OCEAN SHORES, WASHINGTON SANITARY SEWER PROJECT

advertisement
REMEMBER!: PAGE 2 IS MISSING
Category:
Winner or Honorable Mention:
Title of the Project:
City:
Population:
Name:
Title:
Phone:
1,500 to 4,999 Population
Ocean Shores Sanitary Sewer
City of Ocean Shores
3,500
Karen Thevik
Public Works Coordinator
(360) 289-2754
OCEAN SHORES, WASHINGTON
SANITARY SEWER PROJECT
Ocean Shores, Washington is a retirement-vacation community of 12,000 lots and
permanent population of 4,000 people located at the mouth of the Chehalis River. The
community is located entirely on a sand spit peninsula, seven miles long, surrounded by
the Pacific Ocean on the west and south, Grays Harbor on the east, and a mile wide
isthmus on the north. The City was incorporated in the early 1970's after the properties
were subdivided in the 1960's. Since the time of subdivision all lots in the city have been
provided domestic water, at first by a County water district, and later by the City.
Domestic waste from the commercial areas has been collected with a conventional
gravity system and treated with a lagoon system at the south end of the peninsula. The
residential areas have relied on septic systems with on-site disposal.
Septage treatment in the fine sandy soils of the area is less than adequate because of
the high winter water table and the lack of adequate soil depth. Over the years since
development began, the residual amounts of phosphorous and nitrogen in the shallow
soils and ground water rose to alarming levels. Surface waters choked with vegetation
and reduced oxygen levels resulted in areas that once supported high concentrations of
fish life and navigable waters.
Although the natural levels of nitrogen and phosphorous are high because of the marine
influence, the effect of the inadequately treated domestic wastes became apparent.
Studies of the shallow ground waters and the recreational surface waters showed that
approximately 70 percent of the nutrients originated from human waste.
In 1989, the City started a process to plan, design and construct sanitary sewer facilities
for all areas of the City, and County areas around the City. Several small sections of the
City were sewered, as City crews were able to construct collection system. Costs to
construct the collection system in the flat, high ground water, areas were excessive and
frequently, more costly than the value of the lots served. In an effort to reduce costs, the
City, through volunteer committees, began a four-year process to evaluate alternative
and innovative collection conveyance methods from the lot to the treatment plant. The
basic premise involved minimizing costs and constructing a system that fairly assessed
properties as evenly as possible. In 1994, a Public Works Advisory Committee
presented findings to the City Council that recommended construction of a 2 million
gallon per day treatment facility and 100 miles of sewer mains to provide service to over
10,000 lots in the City in two phases: 1) a smaller area in the northeast section of the
City to gain confidence with the legal process, and 2) the remainder of the City to evenly
assess the properties in a large district.
To overcome the expense associated with deep gravity mains, many lift stations and
severe around water conditions, an alternative sewer collection system was proposed.
This system involved conveyance from the lots, to seven centralized locations, with a
seldom seen, alternative type of vacuum sewer. Domestic sewage is collected at
PAGE 2 IS MISSING
The LID 98-01 district encompassed nearly all the remaining unsewered areas in the
City, with a total assessed value of $ 39,000,000. The minimum assessment was
$2,650 and the maximum was $ 5,200, again depending on the "Special Benefit" of
each lot.
Washington State Engineering Consultants together with City Staff and assistance from
the same component manufacturer from Indiana, successfully completed the project
design, bid and construction. The completed project consisted of nine individual
contracts; 90 miles of main line vacuum pipe, 6 vacuum collection structures, and 37
miles of sewer service pipe.
Vacuum sewer mains were installed in narrow trenches in a saw-tooth profile to
minimize trench depth and avoid existing utilities. The mains are laid to a constant 2%
down-slope to encourage gravity flow. Every 500 feet, or so, the pipe is raised with 2450 bends to maintain shallow elevations or perhaps to avoid underground obstacles.
Unlike gravity flow, which requires elevation fall to achieve scouring velocity, the
vacuum system depends upon the inrush of atmospheric pressure air at velocities
approaching 25 miles per hour to carry the sewage toward central collection in a twophased liquid/air flow.
The Vacuum pump station is similar in function to a lift station in a gravity sewer system
in that sewage pumps transfer the sewage from the collection tank through a force main
to the treatment plant. Unlike a lift station, the vacuum station utilizes pumps that create
vacuum in the sewer main lines and the enclosed collection tank. These pumps
maintain the system's vacuum level that is the energy source for the collection system.
As sewage and air enters the system, the system vacuum will slowly decrease.
To accept the flows from the expanding collection system, western Washington
consultants designed a new wastewater treatment facility in 1997 and construction was
completed in 1999. The treatment plant project included nine miles of force mains to
connect all the centralized vacuum collection locations to the treatment plant. Because
of limited land availability, aerated lagoon wastewater treatment was abandoned in
favor of the activated sludge process. This type of process allows wastewater treatment
capacity for the complete build-out of City lots and the service of County areas north of
the City, which are in the recognized Sewer Service Area.
The treatment plant project was financed with short-term financing, and the permanent
financing, will be through the sale of $11 million of revenue bonds. In March of 2000 the
City successfully marketed $39 million of LID bonds, with an interest rate of 7.1 percent,
with assessments pledged for a 15-year repayment.
In conclusion, the City of Ocean Shores sewer project provides cost effective sewer
service to a rapidly growing, environmentally challenged community.
Download