THIRD QUARTER PERFORMANCE EVALUATION REPORT FOR LOWER THUKELA BULK WATER SUPPLY SCHEME (UMGENI) KWAZULU NATAL CHIEF DIRECTORATE: BULK INFRASTRUCTURE PROGRAMME PERIOD: 01 OCTOBER 2014 TO 31 DECEMBER 2014 2 PROGRAMME MANAGEMENT: REGIONAL BULK INFRASTRUCTURE TABLE OF CONTENTS 1. Introduction 2. Background 2.1 Description of project 2.2 Project History 2.3 Project concept, design and plan 2.4 Start date – duration of the programme 2.5 Fund allocated to project 3. Progress to date 3.1 Implementation of approved business plan 3.2 Schedules of work and phasing of the activities 3.3 Risks taken and management thereof 3.4 Capacities dedicated to the programme 3.5 Key challenges within the project 4. Project result and beneficiaries 4.1 Outcomes and outputs 4.2 Beneficiaries and project results. 4.3 Jobs created 5. Conclusions / Lessons Learned 5.1 Main successes and failures of the project to date 5.2 Ownership and sustainability of infrastructure works 6. Recommendations ANNEXURE A: ANNEXURE B: ANNEXURE C: ANNEXURE D: ANNEXURE E: Project Implementation Photos List of villages expected to benefit from Scheme Details of contracts Project schedule Details of job opportunities 31 DECEMBER 2014 3 PROGRAMME MANAGEMENT: REGIONAL BULK INFRASTRUCTURE 1. 31 DECEMBER 2014 INTRODUCTION In terms of Section 10(7) (b) of the Division of Revenue Act No 10 of 2014 (DORA) as promulgated in Government Gazette No 37595 dated 26 April 2014, the transferring national officer must submit a quarterly performance report for all Programmes funded by a Schedule 6 allocation within 45 days after the end of each quarter, in accordance of the relevant framework to the National Treasury. The Regional Bulk Infrastructure Grant (RBIG) is a Schedule 6 indirect conditional grant for the benefit in kind of municipalities. The objective of this Report is to provide a third quarter performance evaluation report of RBIG funded projects, in compliance with the DORA. The objective of this evaluation was to determine whether the progress on the project is commensurate with the expenditure to date as well as to determine whether the project is still on course in terms of the original planning. This performance evaluation report, covering quarter 3 for the 2014/2015 fiscal year, is for the Lower Thukela Bulk Water Supply Scheme (LTBWSS), one of the Regional Bulk Infrastructure Grant projects, currently being implemented by Umgeni Water in the KwaZulu-Natal Province, with Department of Water and Sanitation (DWS) as funder, and Umgeni Water as co-funder. 2. BACKGROUND 2.1 Description of Project With the increase in demand for potable water, many of the towns of the KwaZulu-Natal (KZN) North Coast, from north of Durban to the Thukela River, could soon be experiencing water shortages. The two main water resources used for supply to this area include the Hazelmere Dam on the Mdloti River in the South and an abstraction on the Mvoti River near the town of KwaDukuza. Other small borehole or run-of-river schemes supply some of the smaller remote towns and rural areas. Rapid development of industry and housing is predicted on the KwaZulu-Natal North Coast with over 140 developments proposed along the N2 corridor in this region. This increase in development will exacerbate the need for potable water and even with the proposed upgrade of the Hazelmere Dam and the North Coast Supply System (NCSS); a deficit of greater than 100 Mℓ/d is still expected over the next 20 years. Umgeni Water’s Infrastructure Master Plan (2011) shows the Lower Thukela BWS Scheme as being the option which should be implemented with a matter of urgency to further augment the North Coast Supply System. The Lower Thukela BWS Scheme would supply the coastal area north of Ballito and the resources of the Hazelmere WTP would then be concentrated on the existing demands and growth in eThekwini. For ease of construction and in order to meet intermediate project deadlines the Project has been split into six separate contracts as follows: Contract A1: Civil Works for the Construction of the 55 Mℓ Water Treatment Works. Contract A2: Civil Works for the Construction of the Weir, Abstraction Works and Access Roads. Contract B: Mechanical, Electrical and Instrumentation for Pump Stations, Abstraction Works and the Waterworks. 4 PROGRAMME MANAGEMENT: REGIONAL BULK INFRASTRUCTURE 2.2 31 DECEMBER 2014 Contract C: Civil Works for the gravity main from Mvoti Reservoir to the Command Reservoir in Mandeni. Contract D: Civil Works for Rising Main and Command Reservoir. Contract E: Bulk Electrical Power Supply. Project history A meeting was held on the 17th June 2011 between DWS, Cooperative Governance and Traditional Affairs (CoGTA), Umgeni Water and ILembe District Municipality to discuss an ILembe DM proposal to implement a desalination plant within the district. ILembe DM’s motivation for implementing a seawater desalination plant was to provide a greater assurance of supply of water to the KwaDukuza Local Municipality. ILembe DM contend that with the increase in demand within KwaDukuza, and the impending developments that are proposed within the region, the current sources of potable water will not be sufficient to supply their developed area in the near future. At this meeting it was agreed by all parties that the most appropriate augmentation of water supply to KwaDukuza would be from the Lower Thukela BWS Scheme if this scheme could be implemented in a timely manner. It was therefore agreed that this project should be fast tracked to ensure that no deficit of water is realised within the region. Umgeni Water’s Infrastructure Master Plan (2011) shows the Lower Thukela BWS Scheme as being the option which should be implemented with a matter of urgency to further augment the North Coast Supply System. The Lower Thukela BWS Scheme would supply the coastal area north of Ballito and the resources of the Hazelmere WTP would then be concentrated on the existing demands and growth in eThekwini. Further to the meeting between DWS, Cooperative Governance and Traditional Affairs (CoGTA) , ILembe DM and Umgeni Water, as referenced above, an agreement has been made between DWS and Umgeni Water that Umgeni Water would fund R 600 million of the Lower Thukela BWS Scheme and DWS would fund the remaining project cost. The proviso to this agreement is that the project proceeds immediately to design and implementation. Aurecon Consulting Engineers have completed the technical components of the Detailed Feasibility Study (DFS) on the basis of a total available yield form the Thukela River of 110 Mℓ/d, as informed by DWS. The LTBWSS has therefore been proposed to supply up to a maximum of 110 Mℓ/d potable water to the NCSS. The first phase of the project will be constructed to supply 55 Mℓ/d. The total capital expenditure for the first phase of the project is estimated at R 1 342 million over an implementation period of four years. 2.3 Project concept, design and plan The objective of the project is to meet the supply demands of the future growth of the district identified in the water and sanitation Master Plan for ILembe DM. The project includes the infrastructure required to abstract and treat water from the UThukela River to supply this to secondary bulk and reticulation networks within the ILembe DM. These networks will ultimately supply both developed and backlog areas. This scheme will supply an additional 55 Mℓ/d to the coastal and inland areas of KwaDukuza LM and Mandeni LM. The supply of water to industry will ensure job creation and economic upliftment of the local community. Backlog eradication will be addressed through the implementation of the scheme. 5 PROGRAMME MANAGEMENT: REGIONAL BULK INFRASTRUCTURE 31 DECEMBER 2014 The project also offers construction job opportunities to a community in desperate need of economic assistance. A brief description of all elements of the scheme is given below: Access Road to Abstraction Works: In order to enable the contractor to gain access to the right bank of the river (location of abstraction works) an access road will have to be designed and constructed. Weir and Abstraction Works: These structures, located in or adjacent to the river, serve to create an abstraction point for water which is not encumbered by difficulties caused by sediment deposition, low flows or debris. Low Lift Pump Station: The intakes situated in the abstraction works feed the low lift pump station which is situated behind, and is protected by, the abstraction works. Raw Water Pipeline: Raw water is transferred across the river via a pipeline constructed in the weir and is discharged into the desilting cyclones. Desilting Cyclones: These cyclones serve to remove silt and sand particles from the raw water stream so that it does not have to be dealt with later on in the treatment process. 55 Mℓ/d Water Treatment Plant: The partially desilted raw water is treated at the treatment works to potable standards and any sludge generated disposed of. High lift Pump Station: This pump station forms the start of the potable water distribution system. 900 mm diameter rising Main: This is the transfer pipeline from the high lift pump station to the balancing reservoirs. 35 Mℓ Potable Water Reservoir: This reservoir, situated on the highest point along the pipeline route, serves as a link between the rising main and the gravity main and also adds to operational flexibility. 900 mm diameter Gravity Main: This section of the pipeline forms the final link in the bulk water supply system to the NCSS. Bulk Electrical Supply: 132 KV power supply for the operation of the works. 6 PROGRAMME MANAGEMENT: REGIONAL BULK INFRASTRUCTURE 31 DECEMBER 2014 Figure1: Aerial image and general layout of the proposed Lower Thukela BWSS. The villages that are expected to benefit from the Scheme are listed in Annexure B. 7 PROGRAMME MANAGEMENT: REGIONAL BULK INFRASTRUCTURE 31 DECEMBER 2014 Figure2: Proposed supply areas from the Lower Thukela BWSS 2.4 Start date – duration of the programme The detailed design commenced in July 2011. The design for the scheme was completed by February 2014. The construction of the Gravity Main from Mvoti Reservoir to the Command Reservoir in Mandeni commenced on 13 February 2013. Stage 1 of the pipeline up to Darnall was targeted for commission by July 2014 and was to be initially fed from the Hazelmere System. The Nonoti Bridge Crossing however delayed the Phase 1 implementation to the extent that the Phase 1 completion was discarded and the project completion date taken as the target date for phase 2. The DOT approval for the Nonoti Bridge was finally received on the 28th July 2014. Stage 2 up to the Command Reservoir will be completed by April 2015. The contract is 69% complete. The tender for the Abstraction Works, Weir and Road-works was awarded in September 2013. Construction commenced in November 2013. The initial portion of the weir and abstraction works will be completed by March 2016, thus enabling the Scheme to be commissioned. The remaining work will be completed by September 2016. The tender for the Water Treatment Works was awarded in September 2013. Construction commenced in November 2013. The works will be completed by March 2016. The Inaugural meeting for the Rising Main and Command Reservoir was held on 10 September 2014 with the intention of getting the Contractor to start getting his contractual documentation in place as well as identifying the plants to be rescued with the search and rescue operation on the rising main pipeline route this was followed by the Site Handover Meeting which took place on 1st October 2014. The contract will be completed on 09th February 2016. 8 PROGRAMME MANAGEMENT: REGIONAL BULK INFRASTRUCTURE 2.5 31 DECEMBER 2014 The tender for the Bulk Electrical Power Supply was awarded and the works commenced on 21 October 2014. The contract is scheduled to be complete by 17 October 2015. Funds allocated to project Table 1 below indicates the RBIG funding that has been made available to the project. Table1: Funding for 5 financial years Allocation/ Expenditure 2012/13 R000 2013/14 R000 R 43 636 R 106 992 R 185 000 Co-funding streams: Umgeni Water 3. 2014/15 R000 2015/16 (Including Maphumulo) R000 Total R000 R 344 368 R 864 996 : R 600 000 000 PROGRESS TO DATE A performance evaluation was conducted on 23rd January 2015 by the following team: 3.1 Jayendran Moodley Krish Govender Julius Katze Richard DWS – Regional Office KZN Umgeni Water – Project Manager Bigen Africa DBSA Implementation of the approved business plan Umgeni Water has employed its own staff to manage the project and to provide specialized professional services, financial management and administrative support to the project. Umgeni Water has also appointed external professional service providers and contractors in terms of its supply chain management policies and procedures. Umgeni Water’s Planning Services Department, working in conjunction with Professional Service Provider (PSP), Aurecon Consulting Services, completed the Detailed Feasibility Study in April 2011. During the same period Strategic Environmental Focus (SEF) commenced work on the Environmental Impact Assessment (EIA) and the Environmental Authorisation was obtained in August 2012. Aurecon were appointed as the PSP in June 2011 to undertake the detailed design of the scheme. The design of the gravity main from the Command reservoir in Mandeni to Mvoti Reservoir was completed and put out to tender in April 2012. The tenders closed on 24 May 2012, and an award was made to Esorfranki Pipeline in August 2012. The award however had to be delayed due to an appeal from one of the unsuccessful tenderers. Further delays were experienced with the implementation of UW’s BBBEE Contract Participation Goal (CPG) targets. The tender has since been awarded and construction is underway. The design of the WTP, River Abstraction Works, Weir and other associated was completed and put out to tender in May 2012. The tender closed on 28 June 2012 and was 9 PROGRAMME MANAGEMENT: REGIONAL BULK INFRASTRUCTURE 31 DECEMBER 2014 evaluated but could not be awarded due to shortage of funding. In December 2012 UW took the decision to split the Tender into two smaller work packages so that the Abstraction Works and Weir could be awarded within the funds available from UW’s co-funded portion of R600 million. The tender process for the split contracts is complete and awards of the two contracts have been made. The contract for the Abstraction Works, Weir and Access Roads has been awarded to Group Five Coastal. The contract for the Water Treatment Works has been awarded to Stefanutti Stocks. The Rising Main and Command Reservoir and the Bulk Electrical Power Supply contracts were awarded to Group Five Coastal and Conco (Consolidated Power Projects) respectively. Table 2: Milestones Aurecon Planned date for completion FS/IRS/Design/EIA April 2011 Date FS/IRS/Design/EIA approved April 2011 Preliminary Design Aurecon April 2011 April 2011 EIA Strategic Environmental Focus June 2012 August 2012 Amendments to EIA Strategic Environmental Focus July 2013 October 2013 WUL Operation and Maintenance Plan Aurecon Umgeni Water June 2012 November 2015 July 2013 Pending Financial Funding Plan Umgeni Water April 2011 April 2011 Design Aurecon September 2012 February 2014 Product Name of Organization compiling/ developing Feasibility Study Contract details are summarized in Annexure C. 3.2 Schedules of work and phasing of the activities The Scheme comprises a number of construction contracts, viz. the Abstraction Works, Weir and Roads, the Water Treatment Works, the Mechanical and Electrical work, the Gravity Main, the Rising Main and Command Reservoir and the Bulk Electrical Supply, as described in Section 2.3 above. Construction work on the first contract awarded commenced in February 2013, and the last contract is expected to be completed in September 2016. A tracked programme for the Scheme as at 28 March 2014 is shown in Annexure D. 3.3 Risks taken and management thereof As the Scheme comprises new infrastructure, no risks other than those normally encountered on a project of this size and nature have been taken. The following major 10 PROGRAMME MANAGEMENT: REGIONAL BULK INFRASTRUCTURE 31 DECEMBER 2014 construction risks have been identified at a stakeholder management working session where mitigation measures were identified to reduce these risks to acceptable levels. 3.4 Power supply to site (becoming a huge concern and has been moved up.) High winter flows preclude the construction of the coffer dam in the second winter season Overtopping/failure of coffer dam (for either phase 1 or 2) due to high winter flows Union Strikes such as in Steel Industry & Civil Industry Labour Unrest Cost overrun Shortage of Construction Material Excessive Rain Interdependency of Contract programmes Delayed DWA Discharge Licence Capacities dedicated to the programme The capacities dedicated to the programme are as follows: 3.5 Water Services Authority – ILembe District Municipality. Water Services Provider – Umgeni Water. Funding – DWS – Regional Bulk Infrastructure Grant (RBIG) and Umgeni Water (co-funding). Regulator – DWS. Overall Programme and Project Management – Umgeni Water. Specialized professional services, financial management and administrative support – Umgeni Water. Design, contract administration and construction monitoring – professional service providers appointed by Umgeni Water: (i) Design - Aurecon, (ii) Contract Administration and Construction Monitoring – Bigen Africa. Construction work – various contracting companies awarded contracts by Umgeni Water: (i) Esorfranki Pipelines (Contract C), (ii) Group Five Coastal (Contract A2), (iii) Stefanutti Stocks (Contract A1), (iv) Veolia Water (Contract B), Group Five Coastal (Contract D) and Conco (Contract E). Key challenges within the project Key risk areas include the following: The risk of unusually high flooding during the dry months. This would affect the construction of the Weir and Abstraction Works, potentially causing a year’s delay to the commissioning of the scheme. Various acceleration activities have been undertaken to ensure that the abstraction works reach a certain level of completion to accommodate the wet season flows. Target of mid October 2014. A meeting was held on site with Eskom Project Engineers on the 11 November 2014. The Eskom project engineers felt that it would be realistic to expect the Eskom portion of the work to be done by Sep 2015. The following process was put forward: 1. The secondary plant design is to be presented at the control plant TEF on the 20 November 2014 2. The primary plant design will be presented at the primary plant TEF in the first week of December 2014. 11 PROGRAMME MANAGEMENT: REGIONAL BULK INFRASTRUCTURE 31 DECEMBER 2014 The design was approved and forwarded to the Investment Committee for the budget quote, but confirmed that they would be able to meet implementation and completion date by August/ September 2015. The first dry season target date of mid-October 2014 was not met and the mitigation measures taken by the Contractor to extend the dry season work to end of November 2014 was fortunately not met with high river flows. Access delays to properties along the pipeline route as well as the Nonoti Bridge Crossing design approval by DOT has considerably delayed the completion of gravity main construction and a revised completion date of August 2015 is being targeted. 4. PROJECT RESULTS AND BENEFICIARIES 4.1 Outcomes and outputs Currently the expected outcomes and outputs are on track for the scheme. 4.2 Beneficiaries and project results As stated in Section 2.3 above, the purpose of the project is to supply an additional 55 Ml/d of treated water to the coastal and inland areas of KwaDukuza LM and Mandeni LM. The population projection for the area up to 2035 is 19 149 people in approximately 3 193 households. The supply of water to industry will ensure job creation and economic upliftment of the local community. Backlog eradication will be addressed through the implementation of the scheme. The project also offers construction job opportunities to a community in desperate need of economic assistance. It should be noted that the scheme only addresses the Bulk Infrastructure and that the secondary bulk and reticulation is being undertaken by ILembe DM as the Water Supply Authority. 4.3 Jobs Created Job creation details are summarized in Annexure D. 5. CONCLUSION / LESSONS LEARNED 5.1 Main successes and failures of the project to date A project team, involving all key role-players, has been set up and monthly progress meetings are held ensuring that all parties are kept informed. ILembe DM’s highest priority was to provide water up to Darnall by November 2013. As the LTBWSS will not be operational by then, UW have undertaken to provide water from the Hazelmere system as an interim measure. To achieve this, the Gravity Main contract has already commenced but due to the delays in the award of this contract, water delivery will be achieved by April 2014. The Mechanical and Electrical contract, which has long lead-time equipment purchases, has already been awarded and is now entering the procurement phase. The Civil works for the Abstraction Works, Weir and Access Roads has been awarded and progress is recorded at 46% as opposed to 36% overall time lapsed. The Civil works for the Water Treatment Works has been awarded and is recorded at 30% physical progress against 50% time lapsed. The 30% is however only 2% 12 PROGRAMME MANAGEMENT: REGIONAL BULK INFRASTRUCTURE 31 DECEMBER 2014 below the scheduled programmed progress to date and the contractor is aiming to make up the lost time. 5.2 Ownership and sustainability of infrastructure works Umgeni Water will take ownership of the infrastructure upon completion and provide the management and resources necessary to operate and maintain the scheme. 6. RECOMMENDATIONS The project is on track and sufficient funds have been allocated. 13 PROGRAMME MANAGEMENT: REGIONAL BULK INFRASTRUCTURE 31 DECEMBER 2014 ANNEXURE A: PROJECT IMPLEMENTATION PHOTOS – GRAVITY MAIN Photo1: Pipe laying in progress Photo2: Pipe laying in progress 14 PROGRAMME MANAGEMENT: REGIONAL BULK INFRASTRUCTURE Photo3: Access Roads Photo4: Admin Building 31 DECEMBER 2014 15 PROGRAMME MANAGEMENT: REGIONAL BULK INFRASTRUCTURE Photo5: Sludge Thickeners Photo6: Clari-flocculators A 31 DECEMBER 2014 16 PROGRAMME MANAGEMENT: REGIONAL BULK INFRASTRUCTURE Photo7: Pulsator Photo8: Reservoir 31 DECEMBER 2014 17 PROGRAMME MANAGEMENT: REGIONAL BULK INFRASTRUCTURE Photo9 : Abstraction Works Southbank Photo10: High Lift Pump Station 31 DECEMBER 2014 18 PROGRAMME MANAGEMENT: REGIONAL BULK INFRASTRUCTURE 31 DECEMBER 2014 ANNEXURE B: LIST OF VILLAGES EXPECTED TO BENEFIT FROM SCHEME Projected Water Demands: South of Thukela River to KwaDukuza (Ml/day) DEMAND NODE CURRENT 2009 2010 2015 2020 2025 SOURCE Padianager, Tugela, Mandeni WTW 1.7 1.7 1.9 2.1 2.3 Newark, Hlomendlini Sakhamkhanye Nil 0.7 1.0 1.4 Darnell & Nkwazi Darnell Sugar Mill 2.8 2.9 3.0 3.3 3.3 Zinkwazi Beach Zinkwazi boreholes 1.5 1.6 1.6 10.8 19.1 New Guelderland Nil 0.0 0.0 0.3 1.7 Prince’s Grant, Hyde Boreholes 0.4 0.4 1.1 3.6 3.9 Park, Nonoti Land Restitution Blythedale Boreholes 0.7 1.8 2.1 5.8 9.8 KwaDukuza Mvoti WTW & 19.6 19.6 22.0 25.5 27.7 Hazelmere WTW Total Annual Average daily Demand 26.6 28.1 32.5 52.3 69.2 (Ml/day) Water demands: Lower North Coast: Groutville to Zimbali (Ml/day) DEMAND NODE CURRENT 2009 2010 2015 2020 SOURCE Zimbali reservoir zones Hazelmere WTW 0.9 1.2 2.1 3.0 Avondale reservoir Hazelmere WTW 5.1 6.1 10.7 19.9 zone Mystic river reservoir Nil 0.2 1.0 zone Compensation reservoir Hazelmere WTW 0.9 1.3 2.0 5.9 zone Shakashead reservoir Hazelmere WTW 1.3 2.6 6.4 9.2 zone Thafeni reservoir zone Hazelmere WTW 0.6 1.1 4.3 7.0 Seaton Delaval Nil 1.6 reservoir zone Tinley manor reservoir Nil 1.2 2.9 zone Palm lakes reservoir Hazelmere WTW 0.2 0.4 1.3 3.1 zone Shayamoya / Hazelmere WTW 1.1 1.1 1.1 1.3 Nkobongo reservoir zone Rocky Ridge reservoir Nil 0.2 0.3 zone Honolulu reservoir zone Hazelmere WTW 1.2 1.3 3.8 7.3 Etete reservoir zone Hazelmere WTW 1.2 1.7 4.1 5.9 Total Annual Average Daily Demand 12.5 16.8 37.4 68.4 (Mℓ/day) 2030 2035 2040 2.5 2.7 3.0 1.4 3.3 24.4 2.8 4.0 1.4 3.3 28.7 2.8 4.0 1.4 3.3 29.0 2.8 4.0 13.4 28.6 13.4 29.0 13.6 29.1 80.4 85.3 86.2 2025 2030 2035 2040 3.2 34.0 3.2 45.0 3.2 48.9 3.2 49.4 1.6 1.6 1.6 1.6 9.7 9.7 9.7 9.8 9.7 9.8 9.8 9.9 7.2 4.7 7.2 6.1 7.2 6.1 7.2 6.2 4.3 4.3 4.3 4.3 5.3 7.1 7.8 7.9 2.2 2.9 2.9 3.0 0.3 0.3 0.3 0.3 9.0 5.9 96.9 10.3 10.3 10.4 5.9 5.9 5.9 113.2 117.9 119.1 19 PROGRAMME MANAGEMENT: REGIONAL BULK INFRASTRUCTURE 31 DECEMBER 2014 ANNEXURE C: DETAILS OF CONTRACTS CONTRACT AWARD / START DATE PLANNED COMPLETION DATE ACTUAL COMPLETION DATE EXPENDITURE AS AT 31 DECEMBER 2014 (incl. VAT) % COMPLETION Sept- 11 Feb- 14 N/A R 58 332 335.67 100% Oct-13 Oct-15 N/A R 111 533 912 30% Oct-13 Nov-2015: Ptn A Dec-2015: Ptn B N/A R 182 044 091.86 46% Jan-14 Feb-16 N/A R 22 216 334.70 40% CONTRACT NO. AND NAME CONTRACTOR CONTRACT VALUE (incl. VAT) Lower Thukela Bulk Water Supply – Detail Design Aurecon South Africa (Pty)Ltd R 62 631 886.14 Contract A1 – Water Treatment Works Stefanutti Stocks (Pty) Ltd R 373 397 181.73 Contract A2 – Abstraction, Weir and Access Roads Group Five Coastal (Pty) Ltd R 402 362 112.40 Contract B – Mechanical and Electrical Veolia Water Solution & Technologies SA (Pty) Ltd Contract C – Gravity Main Esorfranki Pipelines (Pty) Ltd R 254 951 000.00 Feb- 13 Dec- 14 N/A R 254 950 988.52 79% Contract D – Rising Main and Reservoir Group Five Coastal (Pty) Ltd R 95 971 769.57 Oct- 2014 Feb-16 N/A R 8 996 551.90 4% Contract E- Bulk Electrical Supply Pending Oct 14 Oct- 15 N/A R0.00 On Schedule LTBWSS: PSP Stage 5-6 and Construction Monitoring Bigen Africa Services (Pty) Ltd Dec- 13 Sep- 16 N/A R 12 915 539.37 24.3% NOTE: R 268 892 000.00 R 480 729 17.31 R 53 071 116.99 Retention monies withheld have been included as expenditure. All figures include 14% VAT. 20 PROGRAMME MANAGEMENT: REGIONAL BULK INFRASTRUCTURE ANNEXURE D: PROJECT SCHEDULE 31 DECEMBER 2014 21 PROGRAMME MANAGEMENT: REGIONAL BULK INFRASTRUCTURE 31 DECEMBER 2014 ANNEXURE E: DETAILS OF JOB OPPORTUNITIES Summary of Decent Job Opportunities Decent job opportunities for people employed at various occupational levels: Decent = Full time for at least 5 months or more Decent job opportunities for the financial year 2014/15 Adult Men No Pers on Days Actual cost on job opportunities No Perso n Days Clerical Ongoing 0 0 R0 0 0 Clerical New 0 0 R0 0 Labourers Ongoing 98 1671 R 549 149.01 Labourers New 15 267 Managerial Ongoing 0 Managerial New Adult Women Actual cost on job opportunities N o Disabled Pers Actual cost on on job Days opportunities No TOTAL Person Days R0 0 0 R0 0 0 R0 0 R0 0 0 R0 0 0 R0 8 133 R 39 574.94 0 0 R0 196 3263 R 1 049 565.38 R 11 728.14 0 0 0 0 0 R0 17 288 R 75 597.28 0 R0 0 0 R0 0 0 R0 0 0 R0 0 0 R0 0 0 R0 0 0 R0 0 0 R0 R0 25 271 R 144489.61 0 0 R0 0 0 R0 42 432 R 279 653.62 0 R0 0 0 0 0 0 R0 0 0 R0 0 0 R0 2 22.5 R 5 798.29 37 462 R 314051.16 2 31 R 15 665.46 0 0 R0 86 1182.5 R 658 659.68 R 10 936.88 0 0 R0 0 0 0 0 0 R0 0 0 R0 2 36 R 10 936.88 0 R0 0 0 R0 0 0 R0 0 0 R0 0 0 R0 0 0 R0 0 0 R0 0 0 R0 0 0 R0 0 0 R0 0 0 R0 0 0 R0 Other Ongoing 0 0 R0 0 0 R0 0 0 R0 0 0 R0 0 0 R0 0 0 R0 Other New 0 0 R0 0 0 R0 0 0 R0 0 R0 0 0 R0 0 0 R0 160 2499 R 1 007 457.79 31 519.5 R 140 467.57 123 1695 R 784712.92 0 1 8 TOTAL Ongoing 164 R 55 240.40 0 0 R0 332 48775 R 1 987878.68 TOTAL New 17 303 R 74 806.02 0 0 R0 2 21 R 11 782.14 0 0 R0 0 0 R0 19 324 R 86 588.16 No Pers on Days R0 0 0 0 R0 0 29 497 R 134 669.28 R 63 869.14 0 0 0 R0 0 0 0 R0 Semi-Skilled Ongoing 17 161 Semi-Skilled New 0 Skilled Ongoing Youth Men Actual cost on job opportunitie s N o Perso n Days R0 0 0 0 R0 0 61 962 R 326172.15 0 2 21 0 R0 0 0 0 R0 R 135 164.01 0 0 0 0 0 45 667 R 323 144.77 Skilled New 2 36 Supervisor Ongoing 0 Supervisor New Youth Women Actual cost on job opportunities Actual cost on job opportunities