Monthly Progress Report – 47 for the Month of June, 2014 1. INTRODUCTION The government of India, through the ministry of Shipping, Road Transport & Highway has entrusted the NHAI with the responsibility of Developing and maintaining various section of Highway. NHAI under the prestigious programme has taken up the four laning of the existing 2 – lane National Highway No. – 33, connection Ranchi, capital of Jharkhand to National Highway No. – 2. Hazaribagh – Ranchi section of NH – 33 is the primary and principal mode of transportation running across Jharkhand connecting most of the backward regions of the state and connecting Jharkhand with other states. Thus improvement and 4 – Laning of NH-33 will not only change the face of the road section in Jharkhand but will also provide the backbone for cultural exchange, social equality and a everlasting impact on its economy. The concession Agreement was signed on 8th -Oct-2009 and the work contract commenced on 8th Aug 2010, upon receipt of order to commence from the NHAI. The Concessionaire kept on submitting all project related documents to the project director NHAI who initially was the IC in charge until the consultant’s agreement was signed and delegated powers transferred to the Independent consultant. The role of IC is defined in RFP and schedule Q for Development, Construction and Operation stages. The Concessionaire’s mobilization and the Independent Engineer’s mobilization status are appended in separate chapter. The Consultancy Contract between NHAI and M/S Unihorn India Private Limited was signed on 6th Aug 2010. The Independent Consultant’s team started mobilizing since that date. The Representative of the employer, the IC and the concessionaire address there are all given below. (1) NHAI :NHAI, PIU 8-402' Road No. 4-C, Ashok Nagar, Ranchi, (2) IC :M/S Unihorn India Private Limited 462/A, “Anupama”, Ashok Nagar, Argora, Ranchi – 834002 (Jharkhand) (3) Concessionaire :M/s Hazaribagh Ranchi Expressway Ltd. 443/A, Ashok Nagar, Ranchi (Jharkhand) Unihorn India Private Limited Page 1 Monthly Progress Report – 47 for the Month of June, 2014 1.1 General:The project envisages construction of four laning of Hazaribagh-Ranchi section of NH-33 from (Km. 40.500 to Km. 114.000) on BOT (Annuity) basis under NHDP phase-III in the state of Jharkhand. The project Highway starts from old chainage at Km 41.600 (Design chainage Km 40.500) from Hazaribagh and ends at old chainage at Km 114.000 at Ranchi. As per design chainage, the actual length of project highway is 73.799 Km. The Concession Agreement envisages that after completion of the New Carriageway, The roadway width in the main Carriageway in stretch (Km 40.500 to Km 114.000) will consist of (a) 4 – lane dual carriageway (b) 1.5 m wide Earthen Shoulder in Urban Section and 2.0 m wide Shoulder in Rural section (c) Median strip of 4.5m in rural area and 1.5m in build area. 1.2 The Site: The project highway aims at developing the two lanes to four lanes from 40.500 to 114.000 in Km including construction of Kujju bypass and Ramgarh Bypass of NH-33 in State of Jharkhand. Thus the construction package for the project includes developing the existing two lane carriageway to four lane dual carriageway configurations including strengthening of existing two lanes between Km 40.500 Km 114.00 including construction of Kujju Bypass and Ramgarh Bypass defined as “Project Highway”. 1.3 Description of the Project Highway :The project highway is generally 2 – lane and road is passing through the built areas of towns and villages enrooted. Important towns along the alignment are Ramgarh, Kujju, Mandu, and Ormanjhi. An index map and location plan of the Project Highway is given at annexed. 1.4 Referencing System:Kilometer stones are existing in entire length of the project highway. It is called the “Existing Chainage”. During topography survey with Total Station, observations made are referred to “Design Chainage”. The relationship between the “Existing Chainage” and the “Design Chainage” as per field surveys of the location of existing Km stones using the Total Station for the “Project Highway” is given at annexed. 1.5 Latitude & Longitude:Latitude and Longitude of the project corridor lies between 24o - 00 N to 23o - 21 N and 85o – 22 E to 85o – 20’ E respectively. Unihorn India Private Limited Page 2 Monthly Progress Report – 47 for the Month of June, 2014 1.6 Terrain:- The project road passes through Rolling to Hilly terrain. Many deficient horizontal curves are observed in Ghat section and needs improvement as per the design considerations. 1.7 Climate :The climatic features of the areas covered by the Project Highway are:Max temperature: 36 Degree Min. temperature: 4.0 Degree Rainfall (normal): 1400 mm 1.8 Existing Pavement Composition and condition :- As per the Pavement composition data collected from site for the Project Highway, its total thickness varies between 280 mm to 400 mm. The road pavement is weak and would require strengthening by bituminous overlays. The pavement mainly comprises of bricks overlaid by WBM and bituminous layers. The WBM course thickness varies between 110 mm to 150 mm, while that of the bituminous layers (including wearing course) between 50 mm to 150 mm. 1.9 Land:The details of existing ROW are appended. 1.10 Abutting land Use:- The Project is characterized by a mix of habituated areas and agricultural land. There are 12 villages /towns along the town Unihorn India Private Limited Page 3 Monthly Progress Report – 47 for the Month of June, 2014 1.11 Key Map:- KEY-MAP OF NH-33 RANCHI – HAZARIBAGH ROAD PROJECT Unihorn India Private Limited Page 4 Monthly Progress Report – 47 for the Month of June, 2014 Unihorn India Private Limited Page 5 Monthly Progress Report – 47 for the Month of June, 2014 2. SCOPE OF WORKS The project envisages construction of new carriageway of the length 71.80 Km/ 74.465 from Km 40.500 Hazaribagh and Km 114.000 at Ranchi in the state of Jharkhand DBFOT (Annuity) basis. Construction of Project Highway on the site set forth in Schedule – A and as per specified in Schedule - B together with provision of Schedule – C and in conformity with the specification and standards set forth in the Schedule - D of concession Agreement. Operation and maintenance of the Project Highway in accordance with the provision of Concession Agreement. 2. 1. Project Facilities: 1. Toll Plaza 2. Roadside Furniture 3. Street Lighting 4. Pedestrian Facilities 5. Landscaping and Tree Plantation 6. Rest Area 7. Truck Lay - Bays 8. Bus- Bay and Bus Shelters 9. Cattle Crossing 10. Development of Site for Wayside Amenities 11. Traffic Aid Posts 12. Medical Aid Posts 13. Vehicle Rescue Posts 14. Telecom System 15. Highway Traffic Management System Unihorn India Private Limited Page 6 Monthly Progress Report – 47 for the Month of June, 2014 2.2 Major Provisions (As per Contract):- Length of Road : 74.465 Km Length of Service Road : 11.355 Km Major Bridge : 01 No’s Minor Bridge Pipe Culvert Box /Slab Culvert : 09 No’s : 74 No’s : 75 No’s. Arch Culvert : 02 No’s Vehicle Underpass : 05 No’s Pedestrian Underpass : 02 No’s ROB : 02 No’s 2.3 Way side Amenities/Safety Provisions:- Truck/Bus Lay-Byes Way side amenities Provision for retro reflective signage’s Cross barrier, railing and plantation Provision for public toilet and drinking water at bus ways Provision for rain water harvesting. Unihorn India Private Limited Page 7 Monthly Progress Report – 47 for the Month of June, 2014 3. Contract Data Name of the Project: - Independent consultancy services for four laning of HazaribaghRanchi section of NH-33 from (Km. 40.500 to Km. 114.00) on DBFOT (Annuity) basis under NHDP phase-III in the state of Jharkhand. Client: - NHAI Length of Road: - 74.465 Km Date of Signing of Concession Agreement: - 8th -Oct-2009 Appointed Date: - 1st Aug 2010 Total Project Cost: - 625.07Crores Construction Period: - 910 days from Appointed date. VGF/Concession period / EIRR: - 18 Years commencing from the appointed date. Scheduled date of Completion: - 27th Jan 2013 Provisional (C.O.D): - 15th Sep 2012 for 58.067 Km. Financial closure: - 18th Aug 2010 Annuity Amount: - 64.08 crore Unihorn India Private Limited Page 8 Monthly Progress Report – 47 for the Month of June, 2014 4. SALIENT FEATURES SN. 1 2 Feature Provision Length 73.799 km Design Speed Plain terrain : 100 km/hr (Ruling) Rolling terrain: 80 km/hr (Ruling) Mountainous Terrain:50 km/hr (Ruling) Steep Terrain : 40 km/hr (Ruling) 3 ROW 60m 4 Roadway 2 X 7.25 m i) No. of lanes 2X2 ii) Lane Width 3.5m iii) Median Width Varies from 1.5 to 4.5 m iv) Edge Strip on Median Side 0.25m v) Paved Shoulder 1.5m vi) Unpaved Shoulder 1.0m - 2.0 m vii) Cross Slopes 2.5% (Carriage way) 2.5% (Paved Shoulder/Interlocking Paved Blocks) 3.0 % (Earthen surface) 5 Gradient i) Ruling 3.3% ii) Limiting 5.0% iii) Exceptional 6.7% 6 Bridges Major - 1 Minor - 9 Box – 75 7 Culverts Pipe – 74 Arch - 2 Major Junctions 5 No’s Minor Junctions 10 No’s 8 Junctions/Intersections 9 Railway crossings (ROB) 02 nos. 10 Service Road 11.355 Kms Bus lay byes 25 Truck lays byes 3 12 Landscaping Plantation & Turfing 13 Pavement Flexible 14 Vehicular Underpass 5 15 Pedestrian Underpass 2 16 Toll Plaza Location Km 101+250 (7 toll lanes in each directions) 11 Unihorn India Private Limited Page 9 Monthly Progress Report – 47 for the Month of June, 2014 5. PROJECT COMPLETION SCHEDULE S.N. Project Milestone Scheduled Time Period Status 1 Minimum 10% of the total cost of financial package 31/01/2011 (Within 180 days from Appointed date). Completed 2 Minimum 35% of the total cost of financial package 31/07/2011 (Within 365 days from Appointed date). Completed 3 Minimum 70% of the total cost of financial package within 730 days from Appointed date Completed 4 Scheduled 4-Laning Date 27/01/2013 (910 days from the appointed date). - 5 P.COD - 15th Sep-2012 for 58.067 Km. Unihorn India Private Limited Page 10 Monthly Progress Report – 47 for the Month of June, 2014 6. Mobilization:Independent Engineer’s Mobilization:- S.N Name Designation Mobilized On A. Key Professional : 1 V.P Jaiswal Team Leader 19/10/2011 2 Sanjay Kumar Highway cum Resident Engg. 21/6/2010 3 Pradeep Kumar Pandey Bridge Engg. 31/07/2010 4 Kishor Kumar Mishra Quality cum Material Engg. 6/8/2010 5 T.P.S Choudhary Sr. Pavement Specialist 1/10/2010 6 Sr.Bridge Design Engineer Alok Bhowmick 1/10/2010 7 Dr. T. V Krishna Murthy Road Safety Expert - 8 P.K Chaddha Financial Expert - 9 Lt. Col. Dharampal (Retd.) Legal Expert - 10 Traffic Engineer Dr. H.K Reddy - 11 Vijay Gupta Highway Design Engineer 1/10/2010 Unihorn India Private Limited Page 11 Monthly Progress Report – 47 for the Month of June, 2014 INDEPENDENT ENGINEER ORGANIZATION CHART National Highway Authority of India Senior Pavement Specialist T.P.S Choudhury Asst. Highway Engineer Mr. Sachin Kumar Resident cum Highway Engineer Er. Sanjay Kumar Asst. Highway Engineer Senor Quality cum Material Expert Er. K. K Mishra Asst. Quality cum Material Engineer Mr. Akhilesh Dwivedi Bridge/Structural Engineer Er. P.K Pandey Asst. Quality cum Material Engineer Mr. Sunil Kumar Senior Bridge Design Engineer Mr. Alok Bhomick Asst. Bridge Engineer Mr. Ranjeet Kumar Asst. Brid Enginee Mr. Dip Na Manda Road Murth fice Staff D Expert countant ice Manager mputer operator shier ice boy oto copy Operator Traffic Financ Legal Unihorn India Private Limited Page 12 Monthly Progress Report – 47 for the Month of June, 2014 6.2. STATUS OF MANPOWER OF CONCESSIONAIRE Sr. No. Position Project requirement Available at site(Nos.) 1 Project Director 1 1 2 Sr.Manager 2 1 3 Associate Manager 1 1 4 Deputy Manager 1 1 5 CAD Operator 1 1 6 Office Assistant 1 1 7 Ameen 1 1 8 Miscellaneous As per req. 3 6.3 STATUS OF MANPOWER OF PROJECT MANAGEMENT CONSULTANT (PMC) Sr. No. Position Project requirement Available at site(Nos.) 1 Team Leader 1 1 2 Bridge Engineer 1 0 3 Sr. Quality cum Material Expert 1 0 4 Highway Engineer 1 0 5 Quantity Surveyor 1 1 6 Office Manager 1 1 7 Miscellaneous As per req. 3 Unihorn India Private Limited Page 13 Monthly Progress Report – 47 for the Month of June, 2014 6.4 STATUS OF MANPOWER OF (E.P.C) Sr. No. Position Project requirement Available at site (Nos.) 1 Project Director 1 1 2 Project Manager 2 1 3 Project Co-coordinator 1 1 4 Deputy Project Managers 1 1 5 Site Engineer / Surveyors 10 5 6 Planning & Billing Engineer 1 1 7 Auto Cad Operator 2 1 8 Operators 20 10 9 Material Engineer 2 1 10 Lab Technician 3 3 11 Accounts & Administration 5 6 12 Miscellaneous Unihorn India Private Limited 30 Page 14 Monthly Progress Report – 47 for the Month of June, 2014 7 KEY PLAN OF MATERIAL SOURCE & PLANTS Unihorn India Private Limited Page 15 Monthly Progress Report – 47 for the Month of June, 2014 8. Status of Work :- (i) Detail of Site Handed Over :Existing ROW has been handed over by the PIU, NHAI Ranchi to the Concessionaire. (ii) Concessionaire 14.1 programme and progress:The Concessionaire submitted 14.1 part program (s-curve, below) Unihorn India Private Limited Page 16 Monthly Progress Report – 47 for the Month of June, 2014 (iii) Project S-Curve:- four Laning of Hazaribagh Ranchi Section of NH-33 54.800 Amount in Rs. Cr. 61.730 68.660 80.000 0.000 0.641 0.981 5.351 2.298 0.981 0.641 20.000 27.341 24.229 19.479 15.433 12.623 41.863 37.644 35.757 33.871 40.000 29.893 48.150 60.000 100.000 100.000 100.000 100.000 100.000 100.000 100.000 100.000 100.000 100.000 100.000 100.000 100.000 100.000 100.000 99.185 97.233 95.123 92.506 87.669 85.955 84.038 81.979 79.150 73.710 100.000 89.365 120.000 9.300 98.75099.00099.05099.15099.19099.240999.450 97.55098.05098.500 95.58095.78096.12096.330 94.35095.050 92.949 90.01991.029 87.539 85.389 83.189 80.280 78.250 72.590 67.580 61.080 54.060 48.210 42.310 39.200 37.830 34.022 29.893 27.341 24.229 19.479 15.433 12.623 5.351 2.297 Aug-10 Sep-10 Oct-10 Nov-10 Dec-10 Jan-11 Feb-11 Mar-11 Apr-11 May-11 Jun-11 Jul-11 Aug-11 Sep-11 Oct-11 Nov-11 Dec-11 Jan-12 Feb-12 Mar-12 Apr-12 May-12 Jun-12 Jul-12 Aug-12 Sep-12 Oct-12 Nov-12 Dec-12 Jan-13 Feb-13 Mar-13 Apr-13 May-13 Jun-13 Jul-13 Aug-13 Sep-13 Oct-13 Nov-13 Dec-13 Jan-14 Feb-14 Mar-14 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 Planned % age Month 0.640 0.340 1.316 3.054 7.271 2.810 4.046 4.750 3.112 2.552 3.978 1.886 1.886 4.220 6.287 6.650 6.930 6.930 5.050 5.440 2.829 2.059 1.917 1.714 1.696 3.141 2.617 2.110 1.952 0.815 0 0 0 0 0 0 0 0 0 0 0 0 0 45 0 Actual % age Month 0.640 0.340 1.316 3.054 7.271 2.810 4.046 4.750 3.112 2.552 4.128 3.808 1.370 3.110 5.900 5.850 7.020 6.500 5.010 5.660 2.030 2.909 2.200 2.150 2.480 1.010 1.920 1.401 0.700 0.530 0.200 0.340 0.21 1.22 0.5 0.45 0.25 0.25 0.05 0.1 0.04 0.05 0.06 0.15 Planned % age Cumulative 0.641 0.981 2.298 5.351 12.623 15.433 19.479 24.229 27.341 29.893 33.871 35.757 37.644 41.863 48.150 54.800 61.730 68.660 73.710 79.150 81.979 84.038 85.955 87.669 89.365 92.506 95.123 97.233 99.185 100.000 100.000 100.000 100.000 100.000 100.000 100.000 100.000 100.000 100.000 100.000 100.000 100.000 100.000 100.000 Actual % age Cumulative 0.641 0.981 2.297 5.351 12.623 15.433 19.479 24.229 27.341 29.893 34.022 37.830 39.200 42.310 48.210 54.060 61.080 67.580 72.590 78.250 80.280 83.189 85.389 87.539 90.019 91.029 92.949 94.350 95.050 95.580 95.780 96.120 96.330 97.550 98.050 98.500 98.750 99.000 99.050 99.150 99.190 99.240 99.300 99.450 Remarks Unihorn India Private Limited Page 17 Monthly Progress Report – 47 for the Month of June, 2014 9. STATUS OF CHANGE OF SCOP No Change. 10. STATUS OF SUSPENSION Nil 11. Details of Villages/Towns S.No. 1. 2. 3. 4. 5. 6. 7. 8. 9. 10. 11. 12. Name of Village/Town Mukund Ganj Babhanabbe Demotand Village Morangi Village Charhi Village Mandu Jorakaram Hasegarha Kujju Bharesh Nagar Ranchi Road Ramgarh Name of District Hazaribagh Hazaribagh Hazaribagh Hazaribagh Hazaribagh Hazaribagh Hazaribagh Hazaribagh Ramgarh Ramgarh Ramgarh Ramgarh Location (Chainage) From (Km.) 42.000 42.500 44.250 47.250 54.300 61.950 67.300 69.000 73.200 77.500 81.400 83.400 Side To (Km.) 43.100 Right Right Right Both Left Right Both Both Left Both Left Both 46.450 48.850 56.800 65.550 76.000 80.100 82.200 88.250 12.Details of Existing Bridges S. No 1 2 3 4 5 6 7 8 9 10 Bridge No. Location/Chainage (Km) Type of Structure Major 86/1 Minor 58/1 Minor 62/1 Minor 71/1 Minor 85/2 Minor 105/1 Minor 109/1 Minor 110/1 Minor 114/1 Minor 116/2 Damodar Bridge 85.810 Bokaro Bridge 57.794 Dudhi Bridge 61.720 Chautham Bridge 71.020 Ramgarh Bypass 84.903 Bhenra Bridge 104.036 Bania Nallah Bridge 108.211 Doma Bridge 109.809 Sapahi Bridge 113.099 Rangoori Bridge 115.582 RCC t-beam & Slab RCC T-beam & Slab RCC T- Beam & Slab Unihorn India Private Limited RCC Slab RCC T- beam Slab RCC T-beam Slab RCC Slab RCC T-Beam & Slab RCC T-Beam & Slab RCC Slab Span Details No. X length (m) Total length (m) Carriage way width (m) 12x20.25 243 7.5 3x13.5 40.5 7.5 2x17 34 7.5 4x8.75 35 7.5 1x17.0 17.5 7.5 2x13 26 7.5 3x7 21 7.5 1x27 27 7.5 2x19.5 39 7.5 3x9 27 7.5 Remarks/O bservation s Page 18 Monthly Progress Report – 47 for the Month of June, 2014 13 Details of Existing Culverts (i)Pipe Culverts Sl. No. 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 CD No. Location (Km) Formation Height Vent Ht. (m) Diameter (m) Existing Width 42/1 42/2 46/1 52/1 58/1 58/2 58/3 59/1 59/2 59/3 60/ 70/1 70/2 74/1 74/2 74/3 74/4 83/1 89/1 90/1 91/1 91/2 91/3 91/4 92/1 92/2 92/3 92/4 92/5 92/6 93/1 93/2 93/3 94/1 94/2 94/3 94/4 94/5 94/6 95/1 95/2 95/3 96/1 96/2 96/3 96/4 96/5 98/1 98/2 100/1 101/1 101/2 102/1 103/1 103/2 108/1 110/1 111/1 114/1 41.600 41.650 45.100 51.250 57.650 57.825 57.900 58.090 58.455 58.720 59.120 69.710 69.818 73.160 73.313 73.447 73.570 82.265 88.925 89.100 90.100 90.560 90.740 90.950 91.100 91.200 91.500 91.675 91.725 91.950 92.050 92.565 92.750 93.625 93.700 93.780 93.850 93.875 93.960 94.325 94.504 94.950 95.260 95.300 95.500 95.650 95.950 97.200 97.800 99.950 100.100 100.800 101.500 102.600 102.700 107.325 109.870 110.700 113.180 1.5 1.5 2 4 4 4 2.9 3 2.5 2 2.1 3.2 3.2 2.7 2.5 2.5 2.5 5.5 2 3 2.5 3 1 4 3 3 2 2.5 2 3 2 2 3 4 6 4.5 2 2 4 4 4 4 2.1 2 2 2.5 2.5 1.5 2 1.5 1.5 1.5 2 2.5 2.5 2 3 5 2.5 0.9 0.9 0.9 0.9 1.2 1.6 1.2 1.2 0.9 0.9 1 1.2 1.2 09 0.9 0.9 0.9 1.2 1.2 1.2 1.2 1.2 0.9 0.9 1.2 0.9 0.9 0.9 0.8 0.9 1.2 0.9 0.8 0.9 1.2 1.2 1.2 1.2 1.2 0.9 0.9 0.9 0.9 0.9 0.9 0.9 0.9 1 1 1 0.9 0.9 0.9 0.9 0.9 1.2 0.9 1.2 1.2 2x0.9 2x0.9 0.9 2x0.9 3x1.2 4x1.2 1.2 3x1.2 0.9 0.9 1 1.2 1.2 12.00 0.9 0.9 0.9 1.2 2x1.2 1.2 1.2 1.2 0.9 0.9 1.2 0.9 0.9 0.9 0.8 0.9 1.2 0.9 0.8 0.9 1.2 1.2 1.2 1.2 1.2 0.9 0.9 0.9 0.9 0.9 0.9 0.9 0.9 2x1.5 1 1 0.9 0.9 0.9 0.9 0.9 1.2 0.9 4x1.2 1.2 22 22 20 25 22.5 22.5 17.5 25 15 12.5 15 20 20 20 17.5 14.4 15 25 16 12 17.5 22 17.5 17.5 20 17.5 18 20 20 24 20 18 18 22 22 22 20 20 20 21 24 20 20 20 20 20 20 20 20 14.8 17.5 20 20 20 20 17.5 17 33 17.5 Unihorn India Private Limited Page 19 Monthly Progress Report – 47 for the Month of June, 2014 (ii) Arch Culverts S. No. Culvert Km/No Existing Chainage (Km) Arch Thickness Formation Height (m) 1 44/1 43.600 0.5 3 2 93/1 92.300 0.5 3 93/2 92.450 4 94/1 5 94/2 Vent Height (m) Clear Span (m) Existing 2 2.5 10 5 4 3.2 16.2 0.5 7 3 3 14 93.315 0.5 3 1 0.9 11 93.350 0.5 5 3 3 16 Unihorn India Private Limited Page 20 Monthly Progress Report – 47 for the Month of June, 2014 (iii). Slab Culverts/ Box Culverts S. No. 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 Culvert Km/No 44/1 44/2 43/1 46/1 47/1 47/2 48/1 48/2 50/1 52/1 52/2 52/3 52/4 53/1 53/2 54/1 54/2 58/1 63/1 64/1 64/2 65/1 65/2 66/1 66/2 67/1 69/1 69/2 69/3 70/1 70/2 70/3 71/1 71/2 72/1 72/2 74/1 74/2 74/3 75/1 75/2 77/1 79/1 80/1 80/2 80/3 81/1 84/1 84/2 89/1 90/1 96/1 100/1 100/2 101/1 106/1 110/1 111/1 Existing Chainage (Km) 43.225 43.848 44.650 45.800 46.550 46.950 47.800 47.950 49.100 51.200 51.500 51.800 51.950 52.100 52.400 53.100 53.500 57.800 62.200 63.550 63.700 64.200 64.400 65.500 65.900 66.200 68.200 68.400 68.700 69.190 69.350 69.500 70.900 70.990 71.200 71.500 73.100 73.500 73.600 74.500 74.550 76.100 78.800 79.300 79.500 79.800 80.450 83.400 83.750 88.200 89.700 95.690 99.500 99.750 100.800 105.375 109.400 110.950 Unihorn India Private Limited Arch Thickness 0.2 0.5 0.2 0.2 0.2 0.2 0.2 0.2 0.3 0.2 0.2 0.2 0.3 0.2 0.25 0.2 0.2 0.2 0.2 0.3 0.3 0.3 0.3 1.5 0.3 0.3 0.25 0.2 0.2 0.25 0.2 0.25 0.3 0.25 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.2 0.4 0.25 0.2 0.2 0.2 0.4 0.3 0.25 0.25 0.3 0.3 3 0.3 0.5 0.3 0.3 Formation Height (m) 2 3.5 3 2 1.5 2 1 2 2.5 3 1.5 1.5 5.5 3 10 2.5 3 2.5 2 1.9 2.2 2 2 0.8 1 1.2 1.5 1 1 1.8 1.8 2.1 4 3.7 1.7 6 1 1 1.5 1.5 1.5 1 6 1.2 1 1 1.5 6 2.1 1.4 1.5 5.6 2.2 3.1 2.5 5 4 3.5 Vent Height m 1 3 1.9 1 1 0.9 0.7 1 107 0.9 0.8 1 3 2 2 1.5 1.3 1.2 1 1.2 1.5 1 1 1 0.5 0.8 1.2 0.5 0.5 1.6 1.7 1.9 3.5 3.4 1.4 3 0.5 0.5 1 1 0.7 0.5 4.8 0.8 0.5 0.5 0.8 5.5 1.7 0.6 1 1.5 1.9 2.8 1.5 4.5 3 3 Clear Span (m) 1.5 3 1 1 1 1 1 1 2.3 1 0.8 1 1.3 1 1.5 1.2 1 1 1 1.5 1.2 1 1 1 1 1.5 1 0.9 1 1 1.3 1.6 3.1 3 1 6 1 1 0.8 1 0.9 1.2 6 1 1.5 1 1 6 1.7 1.3 1.2 1.5 1.5 3.5 2.5 6 3 3 Existing 12.5 9.5 12 12 12.6 13 11.5 12.6 9 12 11.2 12 11.6 11 30 11 11 12 12 12 11.4 12 12 11 12 12 11 11.5 12 11 11.5 11.5 12.5 13.6 17 15 12 12 10 13 12 11.5 12 11.5 10 12 12 11.5 13 11 12 11.5 15.1 21.5 12 12.2 14 11 Page 21 Monthly Progress Report – 47 for the Month of June, 2014 14 Existing Major Junctions Table (A) S.No. Km Section Type Place Joining road Proposed 1 84.750 NH 33 3 Legged Ramgarh (Bokaro Chowk) NH 23 3 Legged 2 85.880 NH 33 4 Legged Ramgarh Chowk Connection road to NH 23 & SH 4 Legged 15 Existing Minor Junctions Table (B) Sl.No. Km Section Type Place Joining road Proposed 1 43.300 NH 33 3 Legged Mukundganj R.E.O. Road 3 Legged 2 46.200 NH 33 3 Legged Sungari Tar R.E.O. Road 3 Legged 3 49.250 NH 33 3 Legged Demo Tar R.E.O. Road 3 Legged 4 56.100 NH 33 3 Legged West Bokaro S.H Road 3 Legged 5 63.275 NH 33 3 Legged Mandu R.E.O Road 3 Legged 6 75.850 NH 33 4 Legged Kujju CCL Road 4Legged 7 83.500 NH 33 3 Legged Giddi Nai Sarai 3 Legged 8 86.500 NH 33 3 Legged Ramgarh Bazar Connection road to NH 23 3 Legged 9 103.250 NH 33 3 Legged Sikkidiri SH Road 3 Legged 10 108.400 NH 33 3 Legged Shastri Chowk R.E.O Road 3 Legged 11 112.300 NH 33 3 Legged Rukka R.E.O Road 3 Legged 12 113.350 NH 33 3 Legged Rukka Dam R.E.O Road 3 Legged Unihorn India Private Limited Page 22 Monthly Progress Report – 47 for the Month of June, 2014 16. Vehicular Underpasses Village Road Rectangular Box 1 × 5.00 6.00 M 2 56.870 57.100 Village Road Rectangular Box 1 × 5.00 6.00 M 3 67.300 67.820 Village Road Rectangular Box 1 × 5.00 6.00 M 4 74.000 73.600 Village Road Rectangular Box 1 × 5.00 6.00 M 5 85.800 85.900 NH- 23 Rectangular Box 1 × 5.00 6.00 M Proposed Spam Arrangement Proposed Structure Type Proposed Structural Configuration 54.840 Design Chainage 54.350 Existing Chainage 1 S.No. Name of Intersecting Roads Total of the Structure (As per Concession Agreement) 17. Pedestrian Underpasses Total of the Structure Proposed Spam Arrangement Proposed Structure Type Proposed Structural Configuration Name of Intersecting Roads Design Chainage Existing Chainage S.No. (As per Concession Agreement) 1 64.000 64.300 Village Road Rectangular Box 1 × 3.50 M 4.25 2 83.050 83.220 Village Road Rectangular Box 1 × 3.50 M 4.25 Unihorn India Private Limited Page 23 Monthly Progress Report – 47 for the Month of June, 2014 18. Cross Section Type Along the Project Corridor:Designed Chainage(km) From To 41+600 43+584 43+734 44+186 44+286 45+884 46+035 46+685 46+835 51+065 51+700 52+250 53+855 55+485 55+600 56+850 56+993 63+250 63+398 64+729 64+879 66+675 67+000 70+500 71+500 71+879 76+008 81+004 81+479 86+479 87+097 89+956 93+280 93+480 94+100 94+340 94+500 94+610 94+735 94+950 95+550 95+650 95+965 96+025 104+066 104+266 104+995 105+195 110+155 110+380 111+830 112+023 112+548 43+584 43+734 44+186 44+286 45+884 46+035 46+685 46+835 51+065 51+700 52+250 53+855 55+485 55+600 56+850 56+993 63+250 63+398 64+729 64+879 66+675 67+000 70+500 71+500 71+879 76+008 81+004 81+479 86+972 87+097 89+956 93+280 93+480 94+100 94+340 94+500 94+610 94+735 94+950 95+550 95+650 95+965 96+025 104+066 104+266 104+995 105+195 110+155 110+380 111+830 112.023 112+548 112+760 Length (m) Drg No. Remarks 1,984.0 150.0 452.0 100.0 1598.0 151.0 650.0 150.0 4230.0 635.0 550.0 1605.0 1630.0 115.0 1250.0 143.0 6257.0 148.0 1331.0 150.0 1796.0 325.0 3500.0 1000.0 379.0 4129.0 4996.0 475.0 5493.0 125.0 2859.0 3324.0 200.0 620.0 240.0 160.0 110.0 125.0 215.0 600.0 100.0 315.0 60.0 8041.0 200.0 729.0 200.0 4960.0 225.0 1450.0 193.0 525.0 192.0 CS/02 CS/06 CS/03 CS/06 CS/02 CS/06 CS/03 CS/06 CS/02 CS/05A CS/05B CS/05A CS/02 CS/06 CS/03 CS/06 CS/02 CS/06 CS/03 CS/06 CS/02 CS/05B CS/02 CS/05A CS/02 CS/04 CS/02 CS/06 CS/03 CS/06 CS/02 CS/05A CS/05B CS/05A CS/05B CS/05A CS/05B CS/05A CS/05B CS/05A CS/05B CS/05A CS/05B CS/02 CS/06 CS/03 CS/06 CS/02 CS/06 CS/03 CS/06 CS/02 CS/06 Right Side Widening In Transition Concentric Widening in Urban Areas In Transition Right Side Widening In Transition Concentric Widening in Urban Areas In Transition Right Side Widening In Ghat Portion Realignment in Ghat In Ghat Portion Right Side Widening In Transition Concentric Widening in Urban Areas In Transition Right Side Widening In Transition Concentric Widening in Urban Areas In Transition Right Side Widening Realignment in Ghat Right Side Widening In Ghat portion Right Side Widening In By Pass Right Side Widening In Transition Concentric Widening in Urban Areas In Transition Right Side Widening In Ghat portion Right Side Widening In Ghat Portion Realignment in Ghat In Ghat Portion Realignment in Ghat In Ghat portion Realignment in Ghat In Ghat portion Realignment in Ghat In Ghat Portion Realignment in Ghat Right Side Widening In Transition Concentric Widening in Urban Areas In Transition Right Side Widening In Transition Concentric Widening in Urban Areas In Transition Right Side Widening In Transition Change in widening schedule can be made by the concessionaire subject to the approval of IC/NHAI. Unihorn India Private Limited Page 24 Monthly Progress Report – 47 for the Month of June, 2014 19. SERVICE ROAD Service Road Locations Sl. No (As per Concession Agreement) Proposed Chainage(km) From(km.) To(km.) Length (Km.) Area 1. 43.734 44.186 0.452 Mukund Ganj Village 2. 46.035 46.685 0.650 Demotand Village 3. 55.600 56.850 1.250 Charhi Village 4. 63.398 64.729 1.331 Mandu Village 5. 81.479 86.972 5.493 Ranchi Road,Nai Sarai and Ramgarh Town 6. 104.266 104.995 0.729 Ormanjhi Block 7 110.380 TOTAL 111.830 1.450 11.355 Irba Village The concessionaire shall provide total 11.355 Km length of service roads. 20. JUNCTIONS a. Major Road Junctions (As per Concession Agreement) S.No. Chainage(km) Type Of Junctions Place Category Of Road 1 40.500 3 Legged End Point of Hazaribagh bypass NH-33 2 72.800 3 Legged Start Point Of Kujju Bypass NH-33 3 76.000 3 Legged End Point Of Kujju bypass NH-33 4 84.800 3 Legged Thana Chowk Ramgarh NH-23 5 85.900 4 Legged Ramgarh Chowk Connecting road to NH23 and SH b. Minor Road Junctions (As per Concession Agreement) S.No. Chainage(km) Place Joining Road Proposed 1 2 3 4 5 6 7 8 9 10 43.300 47.500 49.950 56.100 63.275 83.470 103.250 108.400 112.300 113.350 Mukundganj Sungari Tar Demo Tar West Bokaro Mandu Giddy Sikkidiri Shastri Chowk Rukka Rukka Dam R.E.O Road R.E.O Road R.E.O Road S.H Road R.E.O Road Nai Sarai R.E.O Road R.E.O Road R.E.O Road R.E.O Road 3 Legged 3 Legged 3 Legged 3 Legged 3 Legged 3 Legged 3 Legged 3 Legged 3 Legged 2 Legged Unihorn India Private Limited Page 25 Monthly Progress Report – 47 for the Month of June, 2014 21. Truck Lay Byes (As per Concession Agreement) Location Proposed Chainage (KM) Near Mandu Village In Kujju By Pass Km 60.381 Km. 75.000 Near Ormanjhi Block Km. 101.915 22. Bus Lay Byes (As per Concession Agreement) Sl No. 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 Location Near Morangi Near Morangi (Hatiyari Mor) 15 Mile Mandu Mandu Haseghdha Bonga ( Bhareach Nagar/Sandi) Ramgarh Near Burha Khukhra Lalki Ghat Shahidm Smark (Khatanga Patar Khudia) Chuttupalu Bankheta Piska More Piska More Palu Chai Bagan Ukrid More Ormanjhi Ormanjhi (Near Thana) Near Ormanjhi Chakla (Ormanjhi) Chakla Near Ormanjhi Irba Irba Vikas Unihorn India Private Limited Existing Chainage (Km) Side 46.240 49.950 58.300 63.100 63.300 70.700 77.900 85.820 90.820 LHS LHS RHS RHS LHS RHS LHS RHS RHS 92.300 LHS 95.050 LHS 97.310 98.500 100.300 100.380 LHS RHS RHS LHS 103.605 104.300 106.500 107.300 109.100 109.100 109.250 110.950 112.500 113.600 LHS RHS LHS RHS RHS RHS LHS RHS LHS LHS Page 26 Monthly Progress Report – 47 for the Month of June, 2014 23. Project Accelerated Programme Unihorn India Private Limited Page 27 Monthly Progress Report – 47 for the Month of June, 2014 24. Machinery Deployed at Site:- Mobilizations for the Major Plants and Equipments Mobilizations for the Major Plants and Equipments Si. N. Name of Equipment/Machinery 1 WMM Plants 2 Concrete batching plants 3 Project requirement Available at site (Nos.) 1 (200 TPH) 1 (200 TPH) 1 (30 Cum/Hrs.) 1 (30 Cum/Hrs.) ‘Metso’ Crusher 1 (200 TPH) 1 (200 TPH) 4 Hot Mix Plant 1 (160 TPH) 1 (160 TPH) 5 Excavators 2 (Ex-220 and 260) 2 6 Motor Grader 1 2 7 Crane 1 (60 MT) 1 (60 MT) 8 Generator Set 3 5 9 Dumper 5 15 10 Transit mixer 4 4 11 Sensor Paver 1 1 12 Hydra Cranes 1 2 13 Tandem Roller 1 1 14 Vibratory Roller 1 1 15 Pneumatic Tyre Roller 1 1 16 Loaders 2 2 17 Dozers 2 2 18 Kerb Laying machine 1 1 Unihorn India Private Limited Page 28 Monthly Progress Report – 47 for the Month of June, 2014 25. Emergency Service Location along the Project Highway. A. Major Hospitals & Ambulance Services Sr. Description No. 1 NHAI Ambulance Service -1 (41+600 to 77+000) 2 NHAI Ambulance Service-2 (93+000 to 115+399) 3 Hazaribagh Sadar Hospital, Hazaribagh 4 Govt. General Hospital, Piska 5 Govt General Hospital, Ramgarh 6 Apollo Hospital, Ormanjhi 7 RIMS,Ranchi B. Police stations Sr. Description No. 1 Ormanji Sub Inspector 2 Ramgarh Sub Inspector 3 Kuju Sub Inspector 4 Mandu Sub Inspector 5 Charhi Sub Inspector 6 Mukhtil Sub Inspector C. Highway Patrol Units Sr. Description No. i) IL&FS HighWay Patrol 1 Route Patrolling -1 (41+600 to 77+000) 2 Route Patrolling -2 (93+000 to 115+399) D. Fire Stations Sr. Description No. 1 Ranchi 2 Ramgarh E. Crane and Towing Services Sr. Description No. 1 Crane and Towing Operator Unihorn India Private Limited Contact No 7781014184 7781002285 94311-86077 0651-3241649 08518-255499 06513041555 06512541533 Contact No 9431706183 9431706319 9431413894 9431706234 9472618219 9431706309 Contact No 9771421931 7781002284 Contact No 0651-2490706 06553-225500 Contact No 9771954692 Page 29 Monthly Progress Report – 47 for the Month of June, 2014 26. Linear Progress (Road Works) Main Carriageway R/S Linear Progress (Road Works) Main Carriageway R/S Without Ramgarh Bypass Activity Description Unit Total Length Completed till Last Month Balance Main Carriageway Four Lane C&G Km 58.067 58.067 0 Embankment Km 58.067 58.067 0 Sub-Grade GSB WMM 1st Layer WMM Top Layer DBM 1st DBM top BC Km Km 58.067 58.067 58.067 58.067 0 0 Km 58.067 58.067 0 Km 58.067 58.067 0 Km Km Km 58.067 58.067 58.067 58.067 58.067 58.067 0 0 0 Ramgarh Bypass Activity Description Unit C&G Km Embankment Km Sub-Grade Km GSB Km WMM 1st Layer WMM Top Layer Km Km DBM 1st Km DBM top Km BC KM Unihorn India Private Limited Total Length Completed till Last Month Balance Main Carriageway Four Lane 15.72 15.72 0.00 15.72 15.72 0.00 15.72 15.72 0.00 15.72 15.72 0.00 15.72 15.72 0.00 15.72 15.72 0.00 15.72 15.72 0.00 15.72 15.72 0.00 15.72 15.72 0.00 Page 30 Monthly Progress Report – 47 for the Month of June, 2014 27. Progress of CD & Structure Works. (Month of June 2014) Sl. No. Structure Total No’s of Structure Work Under Progress Work Completed Remarks 1 Major Bridge 01 - 01 - 2 Minor Bridge 09 - 09 - 3 Culverts 152 - 152 - 4 ROB 02 - 02 - 5 Underpasses 07 - 5 VUP & 2 PUP Completed - 6 Grade Separator 01 - 01 - 28. PHYSICAL PROGRESS: (The Progress of the works as on June 2014) Description Achieved Cumulative Physical Progress 99.80% Unihorn India Private Limited Page 31 Monthly Progress Report – 47 for the Month of June, 2014 29.1 Progress Details of Structure: Progress Chart Structure Box Culvert (Package -2) Sl. No. Chainage Strl.No Proposal Section 1 111+705 112/2 New const. 3x3 Completed L&R complete. 2 111+372 112/1 New const. 3x3 Completed L&R complete. 3 107+557 108/1 New const. 6x4.5 Completed L&R complete. 4 104+667 105/2 New const. 2x2 Completed L&R complete. 5 101+920 102/3 New const. 2x2 Completed L&R complete. 6 101+533 102/2 New const. 2x2 Completed L&R complete. 7 97+766 98/5 New const. 2.0x2.0 Completed L&R complete. 8 97+119 98/1 New const. 3.0X3.0 Completed L&R complete. Excv. PCC Raft Wall 1st Wall 2nd Slab RWL Remarks 9 96+309 97/3 New const. 5.0x6.0 Completed L&R complete. 10 96+239 97/2 New const. 2.0x2.0 Completed L&R complete. 11 95+234 96/1 New const. 3.0X3.0 Completed L&R complete. 12 94+778 95/7 New const. 3.2x4.0 Completed L&R complete. 13 93+082 94/1 New const. 1x2.5x2.5 Completed 14 92+772 93/1 New 1x2.5x2.6 Completed 15 91+890 92/3A New const. 1x2.5x2.5 Completed 16 91+711 92/3 New const. 1x2.5x2.5 Completed 17 91+410 92/2 New const. 1x2.5x2.5 Completed 18 91+300 92/1 New const. 1x2.5x2.5 Completed 19 90+702 91/3 New const. 1x2.5x2.5 Completed 20 90+132 91/1A New const. 1x2.5x2.5 Completed 21 89+698 90/2 New const. 1x2.5x2.5 Completed 22 89+306 90/1 New const. 1x2.5x2.5 Completed 23 88+720 89/3 New const. 2x2.5x2.5 Completed 24 83+480 84/2 New const. 2.5x2.5 Completed 25 83+280 84/1A New const. 2.5x2.5 Completed 26 81+840 82/3 New const. 2x2.5x2.5 Completed 27 81+248 82/2 New const. 1x2.5x2.5 Completed 28 80+580 81/2 New const. 1x2.5x2.5 Completed 29 79+720 80/4 New const. 2.5x2.5 Completed 30 76+579 77/2A New const. 1.5x1.5 Completed 31 76+579 77/2 New const. 1.5x1.5 Completed 32 76+130 77/1 New const. 2x2 Completed 33 75+840 76/3 New const. 6x4.5 Completed 34 75+439 76/2 New const. 3x3 Completed 35 75+315 76/1 New const. 2x2 Completed Unihorn India Private Limited Ramgarh Bypass Kujju Bypass Page 32 Monthly Progress Report – 47 for the Month of June, 2014 36 73+406 74/1 New const. 2.5x2.5 Completed 37 70+240 71/3 New const. 2x2 Completed L&R complete. 38 64+375 65/2 New const. 2.5x2 Completed L&R complete. 39 54+000 55/1 New const. 2x2.5 Completed L&R complete. 40 53+472 54/4 New const. 2x2 Completed L&R complete. 41 53+257 54/3 New const. 2x2 Completed L&R complete. 42 50+050 51/1 New const. 2.5x2 Completed L&R complete. 43 44+927 45/3 New const. 3x3.5 Completed L&R complete. 44 44+706 45/2 New const. 3x3 Completed L&R complete. Pipe Culvert (Section-A) HW ist lift HW 3rd &final lift Sl. No. Chainage Strl.No Proposal Section 1 115+360 116/1 widening 1x1200 Completed RHS &completed. 2 112+860 113/2 widening 4x1200 Completed RHS & LHS 3 112+043 113/1 widening 1x900 Completed RHS & LHS 4 110+830 111/1 New 1x1200 Completed RHS & LHS 5 109+507 110/2 widening 1x1200 Completed RHS & LHS 6 109+411 110/1 New 1x1200 Completed RHS & LHS 7 103+477 104/1 widening 1x900 Completed RHS & LHS 8 102+763 103/3 New 1x1200 Completed RHS & LHS 9 102+249 103/2 widening 1x900 Completed RHS &completed. 10 102+132 103/1 widening 1x900 Completed RHS &completed. 11 101+310 102/1A New 1x1200 Completed RHS & LHS 12 101+169 102/1 widening 1x900 Completed RHS & LHS 13 100+691 101/3 widening 1x1200 Completed RHS & LHS 14 100+507 101/2 widening 1x900 Completed RHS &completed. 15 100+315 101/1 widening 1x900 Completed RHS &completed. 16 99+426 100/1 widening 1x900 Completed RHS & LHS 17 98+640 99/4 Widen & Retain 1x900 Completed LHS &completed. 18 98+515 99/3 New 1x1200 Completed RHS & LHS 19 98+210 99/2 New 1x1200 Completed RHS & LHS 20 98+105 99/1 New 2x1200 Completed RHS & LHS 21 97+945 98/6 New 1x1200 Completed RHS & LHS 22 97+680 98/4 New 1x1200 Completed RHS & LHS 23 97+484 98/3 New 1x1200 Completed RHS & LHS 24 97+272 98/2 New 2x1200 Completed RHS & LHS 25 96+808 97/9 Widen & Retain 1x1200 Completed RHS & LHS 26 96+677 97/8 widening 1x1200 Completed RHS &completed. 27 96+601 97/7 widening 1x1200 Completed RHS &completed. 28 96+560 97/6 widening 1x1200 Completed RHS &completed. 29 96+482 97/5 widening 1x1200 Completed RHS & LHS 30 96+413 97/4 widening 2x1200 Completed RHS & LHS 31 96+835 97/10 widening 1x1200 Completed RHS & LHS 32 96+108 97/1 1x1200 Completed RHS & LHS Unihorn India Private Limited Excv. PCC Pipe Laying HW 2nd lift Encase/creddle conc. Remarks Page 33 Monthly Progress Report – 47 for the Month of June, 2014 33 95+666 96/4 1x1200 Completed RHS & LHS 34 95+555 96/3 1x1200 Completed RHS & LHS 35 95+417 96/2 New 1x1200 Completed RHS & LHS 36 94+880 95/9 Retained 1x1200 Completed RHS & LHS 37 94+832 95/8 New 1x1200 Completed RHS & LHS 38 94+656 95/6 New 1x1200 Completed RHS & LHS 39 94+618 95/5 widening 1x900 Completed RHS & LHS 40 94+465 95/4 widening 1x900 Completed RHS & LHS 41 94+331 95/3 widening 1x900 Completed RHS & comp. 42 94+168 95/2 widening 1x1200 Completed RHS & LHS 43 94+993 95/10 widening 1x1200 Completed RHS & LHS 44 94+063 95/1 widening 1x1200 Completed RHS & LHS 45 93+918 94/5 widening 1x900 Completed RHS & comp. 46 93+709 94/4 widening 1x900 Completed RHS & LHS 47 93+483 94/3 widening 1x1200 Completed RHS & comp. 48 88+545 89/2 New 2x1200 Completed 49 88+199 89/1 New 2x1200 Completed 50 87+670 88/1 New 2x1200 Completed 51 86+983 87/3 New 2x1200 Completed 52 86+593 87/2 New 2x1200 Completed 53 86+450 87/1 New 3x1200 Completed 54 85+570 86/1 New 2x1200 Completed 55 84+212 85/1 New 2x1200 Completed 56 83+710 84/4 New 2x1200 Completed 57 83+120 84/1 New 2x1200 Completed 58 82+700 83/3 New 2x1200 Completed 59 82+177 83/1 New 3x1200 Completed 60 80+082 81/1 New 2x1200 Completed 61 79+880 80/5 New 2x1200 Completed 62 79+355 80/3 New 2x1200 Completed 63 79+000 80/1 New 2x1200 Completed 64 78+460 79/2 New 2x1200 Completed 65 78+218 79/1 New 2x1200 Completed 66 74+310 75/3 New 1x1200 Completed 67 74+302 75/2A New 2x1200 Completed 68 74+214 75/2 New 3x1200 Completed 69 74+100 75/1A New 1x1200 Completed 70 73+975 74/2 New 1x1200 Completed 71 72+800 73/1 New 3x1200 Completed 72 71+285 72/2 1x1200 Completed RHS & LHS 73 70+620 71/5 1x1200 Completed RHS & LHS 74 70+520 71/4 1x1200 Completed RHS & LHS 75 70+095 71/2 2x1200 Completed RHS & LHS 76 69+995 71/1 2x1200 Completed RHS & LHS Unihorn India Private Limited Kujju Bypass Page 34 Monthly Progress Report – 47 for the Month of June, 2014 77 69+380 70/2 2x1200 Completed RHS & LHS 78 69+100 70/1 1x1200 Completed RHS & LHS 79 68+890 69/2 1X1200 Completed RHS & LHS 80 66+900 67/3 2x1200 Completed RHS & LHS 81 66+575 67/2 1x1200 Completed RHS & LHS 82 66+200 67/1 1x1200 Completed RHS & LHS 83 64+828 65/4 1x1200 Completed RHS & LHS 84 64+217 65/1 2x1200 Completed RHS & LHS 85 63+015 64/1 1x1200 Completed RHS & LHS 86 59+973 60/1 widening 1x1200 Completed RHS & LHS 87 58+940 59/5 widening 3x1200 Completed RHS & LHS 88 58+752 59/3 widening 1x1200 Completed RHS & LHS 89 58+670 59/2 widening 4x1200 Completed RHS & LHS 90 58+500 59/1 widening 3x1200 Completed RHS & LHS 91 57+610 58/1 1x1200 Completed RHS & LHS 92 54+300 55/3 1x1200 Completed RHS & LHS 93 54+175 55/2 1x1200 Completed RHS & LHS 94 53+155 54/2 1x1200 Completed RHS & LHS 95 53+005 54/1 1x1200 Completed RHS & LHS 96 52+695 53/4 1x1200 Completed RHS & LHS 97 52+375 53/3 1x1200 Completed RHS & LHS 98 52+298 53/2 2x1200 Completed RHS & LHS 99 52+115 53/1 1x1200 Completed RHS & LHS 100 48+835 49/2 1x1200 Completed RHS & LHS 101 48+216 49/1 1x1200 Completed RHS & LHS 102 47+565 48/1 1x1200 Completed RHS& LHS 103 46+940 47/2 1x1200 Completed RHS& LHS 104 46+356 47/1 1x1200 Completed RHS& LHS 105 45+903 46/1 2x1200 Completed RHS& LHS 106 44+375 45/1 2x1200 Completed RHS& LHS 107 43+173 44/1 1x1200 Completed RHS& LHS 108 42+828 43/1 2x1200 Completed RHS& LHS Unihorn India Private Limited Page 35 Monthly Progress Report – 47 for the Month of June, 2014 29.2 Details of Minor Bridge 57+794 (Bokaro Bridge) 61+720 (Dudhi Bridge) 71+020 (Chautham Bridge) 84+903 104+036 (Bhenra Bridge) 108+219 (Baniya Nala Bridge) 58/1 62/1 72/1 85/2 105/1 109/1 Unihorn India Private Limited Part of Str. Chainage Str. No. RHS Wall Lifts Exc. PCC Raft A1 c c P1 c P2 Cap Pedestal & Bearing RCC TBeam Girder Slab Crash Barrier & Broken Kerb 1st 2nd 3rd 4th 5th c c c c c c c c c C c c c c c c c c c c c C c c c c c c c c c c c c c c A2 c c c c c c c c c C c c c A1 c c c c c c c c c C C C C P1 c c c c c c c c c c c c c A2 c c c c c c c c c c c c c A1 C C C C C C C C C C C C C P1 C C C C C C C C C C C C C A2 C C C C C C C C C C C C C A1 c C C c c c c c C c C c c P1 c c c c c c c c c c c c c A2 c c c c C C C C C c C c c A1 c c c c c C C C C C c c C P1 c c c c c c c c c c c c c A2 c C C C C C C C c C C C c A1 c c c c c c c C C c c c c A2 c c c c C C C C C c c c c Remarks Completed Completed Completed Completed Completed Completed Page 36 Monthly Progress Report – 47 for the Month of June, 2014 109+820 (Doma Bridge) 110/3 113+099 (Sapahi Bridge) 114/1 115+595 (Rangoori Bridge) 116/2 A1 c c c C C C C C c P1 c c c c c c c c c c c c c A2 c c c c c c c c c c c c c A1 c c c c c c c c c c c c c P1 c c c c c c c c c c c c c A2 c c c c c c c c c c c c c A1 C C C C c C C C C c C c c P1 C C C C c C C C C c C c c P2 C C C C c C C C C c C c c A2 C C C C c C C C C c C c c Completed Completed Completed 29.3 Details of Major Bridge: 86/2 Part of Str. Str. No. RHS Wall Lifts Exc. PCC Raft A1 c c p1 c p2 Cap Pedestal & Bearing PSC TBeam Girder Slab Crash Barrier & Broken Kerb 1st 2nd 3rd 4th 5th c c c c c C C c C C c c c c c c c C C c C C c c c c c c c c c c C C C c p3 c c c c c c c c c c c c c p4 c c c c c c c c c c c c C p5 c c c C C C C c c c c c c p6 c c c c c c c c c c c c c p7 c c c c c c c C c c c c c p8 c c c c c C C C c c c c c p9 c c c c c c c c c c c c c p10 c c c c c c c c c c c c c p11 c c c c c c c c c c c c c A2 c c c c c c C c c c c c c Unihorn India Private Limited Remarks Page 37 Monthly Progress Report – 47 for the Month of June, 2014 Pedestral & Bearing Cap C C C C c c c c c c Part of Str. Slab PSC TBeam Girder Str. No. Wall Lifts Crash Barrier & Broken Kerb Chainage LHS Raft PCC Exc. C c c c A1 c c c c c p1 c c c c c c p2 c c c c c c c p3 c c c c c c c c p4 c c c c c c c c c c c c c c c c c c c c c c c c c c c c c c p7 c c c c c c c c c c c c p8 c c c c c c c c c c c c c p9 c c c c c c c c c c c c c p10 c c c c c c c c c c c c c p11 c c c c c c c c c c c c c A2 5th 4th 3rd 2nd 1st c c c C C c c c c c c c c c c c c c c c c c c c c c c c c c c c c c c Unihorn India Private Limited 85+817 (Damodar Bridge) p5 86/2 p6 Page 38 Monthly Progress Report – 47 for the Month of June, 2014 30.PROGRESS STRIP CHART OF HIGHWAY & STRUCTURES 30.1 HIGHWAY Unihorn India Private Limited Page 39 Monthly Progress Report – 47 for the Month of June, 2014 30.2 Quality Assurance & Quality Control Laboratory in Morangi & Chuttupalu camp have been established. Borrow area has been approved for the embankment and sub grade material. Third party test have been done for the water & fill material. Mix Design of Granular Sub base has been approved for both the Sections. Mix Design of WMM has been approved for both the Sections. Mix Design of DBM/BC has been approved for both sections by I.E. MPR (QC) UP TO - JUNE - 2014 No. of Test Conducted No. of Test pass No. of Test Fail Grain size analysis Atterberg's Limit Proctor Test Free swelling Test CBR Test Field Compaction Grain size analysis Atterberg's Limit Proctor Test Free swelling Test CBR Test 463 458 455 458 433 4245 1240 1240 1240 1240 880 453 448 445 448 383 4100 1240 1240 1240 1240 874 10 10 10 10 50 145 0 0 0 0 6 Field Compaction 71738 71432 306 Gradation Atterberg's Limit Proctor Test CBR Test Ten Percent Fine Value Water absorptin Field Compaction Gradation Atterberg's Limit Proctor Test Aggregate Impact Value Combined FI & EI Water absorptin Field Compaction Quality of Binder:Absolute Viscosity Kinematic Viscosity Penetration Softening Point Ductility 1779 1700 23 20 13 13 11824 2727 2706 14 1609 1613 13 19440 800 800 800 800 800 800 1773 1694 23 20 13 13 11776 2722 2706 14 1609 1613 13 19308 800 800 800 800 800 800 6 6 0 0 0 0 48 5 0 0 0 0 0 132 0 0 0 0 0 0 Tests 1. OGL 2. EMB/SG/ Borrow Area 3. Granular Sub Base 4. Wet Mix Macadam 5.Bitumen (VG-30) Unihorn India Private Limited Quantity 636921.59 2200872.93 222400.31 205701.37 12928.77 Cum. Test Upto This Month No. of Test Of This Month (JUNE 2014) No. of Test Upto LAST Month Frequency Testing 1test/250 m. 1test/250 m. 1test/250 m. 1test/250 m. 1test/250 m. 1 set = min 6 pits 2test/3000 cum. 2test/3000 cum. 2test/3000 cum. 2test/3000 cum. 1test/3000 cum. 1 set = min 6 pits/ 1 set= min.cum. 10 pits 1/200 1/200 cum. As required As required As required As required 1test/500 m2 1test/100 cum. 1test/100 cum. As required 1test/200 cum. 1test/200 cum. As required 1test/500 m2 1test/Bulker 1test/Bulker 1test/Bulker 1test/Bulker 1test/Bulker 1test/Bulker No. of No. of No. of Test Test Test Conduc pass Fail ted Quantity No. of No. of No. of Test Test Test by I.C Conducte pass Fail d Witnessed 0 0 0 0 0 0 0 0 0 0 0 463 458 455 458 433 4245 1240 1240 1240 1240 880 453 448 445 448 383 4100 1240 1240 1240 1240 874 10 10 10 10 50 145 0 0 0 0 6 0 180 72108 71802 306 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 2 2 0 0 0 0 12 8 8 0 4 4 0 72 2 2 2 2 2 2 1781 1702 23 20 13 13 11836 2741 2720 14 1616 1620 13 19536 802 802 802 802 802 802 1775 1696 23 20 13 13 11788 2736 2720 14 1616 1620 13 19404 802 802 802 802 802 802 6 6 0 0 0 0 48 5 0 0 0 0 0 132 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 370 370 2 2 0 0 0 0 12 14 14 0 7 7 0 96 2 2 2 2 2 2 2 2 0 0 0 0 12 14 14 0 7 7 0 96 2 2 2 2 2 2 0.00 2638.00 125.00 1320.00 37.45 Quantity 636921.59 Unit M2 2203510.93 M3 222525.311 M3 207021.37 M3 12966.22 MT Page 40 Monthly Progress Report – 47 for the Month of June, 2014 Quality of Binder:Absolute Viscosity 6.Modified Elastic Recovery Bitumen (PMB Penetration - 70) Softening Point Ductility 7.Emulsion (SS-1) Viscosity 8.Emulsion (RS-1) Viscosity 354 354 354 354 354 354 27 44 354 354 354 354 354 354 27 44 0 0 0 0 0 0 0 0 9 .Prime Coat Rate of Spray 2245 2245 10 .Tack Coat Rate of Spray 6511 Gradation Binder Content /Gradation 11 . Marshall Stability Dense Bitunimous Aggregate Impact Value Macadam (Gr.1) Combined FI & EI Field Compaction Gradation Binder Content /Gradation 12 . Marshall Stability Dense Bitunimous Aggregate Impact Value Macadam (Gr.2) Combined FI & EI Field Compaction 13 . Gradation Binder Content /Gradation Semi Dense Marshall Stability Bitunimous Aggregate Impact Value Combined FI & EI Concrete Field Compaction Trial Gradation 14. Binder Content /Gradation Bituminous Marshall Stability Concrete (Grade Aggregate Impact Value Combined FI & EI - 2) Field Compaction 0.00 1 1 1 1 1 1 1 0 355 355 355 355 355 355 28 44 355 355 355 355 355 355 28 44 0 0 0 0 0 0 0 0 0 4340.00 8 2258 2258 0 804994.67 24 24 0 6160.00 18 6535 6535 0 2110272.79 0 0 0 0 0 0 0 0 0 0 0 0 4 4 4 4 12 12 5 5 5 5 8 8 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 2 2 6 2 2 4 572 572 1710 1082 1082 1108 713 709 2099 1298 1298 1721 572 572 1710 1082 1082 1108 713 709 2099 1298 1298 1721 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 6 6 6 6 18 18 6 6 6 6 12 12 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 4 4 12 4 4 8 20 20 9 9 27 27 5 5 5 5 0 0 12 12 455 455 439 439 1310 1310 848 848 848 848 3157 3157 0 0 0 0 0 0 0 0 0 0 0 0 0 491.02 665.86 1test/Bulker 1test/Bulker 1test/Bulker 1test/Bulker 1test/Bulker 1test/Bulker 1test/Bulker 1test/Bulker 1 1 1 1 1 1 1 0 1 1 1 1 1 1 1 0 0 0 0 0 0 0 0 0 0 800654.67 1test/500Sq.m 13 13 6511 0 2104112.79 1test/500Sq.m 572 572 1710 1082 1082 1108 709 705 2087 1293 1293 1713 572 572 1710 1082 1082 1108 709 705 2087 1293 1293 1713 0 0 0 0 0 0 0 0 0 0 0 0 2 test/day / plant 2 test/day / plant 20 9 27 5 5 0 12 449 433 1292 842 842 3145 20 9 27 5 5 0 12 449 433 1292 842 842 3145 0 0 0 0 0 0 0 0 0 0 0 0 0 Unihorn India Private Limited 6244.29 2 Set/day of work, 1 Set=3 Specimen 48114.99 1test/50 Cu.m 1test/50 Cu.m 1test/700Sq.m (As per IRC 111 2009) 2 test/day / plant 2 test/day / plant 54533.853 2 Set/day of work, 1 Set=3 Specimen 1test/50 Cu.m 1test/50 Cu.m 1test/700Sq.m (As per IRC 111 2009) 2 test/day / plant 2 test/day / plant 0 2 Set/day of work, 1 Set=3 Specimen 1test/50 Cu.m 1test/50 Cu.m 1test/700Sq.m (As per IRC 111 2009) 2 test/day / plant 2 test/day / plant 36633.79 2 Set/day of work, 1 Set=3 Specimen 1test/50 Cu.m 1test/50 Cu.m 1test/250 Sq.m 8.46 12.11 0.00 148.80 0.00 194.65 6252.75 MT 503.13 665.86 MT 48114.99 MT M2 M2 M3 54682.653 M3 0 M3 36828.44 M3 Page 41 Monthly Progress Report – 47 for the Month of June, 2014 Trial Gradation 15. Binder Content /Gradation Bituminous Marshall Stability Concrete (Grade Aggregate Impact Value Combined FI & EI - 1) Field Compaction Gradation 16. Binder Content /Gradation Aggregate Impact Value Bituminous Combined FI & EI Macadam Field Compaction Grad. & Silt content of FA Gradation of CA AIV F.I Compressive Strength M15 (7 Days) M 15 (28 Days) M 20 (7 Days) M 20 (28 Days) M 25 (7 Days) 17. M 25 (28 Days) Concrete Works M30 (7Days) M30 (28Days) M 35 (7 Days) M 35 (28 Days) M 35 PILE (7 Days) M 35 PILE (28 Days) M 40 (7 Days) M 40 (28 Days) M 45 (7 Days) M 45 (28 Days) 0 55 53 149 92 92 319 92 92 99 95 71 2036 2036 2036 1782 0 55 53 149 92 92 319 92 92 99 95 71 2036 2036 2036 1782 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 4506 7488 4788 9336 2337 5301 795 2193 90 270 153 276 192 372 174 342 4506 7488 4788 9336 2337 5301 795 2193 90 270 153 276 192 372 174 342 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 Unihorn India Private Limited 2701.97 3810.18 110022.35 0 2 test/day / plant 0 2 test/day / plant 0 2 Set/day of work, 1 Set=3 Specimen 0 1test/50 Cu.m 0 1test/50 Cu.m 0 1test/250 Sq.m 0 2 test/day / plant 0 2 test/day / plant 0 1test/50 Cu.m 0 1test/50 Cu.m 0 1test/700Sq.m (As per IRC 111 2009) 0 1 test for every day's work. 29 1 test for every day's work. 29 1 test for every day's work. 29 once in a week. 29 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 249 249 192 522 0 0 3 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 29 29 29 29 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 249 249 192 522 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 986.50 0 0 0 0 0 0 0 0 0 0 0.00 0.00 0 0 0 0 0 0 0 0 0 0 0 0 18 18 18 18 0 55 53 149 92 92 319 92 92 99 95 71 2065 2065 2065 1811 0 55 53 149 92 92 319 92 92 99 95 71 2065 2065 2065 1811 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 189 192 108 462 0 0 3 0 0 0 0 0 0 0 0 0 4755 7737 4980 9858 2337 5301 798 2193 90 270 153 276 192 372 174 342 4755 7737 4980 9858 2337 5301 795 2193 90 270 153 276 192 372 174 342 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 2701.97 M3 3810.18 M3 111008.9 M3 Page 42 Monthly Progress Report – 47 for the Month of June, 2014 Consistency Initial &Final Setting Time Fineness Compres ive Strength 18. ( 3 Days ) Cement ( 7 Days ) ( 28 Days ) Soundness Specific Gravity Gradation Proctor Test 19. Dry Lean FI Concrete (DLC) AIV Field Compaction Test 296 296 0 422 422 0 392 392 0 312 321 312 0 0 25 1 25 25 164 Compres ive Strength 96 Gradation 62 FI 62 AIV 62 20. Pavement Texture Depth 53 Quality Control Flexural Strength (7 Days) 165 (PQC) Flexural Strength (28 Days) 159 Compres ive Strength(7 Days) 177 Compres ive Strength(28 Days) 195 312 321 312 0 0 25 1 25 25 164 96 62 62 62 53 165 159 177 195 Unihorn India Private Limited 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 753197.60 597.48 931.49 0 0 0 0 0 Daily Production As required Daily Production Daily Production 3 Test per 1000 sqm 2 cubes / 150 m3 Daily Production Daily Production Daily Production As per Specification 2 Beams / 150 m3 2 Beams / 150 m3 2 cubes / 150 m3 0 0 0 0 0 0 0 0 0 0 0 3 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 3 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 5921.00 0 0 0 0 0 0 0 0.00 0 0 0 0 0 0 0 0.00 0 0 0 0 0 296 296 0 0 422 422 0 0 392 392 0 0 0 3 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 312 321 315 0 0 25 1 25 25 164 96 62 62 62 53 165 159 177 195 312 321 315 0 0 25 1 25 25 164 96 62 62 62 53 165 159 177 195 Nos. 0 759118.6 of Bags 0 0 0 0 0 0 0 597.48 M3 0 0 0 0 0 0 0 931.49 M3 0 0 0 0 Page 43 Monthly Progress Report – 47 for the Month of June, 2014 31. SAFETY AND TRAFFIC MANAGEMENT Status of PPE on Site:o Usage : - Personal protective equipment (PPE) to reduce employee exposure to hazards when engineering and administrative controls are not feasible or effective in reducing these exposures to acceptable levels. Employers are required to determine if PPE should be used to protect their workers. a. Be appropriate for the risks involved and the conditions at the place of exposure b. Take account of ergonomic requirements, the state of health of the person who wears it and the duration of its use; c. Be capable of fitting the wearer correctly d. Be, so far as is reasonably practicable, effective to prevent or adequately control risks involved without increasing the overall risk o PPE Availability on site :a. These 750mm one piece composite Rubber traffic cones (CRC) come complete with D2 reflective sleeve which fully conforms to BS EN 13422:2004. These road cones are manufactured from recycled material. b. Reflective tapes c. Delineator d. Night Vision Boards e. Head Protection, Hand Protection, Safety Footwear, Yellow High Visibility Clothing. o Functionality :a. Rubber Traffic Cones: - Its Function is on the crossing of roadways, maintenance of freeways, dangerous zone, and Road sites and so on. b. Reflective tapes:-One of the most important attributes of road safety is line visibility. The importance of this function to resist the wear and tear caused by regular traffic and changing climate conditions. These reflective road tapes suitable for both longitudinal and transverse installation in locations that experience substantial traffic activity. c. Delineator:-The road delineators are functioning to its adjacent boundary line of the traffic lane in order that the driver can determine conveniently, correctly and continuously the exact distance of the car from either boundary of the roadway, enabling motorists, as they maintain their normal driving posture, to avoid accidents. d. Night Vision Boards:-The function of Night vision board is to provide the Clear visibility to adjacent boundary line of the traffic lane to avoid accidents. e. Head Protection, Hand Protection, Safety Footwear, Yellow High Visibility Clothing :-These PPE are function in such manner, that the labour on site should be visible from long distance due to the reflective material and protect them from any uncertain hazard happen on site. Deep Cutso Barricading along Excavation:- Any person making any excavation affecting or impacting a county road or public way shall erect and maintain about the excavation site sufficient guards, signals, barricades, and lights to give warning to approaching vehicular and pedestrian traffic. The guards, signals, barricades Unihorn India Private Limited Page 44 Monthly Progress Report – 47 for the Month of June, 2014 and lights shall remain in place until the road is restored to its original condition and all construction associated with excavation completed, including the removal of all rocks, dirt, and construction materials from the road or public way. o Sign Boards:-These Boards are provided to avoid the accidents and to intimate the consumers for taking proper precaution while driving from the Deep cuts areas. a) Management decision taken with respect to safety: - All the ghatt section slope is to be rechecked and is to be rectified if necessary. 31.1 Letters (June- 2014):- S.No Outgoing Date Subject Letter No. 1 3rd June. 14 Reg: - Invoice For the Month of May2014 UNI/RAN/NHAI/INVOICE/14/1717 2 5th June.14 Reg: - Weekly Progress Report. UNI/RAN/NHAI/WPR/14/1718 3 5th June.14 Reg: (-)ve and (+)ve Variations UNI/RAN/NHAI/MEMO/14/1719 4 6th June. 14 Reg: - Balance Invoice Payment. UNI/RAN/NHAI/INVOICE/14/1720 5 6th June.14 Reg: - Extension of services of Independent Engineer, Unihorn India Pvt. Ltd. Up to 30.06.14 UNI/RAN/NHAI/E.O.T/14/1721 6 9th June.14 Site Inspection Report UNI/RAN/NHAI/INSPECTION/14/ 1722 7 9th June.14 Reg: - Defects and Deficiencies UNI/RAN/NHAI/HIGH/14/ 1723 8 10th June.14 Reg: - Submission of Invoice of 3rd Annuity Payment. UNI/RAN/NHAI/Annuity/14/ 1724 9 12th June. 14 Reg: - Weekly progress report UNI/RAN/NHAI/WPR/14/1725 UNI/RAN/NHAI/E.O.T/14/1726 UNI/RAN/NHAI/M.P.R/14/1727 10 12 June. 14 Reg: - Extension of services of Independent Engineer, Unihorn India Pvt. Ltd. Up to 30.06.14 11 13th June. 14 Reg: -M.P.R. For the month of May2014 th Unihorn India Private Limited Page 45 Monthly Progress Report – 47 for the Month of June, 2014 12 16th June. 14 13 18th June. 14 14 18th June. 14 15 19th June.14 16 26th June.14 17 Reg: -Cost Variation Reg: Request for redressal of grievances claim for day’s damages and compensation in accordance with the concession agreement. UNI/RAN/NHAI/VARIATION/14/ 1728 UNI/RAN/NHAI/CLAIM/14/1729 Reg: - Defects and Deficiencies UNI/RAN/NHAI/HIGH/14/ 1730 Reg: - Weekly progress report UNI/RAN/NHAI/WPR/14/1731 Completion Certificate (Schedule – I Test for Ramgarh bypass). UNI/RAN/CONC/HIGH/14/1732 Reg:- Rectification of Rutting at km – 102. UNI/RAN/CONC/HIGH/14/1733 Reg: - Weekly progress report UNI/RAN/NHAI/WPR/14/1734 Reg:- MIS Report of NH-33. UNI/RAN/CONC/MIS/14/1735 26th June.14 18 26th June.14 19 26th June.14 Reg:-Weekly Progress Report 20 27th June.14 21 27th June.14 UNI/RAN/NHAI/WPR/14/1736 Reg:-Information regarding Right to information Act 2005. Unihorn India Private Limited UNI/RAN/NHAI/RTI/14/1737 Page 46 Monthly Progress Report – 47 for the Month of June, 2014 32. LAND ACQUISITION STATUS: Time Period as per CA 100% within 90 Days from Appointed Date Total Land to Balance be Balance land encumbrance handed Encroachment encumbrance land to be over by free land free for four handed over Authority laning for the As per service Road CA (Kms) 73.799 KM 73.499 KM Unihorn India Private Limited _ GM Land at Irba. Reason for Shortfall / Action taken Eviction drives to be required. Page 47 Monthly Progress Report – 47 for the Month of June, 2014 33. NCR Reports. 33.1 MATERIAL PROCUREMENT STATUS Major Material Procurement up to 31 June 2014 Major Material Aggregate 40 20 10 Stone Dust Cement Steel Sand Bitumen PMB Procured Up to Consumption Total This for the Cumulative Balance Unit Requirement Month Month Consumption at site MT MT MT 907292 810746 746450 1032622 957074 829514 500 400 350 1021013 912148 801433 11109 44526 28081 MT MT MT MT MT MT 968340 70549 8248 188000 21380 7890 1047342 70600 8797 188112 21044 8165 450 300 130 610 110 35 1027752 70068 8080 184208 21078 8173 19590 532 717 3904 -34 -8 Unihorn India Private Limited Page 48 Monthly Progress Report – 47 for the Month of June, 2014 33.2 Royalty of Minor Minerals. Sl. No. Month Earth Work Road Way Excavation Earth Work in Filling 1 Aug-10 36433 36579 2 Sep-10 31276 39618 3 Oct-10 54999 61223 4 Nov-10 31951 40048 5 Dec-10 73676 90289 6 Jan-11 52126 68089 7 Feb-11 67885 56342 8 Mar-11 53291 34398 9 Apr-11 17663 21902 10 May-11 29691 25776 11 Jun-11 20700 30221 12 Jul-11 19165 14036 13 Aug-11 1688 37874 14 Sep-11 12515 21674 15 Oct-11 77018 31647 16 Nov-11 69224 46069 17 Dec-11 120103 167264 18 Jan-12 94329 101170 19 Feb-12 65699 260907 20 Mar-12 75051 245554 Unihorn India Private Limited Remarks Page 49 Monthly Progress Report – 47 for the Month of June, 2014 34. Weather Report for the Month of June- 2014. Weather Report For The Month of June - 2014 Chuttupalu camp Weather Condition Rain Fall (mm) Temperature(0c) Humidity (%) Date Max. Min. Cummulative Remarks Rain fall (mm) Max. Min. 1-June-14 2- June -14 37.2 38.0 37.2 38.0 65.0 67.0 38.0 35.0 Sunny Sunny 0.0 0.0 0.00 0.00 3- June -14 38.3 38.3 65.0 32.0 Sunny 0.0 0.00 4- June -14 39.0 39.0 57.0 36.0 Sunny 0.0 0.00 5- June -14 39.2 39.2 58.0 38.0 Sunny 0.0 0.00 6- June -14 39.7 39.7 56.0 40.0 Sunny 0.0 0.00 7- June -14 42.1 42.1 60.0 33.0 Sunny 0.0 0.00 8- June -14 43.0 43.0 63.0 35.0 Sunny 0.0 0.00 9- June -14 43.5 43.5 68.0 37.0 Sunny / Rainy 2.0 2.00 10-June-14 43.8 43.8 62.0 40.0 Sunny 0.0 2.00 11-June-14 44.0 44.0 56.0 31.0 Sunny 0.0 2.00 12-June-14 44.5 44.5 50.0 28.0 Sunny 0.0 2.00 13-June-14 44.1 44.1 48.0 27.0 Sunny 0.0 2.00 14-June-14 44.3 44.3 46.0 30.0 Sunny 0.0 2.00 15-June-14 43.5 43.5 47.0 33.0 Sunny 0.0 2.00 16-June-14 43.0 43.0 48.0 32.0 Sunny 0.0 2.00 17-June-14 42.7 42.7 65.0 40.0 Sunny / Rainy 38.6 40.60 18-June-14 43.0 43.0 66.0 41.0 Sunny 0.0 40.60 19-June-14 38.1 38.1 75.0 43.0 Sunny / Rainy 16.6 57.20 20-June-14 31.3 31.3 77.0 50.0 Sunny / Rainy 29.2 86.40 21-June-14 31.4 31.4 72.0 53.0 Sunny 3.0 89.40 22-June-14 32.6 32.6 70.0 42.0 Sunny 0.0 89.40 23-June-14 35.5 35.5 67.0 41.0 Sunny 0.0 89.40 24-June-14 36.8 36.8 70.0 45.0 Sunny / Rainy 4.0 93.40 25-June-14 37.1 37.1 70.0 38.0 Sunny / Rainy 0.0 93.40 26-June-14 36.3 36.3 78.0 40.0 Rainy 57.0 150.40 27-June-14 37.0 37.0 75.0 45.0 Sunny / Rainy 4.0 154.40 28-June-14 36.5 36.5 77.0 48.0 Sunny / Rainy 2.0 156.40 29-June-14 35.3 35.3 78.0 50.0 Sunny / Rainy 8.4 164.80 34.0 34.0 30-June-14 73.0 45.0 TOTAL RAINFALL MAY - 2014 : 167.00 mm Sunny / Rainy 2.2 167.00 Unihorn India Private Limited Page 50 Monthly Progress Report – 47 for the Month of June, 2014 34.1 Site Photographs. Four Lane Completed Four Lane Completed Unihorn India Private Limited Page 51 Monthly Progress Report – 47 for the Month of June, 2014 Unihorn India Private Limited Page 52