ANNUAL PERFORMANCE EVALUATION REPORT FOR MNCWASA REGIONAL BULK WATER SUPPLY SCHEME EASTERN CAPE CHIEF DIRECTORATE: BULK INFRASTRUCTURE PROGRAMME PERIOD: 01 APRIL 2013 TO 31 MARCH 2014 PROGRAMME MANAGEMENT: REGIONAL BULK INFRASTRUCTURE TABLE OF CONTENTS 1. Introduction 2. Background 2.1 Description of project 2.2 Project History 2.3 Project concept, design and plan 2.4 Start date – duration of the programme 2.5 Funds previously allocated to project 3. Progress to date 3.1 Implementation of approved business plan 3.2 Schedules of work and phasing of the activities 3.3 Risks taken and management thereof 3.4 Capacities dedicated to the programme 3.5 Key challenges within the project 4. Project result and beneficiaries 4.1 Outcomes and outputs 4.2 Beneficiaries and project results. 5. Conclusions / Lessons Learned 5.1 Main successes and failures of the project to date 5.2 Ownership and sustainability of infrastructure works 6. Recommendations ANNEXURE A: Project Implementation Photos ANNEXURE B: List of villages expected to benefit from bulk project ANNEXURE C: Details of contracts awarded under bulk projects ANNEXURE D: Project schedule ANNEXURE E: Details of job opportunities APRIL 2014 3 PROGRAMME MANAGEMENT: REGIONAL BULK INFRASTRUCTURE 1. APRIL 2014 INTRODUCTION In terms of Section 10(7) (b) of the Division of Revenue Act No 2 of 2013 (DORA) as promulgated in Government Gazette No 36555 dated 10 June 2013, the transferring national officer must submit an annual performance report for Schedule 6 within four months in respect of a province and six months in respect of a municipality after the end of the financial year to the National Treasury. The Regional Bulk Infrastructure Grant (RBIG) is a Schedule 6 indirect conditional grant for the benefit in kind of municipalities. The objective of this Report is to provide an annual performance evaluation report covering the 4th quarter of RBIG funded projects, in compliance with the DORA. The objective of this evaluation was to determine whether the progress on the project is commensurate with the expenditure to date as well as to determine whether the project is still on course in terms of the original planning. This performance evaluation report, covering quarter 4 and annual report of the 2013/14 fiscal year, is for the Mncwasa Regional Bulk Water Supply Scheme, one of the Regional Bulk Infrastructure Grant projects, currently being implemented by the Amathole District Municipality (ADM) in the Eastern Cape Province, with Department of Water Affairs (DWA) as funder, and Municipal Infrastructure Grant (MIG) as co-funder. 2. BACKGROUND 2.1 Description of Project Mncwasa Water Supply Project is situated in the Eastern Cape along the Wild Coast and used to be part of the former Transkei area. The area starts north of the Xhora River and ends at the Mpaka River near Hole in the Wall. The area stretches 15 km inland from the Coastal belt and is approximately 242 km2 in extent. There is very little urban development with no towns within this area which consists of 54 rural coastal type villages with an estimated population of 36 378 in 6,063 households. The area is remote, being fairly isolated by the Mbashe River from its administrative areas i.e. Mbashe Local Municipality in Idutywa and Amathole District Municipality in East London. The nearest towns are Elliotdale, Mthatha and Idutywa. The preferred access to Mncwasa is a surfaced road (N2) between Idutywa and Mthatha. At Viedgesville there is a turn off onto the Mqanduli/Coffee Bay road and from there access to Mncwasa would be at the Lutubeni Mission turnoff or via the Zithulele Hospital Road. These access roads are in urgent need of repair and can be impassable in wet weather. 2.2 Project history Water for domestic use in the area was drawn from surface water sources, i.e. streams, rivers and other open water sources. There was generally no existing water infrastructure in the rural villages within the project area. The project was originally divided into four (4) phases, namely: • Phase 1 - construction of the Mndwaka dam, treatment works and rising mains. • Phase 2 - construction of the bulk gravity mains and reservoirs. 4 PROGRAMME MANAGEMENT: REGIONAL BULK INFRASTRUCTURE • • APRIL 2014 Phase 3 - construction of the internal reticulation for the 43 villages (not funded from RBIG programme) Phase 4 - construction of the internal reticulation for the remaining 15 villages (not funded from RBIG programme). Due to ADM‘s policies the project was divided up into 23 projects and afterward four of the projects were combined into two projects and ended up with a total of 21 projects. During April 2012 ADM instructed Sontinga Consulting Services as the Professional Service Provider (PSP) to exclude four villages that fell inside the O R Tambo district due to the legality of cross boarder supply. The bulk pipelines from the regional reservoir to the village reservoirs, including the village reservoirs and village reticulations were redesigned to exclude the four villages. The villages serviced under Phase 4 have now reduced from 15 villages to 11 villages. Refer to figure 1 and 2 showing the change in the scheme. Figure 1 – Original Scope of Work Figure 2 – Revised Scope of Work 5 PROGRAMME MANAGEMENT: REGIONAL BULK INFRASTRUCTURE 2.3 APRIL 2014 Project concept, design and plan Phase 1 - construction of the Mndwaka Dam, Treatment works and rising mains The first phase of the Mncwasa Water Supply Project (MWSP) has been divided up into five sub-phases namely: Phase 1A – Mechanical and Electrical installation to the water treatment works includes the following: Chemical dosing plant to treat raw water. Three rapid gravity sand filter systems. Chlorination plant to disinfect clear water. All pipe work including valves, fittings and flow meters etc. The electrical equipment and wiring for the operation of the new plant. The provision of a complete operation and maintenance manual. Phase 1B – Construction of the 2.5 Mℓ/day Water Treatment Works which includes the following: 5 Mℓ Balancing dam. Water treatment building. Flocculation channels. Sedimentation tank. Sludge ponds. Constructing new recovery pump stations. Backwash pipelines. Operator’s houses Interconnecting pipe work. 980 m long gravel access road of which 180 m will have a concrete surface. Phase 1C – Construction of the Mndwaka Dam which include the following: 27 700 m³ Bulk Earthworks. 30 330 m³ Rubble Masonry Concrete. 2 720 m Drilling and Grouting for Steel Bars. 2 520 m Drilling and Grouting. Pump station. 300 mm dia. Ductile Iron inlet and outlet pipe work, valves and fittings. Three new raw water pump sets. Phase 1D – Mechanical and electrical installation to the pump stations will include the following: Three new clear water pump sets. All pipe work including valves, fittings, flow meters etc. The electrical equipment and wiring for the operation of the proposed new plant. The telemetry equipment and wiring. The provision of a complete operation and maintenance manual. Phase 1E – Construction of the Rising Mains which includes the following: 1 000 m of 250 mm dia. uPVC rising main. 11 240 m of 200 mm dia. ductile iron rising main. Air, scour and check valve chambers. 6 PROGRAMME MANAGEMENT: REGIONAL BULK INFRASTRUCTURE APRIL 2014 2 x Generator rooms Temporary abstraction point, pump, generator and pipeline. Phase 2 - Construction of the Bulk Storage Reservoirs and Bulk Gravity Pipelines The second phase of the Mncwasa Water Supply Project has been divided up into nine sub-phases namely: Phase 2A – The construction of the 5 Ml Regional Reservoir which includes the following: 5 Ml Reinforced Concrete Reservoir Inlet / outlet control chamber Erection of a 1.8 m high security fence 1 km long 5 m wide gravel access road Phase 2B – The construction of Bulk Infrastructure to 8 Villages, which includes the following works: 2 x 125 kℓ Reinforced Concrete Reservoirs 1 x 45 kℓ Reinforced Concrete Reservoir 1 x 70 kℓ Elevated GMS Tank on 10 m GMS stand 3 x Break pressure tanks 10 123 m of bulk pipeline of various sizes in diameter Air, scour and isolating valve chambers Phase 2C – The construction of Bulk Infrastructure to 9 Villages, which includes the following works: 1 x 125 kl Reinforced Concrete Reservoir 1 x 75 kl Reinforced Concrete Reservoir 1 x 55 kl Reinforced Concrete Reservoir 10 555 m of bulk pipeline of various sizes in diameter 34 Air and 22 scour valve chambers Phase 2D – The construction of Bulk Infrastructure to 7 Villages, which includes the following works: 1 x 125 kl Reinforced Concrete Reservoir 1 x 75 kl Reinforced Concrete Reservoir 1 x 60 kl Reinforced Concrete Reservoir 1 x 35 kl Reinforced Concrete Reservoir 16 264 m of bulk pipeline of various sizes in diameter 51 Air and 26 scour valve chambers Phase 2E – The construction of Bulk Infrastructure to 8 Villages, which includes the following works: 1 x 125 kl Reinforced Concrete Reservoir 1 x 85 kl Reinforced Concrete Reservoir 1 x 70 kl Reinforced Concrete Reservoir 1 x 49 kl Elevated GMS Tank on 15 m GMS Stand 7 749 m of bulk of various sizes in diameter. 23 Air and 11 scour valves with chambers. 7 PROGRAMME MANAGEMENT: REGIONAL BULK INFRASTRUCTURE APRIL 2014 Phase 2F & G – The construction of Bulk Infrastructure to 11 Villages, which includes the following works: 1 x 85 kl Reinforced Concrete Reservoir 1 x 75 kl Reinforced Concrete Reservoir 1 x 60 kl Reinforced Concrete Reservoir 1 x 55 kl Reinforced Concrete Reservoir 1 x 50 kl Reinforced Concrete Reservoir 1 x 45 kl Reinforced Concrete Reservoir 1 x 40 kl Reinforced Concrete Reservoir 1 x 30 kl Reinforced Concrete Reservoir 4 x Break Pressure Tanks 22 245 m of bulk pipeline of various sizes in diameter 61 Air and 42 scour valves with chambers. Phase 2H – The construction of Bulk Infrastructure to 7 Villages, which includes the following works: 1 x 125 kl Reinforced Concrete Reservoir 1 x 75 kl Reinforced Concrete Reservoir 1 x 60 kl Reinforced Concrete Reservoir 1 x 50 kl Reinforced Concrete Reservoir 1 x Break Pressure Tanks 14 889 m of bulk pipeline of varying sizes in diameter. 24 Air and 17 scour valves with chambers. Phase 2I – The construction of Bulk Infrastructure to 4 Villages, which includes the following works: 1 x 70 kl Reinforced Concrete Reservoir 1 x 55 kl Reinforced Concrete Reservoir 1 x 30 kl Reinforced Concrete Reservoir 1 x 87 kl Elevated GMS Tank on 10 m GMS Stand 8 127 m of bulk pipeline of varying sizes in diameter. 13 Air and 11 scour valves with chambers. Phase 3 - Construction of the Internal Village Reticulation and Standpipes (not funded by RBIG programme) The third phase of the Mncwasa Water Supply Project has been divided up into seven sub-phases namely: Phase 3A – The construction of internal Village Reticulation to 4 Villages, which includes the following works: 24 603 m of village reticulation ranging between 32 mm and 160 mm in diameter 4 x Break pressure tanks Control chambers 66 standpipes Phase 3B – The construction of internal Village Reticulation to 4 Villages, which includes the following works: 43 537 m of village reticulation ranging between 32 mm and 200 mm in diameter 8 PROGRAMME MANAGEMENT: REGIONAL BULK INFRASTRUCTURE APRIL 2014 16 x Break pressure tanks Control chambers 114 standpipes Phase 3C – The construction of internal Village Reticulation to 9 Villages, which includes the following works: 35 129 m of village reticulation ranging between 32 mm and 110 mm in diameter 11 x Break pressure tanks Control chambers 88 standpipes Phase 3D – The construction of internal Village Reticulation to 7 Villages, which includes the following works: 43 591 m of village reticulation ranging between 32 mm and 160 mm in diameter 15 x Break pressure tanks Control chambers 104 standpipes Phase 3E – The construction of internal Village Reticulation to 8 Villages, which includes the following works: 48 405 m of Village Reticulation ranging between 32 mm and 110 mm in diameter 7 x Reinforce Concrete Break Pressure Tanks 16 x Air Valves Control Chambers 117 Standpipes Phase 3F & G – The construction of internal Village Reticulation to 11 Villages, which includes the following work: 69 314 m of Village Reticulation ranging between 32 mm and 160 mm in diameter 13 x Break Pressure Tanks 18 x Air Valves Control Chambers 161 Standpipes Phase 4 - Construction of the Internal Village Reticulation and Standpipes (not funded by RBIG programme) The fourth phase of the Mncwasa Water Supply Project (MWSP) has been divided up into two sub-phases namely: Phase 4 – The construction of internal Village Reticulation to 12 Villages, which includes the following works: 98 713 m of Village Reticulation ranging between 32 mm and 110 mm in diameter 22 x Break Pressure Tanks 25 x Air Valves 9 PROGRAMME MANAGEMENT: REGIONAL BULK INFRASTRUCTURE APRIL 2014 41 x Control Chambers 243 Standpipes The village names that will benefit from the project are listed in Annexure B. 2.4 Start date – duration of the programme The envisaged dates for executing the phases of this project are as follows: a) b) Phase 1A – Mechanical and Electrical installation to the water treatment works: Contract Start date : September 2009 Contract Completion date : January 2012 Phase 1B – Construction of the Water Treatment Works: Contract Start date : January 2010 Contract completion date : March 2011 c) Phase 1C – Construction of the Mndwaka Dam: Contract Start date : February 2012 Anticipated Contract Completion date : March 2015 d) Phase 1D – Mechanical and electrical installation to the pump stations Contract Start date : April 2011 Contract Completion date : March 2012 e) Phase 1E – Construction of the Rising Mains Contract Start date : April 2010 Contract completion date : May 2011 f) Phase 2A – The construction of the 5Mℓ Regional Reservoir Contract Start date : March 2010 Contract completion date : January 2011 g) Phase 2B – The construction of Bulk Infrastructure to 10 Villages Contract Start date : June 2010 Contract completion date : December 2011 h) Phase 2C – The construction of Bulk Infrastructure to 9 Villages Contract Start date : October 2010 Contract completion date : November 2011 i) Phase 2D – The construction of Bulk Infrastructure to 9 Villages Contract Start date : October 2010 Contract completion date : November 2011 j) Phase 2E – The construction of Bulk Infrastructure to 9 Villages Contract Start date : March 2011 Contract completion date : November 2012 k) Phase 2F&G – The construction of Bulk Infrastructure to 17 Villages Contract Start date : June 2012 Contract completion date : May 2013 10 PROGRAMME MANAGEMENT: REGIONAL BULK INFRASTRUCTURE 2.5 APRIL 2014 l) Phase 2H – The construction of Bulk Infrastructure to 8 Villages Contract Start date : September 2013 Anticipated Contract completion date : August 2014 m) Phase 2I – The construction of Bulk Infrastructure to 10 Villages Anticipated Contract Start date : September 2013 Anticipated Contract completion date : August 2014 n) Phase 3A – The construction of internal Village Reticulation to 5 villages Contract Start date : November 2010 Contract completion date : September 2012 o) Phase 3B – The construction of internal Village Reticulation to 5 Villages Contract Start date : October 2010 Anticipated Contract completion date : September 2013 p) Phase 3C – The construction of internal Village Reticulation to 9 Villages Contract Start date : October 2010 Contract completion date : August 2012 q) Phase 3D – The construction of internal Village Reticulation to 9 villages Contract Start date : October 2010 Anticipated Contract completion date : September 2013 r) Phase 3E – The construction of internal Village Reticulation to 9 Villages Contract Start date : February 2011 Contract completion date : January 2012 s) Phase 3F&G – The construction of internal Village Reticulation to 17 Villages Contract Start date : April 2012 Contract completion date : March 2013 t) Phase 4A – The construction of internal Village Reticulation to 12 Villages Anticipated Contract Start date : TBA Anticipated Contract completion date : TBA Funds previously allocated to project Table 1 below indicates the funding that was made available to the project during the past six financial years. Table 1 Funding for the past 7 financial years 2007 to 2012 Allocation / Spent amount R47 947 441.00 Co-funding streams: District Municipality (from - MIG) 2012/2013 2013/2014 R23 591 172.00 R12 148 093.00 : R140 802 755.00 (mostly on reticulation) 11 PROGRAMME MANAGEMENT: REGIONAL BULK INFRASTRUCTURE 3. APRIL 2014 PROGRESS TO DATE The performance evaluation was conducted on the 4th April 2014 by the team consisting of the following people: 3.1 Zandisile Nonjuzana Kaya Maposa Teddy Dlamini Tim Wood Thando Mkwayimba DWA KWT DWA KWT ZMJV Sontinga Consulting Services (PSP) Sontinga Consulting Services (PSP) Implementation of the approved business plan Currently the following contracts have been awarded out of the planned twenty phases and are at present in construction phase. Work and material complies with standards and quality. PHASE 1: All the Contracts have been awarded under this phase namely: Phase 1A – Supply and installation of Mechanical and Electrical equipment for the proposed mew 2.5 Mℓ rapid gravity water treatment works. Phase 1B – Construction of the balancing dam, water treatment building, flocculation channels, sedimentation tank, sludge pounds and backwash pipe work. Phase 1C – Construction of the Mndwaka Dam. Phase 1D – Supply and installation of mechanical and electrical equipment for the proposed new clear water high lift pump set. Phase 1E – Construction of pumping mains and control chambers. PHASE 2: Eight Contracts has been awarded under this phase namely: Phase 2A – Construction of a 5 Ml Reinforced concrete reservoir. Phase 2B – Construction of reinforced concrete reservoirs elevated steel tank, bulk pipelines and control chambers. Phase 2C – Construction of reinforced concrete reservoirs, bulk pipelines and control chambers. Phase 2D – Construction of reinforced concrete reservoirs, bulk pipelines and control chambers. Phase 2E – Construction of reinforced concrete reservoirs, elevated steel tank, bulk pipelines and control chambers. Phase 2F&G – Construction of reinforced concrete reservoirs, bulk pipelines and control chambers. 12 PROGRAMME MANAGEMENT: REGIONAL BULK INFRASTRUCTURE APRIL 2014 Phase 2H – Construction of reinforced concrete reservoirs, bulk pipelines and control chambers. Phase 2I – Construction of reinforced concrete reservoirs, bulk pipelines and control chambers. PHASE 3 & 4: These projects are for the construction of village reticulation and funded by MIG. Contract details for phases 1 and 2 are summarised in Annexure C. Table 2 Milestones Product Feasibility Study Implementation Readiness Study Preliminary Design EIA WUL Operation and Maintenance Plan Financial Funding Plan Design 3.2 Name of Organization compiling/ developing FST Consulting Engineers Sontinga Consulting Services Sontinga Consulting Services Ninham Shand Sontinga Consulting Services Amathole DM / Sontinga Consulting Services DWA / Amathole DM Sontinga Consulting Services Planned date for completion FS/IRS/Design/EIA Completed Completed Date FS/IRS/Design/EIA approved August 2003 July 2009 Completed August 2008 August 2009 January 2010 January 2010 March 2011 March 2015 July 2009 December 2010 Mndwaka Dam June 2011 December 2010 Mndwaka Dam June 2011 Schedules of work and phasing of the activities The project is split into 4 phases: Phase 1 - construction of the Mndwaka Dam, Treatment works and rising mains The first phase of the Mncwasa Water Supply Project embraces the provision of the Mndwaka Dam, Rising Main from the Mndwaka Dam to the Water Treatment Plant, 2.5 Mℓ Water Treatment Plant and a Rising Main from the Water Treatment Plant to the 5 Mℓ Regional Reservoir located in Ward 1 of the Mbashe Local Municipality including the following: Mndwaka Dam constructed on the Mndwaka River Raw water intake structure Raw water pump station Raw water rising main from the pump station to the balancing dam Raw water balancing dam Treatment of the raw water by constructing a water treatment works (33 ℓ/s) Clear water storage High lift potable water pump station: Potable water rising main from the pump station to the regional reservoir 13 PROGRAMME MANAGEMENT: REGIONAL BULK INFRASTRUCTURE APRIL 2014 Sludge ponds Operators houses Road and parking bays. Phase 2 - Construction of the Bulk Storage Reservoirs and Bulk Gravity Pipelines Phase 2 of the MWSP embraces the provision of the 5 Ml Regional Reservoir and bulk infrastructure from the Regional Reservoir to 54 villages in the Mbashe Local Municipality by means of the following: 5 Mℓ regional reservoir; Gravity mains from the regional reservoir to the service reservoirs; Elevated tanks; Service reservoirs. Phase 3 - Construction of the Internal Village Reticulation and Standpipes (not funded by the RBIG programme) The third phase of the MWSP embraces the provision of water services to 28 170 people located in Ward 17, 18 and 19 of the Mbashe Local Municipality by means of the following: Village reticulation from the storage reservoirs to the standpipes Communal standpipes. Phase 4 Construction of the Internal Village Reticulation and Standpipes (not funded by the RBIG programme) The phase for the MWSP embraces the provision of water services to 8 208 people located in Ward 18 and 19 of the Mbashe Local Municipality by means of the following: 3.3 Risks taken and management thereof 3.4 Village reticulation from the storage reservoirs to the standpipes. Communal standpipes No risks have been taken Capacities dedicated to the programme The capacities dedicated to the project are as follows: Funder: DWA and MIG (for reticulation & Bulk ) Implementing agent: ADM Operation & Maintenance: ADM Consulting Engineer: Sontinga Consulting Services Contractors: o Hlumisa Engineering Services – Phase 1A (Complete) o Roberts Bros Phambile JV – Phase 1B (Complete) o Zana Manzi JV – Phase 1C o RJN Projects – Phase 1D o Mkwanazi Construction – Phase 1E (Complete) o Norland Construction – Phase 2A (Complete) o SOSK Civil & Building Construction – Phase 2B o Bluroca /Mhlonhlorhi Business Enterprise JV – Phase 2C o SOSK Civil & Building Construction – Phase 2D 14 PROGRAMME MANAGEMENT: REGIONAL BULK INFRASTRUCTURE o o o o o o o o o o 3.5 APRIL 2014 Midiro Civils and Construction cc – Phase 2E Zana Manzi Services (Pty) Ltd – Phase 2F&G Give Ziyawa Construction – Phase 3A Khayalihle /Mhlonhlorhi Business Enterprise JV – Phase 3B Zimoza Trading – Phase 3C Khayalihle /Mhlonhlorhi Business Enterprise JV – Phase 3D Zana Manzi Services (Pty) Ltd – Phase 3E Zana Manzi Services (Pty) Ltd – Phase 3F&G Cape Kei Construction Services cc – Phase 2H Cape Kei Construction Services cc – Phase 2I Key challenges within the project The key challenges within the project are as follows: The Contractor for the Construction of Mndwaka Dam is falling further behind schedule even though they have implemented two shifts working per day. The volumes of RMC they require to place per day is around 90 m³ and for the last 28 weeks they have only managed to place an average of 56 m³ per day. Due to labour intensive construction methods used on site placing 56 m³ per day is high compared to similar projects where they only place between 20 and 30 m³, i.e. the Port St John’s Dam. The Contractor was delayed in January 2014 when they returned from December 2013 shutdown period to find out that 33 of their trained personnel were recruited by the mining company and could not report back to work. The Contractor submitted their rate for the construction of clay core rock fill embankment to tie into the gravity section however the final Cost estimate needs to be carried out to ensure that the contract does not go over budget. To register all pipeline servitudes for the scheme in rural areas might be a challenge but discussion with ADM and DWA need to be embarked on to pave a way forward. 4. PROJECT RESULTS AND BENEFICIARIES 4.1 Outcomes and outputs Currently the construction of the Mndwaka Dam is behind programme and expected to be complete by the end of March 2015. Phase 2H&I are on programme and are expected to be complete by December 2014. 4.2 Beneficiaries and project results The project has benefited the project team and community with the following; Involvement of trainee personnel in project whilst gaining experience in all project aspects (design, contract administration and policies). Involvement of local people in the project whilst gaining experience and training on construction and contracting aspects (contract management and various construction methods). Provision of basic water services to the community with a population of 36 378 in 6 063 households, and catering for future domestic demand. 15 PROGRAMME MANAGEMENT: REGIONAL BULK INFRASTRUCTURE 4.3 APRIL 2014 Sourcing of materials from local suppliers and manufactures. Jobs Created Job creation details are summarised in Annexure D. 5. CONCLUSION / LESSONS LEARNED 5.1 Main successes and failures of the project to date The alignment of the infrastructure constructed from RBIG funding and MIG funding has made it possible to progressively increase the supply of water to the communities as the phases are rolled out. To date a total of 716 communal standpipes has been installed and commissioned, which supplies potable water to 43 villages, 4695 households and 28 170 people. This was made possible due to the fact that a temporary supply line has been installed during the construction of the Mndwaka Dam. The Construction of the Mndwaka Dam will take much longer to complete than expected due to the high level of labour intensive methods of construction, but more labour will be employed that originally anticipated. The two additional villages namely Nkalweni and Khwezi will be serviced by the Mncwasa water supply scheme and the contract has gone out to tender. 5.2 Ownership and sustainability of infrastructure works The ADM is the Implementing Agent and will take ownership of the infrastructure, and will also be responsible for the operations and maintenance of the works. ADM will ensure that infrastructure servitudes are registered. 6. RECOMMENDATIONS Award contracts to begin with Phase 4 as soon as possible. Monitor the progress for the construction of the Mndwaka Dam and report on expenditure to determine if the contractor will complete the project in the 2014/2015 financial year. 16 PROGRAMME MANAGEMENT: REGIONAL BULK INFRASTRUCTURE ANNEXURE A: Project Implementation Photos Photo 1 : View of Mndwaka Dam – Phase 1C. Photo 2: Installation of the outlet pipework at Mndwaka Dam – Phase 1C. APRIL 2014 17 PROGRAMME MANAGEMENT: REGIONAL BULK INFRASTRUCTURE Photo 3: First section of the Outlet pipework installed – Phase 1C Photo 4: Installation of pipe work – Phase 2H&I. APRIL 2014 18 PROGRAMME MANAGEMENT: REGIONAL BULK INFRASTRUCTURE Photo 5: Construction of reservoirs in progress – Phase 2H&I. Photo 6: Installing one of the Elevated Tanks – Phase 2I. APRIL 2014 19 PROGRAMME MANAGEMENT: REGIONAL BULK INFRASTRUCTURE APRIL 2014 ANNEXURE B: LIST OF VILLAGES EXPECTED TO BENEFIT FROM THE PROJECT Village name Correct Name households population 60l/c/day Bufumba B Nkw alini Madi Kw alini B Ndity a Ndakana B Khoty ana Koty ana Mndw aka A Mndw aka C Mndw aka D Mndw aka B Nx ulume Nx uluma A Marhashu Mpame C Mkhathali Kw aNkumba A Mgababa Manzamamma Mpame A Kw a Thezi Lumkw ana Mpame B Nkov alini A & B Bafazi Nkw alini B Bafazini Bumbano Kw a Gobeni Mkhatazo A Emboleni A Mboty i B Mqojw eni Mkhatazo B Kw andity a & Kw aNdity a A Makw ay ini A Kw afolokhw e Kw a Tshezi Ngazana Nqilini KuloMbethe / Low er Bufumba Nkumba B/ Khw eleni Zikholokotha Talimofu Phukuma & Nkumba Lubanzi A Xw angu Zithulele Mncw asa Lubanzi B Kw aBotho Kw alolokhw e Makw ay ini B Bufumba B Gambushe Kw aMadi Kw alini B Ndity a Ndakana Khoty ana B Khoty ana A Mndw aka A Mndw aka C Mndw aka D Mndw aka B Nx uluma A Nx uluma B Kw a Rhashu Xanx o Mkhatazo Kumanzibomv u Mgababa Manzamny ama Nqakana Kw a Thezi Lumkw ana Mdikana Ny andeni Bafazi Nkw alini B Bafazini Mbuty e Kw agobene/Dlov a Mkhatazo A Emboleni A Mboty i B Mqojw eni Mkhatazo B Kw andity a & Kw aNdity a A Makw ay ini A Kw afolokhw e Kw a Tshezi Ngazana Nqileni Bongw eni Nkumba B/ Khw eleni Zikholokotha Talimofu Phuthuma Lubanzi A KuXw angu Mhlahlane Giny intsimbi Lubanzi B Mw angw ini Kw alolokhw e Makw ay ini B 216 98 130 212 254 116 132 114 52 55 98 65 74 62 54 83 154 94 30 174 163 71 87 58 119 126 98 144 158 129 146 55 43 144 117 106 88 127 130 62 151 98 87 72 147 121 214 212 151 60 130 76 48 58 1296 588 780 1272 1524 696 792 684 312 330 588 390 444 372 324 498 924 564 180 1044 978 426 522 348 714 756 588 864 948 774 876 330 258 864 702 636 528 762 780 372 906 588 522 432 882 726 1284 1272 906 360 780 456 288 348 77,760 35,280 46,800 76,320 91,440 41,760 47,520 41,040 18,720 19,800 35,280 23,400 26,640 22,320 19,440 29,880 55,440 33,840 10,800 62,640 58,680 25,560 31,320 20,880 42,840 45,360 35,280 51,840 56,880 46,440 52,560 19,800 15,480 51,840 42,120 38,160 31,680 45,720 46,800 22,320 54,360 35,280 31,320 25,920 52,920 43,560 77,040 76,320 54,360 21,600 46,800 27,360 17,280 20,880 Total 6,063.00 36,378.00 2,182,680 Incl 5% for 81,648 losses 37,044 49,140 80,136 96,012 43,848 49,896 43,092 19,656 20,790 37,044 24,570 27,972 23,436 20,412 31,374 58,212 35,532 11,340 65,772 61,614 26,838 32,886 21,924 44,982 47,628 37,044 54,432 59,724 48,762 55,188 20,790 16,254 54,432 44,226 40,068 33,264 48,006 49,140 23,436 57,078 37,044 32,886 27,216 55,566 45,738 80,892 80,136 57,078 22,680 49,140 28,728 18,144 21,924 2,291,814 PROGRAMME MANAGEMENT: REGIONAL BULK INFRASTRUCTURE APRIL 2014 ANNEXURE C: DETAILS OF CONTRACTS AWARDED UNDER THE PROJECT CONTRACT NO. AND NAME 8/2/254/2008-2009 Phase 1A Mechanical and Electrical installation for 2.5Ml WTW 8/2/255/2008-2009 Phase 1B Construction of the 2.5Ml Water Treatment Works 8/2/385/2010-2011 Phase 1C Construction of the Mndwaka Dam 8/2/166/2010-2011 Phase 1D Mechanical & Electrical installation for the clear water high lift pump set 8/2/59/2009-2010 Phase 1E Construction of pumping mains and control chambers CONTRACTOR CONTRACT VALUE (incl. VAT) CONTRACT AWARD / START DATE PLANNED COMPLETION DATE ACTUAL COMPLETION DATE EXPENDITURE AS AT 31 MARCH 2014 (incl. VAT) % COMPLETION Hlumisa Engineering Services R 935 800.00 1 March 2010 28 February 2012 28 February 2012 R 871 489.08 100% Roberts Bros Phambile JV R 11 300 000.00 18 February 2010 23 March 2011 23 March 2011 R 11 273 080.75 100% Zana Manzi JV R 70 172 746.86 23 February 2012 14 September 2014 N/A R 49 221 352.93 70.14% RJN Projects R 4 039 839.68 3 May 2011 15 March 2012 15 March 2012 R 3 511 599 100% Mkwanazi Construction R 11 400 000.00 5 May 2010 23 March 2010 23 March 2010 R 10 210 303.84 100% 23 PROGRAMME MANAGEMENT: REGIONAL BULK INFRASTRUCTURE APRIL 2014 CONTRACTOR CONTRACT VALUE (incl. VAT) CONTRACT AWARD / START DATE PLANNED COMPLETION DATE ACTUAL COMPLETION DATE EXPENDITURE AS AT 31 MARCH 2014 (incl. VAT) % COMPLETION Norland Construction R 6 294 043.98 10 May 2010 31 January 2011 31 January 2011 R 6 197 664.16 100% Sosk Civil & Building Construction R 7 514 920.41 31 May 2010 30 January 2011 15 December 2011 R 5 998 350.06 100% Bluroca/Mhlohlorhi Bus Ent JV R 7 713 244.17 1 October 2010 22 April 2011 30 June 2012 R 7 101 201.90 100% Sosk Civil & Building Construction R 8 495 530.49 1 October 2010 22 April 2011 30 June 2012 R 7 870 708.35 100% 8/2/124/2010-2011 Phase 2E Construction of bulk mains and reservoirs Midiro Civils and Construction R 7 022 241.40 7 March 2011 10 January 2012 30 June 2012 R 6 209 312.59 100% 8/2/131/2011-2012 Phase 2F&G Construction of bulk mains and reservoirs Zana Manzi Services R 11 425 664.94 13 June 2012 18 June 2013 29 May 2013 R 11 239 086.12 100% CONTRACT NO. AND NAME 8/2/60/2009-2010 Phase 2A Construction of a 5 Ml concrete reservoir 8/2/89/2009-2010 Phase 2B Construction of bulk mains and reservoirs 8/2/91/2009-2010 Phase 2C Construction of bulk mains and reservoirs 8/2/87/2009-2010 Phase 2D Construction of bulk mains and reservoirs 24 PROGRAMME MANAGEMENT: REGIONAL BULK INFRASTRUCTURE APRIL 2014 CONTRACTOR CONTRACT VALUE (incl. VAT) CONTRACT AWARD / START DATE PLANNED COMPLETION DATE ACTUAL COMPLETION DATE EXPENDITURE AS AT 31 MARCH 2014 (incl. VAT) % COMPLETION 8/2/230/2012-2013 Phase 2H Construction of bulk mains and reservoirs Cape Kei Construction Services R 12 865 768.04 October 2013 November 2014 Still to be finalized R 4 562 995.03 35.46% 8/2/265/2012-2013 Phase 2I Construction of bulk mains and reservoirs Cape Kei Construction Services R 7 659 922.87 October 2013 November 2014 Still to be finalized R 3 019 702.37 39.42% CONTRACT NO. AND NAME PROGRAMME MANAGEMENT: REGIONAL BULK INFRASTRUCTURE ANNEXURE D: PROJECT SCHEDULE APRIL 2014 25 PROGRAMME MANAGEMENT: REGIONAL BULK INFRASTRUCTURE APRIL 2014 26 PROGRAMME MANAGEMENT: REGIONAL BULK INFRASTRUCTURE APRIL 2014 27 PROGRAMME MANAGEMENT: REGIONAL BULK INFRASTRUCTURE APRIL 2014 ANNEXURE E: DETAILS OF JOB OPPORTUNITIES Project Name and Number Mncwasa Water Supply Scheme Local People employed Decent job opportunities Decent job opportunities from 1April 2013 to 31 March 2014 for local people at various occupational levels: Adult Men Adult Women Decent = Full time for at No Person Actual cost No Person Actual cost No least 5 months or more Days on job Days on job opportunities opportunities Youth Men Person Actual cost No Days on job opportunities Clerical Ongoing Youth Women Person Actual cost No Days on job opportunities 1 Disabled Person Actual cost No Days on job opportunities TOTAL Person Actual cost Days on job opportunities R 18 788 1 0 R 18 788 R0 2 8 R 1 280 R 304 935,00 390 23772 R 2 520 478 R0 0 0 R0 Managerial Ongoing 0 0 R0 Managerial New 0 0 R0 77 3 3 5 8255,3 12 86 20 0 2 0 8 R0 R 3 920 Clerical New Labourers Ongoing Labourers New Semi-Skilled Ongoing Semi-Skilled New Skilled Ongoing Skilled New Supervisor Ongoing Supervisor New TOTAL Ongoing TOTAL New 2 93 6130,7 R 654 908,03 45 2786,6 R 287 731,00 203 0 0 R0 0 0 R0 0 28 2610,8 R 408 312 3 221 R 22 694 1 2 18 8 R 3 500 R 1 400 1 4 R 700 1 4 R 1 400 122 8759,5 R 1 066 720 48 3007,6 3 12 R 2 800 1 4 8 R 1 280 12004 R 1 272 903,50 0 49 2850,50 R0 R 662 R1 R7 R1 0 659 190 000 200 8 1 1 1 0 38 2 1 1 4635,3 8 20 4 788,2 4 48 4 R 89 R R 10 R 481 600 500 700 1 4 R 2 520 R 310 425 242 16659 R 1 942 562 59 3686,7 R 423 704 0 0 R0 471 32113 R 3 743 412 R 700 6 24 R 6 190 2 8 R 1 300 0 0 R0 12 48 R 10 990 Contractor People employed Decent job opportunities Decent job opportunities from 1April 2013 to 31 March 2014 for contractor employees Adult Men Adult Women at various occupational No Person No Person No levels: Decent = Full time Days Days for at least 5 months or more Clerical Ongoing Clerical New Labourers Ongoing Labourers New Managerial Ongoing Managerial New Semi-Skilled Ongoing Semi-Skilled New Skilled Ongoing Skilled New Supervisor Ongoing Supervisor New TOTAL Ongoing TOTAL New 11 1102,9 R 952 000 5 90,34 10 789,75 R 64 476 3 160 R 43 560 29 0 2143 0 R 1 060 036 R0 1 1 0 21 21 0 R0 R0 Youth Men Person Days 1 15 1 110 3 282,04 17 1142,4 5 256 27 0 1805,5 0 Youth Women Person Days No 2 190,02 1 21 1 55 R 43 560 1 42 R 158 560 R0 5 0 308,02 0 R 115 000 Disabled Person Days No R0 R0 0 0 0 0 No R0 R0 TOTAL Person Days 3 0 0 0 13 0 8 0 29 0 9 0 62 0 205,02 0 0 0 1233,9 0 372,38 0 2008,2 0 458 0 4277,5 0 R 1 183 R1 R 21 R4 146 790 000 000 28 PROGRAMME MANAGEMENT: REGIONAL BULK INFRASTRUCTURE APRIL 2014 Consulting Engineer managing the project Decent job opportunities for Consulting Engineer employees at various occupational levels: Decent = Full time for at least 5 months or more Managerial Ongoing Managerial New Other Ongoing Other New TOTAL Ongoing TOTAL New Decent job opportunities from 1April 2013 to 31 March 2014 Adult Men Adult Women No Person No Person No Days Days 1 78 R 265 200 1 0 78 0 R 265 200 R0 0 0 0 0 R0 R0 Youth Men Person Days 1 384 R 210 000 1 0 384 0 R 210 000 R0 Youth Women Person Days No 0 0 0 0 Disabled Person Days No R0 R0 0 0 0 0 TOTAL No Person Days R0 R0 2 0 0 0 462 0 0 0 2 0 462 0 Summary of Decent Job Opportunities Decent job opportunities Decent job opportunities from 1April 2013 to 31 March 2014 for people employed at Adult Men Adult Women Youth Men Youth Women Disabled TOTAL various occupational No Person Actual cost No Person Actual cost No Person Actual cost No Person Actual cost No Person Actual cost No Person Actual cost levels: Decent = Full time Days on job Days on job Days on job Days on job Days on job Days on job for at least 5 months or opportunities opportunities opportunities opportunities opportunities opportunities more Clerical Ongoing 0 0 R0 0 0 R0 1 15 R0 3 190,02 R 18 788 0 0 R0 4 205,02 R 18 788 Clerical New 0 0 R0 0 0 R0 2 8 R 1 280 0 0 R0 0 0 R0 2 8 R 1 280 Labourers Ongoing 93 6130,7 R 654 908 45 2786,6 R 287 731 203 12004 R 1 272 904 49 2850,5 R 304 935 0 0 R 0 390 23772 R 2 520 478 Labourers New 0 0 R0 0 0 R0 0 0 R0 0 0 R0 0 0 R0 0 0 R0 Managerial Ongoing 12 1180,9 R 1 217 200 0 0 R0 2 494 R 325 000 1 21 R0 0 0 R0 15 1695,9 R 1 542 200 Managerial New 0 0 R0 0 0 R0 0 0 R0 0 0 R0 0 0 R0 0 0 R0 Semi-Skilled Ongoing 33 2701,1 R 408 312 3 221 R 22 694 41 4917,3 R 662 659 8 788,2 R 89 481 0 0 R0 85 8627,7 R 1 183 146 Semi-Skilled New 0 0 R0 0 0 R0 2 8 R 1 190 1 4 R 600 0 0 R0 3 12 R 1 790 Skilled Ongoing 11 807,75 R 67 976 1 21 R0 18 1162,4 R 7 000 2 103 R 10 500 0 0 R0 32 2094,2 R 85 476 Skilled New 2 8 R 1 400 1 4 R 700 1 4 R 1 200 1 4 R 700 0 0 R0 5 20 R 4 000 Supervisor Ongoing 3 160 R 43 560 0 0 R0 5 256 R 43 560 1 42 R0 0 0 R0 9 458 R 87 120 Supervisor New 1 4 R 1 400 0 0 R0 1 4 R 2 520 0 0 R0 0 0 R0 2 8 R 3 920 Other Ongoing 0 0 R0 0 0 R0 0 0 R0 0 0 R0 0 0 R0 0 0 R0 Other New 0 0 R0 0 0 R0 0 0 R0 0 0 R0 0 0 R0 0 0 R0 TOTAL Ongoing 152 10980 R 2 391 956 49 3028,6 R 310 425 270 18849 R 2 311 122 64 3994,7 R 423 704 0 0 R 0 535 36852 R 5 437 208 TOTAL New 3 12 R 2 800 1 4 R 700 6 24 R 6 190 2 8 R 1 300 0 0 R0 12 48 R 10 990 29 PROGRAMME MANAGEMENT: REGIONAL BULK INFRASTRUCTURE Project Name and Number APRIL 2014 Mncwasa Water Supply Scheme Local People employed Temporary job opportunities for local people at various occupational levels: Temporary = Less than 5 months Temporary job opportunities from 1 April 2013 - 31 March 2014 Adult Men Person Actual cost No Days on job opportunities No Adult Women Person Actual cost No Days on job opportunities Youth Men Person Actual cost No Days on job opportunities Youth Women Person Actual cost No Days on job opportunities Disabled Person Actual cost No Days on job opportunities TOTAL Person Actual cost Days on job opportunities Clerical Ongoing 0 0 Clerical New 0 0 R0 76 4691,2 R 575 501 Labourers New 0 0 R0 Managerial Ongoing 0 0 R0 Managerial New 0 0 R0 Labourers Ongoing Semi-Skilled Ongoing 18 R 25 868 9 5 387,6 119,8 R 45 988 42 R 12 704 5 2833,9 R 357 712 216,2 7 R 33 134 1 368,5 R 41 670 14 527 R 76 672 0 0 R0 Skilled Ongoing 0 0 R0 Skilled New 0 0 R0 Supervisor Ongoing 0 0 R0 Supervisor New 0 0 R0 TOTAL New 147 R 130 131 Semi-Skilled New TOTAL Ongoing 3 1101,2 44 R 4 966 R0 21 1248,2 R 155 999 14 507,4 R 58 692 47 3050,1 R 390 846 8 412,5 R 46 636 0 0 R0 90 5218,2 R 652 173 0 0 R0 0 0 R0 0 0 R0 0 0 R0 0 0 R0 0 0 R0 Contractor People employed Temporary job Temporary job opportunities from 1 April 2013 - 31 March 2014 opportunities for contractor people at Adult Men Adult Women various occupational No Person No Person No levels: Temporary = Less Days Days than 5 months Youth Men Person Days Youth Women Person Days No Disabled Person Days No No TOTAL Person Days Clerical Ongoing Clerical New Labourers Ongoing 0 0 Managerial Ongoing 0 0 Managerial New 0 0 Semi-Skilled Ongoing 0 0 Semi-Skilled New 0 0 Skilled Ongoing 0 0 Skilled New 0 0 Supervisor Ongoing 0 0 Supervisor New 0 0 0 0 0 0 Labourers New TOTAL Ongoing TOTAL New 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 30 PROGRAMME MANAGEMENT: REGIONAL BULK INFRASTRUCTURE APRIL 2014 Summary of Temporary Job Opportunities Temporary job Temporary job opportunities from 1 April 2013 - 31 March 2014 opportunities for people employed at various Adult Men Adult Women occupational levels: No Person Actual cost No Person Actual cost No Temporary = Less than 5 Days on job Days on job months opportunities opportunities Clerical Ongoing Clerical New Labourers Ongoing Labourers New Managerial Ongoing Managerial New Semi-Skilled Ongoing Semi-Skilled New Skilled Ongoing Skilled New Supervisor Ongoing Supervisor New TOTAL Ongoing TOTAL New 0 0 18 0 0 0 3 0 0 0 0 0 21 0 0 0 1101,2 0 0 0 147 0 0 0 0 0 1248,2 0 R0 R0 R 130 131 R0 R0 R0 R 25 868 R0 R0 R0 R0 R0 R 155 999 R0 0 0 9 0 0 0 5 0 0 0 0 0 14 0 0 0 387,6 0 0 0 119,8 0 0 0 0 0 507,4 0 R0 R0 R 45 988 R0 R0 R0 R 12 704 R0 R0 R0 R0 R0 R 58 692 R0 0 0 42 0 0 0 5 0 0 0 0 0 47 0 Youth Men Person Actual cost No Days on job opportunities 0 0 2833,9 0 0 0 216,2 0 0 0 0 0 3050,1 0 R0 R0 R 357 712 R0 R0 R0 R 33 134 R0 R0 R0 R0 R0 R 390 846 R0 Youth Women Person Actual cost No Days on job opportunities 0 0 7 0 0 0 1 0 0 0 0 0 8 0 0 0 368,5 0 0 0 44 0 0 0 0 0 412,5 0 R0 R0 R 41 670 R0 R0 R0 R 4 966 R0 R0 R0 R0 R0 R 46 636 R0 Disabled Person Actual cost No Days on job opportunities 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 R0 R0 R0 R0 R0 R0 R0 R0 R0 R0 R0 R0 R0 R0 0 0 76 0 0 0 14 0 0 0 0 0 90 0 TOTAL Person Actual cost Days on job opportunities 0 0 4691,2 0 0 0 527 0 0 0 0 0 5218,2 0 R0 R0 R 575 501 R0 R0 R0 R 76 672 R0 R0 R0 R0 R0 R 652 173 R0