Section Cover Sheet Section 02234 Topsoil and Subsoil Stripping 2006-10-31 Use this section to specify requirements for Topsoil and Subsoil stripping. This section applies to stripping requirements for Site areas that will be affected by the Temporary and Permanent Work including excavation and borrow areas; fill placement areas; temporary roads: including temporary access roads, haul roads, detours; construction facilities, lay down and parking areas, Minister’s site office access; and stockpile areas, including Topsoil stockpiles. Normal practice is to reclaim areas that will be returned to its original or equivalent land use in the foreseeable future, and where productivity of the land is a concern. This will typically require that topsoil and subsoil, if present, are stripped and subsequently replaced on areas where significant disturbance has occurred (i.e. excavation or fill placement). Reclamation will usually also apply to any private lands. For areas that will not be returned to original or equivalent land use, and where productivity of the land is not a concern, these areas are normally landscaped. For landscaped areas, only the topsoil is stripped and replaced. This will usually also apply to lands within the permanent right-of way for the project. This approach is consistent with the Environmental Protection and Enhancement Act which specifies that topsoil must be conserved, and that the lands be returned to equivalent productivity. The Act is silent on the question of subsoil stripping, however practice has shown, that in most situations, stripping and replacing of subsoil is required in order to meet that objective. For canal rehabilitation projects, the typical approach is to strip only topsoil within the canal right of way, and to strip topsoil and subsoil within those borrow areas that will be returned to its original or equivalent land use. For a dam and reservoir project, typically only topsoil is stripped from required excavation areas including the footprint of the dam and spillway channels, while topsoil and subsoil is stripped within borrow areas that will be returned to its original or equivalent land use. For sites that are sufficiently large or complex, the involvement of a soils specialist as part of the environmental study phase or preliminary design phase to survey the site and develop stripping recommendations may be warranted. This requirement, as well as the criteria that will be used to establish topsoil and/or subsoil stripping areas, should be reviewed with Alberta Transportation. Edit this section to suit the Contract requirements. Heading of Specification Text Part 1 General 1.1 Definitions Specification Note CWMS Civil Works Master Specification Alberta Transportation Master Specification System Page 1 Section Cover Sheet Section 02234 Topsoil and Subsoil Stripping 2006-10-31 Heading of Specification Text Specification Note .1 & .2 Edit as required to suit the site conditions. [.3] Include and co-ordinate with clause 3.3 if required. 1.2 References [1.3] [Submittals] Part 2 Products Part 3 Execution 3.1 Protection of Existing Facilities 3.2 Stripping If frozen conditions cannot be avoided, specify the location where frozen materials are to be stockpiled and determine the eventual use of the material recognizing that the material may be a mixture of Topsoil and Subsoil. Edit the clauses as required to recognize the mixture of Topsoil and Subsoil. .3 Edit as required. [.4] & [.6] Include for winter construction of canals or other similar works in order to minimize freezing of the underlying materials (mineral soils) which will be excavated and, if suitable, incorporated in fills. .5 Edit as required. .7 Identify specific borrow areas where Subsoil stripping is required after Topsoil stripping. .8 Delete “or as established by the Minister” when stripping is performed under a Lump Sum method of payment. 3.3 Include this clause where a large amount of stripping is required. - Not Used [Removal of Unsuitable Organic Soils] Include and co-ordinate with clause 1.1.3 if required. Co-ordinate with Section 02315 – Excavation or Section 02316 – Excavation [Canal]. CWMS Civil Works Master Specification Alberta Transportation Master Specification System Page 2 Section Cover Sheet Section 02234 Topsoil and Subsoil Stripping 2006-10-31 Heading of Specification Text .1 & .2 3.4 Specification Note Edit as required. Stockpiling Edit to recognize the mixture of Topsoil and Subsoil as noted above. .1 .2 & .3 Edit as required. .4 Edit as required. .7 Edit as required. .8 Edit as required. END OF COVER SHEET CWMS Civil Works Master Specification Alberta Transportation Master Specification System Page 3 Tender No.: [ ] PART 1 GENERAL 1.1 DEFINITIONS 1.2 Section 02234 Topsoil and Subsoil Stripping Page 1 .1 “Topsoil” means the uppermost part of the soil, ordinarily moved in tillage, or its equivalent in uncultivated soils, and normally ranging in depth from [50 mm to 450 mm] [ ]. It corresponds to the surface “A” (organo–mineral) horizon of the soil profile as defined by the Canadian System of Soil Classification. .2 “Subsoil” means the portion of soil material that lies immediately beneath the Topsoil extending to root depth. In exceptional cases, subsoil may be up to [1500 mm] [ ] in depth. It corresponds to the “B” horizon and the upper portion of the parent material as defined by the Canadian System of Soil Classification. In some soils there is no “B” horizon. [.3] “Unsuitable Organic Soils” means soils that contain organic materials and are not suitable for use as earthwork materials or as Topsoil and Subsoil. These soils would include soils that contain too much organic matter for earthwork materials, are contaminated, or do not meet the requirements of Soil Quality Criteria Relative to Disturbance and Reclamation. REFERENCES .1 Provide Topsoil and Subsoil stripping in accordance with the following standards (latest revision) except where specified otherwise. .2 Canadian Soil Survey Committee, 1998, Research Branch, Canada Department of Agriculture, Publication 1646 .1 .3 Soil Quality Criteria Working Group, Soil Reclamation Subcommittee, Alberta Soils Advisory Committee, Alberta Agriculture, March 1987 – Reprinted November 1993, Conservation and Development Branch, Alberta Agriculture .1 [1.3] Canadian System of Soil Classification Soil Quality Criteria Relative to Disturbance and Reclamation [SUBMITTALS] .1 Provide the following submittals. .2 A stripping plan at least 15 days prior to commencing stripping operations that indicates the limits of stripping in each area; the schedule for such work; and, the methods and procedures that will be used for stripping and handling stripped materials; and for preventing wind and water erosion. Tender No.: [ Section 02234 Topsoil and Subsoil Stripping Page 2 ] – PART 2 PRODUCTS PART 3 EXECUTION 3.1 PROTECTION OF EXISTING FACILITIES .1 3.2 NOT USED Locate and protect utility lines, survey reference points, instrumentation, culverts, and all other existing facilities before commencing stripping operations. STRIPPING .1 Do not strip any area without prior authorization of the Minister. .2 Do not drive on undisturbed areas except for performance of the stripping operation. Stay on temporary roads: including temporary access roads, haul roads, detours; construction facilities, lay down and parking areas, Minister’s site office access, and do not disturb grassed or natural areas. .3 Strip Topsoil from the areas where [Common Excavation, Structure Excavation, and Borrow Area Excavation] and fill placement are required. [.4] Do not strip Topsoil from areas more than [500] m in advance of [canal] excavation and fill placement operations. .5 Strip Topsoil from [temporary roads: including temporary access roads, haul roads, detours; construction facilities, lay down and parking areas, Minister’s site office access; and stockpile areas including Topsoil stockpiles]. [.6] Sequence Topsoil and Subsoil stripping to minimize the exposed areas and protect underlying mineral soil from freezing. Where frost penetration has occurred prior to the commencement of Topsoil and Subsoil stripping in a particular area, the Minister will adjust the depth of stripping to include the frozen material. .7 Within [borrow areas] [ .8 Strip Topsoil and Subsoil to the depths specified in the Contract Documents [or as established by the Minister]. .9 Strip Topsoil and Subsoil separately to prevent admixing. .10 Sequence, stagger, and conduct stripping and excavation operations so that undesirable mineral soil does not become mixed with Topsoil or Subsoil. .11 Use equipment with precise depth control, such as a grader, when stripping shallow or variable depths of material. ], strip Subsoil after the topsoil has been removed. Tender No.: [ ] Section 02234 Topsoil and Subsoil Stripping Page 3 .12 Suspend stripping operations during rain, snow, wet ground conditions, high winds, or other conditions that may result in contamination or loss of material. .13 Drain surface water away from the stripped areas to prevent ponding and infiltration in fill placement areas. [3.3] [REMOVAL OF UNSUITABLE ORGANIC SOILS] .1 Excavate Unsuitable Organic Soil in accordance with Section [02315] [02316] – [Excavation] [Excavation [Canal]]. The Minister will determine the extent of Unsuitable Organic Soil. .2 Dispose of Unsuitable Organic Soil at [waste disposal area [nos. ] [Waste Fill zones] [or at locations established by the Minister], and bury under a minimum cover of 1 m of mineral soil. 3.4 STOCKPILING .1 Stockpile Topsoil from [Common Excavation, Structure Excavation, and Borrow Area Excavation], and fill placement areas [adjacent to the stripped area and within the Site Limits as authorized by the Minister] [at locations specified in the Contract Documents] [or as established by the Minister]. .2 Stockpile Topsoil from [ temporary roads: including temporary access roads, haul roads, detours; construction facilities, lay down and parking areas, Minister’s site office access; and stockpile areas except for Topsoil stockpiles] adjacent to the stripped area and within the Site Limits as authorized by the Minister. .3 Stockpile Subsoil from [Borrow Area Excavation] and [ ] areas [adjacent to the stripped area and within the Site Limits as authorized by the Minister] [at locations specified in the Contract Documents] [or as established by the Minister]. .4 Separately stockpile Topsoil, Subsoil, [Topsoil with frozen materials,] [and Subsoil with frozen materials]. .5 Maintain a minimum separation of 3 m between stockpiles of differing materials. .6 Use silt fences and other erosion control measures to prevent soil loss from the stockpiles due to wind or water erosion. .7 Do not interfere with drainage courses with stockpiled material. Keep stockpiles a minimum distance of [30] m from a river, stream, lake, reservoir or other surface bodies of water. Tender No.: [ ] Section 02234 Topsoil and Subsoil Stripping Page 4 .8 Do not stockpile material at slopes steeper than [3H:1V]. .9 Maintain stockpiles in a condition meeting the above requirements. END OF SECTION