Engineering Project Management Civil Engineering Department 2 April 13, 2015 An-Najah National University Civil Engineering Department Faculty of Engineering Construction Engineering and Management Nabil Dmaidi 3 April 13, 2015 Your Expectations of Me Be prepared Be on time Teach for full 50 minute period Fair grading system Front load the class work Do not humiliate students Practice golden rule Provide real world examples Make you think 4 April 13, 2015 Topics 1) Management Functions and introduction of construction project planning and scheduling 2)Construction scheduling techniques 3)Preparation and usage of bar charts 4)Preparation and usage of the Critical Path Method (CPM) 5)Preparation and usage of Precedence Diagramming Method (PDM) 6)Issues relating to determination of activity duration 7)Contractual provisions relating to project schedules 8)Resource leveling and constraining 9)Time cost tradeoff 10)Schedule monitoring and updating. 11)Communicating schedule 12) Project control and earned value Control 13) claims, Safety and Quality control 5 April 13, 2015 Course Outline Introduction and definitions Float Analysis Importance of Scheduling The CPM Calculations Networks, Bar Charts, and Brief introduction on: Imposed Finish Date and Project Control and Earned Value Analysis Resource Allocation /Leveling other CPM Issues Time/Cost Trade-off Precedence Networks Updating Schedules Time-Scaled Logic Diagrams 6 What is the Project April 13, 2015 In order to understand project management, one must begin with the definition of a project. A project can be considered to be any series of activities and tasks that :. ● Have a specific objective to be completed within certain specifications ● Have defined start and end dates ● Have funding limits (if applicable) ● Consume human and nonhuman resources (i.e., money, people, equipment) ● Are multifunctional (i.e., cut across several functional lines) 7 OR April 13, 2015 ‘‘a temporary endeavor undertaken to create a unique product, service, or result’’ 8 Project Life Cycle April 13, 2015 9 Five Process group Project initiation ● Selection of the best project given resource limits ● Recognizing the benefits of the project ● Preparation of the documents to sanction the project ● Assigning of the project manager April 13, 2015 Project planning Project execution ● Definition of the work requirements ● Definition of the quality and quantity of work ● Definition of the resources needed ● Scheduling the activities ● Evaluation of the various risks Project monitoring and control ● Tracking progress ● Comparing actual outcome to predicted outcome ● Analyzing variances and impacts ● Making adjustments ● Negotiating for the project team members ● Directing and managing the work ● Working with the team members to help them improve Project closure ● Verifying that all of the work has been accomplished ● Contractual closure of the contract ● Financial closure of the charge numbers ● Administrative closure of the paper work 10 April 13, 2015 11 April 13, 2015 Successful project management can then be defined as having achieved the project objectives: ● Within Time ● Within Cost ● At the desired performance/Technology level ● While utilizing the assigned resources effectively and efficiently ● Accepted by the customer 12 What is Project Management April 13, 2015 Project management is the planning, organizing, directing, and controlling of company resources for a relatively short-term objective that has been established to complete specific goals and objectives. 13 April 13, 2015 The potential benefits from project management are: ● Identification of functional responsibilities ● Minimizing the need for continuous reporting ● Identification of time limits for scheduling ● Identification of a methodology for trade-off analysis. ● Measurement of accomplishment against plans 14 April 13, 2015 The above definition requires further comment. Classical management is usually considered to have five functions or principles: ● Planning ● Organizing ● Staffing ● Controlling ● Directing 15 April 13, 2015 Planning – Where the organization wants to be in the future and how to get there. Organizing – Follows planning and reflects how the organization tries to accomplish the plan. – Involves the assignment of tasks, grouping of tasks into departments, and allocation of resources. 16 April 13, 2015 Leading – The use of influence to motivate employees to achieve the organization's goals. – Creating a shared culture and values, communicating goals to employees throughout the organization, and infusing employees to perform at a high level. Controlling – Monitoring employees' activities, determining if the organization is on target toward its goals, and making corrections as necessary 17 Management Skills April 13, 2015 Conceptual Skill—the ability to see the organization as a whole and the relationship between its parts. Human Skill—The ability to work with and through people. Technical Skill—Mastery of specific functions and specialized knowledge 18 Constraints of the project April 13, 2015 Project management is designed to manage or control company resources on a given activity, within time, within cost, and within performance. Time, cost, and performance are the constraints on the project. 19 Resources April 13, 2015 We have stated that the project manager must control company resources within time, cost, and performance. Most companies have six resources: ● Money ● Manpower ● Equipment ● Facilities ● Materials ● Information/technology 20 April 13, 2015 Actually, the project manager does not control any of these resources directly, except perhaps money (i.e., the project budget). Resources are controlled by the line managers . The project manager is responsible for coordinating and integrating activities across multiple, functional lines. The integration activities performed by the project manager include: 21 April 13, 2015 ● Integrating the activities necessary to develop a project plan ● Integrating the activities necessary to execute the plan ● Integrating the activities necessary to make changes to the plan 22 April 13, 2015 Project Scheduling Planning, Scheduling, and Control 23 Planning and Scheduling April 13, 2015 Planning and scheduling are two terms that are often thought of as synonymous They are not! Scheduling is just one part of the planning effort. 24 April 13, 2015 Project planning serves as a foundation for several related functions such as cost estimating, scheduling, and project control. Project scheduling is the determination of the timing and sequence of operations in the project and their assembly to give the overall completion time 25 April 13, 2015 Planning is the process of determining how a project will be undertaken. It answers the questions: 1. “What” is going to be done, 2. “how”, 3. “where”, 4. By “whom”, and 5. “when” (in general terms: start and finish). Scheduling deals with “when” on a detailed level… See Figure 1 . 26 April 13, 2015 How much What when The Plan By whom where How Why Figure 1 . Planning and Scheduling 27 The Plan April 13, 2015 PMI defines project management plan as a ‘‘formal, approved document that defines how the project is executed, monitored and controlled”. The plan can include elements that has to do with scope, design and alternate designs, cost, time, finance, land, procurement, operations, etc. 28 April 13, 2015 WHY SCHEDUALE PROJECTS ? 1- To calculate the project completion. 2- To calculate the start or end of a specific activity. 3-To expose and adjust conflict between trades or subcontractor. 4- To predict and calculate the cash flow . 5-To evaluate the effect of changing orders ‘CH’ . 29 April 13, 2015 6- To improve work efficiency. 7- To resolve delay claims , this is important in critical path method ‘CPM’ discussed later.. 8- To serve as an effective project control tool . 30 The Tripod of Good Scheduling System April 13, 2015 1. The Human Factor : A proficient scheduler or scheduling team. 2. The Technology : A good scheduling computer system (software and hardware) 3. The Management : A dynamic, responsive, and supportive management. If anyone of the above three ‘‘legs’’ is missing, the system will fail. 31 Scheduling and project management April 13, 2015 Planning, scheduling, and project control are extremely important components of project management. project management includes other components : • cost estimating and management, • procurement, • project/contract administration, • quality management, • and safety management. These components are all interrelated in different ways. 32 April 13, 2015 Quiz 1 True or False: 1. There are no two projects that are identical 2.Every construction project needs a CPM schedule 3.Planning and scheduling are two names for the same function 4.The maintenance of a large office building is considered a project 5. The renovation of a large office building is considered a project 6.There is one standard way to break down the project into activities for the purpose of creating a schedule 33 April 13, 2015 Bar (Gantt) Charts 34 DEFINITION AND INTRODUCTION April 13, 2015 • A bar chart is ‘‘a graphic representation of project activities, shown in a time-scaled bar line with no links shown between activities’’ The bar may not indicate continuous work from the start of the activity until its end. or Non continuous (dashed) bars are sometimes used to distinguish between real work (solid line) and inactive periods (gaps between solid lines) 35 April 13, 2015 • Before a bar chart can be constructed for a project, the project must be broken into smaller, usually homogeneous components, each of which is called an activity, or a task. Item M 10 Activity Mobilization Bars ( Month or Year ) 36 ADVANTAGES OF BAR CHARTS April 13, 2015 1- Time-scaled 2- Simple to prepare 3- Can be more effective and efficient if CPM based - Still the most popular method 4- Bars can be dashed to indicate work stoppage. 5- Can be loaded with other information (budget, man hours, resources, etc.) 37 April 13, 2015 Bar Charts Loaded with More Info. Such as : budget, man hours and resources . 500$ 220$ 400$ 850$ 140$ 500$ 900$ 10 12 7 11 10 9 15 38 DISADVANTAGES OF BAR CHARTS April 13, 2015 1- Does not show logic 2- Not practical for projects with too many activities - As a remedy, we can use bar charts to show: 1. A small group of the activities (subset) 2. Summary schedules 39 April 13, 2015 Quiz 2 True or False: 1. The bar representing a 4-day activity is twice as long as a bar representing a 2-day activity in a bar chart 2.Bar chart method lost its applicability with the introduction of the Critical Path Method 3.Bars in a bar chart must be connected with relationship lines 4.A bar representing an activity in a bar chart may not be continuous 5. Bar charts and Gantt charts are two different methods. 6.Bar charts can be loaded with information other than the timeline of the project 40 Basic Networks April 13, 2015 41 April 13, 2015 DEFINITION AND INTRODUCTION • A network is a logical and chronological graphic representation of the activities (and events) composing a project. • Network diagrams are the preferred technique for showing activity sequencing. • Two main formats are the arrow and precedence diagramming methods. 42 April 13, 2015 Two classic formats AOA: Activity on Arrow AON: Activity on Node Each task labeled with Identifier (usually a letter/code) Duration (in std. unit like days) There are other variations of labeling There is 1 start & 1 end event Time goes from left to right 43 April 13, 2015 Arrow Diagramming Method (ADM) 1. Also called activity-on-arrow (AOA) network diagram or (I-J) method (because activities are defined by the form node, I, and the to node, J) 2. Activities are represented by arrows. 3. Nodes or circles are the starting and ending points of activities. 4. Can only show finish-to-start dependencies. 44 April 13, 2015 Basic Logic Patterns for Arrow Diagrams Node (Event) i i Node (Event) j Activity Name j j>i Each activity should have a unique i – j value (a) Basic Activity 45 April 13, 2015 2 A 4 B 10 (b) Independent Activities 3 A 6 B 9 (c) Dependent Activities 12 46 April 13, 2015 4 A C 6 B 8 2 Activity C depends upon the completion of both Activities A & B (d) A Merge B 2 A 4 6 C 8 Activities B and C both depend upon the completion of Activity A (e) A Burst 47 April 13, 2015 12 A B C 16 14 18 D 20 Activities C and D both depend upon the completion of Activities A and B (f) A Cross 48 Example April 13, 2015 Draw the arrow network for the project given next. Activity IPA A - B A C A D B E C,D 49 April 13, 2015 Solution : B 30 10 A 20 D E 40 C 50 50 Dummy activity (fictitious) April 13, 2015 * Used to maintain unique numbering of activities. * Used to complete logic, duration of “0” * The use of dummy to maintain unique numbering of activities. 51 April 13, 2015 A Divide node to correct 4 10 B (a) Incorrect Representation 4 A 10 B Dummy 11 (b) Correct Representation 52 Example April 13, 2015 Draw the arrow network for the project given next. Activity IPA A - B A C A D B,C 53 Solution : April 13, 2015 B 10 A 20 D 30 40 C Improper solution B 30 Dummy 40 D 50 10 A 20 C proper solution 54 Example April 13, 2015 Draw the arrow network for the project given next. Activity IPA A - B A C A D B E B,C F C 55 April 13, 2015 Solution : B 30 D Dummy 1 10 A 20 50 E Dummy 2 C 40 F 60 56 April 13, 2015 Removal of Redundant Dummies Original Diagram Diagram after removal of redundant dummies (a) A B A B (b) A B A B C C 57 April 13, 2015 Original Diagram (c) (d) Diagram after removal of redundant dummies A C A C B E B E A C A C B E B E 58 April 13, 2015 Activity Depends Upon Immediately Preceding Activity (IPA) A B C ----A A, B ----A B A B Redundant Relationship C 59 Activity List with Dependencies: Activity A B C D E F G H J K L M Description Site Clearing Removal of Trees Excavation for Foundations Site Grading Excavation for Utility Trenches Placing formwork & Reinforcement Installing sewer lines Pouring concrete Obtain formwork & reinforcing steel Obtain sewer lines Obtain concrete Steelworker availability April 13, 2015 Depends Upon --------A A, B, C A, B, C B, C, J, M B, C, D, E, K D, E, F, G, L ----------------- 60 Removing Redundant Relationships: April 13, 2015 Activity A B C D E F G H J K L M Description Site Clearing Removal of Trees Excavation for Foundations Site Grading Excavation for Utility Trenches Placing formwork & Reinforcement Installing sewer lines Pouring concrete Obtain formwork & reinforcing steel Obtain sewer lines Obtain concrete Steelworker availability Depends Upon --------A A, B, C A, B, C B, C, J, M B, C, D, E, K D, E, F, G, L ----------------- 61 April 13, 2015 L J M A 20 10 F 15 B 5 25 C G E D 35 30 K AOA Representation 40 H 45 62 April 13, 2015 NODE NETWORKS MTHOD (AON) Link Activity number 10 A Activity name 20 B a) Independent Activities 10 A Link 20 B b) Dependent Activities B depends on A 63 April 13, 2015 10 A 30 C 40 D C depends on A & B D depends on C 20 B c) A Merge Relationship 10 A 20 B 30 C 40 D d) A Burst Relationship B depends on A C depends on B D depends on B 64 April 13, 2015 A D A Start Dummy B C E D Finish Dummy B C e) Start & Finish Dummy Activities E 65 Example April 13, 2015 Draw the arrow network for the project given next. Activity IPA A - B A C A D B E C,D 66 April 13, 2015 Solution : B D A E C 67 Example April 13, 2015 Draw the arrow network for the project given next. Activity IPA A - B A C A D B,C 68 April 13, 2015 Solution : B A D C 69 Example April 13, 2015 Draw the arrow network for the project given next. Activity IPA A - B A C A D B E B,C F C 70 April 13, 2015 Solution : B A D E C F PF 71 Lags and Leads April 13, 2015 In some situations, an activity cannot start until a certain time after the end of its Predecessor. Lag is defined as a minimum waiting period between the finish (or start) of an activity and the start (or finish) of its successor. Arrow networks cannot accommodate lags. The only solution in such networks is to treat it as a real activity with a real duration, no resources, and a $0 budget. 72 Examples April 13, 2015 3 Place Concrete 3 Strips Forms 2 A lag in a node network Place Concrete Cure Concrete A lag in an arrow network Strips Forms 73 April 13, 2015 The term lead simply means a negative lag. It is seldom used in construction. In simple language: A positive time gap (lag) means ‘‘after’’ and a negative time gap (lead) means ‘‘before.’’ 74 April 13, 2015 Recommendations for Proper Node Diagram Drawing Incorrect Correct 75 April 13, 2015 A B A B A B A B Improper proper 76 April 13, 2015 Improper Proper 77 April 13, 2015 Improper Proper 78 April 13, 2015 A A B B PS C C Improper Proper (a) Do not start a network with more than one node 79 April 13, 2015 Improper A A B B C C Proper (a) Do not end a network with more than one node PF 80 April 13, 2015 The Critical Path Method (CPM) 81 Introduction April 13, 2015 Suppose you decide with your friend to go in hunting trip. You must do specific activity such that the trip well be at the right way. The following activity must be done. 82 April 13, 2015 From chart you can see that the 3rd activity (preparing the jeep) have the longest period of time any delay with this activity leads to delay in the trip this activity is a “critical activity” Critical activity : An activity on the critical path any delay on the start or finish of a critical activity will result in a delay in the entire project Critical path : The longest path in a network from start to finish 83 April 13, 2015 Steps Required To Schedule a Project The preparation of CPM includes the following four steps: 1- Determine the work activities: The project must be divided into smaller activities or tasks . The activity shouldn’t be more than 14-20 days (long durations should be avoided) Use WBS in scheduling by using an order of letters and numbers 84 April 13, 2015 2- Determine activity duration: Duration = Total Quantity / Crew Productivity The productivity has many sources : 1. The company 2. The market 3. Special books Note: The scheduler must be aware about the non-working days , such as holydays or rain days, etc…… 85 Estimating Activity Duration April 13, 2015 Time Interval Time Interval is selected according to the nature of the activity (seconds - minutes…) It is common practice in construction industry to use calendar day. Use one and only one time unit for any schedule. Sources 1. From company’s record 2. From standard estimating guide 3.Interviewing field personnel. 86 Weather and Contingency Allowance April 13, 2015 Two approaches for assignment of weather allowance: 1. Add the Weather Allowance at the end of the project as a separate activity. 2. Add Weather Allowance to those affected by the weather. 3.Add weather allowance at the end of each construction segment (site preparation, foundation, … etc.) Contingency items Other activities can be added to allow for contingency such as strikes Time Zero The close of the work period immediately preceding the start of the project. 87 April 13, 2015 3- Determine the logical relationships : This step is a technical matter and obtained from the project manager and technical team, and logical relationships shouldn’t confused with constraints 4- Draw the logic network and perform the CPM calculations 88 April 13, 2015 5-Reiew and analyze the schedule: 1. review the logic 2. Make sure the activity has the correct predecessor 3. make sure there is no redundant activity 89 April 13, 2015 6- Implement the schedule: Definition: take the schedule from paper to the execution. 7-Monitor and control the schedule: Definition: comparing what we planed with what actually done. 8-Revise the database and record feedback. 9-Resource allocation and leveling. (will discuss in chapter 6) 90 The WBS (Work Breakdown Structure) April 13, 2015 IT is used to break down the project from one main and relatively big entity into smaller, defined, manageable and controllable units, usually called work groups or tasks, or, at the finest level of detail (which is undesirable) activities 91 Take care!!! April 13, 2015 The deeper you go into the lower levels of the WBS, the more detailed knowledge you’ll need to know. A good rule of thumb is the rule of 1-5-5-5, which entails that each level be broken down into a maximum of five lower levels. 92 Who develops the WBS? April 13, 2015 A WBS is developed by the A/E at the end of the design phase. and/or by the bidders during the proposal (procurement phase). 93 The CWBS (Contract Work breakdown Structure ) April 13, 2015 After contract award, the project manager expands the WBS into a contract work breakdown structure (CWBS). as the initial step in the PLANNING process. The extended CWBS must include the levels at which required reporting information is summarized for submittal to the Owner 94 Uses of the WBS April 13, 2015 The WBS is used to report program status externally to the Owner. The CWBS is used internally to plan the program in detail and to collect status information on a periodic basis for the lowest level of the CWBS, namely the schedule activities. The basis for technical planning and project achievement. 95 The CWBS April 13, 2015 it is a major task to undo. Why??? Because cost collections begins at a CWBS element, The individuals assigned the responsibility for WBS/CWBS development should never lose sight of the fact that the WBS is used for technical planning and status achievement. 96 April 13, 2015 House 1.0 Level 1 Level 2 fine works 1.2 Structural Work 1.1 SubStructure 1.1.1 SuperStructure 1.1.2 Earthwork Foundation 1.1.1.2 1.1.1.1 Columns Roof slabs 1.1.2.1 1.1.2.2 Level 3 Excavation 1.1.1.1.1 Backfilling 1.1.1.1.2 Finishing 1.21 Plaster 1.2.1.1 Doors & Windows frames 1.2.2 Floor tile 1.2.1.2 Electrical Works 1.3 Conduiting 1.3.1 Light Fittings 1.3.2 Level 4 Level 5 97 Conclusion April 13, 2015 The work breakdown structure defines the product elements (work packages). And their interrelations to each other and to the product. The WBS mostly ends with project tasks. Using the tasks you can extract project’s activities. 98 TYPES OF ACTIVITIES April 13, 2015 1. Production Activities Those that can be taken directly from plans and specifications 2. Procurement Activities Procurement of material and equipment 3. Management Decision Activities Activities that can be created by management to avoid certain situations Delay Concrete Company Vacation Deer Hunting 99 Events and Milestones April 13, 2015 An event: a point in time that is usually the start or finish of a certain activity(s) Duration = 0 Important events are called milestones milestones such as NTP and finish milestones such as Substantial Completion An activity has a start date and a finish date An event / milestone has a start date or a finish date 100 Example April 13, 2015 Draw the logic network and perform the CPM calculations for the schedule shown next. Activity IPA Duration A - 5 B A 8 C A 6 D B 9 E B,C 6 F C 3 G D,E,F 1 101 Forward pass calculations April 13, 2015 In mathematical terms, the ES for activity j is as follows : ESj =max( EFi ) where (EFi) represents the EF for all preceding activities. Likewise, the EF time for activity j is as follows : EF j= ESj + Dur j where Dur j is the duration of activity j Forward pass: The process of navigating through a network from start to end and calculating the completion date for the project and the early dates for each activity 102 April 13, 2015 Solution : 0,5 A 5 5,13 B 8 13,22 D 9 13,19 E 6 5,11 C 6 22,23 G 1 11,14 F 3 103 Backward pass calculations April 13, 2015 In mathematical terms, the late finish LF for activity j is as follows : LFj =min(LSk( where (LSk) represents the late start date for all succeeding activities. Likewise, the LS time for activity j (LS j) is as follows : LS j= LFj - Dur j where Dur j is the duration of activity Backward pass: The process of navigating through a network from end to start and calculating the late dates for each activity. The late dates (along with the early dates) determine the critical activities, the critical path, and the amount of float each activity has. 104 April 13, 2015 Solution : 0,5 A 5 0,5 5,13 B 8 5,13 5,11 C 6 10,16 13,22 D 9 13,19 13,22 E 6 16,22 11,14 F 3 19,22 CPM ( ES = LS , EF = LF , TF = FF = 0) 22,23 G 1 22,23 105 Four Types Of Floats April 13, 2015 There are several types of float. The simplest and most important type of float is Total Float (TF) Total float (TF): The maximum amount of time an activity can be delayed from its early start without delaying the entire project. TF = LS – ES or TF = LF - EF or TF = LF - Dur - ES 106 April 13, 2015 Free Float: may be defined as the maximum amount of time an activity can be delayed without delaying the early start of the succeeding activities FFi = min(ESi+1) - EFi where min (ESi+1) means the least (i.e., earliest) of the early start dates of succeeding activities 107 April 13, 2015 In the previous example we can find the free float and total float for each activity as the following : Activity C’s free float, FF = 11 - 11 = 0 days And Activity C’s total float, TF =16 - 11= 5 days …… and so on. Activity Duration ES EF LS LF TF FF A 5 0 5 0 5 0 0 B 8 5 13 5 13 0 0 C 6 5 11 10 16 5 0 D 9 13 22 13 22 0 0 E 6 13 19 16 22 3 3 F 3 11 14 19 22 8 8 G 1 22 23 22 23 0 0 Critical activity Note : We must always realize that FF ≤ TF 108 April 13, 2015 Interfering float: may be defined as the maximum amount of time an activity can be delayed without delaying the entire project but causing delay to the succeeding activities. TF = FF - Int. or Int. F = TF - FF Independent float (Ind. F): we may define it as the maximum amount of time an activity can be delayed without delaying the early start of the succeeding activities and without being affected by the allowable delay of the preceding activities. Ind. Fi = min(ESi+1) – max(LFi-1) – Duri Note: make sure that Ind. F ≤ FF 109 Node Format ES April 13, 2015 Activity ID EF Activity Name LS TF Duration LF FF 110 Example April 13, 2015 Activity Duration IPA A 5 - B 8 A C 6 A D 9 B E 6 B,C F 3 C G 1 D,E,F 111 Tabular Solution April 13, 2015 Activity Duration ES EF LS LF TF A 5 0 5 0 5 0 B 8 5 13 5 13 0 C 6 5 11 10 16 5 D 9 13 22 13 22 0 E 6 13 19 16 22 3 F 3 11 14 19 22 8 G 1 22 23 22 23 0 112 April 13, 2015 Graphic Solution 5, 13 13, 22 B 8 0, 5 5, 13 A 5 0, 5 5 5, 11 C 6 10, 16 D 9 3 13, 19 13, 22 22, 23 E 6 G 1 16, 22 22, 23 8 11, 14 F 3 19, 22 All dates above represent the end of the day 113 Example April 13, 2015 Activity Duration IPA A 5 - B 6 A C 5 A D 3 A E 3 B F 4 B, C G 4 D H 7 B,C,G I 8 E, F J 2 F K 3 H, J L 2 I, J 114 April 13, 2015 B 6 E 3 I 8 L 2 A 5 C 5 F 4 J 2 D 3 G 4 H 7 PF K 3 115 April 13, 2015 Graphic Solution 5, 11 B 6 5, 11 0, 5 A 5 0, 5 1 5, 10 C 5 6, 11 1 11, 14 E 3 15, 23 12, 15 15, 23 11, 15 F 4 I 8 23, 25 L 2 5 15, 17 J 2 11, 15 23, 25 25 PF 20, 22 25 3 5, 8 D 3 8, 11 3 8, 12 G 4 11, 15 3 12, 19 3 19, 22 H 7 K 3 15, 22 22, 25 116 April 13, 2015 Tabular Solution Activity A B C D E F G H I J K L ES 0 5 5 5 11 11 8 12 15 15 19 23 EF 5 11 10 8 14 15 12 19 23 17 22 25 LS 0 5 6 8 12 11 11 15 15 20 22 23 LF 5 11 11 11 15 15 15 22 23 22 25 25 TF 0 0 1 3 1 0 3 3 0 5 3 0 FF 0 0 1 0 1 0 0 0 0 2 3 0 117 End-of-Day Convention April 13, 2015 The dates on the activities represent the “end of day”. That’s why we always start with day 0: end of day 0 = start of day 1 This concept is not applied in computer programs. In computer programs start dates (ES, LS) represent the beginning of the day while finish dates (EF, LF) represent the end of the day 118 Exercise Solution Using The Computer 6, 11 1 12, 14 15, 23 B 6 E 3 I 8 6, 11 13, 15 16, 23 6, 10 12, 15 A 5 C 5 F 4 J 2 1, 5 7, 11 12, 15 21, 22 1, 5 1 5 April 13, 2015 24, 25 L 2 16, 17 24, 25 25 PF 25 3 6, 8 3 9, 12 3 13, 19 3 20, 22 D 3 G 4 H 7 K 3 9, 11 12, 15 16, 22 23, 25 119 Comments on the Solution April 13, 2015 Near-critical activities may be as important as critical activities It is a good practice for the project manager not to give subordinates two sets of dates PM has to choose one set of dates within the range of Early – Late Management may reserve a number of days as “management float” or “time contingency” 120 Float Discussion April 13, 2015 Total float –in general- belongs to a path rather than the activity itself If an activity uses “its” float, successors may lose some or all of “their” float Total float versus free float Total float is broken down into free float, independent float, and interfering float. Researchers have come up with even more types 121 April 13, 2015 The question is: “who owns the float”? Float distribution attempts Review the contract – what if it is not mentioned? Float with resource leveling Shifting activities within their float may affect: Start / finish dates of succeeding activities Resource usage: Labor and equipment (crews) Materials: delivery, storage Cash flow 122 Lags in Node Networks April 13, 2015 A lag is a minimum compulsory waiting period between the start/finish of an activity and the start/finish of the successor Actual waiting period may be greater, but never less than the lag Lags are very common with SS and FF relationships A lead is a negative lag The lag is added in the CPM’s forward pass calculations and subtracted in the backward pass 123 April 13, 2015 Examples: Concrete curing (before formwork stripping or reshoring) Asphalt curing (before striping) Waiting for a permit to be issued Waiting for the delivery of a custom material or equipment 124 Example April 13, 2015 Activity Duration IPA A 5 - B 3 - C 6 - D 7 A E 7 A B F 4 A,B,C G 5 E F H 6 3 4 3 D G I Lag D,G 2 125 April 13, 2015 Graphic Solution 0, 5 5, 12 21, 27 A 5 D 7 H 6 2, 7 14, 21 0 0, 3 7, 14 14, 19 19, 22 27 PS B 3 E 7 G 5 I 3 PF 0 0, 3 7, 14 14, 19 24, 27 27 0, 6 6, 10 C 6 F 4 1, 7 7, 11 4 2 3 21, 27 126 April 13, 2015 Tabular Solution Activity A B C D E F G H I ES 0 0 0 5 7 6 14 21 19 EF 5 3 6 12 14 10 19 27 22 LS 2 0 1 14 7 7 14 21 24 LF 7 3 7 21 14 11 19 27 27 TF 2 0 1 9 0 1 0 0 5 FF 0 0 0 7 0 1 0 0 5 127 Constraints and the CPM April 13, 2015 A Constraint is an externally imposed restriction affecting when an activity can start and/or finished Constraints may conflict with logical relationships Constraints are not alternatives for logic 128 Software Quiz April 13, 2015 On a continuous path: A 6 B 5 C 3 D 9 E 5 F 2 Activities A, B, and C are critical; but D, E, and F not Why? 129 Effect of Imposed Finish Date April 13, 2015 Imposed Finish Date is the project’s completion date, as specified in the contract or stipulated by the owner When compared to the calculated finish date: Calculated finish date < imposed finish date • You are in good shape • What happens if you enter the imposed date? Calculated finish date > imposed finish date • Negative float appears when you enter the imposed date • You need to accelerate / crash the schedule 130 April 13, 2015 Examples with Imposed Finish Dates Repeat Example 3 with imposed finish date of 28 days Repeat Example 3 with imposed finish date of 22 days 131 April 13, 2015 Imposed Finish Date > Calculated Finish Date 3 3 0, 5 5, 11 4 4 11, 14 3 15, 23 B 6 E 3 I 8 8, 14 15, 18 18, 26 5, 10 3 11, 15 8 3 L 2 15, 17 A 5 C 5 F 4 J 2 3, 8 9, 14 14, 18 23, 25 23, 25 26, 28 25 PF 28 6 5, 8 6 8, 12 6 12, 19 6 19, 22 D 3 G 4 H 7 K 3 11, 14 14, 18 18, 25 25, 28 132 April 13, 2015 Imposed Finish Date < Calculated Finish Date -3 -3 0, 5 -2 5, 11 -2 11, 14 -3 15, 23 B 6 E 3 I 8 2, 8 9, 12 12, 20 5, 10 -3 11, 15 2 -3 L 2 15, 17 A 5 C 5 F 4 J 2 -3, 2 3, 8 8, 12 17, 19 23, 25 20, 22 25 PF 22 0 5, 8 0 8, 12 0 12, 19 0 19, 22 D 3 G 4 H 7 K 3 5, 8 8, 12 12, 19 19, 22 133 Negative Float April 13, 2015 Negative float is a situation that occurs when performing an activity even on its early dates, fails to meet the project’s imposed finish date or other constraint It may occur in one of two cases: Before construction starts During construction (after normal start) 134 Calendars April 13, 2015 Each activity has to be assigned a calendar Different crews working for different activities work on different calendars. The crew working for the same activity may work 5 days/week at normal times then switch to 6 or 7 days/week User has to be aware of the impact of such matter on the duration of activities and consequently the project 135 April 13, 2015 Computer scheduling programs can handle calendars: Global, default, and other calendars Recurring holidays Work hours per day Resource calendars Scheduling in other countries 136 Non-Work Days April 13, 2015 Schedulers must take in account non-work days. This includes: Scheduled non-work days such as:. • Holidays, • Shut-downs. Unscheduled non-work days such as: • Rain days (or severe weather), • Other unforeseen interruptions Distribution of unscheduled non-work days 137 April 13, 2015 Event Times in Arrow Networks The early event time, TE, is the largest (latest) date obtained to reach an event (going from start to finish). The late event time, TL, is the smallest (earliest) date obtained to reach an event (going from finish to start). Example Perform the CPM calculations, including the event times, for the arrow network shown below. 138 April 13, 2015 A 10 20 8D d1 10 B E 30 9 5 C 7 60 G5 H 50 8 40 4F Arrow network for example d2 70 139 April 13, 2015 The preceding logic is similar to that of the forward and backward passes: When you are going forward, pick the largest number. When you are going backward, pick the smallest number. TEi i TEj Act. Name Dur. j TLj TLi CPM 140 April 13, 2015 10 A (0,10) 10 (0,10) D 20 8 (10,18) (11,19) B 5 d1 (0,5) (5,10) 7 0 C (0,7) 7 (8,15) 40 4F 15 (19,24) 60 G5 (22,27) (19,27) H 50 27 10 0 10 24 10 (10,19) E 30 9 (10,19) 10 (7,11) (15,19) 19 8 19 (19,27) d2 27 70 27 141 April 13, 2015 Float Calculations From Event Times Total Float TFij = TLj - TEi - Tij Example ( In the previous network ) TF40-50 = TL50 – TE40 – T40-50 = 19 – 7 – 4 = 8 142 April 13, 2015 Free Float FFij = TEj - TEi – Tij Example FF40-50 = TE50 – TE40 – T40-50 = 19 – 7 – 4 = 8 143 Interfering Float INTFij = TLj – TEj Example INTF40-50 = TL50 – TE50 = 19 – 19 = 0 Independent Float INDFij= TEj – TLi - Tij Example INDF40-50 = TE50 – TL40 – T40-50 = 19 – 15 – 4 = 0 April 13, 2015 144 Example April 13, 2015 Draw a network for the following activities Activity Duration IPAs A 2 -- B 2 A C 4 A D 1 C E 4 B,C F 2 B G 1 D H 4 F,E I 2 F J 4 G,H K 4 I,H L 1 K,J 145 The 1 A April 13, 2015 Arrow Network will be: B 2 2 F 3 2 I 9 10 2 2 C 4 4 4 6 E 7 4 D H 11 12 4 J 1 5 K G 1 8 4 L 1 13 146 Forward 0 1 2 A April 13, 2015 Pass calculations (ES, EF) 4 B 2 2 6 F 3 2 C 4 14 I 9 2 2 6 6 4 6 E 7 D 4 14 10 4 1 10 H 18 11 12 4 J 7 5 K 14 G 1 8 4 19 L 1 13 147 backward 0 1 2 A April 13, 2015 Pass calculations (LS, LF) 6 B 2 2 10 F 3 2 C 4 14 I 9 2 2 6 6 4 6 E 7 D 4 14 10 4 1 10 H 18 11 12 4 J 13 5 K 14 G 1 8 4 19 L 1 13 148 April 13, 2015 Specify the Critical Path 0 0 2 2 1 A 6 4 B 2 2 10 6 F 3 2 I 9 6 6 4 6 D E 7 H K 18 4 18 11 12 4 13 7 5 14 14 10 10 4 1 10 2 2 6 6 C 4 14 14 J 14 14 G 1 8 4 19 19 L 1 13 149 April 13, 2015 0 0 1 2 2 A 6 4 B 2 2 10 6 F 3 2 I 9 6 6 4 6 D E 7 H K 18 4 18 11 12 4 13 7 5 14 14 10 10 4 1 10 2 2 6 6 C 4 14 14 J 14 14 G 1 8 4 19 19 L 1 13 150 April 13, 2015 Table of activities Activity Duration IPAs ES EF LS LF TF A 2 -- 0 2 0 2 0 B 2 A 2 4 4 6 2 C 4 A 2 6 2 6 0 D 1 C 6 7 12 13 6 E 4 B,C 6 10 6 10 0 F 2 B 4 6 8 10 4 G 1 D 7 8 13 14 6 H 4 F,E 10 14 10 14 0 I 2 F 6 8 12 14 6 J 4 G,H 14 18 14 18 0 K 4 I,H 14 18 14 18 0 L 1 K,J 18 19 18 19 0 151 Activity Bar / Gantt chart Early Start / Finish EF = ES + D A April 13, 2015 B C D E F G H I J K L 2 4 6 8 10 Time 12 14 16 18 20 152 Activity Bar / Gantt Chart Late Start / Finish LS = LF - D A April 13, 2015 B C D E F G H I J K L 2 4 6 8 10 Time 12 14 16 18 20 153 Bar / Gantt of the previous network April 13, 2015 A B C D E F G H I J K L 2 4 6 8 10 12 14 16 18 20 154 April 13, 2015 Summary TEi i TLi Direction TEj T j TLj Float TF FF Int. F Ind. F 155 True or False: Quiz 4 April 13, 2015 • Determining activities durations is primarily the scheduler’s job • You can find out the project’s estimated completion date after • performing the forward pass only • You can find out the project’s critical path after performing the forward pass only • “Event” is another name for an activity • “Task” is another name for an activity • There could be more than one critical path in a CPM network • Total float must be equal to or greater than free float 156 Definitions April 13, 2015 Activity, or task: A basic unit of work as part of the total project that is easily measured and controlled. It is time- and resource consuming. Backward pass: The process of navigating through a network from end to start and calculating the late dates for each activity. The late dates (along with the early dates) determine the critical activities, the critical path, and the amount of float each activity has. Critical activity: An activity on the critical path. Any delay in the start or finish of a critical activity will result in a delay in the entire project. Critical path: The longest path in a network, from start to finish, including lags and constraints. 157 April 13, 2015 Early dates: The early start date and early finish date of an activity. Early finish (EF): The earliest date on which an activity can finish within project constraints. Early start (ES): The earliest date on which an activity can start within project constraints. Event: A point in time marking a start or an end of an activity. In contrast to an activity, an event does not consume time or resources. Forward pass: The process of navigating through a network from start to end and calculating the completion date for the project and the early dates for each activity. Late dates: The late start date and late finish date of an activity. Late finish (LF): The latest date on which an activity can finish without extending the project duration. Late start (LS): The latest date on which an activity can start without extending the project duration. 158 April 13, 2015 Precedence Diagram 159 The Four Types Relationships April 13, 2015 Activities represented by nodes and links that allow the use of four relationships: 1) Finish to Start – FS 2) Start to Finish – SF 3) Finish to Finish – FF 4) Start to Start – SS 160 April 13, 2015 Finish to Start (FS) Relationship . The traditional relationship between activities. . Implies that the preceding activity must finish before the succeeding activities can start. . Example: the plaster must be finished before the tile can start. Plaster Tile 161 April 13, 2015 Star to Finish (SF) Relationship . Appear illogical or irrational. . Typically used with delay time OR LAG. . The following examples proofs that its logical. Erect formwork steel reinforcement Pour concrete 5 SF Order concrete 162 April 13, 2015 Finish to Finish (FF) Relationship • Both activities must finish at the same time. • Can be used where activities can overlap to a certain limit. Erect scaffolding Remove Old paint FF/1 sanding FF/2 painting inspect Dismantle scaffolding 163 April 13, 2015 Start to Start (SS) Relationship • This method is uncommon and non exists in project construction . Clean surface Spread grout SS Set tile Clean floor area 164 April 13, 2015 Advantages of using Precedence Diagram 1. No dummy activities are required. 2. A single number can be assigned to identify each activity. 3. Analytical solution is simpler. 165 Calculation 1) forward calculations EF = ES + D Calculate the Lag LAGAB = ESB – EFA Calculate the Free Float FF = Min. (LAG) April 13, 2015 166 April 13, 2015 2) Backward calculations For the last task LF=EF , if no information deny that. LS=LF-D Calculate Total Float TF = LS – ES OR LF – EF TFi = Min (lag ij + TFj ) Determine the Critical Path 167 Example April 13, 2015 1) Forward pass calculations 4) Backward pass calculations 5) Calculate total Float (TF = LS – ES OR LF – EF) A 1 2 B 0 1 2 0 0 2 11 1 9 0 D 0 2 11 0 11 16 5 0 0 16 7 E 0 5 7 0 3 10 11 5 4 0 H 0 16 20 20 0 0 20 21 4 5 0 2 16 11 4 C F 0 1 20 0 0 21 3 G 0 10 11 3 14 17 6 3 14 3 20 2) Calculate the Lag ( LAGAB = ESB – EFA) 3) Calculate the Free Float (FF) FF = min.( LAG) ES Dur. LS EF FF 167 TF LF 168 April 13, 2015 6) Determine the Critical Path A 1 2 B 0 1 2 0 0 2 11 1 9 0 D 0 2 11 0 11 16 5 0 0 16 7 E 0 5 7 0 3 10 11 5 4 0 H 0 16 20 20 0 0 20 21 4 5 0 2 16 11 4 C F 0 1 20 0 0 21 3 G 0 10 11 3 14 17 6 3 14 3 20 The critical path passes through the critical activities where TF = 0 ES Dur. LS EF FF 168 TF LF 169 April 13, 2015 Resource Allocation and Resource Leveling 170 April 13, 2015 CATEGORIES OF RESOURCES Labor Materials Equipment’s. 171 Labor April 13, 2015 1. Salaried staff: like-project engineer, secretary. 2. Hourly workers: like-carpenters. Equipment and Materials 1. Construction equipment and materials 2. Installed equipment and materials 172 April 13, 2015 What is resource allocation? Resource allocation(resource loading) : Is the assignment of the required resources to each activity, in the required amount and timing. What Is Resource Leveling? Is minimizing the fluctuations in day-to-day resource use throughout the project. It is usually done by shifting noncritical activities within their available float. It attempts to make the daily use of a certain resource as uniform as possible. 173 April 13, 2015 Why level Resources? 1. When the contractor adds the daily total demand for a specific resource for all activities he must provide the required amount, or work will be delayed. 2. Leveling may also be necessary for an expensive piece of equipment. 3. The main idea of resource leveling is to improve work efficiency and minimize cost during the life of the project. Note: In general, materials do not need to be leveled 174 April 13, 2015 Leveling Resources in a Project oResource leveling is a mathematically complex process. oThe resource-leveling method is called the minimum moment algorithm. o discussed by Robert B. Harris (1978) in his classic textbook, Precedence and Arrow Networking Techniques for Construction 175 Resource need Resource Profiles April 13, 2015 Actual, not leveled Leveled, realistic Ideal Time 176 Sort April 13, 2015 Sort : the process of arranging activities in a list to certain specific order. 177 Priorities & Sorts April 13, 2015 The activities making up the network must be listed in order of their priority of resources allocation. The network shows the logical sequence of activities. (predecessor and successor). The listing of activities must therefore reflects the dependency of some activities . 178 April 13, 2015 Activities Sort Activity Duration ES TF Resource unit A 1 1 0 8H B 9 2 0 9H C 5 2 3 7H D 5 11 0 5H E 4 7 3 4H F 4 16 0 8H G 6 11 3 2H H 1 20 0 4H Activity sort reflects the logic sequence of the network. 179 April 13, 2015 Major Sort Activity Duration ES TF Resource unit A 1 1 0 8H B 9 2 0 9H C 5 2 3 7H E 4 7 3 4H G 6 11 3 2H D 5 11 0 5H F 4 16 0 8H H 1 20 0 4H Activity sort with ES time as Major sort 180 April 13, 2015 Major & Minor Sorts Activity Duration ES TF Resource unit A 1 1 0 8H B 9 2 0 9H C 5 2 3 7H E 4 7 3 4H D 5 11 0 5H G 6 11 3 2H F 4 16 0 8H H 1 20 0 4H Activity sort with ES time as Major sort & TF as Minor Sort 181 Allocated resources April 13, 2015 8H A 9H 9H 9H 9H 9H 9H 9H 9H 9H Activity B 7H 7H 7H 7H 7H C 4H 4H 4H 4H E 5H 5H 5H 5H 5H D 2H 2H 2H 2H 2H 2H G 8H 8H 8H 8H F 4H H 2 4 6 8 10 Time 12 14 16 18 20 182 2 4 6 8 Time 10 12 14 April 13, 2015 16 18 20 8H A 9H 9H 9H 9H 9H 9H 9H 9H 9H B 7H 7H 7H 7H 7H Activity C 4H 4H 4H 4H E 5H 5H 5H 5H 5H D G 2H 2H 2H 2H 2H 2H 8H 8H 8H 8H F 4H H Total Labor 8 16 16 16 16 16 1313 13 13 7 7 7 7 7 10 8 Early start resources aggregation 8 8 4 183 Resource Aggregation April 13, 2015 Resources aggregation: is a summation of the resources that are used to carry out the program on a time period basis. For example, day to day , or week to week. 184 April 13, 2015 Total Labor 8 16 16 16 16 16 1313 13 13 7 7 7 7 7 10 8 8 8 4 Labor 16 14 12 10 8 6 4 2 2 4 6 12 8 10 14 16 18 20 184 Early start resources aggregation diagram (Histogram) Time 185 Late start April 13, 2015 Another histogram can be obtained if Late start considered. Shows different resources demand. And many histograms can be obtained considering a different time in the network. Each histogram shows different resources demand. 186 April 13, 2015 late Start Sorts Activity Duration LS TF Resource unit A 1 1 0 8H B 9 2 0 9H C 5 5 3 7H E 4 10 3 4H D 5 11 0 5H G 6 14 3 2H F 4 16 0 8H H 1 20 0 4H Activity sort with LS time as Major sort & TF as Minor Sort 187 Time 2 4 6 8 April 13, 2015 12 10 14 16 18 20 8H A 9H 9H 9H 9H 9H 9H 9H 9H 9H B 7H 7H 7H 7H 7H Activity C 4H 4H 4H 4H E 5H 5H 5H 5H 5H D 2H 2H 2H 2H 2H 2H G 8H 8H 8H 8H F 4H H Total Labor 8 9 9 9 16 16 1616 16 13 9 9 9 7 7 10 10 10 10 4 Late start resources aggregation 188 April 13, 2015 Total Labor 8 9 9 9 16 16 1616 16 13 9 9 9 7 7 10 10 10 10 4 Labor 16 14 12 10 8 6 4 2 2 4 6 8 10 12 14 16 18 Late start resources aggregation diagram (Histogram) 20 Time 189 April 13, 2015 Total Labor 8 9 9 9 16 16 1616 16 13 9 9 9 7 7 10 10 10 10 4 Labor 16 14 12 10 8 6 4 2 2 4 6 8 10 12 14 16 18 20 Time 189 Early start vs Late start resources aggregation diagram (Histogram) 190 April 13, 2015 Total Labor 8 9 9 9 16 16 1616 16 13 9 9 9 7 7 10 10 10 10 4 Labor 16 14 12 10 8 6 4 2 2 4 6 8 10 12 14 16 18 20 190Time Early start vs Late start resources aggregation diagram (Histogram) 191 E Example 10 5 6 0 0 F 13 10 0 6 16 13 0 6 19 16 C G 4 5 12 1 6 6 11 0 0 11 6 11 I 17 A 1 April 13, 2015 16 16 6 6 22 B 6 6 11 2 3 2 22 14 0 0 14 12 14 8 14 22 0 0 22 H 8 6 16 14 8 8 22 2 22 24 0 0 24 J Dur. LS EF FF TF LF 6 6 22 11 8 0 6 14 ES 19 K D 6 3 192 Activities Sort April 13, 2015 Activity Duration ES TF Resource unit A 5 1 0 8H C 5 6 0 2H D 2 6 6 4H B 4 6 6 9H H 6 8 8 5H E 6 10 6 5H G 3 11 0 2H F 2 11 6 8H I 3 13 6 5H J 8 14 0 2H K 2 22 0 6H Activity sort with ES time as Major sort & TF and duration as Minor Sorts 2 4 6 8 Time 10 12 14 16 18 April 13, 2015 A 8H 8H 8H 8H 8H C 2H 2H 2H 2H 2H D 4H 4H B 9H 9H 9H 9H 9H 9H 9H H 5H 5H 5H E 5H 5H 5H 5H 5H 5H 5H 5H 5H G 2H 2H 2H F 8H 8H I 5H 5H 5H J 2H 2H 2H 2H 2H 2H 2H 2H 6H 6H K Total Labor 20 193 22 24 8 8 8 8 8 15 1516 16 12 20 20 17 12 12 2 2 Early start resources aggregation 2 2 2 2 6 6 Total Labor 8 8 8 8 8 15 1516 16 12 20 20 17 12 12 2 2 2 2 2 2 61946 April 13, 2015 20 18 Labor 16 14 12 10 8 6 4 2 2 4 6 8 10 12 Time 14 16 18 20 22 24 Early start resources aggregation diagram 195 Activities Sort April 13, 2015 Activity Duration LS TF Resource unit A 5 1 0 8H C 5 6 0 2H D 2 12 6 4H B 4 12 6 9H E 6 16 6 5H H 6 16 8 5H G 3 11 0 2H F 2 17 6 8H I 3 19 6 5H J 8 14 0 2H K 2 22 0 6H Activity sort with LS time as Major sort & TF and duration as Minor Sorts 2 4 6 8 Time 10 12 14 16 18 April 13, 2015 A 20 196 22 24 8H 8H 8H 8H 8H C 2H 2H 2H 2H 2H D 4H 4H B 9H 9H 9H 9H E 5H 5H 5H 5H 5H 5H H 5H 5H 5H 5H 5H 5H G 2H 2H 2H F 8H 8H I 5H 5H 5H J 2H 2H 2H 2H 2H 2H 2H 2H 6H 6H K Total Labor 8 8 8 8 8 2 2 2 2 2 2 15 15 11 11 12 20 2017 17 17 6 Late start resources aggregation 6 Total Labor 8 8 8 8 8 2 2 2 2 2 2 15 15 11 11 12 20 20 17 17 17 61976 April 13, 2015 20 18 Labor 16 14 12 10 8 6 4 2 2 4 6 8 10 Time 12 14 16 18 20 22 24 Late start resources aggregation diagram 198 April 13, 2015 Early start Labor 20 18 16 14 12 10 8 6 4 2 Labor 20 18 16 14 12 10 8 6 4 2 Late start 199 Smoothing/Leveling April 13, 2015 Let us program activity F to start by its late start day which is day 17. And activity I to start by day 14. The resulting resources aggregation histogram will be as follows: 2 4 6 8 Time 10 12 14 16 18 April 13, 2015 A 20 200 22 24 8H 8H 8H 8H 8H C 2H 2H 2H 2H 2H D 4H 4H B 9H 9H 9H 9H 9H 9H 9H H 5H 5H 5H E 5H 5H 5H 5H 5H 5H 5H 5H 5H G 2H 2H 2H F 8H 8H I 5H 5H 5H J 2H 2H 2H 2H 2H 2H 2H 2H 6H 6H K Total Labor 8 8 8 8 8 15 1516 16 12 12 12 12 12 12 7 10 10 2 2 2 6 Early start resources aggregation 6 201 Total Labor 8 8 8 8 8 15 15 16 16 12 12 12 12 12 12 7 10 10 2 2 2 6 April 13, 2015 20 18 Labor 16 14 12 10 8 6 4 2 2 4 6 8 10 12 Time 14 16 18 20 22 24 6 202 Smoothing/Leveling April 13, 2015 Let us program activity H to start by its late start time. So its resources demand starts with its Late start date. The resulting resource aggregation and histogram will be as follows: 203 2 A 4 6 8 Time 10 12 14 16 April 13, 2015 20 22 24 8H 8H 8H 8H 8H C 2H 2H 2H 2H 2H D 4H 4H B 9H 9H 9H 9H 9H 9H 9H H 5H 5H 5H 5H 5H 5H E 5H 5H 5H 5H 5H 5H G 2H 2H 2H F 8H 8H I 5H 5H 5H J 2H 2H 2H 2H 2H 2H 2H 2H 6H 6H K Total Labor 18 8 8 8 8 8 15 1516 16 7 15 15 12 7 7 7 7 7 7 7 7 6 6 204 Total Labor 8 8 8 8 2 4 8 15 15 16 16 7 15 15 12 7 7 7 7 7 7 7 7 6 April 13, 2015 6 20 18 Labor 16 14 12 10 8 6 4 2 6 8 10 12 Time 14 16 18 20 22 24 205 Smoothing/Leveling April 13, 2015 In case activity D is split able activity. It could be interrupted to be carried out in tow parts. Let us program activity B to start by 7th day . And activity H to starts by its Late start date. And activity E to start by day 14. The resulting resource aggregation and histogram will be as follows: 2 A 4 6 8 Time 10 206 12 14 16 18 April 13, 2015 20 24 8H 8H 8H 8H 8H C 2H 2H 2H 2H 2H D 4H B 4H 9H 9H 9H 9H H 5H 5H 5H E 5H 5H 5H 5H 5H 5H 5H 5H 5H G 2H 2H 2H F 8H 8H I 5H 5H 5H J 2H 2H 2H 2H 2H 2H 2H 2H 6H 6H K Total Labor 22 8 8 8 8 8 6 11 11 11 11 10 10 11 12 12 12 12 12 12 7 7 Early start resources aggregation 6 6 207 Total Labor 8 8 8 8 8 6 11 11 11 11 10 10 11 12 12 12 12 12 12 7 7 April 13, 2015 6 20 18 Labor 16 14 12 10 8 6 4 2 2 4 6 8 10 12 Time 14 16 18 20 22 24 208 Early Start OR Early Finish April 13, 2015 There are many solutions between the limits of Early Start and Early Finish. The optimal solution is zero fluctuation histogram. Which is hard to be achieved. It is preferred to solve the problem toward the Early start resources aggregation diagram. WHY ?! 209 April 13, 2015 Because if there are labor availability problems to be overcome, they will occur in the early beginning of the project. By other words, if the program based on the Late Start date, it means that all the activities are Critical, and any labor problem will affect the project completion. 210 April 13, 2015 Allocation within resources restraints Another situation which you may face in practice is the restricted resources availability. Where you have to carry out the job with the available resources only. In this case the project duration may be prolonged to suit the availability of the restricted resources. 211 April 13, 2015 Rules for scheduling activities with limited resources 1) schedule activities to start as soon as their predecessors have been completed. 2) if more than one activity using a specific limited resources can be scheduled, priority is given to the activity with early Late Start. ( LS as Major Sort) 3) if tow or more activities have the same Late start, give priority to the activity with least Total Float. (TF as Minor Sort) 4) if the activities have the same Total Float in the minor sort, give the priority to the activity with the Largest Number of Resources. 5) If the activities are tied in the number of resources, give priority to the activity that has already started. 212 Example April 13, 2015 A 1 2 1 0 0 B 1 2 2 11 8H 9 0 Activity desc. ES Dur. LS EF FF TF LF Resources 2 0 11 11 5 16 0 F 11 0 16 16 4 20 0 5H 8H C E G 5 7 3 10 11 5 0 7H 4 0 10 3 14 4H 11 H 16 0 20 9H 2 7 D 6 17 3 2H 20 1 21 0 4H 14 3 20 20 0 21 213 April 13, 2015 Activity Duration ES TF Resource unit A 1 1 0 8H B 9 2 0 9H C 5 2 3 7H E 4 7 3 4H D 5 11 0 5H G 6 11 3 2H F 4 16 0 8H H 1 20 0 4H Activity sort with ES time as Major sort & TF as Minor Sort 214 April 13, 2015 Assume that the available labors in the company restricted to 10 helpers, and the company decided to carry out the job without resorting to hire more labor. The resulting program will exceed the Early finish date based on the network. 215 April 13, 2015 Total Labor 8 16 16 16 16 16 1313 13 13 7 7 7 7 7 10 8 8 8 4 Labor 16 14 12 10 8 6 4 2 2 4 6 12 8 10 14 16 18 20 215 Early start resources aggregation diagram (Histogram) Time Activity 2 A B C E D G F H Total Labor 4 6 8 Time 10 12 14 16 18 20 22 24 26 April 13, 2015 8H 9H 9H 9H 9H 9H 9H 9H 9H 9H 7H 7H 7H 7H 4H 4H 4H 4H 5H 5H 5H 5H 5H 2H 2H 2H 2H 2H 2H 8H 8H 8H 4H 8 9 9 9 9 9 9 9 9 9 7 7 7 7 9 9 9 9 7 10 10 10 2 2 4 12 Labor Limit 10 Labor 216 8 6 4 2 Time Resources aggregation diagram 217 Money and network schedules April 13, 2015 Reminder, cost was one of the elements of project constraints triangle ( COST, TIME & QUALITY). An effective management tries to minimize and integrate the above mentioned elements. CPM provides a mean for relating time and money. The application of resources to a project (materials, manpower and machinery) related to another resource which is MONEY. The value of the resources for each activity represents a component of project cost. 218 Hint Construction costs includes: 1) Materials costs. 2) labor costs. 3) plant and equipment costs 4) overhead costs and profit. April 13, 2015 219 E Example 10 5 6 0 0 F 13 10 0 6 16 13 0 6 19 16 C G 4 5 12 1 6 6 11 0 0 11 6 11 I 17 A 1 April 13, 2015 16 16 6 6 22 B 6 6 11 2 3 2 22 14 0 0 14 12 14 8 14 22 0 0 22 H 8 6 16 14 8 8 22 2 22 24 0 0 24 J Dur. LS EF FF TF LF 6 6 22 11 8 0 6 14 ES 19 K D 6 3 220 April 13, 2015 Activity Duration ES TF Cost ($( A 5 1 0 650 C 5 6 0 1300 D 2 6 6 400 B 4 6 6 1450 H 6 8 8 500 E 6 10 6 1100 G 3 11 0 600 F 2 11 6 350 I 3 13 6 1000 J 8 14 0 1300 K 2 22 0 200 221 2 A C 4 6 8 Time 12 10 B 100 250 9H 9H 300 9H 100 9H F 150 100 K Total cost 22 24 200 200 100 150 100 150 200 200 200 J 20 50 100 150 200 50 50 G I 18 April 13, 2015 150 100 200 200 150 200 200 E 16 200 100 200 100 50 D H 14 200 100100 100 100 150 200 100100 150 100 100 100 200 100 200 100 50 350 550550 400 500 750 450 600 300 350 150 200 100100150 100 100 100 222 Total cost 200 100 200 100 50 350 550550 400 500 750 450 600 300 350 150 200 100100 150 100 100 100 April 13, 2015 800 700 600 500 400 300 200 100 2 4 6 8 10 Time 12 14 16 18 20 22 24 223 Cash Flow April 13, 2015 It is quite significant to the contractor to know the amount of money that would be spent in each stage of the project.( Expenditures) And compare it to the amount of money that would be received. (income) Overtrading Overtrading: arises when the current liabilities of a company exceed the current assets, even though the business is solvent. 224 Total cost Com. cost 200 100 200 100 50 350 550550 400 500 750 450 600 300 350 150 200 100100 150 100 100 100 April 13, 2015 200 300 500 600 650 1000 1550 2100 2500 30003750 4200 4800 51005450 5600 580059006000 6150 6250 63506450 $ 6400 6000 5600 5200 4800 4400 4000 3600 3200 2800 2400 2000 1600 1200 800 400 2 4 Com. cost = Cumulative Cost 6 8 10 Time 12 14 16 22 24 18 20 Cash Flow Diagram 225 April 13, 2015 Retainage Release Expenditures Revenues Cumulative Expenditure s & Revenues Amount of Negative Cash Flow Time (Months) Cash Flow Curve for revenue and expenditures 226 Cash Flow Example April 13, 2015 $ $$$ early $$ planned $ late Time 227 Cash Flow: In and Out $ April 13, 2015 Profit Spending Reimbursement Time 228 Cash Flow Analysis April 13, 2015 Cash flow analysis consists of a detailed examination of funds disbursement (expenditures) and the receipt of revenue. Cash flow shows if surplus fund available during project, or if negative cash position will occur during construction. The cash position of contractor during project whether positive or negative is important. 229 Negative cash position April 13, 2015 Negative cash position means that the revenues obtained from a project insufficient to meet the financial obligations (expenditures) of the project. In this case other fund from the company or from outside sources must be used. 230 Positive cash position April 13, 2015 Positive cash position means that the revenues obtained from a project exceed the financial obligations (expenditures) of the project. In this case surplus (extra) fund available with the contractor. And the contractor may invest this surplus funds for short duration. 231 Materials Management April 13, 2015 Is defined as the planning and controlling of all necessary efforts to ensure that the correct quality and quantity of materials and equipment are appropriately specified in a timely manner, are obtained at a reasonable cost, and are available when needed. 232 Materials management functions April 13, 2015 Identifying. Acquiring. Distributing. Disposing. 233 Objectives of materials management April 13, 2015 Ensure that materials meet the specifications and are on hand when and where required. Obtain the best value for purchased materials. Provide efficient, low-cost transport, security, and storage of materials at construction sites. Reduce any surplus to the lowest level possible. 234 Schedule Updating and Project Control April 13, 2015 235 Schedule updating April 13, 2015 Schedule updating is just one part of the project control process. Schedule updating must reflect Actual work , and involves change orders (CO) . 236 What is an updated schedule? April 13, 2015 A revised schedule reflecting project information at a given data date regarding completed activities , in progress activities , and change in the logic , cost , and resources and allocated at any level . What is data date? The data date is the date as of which all progress on a project is reported. It is also called as- of date and status date . 237 Why Update Schedules? April 13, 2015 Schedules (like cost estimates) are always prepared before the project begins. However, updates must take place routinely for the following two reasons: a. Unintentional events b. Intentional changes Schedules without updating, monitoring, controlling, and corrective action are useless 238 What kind of information is needed for updating schedules ? April 13, 2015 1. Past information : what has happened since the last update ?. 2. Future information : the future category comprises any changes to schedule or schedule items. Future changes are two types : A. logic – driven changes B. user’s changes 239 Frequency of updating April 13, 2015 Construction schedules may be updated monthly , biweekly, weekly, or according to another time interval . Project managers must achieve a delicate balance between updates is too long and one is too short 240 Updating schedules and pay requests April 13, 2015 In many cases , project updating is tied to payment requests. In general , a pay requests is a document submitted by the contractor to the owner , asking for payment for work actually performed (whether .finished or not)during the period since the last pay request. 241 Effect of adding or deleting activities on logic April 13, 2015 An activity in a schedule is usually like a link in a chain ; removing a link may disturb the whole chain if it is not done properly. For example : Deleting activity AS520 in the partial network shown in figure will remove any link between activities in each side. AS210 TL160 AS250 AS245 AS260 242 April 13, 2015 It is strongly recommended that the scheduler review the logic before making any change by first printing a logic report showing all predecessors .and successors for the activity be deleted. 243 Steps for Updating a Schedule 1. April 13, 2015 The Schedule activity list • Filter out completed activities • Eliminating activities in the far future? • Scheduler sends it to the project PM / superintendent • Possibility that PM/superintendent wants to change past events 244 Example 1: No Cost April 13, 2015 245 Example 2: With Cost April 13, 2015 246 April 13, 2015 2. The PM (or superintendent) fills up the form, signs and dates it; and submits it back to the scheduler It is a good idea for the PM to keep a copy for his/her records It is a good idea to assign “ink colors” to different parties 3. The scheduler enters the info in the computer and updates the project, signs and dates the forms 247 April 13, 2015 4. The scheduler prints a preliminary report and discusses it with the PM It is a good idea to produce a summary report (what happened between last update and this update) Based on this discussion, the scheduler makes any necessary adjustments to the schedule or reports Any changes to the schedule requested by the PM have to be documented by the scheduler 248 Myths/Misconceptions About Schedule Updating April 13, 2015 We always produce a complete schedule before the commencement of construction. We just don’t update it, We trust our field staff and subcontractors to follow it. We update projects only when there is a “need” for the update Everything is going well. There is no need for an update 249 Quiz 6 April 13, 2015 True or False: 1. Updating is needed for projects that have duration of at least one year or a minimum budget of QAR 10 million 2. Data date is the date all information was entered in the computer 3. In updating schedules, we must enter not only actual work progress but also any future changes 4. Negative float is an indication that the schedule is not meeting its expected completion date or an interim imposed date 250 April 13, 2015 Project Control 251 Project Control April 13, 2015 Project control is the continuous practice of 1. monitoring work progress, 2. comparing it to baseline budget and schedule, 3. detecting any deviations and their causes, and 4. taking a corrective action wherever and whenever necessary The ability to determine a project status as it relates to the time and schedule selected Also called project tracking Project monitoring? 252 Why Project Control? April 13, 2015 Project control is needed because projects never run exactly as planned. Project control is a cyclical iterative task: do small part of the work and compare to baseline, do corrective measure, adjust plan (if needed), do another part of the work, and so on.. Project control requires measuring work progress and calculating activities percent complete 253 What is a baseline schedule? April 13, 2015 A baseline schedule is a schedule prepared by the contractor ,usually before the start of the project ,and used for performance comparison. Baseline Budget: The project’s original approved budget including any approved changes 254 Percent Complete April 13, 2015 Percent Complete (PC or PCT): is an estimate, expressed as a percent, of the amount of work that has been completed on an activity or a work breakdown structure component. (PMBOK 2008) Percent complete may be used to estimate: Activity Groups of activities / assembly / work package Project 255 Types of Percent Complete April 13, 2015 Depending on the type and nature of the activity, percent complete may be calculated using one of several methods that may yield different results Some methods are more subjective than others None of these methods is wrong. None of them is uniquely considered the right method. Most importantly: Know exactly what each percent complete means Pick one or two parameters to use and then be consistent 256 April 13, 2015 Major objectives for a good control plan: 1. Should accurately represent the work. 2. Permit deviations to be detected, evaluated and forecasted. 3. Should make provision for periodic corrective actions. 257 Level of Control April 13, 2015 Small projects - low cost - short duration Detailed network Reporting mechanism Middle-sized projects (300 activities) Detailed network Summary network Area and craft network 258 Monitoring the Project April 13, 2015 1. Feedback from direct contact Efficient but requires close cooperation between the manager and field personnel. 2. Feedback from photography Record progress and provide permanent documentation of the work. Tell nothing about the time taken to perform the work. 3. Feedback from check-off list Planner prepares a check-off list that is started, to be continued, or to be finished in the next time interval. Effective if the reporting periods are short “Daily, Weekly” and small number of activities involved. Disadvantage: false reporting 259 April 13, 2015 4.Feedback from bar chart. 5.Feedback from networks Advantage: Superintendent has complete information about the status of the project. Disadvantage: Diagram may appear confusing to field personnel. 260 Setting the Target Schedule April 13, 2015 Early Start Schedule: As Target for Control Problem: Required high effort to keep the plan working. Late Start Schedule As Target for Control Problem: Because every activity is timed to start as its latest, project overruns are sure to follow. Activities may be positioned early or late start or somewhat in between. Non-critical activities allow intermediate start. 261 Anticipated target S-Curve April 13, 2015 262 The S-Curve field April 13, 2015 263 April 13, 2015 Sample Project Cost Data 264 April 13, 2015 Early Start Tree 265 Late Start Tree April 13, 2015 266 Target Network April 13, 2015 267 Project S-Curve April 13, 2015 268 Actual Versus Target S-Curves April 13, 2015 269 April 13, 2015 Earned Value Analysis 270 Earned Value Analysis April 13, 2015 Earned Value (EV) Analysis: Earned Value analysis is an integrated cost-schedule approach to monitor and analyze the progress in a project. Earned Value Management (EVM), started in the 1960’s as a method for integrated project cost and schedule control, was designed by the U.S. Air Force and named the Cost/Schedule Planning and Control System. In 1967, it became U.S. DOD policy and was renamed Cost/ Schedule Control Systems Criteria, or C/SCSC 271 The Concept of EVM April 13, 2015 The concept of Earned Value is simple; at any given point find out: 1. The cost of work you have actually done (ACWP), 2. The cost of work you planned to do by this date (BCWS), 3. The amount earned for work performed (BCWP), 4. Calculate schedule and budget variances (SV, CV) 5. Analyze causes for major variances and suggest remedies, 6. Extrapolate these variances to the end of the project (FSV, FCV). 272 Foundations of modern cost control April 13, 2015 What’s more important? • Knowing where you are on schedule? • Knowing where you are on budget? • Knowing where you are on work accomplished? Earned Value Analysis (EVA) addresses all three: • It compares the PLANNED amount of work with what has actually been COMPLETED to determine if COST, SCHEDULE, and WORK ACCOMPLISHED are progressing as planned. 273 EVA Terminology April 13, 2015 BCWS – Budgeted Cost of Work Scheduled Planned cost of the total amount of work scheduled to be performed by the milestone date. (a.k.a. your original plan) BCWP – Budgeted Cost of Work Performed The planned (not actual) cost to complete the work that has been done. Also known as “Earned Value” ACWP – Actual Cost of Work Performed Cost incurred to accomplish the work that has been done to date. 274 Input data for EVA April 13, 2015 Activity schedule, usually in the form of a bar chart. Budgeted cost for each activity. Percent complete for each activity. Cost to date for each activity. 275 Information Needed to Compute April 13, 2015 Budgeted Cost of Work Scheduled (BCWS) Activity budget at completion (BAC) Activity schedule Data date Budgeted Cost of Work Performed (BCWP) Activity budget at completion (BAC) Physical activity progress as a percentage of its total work Actual Cost of Work Performed (ACWP) Each activity’s cost to date from the job costing system 276 Earned Value Reporting - Costs April 13, 2015 Budgeted Cost of Work Performed (BCWP) = earned value of project Actual Cost of Work Performed (ACWP) Cost Variance (CV) Difference between earned and actual costs for the completed work Cost Performance Index (CPI or CI) CV BCWP ACWP BCWP CPI ACWP CPI = 1, on budget CPI < 1, over budget CPI > 1, under budget 277 April 13, 2015 Earned Value Reporting - Schedule Budgeted Cost of Work Performed (BCWP) Budgeted Cost of Work Scheduled (BCWS) Schedule Variance (SV) Difference between the value of work that was planned for completion and the value of the work that was actually completed Schedule Performance Index (SPI or SI) SV BCWP BCWS BCWP SPI BCWS SPI = 1, on schedule SPI < 1, behind schedule SPI > 1, ahead of schedule 278 Earned Value Reporting April 13, 2015 (budgeted) (earned) (actual) Nabil Dmaidi 278 279 April 13, 2015 Example A simple problem will help to illustrate the application of the principles of earned value . A project has been defined that consist of 12 activities for which the estimated cost and duration have been defined see figure . After three and a half month , the activates 1,2,4,5,7 are completed and (6) is one half complete and(8) is three –fourth complete and (3) is half complete. The incurred cost to date are 152000$ . What is the status of this project in terms of the schedule and the budget? Solution 280 April 13, 2015 Activity cost 1 $22000 2 $10000 3 $18000 4 $30000 5 $50000 6 $40000 7 $6000 8 $16000 9 $13000 10 $4000 11 $34000 12 $14000 m1 m2 m3 m4 m5 m6 281 April 13, 2015 Solution ACWP =152000$ BCWS=22000+30000+50000+10000+18000+0.5(40000+ 6000+16000)=161000$ BCWP=22000+30000+50000+10000+6000+0,5(40000) +0.75(16000)+0.5(18000)= 159000$ SV= BCWP-BCWS= -2000$ its behind schedule CV=BCWP-ACWP= 7000$ below the budget EAC=ACWP+(BAC-BCWP)=152000+(257000-159000) = 250000$ 282 Earned Value: Cost and Time Status April 13, 2015 $ + II I - + Time III IV - 283 EVA: The Curve April 13, 2015 284 Quiz 7 April 13, 2015 True or false: 1. Project control is to be practiced by both contractor and owner 2. Project monitoring is part of project control 3. For assistance in calculating progress payments, percent 4. complete for the project is more important than percent complete of individual activities 5. It is possible that different parties compute the “project percent complete” and come up with different estimates, yet none of them is wrong! 6. It is possible to have the scheduler report saying the project is behind schedule while the earned value analysis is showing a positive schedule variance. 285 April 13, 2015 Time-Cost Trade-Off Some amount of knowledge brings more…… 286 Time /cost trade –off analysis April 13, 2015 Time /cost trade –off analysis is the compression of the project schedule to achieve a more favorable outcome in term of project duration , cost , and projected revenues Objective of time /cost trade-off -compress project to an acceptable duration -minimize total project costs Done by selectively crashing specific activities to shorten project duration 287 Time /cost trade –off analysis April 13, 2015 You might think that total project costs will increase when we begin to crash activities But ,total project cost consist of both indirect (project –based ) costs (PBC) and activity – based cost (ABC ) -ABC goes up when we crash activities in an effort to finish the project early -but ,PBC (the indirect cost ) goes down if we finish the project early 288 What Is ‘‘Accelerating’’ a Project? April 13, 2015 Accelerating a project means shortening the normal duration of the project schedule . (also called schedule compression). schedule crashing Schedule acceleration 289 Why Accelerate a Project? April 13, 2015 1. The contractor’s ‘‘normal’’ finish date in the planned schedule does not meet the imposed finish date of the contract. 2. After starting construction and completing a certain percentage of the project, the contractor realizes that the project is behind schedule. 3 -when the contractor may have a contractual monetary incentive to finish ahead of schedule. 4- Sometimes, especially when the economy is doing well, finishing early means—to the contractor—starting another job earlier and, thus, making more profit. 290 Schedule Compression: Multiple Paths April 13, 2015 Path 1 Path 2 Path 3 Path 4 Path 5 Path 6 Path 7 Path 8 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 291 Cost Changing with Schedule Acceleration April 13, 2015 Cost $ Direct Cost Total Cost Indirect Cost 292 Cost April 13, 2015 For the following discussions it is important to remember: Direct costs: Related to putting the facility components in place. They represent the resources used by an activity. (material, labor and equipment). 293 April 13, 2015 Indirect job costs (job overhead): costs that could not be attributed to a specific work item. (such as, site offices, superintendents, security fence & etc.) These costs are generally incurred whether or not productive work achieved. Longer project duration will result in higher indirect costs. 294 April 13, 2015 Operating Overhead costs (company overhead): If the cost cannot be attributed to any specific job, they are operating overhead costs, costs of running business. (head office costs, communications & etc). These costs continue as long as the company exists even one project is running. 295 Logic of Time-Cost Trade-Off April 13, 2015 Assumption: increasing or decreasing an activity’s duration will lead to increased direct costs for that activity. 296 April 13, 2015 Direct Costs Direct costs Project duration General relation of direct costs to project duration 297 April 13, 2015 Assumption: decreasing a project’s duration will lead to lower indirect costs. Indirect Costs indirect costs Project duration General relation of indirect costs to project duration 298 April 13, 2015 Assumption: A project’s duration can be decreased by decreasing the duration of one or more critical activities on the critical path. Assumption: Decreasing a project’s duration may increase or decrease the total cost of a project depending upon whether the additional direct costs required to decrease the activity duration are greater or less than indirect costs savings of decreasing the project’s duration. 299 April 13, 2015 Total project costs Project Costs Direct costs indirect costs Project duration General relation of project costs to project duration 300 Graph analysis April 13, 2015 A project’s total costs combines direct costs and indirect costs. Therefore, the curve of total costs versus duration involves adding the cost amounts of direct and indirect costs curves. Remember, the direct costs curve has a negative slope (direct costs increase as duration decrease) and indirect costs curve has a positive slope (indirect costs decrease as duration decreases). So, the slope of the total costs curves at any point depends whether the slope of direct costs curve less than that of indirect cost curve. 301 How does accelerating a project work April 13, 2015 The duration of the project is equal to the duration of the critical path .Thus to shorten the duration of the entire project ,shorten the duration of the critical path. The cost will vary depending upon which activity duration decreased. Usually, select the activity with least shortening costs. (lowest additional cost per day of shortening) to minimize the additional costs of shortening 302 Reducing Project Duration April 13, 2015 - As the critical path of the network decreased, some non-critical activities lose some amount of their total float. A B C D F 303 April 13, 2015 -Thus, the extent to which an activity can be shortened and still has the effect of shortening the project is limited by the amount of total float exists in the parallel activities. A B C D F 304 April 13, 2015 -As the projects duration decreases, the number of critical paths through the network increases. A B C D F 305 April 13, 2015 -If more than one critical path exist, it is necessary to reduce all critical paths in the network simultaneously, which becomes expensive. A B C D F 306 Four Different Solutions for Each Network April 13, 2015 The schedule can be viewed in several different ways in order to satisfy the client. A client may with to perform the project in the lease cost, or in the least time. Or in any manner satisfies him. 1) All Normal: the original network and activity duration result in all normal solution, based on each activity being performed in its “NORMAL” least cost manner. Remember, it is not necessarily the least cost or least time solution to schedule a project. 307 April 13, 2015 2) Least Cost: considering both direct and indirect costs, it may be possible to find a project duration that minimizes these total costs. By paying more to decrease one or more critical activity (direct cost) and save greater indirect costs. (Means that the result will be total cost saving.) 308 April 13, 2015 Total project costs Project Costs Direct costs indirect costs Project duration General relation of project costs to project duration 309 April 13, 2015 3) Least Time: A project can be shortened beyond its least cost duration. Until a point reached where no activities in the critical path can be physically shortened regardless of how many resources are applied. (results in higher costs) 4) All crash: in this solution, every activity has been shortened as much as physically possible. Its duration the same as the least time solution, but its costs greater. Because the direct cost increases without further reductions in the indirect costs. A fully crashed schedule occurs when all activities shortened to their shortest possible duration 310 April 13, 2015 All crash It is not an efficient approach since some non-critical activities will be shortened without having any shortening influence on the project duration. 311 Logically reducing Project Duration April 13, 2015 The logical approach is to shorten those activities that contribute to reduce the project duration. To begin the time-cost trade-off in a rational manner, basic calculations needed. First compute the early start and early finish times for each activity 312 Example April 13, 2015 Reducing Project Duration to shortest possible duration B E 2 7 2 9 0 0 9 0 0 9 13 16 12 4 4 16 23 3 1 1 2 2 0 0 2 8 6 F 3 1 1 9 1 9 16 7 0 0 16 J 16 18 5 21 2 2 5 3 9 0 7 12 5 13 8 3 7 20 3 16 3 19 4 4 20 23 5 23 28 0 0 28 2 23 K 12 23 4 G 0 L 2 0 D EF FF TF LF 0 9 0 Dur. LS 0 23 0 0 C 0 1 ES 16 7 0 0 A H 4 313 April 13, 2015 By computing the link lag values between activities. (Lag = ESB – EFA). It is logical that there is at least one path between the first activity and last activity where lag values are 0. These activities forming the critical path. (other solution can be derived by computing TF). In the previous network. Activity A,B,F,H and L forming the critical path. 314 April 13, 2015 To shorten the project’s duration it is essential to shorten on of the critical activities. A or B or F or H or L. Without shortening the project will end after 28 days with a cost of 5300 $. This is the normal duration cost. And any decrease in duration will increase the direct cost. The following table shows information about activities. 315 April 13, 2015 Activity Cost / day Normal Duration Crash Duration Normal Cost Crash Cost Days to shorten A - 1 1 800 800 0 B 200 7 4 1000 1600 3 C 100 6 4 300 500 2 D 400 3 2 400 800 1 E 50 3 1 100 200 2 F 150 7 5 500 800 2 G 300 8 4 200 1400 4 H 250 7 6 350 600 1 J 75 5 3 700 850 2 K 500 3 2 500 1000 1 L 350 5 4 450 800 1 316 Identifying activities for 1st compression cycle April 13, 2015 Activity A B F H L Cost/day - 200$ 150$ 250$ 350$ F : Least cost activity to shorten 317 April 13, 2015 From the previous table, it can be noticed that activity F has the least incremental shortening cost. ( 150 $ per day). E.g. Shortening F for 2 days costs 150 x 2 = 300 $. Bear in mind, activities for shortening selected based on cost per day. Not on cycle cost basis. 318 April 13, 2015 How many days activity F could be shortened? The answer in computing the Network Interaction Limit (NIL). So, reducing activity F by 2 days will affect the link lag values of the succeeding activities and TF of parallel activities 319 April 13, 2015 B E 2 7 2 9 0 0 9 0 0 9 13 16 12 4 4 16 23 3 1 1 2 2 0 0 2 8 6 F 3 1 1 9 1 9 16 7 0 0 16 J 16 18 5 21 2 2 5 3 9 0 7 12 5 13 8 3 7 20 3 16 3 19 4 4 20 23 5 23 28 0 0 28 2 23 K 12 23 4 G 0 L 2 0 D EF FF TF LF 0 9 0 Dur. LS 0 23 0 0 C 0 1 ES 16 7 0 0 A H 4 320 April 13, 2015 B E 2 7 2 9 0 0 9 0 9 3 1 1 1 2 2 0 0 2 8 6 F 3 1 1 9 1 9 14 5 0 9 0 0 16 0 21 J 14 16 5 19 2 D 2 5 3 7 0 5 10 5 13 8 1 5 18 1 14 3 17 4 4 18 21 5 21 26 0 0 26 2 21 K 10 21 4 G 0 L 2 0 0 EF FF TF LF 21 0 0 C 0 Dur. LS 14 7 0 0 ES 14 13 12 2 4 16 0 A H 2 321 April 13, 2015 Summary of the first compression cycle Cycle # Activity to shorten Can be shortened NIL Days shortened Cost per day Cost per cycle Total cost Project duration 0 -- -- -- -- -- -- 5300 28 1 F 2 3 2 150 $ 300 $ 5600 26 322 Identifying activities for 2nd compression cycle April 13, 2015 Activity A B F H L Cost/day - 200$ - 250$ 350$ B : Least cost activity to shorten 323 April 13, 2015 B E 2 7 2 9 0 0 9 0 9 3 1 1 1 2 2 0 0 2 8 6 F 3 1 1 9 1 9 14 5 0 9 0 0 16 0 21 J 14 16 5 19 2 D 2 5 3 7 0 5 10 5 13 8 1 5 18 1 14 3 17 4 4 18 21 5 21 26 0 0 26 2 21 K 10 21 4 G 0 L 2 0 0 EF FF TF LF 21 0 0 C 0 Dur. LS 14 7 0 0 ES 14 13 12 2 4 16 0 A H 2 324 April 13, 2015 B E 2 6 2 8 0 0 9 0 8 3 1 1 1 2 2 0 0 2 8 6 F 2 0 0 8 0 8 13 5 0 8 0 0 13 0 20 J 13 15 5 18 2 D 2 5 6 5 0 4 9 13 3 8 0 4 17 0 13 3 17 16 4 4 20 5 20 25 0 0 25 2 20 K 9 20 4 G 0 L 2 0 0 EF FF TF LF 20 0 0 C 0 Dur. LS 13 7 0 0 ES 13 13 11 2 4 16 0 A H 2 325 Summary of the 2nd compression cycle April 13, 2015 Cycle # Activity to shorten Can be shortene d NIL Days shortene d Cost per day Cost per cycle Total cost Project duratio n 0 -- -- -- -- -- -- 5300 28 1 F 2 3 2 150 $ 300 $ 5600 26 2 B 3 1 1 200 200 5800 25 326 Identifying activities for 3rd compression cycle April 13, 2015 Activity A B,C F H L Cost/day - 300$ - 250$ 350$ H : Least cost activity to shorten 327 April 13, 2015 B E 2 6 2 8 0 0 9 0 8 3 1 1 1 2 2 0 0 2 8 6 F 2 0 0 8 0 8 13 5 0 8 0 0 13 0 20 J 13 15 5 18 2 D 2 5 6 5 0 4 9 13 3 8 0 4 17 0 13 3 17 16 4 4 20 5 20 25 0 0 25 2 20 K 9 20 4 G 0 L 2 0 0 EF FF TF LF 20 0 0 C 0 Dur. LS 13 7 0 0 ES 13 13 11 2 4 16 0 A H 2 328 April 13, 2015 B E 2 6 2 8 0 0 8 0 8 3 1 1 1 2 2 0 0 2 8 6 F 2 0 0 8 0 8 13 5 0 8 0 0 13 0 19 J 13 14 5 18 1 D 2 5 5 5 0 3 8 13 3 8 0 3 16 0 13 3 16 16 3 3 19 5 19 24 0 0 24 1 19 K 8 19 3 G 0 L 1 0 0 EF FF TF LF 19 0 0 C 0 Dur. LS 13 6 0 0 ES 13 10 11 2 2 13 0 A H 2 329 Summary of the 3rd April 13, 2015 compression cycle Cycle # Activity to shorten Can be shortene d NIL Days shortene d Cost per day Cost per cycle Total cost Project duratio n 0 -- -- -- -- -- -- 5300 28 1 F 2 3 2 150 $ 300 $ 5600 26 2 B 3 1 1 200 200 5800 25 3 H 1 2 1 250 250 6050 24 330 Identifying activities for 4th compression cycle April 13, 2015 Activity A B,C F H L Cost/day - 300$ - - 350$ B,C : Least cost activities to shorten 331 April 13, 2015 B E 2 6 2 8 0 0 8 0 8 3 1 1 1 2 2 0 0 2 8 6 F 2 0 0 8 0 8 13 5 0 8 0 0 13 0 19 J 13 14 5 18 1 D 2 5 5 5 0 3 8 13 3 8 0 3 16 0 13 3 16 16 3 3 19 5 19 24 0 0 24 1 19 K 8 19 3 G 0 L 1 0 0 EF FF TF LF 19 0 0 C 0 Dur. LS 13 6 0 0 ES 13 10 11 2 2 13 0 A H 2 332 April 13, 2015 B E 2 4 2 6 0 0 6 0 6 9 0 3 1 1 2 2 0 0 2 6 4 F 2 0 0 6 0 6 11 5 0 6 0 0 11 0 17 J 11 12 5 16 1 D 2 5 3 5 0 1 6 13 3 8 0 1 14 0 13 3 14 16 1 1 17 5 17 22 0 0 22 1 17 K 6 17 1 G 0 L 1 2 0 EF FF TF LF 17 0 2 2 11 0 C 0 Dur. LS 11 6 0 1 ES 11 8 0 A H 2 333 Summary of the 4th compression cycle April 13, 2015 Cycle # Activity to shorten Can be shortene d NIL Days shortene d Cost per day Cost per cycle Total cost Project duratio n 0 -- -- -- -- -- -- 5300 28 1 F 2 3 2 150 $ 300 $ 5600 26 2 B 3 1 1 200 200 5800 25 3 H 1 2 1 250 250 6050 24 4 B,C 2 3 2 300 600 6650 22 334 Identifying activities for 5th compression cycle April 13, 2015 Activity A B,C F H L Cost/day - - - - 350$ L : Least cost activity to shorten 335 April 13, 2015 B E 2 4 2 6 0 0 6 0 6 9 0 3 2 1 1 2 2 0 0 2 6 4 F 2 0 0 6 0 6 11 5 0 6 0 0 11 0 17 J 11 12 5 16 1 D 2 5 3 5 0 1 6 13 3 8 0 1 14 0 13 3 14 16 1 1 17 5 17 22 0 0 22 1 17 K 6 17 1 G 0 L 1 2 0 EF FF TF LF 17 0 2 2 11 0 C 0 Dur. LS 11 6 0 1 ES 11 8 0 A H 336 April 13, 2015 B E 2 4 2 6 0 0 6 0 6 9 0 3 1 1 2 2 0 0 2 6 4 F 2 0 0 6 0 6 11 5 0 6 0 0 11 0 17 J 11 12 5 16 1 D 2 5 3 5 0 1 6 13 3 8 0 1 14 0 13 3 14 16 1 1 17 4 17 21 0 0 21 1 17 K 6 17 1 G 0 L 1 2 0 EF FF TF LF 17 0 2 2 11 0 C 0 Dur. LS 11 6 0 1 ES 11 8 0 A H 2 337 April 13, 2015 Summary of the 5th compression cycle Cycle # Activity to shorten Can be shortene d NIL Days shortene d Cost per day Cost per cycle Total cost Project duratio n 0 -- -- -- -- -- -- 5300 28 1 F 2 3 2 150 $ 300 $ 5600 26 2 B 3 1 1 200 200 5800 25 3 H 1 2 1 250 250 6050 24 4 B,C 2 3 2 300 600 6650 22 5 L 1 ∞ 1 350 350 7000 21 338 Identifying activities for 6th compression cycle April 13, 2015 Activity A B,C F H L Cost/day - - - - - NO Crashing 339 April 13, 2015 Reports and presentations 340 INTRODUCTION April 13, 2015 Without a doubt, good communication is an essential component of the successful management effort. This means conveying the right information to the right party at the right time and in the right form. 341 Characteristics of good communication April 13, 2015 1- clarity The information must be clear to the receiving party. 2- simplicity Helps improve understanding. Butting information in briefed sentence/s using a simple language . 342 April 13, 2015 3- Accuracy Professional communications must be accurate, objective, and up to date. 4- preciseness and relevance to the subject Providing too much or irrelevant information May be confusing and counterproductive. (example: LDS) 5- legibility People whose handwriting illegible or difficult to read, should type their communications using the computer. 343 April 13, 2015 6- proper support tools Pictures, tables, charts, statistics, etc. They are more helpful and unilingual. 7- proper level of detail The communicator must balance the amount of information in an intelligent way. 8- good organization and formality sorting and organizing the info. to make it easy for the viewer to read, follow and retrieve. Formality means following the company’s procedures, including the use of standard forms. 344 April 13, 2015 9- Retrievable and transformable Retrieving info. for live (current) projects may be performed easily by Using the computer commands. The ability to convert and open electronic files and to read the info is extremely important ,so using unknown software should be prohibited . 10- Conformance to industry standards Using common language when determining specifications and standards such as ISO,IAI. 345 Reports and Presentations April 13, 2015 -Both are types of communications that aim at conveying information -Report should be clear and complete because its printed materials are the only vehicle for conveying information between the person preparing the report and the person receiving it. - Presentations focus on speakers’ persuasive skills, And the speaker focuses on certain points using oral, visual and written (or printed) tools. Audiences have the opportunity to ask for explanation any point unclear to them. 346 Types of presentations April 13, 2015 1- contract candidate presentations The main focus of this presentation is to convince the owner (or the decision maker) that the presenter not only can do the job but also can do it better than other candidates, Answering the owner’s question “ why should I hire you?” 2- sales and demonstration presentations a presentation to demonstrate a product given by a representative of a manufacturing or vendor. 347 April 13, 2015 3- project status presentations a presentation to upper management about a particular project and its status given by the PM or a team member. 4- management presentations a presentation conducted by the management of a company to its staff to inform them about a new work plan, a new system, a new organization, or something else. 348 Presenter’s skills for good presentation April 13, 2015 1- Focus on the client’s needs Presenting the product or service in the best way that serves the client /audience. 2- honesty the presenter should be honest and objective at all times, especially with regard to facts and numbers. 349 April 13, 2015 5- eye contact The presenter should speak to the audience not to himself or to his notes. 6- body language Body language and hand and arm gestures are important. 8- Manage time wisely Presentations almost always have time limits. Besides, human beings have limited attention span. 9- have a backup plan 350 The power of presentation April 13, 2015 To create a good report we should ask ourselves the following questions: 1- does the report include all the information the report user needs? 2- does the report include any un needed information ? 3- is the information clear and well organized? 351 April 13, 2015 4- is the information presented in the required format? 5- can the look of the report be enhanced ? Remember: 1)Computer is still a tool . 2)There is no “one size fits all” . 352 The power of presentation April 13, 2015 Any report (text or graphic) should contain the following information: 1- the name, the address and the logo of the company and department or division. 2- the name of the person preparing the report and supervisor’s approval (if needed). 3- the name and the location of the project. 353 April 13, 2015 4- date 5- title of the report 6- attachments if any. 7- page numbering. 8- legends. 9- definitions of terms, acronyms and abbreviations that may not be known. 354 printing reports April 13, 2015 After reviewing the final form of the report and before printing it consider the following : make sure that only the needed activities and information are included . margins may be slightly reduced to allow more information per page. 355 April 13, 2015 use the “fit to one page” function in the Print menu. in limited cases you may print o both sides of the paper. using a smaller or a different (narrower) font may help. many reports may remain in electronic form and need not be printed. The scheduler must relate the schedule information to the project manager not only as computer-generated colorful charts ,but in clear language as well. 356 SUMMARY REPORTS April 13, 2015 Summary report should contain : The overall situation of the project. The preceding information as compared with that in the last update. The new critical path, if it changed. Cost information (if applicable). 357 April 13, 2015 Any other information that may help the project manager identify trouble spots or makeup for any lost time. No unnecessary details. The summary report should not exceed one page. It should be written in the form of a memorandum. 358 April 13, 2015 Scheduling as Part of the Project Management Effort 359 Project manager team April 13, 2015 The project manager team consist of: (for large project) assistant PM project superintendent project engineer scheduler estimator safety manager procurement manager accountant 360 Management team April 13, 2015 field personal office personal it may include teams member who are dedicated exclusively to particular project and others who are assigned to project part time or serve on the project for only temporary period . managing project requires several skills as: technical skills managerial skills 361 Scheduling and Estimating April 13, 2015 Scheduling and estimating are related and their relationships is probably one of the most important relationships in project management These two areas intersected in many ways such as the following eight: 1)the estimator need to know how long the project will last in order to estimate certain cost , particularly overhead 2) Scheduling and Estimating department collaborate to provide information to the procurement department 3) The scheduler estimate the duration of activities with help from the estimating department 4)Many schedules are cost loaded . The cost must be imported from the cost estimate 362 April 13, 2015 5) Earned value management 6) progress payment depend on the schedule of value and the percent complete 7) resource allocation and resource leveling may be cost related ,although they are scheduling issues 8)schedule compression always involves a balance between cost and time 363 Construction project involved from many parties 1- General contractor. 2- owner. 3- architect (engineer). 4- subcontractors. 5- government. 6- vendors. April 13, 2015 364 In order to schedule a project there are two approaches April 13, 2015 1- build a master schedule that includes several sub schedule . 2- include all activities in one schedule and assign a responsibility code for each contracting party. 365 Time contingency and management options April 13, 2015 The scheduler or project manager must include a time contingency representing the non work days. This time contingency includes two types of non work days. 1- known dates such as a holidays and planned shut down days. 2-Unknown dates. 366 Scheduling and change orders April 13, 2015 The contractor must then implement the CO in the estimating, scheduling, accounting, and other tracking systems. 367 Procurement Management April 13, 2015 Procurement is the process of acquiring materials , equipment , and services from external sources for use in a project . Procurement is a process that usually starts long before the start of the construction process and ends with project completion or project closeout . 368 April 13, 2015 The two objectives of procurement, from the general contractor’s viewpoint, are as follow: 1- To hire the subcontractor who will actually erect and assemble the project. 2-To purchase the materials called for in the contract. 369 April 13, 2015 Linear Scheduling Method 370 April 13, 2015 Definition A simple diagram to show location and time at which a certain crew will be working on a given operation. 371 Characteristics April 13, 2015 Shows repetitive nature of the construction. Progression of work can be seen easily. Sequence of different work activities can be easily understood . Have fairly high level of detail. Can be developed and prepared in a shorter time period than other formats. 372 Advantages of LSM April 13, 2015 Provides more information concerning the planned method of const. than a bar chart. In certain types of projects, LSM offers some advantages over the network approach. 373 Line of Balance Technique April 13, 2015 LSM has relationships to the line of balance (LOB) technique, developed by US. Navy in the early 1950s. First applied to industrial manufacturing and production control. 374 Three diagrams are used in LOB April 13, 2015 1. Production Diagram Shows the relationships of the assembly operations for a single unit. Similar to AOA, except that it shows only one unit of production. 2. Objective Diagram Used to plot the planned or actual number of units produced vs. time. LSM diagram resembles this diagram. 3. Progress Diagram Shows the number of units for which each of the subassembly operations has been completed. 375 Difference between Objective Diagram and LSM April 13, 2015 O.D. is used to schedule or record the cumulative events of unit completion. LSM is used to plan or record progress on multiple activities that are moving continuously in sequence along the length of a single project. 376 Implementation of LSM April 13, 2015 Can be used for continuous activities rather than discrete activities. Transportation projects; highway const., highway resurfacing and maintenance, airport runway const. and resurfacing, tunnels, mass transit systems, pipelines, railroads. High-rise building construction. Repetitive building units. 377 Elements of the LSM April 13, 2015 Axis Parameters Location Measure of progress. In high-rises and housing const., measures may be stories, floors, subdivisions, apartments, housing units. In Transportation projects, distance (ft. or mile can be used, but division by stations (100ft.) is common) is general. 378 Time April 13, 2015 Hours, days, week, or month - depends on the total project time and level of detail desired in the schedule. Preferable to prepare the schedule based on working days and convert to calendar days only at the end. 379 Activity Production Rates April 13, 2015 Obtained by the usual estimating methods as a function of the activity, equip. characteristics, labor, and job conditions. The initial rate should be associated with the min. direct cost of accomplishing the single activity. 380 Activity Interruption and Restraint April 13, 2015 Prod. rate may vary with locations or time periods. Progress may be interrupted intentionally and restraints may occur between activities due to limited equip. or crews. 381 Buffers April 13, 2015 When const. activities progress continuously in a chain, some spacing between activities is required. This spacing serves as a buffer and may require distance or time interval between activities. 382 Activity Intervals April 13, 2015 Used to describe the period of time between the start and finish of an activity at a particular location. Intervals can be indicated by a broad line, two narrow lines, etc. Monitoring Progress. Working calendar can be marked with a moving symbol or a line, tape, etc. vertically across the diagram. Progress on individual activities would be marked by location rather than time. 383 Project Time Optimization April 13, 2015 The total project time may be such that indirect costs and liquidated damages assessed are more costly than the expense of accelerating certain activities. Cost-duration analysis can be used to minimize the total cost, as follows : Identify all activities that can be accelerated or decelerated. Among the above, consider only those that are at a buffer limitation at both the start and the finish of the activity. 384 April 13, 2015 Of these, select the one activity with the lowest cost slope associated with acceleration (or deceleration). Accelerate (or deceleration) the activity rate of production the maximum feasible amount. Repeat the above steps successively until the optimum project cost and associated duration are obtained. 385 April 13, 2015 Discrete Activities Discrete are best scheduled by other methods. Once the duration is determined by network analysis, it can be scheduled on the LSM diagram and coordinated with the linear activities. Seasonal Adjustments When developing LSM, appropriate adjustments can be made for seasonal effect on construction 386 April 13, 2015 Project Progress and Resource Management Project progress is often estimated by the S-curve with bar chart development. In LSM, the determination of activity progress is facilitated and made more rigorous. 387 April 13, 2015 LSM Schedule 4 3 2 1 2 4 6 8 10 12 14 16 18 20 22 24 388 April 13, 2015 LSM Schedule with Brickwork 4 3 2 1 2 4 6 8 10 12 14 16 1820 22 24 Buffer 389 Four-unit Duplex I-J Fragnet 2 EXC FNDS BLDG 1 7 F&P FNDS & SLAB BLDG 1 2 EXC FNDS BLDG 2 April 13, 2015 8 FRAME BLDG 1 7 F&P FNDS & SLAB BLDG 2 8 FRAME BLDG 2 2 EXC FNDS BLDG 3 7 F&P FNDS & SLAB BLDG 3 8 FRAME BLDG 3 2 EXC FNDS BLDG 4 7 F&P FNDS & SLAB BLDG 4 390 April 13, 2015 Duplex Number LSM Schedule 4 3 2 1 2 4 6 8 10 Days 12 14 16 18 391 April 13, 2015 Construction Delay Claims 392 DEFINITIONS April 13, 2015 Delay: An event or a condition that results in finishing the project later than stipulated in the contract . Claim: a request from one contracting party to another party for additional compensation ,a time extension , or both . Note: a claim is not always a negative action ,nor does it automatically indicate a confrontation . 393 Delay claims and change order April 13, 2015 A CO may be initiated at the request of the Owner ,Contractor , Sub-Contractor. They must submit a request for quotation (RFQ) to initiate their CO , And this request could be an owner decision or a “what if ” inquiry , the quotation may includes a cost estimate and the impact on the schedule . 394 April 13, 2015 To minimize the number of CO’s Owners should define the scope of the project and select a competent designer . Many projects suffer from scope-creep syndrome , in which CO’s keep adding to the project budget and put it at levels far beyond what the owner originally planned. 395 Reasons for delay claims 1- Differing site conditions 2- design errors or omissions 3- changes in Owner’s Requirements 4- Unusually adverse weather 5- Miscellaneous factors 6- Force Majeure April 13, 2015 396 Changes in owner’s requirements April 13, 2015 May constitute a change in the contract and provide a foundation for Cos. Owners are always encouraged to know exactly what the want within their budgetary limits. 397 Force Majeure (superior force) April 13, 2015 In the context of construction projects, this term usually involves three important elements : 1- Something that is superior, overwhelming, or overpowering (i.e, can not be prevented) 2- Something that is unexpected or cannot be reasonably anticipated or controlled. 3- Something that has a destructive or disruptive effect on the construction process. 398 Types of delays resulting in claims 1- Excusable delay. 2- Non excusable delay. 3- Concurrent delays. April 13, 2015 399 Delay claims prevention April 13, 2015 1- Baseline schedules that don’t show logic. 2- baseline schedule with dates rather than logic. 3- Overuse of constrains. 4- Erasing footprints. 5- unrealistic baseline schedule. 6- schedule with logic errors. 7- skipping periodic updates. 8- lack of proper documentation. 9- lack of a reasonable time contingency. 400 Communication and documentation April 13, 2015 Communication means conveying information from one party to other parties across the organization Documentation means saving the information in an organized manner for possible future retrieval. 401 April 13, 2015 Communications and documentation must both contain: Clear information. Provide the proper a mount oh details. Be stored efficiently, so that the information can be retrieved easily . 402 We must document these information April 13, 2015 1- The project baseline schedule that the owner accepted 2- Periodic schedule updates 3- Change orders 4- Job diary 5- Correspondence with the home office 6- Submittal records, such as shop drawings and material samples. 403 April 13, 2015 7- Records of any transmittals 8- Meeting minutes 9- Procurement records 10- Government records 11- Records of payment 12- Project manager’s daily log 404 April 13, 2015 Logbook should include daily information such as the following : • Weather condition: temperature, wind. • Work performance during that day. • The number of workers on-site. • Equipment on-site and its condition. • Any accidents that occurred on-site 405 Methods of resolving claims April 13, 2015 Negotiation The most direct method for resolving any type of construction claim. Requires certain skills that reduce the gap between the negotiation parties. The objective: is to reach a solution that might be acceptable to both parties. 406 April 13, 2015 Mediation When negotiation does not work, either because of lack of trust or a lack of skills, mediation may be an option. The mediator may be an individual or a team. Dispute review boards The owner and the contractor select an independent neutral panel with construction experience when the contract is signed . Rather than waiting until the end of project to settle claims, (DRBs) resolve disputes as they arise. 407 Arbitration April 13, 2015 It is usually a formal process performed by an independent professional arbitrator. Arbitration is voluntary. Arbitration does not require the use of lawyers Litigation When none of the previous work and parties can not reach a settlement, the complaining party uses the other party in a court of law. Construction litigation is usually complicated lengthy, and expensive. 408 Method of Schedule Analysis As- build schedule As – planned schedule Comparison schedule Accelerated schedule Recovery schedule April 13, 2015 409 As-Built Schedule April 13, 2015 The as-built schedule should reflect what actually happened in the filed. Activities are plotted by their real start and real finish , disregarding any logic Contain real budget and real resources 410 As – planned schedule April 13, 2015 The as-planned schedule describes the manners in which the contractor in tended to built the project. 411 Comparison schedule April 13, 2015 revised to incorporate any claimed delays . for delay claim the contractor submits two schedules. without the causative factors with the causative factors 412 Accelerated schedule April 13, 2015 Submitted by the contractor. The project can finish by the contractor finish date. 413 April 13, 2015 Safety & Health Management 414 Introduction April 13, 2015 One of the most important factors that should be taken in consideration in the site, (from engineering point view), is the safety and health management. Safety and health management; is considered as a progress measure of the engineering and construction companies. 415 April 13, 2015 Safety: The condition or state of being safe; freedom from danger or hazard; exemption from hurt, injury, or loss. 416 April 13, 2015 Hazard: A condition with the potential of causing or contributing to an accident or illness. 417 April 13, 2015 418 April 13, 2015 419 April 13, 2015 420 April 13, 2015 421 April 13, 2015 422 April 13, 2015 423 April 13, 2015 Rules in construction area under safety outline: 1) knowing hazards and how to avoid them. this mean know Construction Activity / Corresponding Hazard Identification and activity classification with respect to hazard as shown in the following table . 424 April 13, 2015 • Heavy Equipment Operation • Material Handling • Temporary & Permanent Electricity • Cranes & Critical Lifts • Slings & Lifting Gear • Welding, Cutting & Brazing • Hand/Power Tools • Sanitation & Housekeeping • Scaffolding/Ladders • Manholes Excavations, Pits, Trenching & Shoring • Camp, Site Office & Lay down Yard • Over head Obstruction • Road Construction & Re-routing of Existing Roads • Concrete, Concrete Forms & Shoring • Sandblasting • Thrust Boring • Hot Taps • Personal Safety • Paints & Coatings • Piling Operations • Demolition • Mechanical Equipment • Chemical • Liquefied Petroleum Gas (LPG) • Fuel • Site Operations & Hydrocarbon -Class -Class -Class -Class -Class -Class -Class -Class -Class -Class -Class -Class -Class -Class -Class -Class -Class -Class -Class -Class -Class -Class -Class -Class -Class -Class II II III III III III II I III III II III I I II I I I I II III II III III III III 425 Rules in construction area under safety outline: (cont.) April 13, 2015 2) use Personal Protective Equipments (PPE). • 426 Rules in construction area under safety outline: (cont.) April 13, 2015 3) how to deal with emergency situations and what are the proper steps. 427 Rules in construction area under safety outline: (cont.) April 13, 2015 4) follow the instructions carefully. • 428 Occupational Safety & Health Administration April 13, 2015 An organization that interests in achieving and applying safety factors in the construction field. It deals with the identification and control of environmental and personal hazards in the work place. 429 OBJECTIVE OF S&H MANAGEMENT April 13, 2015 Minimize losses – Avoid injuries – Avoid OSHA fines – Avoid litigation Development and implementation of S&H program is key to good management 430 April 13, 2015 ELEMENTS OF S&H PROGRAMS Top management commitment Goal setting and planning Organization & administration Project safety rules Substance abuse program Emergency management Safety orientation & training Accident investigation & recordkeeping Safety budget Safety in contracts Safety program evaluation TQM integration. 431 UNIQUE FACTORS IN CONSTRUCTION AFFECTING S&H April 13, 2015 Large but diverse and fragmented industry every job is unique with numerous complex tasks Labour intensive work involving large forces Transient workforce which is difficult to train. Complex contractual arrangements leading to multiemployer projects 432 HOW SAFETY SAVES MONEY Economic impacts Direct and indirect accident costs Workers compensation and EMR Accident cost accounting April 13, 2015 433 ECONOMIC IMPACTS OF S&H April 13, 2015 Myth: There is a trade-off between safety and cost and productivity Truth: Safety saves money 434 COSTS ASSOCIATED WITH S&H April 13, 2015 A. Direct (insured) costs of accidents, injuries and illnesses B. Indirect (hidden) costs – uninsured C. Costs associated with company s&h programs -Resource allocations for: Safety director/coordinator Equipment and supplies Time (meetings, inspections, etc.) 435 DIRECT COSTS April 13, 2015 Workers compensation insurance premiums paid by contractor (mainly for medical bills) Liability insurance costs Property related insurance costs. 436 INDIRECT (HIDDEN) COSTS April 13, 2015 Transportation for first aid/medical treatment Delays resulting from accident Wages paid to injured worker for time not worked Loss of crew efficiency Training new/substitute worker. Clean-up, equip. repair, stand-by Rescheduling work Post accident extra safety supervision OSHA and civil fines Legal fees Cost of administrative time for investigations and reports. 437 BASIC AIM OF THE OSHA April 13, 2015 To ensure, so far as possible, every working person safe and healthful conditions in the workplace, which must be free from recognized hazards likely to cause death or serious physical harm. Applicable to all employers – Records of illness/injury must be kept by employers with more than ten employees. – Not applicable to self-employed and work places covered by other federal agencies 438 SUMMARY April 13, 2015 Accidents can be tragic and costly. Safety and health programs prevent injuries and fatalities, and save money Effective program organization and implementation will help achieve OSHA compliance and lead to success at corporate and project levels. 439 April 13, 2015 remember If it is unsafe, just don’t do it... If it is dangerous, always avoid it for all we know Safety is everyone‘s responsibility Good Luck THE END