Introduction: Acknowledgements: This program was funded by a grant from Coastal Zone Management under the Coastal Pollution Remediation program to the Town of Oak Bluffs Shellfish Department. The project represents a cooperative effort between that Department, the two Town Departments of Public Works and the Martha’s Vineyard Commission. The Tisbury DPW, Oak Bluffs Highway and Shellfish Departments and Town Accountant and MV Commission provided in-kind matches for the grant to meet the 25 percent requirement. The project was greatly aided by the insights of Fred LaPiana, Tisbury DPW Director and Richard Combra, Jr., Oak Bluffs Highway Director. Fieldwork was planned by Bill Wilcox and largely carried out by Tonya Jilek, summer intern at the Martha’s Vineyard Commission. Bob Ford, Wallace Ross and Sam Low mapped the catch basins on Vineyard Avenue in Oak Bluffs. Dave Grunden, Oak Bluffs Shellfish Warden and Bill Wilcox, MVC Water Resource Planner, prepared the grant proposal for this project. Chris Seidel, MVC, created the GIS graphics from a vast array of field data. Limitations of the Data Within This Report: The majority of the basin locations shown were mapped with a Trimble Geoexplorer Global Positioning System with accuracy set to near the highest setting that should provide positions to within less than 10 feet. In some cases, 100 percent correction of the positions could not be obtained and the basin locations may not plot up in the pattern they are found on the ground. As we neared completion of the GPS mapping component and began the field mapping for ground slope and extent of the runoff contributing areas for each system, we found additional basins that were then mapped on the Assessor’s base map. These are indicated on the map with a dot in the center of the symbol and may not have the same accuracy when shifted to the aerial photo base map. The roads in both Towns vary in width and presence or absence of sidewalks along their lengths. As a result, the width of impervious surface varies along the length of the road. The widths shown in the following Tables are based on several measurements but do not represent a precise indication of the area of impervious cover. The impervious areas calculated are reasonable approximations of the actual situation and provide a means for comparing one system with another and prioritizing corrective actions. However, a field survey must be conducted to calculate precise runoff values before designing infiltrations systems. On the maps of the collection system, portions of the roadway that are sloped to contribute runoff to the actual collection system are shown. These areas were identified in the field using the Assessor’s Map as a base and represent reasonable outlines of the contribution areas. In addition, in some areas there is sloping ground that is out of the roadway right of way that will add runoff to the system under the right rainfall intensity. This is particularly so in the Tisbury Main Street and Oak Bluffs Circuit Avenue collection systems where the development pattern is dense and the presence of on-lot infiltration capacity is very limited. There are also paved parking areas that will add to CPR Final Report 2 the volume of runoff from off-road land use areas. These parking areas are mentioned in the text that follows but were not measured. Stormwater Collection System- Town of Tisbury Sources Not Mapped: Three substantial stormwater systems within the Town were not mapped as they have been corrected to a large extent by the installation of first flush systems. These include the West Spring Street system that receives runoff from the entire length of West Spring Street back to the grammar school as well as from side streets. The runoff from this roadway exits via a pipe at the head of a small wetland system fed by fresh springs that flow into Tashmoo Pond near the Tisbury Water Department driveway. Drainage from Dunham and Skiff Avenue has been greatly reduced by the installation of an infiltration system that intercepts a large part of the runoff that once flowed into the West Arm of Lagoon Pond. Runoff from Lagoon Pond Road formerly flowed down to a low area and into a catch basin that discharged directly into the West Arm near the drain way for Ben Luce’s Pond. Infiltration capacity was installed along the road right of way to reduce this source. To the east of the crest in Lagoon Pond Road near the intersection with Weaver Lane, runoff formerly flowed down the road to the southeast, across a short stretch of beach and into the main body of Lagoon Pond. This source was also substantially reduced by the installation of infiltration capacity along the road right of way. General Stormwater System description: Tisbury Harbor is the recipient of runoff from a large portion of the Town that is arrayed on the sloping ground around the Harbor to the west and south. The Lagoon receives a lesser amount. Ground slope toward the Harbor ranges from 8 to 15 percent as mapped by the USDA Natural Resource Conservation Service. Soil type is not mapped in the urban areas but nearby in all directions it is Carver loamy coarse sand that is a drouthy soil with significant capacity to infiltrate runoff. The stormwater system can be divided into two isolated systems serving Town roads, two isolated systems serving segments of Beach Road (a State road), the Main Street system and a system that partially links a State Road system to a Town system on Causeway Road. In addition, we identified a residential street system that discharges into the outer Harbor across a 40-foot wide stretch of beach that showed signs of gullying from the volume of discharge running out. All Tisbury systems mapped are shown in Figures 1 and 2. Owen Little Way Discharge: This discharge is a direct outflow into outer Tisbury Harbor after passage through a number of recently installed first-flush basins higher up in the watershed and near the discharge point. As installed, the Owen Little Way system includes two sub-systems that, while they discharge next to each other, are not directly linked. Both systems have first flush basins to reduce pollutant output that consist of leaching pit systems with limestone rock at the bottom and oil absorbent pads at the top. Over 30 of these basins were installed. Many of the streets are curbed preventing loss of runoff onto roadsides. CPR Final Report 3 One segment includes collection along Main Street south of Daggett, Tashmoo, Hemlock and Daggett. This runoff passes into a leaching gallery located near the Yacht Club with excess runoff returning to the discharge pipe and into the outer harbor by direct discharge. The other includes Main Street north of Daggett and Fairfield. The entire watershed is moderate density residential (approximately ½ to 1 acre density). These systems discharge via two 24-inch diameter pipes. During the August 5 rainfall the pipes discharged a noticeably “sooty” looking runoff at high enough rates to roil the surface of the water for some distance beyond the pipe. The data is reported in Table 21 as TIS1. Street length and area for the systems are reported in Table 1. NOTE: IN ALL TABLES OF IMPERVIOUS SURFACES THE LENGTH OF THE STREETS DIRECTLY OVER THE COLLECTION SYSTEM AND THE LENGTH OF STREETS THAT SLOPE TO THE COLLECTION SYSTEM AND CONTRIBUTE TO IT ARE REPORTED SEPARATELY. System North South Table 1: Owen Little Way Stormwater Discharge Street Width of Street and Length of street in Length of street Sidewalk(s) collection system contributing to collection system Main Main Fairfield N William Hatch Daggett Daggett Fairfield N. William Locust Hemlock Authier Tashmoo Tashmoo Franklin Main Owen Little Way TOTAL LENGTH (feet) TOTAL AREA (square feet) 30 30 21 28 18 27 25 21 24 18 19 15 26 26 32 30 20 1075 370 840 350 200 1040 700 650 840 540 335 300 790 160 2180 1440 590 5070 132360 7330 191465 Main Street- Steamship Authority Discharge: This discharge is a direct outflow into Tisbury Harbor. The Main Street system drains a large area of high-density (<1/4 acre) commercial and residential land use. The system discharges via a 36-inch diameter pipe beneath the Steamship Authority pier. A large runoff contribution from areas adjoining the streets is expected to add to the total volume discharged. Most of the streets are curbed preventing loss of runoff onto roadsides. We were not able to obtain a sample from this system due to the location of the discharge and hazards associated with sampling at a site frequented by large vessels. In addition, runoff from two Town CPR Final Report 4 Parking lots and the Steamship Authority Parking lot add to the runoff on Water Street. The school parking lot generates runoff that flows onto Spring Street at the west end of this system. Some runoff from the Catholic Church parking lot on Clough Lane may add to the runoff volume. Table 2: Main Street System Discharging at the Steamship Authority Pier Length of street in Length of street System Street Width of Street and collection system contributing to Sidewalk(s) collection system Main Main William William Franklin Franklin Spring Spring Center Center Pine Look Look Clough Church Colonial Woodlawn Union Water Drummer Greenwood N. William TOTAL LENGTH (feet) TOTAL AREA (square feet) 32 32 24 24 39 34 27 29 25 25 28 27 27 33 30 13 29 32 60 9 27 24 1560 730 280 1170 440 1100 440 1540 1300 325 290 330 260 175 780 700 570 540 650 7065 229075 340 440 390 6115 190165 Causeway Road Discharge: The Causeway Road system collects water from three separate basins and releases it into the head of the extensive lowlands and wetlands associated with Mud Creek. One drainage basin includes Mt. Aldworth Street and part of Delano Road. The second includes approximately 50 percent of the runoff collected by the Edgartown Road-State Road system west of Causeway Road. Half of the flow from this system is diverted into the Causeway Road system by a partially blocked pipe. The third system is Causeway Road itself. All three areas are moderate density residential. The volume of runoff generated is sufficient to carry sand, silt and other debris that has accumulated at the outlet in the upland area before the wetlands. This discharge was not sampled during the course of this study. This discharge location has some advantages in that filtration, absorption and infiltration of sediment, nutrients and bacteria can occur before it reaches Mud Creek. One option for improvement may be the design and installation of a sediment collection system to trap solids for removal and minimize their movement, over time into the wetlands. CPR Final Report 5 Table 3: Causeway Road Stormwater System System Street Width of Street and Sidewalk(s) Causeway Causeway Delano Road Mt Aldworth Edgartown-VH Road (1/2) Edgartown-VH Road (1/2) Cook Road State Road (1/2) State Road (1/2) Look (1/2) TOTAL LENGTH (feet) TOTAL AREA (square feet) 27 27 19 25 42 Length of street in Length of street collection system contributing to collection system 485 244 570 895 1000 42 19 32 32 27 240 180 650 1310 44495 1950 440 1874 84043 State Road Discharge at Beach Street Extension: This discharge is a direct outfall into Tisbury Harbor. The remainder of State Road and Edgartown Road runoff that bypasses the Causeway Road cutoff gathers runoff from Camp Street and William Street and carries it to a 36-inch bypass pipe that begins at the Fire Station and enters the Harbor at the end of Beach Street Extension. While not originating from the same source, Beach Street Extension also includes three other stormwater discharges as described under the section “Five Corners Discharge”. The watershed includes moderate to high-density residential development. Analyses of runoff at this discharge are reported in Table 21 as TIS2. This sample would reflect water quality impacts of both this system as well as the Five Corners system as the pipes are immediately adjacent to each other. Table 4: State Road-Edgartown Road Stormwater System System Street Width of Street and Length of street in Length of street Sidewalk(s) collection system contributing to collection system Edgartown-VH Road (1/2) Edgartown-VH Road (1/2) Cook Road State Road (1/2) State Road (1/2) State Road Camp Street William Look (1/2) Look TOTAL LENGTH (feet) TOTAL AREA (square feet) 42 1100 42 240 19 32 32 32 17 24 27 27 180 650 1950 450 1275 45800 325 1510 440 400 3250 96815 CPR Final Report 6 The outlet area has very low elevation that does not allow installation of infiltration systems. Any effort to reduce the volume and impact from this system should focus on the upper portions of the collection system. Five Corners Discharge at Beach Street Extension: This discharge is a direct outfall into Tisbury Harbor. Runoff from the beginning of Main Street, Beach Street, part of Beach Road and, under the right conditions, part of Water Street enters the basins at the intersection of Beach Street, Water Street and Beach Road known as Five Corners. There is an 18-inch concrete pipe that carries the runoff collected by the catch basins on the north side of this major intersection. There is also a 24-inch diameter pipe that serves the catch basins on the south side of the Five Corners intersection as well as the drains on Beach Road that flow into the intersection. Finally, there is a 12-inch diameter backup pipe. Water Street has two level 12 inch pipes that normally outfall with the Main Street system. However, with sufficient runoff, the system will back up to contribute to the Five Corners system. As these pipes are adjacent to the discharge from the State Road discharge, sample TIS2 was a mixture of these runoff sources. Table 5: Five Corners Stormwater System System Street Width of Street and Sidewalk(s) Beach Street Beach Road Beach Road Main Street TOTAL LENGTH (feet) TOTAL AREA (square feet) 41 42 42 49 Length of street in Length of street collection system contributing to collection system 650 470 470 19740 215 240 1105 47440 Skiff Avenue Discharge: Stormwater from Skiff Avenue and side streets and a portion of Causeway Road flows down into a limestone contactor/detention basin and then outlets across 30 to 40 feet of heavy Phragmites reeds into Mud Creek. The entry point of the contactor bed was mapped with GPS and can be found in Figure 1. The watershed is moderate density residential. Analyses from samples collected after the detention basin are reported in Table 21 as TIS4 and 5. Table 6: Skiff Avenue Stormwater System System Street Width of Street and Length of street in Length of street Sidewalk(s) collection system contributing to collection system Skiff Avenue Skiff Avenue Causeway Road Causeway Road Renear Street Mt. Aldworth Hinckley Circle Davis TOTAL LENGTH (feet) TOTAL AREA (square feet) 34 34 22 22 21 20 19 25 1250 430 450 1700 52400 520 340 200 195 320 2005 48905 CPR Final Report 7 Beach Road Discharge to Lagoon Pond: Along Beach Road there is one system that discharges into the Harbor and a second that discharges into the West Arm of the Lagoon. Both systems are discharges from a State roadway. Available plans for the entire road are not clear and as-built plans could not be obtained. This discharge is a direct outflow into Lagoon Pond. The runoff generated by the intervening stretch of Beach Road between these two systems flows into one or the other but the slope is so gentle it is uncertain. The system draining into the Lagoon discharges between the Piers belonging to Ralph Packer and MV Shipyard. The watershed is commercial and industrial at moderate density. Table 7: Beach Road System Discharging into the Lagoon System Street Width of Street and Length of street in Length of street Sidewalk(s) collection system contributing to collection system Beach Road Beach Road Beach Road TOTAL LENGTH (feet) TOTAL AREA (square feet) 42 42 650 650 27300 700 700 29400 Beach Road Discharge into Tisbury Harbor: This discharge is a direct outfall into Tisbury Harbor from a State roadway. The system draining into the Harbor discharges behind the Mobil Station across from Tisbury Marketplace. The watershed is moderate density commercial/industrial. Analyses of runoff from this watershed are reported in Table 21 as TIS3. System Table 8: Beach Road System Discharging into the Harbor Length of street Street Width of Street and Length of street in contributing to Sidewalk(s) collection system collection system Beach Beach Road Road 42 Beach Road 42 TOTAL LENGTH (feet) TOTAL AREA (square feet) 210 210 500 500 8820 21000 In addition, there are numerous discharges along the length of Beach Road proceeding out of Town to the drawbridge. The rectangular drains along the base of the seawall all appear to discharge directly into the outer Harbor and are mapped as outfalls in Figure 1. Several basins on the bridge discharge directly into the Lagoon or into the channel on the Lagoon side of the bridge with no sediment retention capacity. Two sets of catch basins discharge into the Lagoon by two 12-inch pipes as shown in Figure 1. Grove Street Discharge to Outer Tisbury Harbor: This discharge carries runoff from four residential streets across a limited stretch of beach into the water. During the course of study, we identified the Grove Street runoff discharge as being readily corrected and having adequate elevation to allow the installation of a first-flush leaching CPR Final Report 8 system above groundwater. The drainage area currently includes Grove Street and a portion of Upper Main Street as well as Oak and Pine Streets. Runoff from Oak and Pine Streets plus a portion of Upper Main flows into 5 catch basins (two on Oak Tree and three on Pine Tree Lane with no leaching capacity) and then to a single, inadequate infiltration basin on Harbor View Lane. Currently under moderate to heavy rainfall, the leaching system is overloaded, backs up onto Harbor View Lane and runs down to add to the Grove Street runoff. Volume is sufficient to cut a 12 to 18 inch gully across the beach to the high tide line where recent wave activity had filled it. The contributing areas total over 73000 square feet. The outflow affects Vineyard Haven outer Harbor. System Table 9: Grove Street Discharging into the Outer Harbor Street Width of Street and Length of street in Length of street Sidewalk(s) collection system contributing to collection system Grove Street Oak Street Pine Street Harbor View Upper Main Street TOTAL LENGTH (feet) TOTAL AREA (square feet) 19 22 20 20 29 800 640 600 680 640 3360 73440 CPR Final Report 9 Stormwater Collection System- Town of Oak Bluffs Systems Not Mapped: The South Circuit Avenue system that formerly discharged into Farm Pond has been corrected by installation of an infiltration system in Viera Park. The volume of water has been greatly reduced (after a 1.5 inch rainfall, only a trickle of flow was produced-see Appendix A for a report). In addition, three streets that either discharged into Lagoon Pond by a pipe or by direct surface flow across a short stretch of beach are in process of being corrected with funding from the Section 319 program. These streets include: Vineyard Avenue Extension, Lagoon Road and Hudson Avenue. Mapping: Stormwater systems in the Town of Oak Bluffs that were mapped are shown in Figures 3 and 4 and include the following: 1. Temahigan-Eastville-Beach Road system discharging into the waters of Vineyard Sound (Figure 3- East Chop/Beach Road) 2. New York Avenue West discharging into the waters of Vineyard Sound (Figure 3- East Chop/New York Ave.) 3. New York Avenue East discharging into Oak Bluffs Harbor (Fig.3 Harbor/NY Ave/) 4. Circuit Avenue North-Kennebec discharging to Oak Bluffs Harbor (Fig.3Harbor/Circuit 1) 5. Circuit Avenue South- Kennebec discharging to Oak Bluffs Harbor (Fig.3 Harbor/Circuit 2) 6. Sea View Avenue Extension discharging into Nantucket Sound at the Steamship Authority pier. 7. Sea View Avenue at Ocean Park discharging into Nantucket Sound. 8. Sea View Avenue-Pequot Avenue discharging across jetty beach into Nantucket Sound. (Figure 3- Jetty Beach/Sea View Ave.) 9. Sea View Avenue-Tuckernuck Avenue discharging across Inkwell Beach into Nantucket Sound. 10. Vineyard Avenue West-County Avenue that discharges into wetlands associated with Brush Pond (Figure 3- County Road/Brush Pond). 11. Vineyard Avenue East that discharges into the wetlands south of Sunset Lake. (Figure 3- Vineyard Ave. East). In addition, there are five discharges into Nantucket Sound at regular intervals along the sea wall on Sea View Avenue near Farm Pond. There are two discharges into Lagoon Pond on the approach to the drawbridge on Beach Road. There are two pairs of grates on the Bridge itself with no settling basin. In the North Bluff area, there are a number of catch basins along Circuit Avenue Extension that we believe discharge to the Harbor. There are two catch basins on East Chop Drive towards the north corner of the Harbor that we are reasonably sure discharge through the retaining wall along the Harbor but no pipe was found. There are a number of distributed leaching basins in the area south and southwest of Ocean Park. These are shown as mapped with a triangle symbol in Figure 3. We are reasonably secure in saying that they are leaching basins and not tied into either the Circuit Avenue stormwater system to the west or the systems along Sea View Avenue to the east discharging to Nantucket Sound. CPR Final Report 10 We believe that the line carrying the storm water from the south end of Circuit Avenue out to the Harbor runs as shown in Figure 3 down an alley next to Pomodoro Restaurant and up Fisk Avenue but its exact path is not known. While the exact path is not known, it discharges at Circuit 2 in the Harbor (see Figure 3). The soil type is not mapped in the urban areas but nearby in all directions it is Carver loamy coarse sand that is a drouthy soil with significant capacity to infiltrate runoff. Slopes vary widely from 3 to 8 percent but steepening to 15 percent in some basins. The intensity of development in systems 4 through 9 above is sufficient to generate substantial runoff from roof and driveway surfaces to add to the flow. Temahigan Stormwater System: This system drains into a direct outfall into outer Tisbury Harbor. The system is a Mass Highways collection system. The contributing basin area beyond the road itself is a moderate to low-density residential area. During the mapping, the 12 inch steel outlet pipe was filled with beach sand. In Figure 3 it is labeled East Chop-Beach Road. System Table 10: Temahigan -Eastville-Beach Road Stormwater System Street Width of Street and Length of street in Length of street Sidewalk(s) collection system contributing to collection system Temahigan Temahigan Lyme Elliot Eastville Eastville Beach Road Hospital Drive TOTAL LENGTH (feet) TOTAL AREA (square feet) 28 28 18 18 26 26 29 22 880 95 120 70 475 140 950 2305 36990 530 425 21160 New York Avenue-West Stormwater System: This system is a Mass Highways stormwater system that outfalls through a 20-inch steel pipe directly into the coastal waters off East Chop. The drainage area consists of moderate density residential. East Chop Drive drops sharply to an elevation of less than 10 feet before it flattens out to the beach where the discharge occurs. An infiltration project to reduce the amount of the direct discharge would be best placed on the higher ground near to the junction of East Chop and New York Avenue. This discharge was sampled and is reported in Table 21 as OB3). In Figure 3, it is labeled East Chop-New York Avenue. CPR Final Report System 11 Table 11: New York Avenue-West Stormwater System Street Width of Street and Length of street in Length of street Sidewalk(s) collection system contributing to collection system New York Avenue East Chop Drive Winemack Nahomon Pontiac Cannahoot Munroe TOTAL LENGTH (feet) TOTAL AREA (square feet) 27 26 20 20 20 20 25 2700 330 3030 81480 120 240 330 430 240 1360 28400 New York Avenue-East: New York Avenue slopes strongly downhill toward Oak Bluffs Harbor. Several small roads drain moderate to high-density residential neighborhoods to discharge on New York Avenue as surface flow. This system is a Mass Highway system that drains into the southwest corner of Oak Bluffs Harbor by a 16-inch pipe and is labeled Harbor-New York Avenue in Figure 3. The contributing watershed is moderate density residential on average. The end of the road nearest to the Harbor is low lying limiting any attempt to reduce direct discharge through infiltration at the downhill end. A preliminary proposal prepared by the Natural Resource Conservation Service to divert this runoff into Lakeside Park (Town owned) to the west of Sunset Lake seems to hold promise for a significant reduction in the discharge. This site was sampled for both wet and dry weather runoff analyses and the data is shown in Table 21 as OB1. Table 12: New York Avenue-East Stormwater System System Street Width of Street and Length of street in Length of street Sidewalk(s) collection system contributing to collection system New York Avenue New York Avenue Maple Laurel Cedar Pacific-Spruce Hampson Chestnut complex TOTAL LENGTH (feet) TOTAL AREA (square feet) 30 30 19 19 19 20 19 20 740 740 22200 998 240 570 320 780 665 830 4403 97805 Circuit Avenue North: This system drains a high-density commercial and a small area of high-density residential land use. The discharge enters Oak Bluffs Harbor at the southeast corner from a 16-inch pipe labeled Circuit 1 in Figure 3. Circuit Avenue, Kennebec, Lake and Oak Bluffs Avenue all drain toward the Harbor for at least a portion of their length both within this system and as surface flow along the roadways. Lake and Oak Bluffs Avenue are wide roads with diagonal parking. Several moderate CPR Final Report 12 size public and private paved parking areas on Kennebec contribute to the volume of runoff. The runoff discharge was sampled for both wet and dry weather analyses and the data is shown in Table 21 as OB5. It may be possible to reduce the total volume of runoff by infiltrating separate components on Lake near Ocean Park, Oak Bluffs Avenue beneath the right of way near the old town hall and Ocean Avenue in the right of way or in Ocean Park itself. Once the roads meet near the foot of Circuit Avenue there may be insufficient elevation to address the problem. System Table 13: Circuit Avenue-North and Kennebec Stormwater System Street Width of Street and Length of street in Length of street Sidewalk(s) collection system contributing to collection system Circuit Avenue Circuit Avenue Kennebec Kennebec Oak Bluffs Avenue Oak Bluffs Avenue Lake Avenue Lake Avenue New York Avenue Ocean Avenue Circuit Avenue Ext. TOTAL LENGTH (feet) TOTAL AREA (square feet) 46 46 30 30 81 81 60 40 59 51 40 400 120 425 160 100 475 170 1095 49450 380 120 170 140 1445 85345 Circuit Avenue-South Stormwater System: Circuit Avenue also slopes to the south from the crest of the road near the Post Office park. The system collects runoff from a high-density commercial area as well as high-density residential areas both to the east and to the west of the road. The collected stormwater is carried by a pipe of unknown size down an alley near the present location of the Pomodoro restaurant through the Camp Grounds and out onto New York Avenue across from the Wesley House where it discharges through a 12-inch pipe into the southern end of Oak Bluffs Harbor at the outlet labeled Circuit 2 on Figure 3. Hiawatha Park and Niantic Park might provide infiltration capability for a small portion of the runoff. Additional reduction in discharge volume by infiltration could be gained only through an easement from the private property through which the pipe passes between Circuit Avenue and the Harbor. This location was sampled for both dry and wet weather sample analyses and the results are shown in Table 21 as OB4. CPR Final Report System 13 Table 14: Circuit Avenue-South Stormwater System Street Width of Street and Length of street in Length of street Sidewalk(s) collection system contributing to collection system Circuit Avenue Circuit Avenue Kennebec Kennebec Hiawatha Uncas Bradley Penacook Pequot-Massasoit Narragansett Bayliss TOTAL LENGTH (feet) TOTAL AREA (square feet) 35 20 28 26 16 20 11 18 19 31 16 1000 550 120 1120 38360 330 330 450 640 520 475 170 200 3665 60715 Sea View Avenue-Jetty Beach Stormwater System: The high-density residential area south of Ocean Park slopes toward the east along Samoset, Narragansett and Pequot Avenues where it enters Sea View Avenue and flows into two sets of storm drains. These drains also collect a large amount of runoff from Sea View Avenue itself and discharge through a 12-inch concrete pipe onto the beach known as Jetty Beach (Figure 3 Jetty Beach-Sea View Avenue). This discharge is substantial enough to create a gully that extends across a considerable portion of the beach. The eventual discharge into Nantucket Sound poses little water quality threat due to the dilution available. However, this discharge does pose some threat to the health of beach goers during and shortly after a runoff event. Fecal coliform levels were high in the runoff here. It may be possible to divert this runoff to Waban Park (Town owned) for infiltration if there is adequate elevation. This discharge was sampled for wet weather runoff analyses and is shown as sample OB6 in Table 21. Table 15: Sea View Avenue-Jetty Beach Stormwater System System Street Width of Street and Length of street in Length of street Sidewalk(s) collection system contributing to collection system Sea View Avenue Sea View Avenue Ocean Avenue Samoset Narragansett Pequot TOTAL LENGTH (feet) TOTAL AREA (square feet) 48 48 40 18 24 20 300 240 190 285 350 300 300 14400 1365 38650 Sea View Avenue at Waban Park Stormwater System: The middle of Waban Park is a low area that extends toward the south and drains toward Farm Pond after passing CPR Final Report 14 through a wetland area. Sea View Avenue also reaches a low point at the east edge of the park where Tuckernuck and Sea View intersect. The surface runoff from the highdensity residential area to the north of Waban Park runs down toward the Park and a portion is carried into this stormwater system. Runoff from Sea View Avenue both from the north and south also flows to this low point where it is carried through the sea wall in a 12-inch concrete pipe to discharge across the beach known as the Inkwell Beach. It may be possible to combine the runoff from this segment with that from the previous segment to infiltrate the first flush into Waban Park. Table 16: Sea View Avenue at Waban Park Stormwater System System Street Width of Street and Length of street in Length of street Sidewalk(s) collection system contributing to collection system Sea View Avenue Sea View Avenue Penacook Tuckernuck Waban Pequot TOTAL LENGTH (feet) TOTAL AREA (square feet) 48 48 18 20 18 18 120 120 5760 570 400 400 240 120 1730 49040 Sea View Avenue Steamship Authority Stormwater System: The discharge location at the Steamship Authority could not be found but is believed to be beneath the pier. Runoff draining into two catch basins at the intersection of Sea View Avenue and Oak Bluffs Avenue is carried across Sea View to a catch basin in front of the SSA Office and into the discharge system. The outlet pipe is on the armored shore protection where it flows down to and enters Nantucket Sound. The impact of this discharge on water quality should be minimal due to the small drainage area and the large dilution available. Table 17: Sea View Avenue Steamship Authority Stormwater System System Street Width of Street & Length of street in Length of street Sidewalk(s) collection system contributing to collection system Sea View Avenue Sea View Avenue Ext Oak Bluffs Avenue TOTAL LENGTH (feet) TOTAL AREA (square feet) 48 51 80 240 240 11520 240 120 360 21840 Sea View Avenue at Ocean Park Stormwater System: The swale in Sea View Avenue at about the midpoint of Ocean Park contains two drains that are connected and discharge from a 12-inch steel pipe onto the rock armament on the shore where the runoff enters Nantucket Sound. As in the case of the previous system and for the same reasons, the impact of this discharge on water quality is probably minimal. CPR Final Report System 15 Table 18: Sea View Avenue at Ocean Park Stormwater System Street Width of Street and Length of street in Length of street Sidewalk(s) collection system contributing to collection system Sea View Avenue TOTAL LENGTH (feet) TOTAL AREA (square feet) 59 0 740 740 43660 Vineyard Avenue-County Road Stormwater System: The stormwater from Vineyard Avenue west of the crest in the hill near the Catholic Cemetery runs down to the County Road system that carries the stormwater toward the intersection with Eastville Avenue. Runoff from Eastville Avenue in both directions from the County Avenue intersection flows down to two catch basins at this intersection and also enters the system. Several roadside runoff chutes along the north side of Eastville Avenue will somewhat reduce the flow from this road. The intersection area is low and may not have sufficient elevation to correct this discharge by infiltration. The exact location of the discharge(s) is not known but we believe the outfall is in the wetlands at the head of Brush Pond very near County Road as shown in Figure 3 and labeled County Road-Brush Pond. A mound-shaped feature that extends out from the roadside some 30 feet into the wetland marks the probable discharge location. Around the end of this feature a substantial amount of silt and fine sand was noted indicating the likelihood of a substantial discharge here. A drainage trench in the marsh approaches close to the discharge area such that treatment within the wetland itself may be limited. At one location on the mound a 12-inch diameter hole opened down into standing water implying it may be a large corrugated pipe or concrete structure in decay. Table 19: Vineyard Avenue-County Road Stormwater System System Street Width of Street and Length of street in Length of street Sidewalk(s) collection system contributing to collection system Vineyard Avenue Vineyard Avenue Dreamers Way County Road County Road Eastville Ave. James Place (dirt) Leslie’s Lane Stanley Street Robert’s Way Prospect Avenue (dirt) Buena Vista Street (dirt) TOTAL LENGTH (feet) TOTAL AREA (square feet) 24 24 20 32 32 21 950 140 100 2375 16 16 16 2490 98800 240 1660 475 550 190 520 330 330 3015 68060 Vineyard Avenue East Stormwater System: The Vineyard Avenue East system collects runoff from a number of residential streets that drain down to it. Land use CPR Final Report 16 density is moderate to high. The collected runoff is carried down to discharge in the wetland (on Assessor’s Map 11 Lot 351) that is south of and drains into Sunset Lake. The exact location of the discharge could not be determined and the discharge shown in Figure 3 should be considered approximate. Travel through the large wetland (as much as 8 acres) will probably remove solids and provide some opportunity for significant uptake of nitrogen and phosphorus. Table 20: Vineyard Avenue East Stormwater System System Street Width of Street Length of street in and Sidewalk(s) collection system Vineyard Avenue Vineyard Avenue Winthrop Shawmut Franklin Avenue Potato Farm Norris Marvin (dirt)* Pierce (dirt)* Pacific Perkins 28 28 18 26 20 18 20 12 13 20 19 TOTAL LENGTH (feet) TOTAL AREA (square feet) Length of street contributing to collection system 1450 1450 40600 590 470 780 140 170 140 70 120 120 190 2600 50598 *Dirt roads not included in area calculation Other Probable Discharges into Oak Bluffs Harbor (eastern shore): In addition to the sites listed, surface runoff flows down Pasque and Saco to Circuit Avenue Extension and a large paved parking, passenger staging and auto rental area. This flow discharges through catch basins and a number of discharge pipes through the sheet piling that forms the eastern shore of the Harbor. The probable discharge points mapped with GPS in Figure 3 from south to north along the eastern shore are as follows: At Nancy’s Snack Bar (map 8 lot 284.1) 16-inch diameter Under the pier near Nancy’s (map 8 lot 284.1) 16-inch diameter (reportedly closed) Through bulkhead (map 8 lot 285) 16-inch diameter Under the McCarthy pier (map 8 lot 296.1) 16-inch diameter We believe that the discharge pipe at the McCarthy pier collects runoff from the three catch basins on Circuit Avenue Extension that are at the foot of North Bluff Avenue and possibly the two catch basins at the foot of Saco Avenue. However, it appears more likely that the Saco runoff flows into those catch basins and out the outlet pipe through the bulkhead on map 8 lot 285. In addition, there are three outlets through the cap on the bulkhead to the north near the Island Queen dock area. These provide an exit for the runoff that comes down Sea View Avenue Extension and from the large paved parking area for pick-up/drop-off of commercial ferry passengers. CPR Final Report 17 Stormwater System Runoff Sampling and analyses: Data collected during the course of this study are reported in Table 21. Five runoff discharge sites in each Town were identified for water testing based on the estimated size of the contributory area and the nature of the water body that received the discharge. The purpose of the sampling was to characterize the water quality impact associated with these stormwater discharges, to draw insights about other discharges not sampled and as an input to prioritize systems for correction. Samples were collected during dry weather near where the system discharged directly into a water body to establish background levels of the parameters to be measured. Samples were also collected during rainfall events where sufficient precipitation had fallen to generate runoff. Samples were collected and handled according to the Sampling and Analysis Plan prepared and approved by DEP for a 604(b) funded water quality study carried out in 9 coastal salt ponds during July and August 2003. The Coastal Systems Group of the School for Marine Science and Technology at University of Massachusetts in New Bedford (SMAST) performed all analyses reported. The Dukes County Laboratory performed fecal coliform bacterial analyses. When collected by hand, stormwater samples were collected by plunging a 1-liter HDPE bottle in to a depth of approximately 6 inches below the surface. Where samples could not be collected by hand a dipstick with a rubber stopper was used to get the bottle below the surface at the sample site before pulling the stopper and filling the bottle. The initial water collected was shaken vigorously and dumped to flush the bottle and then the actual sample was collected. Samples were processed either immediately after collection or upon return to the office but in no case more than 1 hour after collection. Samples were filtered through a 0.22micron cellulose-acetate filter into a lab-clean, 60-milliliter, labeled bottle for dissolved nutrient analyses including nitrate, nitrite, ammonium, orthophosphate and dissolved organic nitrogen. Unfiltered samples were poured into similar lab-cleaned, 60 ml bottles for total phosphorus analyses. Known volumes of sample were run through glass fiber filters for particulate carbon and particulate nitrogen analyses. Samples were kept on ice during processing and while shipped via Steamship Authority or by Cape Air to be picked up by lab personnel. Approximately 0.5 liter of the sample was returned to the SMAST lab where known volumes of the samples were filtered onto pre-weighed glass fiber filters for total suspended solids analyses. In the field, data was collected with a calibrated YSI85 meter to gather information on temperature, specific conductivity and dissolved oxygen. The first, dry-weather sample round was collected on 8 May at 5 stations in Tisbury and 5 in Oak Bluffs. These samples were sent to the Wampanoag Tribe laboratory as we hoped they could run the required analyses. Those analyses we knew that lab could not run (TSS, total phosphorus and particulates) were sent to the SMAST lab. Unfortunately, there were unforeseen interferences with the dissolved nutrient analyses run by the local lab so that the data was not reliable. The wind during sample collection CPR Final Report 18 was blowing 20 to 25 mph out of the north causing 1.5 to 2 foot waves at sites TIS1, TIS2 and TIS 3. Following the dry-weather date, we entered a prolonged time period where precipitation did not occur during the early part of the workweek to allow collection and lab analyses. The next date sampled was a wet-weather event in early August when samples were collected only in Tisbury because the event was a short-duration, heavy rainfall and we did not have sufficient personnel available to collect samples simultaneously in Oak Bluffs and Tisbury. Over 0.5 inches fell before sample collection and the rain event had ceased by the time the Tisbury samples were collected. These samples were sent to the SMAST lab for analyses. The third sample event was a dry-weather sampling that occurred on October 14. These samples were collected from 5 identified sites in Oak Bluffs. The last sample round was a wet-weather sample round on 27 October for 6 sites in Oak Bluffs. These samples were also sent to the SMAST lab for analyses. This precipitation event delivered steady rainfall for a period of hours. We estimate that over 0.5 inches had fallen by the time the samples were collected between 3 and 4 p.m. A total of 0.69 inches had fallen in West Tisbury by 4:30 p.m. Tisbury Stormwater Site Sample Results: During the early May sampling round, the following stations were sampled: TIS1 Owen Little Way discharge location TIS2 Beach Street Extension discharge location in the Harbor TIS3 Beach Road discharge location into Harbor TIS4 Beach Road discharge location into Lagoon Pond TIS5 Skiff Ave. discharge location at Mud Creek During sample collection we noted that the surf stirred up by steady winds had suspended a considerable amount of bottom sediment and debris that caused a notable cloudiness and a swirl of visible particles in the water. We believe that the Total Suspended Solids (TSS) results on 8 May are higher at these stations than during the wet weather events on 5 August due to resuspension of bottom materials. Dissolved oxygen values ranged from 92 to 100 percent saturation. Specific conductivity values varied from a high of 44 milli-Siemens (mS) at TIS 1 and TIS3 to a low of 27.6 mS at TIS 5. The tide during collection was early in the flood stage. Samples collected during the 5 August runoff event include the following locations: TIS1, TIS2, TIS3 and TIS 5 as above. TIS4 Skiff Ave discharge after passing limestone contactors but before Mud Creek. During the runoff event on 5 August, the TSS values are comparatively low at all sites except for the Beach Road (Harbor TIS3) discharge where field notes indicate that the pipe discharge was discolored. At stations TIS1, TIS2 and TIS3 discharge volume was CPR Final Report 19 sufficient to cause a rolling motion in the receiving water. Discoloration was also noted at TIS1 but the TSS values are low. Dissolved oxygen saturation ranged from a low of 55% at TIS4 to a high over 100% at TIS1 and TIS5. Specific conductivity values were much the same at TIS1 as they were during the dry-weather round. However, at TIS2, TIS 3 and TIS5 the water was significantly fresher. The discharge at TIS2 varied from 1 to 4 milli-Siemens. At TIS4, the runoff was essentially fresh with a specific conductivity value of 72 micro-Siemens. The tide during collection was mid-flood stage. There were marked increases in Total Dissolved Nitrogen concentrations at TIS1, TIS4 and TIS5 during the rainfall event comprised mainly of dissolved organic nitrogen and, in the case of the latter two, also nitrate and nitrite. Total Phosphorus concentrations also increased dramatically at all sites from less than 1 micro-mole (uM) during the dryweather sample to 3 or more uM during the wet-weather sample round. Particulate nitrogen and carbon values were elevated reflecting the discharge of fine suspended organic matter with the runoff. The Beach Road discharge into the Harbor had the highest values for both of these parameters. Oak Bluffs Stormwater Site Sample Results: A round of dry-weather samples were collected on 14 October as follows: OB1 New York Ave. East discharge location into Harbor OB2 Harbor boat ramp OB3 New York Ave. west discharge location at East Chop OB4 Circuit Ave. South discharge location into Harbor OB5 Circuit Ave. North discharge location into Harbor The tide during collection was high. During this round, TSS values were higher when compared to the concentrations found in May. Total phosphorus values were similar to May but generally somewhat lower. During the wet weather event on 27 October, the discharge at the Jetty Bathing Beach was added as OB6. All other stations are the same (same numbers) as the dry-weather round listed above. TSS values increased by a factor of 2 to 4 times at all stations except the discharge at the boat ramp. This probably reflects the relatively small volume of runoff generated at this location. At OB1 and OB5, TSS values were 150 and 104 milligrams per liter respectively. The tide during the collection was midway to low tide. Total phosphorus concentrations were also increased dramatically at all sites except OB2 by a factor 4 to 10 times the dry-weather results. Total dissolved nitrogen values essentially doubled. Particulate carbon concentration increased tremendously by as much as 40 times at OB1 and OB5 reflecting the discharge of fine organic matter and silt. Particulate nitrogen increased 8 to 12 times at stations OB1, 4 and 5 and by nearly18 times at OB3. OB2, the boat ramp was elevated by only a factor of about 2. CPR Final Report 20 Lab Accuracy: Sample OB7 collected on 27 October is a blind duplicate sample to test the laboratory’s accuracy. This sample is drawn from the same bottle and handled and processed in the same manner but labeled with a different, sequential number. The Total phosphorus was a duplicate of station OB 4 and the results of 5.7 (OB4) and 5.5 (OB7) agree very closely. The dissolved nutrient results were a duplicate of sample site OB3 and show agreement to within less than about 10 percent. Some Interpretations of the Data: By knowing the approximate area of the contributory watershed of each discharge, an approximation of the nutrient loading from a 0.5-inch rainfall can be calculated from the nutrient concentrations measured in the rain event. Except for TIS4, the samples were all collected from the receiving water. Specific conductivity values measured during the Tisbury rain event of 5 August indicate that the TIS2 sample was nearly fresh, implying it is near full-strength runoff. Conductivity values from TIS 1, TIS 3 and TIS5 imply approximately 1/3 to ½ dilution with coastal water. In these samples, this means that the concentration of the nutrients reported is significantly less than the actual stormwater concentration due to mixing with the coastal water. Although field equipment was not used during the 27 October rain event in Oak Bluffs, dilution to at least the same extent can be expected for all samples. In Table 22, the estimated content of fine sediment (Total Suspended Solids or TSS), total dissolved nitrogen (TDN), particulate nitrogen and total phosphorus (Tot. P) are calculated based on their concentration as measured by the lab and the volume of runoff from a ½ inch rainfall discharge. This data represents a glimpse of the quality of the runoff or the mix of runoff and receiving water at one time. We expect but we do not know that the concentration of all these parameters will decrease substantially over time during a larger rainfall or later in the runoff cycle of a moderate rainfall. The values may have been higher if we had sampled earlier in the runoff period. The data indicate a significant amount of Total Suspended Solids are discharged amounting to over 10 pounds per ½ inch volume at all sites except at TIS4 where the limestone contactor apparently slows outflow and allows settling to occur. The discharge in the Harbor from New York Avenue carried a substantial volume of sediment amounting to over 40 pounds per ½ inch volume. The Circuit Avenue north discharge (OB5) also carries a substantial amount of sediment. The total discharge to Oak Bluffs Harbor from the three main collection systems is in excess of 90 pounds per ½ inch volume of runoff. Filters used to create dissolved nutrient samples from the rainfall runoff samples were turned a sooty color at all stations except TIS4 and 5 and OB2. Four filters are photocopied along with an unused filter in the Appendix from stations in Oak Bluffs Harbor and the East Chop discharge from New York Avenue. The discoloration resulted from filtering 100 milli-liters of sample water (less than ½ cup) and indicates the amount of fine matter that is discharged. CPR Final Report 21 In Tisbury, Total Dissolved Nitrogen loading exceeds 0.1 kilograms per ½ inch rainfall volume at most stations. The exception is TIS3 at the Beach Road outfall into the Harbor. In Oak Bluffs, all four stations shown exceed 0.1 kilogram per ½ inch rainfall volume. The discharge of 0.1 kilogram is enough to raise the nitrogen concentration to unacceptable levels in 200 thousand liters of receiving water. (Generally poor water quality results from nitrogen concentrations exceeding 0.5 milligrams per liter.) Total phosphorus includes both dissolved organic and inorganic forms but also the content of particulate matter. All runoff samples contained less than 0.1 kilogram Sources of nitrogen include fertilizer applied to lawns and landscaping that is mobilized by the runoff. Accumulation of street debris is also a source of nitrogen as is the acid rainfall itself. It is also possible that there is a cross-connection with a septic system or where the line is in or near the groundwater by infiltration at pipe connections or damaged sections. Sources of phosphorus include fertilizers and acid rain but are primarily derived from street debris accumulation. Fecal Coliform Bacteria: Runoff also carries with it the droppings of birds, other wild animals and pets that accumulate on the streets. These cause the amount of fecal coliform bacteria to increase. Fecal coliform concentration in shellfishing waters can be cause for closure of the bed. On October 2, five fecal coliform samples were collected and the lab report is included in the Appendix. The sample locations were all in Oak Bluffs Harbor and include the outlets for the boat ramp, New York Ave. discharge into the Harbor (“Our Market)’, Circuit Avenue north (Nancy’s) and south (slip #35) and at Jetty Beach. Coliform concentrations were too high to count at the Jetty Beach outlet and at the Circuit Avenue North outlet. The New York Avenue and Circuit Avenue South discharges were measurable but still very high. CPR Final Report 24 Conclusions and Recommendations: The stormwater discharges identified during this project are substantial sources of sediment, fecal coliform bacteria and, to a somewhat lesser extent when compared to other sources, nitrogen and phosphorus. All the discharges mapped represent large volumes of runoff with the possible exception of the discharges from Beach Road into the Harbor and the Lagoon in Tisbury and some of the discharges in Oak Bluffs from Sea View Avenue into Nantucket Sound. Photographs of selected oulets are attached in the Appendix to this report. Both Towns: Mass Highways should examine the potential for reducing the discharge volume from all the State roadways identified here that discharge directly into coastal waters. Non-structural, relatively less expensive steps that can be taken to reduce the discharge of particulate matter and phosphorus include more frequent street cleaning and catch basin sediment removal. The installation of first flush basins either within the road right of way or, where available, adjacent Town-owned land will decrease the volume of runoff particularly the most contaminated first flush that occurs with the first ½ inch of rainfall. Town-owned land is shown in Figures 1 and 3. These maps should be incorporated in any oil spill contingency planning to identify those areas where spillage of hydrocarbon products on the streets could lead to direct contamination of surface water resources. Oak Bluffs: The Vineyard Avenue-County Road system in Oak Bluffs is a good candidate for flow reduction by infiltration further up in the watershed. The New York Avenue discharge into the Harbor could be diverted to infiltrate a first flush in Lakeside Park. An evaluation confirming this has been done. Drainage from the high-density residential area along Sea View Avenue near Jetty Beach will have a preliminary engineering design to evaluate the potential for infiltrating the first flush into Waban Park. A portion of the flow from Oak Bluffs Avenue and Lake Avenue that contributes to the discharge from the Circuit Avenue North system may also be infiltrated either beneath the road layout or in Ocean Park. The exact location of the Vineyard Avenue East discharge should be identified to assure that there is adequate wetland treatment of this source before it enters Sunset Lake. If the discharge is into surface waters that will offer little treatment, this site may offer an opportunity for a created artificial wetland or sediment settling detention system to pretreat the discharge. CPR Final Report 25 The location of the Vineyard Avenue-County Road discharge into the wetlands around Brush Pond should be confirmed by observation during a runoff event to assure that the discharge flows through enough wetland to reduce sediment and nutrient loads. If not, this site may offer an opportunity for a created wetland or sediment settling system to improve water quality. Stormwater pipe sizes in the Town are largely unknown. Obtaining pipe size information from old records or from former Highway Department personnel should be a priority activity. Tisbury: In Tisbury, we identified the Grove Street runoff problem as one that could be largely corrected by infiltration through a system of first flush basins beneath the road layout. This will be the focus of a preliminary engineering design. In addition, the DPW is already planning to reduce the flow to the Main Street system from the grammar school parking lot by installing a first flush basin along Spring Street. It is recommended that Mass Highways look into reducing the stormwater flow from the State Road segment. This may be possible through placement of first flush basins in the road layout. The Causeway Road discharge may have some negative impact on the wetlands at the head of Mud Creek. An evaluation of this potential was beyond the scope of this study and is not clear at this time. If found to be the case, placement of a limestone contactor/detention bed as is used with the Skiff Avenue discharge may improve water quality and reduce the amount of sediment discharge. The flow here is considerably greater than at Skiff Avenue and some means of settling the sediment before entry into the limestone contactors may be necessary. Placement of first flush systems along the Franklin-William Streets area could offer substantial reduction in flow to the Main Street system. Reduction of flow on William Street will reduce the quantity of runoff going down Camp Street and entering the Beach Street Extension discharge. In general, it is recommended that potential discharge reduction by infiltration be evaluated for inland segments of both the Main Street and Beach Street Extension systems. Mass Highways should examine the Beach Road discharge into Lagoon Pond for alternatives to reduce release of fecal coliform bacteria due to the value of the West Arm of the Lagoon as a shellfish resource and the limited tidal circulation available. CPR Final Report 26 Prioritizing systems for preliminary engineering design: Stormwater discharges that could potentially affect human health are a top priority for correction. These discharges include those that outfall to recreational waters used for swimming and into shellfish producing waters. All samples collected contained excessive numbers of fecal coliform bacteria that can cause health problems and lead to closure of shellfish beds (see page 21 for discussion). Outflows into coastal waters used for swimming in Oak Bluffs include Jetty Beach, Inkwell Beach, New York Avenue (East Chop), Beach Road and, to a lesser extent, the other discharges along Sea View Avenue. In Tisbury, these discharges are Main Street, Owen Little Way, Grove Street and along Beach Road. Discharges into shellfish producing waters include all discharges into Oak Bluffs Harbor and the Vineyard Avenue West discharge into Brush Pond that is tidally connected to Lagoon Pond. In Tisbury, these discharges include the Beach Road discharge into the West Arm of the Lagoon and, indirectly, the discharge from Skiff Avenue into Mud Creek that is tidally connected to the West Arm. Once systems that may impact human health were identified, the next level of evaluation we conducted rested on water quality impacts and feasibility. While not all discharges were analyzed, among those tested, some stand out for higher levels of contaminants (see Table 22): For sediment loading: Beach Road discharge to Tisbury Harbor New York Avenue discharge to Oak Bluffs Harbor Circuit Avenue North discharge to Oak Bluffs Harbor For nitrogen loading: Owen Little Way to outer Tisbury Harbor Skiff Avenue discharge to Mud Creek New York Avenue discharge to Oak Bluffs Harbor Circuit Avenue North discharge to Oak Bluffs Harbor For phosphorus loading: Owen Little Way to outer Tisbury Harbor Skiff Avenue discharge to Mud Creek New York Avenue discharge to Oak Bluffs Harbor Circuit Avenue North discharge to Oak Bluffs Harbor Many of these stormwater systems were shifted to lower priority because they have already been partially upgraded (Owen Little Way and Skiff Avenue) or because preliminary plans for addressing them are available (New York Avenue discharge to Oak Bluffs Harbor). Others pose difficult engineering problems because the lower segment of the stormwater system is at such low elevations that there is insufficient depth for infiltration to be added and remain above the water table (grade at less than about 5 feet MHW). These include both Circuit Avenue discharges, Vineyard Avenue West and Beach Road in Oak Bluffs. The Beach Road, Main Street and Beach Street Extension systems in Tisbury are also constrained by low elevation near the outfall and for a considerable distance up gradient from it. Opportunities to reduce these discharges by infiltrating portions of the contributing flow further up in the watershed should be pursued. CPR Final Report 27 After considering the possible impacts to human health and the potential to correct the entire discharge rather than addressing a small segment further up in the watershed, we chose the Grove Street discharge in Tisbury and the Jetty Beach and Inkwell Beach discharges in Oak Bluffs. The Oak Bluffs sites are discharges to recreational beaches that we believe have sufficient elevation for a suitable engineering design and in which the Department heads in the two Towns were interested. If the Jetty Beach outflow can be corrected, it will have the added advantage of allowing the Town to nourish this beach with dredging material from the entrance to Oak Bluffs Harbor. The Grove Street discharge is less used beach. Beyond these two sites, the general strategy suggested to reduce the impact of the other discharges is to reduce total present-day flow by infiltrating portions of the runoff further up in the watershed. This can be accomplished either by intercepting the flow in the collection system at a location where Town-owned land (or right of way) is available or before it enters the collection system from those roads beyond the system that contribute surface runoff to it. Engineering Plans: Sourati Engineering Group conducted preliminary engineering evaluation of the two sites identified for correction and these designs are attached to this document. The two sites are the Sea View Avenue discharges to Jetty and Inkwell beaches in Oak Bluffs and the Grove Street discharge in Tisbury. Both sites are believed to offer the likelihood of correction by installation of first-flush systems to treat and infiltrate the first ½ inch of runoff. In the case of the Sea View Avenue discharges, the Town-owned Waban Park has potential as an infiltration site. The elevation of the Park may be low enough that some fill may be required. In the case of Grove Street, sufficient elevation for infiltration within the road right of way exists a short distance away from the discharge as the road is steeply sloped. There is no Townowned land in this area.