Mncwasa APE 2013-2014 FINAL

advertisement
ANNUAL PERFORMANCE EVALUATION REPORT FOR MNCWASA
REGIONAL BULK WATER SUPPLY SCHEME
EASTERN CAPE
CHIEF DIRECTORATE: BULK INFRASTRUCTURE PROGRAMME
PERIOD: 01 APRIL 2013 TO 31 MARCH 2014
PROGRAMME MANAGEMENT: REGIONAL BULK INFRASTRUCTURE
TABLE OF CONTENTS
1.
Introduction
2.
Background
2.1
Description of project
2.2
Project History
2.3
Project concept, design and plan
2.4
Start date – duration of the programme
2.5
Funds previously allocated to project
3.
Progress to date
3.1
Implementation of approved business plan
3.2
Schedules of work and phasing of the activities
3.3
Risks taken and management thereof
3.4
Capacities dedicated to the programme
3.5
Key challenges within the project
4.
Project result and beneficiaries
4.1
Outcomes and outputs
4.2
Beneficiaries and project results.
5.
Conclusions / Lessons Learned
5.1
Main successes and failures of the project to date
5.2
Ownership and sustainability of infrastructure works
6.
Recommendations
ANNEXURE A: Project Implementation Photos
ANNEXURE B: List of villages expected to benefit from bulk project
ANNEXURE C: Details of contracts awarded under bulk projects
ANNEXURE D: Project schedule
ANNEXURE E: Details of job opportunities
APRIL 2014
3
PROGRAMME MANAGEMENT: REGIONAL BULK INFRASTRUCTURE
1.
APRIL 2014
INTRODUCTION
In terms of Section 10(7) (b) of the Division of Revenue Act No 2 of 2013 (DORA) as
promulgated in Government Gazette No 36555 dated 10 June 2013, the transferring
national officer must submit an annual performance report for Schedule 6 within four
months in respect of a province and six months in respect of a municipality after the end
of the financial year to the National Treasury.
The Regional Bulk Infrastructure Grant (RBIG) is a Schedule 6 indirect conditional grant
for the benefit in kind of municipalities.
The objective of this Report is to provide an annual performance evaluation report
covering the 4th quarter of RBIG funded projects, in compliance with the DORA. The
objective of this evaluation was to determine whether the progress on the project is
commensurate with the expenditure to date as well as to determine whether the project
is still on course in terms of the original planning.
This performance evaluation report, covering quarter 4 and annual report of the 2013/14
fiscal year, is for the Mncwasa Regional Bulk Water Supply Scheme, one of the
Regional Bulk Infrastructure Grant projects, currently being implemented by the
Amathole District Municipality (ADM) in the Eastern Cape Province, with Department of
Water Affairs (DWA) as funder, and Municipal Infrastructure Grant (MIG) as co-funder.
2.
BACKGROUND
2.1
Description of Project
Mncwasa Water Supply Project is situated in the Eastern Cape along the Wild Coast
and used to be part of the former Transkei area. The area starts north of the Xhora River
and ends at the Mpaka River near Hole in the Wall. The area stretches 15 km inland
from the Coastal belt and is approximately 242 km2 in extent. There is very little urban
development with no towns within this area which consists of 54 rural coastal type
villages with an estimated population of 36 378 in 6,063 households.
The area is remote, being fairly isolated by the Mbashe River from its administrative
areas i.e. Mbashe Local Municipality in Idutywa and Amathole District Municipality in
East London. The nearest towns are Elliotdale, Mthatha and Idutywa. The preferred
access to Mncwasa is a surfaced road (N2) between Idutywa and Mthatha. At
Viedgesville there is a turn off onto the Mqanduli/Coffee Bay road and from there access
to Mncwasa would be at the Lutubeni Mission turnoff or via the Zithulele Hospital Road.
These access roads are in urgent need of repair and can be impassable in wet weather.
2.2
Project history
Water for domestic use in the area was drawn from surface water sources, i.e. streams,
rivers and other open water sources. There was generally no existing water
infrastructure in the rural villages within the project area.
The project was originally divided into four (4) phases, namely:
•
Phase 1 - construction of the Mndwaka dam, treatment works and rising mains.
•
Phase 2 - construction of the bulk gravity mains and reservoirs.
4
PROGRAMME MANAGEMENT: REGIONAL BULK INFRASTRUCTURE
•
•
APRIL 2014
Phase 3 - construction of the internal reticulation for the 43 villages (not funded
from RBIG programme)
Phase 4 - construction of the internal reticulation for the remaining 15 villages
(not funded from RBIG programme).
Due to ADM‘s policies the project was divided up into 23 projects and afterward four of
the projects were combined into two projects and ended up with a total of 21 projects.
During April 2012 ADM instructed Sontinga Consulting Services as the Professional
Service Provider (PSP) to exclude four villages that fell inside the O R Tambo district
due to the legality of cross boarder supply.
The bulk pipelines from the regional reservoir to the village reservoirs, including the
village reservoirs and village reticulations were redesigned to exclude the four villages.
The villages serviced under Phase 4 have now reduced from 15 villages to 11 villages.
Refer to figure 1 and 2 showing the change in the scheme.
Figure 1 – Original Scope of Work
Figure 2 – Revised Scope of Work
5
PROGRAMME MANAGEMENT: REGIONAL BULK INFRASTRUCTURE
2.3
APRIL 2014
Project concept, design and plan
Phase 1 - construction of the Mndwaka Dam, Treatment works and rising mains
The first phase of the Mncwasa Water Supply Project (MWSP) has been divided up into
five sub-phases namely:

Phase 1A – Mechanical and Electrical installation to the water treatment works
includes the following:
 Chemical dosing plant to treat raw water.
 Three rapid gravity sand filter systems.
 Chlorination plant to disinfect clear water.
 All pipe work including valves, fittings and flow meters etc.
 The electrical equipment and wiring for the operation of the new plant.
 The provision of a complete operation and maintenance manual.

Phase 1B – Construction of the 2.5 Mℓ/day Water Treatment Works which
includes the following:
 5 Mℓ Balancing dam.
 Water treatment building.
 Flocculation channels.
 Sedimentation tank.
 Sludge ponds.
 Constructing new recovery pump stations.
 Backwash pipelines.
 Operator’s houses
 Interconnecting pipe work.
 980 m long gravel access road of which 180 m will have a concrete surface.

Phase 1C – Construction of the Mndwaka Dam which include the following:
 27 700 m³ Bulk Earthworks.
 30 330 m³ Rubble Masonry Concrete.
 2 720 m Drilling and Grouting for Steel Bars.
 2 520 m Drilling and Grouting.
 Pump station.
 300 mm dia. Ductile Iron inlet and outlet pipe work, valves and fittings.
 Three new raw water pump sets.

Phase 1D – Mechanical and electrical installation to the pump stations will
include the following:
 Three new clear water pump sets.
 All pipe work including valves, fittings, flow meters etc.
 The electrical equipment and wiring for the operation of the proposed new
plant.
 The telemetry equipment and wiring.
 The provision of a complete operation and maintenance manual.

Phase 1E – Construction of the Rising Mains which includes the following:

1 000 m of 250 mm dia. uPVC rising main.

11 240 m of 200 mm dia. ductile iron rising main.

Air, scour and check valve chambers.
6
PROGRAMME MANAGEMENT: REGIONAL BULK INFRASTRUCTURE


APRIL 2014
2 x Generator rooms
Temporary abstraction point, pump, generator and pipeline.
Phase 2 - Construction of the Bulk Storage Reservoirs and Bulk Gravity Pipelines
The second phase of the Mncwasa Water Supply Project has been divided up into nine
sub-phases namely:

Phase 2A – The construction of the 5 Ml Regional Reservoir which includes the
following:
 5 Ml Reinforced Concrete Reservoir
 Inlet / outlet control chamber
 Erection of a 1.8 m high security fence
 1 km long 5 m wide gravel access road

Phase 2B – The construction of Bulk Infrastructure to 8 Villages, which includes
the following works:

2 x 125 kℓ Reinforced Concrete Reservoirs

1 x 45 kℓ Reinforced Concrete Reservoir

1 x 70 kℓ Elevated GMS Tank on 10 m GMS stand

3 x Break pressure tanks

10 123 m of bulk pipeline of various sizes in diameter

Air, scour and isolating valve chambers

Phase 2C – The construction of Bulk Infrastructure to 9 Villages, which includes
the following works:

1 x 125 kl Reinforced Concrete Reservoir

1 x 75 kl Reinforced Concrete Reservoir

1 x 55 kl Reinforced Concrete Reservoir

10 555 m of bulk pipeline of various sizes in diameter

34 Air and 22 scour valve chambers

Phase 2D – The construction of Bulk Infrastructure to 7 Villages, which includes
the following works:

1 x 125 kl Reinforced Concrete Reservoir

1 x 75 kl Reinforced Concrete Reservoir

1 x 60 kl Reinforced Concrete Reservoir

1 x 35 kl Reinforced Concrete Reservoir

16 264 m of bulk pipeline of various sizes in diameter

51 Air and 26 scour valve chambers

Phase 2E – The construction of Bulk Infrastructure to 8 Villages, which includes
the following works:

1 x 125 kl Reinforced Concrete Reservoir

1 x 85 kl Reinforced Concrete Reservoir

1 x 70 kl Reinforced Concrete Reservoir

1 x 49 kl Elevated GMS Tank on 15 m GMS Stand

7 749 m of bulk of various sizes in diameter.

23 Air and 11 scour valves with chambers.
7
PROGRAMME MANAGEMENT: REGIONAL BULK INFRASTRUCTURE
APRIL 2014

Phase 2F & G – The construction of Bulk Infrastructure to 11 Villages, which
includes the following works:

1 x 85 kl Reinforced Concrete Reservoir

1 x 75 kl Reinforced Concrete Reservoir

1 x 60 kl Reinforced Concrete Reservoir

1 x 55 kl Reinforced Concrete Reservoir

1 x 50 kl Reinforced Concrete Reservoir

1 x 45 kl Reinforced Concrete Reservoir

1 x 40 kl Reinforced Concrete Reservoir

1 x 30 kl Reinforced Concrete Reservoir

4 x Break Pressure Tanks

22 245 m of bulk pipeline of various sizes in diameter

61 Air and 42 scour valves with chambers.

Phase 2H – The construction of Bulk Infrastructure to 7 Villages, which includes
the following works:

1 x 125 kl Reinforced Concrete Reservoir

1 x 75 kl Reinforced Concrete Reservoir

1 x 60 kl Reinforced Concrete Reservoir

1 x 50 kl Reinforced Concrete Reservoir

1 x Break Pressure Tanks

14 889 m of bulk pipeline of varying sizes in diameter.

24 Air and 17 scour valves with chambers.

Phase 2I – The construction of Bulk Infrastructure to 4 Villages, which includes
the following works:

1 x 70 kl Reinforced Concrete Reservoir

1 x 55 kl Reinforced Concrete Reservoir

1 x 30 kl Reinforced Concrete Reservoir

1 x 87 kl Elevated GMS Tank on 10 m GMS Stand

8 127 m of bulk pipeline of varying sizes in diameter.

13 Air and 11 scour valves with chambers.
Phase 3 - Construction of the Internal Village Reticulation and Standpipes (not
funded by RBIG programme)
The third phase of the Mncwasa Water Supply Project has been divided up into seven
sub-phases namely:

Phase 3A – The construction of internal Village Reticulation to 4 Villages, which
includes the following works:

24 603 m of village reticulation ranging between 32 mm and 160 mm in
diameter

4 x Break pressure tanks

Control chambers

66 standpipes

Phase 3B – The construction of internal Village Reticulation to 4 Villages, which
includes the following works:

43 537 m of village reticulation ranging between 32 mm and 200 mm in
diameter
8
PROGRAMME MANAGEMENT: REGIONAL BULK INFRASTRUCTURE




APRIL 2014
16 x Break pressure tanks
Control chambers
114 standpipes
Phase 3C – The construction of internal Village Reticulation to 9 Villages, which
includes the following works:




35 129 m of village reticulation ranging between 32 mm and 110 mm in
diameter
11 x Break pressure tanks
Control chambers
88 standpipes

Phase 3D – The construction of internal Village Reticulation to 7 Villages, which
includes the following works:

43 591 m of village reticulation ranging between 32 mm and 160 mm in
diameter

15 x Break pressure tanks

Control chambers

104 standpipes

Phase 3E – The construction of internal Village Reticulation to 8 Villages, which
includes the following works:

48 405 m of Village Reticulation ranging between 32 mm and 110 mm in
diameter

7 x Reinforce Concrete Break Pressure Tanks

16 x Air Valves

Control Chambers

117 Standpipes

Phase 3F & G – The construction of internal Village Reticulation to 11 Villages,
which includes the following work:

69 314 m of Village Reticulation ranging between 32 mm and 160 mm in
diameter

13 x Break Pressure Tanks

18 x Air Valves

Control Chambers

161 Standpipes
Phase 4 - Construction of the Internal Village Reticulation and Standpipes (not funded by
RBIG programme)
The fourth phase of the Mncwasa Water Supply Project (MWSP) has been divided up
into two sub-phases namely:

Phase 4 – The construction of internal Village Reticulation to 12 Villages, which
includes the following works:

98 713 m of Village Reticulation ranging between 32 mm and 110 mm in
diameter

22 x Break Pressure Tanks

25 x Air Valves
9
PROGRAMME MANAGEMENT: REGIONAL BULK INFRASTRUCTURE


APRIL 2014
41 x Control Chambers
243 Standpipes
The village names that will benefit from the project are listed in Annexure B.
2.4
Start date – duration of the programme
The envisaged dates for executing the phases of this project are as follows:
a)
b)
Phase 1A – Mechanical and Electrical installation to the water treatment
works:
Contract Start date
: September 2009
Contract Completion date
: January 2012
Phase 1B – Construction of the Water Treatment Works:
Contract Start date
: January 2010
Contract completion date
: March 2011
c)
Phase 1C – Construction of the Mndwaka Dam:
Contract Start date
: February 2012
Anticipated Contract Completion date
: March 2015
d)
Phase 1D – Mechanical and electrical installation to the pump stations
Contract Start date
: April 2011
Contract Completion date
: March 2012
e)
Phase 1E – Construction of the Rising Mains
Contract Start date
: April 2010
Contract completion date
: May 2011
f)
Phase 2A – The construction of the 5Mℓ Regional Reservoir
Contract Start date
: March 2010
Contract completion date
: January 2011
g)
Phase 2B – The construction of Bulk Infrastructure to 10 Villages
Contract Start date
: June 2010
Contract completion date
: December 2011
h)
Phase 2C – The construction of Bulk Infrastructure to 9 Villages
Contract Start date
: October 2010
Contract completion date
: November 2011
i)
Phase 2D – The construction of Bulk Infrastructure to 9 Villages
Contract Start date
: October 2010
Contract completion date
: November 2011
j)
Phase 2E – The construction of Bulk Infrastructure to 9 Villages
Contract Start date
: March 2011
Contract completion date
: November 2012
k)
Phase 2F&G – The construction of Bulk Infrastructure to 17 Villages
Contract Start date
: June 2012
Contract completion date
: May 2013
10
PROGRAMME MANAGEMENT: REGIONAL BULK INFRASTRUCTURE
2.5
APRIL 2014
l)
Phase 2H – The construction of Bulk Infrastructure to 8 Villages
Contract Start date
: September 2013
Anticipated Contract completion date
: August 2014
m)
Phase 2I – The construction of Bulk Infrastructure to 10 Villages
Anticipated Contract Start date
: September 2013
Anticipated Contract completion date
: August 2014
n)
Phase 3A – The construction of internal Village Reticulation to 5 villages
Contract Start date
: November 2010
Contract completion date
: September 2012
o)
Phase 3B – The construction of internal Village Reticulation to 5 Villages
Contract Start date
: October 2010
Anticipated Contract completion date
: September 2013
p)
Phase 3C – The construction of internal Village Reticulation to 9 Villages
Contract Start date
: October 2010
Contract completion date
: August 2012
q)
Phase 3D – The construction of internal Village Reticulation to 9 villages
Contract Start date
: October 2010
Anticipated Contract completion date
: September 2013
r)
Phase 3E – The construction of internal Village Reticulation to 9 Villages
Contract Start date
: February 2011
Contract completion date
: January 2012
s)
Phase 3F&G – The construction of internal Village Reticulation to 17
Villages
Contract Start date
: April 2012
Contract completion date
: March 2013
t)
Phase 4A – The construction of internal Village Reticulation to 12 Villages
Anticipated Contract Start date
: TBA
Anticipated Contract completion date
: TBA
Funds previously allocated to project
Table 1 below indicates the funding that was made available to the project during the
past six financial years.
Table 1 Funding for the past 7 financial years
2007 to 2012
Allocation / Spent amount
R47 947 441.00
Co-funding streams:

District Municipality (from - MIG)
2012/2013
2013/2014
R23 591 172.00
R12 148 093.00
: R140 802 755.00 (mostly on reticulation)
11
PROGRAMME MANAGEMENT: REGIONAL BULK INFRASTRUCTURE
3.
APRIL 2014
PROGRESS TO DATE
The performance evaluation was conducted on the 4th April 2014 by the team consisting
of the following people:





3.1
Zandisile Nonjuzana
Kaya Maposa
Teddy Dlamini
Tim Wood
Thando Mkwayimba
DWA KWT
DWA KWT
ZMJV
Sontinga Consulting Services (PSP)
Sontinga Consulting Services (PSP)
Implementation of the approved business plan
Currently the following contracts have been awarded out of the planned twenty phases
and are at present in construction phase. Work and material complies with standards
and quality.
PHASE 1:
All the Contracts have been awarded under this phase namely:

Phase 1A – Supply and installation of Mechanical and Electrical equipment for
the proposed mew 2.5 Mℓ rapid gravity water treatment works.

Phase 1B – Construction of the balancing dam, water treatment building,
flocculation channels, sedimentation tank, sludge pounds and backwash pipe
work.

Phase 1C – Construction of the Mndwaka Dam.

Phase 1D – Supply and installation of mechanical and electrical equipment for
the proposed new clear water high lift pump set.

Phase 1E – Construction of pumping mains and control chambers.
PHASE 2:
Eight Contracts has been awarded under this phase namely:

Phase 2A – Construction of a 5 Ml Reinforced concrete reservoir.

Phase 2B – Construction of reinforced concrete reservoirs elevated steel tank,
bulk pipelines and control chambers.

Phase 2C – Construction of reinforced concrete reservoirs, bulk pipelines and
control chambers.

Phase 2D – Construction of reinforced concrete reservoirs, bulk pipelines and
control chambers.

Phase 2E – Construction of reinforced concrete reservoirs, elevated steel tank,
bulk pipelines and control chambers.

Phase 2F&G – Construction of reinforced concrete reservoirs, bulk pipelines and
control chambers.
12
PROGRAMME MANAGEMENT: REGIONAL BULK INFRASTRUCTURE
APRIL 2014

Phase 2H – Construction of reinforced concrete reservoirs, bulk pipelines and
control chambers.

Phase 2I – Construction of reinforced concrete reservoirs, bulk pipelines and
control chambers.
PHASE 3 & 4:
These projects are for the construction of village reticulation and funded by MIG.
Contract details for phases 1 and 2 are summarised in Annexure C.
Table 2 Milestones
Product
Feasibility Study
Implementation
Readiness Study
Preliminary Design
EIA
WUL
Operation and
Maintenance Plan
Financial Funding
Plan
Design
3.2
Name of Organization
compiling/ developing
FST Consulting Engineers
Sontinga Consulting
Services
Sontinga Consulting
Services
Ninham Shand
Sontinga Consulting
Services
Amathole DM / Sontinga
Consulting Services
DWA / Amathole DM
Sontinga Consulting
Services
Planned date for
completion
FS/IRS/Design/EIA
Completed
Completed
Date
FS/IRS/Design/EIA
approved
August 2003
July 2009
Completed
August 2008
August 2009
January 2010
January 2010
March 2011
March 2015
July 2009
December 2010
Mndwaka Dam
June 2011
December 2010
Mndwaka Dam
June 2011
Schedules of work and phasing of the activities
The project is split into 4 phases:
Phase 1 - construction of the Mndwaka Dam, Treatment works and rising mains
The first phase of the Mncwasa Water Supply Project embraces the provision of the
Mndwaka Dam, Rising Main from the Mndwaka Dam to the Water Treatment Plant, 2.5
Mℓ Water Treatment Plant and a Rising Main from the Water Treatment Plant to the 5 Mℓ
Regional Reservoir located in Ward 1 of the Mbashe Local Municipality including the
following:









Mndwaka Dam constructed on the Mndwaka River
Raw water intake structure
Raw water pump station
Raw water rising main from the pump station to the balancing dam
Raw water balancing dam
Treatment of the raw water by constructing a water treatment works (33 ℓ/s)
Clear water storage
High lift potable water pump station:
Potable water rising main from the pump station to the regional reservoir
13
PROGRAMME MANAGEMENT: REGIONAL BULK INFRASTRUCTURE



APRIL 2014
Sludge ponds
Operators houses
Road and parking bays.
Phase 2 - Construction of the Bulk Storage Reservoirs and Bulk Gravity Pipelines
Phase 2 of the MWSP embraces the provision of the 5 Ml Regional Reservoir and bulk
infrastructure from the Regional Reservoir to 54 villages in the Mbashe Local
Municipality by means of the following:




5 Mℓ regional reservoir;
Gravity mains from the regional reservoir to the service reservoirs;
Elevated tanks;
Service reservoirs.
Phase 3 - Construction of the Internal Village Reticulation and Standpipes (not
funded by the RBIG programme)
The third phase of the MWSP embraces the provision of water services to 28 170
people located in Ward 17, 18 and 19 of the Mbashe Local Municipality by means of the
following:


Village reticulation from the storage reservoirs to the standpipes
Communal standpipes.
Phase 4 Construction of the Internal Village Reticulation and Standpipes (not
funded by the RBIG programme)
The phase for the MWSP embraces the provision of water services to 8 208 people
located in Ward 18 and 19 of the Mbashe Local Municipality by means of the following:


3.3
Risks taken and management thereof

3.4
Village reticulation from the storage reservoirs to the standpipes.
Communal standpipes
No risks have been taken
Capacities dedicated to the programme
The capacities dedicated to the project are as follows:




Funder:
DWA and MIG (for reticulation & Bulk )
Implementing agent:
ADM
Operation & Maintenance: ADM
Consulting Engineer:
Sontinga Consulting Services
Contractors:
o
Hlumisa Engineering Services – Phase 1A (Complete)
o
Roberts Bros Phambile JV – Phase 1B (Complete)
o
Zana Manzi JV – Phase 1C
o
RJN Projects – Phase 1D
o
Mkwanazi Construction – Phase 1E (Complete)
o
Norland Construction – Phase 2A (Complete)
o
SOSK Civil & Building Construction – Phase 2B
o
Bluroca /Mhlonhlorhi Business Enterprise JV – Phase 2C
o
SOSK Civil & Building Construction – Phase 2D
14
PROGRAMME MANAGEMENT: REGIONAL BULK INFRASTRUCTURE
o
o
o
o
o
o
o
o
o
o
3.5
APRIL 2014
Midiro Civils and Construction cc – Phase 2E
Zana Manzi Services (Pty) Ltd – Phase 2F&G
Give Ziyawa Construction – Phase 3A
Khayalihle /Mhlonhlorhi Business Enterprise JV – Phase 3B
Zimoza Trading – Phase 3C
Khayalihle /Mhlonhlorhi Business Enterprise JV – Phase 3D
Zana Manzi Services (Pty) Ltd – Phase 3E
Zana Manzi Services (Pty) Ltd – Phase 3F&G
Cape Kei Construction Services cc – Phase 2H
Cape Kei Construction Services cc – Phase 2I
Key challenges within the project
The key challenges within the project are as follows:

The Contractor for the Construction of Mndwaka Dam is falling further behind
schedule even though they have implemented two shifts working per day. The
volumes of RMC they require to place per day is around 90 m³ and for the last 28
weeks they have only managed to place an average of 56 m³ per day. Due to
labour intensive construction methods used on site placing 56 m³ per day is high
compared to similar projects where they only place between 20 and 30 m³, i.e.
the Port St John’s Dam.

The Contractor was delayed in January 2014 when they returned from December
2013 shutdown period to find out that 33 of their trained personnel were recruited
by the mining company and could not report back to work.
The Contractor submitted their rate for the construction of clay core rock fill
embankment to tie into the gravity section however the final Cost estimate needs
to be carried out to ensure that the contract does not go over budget.
To register all pipeline servitudes for the scheme in rural areas might be a
challenge but discussion with ADM and DWA need to be embarked on to pave a
way forward.


4.
PROJECT RESULTS AND BENEFICIARIES
4.1
Outcomes and outputs
Currently the construction of the Mndwaka Dam is behind programme and expected to
be complete by the end of March 2015.
Phase 2H&I are on programme and are expected to be complete by December 2014.
4.2
Beneficiaries and project results
The project has benefited the project team and community with the following;


Involvement of trainee personnel in project whilst gaining experience in all project
aspects (design, contract administration and policies).
Involvement of local people in the project whilst gaining experience and training
on construction and contracting aspects (contract management and various
construction methods).
Provision of basic water services to the community with a population of 36 378
in 6 063 households, and catering for future domestic demand.
15
PROGRAMME MANAGEMENT: REGIONAL BULK INFRASTRUCTURE

4.3
APRIL 2014
Sourcing of materials from local suppliers and manufactures.
Jobs Created
Job creation details are summarised in Annexure D.
5.
CONCLUSION / LESSONS LEARNED
5.1
Main successes and failures of the project to date
The alignment of the infrastructure constructed from RBIG funding and MIG funding has
made it possible to progressively increase the supply of water to the communities as the
phases are rolled out. To date a total of 716 communal standpipes has been installed
and commissioned, which supplies potable water to 43 villages, 4695 households and
28 170 people. This was made possible due to the fact that a temporary supply line has
been installed during the construction of the Mndwaka Dam.
The Construction of the Mndwaka Dam will take much longer to complete than expected
due to the high level of labour intensive methods of construction, but more labour will be
employed that originally anticipated.
The two additional villages namely Nkalweni and Khwezi will be serviced by the
Mncwasa water supply scheme and the contract has gone out to tender.
5.2
Ownership and sustainability of infrastructure works
The ADM is the Implementing Agent and will take ownership of the infrastructure, and
will also be responsible for the operations and maintenance of the works. ADM will
ensure that infrastructure servitudes are registered.
6.
RECOMMENDATIONS


Award contracts to begin with Phase 4 as soon as possible.
Monitor the progress for the construction of the Mndwaka Dam and report on
expenditure to determine if the contractor will complete the project in the 2014/2015
financial year.
16
PROGRAMME MANAGEMENT: REGIONAL BULK INFRASTRUCTURE
ANNEXURE A: Project Implementation Photos
Photo 1 : View of Mndwaka Dam – Phase 1C.
Photo 2: Installation of the outlet pipework at Mndwaka Dam – Phase 1C.
APRIL 2014
17
PROGRAMME MANAGEMENT: REGIONAL BULK INFRASTRUCTURE
Photo 3: First section of the Outlet pipework installed – Phase 1C
Photo 4: Installation of pipe work – Phase 2H&I.
APRIL 2014
18
PROGRAMME MANAGEMENT: REGIONAL BULK INFRASTRUCTURE
Photo 5: Construction of reservoirs in progress – Phase 2H&I.
Photo 6: Installing one of the Elevated Tanks – Phase 2I.
APRIL 2014
19
PROGRAMME MANAGEMENT: REGIONAL BULK INFRASTRUCTURE
APRIL 2014
ANNEXURE B: LIST OF VILLAGES EXPECTED TO BENEFIT FROM THE PROJECT
Village name
Correct Name
households population 60l/c/day
Bufumba B
Nkw alini
Madi
Kw alini B
Ndity a
Ndakana B
Khoty ana
Koty ana
Mndw aka A
Mndw aka C
Mndw aka D
Mndw aka B
Nx ulume
Nx uluma A
Marhashu
Mpame C
Mkhathali
Kw aNkumba A
Mgababa
Manzamamma
Mpame A
Kw a Thezi
Lumkw ana
Mpame B
Nkov alini A & B
Bafazi
Nkw alini B
Bafazini
Bumbano
Kw a Gobeni
Mkhatazo A
Emboleni A
Mboty i B
Mqojw eni
Mkhatazo B
Kw andity a & Kw aNdity a A
Makw ay ini A
Kw afolokhw e
Kw a Tshezi
Ngazana
Nqilini
KuloMbethe / Low er Bufumba
Nkumba B/ Khw eleni
Zikholokotha
Talimofu
Phukuma & Nkumba
Lubanzi A
Xw angu
Zithulele
Mncw asa
Lubanzi B
Kw aBotho
Kw alolokhw e
Makw ay ini B
Bufumba B
Gambushe
Kw aMadi
Kw alini B
Ndity a
Ndakana
Khoty ana B
Khoty ana A
Mndw aka A
Mndw aka C
Mndw aka D
Mndw aka B
Nx uluma A
Nx uluma B
Kw a Rhashu
Xanx o
Mkhatazo
Kumanzibomv u
Mgababa
Manzamny ama
Nqakana
Kw a Thezi
Lumkw ana
Mdikana
Ny andeni
Bafazi
Nkw alini B
Bafazini
Mbuty e
Kw agobene/Dlov a
Mkhatazo A
Emboleni A
Mboty i B
Mqojw eni
Mkhatazo B
Kw andity a & Kw aNdity a A
Makw ay ini A
Kw afolokhw e
Kw a Tshezi
Ngazana
Nqileni
Bongw eni
Nkumba B/ Khw eleni
Zikholokotha
Talimofu
Phuthuma
Lubanzi A
KuXw angu
Mhlahlane
Giny intsimbi
Lubanzi B
Mw angw ini
Kw alolokhw e
Makw ay ini B
216
98
130
212
254
116
132
114
52
55
98
65
74
62
54
83
154
94
30
174
163
71
87
58
119
126
98
144
158
129
146
55
43
144
117
106
88
127
130
62
151
98
87
72
147
121
214
212
151
60
130
76
48
58
1296
588
780
1272
1524
696
792
684
312
330
588
390
444
372
324
498
924
564
180
1044
978
426
522
348
714
756
588
864
948
774
876
330
258
864
702
636
528
762
780
372
906
588
522
432
882
726
1284
1272
906
360
780
456
288
348
77,760
35,280
46,800
76,320
91,440
41,760
47,520
41,040
18,720
19,800
35,280
23,400
26,640
22,320
19,440
29,880
55,440
33,840
10,800
62,640
58,680
25,560
31,320
20,880
42,840
45,360
35,280
51,840
56,880
46,440
52,560
19,800
15,480
51,840
42,120
38,160
31,680
45,720
46,800
22,320
54,360
35,280
31,320
25,920
52,920
43,560
77,040
76,320
54,360
21,600
46,800
27,360
17,280
20,880
Total
6,063.00
36,378.00
2,182,680
Incl 5%
for
81,648
losses
37,044
49,140
80,136
96,012
43,848
49,896
43,092
19,656
20,790
37,044
24,570
27,972
23,436
20,412
31,374
58,212
35,532
11,340
65,772
61,614
26,838
32,886
21,924
44,982
47,628
37,044
54,432
59,724
48,762
55,188
20,790
16,254
54,432
44,226
40,068
33,264
48,006
49,140
23,436
57,078
37,044
32,886
27,216
55,566
45,738
80,892
80,136
57,078
22,680
49,140
28,728
18,144
21,924
2,291,814
PROGRAMME MANAGEMENT: REGIONAL BULK INFRASTRUCTURE
APRIL 2014
ANNEXURE C: DETAILS OF CONTRACTS AWARDED UNDER THE PROJECT
CONTRACT NO.
AND NAME
8/2/254/2008-2009
Phase 1A Mechanical and
Electrical installation
for 2.5Ml WTW
8/2/255/2008-2009
Phase 1B Construction of the
2.5Ml Water
Treatment Works
8/2/385/2010-2011
Phase 1C Construction of the
Mndwaka Dam
8/2/166/2010-2011
Phase 1D Mechanical &
Electrical installation
for the clear water
high lift pump set
8/2/59/2009-2010
Phase 1E Construction of
pumping mains and
control chambers
CONTRACTOR
CONTRACT
VALUE
(incl. VAT)
CONTRACT
AWARD /
START
DATE
PLANNED
COMPLETION
DATE
ACTUAL
COMPLETION
DATE
EXPENDITURE
AS AT 31
MARCH 2014
(incl. VAT)
%
COMPLETION
Hlumisa Engineering
Services
R 935 800.00
1 March
2010
28 February
2012
28 February
2012
R 871 489.08
100%
Roberts Bros
Phambile JV
R 11 300 000.00
18 February
2010
23 March 2011
23 March 2011
R 11 273 080.75
100%
Zana Manzi JV
R 70 172 746.86
23 February
2012
14 September
2014
N/A
R 49 221 352.93
70.14%
RJN Projects
R 4 039 839.68
3 May 2011
15 March 2012
15 March 2012
R 3 511 599
100%
Mkwanazi
Construction
R 11 400 000.00
5 May 2010
23 March 2010
23 March 2010
R 10 210 303.84
100%
23
PROGRAMME MANAGEMENT: REGIONAL BULK INFRASTRUCTURE
APRIL 2014
CONTRACTOR
CONTRACT
VALUE
(incl. VAT)
CONTRACT
AWARD /
START
DATE
PLANNED
COMPLETION
DATE
ACTUAL
COMPLETION
DATE
EXPENDITURE
AS AT 31
MARCH 2014
(incl. VAT)
%
COMPLETION
Norland
Construction
R 6 294 043.98
10 May 2010
31 January
2011
31 January
2011
R 6 197 664.16
100%
Sosk Civil & Building
Construction
R 7 514 920.41
31 May 2010
30 January
2011
15 December
2011
R 5 998 350.06
100%
Bluroca/Mhlohlorhi
Bus Ent JV
R 7 713 244.17
1 October
2010
22 April 2011
30 June 2012
R 7 101 201.90
100%
Sosk Civil & Building
Construction
R 8 495 530.49
1 October
2010
22 April 2011
30 June 2012
R 7 870 708.35
100%
8/2/124/2010-2011
Phase 2E Construction of bulk
mains and reservoirs
Midiro Civils and
Construction
R 7 022 241.40
7 March
2011
10 January
2012
30 June 2012
R 6 209 312.59
100%
8/2/131/2011-2012
Phase 2F&G Construction of bulk
mains and reservoirs
Zana Manzi
Services
R 11 425 664.94
13 June 2012 18 June 2013
29 May 2013
R 11 239 086.12
100%
CONTRACT NO.
AND NAME
8/2/60/2009-2010
Phase 2A Construction of a 5 Ml
concrete reservoir
8/2/89/2009-2010
Phase 2B Construction of bulk
mains and reservoirs
8/2/91/2009-2010
Phase 2C Construction of bulk
mains and reservoirs
8/2/87/2009-2010
Phase 2D Construction of bulk
mains and reservoirs
24
PROGRAMME MANAGEMENT: REGIONAL BULK INFRASTRUCTURE
APRIL 2014
CONTRACTOR
CONTRACT
VALUE
(incl. VAT)
CONTRACT
AWARD /
START
DATE
PLANNED
COMPLETION
DATE
ACTUAL
COMPLETION
DATE
EXPENDITURE
AS AT 31
MARCH 2014
(incl. VAT)
%
COMPLETION
8/2/230/2012-2013
Phase 2H Construction of bulk
mains and reservoirs
Cape Kei
Construction
Services
R 12 865 768.04
October 2013
November
2014
Still to be
finalized
R 4 562 995.03
35.46%
8/2/265/2012-2013
Phase 2I Construction of bulk
mains and reservoirs
Cape Kei
Construction
Services
R 7 659 922.87
October 2013
November
2014
Still to be
finalized
R 3 019 702.37
39.42%
CONTRACT NO.
AND NAME
PROGRAMME MANAGEMENT: REGIONAL BULK INFRASTRUCTURE
ANNEXURE D: PROJECT SCHEDULE
APRIL 2014
25
PROGRAMME MANAGEMENT: REGIONAL BULK INFRASTRUCTURE
APRIL 2014
26
PROGRAMME MANAGEMENT: REGIONAL BULK INFRASTRUCTURE
APRIL 2014
27
PROGRAMME MANAGEMENT: REGIONAL BULK INFRASTRUCTURE
APRIL 2014
ANNEXURE E: DETAILS OF JOB OPPORTUNITIES
Project Name and
Number
Mncwasa Water Supply Scheme
Local People employed
Decent job opportunities Decent job opportunities from 1April 2013 to 31 March 2014
for local people at various
occupational levels:
Adult Men
Adult Women
Decent = Full time for at
No
Person Actual cost
No
Person Actual cost
No
least 5 months or more
Days
on job
Days
on job
opportunities
opportunities
Youth Men
Person Actual cost
No
Days
on job
opportunities
Clerical Ongoing
Youth Women
Person Actual cost
No
Days
on job
opportunities
1
Disabled
Person Actual cost
No
Days
on job
opportunities
TOTAL
Person Actual cost
Days
on job
opportunities
R 18 788
1
0
R 18 788
R0
2
8
R 1 280
R 304 935,00
390
23772
R 2 520 478
R0
0
0
R0
Managerial Ongoing
0
0
R0
Managerial New
0
0
R0
77
3
3
5
8255,3
12
86
20
0
2
0
8
R0
R 3 920
Clerical New
Labourers Ongoing
Labourers New
Semi-Skilled Ongoing
Semi-Skilled New
Skilled Ongoing
Skilled New
Supervisor Ongoing
Supervisor New
TOTAL Ongoing
TOTAL New
2
93
6130,7
R 654 908,03
45
2786,6
R 287 731,00
203
0
0
R0
0
0
R0
0
28
2610,8
R 408 312
3
221
R 22 694
1
2
18
8
R 3 500
R 1 400
1
4
R 700
1
4
R 1 400
122
8759,5
R 1 066 720
48
3007,6
3
12
R 2 800
1
4
8
R 1 280
12004 R 1 272 903,50
0
49 2850,50
R0
R 662
R1
R7
R1
0
659
190
000
200
8
1
1
1
0
38
2
1
1
4635,3
8
20
4
788,2
4
48
4
R 89
R
R 10
R
481
600
500
700
1
4
R 2 520
R 310 425
242
16659
R 1 942 562
59
3686,7
R 423 704
0
0
R0
471
32113
R 3 743 412
R 700
6
24
R 6 190
2
8
R 1 300
0
0
R0
12
48
R 10 990
Contractor People employed
Decent job opportunities Decent job opportunities from 1April 2013 to 31 March 2014
for contractor employees
Adult Men
Adult Women
at various occupational
No
Person
No
Person
No
levels: Decent = Full time
Days
Days
for at least 5 months or
more
Clerical Ongoing
Clerical New
Labourers Ongoing
Labourers New
Managerial Ongoing
Managerial New
Semi-Skilled Ongoing
Semi-Skilled New
Skilled Ongoing
Skilled New
Supervisor Ongoing
Supervisor New
TOTAL Ongoing
TOTAL New
11
1102,9
R 952 000
5
90,34
10
789,75
R 64 476
3
160
R 43 560
29
0
2143
0
R 1 060 036
R0
1
1
0
21
21
0
R0
R0
Youth Men
Person
Days
1
15
1
110
3
282,04
17
1142,4
5
256
27
0
1805,5
0
Youth Women
Person
Days
No
2
190,02
1
21
1
55
R 43 560
1
42
R 158 560
R0
5
0
308,02
0
R 115 000
Disabled
Person
Days
No
R0
R0
0
0
0
0
No
R0
R0
TOTAL
Person
Days
3
0
0
0
13
0
8
0
29
0
9
0
62
0
205,02
0
0
0
1233,9
0
372,38
0
2008,2
0
458
0
4277,5
0
R 1 183
R1
R 21
R4
146
790
000
000
28
PROGRAMME MANAGEMENT: REGIONAL BULK INFRASTRUCTURE
APRIL 2014
Consulting Engineer managing the project
Decent job opportunities
for Consulting Engineer
employees at various
occupational levels:
Decent = Full time for at
least 5 months or more
Managerial Ongoing
Managerial New
Other Ongoing
Other New
TOTAL Ongoing
TOTAL New
Decent job opportunities from 1April 2013 to 31 March 2014
Adult Men
Adult Women
No
Person
No Person
No
Days
Days
1
78
R 265 200
1
0
78
0
R 265 200
R0
0
0
0
0
R0
R0
Youth Men
Person
Days
1
384
R 210 000
1
0
384
0
R 210 000
R0
Youth Women
Person
Days
No
0
0
0
0
Disabled
Person
Days
No
R0
R0
0
0
0
0
TOTAL
No Person
Days
R0
R0
2
0
0
0
462
0
0
0
2
0
462
0
Summary of Decent Job Opportunities
Decent job opportunities Decent job opportunities from 1April 2013 to 31 March 2014
for people employed at
Adult Men
Adult Women
Youth Men
Youth Women
Disabled
TOTAL
various occupational
No
Person Actual cost
No Person Actual cost
No
Person Actual cost
No Person Actual cost
No
Person Actual cost
No Person Actual cost
levels: Decent = Full time
Days
on job
Days
on job
Days
on job
Days
on job
Days
on job
Days
on job
for at least 5 months or
opportunities
opportunities
opportunities
opportunities
opportunities
opportunities
more
Clerical Ongoing
0
0
R0
0
0
R0
1
15
R0
3 190,02
R 18 788
0
0
R0
4 205,02
R 18 788
Clerical New
0
0
R0
0
0
R0
2
8
R 1 280
0
0
R0
0
0
R0
2
8
R 1 280
Labourers Ongoing
93 6130,7
R 654 908
45 2786,6
R 287 731 203 12004
R 1 272 904
49 2850,5
R 304 935
0
0
R 0 390 23772
R 2 520 478
Labourers New
0
0
R0
0
0
R0
0
0
R0
0
0
R0
0
0
R0
0
0
R0
Managerial Ongoing
12 1180,9
R 1 217 200
0
0
R0
2
494
R 325 000
1
21
R0
0
0
R0
15 1695,9
R 1 542 200
Managerial New
0
0
R0
0
0
R0
0
0
R0
0
0
R0
0
0
R0
0
0
R0
Semi-Skilled Ongoing
33 2701,1
R 408 312
3
221
R 22 694
41 4917,3
R 662 659
8
788,2
R 89 481
0
0
R0
85 8627,7
R 1 183 146
Semi-Skilled New
0
0
R0
0
0
R0
2
8
R 1 190
1
4
R 600
0
0
R0
3
12
R 1 790
Skilled Ongoing
11 807,75
R 67 976
1
21
R0
18 1162,4
R 7 000
2
103
R 10 500
0
0
R0
32 2094,2
R 85 476
Skilled New
2
8
R 1 400
1
4
R 700
1
4
R 1 200
1
4
R 700
0
0
R0
5
20
R 4 000
Supervisor Ongoing
3
160
R 43 560
0
0
R0
5
256
R 43 560
1
42
R0
0
0
R0
9
458
R 87 120
Supervisor New
1
4
R 1 400
0
0
R0
1
4
R 2 520
0
0
R0
0
0
R0
2
8
R 3 920
Other Ongoing
0
0
R0
0
0
R0
0
0
R0
0
0
R0
0
0
R0
0
0
R0
Other New
0
0
R0
0
0
R0
0
0
R0
0
0
R0
0
0
R0
0
0
R0
TOTAL Ongoing
152 10980
R 2 391 956
49 3028,6
R 310 425 270 18849
R 2 311 122
64 3994,7
R 423 704
0
0
R 0 535 36852
R 5 437 208
TOTAL New
3
12
R 2 800
1
4
R 700
6
24
R 6 190
2
8
R 1 300
0
0
R0
12
48
R 10 990
29
PROGRAMME MANAGEMENT: REGIONAL BULK INFRASTRUCTURE
Project Name and
Number
APRIL 2014
Mncwasa Water Supply Scheme
Local People employed
Temporary job
opportunities for local
people at various
occupational levels:
Temporary = Less than 5
months
Temporary job opportunities from 1 April 2013 - 31 March 2014
Adult Men
Person Actual cost
No
Days
on job
opportunities
No
Adult Women
Person Actual cost
No
Days
on job
opportunities
Youth Men
Person Actual cost
No
Days
on job
opportunities
Youth Women
Person Actual cost
No
Days
on job
opportunities
Disabled
Person Actual cost
No
Days
on job
opportunities
TOTAL
Person Actual cost
Days
on job
opportunities
Clerical Ongoing
0
0
Clerical New
0
0
R0
76
4691,2
R 575 501
Labourers New
0
0
R0
Managerial Ongoing
0
0
R0
Managerial New
0
0
R0
Labourers Ongoing
Semi-Skilled Ongoing
18
R 25 868
9
5
387,6
119,8
R 45 988
42
R 12 704
5
2833,9
R 357 712
216,2
7
R 33 134
1
368,5
R 41 670
14
527
R 76 672
0
0
R0
Skilled Ongoing
0
0
R0
Skilled New
0
0
R0
Supervisor Ongoing
0
0
R0
Supervisor New
0
0
R0
TOTAL New
147
R 130 131
Semi-Skilled New
TOTAL Ongoing
3
1101,2
44
R 4 966
R0
21
1248,2
R 155 999
14
507,4
R 58 692
47
3050,1
R 390 846
8
412,5
R 46 636
0
0
R0
90
5218,2
R 652 173
0
0
R0
0
0
R0
0
0
R0
0
0
R0
0
0
R0
0
0
R0
Contractor People employed
Temporary job
Temporary job opportunities from 1 April 2013 - 31 March 2014
opportunities for
contractor people at
Adult Men
Adult Women
various occupational
No
Person
No
Person
No
levels: Temporary = Less
Days
Days
than 5 months
Youth Men
Person
Days
Youth Women
Person
Days
No
Disabled
Person
Days
No
No
TOTAL
Person
Days
Clerical Ongoing
Clerical New
Labourers Ongoing
0
0
Managerial Ongoing
0
0
Managerial New
0
0
Semi-Skilled Ongoing
0
0
Semi-Skilled New
0
0
Skilled Ongoing
0
0
Skilled New
0
0
Supervisor Ongoing
0
0
Supervisor New
0
0
0
0
0
0
Labourers New
TOTAL Ongoing
TOTAL New
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
30
PROGRAMME MANAGEMENT: REGIONAL BULK INFRASTRUCTURE
APRIL 2014
Summary of Temporary Job Opportunities
Temporary job
Temporary job opportunities from 1 April 2013 - 31 March 2014
opportunities for people
employed at various
Adult Men
Adult Women
occupational levels:
No Person Actual cost
No Person Actual cost
No
Temporary = Less than 5
Days
on job
Days
on job
months
opportunities
opportunities
Clerical Ongoing
Clerical New
Labourers Ongoing
Labourers New
Managerial Ongoing
Managerial New
Semi-Skilled Ongoing
Semi-Skilled New
Skilled Ongoing
Skilled New
Supervisor Ongoing
Supervisor New
TOTAL Ongoing
TOTAL New
0
0
18
0
0
0
3
0
0
0
0
0
21
0
0
0
1101,2
0
0
0
147
0
0
0
0
0
1248,2
0
R0
R0
R 130 131
R0
R0
R0
R 25 868
R0
R0
R0
R0
R0
R 155 999
R0
0
0
9
0
0
0
5
0
0
0
0
0
14
0
0
0
387,6
0
0
0
119,8
0
0
0
0
0
507,4
0
R0
R0
R 45 988
R0
R0
R0
R 12 704
R0
R0
R0
R0
R0
R 58 692
R0
0
0
42
0
0
0
5
0
0
0
0
0
47
0
Youth Men
Person Actual cost
No
Days
on job
opportunities
0
0
2833,9
0
0
0
216,2
0
0
0
0
0
3050,1
0
R0
R0
R 357 712
R0
R0
R0
R 33 134
R0
R0
R0
R0
R0
R 390 846
R0
Youth Women
Person Actual cost
No
Days
on job
opportunities
0
0
7
0
0
0
1
0
0
0
0
0
8
0
0
0
368,5
0
0
0
44
0
0
0
0
0
412,5
0
R0
R0
R 41 670
R0
R0
R0
R 4 966
R0
R0
R0
R0
R0
R 46 636
R0
Disabled
Person Actual cost
No
Days
on job
opportunities
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
R0
R0
R0
R0
R0
R0
R0
R0
R0
R0
R0
R0
R0
R0
0
0
76
0
0
0
14
0
0
0
0
0
90
0
TOTAL
Person Actual cost
Days
on job
opportunities
0
0
4691,2
0
0
0
527
0
0
0
0
0
5218,2
0
R0
R0
R 575 501
R0
R0
R0
R 76 672
R0
R0
R0
R0
R0
R 652 173
R0
Download