Project Management & Design II – MAE 435 Rocket Project Final Report CN: 14677 December 1, 2015 Group Members: Wesley Harpster Ryan Horton James Lawrence Karna Shah James “Trey” Simmons Irfan Ali Shaukat Derek Hampton (Business/IT Major) Cindique Simmonds (EET Major) Alexandre Misenheimer (MAE Junior) Amanda Nolan (MAE Sophmore) Project Advisor Dr. Thomas Alberts TABLE OF CONTENTS TABLE OF FIGURES ...................................................................................................... III NOMENCLATURE ......................................................................................................... IV ABSTRACT ...................................................................................................................... VI 1. INTRODUCTION ........................................................................................................ 1 2. LITERATURE REVIEW/BACKGROUND ................................................................ 2 3. METHODS ................................................................................................................... 7 3.1. CENTER OF PRESSURE, CENTER OF GRAVITY, AND STATIC MARGIN ....................... 7 3.2. AVIONICS .............................................................................................................. 10 3.3. ROCKET MOTOR DESIGN PROCESS ........................................................................ 11 3.4. COMPOSITE SOLID FUEL MOTOR PREPARATION .................................................... 11 3.5. 3-D MODELING ..................................................................................................... 13 3.6. MOTOR SIMULATION ............................................................................................. 13 3.7. FINAL LAUNCH MOTOR FUEL SELECTION ………………………………………...14 4. RESULTS .................................................................................................................. 14 4.1. CENTER OF PRESSURE, CENTER OF GRAVITY, AND STATIC MARGIN ..................... 14 4.2. AVIONICS TESTING ................................................................................................ 15 4.3. ROCKET MOTOR HOUSING DESIGN PROCESS ........................................................ 15 4.4. COMMERCIAL TEST LAUNCH ................................................................................. 16 4.5. ALTITUDE PREDICTION FAILURE INVESTIGATION ………………………………..16 4.6. CUSTOM TEST LAUNCH ......................................................................................... 17 I 4.7. FINAL CUSTOM MOTOR LAUNCH ………………………………………………...17 5. DISCUSSION ............................................................................................................ 18 6. CONCLUSION ……………………………………………………………………...19 7. REFERENCES .......................................................................................................... 20 8. APPENDIX ................................................................................................................ 22 8.1. FLIGHT DATA RESULTS ......................................................................................... 22 8.2. COMPUTER-AIDED DRAWINGS .............................................................................. 25 8.3. TABLES AND PLOTS ............................................................................................... 26 8.4. MATLAB CODES .................................................................................................... 30 8.5. PICTURES ............................................................................................................... 31 8.6. GANTT CHART....................................................................................................... 40 8.7 BUDGET……………………………………………………………………………41 II List of Figures Figure 1: Propellant Simulation Properties ……………………………………..…..…………...22 Figure 2: Catalyst Pressure vs. Time Curve ……………………………………....….………….22 Figure 3: Altimeter 2 Flight 2 11 October 2015 ……………………………………………...…23 Figure 4: Altimeter 2 Flight 1 11 October 2015…………………………………………..……..23 Figure 5: Altimeter 2 Flight 3 11 October 2015-Custom …………………………………….…24 Figure 6: Rocket Assembly…………………………………………….………………………...25 Figure 7: Rocket Motor Classification Table………..…………..…………………………….....26 Figure 8: Motor Housing Thickness-Hoop Stress ……………………...………………….……27 Figure 9: Motor Housing Thickness-End Stress…………………………………………………27 Figure 10: Parachute Deployment Testing………………………………………..………….….28 Figure 11: Theoretical vs. Factory Provided Aerodynamic Values……………………………...28 Figure 12: Dual Deployment with Redundancy Wiring Diagram…………………………….…29 Figure 13: Matlab Code for Center of Pressure ………………………………………….……..30 Figure 14: Matlab Code for Coefficient of Drag ……………………………………………......31 Figure 15: Center of Gravity Test……………………………….………………….....…………32 Figure 16: Single Altimeter Avionics Bay Build ………………………………………………..33 Figure 17: Dual Altimeter Avionics Bay Build………………………………………..………...34 Figure 18: Parachute Ejection Charge Testing………………………………………..……...….35 Figure 19: Certification Rocket Open Rocket 3D Model……………………………………..…35 Figure 20: Flight Simulations After Failure Investigation Weight Correction ………………....36 Figure 21: RAS Aero Rocket Model …..………………………………………………………..37 Figure 22: Open Rocket Model …..……………………………………………………………...37 Figure 23: Custom Motor Design 1 ……………………………………………………………..38 Figure 24: Final Custom Motor Design …..……………………………………………………..39 III Nomenclature (CNα)N (CNα)TB (CNα)CS (CNα)CB (CNα)F x̅ x̅N x̅TB x̅CS x̅CB x̅F 𝑠 L, 𝑙𝑛 v K T(B) d sf cr cA l xt S.M. COP CG 𝐶𝐷0 𝐼𝑇𝑜𝑡𝑎𝑙 𝐼𝑆𝑃 t k m gc σh P di th σe Ab r ρ Ae At ε pc pe Normal force coefficient for nose cone Normal force coefficient for fins in the presence of the body Normal force coefficient for conical shoulder Normal force coefficient for conical boat tail Normal force coefficient for fins alone Center of pressure of rocket Center of pressure of nose cone Center of pressure for fins in the presence of the body Center of pressure of conical shoulder Center of pressure of conical boat tail Center of pressure of fins alone Cross sectional area Length of nose cone volume Correction factor for normal force coefficient for fins in the presence of the body Diameter of the body tube Height of fin from body tube to tip Length of fin attached to body tube Length of flat portion at the tip of the fin Length of line connecting the center point of sf with the center point of cA Perpendicular distance from tip of fin start to start of fin against the body tube Static Margin Center of pressure Center of gravity Coefficient of Drag Total Impulse Specific Impulse Operating Time wind resistance factor mass acceleration due to gravity Hoop stress Pressure Inside diameter Thickness End stress Burn area Burn rate Density of fuel Cross-sectional exit area of nozzle Cross-sectional area at the nozzle throat Nozzle expansion ratio - Ae/At Operating pressure of the motor housing Pressure at nozzle exit IV p0 c* 𝑤̇𝑝 M γ T Pressure at maximum altitude Characteristic velocity of the propellant Propellant weight flow Mach number Specific heat ratio Thrust V Abstract The purpose of this project was to launch a high-powered rocket to a maximum height of 10,000 feet using a custom built composite solid fuel rocket motor (CSFM). The center of pressure was found using a three dimensional theoretical analysis method. The center of gravity was found experimentally. The static margin was calculated using both the center of pressure and the center of gravity to determine flight stability of the rocket prior to launch. The avionics bay was built using a MissileWorks RRC3 Altimeter System for in flight control of the parachute deployment charges. The ejection charges were ground tested to ensure proper parachute deployment prior to launch. The system was flight tested twice prior to beginning the CSFM design process to ensure successful parachute deployment during the final launch. A GPS system, a main parachute, and a drogue parachute were used to recover the rocket after the launch. Fuel characteristics, operating pressure, burn area, and nozzle geometry were calculated using computer programs to reach the planned altitude. Altitude and thrust predictions were done using 3-D modeling. The propellant mixture that was used was 76.9% ammonium perchlorate, 5% aluminum powder, and 13% hydroxyl terminated polybutadiene by mass. The CSFM design was tested twice. The first test ensured the propellant design was done correctly. The second test was to reach 10,000 feet. VI 1. Introduction Old Dominion University has established a high powered rocket club with the goal of attending rocket competitions against other universities. In this, Old Dominion Mechanical and Aerospace Engineering Department could achieve national recognition for its students senior design projects, much like the current formula team. In order to make this project more meaningful, a baseline of knowledge must be achieved, through constant improvement at the senior design level. Additionally, a multidisciplinary and undergraduate element must be implemented in order to ensure the knowledge gained is never lost. This project and the previous project have been learning the concepts of high powered rocketry and composite solid fuel motor design (CSFM). This is the most common type of solid rocket motor currently used in military and space applications [7]. Additionally, it is the most common fuel used in high powered rocketry. The knowledge necessary in order to complete the project will be of monumental use in follow on teams in competitions. During the Fall 2014 – Spring 2015 semesters, the ODU Rocket Team built a rocket with a commercial motor which reached an altitude of 4,000 feet. During this launch the avionics bay deployment system incurred a fault which resulted in both main and drogue parachutes deploying at apogee. Additionally, the Fall 2014 – Spring 2015 ODU Rocket team tested a custom CSFM design two times which resulted in failure [1]. The Summer-Fall 2015 Rocket Team was tasked to improve upon the research and design from the previous team. The purpose of this project was to design and build a custom CSFM to successfully launch a rocket to an altitude of 10,000 feet with a payload of five pounds by the end of the fall 2015 semester with a budget of $2,500. 1 2. Literature Review/Background In order to begin purchasing and building a rocket, there are multiple high powered rocket certifications that must be achieved. There are three certification levels which must be passed prior to launching a rocket requiring an M class motor to 10,000 feet according to Tripoli Rocketry Association guidelines [2]. Each certification must be approved by a member of the Tripoli Rocketry Association and it must be done on an approved site. Level I certification requires that a rocket be built and flown successfully using an H or I class motor (impulse between 160.01 and 640.00 n-sec). The level II certification test requires a flight using a J, K, or L class motor. The level III certification requires one successful flight using a level II class motor and an electronic parachute deployment system. Along with the flight, a pre-flight data capture form, rocket drawings, parts list, wiring diagram, and pre-flight checklist must be submitted and reviewed by two Tripoli certifying members prior to the day of the launch. The level III certification launch will use a class M or larger motor (impulse of 5120.01 n-sec or greater). Each of the certifications require that the rocket be free of damage in order to pass [2]. The rocket being used for this project consists of a nose cone, forward payload bay, aft payload bay, fin section and an avionics bay. The nose cone is the very tip of the rocket and does not typically carry a payload. The forward payload bay contains the main parachute used for recovery that deploys at apogee. The aft payload bay contains the drogue parachute used to slow the fall of the rocket while allowing it to fall straight down for ease of recovery. The fin section contains the motor mounts, nozzle, and motor housing and is part of the aft payload bay. The avionics bay contains the electronic board which is responsible to ignite two or four parachute deployment charges depending on its design. 2 In order to fly, the stability of the rocket must be determined by finding the center of gravity and the center of pressure [3, 4]. The distance between these two design features determine the stability of the rocket [3, 4]. Ideal rocket design calls for 1 full diameter of the rocket body tube between the center of gravity and pressure with the center of pressure towards the aft [3-5]. If this is not true the rocket will not self-correct its flight in the air and will not fly straight up [4, 6-9]. There are multiple different avenues to electrical parachute deployment control. Some electronics offer a remotely triggered explosive charge system, which is typically used for rockets reaching an altitude of 5000 feet or less. Above that height, it becomes necessary to use an electronic control board that uses acceleration and altitude as it primary means of parachute ejection. This requires accelerometers and pressure sensors to be integrated into the control board and it must be programmed to deploy each parachute at its desired point in the rockets flight path. The drag coefficient for any rocket must be calculated in order to predict the maximum altitude of any flight prior to launch [4, 10, 11]. This coefficient changes throughout the flight based on the height and speed of the rocket. As the height increases, the density of the air decreases resulting in a lower drag force on the rocket [4, 10, 11]. Additionally, as the rocket approaches the Mach 1, the coefficient of drag gets much larger and causes an increase in the overall drag force [4, 10-12]. The characteristics of a rocket motor, whether commercial or custom, directly affect the performance. In a custom motor, the characteristics are able to be altered by the fuel mixture used and components added to it. For the rocket project, the baseline fuel selected to be used was 3 an APCP composition. This fuel type is widely used for military, space, and rocket hobbyist applications. The question then, is which catalyst to employ. While there are various metal oxides that can be used, each provides a different flare to the fuel. A copper oxide propellant, which is one of the fastest and as a result hottest burning catalyzed propellants, burns blue in color with little smoke. Red iron oxide was chosen for use in the production of our first research motor build. This is because the propellant has a slightly lower burn rate which allows it to be a bit forgiving during operation. This can be demonstrated through the burn rate calculation equation below. 𝑟 = 𝑎 ∙ 𝑃𝑛 In this equation, both variables a and n are the burn rate coefficient and exponent. These are propellant characteristic values that are specific to each propellant composition. These values must be obtained experimentally. For red iron oxide these values are somewhat lower causing a slower increase in burn rate with an increase in pressure. A rocket motor consists of three major parts: propellant, nozzle, and motor housing [4]. Since many of the parameters depend on each other while designing the rocket motor, it is necessary to make a guess based on the desired height of the rockets flight and the length of time that thrust needs to take place [4]. This allows values to be calculated in order to verify the design will work for the particular application [4]. The process is then done in iterations until a working design is mathematically modeled for the motor [4]. The motor was made in a Bates Grain Configuration. In this configuration, the grains are made in optimal lengths based on burn rate of the fuel composition and core diameter used [7, 12, 24]. This allows the motor to achieve maximum thrust nearly instantly and remain at that 4 level or just higher for the duration of the burn [7, 12, 24]. This thrust curve is most preferable during rocket launches because it allows for the greatest use of all of the potential energy stored in the thermochemical reaction of the rocket fuel. The process of building a custom rocket motor is extensive in each step. First, the proper components must be decided upon and simulated to ensure the primary goal is being met. Next, the correct weight of components must be purchased. Lastly, the components must be mixed, cured, and prepared for launch. Rocket fuel consists of five main parts, oxidant, fuel, binder, additives, and catalyst [7, 12, 24]. Other additives for example plasticizers, curing agents and catalysts can be used to either ease production or increase performance. The oxidizer is used to provide oxygen for the combustion of the rocket motor. There are four primary options for composite propellant oxidizer, ammonium perchlorate, ammonium nitrate, potassium perchlorate, and potassium nitrate [7, 12, 24]. Ammonium based oxidizers tend to be more consistent and predictable than potassium based oxidizers. “Rocket Candy” or “Carmel Candy” is an example of a potassium based oxidizer [7]. Due to the low operating temperature and brittle nature of these fuels, they would not be an initial choice with the availability of composite components which are superior in ease of production and energy output. Ammonium based oxidizers tend to be more expensive; however they provide the necessary characteristics to withstand the ignition pressures and reach the proposed altitude [7]. The decision between ammonium nitrate and ammonium perchlorate comes down to preference of the system that is being worked with. The low combustion temperature and slower burning rate characteristics are highlighted in ammonium nitrate. The high burn rate and high impulse characteristics are highlighted in ammonium perchlorate [7, 12, 24]. Since the motor housing 5 used for the rocket was able to withstand high combustion temperatures, ammonium perchlorate was selected. The fuel is the component which will fine-tune the mixture to the preferred specifications. The two main options for fuel are aluminum and magnesium [7, 12, 24]. Aluminum tends to be used with ammonium perchlorate and magnesium tends to be used with ammonium nitrate. In practice the addition of fuel tends to increase the specific impulse of any motor[7, 19, 30]. This only happens to a point however as most compositions do not use more the 18% fuel by mass. The binder chosen for the composite rocket motor is used to bind the other components together. There are several binders which can be chosen for a fuel composition. Examples for binders are R45HT-LO, R45M, R20LM, and more [7, 23]. Each choice has a varying equivalent weight, molecular weight, and chemical ratio. Based on availability, cost, and minimal difference between the binders for the application, R45HT-LO was chosen. The additives used are typically plasticizers and curing agents. Plasticizers, such as dioctyl adipate, are used to ease the mixing process in fuel preparation and allow some flexibility of cured grains without cracking [7, 12, 24]. Curing agents are used to strengthen the grains in order to ensure they remain intact during the burn and acceleration phase of a launch. E744 was used for the composition. Catalysts are the last portion of a propellant mixture which can affect the final product of the composition . The three options for a catalyst are ammonium dichromate, copper oxide, and iron oxide. Each choice has its own positive benefits, however each of them are made to increase the burn rate which will improve performance. Iron oxide was chosen for the composition [7, 24, 30]. 6 Catalysts are typically used in rocket motors to increase the burn temperature which also increases the burn rate. This increase in burn rate directly increases mass flow which increases the fuels specific impulse. Essentially, the addition of a catalyst provides more thrust for every kilogram or pound of propellant. Some typical catalysts include but are not limited to red iron oxide, magnesium oxide, and copper oxide. These are usually transition metal oxides and are well known for their catalytic behavior. They are also known for their explosive qualities when in aerosol form and therefore must be handled with extreme caution. 3. Methods 3.1. Center of Pressure, Center of Gravity, and Static Margin To calculate the center of pressure for the rocket, it was necessary to take every section of a typical rocket body into consideration. The sections used were nose cone, body tube, conical shoulder, conical boat tail, and fins. The relationship of center of pressure of the overall rocket and each of the sections was governed by the coefficient factor of normal force and it’s specific center of pressure (Equation 1) [3]. 𝑥̅ = (𝐶𝑁𝛼 )𝑁 𝑥̅𝑁 + ( 𝐶𝑁𝛼 ) 𝑇𝐵 𝑥̅ 𝑇𝐵 + (𝐶𝑁𝛼 )𝐶𝑆 𝑥̅𝐶𝑆 + (𝐶𝑁𝛼 )𝐶𝐵 𝑥̅𝐶𝐵 ∑ 𝐶𝑁𝛼 (Equation 1) For any nose cone with a circular cross sectional area at the base and a smooth transition throughout, the value of CNα was known to be equal to 2 (Equation 2) [3]. 8 (𝐶𝑁𝛼 )𝑁 = 2 ∫ 𝜋𝑑 𝑑𝑠(𝑥) 𝑑𝑥 𝑑𝑥 𝑏𝑢𝑡 𝑑𝑠(𝑥) 𝑑𝑥 = 𝑠(𝑥) = 𝜋𝑑2 4 (𝑓𝑜𝑟 𝑐𝑖𝑟𝑐𝑢𝑙𝑎𝑟 𝑛𝑜𝑠𝑒 𝑐𝑜𝑛𝑒) (Equation 2) ∴ (𝐶𝑁𝛼 )𝑁 = 2 7 The specific center of pressure for the nose cone was found using the volume, cross sectional area, and length (Equation 3) [3]. 𝐿 − 𝑣⁄𝑠(𝐿) 𝑥̅𝑁 = 𝑠(𝑜) 1− ⁄𝑠(𝐿) (Equation 3) The center of pressure for the fin section always falls on the centerline of the rocket body tube. The calculation CNα for the fin section was shown above as (CNα)TB. The CNα factor for fins was multiplied by a correction factor to adjust value for this situation (Equation 4) [3]. (𝐶𝑁𝛼 ) 𝑇𝐵 = (𝐶𝑁𝛼 )𝐹 𝐾𝑇(𝐵) (Equation 4) The calculation of KT(B) was a relationship between the body tube size and the size of the fins (Equation 5) [3]. 𝐾𝑇(𝐵) = 1 + 𝑟𝐴 𝑠 + 𝑟𝐴 (Equation 5) Then (CNα)F was calculated using dimensions taken from the fins. Since known equations only exist for certain fin shapes, it was calculated using the approximation that cA, the length of the tip of the fin, ran to the end of the fin (Equation 6) [3]. (𝐶𝑁𝛼 )𝐹 = 2 𝑠 12 ( 𝑓⁄𝑑) (Equation 6) 2 2𝑙 ) 1+√1+( 𝑐𝑟 +𝑐𝐴 Then using fin geometry as well geometry of the entire rocket, the center of pressure of the fin section was found in relation to the distance from the front of the nose cone (Equation 7) [3]. 𝑥̅ 𝑇𝐵 = 𝑥𝐹 + 𝑥𝑡 𝑐𝑟 +2𝑐𝐴 3 (𝑐 𝑟 +𝑐𝐴 1 𝑐 𝑐 ) + 6 (𝑐𝑟 + 𝑐𝐴 − 𝑐 𝑟+𝑐𝐴 ) 𝑟 (Equation 7) 𝐴 8 Then the original equation can be represented in the terms of the coefficient of forces and the specific center of pressures (Equation 8) [3]. 𝑥̅ = (𝐶𝑁𝛼 )𝑁 𝑥̅ 𝑁 +𝐾𝑇(𝐵) (𝐶𝑁𝛼 )𝐹 𝑥̅ 𝑇𝐵 ∑ 𝐶𝑁𝛼 (Equation 8) Following this process and using a MATLAB code (Figure 10), the center of pressure for the rocket was found [3]. Additionally the rocket was 3D modeled using Open Source Rocketry and it was found to coincide with the calculated center of pressure. Then the center of gravity for the rocket was found. This was found by tying a rope around the rocket and moving it until the point at which the rope alone will balance the weight of the rocket. Then a measurement was taken from the tip of the nose cone to the point at which the rocket balances (Figure 12). The key piece of information derived from both of these values is the static margin [3]. 𝑆. 𝑀. = (𝐶𝑂𝑃 − 𝐶𝐺)/𝑑 (Equation 9) The design point that was chosen for the rocket was for a static margin value greater than 1.5 and less than 4 [4, 10, 11, 13]. This range of values was chosen to allow for marginal changes in the center of pressure that occur during flight due to weights shifting and angle of attack [4, 10, 11, 13]. 9 3.2. Avionics The avionics bay electrical control board chosen was the Rocket Recovery Controller (RRC3) altimeter avionics system from Missile Works Corporation. For the certification flights, this board was mounted on a purchased carbon fiber frame. All of the electrical control components were then mounted on a custom aluminum sled. This sled was then mounted into the avionics bay section of the rocket using long screws, rubber and regular washers, nuts, and covered in epoxy to minimize vibration during thrust (Figure 16). This design was changed when a GPS and dual redundant RRC3 boards were used in the avionics bay. The rocket used to achieve a 10,000 ft. launch utilized a dual board RRC3 system for redundancy. The two boards were used from the spring 2015 rocket group’s avionics bay. Both boards were mounted on a purchased 3-D printed frame, which were assembled with two zinc rods. These rods were inserted through holes located at certain points on the printed frames and then thread locked to remain secure. One custom aluminum sled was machined on which the GPS system was mounted. This custom sled was attached to the bottom of the secondary altimeter using eyehooks and fastened with JB weld to avoid any vibrations or stresses on the eyehooks or the rods. New aluminum bulk heads were also machined and milled and the whole bay was fastened with lock nuts and thread lock. The boards were wired using dual redundancy schematics (Figure 17). The purpose of redesigning the avionics bay was to reduce weight and space constraints within the bay due to the addition of the custom sled and the GPS system. The ejection charges used to deploy the main and drogue parachutes were built using an online design tool [14]. The charges were built to reach the design pressure of 12.5 psi inside the forward and aft payload bay. The materials used for the build were FFFF black powder, finger 10 tips of rubber gloves, an electrical motor igniter, and rubber bands. The black powder was weighed out and placed in the tips of the glove, the igniter was inserted, and a rubber-band was used to seal the charge. The charges were tested by assembling the rocket, bypassing the electrical control board, and detonating the charges using a 9 volt battery. Testing was performed on the ground by bypassing the avionics board (Figure 18). 3.3. Rocket Motor Design Process The design of the motor housing must take both internal pressure and temperature into consideration. The primary forces of concern on the motor housing were as a result of the internal pressure. All other forces were assumed to be negligible in comparison. Using this assumption the design of a motor housing then becomes a pressure vessel calculation (Equation 10) [15]. 𝜎ℎ = 𝑃(𝑑𝑖 +𝑡ℎ) 2𝑡 𝑃𝑑 𝜎𝑒 = 4𝑡ℎ𝑖 (Equation 10) These equations were solved for t and programmed into excel to produce a graph of necessary wall thickness based on the use of an aluminum 6061-T6 motor housing material. The calculations were done using the yield stress of the given materials. The adiabatic flame temperature for an AP/Al/HTPB motor is approximately 3000 K [16-20]. The actual surface will not reach this temperature, but since it exceeds the melting point for aluminum 6061-T6, a phenolic liner was used in every motor in order to maintain structural integrity [9, 18, 21, 22]. 3.4. Composite Solid Fuel Motor Preparation Prior to making fuel, an excel file provided by a rocket enthusiast was used in order to determine the mass necessary in grams of each component of the fuel (Figures 23, 24). As 11 previously stated, the baseline fuel selected was an APCP composition with a red iron oxide catalyst. After this was determined, the core diameter and nozzle throat needed to be designed to support the fuel. Fpred and BurnSim were the two software used to complete these steps. Multiple software programs were used for redundancy in order to ensure the design would perform as expected. Once the preliminary calculations were completed and the components were purchased, the fuel was mixed. A specific order of mixture was followed to ensure that everything cured the correct way. The liquid components were weighed and added first. This consists of a binding agent (R45HTLO), curative (E744), and plasticizer (dioctyl adipate). The first dry component added was the metal oxide catalyst (red Iron oxide), which ensures all of the particles are captured by the liquid. The addition of the metal oxide catalyst was arguably the most important due to the explosive nature of aerosolized metal oxides. Finally, the ammonium perchlorate was added. After the fuel was mixed, it was placed in a vacuum. The vacuum increases the specific impulse of the fuel by removing microscopic air pockets thus increasing the density. After completion of the mixing process, the fuel was rolled and smashed into precut propellant grain tubes where the length was previously determined during nozzle and core diameter calculations. Proper care must be taken in order to minimize air pockets in the propellant grains during this step. Air pockets in propellant grains would increase the burn area drastically which in turn would increase burn rate. This self-sustaining process could quickly result in catastrophic failure of the motor. Mold release was also used to allow the grains to free themselves of the molds in order to reduce breaking and cracking after curing. The composition was left to cure for 4 days, though normally the process varies between 3 hours and 3 days depending on the binder used. When the cure completed, the composition was ready for flight. 12 3.5. 3-D Modeling The three types of software that were used to model and simulate the rocket were Autodesk Inventor, Open Source Rocketry, and RASAero II (Figures 6, 19, 21 and 22). These simulations were used in order to obtain a prequalification permission to launch prior to launch day. The primary use for Autodesk Inventor was to accurately model the bulkheads and GPS mounting plate. Open Source Rocketry and RASAero II were used to model the rocket, and simulate the flight based on the rocket dimensions and motor selected or designed. Based upon the model of the rocket, the program calculates the coefficient of drag, center of mass, center of gravity and other basic properties needed to properly simulate test flights. Each interior and exterior component must be modeled to scale in the rocket assembly in order for the simulation to be accurate. Prior to purchasing or machining a part, we ensured it would coincide properly with the simulation. With a completed assembly, an estimated altitude was determined. 3.6. Motor Simulation In order to simulate the motor build, first the fuel composition calculation spreadsheet was used to obtain key propellant characteristics such as burn rate exponent, coefficient, C-Star, gamma, and density. These values were then entered into both BurnSim and Fpred in order to obtain two separate expected burn results using a Bates Grain Configuration. The results would use the applied nozzle throat area and operating pressure in order to obtain a thrust for each second during the burn. These values were then used in a conservative manner in order to allow for minor fluxes in operating pressure to allow for a successful flight of the rocket without catastrophic failure of the motor. 13 3.7. Final Launch Motor Fuel Selection The final launch required the rocket to break 8,000 feet. This solely, drove the design parameters. The options were to build a long 54 millimeter motor or a very short 75 millimeter motor. In either case, some very creative fuel composition methodology would need to be employed. Due to the extremely fast burning and unforgiving behavior of long skinny motors the 75 millimeter diameter four grain slow burn motor was chosen. This motor composition consisted of 74.75% AP, 2.54% Al, 3.5% dioctyl adipate, 11.74% R45HT-LO, 0.75% black copper oxide, 4.5% strontium oxide, and 0.3% tepanol. The key ingredient was the strontium carbonate. This decreased the burn rate coefficient and exponent to less than 1, thus creating a very stable and forgiving fuel that burns at about half the rate of our initial rocket fuel. 𝑟 = 𝑎 ∙ 𝑃𝑛 Therefore, this fuel was chosen in order to minimize the chance of catastrophic motor failure during motor ignition and burn. 4. Results 4.1. Avionics Testing Testing of the custom designed and built ejection charges were conducted for the certification rocket and the team rocket. During testing the charge built performed as expected outside of the rocket housing. Upon initial testing the drogue chute in the forward payload bay was a success using 1.3 g black powder. The follow on test of the main chute in the aft payload bay did not deploy using 2 g black powder. The black powder was then increased to 2.2 g and tested again with another failure. The main chute was then tested in the forward bay using 1.3 g 14 of black powder with success. The drogue chute was then tested in the aft bay with 2 g of black powder successfully. A retest was done with the drogue chute in the aft bay using 1.48 g of black powder with success. The ejection charge designed for launch days will be the drogue chute in the aft bay with 1.48 g of black powder and the main chute in the forward bay with 1.3 g of black powder (Figure 5). The follow on testing of the team rocket found two successful tests at 1.68 grams of black powder in the forward bay with the main parachute and 2.3 grams in the aft bay with the drogue parachute. 4.2. Rocket Motor Design Process The motor housing design was graphed for both hoop stress and end stress felt in the motor housing. The results indicate that the primary design concern for any motor housing is the hoop stress (Figure 4 and 5). Additionally, this provides a much quicker reference for design of various motor housings depending on design requirements. Using a safety factor of four the motor housing would still fit inside of the main rocket that will be used for the final launch. 4.3. Center of Pressure, Center of Gravity and Static Margin The calculation for the stability of the rocket was solved using the center of pressure, center of gravity and static margin. The center of pressure was determined to fall at 54.3 inches down from the tip of the nose cone. The center of gravity was found experimentally to be 45.3 inches from the tip of the nose cone. These values were used to produce a designed static margin of 2.25 (Equations 1-9). The rocket nose cone provided from the kit was swapped out for a previous rockets nose cone due to material issues. Therefore, the geometry only changed slightly and we were able to compare our theoretical calculated values against the values provided with the kit. The static margin for the rocket as purchased was 1.75. The distance between the center 15 of pressure and center of gravity was 7 inches which leads to the conclusion that our rocket is stable and ready for flight as built (Figure 7) [23]. 4.4. Commercial Test Launch The first flight using the K695R motor was simulated at 3,675 feet. The altimeters recorded a maximum altitude of 4,029 feet. %𝐸𝑟𝑟𝑜𝑟 = |3675 − 4029| ∗ 100% = 9.633% 3675 The value of 9.633% error is a bit on the high side but still acceptable for rocketry standards. The more troubling part is the simulations are designed to be best case scenario and therefore are rarely over shot by more than 1-2%. The second flight which was on a L1250DM was projected to go to 9,360 feet, however; it went 11,960 feet. %𝐸𝑟𝑟𝑜𝑟 = |9360 − 11960| ∗ 100% = 27.77% 9360 The 27% error seen in the second flight is completely unacceptable. 4.5. Altitude Prediction Failure Investigation Due to the large unexpected error in the predicted slight simulation for the commercial L1250-DM motor, a failure investigation was conducted. Upon examination of the 3-D model nothing appears to be out of the ordinary. The only way to achieve a significant increase in altitude was to decrease the overall rocket weight significantly. Based upon this, the rocket was dissembled and reweighed 3 times on two separate scales. The rocket weighed approximately three pounds lighter than what it was simulated at. After adjusting the model the flight 16 simulations were consistent with actual maximum altitude of flight (Figure 20, Figure 3 and Figure 4). 𝐾695𝑅 𝑆𝑖𝑚𝑢𝑙𝑎𝑡𝑖𝑜𝑛 𝑃𝑜𝑠𝑡 𝑊𝑒𝑖𝑔ℎ𝑡 𝐶𝑜𝑟𝑟𝑒𝑐𝑡𝑖𝑜𝑛 %𝐸𝑟𝑟𝑜𝑟 = 𝐿1250 − 𝐷𝑀 𝑃𝑜𝑠𝑡 𝑊𝑒𝑖𝑔ℎ𝑡 𝐶𝑜𝑟𝑟𝑒𝑐𝑡𝑖𝑜𝑛 %𝐸𝑟𝑟𝑜𝑟 = |4029 − 4142| ∗ 100% = 2.73% 4142 |11960 − 12087| ∗ 100% = 1.05% 12087 4.6. Custom Test Launch There was only one flight completed using the Ammonium Perchlorate Composite Propellant (APCP). The altimeters recorded a maximum altitude of 2,503 feet. %𝐸𝑟𝑟𝑜𝑟 = |3156 − 2503| ∗ 100% = 20.69% 3156 The estimated altitude from the rocket simulation was based on a J-800 motor because of the similar thrust-time curves. The error was largely due to significant discrepancies in the rocket model prior to the flight 4.7. Final Custom Launch The final custom motor launch was a complete success. The expected altitude was 8,179 feet and the actual achieved altitude was 8,111 feet. %𝐸𝑟𝑟𝑜𝑟 = |8179 − 8111| ∗ 100% = 0.8314% 8179 The motor performed within 1% of the expected altitude and came off without a hitch. This verified our rocket model and altitude simulation process. Additionally, our motor design approach was verified through this as well. 17 5. Discussion The summer 2015 – fall 2105 rocket project was tasked to launch a rocket using a custom CSFM to a height of 10,000 feet using a budget of $2,500 by December 12, 2015. In order to achieve this, some lessons learned were applied from the fall 2014 – spring 2015 rocket project. The test stand design was modified from a horizontal to a vertical orientation to provide an inherently stable design eliminating the need to anchor the stand down [1]. Additionally, the fuel that has been selected for the CSFM build has been changed from a potassium nitrate and sugar mixture to AP/Al/HTPB due to the significant amount of current research available. Also, in the previous rocket project an expert cited the possibility of their fuel selection being a cause for the failure in the motor testing [1]. The rocket project at this point has achieved all of the initial tasks with some unavoidable edits to the original goal. Due to Tripoli Rocketry Association we were unable to actually attain an altitude of 10,000 feet on a custom motor. Additionally, the launch was not done with a payload on board. Due to the maximum launch height of 9,000 feet, we chose to break 8,000 feet using the empty mass of the rocket. The CSFM design can easily be scaled up using burn simulations and flight simulations in order to achieve 10,000 feet. In addition an additional five pounds payload flight can easily be completed after simulations. The next step in the progression for this project should be to start preparations for competition. The necessary base knowledge and skills have been passed down and demonstrated by undergraduates who should be able to perform well in a rocket competition. 18 6. Conclusion The team was able to complete 100% of the project scope. Due to Tripoli regulations, we were not able to fly to 10,000 feet on the custom motor flight. The same design process could be employed with the goal of achieving a higher altitude and the same result could be achieved. Additionally, the five pound payload could be added anywhere to any rocket model and the custom motor would then be designed in a manner in which to ensure a 5 pound payload reached the desired altitude. The only reason the payload was not included is because originally that part of the competition was to be designed by the SEDS who failed to continue working on their portion of the project. 19 7. References [1] C. B. Nathan Akers, Paul Campbell, Charles Juenger, Brian Mahan, Chris Skiba, Michael Weber, Michael Wermer, "Rocket Project Final Report ", ed. Old Dominion University 2015, p. 62. T. R. A. Inc., "High Powered Rocketry Certification," ed, p. 4. J. S. Barrowman and J. A. Barrowman, "The theoretical prediction of the center of pressure," Catholic University Master’s thesis, 1966. E. Fleeman, Tactical Missile Design, Second ed. Reston, VA: American Institute of Aeronautics and Astronautics, Inc., 2006. S. M. (July 21, 2015). Chapter 3 - Drag Force and Drag Coefficient. Available: http://faculty.dwc.edu/sadraey/Chapter%203.%20Drag%20Force%20and%20its%20Coefficient. pdf X.-b. Li, J.-w. Dong, Y.-j. Wang, and Z.-z. Jin, "Zero-lift drag coefficient identification of rocket target," Journal of Solid Rocket Technology, vol. 33, pp. 5-8, 02/ 2010. E. R. Prince, S. Krishnamoorthy, I. Ravlich, A. Kotine, A. C. Fickes, A. I. Fidalgo, et al., "Design, Analysis, Fabrication, Ground-Test, and Flight of a Two-Stage Hybrid and Solid Rocket," in 49th AIAA/ASME/SAE/ASEE Joint Propulsion Conference, 14-17 July 2013, Reston, VA, USA, 2013, p. 25 pp. R. A. Struble, "The Trajectory of a Rocket With Thrust," Journal of Jet Propulsion, vol. 28, pp. 472-478, 1958/07/01 1958. N. Kubota (2015). Propellants and Explosives : Thermochemical Aspects of Combustion (3 ed.). Available: http://ODU.eblib.com/patron/FullRecord.aspx?p=1998813 S. Mark and T. Richard, "Evaluation of CFD code CFD-ACE for application to rocket problems," in 36th AIAA/ASME/SAE/ASEE Joint Propulsion Conference and Exhibit, ed: American Institute of Aeronautics and Astronautics, 2000. T. Brown, B. Fred, H. Thomas, H. Wayne, T. Brown, B. Fred, et al., "Drag and moment coefficients measured during flight testing of a 2.75-in. rocket," in 35th Aerospace Sciences Meeting and Exhibit, ed: American Institute of Aeronautics and Astronautics, 1997. N. Hall. (July 20, 2015). The Drag Coefficient. Available: https://www.grc.nasa.gov/www/K12/airplane/dragco.html A. Fedaravičius, S. Kilikevičius, and A. Survila, "913. Optimization of the rocket's nose and nozzle design parameters in respect to its aerodynamic characteristics," Journal of Vibroengineering, vol. 14, pp. 1885-1891, 2012. J. Anderson. (August 3, 2015 ). Black Powder. Available: http://www.rockethead.net/black_powder_calculator.htm J. K. N. Richard G. Budynas, Shigley's Mechanical Engineering Design, Ninth ed. New York, NY: McGraw-Hill, 2008. A. M. Hegab, H. H. Sait, A. Hussain, and A. S. Said, "Numerical modeling for the combustion of simulated solid rocket motor propellant," Computers & Fluids, vol. 89, pp. 29-37, 1/20/ 2014. R. J and O. J, "Combustion modeling of aluminized propellants," in 15th Joint Propulsion Conference, ed: American Institute of Aeronautics and Astronautics, 1979. Y. Chang, L. W. Hunter, D. K. Han, M. E. Thomas, R. P. Cain, and A. M. Lennon, "Solid rocket motor fire tests: Phases 1 and 2," AIP Conference Proceedings, vol. 608, p. 740, 2002. L. Luigi De, P. Christian, R. Alice, S. Marco, M. Elisa, M. Filippo, et al., "Aggregation and Incipient Agglomeration in Metallized Solid Propellants and Solid Fuels for Rocket Propulsion," in 46th AIAA/ASME/SAE/ASEE Joint Propulsion Conference & Exhibit, ed: American Institute of Aeronautics and Astronautics, 2010. [2] [3] [4] [5] [6] [7] [8] [9] [10] [11] [12] [13] [14] [15] [16] [17] [18] [19] 20 [20] [21] [22] [23] V. Sekkar and T. S. K. Raunija, "Hydroxyl-Terminated Polybutadiene-Based Polyurethane Networks as Solid Propellant Binder-State of the Art," Journal of Propulsion and Power, vol. 31, pp. 16-35, 2015/01/01 2014. J. D. G. Lengelle, J.F. Trubert. (2003, June 29). Combustion of Solid Propellants (January 2004 ed.) [Research Article]. J. R. E. Grant, L. R, and S. M, "A study of the ignition of solid propellants in a small rocket motor," in Solid Propellant Rocket Conference, ed: American Institute of Aeronautics and Astronautics, 1964. M. Rocketry, "Super DX3 All Fiberglass Kit," 2009. 21 8. Appendix 8.1. Flight Data Results Figure 1: Propellant Simulation Properties Figure 2: Catalyst Pressure vs Time Curve 22 Figure 3: Altimeter 2 Flight 2 10 October 2015 Figure 4: Altimeter 2 Flight 1 10 October 2015 23 Figure 5: Altimeter 2 Flight 3 11 October 2015 – Custom 24 8.2. Computer-Aided Drawings Figure 6: Rocket Assembly 25 8.3. Tables and Plots Figure 7: Rocket Motor Classification Table 26 Figure 8: Motor Housing Thickness - Hoop Stress Figure 9: Motor Housing Thickness – End Stress 27 Figure 10: Parachute Deployment Testing Test 1 Test 2 Test 3 Test 4 Test 5 Test 6 Test 7 Charge Size (g) Chute Used 1.3 N/A 1.3 drogue 2 main 2.2 main 1.3 drogue 2 main 1.48 drogue Results drogue main aft bay forward bay Purpose Test to see if the charge will detonate drogue deployment fwd bay main deployment aft bay main deployment aft bay main deployment fwd drogue deployment aft bay drogue deployment aft bay Result Success Success Fail Fail Success Success Success 1.48g 1.3g Figure 11: Theoretical vs Factory Provided Aerodynamic Values Theoretical Values COP COG Static Margin 54.3 in 45.3 in 2.25 Factory Provided Values COP COG Static Margin 48 in 41 in 1.75 28 Figure 12: Dual Deployment with Redundancy Wiring Diagram 29 8.4. Matlab Codes Figure 13: Matlab Code for Center of Pressure %This code will calculate the center of pressure for a rocket %%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%% %%%%%SURFACE AREA OF NOSE CONE AND COP FOR CONE%%%%% h_nose = 0.5; %this is the height of incremental measure D_nose = [0.35 0.60 0.79 0.92 1.09 1.25 1.42 1.56 1.67 1.80 1.94 2.12 2.18 2.393 2.4985 2.50 2.615 2.6955 2.810 2.8691 2.935 3.016 3.113 3.185 3.2515 3.3410 3.398 3.409 3.527 3.5895 3.646 3.698 3.751 3.807 3.856 3.9 3.932 3.9765 4.005 4.024 4.036 4.045 4.05 4.054 4.057 4.057 4.057 4.057]; %diameter measurements B = length(D_nose); %end of loop setting i = 1; Nose_Vf = 0; CN_Alpha_nose = 2; %eqn 1 while i <= B Nose_V = pi()*(D_nose(i)/2)^2*h_nose; Nose_Vf = Nose_Vf + Nose_V; i = i+1; end COP_Cone_Section = (24 - (Nose_Vf/((pi()*4^2)/4))); %Eqn 2 %%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%% %%%%%SURFACE AREA OF FINS AND COP FOR FINS%%%%% s = 3.776; Xf = 64; cr = 11.04; ca = 4.54; l = 4.406; Xt = 6.50; d = 4; ra = 2; CN_Alpha_Fins = (12*(s/d)^2)/(1+sqrt(1+(2*l/(cr+ca)))); %eqn 3 CN_Alpha_TB = (1+ra/(s+ra))*CN_Alpha_Fins; COP_Fin_Section = Xf + (Xt/3)*((cr+2*ca)/(cr+ca))+(1/6)*(cr+ca((cr*ca)/(cr+ca))); %Note: Fin geometry assumed square in rear for calculations purposes %%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%% %%%%%COP%%%%% COP = (CN_Alpha_nose*COP_Cone_Section+CN_Alpha_TB*COP_Fin_Section)/(CN_Alpha_nose+C N_Alpha_TB); %%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%% %%%%%Stability Check%%%%% CG = 54.2632-9; Static_Margin = (COP - CG)/d; 30 Figure 14: Matlab Code for Coefficient of Drag %Mach Number M = linspace(0.1,2,20); %Input Data %l = missile body length prompt1 = 'missile body length: '; l = input(prompt1); %ln = nose length prompt2 = 'nose length: '; ln = input(prompt2); %d = missile body diameter prompt3 = 'missile body diameter: '; d = input(prompt3); %q = dynamic pressure prompt4 = 'dynamic pressure: '; q = input(prompt4); %Nozzle Exit Area prompt5 = 'nozzle exit area: '; Ae = input(prompt5); %Sref = cross sectional area prompt6 = 'cross sectional area: '; Sref = input(prompt6); %Equations Cdbodyfriction = 0.053*(l/d)*[M/(q*l)].^0.2; if M>1 Cdbasecoast = 0.25/M; else Cdbasecoast = (0.12+0.13*M.^2); end if M>1 Cdbasepower = ((1-(Ae/Sref))*(0.25/M)); else Cdbasepower = ((1-(Ae/Sref))*(0.12+0.13.*M.^2)); end Cdbodywave = ((1.586+(1.834./M.^2))*(atan(0.5/(ln/d))).^1.69); Cdbodycoast = Cdbodywave+Cdbasecoast+Cdbodyfriction; Cdbodypower = Cdbodywave+Cdbasepower+Cdbodyfriction; Cd_zerolift = Cdbodyfriction+Cdbodywave+Cdbasecoast+Cdbasepower Cd_induced = Cdbodycoast + Cdbodypower Cd = Cdbodyfriction + Cdbodywave + Cdbodycoast + Cdbodypower + Cdbasepower + Cdbasecoast Cd2 = Cd_zerolift + Cd_induced plot(M,Cd) 31 8.5. Pictures Figure 15: Center of Gravity Test 32 Figure 16: Single Altimeter Avionics Bay Build 33 Figure 17: Dual Altimeter Avionics Bay Build 34 Figure 18: Parachute Ejection Charge Testing Figure 19: Certification Rocket Open Rocket 3D Model 35 Figure 20: Flight Simulations After Failure Investigation Weight Correction 36 Figure 21: RAS Aero Rocket Model Figure 22: Open Rocket Model 37 Figure 23: Custom Motor Design 1 Propellant designation Propellant density 77_5 0.06 lb/in^3 GRAINS TO BE CAST Grain #1 Diameter Length Core (mandrel) dia. Number of grains Expected waste, % Ingredient Ammonium perchlorate 400 um Ammonium perchlorate 200 um Ammonium perchlorate 90 um Aluminum atomized -400 mesh Red Iron Oxide R45HTLO R45M HTPB Dioctyl adipate Castor oil E744 IPDI Dibutyltin dilaurate PAPI Tepanol Total wt. Percent solids PREPARATION STEPS Mix liquid ingredients Add metals Add curative Vacuum process Grain #2 1.25 2 0 16 2 Grain #3 1.8 3.2 0.625 6 NEEDED Actual Used: THIS BATCH 0.00 1755.22 0.00 113.98 2.28 0.00 0.00 296.34 0.00 68.39 0.00 45.59 0.00 0.00 2281.78 95.00% 0 0 Original batch: Weight Percent 0.00 0.0% 77.00 76.9% 0.00 0.0% 5.00 5.0% 0.10 0.1% 0.0% 0.0% 13.00 13.0% 0.00 0.0% 3.00 3.0% 0.0% 2.00 2.0% 0.0% 0.0% 0.0% 0.00 0.0% 100.1 DATA AND COMMENTS Cure 38 Figure 24: Final Custom Motor Design Propellant designation Propellant density MG3 0.058 lb/in^3 (95% theoretical density) GRAINS TO BE CAST Grain #1 Diameter Length Core (mandrel) dia. Number of grains Expected waste, % Ingredient Ammonium perchlorate 200 um Strontium Carbonate Black Copper Oxide Aluminum -325 mesh R45 HTLO Dioctyl adipate Castor oil Dibutyltin dilaurate Tepanol IPDI E744 PAPI Grain #2 1.8 2.6 0.75 0 3 Grain #3 1.8 3.1 0.625 0 NEEDED Actual Used: THIS BATCH 891.55 53.67 8.95 29.82 0.00 139.55 41.74 0.00 0.00 3.58 0.00 25.05 0.00 2.55 5.1 1 2 Original batch: Weight Percent 74.75 74.7% 4.50 4.5% 0.75 0.7% 2.50 2.5% 0.0% 11.70 11.7% 3.50 3.5% 0.0% 0.0% 0.30 0.3% 2.10 0.0% 2.1% 0.0% Silicone Oil 3 drops per Kg. Total wt. Percent solids PREPARATION STEPS Mix liquid ingredients Add metals Add curative Vacuum process 1193.90 82.42% 100.1 DATA AND COMMENTS Cure 39 8.6. Gantt Chart 40 8.7 Budget Main Budget Including Labor Costs Task # 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 Task Title Research & Project Specification Inventor Design Chemistry Rocket Build Avionics Thermometer Pressure Gauges Load Cell Thermodynamics Level I Certification Level II Certification Test Stand Design Gas Dynamics Pre-Flight Data Form Drawings Parts List Wiring Diagram Pre-Flight Test Stand Build Matlab Code Level III Certification Engine Build Commercial Motor Test Custom Motor Test Data Analysis Re-Build Motor Re-Test Motor Test Launch Managerial Duties Names Wes, Trey, Karna, James, Irfan, Ryan Trey, James, Irfan Ryan, Trey, Wes, Irfan Wes, Trey, Karna Wes, Trey, Karna James, Irfan James, Irfan James, Irfan Ryan, Trey, Wes, Irfan Wes, Trey, Karna Wes, Trey, Karna James, Irfan Ryan, Trey, Wes, Irfan Wes, Trey, Karna Wes, Trey, Karna Wes, Trey, Karna Wes, Trey, Karna Wes, Trey, Karna James, Irfan Ryan, Trey, Wes, Irfan Wes, Trey, Karna Wes, Trey, Karna, Irfan, Ryan James, Irfan Wes, Trey, Karna, Ryan Wes, Trey, Karna, James, Irfan, Ryan Wes, Trey, Karna, James, Irfan, Ryan Wes, Trey, Karna, James, Irfan, Ryan Wes, Trey, Karna, James, Irfan, Ryan Wes, Trey Work Days Labor Rate Labor Costs Materials Equipment Facilities Subcontractors Travel Contingency Total Costs 25 $150.00 $3,750.00 $3,750.00 10 $75.00 $750.00 $750.00 5 $100.00 $500.00 $500.00 5 $75.00 $375.00 $300.00 $675.00 5 $75.00 $375.00 $90.00 $465.00 5 $50.00 $250.00 $140.00 $390.00 5 $50.00 $250.00 $260.00 $510.00 5 $50.00 $250.00 $355.00 $605.00 10 $100.00 $1,000.00 $1,000.00 5 $75.00 $375.00 $103.00 $70.00 $20.00 $568.00 5 $75.00 $375.00 $45.00 $20.00 $440.00 10 $50.00 $500.00 $85.00 $585.00 10 $100.00 $1,000.00 $1,000.00 15 $75.00 $1,125.00 $1,125.00 15 $75.00 $1,125.00 $1,125.00 15 $75.00 $1,125.00 $1,125.00 15 $75.00 $1,125.00 $1,125.00 15 $75.00 $1,125.00 $1,125.00 10 $50.00 $500.00 $500.00 10 $100.00 $1,000.00 $1,000.00 5 $75.00 $375.00 $350.00 $20.00 $745.00 35 $125.00 $4,375.00 $2,200.00 $6,575.00 40 $50.00 $2,000.00 $20.00 $2,020.00 5 $100.00 $500.00 $500.00 $20.00 $1,020.00 5 $150.00 $750.00 $100.00 $850.00 5 $150.00 $750.00 $1,000.00 $1,750.00 5 $150.00 $750.00 $40.00 $790.00 5 $150.00 $750.00 $40.00 $790.00 20 $50.00 $1,000.00 $1,000.00 325 $28,125.00 $4,085.00 $1,443.00 $70.00 $0.00 $ 180.00 $0.00 $33,903.00 Conclusion of Budget: The total budget for the entire project will be $33,903.00 Funds Received: The ODU Rocket Team received $3,086.00 for the Summer 2015 and Fall 2015 semesters. - The ODU Mechanical and Aerospace Engineering department donated $1,586.45 The National Aeronautics and Space Association (NASA) donated $500.00 Old Dominion University donated $1000.00 ]Funds Spent: The ODU Rocket Team spent $3,468.15 during the Summer 2015 and Fall 2015 semesters. - Approximately $971.56 was spent for testing Approximately $696.51 was spent for launch preparation Approximately $250.08 was spent for miscellaneous equipment Approximately $50.00 was spent on shipping $1,500.00 was owed back to Mechanical and Aerospace Engineering department based on the loans initially given 41 Budget Analysis: Certification Testing Design Total Cumulative Budgeted Cost (CBC) Cumulative Actual Cost (CAC) Calculated Earned Value (CEV) Cost Performance Index (CPI) Cost Variance (CV) Forecast Cost at Completion (Eq. 1) Forecast Cost at Completion (Eq.2) To-Complete Performance Index (TCPI) Certification Testing Design Total Cumulative Budgeted Cost (CBC) Cumulative Actual Cost (CAC) Calculated Earned Value (CEV) Cost Performance Index (CPI) Cost Variance (CV) Forecast Cost at Completion (Eq. 1) Forecast Cost at Completion (Eq.2) To-Complete Performance Index (TCPI) TBC $9,388.00 $6,190.00 $18,075.00 $33,653.00 1 $0.00 $0.00 $750.00 $750.00 $750.00 $750.00 $750.00 1.00 $0.00 $33,653.00 $33,653.00 1.000000 2 $0.00 $0.00 $750.00 $750.00 $1,500.00 $1,500.00 $1,500.00 1.00 $0.00 $33,653.00 $33,653.00 1.000000 13 TBC $0.00 $9,388.00 $6,190.00 $250.00 $18,075.00 $2,825.00 $33,653.00 $3,075.00 $22,053.00 $19,603.04 $17,893.00 0.91 -$1,710.04 $36,869.23 $35,363.04 1.121711 3 $0.00 $0.00 $750.00 $750.00 $2,250.00 $2,250.00 $2,250.00 1.00 $0.00 $33,653.00 $33,653.00 1.000000 14 $0.00 $250.00 $625.00 $875.00 $22,928.00 $20,478.04 $18,768.00 0.92 -$1,710.04 $36,719.28 $35,363.04 1.129795 4 $0.00 $0.00 $750.00 $750.00 $3,000.00 $3,337.60 $3,000.00 0.90 -$337.60 $37,440.08 $33,990.60 1.011136 15 $0.00 $250.00 $625.00 $875.00 $23,803.00 $21,353.04 $19,643.00 0.92 -$1,710.04 $36,582.69 $35,363.04 1.139028 5 $0.00 $0.00 $750.00 $750.00 $3,750.00 $4,087.60 $3,750.00 0.92 -$337.60 $36,682.67 $33,990.60 1.011419 16 $0.00 $250.00 $625.00 $875.00 $24,678.00 $22,228.04 $21,143.00 0.95 -$1,085.04 $35,380.04 $34,738.04 1.094971 6 $675.00 $375.00 $500.00 $1,550.00 $5,300.00 $5,366.60 $4,925.00 0.92 -$441.60 $36,670.50 $34,094.60 1.015612 17 $0.00 $250.00 $625.00 $875.00 $25,553.00 $23,103.04 $24,143.00 1.05 $1,039.96 $32,203.40 $32,613.04 0.901425 7 $465.00 $375.00 $500.00 $1,340.00 $6,640.00 $6,616.60 $5,541.25 0.84 -$1,075.35 $40,183.79 $34,728.35 1.039774 18 $0.00 $250.00 $625.00 $875.00 $26,428.00 $23,978.04 $25,018.00 1.04 $1,039.96 $32,254.10 $32,613.04 0.892510 8 $898.00 $1,505.00 $500.00 $2,903.00 $9,543.00 $8,756.68 $6,793.75 0.78 -$1,962.93 $43,376.42 $35,615.93 1.078844 19 $0.00 $250.00 $625.00 $875.00 $27,303.00 $24,853.04 $25,893.00 1.04 $1,039.96 $32,301.37 $32,613.04 0.881822 9 $1,875.00 $335.00 $500.00 $2,710.00 $12,253.00 $11,451.68 $8,495.00 0.74 -$2,956.68 $45,365.91 $36,609.68 1.133176 20 $0.00 $250.00 $1,000.00 $1,250.00 $28,553.00 $26,299.55 $26,768.00 1.02 $468.45 $33,064.06 $33,184.55 0.936295 10 $1,875.00 $250.00 $500.00 $2,625.00 $14,878.00 $14,076.68 $9,245.00 0.66 -$4,831.68 $51,240.94 $38,484.68 1.246812 21 $0.00 $850.00 $0.00 $850.00 $29,403.00 $27,149.55 $27,618.00 1.02 $468.45 $33,082.19 $33,184.55 0.927969 11 $1,875.00 $250.00 $500.00 $2,625.00 $17,503.00 $16,849.68 $10,893.00 0.65 -$5,956.68 $52,055.66 $39,609.68 1.354494 22 $0.00 $0.00 $1,750.00 $1,750.00 $31,153.00 $27,899.55 $28,468.00 1.02 $568.45 $32,981.02 $33,084.55 0.901198 23 $0.00 $0.00 $750.00 $750.00 $31,903.00 $28,649.55 $29,318.00 1.02 $668.45 $32,885.71 $32,984.55 0.866402 1. Calculations End of Week 24 - 12 $725.00 $250.00 $500.00 $1,475.00 $18,978.00 $18,324.68 $13,393.00 0.73 -$4,931.68 $46,044.98 $38,584.68 1.321736 Total Budgeted Cost (TBC) = $33,653.00 Cumulative Budget Cost (CBC) = $33,653.00 Cumulative Actual Cost (CAC) = $30,399.55 Cumulative Earned Value (CEV) = $30,399.55 Cost Performance Index (CPI) = $1.00 Cost Variance (CV) = $0.00 Forecasted Cost at Completion (FCAC Formula 1) = $33,653.00 Forecasted Cost at Completion (FCAC Formula 2) = $33,653.00 To-Complete Performance Index (TCPI) = 1.00 42 24 $1,000.00 $0.00 $750.00 $1,750.00 $33,653.00 $30,399.55 $30,399.55 1.00 $0.00 $33,653.00 $33,653.00 1.000000 2. Plot CBC, CAC, and CEV Curves Estimated Budget + Labor Costs 40000 Cumulative Budget Cost 35000 30000 Cumulative Budgeted Cost (CBC) 25000 Cumulative Actual Cost (CAC) 20000 Calculated Earned Value (CEV) 15000 10000 5000 0 0 10 20 30 Weeks 43 3. Summary of Budget Based on the budget analysis, the project has been completed. This conclusion can be driven from the Cost Performance Index (CPI) being $1.00, and the Cumulative Actual Cost (CAC) and Cumulative Earned Value (CEV) being the same. In comparison to the Cumulative Budgeted Cost (CBC) we spent approximately $3,253.45 less than originally budgeted for. This difference came from the availability of funds that we had access to. Unfortunately we did not have enough money as originally planned to allow us to purchase certain parts. Thankfully we were still able to complete the project with this minor budget issue. In the first weeks of the project we fell behind on progress. Around week 17 we were able to catch up to everything that needed to be done. This is shown by our CPI eclipsing 1.00. The budget based solely on items purchased, leaving out labor, travel etc, ended at a balance of -$381.70. $3,086.45 was received overall and $3,468.15 was spent. This is because originally we expected to receive more money from Old Dominion University so we budgeted accordingly. Unfortunately we only received $1,000 of the $3,000 which we originally planned for. We are thankful for the assistance from the ODU Mechanical and Aerospace Engineering department to allow us to complete our project. 44