Session 9 (325K MS-PowerPoint file)

advertisement
Software Project Management
Session 9: Project Control
Q7503, Fall 2002
1
Today
•
•
•
•
•
Session 8 Review
Project Control
Status Reporting
Earned Value Analysis
MS Project
Q7503, Fall 2002
2
Session 8 Review
• Project roles and team structure
• CMM
• Requirements
Q7503, Fall 2002
3
Project Control
• Ongoing effort to keep your project on track
• 4 primary activities:
– 1. Planning performance
• A SDP, schedule, and a control process
– 2. Measuring status of work performed
• Actuals
– 3. Comparing to baseline
• Variances
– 4. Taking corrective action as needed
• Response
• Prerequisite to good control is a good plan
Q7503, Fall 2002
4
Project Control
• “Control”
• Power, authority, domination. No.
• Guiding a course of action to meet an objective. Yes.
• Principles
• Work is controlled, not workers
– Control helps workers be more effective & efficient
• Control based on work completed
– Use concrete deliverables
• Balance
– Appropriate level between too much and too little
– Includes:
» Micro-managing vs. neglect
» Too much tracking detail vs. too little
Q7503, Fall 2002
5
Progress Monitoring
• The 3 key Progress Monitoring Questions
– What is the actual status?
– If there’s a variance, what is cause?
– What to do about it?
• Possible responses
• 1. Ignore
• 2. Take corrective action
• 3. Review the plan
Q7503, Fall 2002
6
Progress Monitoring
• Monitoring rates
– Daily, weekly, monthly
– If problems occur – then adjust
• You may have to monitor problem areas more closely
• For some period of time
• Almost always there’s one or more areas under closer scrutiny
• Status Reporting
– Part of the communications management plan
– Which is usually just a section of SDP
Q7503, Fall 2002
7
Status Reports
• From team to PM, from PM to stakeholders
• Typical format for latter
– Summary
– Accomplishments for this period (done)
• Tasks, milestones, metrics
– Plans for next period (to-do)
– Risk analysis and review
– Issues & Actions
• Shoot for weekly updates
– Email notes, then hold brief meeting
– More frequently during crises
Q7503, Fall 2002
8
Programming Status Reporting
• A programmer reports that he’s 90% done.
– What does this mean?
• A programmer reports completing 4,000 LOC on
estimated 5,000 LOC effort.
• Is this 80% complete?
• Quality?
• Ratio, estimated to completed?
– Your estimates could have been wrong
• If you can’t measure scope or quality you don’t know “reality”
• You really only know cost (hours spent)
• How can you improve this?
Q7503, Fall 2002
9
Binary Reporting
• Work packages (tasks) can only be in one of 2
states: complete or incomplete
– No partial credit
• Preferred to anything subjective!
• “90% Complete Syndrome”
– Software is 90% complete 90% of the time
• Use lower-level task decomposition
• Tangible exit criteria
• Plan for 4-80 staff hours of effort per task
Q7503, Fall 2002
10
Earned Value Analysis (EVA)
•
•
•
•
a.k.a. Earned Value Management (EVM)
a.k.a. Variance Analysis
Metric of project tracking
“What you got for what you paid”
– Physical progress
• Pre-EVA ‘traditional’ approach
• 1. Planned time and costs
• 2. Actual time and costs
• Progress: compare planned vs. actual
• EVA adds third dimension: value
• Planned, actual, earned
Q7503, Fall 2002
11
Earned Value Analysis
• Forecasting
– Old models include cost & expenditure
– EVA adds schedule estimation
• Measured in dollars or hours
– Often time used in software projects
• Performance Measurement Baseline (PMB)
• Time-phased budget plan against which contract performance
is measured
• Cost & schedule variances go against this
• Best via a bottom-up plan
Q7503, Fall 2002
12
Earned Value Analysis
• Different methods are available
– Binary Reporting
– Others include
• Based on % complete
• Weights applied to milestones
• EVA can signal errors as early as 15% into
project
• Alphabet Soup
Q7503, Fall 2002
13
Earned Value Analysis
– 3 major components
• BCWS: Budgeted Cost of Work Scheduled
– Now called “Planned Value” (PV)
– “Yearned”
– How much work should be done?
• BCWP: Budgeted Cost of Work Performed
–
–
–
–
Now called “earned value” (EV)
“Earned”
How much work is done?
BCWS * % complete
• ACWP: Actual Cost of Work Performed
– Now called “Actual Cost” (AC)
– “Burned”
– How much did the work done cost?
Q7503, Fall 2002
14
Derived EVA Variances
• SV: Schedule Variance
– BCWP – BCWS
– Planned work vs. work completed
• CV: Cost Variance
– BCWP – ACWP
– Budgeted costs vs. actual costs
• Negatives are termed ‘unfavorable’
• Can be plotted on ‘spending curves’
– Cumulative cost (Y axis) vs. Time (X axis)
– Typically in an ‘S’ shape
• “What is the project status”?
– You can use variances to answer this
Q7503, Fall 2002
15
Earned Value Analysis
Q7503, Fall 2002
16
Derived EVA Ratios
– SPI: Schedule Performance Index
– BCWP / BCWS
– CPI: Cost Performance Index
– BCWP / ACWP
– Problems in project if either of these less than 1
(or 100%)
Q7503, Fall 2002
17
Earned Value Analysis
• Other Derived Values
• BAC: Budget At Completion
– Sum of all budges (BCWS). Your original budget.
• EAC: Estimate At Completion
–
–
–
–
Forecast total cost at completion
EAC = ((BAC – BCWP)/CPI) + ACWP
Unfinished work divided by CPI added to sunk cost
If CPI < 1, EAC will be > BAC
• CR: Critical Ratio
–
–
–
–
SPI x CPI
1: everything on track
> .9 and < 1.2 ok
Can be charted
Q7503, Fall 2002
18
EVA Example
As of 1-July where are we?
BCWS
BCWP
ACWP
Q7503, Fall 2002
19
EVA Example
CV
SV
CPI
SPI
CR
Q7503, Fall 2002
20
Earned Value Analysis
• BCWS
– Use ‘loaded labor’ rates if possible
• Direct pay + overhead
• Remember it’s an aggregate figure
– May hide where the problem lies
– Beware of counterbalancing issues
• Over in one area vs. under in another
Q7503, Fall 2002
21
Earned Value Analysis
• Benefits
– Consistent unit of measure for total progress
– Consistent methodology
• Across cost and completed activity
• Apples and apples comparisons
– Ability to forecast cost & schedule
– Can provide warnings early
• Success factors
– A full WBS is required (all scope)
– Beware of GIGO: Garbage-in, garbage-out
Q7503, Fall 2002
22
The MS-Project Process
•
•
•
•
•
•
•
•
Move WBS into a Project outline (in Task Sheet)
Add resources (team members or roles)
Add costs for resources
Assign resources to tasks
Establish dependencies
Refine and optimize
Create baseline
Track progress (enter actuals, etc.)
Q7503, Fall 2002
23
Project Overview
• This is a ‘quickie’ overview
• We will return to all of these steps
individually over the next few weeks
• Sample project from McConnell
Q7503, Fall 2002
24
Project UI
• Views
– Default is Gant Chart View
• 2 panes
• Task Sheet on left (a table)
• Gantt Chart on right
– View Bar on far left
Q7503, Fall 2002
25
Project UI
(Un)Link Buttons
Toolbars
Outline
Buttons
Indicators
Timescale
Enter Tasks
Here
Gantt Chart
View Bar
Task Bars
Task Sheet
Milestone
Split Bar
Q7503, Fall 2002
26
Create Your Project
• File/New
• Setup start date
• Setup calendar
– Menu: Project/Project Information
– Often left with default settings
– Hours, holidays
Q7503, Fall 2002
27
Enter WBS
•
•
•
•
•
Outlining
Sub-tasks and summary tasks
Do not enter start/end dates for each
Just start with Task Name and Duration for each
Use Indent/Outdent buttons to define summary
tasks and subtasks
• You can enter specific Start/End dates but don’t
most of the time
Q7503, Fall 2002
28
Establish Durations
• Know the abbreviations
– h/d/w/m
– D is default
• Can use partial
– .5d is a half-day task
• Elapsed durations
• Estimated durations
– Put a ‘?’ after duration
Q7503, Fall 2002
29
Add Resources
• Work Resources
– People
• Material Resources
– Things
– Can be used to track costs
• Ex: amount of equipment purshased
– Not used as often in typical software project
Q7503, Fall 2002
30
Resource Sheet
• Can add new resources here
– Or directly in the task entry sheet
• Beware of mis-spellings (Project will create near-duplicates)
• Setup costs
– Such as annual salary (put ‘yr’ after ‘Std. Rate’)
Q7503, Fall 2002
31
Effort-Driven Scheduling
• MS-Project default
• Duration * Units = Work
• Duration = Work / Units (D = W/U)
• Work = Duration * Units (W = D*U)
• Units = Work / Duration (U = W/D)
• Adding more resources to a task shortens duration
• Can be changed on a per-task basis
• In the advanced tab of Task Information dialog box
• Task Type setting
• Beware the Mythical Man-month
• Good for laying bricks, not always so for software
development
Q7503, Fall 2002
32
Link Tasks
• On toolbar: Link & Unlink buttons
– Good for many at once
• Or via Gantt chart
– Drag from one task to another
Q7503, Fall 2002
33
Milestones
• Zero duration tasks
• Insert task ‘normally’ but put 0 in duration
Q7503, Fall 2002
34
Make Assignments
• Approach 1. Using Task Sheet
– Using Resource Names column
– You can create new ones by just typing-in here
• 2. Using Assign Resources dialog box
– Good for multiple resources
– Highlight task, Tools/Resources or toolbar button
• 3. Using Task Information dialog
– Resources tab
• 4. Task Entry view
– View/More Views/Task Entry
– Or Task Entry view on Resource Mgmt. toolbar
Q7503, Fall 2002
35
Save Baseline
• Saves all current information about your project
– Dates, resource assignments, durations, costs
Q7503, Fall 2002
36
Fine Tune
• Then is used later as basis for comparing against
“actuals”
• Menu: Tools/Tracking/Save Baseline
Q7503, Fall 2002
37
Project 2002
• 3 Editions: Standard, Professional, Server
• MS Project Server 2002
•
•
•
•
•
Upgrade of old “Project Central”
Includes “Project Web Access”, web-based UI (partial)
Workgroup and resource notification features
Requires SQL-Server and IIS
“Portfolio Analyzer”
– Drill-down into projects via pivot tables & charts
• “Portfolio Modeler”
– Create models and “what-if” scenarios
• SharePoint Team Services integration
Q7503, Fall 2002
38
Project 2002
• MS-Project Professional
– “Build Team” feature
• Skills-based resource matching
– Resource Pools: with skill set tracking
– Resource Substitution Wizard
• “Project Guide” feature
– Customizable “process component”
Q7503, Fall 2002
39
MS-Project Q&A
• Your WBS in Project
• How did it go?
• Any questions?
Q7503, Fall 2002
40
Homework
• Schwalbe: 7 “Project Quality Management”
• URLs
– “Introduction to Software Testing”
• http://www.iplbath.com/pdf/p0820.pdf
– “Introduction to Software Testing Principles”
• http://www.qestest.com/principl.htm
• Project plan:
– Develop and submit an initial copy of the project plan
(limited to tasks & milestones) for your individual
project
Q7503, Fall 2002
41
Questions?
Q7503, Fall 2002
42
Download