STORM WATER POLLUTION PREVENTION PLAN (SWPPP)
FOR
CONSTRUCTION ACTIVITIES
CALIFORNIA 2009-0009-DWQ
CONSTRUCTION GENERAL PERMIT
AS AMENDED BY 2012-0006-DWQ
PROJECT TITLE
Project Street Address
City, St. Zip
WDID#___________
Risk Level 1 Project
PREPARED BY
ADD LOGO
DATE: Month Day, Year
REVISED:
Owner/Legally Responsible Person
North County Transit District
Peykan Abbassi, Chief Development Officer
810 Mission Avenue
Oceanside, CA92054
760.966.6684
pabbassi@nctd.org
Qualified SWPPP Developer
Company Name
Full Name
Street Address
City, St. Zip
Phone number
Email address (bold)
SWPPP Preparation Date:
Month Day, Year
Estimated Construction Dates:
Construction Start Date: Month Day, Year Construction Completion Date: Month Day, Year
TABLE OF CONTENTS
1
SWPPP REQUIREMENTS ................................................................................................................... 1
1.1
1.2
1.3
1.4
1.5
1.6
1.7
1.8
1.9
1.10
2
PROJECT AND SITE INFORMATION ................................................................................................. 9
2.1
2.2
2.3
2.4
2.5
2.6
3
Effluent Standards ................................................................................................................... 20
Good Site Management Housekeeping .................................................................................. 20
Non-Storm Water Management.............................................................................................. 22
Erosion Control ........................................................................................................................ 22
Sediment Controls ................................................................................................................... 22
Run-on and Run-off Controls................................................................................................... 22
BEST MANAGEMENT PRACTICES ................................................................................................. 23
4.1
4.2
4.3
5
Project and Site Information ...................................................................................................... 9
2.1.1 Vicinity Map ................................................................................................................ 11
Storm Water Run-On from Offsite Areas ................................................................................. 12
Findings of the Construction Site Sediment and Receiving Water Risk Determination .......... 12
Construction Schedule ............................................................................................................ 12
Potential Construction Site Pollutant Sources ......................................................................... 12
2.5.1 Potential Sources of Sediment ................................................................................... 13
2.5.2 Other Pollutants Sources............................................................................................ 13
Identification of Non Storm Water Discharges ........................................................................ 16
2.6.1 Expected Non-Storm Water Discharges and Controls ............................................... 17
RISK LEVEL 1 SPECIFIC PROJECT REQUIREMENTS .................................................................. 20
3.1
3.2
3.3
3.4
3.5
3.6
4
Introduction ................................................................................................................................ 1
Certifications .............................................................................................................................. 2
1.2.1 Legally Responsible Person ......................................................................................... 2
1.2.2 Approved Signatory Certification .................................................................................. 2
1.2.3 Certifications by Qualified SWPPP Developer ............................................................. 3
1.2.4 Qualified SWPPP Practitioner ...................................................................................... 4
Permit Registration Documents (PRDs) .................................................................................... 5
SWPPP Availability and Implementation ................................................................................... 5
SWPPP Amendments ............................................................................................................... 5
Retention of Records ................................................................................................................. 6
Required Non-Compliance Reporting ....................................................................................... 6
Annual Report ............................................................................................................................ 6
Changes to Permit Coverage .................................................................................................... 7
Notice of Termination ................................................................................................................ 7
Erosion and Sediment Control................................................................................................. 23
4.1.1 Erosion Control BMPs ................................................................................................ 23
4.1.2 Sediment Control BMPs ............................................................................................. 24
4.1.3 Wind Erosion Control .................................................................................................. 25
4.1.4 Tracking Control ......................................................................................................... 26
BMP Implementation Specific for this Project for Non-Storm Water Management and
Material Management .............................................................................................................. 26
4.2.1 Non-Storm Water Management BMPs ....................................................................... 26
4.2.2 Waste Management and Materials Pollution Controls ............................................... 26
Post-Construction Storm Water Management Measures ........................................................ 28
4.3.1 Post-Construction Runoff Reduction .......................................................................... 30
BMP INSPECTION AND MAINTENANCE......................................................................................... 31
5.1
BMP Inspection and Maintenance ........................................................................................... 31
Storm Water Pollution Prevention Plan
iii
Project Title
6
TRAINING ........................................................................................................................................... 32
7
RESPONSIBLE PARTIES AND OPERATORS ................................................................................. 34
7.1
7.2
8
Responsible Parties ................................................................................................................. 34
Contractor List ......................................................................................................................... 34
CONSTRUCTION SITE MONITORING PROGRAM (CSMP) ............................................................ 35
8.1
8.2
8.3
Introduction .............................................................................................................................. 35
8.1.1 Visual Monitoring, Inspection, and Sample Collection Requirements ........................ 35
8.1.2 Visual Monitoring, Inspection, and Sample Collection Locations ............................... 36
8.1.3 General Provisions ..................................................................................................... 38
Visual Monitoring, Inspections, and Recording Methods ........................................................ 38
8.2.1 Weekly BMP Inspection .............................................................................................. 38
8.2.2 Quarterly Non-Storm Water Inspection ...................................................................... 39
8.2.3 Pre-Storm, During Storm, and Post-Storm Inspection ............................................... 39
Sampling Collection and Recording Methods ......................................................................... 40
8.3.1 Sampling Methods ...................................................................................................... 40
8.3.2 Non-Visible Pollutant Sampling .................................................................................. 41
LIST OF FIGURES
Figure 1: Vicinity Map .................................................................................................................................. 11
LIST OF TABLES
Table 1: Potential Sources of Sediment from Construction Activities ......................................................... 13
Table 2: Construction Activity, Associated Pollutants, and Equipment ...................................................... 13
Table 3: Potential Construction Site Pollutants ........................................................................................... 14
Table 4: Summary of Visual Monitoring, Inspection, and Sample Collection Requirements ...................... 36
Table 5: Summary of Potential Non-Visible Pollutants ............................................................................... 41
Storm Water Pollution Prevention Plan
iv
Project Title
APPENDICES
APPENDIX A: CONSTRUCTION GENERAL PERMIT DOCUMENTS
A-1: Construction General Permit Order No. 2009-0009-DWQ
A-2: Amendment Order No. 2012-0006-DWQ
APPENDIX B: SUBMITTED PERMIT REGISTRATION DOCUMENTS (PRDs)
B-1: Notice of Intent (NOl)
B-2: Risk Assessment (Construction Site Sediment and Receiving Water Risk Determination)
B-3: SWPPP Map(s)
APPENDIX C: SWPPP AMENDMENT LOG
APPENDIX D: SUBMITTED CHANGES TO PRDS (DUE TO CHANGE IN OWNERSHIP, CONTACTS,
OR ACREAGE)
APPENDIX E: CONSTRUCTION SCHEDULE
APPENDIX F: CASQA BMP HANDBOOK FACT SHEETS
APPENDIX G: CONSTRUCTION SITE MONITORING PROGRAM DOCUMENTS
G-1: CSMP Checklist
G-2: Discharge Sampling Report
G-3: Exemption Records
G-4: CSMP Locations Map
APPENDIX H: CERTIFICATIONS AND QSP TRAINING LOG
APPENDIX I:
RESPONSIBLE PARTIES
APPENDIX J:
CONTRACTORS AND SUBCONTRACTORS
APPENDIX K: CHAIN OF CUSTODY AND ANALYTICAL RESULTS
Storm Water Pollution Prevention Plan
v
Project Title
LIST OF ACRONYMS
BAT - Best Available Technology Economically Achievable
BCT - Best Conventional Pollutant Control Technology
BMP - Best Management Practices
BOD - Biochemical Oxygen Demand
CFR - Code of Federal Regulations
CGP - NPDES General Permit for Storm Water Discharges Associated with Construction Activities
COC - Chain of Custody
CPESC - Certified Professional in Erosion and Sediment Control
CPSWQ - Certified Professional in Storm Water Quality
CSMP - Construction Site Monitoring Program
CWA - Clean Water Act
DWQ - Division of Water Quality
EPA - Environmental Protection Agency
LRP - Legally Responsible Person
LUP - Linear Underground/Overhead Projects
MRR - Monitoring and Reporting Requirements
MS4 - Municipal Separate Storm Sewer System
NAL - Numeric Action Level
NEL - Numeric Effluent Limitation
NICET - National Institute for Certification in Engineering Technologies
NOAA - National Oceanic and Atmospheric Administration
NOI - Notice of Intent
NOT - Notice of Termination
NPDES - National Pollutant Discharge Elimination System
NRCS - Natural Resources Conservation Service
NTU - Nephelometric Turbidity Units
O&M - Operation and Maintenance
PRDs - Permit Registration Documents
REAP - Rain Event Action Plan
RUSLE - Revised Universal Soil Loss Equation
RW - Receiving Water
RWQCB – Regional Water Quality Control Board
SMARTS - Storm Water Multi Application Reporting and Tracking System
SUSMP - Standard Urban Storm Water Mitigation Plan
SWMP - Storm Water Management Program
SWPPP - Storm Water Pollution Prevention Plan
SWRCB – State Water Resources Control Board
TMDL - Total Maximum Daily Load
WDID - Waste Discharge Identification Number
WQO - Water Quality Objective
Storm Water Pollution Prevention Plan
vi
Project Title
1 SWPPP REQUIREMENTS
1.1
Introduction
This SWPPP is written for a project with coverage under the State Water Resources Control
Board Order No. 2009-0009-DWQ, General Permit No. CAS000002 and Amendment Order No.
2010-0014-DWQ as a Risk Level 1 project.
NCTD/Client organization/company Name will ensure that the SWPPP is developed and
amended or revised by a Qualified SWPPP Developer (QSD) to insure that:
1. All pollutants and their sources, including sources of sediment associated with
construction are controlled.
2. All non-storm water discharges are identified and either eliminated, controlled, or
treated.
3. Best Management Practices (BMPs) are effective and result in the reduction or
elimination of pollutants in storm water discharges and authorized non-storm water
discharges from the project site during construction.
4. Post-construction stabilization BMPs installed to reduce or eliminate pollutants are
effective and properly maintained.
Storm Water Pollution Prevention Plan
1
Project Title
1.2
Certifications
1.2.1
Legally Responsible Person
The Legally Responsible Person (LRP) for this project is listed below and shall be considered
the owner of this project.
North County Transit District
Peykan Abbassi, Chief Development Officer
810 Mission Avenue
Oceanside, CA92054
760.966.6684
pabbassi@nctd.org
1.2.2
Approved Signatory Certification
The Approved Signatory (AS) for this project is listed below and is legally authorized to sign and
certify Permit Registration Documents and all other Permit related documents on behalf of the
LRP through the Storm Water Multi-Application Reporting and Tracking System (SMARTS).
Approved Signatory Name
Title/Position
810 Mission Avenue
Oceanside, CA92054
Phone Number
Storm Water Pollution Prevention Plan
2
Project Title
1.2.3
Certifications by Qualified SWPPP Developer
Client organization/company Name will ensure that SWPPPs are written, amended and certified
by a Qualified SWPPP Developer (QSD).
Company Name
Developer Full Name, Title (e.g. Project Engineer)
Developer Street Address
City, State Zip
Phone Number
Qualifications: ______________(ex: California registered civil engineer – License No. XXXXX)
______________(ex: CPESC No. XXXX)
______________(ex: QSD No. XXX)
Date:
QSD Signature:
Print QSD Name: Full Name
QSD Title: Title (e.g. Project Engineer)
Storm Water Pollution Prevention Plan
3
Project Title
1.2.4
Qualified SWPPP Practitioner
Client organization/company name will ensure that all BMPs required by this General Permit are
implemented by a Qualified SWPPP Practitioner (QSP). The QSP is responsible for non-storm
water and storm water visual observations, sampling and analysis (as required), and for
ensuring full compliance with the permit and implementation of all elements of the SWPPP.
A QSP may delegate any or all of the activities associated with their responsibilities to a
designee who has received project specific SWPPP training to perform the task(s)
appropriately, but the QSP shall ensure adequate deployment. A list of name(s), address(es),
and telephone number(s) of the person(s) trained by the QSP for SWPPP management and
implementation, water pollution control, and Permit compliance during construction, shall be
provided and included in Appendix I: Responsible Parties. Documentation of all training for
individuals responsible for activities associated with compliance with this General Permit (formal
and informal) shall be documented and included in Appendix H.
The QSP for the project is listed below and shall be considered the initial contact for all storm
water related issues.
Company Name
Practitioner Full Name, Title (e.g. Project Engineer)
Practitioner Street Address
City, State Zip
Phone Number
Qualifications: ______________(ex: California registered civil engineer – License No. XXXXX)
______________(ex: CPESC No. XXXX)
Qualifications and documentation of the QSP are included in Appendix H.
Specific responsibilities of the QSP are as follows:
1. Implement prompt and effective erosion and sediment control measures.
2. Implement all non-storm water management and materials and waste management
activities such as: monitoring discharges; maintaining consistent overall general site
clean-up; making sure vehicle and equipment cleaning, fueling, and maintenance areas
are properly maintained; ensuring adequate on-site spill control materials and
equipment; ensuring that no materials other than storm water are discharged such that
they will not have an adverse effect on receiving waters or storm drain systems; and
preventing any other unauthorized discharges.
3. Ensure proper maintenance of BMPs and ensure immediate repairs to BMPs, as
needed.
4. Conduct or oversee routine storm water and non-storm water inspections, as required.
5. Conduct or oversee pre-storm inspections.
6. Conduct or oversee storm event inspections.
7. Conduct or oversee post-storm inspections.
Storm Water Pollution Prevention Plan
4
Project Title
8. Evaluate and initiate updates and amendments to the SWPPP based on field
inspections and scope of work. Document and coordinate amendments with the QSD.
9. Ensure submittal of the annual report and all supporting documentation to State Water
Resources Control Board (SWRCB) via SMARTS by September 1 of each year.
10. Submit in a timely fashion any and all Notices of Discharge and reports of Illicit
Connections or Illegal Discharges to the San Diego Regional Water Quality Control
Board (RWQCB).
1.3
Permit Registration Documents (PRDs)
PRDs will be filed electronically to the SWRCB via SMARTS by the LRP or Approved Signatory
no later than 7 days prior to the commencement of construction activities. Permit coverage shall
not commence until the PRDs and the annual fee are received by the SWRCB, and a Waste
Discharge Identification Number (WDID) number is assigned and sent by SMARTS.
The following PRDs are contained in Appendix B of this SWPPP:
1. Notice of Intent (NOI)
2. Risk Assessment (Construction Site Sediment and Receiving Water Risk Determination)
3. SWPPP Map
PRDs must be updated to reflect changes in ownership, contact information, construction
duration, or project acreage. These updated documents must be submitted through SMARTS
and included in Appendix D. This SWPPP is also required to be filed electronically and has been
submitted to the SWRCB as a PRD.
1.4
SWPPP Availability and Implementation
The General Permit (Section XIV.C) requires the SWPPP be available at the construction site
during working hours while construction is occurring and shall be made available upon request
by a State or Municipal inspector. When the original SWPPP is retained by a crewmember in a
construction vehicle and is not currently at the construction site, current copies of the BMPs and
map/drawings will be left with the field crew and the original SWPPP shall be made available via
a request by radio/telephone. The SWPPP will be implemented concurrently with the start
of ground disturbing activities.
1.5
SWPPP Amendments
The General Permit requires that SWPPP be amended or revised by a QSD (Section XIV.A)
and that the SWPPP include a listing of the date of initial preparation and the date of each
amendment. Amendments must be signed by a QSD (Section VII.B.6). It is recommended that
all amendments be dated, logged on the Amendment Log, and placed in Appendix C of the
SWPPP.
The SWPPP must be revised or modified:

To reflect modifications to storm water control measures made in response to a change
in design, construction, operation, or maintenance at the construction site that has or
could have a significant effect on the discharge of pollutants to the waters of the United
States that has not been previously addressed in the SWPPP.
Storm Water Pollution Prevention Plan
5
Project Title

If during inspections or investigations by site staff, or by local, state, tribal or federal
officials, it is determined that the existing storm water controls are ineffective in
eliminating or significantly minimizing pollutants in storm water discharges from the
construction site.

Based on the results of an inspection, as necessary to properly document additional or
modified BMPs designed to correct problems identified. Revisions to the SWPPP must
be completed in a timely manner.
Amendments to the SWPPP will be prepared and certified by the QSD; documented on the
SWPPP amendment form; and tracked on the amendment log. Fill out the forms completely;
document the reason for the amendment and how it modifies current conditions. Cross out the
old information in the SWPPP that is being amended and note the amendment number that
replaces the information next to the item.
1.6
Retention of Records
The General Permit (Sections I.J.69 and IV.G) requires that all dischargers maintain a paper or
electronic copy of all required records for three years from the date generated or date
submitted, whichever is last. These records must be available at the construction site until
construction is completed. Client organization/company Name will furnish the RWQCB,
SWRCB, or US Environmental Protection Agency (EPA), within a reasonable time, any
requested information to determine compliance with this General Permit. State in the SWPPP
where documents will be kept and how these requirements will be met. RWQCBs may require
records to be retained for longer periods.
1.7
Required Non-Compliance Reporting
Client organization/company Name will give advance notice to the RWQCB and local storm
water management agency of any planned changes in construction activity, which may result in
noncompliance with the General Permit requirements.
The General Permit identifies several areas of non-compliance reporting. It is the responsibility
of the permittee to properly document reportable discharges or other violations of the General
Permit. Exceedances and violations will be reported using the SMARTS system and will include
the following:
1.8

Self-reporting of any discharge violations or to comply with RWQCB enforcement
actions.

Discharges which contain a hazardous substance in excess of reportable quantities
established in 40 CFR §§ 117.3 and 302.4 unless a separate National Pollutant
Discharge Elimination (NPDES) Permit has been issued to regulate those discharges.
Annual Report
Each permittee will prepare, certify, and electronically submit an Annual Report via SMARTS no
later than September 1 of each year. An Annual Report is required of projects that are enrolled
for more than one continuous three-month period during the year. Reporting requirements are
identified in Section XVI of the General Permit and include providing a summary of:
1.
A summary and evaluation of all sampling and analysis results, including copies of
laboratory reports.
Storm Water Pollution Prevention Plan
6
Project Title
2.
The analytical method(s), method report unit(s), and method detection limit(s) of each
analytical parameter (analytical results that are less than the method detection limit shall
be reported as “less than the method detection limit”).
3.
A summary of all corrective actions taken during the compliance year.
4.
Identification of any compliance activities or corrective actions that were not
implemented.
5.
A summary of all violations of the General Permit.
6.
The names of individual(s) who performed the facility inspections, sampling, visual
observation (inspections), and/or measurements.
7.
The date, place, time of facility inspections, sampling, visual observation (inspections,
and/or measurements, including precipitation (rain gauge).
8.
Documentation of all training for individuals responsible for all activities associated with
compliance with this General Permit.
9.
Documentation of all training for individuals responsible for BMP installation, inspection,
maintenance, and repair.
10.
Documentation of all training for individuals responsible for overseeing, revising, and
amending the SWPPP.
1.9
Changes to Permit Coverage
The General Permit (Section II.C) allows a permittee to reduce or increase the total acreage
covered under the General Permit when a portion of the project is complete and/or conditions
for termination of coverage have been met; when ownership of a portion of the project is sold to
a different entity; or when new acreage is added to the project.
To change the project acreage, the permittee will electronically file changes to the PRDs using
SMARTS. These revisions include updated site information, a modified SWPPP map, and other
appropriate SWPPP updates. All updated PRDs should be included in Appendix D. In addition,
the landowner of the removed acreage will be notified of the applicable requirements for
obtaining permit coverage and new landowner information (including name, address, phone
number, and email address) will be documented and included in the SWPPP.
1.10
Notice of Termination
To terminate coverage under the General Permit, the permittee will first submit a final Annual
Report and then a Notice of Termination (NOT) electronically via SMARTS. Photos are
required to be submitted with the NOT. Filing an NOT certifies that all General Permit
requirements have been met. The NOT is submitted when the construction project is complete
and within 90 days of meeting all General Permit requirements for termination and final
stabilization (Section II.D). Requirements include:

The site will not pose any additional sediment discharge risk than it did prior to
construction activity.

All construction related equipment, materials and any temporary BMPs no longer
needed are removed from the site.
Storm Water Pollution Prevention Plan
7
Project Title

Post-construction storm water management measures are installed and a long-term
maintenance plan that is designed for a minimum of five years has been developed.
The NOT must demonstrate that the project meets all of the requirements of Section II.D.1 of
the General Permit by one of the following methods:

Photo Documentation: 70% final cover method (no computational proof required)

Revised Universal Soil Loss Equation: RUSLE/RUSLE2 method (computational proof
required)

Results of Testing and Analysis: Custom method (discharger demonstrates that site
complies with final stabilization)
Storm Water Pollution Prevention Plan
8
Project Title
2 PROJECT AND SITE INFORMATION
2.1
Project and Site Information
Project Name is located in the City of ______. Like most regions of Southern California, City
Name has a Mediterranean climate with hot, dry summers and cool winters. City Name has an
annual rainfall of xx – xx inches, with most precipitation falling in the months between ______
and _________.
The Project Name site is direction (e.g. west) of adjacent street name and direction (e.g. north)
of other adjacent street name (see Figure 1 - Vicinity Map included in Section 2.1.1). The project
site currently consists of ________(ex: mass graded pads). Client organization/company Name
proposes to develop ________ (ex: parcels XX), for _________ (ex: industrial use). Additional
Info (ex: extension of existing maintenance yard). All work is expected to be completed by
Month, Year. Detailed SWPPP Map drawings are located in Appendix B.
This project is located in the __________ Watershed. It drains to the main reach of
the___________(ex: San Luis Rey River) . The river travels south and eventually discharges to
the__________(ex: Pacific Ocean) near the City of __________(ex: Oceanside).
Storm Water Pollution Prevention Plan
9
Project Title
Project Information Summary
Project/Site Name: ___________
Project Street/Location: ________ (Ex: NW Corner of Mission Avenue and Myers Street)
Project Acreage: xx.xx
City: __________
State: California
ZIP Code: xxxxx
County: San Diego
Latitude: xx.xxxxxx Longitude: -xxx.xxxxxx Regional Board: San Diego
WDID: x xxxxxxxx
Are storm water discharges from the Site subject to post construction requirements from the
Phase II MS4 Permit?
Yes No
If so, are post construction requirements addressed in this SWPPP Yes No
Description: A separate Water Quality Management Plan will address post construction water
quality management and BMPs.
Previous Land Use: ___________ ex: Open Space
Proposed Land Use: ___________ex: Industrial
Existing Site Impervious Area: xx.x acres
Existing Site Pervious Area: xx.x acres
Existing Runoff Coefficient: 0.xx
Proposed Site Impervious Area: xx.x acres
Proposed Site Pervious Area: xx.x acres
Proposed Runoff Coefficient: 0.xx
Are there any known contaminants on site from previous land uses or operations?
Yes
No
Description: None
This site must address all requirements of NCTD Storm Water
Yes No
Management Plan (SWMP) Post Construction Stormwater
section. .
If answering “NO” then Post Construction Run Off requirements are located in N/A
Receiving Water Information: San Luis Rey River
Does this project discharge to a water body listed as impaired due to
Sedimentation/Siltation or Turbidity pursuant to Clean Water Act, Section Yes No
Does the site drain into a water body with a sediment-related TMDL?
Yes
No
Does the disturbed area discharge to a water body with designated beneficial
uses of SPAWN & COLD & MIGRATORY? Yes No
This project is located in the __________ Watershed. It drains to the main reach of
the___________(ex: San Luis Rey River) . The river travels south and eventually discharges to
the__________(ex: Pacific Ocean) near the City of __________(ex: Oceanside). No sediment
TMDL has been developed for the___________(ex: San Luis Rey River). The project does not
drain to a sediment sensitive water body so it has a “Low” Receiving Water Risk.
Storm Water Pollution Prevention Plan
10
Project Title
2.1.1
Vicinity Map
Insert Image of Vicinity Map
Figure 1: Vicinity Map
Storm Water Pollution Prevention Plan
11
Project Title
2.2
Storm Water Run-On from Offsite Areas
The Construction General Storm Water Permit requires (Section XIV.A.4) that the SWPPP
address calculations and design details as well as BMP controls for site run-on.
The project site currently consists of …. The project will develop …. Current run-on and post
construction run-on will (not) change as a result of this project.
2.3
Findings of the Construction Site Sediment and Receiving Water Risk
Determination
A site risk analysis was conducted using the CGP’s Risk Determination Worksheet to determine
the Risk Level for this project.
Project location and schedule information was used to determine the R-factor, K-factor, and LSfactor components for the project.

The EPA’s Rainfall Erosivity Calculator tool to calculate the project R-factor. R = xxx.xx

The project K-factor was obtained using the []. K = xx.xx

The project LS-factor was obtained using the []. LS = x.xx
The project erosion estimate (R*K*LS) is xx.xx tons per acre, which translates to a “low” Site
Sediment Risk Factor.
The project site is located in the ___________Watershed. It drains to the ___________ which
flows to the ___________. None of the downstream receiving waterbodies are on the 303(d) list
or have a Total Maximum Daily Load (TMDL) for sediment. The project does not drain to a
sediment impaired water body; therefore, it has a “Low” Receiving Water Risk.
The combination of a “Low” Site Sediment Risk Factor and a “Low” Receiving Water Risk
results in a Risk Level 1 project.
The Risk Determination Worksheets are included in Appendix B.
2.4
Construction Schedule
Estimated Project Start Date: Month Day, Year
Estimated Project Completion Date: Month Day, Year
If the project completion date will need to be extended beyond the original end date, the Risk
Level will need to be recalculated.
The Contractor shall provide a detailed schedule for the ground disturbing and BMP installation
activities. Scheduled activities should include describe construction activities, and final
stabilization. A detailed construction schedule should be placed in Appendix E.
2.5
Potential Construction Site Pollutant Sources
A list of potential pollutants and their respective sources is located in the following sections. This
list should be used to identify any areas of the site where additional BMPs are necessary to
Storm Water Pollution Prevention Plan
12
Project Title
reduce or prevent pollutants in storm water discharges and authorized non-storm water
discharges. The list identifies non-visible pollutants which are known, or should be known, to
occur on the construction site. At a minimum, when developing BMPs, Client
organization/company Name will do the following:
1. Consider the quantity, physical characteristics (e.g., liquid, powder, solid), and locations
of each potential pollutant source handled, produced, stored, recycled, or disposed of at
the site.
2. Consider the degree to which pollutants associated with those materials may be
exposed to and mobilized by contact with storm water.
3. Consider the direct and indirect pathways that pollutants may be exposed to storm water
or authorized non-storm water discharges.
4. Conduct an assessment of past spills or leaks, non-storm water discharges, and
discharges from adjoining areas.
5. Ensure retention of sampling, visual observation, and inspection records.
6. Ensure effectiveness of existing BMPs to reduce or prevent pollutants in storm water
discharges and authorized non-storm water discharges.
2.5.1
Potential Sources of Sediment
Table 1: Potential Sources of Sediment from Construction Activities
Vehicle tracking
Grading operations
Exposed soils and slopes
Import/export operations
Utility excavation operations
Landscaping operations
Topsoil stripping and stockpiling
Fine grading of home sites
2.5.2
Other Pollutants Sources
Table 2: Construction Activity, Associated Pollutants, and Equipment
Activity Type
Pollutant
Visually
Observable
Soil Disturbance:
Clear & Grub
Remove and Re-compact
Fine Grading
Trenching
Stockpiling
Sediment and organics
Sediment
Sediment
Sediment
Sediment
Cloudy to opaque
Cloudy to opaque
Cloudy to opaque
Cloudy to opaque
Cloudy to opaque
Asphalt:
Street Construction
Street Improvements
Hydrocarbons
Hydrocarbons
Oily sheen
Oily sheen
Storm Water Pollution Prevention Plan
13
Project Title
Hydrocarbons
Visually
Observable
Oily sheen
pH
pH
pH
pH
pH
pH
pH
pH
Cloudy to Milky
Cloudy to Milky
Cloudy to Milky
Cloudy to Milky
Cloudy to Milky
Cloudy to Milky
Cloudy to Milky
Cloudy to Milky
Sawdust
Paint (when wet)
Gypsum/Joint Compound
Ceramic dust
Sawdust
PVC Glue (when wet)/Plastic
Copper/Plastic/Metals
Sheet metal/fiberglass wool
Containers/mulch/soil
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Activity Type
Pollutant
Street Demolition
Concrete Laden Liquid:
Curb & Gutter
Sidewalks
Foundations
Driveways
Medians
Stuccoing
Grouting
Concrete washouts/Clean up
General:
Framing
Painting
Dry Walling
Tiling
Cabinet Building/Installing
Plumbing
Wiring/Electrical Utilities
Heating/Air Conditioning
Landscaping
Equipment Type
Equipment Type
Backhoe loader(s)
Water truck(s)
Scraper(s)
Loader(s)
Bull dozer(s)
Motor-grader
Excavator(s) / Track hoe(s)
Dump trucks (10-wheel)
Belly/Bottom dumps (tractor/trailer)
Tractor: skip loader
Skid steer loaders (Bobcat)
Concrete delivery trucks
Portable concrete mixers
Compaction equipment
Fork & Rough-terrain lifts
Generator(s)
Concrete boom pumps
Concrete pumps
Asphalt planer / grinder
Asphalt paving machine
Street striping equipment
Building material delivery trucks
Personal cars and light trucks
Waste hauling trucks
Trencher(s)
Stucco/Plaster spray pumps
Spray paint equipment (airless)
Hole drilling rig
Check YES box on left if potential construction site pollutant applies to this site. Update as
necessary.
Table 3: Potential Construction Site Pollutants
YES
Material Type
Diesel Fuel
Visually
Observable
Pollutant
Petroleum distillates, naphthalene,
xylene
Storm Water Pollution Prevention Plan
14
Sheen/Stain
Typical Location
Staging area, pole
sites
Project Title
YES
Material Type
Visually
Observable
Pollutant
Gasoline
Benzene, toluene, xylene, MTBE
Sheen/Stain
Hydraulic Oil
Mineral oil, trace additives
Sheen/Stain
Engine Oil
Mineral oil, additives, combustion
byproducts
Sheen/Stain
Transmission
Oil
Mineral oil, trace additives
Sheen/Stain
Engine Coolant
Ethylene and propylene glycol, heavy
Green/red
metals
Grease
Petroleum hydrocarbons
Sheen/Stain
Kerosene
Petroleum hydrocarbons
Sheen/Stain
Fertilizer
Nitrogen, phosphorus
No
Pesticide
Herbicide
Water-insoluble chlorinated
hydrocarbons, organophosphates,
carbonates, and pyrethrums.
Chlorinated hydrocarbons,
organophosphates
Varies
Varies
Soil
Amendments
Nutrients, organic matter
No
Concrete (wet)
Fly cash, heavy metals, Portland
cement
White solid
Concrete coring
Turbidity and pH
slurry
Concrete
Turbidity and pH
sawing slurry
Aluminum calcium iron oxide, calcium
Cement
sulfate
Drywall joint
Pigment, vinyl acetate
compound
Grout
Silica sand, Portland cement
Paint
Ethylene glycol, titanium oxide, VOC
Sealers
Diacetone alcohol
White
powder
Colored
liquid
Block wall & Home
construction
Animal waste
Animal waste
Asphalt
Asphalt fumes, cutback asphalt,
Yes
Black
material
Creamy
white
Suds, foam,
froth
15
Pole foundations
Home construction
Yes
Storm Water Pollution Prevention Plan
Material storage
area
Material storage
area
White putty
Sanitary waste Human waste
Varied
Material storage
area
Gray
powder
Gray liquid
White/yellow
Glass Oxide, urea extended phenol
Staging area, pole
sites
Staging area, pole
sites
Staging area, pole
sites
Staging area, pole
sites
Staging area, pole
sites
Staging area, pole
sites
Staging area
Material storage
area
Home construction
& streets
Home construction
& streets
Home construction
& streets
Gray liquid
Adhesives
Curing
Compounds
Waste wash
water
Typical Location
Home construction
Home construction
& Streets
Home construction
Staging areas & all
construction areas
All areas
Streets
Home construction
& Streets
All areas
Project Title
YES
Material Type
Wood
Preservatives
Cleaning
Solvents
Sediment
Vegetation
Solid Waste
Pollutant
Arsenic
Perchloroethylene, methylene
chloride, TCE
Soil, Turbidity, dust
Organic matter
Floatable and blowable trash and
debris
Visually
Observable
Typical Location
Amber liquid
Home construction
Varies
Staging areas
Muddy
Yes
All areas
All areas
Yes
All areas
Home construction
& material storage
areas
Tile
Historic land
use
contaminants (if
applicable)
2.6
Identification of Non Storm Water Discharges
All efforts are to be made to minimize non-storm water discharges. On-site inspections will
include observations for non-storm water discharges. Activities that may result in discharges will
be monitored and controlled as needed.
Authorized non-storm water discharges include:

Discharges from fire-fighting activities.

Fire hydrant flushing.

Waters used to wash vehicles where detergents are not used.

Water used to control dust.

Potable water including uncontaminated water line flushing.

Routine external building wash down that does not use detergents.

Uncontaminated air conditioning or compressor condensate.

Uncontaminated ground water or spring water.

Foundation or footing drains where flows are not contaminated with process materials
such as solvents.

Uncontaminated excavation dewatering.

Landscape irrigation.
The discharge of non-storm water is authorized under the following conditions:

The discharge does not cause or contribute to a violation of any water quality standard.
Storm Water Pollution Prevention Plan
16
Project Title

The discharge does not violate any provision of the Construction General Storm Water
Permit.

The discharge is not prohibited by the applicable Basin Plan

The SWPPP includes and implements BMPs required by the General Permit to prevent
or reduce the contact of the non-storm water discharge with construction materials or
equipment

The discharge does not contain toxic constituents in toxic amounts or (other) significant
quantities of pollutants.

The sampling information is reported in the Annual Report.
If any of the above conditions are not satisfied, the discharge is not authorized by the General
Permit and not permitted by this SWPPP. Notify the RWQCB of any anticipated non-storm water
discharges not already authorized by the General Permit, the Phase II MS4 Permit, or another
NPDES permit, to determine whether a separate NPDES permit is necessary.
2.6.1
Expected Non-Storm Water Discharges and Controls
Allowable non-storm water discharges anticipated to be encountered in this project include the
following:
Fire Hydrant Flushing
In the event there is a need to flush the fire hydrant the person performing the operation will
ascertain from the owner, contractor of the water line, or, fire department that there are no
chemicals or other pollutants contained in the water. The flushed water will be diverted away
from disturbed soils and into the storm drain system via a paved surface or lined channel so that
erosion, scour and sediment laden discharges will be avoided. If chlorination is present, water
will be dechlorinated prior to discharge. Contractor will place gravel bag check dams in the
drainage swale to slow the velocity of the discharge. Contractor will verify that velocity
dissipaters are installed, maintained and functioning prior to the discharge. Contractor will
monitor discharged water and cease operations in the event sediment or other pollutants are
being discharged as a result of the fire hydrant flushing.
Responsible party: Underground contractor, water department, fire department
Waters to Control Dust
Dust control will be implemented via a small diameter (3/4" to 1") fire or garden hose or with a
water truck depending on the area being serviced when wind exceeds 15 MPH or when there is
visible dust generated from the site. Water to be used for dust suppression shall be nonchlorinated. Water will be sprayed to avoid any surface run off. Any discharges from the
property will be observed and operations ceased if levels of sediment in the discharge pose a
negative impact on the drainage system or receiving waters.
Responsible party: QSP & all trades are responsible to control dust for their operations.
Potable Water Including Uncontaminated Water Line Flushing
Storm Water Pollution Prevention Plan
17
Project Title
Domestic water lines will be flushed prior to completion. The owner or contractor of the water
line will confirm that there are no chemicals or other pollutants contained in the water. If water
supply is chlorinated, dechlorination steps will be taken prior to discharge, most likely using
dechlorination tablets. Most of the discharge will infiltrate into the ground due to the permeability
of existing soils. Any run off will be diverted away from disturbed soils and into the storm drain
system via a paved surface or lined channel so that erosion, scour and sediment laden
discharges will be avoided. Contractor will place gravel bag check dams in the drainage swale
to slow the velocity of the discharge. Contractor will verify that velocity dissipaters are installed,
maintained and functioning prior to the discharge. Contractor will monitor discharged water and
cease operations in the event sediment or other pollutants are being discharged as a result of
the uncontaminated water line flushing. Prior to discharge from the site, potable water must
be de-chlorinated.
Responsible party: Underground "wet" utility contractor
Routine external building wash downs without detergents
Building siding may be washed down prior to the application of paint.
The contractor will use the least amount of water possible to wash the buildings. Any residues
including calking or adhesives will be removed and properly disposed of prior to the wash down.
Contractor will use a spray nozzle that will shut off and stop the flow of water when not in use.
Contractor will inspect inlet protection to be sure it is in place and functional prior to wash down.
Sediment controls will be installed at the low end of the drainage swales in an area where it will
prevent the water from discharging directly into the inlets. Inlets will be in place and functional.
Responsible party: Painting contractor
Uncontaminated air conditioning or compressor condensate
The discharges from air conditioning condensate is expected to be seasonal and at a minimum.
Waters will be diverted into the landscaped and permeable areas so as not to be discharged
into the storm drain system. The discharges will be monitored and if there is a chance of
discharge to the storm drain system, BMPs will be installed to divert the water to a permeable
area.
Responsible party: QSP
Landscape Irrigation
Irrigation water will be sprayed on permeable surfaces only. Landscape irrigation areas will be
monitored to prevent over watering. Watering times and schedules will be adjusted in the event
there is surface run off from the irrigated areas.
Responsible party: QSP & Landscape and irrigation contractor.
Any changes in construction that will produce other allowable non-storm water discharges will
be identified. The SWPPP will be amended and the appropriate erosion and sediment controls
will be implemented.
Storm Water Pollution Prevention Plan
18
Project Title
Compliance with the General Permit does not relieve the project of other potentially applicable
discharge requirements of the various other plan requirements such as but not limited to the
Basin Plan, ASBS, the Phase II MS4 Permit, or adopted TMDL allocations.
Storm Water Pollution Prevention Plan
19
Project Title
3 RISK LEVEL 1 SPECIFIC PROJECT REQUIREMENTS
3.1
Effluent Standards
Client organization/company Name will comply with the narrative effluent standards (listed
below) for Risk Level 1 projects.
1. Storm water discharges and authorized non-storm water discharges regulated by this
General Permit shall not contain a hazardous substance equal to or in excess of
reportable quantities established in 40 C.F.R. §§ 117.3 and 302.4, unless a separate
NPDES Permit has been issued to regulate those discharges.
2. Dischargers shall minimize or prevent pollutants in storm water discharges and
authorized non-storm water discharges through the use of controls, structures, and
management practices that achieve BAT for toxic and non-conventional pollutants and
BCT for conventional pollutants.
Risk Level 1 dischargers are not subject to a numeric effluent standard.
3.2
Good Site Management Housekeeping
Client organization/company Name will implement good site management (i.e., "housekeeping")
measures for construction materials that could potentially be a threat to water quality if
discharged. At a minimum, the good housekeeping measures shall consist of the following:
1. Identify the products used and/or expected to be used and the end products that are
produced and/or expected to be produced. This does not include materials and
equipment that are designed to be outdoors and exposed to environmental conditions
(i.e. poles, equipment pads, cabinets, conductors, insulators, bricks, etc.).
2. Cover and berm loose stockpiled construction materials that are not actively being used
(i.e. soil, spoils, aggregate, fly-ash, stucco, hydrated lime, and others identified by the
QSP.). Inactive areas must be stabilized. Inactive areas are defined as stockpiled
materials or disturbed areas that are not scheduled to be re-disturbed for at least 14
days or have not been disturbed for 14 days. Note: with the onset of precipitation all
stockpile materials shall be protected.
3. Store chemicals in watertight containers with appropriate secondary containment to
prevent any spillage or leakage or in a storage shed providing complete enclosure.
4. Minimize exposure of construction materials to precipitation (not applicable to materials
designed to be outdoors and exposed to the environment).
5. Implement BMPs to control the off-site tracking of loose construction and landscape
materials.
Client organization/company Name will implement good housekeeping measures for waste
management, which at a minimum shall consist of the following:
1. Preventing disposal of any rinse or wash waters or materials on impervious or pervious
site surfaces or into the storm drain system.
Storm Water Pollution Prevention Plan
20
Project Title
2. Ensuring the containment of sanitation facilities (e.g., portable toilets) to prevent
discharges of pollutants to the soil, storm water drainage system, or receiving water. All
sanitation facilities must have secondary containment.
3. Cleaning or replacing sanitation facilities and inspecting them regularly for leaks and
spills.
4. Covering waste and recycling disposal containers at the end of every business day and
prior to a rain event. Waste and recycling disposal containers include trash cans, trash
bins, and recycling bins.
5. Preventing discharges from waste disposal containers to the storm water drainage
system or receiving water. Containing and securely protecting stockpiled waste material
from wind and rain at all times unless actively being used.
6. Implementing procedures that effectively address hazardous and non-hazardous spills.
7. Developing a spill response and implementation procedure prior to commencement of
construction activities. To these ends, the SWPPP shall require that:

Equipment and materials for cleanup of spills shall be available on site and that
spills and leaks shall be cleaned up immediately and disposed of properly.

Appropriate spill response personnel are assigned and trained.
8. Ensuring the containment of concrete washout areas and other washout areas that may
contain additional pollutants to prevent discharge into the underlying soil and onto the
surrounding areas.
Client organization/company Name will implement good housekeeping for vehicle storage and
maintenance, which at a minimum, shall consist of the following:
1. Preventing oil, grease, or fuel from leaking into the ground, storm drains or surface
waters.
2. Implementing appropriate BMPs whenever equipment or vehicles are fueled,
maintained, or stored.
3. Cleaning leaks immediately and disposing of leaked materials properly.
Client organization/company Name will implement good housekeeping for landscape materials,
which at a minimum shall consist of the following:
1. Containing stockpiled materials such as mulches and topsoil when they are not actively
being used.
2. Containing fertilizers and other landscape materials when they are not actively being
used.
3. Discontinuing the application of any erodible landscape material at least 2 days before a
forecasted rain event (50 percent or greater chance of producing precipitation) or during
periods of precipitation.
4. Applying erodible landscape material at quantities and application rates according to the
manufacturer’s recommendations or based on written specifications by knowledgeable
and experienced field personnel.
Storm Water Pollution Prevention Plan
21
Project Title
5. Stacking erodible landscape material on pallets and covering or storing such materials
when not being used or applied.
Client organization/company Name will implement good housekeeping measures on the
construction site to control the air deposition of site materials and from site operations. Such
particulates can include, but are not limited to, sediment, nutrients, trash, metals, bacteria, oil
and grease and organics.
3.3
Non-Storm Water Management
Client organization/company Name will practice proper management of non-storm water by:
1. Implementing measures to control all non-storm water discharges during construction.
2. Washing vehicles in such a manner as to prevent non-storm water discharges to surface
waters or Municipal Separate Storm Sewer System (MS4) drainage systems.
3. Cleaning streets in such a manner as to prevent unauthorized non-storm water
discharges from reaching surface water or MS4 drainage systems.
3.4
Erosion Control
Client organization/company Name will practice proper and effective erosion control by:
1. Implementing effective wind erosion control.
2. Providing effective soil cover for inactive areas, all finished slopes, and utility backfill.
3. Limiting the use of plastic materials when more sustainable, environmentally friendly
alternatives exist. Where plastic materials are deemed necessary, Client
organization/company Name will consider the use of plastic materials resistant to solar
degradation.
3.5
Sediment Controls
Client organization/company Name will practice proper and effective sediment control by:
1. Establishing and maintain effective perimeter controls as needed, and implementing
effective BMPs for all construction entrances and exits to sufficiently control erosion and
sediment discharges from the site.
2. At minimum, designing sediment basins according to the guidance provided in California
Stormwater Quality Association (CASQA’s) Construction BMP Handbook on sites where
sediment basins are to be used.
3.6
Run-on and Run-off Controls
Client organization/company Name will effectively manage all run-on, all runoff within the site
and all runoff that discharges off the site. Run-on from off site shall be directed away from all
disturbed areas or shall collectively be in compliance with the effluent limitations in this General
Permit.
Storm Water Pollution Prevention Plan
22
Project Title
4 BEST MANAGEMENT PRACTICES
The LRP will be responsible for installing and maintaining BMPs throughout the duration of the
project. The QSP will inspect BMPs and provide recommendations for BMP installation and
maintenance. Copies of BMP fact sheets specific to this project are located in Appendix F of this
SWPPP.
4.1
Erosion and Sediment Control
4.1.1
Erosion Control BMPs
Erosion control, also referred to as soil stabilization, consists of source control measures that
are designed to prevent soil particles from detaching and becoming transported in storm water
runoff. Erosion control BMPs protects the soil surface by covering and/or binding soil particles.
This project will implement the following practices for effective erosion control:

EC-1: Scheduling
Proper scheduling of construction will be the most effective BMP associated with this
project. Client organization/company Name (and/or the Contractor) shall reduce the
discharge of pollutants from the site by scheduling activities in a manner that will limit
exposure of disturbed soil to wind, rain, and storm water run-on and runoff. Proper
attention to the construction schedule should be given as the rainy season nears or at
the onset of a rain event.

EC-2 Preservation of Existing Vegetation
The Contractor shall protect and preserve existing vegetation within the Project area as
long as practicable before removing. The Contractor shall preserve and protect existing
vegetation adjacent to all work areas. The protection and preservation of such
vegetation will serve to control erosion and filter out sediment.

EC-5: Soil Binders
Client organization/company Name (and/or the Contractor) shall reduce the discharge of
pollutants from the site by applying soil binders to disturbed soil surfaces that may be left
temporarily to prevent water and wind induced erosion of exposed soils.

EC-7: Geotextiles and Mats
Exposed, disturbed areas (stockpiles) shall be temporarily covered with plastic covers,
matting, or rolled erosion control products at the end of each day and prior to rain.
Where plastic materials are deemed necessary, the contractor shall use plastic materials
resistant to solar degradation.

EC-10: Velocity Dissipation Devices
Client organization/company Name (and/or the Contractor) shall install velocity
dissipation devices at the discharge points of the concrete swales to prevent erosion.
The velocity dissipation device shall conform to the rock rip-rap pad as specified in
design plans.

EC-16: Non-Vegetative Stabilization
Storm Water Pollution Prevention Plan
23
Project Title
Client organization/company Name (and/or the Contractor) shall stabilize the substation
by adding a three inch layer of 1”-2” crushed rock on the exposed soil area.

EC-11: Slope Drains
Sufficient erosion control materials, as detailed in Appendix F, will be maintained on site to allow
implementation, in conformance with General Permit requirements and as described in this
SWPPP. This includes implementation requirements for active areas and inactive areas that
require deployment before the onset of rain events.
4.1.2
Sediment Control BMPs
Sediment controls are structural measures that are intended to complement and enhance the
selected erosion control measures and reduce sediment discharges from active construction
areas. Sediment controls are designed to intercept and settle out soil particles that have been
detached and transported by the force of water. This project will implement the following
practices for effective sediment control:

SE-1: Silt Fence
Silt fences are a temporary sediment barrier consisting of woven geotextile stretched
across and attached to supporting posts, trenched-in, and supported with wire mesh
fence. The Contractor shall check periodically and make sure all silt fences are in place.
If the silt fence is ripped due to heavy sediment and or high wind intensity, one shall
replace immediately.
See Appendix B-3: SWPPP Map(s) for detailed placement of the Silt Fences.

SE-4: Check Dam
Check dams shall consist of gravel bags and be placed within the proposed concrete
swales located at the project site. Gravel bags shall be stacked one bag high, span the
entire with of the swale, and be spaced every 50 feet. Gravel bags which become
clogged with sediment or damaged will be replaced as directed by the QSP to ensure
the free flow of water. Sediment detained by the check dams shall be removed when the
sediment is 1/3 the height of the check dam or as directed by the QSP.

SE-5: Fiber Rolls
Client organization/company Name (and/or the Contractor) shall install fiber rolls along
the perimeter of the project area and as designated on the SWPPP Map. The fiber rolls
must extend to cover the entire disturbance area around the substation. Fiber rolls must
be trenched and backfilled into the ground 1/4 to 1/3 the thickness of the roll. Fiber rolls
shall be staked into the ground using wood stakes with a minimum length of 24 inches,
spaced at a maximum of 4 feet. If more than one fiber roll is placed in a row, the rolls
should be overlapped, not abutted. Once final stabilization of the site has been
completed the fiber rolls must be removed from the site. Sediment buildup behind the
fiber rolls shall be removed when it reaches 1/3 the height of the roll. Fiber rolls, which
become clogged with sediment or damaged, will be replaced as necessary to ensure the
free flow of water.
Storm Water Pollution Prevention Plan
24
Project Title

SE-6: Gravel Bag Berm
Gravel bag berms shall be used in place of fiber rolls on impervious surfaces. Approval
from the QSP must be obtained prior to implementation. Gravel bags shall be stacked
two (2) bags high. Client organization/company Name (and/or the Contractor) shall
remove this sediment periodically, and especially after heavy rains. Gravel bags, which
become clogged with sediment, shall be replaced as necessary to ensure the free flow
of water. Sediment detained by the check dams shall be removed when the sediment is
1/3 the height of the check dam or as directed by the QSP.

SE-7: Street Sweeping and Vacuuming
Client organization/company Name (and/or the Contractor) shall inspect all construction
access points daily for sediment track out. Sediment track out onto paved surfaces must
be swept clean per the standards identified in CASQA BMP Fact Sheet SE-7. If hand
sweeping cannot maintain clean roadways then a street sweeper will be used.

SE-10: Storm Drain Inlet Protection
Sufficient quantities of temporary sediment control materials, as detailed in Appendix F, will be
maintained on-site throughout the duration of the project to allow implementation of temporary
sediment controls in the event of predicted rain and for rapid response to failures or
emergencies, in conformance with other Permit requirements and as described in this SWPPP.
This includes implementation requirements for active areas and non-active areas before the
onset of rain.
All BMP materials shall be certified weed free in an effort to control the spread of noxious
weeds.
4.1.3
Wind Erosion Control
Wind erosion control consists of applying water or other dust palliatives to prevent or minimize
dust nuisance. This project will implement the following practices for effective wind erosion
control:

WE-1: Wind Erosion Control
This BMP, along with NS-1 – Water Conservation Practices, will be implemented to
provide Dust Control and prevent discharges from dust control activities and water
supply equipment. Water will be applied to disturbed soil areas of the project to control
dust. Water equipment leaks will be repaired immediately. Water application rates will
be minimized, as necessary, to prevent runoff and ponding.
Water trucks and/or a portable tank shall be made available to the field crews (if needed)
with an adequate supply of non-chlorinated water to be used as necessary to mitigate
the generation of airborne dust particulates from the construction sites. Water used for
dust control will be applied in such a manner to minimize runoff from the site.
Water trucks and/or a portable tank shall be made available to the field crews with an adequate
supply of non-chlorinated water to be used as necessary to mitigate the generation of airborne
dust particulates from the construction sites. Water used for dust control will be applied in such
a manner to minimize runoff from the site.
Storm Water Pollution Prevention Plan
25
Project Title
4.1.4
Tracking Control
Tracking control consists of preventing or reducing the tracking of sediment off-site by vehicles
leaving the construction area. This project will implement the following practices for tracking
control:

TC-1: Stabilized Construction Entrance/Exit
Client organization/company Name (and/or the Contractor) shall install a stabilized
construction entrance at the point of entrance/exit of the construction site to reduce the
tracking of mud and dirt onto public roads by construction vehicles. Design of
construction entrance shall follow the standard set out in the BMP Fact Sheet TC-1.

TC-2: Stabilized Construction Roadway
The Contractor shall locate and stabilize a construction roadway prior to start of the
project. A stabilized construction roadway is used for onsite vehicle transportation routes
such as access roads, subdivision roads, and parking areas and should be frequently
maintained to prevent erosion and control dust.

SE-7: Street Sweeping and Vacuuming
Client organization/company Name (and/or the Contractor) shall inspect all construction
access points daily for sediment track out. Sediment track out onto paved surfaces must
be swept clean daily and as needed.
4.2
BMP Implementation Specific for this Project for Non-Storm Water
Management and Material Management
4.2.1
Non-Storm Water Management BMPs
Non-storm water management BMPs are source control BMPs that prevent pollution at their
source by limiting or reducing potential pollutants at their source or eliminating off-site
discharge. These practices involve day-to-day operations of the construction site and are
usually under the control of the contractor. These BMPs are also referred to as “good
housekeeping practices” which involve keeping a clean, orderly construction site. This project
will implement the following practices for effective non-storm water management controls:

NS-1: Water Conservation Practices
The Contractor shall use water in a manner, which will not cause erosion or transport
pollutants off-site. Water application rates will be minimized as necessary to prevent
runoff and ponding. Water equipment leaks will be repaired immediately.

NS-3: Paving and Grinding Operations
The Contractor is responsible for preventing or reducing the discharge of pollutants from
paving operations, using measures to prevent run on and runoff pollution, properly
disposing of wastes, and scheduling paving around rain events. Materials for paving
should be stored away from drainage courses and BMPs installed to divert runoff or to
trap and filter sediment. Contractors are responsible for proper disposal of Portland
cement concrete and asphalt concrete in conformance with WM-8, Concrete Waste
Management.
Storm Water Pollution Prevention Plan
26
Project Title

NS-6: Illicit Connection/Discharge
Illicit connection/discharge and reporting is applicable anytime an illicit connection or
discharge is discovered or illegally dumped material is found on the Project site.

NS-9: Vehicle and Equipment Fueling
This BMP will be utilized to manage onsite cleaning activities. Temporary fueling area(s)
shall be field located by the QSP. Should locations change, or if additional fueling areas
are necessary, the QSP, or designated personnel, shall update the SWPPP Maps to
show their respective locations.
Fuel trucks, each equipped with absorbent spill clean-up materials, will be used for all
on-site fueling, whether at the temporary fueling area(s) or for mobile fueling elsewhere
on the site. All mobile fueling operations will be conducted at least 50 feet away from
storm drain inlets and drainage facilities and on a level graded area. All mobile fueling
shall be conducted on impervious surfaces and the use of drip pans shall be
implemented.

NS-10: Vehicle and Equipment Maintenance
Several types of vehicles and equipment will be used throughout the project, including
trucks and trailers, backhoes, field buggies, forklifts and generators. This BMP will be
utilized to prevent discharges of vehicle fluids during maintenance activities.
All vehicle maintenance will be conducted at least 50 feet away from drainage courses
and on a level graded area. The Contractor will place drip pans, plastic sheeting, or
absorbent material under vehicles and equipment while parked overnight, in storage,
and when requiring maintenance activities that involve grease, oil, solvents, or other
vehicle fluids.

NS-12: Concrete Curing
Concrete work shall NOT be scheduled during times of rain. A water tight concrete
washout, as described in BMP Fact Sheet NS-12, shall be brought on or constructed
and used on-site whenever concrete work is scheduled. Any concrete waste shall be
temporarily stored in the washout and hauled off site as soon as the washout is 75% full
or no longer needed. All concrete washouts must be located a minimum of 50 feet away
from drainage courses and on a level graded area.

NS-13: Concrete Finishing
Concrete work shall NOT be scheduled during times of rain. A water tight concrete
washout as described in BMP Fact Sheet NS-12 shall be brought on or constructed and
used on-site whenever concrete work is scheduled. Any concrete waste shall be
temporarily stored in the washout and hauled off site as soon as the washout is 75% full
or no longer needed. All concrete washouts must be located at a minimum of 50 feet
away from drainage courses and on a level graded area.
4.2.2
Waste Management and Materials Pollution Controls
Waste management and materials pollution control BMPs, like non-storm water management
BMPs, are source control BMPs that prevent pollution by limiting or reducing potential pollutants
Storm Water Pollution Prevention Plan
27
Project Title
at their source before they come in contact with storm water. These BMPs are also referred to
as “good housekeeping practices” which involve keeping a clean, orderly construction site.
Waste management consists of implementing procedural and structural BMPs for handling,
storing and disposing of wastes generated by a construction project to prevent the release of
waste materials into storm water runoff or discharges through proper management of the
following types of wastes: solid, sanitary, concrete, hazardous, and equipment-related washes.
This project will implement the following practices for effective waste management controls:

WM-1: Material Delivery and Storage
The Contractor shall utilize stabilized areas, as necessary, to prevent potential spills and
unnecessary tracking of sediment. Chemicals will be stored in watertight containers
equipped with secondary containment or stored inside a storage shed. Spill clean-up
materials, material safety data sheets, material inventory, and emergency contact
numbers will be maintained by the Contractor on-site.

WM-2: Material Use
See Material Delivery and Storage description above.

WM-3: Stockpile Management
Stockpiles will be located within the project site and must be shown on the SWPPP Map.
Stockpile Management will consist of the following:

o
Stockpiles must be located a minimum of 50 feet away from concentrated flows
of storm water and drainage courses.
o
Stockpiles require proper wind erosion control. See WE-1, Wind Erosion Control
for specifics of this BMP.
o
Stockpiles shall be covered and/or protected with perimeter sediment control at
the end of each day and prior to the onset of precipitation as described in BMP
EC-7, Geotextiles and Mats, in Section 4.1.1 above. QSP will provide direction
on this protection. Stockpiles may be required to be covered daily at the direction
of NCTD or the QSP.
WM-4: Spill Prevention and Control
The Contractor shall implement WM-4, Spill Prevention and Control, and the following
measures to address hazardous and non-hazardous spills at the project site.
o
Maintain equipment and spill clean-up materials available on-site, including, but
not limited to shovels, brooms, spills absorbent rags, and proper waste
containment (i.e. non-permeable, water proof spill containment bin). Waste
materials shall be labeled and disposed of properly in accordance with local,
state, and federal requirements.
o
Maintain Project-specific material safety data sheets, material inventory, and
emergency contact numbers on-site.
Storm Water Pollution Prevention Plan
28
Project Title
o

In the event of a leak or spill of hazardous substances used, stored, or generated
on-site, implement proper spill clean-up procedures to prevent pollutant
discharges to storm drain systems. Spills of oil, petroleum products, and
substances listed under 40 CFR parts 11, 117, and 302, and sanitary and septic
wastes shall be contained and cleaned up immediately.
WM-5: Solid Waste Management
Client organization/company Name (and/or the Contractor) shall implement this BMP
whenever wastes are generated, stockpiled, or removed from the project. These areas
shall be field located by the QSP. Due to potential windy conditions occurring at the
project site, trash shall be placed in waste containers equipped with functional lids.
Containers will be covered at all times unless actively used and during rain events.
Implementation of this BMP will minimize storm water contact with waste materials and
prevent waste discharges. Solid waste, including rubble stockpiles, shall be removed
and disposed of weekly at an authorized off-site facility.

WM-6: Hazardous Waste Management (if needed)
The Contractor shall implement this BMP to prevent or reduce the discharge of
hazardous materials to stormwater or watercourses. Contractor shall place hazardous
materials in a non-permeable, waterproof spill containment bin and provide training of
employees and subcontractors.

WM-7: Contaminated Soil Management (if needed)
The Project areas have no known history of contaminate soil or other impairments.
However, Contractor shall utilize contaminated soil management to address the
possibility of construction activities occurring near contaminated soils. Contractor shall
instruct employees to recognize evidence of contaminated soil such as buried debris,
discolored soil, and unusual odors.

WM-8: Concrete Waste Management
Temporary concrete washout facilities will be field located by the QSP. In the event this
area is relocated or additional areas are added, the QSP, or designated personnel, shall
update the Site Map to show respective locations. All washout facilities shall be brought
on or constructed and maintained in sufficient quantity and sized to contain all liquid and
concrete waste generated by washout operations and placed a minimum of 50 feet from
existing water courses, and apart from construction traffic areas. Concrete washout
facilities must be water tight. A sign shall be installed adjacent to the washout facility to
inform concrete equipment operators to utilize the proper facilities. The concrete
washout shall be emptied when it is 75 percent full.

WM-9: Sanitary/Septic Waste Management
The Contractor shall eliminate the discharge of construction sanitary/septic wastes. This
BMP is applicable to temporary and portable sanitary/septic systems on construction
sites and associated areas. Portable toilets will be field located and shown on the Site
Map. Should locations change, or if additional portable toilets are necessary, the QSP,
or designated personnel, shall update the Site Map. Weekly maintenance shall be
provided and wastes will be properly disposed of at appropriate offsite facilities. The
toilets shall be located a minimum of 50 feet away from concentrated flow paths and
Storm Water Pollution Prevention Plan
29
Project Title
shall be equipped with secondary containment trays and staked down to reduce the risk
of tipping.
4.3
Post-Construction Storm Water Management Measures
4.3.1
Post-Construction Runoff Reduction
The Project t Title is located in an area subject to a Phase 2 MS4 Permit approved Storm Water
Management Plan (SWMP). Post-construction requirements of the Phase II MS4 Permit are
effective July 1, 2015. Therefore, this project IS NOT required to meet the post-construction
runoff reduction measures specified in the General Permit. The post-construction measures in
the General Permit are required for projects that are not located in an area subject to a MS4
Permit approved SWMP.
Storm Water Pollution Prevention Plan
30
Project Title
5 BMP INSPECTION AND MAINTENANCE
5.1
BMP Inspection and Maintenance
Inspections of active construction areas will be conducted by the Site QSP or their qualified
designee who has received project specific SWPPP training as follows:

Weekly

Prior to a forecast storm event

After a rain event that causes runoff from the construction site

At 24-hour intervals during extended rain events.

Quarterly non-storm water visual inspections
Daily inspections will be performed by the QSP or a designee with appropriate training to verify
that the appropriate BMPs for storm water and non-storm water are being implemented in the
following construction site locations:

Areas where active construction is occurring (including staging areas)

Project excavations are closed, with properly protected spoils, and that road surfaces
are cleaned of excavated material and construction materials such as chemicals by
either removing or storing the material in protective storage containers at the end of
every construction day

Land areas disturbed during construction are returned to preconstruction conditions or
an equivalent protection is used at the end of each workday to eliminate or minimize
erosion and the possible discharge of sediment or other pollutants during a rain event.
If deficiencies are identified during BMP inspections, repairs or design changes to BMPs must
be initiated within 72 hours of identification and need to be completed as soon as possible.
Construction Site Monitoring Program (CSMP) Checklists, located in Appendix G-1, should be
utilized to assess the condition of site compliance. See Section 8, Construction Site Monitoring
Program, for guidance in filling out the CSMP Checklist. Completed checklists shall be kept in
Appendix G-1 of the SWPPP.
Storm Water Pollution Prevention Plan
31
Project Title
6 TRAINING
The General Permit requires (Section VII) that all elements of the SWPPP be developed by a
QSD and implemented by a QSP. The QSP may delegate tasks to trained employees provided
adequate supervision and oversight is provided.
Personnel at the site shall receive training appropriate for individual roles and responsibilities on
the project. Appropriate personnel shall receive training on SWPPP implementation, BMP
inspection and maintenance, and record keeping. Document all training activities (formal and
informal) in the QSP Training Log located in Appendix H. Training documentation must also be
submitted in the Annual Report.
Qualified SWPPP Developer - Client organization/company Name will ensure that SWPPPs are
written, amended and certified by a Qualified SWPPP Developer (QSD). A QSD shall have one
of the following registrations or certifications, and appropriate experience:

California registered professional civil engineer;

California registered professional geologist or engineering geologist;

California registered landscape architect;

Professional hydrologist registered through the American Institute of Hydrology;

Certified Professional in Erosion and Sediment Control (CPESC)™ registered through
Enviro Cert International, Inc.;

Certified Professional in Storm Water Quality (CPSWQ)™ registered through Enviro Cert
International, Inc.

Professional in erosion and sediment control registered through the National Institute for
Certification in Engineering Technologies (NICET);
Before performing construction activities, a QSD shall have attended a SWRCB-sponsored or
approved QSD training course. Client organization/company Name will list the name and
telephone number of the currently designated Qualified SWPPP Developer(s) in the SWPPP.
The designated Qualified SWPPP Developer is:
Name
Developer Full Name
Phone Number
______________
Qualification(s)
________ , ___________ , ____
Qualified SWPPP Practitioner - Client organization/company Name will ensure that all BMPs
required by this General Permit are implemented by a Qualified SWPPP Practitioner (QSP). A
QSP is a person responsible for non-storm water and storm water visual observations, sampling
and analysis. Effective two years from the date of adoption of this General Permit, a QSP shall
be either a QSD or have one of the following certifications:

Certified erosion, sediment and storm water inspector registered through Enviro Cert
International, Inc.
Storm Water Pollution Prevention Plan
32
Project Title

Certified inspector of sediment and erosion control registered through Certified Inspector
of Sediment and Erosion Control, Inc.
Before performing construction activities, a QSP shall have attended a SWRCB-sponsored or
approved QSP training course.
The designated Qualified SWPPP Practitioner(s) is(are):
Name
Practitioner Full Name
Phone Number
______________
Qualification
________
The QSP(s) identified above will provide direction to the following contractors, subcontractors,
superintendents and others as listed in Section 7.
Storm Water Pollution Prevention Plan
33
Project Title
7 RESPONSIBLE PARTIES AND OPERATORS
7.1
Responsible Parties
The discharger shall include, in the SWPPP, a list of all parties responsible for implementation
of the SWPPP. This list shall include telephone numbers, work addresses, and email
addresses. Specific areas of responsibility for each person shall also be included. This list is
included in Appendix I.
7.2
Contractor List
Client organization/company Name will include, in the SWPPP, a list of names of all contractors,
subcontractors, and individuals who will be directed by the Qualified SWPPP Practitioner. This
list shall include telephone numbers and work addresses. Specific areas of responsibility of
each subcontractor and emergency contact numbers shall also be included. This list is included
in Appendix J.
Storm Water Pollution Prevention Plan
34
Project Title
8 CONSTRUCTION SITE MONITORING PROGRAM (CSMP)
8.1
Introduction
This Construction Site Monitoring Program (CSMP) is a guide for the Client
organization/company Name QSP and/or qualified individual(s) supervised by the QSP for
monitoring and sampling procedures and instructions. This CSMP has been designed to meet
Risk Level 1 requirements for the project title.
The QSP is to determine whether BMPs included in the SWPPP are effective and if immediate
actions are needed and/or SWPPP revisions are necessary to reduce pollutants in storm water
and authorized non-storm water discharges. The QSP is responsible for implementing the
requirements of the CSMP from the commencement to the completion of construction activity.
Additionally, the QSP must ensure the site is stabilized after all construction activity has been
completed.
This CSMP was developed to address the following objectives:

To demonstrate that the site is in compliance with the Discharge Prohibitions of this
General Permit.

To determine whether non-visible pollutants are present at the construction site and are
causing or contributing to exceedances of water quality objectives.

To determine whether immediate corrective actions, additional Best Management
Practice (BMP) implementation, or SWPPP revisions are necessary to reduce pollutants
in storm water discharges and authorized non-storm water discharges.

To determine whether BMPs included in the SWPPP are effective in preventing or
reducing pollutants in storm water discharges and authorized non-storm water
discharges.
Revisions to the CSMP are the responsibility of Client organization/company Name and will be
performed when any of the following occur:

Site conditions or construction activities change such that a change in monitoring is
required to comply with the requirements and intent of the General Permit.

The RWQCB reviews the CSMP and requires revisions to be made.

The RWQCB requires additional CSMP requirements including sampling and analysis of
discharges to CWA § 303(d)-listed water bodies.
8.1.1
Visual Monitoring, Inspection, and Sample Collection Requirements
This CSMP requires routine and storm-related visual monitoring and inspections as well as
requisite, conditionally based sample collection for the construction site. All blank forms (CSMP
Checklist, Discharge Sampling Report, and Exemption Records) can be found in Appendix G.
Completed forms shall also be kept in Appendix G. Visual inspections and sample collection
shall be conducted per the following table:
Storm Water Pollution Prevention Plan
35
Project Title
Table 4: Summary of Visual Monitoring, Inspection, and Sample Collection Requirements
Action
Visual Monitoring, Inspections, and Recording
Form
BMP
Log
Type
Daily
BMP
Risk Level 1
Requirement
8.1.2
Sample Collection and Recording
CSMP Checklist
Discharge Sampling Report
Weekly
BMP
Quarterly
NonStormwater
PreStorm
During
Storm
PostStorm
X
X
X
X
X
Stormwater
Discharge
Receiving
Water
Non-Visible
Pollutants
X
Visual Monitoring, Inspection, and Sample Collection Locations
The visual monitoring, inspections, and sample collection requirements displayed in Table 5,
above, will be conducted at the locations identified in this section.
BMP Locations
BMP locations are shown on the SWPPP Map in Appendix B.
Drainage Areas
Drainage areas are shown on the CSMP Locations Map in Appendix G and described below.
Location
Name
Description
DA-1
Describe the location of the first drainage area.
DA-2
Describe the location of the second drainage area.
DA-3
Describe the location of the third drainage area.
…
…
Storm Water Storage and Containment Areas
Storm water storage and containment areas are shown on the CSMP Locations Map in
Appendix G and described below.
Location
Name
Description
SC-1
Describe the location of the first Storage and Containment Area.
SC-2
Describe the location of the second Storage and Containment Area.
SC-3
Describe the location of the third Storage and Containment Area.
…
…
Storm Water Pollution Prevention Plan
36
Project Title
Storm Water Discharge Points
Storm water discharge points are shown on the CSMP Locations Map in Appendix G and
described below.
Location
Name
DP-1
Description
Describe the location of the first Discharge Point.
DP-2
Describe the location of the second Discharge Point.
DP-3
Describe the location of the third Discharge Point.
…
…
Contaminated Non-Visible Pollutant Sampling Points
Contaminated non-visible pollutant sampling points are shown on the CSMP Locations Map in
Appendix G and described below.
Location
Name
Description
NV-1
Describe the location of the first Contaminated No-Visible Pollutant Sampling
Point.
NV-2
Describe the location of the first Contaminated No-Visible Pollutant Sampling
Point.
NV-3
Describe the location of the first Contaminated No-Visible Pollutant Sampling
Point.
…
…
Uncontaminated Non-Visible Pollutant Sampling Points
Uncontaminated non-visible pollutant sampling points are shown on the CSMP Locations Map
in Appendix G and described below.
Location
Name
Description
UNV-1
Describe the location of the first Uncontaminated No-Visible Pollutant Sampling
Point.
UNV-2
Describe the location of the first Uncontaminated No-Visible Pollutant Sampling
Point.
UNV-3
Describe the location of the first Uncontaminated No-Visible Pollutant Sampling
Point.
…
…
Storm Water Pollution Prevention Plan
37
Project Title
8.1.3
General Provisions

A qualifying rain event is defined in the CGP as a rain event producing ½ inch or more of
precipitation.

A minimum of 48 hours of dry weather will be used to distinguish between separate
qualifying rain events.

Visual monitoring, inspections, and sample collection are not required under the
following conditions:
o
During dangerous weather conditions such as flooding and electrical storms
o
Outside of scheduled site business hours.
If no required visual observations (inspections) or samples are collected due to these
exceptions, include a written explanation (Exemption Record) in Appendix G-3 of the
SWPPP and in the Annual Report. Each Exemption Record shall document the reasons
why the visual monitoring, inspection, and/or sample collection was not conducted.

8.2
All completed forms (CSMP Checklists, Discharge Sampling Reports, and Exemption
Records), and follow up actions shall be kept in the field copy of the SWPPP (Appendix
G) throughout the duration of construction and for at least 3 years after NOT has been
issued.
Visual Monitoring, Inspections, and Recording Methods
The following sections describe the tasks required for each of the visual monitoring and
inspections required in Section 8.1.1. The locations for each visual monitoring and inspection
are described in Section 8.1.2 and shown in the CSMP Locations Map in Appendix G. All
corrective actions shall be recorded as an attachment to the form on which they were identified.
If identified deficiencies require design changes, including additional BMPs, the implementation
of changes will be initiated within 72 hours of identification and be completed as soon as
possible. When design changes to BMPs are required, the SWPPP shall be amended to reflect
the changes.
8.2.1
Weekly BMP Inspection
Weekly inspections of all BMPs shall be conducted to:

Inspect all storm water drainage areas for the presence or absence of floating and
suspended materials, a sheen on the surface, discolorations, turbidity, odors, and
source(s) of any observed pollutants;

Identify any spills, leaks, or uncontrolled pollutant sources that have or may discharge
from the site;

Inspect all BMPs;

Identify all BMPs that need maintenance to operate effectively;
Storm Water Pollution Prevention Plan
38
Project Title

Identify all BMPs that have failed;

Identify all BMPs that could fail to operate as intended;

Identify the need for additional BMPs;

If needed implement appropriate corrective action items to repair all BMPs that need
maintenance or have failed (include updates in SWPPP); and

Inspect all locations of stored or contained storm water for the presence or absence of
floating and suspended materials, a sheen on the surface, discolorations, turbidity,
odors, and source(s) of any observed pollutants.
Weekly BMP inspections shall be recorded on the CSMP Checklist form. Weekly BMP
inspections shall be performed once during each week throughout the project. All corrective
action shall be recorded on the CSMP Checklist form or included as an attachment.
8.2.2
Quarterly Non-Storm Water Inspection
Quarterly inspections of each drainage area shall be conducted to:

Identify any presence or evidence of any non-storm water discharge for each drainage
area (authorized or unauthorized);

Record pollutant characteristics (floating and suspended material, sheen, discoloration,
turbidity, odor, etc.);

Identify source of discharge; and

If needed implement appropriate corrective action items to eliminate unauthorized nonstorm water discharges and to reduce or prevent pollutants from contacting non-storm
water discharges.
Quarterly BMP inspections shall be recorded on the CSMP Checklist form. Quarterly BMP
inspections shall be performed once during each quarter (January-March, April-June, JulySeptember, and October-December) throughout the project.
8.2.3
Pre-Storm, During Storm, and Post-Storm Inspection
Pre-storm, during storm, and post-storm inspections shall be conducted to:

Inspect all storm water drainage areas for the presence or absence of floating and
suspended materials, a sheen on the surface, discolorations, turbidity, odors, and
source(s) of any observed pollutants;

Identify any spills, leaks, or uncontrolled pollutant sources that have or may discharge
from the site;

Inspect all BMPs;

Identify all BMPs that need maintenance to operate effectively;

Identify all BMPs that have failed;

Identify all BMPs that could fail to operate as intended;
Storm Water Pollution Prevention Plan
39
Project Title

Identify the need for additional BMPs;

If needed implement appropriate corrective action items to repair all BMPs that need
maintenance or have failed (include updates in SWPPP); and

Inspect all locations of stored or contained storm water for the presence or absence of
floating and suspended materials, a sheen on the surface, discolorations, turbidity,
odors, and source(s) of any observed pollutants.
Pre-storm inspections shall be recorded on the CSMP Checklist form. Pre-storm inspections
shall be performed within 48-hours prior to a predicted rain event with a 50% or greater
probability of precipitation. The forecast shall be recorded from http://www.srh.noaa.gov/ and
included as an attachment to the CSMP Checklist form. All corrective action shall be recorded
on the CSMP Checklist form or included as an attachment.
During storm inspections shall be recorded on the CSMP Checklist form. During storm
inspections shall be performed each day that rainfall occurs within an extended rain event. This
applies to rain events which were predicted to have a 50% or greater probability of precipitation
or have accumulated at least ½ inch of rain. All corrective action shall be recorded on the CSMP
Checklist form or included as an attachment.
Post-storm inspections shall be recorded on the CSMP Checklist form. Post-storm inspections
shall be performed within 48-hours following the conclusion of a qualifying rain event. A
summary of precipitation for the entire qualifying rain event shall be included as an attachment
to the CSMP Checklist form. All corrective action shall be recorded on the CSMP Checklist form
or included as an attachment.
8.3
Sampling Collection and Recording Methods
8.3.1
Sampling Methods
The QSP shall be responsible for all sampling requirements. The QSP may designate and train
another person to perform the sampling. Any person, besides the QSP, that will perform
sampling should be listed below.
Type of Sampling
Non-Visible
Pollutant
Person to Perform Sampling
List person, default is QSP
Phone Number
###-###-####
All samples that require laboratory analysis should be take to TBD or a comparable lab. An
example Chain of Custody (COC) for TBD is included in Appendix K. Records of all COCs shall
be kept in Appendix K. Contact information for TBD is included below:
Insert Laboratory Name & Address
All sample collected must meet the following conditions:

Samples shall be taken at all applicable discharge points shown on the CSMP Locations
Map in Appendix G to effectively characterize the site conditions.
Storm Water Pollution Prevention Plan
40
Project Title

Rain event samples shall be collected during the first two hours of discharge from a
qualifying rain event. If it is unclear whether or not the discharge is part of a qualifying
rain event, a sample should still be taken.

Records of all analytical results from the project shall be kept in Appendix K of the
SWPPP. Records shall be kept for at least three years after the NOT is issued.

Records shall include the method detection limits and reporting units, and the analytical
techniques or methods used. Quality assurance/quality control records and results.
8.3.2
Non-Visible Pollutant Sampling
Non-visible pollutant sampling is required due to any breach, malfunction, leakage, or spill
observed during a visual inspection which could result in the discharge of pollutants to surface
waters that would not be visually detectable in storm water.
Non-visible pollutant samples collected must meet the following conditions:

Samples that are taken shall be analyzed for all non-visible pollutant parameters shown
in Table 5, below.

A sample shall be collected of storm water that has not come in contact with the
disturbed soil or the materials stored or used on-site (uncontaminated sample) for
comparison with the discharge sample.

Compare the uncontaminated sample to the samples of discharge using field analysis or
through laboratory analysis.
Potential Non-Visible Pollutants
Potential pollutants are shown in detail in Section 2.5. A summary of potential non-visible
pollutants is shown in Table 5, below.
Table 5: Summary of Potential Non-Visible Pollutants
Potential NonVisible Pollutants
Sealant (MMA)
Curing Compounds
Source (activity or material)
Water Quality
Indicator
Constituent
Methyl
methacylate
Concrete Work
Concrete Work
Polymer/Co-polymers
Soil Amendments/Dust Control
Storm Water Pollution Prevention Plan
41
EPA 625 (SVOC)
VOCs
EPA 601/602 or EPA
624
SVOCs
EPA 625 (SVOC)
Al; Ca; Va; Zn
EPA 200.8 (Metal);
EPA 200.7 (Calcium)
Organic Nitrogen
EPA 351.3 (TKN)
BOD
EPA 405.1 (BOD)
Concrete Work
Ash, Slag, Sand
Analytical Method
Project Title
Potential NonVisible Pollutants
Source (activity or material)
Storm Water Pollution Prevention Plan
42
Water Quality
Indicator
Constituent
Analytical Method
COD
EPA 410.4 (COD)
DOC
EPA 415.1 (DOC)
Nitrate
EPA 300.0 (Nitrate)
Sulfate
EPA 300.0 (Sulfate)
Nickel
EPA 200.8 (Metal)
Project Title
Appendix A
Construction General Permit Documents
Storm Water Pollution Prevention Plan
Project Title
A-1: Construction General Permit Order No. 2009-0009-DWQ
Storm Water Pollution Prevention Plan
Project Title
A-2: Amendment Order No. 2012-0006-DWQ
Storm Water Pollution Prevention Plan
Project Title
Appendix B
Submitted Permit Registration Documents (PRDs)
Storm Water Pollution Prevention Plan
Project Title
B-1: Notice of Intent
Storm Water Pollution Prevention Plan
Project Title
B-2: Risk Assessment (Construction Site Sediment & Receiving Water Risk
Determination)
Storm Water Pollution Prevention Plan
Project Title
B-3: SWPPP Map(s)
Storm Water Pollution Prevention Plan
Project Title
Appendix C
SWPPP Amendment Log
Storm Water Pollution Prevention Plan
Project Title
SWPPP AMENDMENT LOG
Amendment
No.
Name of
QSD
Storm Water Pollution Prevention Plan
Description
Date
Project Title
Appendix D
Submitted Changes to PRDs
(due to change in ownership, contacts, or acreage)
Storm Water Pollution Prevention Plan
Project Title
Appendix E
Construction Schedule
Storm Water Pollution Prevention Plan
Project Title
Construction Schedule (or replace with contractor provided schedule)
Estimated Dates
Event or Construction Phase
Start of Construction
Installation of Sediment Control BMPs
Installation of Erosion Control BMPs
Clearing and Grubbing
Demolition
Rough Grading
Concrete Pouring Activities
Street/Access Road Paving
Vertical Construction
Temporary Stabilization
Other:
Other:
Other:
Other:
Final Landscaping and Stabilization
Storm Water Pollution Prevention Plan
Project Title
Appendix F
CASQA BMP Handbook Fact Sheets
Storm Water Pollution Prevention Plan
Project Title
Appendix G
Construction Site Monitoring Program Documents
Storm Water Pollution Prevention Plan
Project Title
G-1: CSMP Checklist
Storm Water Pollution Prevention Plan
Project Title
CONSTRUCTION SITE MONITORING PROGRAM (CSMP) CHECKLIST
Project Name
Inspector’s Name
Inspector’s Title
Inspector Company
Pictures taken?
Time of Inspection
Date of Inspection
Inspection Type
(Check Applicable)
Weather (circle all
that apply)
Most Recent Storm
Data
Date Inspection Report Written

Weekly
 Prior to forecast rain

24-hr intervals during extended rain
 After a rain event

Other
Sunny
 Quarterly Non Stormwater
__
Partly Sunny
Partly Cloudy
Cloudy
Storm Start Date & Time:
Current Rain Gauge Reading
(inches)
Visual Monitoring, Inspection, and Sampling
Locations Observed (see section 8 of SWPPP)
Stage of
Construction
Rainy
Windy
Storm Duration (hrs):
Total Storm Rainfall
(inches)
Activities Completed
Approximate
Exposed Site Area
GENERAL INFORMATION
Is the site in compliance with the SWPPP and the permit requirements?

Yes

No
If NO, indicate tasks necessary to bring the site into compliance in the area below. Include dates each task will be completed.
Was water quality sampling part of this inspection?

Yes

No
If YES, see the results on the final page of the inspection form.
Sign the following certification:
“I certify that this inspection form is true, accurate, and complete, to the best of my knowledge and belief.”
Signature __________________________________________________________________________________
Storm Water Pollution Prevention Plan
Project Title
CONSTRUCTION SITE MONITORING PROGRAM (CSMP) CHECKLIST
Requirement
Yes No N/A
Corrective Action/Location
Temporary Erosion Controls
Does the applied erosion control provide 100% coverage for the
required areas?
Are there any non-vegetated areas that need erosion control?
Is the area where erosion control is required free from visible
erosion?
Do any vegetated areas require maintenance, irrigation,
fertilization, or mulching?
Are there any areas of the site that are disturbed, but will likely lie
dormant for over 14 days?
Do any erosion control BMPs require maintenance?
Temporary Sediment Controls
Are temporary sediment controls functional, and installed in
accordance with the details and/or the SWPPP Map?
Do any sediment control BMPs require maintenance?
Is the built-up sediment less than 1/3 the height of the barrier?
Are water bars or check dams installed where necessary and
properly spaced according to the SWPPP Map?
Are sediment controls installed and maintained in accordance
with the SWPPP map, functional and maintained?
Are silt fences and fiber rolls placed on level contours?
Storm Drain Inlet Protection
Are storm drain inlet BMPs internal to the project installed and
maintained properly?
Are offsite storm drain inlet BMPs installed and maintained
properly?
Stockpiles
Are inactive stockpiles covered and protected from run-on, run-off
from adjacent areas, and from winds?
Are stockpiles located at least 50 feet from concentrated flows,
downstream drainage courses and storm drain inlets?
Concentrated Flows
Are concentrated flow paths free of visible erosion?
Tracking Control
Does the project have a stabilized construction site entrance/exit
and is it installed correctly according to the SWPPP?
Are points of ingress/egress to public/private roads inspected,
swept, and maintained according to the SWPPP?
Wind Erosion Control
Is dust control implemented?
Dewatering Operations
Is dewatering handled in conformance with the dewatering permit
issued by the RWQCB?
Is required treatment provided for dewatering effluent?
Storm Water Pollution Prevention Plan
Project Title
CONSTRUCTION SITE MONITORING PROGRAM (CSMP) CHECKLIST
Requirement
Yes No N/A
Corrective Action/Location
Vehicle & Equipment Fueling, Cleaning, and Maintenance
Are vehicle and equipment fueling, cleaning, maintenance and
parking areas reasonably clean and free of spills, leaks, or any
other deleterious material?
Are vehicle and equipment fueling, cleaning and maintenance
activities performed on an impermeable surface in dedicated
areas? If no, are drip pans used?
Are dedicated fueling, cleaning, and maintenance areas located
at least 50 feet away from downstream drainage facilities and
watercourses, and protected from run-on and runoff?
Is wash water contained for infiltration/ evaporation?
Is on-site cleaning limited to washing with water (no soap, soaps
substitutes, solvents, or steam)?
On each day of use, are vehicles and equipment inspected for
leaks?
Waste Management & Materials Pollution Control
Are material storage areas and washout areas protected from
run-on and runoff, and located at least 50 feet from concentrated
flows and downstream drainage facilities?
Are material handling and storage areas clean; organized; free of
spills, leaks, or any other deleterious material; and stocked with
appropriate clean-up supplies?
Are liquid materials, hazardous materials, and hazardous wastes
stored within secondary containment?
Are packaged materials stored on pallets?
Are hazardous materials and wastes stored in appropriate,
labeled containers?
Are secondary containment facilities and packaged materials
covered or protected when inactive?
Are temporary concrete washout facilities designated and water
tight?
Are concrete wastes, including residues from cutting and grinding,
contained and disposed of off-site or in concrete washout
facilities?
Are spills from mobile equipment fueling and maintenance
properly contained and cleaned up?
Is litter from work areas within the construction limits of the project
site collected and placed in dumpsters with lids?
Are trash receptacles provided in the Contractor’s yard, field
trailer areas, and at locations where workers congregate for lunch
and break periods?
Are waste management receptacles free of leaks?
Is the site free of litter?
Are waste management receptacles filled at or beyond capacity?
Are portable toilets placed within containment to prevent the
discharge (leaking) of pollutants?
Spill Control and Response
Are there proper spill clean-up materials, and posted spillreporting procedures for hazardous materials and wastes in open
and accessible locations adjacent to storage areas?
If a spill has occurred, was the QSP contacted within 24 hours of
a spill of a hazardous substance?
Storm Water Pollution Prevention Plan
Project Title
CONSTRUCTION SITE MONITORING PROGRAM (CSMP) CHECKLIST
Requirement
Yes No N/A
Corrective Action/Location
Non-Storm Water Discharges
Is there any evidence of illicit discharges or illegal dumping on the
project site?
If yes, has the QSP been notified?
If there has been an unauthorized or non-storm water discharge,
has it been immediately contained, cleaned up and documented
in the SWPPP?
If yes, has the QSP been notified?
Discharge Points
Are discharge points and discharge flows free from visible
pollutants?
Are discharge points free of any significant erosion and
deposition?
SWPPP Update
Does the SWPPP adequately reflect the current site conditions
and contractor operations?
Are all BMPs shown in the SWPPP Map also installed on the
construction site?
Are the SWPPP and NOI on-site where it is accessible to others?
Does the SWPPP contain a current list of potential pollutant
sources?
General
If this is a pre-storm inspection, is a Rain Even Action Plan
(REAP) also being developed? (traditional projects only)
Are there any other potential stormwater or non-stormwater
pollution control concerns at the site?
Storm Water Monitoring
Is there a 50% chance of rain or greater in the forecast?
(http://www.weather.gov) Note: Print and attach NOAA forecast
to this checklist.
If a storm event occurred recently, did it produce precipitation of
0.5 inch or more? If so, this should be a post-storm inspection.
Are there any noticeable odors or visible sheen on the surface of
any runoff or discharges?
Storm Water Pollution Prevention Plan
Project Title
G-2: Discharge Sampling Report
Storm Water Pollution Prevention Plan
Project Title
DISCHARGE SAMPLING REPORT
Sampler’s Name: _____________________________
Date: ________________________
Type of Sampling Event (Circle One): Rain Event
Non-Stormwater
*Non Visible Pollutant Sampling Event? (Circle One) Yes
No
*Note: Non-visible pollutant sampling is only required if there is potential for non-visible pollutants to discharge from
the site. See Section 8.3.2 of the SWPPP for additional guidance and requirements for non-visible pollutant sampling.
Sampling Location
Time of
Sample
(Consult CSMP
Locations Map for Name Collection
and Location of
Sampling Points)
Parameter
(pH, Turbidity, or
Specific NonVisible Pollutant)
Analysis
Performed
By
(List Laboratory
or Person)
Result
(Include units)
% of Total
Site
Discharge
Sampler’s Signature: _____________________________
Storm Water Pollution Prevention Plan
Project Title
G-3: Exemption Records
Visual monitoring, inspections, and sample collection are not required under the following
conditions:
 During dangerous weather conditions such as flooding and electrical storms

Outside of scheduled site business hours.
If no required visual observations (inspections) or samples are collected due to these
exceptions, complete a form below. Each form shall document the reasons why the visual
monitoring, inspection, and/or sample collection was not conducted. Completed forms shall be
included in Appendix H.
Time:
Date:
Exemption
□ Dangerous weather conditions
Type:
Details of Exemption:
□ Outside of scheduled site business hours
Time:
Date:
Exemption
□ Dangerous weather conditions
Type:
Details of Exemption:
□ Outside of scheduled site business hours
Time:
Date:
Exemption
□ Dangerous weather conditions
Type:
Details of Exemption:
□ Outside of scheduled site business hours
Time:
Date:
Exemption
□ Dangerous weather conditions
Type:
Details of Exemption:
□ Outside of scheduled site business hours
Storm Water Pollution Prevention Plan
Project Title
G-4: CSMP Locations Map
Storm Water Pollution Prevention Plan
Project Title
Appendix H
Certifications and QSP Training Log
Storm Water Pollution Prevention Plan
Project Title
QSP Training Log
Date
QSP Training Topic
Storm Water Pollution Prevention Plan
Name of Trainee
QSP Initial
Project Title
Appendix I
Responsible Parties
Storm Water Pollution Prevention Plan
Project Title
Responsible Parties
Title and Contact Information
Area of Responsibility
Legally Responsible Person:
Entity Name_NCTD
LRP Contact Person: Peykan Abbassi, Chief
Development Officer
Address: 801 Mission Avenue
City, State, Zip:Oceanside, CA 92054
Telephone Number: 760.966.6684
Email: pabbassi@nctd.org
Property Owner and Permittee under the General
Permit
Authorized Signatory for the LRP:
Contact Person: Full Name
Address: 801 Mission Avenue
City, State, Zip: Oceanside, CA 92054
Telephone Number: TBD
Email: TBD
Authorized to sign (and certify) on behalf of the
LRP: the Notice of Intent, Notice of Termination,
Changes to the Permit Registration Documents,
SWPPP Certification, Annual Reports, NonCompliance reports, and any other information
requested by the RWQCB, SWRCB, or EPA under
the General Permit.
Qualified SWPPP Developer:
Company Name: Name
QSD Name: Name, Title
Address: street address
City, State, Zip: City State, zip
Telephone Number: _____________
Email: _____________
Draft the SWPPP and any SWPPP amendments
and certify compliance of the SWPPP with the
General Permit.
Qualified SWPPP Practitioner:
Company Name: ___________
QSP Name:_____________
Address:_______________
City, State, Zip:_____________
Telephone Number (including emergency contact
number[s]):____________
Fax:____________
Email:________________
Implement the SWPPP on a daily basis at the
Project, oversee the training of contractors and
other personnel undertaking SWPPP-related
duties, monitor and direct contractors with SWPPP
responsibilities (including those installing or
maintaining BMPs), oversee the inspection and
monitoring programs, perform inspections or
delegate others to do so (see other delegated
inspectors below), prepare reports required by the
SWPPP for review and certification by the LRP’s
representative.
SWPPP Inspector(s):
Company Name: _________
Name:___________
Address:_________
City, State, Zip:___________
Telephone Number (including emergency contact
number[s]):__________
Fax:____________
Email:__________
Conduct inspections under the supervision of the
QSP.
Storm Water Pollution Prevention Plan
Project Title
Title and Contact Information
Contractor/Subcontractor
Company Name: __________
Name:______________
Address:__________
City, State, Zip: ____________
Telephone Number (including emergency contact
number[s]):___________
Fax: ____________
Email:_____________
Storm Water Pollution Prevention Plan
Area of Responsibility
Install, maintain, and replace erosion and sediment
controls.
Project Title
Appendix J
Contractors and Subcontractors
Storm Water Pollution Prevention Plan
Project Title
CONTRACTORS AND SUBCONTRACTORS
Contractor/Subcontractor
Name and Address
Contact Person/
Phone Number
Storm Water Pollution Prevention Plan
Activity
Start
Date
End
Date
Project Title
Appendix K
Chain of Custody and Analytical Results
Storm Water Pollution Prevention Plan
Project Title