notional and to demonstrate that management has identified all the relevant factors, has instituted corrective or preventive action, and is monitoring that the plans are being implemented. In addition, the Risk Assessment shall identify: The risk to health, i.e. whether the potential for harm to health from exposure is reasonably foreseeable unless adequate precautionary measures are taken. What measures for prevention, or adequate control to minimise the risk from exposure to Legionella, should be taken. The assessment shall include identification and evaluation of potential sources of risk and: the particular means by which exposure to Legionella from hot water is to prevented; or if prevention is not reasonably practicable, the particular means by which the risk from exposure to Legionella from hot water is to be minimised. Where the assessment demonstrates that there are no reasonably foreseeable risks or that risks are insignificant and unlikely to increase, no further assessment or measures are necessary. However, the assessment shall be reviewed bi-annually and any necessary changes implemented or where there is reason to believe that the original assessment may no longer be valid. This may be because of, for example: changes to the plant or water or its use; changes to the use of the building in which it is installed; the availability of new information about risks or control measures; the results of checks indicating that the control measures are no longer effective. The Risk Assessment shall include the following areas of the systems: Page 20 of 79 MANAGEMENT CONTROL POLICY:LEGIONELLA UWE _______________________________________________________________________________________________________________________________ 3.1.1 COLD WATER SERVICES Storage Location, access and physical condition and hygiene standard of all domestic Water Storage Tanks Design and configuration of all domestic Water Storage Tanks. Capacity requirements and available storage capacities of all domestic Water Storage Tanks. Temperature profiles of all domestic Water Storage Tanks. Biological activities of all domestic Water Storage Tanks. Water Supply Regulations parameter compliance of all domestic Water Storage Tanks. Distribution Location, access and physical condition of all domestic distribution pipe-work (where accessible). Design and configuration of all domestic distribution pipe-work. Temperature profiles of all domestic distribution services and outlets. Biological activities of all distribution services. Presence of dead-legs and areas of low-flow within all the domestic distribution services. Usage considerations of all domestic distribution services. 3.1.2 HOT WATER SERVICES Hot Water Generation and Storage Location, access and physical condition of all domestic Hot Water Generating Units. Design and configuration of all domestic Hot Water Generating Units. Temperature profiles of all domestic Hot Water Generating Units, to include; flow, return and drain temperatures. Capacity requirements and available storage capacities of all domestic Hot Water Generating Units. Presence of temperature stratification within domestic Water Storage Calorifiers. Biological activities of all domestic distribution services. Distribution Physical condition of all domestic distribution pipe-work (where known / accessible). Page 21 of 79 MANAGEMENT CONTROL POLICY:LEGIONELLA UWE _______________________________________________________________________________________________________________________________ Design, configuration and accessibility of all domestic distribution pipe-work. Temperature profiles of all domestic distribution services and outlets. Biological activities of all domestic distribution services. Presence of dead-legs and areas of low-flow within all the domestic distribution services. Usage considerations of all domestic distribution services. 3.1.3 Presence of space-heating within all domestic distribution pipe-work. Condition, temperature profiles and operation status of all showerheads within all domestic distribution services. Presence of undesired lengths of blended water pipe-work within all domestic distribution services. Presence of undesired lengths of blended water pipe-work within all associated distribution services. Temperature profiles of associated "direct-fed" distribution services and all "blended" outlets. THERMOSTATIC MIXING VALVES (TMVs) Condition of all TMVs fitted. Temperature profiles of all water dispensed from TMVs. Accessibility of all TMVs fitted. Installation and operation status of all TMVs fitted. 3.1.4 MANAGEMENT, MAINTENANCE, MONITORING AND RECORD KEEPING Presence of and adequacy of all implemented Monitoring and Maintenance Programmes in place. Presence of and adequacy of all implemented Record Keeping Programmes in place. Presence of and adequacy of all implemented Auditing Programmes in place. All areas listed above shall be measured and a risk rating given indicating the contribution of each area to the overall Risk. Page 22 of 79 MANAGEMENT CONTROL POLICY:LEGIONELLA UWE _______________________________________________________________________________________________________________________________ 3.1.5 CURRENT RISK ASSESSMENT STATUS The Responsible Person shall ensure that Legionella Risk Assessments are carried out and will be required to maintain a record of these. In addition, a “Current Risk Assessment Status” listing shall be maintained for the site. 3.1.6 INTERIM REPORTS For all buildings/areas assessed to be of Moderate Risk or higher, the Risk Assessor shall issue an “Interim Problem Notification Form” indicating any necessary immediate corrective and remedial actions that need to be carried out. In addition, the “Interim Problem Notification Form” shall indicate the Short/Medium-term and Long-term corrective and remedial actions that need to be carried out. 3.1.7 PREPARATION OF AN ACTION PLAN On completion of the Risk Assessments, the Responsible Person shall undertake the following: Consider the Risk Assessments, Interim Problem Notification Form Reports and Consultancy Memoranda pertaining to each building, and ensure the design, arrangement, implementation and management of all necessary Remedial Works required to allow the systems to comply with the current and relevant guidelines and legislation, and to ensure minimisation or control of the prevailing risk. Consider the Risk Assessments, Interim Problem Notification Form Reports and pertaining to each building, and ensure the design, arrangement, implementation and management of all Pre-Planned Maintenance Programmes required to allow the systems to comply with the current and relevant guidelines and legislation, and to ensure minimisation or control of the prevailing risk. Page 23 of 79 MANAGEMENT CONTROL POLICY:LEGIONELLA UWE _______________________________________________________________________________________________________________________________ 3.2 SYSTEM/PLANT DESIGN, INSTALLATION AND MAINTENANCE 3.2.1 GENERAL DESIGN AND INSTALLATION CONSIDERATIONS All water using equipment that can affect the water supply, the environment and the user shall be monitored regularly and be subjected to the following regime: All designs must be carried out and presented in accordance with all relevant and current Guidelines, British Standards and “best-practices”. The systems shall be carefully designed to eliminate or minimise aerosol production and excessive water retention. They must also be designed to be readily drained and cleaned. No materials used in construction shall include those that are known to harbour or provide nutrient for bacteria. Any materials that come into contact with the water in a hot and cold water installation shall comply with the requirements of the Water Supply (Water Fittings) Regulations 1999. (The list of products and materials that have been assessed for compliance with the Water Supply (Water Fittings) Regulations 1999 requirements are listed in the current edition of Water Fittings and Materials Directory that is updated every six months. Further information on the selection of materials can be found in BS6700 and BS6920. The use of flexible braided rubber hoses shall be discouraged in the installation of facilities, and only WRAS approved hoses will be allowed. Preference should be given to fixed pipe-work, constructed from materials in use within the system. The systems as identified by risk assessment shall be maintained in a clean and sound condition and must be easily and safely accessible. All systems shall be frequently used (at least weekly), or suitably flushed to simulate the necessary usage frequency, in order to avoid stagnant water which will increase the potential of bacterial growth and proliferation. The usage frequency shall be regularly monitored and reported upon. All plant and distribution pipe-work (where accessible) shall be clearly labelled. 3.2.2 COLD WATER STORAGE TANKS Cold water storage tanks shall be constructed from non-deleterious materials which must be WRc approved. Cold water storage tanks shall be designed in accordance with BS6700 (glass-reinforced plastic (GRP) tanks should comply with BS7491 Parts 1, 2 and 3), installed in appropriate and suitable locations to allow easy and safe access to facilitate inspection and maintenance. Sectional Cold Water Storage tanks shall be designed with external assembly flanges and selfdraining profiles, since this arrangement facilitates easy cleaning of internal surfaces. Externally located Cold water storage tanks shall be suitably protected from environmental conditions, particularly the local high ambient temperatures for all new buildings and, where practicable, for existing installations. Ventilation shall be achieved by means of louvered doors fitted with insect screens. Cold water storage tanks shall be protected from the ingress of light, insects and birds. Cold water storage tanks shall be sized and arranged so as to minimise retention time of stored water (24hrs maximum), and therefore to increase the rate of stored water exchange. Page 24 of 79 MANAGEMENT CONTROL POLICY:LEGIONELLA UWE _______________________________________________________________________________________________________________________________ Cold water storage tanks shall be subjected to a “need” test which requires the user to question the presence of each unit and consider its removal if the services it supplies can be, equally well, supplied by converting the systems to domestic Mains fed only. Each unit shall be subjected to an annual “drop-test”, or metered equivalent, designed to ascertain the capacity and demand requirements of each system, in order to ensure that excessive volumes of water are not unnecessarily stored. Eliminating storage within a system would also allow the negation of the necessary PPM Programme tasks and their replacement with much less onerous, more infrequent and less costly tasks to be carried out. All associated pipework and valves should be adequately insulated and clearly labelled to identify their purpose. Where Cold water storage tanks are linked “in parallel”, each feed to each tank shall be fitted with a water meter in order to allow for confirmation of equal and uniform usage from all tanks in the configuration. Various arrangements of pumping systems are indicated in BS6700. Where booster pumps are to be installed, a break cistern will be required between the mains supply pipe and the pumps. This is required in order to comply with the Water Supply (Water Fittings) Regulations 1999 with regard to prevention of backflow. Control of the pump(s) should be fully automatic in operation and controlled by pressure sensors. Where two or more pumps are installed, the design flow should be achieved with one pump stationary (or out of service). Automatic control should be provided to cyclically and sequentially control all pumps to ensure that each is regularly brought into service. Cold water storage tanks shall be maintained in good condition, clean from excessive corrosion, sludge deposition, scale deposition. Stored water shall be maintained at a temperature of ≤20oC or <2oC above the supply). Where indicated and when it is deemed necessary and practicable, Cold Water Storage Tanks shall be upgraded, refurbished, modified or replaced so that they may comply with current Water Supply (Water Fittings) Regulations 1999. Following these works, each tank shall be cleaned and disinfected in accordance with BS6700 and L8 prior to it being allowed back into service. Cold Water Storage Tanks shall be subjected to periodic monitoring to include: Temperature monitoring. General physical inspections. Cold Water Storage Tanks shall be subjected to a clean and disinfection, when the results of the monitoring indicate the need. Page 25 of 79 MANAGEMENT CONTROL POLICY:LEGIONELLA UWE _______________________________________________________________________________________________________________________________ 3.2.3 HOT WATER CALORIFIERS Calorifiers shall be installed in appropriate and suitable locations to allow easy and safe access to facilitate inspection and maintenance. Where more than one Calorifier or heating device is used, they shall be connected in parallel, taking care to ensure that the flow can be balanced so that the water temperature from all the Calorifiers exceeds 60°C at all times, except for short periods of high demand. The combined storage capacity and heater output must be sufficient to ensure that the outflow temperature, at continuous design flow (at least 20 minutes) from calorifiers or other heaters, should not be less than 60°C. This applies to both circulating and noncirculating hot water systems. The positioning of the control and high limit thermostats, cold feed and return water connections must ensure that these temperatures are achieved. Means should be taken to prevent warm water entering the cold-feed. A check valve shall be provided in the cold feed, as close to the calorifier as practicable, to prevent such circulation. However, the installation of such a check valve shall not be carried out in systems that use the cold feed for expansion. In these cases, the installation of a U-bend or S-bend in the cold-feed, sufficient distance from the connection to the calorifier, so that water which is warm is not displaced (on heating up) beyond the bend and the vertical pipe rise shall be carried out. On new installations expansion vessels shall be located on the cold feed rather than on the hot water side of the system. The length of pipework between the expansion vessel and cold feed shall be as short as practicable, e.g. less than 1 meter. Expansion vessels shall be subjected to a weekly flushing regime (if practicable). Ensure that the diaphragm (or bag) is not damaged during the process. Risk Assessments should be carried out on vessels to determine whether they pose a risk. The practice of terminating the air vent over the Water Storage Tank shall be discouraged. The vent should be arranged to discharge over a separate tun-dish arrangement, with visible Type A air gap, sited at a level that takes account of the hydrostatic head of the system. The calorifier or water heater should be provided with a suitable safety valve of appropriate size and vacuum release arrangement. Where water quality indicates the need, cathodic protection from galvanic action by means of sacrificial anodes shall be provided. Calorifiers should be fitted with a de-stratification pump, where necessary, in order to avoid temperature stratification of the stored water. Some semi-storage/high-efficiency Calorifiers are supplied with an integral pump that circulates water in the Calorifier. Destratification pumps shall not be fitted to this type of unit. A single circulating pump shall normally be installed in the return. If, for reasons of reliability, two pumps are installed in parallel they shall be arranged to have individual nonreturn and service valves and be controlled such that each one is brought into operation every seven days. It is also allowable to have a system utilising one pump ion line, with a (disconnected) spare available for immediate replacement as required. When Calorifiers are isolated from the system (for whatever reason), the associated distribution system shall be subjected to DAILY flushing. However, this is only necessary when the Calorifier isolated is the sole supply of HWS to that distribution system. Where more than one Calorifier supplies the distribution services, the isolated calorifier shall be drained down and allowed to remain drained whilst off line. Page 26 of 79 MANAGEMENT CONTROL POLICY:LEGIONELLA UWE _______________________________________________________________________________________________________________________________ A suitably sized drain shall be connected to the base of each calorifier (where practicable). Calorifiers shall be maintained at the following temperature profiles at all times: Stored /Flow at ≥60.0oC. Return /Outlets at ≥50oC. In order to ensure that the temperatures required to achieve thermal disinfection (>60ºC for the “Flow” and >50ºC for Outlets) are maintained, it is important to ensure that: 1. 2. 3. Ideally, the Calorifiers should be allowed to operate continuously ensuring that the heat source is available constantly. Where the Primary Heating Source is not set by a timer, the heating source should be left ‘on’ at all times. Where the Timers are fitted and operated and cannot be removed, it is important to ensure that the units are allowed to operate at a temperature of (min) >60ºc for at least 1 hour from, when they come ‘on line’, before any water is drawn from them. Where a building is to remain un-occupied, the calorifier should be emptied and pasteurised before being allowed back ‘on-line’. Calorifiers shall be subjected to regular check for “Flow” and “Return” temperature. Cistern-type water heaters shall be maintained such that the cold tank part of the heater is kept clean and at the correct temperature, and the hot tank part maintained at a temperature of >60.0 oC allowing for distribution temperatures of >50.0oC. A screened vent and an insect/rodent overflow screen shall be fitted to the tank part of the units. Instant water heaters (less than 15 litres in volume), including combination boilers, usually store small water volumes, and because of this they do not usually need to be operated within the temperature profile and limits prescribed for larger systems (≥60 oC for the ‘flow’ and (≥50 oC for the ‘return’ and ‘outlet’) which are necessary for thermal disinfection. These units can, therefore, be operated at “safe” temperatures of ≤41.0oC although they should be switched-on at all times to ensure and encourage adequate use. Infrequent use of these units (less than twice-weekly) would increase the potential of bacterial growth and proliferation (as would be the case in all infrequently used areas throughout the system – both hot and cold), although particularly in this case because of the low temperatures where operated. Calorifiers shall be subjected to inspections for water quality, calorifier physical condition, temperature and bacterial activity (when necessary). Calorifiers shall be subjected to a regular blow-down and flush via the drain point where fitted. Cleaning, flushing and pasteurisation shall be carried out in the event of major modifications or after a period out of service, before Calorifier is returned to service. Pasteurisation shall also be carried out when the stored water temperature falls below 45.0 oC for more than 1 hour before the Calorifier is returned to service. 3.2.4 HOT WATER AND COLD WATER DISTRIBUTION SYSTEMS The design and installation of the hot and cold water distribution system shall comply with the Water Supply (Water Fittings) Regulations 1999 and BS6700. The design of the pipework shall ensure that there is no possibility of a cross-connection between installations conveying potable water and an installation containing non-potable water or water supplied from a private source (untreated). There shall be no possibility of backflow towards the source of supply from any tank, cistern or appliance, whether by back siphonage or otherwise. All cold distribution pipework, mains and tank down feeds shall be located, as far as is Page 27 of 79 MANAGEMENT CONTROL POLICY:LEGIONELLA UWE _______________________________________________________________________________________________________________________________ practicable, to minimise heat gains from their environment. Pipework shall not be routed through hot ducts or run adjacent to heat sources, such as radiators. All pipework shall be insulated, except for any exposed final connections to facilities, and should be arranged to eliminate or minimise dead-legs. As far as possible, the objective shall be to design the cold water systems to ensure that the inlet, outlet and surface water temperatures of cold water storage tanks are not greater than 20°C or two degrees above that measured at the main water meter. At cold water draw-off points, a temperature of 20°C or 2°C above the temperature measured in the source cold water storage tanks shall be reached within one minute. Stagnation shall be avoided. Hot and cold water services shall be sized to provide sufficient flow at draw-off points. The aim shall be to promote turnover of water by means of; the design of the distribution circuitry, adequate usage and avoidance of “disused” areas. Separate, human, drinking water systems should normally be provided directly from the mains without storage, with stored cold water (down service) being used solely for supplies to WCs, wash hand basins, etc. The supply shall not be softened. Additionally, it shall be established that the usage is sufficient to avoid deterioration in water quality, for example, that the inlet water temperature does not exceed 20OC and that the outlet does not remain unused. Stored Water at UWE is considered fit for potable use. The water supply to vending equipment shall be taken from a potable supply up stream of a regularly used outlet with the minimum of intervening pipe run i.e. less than 3 metres. The supply shall not be softened. Additionally, it shall be established that the usage is sufficient to avoid deterioration in water quality, for example, that the inlet water temperature does not exceed 20OC and that the outlet does not remain unused. Designated drinking water systems and outlets water temperatures shall be measured at regular intervals. Temperatures must be aimed to be maintained within +/- 2oC from incoming mains water temperature. Temperature monitoring must be supported with periodic microbiological analysis for the presence of E.coli and/or presumptive coliforms (from representative locations). The equipment shall be positioned so that the warm air exhaust does not impinge directly on taps or hoses supplying cold water. The domestic hot water system shall not be used for heating purposes. This includes all radiators, towel rails, heated bedpan racks etc, whatever the pipework configuration. Central “common blending” systems shall not be used unless all showers are used on a regular basis, since the length of distribution pipework containing water in the temperature range that supports bacterial growth and proliferation would far exceed the maximum permissible lengths mentioned above. A representative number of outlets, both CWS and HWS, shall be measured at least once annually and a representative number ("direct" fed Sentinel taps) shall be measured at monthly intervals. Temperatures shall be measured after two minutes for the CWS and one minute for the HWS at full flow and be maintained at <20oC and >50oC respectively. Temperature monitoring shall be supported with regular microbiological sampling when considered necessary. Page 28 of 79 MANAGEMENT CONTROL POLICY:LEGIONELLA UWE _______________________________________________________________________________________________________________________________ 3.2.5 THERMOSTATIC MIXING VALVES The temperature from sentinel outlets shall be measured on a monthly basis and maintained at: 41oC for showers 41oC for basins The pipe-work length from the TMV to the outlet shall be restricted to a maximum of two metres. All TMVs shall be fitted with strainers, (but only if a regular cleaning regime can be guaranteed) isolation valves and non-return valves. All TMVs shall be accessible (as far as reasonably practicable). All TMVs fitted to showers shall be inspected and subjected to a fail-safe test on a six-monthly basis (carried out as described in the manufacturer’s instructions). All TMVs shall be subjected to a strip-down, cleaning and disinfection when necessary as indicated by the results of the inspection programme. 3.2.6 INFREQUENTLY USED OUTLETS Management staff shall have the responsibility of identifying all infrequently used outlets within their area and subjecting these to a weekly flushing programme as described in Deadleg Flushing Pro-Forma, see Appendix 5.2. The completed forms shall be retained within the log-book for the site. Where infrequently used facilities are deemed to be no longer required, they should be removed. Where a building or sections of the system remain unused for long periods of time, the following steps shall be undertaken as follows: Flush all water facilities (including toilet and urinal cisterns) thoroughly on a weekly basis whilst the building is not in use. If the facilities within a building are to remain unused for a prolonged period (more than one month), then the system shall be drained down (including all vessels) and cleaned and disinfected (any calorifiers are to be pasteurised) prior to being allowed back ‘online’ N.B. For the “Area Closure and Opening Process and Dead-leg Flushing Pro-Forma, see Appendix 5.3. Consideration shall be given to isolating the unused sections from the system and possibly removing pipe-work and fixtures completely to avoid "dead-legs". In addition to the flushing regime described above, careful consideration should be given to the usage requirements of the system and any required system changes made accordingly. If it is deemed that the facilities are being used seasonally or remain unused for prolonged periods of time, then the following should be considered where practical: Re-engineer the system so that all CWS throughout the system are provided directly off the MCWS supply. This action will enable the isolation and removal of any cold water storage tanks As part of the re-engineering of the CWS, it is also recommended that any water storage calorifiers are isolated and removed from the system and replaced with the Page 29 of 79 MANAGEMENT CONTROL POLICY:LEGIONELLA UWE _______________________________________________________________________________________________________________________________ required number of ‘mains’ fed instantaneous, point-of-use or multipoint water heaters of less than 15 litres in volume. The absence of water storage vessels will reduce the inherent risk of storing stagnant water although it would not negate the need for flushing the remaining system. Fire hose-reels which are supplied by the Domestic Mains, where the line supplying the hose-reels is quite exclusive, distinct and separate from the line supplying domestic facilities, the fire line shall be fitted with a suitable RPZ valve. Where the fire and domestic supplies share the same line, each hose-reel spur shall be fitted with a double check valve. It is important, however, to ensure that the valves are fitted as close to the domestic line as possible in order to ensure that the dead-leg up-to the valves is kept as small as possible. Although the removal of fire hose-reels and their replacement with local fire extinguishers is the ideal solution, this may not be readily practicable in some cases where the above alternatives may be suitable. Where the installation of RPZ or double check valves is not practicable, each unit shall be subjected to a Weekly flushing regime in order to minimise stagnation and the potential for increased bacterial proliferation. Regular checking of the hose-reels, for operational integrity, shall be maintained. This task, however, shall be carried out with due care and attention – ensuring that the creation of aerosols is maintained as practicably low as possible. Plumbed eyewash units should be flushed weekly to reduce bacterial contamination and to verify proper operation. The water in a self-contained (bottle) eyewash station must be refilled, disposed, and maintained in accordance with manufacturer’s instructions. Emergency showers should also be flushed weekly to clean the line and verify proper operation. 3.2.7 SHOWERS All showers (shower-heads and associated hoses) shall be maintained in a good and clean condition and free from excessive scale and dirt deposition. In all user areas, all showers, which have a hot and cold supply, shall be fed via TMVs which shall be maintained and operated at 41oC. Central “common blending” shower-block systems shall not be used and all pipe-work length from the TMV to the shower-head shall be restricted to a maximum of two metres. Where “common blending” shower-block systems are already in place and showers are not in regular use. Each system shall be fitted with a solenoid valve (at the furthest point from the mixer valve), programmed to automatically purge water for a three minute period each day. All showers which have a hot and cold supply shall be subjected to regular temperature monitoring. The temperature monitoring shall be supported with regular microbiological testing. All shower-heads shall be inspected on a quarterly basis and de-scaled, cleaned and disinfected. The disinfection process shall include all associated hoses. Where biological results indicate significant local bacterial contamination, the contaminated shower shall be removed from use and chlorinated. Page 30 of 79 MANAGEMENT CONTROL POLICY:LEGIONELLA UWE _______________________________________________________________________________________________________________________________ 3.3 PRIMARY METHODS OF CONTROL 3.3.1 PRIMARY METHOD OF BACTERIAL CONTROL - TEMPERATURE This is achieved by keeping domestic cold water at temperatures of less than 20 oC and hot water at temperatures, when supplied from water heaters of greater than 15 litres in volume, of more than 60oC and more than 50oC for the stored and distribution services respectively. In order to ensure maximum efficiency of the Thermal Disinfection method, it is important to keep all systems clean and well used at all times and at the correct temperatures. The efficacy of the bacterial control methods shall be monitored by the implementation of a suitable monitoring and reporting Programme which shall encompass all water systems across all sites. During specific circumstances, when “Thermal Control” or Water Treatment is shown, by the various PPM Programme Monitoring Tasks, to be failing, the water quality shall be maintained by ensuring the shot-dosing of a suitable disinfecting agent, the levels of which must be maintained within the recommended limits for achieving disinfection as specified within the current edition of BS6700: Clause 3:1:10:1997 and L8 – The Control of Legionella bacteria in water systems – Approved Code of Practice & Guidance 2001. 3.3.2 CONTINUOUS ONLINE DOSING OF WATER SYSTEMS – BOWER ASHTON Where temperature control has been shown to be ineffective then an alternative method based on the use of chlorine dioxide shall be implemented. Disinfection of the water is carried out by the automatic dosing of chlorine dioxide into the water. Continuous monitoring of chlorine dioxide levels is undertaken with the intent of maintaining a minimum of 0.1mg/l as Chlorine Dioxide at the outlets. In the event that this function is undertaken by contractor it will be expected that the contractor will arrange for this monitoring to take place and will also undertake a call out procedure to investigate low chlorine dioxide levels. Routine maintenance and monitoring of the chlorine dioxide dosing system is to be undertaken monthly. Running through taps to ensure that chlorine dioxide is present is also to be undertaken at sentinel outlets every month utilising site report sheet. Page 31 of 79 MANAGEMENT CONTROL POLICY:LEGIONELLA UWE _______________________________________________________________________________________________________________________________ 3.4 LEGIONELLA MAINTENANACE TASK FREQUENCIES As a minimum standard UWE have adopted the following tasks and frequency of tasks that are required to comply with L8. Task Problem Notification System Alterations Frequency Interim Problem Notification AS REQUIRED Plant/System Alterations and Modifications Notification AS REQUIRED Temperature Monitoring 6 MONTHLY General Inspections 6 MONTHLY Biological Monitoring 6 MONTHLY Clean and Disinfection ANNUAL Temperature Monitoring MONTHLY General Inspections 6 MONTHLY Biological Monitoring 6 MONTHLY Clean and Disinfection/Pasteurisation AS REQUIRED Temperature Monitoring MONTHLY General Inspections MONTHLY Biological Monitoring MONTHLY Clean and Disinfection AS REQUIRED Temperature Monitoring QUARTERLY General Inspections QUARTERLY Biological Monitoring QUARTERLY Shower Head Clean and Disinfection QUARTERLY Flushing WEEKLY Fault Notification MONTHLY Plant Service Visit 6 MONTHLY Chemical Residual Testing MONTHLY Selected outlets 6 MONTHLY Failing Systems AS REQUIRED Selected outlets 6 MONTHLY Failing Systems AS REQUIRED Cold water storage tanks Water Storage Calorifiers Distribution Systems (*Sentinel Outlets) Showers & Mixer Valves Dead-Leg/Areas of Low-Flow Defect Log Completion Chlorine Dioxide Legionella Testing TVCC Testing Page 32 of 79 MANAGEMENT CONTROL POLICY:LEGIONELLA UWE _______________________________________________________________________________________________________________________________ All Remedial Works and Pre-Planned Maintenance Work, whether carried-out by appointed Contractors or by The UWE personnel, or otherwise, shall be carried out in accordance with the following requirements and shall: Comply with ACoP L8 – “The Control of Legionella bacteria in water systems – Approved Code of Practice & Guidance 2001”. Comply with Control of Substances Hazardous to Health Regulations 1999, Regulation 6 (COSHH). Comply with all the legal requirements of this document. Comply with this Policy and use the Reporting and Logging Programme employed on site. Only those persons who have appropriate training and can demonstrate competency in Legionellosis management to be allowed to work on UWE systems. All measuring equipment and fixed sensors shall be adequately and validly calibrated and accompanied by a current calibration certificate. Appropriate temperature “correction factors” shall be applied to surface temperatures Refer to BSRIA Application Guide AG 4/94 – Guide Legionellosis – temperature measurements for hot and cold water services. All biological analysis shall be carried out by a suitably UKAS accredited laboratory. Page 33 of 79 MANAGEMENT CONTROL POLICY:LEGIONELLA UWE _______________________________________________________________________________________________________________________________ 3.5 CONTROL PARAMETERS AND INTERPRETATION OF RESULTS 3.5.1 TEMPERATURES: COLD WATER TEMPERATURES Mains Cold Water: Boosted Cold Water: Tanked Cold Water: Sentinel Outlet Cold Water: Maximum 20oC * * Maximum 20oC * Maximum 20oC* Maximum 20oC or 20 C above supply temperature HOT WATER TEMPERATURES Storage Calorifier “Set” point: Storage Calorifier “Flow”: Storage Calorifier “Return”: Storage Calorifier “Drain”: Storage Calorifier “Cold-feed”: Sentinel Outlet Hot Water: Minimum 60oC Minimum 60oC Minimum 50oC Minimum 50oC Maximum 20oC Minimum 50oC Cistern-type Water Heater “Set” point: Cistern-type Water Heater “Flow”: Cistern-type Water Heater “Cold-feed”: Sentinel Outlet Hot Water: Minimum 60oC Minimum 60oC Maximum 20oC Minimum 50oC Instant Water Heater (>15 litres) “Set” point: Instant Water Heater (>15litres) “Flow”: Instant Water Heater (>15litres) “Cold-feed”: Sentinel Outlet Hot Water: Instant Water Heater (<15litres) “Set” point: Instant Water Heater (<15litres) “Flow”: Instant Water Heater (<15litres) “Cold-feed”: Sentinel Outlet Hot Water: Minimum 60oC Minimum 60oC Maximum 20oC Minimum 50oC Comfort Comfort Maximum 20oC Comfort BLENDED WATER TEMPERATURES Maximum 41oC Maximum 41oC Showers: Basins/Sinks: 3.5.2 MICROBIOLOGICAL ANALYSIS PROCEDURE - WHEN AND HOW TO SAMPLE DOMESTIC WATER SYSTEMS? In general biological sampling will only be carried out on an 6 monthly basis which will be dependant on the failure of other control measures such as temperature and usage. This will normally be notified as required by the Water Treatment contractor. However a set of samples should be taken 6 monthly on a small number of outlets for Legionella Pneumophilia testing., This is to establish the efficacy of the primary control measure, and may be discontinued when an established pattern of negative samples is established. Page 34 of 79 MANAGEMENT CONTROL POLICY:LEGIONELLA UWE _______________________________________________________________________________________________________________________________ Sampling must be carried out in accordance with the relevant sample collection protocols. Sampling from tanks must be carried out as far from the inlet as possible. Page 35 of 79 MANAGEMENT CONTROL POLICY:LEGIONELLA UWE _______________________________________________________________________________________________________________________________ RESULTS INTERPRETATION – WHAT DO THE RESULTS MEAN – DOMESTIC WATER SYSTEMS? Legionella Pneumophilia <102cfu/l >102cfu/l - <103cfu/l >103cfu/l - <104cfu/l Border Line Significant Highly Significant T.V.C.C. (at either 22oC or 37oC) <102cfu/ml >102cfu/ml - <103cfu/ml >103cfu/ml Insignificant Border-Line Significant Escherichia coli and Pseudomonas aeruginosa <1cfu/100ml >1cfu/100ml Insignificant Significant Page 36 of 79 MANAGEMENT CONTROL POLICY:LEGIONELLA UWE _______________________________________________________________________________________________________________________________ 3.5.3 RESULTS REPORTING – HOW AM I TOLD ABOUT THE RESULTS? Sample Collected Sample to laboratory within 24 hrs from collection under conditions described in appropriate protocol Legionella Samples Other Samples “Presumptive” Results reported to Contractor within 10 working days “Final” Results reported to Contractor within 6 working days “Presumptive” Results reported to RP within 1 working day – in writing “Final” Results reported to RP within 1 working day – in writing Follow Actions described in “Presumptive Positive” If Results are Significant or higher - follow Actions described in Section 13.4 Phone client and email “Presumptive Negative” If Results are Borderline, wait for final results before action is taken Phone client and email Wait for final results before action is taken “Final” (email) Results reported to Contractor within 14 working days “Final” Results reported to RP within 1 working day – in writing Follow Actions described in Page 37 of 79 MANAGEMENT CONTROL POLICY:LEGIONELLA UWE _______________________________________________________________________________________________________________________________ Page 38 of 79 MANAGEMENT CONTROL POLICY:LEGIONELLA UWE _______________________________________________________________________________________________________________________________ 3.5.4 ACTIONS AFTER ANALYSIS RESULTS – WHAT DO I DO NOW? Sample Insignificant Border-Line Significant NO NEED FOR SYSTEM TO BE PUT OUT-OF-USE AT THIS STAGE NO NEED FOR SYSTEM TO BE PUT OUT-OF-USE AT THIS STAGE Maintain current monitoring regime. Do not re-sample. Clean, descale and disinfect outlet (whether tap or shower) and flush outlet thoroughly (for at least 2 minutes) and resample taking only a Pre-Flush sample. Insignificant Border-Line Significant Highly-Significant Highly-Significant Do not re-sample. Consider the source of contamination and review Risk Management Programme. Follow Processes above Page 39 of 79 MANAGEMENT CONTROL POLICY:LEGIONELLA UWE _______________________________________________________________________________________________________________________________ 3.6 RECORD KEEPING 3.6.1 REQUIREMENTS Add in info for Aqualog All findings and results from each task shall be entered in the appropriate, Building specific, Log-sheet in the UWE Reporting and Logging manuals. All records shall be kept and maintained for at least five years. All entries shall be dated and bear the signature of the person carrying out each task. The Data Recording Format shall: Identify the installation requiring attention and how it operates. Record results of the initial commissioning (if available) and any re-commissioning so that observations made during maintenance checks can be compared. Define the maintenance task or observation required and the frequency. Provide for the recording of maintenance observations and results and for comments to be made in respect of any defect seen during the inspection. This facility should exist for each item of plant individually and for overall system observations. Provide for, and make reference to, any separate observation sheet required to record extensive or abnormal observations which cannot be noted on the routine inspection sheets. Facilitate cataloguing and cross-referencing to other Data Recording Formats for plant/installations on the same Site (for example, the refrigeration plant, the chilled water installation, the air conditioning plant and the heat source). Provide dates and results of inspections, tests and all associated works and procedures. Provide dates for next scheduled inspection, test and associated works visits. 3.6.2 CURRENT REPORTING AND LOGGING FORMAT The current Reporting and Logging Programme is enclosed, for reference in Appendix 5 Page 40 of 79 MANAGEMENT CONTROL POLICY:LEGIONELLA UWE _______________________________________________________________________________________________________________________________ 3.7 AUDITING The UWE Responsible Person: Have Overall Responsibility for Auditing the Legionellosis Management & Control Programmes across UWE Shall carry-out, a detailed audit to assess the compliance of the Legionellosis Management & Control Programme implemented in buildings under their control with ACoP L8 and in particular the status of the Risk Assessment Schedules, the Management Structures and Control procedures. Page 41 of 79 MANAGEMENT CONTROL POLICY:LEGIONELLA UWE _______________________________________________________________________________________________________________________________ 4.0 LEGIONELLA OUTBREAK ACTION PLAN To allow for the management of any incident, an Outbreak Committee shall be formed whose members shall be made aware of their responsibilities, and all shall have nominated deputies, who must also be aware of their places in the outbreak team. The Committee shall consist of: Policy Holder Responsible Person. Engineering Technical Staff Representative UWE Safety Advisor. Legionella Consultant. Occupational Health Doctor For the purposes of this document, a “Limited Outbreak” will mean that one person on the site, or with specific site connections, is known to have Legionellosis. An “Outbreak” will mean that two or more persons on the site, or with specific site connections, are known to have Legionellosis. Notification of this type of infection will usually be received from an external agency such as the local Environmental Health department or from local hospitals, clinics etc. It is the duty of the Responsible Person to assemble the Outbreak Committee with all speed. Where no more than one person is known to be infected (Limited Outbreak), no notification of external bodies/organisations/departments shall be necessary. Where two or more persons are known to be infected, from an identified source - over a sixmonth period, would constitute an “Outbreak”. This shall require the Responsible Person, via the Outbreak Committee, to notify the Local Health Authority (Consultant in Communicable Disease Control if one is appointed), the Health Protection Agency (ex PHLS) and the HSE through the recognised route of notification (RIDDOR). In addition to informing and summoning the above, the Responsible Person shall be responsible for informing the “Duty Holder” of the prevailing situation. All actions instructed by the Outbreak Committee and undertaken by whoever shall be entered in the site “Legionella Incident Book”. Once initial outbreak evidence is received, decisions will need to be taken as to isolation of systems, plant etc. The situation of the infected person(s) may have some effect on this action, but it is probable that all high risk equipment will be shut down and isolated. It is important that no general remedial addition of disinfectants is used at this stage. A sampling procedure must be established and carried out. The advice and/or assistance of the Health Protection Agency may be sought by the Consultant at this stage. When sampling is completed to the satisfaction of the HSE, a remedial disinfection programme will be initiated. All actions shall be documented with all sampling and results of same recorded. The outbreak incident will only be deemed to be over when so described by the HSE. All personnel associated with the investigation of the incident shall be involved in a review of all the actions taken in order to reduce the risk of a reoccurrence, and to assimilate any lessons to be learnt. Page 42 of 79 MANAGEMENT CONTROL POLICY:LEGIONELLA UWE _______________________________________________________________________________________________________________________________ SECTION 5 – APPENDICES TECHNICAL Page 43 of 79 MANAGEMENT CONTROL POLICY:LEGIONELLA UWE _______________________________________________________________________________________________________________________________ SECTION 5.3 CLOSING/OPENING OF BUILDING/AREA Page 44 of 79 MANAGEMENT CONTROL POLICY:LEGIONELLA UWE _______________________________________________________________________________________________________________________________ LEGIONELLA MANAGEMENT AND CONTROL TASKS System/Plant HOT AND COLD WATER DISTRIBUTION SYSTEMS Task Description: AREA CLOSURE AND OPENING PROCEDURES If the Maintenance Staff or appointed contractor cannot, at any stage, comply with any part of this Specification, then an alternative Specification shall be agreed which, both; meets the requirements of current legislation and the needs of the Site. This Section to be completed prior to area closure Area proposed closure: Reason for proposed closure: Period of closure: Date for proposed closure: Date of opening: Is the whole of the area proposed for closure? Yes No If No, specify: Is area supplied from a stand-alone system or from other? Yes No If No, specify: Will the use of the area change following re-opening: Yes No If Yes, specify: Has area been isolated from its domestic water supply? Yes No If Yes, date? If area not isolated, is it on “Flushing” Programme? Yes No If Yes, start date: If No, what other measures have been taken, if any? This Section to be completed at least Three Days prior to area opening i. Water temperatures to be recorded 3 times in 24 hours and must reach the required limits each time. ii. TMVs and Shower-heads (including shower hoses where fitted) shall be cleaned and disinfected. iii. Where area is supplied by a stand-alone system, the Cold water storage tank(s) shall be cleaned and disinfected and the calorifier(s) pasteurised. iv. Water samples shall be taken for microbiological analysis (T.V.C.C., Legionella spp., Pseudomonas spp. and E.coli). v. The whole system shall continue to be flushed on a daily basis until the building/area is re-occupied. The area shall not be permitted to re-open if any of the measured parameters (temperature and biological contamination) fall outside the recommended limits. All required actions have been undertaken and the associated temperatures and sampling results found to be within the recommended limits. The area is, therefore, permitted to re-open: Responsible Person: Signed: ............................................................. Page 45 of 79 Date: ................................................. MANAGEMENT CONTROL POLICY:LEGIONELLA UWE _______________________________________________________________________________________________________________________________ SECTION 5.1 LEGIONELLA MANAGEMENT AND CONTROL TASKS Page 46 of 79 MANAGEMENT CONTROL POLICY:LEGIONELLA UWE _______________________________________________________________________________________________________________________________ LEGIONELLA MANAGEMENT AND CONTROL TASKS System/Plant HOT AND COLD WATER DISTRIBUTION SYSTEMS Task Description: DEAD-LEG AND INFREQUENTLY USED OUTLET FLUSHING Frequency: WEEKLY Limits: EXPECTED USAGE FREQUENCY: MAXIMUM DEAD-LEG LENGTH: DAILY 300MM If the Maintenance Staff or appointed contractor cannot, at any stage, comply with any part of this Specification, then an alternative Specification shall be agreed which, both; meets the requirements of current legislation and the needs of the Site. Systems or individual outlets that are not frequently used allow the development of stagnant water conditions, which increase the potential of bacterial growth and proliferation, including Legionella. In order to remove any stagnation that may have developed or to stop stagnation from occurring in the first place, it is important to introduce a "flushing" programme where necessary. The flushing programme must be designed so that it allows for the whole dead-leg to be removed. This is achieved by ensuring that the flushing is carried out at the specified system or outlet and for an appropriate length of time. The length of time of purging water from the system is important because it is vital to ensure that all the stagnant water has been expelled from the pipe-work and at least until "circulating" or "fresh" water is drawn from the outlet (water at temperatures exhibited throughout the rest of the system). The flushing programme should follow the procedure outlined below: Identify areas/outlets to be flushed. Ensure that the system/outlet can be flushed (for a minimum of 3 minutes) safely and in a tidy manner into an appropriate drain if not plumbed for drainage. Ensure that the purging of water from outlets does not create an unnecessary amount of aerosol at least no more than would be created when outlet is operated normally. Ensure that "splash-back" is minimised, where practicable, by placing a sponge or another material capable of absorbing some of the force of the water against the surface of the appliance. Purge the hot and the cold or the mixed water in turn for a minimum of 2 minutes or for a period of time necessary to draw water from the outlet at temperatures exhibited throughout the rest of the system. If a system or an area consisting of multiple outlets requires flushing, it is important to begin with the nearest outlet to the main distribution pipe-work, working progressively away from the main distribution pipe-work. Where showers need to be flushed, it is important to ensure that, where practicable, the shower-head is removed in order to reduce the potential of aerosol production. Where the head is fixed, exposure to the aerosol produced must be minimised. One method that can be employed in this situation is the use of a transparent plastic bag, fixed around the shower- head, with one corner pierced to allow partial discharge of water. Consider whether the system/outlet can be removed negating further flushing. Log all procedures and results. Page 47 of 79 MANAGEMENT CONTROL POLICY:LEGIONELLA UWE _______________________________________________________________________________________________________________________________ Page 48 of 79 MANAGEMENT CONTROL POLICY:LEGIONELLA UWE _______________________________________________________________________________________________________________________________ LEGIONELLA MANAGEMENT AND CONTROL TASKS Task No: LEG 01 Task: COLD WATER STORAGE TANK TEMPERATURE MONITORING Frequency: AS SPECIFIED IN SECTION 3.4 Limits: INCOMING MAINS TEMPERATURE: STORED WATER TEMPERATURE: <20oC <20oC If the Maintenance Staff or appointed contractor cannot, at any stage, comply with any part of this Specification, then an alternative Specification shall be agreed which, both; meets the requirements of current legislation and the needs of the Site. Task Description Using a long probe, electronic and calibrated thermometer, measure and record the temperature of the body of the stored water. Remember to measure and record temperature reading from as far away from the ball cock as possible. Care must be taken as not to contaminate the stored water by the use of unclean temperature probes. Operate ball valve and measure the temperature of the water after 2 mins. Measure and record the ambient temperature near to where the tank is located. Page 49 of 79 MANAGEMENT CONTROL POLICY:LEGIONELLA UWE _______________________________________________________________________________________________________________________________ LEGIONELLA MANAGEMENT AND CONTROL TASKS Task No: LEG 02 COLD WATER STORAGE TANK GENERAL CONDITION AND BIOLOGICAL ACTIVITY INSPECTION Task: Frequency: AS SPECIFIED IN SECTION 3.4 Limits: WATER SUPPLY (WATER FITTINGS) REGULATIONS 1999 COMPLIANT. NO CORROSION. NO SLUDGE DEPOSITION. NO STAGNATION. NO BIOLOGICAL CONTAMINATION (<100cfu/ml) If the Maintenance Staff or appointed contractor cannot, at any stage, comply with any part of this Specification, then an alternative Specification shall be agreed which, both; meets the requirements of current legislation and the needs of the Site. Task Description If insulation allows for inspection of the external condition of the tank walls, inspect for corrosion pitting and leaks. Visually inspect internal walls of tank for signs of scale deposition, corrosion and slime deposits. Visually inspect tank and associated valves/pipework for leaks. Visually inspect bottom of tank for sludge deposition and state amount: 1 = slight and 10 = heavy Visually inspect internal walls of tank for corrosion and state amount: 1 = slight and 10 = heavy Visually inspect for signs of stagnation such as water surface dirt, oil films, insects, smell, low input. Visually inspect water surface for; dirt, oil films, insects and state amount: 1 = slight and 10 = heavy Visually inspect for slimy deposits on the internal walls of tank and state the colour of substance and state amount; 1 = slight and 10 = heavy Visually inspect for algae growth indicated by either green or red plant like growth on water surface Visually inspect the insulation for signs of wear and tear and areas where the insulation has been removed Visually inspect that the lid is correctly fitted and that any bolts are securely tightened. Visually inspect that all insect/rodent screens fitted are clear from debris so that water can flow easily. Visually inspect that the ball valve opens and closes correctly. Visually inspect all pipework for signs of corrosion and leaks, and check the condition of insulation fitted. Visually inspect all valves for correct operation, signs of corrosion and leaks. Visually inspect all booster pumps fitted for correct operation. When instructed to do so, using a suitable sterile container, collect a water sample and submit for biological analysis. The analysis should measure the presence of contamination by general bacteria (Total Viable Colony Count – T.V.C.C.) Indicate the date that the tank was last cleaned and disinfected and indicate whether it was disinfected as routine or due to adverse conditions. Carry out an Annual Drop-test or verify usage by meter. Page 50 of 79 MANAGEMENT CONTROL POLICY:LEGIONELLA UWE _______________________________________________________________________________________________________________________________ LEGIONELLA MANAGEMENT AND CONTROL TASKS Task No: LEG 03 Task: TANK CLEANING Frequency: AS SPECIFIED IN SECTION 3.4 Limits: MINIMUM LEVEL OF CL2 INITIALLY: 50ppm MINIMUM LEVEL OF CL2 AFTER 1HR 30ppm MAXIMUM LEVEL OF CL2 AT END <1ppm If the Maintenance Staff or appointed contractor cannot, at any stage, comply with any part of this Specification, then an alternative Specification shall be agreed which, both; meets the requirements of current legislation and the needs of the Site. Task Description The pH of the water shall be measured and must be between 5.5 and 9.0 before chlorinating solution is introduced. If pH is found to be below 5.5 the system shall be drained, flushed and refilled to level of overflow with fresh water. The tank(s) shall be filled to the level of the overflow with fresh water and chlorinating agent to give a minimum free chlorine concentration of 50ppm (50mg/l), and when full, allow to stand for 1 hour. After 1 hour, measure free chlorine level, if free chlorine level is below 30ppm, repeat step ii. The tank(s) shall be drained and then thoroughly flushed out with clean mains water until tests indicate that the residual chlorine concentration is no greater than 0.5ppm (0.5mg/l), or that present in the mains water supply. Where the volume exceeds 5000 litres, the disinfected water must be neutralised, using sodium thiosulphate, before disposal. The neutralised waste MUST NOT be drained through the system. Fix ball valve in close position. Isolate Tank from system. Outlets should be sealed from inside tank. Empty the Tank via drain-point or by using a submersible or barrel type pump, in the absence of a drain-point or should draining from drain-point is impracticable. Clean Tank and remove all deposits of scale, corrosion and sludge deposition using a combination of hand scraping and brushing together with application of chemicals to dissolve or soften the scale (where necessary). Vacuum out all loose debris and deposits. When using high-pressure jet washers to clean the internal surfaces of the Tank, suitable PPE must be used, including a positive pressure respirator. In this circumstance, the escape of aerosols must be restricted or, certainly, minimised. Where oil and grease contaminants on the tank surface are implicated, they shall be removed using suitable degreasants. Where necessary (and practicable) the tank can be steam cleaned to remove grease contaminants. Where “significant” or “highly-significant” levels of biological contamination is reported, the Tank shall be disinfected (using the disinfection method below), before the cleaning process is commenced. Record on appropriate log sheet Page 51 of 79 MANAGEMENT CONTROL POLICY:LEGIONELLA UWE _______________________________________________________________________________________________________________________________ LEGIONELLA MANAGEMENT AND CONTROL TASKS Task No: LEG 04 Task: TANK DISINFECTION USING BIOCHEM B600/B400 Frequency: AS SPECIFIED IN SECTION 3.4 Limits: MINIMUM LEVEL OF CL2 INITIALLY: 50ppm MINIMUM LEVEL OF CL2 AFTER 1HR 30ppm MAXIMUM LEVEL OF CL2 AT END <1ppm T.V.C.C. LEVEL: <100cfu/ml If the Maintenance Staff or appointed contractor cannot, at any stage, comply with any part of this Specification, then an alternative Specification shall be agreed which, both; meets the requirements of current legislation and the needs of the Site. Task Description The pH of the water shall be measured and must be between 5.5 and 9.0 before chlorinating solution is introduced. If pH is found to be below 5.5 the system shall be drained, flushed and refilled with fresh water to level of overflow. The tank(s) shall be filled to level of overflow with fresh water and chlorinating agent to give a minimum free chlorine concentration of 50ppm (50mg/l), and when full, allow to stand for 1 hour. After 1 hour, measure free chlorine level, if free chlorine level is below 30ppm, repeat step ii. The tank(s) shall be drained and then thoroughly flushed out with clean mains water until tests indicate that the residual chlorine concentration is no greater than 0.5ppm (0.5mg/l), or that present in the mains water supply. Where the volume exceeds 5000 litres, the disinfected water must be neutralised, using Chemclense C400, before disposal. The neutralised waste MUST NOT be drained through the system. Using a suitable sterile container, collect a water sample and submit for biological analysis. The analysis should measure the presence of contamination by general bacteria (Total Viable Colony Count – T.V.C.C.). Record on appropriate log sheet. Page 52 of 79 MANAGEMENT CONTROL POLICY:LEGIONELLA UWE _______________________________________________________________________________________________________________________________ LEGIONELLA MANAGEMENT AND CONTROL TASKS Task No: LEG 05 CALORIFIER MANUAL TEMPERATURE BIOLOGICAL ACTIVITY INSPECTION Task: Frequency: AS SPECIFIED IN SECTION 3.4 Limits: FLOW TEMPERATURE: RETURN TEMPERATURE: COLD FEED TEMPERATURE: T.V.C.C. LEVEL: MONITORING AND ≥60oC O ≥50 c <20oC <100cfu/ml If the Maintenance Staff or appointed contractor cannot, at any stage, comply with any part of this Specification, then an alternative Specification shall be agreed which, both; meets the requirements of current legislation and the needs of the Site. Task Description Measure and record the “Set” temperature setting of the thermostat (if fitted and calibrated). Temperature to exceed 60oC. Measure and record the “Flow” temperature using a contact thermometer or calibrated gauge. Temperature to be taken from “Flow” pipework as close to the Calorifier as possible. Temperature to exceed 60oC. Measure and record the “Return“ temperature using a contact thermometer or calibrated gauge. Temperature to be taken from “Return” pipework as close to the Calorifier as possible. Temperature to exceed 50oC. When instructed to do so, isolate Cold Feed and open drain point into a bucket and collect approximately the first litre of water discharged. Using a suitable sterile container, collect a water sample and submit for biological analysis. The analysis should measure the presence of contamination by general bacteria (Total Viable Colony Count – T.V.C.C.). Discard this and collect a further 10 litres of water. Measure and record temperature. Temperature to exceed 60oC. Measure and record the “Cold Feed“ temperature using a contact thermometer or calibrated gauge. Temperature to be taken from “Cold Feed” pipework one metre from the Calorifier as possible. Temperature NOT to exceed 20oC. Record on appropriate log sheet N.B. 1: If contact probe is to be used for temperature monitoring through copper pipework, a 2oC temperature adjustment must be added to the recorded temperature before reporting temperature on the Log-sheet and the use of the contact probe noted with the result. N.B. 2: The temperature measurements shall be carried out at different times during the day in order to allow indicative temperature monitoring of the vessel during a typical daily usage profile. Page 53 of 79 MANAGEMENT CONTROL POLICY:LEGIONELLA UWE _______________________________________________________________________________________________________________________________ LEGIONELLA MANAGEMENT AND CONTROL TASKS Task No: LEG 06 Task: CALORIFIER PASTEURISATION Frequency: AS SPECIFIED IN SECTION 3.4 Limits: T.V.C.C. LEVEL: <100cfu/ml If the Maintenance Staff or appointed contractor cannot, at any stage, comply with any part of this Specification, then an alternative Specification shall be agreed which, both; meets the requirements of current legislation and the needs of the Site. Task Description Purge Calorifier via drain point and refill. Isolate all valves on the incoming and outlet sides. Ensure that the “blow” valve is capable of withstanding temperatures of up to 80oC. Bring Calorifier to 70oC (if practicable) and allow to stand at this temperature for at least 1 hour. Ensure that no water is drawn from the Calorifier whilst pasteurisation in progress. Allow Calorifier to reach its normal operating temperature, 60oC, and return to service. Using a suitable sterile container, collect a water sample and submit for biological analysis. The analysis should measure the presence of contamination by general bacteria (Total Viable Colony Count – T.V.C.C.). Record on appropriate log sheet Page 54 of 79 MANAGEMENT CONTROL POLICY:LEGIONELLA UWE _______________________________________________________________________________________________________________________________ LEGIONELLA MANAGEMENT AND CONTROL TASKS Task No: LEG 07 Task: CALORIFIER GENERAL CONDITION INSPECTIONS Frequency: AS SPECIFIED IN SECTION 3.4 Limits: WATER SUPPLY (FITTINGS) REGULATIONS 1999 COMPLIANT. NO CORROSION. NO SLUDGE DEPOSITION. NO STAGNATION. NO BIOLOGICAL CONTAMINATION (<100cfu/ml) If the Maintenance Staff or appointed contractor cannot, at any stage, comply with any part of this Specification, then an alternative Specification shall be agreed which, both; meets the requirements of current legislation and the needs of the Site. Task Description Report on the operational status of Calorifier by checking the status of the associated isolation valves. If the Calorifier is OFF, indicate the date it came Off-line. Report on the status of Inlet Valve and Outlet Valve. Report on the operational status of the circulation pump(s) and shunt pump(s). Visually inspect Calorifier and associated valves for leaks. Visually inspect all pipework for signs of corrosion and leaks, and visually inspect the condition of insulation fitted. Visually inspect all valves for correct operation, signs of corrosion and leaks. Visually inspect all pumps fitted for correct operation and leaks. Measure and record the temperature setting of the thermostat (if fitted). Open the cold feed valve and then open the drain point allowing enough water to flow through so that any water discoloration is removed. Visually inspect the insulation for signs of wear and tear and areas where the insulation has been removed. When instructed to do so, isolate Cold Feed and open drain point into a bucket and collect approximately the first litre of water discharged. Using a suitable sterile container, collect a water sample and submit for biological analysis. The analysis should measure the presence of contamination by general bacteria (Total Viable Colony Count – T.V.C.C.). Visually inspect that any gauges fitted are operating correctly. Compare against calibrated instruments. Indicate the date that the calorifier was last pasteurised and indicate whether it was disinfected as routine or due to adverse conditions. Indicate the date of the last insurance inspection (where applicable). Page 55 of 79 MANAGEMENT CONTROL POLICY:LEGIONELLA UWE _______________________________________________________________________________________________________________________________ LEGIONELLA MANAGEMENT AND CONTROL TASKS Task No: Task: Frequency: Limits: LEG 10 COLD WATER TEMPERATURE MONITORING - DCWS & MAINS SUPPLY OUTLETS AS SPECIFIED IN SECTION 11.0 MAINS TEMPERATURE: <20oC within 1 minute DCWS TEMPERATURE: <20oC within 1 minute If the Maintenance Staff or appointed contractor cannot, at any stage, comply with any part of this Specification, then an alternative Specification shall be agreed which, both; meets the requirements of current legislation and the needs of the Site. Task Description Using an electronic and calibrated thermometer with a suitable probe, measure and record the outlet temperature of the incoming Mains (usually from the tank ball-valve – if one is present, or from the nearest outlet. The measurements shall be carried out after allowing the water to run for 2 minutes, at full-flow. This temperature shall not to exceed 20oC. Measure and record the outlet temperature of each designated “Sentinel” outlet, from each branch and subbranch of the distribution system, indicating whether Mains or Tanked fed. The measurements shall be carried out after allowing the water to run for 2 minutes, at full-flow. This temperature shall not exceed 20oC. Where the temperature exceeds 20oC, the cold water temperature at the incoming Mains shall be measured an recorded (see above). N.B. 1: On each monitoring visit, the temperature of the source supply (Mains or Tank) shall be measured. Visually inspect and record the colour, and flow-rate of the water from the outlets inspected. The water shall be clear from any discolouration and must run freely without any restrictions. Page 56 of 79 MANAGEMENT CONTROL POLICY:LEGIONELLA UWE _______________________________________________________________________________________________________________________________ LEGIONELLA MANAGEMENT AND CONTROL TASKS Task No: LEG 11 Task: HOT WATER TEMPERATURE MONITORING - DIRECT FED OUTLETS Frequency: AS SPECIFIED IN SECTION 3.4 MINIMUM TEMPERATURE AT FURTHEST OUTLET: >50oC within 1 minute Limits: If the Maintenance Staff or appointed contractor cannot, at any stage, comply with any part of this Specification, then an alternative Specification shall be agreed which, both; meets the requirements of current legislation and the needs of the Site. Task Description Measure and record the outlet temperature, of each designated “Sentinel” outlet, from each branch and subbranch of the distribution system, indicating the source calorifier. The measurements shall be carried out after allowing the water to run for 1 minute, at full-flow. This temperature shall not be less than 50oC. Where the temperature is not achieved, the hot water “Flow” from the corresponding source calorifier shall be measured and recorded. N.B. 2: On each monitoring visit, the temperature of the source supply (Calorifier etc.) must be measured. This must include the "flow" and "return" temperatures of each Unit in the system Visually inspect and record the colour, and flow-rate of the water from the outlets inspected. The water shall be clear from any discolouration and must run freely without any restrictions. Page 57 of 79 MANAGEMENT CONTROL POLICY:LEGIONELLA UWE _______________________________________________________________________________________________________________________________ LEGIONELLA MANAGEMENT AND CONTROL TASKS Task No: LEG 12 Task: HOT WATER TEMPERATURE MONITORING - BLENDED OUTLETS Frequency: AS SPECIFIED IN SECTION 3.4 FROM THE TMV 41oC for showers and basins/sinks Limits: TO THE TMV >50oC HWS to the TMV <20oC CWS to the TMV If the Maintenance Staff or appointed contractor cannot, at any stage, comply with any part of this Specification, then an alternative Specification shall be agreed which, both; meets the requirements of current legislation and the needs of the Site. Task Description 1. 41oC for showers and basins/sinks etc. Where these temperatures are exceeded, the TMV shall be adjusted in order to allow the unit to operate within the recommended temperature limits described above. Using an electronic and calibrated thermometer with a suitable contact probe, measure and record the temperature of the HWS and CWS supply pipes of each TMV. The temperature of the CWS shall not exceed 20 oC and the temperature of the HWS shall not be less than 50oC. The measurements shall be carried out following task 1. (i). 2. SHOWERS Measure and record the “Initial” and “Final” outlet temperature, of each shower and bath fitted with a Thermostatic Mixing Valve (TMV or otherwise). The measurements shall be carried out immediately and after allowing the water to run for 1 minute at full-flow respectively. The “Initial” and “Final” outlet temperature measured shall not to exceed: SINKS AND BASINS Measure and record the “Initial” and “Final” outlet temperature, of the HOT water outlet of each sink, basin and other non-full body immersion outlets fitted with a Thermostatic Mixing Valve (TMV or otherwise). The measurements shall be carried out immediately and after allowing the water to run for 1 minute at full-flow respectively. The “Initial” and “Final” outlet temperature measured shall not exceed 41oC. Where these temperatures are exceeded, the TMV shall be adjusted in order to allow the unit to operate within the recommended temperature limits described above. Using an electronic and calibrated thermometer with a suitable contact probe, measure and record the temperature of the HWS supply pipe ONLY of each TMV. The temperature of the HWS shall not be less than 50oC. The measurements shall be carried out following task 2. (i). Measure and record the COLD water outlets of each sink, basin and other non-full body immersion outlets fitted with a Thermostatic Mixing Valve (TMV or otherwise). The measurements shall be carried out immediately and after allowing the water to run for 2 minutes at full-flow respectively. The outlet temperature measured shall not exceed 20oC. Page 58 of 79 MANAGEMENT CONTROL POLICY:LEGIONELLA UWE _______________________________________________________________________________________________________________________________ LEGIONELLA MANAGEMENT AND CONTROL TASKS Task No: LEG 13 SHOWER HEAD CLEANING AND DISINFECTION USING CHEMCLENSE C202SH Task: Frequency: 3 MONTHLY Limits: AS DICTATED BY CALCIUM CARBONATE DEPOSITS – MIN 30 MINUTES FOR DISINFECTION If the Maintenance Staff or appointed contractor cannot, at any stage, comply with any part of this Specification, then an alternative Specification shall be agreed which, both; meets the requirements of current legislation and the needs of the Site. Task Description Dismantle the shower assembly and inspect the internal surfaces for signs of scale, biofilm and other deposits/particulates. Clean & disinfect the showerhead by placing the head in a solution of Chemclense C202SH* for a maximum of 30 minutes. Refer to Product Data Sheet PDC202SH for further detail. After 30 minutes, remove the shower head and rinse with clean mains water until all traces of chemical have been removed. Reassemble the shower head and flush through with hot shower water. Record the activity on the technical test data record sheet NOTES: a) Chemclense C202SH is an acidic product and when being used, appropriate Health & Safety precautions must be taken. These will include as a minimum, chemical resistant gloves and goggles. Refer to Chemclense C202SH COSHH data. b) Chemclense C202SH is to be used as two parts water to one part chemical. Where scaling is severe, Chemclense C202SH may be used neat. The product contains a colour change indicator which goes from yellow to blue/green as the descaling power is exhausted. c) Chemclense C202SH has been formulated for all materials of construction. Page 59 of 79 MANAGEMENT CONTROL POLICY:LEGIONELLA UWE _______________________________________________________________________________________________________________________________ Page 60 of 79 MANAGEMENT CONTROL POLICY:LEGIONELLA UWE _______________________________________________________________________________________________________________________________ LEGIONELLA MANAGEMENT AND CONTROL TASKS Task No: Frequency: LEG 14 THERMOSTATIC MIXING VALVE (TMV) DISINFECTION USING BIOCHEM B400/B600 AS SPECIFIED IN SECTION 3.4 Limits: MINIMUM 100mg/l as Chlorine FOR 20 MINS Task: CLEANING AND If the Maintenance Staff or appointed contractor cannot, at any stage, comply with any part of this Specification, then an alternative Specification shall be agreed which, both; meets the requirements of current legislation and the needs of the Site. Task Description Each TMV shall be removed from its location and replaced with a new or previously serviced TMV. The removed TMV shall be taken to a suitably equipped work-shop for service. At the work-shop, each TMV shall be dismantled and physically cleaned from all scale deposits and scale deposition (using a suitable descaling solution where necessary). Rinse in clean water, allow to drip-dry and store in a cool and dry place. Immediately prior to re-installation (same day), all components shall be disinfected (this applies to all cleaned and new components). All components shall be flushed with clean water and immersed in a Sodium hypochlorite disinfectant solution (100 ppm) for 20 minutes minimum. Remove components from disinfectant solution and rinse with clean water to remove presence of chlorine. Reassemble, refit and test operation of valve, including fail-safe test. Measure and record and adjust (if necessary) the “maximum” outlet temperature. Record the date that TMV has been replaced. Page 61 of 79 MANAGEMENT CONTROL POLICY:LEGIONELLA UWE _______________________________________________________________________________________________________________________________ LEGIONELLA MANAGEMENT AND CONTROL TASKS Task No: LEG 15 AHU TRAP CLEANING AND DISINFECTION USING BIOCHEM B400/600 Task: Frequency: AS SPECIFIED IN SECTION 3.4 Limits: MINIMUM 100mg/l as Chlorine FOR 20 MINS If the Maintenance Staff or appointed contractor cannot, at any stage, comply with any part of this Specification, then an alternative Specification shall be agreed which, both; meets the requirements of current legislation and the needs of the Site. Task Description Each trap shall be removed from its location and taken to a suitably equipped work-shop for service. At the work-shop, each trap shall be dismantled and physically cleaned from all scale deposits and scale deposition (using a suitable descaling solution where necessary). Rinse in clean water, allow to drip-dry and store in a cool and dry place. Immediately prior to re-installation (same day), all components shall be disinfected (this applies to all cleaned and new components). All components shall be flushed with clean water and immersed in a Biochem B400/B600 disinfectant solution (100 ppm) for 20 minutes minimum. Remove components from disinfectant solution and rinse with clean water to remove presence of chlorine. Reassemble, refit and fill trap with clean water. Record the date that the trap has been replaced. Page 62 of 79 MANAGEMENT CONTROL POLICY:LEGIONELLA UWE _______________________________________________________________________________________________________________________________ LEGIONELLA MANAGEMENT AND CONTROL TASKS Task No: LEG 16 AHU COMPONENTS INSPECTION, CLEANING AND DISINFECTION OF PERMANENTLY OR INTERMITTENTLY WETTED SURFACES WITHIN THE AIR HANDLING SYSTEM Task: Frequency: AS SPECIFIED IN SECTION 3.4 Limits: MINIMUM 100 mg/l as Chlorine for 3 minutes minimum (using spray) If the Maintenance Staff or appointed contractor cannot, at any stage, comply with any part of this Specification, then an alternative Specification shall be agreed which, both; meets the requirements of current legislation and the needs of the Site. Task Description Report on the operational status of the unit. Visually inspect the condition of the external surfaces of the unit and comment. Visually inspect (if possible) the condition of the internal surfaces of the unit and comment. If practicable, isolate unit in order to allow for thorough internal inspection to be carried out. Visually inspect the condition of all traps fitted and comment. Visually inspect (if possible) the condition of the drip-trays of the unit and comment. If practicable, isolate unit in order to allow for thorough internal inspection of the drip-trays to be carried out. Alternatively, remove driptrays from the system and inspect. Visually inspect (if possible) the condition of the drip-tray drains of the unit and comment. Visually inspect (if possible) the condition of the eliminators of the unit and comment. Visually inspect (if possible) the condition of the filters fitted and comment. Visually inspect (if possible) the condition of the humidifier components of the unit and comment. Visually inspect (if possible) the condition of the Chiller battery fitted and comment. Visually inspect (if possible) the condition of the Heater battery and comment. Using clean cloth, wipe over the unit components to be disinfected. To disinfect, spray the components with a chlorine donor solution of 100 ppm strength, using small hand spray. Allow to stand for 3 mins only. Spray with fresh clean water. Dry area with clean and clean cloth. Page 63 of 79 MANAGEMENT CONTROL POLICY:LEGIONELLA UWE _______________________________________________________________________________________________________________________________ SECTION 5.2 TECHNICAL TEST DATA RECORD SHEETS Page 64 of 79 MANAGEMENT CONTROL POLICY:LEGIONELLA UWE _______________________________________________________________________________________________________________________________ Page 65 of 79 MANAGEMENT CONTROL POLICY:LEGIONELLA UWE _______________________________________________________________________________________________________________________________ Page 66 of 79 MANAGEMENT CONTROL POLICY:LEGIONELLA UWE _______________________________________________________________________________________________________________________________ Page 67 of 79 MANAGEMENT CONTROL POLICY:LEGIONELLA UWE _______________________________________________________________________________________________________________________________ Page 68 of 79 MANAGEMENT CONTROL POLICY:LEGIONELLA UWE _______________________________________________________________________________________________________________________________ Page 69 of 79 MANAGEMENT CONTROL POLICY:LEGIONELLA UWE _______________________________________________________________________________________________________________________________ Page 70 of 79 MANAGEMENT CONTROL POLICY:LEGIONELLA UWE _______________________________________________________________________________________________________________________________ Page 71 of 79 MANAGEMENT CONTROL POLICY:LEGIONELLA UWE _______________________________________________________________________________________________________________________________ Page 72 of 79 MANAGEMENT CONTROL POLICY:LEGIONELLA UWE _______________________________________________________________________________________________________________________________ SECTION 6 APPENDICES – DOCUMENTARY SECTION 6.1 POLICY RECEIPT DOCUMENT From: ………………………………………..………………. Date: ………………………………………………………… Copy No.: ………………………………………………………… CONFIRMATION OF RECEIPT OF DOCUMENT This is a written confirmation that I am in possession of an authorised copy of the UWE Policy – “Management Document for the Management and Control of Legionellosis Including Legionnaires Disease”, the number of which is listed above. In signing this receipt, I confirm that I will ensure the safe-keeping and integrity of this document. I also confirm that I will not copy or issue, to a third party or otherwise, the whole document or any part of it, for whatsoever purpose, without the written consent of the UWE Responsible Person. Signature: ………………………………………..…….…. Name: Date: ………………………………………………………… ………………………………………………………….. Page 73 of 79 MANAGEMENT CONTROL POLICY:LEGIONELLA UWE _______________________________________________________________________________________________________________________________ Page 74 of 79 MANAGEMENT CONTROL POLICY:LEGIONELLA UWE _______________________________________________________________________________________________________________________________ 6.2 RESPONSIBILITIES NOTIFICATION Page 75 of 79 MANAGEMENT CONTROL POLICY:LEGIONELLA UWE _______________________________________________________________________________________________________________________________ To: ……………………………………………………………. From: ………………………………………..……………….. Date: ………………………………………………………… Re: NOMINATION OF RESPONSIBILITY FOR THE MANAGEMENT & CONTROL OF LEGIONNAIRES’ DISEASE AND SAFE HOT WATER MANAGEMENT I nominate as the “Responsible Person" for the Management & Control of Legionnaires ’ Disease for all the buildings currently occupied, owned and maintained by the Institute (under a full maintenance lease or otherwise). The responsibilities of this nominated position include: Overall Responsibility for the Implementation of the Legionellosis Management & Control Programmes, across UWE Have Overall Responsibility for Auditing the Legionellosis Management & Control Programmes across UWE, and reporting all findings to the "Legionella Risk Management Steering Committee". Advise others on all matters relating to the Management & Control of Legionellosis Management and ensure that they are informed of all changes, or proposed changes, in the legislation/recommendations relating to Legionellosis which may affect UWE, in general, and the buildings under their control, specifically. Where necessary, carry out a Tender Process and select suitable Water Treatment/Hygiene Contractors or Consultants for the provision of services pertaining to Legionellosis Management & Control. Assess the training needs for training of staff involved in the Legionellosis Management & Control and Programme and liaise between suitable training establishments, Consultants to provide approved Training Courses. Ensure personal training records are kept up to date. I accept this nominated position and I undertake to implement all specified requirements as described in the Institute’s “POLICY FOR THE MANAGEMENT AND CONTROL OF LEGIONELLOSIS INCLUDING LEGIONNAIRES DISEASE AND THE MANAGEMENT Name: Signature: …………………………..…………….. Date: ………………………………………… Page 76 of 79 MANAGEMENT CONTROL POLICY:LEGIONELLA UWE _______________________________________________________________________________________________________________________________ Page 77 of 79 MANAGEMENT CONTROL POLICY:LEGIONELLA UWE _______________________________________________________________________________________________________________________________ SECTION 7 APPENDICES - ESTATE . Page 78 of 79 MANAGEMENT CONTROL POLICY:LEGIONELLA UWE _______________________________________________________________________________________________________________________________ - PROCEDURE WHEN WATER QUALITY IS OUT OF SPECIFICATION Dear all, Due to an issue with the water quality within the site/building we need to take the following precautions Do NOT drink cold water from any tap on site. There is plenty of bottled water in stores to supply cold drinks. The restaurant staff are aware of the problem and have taken suitable precautions to protect their meals. Hot drinks and boiled water are perfectly safe to drink. There is no danger from washing hands or clothes in the site water. The hostels are on our system so the water they are included in this notice. A few houses are fed from this part of the site. They have been informed. The nursery is also fed from here. They have also been informed and supplied with bottled water. These are precautionary measures and we are assured that there is no risk to health if the precautions above are followed. We expect to have the problem repaired shortly and will then start flushing the water system and checking the treatment levels. Once the water is declared safe by analysis, we will inform you all. Contact point ……… Page 79 of 79