P a g e | 79 11 REFCL management of harmonics All electricity distribution networks suffer from distortion of the pure 50Hz sinusoidal voltage waveform caused by non-linear customer loads. These distortions are described in terms of mathematically equivalent harmonic voltages and currents. Network harmonic voltages can cause harmonic currents to flow in earth faults, so they are therefore relevant to powerline fire risk. One REFCL technology, the GFN, has the capability to inject a synthesised voltage waveform to cancel network harmonic voltages and reduce harmonic currents flowing in faults. This capability was explored in Kilmore Tranche 4 tests. The tests confirmed the capability was effective but revealed that further GFN development would be required to realise the potential benefits of this feature in addressing fire risk from network earth faults. 11.1 Summary of findings and recommendations The effects of network harmonics on fire risk in a REFCL-protected network were explored in the KMS test program. The following conclusions were drawn: 1. In some circumstances, harmonic currents generated by customer loads can flow in a network earth fault and they may have the potential to increase fire risk. 2. It is likely the contribution of harmonic currents to fire risk is second order. 3. Tests demonstrated that: a. Harmonics do not significantly increase fire risk from GFN diagnostic tests to confirm the presence of a fault and identify the faulted powerline. b. GFN measurement of low-order network voltage harmonics is consistent with that performed by other network voltage monitoring devices; c. The GFN has the capability to effectively reduce low-order harmonic components of earth fault current; d. Further product development would be required for the GFN harmonic compensation capability to provide its full potential fire risk benefits; and e. The GFN can itself produce some harmonic fault current when it displaces network voltages – this is likely to be a property inherent in all ASC-based REFCLs. It is recommended that industry work with the GFN manufacturer to further develop the GFN harmonic compensation capability to reduce fire risk in network earth faults. 11.2 Fire risk from harmonics in network earth faults Many electrical devices have non-linear voltage-current characteristics. When 50Hz network voltages supply customer loads that include such devices, the network load current contains harmonics, i.e. components at frequencies that are multiples of 50Hz. When harmonic currents flow in the series impedances of powerlines, they create harmonics in network voltages. A typical frequency spectrum of a KMS21 test network voltage is shown in Figure 1 – harmonic voltages of between one and 30 volts extend in frequency up to 1600Hz. In a single phase to earth fault, harmonic network voltages produce harmonic components of fault current that increase the total rms fault current. If a REFCL is used to cancel the 50Hz component of fault current, the harmonic currents will remain largely unaffected and their presence can significantly increase the magnitude of residual fault current and thereby potentially increase fire risk from ground ignition. This is illustrated by Figure 2 which shows the 50Hz voltage on the faulted conductor has been reduced by the GFN from its pre-fault value of 12,700 volts to about 65 volts. However, the postfault harmonic voltage magnitudes remain of the same order as before the fault, i.e. between one 1 © Marxsen Consulting Pty Ltd Документ1 Friday, 4 December 2015 P a g e | 80 volt and 30 volts1. The harmonic components of fault current are of a similar magnitude to the 50Hz component of fault current. Figure 1: KMS Test 651 frequency spectrum of pre-fault White phase voltage 1 The marked increase in the third harmonic voltage from 6 volts to 60 volts is due to the GFN itself – see Section 11.8. © Marxsen Consulting Pty Ltd Документ1 Friday, 4 December 2015 P a g e | 81 Figure 2: KMS Test 651 (400Ω fault) frequency spectrum of White voltage and fault current immediately post-fault Ignition tests indicate that total rms of fault current is likely to be the most meaningful measure of the environmental energy release that drives fire risk. Harmonic components increase the total rms © Marxsen Consulting Pty Ltd Документ1 Friday, 4 December 2015 P a g e | 82 value of fault current in accordance with a root-sum-of-squares formula: 𝑛=∞ 𝑖𝑟𝑚𝑠 = √ ∑ (𝑖𝑛 )2 𝑛=0 This means that an additional harmonic component equal in size to the 50Hz component would increase the total rms fault current by 40%, not 100%. The fire risk contribution of harmonic components of fault current is therefore only likely to be significant if the harmonics are of a similar order of magnitude to the 50Hz component. 11.3 Increased ground ignition fire risk from harmonics High impedance faults are realistic representations of known fire causes, e.g. a live high voltage wire falling into dry grass on dry ground. When the fault impedance is high, the ignition mechanism is ground ignition rather than bounce ignition. In a high impedance fault, both the 50Hz and harmonic components of fault current are reduced to low levels by the fault impedance. The 50Hz component is reduced more because of the high impedance presented by the resonant neutral-earth connection (the parallel combination of the ASC coil and the combined capacitance of the network and the ASC tuning capacitors), as well as by the RCC compensation to cancel the 50Hz component of voltage on the faulted phase. This is illustrated by Figure 3 for a 40,000 Ohm earth fault. The fifth harmonic of the fault current is 1.2mA which is consistent with the pre-fault value of fifth harmonic voltage (49 volts) divided by the fault resistance (40kΩ). The 50Hz component of fault current is 2.5mA which less than one-hundredth of the 320mA that the 40kΩ fault resistance alone would produce with an applied 50Hz voltage of 12,700 volts. Figure 3: KMS Test 634 (40,000Ω fault) fault current with RCC compensation © Marxsen Consulting Pty Ltd Документ1 Friday, 4 December 2015 P a g e | 83 In ‘wire on ground’ ignition tests with the GFN in service, once the GFN detected and compensated for the fault, no ground ignitions occurred. The tests outlined in Section Ошибка! Источник ссылки не найден. above confirm that fault current of 0.5 amps is required for ground ignition in a worstcase earth fault. For a relatively high total harmonic voltage of, say, 500 volts to generate this level of harmonic current the fault impedance would have to be not more than 1,000 Ohms. Even in this worst-case situation, there are two considerations that indicate the fire risk from harmonics would at most be second order: 1. It is difficult to postulate realistic circumstances in which just three metres of conductor on the ground would have a fault resistance as low as 1000 Ohms without assuming higher levels of soil and fuel moisture content than would be consistent with worst-case fire weather and fuel conditions. 2. Detection of such a fault would be relatively fast, both in the initial instance and in the GFN fault-confirmation test, so the harmonic current flow would last at most about five seconds the period between the fault and the first steps of the fault-confirmation test. A fault current of 0.5 amps generally takes longer than this to produce ground ignition – often tens of seconds. Whilst there is no guarantee that a particular combination of factors capable of starting a fire from harmonic currents can never occur, the probability of this combination is considered to be relatively low, i.e. fire risk from harmonic currents is likely to be a second order risk. 11.4 Fire risk from harmonics in diagnostic tests In high-impedance faults, the key factor in fire risk is the current produced in diagnostic tests such as the fault-confirmation test. The GFN performs such tests by injecting a 50Hz voltage. This leaves harmonic components of fault current largely unaltered as can be seen from Figure 4 - the faultconfirmation test increased the 50Hz current by twenty-five times from 2.5mA to around 65mA (shortly afterwards the FCT re-detected the fault at a current of 132mA), but the fifth harmonic current remained unchanged at 1.2mA. It can be concluded that harmonic currents do not significantly increase fire risk in diagnostic tests. © Marxsen Consulting Pty Ltd Документ1 Friday, 4 December 2015 P a g e | 84 Figure 4: KMS Test 634 (40,000Ω fault) fault current during GFN fault confirmation test (Stage 1, Step2) This leads to the conclusion that in high impedance faults, harmonics are unlikely to contribute significant fire risk from ground ignition. 11.5 Increased bounce ignition fire risk from harmonics The ignition mechanism in low impedance faults tends to be bounce ignition. The REFCL response required to prevent fires from this cause is fast reduction in the voltage on the faulted conductor to less than 1,900 volts in 85 milliseconds. For a relatively high level of network harmonics of perhaps 500 volts, the root-sum-of-squares addition means the total voltage at 85 milliseconds would only be increased by 3.4% to 1,960 volts compared to the 1,900 volts 50Hz component. The effect of this increase on bounce ignition fire risk would likely be immaterial. 11.6 Measurement of harmonics by the GFN The GFN samples the network voltage waveforms with 16-bit precision at a rate of 100 samples per 50Hz cycle. To measure harmonics the GFN applies a discrete Fourier transform to groups of 100 samples. GFN documentation does not identify the window function (if any) applied prior to the transform calculation to minimise spectral leakage. Theory predicts this arrangement should be capable of measuring harmonics up to about 2 kHz, i.e. to the 40th harmonic of the 50Hz fundamental. However, the voltage waveforms seen by the GFN are produced by an electromagnetic voltage transformer on the substation’s 22kV busbars. The limited bandwidth of this type of transformer may affect measurement accuracy at higher harmonic frequencies. A manually synchronised spot check was performed to compare measurements on two selected loworder harmonics supplied by three devices: 1. The GFN supplied by the substation 22kV bus voltage transformer; 2. An Elspec supply quality meter in the zone substation also supplied by the substation 22kV bus voltage transformer; and © Marxsen Consulting Pty Ltd Документ1 Friday, 4 December 2015 P a g e | 85 3. The Gen3i data acquisition system at the test site supplied by a wide-band capacitive voltage divider. The three sets of readings are shown in Table 1. Table 1: comparison of harmonic measurements - red phase voltage 8th October 2015 at about 1:20pm Harmonic Time GFN2 Gen3i Elspec 5th (250Hz) 1:23:45 pm 0.2 (30-50 volts) 48 volts 48 volts 7th (350Hz) 1:18:30 pm 0.1 (10-30 volts) 25.2 volts 27.1 volts Within the limitation imposed by the single significant figure display of the GFN, its displayed readings were consistent with the measurements taken by the other two devices. This spot check also indicated that the limited bandwidth of the busbar voltage transformer was not a material factor in accurate measurement of harmonics up to 350Hz3. 11.7 Compensation of harmonics by the GFN The GFN has the capability to include low-order harmonic components into its RCC-injected compensation voltage to cancel corresponding harmonic components of fault current. This capability was tested in the Kilmore test program. Test 723 best illustrated its effectiveness as shown in the three fault current frequency spectra set out in Figure 5, Figure 6 and Figure 7 together with the fault current waveforms associated with each. With no harmonic compensation, Figure 5 shows that the third harmonic and fifth harmonic components of the fault current are of the same order of size as the 50Hz component. Those two components increased the total rms fault current by 94% above the 50Hz value. After manipulation of the GFN harmonic compensation settings, Figure 6 shows the third harmonic component of fault current has been reduced by 90%. However in the 23 second period since the first record, the fifth harmonic component of fault current has increased by 37% to 0.14 amps. After further manipulation of the GFN harmonic compensation settings, Figure 7 shows the fifth harmonic component of fault current has been reduced by 70%. At this point, the third and fifth harmonic components of fault current were increasing the total rms fault current by just 6% above the 0.117 amps 50Hz value. Though Test 723 demonstrates an effective capability to compensate low-order harmonic components of fault current, this was done by manual manipulation of GFN settings. To reduce fire risk by minimising fault current caused by network harmonics, the GFN must include a dynamic capability to measure and cancel the ever-changing levels of low-order harmonics on the network. It is recommended that industry work with the GFN manufacturer to enhance the harmonic compensation capability of the GFN to minimise fire risk from network harmonics. 2 The GFN readings shown are those available on the front panel and only had one significant figure displayed. The GFN only displays the 3rd, 5th, 7th and 9th harmonics though its measurement system is theoretically capable of measuring harmonics up to the 40th. 3 The Gen3i readings used a wide-band capacitive transducer, whereas the Elspec readings used the substation busbar electromagnetic voltage transformer. © Marxsen Consulting Pty Ltd Документ1 Friday, 4 December 2015 P a g e | 86 Figure 5: KMS Test 723 (400Ω fault) fault current with 50Hz compensation only © Marxsen Consulting Pty Ltd Документ1 Friday, 4 December 2015 P a g e | 87 Figure 6: KMS Test 723 fault current with third harmonic compensation © Marxsen Consulting Pty Ltd Документ1 Friday, 4 December 2015 P a g e | 88 Figure 7: KMS Test 723 fault current with both third and fifth harmonic compensation © Marxsen Consulting Pty Ltd Документ1 Friday, 4 December 2015 P a g e | 89 11.8 Generation of harmonics by the GFN The response of a GFN to an earth fault, i.e. voltage injection by the RCC to cancel the voltage on the faulted phase, can itself produce harmonic components of fault current. 11.8.1 How a non-linear ASC coil generates harmonic earth fault currents The mechanism is as follows: 1. Harmonics in the magnetising current drawn by the ASC coil When the GFN compensates the 50Hz component of earth fault current, it effectively applies a synthesised pure 50Hz sinusoid voltage across an iron-cored inductor (the ASC coil) that is in resonance with the capacitance of the network in parallel with the capacitors in the ASC unit itself. The iron core of the coil is not linear and it will draw some harmonic currents from the pure 50Hz source voltage applied by the RCC. The harmonic current components generated by the coil’s nonlinear characteristics will flow in both the coil and the RCC inverter. 2. Harmonic voltage produced on the neutral of the transformer and on all network conductors If the RCC were an ideal voltage source, the harmonic currents flowing between the RCC and the ASC coil would not affect network voltages. However, the non-zero source impedance of the RCC4 means they produce harmonic components of neutral voltage. The resonant combination of the coil and the combined network plus ASC capacitance will have very high impedance at 50Hz but lower impedance at frequencies other than 50Hz – the actual value will depend on the total system (network plus ASC) damping. This impedance forms a voltage divider with the RCC source impedance to produce a harmonic voltage across the ASC coil, i.e. at the neutral point of the transformer. For lower harmonic frequencies, this harmonic voltage will appear between every powerline conductor in the whole network and earth. 3. Harmonic current flow in an earth fault When a single phase earth fault is present, the harmonic voltage on the faulted conductor will produce a harmonic current in the circuit loop comprising: The substation transformer winding between the neutral-ASC coil connection and the faulted phase of the substation 22kV busbars; The faulted phase conductor from the substation 22kV busbars to the fault location; Through the fault to earth; and Through the earth back to the ASC coil-earth connection at the substation. 11.8.2 Factors that determine the magnitude of harmonic fault current Two main factors will influence the magnitude of the harmonic component of fault current caused by the GFN response to the fault: 1. Harmonic neutral voltage: The magnitude of the harmonic voltage across the ASC coil is likely to be close to the magnitude of harmonic magnetising current necessary to support the 50Hz voltage applied across the coil by the RCC multiplied by the effective source impedance of the RCC. Other factors are likely to be second order. 4 This impedance is due to the length of 345 volt cables between the RCC inverter and the ASC coil as well as the leakage flux between ASC windings. The 37:1 turns ratio of the ASC multiplies the impedances of these elements by 1350 times when they are seen from the 22kV network. © Marxsen Consulting Pty Ltd Документ1 Friday, 4 December 2015 P a g e | 90 2. Earth fault loop impedance: two impedances will determine the magnitude of the harmonic component of fault current produced by the harmonic voltage across the coil: a. Transformer winding impedance: the substation transformer will offer some impedance to the harmonic current flow. Transformers can have complex internal magnetic configurations which may influence this impedance. For example, most large substation transformers (such as the one at KMS) have three limbs to the internal iron core. The internal distribution of magnetic flux this produces means that lower impedance may be offered to the flow of triplen5 harmonic currents on the network and higher impedance to harmonics at other frequencies. The detailed modelling that would be required to confirm this was beyond the scope of this project. However, the test results did indicate a qualitative difference between the behaviour of triplen harmonics and that of other harmonics in the fault current. b. Fault resistance: the fault resistance impedes current flow equally at all frequencies. A high-impedance fault will greatly reduce harmonic current flow, whereas a lowimpedance fault can produce high harmonic currents. In summary, the non-linearity of the ASC coil can create some harmonic fault current even if there are no harmonics in pre-fault network voltages. 11.8.3 Confirmation in simulations Simulations of the response of a GFN with a non-linear ASC iron core were used to confirm the mechanism for generation of harmonic fault currents by a GFN. These were not exact simulations but served to verify the concept. The model used is shown in Figure 8. Figure 8: conceptual model of GFN response to an earth fault with non-linear ASC coil The non-linearity is introduced by the Zener diodes D5 and D6 (±15,000 volts withstand) and D7 and D8 (±10,000 volts withstand). The source impedance of the RCC is modelled by R14 and L4 (50Ω+j50Ω), equivalent to about 50 milliohms on the low voltage side of the ASC. The concept simulation results are set out in Table 2. 5 Any odd harmonic number divisible by three: 3rd, 9th, 15th, 21st, etc. © Marxsen Consulting Pty Ltd Документ1 Friday, 4 December 2015 P a g e | 91 Table 2: simulation of non-linear ASC - effect on fault current Simulation ASC coil RCC source impedance Fault current (amps rms) Fault current harmonics 1 Linear (50+j50) Ohms 0.10 Amps 50Hz only 2 Non-linear (50+j50) Ohms 2.67 Amps Mainly harmonics 3 Non-linear Zero Ohms 0.002 Amps 50Hz only The results in Table 2 confirm that ASC non-linearity combined with finite (i.e. non-zero) RCC source impedance will produce harmonic fault currents. The fault current waveform produced in Simulation 2 (non-linear ASC with finite RCC source impedance) is shown in Figure 9. Figure 9: fault current result in simulation of non-linear ASC with finite RCC source impedance It was concluded that the conceptual mechanism described in Section 11.8.1 above is a probable cause of some harmonic current components in network earth faults when a GFN is present. 11.8.4 Confirmation in test results This phenomenon was observed in the KMS test results. Ten tests were analysed for harmonic components of voltages before and after fault detection and RCC response. Pre- and post-fault measurements were only a few seconds apart. However, harmonic levels vary continuously on the network due to changes in customer loads so even this short interval may have involved changes due to factors outside the experiment. To find underlying patterns, averaging over a group of tests was used. Seven of the tests had a 40,000 Ohm fault resistance and three had a 400 Ohm fault resistance. The average harmonic levels across all ten tests are shown in Table 3 to Table 5. Table 3: pre-fault voltage harmonics (volts rms) Phase Red White Blue All 50Hz 12330.2 12208.9 12982.4 12507.2 150Hz 12.6 6.8 13.3 10.9 © Marxsen Consulting Pty Ltd 250Hz 37.2 45.7 32.4 38.4 350Hz 26.8 26.3 21.9 25.0 Документ1 450Hz 4.0 1.6 3.3 3.0 550Hz 7.8 19.0 9.8 12.2 650Hz 11.4 19.4 16.2 15.7 Friday, 4 December 2015 P a g e | 92 Table 4: post-fault voltage harmonics with full RCC compensation (volts rms) – un-faulted phases Phase Red White Blue All 50Hz 21572.8 21580.0 21577.2 21576.7 150Hz 51.6 56.9 46.7 51.7 250Hz 28.9 39.1 24.7 30.9 350Hz 26.5 23.4 20.1 23.4 450Hz 5.3 4.5 7.2 5.7 550Hz 9.1 19.9 12.9 14.0 650Hz 13.6 20.7 17.4 17.2 550Hz 8.9 650Hz 15.3 Table 5: post-fault harmonics with full RCC compensation (volts rms) – faulted phase Phase Faulted 50Hz 85.2 150Hz 54.3 250Hz 39.3 350Hz 11.7 450Hz 7.8 The pattern detected in the test results was: 1. RCC action was associated with increases in triplen harmonic voltages: The triplen voltage harmonics increase in the post-fault period when there is 12.7kV of 50Hz voltage across the ASC coil. The increase in the third harmonic (150Hz) was particularly dramatic – in tests it increased by a factor of five times. The ninth harmonic (450Hz) approximately doubled. 2. Non-triplen harmonic voltages seemed uncorrelated with RCC action: The effect of the fault and its compensation on non-triplen voltage harmonics was mixed: the change in the fifth was within the normal test-to-test variation, the seventh was approximately halved on the faulted phase but remained unaltered on the un-faulted phases, the eleventh appeared slightly diminished on the faulted phase but unchanged on the others, and the thirteenth was affected hardly at all. Because third harmonic currents are zero-sequence, they cannot be generated by customer loads except in a network of unbalanced impedances – and even in that situation, they are usually small. The large increase in the third harmonic seen in KMS tests when a fault is applied is almost certainly due to the non-linearity of the magnetising curve of the ASC coil. 11.8.5 Relevance to fire risk This phenomenon may tend to increase potential fire risk as it can drive a significant 150Hz component of fault current. The ratio of fundamental to harmonic components of fault current in the ten tests is shown in Table 6, grouped and averaged by fault resistance. Table 6: harmonic components of residual fault current averaged over ten tests Fault 40,000Ω 400Ω 50Hz 100% 100% 150Hz 80% 93% 250Hz 68% 43% 350Hz 20% 16% 450Hz 13% 10% 550Hz 12% 10% 650Hz 26% 11% The third harmonic component of fault current was about 85% of the 50Hz current. This increased the total rms value of fault current by about 30% above the 50Hz value. If the third harmonic component of fault current was solely that driven by network voltages without the effect of the ASC coil (i.e. five times less), the total rms value of fault current would only have been increased by 1-2% above the 50Hz value. It is recommended that the GFN manufacturer consider the addition of triplen harmonic compensation to cancel the harmonic current generated by the ASC coil and minimise fire risk from triplen harmonic fault currents. Section 11.7 above indicates the GFN has the capability to do this with appropriate settings. © Marxsen Consulting Pty Ltd Документ1 Friday, 4 December 2015 P a g e | 93 12 REFCL management of two-phases-to-ground earth faults Network faults that convey current from two phase conductors to earth arise most commonly from two causes: fallen trees on powerlines and a fallen conductor which remains connected to the powerline on the ‘downstream’ side of the break (called a back-fed fault). Both of these faults involve potential fire risk. Tests were performed at the Kilmore South test site to better understand the capability of a REFCL (specifically the GFN) to manage this risk. 12.1 Summary of findings and recommendations The test results indicate that the current GFN design will significantly reduce fire risk in two-phasesto-ground earth faults. However, the test results confirmed that the GFN product is not yet optimised for minimum fire risk in these types of faults, though there appears to be clear potential to achieve this outcome. It is recommended that the GFN manufacturer be encouraged to enhance the GFN design to apply effective compensation to reduce fault current in all types of earth fault and to apply the same faultconfirmation test (proven to have low fire risk) to detect sustained faults and allow fast powerline disconnection to reduce fire risk. 12.2 Relevance to fire risk Back-fed and other two-phases-to-ground earth faults are relevant to fire risk: 12.2.1 Back-fed faults (wire down, ‘downstream’ end remains connected) Back-fed faults are ‘wire down’ earth faults where the break in the conductor leaves the fallen wire on the ground connected to the downstream side of the powerline, i.e. connected at the end furthest from the source substation. It is not energised directly from the substation but can convey customer load current (from customers downstream of the break) into the earth. This current can be sufficient to start a fire. Back-fed faults are notoriously difficult to detect with traditional powerline protection systems. They may remain undetected for some time which further increases the fire risk. Though back-fed faults are not as common as normal earth faults, they are not rare. Their occurrence is determined by the random location of conductor breakages under the stress of high wind conditions. The 2014 Theoretical Study investigated back-fed faults using the model shown in Figure 10. Figure 10: theoretical model of back-fed earth fault on a resonant earthed network Break © Marxsen Consulting Pty Ltd Документ1 Friday, 4 December 2015 P a g e | 94 The Study concluded: The response of a REFCL-protected network to a back-fed fault is the same as to a direct-fed earth fault with some adjustment to the parameters: the effective fault resistance is the actual fault resistance plus half the phase-to-phase resistance that represents the customer load downstream of the conductor breakage. The neutral voltage displacement may be as little as half that which would occur if the fault was not back-fed. This means that detection of back-fed faults may only be half as sensitive as normal faults having the same fault resistance. Fault detection sensitivity will depend on the customer load downstream of the conductor breakage. To detect a one amp back-fed earth fault, the customer load downstream of the breakage would have to be at least 200kW and the REFCL fault detection threshold would have to be a neutral voltage displacement equal to not more than 10% of nominal voltage. Though not common, back-fed faults present a clear fire risk when they occur in high fire risk conditions, so the response of a REFCL to this type of fault is of relevance to fire risk reduction. A back-fed fault is simply a special case of a two-phases-to-ground earth fault where the fault current flows from the two unbroken phase conductors through the customer loads to the fallen wire and thence to earth. Analysis of back-fed faults often relies on an assumption that customer load located downstream of the fault location is balanced (equal load on each of the three phases). However whilst load balance is an objective of network planners, it is not always achieved in practice. With unbalanced load, a back-fed earth fault is equivalent to the more general case of a two-phases-to-ground earth fault – which may be balanced or unbalanced depending on circumstances. 12.2.2 Two-phases-to-ground earth faults (‘tree in powerline’ faults) One of the most common causes of a two-phases-to-ground earth fault is trees near powerlines. When a tree falls across or into a powerline, there are a number of possible outcomes, each of which can present a different form of earth fault to the high-voltage network: 1. Fallen tree branch resting on one powerline conductor: this is an instance of a ‘branch touching wire’ earth fault. The fire risk from such faults can be greatly reduced by a REFCL as outlined in Section 13 below. 2. Fallen tree resting on two or more powerline conductors: this can present as a combination of a ‘branch touching wire’ earth fault plus a ‘branch across wires’ fault or even a direct phase-to-phase fault if the two phase conductors are brought into contact with each other by the weight of a tree branch. 3. Fallen tree entangled in powerline conductors with multiple current paths to earth: a common example of this is when a fallen tree brings the conductors low (though still not touching ground) and tree branches come to rest on the ground on the far side of the powerline. It can present as a two-phases-to-ground earth fault or a three-phases-to-ground earth fault. Again, if any two conductors touch, a direct phase-to-phase fault will occur. 4. Fallen tree and powerline conductors on ground: This usually occurs if poles break or fall or conductors break under the weight of a tree. Again, it can present as a ‘wire down’ earth fault, a two-phases-to-ground earth fault or a three-phases-to-ground earth fault and if two conductors touch, a direct phase-to-phase fault. © Marxsen Consulting Pty Ltd Документ1 Friday, 4 December 2015 P a g e | 95 A REFCL can manage many of the fire risks in this complex set of scenarios while some others may remain relatively unaffected by its presence. For example, direct phase-to-phase faults (conductor clash or flashover) will normally be addressed by fast overcurrent protection systems6 - the REFCL cannot respond to them. Phase-to-phase vegetation faults (‘branch across wires’) will also be undetected by a REFCL. However, unless the branch concerned is fully detached from the tree and suspended above ground, this type of fault may be accompanied by an earth fault that is detectable by a REFCL. Both two-phases-to-ground and three-phases-to-ground earth faults create earth current that is detectable by a REFCL, either as neutral current (by an SSFCL) or as neutral voltage displacement (by a GFN or ASC). Whilst the set of tree fault scenarios listed above is complex, it presents only a limited range of fault types that create earth current: they are single-phase-to-ground earth faults or two-phases-toground earth faults, combined with various permutations of phase-to-phase faults. For example, a three-phases-to-ground earth fault can be accurately modelled as a two-phases-to-ground earth fault plus a set of three phase-to-phase faults. Hence the way in which a REFCL responds to twophases-to-ground earth faults has an important bearing on fire risk from all fault types involving trees, as well as from back-fed faults whether balanced or unbalanced. If a REFCL detects a two-phases-to-ground earth fault and responds by quickly disconnecting the powerline7, fire risk from many complex tree faults as well as back-fed earth faults may be reduced. The Kilmore South test program included a series of tests of resistive two-phases-to-ground earth faults with the GFN in service, including balanced faults equivalent to back-fed earth faults with balanced downstream customer load. The other two REFCL configurations were not tested with these types of faults as they were not yet compliant with the draft REFCL performance standard. 12.3 GFN treatment of two-phases-to-ground earth faults The GFN (and other fault detection schemes in resonant earthed systems) detects the presence of a fault by the magnitude of the neutral voltage and deduces the type of fault from the phase angle of the neutral voltage: 1. If the neutral voltage closely aligns with one of the network phase voltages, this indicates the fault is a single-phase-to-ground earth fault on that phase. 2. If the neutral voltage does not align with any single network phase voltage, this indicates that the fault is a two-phases-to-ground earth fault involving the two phases that have voltages ‘to either side’ of the neutral voltage. To allow for measurement errors and various factors that can disturb the measured phase of the neutral voltage, ‘phase angle zones’ are defined. The GFN has six zones, each of approximately8 60 degrees width: three centred on the three phase voltages; and three centred on the mid-points between each pair of phase voltages. Depending on which zone the neutral voltage falls within, the two associated GFN responses are: 1. Phase zone: the GFN treats the fault as a standard single-phase-to-ground earth fault, i.e. it uses RCC compensation to reduce the voltage on that phase close to zero; uses the FCT to 6 Disconnection times, potential ignition outcomes and fire risks of such events are beyond the scope of this report. 7 The 2015 Vegetation Conduction Ignition test program found that interruption of supply within five to ten seconds might substantially reduce fire risk from ‘branch across wires’ faults. (Refer Vegetation Conduction Ignition project report Section 8.6, page 62). This speed of response is within REFCL capability. 8 With standard GFN settings, the phase zones are 66 degrees wide and the inter-phase zones 54 degrees wide. The relative widths of the two classes of zones can readily be modified by changing a setting. © Marxsen Consulting Pty Ltd Документ1 Friday, 4 December 2015 P a g e | 96 test for the fault after a few seconds; and then either disconnects the powerline9 if the fault is still present, or removes the compensation if the fault has disappeared. 2. Inter-phase zone: the GFN treats the fault as a back-fed fault; it applies no compensation and immediately disconnects the powerline (once it has been identified – this can take some seconds). The ‘inter-phase zone’ response has been developed to suit conditions in other countries that use the GFN product. The rationale of the immediate disconnection response is that such a fault will always involve a live wire on the ground with unacceptable public safety risk. 12.4 GFN test results: two-phases-to-ground earth faults The GFN was tested using bolted resistive fault tests with different combinations of available highvoltage resistors to simulate a two-phases-to-ground earth fault. The configuration is shown in Figure 11 and the resistance values in each test configuration are listed in Table 7. The test conditions included two relatively unrealistic features: 1. The fault impedances were relatively high compared to many real earth faults of this type. This was partly compensated by increased fault detection sensitivity in Test 728 and later tests; and 2. To protect the high-voltage resistors from thermal overload, fault current duration was limited to less than one second in tests with the 15,200 Ohm common resistor and less than 700 milliseconds in tests without it, i.e. fault duration was too short for the GFN to find a sustained fault using its FCT. Figure 11: two-phases-to-ground earth fault configuration Table 7: resistance values in KMS two-phases-to-ground earth fault tests Test 727 728 729 730 731 732 733 734 735 736 737 Phase 1 Blue Blue White White White Red Red Red Blue Blue White R1 (Ω) 8,350 8,350 8,350 16,700 16,700 16,700 16,700 16,700 16,700 16,700 16,700 Phase 2 White White Blue Blue Blue Blue Blue White White White Blue R2 (Ω) 16,700 16,700 16,700 16,700 16,700 16,700 16,700 16,700 16,700 8,350 8,350 R_common (Ω) 15,200 15,200 15,200 15,200 0 0 0 0 0 0 0 9 This is subject to the operating policy of the network owner that applies at the time of fault occurrence. Disconnection is the appropriate policy at times of extreme fire risk. © Marxsen Consulting Pty Ltd Документ1 Friday, 4 December 2015 P a g e | 97 Eleven tests were performed and the GFN response recorded. These are listed in Table 8. Table 8: GFN responses to two-phases-to-ground earth faults Test 727 728 729 730 731 732 733 734 735 736 737 GFN response Fault not detected (threshold 0.5A) White phase compensated, no FCT (threshold set to 0.2A) Blue phase compensated, feeder not identified, FCT White phase compensated, feeder not identified, FCT White phase compensated, feeder identified, FCT Blue phase compensated, feeder not identified, FCT Detected, no compensation, feeder not identified, no FCT Late compensation of White phase, no FCT Late compensation of Blue phase, FCT Reverse earth fault detected, no compensation Blue phase compensated, FCT Max fault current 0.34A 0.35A 0.37A 0.27A 0.75A 0.76A 0.76A 0.69A 0.74A >0.92A 1.33A The conclusions drawn from the test results were: 1. The GFN detected the two-phases-to-ground earth faults in all tests where the earth current exceeded the fault detection sensitivity setting. 2. In those tests where the GFN applied voltage compensation using the RCC, it was always applied to reduce the voltage on one of the two phases involved in the fault. 3. ASC tuning mismatch and network capacitive imbalance can cause the phase of the neutral displacement produced in low-current two-phases-to-ground earth faults to vary somewhat from that expected from theory and this can influence determination of fault type. 4. The GFN response was not always consistent, with different responses recorded in tests having identical conditions. The observed response was not always as expected based on existing knowledge of the GFN design. 5. The GFN response to two-phases-to-ground earth faults is complex and somewhat uncertain due to multiple internal processes running in parallel within the GFN firmware. 6. The demonstrated GFN performance in two-phases-to-ground earth faults is not optimised for lowest fire risk, though the GFN appears to have the capability to deliver this. The result of each test was discussed and analysed in some detail with the GFN manufacturer on site. It was recognised that the GFN design had not yet been optimised for low fire risk in this class of earth faults. These discussions tended to confirm the potential for this to be done. 12.5 Fire risk reduction with the current GFN design Although the test results demonstrated the GFN is not yet optimised to reduce fire risk in this class of faults, it is clear that its current design would nevertheless achieve some reduction in fire risk. 12.5.1 Back-fed faults There are reasonable grounds to believe that a REFCL-protected network will not have fires resulting from back-fed faults: For a conductor breakage to create a back-fed earth fault without creating a simultaneous direct-fed earth fault, the break must be at the end of the span closer to the source substation, so in the worst case the length of conductor on the ground would be not less than 16 metres by the logic of Section Ошибка! Источник ссылки не найден. on page Ошибка! Закладка не определена.. The current into the earth required to start a fire would be 2.4 amps based on the ignition threshold of 0.15 amps per metre. © Marxsen Consulting Pty Ltd Документ1 Friday, 4 December 2015 P a g e | 98 A REFCL set to detect a 0.5 amp direct-fed earth fault would detect a back-fed earth fault involving one amp of current into the earth provided the downstream customer load was high enough – more than about 200 kilowatts. At times of high fire risk, ‘downstream’ customer load is likely to be higher (due to air conditioning, refrigeration and water pumping) rather than lower. Most faults on a 22kV powerline would have more than 200 kilowatts of downstream load at these times. Simulations of a back-fed fault on the larger Frankston South network demonstrate that there is no combination of downstream load and fault resistance that results in an undetectable back-fed fault capable of causing a fire with 16 metres of conductor on the ground10. Lower levels of downstream load make the fault hard to detect, but they also reduce the fault current below the 2.4 amp ignition threshold. The simulations also indicate that downstream load balance does not materially alter this conclusion: severely imbalanced load makes the fault detection faster while producing a higher current to earth for only the first few tens of milliseconds – insufficient time for a ground ignition. The GFN with its FCT could enable disconnection of a powerline on which a back-fed fault has occurred before a fire could start. Disconnection as soon as the fault is confirmed by the FCT to be still present is likely to be required for public safety as well as fire risk reduction. 12.5.2 Tree faults There are reasonable grounds to believe that a REFCL protected network will have 50% to 90% less fire risk from tree faults compared to a non-REFCL network: All tree faults involve some earth fault current that is potentially detectable by a REFCL11. Trees that fall on powerlines usually have a trunk diameter greater than 100mm at the point of contact with the powerline. The 2015 Vegetation Conduction Ignition test program demonstrated that larger (80-90mm) diameter branches generate an initial earth fault current of more than one amp and that this initial current will increase as the square of the diameter. This implies that tree faults that involve more than one phase of the powerline will normally produce earth fault current in excess of one amp, i.e. in excess of the REFCL fault detection sensitivity, so they will be detected. Vegetation faults take seconds or tens of seconds to produce a ground-level fire. The 2015 Vegetation Conduction Ignition test program indicated that interruption of supply to the fault within ten seconds would reduce fire risk by the order of 50%. Interruption within five seconds would cut fire risk by perhaps 90%. The GFN’s FCT normally detects a sustained one amp fault in the first few steps, i.e. about five or six seconds after initial fault detection. The GFN with its FCT could enable disconnection within five to ten seconds of a powerline on which a tree fault has occurred, making a 50% to 90%12 reduction of fire risk possible. 10 There are combinations that create other public safety risks, e.g. electrocution if someone approaches or touches the fallen wire. 11 The only vegetation fault type that cannot be detected by a REFCL is a pure ‘branch across wires’ fault, i.e. where the branch is completely detached from the tree and suspended wholly above the ground. 12 The FCT starts about four seconds after the fault is detected and is complete about six seconds later. © Marxsen Consulting Pty Ltd Документ1 Friday, 4 December 2015 P a g e | 99 12.6 Approaches for lower fire risk in two-phases-to-ground earth faults Although the current GFN design is likely to provide fire risk reduction in two-phases-to-ground earth faults, the tests revealed that under extreme conditions (high fault impedances) it is not optimised for consistent delivery of maximum fire risk benefits. Further product development could achieve this. Provided the magnitude and phase angle of RCC compensation is carefully chosen, fault current to earth in any type of earth fault can be cancelled, whether it is a single-phase-to-ground fault or a two-phases-to-ground fault, balanced or unbalanced. In two-phases-to-ground earth faults the optimum response may be: 1. Use the RCC to apply the compensation required to bring the earth fault current to a very low value. The measurements required to correctly calculate the magnitude and angle of the required compensation are already gathered by the GFN but the calculation of the compensation appears constrained somewhat by the currently imposed dichotomy in the GFN’s internal logic processes between normal earth faults and reverse (back-fed) earth faults. 2. Once the correct compensation has been applied to reduce the earth fault current to a level close to zero, use the FCT to test for a sustained fault and identify the faulted powerline. The Kilmore South tests have confirmed the FCT can be performed with minimal additional fire risk. 3. If the fault is confirmed to be a sustained fault, apply the network owner’s policy for such faults (in high fire risk conditions, immediately disconnect the powerline). It is recommended that the GFN response to two-phases-to-ground earth faults be re-engineered to provide this response without reliance on any assumptions about whether such faults are balanced or not. This will reduce fire risk in both back-fed faults (usually but not always reasonably balanced) and tree faults (often grossly unbalanced). It will also enhance public safety in ‘wire down’ faults. © Marxsen Consulting Pty Ltd Документ1 Friday, 4 December 2015 P a g e | 100 13 REFCL management of vegetation earth faults This section describes ‘branch touching wire’ vegetation earth fault tests staged at Kilmore South with a REFCL in service. The tests at Kilmore South validated the simulation of REFCL action used in the Vegetation Conduction Ignition test program completed earlier in 2015 at Springvale13 and hence confirmed the Springvale test results can be applied to REFCL-protected networks. This rigorous confirmation allows the conclusion to be reliably drawn that REFCLs can cut fire risk from ‘branch touching wire’ earth faults by a factor of twelve, from 100% to 8%, when averaged across all of the eleven species tested at Springvale. The Kilmore tests also demonstrated that this benefit will be delivered even when a ‘soft’ fault-confirmation test is used to confirm the fault is sustained and identify the 22kV powerline upon which it is located. 13.1 Summary of findings A total of 61 valid vegetation ignition tests carried out at Kilmore South showed that: 1. The Kilmore South test results, when combined with those from the Springvale tests, show REFCL network protection can cut fire risk from ‘branch touching wire’ earth faults averaged over a wide range of species, from 100% to 8%. 1. A GFN can detect current in a ‘branch touching wire’ earth fault at a level of 0.5 amps and upon detection, reduce current through the vegetation to a level close to zero. 2. Vegetation earth fault fire probability is not materially affected by diagnostic tests that comply with the REFCL performance standard. 13.2 The Kilmore vegetation earth fault t ests The 2015 REFCL Technologies test program tests at Kilmore included 61 valid ignition tests on sample branches of Willow (Salix Sp.). The 61 valid tests included 19 that produced fires. The fire probability from statistical analysis of the Kilmore tests is shown in comparison with 0.5 amp artificially current-limited tests of Willow at Springvale in Figure 12. Figure 12: comparison of Kilmore and Springvale tests of Willow branches 100 Fire probability (%) 80 60 40 20 0 Kilmore Springvale 13 Over 1,000 tests carried out at Springvale earlier in 2015 on a wide range of vegetation species showed that: if it could be confirmed that a REFCL can detect current in ‘branch touching wire’ earth faults at a level of 0.5 amps and upon detection interrupt that current, then the probability of fire from such faults would be reduced by a factor of around ten to 8% (less than 13% with 95% confidence); and secondly, for tests limited to 0.5 amps current, Willow was the worst case species with a fire probability of 36%. The 31% fire probability of Willow in ‘branch touching wire’ earth fault tests done at Kilmore with a GFN in service is, within the limits of statistical certainty, the same as the 36% Springvale result with an NER in service and test current artificially limited to 0.5 amps. © Marxsen Consulting Pty Ltd Документ1 Friday, 4 December 2015 P a g e | 101 The Kilmore ‘branch touching wire’ tests drew extensively on concepts and designs developed in the 2015 Vegetation Conduction Ignition test program, including: Defined worst case conditions for ignition (45°C air, turbulent 10-15 kph airflow, samples conditioned for approximately 8-24 hours at 45°C and kept in 2°C storage at all other times) Test rig (two parallel 19/3.25AAC conductors 1.5m apart: an earthed one supporting the thicker end of the sample and the other energised at 12.7kV supporting the thin end) Fire start criteria (prior to any flashover, small embers must reach the floor of the rig at 350°C or higher, or larger ones at 250°C or higher) Sample diameter (thick end) around 25-30mm and sample length about 2.5 metres. The Kilmore experiments varied from those at Springvale in some minor respects: There was 400 Ohm series resistance in the high voltage supply, instead of 200 Ohms. Given this was only a 1.5% variation in total current path resistance, it was considered to have negligible influence on the results Only Willow (Salix Sp.) tests were analysed as it was not possible to obtain enough suitable samples of the other identified worst-case species, Desert Ash (Fraxinus Angustifolia) The vegetation samples were harvested in October, i.e. mid-spring, rather than February and March (late in a relatively cool summer). The small size of the KMS network meant the GFN was extremely sensitive. To mimic the 0.5 amp fault detection sensitivity typical of larger networks, it was desensitised - the fault detection threshold was increased from 23 volts (2,650 volts neutral displacement) to 40 volts (4,620 volts neutral displacement). The current immediately prior to detection of vegetation faults by the GFN was recorded and is shown in Figure 13. The average fault detection sensitivity demonstrated in the 59 valid tests in which fault detection took place was 0.40 amps. Figure 13: fault current immediately prior to fault detection by the GFN 14 12 Count (n = 59) 10 8 6 4 2 0 0.1 0.2 0.3 0.4 0.5 0.6 Current at which fault was detected (Arms) The moisture content and diameter (thicker end) of samples were also recorded. The values are shown in Figure 14. © Marxsen Consulting Pty Ltd Документ1 Friday, 4 December 2015 P a g e | 102 Figure 14: Salix Sp. vegetation sample moisture content and diameter 70 35 Sample moisture 30 50 Count (n = 84) Count (n = 84) 60 40 30 20 Sample diameter 25 20 15 10 5 10 0 0 20 25 30 35 40 10 45 15 20 25 30 35 40 45 Diameter (mm) Moisture (%) The sample moisture levels and diameters were close to the recorded average values for Salix samples in the Springvale tests (39% moisture and 26mm diameter). It was concluded that the Kilmore tests were an adequate replication of the Springvale tests to allow direct application of fire probability results from the Springvale tests to REFCL protected networks. 13.3 The ‘flarc’ – a qualitative difference with REFCL protection ? The Springvale tests revealed all vegetation faults progress through four stages. The Kilmore tests showed the first three stages were unchanged by the presence of the GFN. However, the fourth was qualitatively different for reasons not yet understood. At Springvale, the fourth stage was a flashover – flame being an excellent conductor, once a continuous line of flame was established from one wire to the other, an arc instantly formed and the current immediately increased to the 64 amp limit set by the series resistor in the rig’s high-voltage supply. The test ended in a flash of light. In the Kilmore tests, nearly every time a continuous line of flame formed between the two wires supporting the branch, the test sample settled into a relatively steady state condition that became known among the test team as a ‘flarc’- a combined flame and arc but not a flashover. In a flarc, the current was rich in harmonics and remained relatively steady for many seconds at a level generally below 0.5 amps. Some data recorded during a typical flarc event is shown in Figure 15. Figure 15: KMS Test 749 Salix sample - extended flarc from 122 seconds14 14 The same chart processing tools were used in both ‘wire down’ and vegetation ignition tests. The vertical axis labelled ‘Soil Current’ here shows the vegetation current in the latter tests. © Marxsen Consulting Pty Ltd Документ1 Friday, 4 December 2015 P a g e | 103 © Marxsen Consulting Pty Ltd Документ1 Friday, 4 December 2015 P a g e | 104 It can be seen from Figure 15 that during the 12 second period of the flarc, the voltage across the burning branch was around 9,000 volts (the voltage waveform was an almost pure 50Hz sinusoid) but the current remained between 0.4 and 0.5 amps with a very non-sinusoidal waveform suggestive of a bi-directional voltage limiting mechanism (thresholds at plus/minus some kilovolts) in series with a high source impedance (of the order of ten kilo-ohms). In only a few tests did a flarc result in a form of flashover, e.g. Test 772, but the flashover current was well below the level allowed by the 400 Ohm current-limiting resistor in the high-voltage supply to the test rig15. Identification of the physical mechanism behind the flarc phenomenon was beyond the scope of this project. The relevance of flarcs for fire risk was also not clear. Flashovers are unrealistic features of ‘branch touching wire’ faults. If they are realistic for other types of earth faults (e.g. wire into low vegetation), the production of flarcs in a REFCL-protected network may have some bearing on fire risk. Ignition tests on such fault types were beyond the scope of this project. The flarc phenomenon is recorded here for possible future reference as a strikingly different and unexplained outcome of the KMS vegetation ignition tests. 15 The current limit was 32 amps, but the few flashovers that did occur appeared to only reach 5-10 amps. © Marxsen Consulting Pty Ltd Документ1 Friday, 4 December 2015 P a g e | 105 14 REFCL technologies test program design The 2015 REFCL Technologies test program used a custom-built test facility located at Kilmore South about 50 kilometres north of Melbourne. Site commissioning, proof-of-concept tests and the first three tranches of the main test program comprised 538 tests done over 26 test days in May and June. A further 297 tests were done in Tranche 4 over 20 test days in September and October. The design elements of the test facility and test program are described in the following sections. 14.1 Use of 2014 REFCL Trial design A detailed description of the experiment design and test site concept is set out in the 2014 REFCL Trial report. The key elements carried over into the KMS tests included: 1. 2. 3. 4. 5. 6. 7. 8. The underlying principles of realism, direct comparison, and worst case conditions Selection of conductor type, conductor impact speed and bounce height Selection of soil, fuel and soil-fuel bed geometry Selection of worst case fire weather conditions and fuel moisture content Overall site concept including safety architecture Test procedures and site operating procedures The ‘wire down’ test rig The data acquisition system and transducers Changes made to the Frankston design were primarily matters of detail. They included: 1. Use of insulated shipping containers for the test rig and soil-bed conditioning spaces – this reduced heater load and allowed removal of the air diffuser around the ignition test space. 2. Use of isolated LV supply to the Control Hut instead of a separate generator 3. Use of normal LV supply to the test rig and HV yard equipment instead of a generator 4. Overhead HV supply to the test rig instead of short lengths of underground cable 5. Omission of the ‘sandpit’ parallel current path in the test rig container 6. Use of a GoPro camera in the test ignition space as the recorder of fire results 7. Use of a wideband 200.0mΩ coaxial shunt to measure soil current. The test site is shown in Figure 16, Figure 17 and Figure 18. Figure 16: Kilmore South test site prior to construction © Marxsen Consulting Pty Ltd Документ1 Friday, 4 December 2015 P a g e | 106 Figure 17: the Kilmore South test facility under construction The test facility was commissioned on 11th May 2015. Figure 18 shows its condition during test days. Figure 18: the Kilmore South test facility as commissioned 14.2 Use of 2015 Vegetation Conduction Ignition test program design A detailed description of the experiment design and test site concept is set out in the 2015 Vegetation Conduction Ignition Test Program report. The key elements carried over into the KMS tests included: 1. Test procedures and site operating procedures for vegetation earth fault simulation 2. The vegetation conduction ignition test rig Significant changes made to the Springvale design included: 1. 2. 3. 4. Use of 400 Ohm resistor in the test rig high-voltage supply instead of 200 Ohms Omission of the automated system to terminate a test when a set current limit was reached Omission of custom-designed transducers to capture high frequency fault signatures Modified test procedure to include real-time monitoring of infrared camera vision and to manually terminate a test if fire start criteria were met. 14.3 The test network – feeder KMS21 High voltage supply to the test site was from feeder KMS21 which comprised the total test network. Prior to commencement of the test program the following works were carried out on the test network: 1. Network hardening: all surge diverters were disconnected. As part of GFN commissioning, each phase of the network was ‘soaked’ for 20-40 minutes at 22kV using the RCC to control © Marxsen Consulting Pty Ltd Документ1 Friday, 4 December 2015 P a g e | 107 neutral displacement voltage. This approach appeared to be successful as there were no cross-country faults experienced during the test program. 2. Network balancing: the residual current (with NER in service) was reduced from 0.5 amps to 0.19 amps by re-phasing two-wire spur take-off points. For Tranche 4, further changes reduced this to 0.12 amps. 14.3.1 Network capacitive balance With the NER in service, the residual voltage16 at the test facility was typically less than fifteen volts as shown in Figure 19. Figure 19: Residual voltage and phase voltages at the test facility with NER in service (Tests 58 and 362) 100.000 100.000 Test 362: 17 June 4:20pm Residual Voltage (V) Residual Voltage (V) Test 58: 19 May 12:53pm 10.000 7.619 2.469 1.000 0.831 1.102 0.959 0.851 0.653 0.961 0.930 0.776 0.633 0.477 0.407 0.330 2.340 1.540 1.000 0.735 0.524 0.522 0.383 0.381 13.043 10.000 0.245 0.187 0.165 0.123 0.100 0 200 0.977 0.952 0.865 0.837 0.749 0.717 0.750 0.674 0.585 0.465 0.345 0.257 0.245 0.243 0.680 0.479 0.100 400 600 800 1000 0 1200 200 400 600 800 1000 1200 Frequency (Hz) Frequency (Hz) The neutral voltage measured at the zone substation was 1.6 volts, consistent with the measured neutral current of 0.19 amps and the nominal 8Ω value of the NER, so the 7-13 volt residual voltage recorded at the test facility was mainly due to unbalanced powerline voltage drop caused by customer load current flowing in the series impedance of the phase conductors between the zone substation and the test facility. This could have caused unbalanced capacitive currents from each phase conductor to ground. Measurement error may have made a small (perhaps one volt) contribution to the recorded residual. With the GFN in service, the recorded phase to earth voltages and calculated residual voltage at the test facility (Test 45 pre-fault, Monday 18th May 2015, 3:46pm) are shown in Table 9. Table 9: test network phase and residual voltages early in the test program Test and date Red White Blue Residual Test 45 18/5/2015 15,327 Vrms 11,918 Vrms 12,162 Vrms 2,309 Vrms The large residual voltage was caused by network capacitive imbalance. It equalled the product of the imbalance current and the network damping resistance. The value shown in Table 9 indicates the damping resistance of the test network was about 12 kilo-Ohms since the capacitive imbalance current was 0.190 amps. This quantity can only be measured once some form of high-impedance 16 The residual voltage at the test facility is the instantaneous average of the three phase-to-earth voltages. It is a notional neutral displacement (there is no 22kV network neutral available except at the zone substation). © Marxsen Consulting Pty Ltd Документ1 Friday, 4 December 2015 P a g e | 108 earthing, such as the GFN, has been established. The residual was closely aligned with Blue phase volts17 as shown in Figure 20. Later in the test program, the GFN’s U0 Injector was used to reduce standing neutral displacement. This device comprises a capacitor connected to the 240 volts supply to the RCC cubicle and the lowvoltage winding of the GFN’s ASC. The capacitor can be any combination of two 84µF capacitors, i.e. one half (with the two in series), one capacitor, or twice that value (the two capacitors in parallel). With one capacitor, the U0 Injector adds 6.3 amps of current into the low-voltage ASC winding which is equivalent to 0.22 amps on the high-voltage network. The phase of the injection is set by the phase of the 240 volts supply, i.e. there are three options separated by 120 degrees. A second U0 injector provided more options for the Tranche 4 tests. Figure 20: Test facility voltages 18th May 2015 (Test 45 pre-fault) 25000 6000 20000 4000 10000 2000 Residaul Voltage (V) Phase-to-earth voltages (V) 15000 5000 0 0 -5000 -2000 -10000 -15000 -4000 -20000 -25000 -6000 0 0.004 0.008 0.012 0.016 0.02 Time (seconds) Red V White V Blue V Residual The U0 Injector can only be used to improve fault detection sensitivity. It may not improve faultlocation or fault-confirmation sensitivity as the measured powerline currents still remain unbalanced. After the U0 Injector was connected and adjusted, the residual voltage at the test facility was reduced as shown in Table 10. Further reductions were achieved for Tranche 4 by additional network balancing and adjustment of dual U0 injectors. Table 10: test network phase and residual voltages after application of U0 injector Test and date Red White Blue Residual Test 101 27/5/2015 13,397 Vrms 12,593 Vrms 13,626 Vrms 893 Vrms Test 518 24/6/2015 12,711 Vrms 13,269 Vrms 13,826 Vrms 843 Vrms Test 658 5/10/2015 12,051 Vrms 11,900 Vrms 12,720 Vrms 494 Vrms 17 On the HMI screen of the GFN, neutral displacement is indicated by a dot indicating the voltage of the earth with respect to the centre of the three-phase set of voltages, i.e. it is the opposite of the calculated residual voltage which is the voltage of the centre of the three-phase voltage set with respect to earth. © Marxsen Consulting Pty Ltd Документ1 Friday, 4 December 2015 P a g e | 109 Different U0 injector settings were used in the course of the test program, producing different phase on the residual voltage as shown in Figure 21. Figure 21: phase and residual voltages in Tests 101 and 518 25000 6000 25000 6000 Test 101 Test 518 20000 20000 4000 4000 15000 0 0 -5000 -2000 -10000 -15000 Residaul Voltage (V) 2000 5000 10000 2000 5000 0 0 -5000 Residaul Voltage (V) 10000 Phase-to-earth voltages (V) Phase-to-earth voltages (V) 15000 -2000 -10000 -15000 -4000 -20000 -4000 -20000 -25000 -6000 0 0.004 0.008 0.012 0.016 -25000 0.02 -6000 0 0.004 0.008 Time (seconds) Red V White V Blue V 0.012 0.016 0.02 Time (seconds) Residual Red V White V Blue V Residual The use of the U0 Injector was sufficient to allow fault detection sensitivity of better than 0.5 amps, though the residual imbalance meant detection sensitivity was different on the different phases of the network. It also limited the sensitivity threshold that could be applied in tests of the faultconfirmation/powerline-identification test of the GFN. 14.3.2 Network voltage harmonics Harmonic levels on the KMS21 network were low compared to levels on other rural networks in Victoria. The values shown are compared with spot check readings on other Victorian substations in Table 11. The KMS measurements were taken late afternoon on Mondays in May and October, whereas the measurements at the four other substations were taken at 5:30 pm on a Tuesday in late June. Table 11: spot check comparison of network voltage harmonics Harmonic KMS Test16 KMS Test658 BAN BAS WND WBE KMS as % of others 3rd 5th 7th 9.3 28.1 11.9 4.0 14.9 17.5 16.7 45.5 68.1 19.8 157.1 93.1 16.7 82.5 93.3 19.6 188.8 66.5 36% 18% 19% The harmonics in test facility phase voltages and residual voltage are shown in Figure 22. © Marxsen Consulting Pty Ltd Документ1 Friday, 4 December 2015 0 100 200 300 400 500 600 700 800 900 1000 1100 1200 1300 1400 1500 1600 1700 1800 1900 2000 2100 2200 2300 2400 2500 2600 2700 2800 2900 3000 3100 3200 3300 3400 3500 3600 3700 3800 3900 4000 4100 4200 4300 4400 4500 Volts (rms) 0 100 200 300 400 500 600 700 800 900 1000 1100 1200 1300 1400 1500 1600 1700 1800 1900 2000 2100 2200 2300 2400 2500 2600 2700 2800 2900 3000 3100 3200 3300 3400 3500 3600 3700 3800 3900 4000 4100 4200 4300 4400 4500 Volts (rms) P a g e | 110 Figure 22: KMS Test 16 pre-fault voltage harmonics 11th May 2015 6:01 pm 100000.00 10000.00 Phase voltages at test facility 1000.00 100.00 10.00 1.00 0.10 0.01 Frequency (Hz) Red © Marxsen Consulting Pty Ltd White Документ1 Blue 1000.00 Residual volts at test facility 100.00 10.00 1.00 0.10 0.01 Frequency (Hz) Friday, 4 December 2015 P a g e | 111 14.3.3 Network load The KMS21 feeder load current profile is shown in Figure 23. The 2014 Theoretical modelling study identified average peak powerline load in Victorian rural networks as 160-240 amps. The KMS21 peak load was only 5-10% of this. Figure 23: KMS21 feeder phase currents prior to start of test program 8.0 KMS21 phase currents 22 April to 1 May 2015 160 7.0 140 6.0 100 4.0 Count (N = 460) Current (amps) 120 5.0 3.0 80 60 2.0 40 1.0 20 0.0 1 49 97 145 193 241 289 337 0 385 0 1 2 3 4 Time (30 minute intervals) Red White 5 6 7 8 9 10 Phase current (A) Blue Red White Blue Figure 24: KMS21 load current in last week of Tranche 3 tests 16 KMS21 phase currents 0600 22nd - 1830 25th June 2015 14 140 12 100 8 Count (n = 652) KMS21 phase current (A) 120 10 6 80 60 4 40 2 20 1 11 21 31 41 51 61 71 81 91 101 111 121 131 141 151 161 171 181 191 201 211 221 231 241 251 261 271 281 291 301 311 321 331 341 351 361 371 381 391 401 411 421 431 441 451 461 471 481 491 501 511 521 531 0 Red White © Marxsen Consulting Pty Ltd 0 0.0 Time (intervals of 10 Minutes) 1.0 2.0 3.0 4.0 5.0 6.0 7.0 8.0 9.0 10.0 11.0 12.0 13.0 14.0 15.0 16.0 Phase current (Arms) Blue Red Документ1 White Blue Friday, 4 December 2015 P a g e | 112 15 Appendices Appendix A: Test records 113 Appendix B: HRL Technology REFCL Trial report 130 © Marxsen Consulting Pty Ltd Документ1 Friday, 4 December 2015 P a g e | 113 15.1 Appendix A: Test records The following tables summarise the tests and results, except for lo-sag covered conductor tests. An audited spreadsheet of all tests (Test log BAS edit 26-10-15.xlsx) is the master record for this data. 15.1.1 Valid ignition tests All ignition tests were audited against a number of criteria to verify the result could reliably be regarded as valid. Table 12: Valid ‘wire down’ ignition tests – GFN (GFN3 firmware, 100 Ohm, White phase) Test No. Date 298 16/06/2015 304 16/06/2015 305 16/06/2015 306 16/06/2015 307 16/06/2015 308 16/06/2015 309 16/06/2015 310 16/06/2015 311 16/06/2015 312 16/06/2015 313 16/06/2015 314 16/06/2015 315 16/06/2015 316 16/06/2015 318 16/06/2015 319 16/06/2015 320 17/06/2015 321 17/06/2015 322 17/06/2015 323 17/06/2015 324 17/06/2015 325 17/06/2015 326 17/06/2015 327 17/06/2015 328 17/06/2015 329 17/06/2015 330 17/06/2015 331 17/06/2015 332 17/06/2015 333 17/06/2015 334 17/06/2015 335 17/06/2015 336 17/06/2015 337 17/06/2015 338 17/06/2015 340 17/06/2015 341 17/06/2015 342 17/06/2015 343 17/06/2015 344 17/06/2015 345 17/06/2015 Time 8:50:16 13:22:10 13:36:45 13:50:42 15:26:07 15:47:30 16:02:00 16:08:56 16:16:00 16:23:12 16:29:53 16:39:00 16:47:00 16:59:24 17:12:52 17:19:13 8:56:15 9:08:53 9:18:55 9:26:38 9:43:33 9:50:36 10:04:21 10:09:43 10:24:35 10:32:53 10:40:07 10:46:02 10:53:26 11:01:00 11:08:37 11:16:37 11:22:31 11:28:27 11:35:50 12:56:08 13:04:47 13:14:49 13:23:55 13:32:13 13:38:40 © Marxsen Consulting Pty Ltd Peak Bounce Current 2.0 2.4 2.5 6.8 0.1 4.5 6.3 7.2 5.5 7.7 6.4 5.8 6.3 7.2 5.7 6.2 8.1 7.6 6.9 4.3 3.9 4.5 5.6 4.1 4.7 4.1 6.0 5.5 6.2 6.3 5.4 5.7 7.5 12.1 6.8 5.2 5.9 4.9 5.4 10.1 6.6 Bounce Current Peak FCT Peak FCT Residual Duration current voltage Volts I2t (A2s) Fire 38 0.16 3282 300 0.008 N 49 0.32 2792 95 0.05 N 54 0.87 3485 95 0.28 Y 49 1.86 5541 95 2.06 Y 18 0.5 11000 100 0.33 Y 68 1.07 4690 90 0.57 N 37 0.21 1617 95 0.02 N 66 0.37 2135 110 0.06 N 64 0.49 2767 90 0.19 N 62 0.44 2092 90 0.09 N 65 0.62 3609 90 0.13 Y 63 0.45 2542 790 0.13 N 65 0.28 1726 890 0.18 N 63 0.45 1905 1030 0.22 N 66 0.18 1505 1000 0.1 N 58 0.27 1803 950 0.05 N 57 0.24 1447 930 0.16 N 44 0.21 1447 1090 0.52 N 61 0.38 2205 1100 0.47 N 59 0.57 2835 1030 0.27 N 57 0.16 1652 1020 0.07 N 58 0.39 2770 990 0.13 N 56 0.25 1867 1030 0.14 N 40 0.22 2862 1020 0.02 N 55 0.62 2926 1060 0.38 N 58 0.21 1774 1050 0.19 N 64 0.21 1722 1030 0.09 N 47 0.28 1761 1060 0.05 N 65 0.16 1459 1090 0.08 N 61 0.29 1826 1090 0.06 N 72 0.29 2577 2250 1.03 N 73 0.34 2584 2220 2.29 Y 40 0.61 2374 2200 10.92 Y 35 1.37 2175 2000 49.29 Y 38 0.71 2335 2200 9.13 Y 45 0.33 2659 2320 2.19 N 66 0.39 2900 2300 1.79 Y 74 0.37 2942 2250 4.03 Y 57 0.31 2538 2280 1.93 N 57 0.96 2167 2050 31.86 Y 64 0.37 2315 2100 3.65 N Документ1 Friday, 4 December 2015 P a g e | 114 Test No. Date 346 17/06/2015 347 17/06/2015 348 17/06/2015 349 17/06/2015 350 17/06/2015 351 17/06/2015 352 17/06/2015 353 17/06/2015 354 17/06/2015 355 17/06/2015 356 17/06/2015 357 17/06/2015 358 17/06/2015 359 17/06/2015 360 17/06/2015 361 17/06/2015 363 18/06/2015 364 18/06/2015 365 18/06/2015 366 18/06/2015 367 18/06/2015 368 18/06/2015 369 18/06/2015 370 18/06/2015 371 18/06/2015 372 18/06/2015 390 19/06/2015 429 22/06/2015 430 22/06/2015 431 22/06/2015 432 22/06/2015 433 22/06/2015 434 22/06/2015 435 22/06/2015 436 22/06/2015 437 22/06/2015 438 22/06/2015 439 23/06/2015 440 23/06/2015 441 23/06/2015 442 23/06/2015 444 23/06/2015 445 23/06/2015 446 23/06/2015 447 23/06/2015 448 23/06/2015 450 23/06/2015 Time 13:48:05 14:06:02 14:14:12 14:21:12 14:27:15 14:35:59 14:41:19 14:48:50 14:54:54 15:09:19 15:15:33 15:21:53 15:30:30 15:37:52 15:44:20 15:52:07 10:21:00 10:29:21 10:36:28 10:43:00 10:50:06 11:01:30 11:09:50 11:16:50 11:23:16 11:31:13 10:52:44 16:18:16 16:25:02 16:30:56 16:39:30 16:47:44 16:55:33 17:01:59 17:07:25 17:15:24 17:22:11 8:55:20 9:02:34 9:21:12 9:29:31 9:49:15 9:58:21 10:09:58 10:27:41 10:46:55 11:14:16 © Marxsen Consulting Pty Ltd Peak Bounce Current 10.7 8.3 6.3 6.6 7.3 8.4 7.9 8.4 9.4 8.3 7.8 9.4 9.6 10.3 9.2 8.2 9.9 9.5 10.4 9.2 10.1 9.1 9.5 9.7 10.8 10.3 8.0 10.8 11.4 9.9 9.6 11.2 10.9 10.5 10.4 8.2 11.1 9.7 9.6 9.3 9.3 9.2 10.0 10.7 9.8 8.2 13.2 Bounce Current Peak FCT Peak FCT Residual Duration current voltage Volts I2t (A2s) Fire 62 1.19 2064 1860 43.1 Y 38 0.75 2408 2060 10.42 Y 55 0.39 2233 2150 6.25 Y 59 0.27 1701 1680 1.61 N 64 0.42 1734 1620 3.38 N 56 0.51 1722 1620 3.66 Y 66 0.53 1727 1550 3.75 N 63 0.5 1719 1600 4.74 N 64 0.37 1736 1600 2.51 N 70 0.29 1922 1600 0.79 N 55 0.56 1637 1620 7.61 Y 53 0.49 1743 1610 3.19 Y 38 0.59 1705 1600 7.05 Y 59 0.49 2012 1640 1.37 N 58 0.56 1600 1640 6.85 N 61 0.37 1953 1600 1.17 N 64 0.56 2120 95 0.15 N 48 0.42 2016 180 0.08 N 48 0.71 2549 200 0.22 N 43 0.51 1994 220 0.1 N 49 0.64 1965 220 0.25 N 53 0.63 1949 230 0.27 N 52 0.57 1989 190 0.18 N 47 0.37 1975 210 0.18 N 58 0.62 2010 190 0.14 N 55 0.61 1972 210 0.39 N 48 0.41 1631 165 0.07 N 56 1.44 2913 1300 1.23 Y 49 0.43 1466 1300 1.98 Y 52 0.4 1720 1300 1.39 N 52 1.31 2946 1330 2.87 Y 53 0.45 2243 1300 0.64 N 60 0.53 2270 1300 0.75 N 47 0.44 1696 1350 1.2 N 48 0.3 2293 1320 0.03 N 57 0.43 1618 1270 1.2 N 54 0.37 1780 1350 0.67 N 53 0.6 2334 1400 0.85 Y 47 0.37 1705 1330 0.4 N 57 0.33 1420 1315 0.64 N 48 0.42 1411 1300 1.33 N 55 0.33 1537 1380 1 N 57 0.42 1696 630 0.08 N 54 0.33 1659 500 0.04 N 48 0.36 1992 290 0.07 N 55 0.23 2104 430 0.02 N 49 0.75 1977 360 0.25 Y Документ1 Friday, 4 December 2015 P a g e | 115 Test No. Date 451 23/06/2015 452 23/06/2015 453 23/06/2015 454 23/06/2015 455 23/06/2015 456 23/06/2015 457 23/06/2015 458 23/06/2015 459 23/06/2015 460 23/06/2015 466 23/06/2015 467 23/06/2015 468 23/06/2015 469 23/06/2015 470 23/06/2015 471 23/06/2015 472 23/06/2015 473 23/06/2015 474 23/06/2015 475 23/06/2015 476 23/06/2015 486 24/06/2015 487 24/06/2015 488 24/06/2015 493 24/06/2015 494 24/06/2015 495 24/06/2015 496 24/06/2015 497 24/06/2015 498 24/06/2015 499 24/06/2015 500 24/06/2015 501 24/06/2015 502 24/06/2015 503 24/06/2015 504 24/06/2015 505 24/06/2015 506 24/06/2015 507 24/06/2015 510 24/06/2015 511 24/06/2015 512 24/06/2015 513 24/06/2015 514 24/06/2015 515 24/06/2015 517 24/06/2015 518 24/06/2015 Time 11:23:22 11:32:46 11:38:14 11:43:58 11:50:10 11:55:46 12:06:05 12:13:10 12:20:22 12:26:11 15:54:55 16:00:25 16:06:18 16:12:55 16:31:02 16:37:46 16:45:10 16:50:58 16:59:11 17:05:03 17:11:33 13:05:00 13:12:39 13:35:08 14:07:11 14:16:15 14:24:17 14:33:10 14:40:16 14:47:32 14:54:57 15:03:03 15:10:22 15:17:22 15:25:30 15:30:54 15:38:02 15:44:30 15:51:33 16:10:40 16:17:34 16:23:30 16:29:34 16:36:45 16:43:35 17:01:42 17:09:29 © Marxsen Consulting Pty Ltd Peak Bounce Current 13.5 12.9 13.5 12.9 12.2 13.5 12.1 13.5 13.4 12.4 14.1 12.9 13.3 13.6 13.1 13.0 12.6 13.1 13.5 13.1 13.7 9.4 9.7 10.1 9.8 10.2 10.8 11.4 13.0 13.6 10.7 11.3 12.5 12.1 11.8 11.3 13.0 13.0 12.3 11.0 10.5 12.9 13.5 9.8 12.5 13.3 11.7 Bounce Current Peak FCT Peak FCT Residual Duration current voltage Volts I2t (A2s) Fire 46 0.31 1628 480 0.02 N 46 0.28 1248 500 0.03 N 49 0.61 2041 520 0.05 N 45 0.24 1684 520 0.02 N 56 0.9 2016 540 0.25 N 40 0.82 2503 550 0.19 N 47 0.67 2430 600 0.55 N 49 0.74 2445 620 0.3 Y 49 0.56 2318 500 0.2 Y 47 0.45 2074 440 0.08 N 41 0.78 2845 175 0.2 N 44 1.34 2298 190 0.75 Y 48 0.61 1898 220 0.18 N 48 0.59 1926 230 0.11 N 42 0.71 1995 1900 5.82 Y 53 1.68 3434 1920 3.25 Y 48 0.75 1950 1900 7.9 N 53 0.99 1867 1800 21.22 Y 50 1.03 2014 1800 16.69 Y 54 1.03 1915 1700 30.02 Y 48 0.8 1903 1800 10.85 Y 53 0.49 1991 130 0.09 N 51 0.38 2039 140 0.06 N 0.22 2167 100 0.02 N 47 0.33 2039 480 0.02 N 48 0.29 2047 480 0.03 N 48 0.46 2084 490 0.08 N 49 0.53 2840 500 0.11 Y 46 0.48 3744 500 0.06 N 46 0.76 2273 515 0.25 N 63 1.82 4501 530 1.75 N 48 1.02 3688 530 0.39 Y 56 0.75 3737 530 0.22 N 54 1.02 3038 540 0.21 N 50 0.89 3744 550 0.2 N 40 1.57 3421 550 0.84 Y 51 0.46 2564 560 0.13 N 42 1.59 3725 560 0.56 Y 48 0.91 3578 580 0.24 N 49 0.72 2844 1030 0.17 Y 49 0.39 2946 1020 0.14 Y 42 1.18 3896 1000 0.43 Y 51 0.56 2757 960 0.1 N 48 0.56 3294 970 0.13 Y 47 0.74 2773 940 0.35 N 49 0.19 1895 1040 0.05 N 40 2.33 5683 990 1.66 N Документ1 Friday, 4 December 2015 P a g e | 116 Test No. Date 519 24/06/2015 520 25/06/2015 521 25/06/2015 522 25/06/2015 523 25/06/2015 524 25/06/2015 525 25/06/2015 526 25/06/2015 527 25/06/2015 528 25/06/2015 529 25/06/2015 530 25/06/2015 531 25/06/2015 Time 17:15:36 8:53:44 9:04:40 9:11:58 9:19:29 9:24:16 9:31:14 9:38:12 9:44:26 9:51:10 9:58:26 10:03:40 10:32:15 Peak Bounce Current 13.0 10.3 9.2 9.6 10.3 11.1 10.2 10.7 12.2 12.3 11.1 5.3 6.7 Bounce Current Peak FCT Peak FCT Residual Duration current voltage Volts I2t (A2s) Fire 50 1.01 2634 980 0.93 Y 50 0.54 3238 830 0.12 N 51 0.78 3879 1000 0.26 Y 40 0.5 2998 1000 0.19 N 54 0.58 2798 1030 0.19 N 49 0.55 2781 1030 0.19 N 45 0.3 1988 1090 0.03 N 42 0.32 2298 1130 0.04 N 48 0.47 2259 1090 0.09 N 46 1.56 4603 880 0.47 N 55 0.29 3429 950 0.04 N 73 1.35 8637 1000 1.8 Y 38 0.36 3190 100 0.11 N Table 13: Valid ‘wire down’ ignition tests – GFN (GFN4 firmware) Test No. Date Time Resistance Supply Phase 779 781 782 783 784 787 793 795 798 799 800 801 802 803 804 805 806 807 808 818 819 820 821 822 823 13/10/2015 13/10/2015 13/10/2015 13/10/2015 13/10/2015 13/10/2015 13/10/2015 13/10/2015 13/10/2015 13/10/2015 13/10/2015 13/10/2015 13/10/2015 13/10/2015 13/10/2015 13/10/2015 14/10/2015 14/10/2015 14/10/2015 14/10/2015 14/10/2015 14/10/2015 14/10/2015 14/10/2015 14/10/2015 10:01:00 10:23:00 10:32:03 10:45:00 10:52:12 11:47:50 15:07:23 15:42:30 16:13:22 16:22:09 16:37:27 16:46:05 16:59:29 17:06:59 17:14:14 17:21:32 9:09:00 9:20:04 9:33:18 12:12:46 12:21:02 12:31:18 12:39:05 12:50:15 12:56:12 400 400 400 400 400 400 400 400 400 400 400 400 400 400 400 400 400 400 400 100 100 100 100 100 100 Blue White White White White White White White White White White White White White White White White White White White White White White White White © Marxsen Consulting Pty Ltd Bounce Bounce Current Current (manual) Duration Документ1 0.17 0.09 0.09 0.11 0.09 1.23 0.07 0.08 0.24 0.03 0.03 0.03 0.08 0.04 0.05 0.05 0.07 0.07 0.08 0.03 0.07 0.06 0.05 0.04 0.05 46 46 39 51 39 103 38 36 56 39 44 43 37 46 45 46 45 37 39 37 45 37 44 36 35 Ground Current Ground Current Duration Fire 0.32 0.11 0.14 0.09 0.09 0.15 0.23 0.12 0.12 0.11 0.11 0.34 0.11 0.15 0.11 0.03 0.27 0.06 0.11 0.1 0.1 0.16 0.09 0.11 19800 8470 49790 2000 2640 49770 35340 620 38050 59610 109770 38460 43790 16430 19560 40180 92070 33960 108110 7000 20500 16600 21350 14800 Y N N N N N N Y N N N N Y N Y Y N Y N Y N Y Y N Y Friday, 4 December 2015 P a g e | 117 Table 14: Valid ‘wire down’ ignition tests - ASC+FPE (100 Ohms Blue phase) Test No. 214 215 Date 3/06/2015 3/06/2015 Time 16:54 17:09 Peak Bounce Bounce Current Current Duration 10.08 136 11.01 58 Fire N N Table 15: valid NER vegetation conduction ignition tests (blue phase, 400 Ohms, species: Salix) Test No. Date Time Fire Valid 695 696 697 698 699 700 701 702 703 764 8/10/2015 8/10/2015 8/10/2015 8/10/2015 8/10/2015 8/10/2015 8/10/2015 8/10/2015 8/10/2015 12/10/2015 9:25:50 9:34:29 9:42:10 9:50:35 9:57:55 10:06:24 10:13:22 10:19:53 10:27:55 13:25:53 N N Y Y Y Y Y N Y N Y Y Y Y Y Y Y Y Y Y © Marxsen Consulting Pty Ltd Документ1 Current Initial Final Flow Current Current Duration 135910 130980 119480 90380 105870 76240 96030 44520 117860 134350 0.03 0.04 0.06 0.03 0.03 0.04 0.04 0.06 0.03 0.03 0.57 0.32 0.53 0.6 0.74 0.77 0.54 0.5 0.64 0.52 Friday, 4 December 2015 P a g e | 118 Table 16: valid ‘wire down’ ignition tests – SSFCL+FPE (100 Ohms) Test No. 132 133 143 384 385 386 387 388 391 392 393 394 395 396 397 398 399 400 401 402 403 404 405 406 407 408 409 410 411 412 414 415 416 417 418 419 420 421 422 423 424 425 426 427 428 Date 28/05/2015 28/05/2015 28/05/2015 19/06/2015 19/06/2015 19/06/2015 19/06/2015 19/06/2015 19/06/2015 19/06/2015 19/06/2015 19/06/2015 19/06/2015 19/06/2015 19/06/2015 19/06/2015 19/06/2015 19/06/2015 19/06/2015 19/06/2015 19/06/2015 19/06/2015 19/06/2015 19/06/2015 19/06/2015 19/06/2015 19/06/2015 19/06/2015 19/06/2015 19/06/2015 22/06/2015 22/06/2015 22/06/2015 22/06/2015 22/06/2015 22/06/2015 22/06/2015 22/06/2015 22/06/2015 22/06/2015 22/06/2015 22/06/2015 22/06/2015 22/06/2015 22/06/2015 Time 13:44 14:00 16:20 9:28:00 9:34:56 9:39:57 9:47:10 9:52:59 11:10:39 11:39:59 11:43:06 11:48:31 11:56:44 12:52:39 12:57:51 13:03:51 13:08:10 13:12:13 13:22:17 13:28:04 13:33:01 13:38:02 13:43:24 13:48:21 13:56:12 14:02:10 14:07:52 14:12:15 14:18:13 14:23:23 12:39:18 14:06:00 14:15:41 14:22:19 14:28:02 14:44:12 14:52:16 14:58:56 15:07:50 15:14:58 15:25:24 15:34:51 15:42:29 15:47:30 15:54:21 © Marxsen Consulting Pty Ltd Supply Phase Blue Blue Blue White White White White White White White White White White White White White White White White White White White White White White White White White White White White White White White White White White White White White White White White White White Peak Bounce Bounce Current Current Duration I2t (A2s) 7.2 80 6.4 73 5.3 82 6.2 77 2.5 6.1 159 4.9 5.7 161 4.5 6.4 159 6.0 6.7 156 7.0 7.0 141 6.1 7.2 132 6.1 7.1 135 4.8 6.9 135 6.0 7.3 139 6.3 7.3 120 5.6 7.6 116 5.4 7.1 121 5.4 7.2 120 5.5 7.0 124 5.6 7.3 95 4.5 7.2 97 4.7 7.8 97 5.6 7.6 91 4.9 7.6 98 5.3 7.6 102 5.6 7.1 89 4.2 7.6 91 5.0 7.3 89 4.5 7.4 89 4.2 7.5 93 4.8 7.4 82 3.9 7.0 73 3.1 6.7 80 3.0 6.9 83 3.8 6.8 84 3.6 6.8 74 3.2 6.8 78 3.4 7.2 77 3.5 7.3 77 3.7 7.0 85 3.6 7.3 77 3.6 6.8 93 3.5 7.0 88 3.8 7.6 86 4.1 7.1 90 3.6 7.2 92 4.2 Документ1 Fire N N N N Y Y Y Y Y Y Y N Y Y Y Y Y Y Y N Y N N N N Y N Y Y N N N N N N N N N Y N Y N N Y N FPE Delay (ms) 0 0 0 0 80 80 80 80 60 60 60 60 60 40 40 40 40 40 20 20 20 20 20 20 10 10 10 10 10 10 0 0 0 0 0 0 0 0 0 0 10 10 10 10 10 Friday, 4 December 2015 P a g e | 119 Table 17: valid GFN vegetation conduction ignition tests (GFN4 firmware, 400 Ohms, species: Salix) Test No. Date Time Supply Phase 661 662 663 664 665 666 667 668 669 670 671 672 674 675 676 677 678 679 680 681 682 683 684 685 686 688 689 690 691 693 694 705 706 707 708 709 711 712 713 714 715 7/10/2015 7/10/2015 7/10/2015 7/10/2015 7/10/2015 7/10/2015 7/10/2015 7/10/2015 7/10/2015 7/10/2015 7/10/2015 7/10/2015 7/10/2015 7/10/2015 7/10/2015 7/10/2015 7/10/2015 7/10/2015 7/10/2015 7/10/2015 7/10/2015 7/10/2015 7/10/2015 7/10/2015 7/10/2015 7/10/2015 7/10/2015 7/10/2015 7/10/2015 7/10/2015 7/10/2015 8/10/2015 8/10/2015 8/10/2015 8/10/2015 8/10/2015 8/10/2015 8/10/2015 8/10/2015 8/10/2015 8/10/2015 9:58:16 10:09:10 10:20:30 10:39:28 10:54:35 11:09:00 11:42:00 11:54:22 12:06:04 12:18:20 13:38:59 13:47:52 14:02:28 14:11:24 14:25:46 14:34:58 14:49:35 15:00:57 15:10:52 15:22:02 15:31:19 15:47:12 15:55:52 16:02:42 16:17:59 16:37:25 16:47:13 16:54:15 17:03:35 17:22:37 17:28:23 11:13:51 11:21:37 11:34:16 11:43:25 11:51:12 13:29:39 13:41:23 13:52:53 14:01:22 14:14:22 White White White White White White White White White White Blue Blue Blue Blue Blue Blue Blue Blue Blue Blue Blue Red Red Red Red Red Red Red Blue Blue Blue White White White White White White White White White Blue © Marxsen Consulting Pty Ltd Fire N N N N N N N N Y Y Y N Y Y N N N Y Y N N N N Y N N N N Y N N Y Y Y N Y N Y N N N Документ1 Current Initial Final Flow Current Current Duration 39430 109930 38240 100470 40360 130320 40920 139060 161190 137980 114640 106200 140700 113580 39500 32460 170810 158460 149620 137470 24410 26980 55790 136990 107430 134240 32230 26640 185430 22500 40390 138290 200000 125950 154810 123530 210850 217240 123990 116100 134750 0.06 0.04 0.05 0.03 0.04 0.04 0.06 0.04 0.07 0.05 0.04 0.04 0.05 0.04 0.07 0.09 0.07 0.1 0.09 0.09 0.21 0.14 0.07 0.03 0.02 0.05 0.06 0.13 0.1 0.14 0.13 0.06 0.05 0.03 0.04 0.03 0.05 0.03 0.03 0.04 0.05 0.45 0.37 0.22 0.27 0.29 0.54 0.3 0.34 0.36 0.36 0.36 0.42 0.39 0.51 0.3 0.33 0.48 0.4 0.44 0.39 0.39 0.34 0.32 0.48 0.39 0.41 0.34 0.38 0.45 0.39 0.41 0.33 0.3 0.46 0.33 0.13 0.3 0.32 0.34 0.31 0.51 Species Salix Salix Salix Salix Salix Salix Salix Salix Salix Salix Salix Salix Salix Salix Salix Salix Salix Salix Salix Salix Salix Salix Salix Salix Salix Salix Salix Salix Salix Salix Salix Salix Salix Salix Salix Salix Salix Salix Salix Salix Salix Friday, 4 December 2015 P a g e | 120 Test No. Date Time Supply Phase Fire 716 718 719 742 743 744 745 746 747 748 749 750 759 761 766 767 768 769 770 771 772 788 790 791 792 8/10/2015 8/10/2015 8/10/2015 9/10/2015 9/10/2015 9/10/2015 9/10/2015 9/10/2015 9/10/2015 9/10/2015 9/10/2015 9/10/2015 12/10/2015 12/10/2015 12/10/2015 12/10/2015 12/10/2015 12/10/2015 12/10/2015 12/10/2015 12/10/2015 13/10/2015 13/10/2015 13/10/2015 13/10/2015 14:25:16 14:45:31 14:55:22 11:53:06 12:00:53 12:06:29 12:16:51 12:35:18 12:43:10 12:50:49 13:00:40 13:10:28 12:16:59 12:36:15 14:50:05 14:57:37 15:05:28 15:13:52 15:22:12 15:29:37 15:37:48 12:20:20 12:57:02 13:05:11 14:19:49 Blue Blue Blue White White White Blue Blue Blue Blue Blue Blue Blue Blue Blue Blue Blue Blue Blue Blue Blue White White White White Y N Y N N Y Y Y N N Y N N N Y N N N N N N N N Y N Current Initial Final Flow Current Current Duration 136520 118180 169070 157200 40270 130640 161120 130960 120400 160140 133490 128780 160570 52890 111830 53320 47370 128340 121080 117110 105450 64740 127970 214170 60510 0.05 0.04 0.06 0.03 0.07 0.05 0.06 0.05 0.03 0.06 0.04 0.05 0.05 0.08 0.02 0.07 0.07 0.02 0.02 0.02 0.03 0.11 0.03 0.07 0.05 0.37 0.46 0.57 0.44 0.34 0.47 0.51 0.49 0.58 0.48 0.58 0.4 0.48 0.4 0.45 0.36 0.36 0.44 0.48 0.53 0.35 0.36 0.31 0.47 0.28 Species Salix Salix Salix Salix Salix Salix Salix Salix Salix Salix Salix Salix Salix Salix Salix Salix Salix Salix Salix Salix Salix Salix Salix Salix Salix Table 18: valid GFN vegetation conduction ignition tests (GFN4 firmware, 400 Ohms, species: F. Angustifolia) Test No. Date Time Supply Phase Fire 751 752 753 754 755 756 760 762 765 9/10/2015 9/10/2015 9/10/2015 9/10/2015 9/10/2015 9/10/2015 12/10/2015 12/10/2015 12/10/2015 13:49:47 13:56:02 14:03:24 14:10:23 14:17:27 14:23:45 12:27:48 12:49:49 14:53:54 Blue Blue Blue Blue Blue Blue Blue Blue Blue N N N N N N N N N © Marxsen Consulting Pty Ltd Документ1 Current Initial Final Flow Current Current Duration 51030 29810 19870 21470 23180 48710 44350 59480 47820 0.09 0.15 0.24 0.14 0.15 0.06 0.11 0.09 0.12 0.43 0.43 0.4 0.41 0.4 0.37 0.41 0.39 0.41 Friday, 4 December 2015 P a g e | 121 15.1.2 Bolted resistive fault tests The following tests were performed with the test rig shorted out by a length of flexible welding cable. They were performed to for setup purposes and to explore and measure the performance of each REFCL type. Table 19: Bolted resistive fault tests Test No. 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 59 60 61 62 63 64 65 66 67 68 69 70 71 72 73 74 75 76 77 78 79 80 81 82 83 96 97 98 99 100 209 Date 11/05/2015 11/05/2015 11/05/2015 11/05/2015 11/05/2015 11/05/2015 11/05/2015 11/05/2015 11/05/2015 11/05/2015 11/05/2015 11/05/2015 11/05/2015 11/05/2015 11/05/2015 11/05/2015 19/05/2015 19/05/2015 19/05/2015 21/05/2015 21/05/2015 21/05/2015 21/05/2015 21/05/2015 21/05/2015 21/05/2015 21/05/2015 21/05/2015 21/05/2015 21/05/2015 21/05/2015 21/05/2015 21/05/2015 21/05/2015 21/05/2015 22/05/2015 22/05/2015 22/05/2015 22/05/2015 22/05/2015 22/05/2015 25/05/2015 25/05/2015 25/05/2015 25/05/2015 25/05/2015 2/06/2015 © Marxsen Consulting Pty Ltd Time 14:50 15:05 15:08 15:09 15:12 15:33 15:37 15:53 15:56 16:28 16:45 16:48 17:10 17:18 17:40 18:01 15:01 16:51 17:18 13:44 14:06 14:15 14:55 14:59 15:59 16:13 16:19 16:33 16:55 17:00 17:14 17:57 18:24 18:31 19:05 9:16 9:38 9:49 9:52 10:33 10:38 14:49 15:05 15:12 15:25 15:34 13:16 Protection Compensation NER NER NER NER NER NER NER NER NER NER NER NER NER NER NER NER SSFCL SSFCL SSFCL SSFCL FPE SSFCL FPE SSFCL FPE SSFCL FPE SSFCL FPE SSFCL FPE SSFCL FPE SSFCL FPE SSFCL FPE SSFCL FPE SSFCL FPE SSFCL FPE SSFCL FPE SSFCL FPE SSFCL FPE SSFCL FPE SSFCL SSFCL FPE SSFCL FPE SSFCL FPE SSFCL FPE SSFCL FPE ASC FPE ASC FPE ASC FPE ASC FPE ASC FPE ASC - Документ1 Resistance 15600 15600 15600 15600 15600 15600 15600 15600 15600 6400 6400 6400 1600 400 200 100 15600 15600 6400 6400 6400 6400 3200 3200 3200 1600 1600 1600 1600 1600 1600 1600 400 400 1600 400 200 100 100 0 0 1600 400 400 100 0 100 Phase Blue Blue Blue Blue Blue Blue Blue Blue Blue Blue Blue Blue Blue Blue Blue Blue Blue Blue Blue Blue Blue Blue Blue Blue Blue Blue Blue Blue Blue Blue Blue White Red Red Blue Blue Blue Blue Blue Blue Blue Blue Blue Blue Blue Blue Blue Friday, 4 December 2015 P a g e | 122 Test No. 210 211 212 213 293 294 295 296 300 301 302 303 373 374 375 376 377 378 379 380 381 382 413 461 462 463 464 477 478 479 480 481 482 483 484 485 Date 2/06/2015 2/06/2015 3/06/2015 3/06/2015 15/06/2015 15/06/2015 15/06/2015 15/06/2015 16/06/2015 16/06/2015 16/06/2015 16/06/2015 18/06/2015 18/06/2015 18/06/2015 18/06/2015 18/06/2015 18/06/2015 18/06/2015 18/06/2015 18/06/2015 18/06/2015 22/06/2015 23/06/2015 23/06/2015 23/06/2015 23/06/2015 24/06/2015 24/06/2015 24/06/2015 24/06/2015 24/06/2015 24/06/2015 24/06/2015 24/06/2015 24/06/2015 Time 13:36 13:44 15:52 16:16 16:52:00 16:58:27 17:02:00 17:06:10 11:05:00 11:13:56 11:35:00 11:46:00 14:55:55 15:03:00 15:11:00 15:43:41 16:46:53 17:12:43 17:22:38 17:37:00 17:54:42 18:05:48 12:03:17 14:38:00 14:40:00 14:45:00 15:06:59 9:59:00 10:09:00 10:25:00 10:58:00 11:27:42 11:34:00 11:48:10 11:53:00 12:01:00 Protection Compensation Resistance ASC 100 ASC 100 ASC 100 ASC 100 GFN3 RCC 15600 GFN3 RCC 15600 GFN3 RCC 15600 GFN3 RCC 15600 GFN3 RCC 25400 GFN3 RCC 25400 GFN3 RCC 25400 GFN3 RCC 25400 SSFCL FPE 15300 SSFCL FPE 100 SSFCL FPE 100 SSFCL FPE 100 GFN3 RCC 100 GFN3 RCC 12800 GFN3 RCC 12800 GFN3 RCC 6400 GFN3 RCC 3200 GFN3 RCC 100 GFN3 RCC 3300 GFN3 RCC 3300 GFN3 RCC 3300 GFN3 RCC 3300 GFN3 RCC 3300 GFN3 RCC 8.3/16.7+3.2 GFN3 RCC 8.3/16.7+3.2 GFN3 RCC 16.7/8.3+3.2 GFN3 RCC 8.3/8.3+3.2 GFN3 RCC 16.7/16.7+400 GFN3 RCC 16.7/16.7+400 GFN3 RCC 16.7/16.7+400 GFN3 RCC 16.7/16.7+400 GFN3 RCC 16.7/16.7+400 Phase Blue Blue Blue Blue White White White White White White White White White White White White White White White White White White White White White White White Blue/White Blue/White Blue/White Blue/White Blue/White Blue/White Red/White Red/White Red/White Table 20: Tranche 4 GFN bolted resistive fault tests with GFN4 firmware Test No. Date Time Resistance Supply Phase 602 603 604 605 606 607 608 621 622 623 30/09/2015 30/09/2015 30/09/2015 30/09/2015 30/09/2015 30/09/2015 30/09/2015 1/10/2015 1/10/2015 1/10/2015 14:33:00 14:50:39 15:18:20 15:31:30 15:55:35 16:07:00 16:15:30 12:22:12 12:28:05 12:38:19 25050 25050 25050 25050 25050 25050 25050 25050 25050 25050 White White White White Blue Blue Blue White White White © Marxsen Consulting Pty Ltd Документ1 Current Initial Flow Current Duration 125 200 190 176 537 546 488 289 235 235 0.44 0.43 0.43 0.43 0.53 0.54 0.52 0.48 0.47 0.48 Friday, 4 December 2015 P a g e | 123 Test No. Date Time Resistance Supply Phase 624 625 626 627 628 629 630 631 632 633 634 635 636 637 638 639 640 641 642 643 644 645 646 647 649 650 651 652 653 654 655 656 657 658 720 721 722 723 724 725 726 739 809 810 811 813 814 815 1/10/2015 1/10/2015 1/10/2015 1/10/2015 1/10/2015 1/10/2015 1/10/2015 1/10/2015 1/10/2015 1/10/2015 5/10/2015 5/10/2015 5/10/2015 5/10/2015 5/10/2015 5/10/2015 5/10/2015 5/10/2015 5/10/2015 5/10/2015 5/10/2015 5/10/2015 5/10/2015 5/10/2015 5/10/2015 5/10/2015 5/10/2015 5/10/2015 5/10/2015 5/10/2015 5/10/2015 5/10/2015 5/10/2015 5/10/2015 8/10/2015 8/10/2015 8/10/2015 8/10/2015 8/10/2015 8/10/2015 8/10/2015 9/10/2015 14/10/2015 14/10/2015 14/10/2015 14/10/2015 14/10/2015 14/10/2015 12:56:23 13:26:34 13:30:37 13:42:12 13:44:05 13:45:44 14:05:46 14:08:22 14:10:19 14:42:27 11:14:16 11:23:30 11:26:15 11:38:57 11:42:48 11:55:00 12:00:08 12:02:33 12:09:30 12:17:30 12:23:59 12:44:05 12:56:23 12:57:00 14:20:33 15:18:16 16:01:11 16:03:28 16:13:14 16:15:13 16:37:24 16:41:53 16:45:46 16:57:52 15:24:11 15:34:00 15:40:37 16:19:03 16:46:19 16:50:59 17:01:22 10:49:24 10:00:30 10:06:35 10:10:54 10:25:03 10:29:28 10:33:42 25050 25050 25050 25050 25050 25050 400 400 400 400 40000 40000 40000 40000 40000 40000 40000 40000 25050 25050 25050 25450 25450 25450 400 400 400 400 400 400 25450 25450 25450 400 400 400 400 400 400 400 400 400 400 400 400 15600 15600 15600 Blue Blue Blue Red Red Red White White White Blue White White White Blue Blue Red Red Red Red Blue White Blue Blue Blue Blue Blue White White Red Red White White White White Blue Blue Blue Blue Blue Blue Blue White White Blue Red Red Blue White © Marxsen Consulting Pty Ltd Документ1 Current Initial Flow Current Duration 350 350 350 270 270 230 50 58 55 65 350 350 350 530 550 400 420 395 235 325 240 340 350 350 60 60 60 50 55 55 240 250 2665 3038 63 112070 165040 180650 80 60 60 45 55 63 58 218 291 245 0.51 0.51 0.51 0.47 0.47 0.47 18.48 18.48 18.06 19.79 0.31 0.3 0.3 0.32 0.32 0.3 0.31 0.31 0.48 0.51 0.47 0.51 0.51 0.5 19.65 19.8 18.43 18.5 18.84 18.83 0.47 0.47 0.48 >2.6 20.09 0.4 20.1 >2.64 18.52 19.61 18.34 0.76 0.81 0.76 Friday, 4 December 2015 P a g e | 124 15.1.3 Setup and invalid tests The following tests were performed for the purposes of setup or they were ruled invalid for some reason and excluded from the sets of ignition results used in some analyses. Table 21: Setup and invalid tests – earlier versions of GFN firmware (up to Test 292) Test No. 35 36 37 38 39 40 41 42 43 44 45 Date 18/05/2015 18/05/2015 18/05/2015 18/05/2015 18/05/2015 18/05/2015 18/05/2015 18/05/2015 18/05/2015 18/05/2015 18/05/2015 Time 13:33 13:45 14:08 14:11 14:23 14:27 14:44 15:18 15:22 15:26 15:46 © Marxsen Consulting Pty Ltd Test Type Bolted Bolted Bolted Bolted Bolted Bolted Bolted Bolted Bolted Bolted Bolted Protection GFN1 GFN1 GFN1 GFN1 GFN1 GFN1 GFN1 GFN1 GFN1 GFN1 GFN1 Документ1 Compensation RCC Resistance 15600 15600 12800 12800 6400 6400 3200 3200 3200 3200 3200 Supply Phase Blue Blue Blue Blue Blue Blue Blue Blue Blue Blue Blue Friday, 4 December 2015 P a g e | 125 Test No. 45 84 85 86 87 88 89 90 91 92 93 94 95 101 102 103 104 105 106 107 108 109 110 111 112 113 114 115 116 117 118 119 120 121 123 124 125 126 127 128 129 130 131 152 153 154 155 156 157 158 159 160 Date 18/05/2015 22/05/2015 22/05/2015 22/05/2015 22/05/2015 22/05/2015 22/05/2015 22/05/2015 22/05/2015 25/05/2015 25/05/2015 25/05/2015 25/05/2015 27/05/2015 27/05/2015 27/05/2015 27/05/2015 27/05/2015 27/05/2015 27/05/2015 27/05/2015 27/05/2015 27/05/2015 27/05/2015 27/05/2015 27/05/2015 27/05/2015 27/05/2015 27/05/2015 27/05/2015 27/05/2015 27/05/2015 27/05/2015 27/05/2015 28/05/2015 28/05/2015 28/05/2015 28/05/2015 28/05/2015 28/05/2015 28/05/2015 28/05/2015 28/05/2015 29/05/2015 29/05/2015 29/05/2015 29/05/2015 29/05/2015 29/05/2015 29/05/2015 29/05/2015 29/05/2015 Time 15:46 12:01 12:09 12:23 13:22 13:47 13:54 14:19 14:24 12:06 12:25 12:51 13:10 9:16 10:04 10:34 10:36 10:42 11:14 12:11 13:58 14:11 15:11 15:23 15:36 15:52 15:58 16:21 16:41 16:53 17:05 17:17 17:35 17:49 9:09 10:01 10:13 10:31 10:44 11:03 11:17 11:32 11:48 9:05 9:33 9:41 9:51 10:00 10:16 10:26 10:34 10:43 © Marxsen Consulting Pty Ltd Test Type Bolted Bolted Bolted Bolted Bolted Bolted Bolted Bolted Bolted Bolted Bolted Bolted Bolted Bolted Bolted Bolted Bolted Bolted Ignition Ignition Ignition Ignition Ignition Ignition Ignition Ignition Ignition Ignition Ignition Ignition Ignition Ignition Ignition Ignition Ignition Ignition Ignition Ignition Ignition Ignition Ignition Ignition Ignition Ignition Ignition Ignition Ignition Ignition Ignition Ignition Ignition Ignition Protection GFN1 GFN1 GFN1 GFN1 GFN1 GFN1 GFN1 GFN1 GFN1 GFN1 GFN1 GFN1 GFN1 GFN2 GFN2 GFN2 GFN2 GFN2 GFN2 GFN2 GFN2 GFN2 GFN2 GFN2 GFN2 GFN2 GFN2 GFN2 GFN2 GFN2 GFN2 GFN2 GFN2 GFN2 GFN2 GFN2 GFN2 GFN2 GFN2 GFN2 GFN2 GFN2 GFN2 GFN2 GFN2 GFN2 GFN2 GFN2 GFN2 GFN2 GFN2 GFN2 Документ1 Compensation RCC RCC RCC RCC RCC RCC RCC RCC RCC RCC RCC RCC RCC RCC RCC RCC RCC RCC RCC RCC RCC RCC RCC RCC RCC RCC RCC RCC RCC RCC RCC RCC RCC RCC RCC RCC RCC RCC RCC RCC RCC RCC RCC RCC RCC RCC RCC RCC RCC RCC RCC RCC Resistance 3200 15600 15600 15600 6400 6400 6400 6400 6400 1600 400 100 0 100 100 15200 15200 15200 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 Supply Phase Blue Blue Blue Blue Blue Blue Blue Blue Blue Blue Blue Blue Blue Blue Blue Blue Blue Blue Blue Blue Blue Blue Blue Blue Blue Blue Blue Blue Blue Blue Blue Blue Blue Blue Blue Blue Blue Blue Blue Blue Blue Blue Blue Blue Blue Blue Blue Blue Blue Blue Blue Blue Friday, 4 December 2015 P a g e | 126 Test No. 161 162 163 164 165 166 167 168 169 170 171 172 173 174 175 176 177 178 179 180 181 182 183 184 185 186 187 188 189 190 191 192 193 194 195 196 197 198 199 200 201 202 203 204 205 206 207 208 217 218 219 220 Date 29/05/2015 29/05/2015 29/05/2015 29/05/2015 29/05/2015 29/05/2015 29/05/2015 29/05/2015 29/05/2015 29/05/2015 29/05/2015 29/05/2015 29/05/2015 29/05/2015 29/05/2015 29/05/2015 29/05/2015 29/05/2015 1/06/2015 1/06/2015 1/06/2015 1/06/2015 1/06/2015 1/06/2015 1/06/2015 1/06/2015 1/06/2015 1/06/2015 1/06/2015 1/06/2015 1/06/2015 1/06/2015 1/06/2015 1/06/2015 1/06/2015 1/06/2015 1/06/2015 1/06/2015 2/06/2015 2/06/2015 2/06/2015 2/06/2015 2/06/2015 2/06/2015 2/06/2015 2/06/2015 2/06/2015 2/06/2015 4/06/2015 4/06/2015 4/06/2015 4/06/2015 Time 10:51 11:02 11:12 11:22 11:29 11:36 11:48 12:04 13:26 13:34 13:40 13:47 13:53 14:02 14:09 14:17 14:25 14:32 12:00 12:15 12:25 12:33 13:34 13:45 14:23 14:38 14:51 15:23 15:32 16:23 16:31 16:40 16:48 16:57 17:04 17:13 17:22 17:59 9:31 9:47 9:53 10:03 10:17 10:25 10:40 10:52 11:03 11:15 11:47 12:04 12:34 12:36 © Marxsen Consulting Pty Ltd Test Type Ignition Ignition Ignition Ignition Ignition Ignition Ignition Ignition Ignition Ignition Ignition Ignition Ignition Ignition Ignition Ignition Ignition Ignition Ignition Ignition Ignition Ignition Ignition Ignition Ignition Ignition Ignition Ignition Ignition Ignition Ignition Ignition Ignition Ignition Ignition Ignition Ignition Ignition Ignition Ignition Ignition Ignition Ignition Ignition Ignition Ignition Ignition Ignition Bolted Bolted Bolted Bolted Protection GFN2 GFN2 GFN2 GFN2 GFN2 GFN2 GFN2 GFN2 GFN2 GFN2 GFN2 GFN2 GFN2 GFN2 GFN2 GFN2 GFN2 GFN2 GFN2 GFN2 GFN2 GFN2 GFN2 GFN2 GFN2 GFN2 GFN2 GFN2 GFN2 GFN2 GFN2 GFN2 GFN2 GFN2 GFN2 GFN2 GFN2 GFN2 GFN2 GFN2 GFN2 GFN2 GFN2 GFN2 GFN2 GFN2 GFN2 GFN2 GFN2 GFN2 GFN2 GFN2 Документ1 Compensation RCC RCC RCC RCC RCC RCC RCC RCC RCC RCC RCC RCC RCC RCC RCC RCC RCC RCC RCC RCC RCC RCC RCC RCC RCC RCC RCC RCC RCC RCC RCC RCC RCC RCC RCC RCC RCC RCC RCC RCC RCC RCC RCC RCC RCC RCC RCC RCC RCC RCC RCC RCC Resistance 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 Supply Phase Blue Blue Blue Blue Blue Blue Blue Blue Blue Blue Blue Blue Blue Blue Blue Blue Blue Blue Blue Blue Blue Blue Blue Blue Blue Blue Blue Blue Blue Blue Blue Blue Blue Blue Blue Blue Blue Blue Blue Blue Blue Blue Blue Blue Blue Blue Blue Blue Blue Blue Blue Blue Friday, 4 December 2015 P a g e | 127 Test No. 221 222 223 224 225 226 227 228 229 230 231 232 233 234 235 236 237 238 239 240 241 242 243 244 245 246 247 248 249 250 251 252 253 254 255 256 257 258 259 260 261 262 263 264 265 266 267 268 269 270 271 272 Date 4/06/2015 4/06/2015 4/06/2015 4/06/2015 4/06/2015 4/06/2015 4/06/2015 4/06/2015 4/06/2015 4/06/2015 4/06/2015 4/06/2015 4/06/2015 4/06/2015 4/06/2015 4/06/2015 4/06/2015 4/06/2015 4/06/2015 4/06/2015 4/06/2015 4/06/2015 4/06/2015 4/06/2015 4/06/2015 4/06/2015 4/06/2015 4/06/2015 4/06/2015 5/06/2015 5/06/2015 5/06/2015 5/06/2015 5/06/2015 5/06/2015 5/06/2015 5/06/2015 5/06/2015 5/06/2015 5/06/2015 5/06/2015 5/06/2015 5/06/2015 5/06/2015 5/06/2015 5/06/2015 5/06/2015 5/06/2015 5/06/2015 5/06/2015 5/06/2015 5/06/2015 Time 13:12 13:24 13:35 13:59 14:08 14:15 14:28 14:39 14:45 14:52 14:59 15:05 15:13 15:19 15:27 15:38 16:25 16:32 16:37 16:45 16:51 17:01 17:07 17:13 17:19 17:24 17:31 17:38 17:44 9:27 9:35 9:41 9:48 9:55 10:01 10:09 10:18 10:27 11:54 12:01 12:07 12:21 12:27 12:38 12:44 12:52 13:13 13:19 13:42 14:04 14:08 14:15 © Marxsen Consulting Pty Ltd Test Type Ignition Ignition Ignition Ignition Ignition Ignition Ignition Ignition Ignition Ignition Ignition Ignition Ignition Ignition Ignition Ignition Ignition Ignition Ignition Ignition Ignition Ignition Ignition Ignition Ignition Ignition Ignition Ignition Ignition Ignition Ignition Ignition Ignition Ignition Ignition Ignition Ignition Ignition Ignition Ignition Ignition Ignition Ignition Ignition Ignition Ignition Ignition Ignition Ignition Ignition Ignition Ignition Protection GFN2 GFN2 GFN2 GFN2 GFN2 GFN2 GFN2 GFN2 GFN2 GFN2 GFN2 GFN2 GFN2 GFN2 GFN2 GFN2 GFN2 GFN2 GFN2 GFN2 GFN2 GFN2 GFN2 GFN2 GFN2 GFN2 GFN2 GFN2 GFN2 GFN2 GFN2 GFN2 GFN2 GFN2 GFN2 GFN2 GFN2 GFN2 GFN2 GFN2 GFN2 GFN2 GFN2 GFN2 GFN2 GFN2 GFN2 GFN2 GFN2 GFN2 GFN2 GFN2 Документ1 Compensation RCC RCC RCC RCC RCC RCC RCC RCC RCC RCC RCC RCC RCC RCC RCC RCC RCC RCC RCC RCC RCC RCC RCC RCC RCC RCC RCC RCC RCC RCC RCC RCC RCC RCC RCC RCC RCC RCC RCC RCC RCC RCC RCC RCC RCC RCC RCC RCC RCC RCC RCC RCC Resistance 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 Supply Phase Blue Blue Blue Blue Blue Blue Blue Blue Blue Blue Blue Blue Blue Blue Blue Blue Blue Blue Blue Blue Blue Blue Blue Blue Blue Blue Blue Blue Blue Blue Blue Blue Blue Blue Blue Blue Blue Blue Blue Blue Blue Blue Blue Blue Blue Blue Blue Blue Blue Blue Blue Blue Friday, 4 December 2015 P a g e | 128 Test No. 273 274 275 276 277 278 279 280 281 282 283 284 285 286 287 288 289 290 291 292 Date 5/06/2015 5/06/2015 5/06/2015 5/06/2015 15/06/2015 15/06/2015 15/06/2015 15/06/2015 15/06/2015 15/06/2015 15/06/2015 15/06/2015 15/06/2015 15/06/2015 15/06/2015 15/06/2015 15/06/2015 15/06/2015 15/06/2015 15/06/2015 Time 14:21 14:26 14:31 14:37 13:14 13:17:00 13:21:03 13:25:35 13:28:57 13:49:00 14:12:00 14:15:00 14:16:00 14:32:45 14:55:00 15:01:17 15:08:40 15:21:00 15:26:15 15:31:00 Test Type Ignition Ignition Ignition Ignition Bolted Bolted Bolted Bolted Bolted Bolted Bolted Bolted Bolted Bolted Bolted Bolted Bolted Bolted Bolted Bolted Protection GFN2 GFN2 GFN2 GFN2 GFN2 GFN2 GFN2 GFN2 GFN2 GFN2 GFN2 GFN2 GFN2 GFN2 GFN2 GFN2 GFN2 GFN2 GFN2 GFN2 Compensation RCC RCC RCC RCC RCC RCC RCC RCC RCC RCC RCC RCC RCC RCC RCC RCC RCC RCC RCC RCC Resistance 100 100 100 100 15600 15600 15600 15600 15600 15600 15600 15600 15600 15600 15600 15600 15600 15600 15600 15600 Supply Phase Blue Blue Blue Blue Blue Blue Blue Blue Blue White White White White Blue White White White White White White Table 22: set-up and invalid tests - other reasons (all ignition tests on white phase) Test No. 17 18 19 20 21 22 23 32 49 50 51 52 56 57 58 134 135 136 137 138 139 140 141 142 144 145 146 147 148 149 150 151 Date 11/05/2015 11/05/2015 11/05/2015 11/05/2015 11/05/2015 14/05/2015 14/05/2015 14/05/2015 19/05/2015 19/05/2015 19/05/2015 19/05/2015 19/05/2015 19/05/2015 19/05/2015 28/05/2015 28/05/2015 28/05/2015 28/05/2015 28/05/2015 28/05/2015 28/05/2015 28/05/2015 28/05/2015 28/05/2015 28/05/2015 28/05/2015 28/05/2015 28/05/2015 28/05/2015 28/05/2015 28/05/2015 Time 18:38 18:44 19:20 19:22 19:27 13:21 13:40 14:48 11:00 11:21 11:29 11:40 12:40 12:47 12:53 14:14 14:28 14:44 14:58 15:11 15:19 15:26 15:39 16:13 16:28 16:36 16:47 16:53 17:05 17:12 17:18 17:26 © Marxsen Consulting Pty Ltd Protection Compensation NER NER NER NER NER NER NER NER NER NER NER NER NER NER NER SSFCL FPE SSFCL FPE SSFCL FPE SSFCL FPE SSFCL FPE SSFCL FPE SSFCL FPE SSFCL FPE SSFCL FPE SSFCL FPE SSFCL FPE SSFCL FPE SSFCL FPE SSFCL FPE SSFCL FPE SSFCL FPE SSFCL FPE Документ1 Resistance 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 Invalid reason No grass No grass No grass No G3i record G3i noise trigger Same bed Short test No G3i record Arm sitting high Arm sitting high Arm sitting high Arm sitting high Arm sitting high Arm sitting high Arm sitting high Conductor tilted Conductor tilted Conductor tilted Conductor tilted Conductor tilted Conductor tilted Conductor tilted Conductor tilted Conductor tilted Conductor tilted Conductor tilted Conductor tilted Conductor tilted Conductor tilted Conductor tilted Conductor tilted Conductor tilted Friday, 4 December 2015 P a g e | 129 Test No. 216 297 299 317 339 383 443 465 489 490 491 492 508 509 516 532 536 537 538 Date 3/06/2015 15/06/2015 16/06/2015 16/06/2015 17/06/2015 19/06/2015 23/06/2015 23/06/2015 24/06/2015 24/06/2015 24/06/2015 24/06/2015 24/06/2015 24/06/2015 24/06/2015 25/06/2015 25/06/2015 25/06/2015 25/06/2015 Time 17:16 17:28:40 8:59:44 17:06:30 12:41:39 9:19:00 9:36:58 15:47:26 13:40:00 13:50:57 13:56:35 14:00:20 16:00:48 16:04:53 16:51:08 10:38:43 12:51:53 13:34:23 13:52:49 Protection Compensation ASC FPE GFN3 RCC GFN3 RCC GFN3 RCC GFN3 RCC SSFCL FPE GFN3 RCC GFN3 RCC GFN3 RCC GFN3 RCC GFN3 RCC GFN3 RCC GFN3 RCC GFN3 RCC GFN3 RCC GFN3 RCC NER NER NER - Resistance 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 3300 100 100 Invalid reason Tripped power no record Not detected on bounce Not detected in FCT GFN malfunction Not detected on bounce No FPE operation No RCC operation Odd GFN behaviour Same bed Same bed Same bed Same bed Same bed Same bed GFN malfunction Arm sitting high Duration too long Arced to bow Fulgurite Table 23: Tranche 4 setup and invalid tests Test No. Date Time 659 660 673 687 692 704 710 717 741 763 773 774 775 776 777 778 780 789 794 796 797 816 817 824 825 826 827 828 829 830 831 832 833 834 835 7/10/2015 7/10/2015 7/10/2015 7/10/2015 7/10/2015 8/10/2015 8/10/2015 8/10/2015 9/10/2015 12/10/2015 12/10/2015 12/10/2015 12/10/2015 12/10/2015 12/10/2015 12/10/2015 13/10/2015 13/10/2015 13/10/2015 13/10/2015 13/10/2015 14/10/2015 14/10/2015 15/10/2015 15/10/2015 15/10/2015 15/10/2015 15/10/2015 16/10/2015 16/10/2015 16/10/2015 16/10/2015 16/10/2015 16/10/2015 16/10/2015 9:37:00 9:42:30 13:55:35 16:28:57 17:13:58 10:37:11 12:04:20 14:37:04 11:44:00 13:17:04 15:50:17 17:07:43 17:11:44 17:14:59 17:18:00 17:28:54 10:06:01 12:26:28 15:20:58 16:02:58 16:06:54 11:35:02 11:51:00 16:25:24 16:30:13 16:39:07 16:49:47 17:06:13 8:46:36 8:54:10 9:07:20 10:29:32 10:35:25 11:42:39 11:47:56 Test Type Protection Vegetation Vegetation Vegetation Vegetation Vegetation Vegetation Vegetation Vegetation Vegetation Vegetation Vegetation Ignition Ignition Ignition Ignition Ignition Ignition Vegetation Ignition Ignition Ignition Ignition Ignition Ignition Ignition Ignition Ignition Vegetation Ignition Ignition Vegetation Ignition Ignition Ignition Ignition © Marxsen Consulting Pty Ltd GFN4 GFN4 GFN4 GFN4 GFN4 NER GFN4 GFN4 GFN4 NER GFN4 GFN4 GFN4 GFN4 GFN4 NER GFN4 GFN4 GFN4 GFN4 GFN4 NER GFN4 NER NER GFN4 GFN4 GFN4 NER GFN4 GFN4 NER GFN4 NER GFN4 Compe nsation RCC RCC RCC RCC RCC NIL RCC RCC RCC NIL RCC RCC RCC RCC RCC NIL RCC RCC RCC RCC RCC NIL RCC NIL NIL RCC RCC RCC NIL RCC RCC NIL RCC NIL RCC DAQ Notes Willow branch. Phase to earth. Not valid test. Not a valid test. Branch fell off. Invalid test. Sample was tied. Sample fell offf. Ivalid test. Branch fell off. Invalid test. Sample broke in half. Not a valid test. ACR tripped. No GEN3i data. Not a valid test. Sample fell off. Invalid test. Willow sample. Invalid test because GFN detection sensitivity was 15V, instead of 40V. Desert ash branch. Same branch as test 762. Not a valid test. Current span = 5A. Flashover. GFN didn't perform FCT and released fault. GFN malfunction? 248° ember. Not a valid test. Setting up ignition tests. Not a valid test. Not a valid test. Arm fall time = 12.579s. Not a valid test. Arm fall time = 12.579s. Not a valid test. Same bed as 779. Invalid test. GFN didn't find fault. GoPro video says 773. IR camera span was on <120°. Willow branch. Nearly flashover at ~1.14A. Arm lifted at 62s mark. No fire untill that point. RCC miscalibrated by 65V. GFN detection sensitivity set to 15V. Same bed. Not a valid test. RCC miscalibrated by 130V. Wet soil bed. Demo test. Not valid. Used soil bed. Demo test. Not valid. Arm timing test. Arm fall time =12579ms. Dry bed New bed. 100A current span. 100A current span. GFN setting was still at elevated residual. Rehearse vegetation test Practice test 1 Practice test 2 Practice test 3 Test for media 1 Test for media 2 Repeat test 1 for media Repeat test 2 for media Документ1 Friday, 4 December 2015 P a g e | 130 15.2 Appendix B: HRL Technology REFCL Trial report © Marxsen Consulting Pty Ltd Документ1 Friday, 4 December 2015