Annual Review - Summary Sheet Title: Support to universal access to long lasting insecticide-treated nets in Equateur Programme Value: £24m Programme Code: Review Date: February 2015 Start Date:07/01/2011 Summary of Programme Performance 1 2 Year 2 A+ Programme Score Low low Risk Rating 3 A+ low End Date:31/10/2015 4 A low Summary of progress and lessons learnt since last review The last annual review focused on the achievements of the Equateur mass campaign to distribute Long Lasting Insecticide Treated Nets (LLINs), which was by then complete. Since then, the programme has shifted to one of routine distribution of nets, with the aim of maintaining coverage and therefore the positive health impact, until the next mass distribution. This is currently scheduled for November 2015. Therefore, this annual review focuses only on the routine distribution and accompanying activities. The routine distribution itself suffered from several important setbacks. These include delays in procurement, problems with staff recruitment and finally the outbreak of Ebola in the province. After the outbreak, distribution activities were suspended for four months in 12 of the 42 targetted health zones. However, despite the slow start and access problems, the key milestone of number of nets distributed had reached 94% of its target by December 2014. The project has successfully procured all the necessary LLINs for routine distribution and they are now available in each health district. The three other supporting outputs relating to: Behaviour Change; Communication; Monitoring and Evaluation; and Health Systems Strengthening, are all on track overall. To elaborate: the project has played a key role in reinforcing and maintaining behaviour change acquired through the mass campaign and it has strengthened the health system by providing training and supervision as well as supporting the activities by provincial, district and health zone teams. The project has also established a good partnership with the national and provincial government. On balance, however, we have decided to award an A score, given the importance of the nets distributed in a context where the Ebola outbreak prevented routine activities in 29% of the targeted health zones for four months. However, efforts must be made to improve the monitoring of the project which has not yet caught up from its slow start. Reflections and Lessons This project is contributing to more than half of the 9 million LLINs targeted by the DRC Country Operational Plan. As DRC is recognised worldwide to be the country with the second highest burden of malaria, this project is fully in line with DFID’s Results Framework for Malaria and has a focus on the prevention services identified to support the achievement of mortality and morbidity reduction. LLINs are recognised by the national malaria programme (PNLP) to be a major and a cost effective intervention to prevent malaria in DRC and they have been implemented for more than 9 years. According to the most recent Demographic Health Survey (DHS 2013-14) there has since then been substantial progress on ownership and use of LLINs, including by pregnant women and children under five (U5) who are both important target groups. Nationally, the LLIN utilization by U5 increased from 6% in 2007 to 56% in 2013 i. We would expect this to have a substantial impact on the level of U5 mortality as malaria is recognized to be one of the three major causes of child mortality. So this could be part of explanation for the decrease of childhood mortality: U5 mortality has decreased from 148 per 1,000 live births in 2007 to 104 in 2013 ii. Nonetheless, there remain some questions about the LLIN approach. In Equateur, 83% of households possess LLINs but only 63% of households used a LLIN the night before the DHS survey. This raises the question of whether there is a problem of acceptance of LLIN by the population or access to LLINs, or both. In order to explore this, the project is implementing operational surveys to assess the use of the nets and determine the factors that could prevent their use. When the routine distribution began, activities were initially implemented only in the public health facilities. It became clear that this was not sufficient to deliver the target of nets distributed, so in October, private health facilities (where most pregnant women seek health) were integrated into the programme. In future, this comprehensive approach should be used from the outset. According to the current information from PNLP, the whole province will not be covered by the next mass distribution in 2015. One district will be supported by the DFID DRC Health care programme (ASSP) using nets donated from AMF (Against Malaria Foundation), two districts will be supported by USAID and the two remaining districts: Mongala and Tshuapa (with 24 health zones which represent more than the half of the zones where we are implementing routine distribution) are still looking for funds and might not be covered in 2015. We need to work with PNLP and others to try to find a solution to this. Gender : This project predates the introduction of gender reviews into DFID DRC’s regular programme management approach. It is focused on distribution of bed nets to vulnerable people, especially pregnant women and children under five. It therefore has an inherent positive gender focus. The distribution of bed nets is one of the three components of DFID DRC’s new malaria project: “Support to Malaria Control”. This new programme does have a regular gender review. We propose that for the short remaining duration of the older project, we will incorporate it into this existing regular gender review. Population Service International (PSI) – the implementing partner - is currently developing a gender strategy and we will update the gender review in May 2015. Annex 1: ‘Support to Malaria Control’ gender review (to be updated in May 2015) . A. Introduction and Context (1 page) DevTracker Link to Business Case: http://devtracker.dfid.gov.uk/projects/GB1-202251/ DevTracker Link to Log frame: http://devtracker.dfid.gov.uk/projects/GB1-202251/documents/ Outline of the programme Malaria is a significant public health problem in the Democratic Republic of Congo, with 97% of the population living in endemic zones and a malaria prevalence rate of 32%. Malaria is the leading cause of morbidity and one of the three highest causes of mortality, especially among women and children under five, for whom malaria accounts for 54% and 48% respectively of all hospitalisations. In 2006, DRC was estimated to have 11% of all malaria cases in the WHO African region. The Government of DRC’s National Malaria Control Programme (Programme National de Lutte contre le Paludisme, PNLP) has a five-year strategic plan that was developed in 2008 with support from international partners, including DFID. This strategic plan aims to ensure 80% of the population have – and correctly use - long lasting insecticidetreated nets (LLINs). This is to be achieved by the distribution of LLINs to all households, complemented by communication and social mobilisation activities. The goal of this project is to contribute to the reduction by 50% of malaria-related morbidity and by 20% of malariarelated mortality in children under five in DRC. The project purpose is to maintain and increase correct LLIN use among under five children and pregnant women in Equateur province. The project started in December 2010. The delivery mechanism of bed nets was initially carried out through a mass campaign for the whole province (during the two first years of the project – 2011 and 2012). A cost extension was approved in 2013. This was for routine distribution, in order to maintain the health impact of the completed mass distribution until the next mass distribution due in November 2015. The routine distribution of LLINs is taking place through health zones’ structures in 42 health zones out of the 69 in Equateur province. The 27 other health zones are already covered by DFID ASSP and other donors such as Global Fund and PMI (US President Malaria Initiative). The project is now due to end in October 2015. The mass distribution of 4.25 million LLINs in Equateur was expected to: Protect 8.5 million people from malaria for up to three years Avert an estimated 22 million episodes of malaria Avert the deaths of an estimated 250,000 children under five Increase demand and use of bed nets among the population of Equateur, Democratic Republic of Congo The routine distribution of 609,616 LLINs through antenatal and growth monitoring services in health facilities in 42 Health Zones in Equateur is expected to: Ensure that 80% of pregnant women and under-fives are protected from malaria. Increase demand for LLINs through effective communication and social mobilisation. strengthen the health system capacity to manage malaria prevention interventions at the operational level. B: PERFORMANCE AND CONCLUSIONS This annual review was conducted in January 2015 with data collected up to the end of December 2014. It covers the implementation of the project from March 2014 to December 2014 and therefore refers only to routine distribution activies: the preceding mass distribution was covered in previous annual reviews. Th progress of the routine distribution has been affected by a series of delays, not all of which were within PSI’s control. There was a 3-month delay between the end of the original LLIN mass distribution campaign project and the approval of the new routine distribution project due to a long negotiation on the details of the extension. PSI and DFID had to agree on the extension budget, the logframe and intervention area of routine intervention. As a result, PSI/ASF had to close both its Mbandaka and Lisala offices and most of the project staff were transferred to other LLIN distribution projects. After the approval, PSI/ASF had to recruit all new staff and identify new office and warehouse space and the recruitment process took more time than expected. The implementation started late in quarter 1 of 2014 but due to a delay in the international procurement of commodities and the recruitment process of the staff, the distribution itself was only effective in quarter 2 of 2014. So by this time the programme was already running 6 months late. The routine distribution started in June 2014 for Mongala district (12 health zones ), in August 2014 for Mbandaka district (3 health zones) and September 2014 for Equateur district (15 Health zones). With the outbreak of Ebola in the province, the 12 health zones of Tshuapa district were placed under quarantine by the Government and no activities were implemented in those health zones during this period until December 2014. Annual outcome assessment According to the logframe, the overall outcome performance is measured by three indicators which focus on the correct use of LLINs. These indicators are: 1) the percentage of children under five who slept under a LLIN the night before the study, 2) the percentage of pregnant women who slept under a LLIN the night before the study, 3) the percentage of households that have at least one LLIN hung in the house. For all of these indicators, the objective of the project is to see at least 80% of the targeted vulnerable groups using effectively the insecticide treated nets. The most recent available survey data is the Demographic Health Survey DHS 2013-14 carried out from November 2013 to February 2014 and published in May 2014. The DHS does not report directly on the above outcome indicators. But it does give some indication of improved LLIN use by the groups we are interested in for this programme: In Equateur, LLIN utilization rate by U5 children increased from 2% in 2007 to 65% in 2013 There is also mention of an increasing use of LLINs by pregnant women, from 7% in 2007 to 60% in 2013 for the whole country, in the province of Equateur this rate increased from 7 % to 71%.. In Equateur province, the DHS concluded that the ownership of LLIN has reached 83% and then exceeded the national objective expected to 80%. On the logframe outcome indicators, the most recent data we have is from the post-campaign survey carried out by Kinshasa Public Health School in September 2013 six month after the mass distribution. It demonstrated the following results: Table 1: Post campaign findings Coverage Indicators Before distribution(2011) Percentage of households with 76.0% After distribution(2013) 87.2% MILD suspended Percentage of pregnant women 39.4% who slept under LLIN the night before the survey Percentage of children under five 29.9% who slept under an LLIN the night before the survey 70.0% 79.9% By considering the findings from these two surveys with similar results even if they did not use the same methodology, two indicators out of three for the outcome are already reached. We believe that the project therefore remains on track to achieve its overall outcome. Overall output score and description The project’s performance is measured by the following outputs :. Output title Overall output Impact weight score comments 1.LLINs distribution A 65% 2.Behaviour change communication A (malaria prevention) 3.Monitoring and evaluation B 4.Health system strengthening A 15% Output moderately did not meet expectation Output met expectation 10% 10% Output met expectation Output met expectation Overall, the programme has scored an A (outputs met expectation) as all outputs were implemented and the majority of their indicators have met expectations. 1. LLINs distribution through routine channels: Up to the end of December 2014, routine distribution of LLINs to beneficiaries was scaled up throughout 42 health zones and resulted in the distribution of 279,317 LLINs to the targeted beneficiaries against a milestone of 295,000. 2. Behaviour change communication: Interest and awareness was raised as how to prevent malaria. Intensive Communication activities were carried out during the reporting period ranging from mass media (radio spots and posters) to Inter Personal Communication during home visits, Antenatal Care (ANC) and immunization activities Women groups, churches and mosques were also used as a means for social mobilisation and sensitisation. 3. Monitoring and evaluation: Supervisions were carried out by health zones staff that in turn were supervised by both the district and provincial level of health officials. For the remaining time of the project, there is a need for PSI to reinforce and improve the number of monitoring visits held at health zone and district level given the poor performance against these indicators. 4. Health system strengthening: The training of actors was completed in all the targeted health districts. The project was officially launched by the Governor of Equateur province in the presence of DFID DRC who handed over 46 lap top computers, 46 printers to improve quality data collection, analysis and storage by the health system and 585 bicycles to facilitate supervision activities carried out by head nurses. Key challenges Due to the poor conditions in rural areas including lack of adequate sleeping places in homes and problems caused by the type of bed (wooden platform with rough edges), the lifespan of LLINs is reduced and cannot last for three years as recommended by WHO. The logistics of operating in Equateur are very difficult. Several health areas are located alongside the Congo river with no communication network coverage and are hardly accessible. The poor conditions of the road make any kind of movement limited. The two health facility channels recommended by PNLP for the routine distribution of nets to pregnant wormen are antenatal attendance and use of facilities in childbirth. In Equateur, it is noted that a significant number of pregnant women do not attend antenatal care though they do use health facilities for childbirth. This limits the opportunity for routine distribution to this group. Key lessons The assessment of the Equateur context, local opportunities and constraints lead to the following lessons: To maintain the high level of bed nets coverage after the mass campaign (universal access) by using routine channels, there is a need to implement this approach in both private and public health facilities instead of relying only in the public health facilities. To reach each vulnerable population with the routine approach, it was noted that a significant number of pregnant women do not attend antenatal care but deliver in health facilities. Provision should be therefore taken to supply this group of beneficiaries during delivery period. These two above lessons comply with WHO advice to each National Malaria control Programme to develop its own net distributions strategy based on analysing the context of its local opportunities and constraints, and then identify complementary distribution mechanisms. Further innovative solutions may be needed where access and/or quality of antenatal care and Expanded Programme on Immunisation services are inadequate. Although mass communication through radio spots is useful to increase LLIN use, it is more appropriate for urban areas, while Interpersonal communication and home visits are necessary to increase the use of bed nets in rural settings where the greater population are found. To improve quality data collection and timely reporting by health personnel, operation support should be provided using a performance based motivation method. These lessons will be shared with all malaria stakeholders in country through regular meetings held by the malaria network under the leadership of the PNLP, Key actions DFID and PSI started discussions with the PNLP on the current prevention approaches used in country based on the lessons learnt from this project and will use future key findings from the operational surveys carried out through this project to help update DRC prevention approaches by the end of the first semester 2015. The topics of these surveys are the following: the durability of LLINs in the DRC context; the determinants of LLINS use and non-use among the population in DRC; a review of the first cycle of LLINS mass distribution campaign in DRC. PNLP should update the routine approach and look for additional delivery mechanisms in the country based on the Equateur experience to be shared by PSI by the end of June 2015 PSI should intensify Interpersonal communication by including more community health workers into the project, and encouraging home visits to increase the use of LLINs, from now until the end of the project. PSI should also review the number of community workers required at health area level based on the size and geography of each health area by March 2015. Due to inaccessibilty of remote health areas, PSI should also increase the number of monitoring/ evaluation staff to ensure the good quality of data collection by March 2015. Has the logframe been updated since the last review? No, the log-frame was not changed since last annual review in February 2014 but was updated in conjunction with PSI/ASF as part of the previous annual review process to reflect the additional activities agreed as part of the costextension granted in October 2013. This change was not considered in the last review as the routine activities were not yet implemented. Additional Key Points In addition to the points raised above, the baseline of key indicators should be updated by considering the finding from the recent DHS 2013-2014 before the end of March 2015. Summary of responses to issues raised in previous annual reviews The routine approach used in this project will contribute to maintain the bed nets coverage reached with the mass distribution and will protect the DFID investment in the province. The main recommendations of the last annual review were linked to the mass campaign distribution, especially the monitoring of the bed nets use through pre and post campaign surveys as the hang up activities were cancelled. The benefit of the home visits carried out by community health workers is to encourage population to hang up the bed nets and to use it correctly. Two surveys are planned this year to assess the duration of use of a LLIN by households in DRC and determine factors that might prevent effective use of LLINs in DRC. The last recommendation focused of the evaluation of the most effective medium in reaching members of the population, the interpersonal communication used in the routine distribution? is judged to be more effective as it allows discussion between community workers, health staff and beneficiaries and contributes to increase or maintain the behaviour change. Recommendations Two health districts where the project is implemented have not yet received funds for a second cycle of mass distribution according to WHO recommendations. We will therefore need to consider what further action we or others could take which might help protect our investment and maintain health impact in the province while PNLP is looking for a funding donor. DFID, PSI and PNLP will use the findings of the ongoing survey linked to the use of LLINs to update the national strategy on malaria prevention in the second semestrer of 2015 . PSI and PNLP should explore other mechanisms for the delivery of LLINs during routine distribution to sustain universal coverage in the second semester of 2015 . With the challenging environmnent of work in Equateur, it is important for PSI to increase the capacity of its staff by recruiting two or three additional staff to ensure a good geographical coverage of all the health districts at the same period and data collection. PSI should update the logframe by considering the recent DHS result as baseline in March 2015. . PSI should focus more on interpersonal communication in rural areas and increase the capacity of community workers to give key messages linked to the maintenance of bed nets by March 2015. DFID should work with PSI to improve the financial forecast and increase accuracy before the new financial year. C: DETAILED OUTPUT SCORING (1 page per output) The following output will be scored according to the achievement against milestones for each output indicator. Title LLINs distribution Output number per LF 1 Output Score A Risk: Low Impact weighting (%): 65% Risk revised since last AR? no Impact weighting % revised Yes from 70% during since last AR? the mass campaign Indicator(s) Milestones 2014 Number of LLINs 295 000 distributed through routine channels Number of health facility 1 725 providers trained for LLIN routine distribution. Progress up to December 2014 comments 279 317 Moderately did not meet expectation (94%) 1 731 Met expectation (100%) Despite the delay in the implementation of routine distribution due to the international procurement and transportation of bed nets that took 8 months, the long process to recruit local staff in Equateur and, the outbreak of Ebola in Tshuapa district; the project has made big efforts and has distributed 279,317 against the milestone of 295,000 through the classic antenatal care and immunizations activities in private and public health facilities. During the implementation, it was observed that significant number of Pregnant women did not attend antenatal care but come to give birth in health facilities. This led the project team to decide, in collaboration with PNLP, to consider the delivery period as a complementary chanel mechanism of routine distribution in the province. In total, 169,251 bednets were distributed through ANC channel and 110,066 during immunization services. Trainings on routine distribution, LLIN quantification, use of supervision tools, data collection, and data analyses, were provided to 132 members of the health zones teams and also 799 community health workers (PresiCOSA) and 800 head nurses. In total 1,731 health providers were trained. While visiting the rural areas in Equateur, we noted that the type of bed (wooden platform with rough edges) used leads to a fast ripping of nets which results in a short lifetime of LLINs. With the reality of this Congolese context : is it realistic for PNLP to respect the time frame of 3 years to renew LLINs distribution? Is the combination of campaign and routine sufficient to maintain the coverage or do we need to find additional delivery mechanisms to ensure the full coverage? We are planning to use the findings from the ongoing studies (including lessons learnt from the first cycle of bed nets distribution in DRC and the durability of bed nets) to respond to these questions. Output Title Behaviour change communication Output number per LF 2 Output Score A Risk: Low Impact weighting (%): 15% Risk revised since last AR? No Impact weighting % revised no since last AR? The performance of this output was measured by two indicators: the first indicator concerns radio spots on malaria prevention in general with a particular accent on the correct use of LLINs. The second indicator measures radio programmes where invitees talk about the benefit of protecting pregnant women and U5 children from malaria by the correct use of LLINs and where they were distributed. Indicator(s) Milestones 2014 the number of radio spots 12 144 broadcast on malaria prevention Number of radio programme on 264 malaria prevention organized at health zone level Progress up December 2014 12 621 172 to Comments Met expectation (104%) Substantially did not meet expectation (65%) Intensive Communication activities were carried out ranging from mass media (radio spots and posters) to Inter Personal Communication during home visits, Antenatal Care (ANC) and immunization services. Women groups, churches and mosques were also used as means for social mobilisation and sensitisation in order to increase the correct use of LLIN. While the sensitisation concerning malaria prevention continued in the all targeted health zones, radio programmes on LLINs routine distribution was halted in the12 health zones affected by the Ebola outbreak. The outbreak prevented the provision of bednets in 12 health zones until the end of the quarantine, in November 2014. The sensitisation boosted the utilisation rate of ANC and immunization services in targeted areas. As a result, 2,366 health talks were carried out during the reporting period, 60,385 pregnant women were recorded having attended ANC health talks on malaria prevention, 63,337 caretakers who attended immunization services health talks and 32,428 households visited by community health workers. Moreover, social mobilization activities continue in the form of announcements in churches, mosques, women group gathering. Output Title Monitoring and evaluation Output number per LF 3 Output Score B Risk: low Impact weighting (%): 10% Risk revised since last AR? No Impact weighting % revised Yes from 15% during since last AR? the mass campaign Indicator(s) Milestones 2014 Number of monthly monitoring visits hold at health zone level, Number of quarterly monitoring visits hold at district level, Monthly completion of health facility reports Monthly submission of health facility reports , Monthly completion of health zone reports Monthly submission of health zone monthly reports 504 Progress up December 2014 172 16 6 80% 85% 80% 100% 80% 85% 80% 100% to Comments Substantially did not meet expectation (34%) Substantially did not meet the expectation (38%) Moderately exceeded expectation (106%) Substantially exceeded expectation (125%) Moderately exceeded expectation (106%) Substantially exceeded expectation (125%) As initially planned , each health heath zone among the 42 health zones targeted by routine distribution had to carry out one monitoring visit per month while each of the four health districts had to carry out one monitoring visit per quarter in order to ensure the smooth running of the project. The underperformance of some indicators is explained by the following factors : the routine distribution started only in June 2014 for Mongala district (12 health zones ), in August 2014 for Mbandaka district (3 health zones), September 2014 for Equateur district (15 Health zones ) and finally in December 2014 for Tshuapa district (12 health zones where Ebola outbreak happened. Beside this, PSI has not been effective in the startup of routine activities, primarily in the deployment of bed nets from the warehouse to the targeted health zones , training for health and community workers considered as pre-requisite before starting supervision, and finally the recruitment process new staff was long and took more time . Despite this, health teams were motivated to perform well on other indicators by the support the project provided. This support consists of IT equipment, monthly running costs and bicycles for monitoring and evaluation activities (details in output 4). For the remaining time of the project, there is a need for PSI to reinforce and improve the number of monitoring visits held at health zone and district level given the poor performance against these indicators. Output Title Health system strengthening Output number per LF 4 Output Score A Risk: low Impact weighting (%): 10% Risk revised since last AR? n/a Impact weighting % revised n/a since last AR? This output has been added as a result of the project’s extension to cover health system strengthening to increase the provincial health official’s capacity to monitor and supervision activities and will be considered for this annual review. Indicator(s) Milestones 2014 Number of Health zones targeted 42 from the project area that been equipped with computer hardware Proportion of health zones having 100% received supervision support, Proportion of health zone offices 80% having received supervision visit from health district staff once per quarter Proportion of health facilities having 7 5% received supervision visit from health zone staff once per month Progress up December 2014 42 71% 71% 100% to Comments Met expectation (100%) Moderately did not meet expectation (71%) Moderately did not meet expectation (89%) Substantially exceeded expectation (133%) Efforts have been taken to continue to strengthen the health system by providing training and supervision as well as supporting for operations for the efficient running of activities by provincial, district and health zones teams. Each health zone has received a laptop computer + printer to improve quality data collection, analyses and storage. Health facilities nurses received bicycles to improve supervision activities. Operational supports provided monthly by health zones after a presentation of activities and data consolidated reports. These contributed to the improvement in the supervision activities although because of the delay in the project start the 2014 milestone to for the number of supervision visits was lower than expected. D: VALUE FOR MONEY & FINANCIAL PERFORMANCE Key cost drivers and performance Commodities constitute the key cost driver: as there is no local market for LLIN in DRC, PSI/ASF our implementing partner launched a competitive tender for the procurement and international transport of LLINs and the contract was signed with Vestergaard Frandsen Group South Africa. This process allowed PSI to procure 582,574 LLINs representing 95.5% of the LLIN needed to cover the project period in the 42 Health Zones, 4.5 % of the project needs were covered by the remaining stock of the mass campaign. The unit cost paid by PSI for two-place LLINs was $2.53, lower than the budgeted cost of $2.7 per LLIN, resulting in a saving of $98,994. Cost of transporting commodities has been another key cost driver, the remoteness of the locations in Equateur makes travel and transportation of materials very expensive. There are different layers in transporting commodities: International shipping from manufacturer in South Africa to DRC entry point (Matadi); from Matadi to PSI central warehouses (Kinshasa) by road; from Kinshasa to PSI provincial warehouses (Equateur/Mbandaka) by boat; from Mbandaka to different health zones by road or boat and finally from health zones to health facilities by car or bicycle. Table 2: Project costs by output and category Spend (October 2013PSI Budget category February 2015) Commodities (LLINs) £1,061,501 Sampling and testing £1,373 £91,098 Output1: LLINs Shipping and handling Training £89,321 distribution Procurement fees £42,460 Output 2: Promotion and Advertising £19,356 Behaviour change Communication and Education £63,671 Research and evaluation (studies) £61,911 Output 3: M&E Travel and subsistence £274,342 £22,881 Output 4: health Consultants Equipment £114,339 system strengthening Sub awards (operating cost – health districts and health zones) £65,762 Staff Personnel and fee rate £185,053 Office Other direct cost £121,226 Management Administrative fee £129,998 TOTAL PROJECT COST £2,344,292 Output % of total project expenditure 55% 4% 14% 9% 7% 5% 6% 100% In total , 82% of the budget was spent on programme delivery and health system strengthening, 11% on PSI office and management fees and 7% on staff. VfM performance compared to the original VfM proposition in the business case This project memorandum predates DFID Business Case, thus does not have the same VfM measures. A cost and time extension that was approved in October 2013 (Quest 4212123) set the following comparators: Table 3: Mass vs routine distribution unit cost Province Coverage Mass distribution in 4.2m LLINs for 8.5m people Equateur Total cost Unit cost* Comments £20m £4.58 Mass distribution with a limited time for the campaign Routine distribution through health services over 2 years Equateur extension 609,616 LLINs for 894,104 £3.9m £5.99 pregnant women and (excluding children under 1 £300k for operational research) Mass distribution in 4.4m LLINs for 7.2 m people £20m £4.57 Kasai Occidental Mass distribution with a limited time for the campaign *The unit cost includes the price of a net plus procurement fee, transport and distribution cost. The logistics of operating in Equateur are extremely difficult, with chronically limited transport, infrastructure and communications network. The road infrastructure is limited and in very poor condition, exacerbated by constant rain making any kind of movement extremely hard. Any imports arrive by river (4-5 weeks from Kinshasa) or by air to Mbandaka. Several health areas are located alongside of the Congo River with no communication network coverage and are hardly accessible. Despite the challenging context in Equateur, the extension represents value for money, and is expected to achieve a unit cost of £5.99. The number of expected malaria episodes averted through LLIN use by pregnant women and children less than one year old would result in more cost effective and significant health impact than that associated with the treatment of malaria episodes in absence of LLIN use. AS DFID primary health care project (ASSP) is also implementing routine distribution within the supported health zones, it will be important to try to compare the unit cost in both of DFID supported programme when data become available. Assessment of whether the programme continues to represent value for money The routine distribution of LLINs is expected to maintain the impact of the mass distribution for longer, by continuously replacing LLINs over time, reinforcing and maintaining behaviour change, and strengthening the health system by providing training and supervision. The intervention will be provided until 2015, when the next mass distribution of LLINs in Equateur is scheduled to take place. Although the unit cost of LLINs for this extension is higher than the £4.58 achieved by PSI for the mass distribution in Equateur, this is not unexpected, as routine distribution takes place over a longer time period and is less able to achieve scale of economy than mass distribution. This observation is consistent with evidence from Uganda demonstrating that the delivery cost of bed nets is higher through antenatal care than through mass campaignsiii . The higher unit cost may at least be partly offset by additional impact per net distributed. Firstly, through routine distribution, LLIN delivery will be targeted towards those most vulnerable to malaria, i.e. pregnant women and children under one year old. Secondly, the intervention is expected to slow the rate at which the coverage achieved by the last mass distribution in Equateur will decline over time, thereby prolonging and protecting its impact. There are limited data available on the unit cost of routine distribution elsewhere which would allow us to benchmark the figure of £5.99. Furthermore, differences in methodology mean that in general, where unit costs of LLIN distributions are available, they are difficult to compare meaningfully. This has led to the authors of one review of the cost of LLIN distribution to observe that: “The cost of different ITN delivery strategies is important when deciding which ones to scale-up, yet it is one of the knowledge gaps remaining to be filled. Many strategies have not been costed at all and only some of the existing cost-estimates have been derived using appropriate methods. Well-conducted studies have often used outputs that are difficult to compare”iv . In view of the limited evidence for the relative cost-effectiveness of different delivery strategies for LLINs, PSI is now carrying out four different studies on 1) the cost effectiveness of routine after mass campaign, 2) determinants of bed nets retention and use, 3) lessons learnt from the first cycle of bed nets distribution in DRC and 4) the durability of bed nets. The results of these studies are due by the end of the first semester of 2015 and findings will be shared with PNLP in order to review or update the current strategy for LLINs distribution in DRC. However, the project is operating within the estimated cost and there is no fear of an overspend in the remaining project’s lifetime. Quality of financial management Table 4: Extension budget burn rate Financial year 11/12 & 12/13 Mass distribution Routine distribution Forecast/budget £20m Spend to date £19.8m % 99 £4.2m £2.3m 55 13/14 14/15 £1.6m £2.4m £1.6m £1.3m 100 54 15/16 2011-2015 Total budget £0.2m £24m £22.7m 95 Comments Remaining 1% included in the extension Routine intervention ends in October 2015 Remaining £1.07m. Discussion ongoing whether this can be transferred into 15/16 To date, the spend and forecast for financial year 2014/2015 accounts for 54% of burn rate but this has raised the whole project’s spend to 95%. The reason of this underspend is two-fold: the delay in starting the implementation of the project’s extension, the suspension of activities for up to 4 months in 12 health zones affected by Ebola and the inaccuracy of PSI forecasts over the year. While the Ebola was unpredictable, PSI should have predicted the delay that was caused by the recruitment of staff in Equateur, the purchase of LLINs and their delivery in Equateur and forecast accordingly. While the project’s extension started in October 2013, the purchased LLINs were delivered in Equateur in July 2014. There was a 3-month delay between the end of the original LLIN distribution campaign project and the beginning of the new routine distribution project. PSI had to close both its Mbandaka and Lisala offices and most of the project staff were transferred to other LLIN distribution projects in Kinshasa and Province Orientale. This resulted in start-up delays, as PSI had to recruit all new staff and identify new office and warehouses. While strong sensitisation boosted the utilisation rate in ANC and immunization services (in health facilities), hence increased the distribution of bednets to pregnant women and U5 children, some other activities were partly funded. This is the case of research studies (costing around GBP 300k) planned in the last quarter of this year but to be completed and then fully paid in the next financial year. Besides, 12 health zones affected by Ebola did not receive running costs and trainings of health providers for four months during which they were under quarantine. Due to 2025/2016 budget constraints, discussion is ongoing within DFID DRC health team on the transfer of 2014/2015 underspend to the following year. The remaining 5% should be expected to be spent in the 9 remaining months before the project’s end. DFID is looking forward to working with PSI on forecasts’ accuracy. DFID and PSI will need to agree a spending schedule for remaining activities which are: pay the remaining funds for studies, transport of LLINs from PSI warehouses to health zones – health facilities, operating support to health districts and health zones for monitoring activities and PSI staff salaries. Date of last narrative financial report Date of last audited annual statement 12 February 2015 June 2014 E: RISK Overall risk rating: Low/Medium/High Low Overview of programme risk During the reporting period, the health district of Tshuapa particularly the Boende health zone which is part of the project experienced an outbreak of Ebola haemorrhagic fever leading to the declaration of quarantine in the Tshuapa health district , this situation highly compromised the start of activities in the entire Tshuapa health district, ASF/PSI put in place an Ebola prevention strategy which consists of continuous education for staff, and monitoring of staff movement to avoid any infection, LLINs leakage was experienced during the mass campaign in Tshuapa health district particularly, to prevent similar situation, ASF/PSI opted to store in Mbandaka all LLINs destined for distribution in Tshuapa, Health zones in Tshuapa will be supplied quarterly and the provincial NMCP and ASF will intensify joint supervision activities with focus in Tshuapa. These LLINS were recoverd with the involvement of the provincial government one week after. ASF/PSI has developed and put at the disposal of each zones and health centres, tools to track LLINs movement. Monthly data on the balance between the number of LLINs received by each health zone and the number of LLINs distributed to beneficiaries are recorded for better accountability. An early closure of the project in March 2015 as initially planned with the RAR cut will present the following risks: 1. Undistributed LLINs (about 300,000) will be left to provincial health officials with no guarantee of results 2. The absence of PSI will increase the likelihood of interference of the provincial authorities in misuse of LLINs 3. The lack of incentives might lead to a loss of motivation in district and health zones teams It is likely that the two health districts supported by this current project will not benefit from the second cycle of mass bed nets distribution due to the lack of financial funds , there is a risk of losing the benefit gained with the extension that maintained the high coverage of bed nets. Outstanding actions from risk assessment Consider what actions we or others might take to project the benefit of our investment in the province. Outstanding actions from due diligence A comprehensive Due Diligence Assessment (DDA) was conducted with PSI DRC team in person and their Deputy Regional Director over the phone. The DDA was signed off by DFID DRC Head of Office on 27 October 2014 (Quest 4706468). The following recommendations were made: DDA recommendation DFID to be advised of timing of Internal Audit visits and consider requesting a meeting with the team to better understand risk environment PSI to include the risk matrix with updates and future actions as part of their quarterly reporting status Outstanding: waiting the visit of PSI Internal Audit Implemented. An updated risk matrix is part of six monthly report DFID to maintain their current practice of seeking Ongoing confirmation of forecasts at regular intervals. And also seeking to improve communication and understanding with PSI finance team Ensure that PSI’s recognised purchase and Implemented. PSI distribution process are detailed in their financial sends quarterly and narrative reports. And that funds to contractors detailed financial are clearly set out in reporting to DFID. reports. Additional information is also produced on DFID’s demand. F: COMMERCIAL CONSIDERATIONS Delivery against planned timeframe The routine activities started with a delay for the following reasons: the approval of the extension of the project took three months before being effective, in the meantime the office was closed in Equateur. PSI was obliged to recruit new staff to start the project with a focus on local recruitment to promote local ownership of the project and to ensure at least 30% gender balance in staffing. This process lasted for 4 months. During the implementation of this project, with the outbreak of Ebola, the activities were suspended in one district for 4 months (in 12 health zones). However, and in regard to the current performance compared to 2014 planned milestone, it is likely that with the available means, the implementer will meet the end of project targets. However, the £200k forecasted for this programme in 15/16 (due to the resource allocation round) will not be sufficient to support the distribution of more than 300,000 LLINs planned for next financial year, we anticipate that there is a need to look for a way to consider if there is space in the budget for the next year in order to continue the implementation of the project. Performance of partnerships The project is implemented under the leadership of the National Malaria Control Programme (PNLP) and is contributing to their objectives. PSI is in regular communication with both government, provincial and central health stakeholders and authorities to share relevant project documents and information, and to address concerns that have arisen over financial and technical management, transparency and reporting at the provincial level. Regular meetings are held between DFID, PSI and the National Malaria Control Programme staff at both central and provincial level to evaluate progress on activities implementation. This collaboration has helped PSI and PNLP to jointly develop alternative solutions to reach more beneficiaries by including the private sectors facilities into the project and by tracking pregnant women who never attend ANC but seek health facilities during delivery period. PSI is also working with local transporters to move LLINs from PSI central and provincial warehouses to health zones. PSI is also working with local radio stations to broadcast key messages about routine distribution, malaria prevention and correct use of a LLIN. Asset monitoring and control Programme’s assets are those used in the previous mass distribution in the province of Equateur and a few ones from the UNDP DFID funded project that was completed in the province. In particular, vehicles and motorbikes are now used and in poor condition. PSI keeps good electronic and physical record of programme’s assets. The PSI’s project manager reviews project’s assets inventory on a quarterly basis as per PSI guidance and DFID’s accountable grant provision on assets. The updated assets list is sent to DFID as an annex to the narrative report every six months. On a recent field visit, spotchecks were conducted by DFID team on assets used by PSI staff in Mbandaka and those used by two health zones management teams in Mbandaka and Bikoro. DFID team was satisfied of the level of asset management on the field. DFID and PSI will agree on the future of usable assets before the project’s end. G: CONDITIONALITY Update on partnership principles Not applicable H: MONITORING & EVALUATION Evidence and evaluation There is no evaluation planned for this project as the post campaign survey carried out in 2013 has already demonstrated the impact of the mass campaign, especially for the following indicators: the ownership of LLIN by household in Equateur increased from 55.5% to 90.8%. The percentage of children under five who slept under an LLIN the night before the survey rose from 29.9% to 79.9%. This high coverage is also confirmed by the recent findings from DHS 2013-14 published in May 2014) The project has planned to carry out four operational research studies in order to get evidences on malaria prevention strategies used in DRC and feed discussion aimed to update the current approaches implemented in the country. Four tenders have been launched since October 2014 to select research agencies which will then conduct the following studies: a) The determinants of LLIN use and non-use among the population in DRC: The main objective of this study is to explore and identify the causes of non-use of LLINs and the expectations of beneficiaries b) The durability of LLINs in the DRC context: The objective of this study is to determine the sustainability (physical integrity and persistence) of LLINs in the field to adapt the cycle and LLINs distribution arrangements in the DRC. c) The cost effectiveness of the distribution of routine after campaign mass of LLINs (specific to Equateur province): the objective of this study is to determine the unit cost of routine distribution in DRC and the level of coverage and use of LLINs in the Health Zones with supported post campaign routine distribution of LLINs compared to health zones without supported post campaign routine distribution. d) A Review of the first cycle of LLINs mass distribution campaigns in DRC: The objective of this study will be to review the first round of mass distribution of LLINs campaigns that took place in the DRC since the first strategic plan (2009) in order to draw lessons that can help further improvement of the next mass distribution campaigns in the country. The findings for these studies are expected at the end of June 2015 and will feed discussions on malaria prevention strategies in DRC. Monitoring progress throughout the review period In collaboration with PNLP, provincial MoH, and key malaria partners, the programme has supported the harmonization of existing routine LLIN distribution tools such as the beneficiary register, the LLIN inventory sheet, stock reception and movement documents among health zones. Routine monitoring data is collected on a monthly basis at the health facilities level and then transferred into a monthly summary sheet submitted respectively to health zone level, and the health district level. A review of routine monitoring data is conducted on a monthly basis at health zone level and quarterly basis at health district level. ASF/PSI M&E staff work closely with government staff at each level of the health system to ensure quality of data and contribute to reinforcing the data management system during regular and joint supervisions. PSI and DFID team meet on regular basis ( each month) to discuss and update the progress of the project. During our recent visit to Equateur (from19th to 22ndJanuary 2015), we met with various provincial authorities, the governor, the provincial minister of health, Provincial Medical Inspector, the provincial coordinator of PNLP, the heath zone management teams (equipes cadres des zones de santé) of Bikoro and Mbandaka, the communities and health workers in the following health areas: Penzele, Botende,Bikoro and Mbandaka. All authorities appreciate the impact of this intervention as it has boosted some indicators such as the rate of antenatal care ( ANC) and immunization coverage. By providing IT kits to each health zone and supporting training and supervision in the these 42 health zones without any other external assistance, this project is judged to be really important for the province and has a big impact on the strengthening of the health system after the closure of World Bank project in the province. The excellent collaboration between the implementing partner and health authorities is a key element that has contributed to the effectiveness of the project as everybody is involved to address/or solve issues/obstacles identified during the implementation, for example, the additional delivery mechanism of bed nets at birth delivery and the integration of private facilities into the project are the outcomes of this kind of collaboration. This annual review process consisted of the following components: -Regular meetings with PNLP -Monthly meetings with PSI -Field visit to two health zones In Equateur (Mbandaka, Bikoro) -Reviews of four financial and two narrative reports -Feedback meeting with PSI, Health zones management meeting, health workers, community workers, and beneficiaries. i Measure DHS ICF international, DHS2013-2014, Final report published in May 2014 Measure DHS ICF international, DHS2013-2014, Final report published in May 2014 iii Kolaczinski J, “Cost and effects of two public sector delivery channels for LLIN in Uganda”, published on 20 April 2010 iv Kolaczinski, J and Hanson K (2006). “Costing the distribution of insecticide-treated nets: a review of cost and cost-effectiveness studies to provide guidance on standardization of costing methodology” published on line in 2006. ii Smart Guide i